You are on page 1of 5

REFINING

Improving hydrotreater
operations
Improvements made during naphtha hydrotreater operations at a Middle East
refinery focused on the diameter of crude unit overhead line, better corrosion
control, an upgraded catalyst grading system and higher furnace temperatures
Gene J Yeh Daniel Longstaff Abdullah Al-Mahrous Olavo C Dias
Saudi Aramco

Process modifications
A
detailed evaluation of the naph- ty, was formed to tackle these two prob-
tha hydrotreater (NHT) unit at a A request was made to conduct a lems to allow successful implementa-
Saudi Aramco refinery was con- detailed evaluation of the NHT unit to tion of the planned 40Mbpd CCR
ducted to allow successful project imple- allow implementation of the CCR Plat- Platformer project. The task force team
mentation in the near future for former project in the future that will be performed the following tasks to evalu-
increased capacity of the refinery’s cat- based on the previously mentioned ate the cause of the high- pressure drops
alytic reformer. The catalytic reformer 40Mbpd capacity versus the 35Mbpd in the NHT:
project will incorporate UOP’s propri- design with a desired five-year cycle life. — Checked the history of pH, chloride
etary CCR Platformer technology and Currently, high-pressure drops in the and iron data of crude unit overhead
will be based on 40Mbpd versus the cur- reactor requires skimming every 18 water
rent 35Mbpd design with a desired five- months while high tube skin tempera- — Reviewed the crude unit inspection
year cycle life. High pressure-drop in the tures in the heater requires cleaning reports
reactor and high heater tube skin tem- every four years. Two heater tubes in — Reviewed the NHT inspection reports
peratures in the NHT unit currently Pass A were replaced in 1996. All heater — Reviewed the NHT reactor pressure
require reactor skimming every 18 tubes were cleaned mechanically in drop experience from Saudi Aramco’s
months and the charge heater cleaning May 1997 and June 2001 as a result of refineries A and B
every four years. scale buildup. — Evaluated the suitability of convert-
Analyses showed that high-pressure The maximum allowable pressure ing the existing reformer reactor one
2
drop in the NHT reactor was primarily drop in the reactor was set at 3.5kg/cm (Reactor 1) as a swing NHT reactor
caused by iron sulphide (FeS) corrosion in order to protect equipment down- — Evaluated the suitability of using a
products that were deposited in the first stream of the recycle compressor. The filter to remove particulates from naph-
foot of the main catalyst bed. It was estab- high tube skin temperatures in the tha feed
lished that these corrosion products came heater presented a potentially haz- — Analysed compositions of reactor
from the crude unit overhead and, to ardous condition and caused accelerat- fines and pump suction deposits col-
some extent, from the NHT charge heater. ed degradation of the heater tubes. lected in June 2001
The top catalyst layer in the NHT reactor Operational extension is essential if — Inspected the top of the NHT reactor
was disturbed due to the high feed vapour the NHT is to perform adequately once and collected reactor fine samples for
velocity combined with a short distance the CCR project is complete in the analysis in October 2002
between distributor and the top bed. future, without causing premature
Uneven distribution to the heater plant outage. Corrosion source
passes, heater overload and scale build-up A task force team, consisting of repre- A key contributor to high corrosion
were most likely the causes of high tube sentatives from various engineering rates of the crude unit overhead was
skin temperatures in the heater. The feed departments in Dhahran and the facili- high velocities in the atmospheric dis-
and recycle gas mixture was not com- tillation column over-
pletely vaporised at the heater inlet caus- head line. The velocity in
ing uneven distribution to the four heater Accelerated corrosion this 30in line was
due to loss of FeS film
passes. This became worse as the (black water)
141ft/sec while the gen-
upstream F/E heat exchangers fouled erally acceptable rate is
Rate of corrosion, mpy

near the end-of-run (EOR). Furthermore, less than 100ft/sec. This


the charge heater needed to fire harder to was verified by UT sur-
compensate for the loss of heat transfer in veys that showed flow-
these heat exchangers. enhanced corrosion rates
Findings and recommendations to as high as 40mpy. In
improve operating performance are dis- addition, inspection
cussed. These include changing crude reports suggest that the
unit overhead line from 30in to 36in, significant fouling of
improved corrosion control of the crude shell side (feed side) of
unit overheads, optimising the catalyst the NHT F/E heat
grading system, upgrading the heater 2 4 6 6.8 8 exchangers most likely
pH
metallurgy to 9Cr and increasing the came from the crude unit
heater inlet temperature to 275ºF to allow Figure 1 Crude overhead accumulator water analysis: overhead.
100% vaporisation. effect of pH sulphide corrosion Review of the crude

