You are on page 1of 6

Fouling mitigation using Helixchanger®

heat exchangers

This article demonstrates the Helixchanger option in reducing the


velocity-dependent fouling in heat exchangers.

heat exchanger results in higher fouling and shorter run


By Bert Boxma, Heat Transfer ABC, The Netherlands lengths between periodic cleaning and maintenance of
tube bundles.
In a Helixchanger heat exchanger, the conventional segmen-
Introduction tal baffle plates are replaced by quadrant shaped baffles posi-
Heat exchanger fouling causes a major economic drain tioned at an angle to the tube axis creating a uniform veloc-
on industries today. In most industrialized countries ity helical flow through the tube bundle. Near plug flow
these losses amount to 0.25 to 0.30 percent of the gross conditions are achieved in a Helixchanger heat exchanger
national product (GNP). Costs associated with exchanger with little back-flow and eddies, often responsible for foul-
fouling are reflected in over-sizing of the heat exchangers ing and corrosion. Exchanger run lengths are increased by
leading to not only the incremental capital and instal- 2 to 3 times those achieved using the conventionally baffled
lation costs but also the operation, maintenance and shell and tube heat exchangers. Heat exchanger performance
downtime costs adding up to a staggering 2.5 to 3.0 times is maintained at a higher level for longer periods of time
the initial purchase price of heat exchangers. High perfor- with consequent savings in total life cycle costs (TLCC) of
mance heat exchangers are particularly susceptible due to owning and operating Helixchanger heat exchanger banks.
greater loss of performance under fouling conditions. Feedback on operating units as well as case studies are
More than 35-40% of heat exchangers employed in presented to illustrate the improved performance and
global heat transfer processes are of the shell and tube economics achieved by employing the Helixchanger heat
type of heat exchangers. This is primarily due to the exchangers.
robust construction geometry as well as ease of mainte-
nance and upgrades possible with the shell and tube heat Fouling characteristics
exchangers. The principal mechanisms of fouling are reported to be
In a shell and tube heat exchanger, the conventional seg- as follows:
ment baffle geometry is largely responsible for higher • Particulate matter in flows
fouling rates. Uneven velocity profiles, back-flows and • Crystallization
eddies generated on the shellside of a segmentally-baffled • Chemical reaction

Heat Exchanger World January 2021 1


• Corrosion processes
• Biological mass accumulation
This paper covers the impact of shellside fouling on the
Reactor 550-800°F
thermal performance and economics of shell and tube 550-800°F
heat exchangers employed in the refinery and petro- Preheat
chemical plant processes. Furnace

300-500°F
Refinery applications
Generally, the fouling deposits occur as high molecular To Reformer
75 - Or Product
weight polymers are formed in the crude preheat sys- Naphtha Feed 300°F Blending
From Storage
tems. Products of corrosion and inorganic salts mix with Or Crude Unit Feed/Effluent Exchangers
the polymers and increase the volume of the fouling
Fig. 2 Schematic of a Naphtha Hydrotreater Unit

»
deposits.
Most of the heat input in a refinery takes place in the
Crude Unit where the crude oil is preheated in heat ex- maintenance and cleaning costs of heat exchangers could
changer trains prior to further heating to elevated tem- significantly affect the plant operating costs. Anti-fouling
perature in a fired heater (furnace). See Fig. 1. The total agents are often added to the process streams to reduce the
refinery output is relying on the uniform operation of fouling tendencies and improve the plant economics.
the crude unit with consistent outlet temperatures at The total fouling related expenses in the major refining units in
desired flow rates. Preheat exchanger performance is, the USA alone is estimated to be approximately US$ 1.4 billion
therefore, vital in reducing the fuel consumption in the a year. The total fouling related costs for major industrialized
downstream furnace and supplying the uniform crude nations is estimated to exceed US$4.4 billion annually.
flow to the furnace over a desired run cycle. Considering that the Refinery fouling related costs
The second most important process unit in the refinery is represent a minor portion of the fouling related costs in
the Hydrotreater. The process stream in a Hydrotreater all industries, the fouling mitigation technology deserves
reacts with hydrogen in presence of a catalyst at elevated a greater attention.
temperature and pressure to remove sulfur and nitrogen.
The major fouling in this unit occurs in the feed/effluent Fouling mitigation technology
heat exchangers. In these exchangers, the cold Naphtha feed The Tubular Heat Exchanger Manufacturers Association
is preheated using the hot product effluent. See Fig. 2. (TEMA) standards suggest fouling factors for several
Fouling in the Feed/Effluent heat exchangers can decrease fluids based upon the asymptotic fouling model as
the outlet preheat temperature of Naphtha causing more described by Kern and Seaton (1959). In this model the
fuel consumption in the furnace and/or reduce the Naphtha competing fouling mechanisms lead to an asymptotic
flow rate. fouling resistance beyond which no further increase in
The last refinery process where heat exchangers are em- fouling occurs. The asymptotic values are, therefore,
ployed as Feed/Effluent heat exchangers is the Reformer recommended as the design fouling factors in the TEMA
Unit. See Fig. 3 for a schematic of this unit. Reforming standards. This approach does not particularly address
is a catalytic process designed to increase the antiknock the fouling phenomenon such as that at the “hot” end
quality of the naphtha streams. The dehydrogenation in of a crude preheat train, since fouling there does not
this unit converts the naphthenes to aromatics. Fouling exhibit the asymptotic behavior.
in the preheat exchangers play a vital role in reducing Ebert and Panchal (1997) have presented a fouling model
the heat transfer coefficient, often by 25-30% in three(3) that is expressed as the average (linear) fouling rate un-
months and as low as 50% in six(6) months after startup. der given conditions as a result of two competing terms,
Added fuel costs in the downstream furnace as well as namely, a deposition term and a mitigation term.

