You are on page 1of 9

!

@ SOCIETY FOR
VRGYAtm\'
PREPRINT
NUMBER
MINING, METALLURGY,
AND EXPLORATION, INC. 96-46
P.O. BOX 625002· LITTLETON, COLORADO· 80162-5002

PRACTICAL ELEMENTS OF PROJECT MANAGEMENT


FOR UNDERGROUND CONSTRUCTION

D. R. Gehring

Hecla Mining Co.


Lovelock, Nevada

For presentation at the SME Annual Meeting


Phoenix, Arizona - March 11-14,1996

Permission is hereby given to publish with appropriate acknowledgments, excerpts or


summaries not to exceed one-fourth of the entire text of the paper. Permission toprint in more
extended form subsequent to publication by the Society for Mining, Metallurgy, and Exploration
(SME), Inc. must be obtained from the Executive Director of the Society.
I. If and when this paper is published by the SME, it may embody certain changes made by
agreement between the Technical Publications Committee and the author so that the form in
which it appears is not necessarily that in which it may be published later.
Current year preprints are available for sale from the SME, Preprints, P.O. Box 625002,
littleton, CO 80162-5002 (303-973-9550). Prior year preprints may be obtained from the
Engineering Societies library, 345 East 47th Street, New York, NY 10017 (212-705-7611).

PREPRINT AVAILABILITY LIST IS PUBLISHED PERIODICALLY IN


MINING ENGINEERING
1

ABSTRACT description of how the work is to be performed, but


rather, a specific description of what will be performed.
Effective project management is an excellent This distinction is discussed in detail later. For now,
technique for meeting a goal through set, well-defined consider the scope of work as being formed by the goal,
objectives. Even though project management is objectives and design criteria. These three items are
successfully used throughout the world in various viewed simply as:
construction projects, underground mining has unique
characteristics that require approaches that vary from Goal: "The reason the project exists, the
classical project management theory. Typically, a end result"
project includes four main stages: definition, planning,
implementation and control. Definition and planning Objectives: "The necessary tasks required to
are often the most overlooked stages, but are arguably meet the goal"
the most important. This paper addresses practical
techniques for the definition and planning of projects Design Criteria: "The rules that will be followed
for underground construction. when performing necessary
activities to meet the objectives".
INTRODUCTION
The scope of work has a direct relationship with the
Creating projects to reach a goal is not new to schedule and budget as illustrated in Figure 1 (Ira Bitz
American industry. In fact, all major construction & Associates, 1991).
projects from sky scrapers to bridges are completed
using similar project management techniques.
However, modern project management is relatively new
and was not formalized until 1962 when NASA and the
Department of Defense recognized the necessity to
develop uniform project management procedures
throughout the aerospace industry (Moder, Phillips,
Davis, 1983). This management method was not
intoduced to the mining industry until the early 1970s
(Britton, 1983). SCOPE OF WORK
Project management typically follows an organized
Figure 1
process comprised offour main stages: definition,
planning, implementation and control. To illustrate the
To understand this relationship, assume the length of
importance of effectively utilizing definition and
each leg of the triangle represents the magnitude of
planning, actual examples from the underground mining
each item, and the peak of the triangle is a fixed point.
industry are presented. These examples will
Therefore, if the scope of work expands, this is
demonstrate the complexities of project management
represented by increasing the length of this leg.
for underground construction and provide an
However, because the scope of work is directly linked
opportunity to examine practical alternatives where
to the budget and schedule, it is not possible to change
appropriate.
the scope of a project without effecting either the
budget or schedule, Figure 2. Similarly, it is not
PROJECT DEFINITION
possible to change either the budget or schedule without
affecting the scope of work.
Definition is the most critical stage of a project.
This stage is the foundation from which the project is
built. As in a building, if the foundation is faulty, the
rest of the structure will, at some point, fail.
Projects not properly defined from the beginning can
result in a tremendous amount of wasted effort.
Similarly, project risk escalates if the appropriate level
of definition is never introduced. Examples, discussed , ,
later in this paper, show that where the project
definition was not accurate, the project was not
._-------------_.
SCOPE OF WORK
successful. Figure 2
Scope of Work This relationship is realized even with small changes
in the scope of work. The result of small incremental
Project definition is accomplished, primarily, scope changes over the life of the project is kno\'m as
through the scope of work. For underground projects,
scope creep. Each change by itself may seem
the scope of work should not be considered a insignificant, however, when combined, they can have a
2

