7. Protection of Transmission ee
LinesIntroduction
> Power transfer from generation to load centres
requires line infrastructure at different voltage levels.
> All line are interconnected with each other to form a
power pool known as power grid.
> In case of power grids, the protection selectivity
should be carried out efficiently so as to localize the
impact of fault to as smaller area as possible.
» Therefore, the time coordination of relays is very
important in protection settings at different levels of
lines such as transmission, sub-transmission,
distribution.General considerations in relay settings
> Select the ratios of all CTs
> Select the pick-up values of relays
= Must be more than allowable maximum load with certain margin
= Must be less than smallest fault current
Thmax > Ipy > Ip¢min
> Select the operating times of relays
= Relay must get an adequate chance to protect the zone under its
primary protection.
= The fault must be sensed by all relays.
= The primary protection is the first to operate, its operating time
being less than that of the back-up relay.
= Setting process has to be started from the relay at the tail end of the
system as it is not constrained by the selectivity problems.
= All other upstream relay settings are tied up with their downstream
neighbours.General considerations in relay settings ..
» Selection of relay operating time needs to consider the
following aspects
= The time required by the relay to operate (Tp).
= Time required by CB to open (Tc)
= Selective time interval (STI) is the time to be included to
incorporate the relay coordination between primary and
backup protection.
> Total operating time of any protection to carry out the
fault isolation
Top = Tr + Teg + Tsr1Radial Distribution Feeder
> Distribution feeder lines supply power to substations for
subsequent supply to the end user.
> Radial Distribution feeders are simplest and least
expensive for construction and protection point of view.
A
> Consider the radial
distribution feeder
consisting of 3 load
points.
Source
» Protection apparatus (Ry
and R,) are installed
after bus A and bus B.
* Consists of power
transducer (CT), fault
detection relay and fault
clearing CB.
Relay operating time — Fault current
Pa
og
234
Tale
oa)
Fault locationApplication of DTOC relay
= For the protection of radial Distribution Feeder
>» Given Data: "
Source
= Relay operating time: Tp = 0.25 x : :
= CB opening time: Teg = 0.55 ia 7 7
"STE: Tsp = O.1s + Load Load L¥ad
» Task: Set the DTOC (Definite time over-current relays)
relays to carry out the proper coordination
> Rg is tail end relay so it should operate in minimum time
Tp =0As
> Rx, must be set to have coordination with Rg
* Relay operating time: Tp p = Tr,4 + Tcp,p + Tsr; = 0.85
» Drawbacks:
= All relays are DTOC, so operating time is fixed for all relays.
= Rg operation is much slower even in case of severe fault within
primary zone of R,, which is not desirable.Application of IDMT relays
Bus A Bus B Bus C
Igmin | 3500A | 2000A | 10004
Ig max |4000A | 3000A | 1500A
For the protection of radial Distribution Feeder
Source Xs PR
Load] ®* Load) B® Loa
+ 200A 160A” 804
> Rg provides primary protection to line BC
» Ry, Provides primary protection to line AB, and back-
up protection to line BC
> Design OC protection using IDMT relays considering
25% overload.
> Use 1A relays, 0.5s CBs, and 10% coordination time.
> Time settings using i IDTM characteristics
TR
~ PSMooz —4
x TSMApplication of IDMT relays ..
CT ratios and plug settings
> Relay Rg
= Maximum load current considering 25% overload
T,max = 80 X 1.25 = 100A
= Plug setting can be selected as 100% for maximum overload:
PS=1
" CT ratio: 100: 1
> Relay Ry
= Maximum load current
Imax = (80 + 160) x 1.25 = 300A
= PS=1
* CT ratio: 300: 1Application of IDMT relays ..
Time settings at Relay Rg
» Fastest operation is desirable (no coordination): TSM = 0.1
>» For maximum fault current at B: PSM = 30
» Actual operating time for imate fault current
Trp = tr X TSM = 39002 4 * 0.1 = 0.25
Time settings at Relay Ry
> Tra =Tre + Tce,p + Tsrr = (0.2 + 0.5) X 1.1 = 0.775
> Operating time for maximum fault at bus B: Tp 4 = 0.77s
> PSM at Ry for maximum fault at B: PSM = = =10
>» TSM can be calculated as follows:
Tra = seas X TSM — TSM = 0.26
100.02 —Application of IDMT relays ..
Operation Time of Ry in Zone-1:
Operation Time of Rg:
For J max= 4000A For F max= 30008
4000
PSM = —— = 13.33
Fg = 04
RA= 330.02 4,
For J; nin= 3500
PSM = ——
0.14
Pattern of operating times of Ry and
R, for maximum fault currents
Fault location
410Application of Directional Relay to Three Phase Feeder
LL fault between
phases 6 and c
Veg
Vie Voc, Lf
UV,
Vow
>
*
> General guidelines about the voltage of pressure coil:
= Under ideal conditions, MTA line is parallel to the voltage of
pressure coil.
= It means that torque will be maximum when current is in phase to
the voltage of pressure coil.
= In three phase systems, the different combinations of voltages are
available. (a, b,c, ab, bc, ca, a+b, b+c, ct+a)
= Voltage for pressure coil should be selected to produce maximum
torque in case of forward faults.