Professional Documents
Culture Documents
Purpose)
This background is used for P&ID check which is performed by GES engineer and this
document explains general rule for indication of P&ID.
(Note) Indication of P&ID shall be represented based on project specification.
[P&ID]
P&ID means “Piping and Instrument Diagram” and P&ID is prepared based on PFD (Process
Flow Diagram).
1. General
P&ID is composed of the following drawings.
(1) Lead Sheet : Symbols/Lines/変数/簡略図 of instrument system are difined in Lead Sheet
(2) P&ID : Process Unit / Utility Facility / Offsite Facilities with Equipment / Piping /
Instrument
(3) Header Diagram (= Distribution Diagram) : For Utility Header (Steam / BFW / Steam
Condensate / Cooling Water / Plant Water / Potable Water / Plant Air / Instrument Air /
Nitrogen / Fuel Oil / Fuel Gas , etc)
(ii) For Blow Down System / Drain Recovery System / Slop Oil Recovery System / Flushing
Oil System
(*)The followings are drain recovery systems.
Hydrocarbon Oil Recovery System: Recovered hydrocarbon is mixed with feed or is
treated by incineration.
Solvent Recovery System: Solvent is recovered from absorber and is recycled.
Harmful Fluid Recovery System: Harmful component, such as benzene, is recovered
and recovered harmful fluid is mixed with feed,
1/40
basically.
Chemical Sewer Recovery System : Chemical, such as waste acidity or waste alkali is
recovered and is treaded by neutralization.
Then, neutralized waste is disposed as waste
water.
Clean Water Sewer System : Waste water which does not includes oil, such as rain
water, is treated
Oily Waste Sewer System : Oily waste water is recovered and treated in order to
remove oil.
(4) Interconnecting Diagram : Interconnecting Diagram indicates piping on pipe rack / pipe
sleeper between units.
(5) Vendor P&ID : Vendor P&ID is prepared by vendor of equipment and it shows detail of
required piping/instrument/etc.
(2) Piping
The followings are piping symbols which indicate service of lines.
(2) Instrument
The followings are instrument signal symbols which indicate service of lines.
A : Rating
11 : Material
(ex. 11,13: Carbon Steel (Non-Killed),
15: Carbon Steel (Killed),
31: 304SS)
2 : Corrosion Allowance (C.A.)
B : Service
(ex. A: General,
B: Hydrocarbon/Steam/BFW,
C: Steam (General),
D: Steam (Superheated),
E: Alkali / Rich Amine,
F: Liquid/Vapor including CO2,
G: Lube Oil / Seal Oil,
J: Potable Water / Instrument Air,
K: Air Form Liquid)
5/40
(vi) Type of Insulation / Insulation Thickness
[Hot Insulation]
Hot insulation is required for the following purpose
- To avoid decreasing temperature of fluid by heat loss.
- To avoid solidification by heat loss, especially during winter season
Note) Potable water line shall be insulated in order to avoid increasing temperature by solar
radiation, since potable water is used for eye washing incase of emergency.
[Cold Insulation]
Cold insulation is required in order to avoid heat input from outside.
Note) If heat loss is allowed with considering process view point, cold insulation is not
required.
[Trace / Jacket]
If insulation is not enough in order to keep temperature of fluid, the followings are to be
considered.
- Steam trace or electrical trace
- Jacket Piping
[Acoustic Insulation]
Acoustic insulation is required in order to avoid noise if noise is occurred and is higher than
the criteria of noise.
(The Criteria of noise is specified in project specification.)
5. Valve Selection
6/40
The followings are valve symbols.
Some of manual valves are locked at opened (or closed) position with chain (wire) / key In
order to avoid mis-operation of manual valves.
LO (Locked Open) (*= CSO (Car Sealed Open)) : fixed with opening position
LC (Locked Close) (*= CSC (Car Sealed Close)) : fixed with closed position
7. Prevention of Backflow
Check valve is required for the following service in order to avoid back flow.
- Discharge of Pump
- Discharge of Compressor
- Incase mixing of two lines, upstream of mixing point on each line.
(*) Stop Check Valve : Stop check valve equip handle in order to fix inside disc and used as
check valve and block valve.
Stop check valve can be considered if there is cost merit, such as high pressure steam
service.
8/40
(i) Flame Arrestor
Flame arrestor is required in order to avoid propagation of flame.
Flame arrestor is made from wire mesh or small clearance material.
Fire cannot go through small clearance material and fire will extinguish.
(ii) Strainer
Strainer is used to remove small particle which is included in fluid in order to avoid
damage / plugging for equipment at downstream. The followings are type of strainers and
the type of strainers shall be represented on P&ID.
- Y type strainer
- T type strainer
- Bucket type strainer
- Cone strainer
9/40
(iv) Blind Flange
Blind flange is equipped on the end of utility header in order to perform maintenance
utility header by removing the blind flange, if required.
(x) Desuperheater
When operating temperature of steam is superheated and saturated steam is required,
desuperheater is equipped on steam line in order to decrease temperature by introducing
BFW through spray nozzle of desuperheater.
(xi) Ejector
10/40
(xii) Flange
Basically, flange of piping is not represented on P&ID. However, flange is required for
special purpose, flange is represented on P&ID.
(ex.) Blind plate / Buttery Limit of Construction Buttery Limit
(xiii) Reducer
(xiv) Screwed Cap / Screwed Plug
(xv) Removal Spool
(ex) “Removal Spool” is required in order to
(絵を追加 BPA Main Reactor OVHD の MH)
(xvi) Swing Elbow
Swing elbow is used in order to change connection of lines by change direction of “Swing
Elbow”.