69
P T Q WINTER 2005
w w w. e p t q . c o m
REFINING

unit overhead accumulator water analy-


sis showed that while on the average
the pH control was good there were
occasions when the pH fluctuated from
its target range of 5.5 to 6.5. It is well
known that the FeS protective film
tends to be sloughed off when the pH is
between 6.8 and 7.3. (Figure 1), result-
ing in accelerated corrosion. However,
this had a minor effect, compared with
flow-enhanced corrosion caused by
high velocities in the crude unit over-
head line.
The refinery did not process tank
farm naphtha from 1999 to 2001 but
had still suffered high-pressure drops
in the reactor. This indicated that
imported naphtha and/or tank corro-
sion were not main sources for corro-
sion products.
The inspection report showed that
NHT charge heater tubes suffered a high Figure 2 Naphtha filter residue
corrosion rate from 1995 to 2001. The
corrosion rates for some heater tubes lates in naphtha feed consisted mainly trash baskets were used. The distance
were found to be 13mpy, which is much of iron oxides and FeS, which were, between the top of the grading system
higher than the acceptable rate of most likely, corrosion products from the and the bottom plate of the distributor
5mpy. This high corrosion rate in tubes crude column overhead. Iron oxide was was only 45cm. Such a short distance
contributed to some extent to pressure formed from iron corrosion in the pres- combined with a high feed vapour veloc-
drop problem in the reactor. ence of water. Between the crude unit ity created the slope at the outer rim of
overhead and the NHT, there were no the top bed. To smooth flow distribution,
Analytical results opportunities for water or steam to con- a recommendation was submitted to
X-ray diffraction (XRD) results showed tact the naphtha. It was concluded lower the top level in the reactor by 10
that deposits from the charge pump therefore that the source of these iron cm and add a layer of 1in ceramic ball to
suction filter consisted of mainly iron oxide particles was from the crude unit hold the catalyst.
oxide and some FeS. Reactor fine sam- overhead. SEM indicated that particu-
ples contained mainly FeS. The details late sizes were in the range of one to Actual refinery experience
are summarised in Table 1. two microns (Figure 2). As seen in the Naphtha feed at Saudi Aramco’s Refin-
X-ray fluorescence (XRF) did not figure, there are two types of particu- ery A was a mixture of straight-run (SR)
detect Cr (from stainless steel corrosion) lates – needle type and round crystal naphtha, hydrocracker naphtha, and
in the reactor fines down to levels of type. The needle type of particulate is imported naphtha. The imported naph-
500ppm, and scanning electron mainly Fe2O3 and the other is FeS. tha contained corrosion products and
microscopy (SEM) did not show Cr in During catalyst skimming in Octo- scales. The typical particulate content
the reactor fines (<1000ppm), indicat- ber 2002, a few catalyst and fine sam- was 1.2mg/l.
ing that corrosion products might not ples were collected from varying Refinery A had a high-pressure drop
originate from the furnace tubes, which depths in the reactor. It was found that problem in the NHT of a reformer
contains 1.5% Cr. This suggests that the the sample of the first foot of the main before 1992. Using a catalyst grading
fines originated from an upstream catalyst bed was full of fines and most system and putting the heavy naphtha
source, probably the crude unit. SEM of the fines consisted of FeS. The par- splitter in service solved the problem.
also indicated that reactor fines were ticle size of the corrosion products was Cycle life increased from one to three
well dispersed and were very fine- very small, which enabled some of the years after the installation of the bed
grained. particles to pass the catalyst grading grading.
Two naphtha grab samples contained system so that they deposited in the Naphtha feed at Saudi Aramco’s
0.4 and 0.5mg/l of particulates. Particu- main catalyst bed. Refinery B was from the crude unit, a
hydrocracker, or a tank farm. No
XRD results of charge pump inlet scale, NHT inspection imported naphtha was used as in Refin-
furnace scale and reactor fine When the reactor was inspected ery A. Start-of-run (SOR) pressure drop
2
during catalyst skimming in was 0.6kg/cm . Catalyst grading was
Sample Charge pump Furnace Reactor October 2002, it was found that implemented in September 2000. Prior
inlet scale scale fines the top layer had been disturbed. to using a catalyst grading, the pressure
2
Iron oxide 88% ND ND At that time a catalyst grading drop would increase to 2kg/cm after
Hydrated iron oxides 5% 1% ND system was implemented to about 18 months on service. After the
Iron sulphide 7% 96% 95% replace conventional ceramic catalyst grading system was installed,
Poorly crystallised ball layers and trash baskets at the pressure drop only increased to
2
Alumina catalyst the top of the reactor. 1kg/cm after 18 months in service,
particles ND ND 1% The centre portion of the top indicating that the catalyst grading sys-
Total 100% 97% 96% layer was flat, but the outer rim tem was effective.
ND: not detectable was sloped. The refinery had not Based on the performance of the cat-
experienced this phenomenon alyst grading systems installed at
Table 1 before when ceramic balls and refineries A and B, engineers at this