dramatic effect on the scope and associated budget and enough ore existed in this area to warrant further
schedule. A properly generated scope of work will detailed exploration.
~ enhance project success and minimize the potential of All of the perspectives of the project intent varied.
scope creep. Consequently, the goal statement did not accurately
To further examine the importance of a properly reflect the desires of any of the departments. To
generated scope of work, actual examples from examine the goal statement critically, it is sometimes
underground projects will be used. Following an easier to take a literal perspective. For example, what
example, an alternative will be presented. The happens if a hole is abandoned before it reaches the
alternatives presented should not be considered the ore? The footage still counts against the 10,000 feet
answer, but rather a workable solution. even though no core is recovered from the area of
In order to maintain company confidentiality, the interest. Likewise, would four 2,500-foot long holes,
examples are taken from a variety of mining operations successfully drilled, complete the project? It may give
and have been changed so as not to identify a particular some limited delineation to the area but the exploration
company. However, the content, including actual cost, department intended to recover more than four sample
schedule, etc., have not been altered. intervals. Examination of this goal statement clearly
shows that it does not adequately define the end result
Goal: For many businesses, including many mining of the project.
companies, the concept of goal creation is second This project failed as a result of not meeting the goal
nature. However to avoid confusion, a goal statement that management had intended. Additional funds had to
here will be defmed as a one or two sentence statement be requested to complete the project.
that accurately defines the expected end result of a
project. The statement should be non-subjective and Alternative to Example I:
consistent with, and possibly even reference, a division
or company's overall goals. The goal statement presented in Example I does not
convey the intended end result of the project. An
Example I: Goal Statement alternative goal statement could read:

An underground mining company started a project to Define the potential of the East Zone
identify ore reserves within close proximity to existing area in a way that adds minable )
operations. After the geology department had identified reserves to the operations plan by the
an area that provided the greatest potential, the end of the fiscal year so that
following project goal statement was created: uninterrupted production can
enhance the division's business plan.
Drill 10,000 feet of core to delineate the East Zone
Vein area. In this example the end result, including a time
frame, is clear. Depending on one's perspective, there
The goal statement was generated by the exploration may not be much difference between Example 1 and the
department who knew what they wanted to accomplish. alternate goal statement. However, what may seem
The goal statement, to them, was something that obvious depends greatly on perspective. In order to
management required, and beyond that, had little value. save time and not waste effort pursuing projects that
From the exploration department's perspective, the goal will never (or should never) be funded, it is important to
statement was not a necessary form of communication take the time to generate a goal statement that can be
because the goal was obvious to everyone at the agreed upon by everyone. Often the vision of a General
property. Manager is different from that of a front line supervisor
An inquiry of the other departments on the property or exploration geologist.
contradicted the goal statement assumption of the Underground projects require particular attention to
exploration department. An examination of the the goal statement due to condition uncertainties. The
operations department revealed that the operator's more familiar the project team is with a project, and all
choice of project outcomes was immediate ore reserves. of the parameters that affect its outcome, the less time is
From their perspective, the plan had to include required for goal generation. For example, the time
establishing haulage ways and performing other spent determining the goal of building a new
activities to prepare for mining. Management thought it McDonald's restaurant is quite different from a project
had requested a project that would prove ore reserves so to expand an existing underground mining operation.
- a new production area could be developed with a The unknowns in each case are significantly different.
secondary project.
The exploration department, when producing the Objectives: After the goal statement is defined, the
goal statement, was thinking in terms of delineation, not next logical step involves determining which tasks are
definition to a standard of proven reserves. The actual required to achieve the goal. These systematic
intent of the exploration department was to show that definable tasks are the objectives. It is important to
note that the objectives are not a detailed description of
3

