Huawei Power Cube 1000

(Hybrid Solution )
Cabinets overview

PC 1000 - ESC 720 PC 1000 - ICC 330 H1 C4


2
Installation dimensions and Cabinet Cable Hole Positions (ESC720 + ICC330)

3 12 November 2019
PC 1000 - ICC 330 H1 C4
• Battery Branch > 2 ×250 A Fuse
• LLVD Branch 2 ×80 A MCB, 2 ×63A MCB (LLVD1)
• BLVD Branch 1 ×63 A MCB, 4 ×32 A MCB, 2 ×16 A MCB (LLVD2)
• AC input (4*25mm) connected to AC panel
• Commissioning switch on auto mode (the system is under automatic control)
• Rectifiers Group ( 7 PSU with power 3000 W for each one and
• DG battery charger with output 12.5 – 14.2 V connected to DG battery

installed in slot 8
• Cabinet dimensions ( 1600 mm x 650 mm x 820 mm)

Battery charger
4
PC 1000 - ICC 330 H1 C4
• GIM board is interference card for:
 DG hybrid signal (DG1 port NC and COM (2)
 AI 1 to detect the fuel level (6)

• SMU board is monitoring power system and we can use:


 Local area connection port (system management)connected to ENEC(1) 2
 CAN port connected to COM_IN of last LI battery (2)

• UIM Board is alarms interface and we can use :


 COM port to monitor battery cabinet air condition (1)
 DIN1 port for battery cabinet door alarm
 BAT TEMP port for battery cabinet temperature
 TEM-HUM for temperature and humidity for ICC (REC cabinet)
 TEMP 1 for temperature for ICC (REC cabinet)
 Gate for temperature for ICC (REC cabinet)

5
PC 1000 - ESC720
• Dimensions >( 2030 mm x 815 mm x 735 mm)
• Max Capacity 8 Lithium modules
• Module Capacity 100 AH
• Contains 4 DC power bus bars
• DC cables size 35 mm from DC bars to ICC on
fuse 250 A

Insert Confidentiality Level in slide footer 6


PC 1000 - ESC720

COM_IN

power box then


CB 63 A on BLVD
(Prefabricated)

COM_OUT

+ VE
SMU Air Condition Connections
Battery Connections - VE
7
System Cables Connections

8
System Cables Connections

9
Hybrid Activation
• From SMU  Site Maintain  Pass 000001  Gen Self Check  Yes
• After few minutes the result should be succeed if all connection are OK
• Get IP from System Wizard and log into the cabinet via browser (HTTPS:/ cabinet IP ) and check configuration
• We should make sure that the firmware is upgraded(the same view for inserted PS’S)

admin
Changeme

10
Check The Software Version

Insert Confidentiality Level in slide footer 11 12 November 2019


Site ID and System Type

12
Management Configuration

13
DOD and Max Charge time

14
Total and remaining capacity check

Insert Confidentiality Level in slide footer 15 12 November 2019


Charging Current

16
Fuel Sensor Parameters

Insert Confidentiality Level in slide footer 17


Fuel Sensor Parameters

Insert Confidentiality Level in slide footer 18 12 November 2019


Door Alarm Configuration

Insert Confidentiality Level in slide footer 19


Door Alarm Configuration

Insert Confidentiality Level in slide footer 20


Check Hybrid status / Switch Reason (DOD or Battery Full)

Insert Confidentiality Level in slide footer 21


System Query ( Hybrid Performance) to check operation historical log

Insert Confidentiality Level in slide footer 22


Alarm configuration and testing

• The alarms should be configured and tested through :


1st : ENEC > Confirmation mail that the cabinet is reachable
2nd : OSS through EMUA or OVP by applying alarm mapping ‘check alarm mapping sheet ‘ >Confirmation
mail from Huawei integration team that all alarms are configured and tested
We can upload configuration file with all alarms and operation parameters needed

• We should test below alarms from the site and check TT as usual :
DG start failure – DG stop failure – DG abnormal start – DG abnormal stop
Rectifier communication failure - Load fuse break-Fan alarm-battery temperature
Li battery Failure - Door alarms – fuel level

23
Alarms simulation
• We must check hybrid operation is OK
• 1st condition DG is ON
Trip DG CB
 Cabinet alarmed “Generator abnormal stop or Genset work abnormal ” then clear it after checking
 Convert DG on manual mode
Wait till the remaining capacity reach 100% (we can accelerate charging by switching off some LI battery
modules)
 Cabinet alarmed >”Generator fail to stop or Genset work abnormal “then clear it by backing DG on auto mode
and switch on all LI batteries
• 2nd condition DG is OFF
Put DG on manual mode
Cabinet alarmed >”Generator abnormal start or Genset work abnormal “ then clear it by backing on auto mode
Trip DG CB or trip
Set DOD 5% or (100 - remaining capacity )
Cabinet alarmed >”Generator fail to start or Genset work
24
abnormal “then clear it and reset DOD to 55%
Mohamed El Zayat

25