70
P T Q WINTER 2005
REFINING

refinery installed a catalyst grading sys- NHT operating conditions. The calcu- ised at middle-of-run (MOR) of F/E heat
tem at the top of the NHT reactor in lated SOR pressure drop for the first exchanger cleaning cycle in September
2
June 2001. The SOR pressure drop was CCR Platformer reactor was 2.2kg/cm 1999 and 78% vaporised at end-of-run
typical at 1.6 and the pressure drop at 38.2Mbpd if used for NHT service. (EOR) in May 2001. The heater inlet
2
increased to only 2.2kg/cm in August The piping and an extra batch of cata- temperatures were 260°C and 255°C at
2002. Subsequently, the NHT suffered lyst are also required. This idea was MOR and EOR of that cycle, respective-
two upsets and the reactor pressure abandoned due to unfavourable eco- ly (Table 2). At SOR in July 2001, after
2
drop increased to 4.6kg/cm . Such a nomics. F/E exchangers had been cleaned, the
high-pressure drop forced the NHT to According to the analytical results, heater inlet temperature was 266°C and
shutdown for reactor skimming in the size of the particulates in naphtha 94% of the feed mixture was vaporised.
October 2002. During the shutdown, was mainly 1–2 microns. The mesh size Table 2 also indicates that heat
catalyst and fine samples of each cata- of a typical filter is 10 or 25 microns. It absorption rates for F/E heat exchangers
lyst layer were collected for further is not practical to use filters to remove at MOR and EOR were 100.5MMBtu/hr
analyses. particulates with 1–2 microns particle and 95MMBtu/hr, respectively. The
It was found that the catalyst sample size due to high-pressure drop require- design heat absorption rate was
from the first foot of the main catalyst ment and frequent plugging. Corrosion 116MMBut/hr. This indicated that F/E
bed contained a large amount of fines. products, which caused high pressure heat exchangers were fouled and lost
Since most of the fines were concentrat- drops in the NHT reactor, came from heat transfer efficiency at MOR and
ed in the first foot of the main catalyst, crude unit overhead and to some extent EOR of the cycle. Also shown in Table 2,
this was the source of the pressure drop. the NHT charge heater. the design heat duty of the charge
The fines consisted of dispersed corro- heater was 36.6MMBtu/hr.
sion products from the upstream units Heater tube skin temperature However, the charge heater heat
(FeS). The corrosion products were fine- The investigation team performed the duties at MOR and EOR were
ly dispersed, which enabled them to following tasks associated with high 45.5MMBtu/hr and 51.1MMBtu/hr,
partially pass the grading system and heater tube skin temperatures: respectively, much higher than the
deposit in the main catalyst bed. — Checked heater inspection report design rate. When the F/E heat
Based on these analytical results, the — Analysed compositions of heater exchangers fouled, the charge heater
grading system is optimised to accom- scale samples collected in June 2001 needs to compensate for loss of heat
modate small fines to further alleviate — Simulated F/E heat exchanger perfor- transfer in the F/E heat exchangers.
pressure drop. mance, the state of feed mixture at the The naphtha feed mixture at the
The standard metallurgy for the NHT heater inlet, the required naphtha feed heater inlet was designed to be 100%
reactors is 1-1/4 Cr base metal with type temperature to achieve 100% vaporisa- vapour for even flow distribution to
405 or 410 stainless steel lining. In tion at the heater inlet, and the required heater passes. If it was not totally vapor-
order to use the existing reformer Reac- heater duty ised, there was uneven distribution in
tor 1 as a swing reactor, it is necessary to — Checked the heater integrity the four heater passes. Furthermore, the
install a lining and then perform post- — Reviewed the NHT heater experience charge heater needed to fire harder to
weld heat treatment. Additional modifi- from refineries A and B of Saudi Aramco compensate for the loss of heat transfer
cations would need to be made to The simulation model was developed in the F/E heat exchangers.
convert the reactor internals from radi- using HYSYS software. The simulation This uneven distribution and over-
al flow to down-flow service. The reac- results indicated that the feed mixture firing in the heater results in scale build-
tor size was not ideal for the current at the heater inlet was only 84% vapor- up and increases in the high tube skin