how the work will be done, but rather the measurable the underground mining industry is very traditional, or
non-distinct tasks that are required to meet the goal. because project management is relativity new and
) The objectives must be non-distinct, or general, so that unfamiliar within the industry. However, there seems
the desired end result is stated rather than the process to be a tendency to begin planning and scheduling the
used to reach the objective. detailed work without properly examining what
objectives need to be accomplished. Because
Example 2: Objectives conditions of underground projects are rarely
consistent, similar experience does not always apply.
An underground mining company started a project to Therefore, it is important not to limit the project's
develop and mine a secondary ore body. The project success by using historical procedures to pre-determine
goal statement required the following objectives: what methods will be used to meet the goal.
Objectives should face great scrutiny during their
Objectives: generation. It must be considered that every action that
1) Complete all engineering and construction brings the company closer to the goal is productive and
drawings. every action that does not bring a company closer to the
2) Procure equipment and materials for goal is not productive. (Goldratt, 1984). Therefore, if
development and mining. an action, or task, is not required to meet the goal, it is
3) Install 150 hp fans for ventilation. not an objective of that project. Conversely, if all the
4) Install services sufficient to support objectives are not defined and carried out, then the goal
development and production. cannot be reached.
5) Develop access drift ...
Etc. Design Criteria: The final step in the project definition
stage is the development of the design criteria. Design
The objectives offered in this example are somewhat criteria are the rules that are followed while working to
simplified, but very similar to the actual project meet the objectives. Often people refer to this stage as
objectives. This project ended with the successful listing the assumptions. Even though the design criteria
completion of all the objectives, however, the 150 hp contain assumptions, they must be a more
fans were the wrong choice for the application and did comprehensive list that identifies the known and
) not provide adequate air flow. engineered physical characteristics of the project, e.g.,
The failure of this project resulted from unbudgeted equipment, geology, ventilation requirements.
expenditures required to purchase larger fans. Establishing the design criteria may take the longest
amount of time in the definition stage. Depending on
Alternative to Example 2: the type of the project, varying degrees of engineering
may be required to determine some of the design
All of the objectives met the criteria of an objective, criteria. Additionally, if the project manager has been
except number three. For an objective to be in given a goal, rather than discrete specifications, then a
existence, it must be required to meet the goal. An short project should be undertaken to define the design
alternate objective for number three could be: criteria (Ira Bitz & Associates, 1991).
For a large or complex project, risks can generally be
3) Install the facilities to provide sufficient air reduced by developing the design criteria during a
flow to maintain air qualities at or below separate phase of the project. In this case, the
Threshold Limit Values. development of the design criteria is best handled by
sub-dividing the project into engineering and
This statement passes the test for valid objectives. It construction phases. The engineering phase provides
is a measurable, non-distinct task that is required to the definition and estimation that is ultimately used to
meet the goal. obtain funding for the second, or construction phase.
As mentioned earlier, the objective must be This division places only the funds allocated for
measurable so that everyone can tell when the objective engineering at risk without jeopardizing the funds
is reached, and it must be required to achieve the goal. required for construction. It has the additional
However, the objective must also be non-distinct in that advantage of formalizing the process of establishing the
it should not address the specifics of the actual work design criteria.
required.
A common problem in the mining industry is to skip Example 3: Design Criteria
the goal statement and objectives and start with the
detailed description of the actual work to be performed. An underground mining company began a project to
In this case, the type of fan to be installed was a expand reserves and increase productivity by
description of the work to be performed, not a constructing a system of drifts, continuous miners and
description of what was required. I like to call this conveyors. The project managers did very well in
condition Nike-itis, after the sales slogan popularized ensuring that the project had a well-defined scope of
by the Nike Company -- Just Do It! It may be because
4