(xvii) Weep Hole
Weep hole is equipped on vent-to-atmosphere line in order to drain out rain water.
(xviii) Piping Header
Piping header shows side view of header line.
(xix) Funnel
Funnel is used for recover drain water or oily water.
9. Isolation
“Isolation” is required in order to achieve the following purpose.
- Isolate two systems during normal operation
- To avoid leakage of process fluid to atmosphere
- For Maintenance / Rectify of equipment / instrument
11/40
- To enter equipment (Column / Vessel) safely for inspection / maintenance
12/40
(3) Double Block Valve
Double block is required for the service that is mentioned in chapter “Permanent Blind” in
order to ensure isolation.
Break point shall be decided in order to bear material for all operating conditions.
- As for operating pressure, it should be considered that upstream pressure reaches to the
farthest manual valve if there are some valves.
(*) If the above said farthest valve is defined as “LO”, it is not necessary to consider that
upstream pressure reaches to the farthest “LO” manual valve.
13/40
14/40
15/40
16/40
12. Utility Connection Configuration
There are two kinds of utility use (a) and (b) as below.
(a) Utility for continuous use: (ex) Steam is introduce into system during normal
17/40
operation
(b) Utility for temporary use: (ex) Steam is introduced into system in order to purge
hydrocarbon during shutdown
19/40
(ii) Sampling Connection for hazardous service
(with Sample Cylinder)
- Lethal Fluid
- LNG
- Vapor
20/40
14. Special Consideration on Piping Design
(i) Gravity Flow
Height of downstream piping shall not be higher than height of piping inlet
(* Any “Pocket” is acceptable.)
21/40
(ii) No Pocket
Both “High Pocket” and “Low Pocket” is not allowed.
22/40
(v) Free Drain
Low Pocket is not allowed.
Horizontal line is acceptable.
Ex.) Inlet / Outlet Piping of PSV
Outlet Piping of Condenser (incase of two phase flow)
Lead tube of Differential Pressure Instrument for Vapor Service
Upstream / Downstream Piping for Valve on Steam Line (Normally Close)
(vi) Slope
Low Pocket is not allowed.
Piping shall be designed in order to flow drain toward specified direction.
Slope shall be required for horizontal line (“1 / 500” means that piping shall dip 1m height
per 500m distance.)
(xi) Symmetrical
Piping shall be arranged in order to distribute flow equally.
Ex.) Distribute two-phase-fluid into two lines equally.
Draw off liquid from column with two lines
24/40
(xii) Min.
Minimize distance as much as possible, if piping arrangement can be designed.
(xx) On Ground
Control Valve is required to locate on ground for maintenance.
(xxi) Grouped
If some valves shall be located nearly in order to operate, these valves shall be
specified as “Grouped”.
27/40
(ii) Indication of Information on Instrument System
Instrument Number : Instrument Number is consisted with the following items.
Unit Number (ex) 04
Functional Identification (ex) FIC
Instrument Serial Number (ex) 001
Suffix (ex) A/B/C or S for Spare Instrument
28/40
Sample of Functional Identification is as below.
29/40
FI : Flow Idicator
LC : Level Controller
PIC : Pressure Indicator Controller
PV : Pressure Control Valve
PSV : Pressure Safety Valve
Local
Instrument
30/40
The followings are suffix of level primary element.
31/40
The followings are symbol of hand switch.
Air Failure Action : When instrument air failure occurred, air actuated valve will open or close
or keep the position.
FO (Failure Open)
32/40
FC (Failure Close)
FL (Failure Locked)
Stopper for Control Valve : If control valve is not allowed to close completely, mechanical
stopper (or stopper by software) shall be equipped.
(*) Motor Operated Valve : If control valve is controlled by electric power, this control valve is
called “Motor Operated Valve”.
TSO (Tight Shut Off) : If control valve shall be closed completely and leakage shall be limited
strictly, valve shall be noted as “TSO”.
Generally, if valve size is bigger than 8”, hand wheel is equipped and bypass is not adopted.
The reason is as below.
- Globe valve which is bigger than 8” requires special order and the cost is relative high.
- It is difficult to control flow rate with using manual valve which is larger than 8”.
- It is expected that plugging of foreign material may not occur if control valve size is bigger
than 8”.
33/40
(iv) Indication of Instrument System on P&ID
Sample of instrument system is as below.
- Control Loop
34/40
- Feed-forward Control
35/40
- Compensation
36/40
- On/Off Control by DCS
37/40
- Pump Auto Startup System
Around Equipment : The following items are represented on P&ID around equipment.
Nozzle
Vent
Drain
Utility Connection : When maintenance of equipment is performed, inside of equipment shall
be purged by nitrogen. For the above said purpose, Utility Connection is required for
38/40
equipment.
Pump
Spare Pump : Spare pump is basically required, since rotating machine is easy to be
damaged with compared to other equipment, such as vessel.
39/40
Driver :
Check Valve : Check valve is required at discharge line in order to avoid back flow through
standby pump.
Strainer : Strainer is required at suction line in order to remove small particle, since if small
particle is send to pump, pump will be damaged.
Drain/Vent : Drain is required for maintenance of pump in order to withdraw liquid from the
inside of pump.
Vent is required in order to fill pump with liquid completely, since if vapor is remained inside
of pump, pump impeller may be damaged by cavitation.
Pressure Gauge : To check the head developed and control the discharge valve opening.
Safety Valve :
Pulsation Damper : for reciprocating pump, pulsation dumper is required.
Check Valve Bypass :
Pump Minimum Flow Bypass
40/40