Professional Documents
Culture Documents
GE A 353 14 7
CONTENTS
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
APPENDICES
GE A 353 14 7
GE A 353 14 7
1. OBJECTIVE
The objective of this document is to set recommended Offshore Platform Plot Plan
guidelines based from collective experience acquired during involvement in design,
construction, operation and maintenance. This guideline is not to be construed as a
specification nor it is intended to override any other codes, standards and practices.
The guidelines contained in this document do not encompass all aspects of Offshore
Platform Plot Plan – it is only intended to augment engineering judgement. As
engineering requirements vary from one project to another, the principles set forth in
this document is provided to users for consideration and decision to implement.
♦ Piping LDE
♦ Piping Engineers
♦ Piping Designers
♦ Piping Checkers
2. SCOPE
Unless otherwise stated in the Project/Piping Quality Plan, this guide document
applies to all offshore platform projects carried out by TECHNIP.
3. REFERENCES
GE A 353 14 7
♦ ASTM F1166 : Standard Practice for Human Engineering Design for Marine
Systems, Equipment and Facilities
GE A 353 14 7
4. TERMINOLOGY
5. INSTRUCTIONS
The Platform orientation and elevations are generally most influenced by prevailing
wind, water current directions and water levels. When establishing the orientation
and space requirements of facilities, the following considerations should be taken into
account:
To maintain the integrity of the Safe Area, non-hazardous facilities shall be located
upwind and upcurrent (wind and water current are generally on the same direction) of
hydrocarbon and other hazardous facilities to ensure that:
1) In the event of a major gas leak prevailing wind will direct fire, smoke, and
escaping hydrocarbon gases away from the Safe Area as well as away from the
facilities.
2) In the event of a major oil spill prevailing water current will direct pool fires away
from the Safe Area as well as away from the facilities.
GE A 353 14 7
Compressor Air Intakes should be located away from hazardous area and
preferably upwind or crosswind to avoid vapour ingestion in case of leakage
from compressors and associated piping.
4) Airlocks
Separate air locks should be provided for Battery Rooms to avoid the potential
for hydrocarbon ingress from batteries to adjacent rooms.
Pool fires can occur when liquid hydrocarbons leak onto sea surface and ignite that
are likely to threaten the structural integrity of the Platform jackets. Hydrocarbon
risers, wellheads and equipment handling high volume hydrocarbon inventories shall
be located as far as downwind as possible as these facilities can leak and cause pool
fires.
GE A 353 14 7
Hydrocarbon risers constitute majority of flammable inventories that can create gas
clouds and oil spills of considerable size upon rupture. Locate hydrocarbon risers as
far as downwind as possible to take advantage of prevailing wind and water current
to direct gas leaks and oil spills away from the platform.
5.1.1.6 Helideck
• Helideck Elevation
Helideck should ideally be located above or at least equal to, all significant
surrounding structures such as platform cranes, telecommunication towers,
accommodation and other high structures or solid obstacles. This will minimise
interference and occurrence of turbulence and downdraft downwind of adjacent
structures.
Helideck should not be located more than 60m above sea level as helicopter
operations can be adversely affected by low cloud base conditions.
Conversely low level helidecks may also adversely affect helicopter operations due to
one-engine-inoperative performance characteristics. It should be noted that following
a power failure, it may be necessary for the helicopter to descend and gain sufficient
speed and safely fly away or to land on the water. The minimum level of the
helideck is generally 15m for Performance Class 2 helicopters however this requires
further confirmation from aviation authorities.
• Helideck Location
♦ Located at a safe area and helicopter should not fly over hydrocarbon facilities to
reach the helideck.
♦ Free from potentially explosive atmosphere, flare, vents and other possible
hydrocarbon releases.
GE A 353 14 7
♦ Clear from smoke emitted by generators, gas turbines and other emissions that
reduce pilot’s visibility as well as hot gas plumes during landing and take-off.
♦ Clear or at least away from solid blocks or structures that may cause air
turbulence and affects helicopter landing and take-off operations.
♦ Clear from platform crane other moving obstacles that may distract pilot’s
attention.
♦ Locate facilities adjacent to helideck within the permitted limits of 150˚ Limited
Obstacle Sector (LOS).
♦ Availability of clear air gap below the helideck to avoid excessive vertical airflow
that affects helicopter operations.
• Helideck Orientation
There could always be trade-off between helicopter crosswind operations and gas
releases, turbulent wakes, exhaust plumes towards the landing area.
♦ Upwind
♦ Crosswind
GE A 353 14 7
♦ Downwind
Locate helideck in such a manner that the obstacle free sector has the most
favourable direction for helicopter operations. Location and orientation should
ensure that helicopter operations should take advantage of the seasonal wind
directions by:
2) Clear Overshoot
Approach flight paths should provide for an overshoot which does not encroach
on the restricted zone in the event that the landing approach is aborted.
• Environmental Effects
GE A 353 14 7
• Aerodynamic Effects
Helidecks are basically flat plates and relatively streamlined structures and isolation
would present little disturbance to the wind flow. Difficulties arise because the wind
must deviate around the bulk of the offshore installation causing turbulent airflows
that can seriously affect helicopter operations. The effects fall into three main
categories:
♦ Flow around large items of superstructure, notably cranes, drilling derricks and
exhaust stacks.
♦ Hot gas flows emitted from exhausts outlets and flare systems.
Hot gas emissions from gas turbine generators( temperatures in excess of 400˚C are
normal) , generator exhaust from mobile units, flare radiation, are common sources
of sudden increases in environmental temperature over ambient can cause an abrupt
loss of engine and rotor performance at most critical stage of the helicopter
operations.
GE A 353 14 7
The helideck design should seek to ensure that no equipment and laydown areas
below helideck or adjacent to helideck are located to avoid bulky or tall items that
may cause turbulence.
1) Supply boats should normally approach against the prevailing wind and water
current directions to reduce the possible risk of impact to the Platform structure
upon power loss. Ideally boat landing location should be located parallel to the
prevailing wind and water current directions but it is also acceptable to locate
this perpendicular provided the supply boat can approach against the prevailing
wind and water directions.
2) The boat fender should extend away from the jacket structure to avoid collision
between the topside structure and Supply Boat mast. At least 1500mm
clearance from the topside structure and the Supply Boat mast is generally
considered adequate to compensate the Supply Boat movement during transfer
operations.
3) At the early stage of the layout, the Supply Boat details must be requested from
the Clients to support layout studies.
