PROJECT: PROPOSED 5 STOREY BUILDING WITH PENTHOUSE

LOCATION: 258 SAMSON ROAD CALOOCAN CITY


BILLING NO. 7
SUMMARY OF BILLING (AS OF AUGUST 21,2021)

REBARS
DIAMETER WEIGHT (KGS) UNIT COST (PHP) AMOUNT
10 mm 1061.89776 PHP 4.50 4778.53992
12 mm 1811.52 PHP 4.50 8151.84
16 mm PHP 3.50 0
20 mm 896.391 PHP 3.50 3137.3685
25 mm 520.155 PHP 3.50 1820.5425
PHP 17,888.29

FORMWORKS
AREA (SQ. M) UNIT COST (PHP) AMOUNT
column 2nd lift 26.558 220 PHP 5,842.76
slab 182.927 220 PHP 40,243.94
runner 5.4625 220 PHP 1,201.75
PHP 47,288.45

CONCRETING
VOLUME (CU. M) UNIT COST (PHP) AMOUNT
200 0

BILLING AMOUNT PHP 65,176.74


STIRRUPS

BEAM DIAMETER LENGTH (METER) PIECES TOTAL LENGTH KG/M PHP/KG TOTAL PHP total kg

FRB4,FRB4 10 1.62 212 343.44 0.616 PHP 4.50 952.01568 211.55904

FRB2A,FRB3A 12 1.92 212 407.04 0.888 PHP 4.50 1626.53184 361.45152

FRB2,FRB3 12 2.62 216 565.92 0.888 PHP 4.50 2261.41632 502.53696

FRB2,FRB3 12 2.62 216 565.92 0.888 PHP 4.50 2261.41632 502.53696

FRB1,FRB1 12 2.32 216 501.12 0.888 PHP 4.50 2002.47552 444.99456

FRB5 10 1.52 28 42.56 0.616 PHP 4.50 117.97632 26.21696

FCB1,FRB6,FRB7,FCB2 10 1.62 113 183.06 0.616 PHP 4.50 507.44232 112.76496

B33,B34,B34A,b35,b36, b37 10 1.52 204 310.08 0.616 PHP 4.50 859.54176 191.00928

B29,b38 10 1.62 184 298.08 0.616 PHP 4.50 826.27776 183.61728

FRB8,FRB9,FRB10 10 1.52 102 155.04 0.616 PHP 4.50 429.77088 95.50464

B27,b28 10 1.4 106 148.4 0.616 PHP 4.50 411.3648 91.4144

FRB12,FRB13,FRB14,FRB15,FCB4 10 1.52 160 243.2 0.616 PHP 4.50 674.1504 149.8112

12930.37992
MAIN BARS ADDITIONAL

BEAM DIAMETER(MM) LENGTH (M) KG/M PIECES TOTAL KG PHP PER KG AMOUNT

FRB12, FCB4 25 7.5 3.853 18 520.155 PHP 3.50 PHP 1,820.54

FRB6, FCB2 20 10.5 2.466 7 181.251 PHP 3.50 PHP 634.38

20 8.5 2.466 7 146.727 PHP 3.50 PHP 513.54

FRB5 20 5.5 2.466 7 94.941 PHP 3.50 PHP 332.29

FRB10 20 6 2.466 6 88.776 PHP 3.50 PHP 310.72

B34A 20 6 2.466 6 88.776 PHP 3.50 PHP 310.72

B37 20 6 2.466 6 88.776 PHP 3.50 PHP 310.72

B27,B28 20 10.5 2.466 8 207.144 PHP 3.50 PHP 725.00

PHP 4,957.91
FORMWORKS COLUMN 2ND LIFT 3RD TO 4TH FLOOR

LENGTH WIDTH PERIMETER HEIGHT AREA UNIT COST (PHP) AMOUNT PIECES TOTAL AMOUNT

0.54 0.54 2.16 0.7 1.512 220 332.64 15 4989.6

0.64 0.3 1.88 0.7 1.316 220 289.52 2 579.04

0.64 0.25 1.78 0.7 1.246 220 274.12 1 274.12

5842.76

SLAB
PANEL LENGTH WIDTH AREA UNIT COST (PHP) AMOUNT
1 8.17 5.6 45.752 220 10065.44
2 5.26 4 21.04 220 4628.8
3 4.3 4.25 18.275 220 4020.5
4 8.2 4.7 38.54 220 8478.8
5 4.1 2.4 9.84 220 2164.8
6 2.75 1.92 5.28 220 1161.6
7 17 2.6 44.2 220 9724
40243.94

runner 21.85 0.25 5.4625 220 1201.75