Professional Documents
Culture Documents
TARGET
ABSTRACT
The traditional concept of Optimum Drill and Blast is that it is achieved when
ore is produced at the lowest unit cost and due to the complexities of most mining
operations represents a band which extends either side of an overall cost minima.
The above definition implies that Optimum Drill and Blast is static and once
blasting is within the band around the cost minima then the process is optimised.
However mining operations are not static with many events both long and short
term impinging on the cost structure and productivity. Thus Optimum Drill and
Blast is dynamic with the consequent need to both continuously monitor and
improve the drilling and blasting process to ensure that is still within the
optimised band. This paper expands the definition of Optimum Drill and Blast
and presents a strategy to move a particular operation towards Optimal Drill and
Blast by continuous improvement which utilises a team approach based on
altering one blast design parameter at a time. One half the pattern is kept
standard with other half containing the design change. The blast is evaluated and
if the new design produces better results then two more split blasts are fired and if
the new design produces consistently better outcomes then it becomes the
standard. The process is then repeated with the next design change and so on. It
is in this manner that a mines drilling and blasting can logically move towards
Optimal Drill and Blast or respond to changes in mining or operational
parameters that affect the cost structure and therefore the blasting parameters
required to produce a saleable product at the lowest unit price. Two Case Studies
are presented which illustrate the concept that Optimal Drill and Blast is dynamic.
INTRODUCTION
Optimum Drill and Blast is achieved when ore is produced at the lowest unit
price for a mining operation. Traditionally this definition implies that:
- Drilling and blasting costs must be analysed as part of the overall mining cost.
-Blast designs must be refined based on overall (drilling, blasting, loading,
hauling, crushing, beneficiation etc) cost effectiveness.
-Optimum drill and blast represents a band which extends either side of the
overall cost minima, figure 1 below.
Based on the above definition it is therefore possible to optimise the Drill and
Blast Operations at a particular mine site and once optimised the only
requirement is to track costs and subtly alter the blast design to maintain the
status quo. However mining operations are not static as various
mining/equipment/rock type and cost parameters are in a constant state of change
thereby making Optimum Drill and Blast difficult to achieve. Blast design
therefore must be in a constant state of change to match the changes in rock
types, production parameters etc. The definition of Optimum Drill and Blast
therefore needs expanding to:
Optimum Drill and Blast is achieved when ore is produced at the lowest
unit price for a mining operation at a particular mining rate for a particular
set of operational parameters.
The question becomes how to achieve Optimum Drill and Blast in a dynamic
environment with the goal posts continually changing. Obviously care must be
taken in implementing any changes to blasting design as drill and blast costs as a
proportion of the overall mining cost only vary from a low of some 3% to a high
of 20% generally. Thus any changes in drilling and blasting especially, any
reductions in these costs, must be carefully monitored as a slight reduction in drill
and blast costs may be swamped by increases in loading, hauling, crushing etc
costs.
TEAM APPROACH
Each one of the steps must be implemented and carried out in a quality
manner. If this is not achieved and there is not good communication between
each of the steps then continuous improvement with the aim of obtaining
optimum drill and blast will not be achieved.
The Drilling and Blasting team approach commences with the blast design
which must then be laid out in the field after the appropriate bench preparation.
Good bench preparation enables the drill to move onto the pattern easily and set
up for each hole efficiently as less time is taken to level the drill and commence
drilling. Each hole will be the same depth as the bench is the same RL across the
pattern. Each individual hole must be clearly marked with the hole number and
depth so that the driller can move onto the hole and be confident that the correct
hole with the correct depth is being drilled.
As the pattern is being laid out it must be checked by the pattern designer in
the field to ensure that the actual pattern matches the designed pattern as closely
as possible. The face position maybe different to that originally surveyed leading
to hole crowding (excess holes in the front row). This can be overcome by
making adjustments to the hole positions so as to still obtain good
energy/explosive distribution whilst minimising the number of additional holes.
The cost reductions are significant as savings arise in drilling, explosive,
explosive accessory costs, clean up costs due to less flyrock, reduced excavation
equipment downtime awaiting the blast clean up due to excessive flyrock and
higher initial loading rates due to a smaller low productive digging zone, figure 3.