The location of flare downwind of the facilities would ensure that prevailing wind will
direct un-ignited hydrocarbon gases (in case of a flare failure), toxic gas
concentrations, and hot gas streams away from the Safe Area, air intakes, crane cab,
operating areas and adjacent Platform. On the contrary an ignited flare is also a
potential ignition source that could pose as a hazard when prevailing wind would
direct hydrocarbon leaks towards the ignited flare. Downwind location should not be
considered unless the flare is high or far (as in the case of a remote flare) to avoid
risk. The location of flare perpendicular the prevailing wind is generally the preferred
option as it eliminates most of the major risks.
GE A 353 14 7
Dispersion calculations will be required to establish the exclusion zones for supply
boat and helicopter approaches as well the relative location of hazardous vents away
for the facilities
The orientation of generator exhausts shall ensure that prevailing wind will direct
smoke and hot gases away from the Safe Area, cranes cabs, helideck, operating
areas, HVAC air intakes, generator air intakes.
Generator exhausts are generally fitted with spark arrestors with a tail pipe located at
least 4500mm away from air intake to avoid cross flow of fresh air and hot gas.
Gas Turbine Generators and Direct Fired Heaters generally burn toxic gases. The
characteristics of exhaust stacks should be arranged to ensure that toxic
concentrations of pollutants should not drift or settle at Safe Area and other operating
areas. These are generally located at least 2m outside the hazardous area with the
stack height defined considering SO2 dispersion and exhaust gas temperature profile
with respect to Crane Cab and adjacent elevated access platforms.
In case of emergency, the Platform orientation should allow the vessel to evacuate
the Platform safely by drifting away from the facilities with the aid of the prevailing
wind and water current.
The possibility of damage to the subsea pipeline and cable should be minimised by
ensuring that these are routed away from the Platform crane drop zones, boat
landing, Jack-up Rig approach and vessel mooring points.
The Platform Crane should be located on the same side as the Boat Landing where
supply boats approach during normal transfer operations.
GE A 353 14 7
In order to maximise power generation efficiency, the solar arrays should face the
sun radiation on the east and west directions where the sun rises and sets
respectively.. In addition to that it should also face towards southern or northern
hemisphere depending on the geographical location of the platform. Cantilevered
platforms are generally provided to allow supporting, inspection and periodic cleaning
of solar arrays. The location and elevation of the solar arrays must take into account
the following:
1) No structures or equipment should protrude and create shadow above the solar
arrays so as to reduce its power generation efficiency.
2) The solar arrays should be located away and well clear from the 180° falling
obstacle sector of helicopter approach and departure.
The Platform orientation should have the provision for a vessel approach to allow
installation of major future facilities without posing any significant obstacles from
subsea pipelines, flare / vent booms, interconnecting bridges, crane and other
sensitive facilities.
Any structure or equipment located in the wave zone shall be capable of withstanding
the forces imposed by wave impact, and facilities located at the splash zone region
must be protected from potential corrosion and marine growth. Factors dictating the
deck elevations include:
The topside structures should be located above the wave zones. Non-cylindrical
structural members often pose as a geometrical constraint in setting the Lowest Deck
elevation. To optimise the cost topside deck structures, it is normal to provide a
1500mm minimum air gap from the bottom of the lowest deck structure and above
the 100-year wave crest.
Consideration shall be given to “Green water effect” and particle velocity, especially
applicable to floating platforms and whose effect may be felt well above the air gap.
Design boundaries shall be defined at early stage and effect in piping material
selection and stress analysis to be taken into account for piping subject to these
forces (i.e. GRE or Plastic piping is not advisable to be installed in such areas)..
GE A 353 14 7
The Riser ESDV should be located above the 100-year wave crest and preferably
above 1500mm air gap to protect this from forces imposed by the highest wave
impact. It is also acceptable to locate the riser ESDV within the air gap provided this
is supported to withstand the loads imposed by the 100-year wave.
Consideration shall be given to “Green water effect” and particle velocity, especially
applicable to floating platforms and whose effect may be felt well above the air gap.
Design boundaries shall be defined at early stage and effect in piping material
selection and stress analysis to be taken into account for piping subject to these
forces (i.e. GRE or Plastic piping is not advisable to be installed in such areas).
To allow a gravity collection of effluents from the Platform, the Drain Tank shall be
located at the lowest level of the Platform. These should preferably be located above
the air gap of 100-year wave crest when it is practical. In most of cases the cost of
additional jacket legs and lifting/ transportation limitations of topside facilities would
require these to be located within the highest wave zone. In this case these must be
supported to withstand the loads imposed by the 100-year wave crest. 1 (Refer the
foot note)
The boat landing structures are normally designed into different stages of elevations
to cater for variations in water levels.
Utility connections at Boat landing Level should be located above the splash zone to
protect these from potential corrosion and marine growth. 1 (Refer the foot note on
Page No.15)
For Floatover installation, the topside and jacket configuration will be dictated by the
marine spread of installation barge. The platform orientation must also take into
account the installation of topsides facilities, with reference to prevailing wind
direction. Refer to Appendix 13 for a typical floatover installation photograph.
GE A 353 14 7
5.6.9 Examples
See Appendix - 3 for Typical Arrangement of manned and unmanned platforms, see
Appendix - 10 for Typical Arrangement gas injection platform.
6. FACILITIES LAYOUT
GE A 353 14 7
internal combustion engines, etc.) taking into account of the gas releases that can
occur in normal operation.
It is not the aim of Hazardous Area Classification to guard against the ignition of
flammable vapour from releases with a very low probability of occurrence, such as
catastrophic failures, though these must be considered during the layout stage.
Types of Hazardous Zones are generally classified into:
2) Locating the wellheads far away from ignition sources, fuel storage, and rotating
equipment.
3) Protecting these from dropped objects during drilling and workover operations by
providing a plated structural support above the Christmas trees.
4) Locating the conductors preferably within the jackets or outboard the jacket with
a provision for conductor fenders to protect these from the impact of Drilling /
Workover Rigs as well as from support vessels approaching the Platform.
The location and configuration of the Wellhead Area is also influenced by other
factors:
1) These must be located where adequate structural support can be provided for
the conductors, drilling and workover equipment.
2) These must be accessible by Drilling and Workover Rigs. The drilling rig options
shall be considered and evaluated during the early stage of the design.
GE A 353 14 7
requirements of the drilling program. Typically the drilling rig must be able to
reach all the slots without requiring the vessel to move to another location to drill
slots located at extreme locations.
Removable hatch covers shall provide over well slots for Drilling and Workover
operations.
The production and test manifold location shall take into account the required flowline
flexibility to compensate the wellhead movement and pipe thermal expansion.
See Appendix - 6 for Typical details of wellhead / Christmas trees and blow out
preventer
1) Riser Location
Risers contain the major hydrocarbon inventory in the platform. These can
create gas clouds and oil spills of considerable size upon rupture. Locate
hydrocarbon risers as far as downwind as possible to:
Take advantage of the prevailing water current to cause oil spills to drift
away from the Platform.