REACTORS
880-960°F 880-960°F
Ambient

880-960°F
225-300°F
Desalter
225-300°F
Crude Storage
Gas
3,000 Bbi/SD
Heat Exchangers
Naphtha
D
23,000 Bbi/SD I
Middle Distillate
S
T 700- 450-
24,000 Bbi/SD I 750°F 550°F
L Reheat Furnace Reheat Furnace
Gas Oil L 500°F
A
40,000 Bbi/SD T Furnace 300-500°F
Residuum
I
O
N
10,000 Bbi/SD Preheat Exchanger Train
Naphtha Feed From
Hydrotreater Preheat Furnace
200-300°F Feed/Effluent Exchangers
Fig. 1 Schematic of a Crude Unit
»

Fig. 3 Schematic of a Reformer Unit


»

2 Heat Exchanger World January 2021


Fouling Rate = (deposition term) - (anti-deposition term) 0.9 A
0.8
dRf B
b δ –E 0.7
= a Re Pr exp ( ) – gtW (1)
dt RTfilm
0.6
C A–Pe=Infinite
B–Helical Baffle

Effectiveness, E
C–Segmental
0.5 D Baffle
where α, β, γ, and δ are parameters determined by regres- D–Pe=0
sion, τw in the shear stress at the tube wall and Tfilm is the 0.4

crude film temperature ( average of the local bulk crude 0.3


and local wall temperatures).
0.2
The relationship in Eq. (1) points to the possibility of
0.1
identifying combinations of temperature and velocity be-
low which the fouling rates will be negligible. Ebert and 0.0
Panchal (1997) present this as the “threshold condition”. 0 1 2 3 4 5 6 7
The model in Eq. (1) suggests that the heat exchanger ge- Number of Transfer Units, NTU
ometry which affects the surface and film temperatures,
velocities and shear stresses can be effectively applied to » Fig. 6 Heat exchanger effectiveness for different geometries
maintain the conditions below the “threshold conditions”
in a given heat exchanger. Optimum design of a Helixchanger heat exchanger
In a Helixchanger heat exchanger, the quadrant shaped offers the following characteristics.
baffle plates are arranged at an angle to the tube axis in • Uniform flow velocities through the tube bundle
a sequential pattern, creating a helical flow path through offering uniform film and metal temperatures.
the tube bundle See Fig. 4. Baffle plates act as guide vanes • Elimination of backflow and eddies
rather than forming a flow channel as in conventionally • Shellside flow approaches plug flow conditions
baffled heat exchanger. Uniformly higher flow veloci- improving the temperature driving force.
ties achieved in a Helixchanger heat exchanger offers • Higher flow velocities are achieved with correspond-
enhanced convective heat transfer coefficients. See Fig. 5. ingly lower pressure drops, thereby improving sheer
Helical baffles address the thermodynamics of shellside stress at the heat transfer surface.
flow by reducing the flow dispersion primarily respon- • Reduced shell size achieved with the Helixchanger
sible for reducing heat exchanger effectiveness. Least option, offers higher tubeside velocities as a secondary
dispersion (high Peclet Numbers) achieved with the benefit in reducing the tubeside fouling rates as well.
helical baffle arrangements approach that of a plug flow All of the above characteristics achieved in a Helixchanger
condition resulting in high thermal effectiveness of the heat exchanger contribute significantly in lowering the foul-
heat exchanger. See Fig. 6. ing rates and maintain higher performance during longer
run cycles as compared to conventional heat exchangers.

