You are on page 1of 21

IBC/Energy Conference 2014

LNG Carriers & FSRUs

LNG Demand and Cooperation Opportunities


in Pakistan

Dr Gulfaraz Ahmed
Former CEO OGDCL, Federal Secretary Petroleum
18 June 2014 at Grand Hyatt Hotel Shanghai
Pakistan Primary Energy Supply Mix (%)
64.8 Million TOE (2012-2013)
6 % 0.5 %
12.8 %
Co
Hydro al
& Nuc
N Gas 48.2 %

Oil
32.5 %

natural Gas Oil Hydro & Nuclear Coal LPG

Natural gas based energy economy: 1st Iran, 2nd Russia, 3rd Pakistan
Country wide gas transmission, distribution and utilization network
83 % of oil consumed is imported that equals 27% of total energy mix
Coal input is 1/4th of world average: environmentally cleaner energy mix 05/14
Natural Gas Consumption by Sector (%)
1.506 tcf in 2012-2013

3.2 3.1 Power


7.9
Domestic
28.6
CNG
Industry
11.7 Power
Fertilizer
Feed Fertilizer
Feedstock
Transport (CNG)
Industry Domestic
Commercial
22.4
23 Fertilizer Power

05/14
Electricity Generation by Fuel
96122 GWh (2012-2013)
4% 0.1 %
35.9 %

28.2 % Generation
Cost/KWh
N Gas Oil N Gas: Rs 4.5-5.5
Industrial Fuel Oil: Rs 17-18
tariff highest Diesel: Rs 22
in the world Nuclear: Rs 7-8
Coal: Rs 9-10
31.1 % Hydro
The world dreads generating electricity with oil: India & USA
generate less than 1%. No country’s economy can sustain generating
35.9% electricity using oil for years on end. 05/14

Urgent need to replace oil by natural gas, nuclear and coal in power
Fuel Consumption for Thermal Power
Generation 2012-2013
Diesel Oil: 218584 tons oil equivalent
Furnace Oil (FO): 7342755 tons oil equivalent
Natural Gas: 7084177 tons oil equivalent

There is an urgent need to replace whole of diesel oil and


most of FO in power generation for economical reasons as
the oil generated power is very expensive resulting in most
expensive power tariff especially for industry even with a
massive subsidy

Pakistan has fairly clean power generation mix and has no


environmental pressure but it is for reducing the cost of oil
generated power, that it is seeking to import LNG for
replacing diesel and FO 5
Natural Gas Discovered, Produced
and Remaining Reserves on 1.7.2013
Daily Production: 4126 MMCFD

25.055
tcf
Remaining Produced
32.021
tcf

Produced tcf Remaining Reserves tcf 05/14


Natural Gas Production & Demand
History and Projection MMCFD
9000
Actual Projection
8000
Unconstrained Demand of 8000
7000 MMCFD in 2012-2013
Shortfall
6000
over 100%
Constrained Demand
5000

4000
Indigenous Production
3000

2000

1000

Constrained demand growing at 6% yearly, production projected declining


at 2% yearly. Unconstrained demand in 2012-2013 is 8000 MMCFD 05/14
Pakistan Natural Gas Supply Shortfall
Forecast by SSGCL (BCFD)

8
y = 0.0142x2 - 56.779x + 56758
7 R² = 1
Billion Cubic Feet per Day

6.47
6
(46 mpta)
5
4 3.4 BCFD
3.88 (30 mpta)
3
2 2 (15 mpta)
1
0
2010 2012 2014 2016 2018 2020
Year
IP Gas Pipeline not likely to start delivering 1 BCFD gas to Pakistan in November 2015
TAPI Gas pipeline projected to deliver 2 BCFD by November 2018
Natural Gas Import Plan
Pakistan is facing natural gas shortage of 50 % exceeding 2
BCFD in constrained demand and 4 BCFD in unconstrained demand
scenario. While pursuing gas import through regional pipelines
from Iran and Turkmenistan, decision reliance has been placed on
import of LNG in short to medium time-frame.
Three LNG receiving infrastructure projects at Port Qasim,
Karachi have been approved by Cabinet Committee (ECC) in
principle. These projects will provide LNG receiving, storage,
regasification and transfer facilities.
(i) Fast Track Terminal Project – 400 to 500 MMCFD
(ii)SSGC LPG Retrofit Project – 500 MMCFD
(iii)New LNG Terminal Project(s) – 500 to 1,000 MMCFD