work consisting of a goal, objectives and design During the planning stage the schedule and budget
criteria. are developed. These two items are very much related
The entire project was estimated at nearly and are often developed simultaneously.
$200,000,000. Unfortunately, during final engineering,
and after board approval, it was realized that the design Schedule
criteria for the particle size produced by the continuous
miners was incorrect. The mistake was fairly obvious. The schedule is used to predict, and later track, the
However, none of the production engineers or operators duration of a project. Typically the schedule is
had taken the necessary time to review the design generated by determining the duration of the individual
criteria with close enough scrutiny to catch the error. tasks required to complete the project. The sum of
The miners and conveyors had to be re-sized to these tasks (taking into consideration parallel tasks and
account for the change in design criteria. The design dependencies) generally define the total duration of the
change increased project cost by $50,000,000 above the project.
original, board approved, estimate. In estimating an activity's duration, the activity
This project failed due to erroneous information in should be considered independently of activities
the design criteria, resulting in a 25% increase to preceding or succeeding it. It is also best to assume a
project capital. normal level of manpower, equipment, or other
resources for each activity (Moder, Phillips, Davis,
Alternative to Example 3: 1993).
Much work has been done on generating project
The project scope of work was properly defined, and schedules through the use of Critical Path Method
the engineers that completed the initial design of the (CPM), Program Evaluation Review Techniques
miners and conveyor systems did so while considering (PERT) and Dynamic Programming (Moder, Phillips,
the design criteria. The failure occurred by not Davis, 1993 & Hartman 1992). This paper will not
effectively communicating all the aspects of the scope discuss the use of any particular technique, but rather,
of work to every department involved in the project. the importance of generating the necessary information
The project team should take the time to review all to properly schedule a project regardless of the
aspects of the project definition phase, including the scheduling technique applied.
design criteria, with every department involved. To generate the schedule it is important to first
Project management is only successful when the determine what tasks are required and what resources
project manager and his team have a clear are available to perform the tasks. These functions are
understanding of the project objectives and the factors best handled through the use of the Work Breakdown
needed to achieve the objectives (Britton, 1983). It is Structure (WBS) and the Organization Breakdown
not always easy to communicate with everyone because Structure (OBS).
operations people are busy. However, it is still critical
for the project manager to get input and buy-in for the Work Breakdown Structure: The Work Breakdown
scope of work (Fudge, 1995). Communication during Structure (WBS) is an effective means for planning the
the definition phase must be more direct than simply individual jobs or work packages that are required to
circulating reports or memos. meet an objective. In 1962 the Department of Defense
To facilitate the buy-in process, the commitment to and NASA jointly issued a manual entitled DOD and
give the definition stage a high priority must come from NASA Guide, PERT/Cost Systems Designs which '
the upper management level. Unfortunately, many included as a key feature the utilization of a Work
managers of mining companies do not request project Breakdown Structure. The DOD-NASA Guide
status information until after the definition and planning described the concept as beginning with the highest
stages. Usually the first reports circulated within a level of the program and dividing them into their
company refer to the activities, budget and schedule and component parts. These are further divided and
are intended for managing project variance. Even subdivided into more detailed units. The subdivision of
though this is an important function of project the work breakdown continues until it reaches the level
management, it does nothing to assist in project where the end item subdivisions finally become
definition. manageable units for planning (Moder, Phillips, Davis,
1993).
PROJECT PLANNING The work package can be considered a WBS level
task if it is clearly a subset of an objective generated
After the scope of work is defined, the planning during the definition stage. The WBS should be
stage can begin. For the project team it is important to continued to a level of detail that is appropriate for the
make the distinction between the definition and work to be performed. It is this level of detail and
planning stages. If the two stages are combined, it is planning that is important in underground mining where
easy to leave the definition stage prematurely. logistics can seriously hamper project schedules. At the
same time it must be realized that a practical level of
planning should be performed. For example, while it
5