Helixchanger feedback

Case 1: Crude Preheat Train, Refinery in USA


This application consists of two parallel trains of two ex-
changers in series. Desalted crude is preheated from about
450°F to 500°F in this exchanger with 680°F tar, before
being sent to the crude furnace for further heating. It is a
highly fouling application. The existing segmental baffle
exchangers required cleaning once per year. Fig 7 (a) shows
the performance of these exchangers in the last operation
Fig. 4 HELIXCHANGER Heat Exchanger cycle. After cleaning in mid-1998, the heat duty achieved
»
Shell-Side Heat Transfer Coefficient

8000
7000
6000 S Segment
5000 Helix 17 deg.
Helix 40 deg.
4000
Helix 44 deg.
3000
Helix 35 deg.
2000 Helix 24 deg.
1000
0
0 2 4 6 8 10 12 14 16 18 20
Pressure Drop
Fig. 5 Measured heat transfer coefficient v/s pressure drop on shellside for various baffle systems
»

Heat Exchanger World January 2021 3


Tar/Crude: Pre-Helical Tar/Crude: Post-Helical
35 43
41

Crude Duty, MMBtu/h


30 39
Crude Duty, MMBtu/h

37
25
35
33
20
31

15 29
27
10 25
7/24/98 9/12/98 11/1/98 12/21/98 2/9/99 3/31/99 5/20/99 7/9/99 8/28/99 3/15/00 5/4/00 6/23/00 8/12/00 10/1/00
Time Time
Fig. 7(a) Case 1: Performance of Segmental Bundles Fig. 7(b) Case 1: Performance of HELIX Bundles
»

»
in these exchangers varied from about 24 MMBtu/hr Replacement HELIX bundles were offered targeting the
to 17 MMBtu/hr in mid-1999. The first set of HELIX original heat duty in the fourteen(14) crude preheat
bundles were installed in mid-1999. Fig 7 (b) shows the exchangers. The earlier segmental bundles required clean-
performance of these bundles after more than 6 months in ing once every year. As of Mar-2003, the HELIX bundles
operation. Between Mar-2000 and Sep-2000, the heat duty have demonstrated more than 2 years of continuous
achieved in these bundles varied from 37 MMBtu/hr. to 33 enhanced heat transfer performance. Fig 8 (a) & (b) shows
MMBtu/hr. In mid-2001, the average heat duty achieved sample data as variation of overall heat transfer coefficient
in the HELIX bundles was 29MMBtu/hr. As evident, the with time between the segmental and the HELIX bundles,
HELIX bundles achieved, on average, more than 50% in the hottest four of the crude preheat exchangers. In this
higher duty than the earlier segmental bundles. This was set of exchangers, crude is preheated from 370°F to about
a result of the significantly reduced fouling accumulation 475°F using 540°F heavy vacuum gas oil (HVGO). It is
on the heat transfer surface and the enhanced heat transfer limited by temperature cross. The helical data in Fig 8 (b)
performance achieved in the HELIX design. Evaluation after Dec 1 is to be excluded as it corresponds to a sudden
of typical mid-2001 data on the HELIX bundles showed 25% drop in crude flow rates combined with a 25°F drop
the total fouling resistance to be around 0.022 hr ft2 °F/ in HVGO inlet temperature. Although it may be observed
Btu, which was less than 50% of the fouling resistance from the graphs that the HELIX bundles show marginal
observed in the segmental bundles. The higher average improvement in the drop in overall heat transfer coef-
heat transfer performance of the HELIX bundles resulted ficient with time in the initial stages, it has since achieved
in valuable savings in fuel cost in the downstream fired and sustained an asymptotic level of performance much
heater. Inspection of these bundles in early 2002 showed higher than the performance level achieved in the earlier
little fouling on the heat transfer surface. In summary, the segmental bundles. The HELIX bundles are reportedly
HELIX bundles achieved 2-3 times longer operation run- expected to achieve more than 3 years of continuous op-
lengths between cleaning than the earlier segmental bun- eration, thus increasing the run-length by 3 times.
dles while achieving enhanced heat transfer performance. The crude overhead condenser application consists of
The feedback on the application has led to the specification four parallel trains of two shells in series. 50% capacity
of HELIX bundles in many crude preheat trains at differ- upgrade was offered for this service using helical baffles
ent facilities of this processor. in low-finned tube bundles within limited shellside pres-
sure drop. The plant has confirmed achieving the capacity
Case 2: Crude Unit, Refinery in Canada upgrade and has reported, as of Mar-2003, more than
Twenty-two(22) HELIX units are in service at this refin- two(2) years of successful continuous operation with
ery – fourteen(14) in crude preheat service and eight(8) these HELIX bundles. Earlier segmental bundles required
in crude overhead condenser service. 2-3 times cleaning in this time period. The HELIX bun-

