You are on page 1of 2

APPLICATION NOTE

Ensuring Shielding Integrity to Ground in a


Leviton Shielded Twisted Pair Installation
by Dan Underbrink, RCDD, Principal Applications Engineer, Leviton Network Solutions

TR 2. Run a Telecommunications Equipment Bonding


Conductor (TEBC) for each row of racks or cabinets
from the SBB.
TBB • This is typically a #6 AWG bare or green-insulated
(telecommunications TEBC stranded copper wire.
bonding backbone)
(telecommunications equipment
bonding conductor) • If insulated, the insulation must be appropriate
for the space through which the TEBC runs
(e.g., use plenum CMP insulation if running
SBB through a plenum space).
(secondary bonding bussbar)
• Connections of TEBC to the SBB should be made
with an appropriate-size, UL listed, two-hole crimp
style lug.
The following recommendations are best practices for
ensuring shield integrity to ground for any Leviton shielded 3. Ensure a specific equipment grounding element
installation. The points below highlight grounding and for each rack or cabinet.
bonding elements within a single telecommunications
• Equipment connections to each rack or cabinet
room. The ANSI/TIA-607-C standard outlines additional
from the TEBC may use any one of the following
elements required for a larger Telecommunications
three methods:
Grounding System.
• A Horizontal Rack Bonding Bussbar (Horizontal
1. Install the Telecommunications Grounding System RBB) mounted to the rack or cabinet vertical
per TIA-607-C. equipment mounting rails.

• Use a Secondary Bonding Bussbar (SBB), formerly • A Vertical Rack Bonding Bussbar (Vertical RBB)
known as a Telecommunications Grounding mounted to and running the full height of the
Bussbar or TGB, within the Telecommunications rack or cabinet.
Room/Horizontal Cross-connect (TR/HC) • A #6 AWG Rack Bonding Conductor (RBC)
• The SBB should be bonded to the running full height of the rack or cabinet
Primary Bonding Bussbar (PBB), formerly • For each of the three rack/cabinet options above,
Telecommunications Main Grounding Bussbar connections are made to the TEBC via irreversible
or TMGB). This bonding element is called the compression-type connections.
Telecommunications Bonding Backbone (TBB).
• The rack or cabinet itself is independently
• Connections of SBB to the PBB should be made bonded to the TEBC via irreversible compression-
with an appropriate-size, UL listed, two-hole type connection. This ensures the structural
crimp style lug and appropriate gauge cable. metal of the rack or cabinet is bonded to the
• The PBB should be bonded via Telecommunications Telecommunications Grounding System in case
Bonding Conductor (TBC) to Structural that metal should become inadvertently energized.
Steel/Building Ground. If a bond to structural • Note: the grounding/bonding parts mentioned
steel cannot be obtained, use the electrical above are not provided by Leviton. Each of the
system ground point. elements above should be installed and tested
• Use recommendations from the TIA-607-C per manufacturer recommendations to ensure
standard for proper conductor gauge for all a low-impedance path to ground.
of the above TBB and TBC connections.

Leviton Network Solutions 2222 - 222nd St. SE Bothell, WA 98021 Tech Support: 800.824.3005 +1.425.486.2222 Fax: 1.425.485.9170 www.leviton.com
© 2017 Leviton Manufacturing, Inc All rights reserved. Subject to change without notice.
APPLICATION NOTE

4. Install Leviton shielded permanent link (work area 5. The field tester should be set for the appropriate
jack to patch panel) or channel (includes patch category rating for the wiring system (i.e. Cat 5e,
cords at both ends) per the Leviton Shielded Cat 6, or Cat 6A) and for FTP cable type.
Connector Instruction Sheet. • Field tester shield continuity testing should
• A Leviton shielded patch panel must be used. be enabled.
Various standard and high-density options are • All permanent links or channels should be
available, as well as flat and angled shielded options. characterized with the field tester, including
• All patch cords used must be shielded patch cords. shield integrity test. Repairs of any problem
• Leviton Shielded Patch Panels are engineered to links should be undertaken and completed.
provide a low impedance path from the shielded 6. Finally, an individual equipment Unit Bonding
connector bodies (i.e. shielded jacks) to the Conductor (UBC) should be installed from each
Patch Panel sheet metal. shielded patch panel to whatever element was
• A grounding stud is provided on the provided for rack or cabinet bonding (i.e. Horizontal
standard-density shielded patch panels. RBB, Vertical RBB, or RBC). This ensures bond
• For high-density shielded patch panels, integrity of the shielded links or Channels to the
the ground stud is accomplished via installation Telecommunications Grounding System.
of a long rack-mount screw provided with the • If RBC was chosen as the rack or cabinet
panel. Follow specific instructions that are bonding element, UBC connections to the RBC
included with these panels to ensure that are accomplished via irreversible compression
adequate grounding is accomplished as part type connector.
of panel installation. • UBC connections to RBBs should be made with
• If the permanent link or channel architecture UL listed two-hole lugs.
includes a consolidation point (CP): • Best practice would be for each shielded patch
• Shield continuity must be maintained across panel UBC to be a #6 AWG wire (NEC and TIA-607-C
the CP interconnect. require a minimum #12 AWG for the UBC).
• Leviton recommends a shielded patch panel in • The thought behind the #6 AWG UBC as best
the CP for interconnect purposes. Standards do practice is that this element is bonding the
not allow cross-connects in a CP. shields of all links or channels in the shielded
• Grounding for this architecture is still performed patch panel (i.e. 24 or 48 Links or Channels).
at the TR shielded patch panel (i.e. no shield • If most or all of these shields were to become
grounding performed at/within the CP). inadvertently energized, one would want a
• Horizontal cable section A will be a shielded UBC of sufficient size to reliably shunt this
cable running from the TR shielded patch undesirable energy to ground.
panel to the rear of jack in the CP shielded In summary:
patch panel.
• Install and verify the Telecommunications Grounding
• Horizontal cable section B will be a shielded System (TBC, PBB, TBB, SBB, TEBC, and RBB or RBC)
plug-to-jack cable assembly running from the Per ANSI/TIA-607-C.
front of the CP panel (shielded plug end into CP
shielded jack in the patch panel and shielded • Install and verify all Leviton shielded permanent
jack end into workstation outlet). links or channels.

• Alternately, horizontal cable section B may be • Install individual #6 AWG equipment Unit Bonding
a plug-to-open cable assembly (shielded plug Conductors (UBC) between each shielded patch
end into CP shielded jack in the patch panel and panel and the rack or cabinet bonding element.
open end cut to length and field terminated to • Shielded permanent links or channels are bonded to
a shielded jack for the workstation outlet). the Telecommunications Grounding System at one
• Shielded plug-to-jack or plug-to-open cable point (the shielded patch panel). No grounding is
assemblies are make-to-order products done at the work area connector (which is typically
available from Leviton. a jack in a wallplate).
Learn more about Leviton shielded solutions at
Leviton.com/Copper.
H17 6911

Leviton Network Solutions 2222 - 222nd St. SE Bothell, WA 98021 Tech Support: 800.824.3005 +1.425.486.2222 Fax: 1.425.485.9170 www.leviton.com
© 2017 Leviton Manufacturing, Inc All rights reserved. Subject to change without notice.

You might also like