may be important for an engineer to plan the logistics of The scope of work, once generated, should be
a four hour concrete pour, rarely is it necessary to plan subject to change only through a fairly high level of
each blast of a development heading (Fudge, 1995). authorization. To prevent scope creep, the finalized
To illustrate the use of a Work Breakdown Structure, scope of work should be looked at as law. The WBS on
an objective and associated work breakdown from a the other hand should remain somewhat flexible during
sample project are shown in Figure 3. For this example planning and construction stages to take advantage of
we will assume the requisite goal, objectives and design positive project variances.
criteria have been developed. Considering Figure 4, WBS# 2.2, if it was later
realized that the steel pipe could be replaced with a high
Objective: 2) Drive a drift from the 2300 Drill Station density polyethylene pipe, then the project should have
to the High Grade Vein the flexibility to allow for such changes. Provided the
change to the WBS does not affect the overall project
WBS 2.0 Drifting goal or objectives it should not be prevented. This does
not mean, however, that changes to the WBS should not
2.1 Clean-up and prepare 2300 Drill be communicated. One key to successful project
Station management is effectively communicating ideas,
2.2 Install new steel 2" water and 4" air desires and goals (Britton, 1983).
line from shaft station The completed WBS, when brought to the highest
2.3 Establish survey control practical order, will consist of the work tasks that can
2.4 Drive 100 feet of 12' x 13' drift be logically assigned to a person or group of persons.
Etc. From this detailed structure the resource assignment to
complete each task, known as the Organizational
Figure 3 Breakdown Structure, can be generated.

This example shows a second order WBS. The first Organizational Breakdown Structure: The
order would be considered the primary category of Organizational Breakdown Structure (OBS) is
Drifting. If necessary, additional orders of the WBS generated by assigning people or groups of people to
can be generated as depicted in Figure 4. the Work Breakdown Structure. Assigning resources to
each task of a properly generated WBS ensures that no
WBS 2.0 Drifting job will "fall through the cracks". Considering our
previous drifting example, an associated OBS is
2.1 Clean-up and prepare 2300 Drill combined with the WBS as represented in Figure 5.
Station
2.1.1 Remove drill deck WBS# Description OBS
2.1.2 Remove slimes dam 2.0 Drifting
2.1.3 Muck out drill mud 2.1 Clean-up and prepare 2300 Drill
2.2 Install new steel 2" water and 4" air Station
line from shaft station 2.1.1 Remove drill deck A-Crew
2.3 Establish survey control 2.1.2 Remove slimes dam B-Crew
2.4 Drive 100 feet of 12' x 13' drift 2.1.3 Muck out drill mud C-Crew
Etc. 2.2 Install new steel 2" water and 4" Utility
air line from shaft station Crew
Figure 4 2.3 Establish survey control Survey
2.4 Drive 100 feet of 12' x 13' drift Z-Crew
The WBS order required is usually dictated by the
complexity of the tasks involved and the varying
Figure 5
resources that are required to perform each task.
Dividing the work into small manageable work
The completed Work Breakdown Structure and
packages makes it easier to generate the schedule and
Organizational Breakdown Structure give an exact
bUdget.
representation of who is responsible for each tasks.
Projects that have fallen prey to Nike-itis, or the Just
Do It! syndrome, often skip project definition and start
Budget
with the WBS. A second and more subtle error is to
consider the WBS as part of the scope of work. Both of
The budget and associated project economics are
these should be avoided. Starting the WBS before
often considered the single determining factor to project
project definition creates an obvious risk of project
viability. There is a true cost to complete any project,
failure. Including the WBS within the scope of work
and it is the charge of the project estimators to predict
complicates scope generation and limits the WBS to
this cost as accurately as possible. After the final
being considered as "the plan", as shown previously by
project budget number is generated, this amount is
the fan selection in Example 2.
6

viewed as the ''true'' cost of the project regardless of the expenditures. Using one spreadsheet for the entire
accuracy. project cycle, from estimating to tracking, provides
To simpliry the discussion of generating a project instant information for managing variance. An
budget, consider the budget to be the result of a base example of a project cycle spreadsheet that uses the
estimate and contingency. previous drifting example is shown in Figure 6.