71
P T Q WINTER 2005
REFINING

Heat requirement for current operation

Required heat F/E heat Charge heater % Vaporisation at


absorption, Btu/hr exchanger heater inlet

Design heat absorption, Btu/hr – 1.16x108 3.66X107 –

Sept, 99 at MOR, dirty F/E 120-260°C in F/E exchanger 1.005x108 – 84


260-330 in heater – 4.547x 107 –

May, 01 at EOR, dirty F/E 120-255°C in F/E exchanger 0.95x108 – 78


255-330 in heater – 5.112x 107 –

July, 01 at SOR, clean F/E 122-266°C in F/E exchanger 1.066x108 94


266-328 in heater – 3.74x 107 –

Table 2

temperatures in the heater. The mini- ber 1999), 51.1MMBbtu/hr at EOR (May using twisted tubes, and/or installation
mum temperature to have 100% vapour 2001), and 37.4MMBtu/hr at SOR with of tube inserts. A detailed analysis of the
at heater inlet was 270°C based on a clean F/E heat exchangers (July 2001). entire heat exchanger preheat train was
2
29.9kg/cm g pressure and a 38.2Mbpd To ensure 100% vaporisation at the recommended.
feed rate. For a 40Mbpd feed rate, the heater inlet, the feed mixture tempera- Analytical results show that the fur-
minimum temperature to achieve 100% ture at the heater inlet needs to be nace scale sample (collected in June
vapour at heater inlet was 271°C. To 275°C. For a heater inlet temperature of 2001 T/I) was composed of mainly FeS.
provide a safe margin, a minimum 275°C, the heat absorption rates It also contained some coke. The details
heater inlet temperature of 275°C was required to raise the reactor inlet tem- were previously presented in Table 1.
selected to ensure 100% vaporisation. peratures to 330°C at 38.2 and 40Mbpd Inspection indicated that the heater
To reach 100% vaporisation at the feed rates are 31.0 and 32.4MMBtu/hr, tube thickness decreased significantly
heater inlet, Table 3 shows that the respectively (Table 4). These heat from 1995 to 2001. The existing heater
required naphtha feed temperature was absorption rates are lower than the tube is 1–1/4 Cr. Normally, 9 Cr tube is
221°C at MOR (September 1999), 243°C design rate, indicating that the charge used in this type of heater service. The
at EOR (May 2001), and 183°C at SOR heater is capable of providing the sulphidic corrosion rate is a function of
with the clean F/E exchangers (July required heat for the future operations. tube temperature, H2S content and
2001). The typical naphtha feed tem- Table 4 also summarises that the heat material (Gutzeit, 1986). The corrosion
perature was 136°C. The idea of increas- absorption rates required to raise feed rate for some heater tubes was found to
ing feed temperature to reach 100% mixture temperature from 120°C to be 13mpy, which is much higher than
vaporisation at the heater inlet was 275°C at 38.2 and 40Mbpd feed rates the acceptable rate of 5mpy. If upgraded
abandoned due to limitation of the are 115 and 120MMBtu/hr, respectively. to 9 Cr, the tube corrosion rate was esti-
design temperature of some equipment. The design heat absorption rate for the mated to be 2.8mpy. In addition, the
F/E heat exchangers was 116MMBtu/hr, upgrade to 9 Cr would increase the
Charge heater load which was not achieved even with allowable skin temperature of the tubes
The charge heater was designed for a clean heat exchangers. and extend tube life.
35Mbpd feed rate with 100% vapour at This indicates that to raise feed mix- The NHT charge heater in Refinery A
the heater inlet. The design heat absorp- ture temperature from 120°C to 275°C, did not have a high tube skin tempera-
tion duty for the heater was 36.6 the current F/E heat exchangers need to ture problem. The heater inlet tempera-
MMBtu/hr. If the feed mixture at the be evaluated and modified to accom- ture was 266°C and pressure was
2
heater inlet was not fully vaporised, the modate the future operating conditions 28.7kg/cm g. Refinery A naphtha feed
heater needed to compensate for the and fouling allowance to achieve a was lighter and recycle gas rate was
loss of heat transfer in the F/E heat heater inlet temperature of 275°C for a higher. Simulation results indicated that
exchanger. The calculated heat absorp- five-year cycle. feed mixture was fully vaporised at
tion duties at a 38.2Mbpd charge rate Options include the conversion to these conditions. The heater tube has
were 45.5MMBtu/hr at MOR (Septem- the helically baffled heat exchanger, been upgraded to austenitic SS-221.