Naturally keep the risers far away from the Safe Area and known ignition
sources.
Routed away from the Platform Crane drop zones so as to keep these away
from dropped object during routine transfer operations.
Routed away from boat landing to protect these from supply boat impact
upon power loss and should the vessel losses draft on a shallow water.
Routed away from the jack-up rig approach and vessel mooring points to
protect from jack-up legs and during drilling, workover and maintenance.
Hydrocarbon subsea pipeline shall not be routed close to the Safe Area due to
the consequences of considerable gas leaks and pool fires that can occur and
cause a life threatening impact to the Platform.
GE A 353 14 7
The Riser ESDV's primarily isolates the pipeline inventory from the topside
facilities during emergency. In order to achieve maximum ESDV reliability
ensure that:
These are located on an operating level that can easily be accessed at all
times with sufficient area and lifting facilities to allow quick operation,
inspection, testing and maintenance.
These are located below the lowest level of the platform and close to the
base of the vertical riser in order to isolate the majority of the pipeline
inventory from topside incident.
These are located out of the path of projectiles emitted from an explosion of
adjacent equipment.
1) Launcher and Receiver shall be located in a well ventilated areas with their
doors facing outboard of the platform and away from adjacent critical facilities to
reduce the possibility of any projectiles from hitting personnel, adjacent critical
equipment and the Safe Area in the event of a closure failure.
2) Lifting facilities should be taken into account with due consideration for space
requirement for handling and storage of pigging tools. Horizontal launchers and
receivers suitable for intelligent pigging with nominal size 12” and above are
generally provided with lifting facilities.
3) The space requirements for pigging operation must be considered such as:
Riser bends
Approximate riser bend radii to allow passage of tools can be taken initially
as:
GE A 353 14 7
5) Where launchers and receivers are located adjacent to each other, a minimum
clearance of 500mm between should be maintained between valves and flanges
to allow adequate access for wrench and bolt tensioners.
7) Spheres may hold up or be destroyed if barred tees are used. The space
requirement for sphere tees should be considered when spheres are to be used
during pigging operation.
8) For horizontal receivers the barrel may be sloped (typically 1:100) down towards
the end of the closure to improve draining of liquids from the barrel horizontal
launchers may be sloped (typically 1:100) down towards the pipeline for
bidirectional traps the barrel should be level.
1) Gas compressors and its associated facilities such as scrubbers, coolers and
piping represent the highest gas release that create potential hazard due to
ignition associated with rotating equipment. Ensure that these are located on a
well-ventilated area to allow prevailing wind to disperse hydrocarbon gases away
from the area.
2) Compressors having horizontal split casing will require removal of top casing to
be removed before the rotor assembly can be lifted. The maintenance envelope
requires considerable space taking into account the weight and space
requirement for removable spools, top casing and the rotor assembly.
3) Compressors having vertical split type will require removal of the rotor assembly
without necessarily dismantling removable spools or other piping components.
The maintenance envelope requires less space as horizontal split casing type
but care must taken so as not to obstruct the rotor withdrawal area.
4) Compressor bearings receive lubricating oil from the lube oil console. These
consoles maybe standalone unit or directly mounted on the compressor
GE A 353 14 7
6.1.6 Vessels
2) The major axes of the horizontal vessels should be along the natural ventilation
path to reduce the potential for an explosion overpressure.
4) All instruments, stand pipes, sampling points should be located at one side of a
horizontal vessel to facilitate operation and maintenance.
6.1.7 Pumps
1) Pump suction and discharge should face and be located close to the equipment
from fluid intake.
2) When locating the pumps, ensure that NPSH requirements are met.
3) Where practical horizontal pumps should be grouped with the pump drives lined
facing the maintenance aisles so as to facilitate withdrawal of pump motor.
GE A 353 14 7
4) Specialists select pumps and the Piping Designer has little influence on the
basic selection. However the Layout Designer can request preferred orientation
for suction/discharge and NPSH limitations during the early stage of the design.
5) Some pumps require seal oil tanks that could take more space than the pump.
Ensure that the installation requirements of seal oil tanks are taken into account
when establishing the pump spacing.
6) MOL (Main Oil Line) Pumps should be located in well-ventilated area due to the
large inventory of high-pressure oil involved and potential hazards associated
with rotating equipment.
7) Pumps handling flammable products shall not be located under air coolers,
piperacks and vessels.
9) High-pressure charge pump should be separated from any other major process
equipment and other pumps.
10) When locating pumps, consideration shall be given to minimum straight run
requirement on suction (and sometimes discharge) piping, specially for large
diameter piping.
2) The working areas shall be kept clear of any piping and accessories to facilitate
removal of tube bundle, channel, shell cover, as well as for maintenance and
cleaning.
3) Provide lifting facilities and ensure the tube bundles can be withdrawn easily
without posing any hindrance to escape route.
5) Plate type heat exchangers require access for the opening of covers and
removal of plates.
6) Provide adequate space around the heat exchangers for the portable pickling
and passivation tanks that will be used during routine and turnaround
maintenance.
GE A 353 14 7
Gas Air Coolers bundles are highly vulnerable to damage within a few minutes under
fire exposure. Air movement increases the fire escalation and that the failure of a
tube could release additional combustible fluid to the fire hence these are considered
as having the high ability in promoting fire escalation. In the sitting of air coolers, due
consideration shall be taken of the fire hazards associated with the release of
flammable fluids that could be in contact from equipment and piping beneath or
adjacent to the coolers.
These are traditionally located above the main pipe rack and strategically located
such that all burdens can be lifted out without lifting over live hydrocarbon equipment.
1) Fired Heaters (at least 10m) and Gas Compressor (at least 5m) must be located
away from Air Coolers.
2) Pumps, other equipment, valves and flanges handling hydrocarbons should not
be located below the air coolers.
4) The cooler tube bundles are susceptible to mechanical damage hence these
must be afforded with maximum protection from dropped objects by keeping
these away from crane dropped zones during routine maintenance.
5) Air Coolers shall be located so that the hot air emitted is not a hazard or an
inconvenience to personnel and has no adverse effect on the operation of
adjacent equipment. Generally these are preferably located downwind of the
facilities to take advantage of the prevailing wind to disperse hot air away from
operating areas.
6) Care shall be taken when placing induced draft and forced draft coolers adjacent
to each other so as to ensure that personnel maintaining the cooler fans of
induced coolers will not be exposed to hot air coming from the forced draft
coolers. Locate induced coolers upwind of forced draft coolers to take advantage
of the prevailing wind to disperse hot air away from operating area.