Presently Fast Track Terminal Project is being executed on


priority. The other two proposed projects will be taken up in
Phase 2 of LNG import.
Emerging LNG Import Market & Terminals
Trend
No of LNG importers has nearly doubled since 2005

Emerging LNG importers includes: Bahrain, Croatia, Jamaica,


Lithuania, Pakistan, Philippines, South Africa and Uruguay

Half of the new importers since 2005 have selected FSRUs over the
land based terminals for:
• lower investment cost,
• Shorter time of completion
• Interim LNG import solution till completion of permanent
terminals
• Flexibility of deployment/redeployment

Pakistan has decided on a fast tracked FSRU which is being set up by


private investors on a tolling fee basis. The first LNG shipment is
targeted for end November 2014
LNG Purchase/Import Plan
• Government of Pakistan is pursuing import of LNG from
Qatar on Government to Government negotiation basis
through a long term (20 years) contract. Pakistan State Oil
Company Limited (PSOCL) and Qatargas Operating Company
Limited (QOCL) have been nominated to negotiate and
finalize the contract
• In addition, Expression of Interest has been invited through
Enquiry No. LNG 001/2014 for supply of 3 mpta of LNG for 5
years on Delivery Ex-Ship (DES) basis between November 01,
2014 to March 31, 2015. Qatar will also compete under this
offer
• Additional 12 mpta LNG import capacity would be built up to
2018


LNG Import Infrastructure

• Fast-track 400 million cubic foot gas (3mtpa LNG) for import
between November 01, 2014 and March 31, 2015 November
2105
• One FSRU based terminal is being developed in private
sector at Port Qasim, Karachi by M/s Engro - Elengy Private
Limited (EEPTL) after competitive bidding process at a
levelized tolling tariff of $0.66/MMBTU. An LNG Service
Agreement (LSA) was executed between EETPL and SSGCL on
April 30, 2014. The FSRU has been leased by EEPTL from
Exilrate.
• Additional Terminals are being planned but work will also be
started on a land-based terminal in parallel to increase LNG
import capacity to 15 mpta by end of 2017 and to phase out
leased FSRUs in the long run
Fast Track Terminal Project

M/s Inter State Gas System (ISGSL) called bids for obtaining the
LNG services of receiving, storage, re-gasification and delivery of
regasified LNG to Southern Gas Company Limited (SSGCL)
receiving point in the vicinity of Port Qasim, Karachi.

M/s Elengy Terminal Pakistan Limited (ETPL) emerged as the


successful bidder at a levelized tolling tariff of $0.66/MMBTU.

An LNG Service Agreement (LSA) was executed between ETPL


and SSGCL on 30-04-2014. The Implementation Agreement
between ETPL and Port Qasim Authority (PQA) has been
initialed on 23-05-2014 and approved by Ministry of Shipping.

Maximum completion time from the date of signing of LSA is


335 days (11 months)
Consumer Prices in Inexpensive Indigenous
Natural Gas Supply Regime

Consumer Prices include about 20% taxes inclusive of GST 17.5% and
Gas Development Surcharge 2.5%
Power/Industry/Fertilizer Fuel: US $ 6/million BTU Commercial: US $
7.7/million BTU
CNG: US $ 8/million BTU
Fertilizer Feedstock: US $ 1.2/million BTU
Domestic:
Lowest Slab: US $ 1.2/million BTU
Highest slab: US $ 6.4?million BTU
Weighted Average(WA) Price ~ US $ 5/million BTU
Weighted Average(WA) less 20% Taxes ~ US $ 4/million BTU