Base Estimate: The base estimate is the most likely Contingency: Contingency typically refers to a certain
true cost. During the estimating phase it is best to take amount of expenditure above the base estimate that will
an approach of total honesty. Being optimistic or be spent somewhere in the project. Contingency is in
pessimistic is detrimental. Underestimating the project place to cover any unforeseen costs. Therefore if a
may lead to inevitable economic failure. particular item is expected to cost more than the base
Overestimating may cause the project to appear estimate, it should not be considered an unknown cost
uneconomic and consequently, not be approved for assumed to be covered by contingency. If it is known
funding. A second problem caused by overestimating that the cost estimate is low, the estimate should be
results when a project is able to obtain funding due to changed to reflect more accurately the true cost.
favorable economics, but results in the company tying Contingency is also used to account for items that
up funds that could be used to fmance other projects. cannot be adequately defined. It is not always practical
Project costs are effectively estimated using the to generate a detailed cost estimate on every line item.
Work Breakdown Structure while referencing the Consequently, accuracy can vary depending on the
design criteria. This method of estimating is similar to amount of effort expended to generate the estimate.
zero based budgeting and is helpful to include all the It should be noted that contingency is different than
items that contribute to the cost of the project. Using accuracy. Contingency is in place to account for parts
the WBS as an outline for estimation decreases the of the estimate that are missing, where accuracy is a
potential for leaving out parts of the estimate. It is a measure of the variance between the base estimate and
much more significant error to omit a line item estimate true cost. Accuracy is typically proportional to the
then it is to under or overestimate a line item (Fudge, amount of engineering applied to the estimate, and/or
1995). the experience of the estimator.
An additional advantage of doing a line item The accuracy should be such that there is an equal
estimate is the application of contingency. For review probability of being under or going over the base
purposes and to guard against the possibility of estimate. In cases where the accuracy is more likely to
overestimating, it is important to never hide the go over the estimate, e.g., growth allowance, escalation,
contingency by inflating the base estimate. Rather, etc., the upper accuracy limit should be included within
produce the most the accurate base estimate possible the contingency. Depending on company philosophy,
and apply a realistic contingency to each item or logical the upper accuracy limit may only be used for
area of the project. sensitivity analysis. Administering accuracy is a
Designed properly, an estimating spreadsheet subject that must be discussed by the project team so it
showing line item estimates can also be used to track can be clearly communicated. For the purposes of this

PROJECT CYCLE SPREADSHEET

ESTIMATED MATERIAL COSTS MATERIAL COSTS TR<l.CKI"G


WBS# Material!. COSI Unil Cost ConI. Quantity Qt,. Coni Base Costs Conllngency Estlmaled COS! Actual Remainm!! Coni, Used O.. cr-run
1.0 Drifting
,Bolts & Plates $ 4.64 ea 2% 300 5%. $ 1.391.00 7% S 1.489.44 $ 1.489.44 $
~Sholcrele
.,
'$ 235.00 yd 2% 5 100% $ 1.175.00 102% $ 2.373.50 $ 2.373.50 S
Powder S 0.16 'Ib, 2% 2500 10% S 405.00 12~o S 45360 $ 453.60 S
:Primers S 1.40 ea 2% 550 10% $ 770.00 12% S 862.40 $ 862.40 S
iBits $ 10.00 ea 2% 9 10% $ 90.00 : 12% S 100.80 $ 100.80 S
'Drill Sleel $ 37.40 ea 2% 4 20%J S 149.60 22% S 182.51 $ 182.51 S
'Ventilation Supplies S 4.80 fI 2% 100 20% S 480.00 22% S 585.60 $ 585.60 S
:2" Steel pipe '$ 1.22 :ft 2% 100 S 12i.oo 2% $ 124.44 S 124.44 S
4" Steel pipe ,S 3.40 fI 2% 100 $ 340.00 2% $ 346.80 S 346.80 S
12" Couplings $ 4.31 'ea 2% 6 10% $ 25.86 12% S 28.96 $ 28.96 S
,4" Couplings '$ 7.90 ea 2% 6 10% $ 47.40 12%, $ 53.09 $ 53.09 S
,2" Ball valve S 38.28 ea 2% I $ 38.28 2% $ 39.05 $ 39.05 $
14" Ball valve '$ 84.93 .ea 2% I ,$ 84.93 2'% S 86.63 S 86.63 S
;Loader fuel & main!. $ 8.90 ft 25%, 100 S 890.00 25% S 1.112.50 $ 1,112.50 S
'Small lools and misc supplies S 2.00 ft 25%, 100 S 200.00 25% S 250.00 S 250.00 S