7) Cooler elevations should not be set lower than any nearby elevated access
platforms to avoid the potential for hot air being directed towards adjacent
operating areas. If unavoidable needs to be studied / coordinated with safety /
projects.
8) Where possible, air coolers should be grouped with a common elevation. Air
coolers of different fan intake elevation shall not be located adjacent to one
another to avoid hot air recirculation.
9) Platforms are required below the air cooled exchangers to access the motors
and fan drives. These platforms must allow access without scaffolding. The
height of the fan inlets of forced draft coolers or of the underside of the bundle of
GE A 353 14 7
induced draft coolers shall be at least one fan diameter above the nearest solid
horizontal obstruction to airflow.
10) For forced draft air coolers permanent maintenance access beneath the fans
must be provided, the area and construction of the fan access platform must not
restrict the air flow to the fans.
11) Where coolers are located above piperacks, the minimum clearance should be
at least 2.4m from the top of the pipes with due consideration for the minimum
headroom to maintain the motors.
12) Supports of the air coolers should preferably coincide with the piperack width to
transmit the air cooler loads to the piperack column.
14) The maximum tube bundle overhang is taken as 1m from the cooler column
supports.
15) Provisions for thermal expansion of the tubes shall be taken into account. The
tubes must be free to expand independently of the structure. Nozzles between
the tube bundles shall be fixed end to minimise thermal expansion stresses.
Flare Knockout Drums are critical equipment during emergency depressurisation that
their locations require protection from the hazard from adjacent high pressure/high
volume hydrocarbon inventories, ignition sources and rotating equipment. These
drums generally handle H2S and it is always mandatory to locate these at well
ventilated area, preferably at the end, downwind or crosswind of process area where
prevailing wind can provide aid to disperse toxic gases away from the Platform.
Free draining condensate from flare headers towards the drums always dictate these
equipment to be located at the lowest level of the platform.
To maintain a dry gas supply, Fuel Gas Scrubbers should be located below the users
to allow free draining condensates from the headers back to the scrubber.
1) Centrifuges
GE A 353 14 7
The supporting structure must provide for space for the removal of the entire
centrifuge.
2) Filters
2) The routine operational swing zones shall not pass over live equipment and
facilities “containing hydrocarbons” unless the same has been provided with
adequate dropped object protection (DOP). Crane movement above such
equipment shall be performed only for major maintenance activities after the
equipment have depressurised and drained and all safety measures put in place
by Operators.
3) Platform Cranes are generally provided with boom rest and sheave maintenance
platform.
4) A further consideration is the capacity and reach of the platform crane to rig
workover equipment.
The study considers the normal operational activities that will be carried out during
the lifetime of the facility. Other activities such as construction/ installation and initial
startup will not be part of this study and must be considered in the construction
procedures.
The study should be performed once Plot Plan, material handling study (philosophy)
and equipment list has been issued for Client approval.
GE A 353 14 7
2) Lifting routes will be identified as such to minimize the requirement to lift objects
over live equipment or areas where significant damage could occur.
3) Where possible, lifts will be routed to avoid passing over hydrocarbon equipment
and systems. This includes sea-lines from platforms.
4) Each lift will be carried out within the capacity of the lifting device.
6) The potential for damage from a swinging load will be minimized. Items to be
lowered on designated areas (deck laydown area) before transporting them, by
trolleys, trucks and transportation devices, to the required destination.
Diesel Storage Tanks may be potentially hazardous due to liquid fuel contained and
the associated venting of gases. These should be remote or otherwise protected
from wellheads and potential sources of ignition such as rotating equipment,
workshops and Living Quarters.
Local, not normally manned Control Rooms and Switchgear, MCC rooms may be
located outside the Safe Area adjacent to the respective equipment where
appropriate.
1) Gas Turbine Generators shall be located in Safe Area and remote from process
area as practical.
2) Suitable laydown areas shall be provided close to the equipment for the
components dismantling during maintenance. Such components include
sections of acoustic enclosures, casings, ducting, covers, rotors, and sections of
exhaust diffuser.
GE A 353 14 7
Diesel Engines located at hazardous areas are generally provided within enclosures
to reduce ignition probability.
The Safe Area provides a safe environment for Platform monitoring and control from
which to supervise emergency response. The facility control centre shall be situated
and protected such that it remains unaffected by any hazardous events occurring in
the Platform. This shall be designed such that its endurance for prolonged events is
compatible with the overall plan for escape and evacuation. It shall not only include
structural endurance but also for the continuous provision of supporting utilities such
as power, communications, air supply, firewater, controls, etc. The facilities located at
the Safe Area generally include:
1) Living Quarters
2) Temporary Refuge
5) Helideck
8) Control Room
9) Instrument/Technical Room
18) Workshops
GE A 353 14 7
20) Offices
21) Laboratories
To ensure the integrity of support facilities at Safe Area layout considerations must
take into account:
Living Quarters are permanently manned where personnel maybe sleeping thus
reducing their capacity to react during emergency. Their location and occupancy
shall therefore ensure that these are protected from fires, explosions, noise,
unpleasant odours, and shall be located in an area so designed to provide personnel
a sense of safety and remoteness from operations. Because Living Quarters are
potential source of ignition, these shall be isolated from fuel sources to the greatest
extent practical.
The firewall maybe an integral part of the Living Quarters. In this case, windows
facing the process area shall be eliminated and other openings should be minimised.
6.3.3 Helideck
1) Do not use handrails at landing areas, as these are potential obstacles. In lieu of
the handrails, provide safety nets around the helideck for personnel protection.
2) There should be minimum two access points to the helideck. The arrangements
should be optimised to ensure that:
Personnel will be able to escape upwind of the landing area in the event of
accident at helideck level.
GE A 353 14 7
3) Ensure that the foam monitors will not cause injury to escaping personnel when
these are in operation during emergency situation.
Control Rooms are permanently manned. As their operation are strictly for authorised
personnel only, the access corridors shall be arranged to ensure that personnel will
not pass through the Control Room to access other rooms. Control Rooms should be
located near the bridge landing and at least at most accessible deck to allow a quick
response and evacuation during emergency.
Instrument/Technical Rooms are not permanently manned with limited occupancy for
authorised personnel performing controlled activities. These shall be located in Safe
Area and away from the process area as these are housing ignition sources and
essential equipment and instrument for emergency.
Power Generation and Distribution are potential sources of ignition. These are
located upwind or crosswind of the Platform and segregated from hazardous areas to
ensure a reliable power source during emergency. All equipment associated with
emergency power (generator, switchboard, batteries, rectifiers, inverters, etc.) shall
be located in non-hazardous areas with adequate protection against fire and
explosion. Other layout consideration include:
Diesel Storage Tanks in the Safe Area shall be limited to Day Tanks contained in
the equipment base of the Diesel Generators. Bulk Storage Tanks shall not be
located at the Safe Area.