Required naphtha feed temperature for full vaporisation at heater inlet

Condition Date Flow rate, UA, Btu/F hr % of U0 Heat transfer in F/E Naphtha temp required
mbpd exchanger, Btu/hr for 100% vaporisation

MOR, dirty F/E Sep, 99 38.2 5.05x105 65 1.005x108 221°C

EOR, dirty F/E May, 01 38.2 4.4x105 57 0.95x108 243°C

SOR, clean F/E Jul, 01 38.2 6.57x105 85 1.066x108 183°C

Table 3

72
P T Q WINTER 2005
REFINING

Heat requirement for future operation

Required heat F/E heat exchanger Charger heater


absorption, Btu/hr
Design heat absorption,
Btu/hr – 1.16x108 3.66x107
8
40 MBPD 120-275°C in F/E exchanger 1.199x10 –
275-330°C in heater – 3.24x107
38.2 MBPD 120-275°C in F/E exchanger 1.15x108 –
275-330°C in heater – 3.097x107

Table 4

Refinery B experienced high heater improve heat transfer


tube skin temperatures. The radiation — No design changes or modifications
heater tube has been updated to 9 Cr- 1 are needed to the charge heater; it is
Mo. In 2001, Refinery B had a tube rup- capable of providing the required duty
ture in the convection section of the for the future operations.
charge heater. The tube scale consisted
of coke and iron. The heater inlet tem- Improvements
perature was 255°C and outlet tempera- Guidelines have been provided to
ture was 305°C. improve NHT operations to allow
Simulation results indicated that the implementation of the CCR Platformer
feed mixture was not fully vaporised project in the future that will be based
under these conditions. Uneven distri- on 40Mbpd versus the 35Mbpd design
bution to the heater passes, heater over- with a desired five-year cycle life. The
load, and scale build-up were most primary focus of the study was to
likely the causes for the high tube skin address the reactor pressure drop caused
temperatures in the heater. by FeS corrosion products and high tube
temperatures in the charge heater due
Recommendations to uneven distribution in the heater
To allow successful implementation of passes.
the CCR Platformer project in the The FeS products were traced to high
future, the following recommenda- corrosion in the crude unit overhead
tions were made: and possible corrosion in the 11/4 Cr –
— Change crude overhead line from Mo heater tubes at the high tempera-
30" to 36in to minimise flow-enhanced ture locations. The uneven distribution
corrosion and subsequent FeS deposits to the heater passes, heater overload
in the system. Also, ensure consistent and scale build-up were identified as
pH control in the crude unit overhead likely causes of high tube skin tempera-
— Maintain a distance of 55cm mini- tures.
mum between the bottom of the dis-
tributor and the top level in the
reactor. Install 10cm of 1in ceramic
balls to the top layer to secure the grad- Gene Yeh is a senior engineer in the pro-
ing system and prevent disturbances of cess and control systems department of
the top bed Saudi Aramco in Dhahran, Saudi Arabia.
— Optimise the grading system to He holds a BS in chemical engineering and
accommodate small fines to alleviate a ME and a PhD in chemical and fuels
pressure drop and sock-load 1/8in and engineering.
1
/16in shape catalysts; replace all the E-mail: gene.yeh@aramco.com.
catalyst after 10-year service to ensure Daniel Longstaff is a senior scientist at
good strength of the catalyst Saudi Aramco in Dhahran. He holds a BS
— Feed sweet naphtha to keep the CCR in fuels engineering, an MS in chemical
Platformer unit running, if necessary, engineering and a PhD in fuels engineer-
during skimming of the NHT reactor ing.
— Upgrade heater tubes to 9 Cr for bet- Abdullah Al-Mahrous is an industrial
ter corrosion resistance; the existing cleaning engineer at Saudi Aramco in
1–1/4 Cr tube metallurgy is not opti- Dhahran, and holds a BS degree in chem-
mal for this service ical engineering.
— Maintain the heater inlet tempera- Olavo C Dias is a downstream engineer-
ture above 275°C to ensure 100% ing specialist with the corrosion technolo-
vaporisation by modifying the F/E heat gy unit in Saudi Aramco. He obtained an
exchangers to increase heat transfer MS in metallurgy from Penn State Univer-
(using helical baffles, twisted tubes or sity and has previously held key plant/cor-
tube inserts); if practical, consider porate positions in major oil and gas
adding heat exchanger capacity to companies.

73
P T Q WINTER 2005

You might also like