DRILLING
The drills should either have drill monitors or the drillers should be logging
EXPLOSIVE LOADING/STEMMING/TIE IN
Care must be taken to ensure that the explosive loading requirements, the
stemming lengths and the timing design are clearly presented in an easily
understood pictorial format so that the blast crew can implement the design easily
and efficiently. These design parameters must be discussed with the blast crew to
ensure that they understand the design and they should be given several copies of
the pictorial representation of the blast that can be taken into the field and used to
check that the design parameters are being followed.
Each blast should also be monitored for vibration and airblast levels if these
are of concern (final wall stability, near neighbours, statutory requirements).
Ideally, careful drilling, explosive loading and blasting cost records should be
maintained on a shot by shot basis. These costs should be tracked and graphed on
a historical cost data base on a shot by shot and pit by pit basis if the costing
system is designed to do this and it is a relatively simple mining operation. In
many mining operations the costing system is set up to produce monthly statistics
and these should be used to compare to other monthly statistics.
The major strategy behind blast optimisation is to only alter one blasting
parameter at a time. One half of the pattern is the standard or original design
with one half being the new design. The blast is fired and if the new design is
evaluated as being an improvement then two more shots should be fired as
described above in the same rock type. If the new design performs better than the
standard on the three successive shots then the new design becomes the standard
design. The same or a new parameter is then altered based on the likelihood to
improve blasting. The parameter selection and the amount of alteration is based
on previous blasting evaluations. This is trialled as per the above strategy as it
provides a methodical approach to drill and blast optimisation based on
continuous improvement. If more than one parameter is altered simultaneously it
is often impossible to determine the relative effects that each of the parameters
had on the blasting results of the new design thereby making logical progress to
optimal blasting impossible to achieve.
This drill and blast optimisation strategy must involve the team approach as
this provides the sound basis where data collected at the evaluation/performance
quantification stage can be reliably used for design refinement. If the team
approach is not used and the initial design is not correctly implemented in each of
the stages prior to blast evaluation then the data collected is based on the
erroneous assumption that the initial design is not optimised. The design may in
fact be optimal but it has not been implemented correctly. Thus when the design
refinement is subsequently used even worse blasting results may occur. The team
approach coupled with only altering one parameter at a time therefore provides a
logical approach with which to implement and maintain a drill and blast
optimisation program that will quickly react to changing mining parameters, rock
types and costs.
CASE STUDIES
The first case study concerns the BHPIO (BHP Iron Ore) mine located at
Newman in Western Australia, figure 4. The main deposit is centred on Mt
Whaleback which is located at the Southeastern end of the Hamersley Iron Ore
Province about 1,200km North of Perth, the capital city of Western Australia.
The deposit is about 5.5km long, up to 1.5km wide and extends some 500m
below the original surface at its deepest point. Mt Whaleback originally
The operation had eight Bucyrus - Erie 60R (seven electric, 1 diesel electric)
Series 11/111 blasthole drills capable of drilling 380mm diameter production
blastholes to an average depth of 18m. Blastholes were charged with about 1
tonne of ANFO in dry holes or 1.6 tonnes of heavy ANFO in damp holes. These
charges were initiated with detonating cord (10g/m) and cast PETN boosters.
Blasted material was dug by crawler mounted electric shovels having buckets
ranging in size from 7.6m3 to 22m3. The shovels fed a fleet of diesel-electric
rear dump trucks of 120, 190 and 200 short ton capacity which hauled the
material to the crushers or waste dumps.
The literature search indicated that rock properties play a major role in
determining both the fragmentation characteristics of a blast and the main blast
pattern design parameters of burden, spacing, stemming and subdepth lengths if
the same explosive and blasthole diameter is used. The minimal geological data
previously utilised had resulted in the use of only two production patterns - one
for ore and the other for waste, Table 1.
The first attempt at integrating geological data with blast pattern design on Mt
Whaleback was based on the use of lithological, stratigraphic and ore type
information. Ore type data are derived from the Pilbara Iron Ore Classification
(PIOC) which is based on the physical (hardness, density), mineralogical and
genetic characteristics of the ore, Figures 5 and 6. The classification also extends
to the two main waste rocks, BIF and shale, Figure 7. Ore type plans indicate that
many areas on Mt Whaleback can be divided into various PIOC zones thus
making it very useful in blast pattern design. However, even though some major
advances were made using this system only limited blast pattern experimentation
was undertaken towards obtaining optimal drilling and blasting.