2) Battery Rooms
Battery rooms are sometimes classified because of hydrogen evolution from the
batteries. These can be unclassified provided that the enclosure is adequately
ventilated with a provision for a vent outside the enclosure.
3) Transformers
GE A 353 14 7
6.3.7 Workshops
Workshops are not permanently manned and generally house equipment that is
potential ignition sources and where hot work normally takes place. These are
located outside the hazardous area, pressurised or purged with air from a Safe Area.
Workshops should preferably be located where these are readily accessible by
Platform Crane or other handling devices.
Store Rooms are not permanently manned and generally contain flammable
materials such as paint should be located outside the outer edge of the deck away
from the Safe Area and most likely escape routes.
6.3.9 Offices
Offices are permanently manned that may include personnel who are not aware of
the specific danger of an installation containing hydrocarbons. These should
preferably be located at the edge of any restricted area and at a sufficient distance so
that life is not endangered in case of explosion and subsequent fire.
6.3.11 Laboratories
Laboratories shall be located away from Control Room due to the potential of
possible toxic gas from samplers.
Laboratories could be located at hazardous provided the air intake of the HVAC
system is at a safe area.
GE A 353 14 7
during fire emergency. The arrangement shall ensure that a single fire or explosion
can not impair their capacity to meet firewater demand. The acceptable
arrangements are:
Two pumps are located close to each other and separated by a firewall to avoid
the potential for a single fire or explosion that could render both pumps
inoperable. This alternative arrangement should only be considered when
remote location is not practical.
6.3.14 HVAC
Heating, Ventilating and Air-conditioning (HVAC) forms part of the essential safety
services of the Platform and complements area classification requirements
associated with electrical equipment. HVAC systems are provided to:
2) Provide comfort, health and welfare in manned areas and appropriate operating
environment in other enclosures.
GE A 353 14 7
auxiliary equipment into the overall Platform layout during the early stages of design.
Machinery and equipment for this service are usually arranged in a separate area.
To ensure the integrity of the Safe Area, hydrocarbon bearing lines shall not be
routed across or in the vicinity of the Living Quarters, Control Rooms Electrical
Rooms, Instrument/Technical Rooms, HVAC and other critical services. Where a
bridge landing is located at the vicinity of the Safe Area, welded joints should be
considered in lieu of flanged joints.
Noisy facilities must be segregated from quiet facilities and dry facilities must be
segregated from wet facilities.
6.4 Bridges
1) Locating risers and hydrocarbon bearing equipment away from the bridge.
5) Not locating facilities particularly workshops and electrical substations. The only
exception is the fire monitors located strategically along the bridge.
6) By providing adequate headroom for the supply boat to pass under the bridge
when required.
6.5 Piperacks
Keep all process, large, alloys, exotic and heavy wall lines as short as possible.
GE A 353 14 7
Locate utility lines such as air, water, nitrogen, steam at highest level.
Locate large lines near the columns in order to minimise bending moment and
yield a light piperack structure.
Sloping lines should be grouped together to allow a flat turn expansion loop and
to simplify a common support attachment to the piperack.
Where practical, do not locate piperack spurs opposite to each other (“cross”) to
avoid complicated piping crossings.
Routing of sloping flare lines towards a large diameter Knock-out Drum will
dictate considerably high elevation that sets this apart from other lines on the
piperack. To support this independently or integrate along with the other lines
require careful planning and studies.
If cable trays are required to be routed on the piperack, locate these at highest
level to keep these away from possible hydrocarbon spills in case of leak.
These can be integrated along with utility lines if space permits and should be
located close to the piperack column for ease of inspection and maintenance.
The area below the piperack should be kept clear of obstructions for mobile
equipment access during maintenance.
20- 30% of piperack width is generally recommended space for future lines.
Spare capacity is preferred to be provided separately on each tier to provide
flexibility to distribute the future expansion of piping services among the tiers.
Alternately, create a separate a spare tier at top level for ease of installation in
the future.
The width of the piperack should remain homogenous for the entire length of a
unit to allow a clear passage of mobile equipment under the piperack.
GE A 353 14 7
Steel is used for piperack for ease of construction, future expansion, has more
flexibility to accommodate make-up supports.
The layout should take into account the installation of future facilities considering the
following:
The potential for errors during operations and maintenance is greatly reduced with a
simple equipment arrangement whose function, status, controls and interconnections
are transparent to all. To increase the degree of inherent safety, ensure that the
layout is presented in a clear and concise manner by:
2) Grouping equipment of the same service that shares common utility and
maintenance requirements together in order to reduce the degree of piping
interconnections, as well as to minimise hydrocarbon inventories as a result of
optimum piperuns. Crossovers between sections of the Platform can cause
confusion during operation and maintenance and tends to increase the
complexity of control and shutdown logic.
GE A 353 14 7
Human Factor is a separate study that must be considered and applied during the
early design stage of Projects and incorporated in layout.
Accessibility identifies the effort required for a healthy human being to reach devices
such as an instrument, measuring element, instrument process connection,
instrument utility connection, block valve or sampling point for the purpose of
operational attention or regular maintenance. It includes the ability to reach such a
device with all tools required to perform operational attention or maintenance.
Accessibility levels are defined as follows:
1) Permanent Accessibility
GE A 353 14 7
2) Limited Accessibility
3) Poor Accessibility
4) Inaccessibility
Apart from the requirements for specific types of components and instruments as
given in the relevant sections, field-mounted instruments shall be installed
considering the following aspects:
5) Heavy equipment such as control valves and inline flow meters of 4” NPS and
larger and all positive displacement meters and turbine meters should be
GE A 353 14 7
6) Instruments and their impulse lines shall be surrounded by sufficient free space
to allow rodding-out of process connections and the removal of:
Permanent and easy access for maintenance purposes used to be the dominant
factor in selecting the physical location of plant mounted instruments. This resulted in
long impulse lines and additional ladders/platforms.
The objective in Platform design is economy in the use of space and Platform
volume. Providing space around individual equipment would generally imply an
increase in the allocated space. Space sharing is an effective solution to meet the
usual Platform design limitations and arrive with a reasonable access. This can be
achieved by:
1) Grouping of Equipment
2) Laydown Areas
Where possible, locate laydown areas common to other items to minimise deck
space.
3) Escape Routes
4) Stairways
GE A 353 14 7
5) Platform Volume
Consider using elevated platform over low level piping versus congesting upper
areas with piping. Utilise Mezzanine platforms as much as possible to make
most effective use of Platform volume.