14
Economics of Replacement of Diesel and Fuel Oil
in Power Generation by Imported LNG
1.0 mpta in BTU content = 1.104642 million tons HSD per year in
power generation
1.0 mpta in BTU content = 1.192733 million tons FO per year in power
generation
HSD used in power generation per year = 0.218584 million tons
FO used in power generation per year = 7.342755 million tons
LNG required to replace whole of diesel in power = 0.2 mpta
First 3 mpta will replace diesel and 3.33 million tons of Fuel Oil in
power generation
Average cost of diesel per ton:
Average cost of FO per ton (Jul13-Feb14): US$ 665
Cost of 3.33 million tons = US $ 2,214 billion
Breakeven Equivalent cost of 2.8 mpta = 2214 million
Breakeven Equivalent Cost of 1.0 mpta = 790 million
However, Pakistan is seeking to reduce the generation cost by
replacing FO by LNG, which has to be cheaper than breakeven price15
LNG Import Economics for Break-even Fuel
Replacement
Equivalent cost at power plant site ~ US $ 15.5/million BTU
FSRU fee/transportation to plant ~ US $ 1/ million BTU
Break-even Price of LNG Ex Ship ~ US $ 14.5/million BTU

Use of natural gas will result in 20% higher thermal


efficiency so cost of power generated by LNG would be
20% less than that of FO, which will have a positive impact
on economy.

However, 3 mpta imported LNG at $14-14.5 per million BTU


will increase the weighted average natural gas sale price
before tax by 30%. The first 3mpta will therefore will not
be added to gas supply but earmarked for replacement of
diesel and LSFO. 16
Impact of LNG Import at Maximum Cut-off Price of US$
14/million BTU DES (FO Breakeven Price) on Natural
150 Gas Sale Price $ 10.0 2019
% Increase in Gas Sale Price

120 $ 8.8 2018

90 $ 7.6 2017

60 $ 6.4 2016

30 $ 5.2 2015
LNG import increasing @ 3mpta per year
0 $ 4.0 2014
0 3 6 9 12 15
LNG Import mpta
Expectations of Government of Pakistan in LNG
Import

The News Daily of June 10, 2010 reported that according to


a representative of the Ministry of Petroleum & Natural
Resources, GOP expects a reduction of 30% in generation
cost through substitution of FO with RLNG. Accordingly 30%
reduction from the breakeven cost of US$ 790 million for 1.0
mpta comes to US$ 553 million which gives per million BTU
of RLNG of about US $ 11 per million BTU. Taking nearly 30%
increase in thermal efficiency with natural gas, the DES price
of LNG works out to be US $ 14.3 per million BTU.

18
Installed Capacity MW
30000
For 2014, 2800 MW Installed Capacity with
28000 65% Plant Availability and 75% Plant Factor, it
will generate !20,000 GWh that would meet 26000
26000
the Demand and there would be no load
24000 shedding. 5000 MW short
22477
22000 22797
20922
20000 19257 19450 19420 19786
17399 17498 19384 19420
18000 17798
17799
15658 For 2011, with 65% plant availability and
16000
15662 75% plant factor 26000 MW generates
14000 110,000 GWh that would meet the
demand and no load shedding for 5 %
12000 GDP growth. 3000 MW short
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
04/2014
Gross Generation GWh
120000
For 2011, 22797 MW with 65% Plant Availability
and 75% Plant Factor generate about 95091 Gwh. 110000
110000 110000
Leaving a short fall of 14000 GWh. For no load

14000
shedding 26000 MW will generate 110000 GWh
100000 26000MW. Short fall 3000MW
98213 95358
95661
95091
94385
90000
91616
85629
83269
80000 80627
For 2014, 28000 MW with
75782
72405 similar availability/factor will
70000 generate 120000 GWh for no
65402 68117
load shedding for GDP Growth
62102 65751
60000 of 5%
1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
04/14
Fiscal year starting on July 01
Opportunities for Investment/Cooperation

1. investment in up-stream oil and gas exploration and


production: attractive policy offering $ 6-7/MCF
2. Investment and partnership in power sector: coal,
hydroelectricity, solar and wind power plants
3. Communication infrastructure: Gawadar – Kashghar
Economic Corridor
4. Industry/manufacturing: low labor & raw materials
cost and attractive investment packages
5. Agriculture: corporate farming, processing and value
adding
6. Education: private sector institutions

You might also like