U oper - Non Helical U oper - Helical

90.0 90.0
2 Months after Start-up
80.0 80.0 Slope is 0.148 if data after
Dec.1 is excluded
Btu/hr ft2 F

Btu/hr ft2 F

70.0 70.0

60.0 60.0

50.0 50.0

40.0 40.0
Y = -0.1744x + 5491.7 Y = 0.1984x + 7388.5
30.0 30.0
8/17/01
8/24/01
8/31/01
9/7/01
9/14/01
9/21/01
9/28/01
10/5/01
10/12/01
10/19/01
10/26/01
11/2/01
11/9/01
11/16/01
11/23/01
11/30/01
12/7/01
12/14/01
12/21/01
12/28/01
9/16/00
9/30/00
10/14/00

10/28/00

11/11/00

11/28/00

12/3/00

12/23/00
1/6/01
1/20/01
2/3/01

2/17/01

3/3/01

3/17/01

3/31/01

4/14/01

4/28/01

Fig. 8(a) Case 2: Performance of Segmental Bundles Fig. 8(b) Case 2: Performance of HELIX Bundles
»

4 Heat Exchanger World January 2021


dles have achieved significantly enhanced heat transfer
performance and have sustained this performance for
a long period of time. 3-4 times longer run-length has
already been achieved with these bundles.

Case 3: Feed/Effluent Exchangers, Hydrotreater


Unit, Refinery in the Netherlands
This application consists of four ‘BEU’ shells in series.
The reactor effluent condenses in the tube while the feed
vaporizes on the shellside. The existing segmental bundles
experienced severe shellside fouling requiring cleaning
twice per year. Replacement HELIX bundles were supplied
for this application. They were installed in 1998. Fig 9
Fig. 10(a) Case 4: Segmental Bundle with Heavy Fouling

»
(a) and (b) show photographs of the hottest and coldest
HELIX bundles after one year in operation. Insignificant
fouling was observed in the COLD bundle while uniform
scale type of fouling was observed on the heat transfer
surface in the HOT bundle. The processor has reported
extending the runlength of this unit by 3-4 times with
the application of the HELIX bundles. These bundles have
achieved 25% larger throughput within limiting hydraulic
constraints. It was also reported that the significantly
enhanced heat transfer performance
of the HELIX bundles have provided substantial additional
savings by not requiring downstream heater modifications.
Fig. 10(b) Case 4: HELIX Bundle with Uniform Fouling
»

Case 4: Feed/Effluent Exchanger, Unifining-


Platforming Unit, Refinery.in Italy
This Feed/Effluent exchanger is a four shells-in-series unit the photograph of the U-bend end of this HELIX bundle,
with feed vaporizing on the shellside and effluent condens- with uniformly distributed fouling over the heat transfer
ing in the tubes. The existing segmental-baffled bundles surface. Significant cost savings have been achieved by the
experienced severe uneven fouling, requiring cutting of application of the HELIX bundle in this unit, by its reli-
the shell for access to the bundle. Fig 10 (a) shows the able operation, its reduced fouling characteristics and its
heavily fouled segmental bundle inside the halfcut shell. consistent enhanced heat transfer performance.
A replacement HELIX bundle was installed in the second
hottest shell of this unit in year 2000. Fig 10 (b) shows Conclusions
Heat exchanger fouling has been very costly for the
industry both in terms of capital costs of heat exchanger
banks as well as the operation and maintenance costs
associated with it.
The HELIXCHANGER heat exchanger when applied in typi-
cally fouling services, has proven to be very effective in reduc-
ing the fouling rates significantly. Three to four times longer
run lengths are achieved between bundle cleaning operations.
Proper attention is required in designing the heat
exchangers placed at the hot end of crude oil pre-heat
operations where temperatures and velocity thresholds
are highly dependent on heat exchanger geometry.
The helical baffle design offers greater flexibility in
selecting the optimum helix angles to maintain the
Fig. 9(a) Case 3: Coldest HELIX Bundle
»

desired flow velocities and temperature profiles to keep


the conditions below the “fouling thresholds”.