The requirement for access around equipment as well as the overall facilities shall be
considered carefully during the early stage of the design taking into account the
following factors:
3) Equipment that requires attention on less regular basis need not be provided
with permanent platforms or ladders unless emergency access is a requirement.
4) Provisions should be provided for all routine operations that will involve handling
and storage of materials.
6) Equipment parts, instruments, valve handwheels, and piping shall not protrude
into the access ways.
7) Provisions should be made to prevent contact with hot and cold surfaces.
4) Catalyst change-out
5) Well testing
GE A 353 14 7
6) Drilling/workover
Where simultaneous drilling and production may take place, sufficient space should
be available for pipe handling, mud handling, chemical deliveries, sludge removal,
workover equipment, and other well operations without interfering with production.
1) Access Platforms
Elevated access platforms should only be provided where operating areas are
not accessible from Platform deck levels.
2) Stairs
3) Stairway Landing
4) Ladders
GE A 353 14 7
Passive Fire Protection performs its function without relying on activation. The
primary function of passive protection is to retard the rate of temperature increase of
vital equipment and/or supporting steel structures to allow continuous operation and
prevents failure during emergency. It gives protection only for a limited time and is
only effective adequate when Active Fire Protection and fire-fighting capabilities can
be deployed before the system loses its protective properties. Passive Fire Protection
is normally applied to:
GE A 353 14 7
1) Fire/Blast Wall
2) Firewalls
The Firewater Main is normally designed as a ring or loop with sectioning valves to
provide a reliable source of firewater supply on demand. The piping layout must
ensure the integrity firewater ring main by:
GE A 353 14 7
♦ Routing this away as far away from process area and surrounding structure
affords maximum protection to the pipework to reduce the possibility of damage
from fire, explosion or other occurrences.
Locate deluge valves adjacent to escape routes and outside the protected area to
allow easy operation by evacuating personnel.
Locating deluge valves and deluge valves manifolds, needs to take into consideration
the effect of potential jet fire reaching the fire fighting system protection can be
achieved locating the manifold for away of providing a fire wall.
The goal of the Fire Monitor is to provide a reliable means for personnel to
supplement deluge and sprinkler system by directing water at specific areas.
Monitors are oscillated or operated automatically and may be required at strategic
locations and utilised for the application of water or foam. The location of monitors
must ensure so as not to impede escape routes, away from radiant heat, and it is a
hazard to personnel when it is operated. The isolation valve must be located local to
the monitor to facilitate maintenance.
The goal of Fire Hydrants is similar to Fire Monitors and these are operated through
manually deployed water discharge equipment. Hydrants are often located along
access routes with their cabinets mounted adjacent to the hydrants to store hose,
couplings and branch pipes. The isolation valve shall be located local to the monitor
to facilitate maintenance.
Hose Reels are manually operated fixed units that are permanently connected to the
firewater ring main. These are operating with a lower flowrates that can be deployed
more quickly than the fire hydrants. Consequently hose reels are used only in Safe
Areas and in some cases in Helideck and process areas where they deliver foam to
back up monitors.
GE A 353 14 7
AFFF (Aqueous Film Forming Foam) are used where foam is capable of
extinguishing liquid fires. These are skid-mounted, consisting of premix foam tanks
proportioner with controls interfaced with fire and gas panels. Individual deluge
valves are provided for each area to be protected.
Twin Agent Units are used where large scale of spill oil fire is expected. These are
skid-mounted equipped with AFFF and compatible dry chemical agent and discharge
hose reel.
Portable Fire Extinguishers are strategically located around the Platform for first aid
fire fighting purpose on small fires. Wherever possible their locations are coordinated
along with the positions of hose reels, and along escape routes. Space margins
should be taken into account to accommodate portable extinguishers along operating
areas, enclosures and escape routes.
9. PLATFORM EVACUATION
Personnel shall be provided with adequate facilities to evacuate the platform during
emergency. In principle three methods of evacuation from Offshore Platform are
generally provided:
2) Lifeboat Location
GE A 353 14 7
♦ Environmental Considerations
Prevailing wind and water current shall not direct lifeboats towards the
jacket structure.
♦ Launching Orientation
Where practical, the launching orientation should be away from the platform.
When two or more lifeboats are required, the location shall ensure that
lifeboats do not cross each other's path when launched.
♦ Obstacles
Methods of rapid evacuation from the platform should be provided to allow for
incidents, whose severity and speed are such that an orderly, controlled evacuation
could not take place. A tertiary method of evacuation shall be provided to permit
direct access to the sea.
1) Liferafts
Particular precaution to be taken locating life boats on floaters. Life boat may be
used during platform’s damaged conditions which are usually considered around
15 degrees inclination. Consider this condition to ensure that the boat launching
path will not hinder the deck(s) or hull below during damaged conditions.
Liferafts are generally cradle mounted and weighing approximately 180 kg that
will require certification every 12 months hence lifting facility should be
considered.
GE A 353 14 7
2) Lifebuoys
Lifebuoys are located at strategic points around the Platform. Actual numbers of
Lifebuoys is visible from any point on the outside walkway of the Platform.
Evacuation routes are defined as leading from the Temporary Refuge to the point of
departure from the installation. They should be designed to allow for the fact that
they need to be usable by a large number of personnel, including stretcher case, and
injured persons at a time when fire may be well established. A minimum two
evacuation routes should generally lead from Temporary Refuge to:
♦ Bridge
♦ Lifeboat
♦ Hellideck
Primary Escape Routes are generally located at the periphery of the platform that will
direct personnel from working areas to Temporary Refuge or to the point of
evacuation. A clear width of 1200mm and 2200mm headroom is typically maintained
to permit the passage of personnel bearing injured personnel. Wider escape routes
(1500mm wide) are required where more than 50 personnel are present such as
accommodation areas.
Secondary Escape Routes are generally located at working areas that will direct
personnel to Primary Escape Routes. A clear width of 1000mm and 2200mm
headroom is typically maintained where escape in one direction is required.
A minimum of two separate and remote exits shall be provided to enclosed or open
areas. Where practical, escape routes should form as a ring external to the
GE A 353 14 7
9.4.5 Arrangement
1) Hazardous vents
2) Hazardous chemicals
3) Laydown areas
4) Hatches
5) Explosion panels
9.4.8 Protection
Escape routes leading to the Temporary Refuge may require protection from direct
exposure from intense heat coming from fire or flare radiation passive or active
means of personnel protection and generally provided such as water curtains, heat
shield and fire/explosion shield.
9.4.9 Doors
Hinged doors from enclosed area shall open outwards in the direction of escape
routes and should open into the non-hazardous area if these are used as a normal
access adjacent to hazardous areas.