The major impetus for the implementation of the 1986 program and the
continuation of the program into 1987 was that the operation became drill
constrained when two of eight 60R blasthole drills suffered major breakdowns
that required several months to rectify. The problem then became one of
attempting to produce enough broken rock to meet the production plan without
significantly affecting loading, hauling and crushing rates and costs.
The above program was very successful as a 116% pattern expansion was
undertaken in soft ore which resulted in no loss of digging rates or increase in
either shovel maintenance, haulage or crushing costs. Pattern expansion was also
successfully trialled in footwall shale (95%) and overburden BIF (65%). Full
details of this work may be found in Bellairs et al (1986) and Bellairs (1987).
The second case study involves a quarry that was set up to produce crushed
and sized aggregate. This quarry was designed to be a relatively small operation
capable of producing 10,000 tonnes of product per month but customer
requirements rapidly increased to a point where 45,000 tonnes were required on a
monthly basis. The quarry was faced with either not satisfying customer demand,
expending large amounts of capital to expand a nominal 10,000tpm crusher to
cope with the demand or some other alternative to obtain the 45,000tpm rate.
The quarry rejected the idea of not satisfying customer demand but did not want
to spend the capital to increase the crushing capacity as the increased demand
may have evaporated just as quickly as it increased. The decision was made to
increase the crusher throughput by firstly achieving better fragmentation during
blasting. Oversize was considered to be the major reason limiting crusher
throughput due to blockages, longer retention time in the crusher etc.
Video analysis of the new design indicated that stemming ejection was
occurring but the fragmentation was excellent with no oversize. Blasthole barrels
were visible at the back of the 5 - 6 row deep shots with the rock being heaved off
the rock face. The muckpile was extremely easy to dig utilising a FEL resulting
in high excavation rates. This increased fragmentation, the elimination of
oversize and the introduction of a second shift has resulted in an average monthly
saleable product of 45,000 tonnes being achieved.
CONCLUSIONS
The two case studies graphically illustrate the dynamic nature of the concept
of Optimum Drill and Blast. The entire drill and blast process must be optimised
for a mine using the current mining parameters. The best method of achieving
this is to use the team approach outlined in this paper which utilises "Attention to
Detail" or a quality approach to each of the steps from the initial blast design
through to design refinement. It is imperative that the person designing the blast
be in control of the entire team to ensure that the design is implemented correctly
and to provide the communication link throughout the process. The strategy
employed for blast design optimisation is to alter only one parameter at a time.
One half of the pattern is the standard or original design with one half being the
new design. The blast is evaluated and if the new design provides better results
then two more blasts should be fired and if it continues to provide better results
then the new design becomes the standard. The process is then repeated a
number of times until the drill and blast process is optimised. This strategy
combined with the Team Approach provides a continuous improvement cycle to
either move a mine towards optimal Drill and Blast or to maintain a mines drill
and blast within the optimised band.
The Team Approach also provides the best mechanism for the drilling and
blasting process to be quickly optimised when stepwise changes either short term
or longer term occur in production, or cost parameters, and or customer demand.
ACKNOWLEDGMENTS
REFERENCES
Bellairs, P.G, Sheppard, I., and Bulters, J., 1986. Blasthole Density Logging
as an Aid to Blast Pattern Design, The Aus IMM/IE Aust Newman Combined
Group: Large Open Pit Mining Conference, Newman.
SHALE BIF
4020 HARD shale usually black shale 3020 HARD - ringing sound when hit with
hammer - jarring - dense - can look like ore
4040 MEDIUM HARD red, green, 3040 MEDIUM HARD - thud sound when hit
pink, black shales with hammer - easily broken by hammer
blow
4060 SOFT oxidised/leached shales 3060 SOFT - broken with hands - runny - dug out
of face with hands - dusty - biscuity BIF
FIGURE 7 Number Mnemonic For Pilbara Iron Ore Classification Waste Rocks