Tolal Mattrial Cost S 6,210.01 30% S 8.089.32 S S 8.08932 S S

ESTIMATED L<l.BOR COSTS LABOR COSTS TRACKING


WBS' Labor COSI Unit COSI ConI Quanti!)' Schedule Cont. Base Costs Contingency Estimaled COSI AClual Remaining ConI. Used Over-run
2.0.Drifting
Miner ,$ 150.00 shifl 5% 8 15% S 1.200.00 20% $ 1.440.00 S 1,440.00 S
!MinerlMechanic ,$ 130.00 .shifl 5% 8 lS% S 1.040.00 20% $ 1.248.00 S 1.248.00 S
iMiner helper $ 110.00 shifl 5% 8 15% S 880.00 20% $ 1.056.00 S 1.056.00 S

Total Labor Costs S 3.120.00 20% $ 3.144.00 S S 3.744.00 S S

Figure 6
7

discussion, estimation accuracy is not addressed reminder, and indicates to anyone reviewing the project,
separately, but rather is included within the that the estimate of shotcrete usage is not certain and
contingency. Therefore if the confidence of an estimate requires additional engineering. If the estimator had
is low, i.e., low accuracy, a higher contingency is simply doubled the estimate and applied a lower
applied. contingency, it would appear that the required quantity
With a line item cost estimation, contingency can be of shotcrete was known.
applied to each individual item. This method of SCHEDULE CONTINGENCY: Schedule
estimation can be taken a step further and actually be contingency shows the degree of confidence in the
used to track the cost for each line item to determine estimate for the units oflabor. For this example the
how much contingency has been used and in what areas schedule contingency reflects some degree of
the project may be over budget. uncertainty that could be related to an unknown rock
Underground construction projects contain a certain type or geologic structure that may cause ground
degree of estimation risk that few surface projects control difficulties. Again, this contingency indicates
share. Therefore, to appropriately manage the use of that additional engineering or other information is
contingency, it is helpful to view contingency from four required to "firm up" the estimate. It is important to
perspectives: cost, quantity, schedule and scope note that the base unit rates, e.g., development feet-per-
change. manshift, must not include any contingency. The
COST CONTINGENCY: Cost contingency can be development rates must be those that can be reasonably
viewed as the degree of confidence the estimator has in expected, neither the optimum, theoretically
a cost quote or estimate for a line item unit price. determined, nor the pessimistic "padded" rate.
Considering Figure 6, because the unit price for the The schedule contingency, when multiplied by the
shotcrete was obtained with a quote from a vendor, the base duration, produces a number of manshifts, or
degree of confidence in the price per yard is quite high, equivalent days a project may overrun. These "overrun
and a low contingency of 2% is appropriate to cover days" should then be added to the schedule to reflect
any escalation. If on the other hand, a particular line the schedule contingency. The addition of these days to
item could only be estimated, and it was not practical to the schedule will add cost to all of the fixed, or time
obtain a hard quote, then the unit cost contingency dependent, cost of the project, e.g., manpower,
would be higher. overhead, power, etc.
Cost contingency should also apply to labor. The For many estimators the idea of applying a general
unit rates are subject to change sometimes regardless of 10% to 15% contingency to a project is acceptable.
project schedule. For example, if a labor contractor is This across-the-board contingency is usually applied to
selected due to a manpower shortage, the unit rates may the total project base estimate that includes costs for
increase with little change to the schedule. Also, it is material and labor. However, for underground projects,
possible to require overtime to maintain a project it is difficult to add people to reduce, or make-up, time
schedule when it was not considered in the base on the schedule. Therefore, what typically happens, is
estimate. that any contingency manhours required are worked by
QUANTITY CONTINGENCY: Quantity the same crews, which results in a schedule overrun.
contingency refers to the number of units required for SCOPE CONTINGENCY: Scope contingency
the project. Again, looking at Figure 6, there is a good reflects the confidence that all the estimating items are
estimate of the price per unit of shotcrete, however, accounted for and that the proj ect scope of work is not
there is little confidence in the estimated number of subject to change. In a thorough estimate where the
yards required. Therefore, the estimator applied a project team feels all items have been accounted for.
contingency of 100% to indicate a low confidence in this contingency may be small, 1-2%. If the project
the estimate. team is not confident with the estimate the contingency
Showing the 100% quantity contingency serves as a may be 10% or more. In Figure 7 the application of