Nomenclature
E activation energy, J/mol K
Pr Prandtl number
R gas constant, J/mol K
Re Reynolds number
Rf fouling resistance, m2 K/kW
t time, s
T temperature, K
α, β, γ, δ constants in Eq. (1)
Fig. 9(b) Case 3: Hottest HELIX Bundle τw Wall shear stress, Pa
»

Heat Exchanger World January 2021 5


References Industrial Heat-Exchange Equipment, Begell House,
New York, pp. 451-460.
Kern, D. Q. and Seaton, R. E., 1959, A Theoretical Analysis of
Thermal Fouling, Br. Chem. Eng., Vol. 4, No. 5, pp. 258-269. Kral, D., Stehlik, P., van der Ploeg, H. J., and Master, B. I.,
1996, Helical Baffles in Shell-and-Tube Exchangers, Part I:
Ebert, W. A. and Panchal, C. B., 1997, Analysis of Exxon Experimental Verification, Heat Transfer Engineering,
crude-oil slip stream coking data, Fouling Mitigation of Vol. 17, No. 1, pp. 93-101.

van der Ploeg, H. J., and Master, B. I., 1996, Helically Baf-
ABOUT BERT BOXMA fled Heat Exchangers – Design Option for Reactor Feed/
Effluent Heat Exchange, Advances in Industrial Heat
Mr Bert Boxma is CEO of Heat (NLAHX) was presided over Transfer, IChemE, UK.
Transfer ABC B.V. and has by Bert for eleven years.
more than thirty-five years of After starting his career in
experience, specialised in heat Engineering, he moved into
Storey, D., and van der Ploeg, H. J., 1997, Compact ex-
exchangers. His company the Business Development changer to reduce refinery fouling, Petroleum Technology
is member of Heat Transfer of Helixchanger, an advanced Quarterly, Autumn 1997, pp. 88-89.
Research Inc. (HTRI) USA shell & tube type of heat ex-
and he has been familiar with changer. This product started van der Ploeg, H. J., and Master, B. I., 1997, A new shell-
HTRI’s software products with almost no Western and-tube option for refineries, Petroleum Technology
since 1982. references and is now globally
He holds a B.Sc. in Chemical accepted. Quarterly, Autumn 1997, pp. 91-95.
Engineering from the High He started his Company in
Technical School in Gronin- 2006. Technology Transfer Chunangad, K., and Master, B., 1998, Helixchanger:
gen The Netherlands. He was through courses is his driving malfunctioning heat exchang- Performance Enhancement with Greater Reliability,
a member of the Task Force force to teach the ABC of Heat ers using fouling mitigation First Int. Symp. on Innovative Approaches For Improv-
of ISO 16812 and ESDU’s Transfer in a mix of theory technologies. His advice is used ing Heat Exchanger Reliability, 1998, Materials Tech.
Crude Oil Fouling Working and practical aspects through to help deal with fluid induced
Party. Additionally, he was the workshops and detailed pres- vibration when the exchanger Inst. of the Chemical Process Industries, Houston, Texas,
first Chairman and founder of entations. To date more than is suffering from fluid elastic- pp. 12-21.
HTRI’s Communication Com- 1000 engineeers, representing or acoustic vibration.
mittee: CC-Holland. 250 companies have followed He has published many Chunangad, K. S., Master, B. I., Thome, J. R., and Tolba,
Bert is a guest lecturer his courses in Europe, and the articles explaining the use of M. B., 1999, Helixchanger Heat Exchanger: Single-
at three Dutch Universi- Far and Middle East countries. advanced type heat exchang-
Phase and Two-Phase Enhancement, Proceedings of the
ties (Twente, Delft, and In addition to courses, Bert ers in combination with the
Eindhoven). The Dutch Heat has provided many main end subject Total Life Cycle Cost International Conference on Compact Heat Exchangers
Exchanger Action Group users with solutions for their Analysis. and Enhancement Technology for the Process Industries,
1999, Begell House, New York, pp. 471-477.

6 Heat Exchanger World January 2021

You might also like