GE A 353 14 7
Where applicable, escape routes should be separated from material handling routes
like monorail access.
The primary Muster Areas will normally be provided within the Temporary Refuge.
There shall be sufficient free floor area at each muster location to accommodate one
full lifeboat complement of 0.56 m2 per person, with an additional allowance for
stretchers and breathing apparatus if required. The number of areas may
correspond with the number of lifeboat. A minimum requirement is to provide Muster
Areas for each of the Lifeboat required in evacuating the full personnel on board.
The limited space at unmanned Platform generally leads to a Muster Area located at
hazardous area.
Permanently manned Platforms laden with H2S are generally provided with
emergency Breathing Apparatus to protect personnel where an emission of toxic gas
may occur. Breathing Apparatus are located at Living Quarters, Lifeboat Muster
Areas, and Liferafts station with facilities for off-take from Cascade Breathing Air
System. Air reservoirs are provided for all personnel with adequate space at off-take
stations to ensure that no congestion will occur during emergency.
Refer GE-A353-13.
GE A 353 14 7
subject to special construction techniques that are beyond the scope of Material
Handling Study.
Dropped Object Studies will be performed under a separate review and report.
Mechanical handling aids should be provided when transfer materials exceed manual
handling limitations. Where direct lift access from the platform cranes is not available,
lifting devices such as monorails, lifting lugs, chain hoists, and davits should be
provided where applicable. Provision should also be made for these components to
be transferred to a laydown area where these can be lifted by the platform cranes.
The Platform Crane will support normal transfer operations from/to supply boat and
transfer operations between laydown areas on different decks of the Platform.
GE A 353 14 7
Monorails should used to lift materials and where horizontal movement is required to
transfer these to another location such as laydown areas, stores and workshops.
These are installed along with trolley hoists fitted with safety device against wheel
failure. Where loads exceed 2 Tons, the use of monorail to transfer material is
desirable.
10.2.4 Trolleys
Trolleys with inflatable or solid wheels that can spread over grated decks should
generally be used to transfer materials around the Platform where materials are 1
Ton and below. These are suitable of being pulled or pushed manually and able to be
steered around corners. Trolleys are equipped with steering at both axles with fail-
safe brakes and these are used in association with lifting devices as these capable of
lifting materials. Approximate size and weight: 1200mm L x 900mm W x 270mm H
(excluding pushbar) and weighing 32 kg.
Pallet Trucks should generally be used over plated deck to transfer materials around
the platform for loads ranging from 0.5-2 Tons. Like Trolleys, these are suitable of
being pulled or pushed manually and able to be steered around corners. Pallet
Trucks are equipped with steering at both axles with fail-safe brakes. Unlike Trolleys
these are capable of lifting and lowering materials that can be controlled through its
hydraulic handle or tugbar. Approximate size and weight: 1600mm L x 600mm W x
80mm H (excluding tugbar) and weighing 80 kg.
Adjustable girder clamps should be used in combination with chain hoists where pre-
installed lifting lugs are not practical.
10.2.8 Davits
In view of the risks involved in lifting transfer materials above process equipment
during normal operation, davits are usually used to handle large size relief valve,
other components and equipment internals on elevated platforms of equipment. A
GE A 353 14 7
clear lifting access shall be provided with a provision for a laydown area at Platform
deck level for further transport by handling devices. Davits are also used over
hatches or elevated working areas where other lifting devices are not practical to use.
Pulling devices should be used when materials would be moved horizontally. The
proper operation of these devices requires temporary padeyes located on columns,
walls, or floors where cables could be attached.
Manually operated hydraulic “elephant” cranes should be used to lift materials over
plated areas. The combination of lifting and lowering movements gives a high
flexibility of handling materials up to maximum capacity of 1 Ton. These are used in
association with trolleys, as these are not recommended for horizontal transportation
of materials.
Temporary Frames are lightweight bolted construction complete with trolley hoist that
can easily be assembled and dismantled with a provision for height adjustment.
Temporary frames should be used for the smaller, lighter items that may require
handling that were not specifically itemised in the handling procedures.
Plated Platform deck has the benefit to accommodate pallet truck for easy transfer of
materials in the Platform. In view of the risks associated with explosion overpressure,
deck grating is generally preferred as opposed to deck plating in order to aid
dispersion of hydrocarbon gases. As a minimum, plated decks for pallet truck access
are should be provided to facilitate handling and transfer of materials.
10.2.13 Ramps
Ramps should be provided where trolleys/pallet trucks pass across bunded areas.
GE A 353 14 7
The supply boats will normally carry workover materials and logistics supplies. For a
manned Platform, ensure the facility has provision for a supply boat berthing facility.
Jack-up Barge and Derrick Cranes would only be used during major maintenance
and shutdown and where main equipment or materials can not be handled by the
platform cranes.
1) Laydown areas should be provided for all items that need access for component
removal.
5) Where possible, laydown areas should be visible from the crane operator.
6) Laydown areas are generally plated with drain outlets to contain hydrocarbon
and hazardous effluents.
1) Ensure that crane operator has a direct view on the supply boat deck.
2) Ensure that the Platform crane must be able to access supply boats approaching
the platform during normal transfer operations.
3) Ensure that the Platform crane setting elevation and location meet maintenance
and Workover requirements.
4) Provide safety barriers at sensitive locations where vulnerable facilities are prone
to damage due to frequent crane movement.
6) Where possible, safety escape routes should be separated from handling ways.
GE A 353 14 7
7) Ensure that no piping or other obstacles are routed or located below the
monorail to allow a safe transfer operation of materials.
9) Provide storage areas for wireline equipment, pigging tools, and other platform
supplies.
10) Provide removable access hatches over Wellhead/Christmas trees and other
component below operating level where lifting is a constraint.
11) Ensure that there is adequate vertical clearance for lifting lugs and chain hoists.
12) Provide lifting facilities over large pumps motors and rotating equipment.
13) Minimise the number of pre-installed lifting lugs due to requirements of routine
certification.
Plot plan involves multi-discipline effort that is therefore imperative that this must be
checked by a Sr. Piping Designer in terms of drawing formats but safety, process,
maintenance, operation other highly technical design elements must be checked by a
Installation and HFE Engineers. Checking must be supported by a comprehensive
Checklist (list can be expanded as required) outlined in Appendix - 1.
12. FEEDBACK
As this is a Guide Document, feedback from the end user for the documents and
working methods improvement is important. Suggestions about the document itself
should be directed to the Piping Head of Discipline.
All suggestions must be in writing. Feedback form is included at the end of this
document (see Appendix - 14).
13. RESPONSIBILITIES
The Piping Head of Discipline is responsible for ensuring that this procedure is
applied for each Project, where applicable.