PROJECT SUMMARY

TOTAL PROJECT COSTS


Estimated Estimated Subtotal Scope Total Total
WBS# Description Material Costs Labor Costs Costs Contingency Costs Contingency
1.0 Engineering $ 3,400.00 $3,400.00 5% $3,570.00 10%
2.0 Drifting '$ 8,089.32 '$ 3,744.00 $ I 1,833.32 5% $12,424.98 33%
3.0 Track Installation $ 2,500.00 $ 2,600.00 $ 5,100.00 2% $5,202.00 12%
4.0 Grizzly Installation $ 4,500.00 $ 3,200.00 $ 7,700.00 $7,700.00 5%

Total Project Costs $ 15,089.32 $ 12,944.00 $ 28,033.32 3% $ 28,896.98 23%

Figure 7
8

scope contingency is shown in relation to the drifting Fudge, T.F., September, 1995, Manager, Hecla Mining
project presented in Figure 6. Company, Lucky Friday Mine, personal phone
Contingency is not intended to "pad" a project or interview.
add "fudge factors", the purpose is to get the estimate as
close as practical to the true cost of the project. Hartman, H.L., 1992, SME Mining Engineering
Consequently, contingency reported in this manner, is Handbook, 2nd ed. Vol 1, Society for Mining,
more accurate, easier for review, and reduces the Metallurgy, and Exploration, Inc., Littleton,
possibility of "double dipping". Colorado.
The previous example shows a very rigorous
approach to the application of contingency. Many Moder, J.J., Cecil, P.R., Edward, D.W., 1983, Project
estimators mentally combine these contingencies and Management with CPU PERT and Precedence
report contingency by objective, or even only one for Diagramming, 3rd ed., Van Nostrand
the total project. Combining contingencies can work if ReinholdCompany Inc.
the project is low risk, or if the estimator has a lot of
experience with similar projects.

CONCLUSION

Project management is proving to be a useful


management technique for managing underground
projects. However, the difficult, and often uncertain,
conditions of underground projects require particular
attention to definition and planning. It is rarely
practical to plan for all possibilities for underground
construction projects, however, if the project is well
defined with an accurate scope of work, decisions that
must be made in the field are more effective.
The techniques presented here are simply an
overview and are intended as guidelines for
defining and planning underground projects. Each
technique deserves considerably more time and could,
in itself, be the topic of books or papers. These
techniques may not be applicable for every project,
however, the basic concept of taking an appropriate
amount of time to define and plan a project will result
in increasing the chance of success for underground
mining projects.

ACKNOWLEDGMENTS

The author would like to thank Hecla Mining


Company for the permission to submit this paper. The
author would also like to thank Mr. Art Verdugo, the
manager of engineering for Magma Copper Company,
for his inspiration and guidance.

REFERENCES

Bitz, I. & Associates, 1991, Basic Project Management,


Unpublished, presented by American Management
Association.

Britton, S.O., 1983, Construction Engineering in


Underground Coal Mines, Society of Mining
Engineers of the A.I.M.E., New York, New York.

Eliyahu, O.M. & Cox, l, 1992, The Goal, North River


Press.

You might also like