PRE-COMMISSIONING CHECK LIST

Valves
Client Contract No
Project Name & Location Date
Plant Area From
Tag / System To
Drawing Form No
Sheet 1 of 1
Equipment Description
Rev.
LINE NO(S). TEST MEDIUM

PEFS LOCATION

Inspected by

Item Description DAAM CO SOC

01 Compare the type, pressure class and material of the valve with the design and
specification requirements

02 Check the valve installation for correct direction of flow, particularly for globe
check valves
NOTE: The flow direction of gate and ball valves could differ from Cm direction
for pressure sealing in closed position

03 End covers of valves shall be removed only immediately before installation and it
shall be checked that the valve is clean

04 Check the proper torque for the handwheel or mechanical actuator

05 Check for proper lubrication of handwheel bearings, spindles and actuator


gearboxes

06 Check for free-running of any chainwheel operation

07 Check for correct installation, commissioning and testing of any electric,


mechanical or hydraulic actuator

08 Check that correct pins are fitted at handwheels

09 Check for proper lubrication and adjustment of taper plug valves

10 Check that valve operates smoothly through its full range

VALVE DETAILS:
Vendor Valve Type Serial No.
Model Seat Material Plug / wedge etc material
Size Rating
REMARKS / OBSERVATIONS:

TITLE NAME SIGNATURE DATE


Prepared by