This procedure is valid from the date of signature and appearance in Lotus Notes.
The distribution of the procedure is the responsibility of the Piping Head of Discipline.
This procedure is issued to all personnel having access to the Lotus Notes system.
Personnel not having access to Lotus Notes shall be copied the required documents
on an “as-needed” basis separately by the Discipline QMR.
GE A 353 14 7
The Piping Discipline Secretary retains the signed original of this procedure.
Standard forms referred to within the procedure are available for view and printout
from the attachment files in Lotus Notes. Forms to be completed in the computer are
accessible in the “O” drive on a “read-only” basis. No modification or revision to any
form is allowed without notifying Discipline Head.
When revision of the Guide Document is required, the Discipline Head of the QMR
shall print the affected part of the procedure. The electronic file will be revised,
incorporating the comments and issued at the next revision at the discretion of the
Discipline Head.
GE A 353 14 7
APPENDIX 1
(8 PAGES)
GE A 353 14 7
♦ = Checked
Item
Details N/A = not
No.
applicable
1.0 DRAWING CHECK
1.1 Title
1.2 Drawing and sheet number
1.3 Revision number and description
1.4 Presence of all required signatures
1.5 Key Plan
1.6 North arrow
1.7 Prevailing wind direction
1.8 Wind rose
1.9 Scale
1.10 Presence of graphic scale
1.11 Notes
1.12 Line densities, text heights, presentation
1.13 Equipment Schedule
1.14 Legend
1.15 Matchlines
1.16 Battery Limits and Boundaries
1.17 Reference drawings (Field Layouts, Plot Plans, Equipment List)
1.18 Sections correctly cross-referenced to plans
1.19 Steel grid references
1.20 Deck Level Designation (Cellar Deck, Lower Deck, Main Deck, etc.)
1.21 Extents of plated / grated decks in accordance with Safety requirements
1.22 Dimensions and elevations
1.23 Primary steelwork, access platforms, staircases, ladders, handrails
1.24 Firewalls and cladding for buildings and rooms
1.25 Equipment are shown to the correct size
1.26 Mean Sea Level
1.27 100-year wave crest
1.28 Splash zone
1.29 Escape routes are shown
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
GE A 353 14 7
APPENDIX 2
(3 PAGES)
GE A 353 14 7
Required Level of
Access Access
Fixed Ladder
Accessibility
Scaffolding
No. Description
Platform
Platform
Portable
Ladder
Mobile
Fixed
A AROUND EQUIPMENT
Manhole less than 4m above deck level 2 No No Yes No No
Manhole more than 4m above deck level 1 Yes No No No No
Vent and drain 2 No No Yes No A
Utility connection 2 No No Yes No A
Top nozzles 2 No No Yes No A
Spectacle blind, spades and spacers 2 No No Yes No A
Removable spools 2 No No Yes No A
Local mounted pressure indicator(Note 4) 2 No Yes No No No
Pressure switches and transmitters 2 No No Yes A No
Local mounted temperature indicator(Note 4) 2 No Yes No No No
Thermocouple or resistance temp. detector 2 No No Yes A No
Tank gauge 1 Yes No No No No
Level gauges 1 Yes A No No No
Displacer/float type level controller 1 Yes A No No No
Differential head type level transmitter 1 Yes A No No No
Capacitance level probe 2 No No Yes A No
Level switch 2 No No Yes A No
B VALVES
Regularly operated valves 1-1/2” and below 1 Yes A No No No
Regularly operated valves 2” and above 1 Yes No No No No
Emergency valves 1 Yes No No No No
Throttling valves 1 Yes No No No No
Bleed valves 1 Yes A No No No
Sampling connections 1 Yes No No No No
Utility stations 1 Yes No No No No
Deluge valves 1 Yes No No No No
Fire monitor, hydrant, and hose reel isolation valves 1 Yes No No No No
Firewater ring main sectioning valves 2 No No Yes No No
Process vents and drains 2 No No Yes A No
Sub-header root valve of utility piping 2 No No Yes A No
Purge connections 2 No No Yes A No
Hydrotest vents and drains 3 No No No No Yes
GE A 353 14 7
Required Level of
Access Access
Fixed Ladder
Accessibility
Scaffolding
No. Description
Platform
Platform
Portable
Ladder
Mobile
Fixed
Tie-in valves 3 No No No No Yes
Check valves 3 No No No No Yes
GE A 353 14 7
Required Level of
Access Access
Fixed Ladder
Accessibility
Scaffolding
No. Description
Platform
Platform
Portable
Ladder
Mobile
Fixed
Restriction orifices 2 No No Yes A No
Flow switches 2 No No Yes A No
Annubar flow sensors 2 No No Yes A No
Flow straightening vanes 2 No No Yes A No
Notes:
1) Levels of accessibility (To be validated on based on specific Project requirements):
Level 1- A device is considered permanently accessible if it is located not more than 500mm horizontally
away from and not more than 1700mm vertically above operating platform.
Level 2- A device has a limited accessibility if it is located not more than 1000mm horizontally away from
and at a height between 1700mm and 4000mm above operating platform.
Level 3- A device has a poor accessibility if it is located more than 4000mm above operating platform.
2) “A” denotes acceptable means of access.
3) Instrument access under Piping responsibility is limited only to direct mounted indicating instruments,
measuring elements such as orifice plates, body of in-line flowmeters, level controllers, level gauges block
valves of switches/transmitters, probes, thermocouples, and temperature detectors.
4) Limited accessibility is acceptable for direct mounted indicating instruments provided they could be read
from a permanent operating platform. The instrument should not be more than 500mm horizontally and
2000mm vertically from operating platform.
GE A 353 14 7
APPENDIX 3
(6 PAGES)
GE A 353 14 7
APPENDIX 4
(6 PAGES)
GE A 353 14 7
APPENDIX 5
(2 PAGES)
GE A 353 14 7
APPENDIX 6
(5 PAGES)
GE A 353 14 7
APPENDIX 7
(22 PAGES)
GE A 353 14 7
APPENDIX 8
(3 PAGES)
GE A 353 14 7
APPENDIX 9
(1 PAGE)
GE A 353 14 7
APPENDIX 10
(7 PAGES)
GE A 353 14 7
APPENDIX 11
(4 PAGES)
GE A 353 14 7
APPENDIX 12
(3 PAGES)
GE A 353 14 7
APPENDIX 13
(1 PAGE)
GE A 353 14 7
APPENDIX 14
(1 PAGE)
GE A 353 14 7
Any user who identifies an inaccuracy error or ambiguity is requested to notify the
originator. So that appropriate action can be taken. The user is requested to return
this page fully completed, indicating the amendment recommended.
To :................................................