1. Materials Requirement Planning (MRP): Determine requirements raised for a material from
planning or manually by buyer.
2. Source Determination: Determine list of suppliers based on previous transaction history or long
term agreements available in system and request quotes from them.
3. Vendor Selection: Compare quotes from all suppliers and select most suitable one for the
requirement.
4. Procurement of Goods/Services: Create contracts with the selected supplier and raise Purchase
Order (PO) and send to supplier. Monitor PO at regular intervals and check with supplier on
delivery.
5. Goods Receipt and Inventory Management: Receive goods/services in your premises and create
Goods Receipt transaction against PO in book of records for the received qty. Check if the
received quantity is within the tolerance limits agreed upon with supplier in contracts.
6. Invoice verification and Payments to Supplier: Receive invoice from supplier for the goods
supplied, process the Invoice and make payments to the supplier.
Procurement Types:
Let’s now discuss the procurement types. There can be multiple ways based on which procurement types
can be categorized. Here is the representation of basis-wise types.
MM FLOW
Based on the material being procured, there can be two Procurement Types
involved in the Purchasing Process. These are described below.
Procurement for direct consumption: This refers to the Materials procured for direct
consumption and not for storage. These may or may not have a master record
created and will need account assignment when an order is created to specify
where it is going to be consumed. Consumption account gets updated with value
when goods are received against PO in such scenarios. This also covers any
services we get from third party sources/suppliers.
Need to Procure
Based on the need to procure and process of implementation, there can be three
Procurement Types involved in the Purchasing Process. These are as below.
MM FLOW
One-time Purchase Order: Purchase order is created directly without reference to
any existing contracts/agreements. This is used mostly for materials/services
needed on irregular basis.
Stock transfer using Stock Transport Order: This is the Process in which a plant orders
goods from another plant within the organization to meet the requirements using
STO (Stock Transport Order). Stock gets transferred from one plant to another by
processing this STO creating deliveries.
Direct Shipments/Drop Shipments: This is also known as Third party processing. Sales
order when received from customer is forwarded to a supplier/manufacturer who
can supply the goods directly to the customer. This eliminates the intermediate
process of buying from supplier, stocking and supplying to customer reducing
overall costs.
MM FLOW
2
The stock is moved according to the entries, withdrawals and transfers of stocks.
On the diagram, there are entries linked to the internal production of finished or semi-
finished products (module PP), or entries linked to purchases (module MM Purchases
detailed in this document).
There are also outputs linked to sales and distribution (module SD)
Each stage of the purchasing process corresponds to a transaction, the main ones of
which are listed below :
MM FLOW
MM FLOW
The most important SAP MMBE SAP Stock Overview MMBE Tcode are: