You are on page 1of 435

Architect’s Legal Handbook

The Architect’s Legal Handbook is the most widely used reference on the law for practicing architects and the established textbook on
law for architectural students.

Since the last edition of this book in 2010, the legal landscape in which architecture is practised has changed significantly: the long-
standing procurement model with an architect as contract administrator has been challenged by the growing popularity of design and build
contracts, contract notices in place of certificates, and novation of architect’s duties.

The tenth edition features all the latest developments in the law which affect an architect’s work, as well as providing comprehensive
coverage of relevant UK law topics. Key highlights of this edition include:

● an overview of the legal environment, including contract, tort, and land law;
● analysis of the statutory framework, including planning law, health and safety, construction legislation, and building regulations in
the post-Grenfell legal landscape;
● procurement and the major industry construction contract forms;
● building dispute resolution, including litigation, arbitration, adjudication, and mediation;
● key fields for the architect in practice, including architects’ registration and professional conduct, contracts with clients and collateral
warranties, liability in negligence, and insurance;
● entirely new chapters on various standard form contracts, architects’ responsibility for the work of others, disciplinary proceedings,
and data protection;
● tables of cases, legislation, statutes, and statutory instruments give a full overview of references cited in the text.

The Architect’s Legal Handbook is the essential legal reference work for all architects and students of architecture.

Anthony Speaight QC – Barrister, in practice at 4 Pump Court, Temple, London. Bencher of Middle Temple. His publica-
tions include The Law of Defective Premises (co-author) and the Butterworths Professional Negligence Service (contribu-
tor). Anthony is a past member of the Council of the Society of Construction Law, past chairman of the Editorial Board of
Counsel, Journal of the Bar of England & Wales, and past Chairman of the Bar Council’s Access to the Bar Committee.
He acts as a supervisor of dissertations at the King’s College London Centre of Construction Law. He is an accredited
Adjudicator and trained Mediator.

Matthew Thorne – Barrister, in practice at 4 Pump Court, Temple, London, and member of Inner Temple. He is on the com-
mittee of the Technology and Construction Bar Association, chairman of Junior TECBAR, and a member of the Society of
Construction Law and Professional Negligence Bar Association. He is ranked in the legal directories as a leading junior in
Construction and Professional Negligence. He has been a co-author of LexisPSL Adjudication and is the author of Becoming
a Barrister. He is an accredited Adjudicator.
Praise for previous editions

“Probably the most important legal book for architects.”


Architect’s Journal

“A must for every practice. A handbook that should be readily accessible to every responsible architect.”
Architect and Surveyor

“This popular reference book for both practitioners and students has been prepared by a team of eminent contributors and encompasses
the general principles of law, building contracts, statutory rights and the architect in practice.”
The ASI Journal

“The Architect’s Legal Handbook serves to make us aware of those areas in which the law overlaps with architectural practice and all the
more easily avoid those pitfalls that trap the unwary. As a combination legal primer and security blanket this is an essential purchase for
both Part III candidates and architects alike.”
Peter Robinson, Royal Incorporation of Architects in Scotland journal (RIAS)

Praise for the tenth edition

“… the standard text of choice for architectural students and practitioners alike … I welcome this latest edition as a valuable source for
architects in practice.”
Mrs Justice O’Farrell DBE, Judge in Charge, Technology and Construction Court
Architect’s Legal Handbook
The Law for Architects

Tenth edition

Edited by
Anthony Speaight QC and Matthew Thorne
Tenth edition published 2021
by Routledge
2 Park Square, Milton Park, Abingdon, Oxon, OX14 4RN
and by Routledge
52 Vanderbilt Avenue, New York, NY 10017
Routledge is an imprint of the Taylor & Francis Group, an informa business
© 2021 Taylor & Francis
The right of Anthony Speaight QC and Matthew Thorne to be identified as the authors of
the editorial material, and of the authors for their individual chapters, has been asserted in
accordance with sections 77 and 78 of the Copyright, Designs and Patents Act 1988.
All rights reserved. No part of this book may be reprinted or reproduced or utilised in any
form or by any electronic, mechanical, or other means, now known or hereafter invented,
including photocopying and recording, or in any information storage or retrieval system,
without permission in writing from the publishers.
Trademark notice: Product or corporate names may be trademarks or registered trademarks,
and are used only for identification and explanation without intent to infringe.
First edition published by Architectural Press 1973
Ninth edition published by Architectural Press 2010

Notices
Knowledge, law and best practice in this field are constantly changing. As new research and
experience broaden our understanding, changes in research methods, professional practices,
or medical treatment may become necessary. The updated position should always be verified
by those making use of this book.
Practitioners and researchers must always rely on their own experience and knowledge in
evaluating and using any information, methods, compounds, or experiments described herein.
In using such information or methods they should be mindful of their own safety and the
safety of others, including parties for whom they have a professional responsibility.
To the fullest extent of the law, neither the Publisher nor the authors, contributors, or editors,
assume any liability for any injury and/or damage to persons or property as a matter of
products liability, negligence or otherwise, or from any use or operation of any methods,
products, instructions, ideas or information contained in the material herein.
British Library Cataloguing-in-Publication Data
A catalogue record for this book is available from the British Library
Library of Congress Cataloging-in-Publication Data
Names: Speaight, Anthony, editor. | Thorne, Matthew, editor.
Title: Architect’s legal handbook: the law for architects/edited
by Anthony Speaight QC and Matthew Thorne.
Description: Tenth edition. | Milton Park, Abingdon, Oxon; New York, NY:
Routledge, 2021. | Includes bibliographical references and index.
Identifiers: LCCN 2020028951 (print) | LCCN 2020028952 (ebook) | ISBN
9780367233679 (hardback) | ISBN 9780367233686 (paperback) | ISBN
9780429279546 (ebook)
Subjects: LCSH: Architects–Legal status, laws, etc.–Great Britain. |
Architectural contracts--Great Britain. | Building laws–Great Britain.
Classification: LCC KD2978 .A35 2021 (print) | LCC KD2978 (ebook) | DDC
343.4207/872–dc23
LC record available at https://lccn.loc.gov/2020028951
LC ebook record available at https://lccn.loc.gov/2020028952

ISBN: 978-0-367-23367-9 (hbk)


ISBN: 978-0-367-23368-6 (pbk)
ISBN: 978-0-429-27954-6 (ebk)
Typeset in Times New Roman
by Deanta Global Publishing Services, Chennai, India
Contents

Foreword ix 8 Business tenancies – architects’ offices 43


9 Estoppel 44
Editor’s preface xi
Acknowledgements xiii 5 Introduction to Scots law 45
Catriona Macleod
List of contributors xiv 1 Scots law: a distinct legal system 45
2 Historical context 45
3 Modern context: devolution 45
Part A: General principles of law 4 Scotland and European law 46
5 Scotland and human rights 46
1 Introduction to English law 3
6 Categorisation of Scots law 46
Anthony Speaight QC
7 Sources of Scots law 46
1 The importance of law 3
8 The court structure 47
2 The place of English law 3
9 Branches of Scots law 49
3 Sources of English law 4
10 Limitation of actions/prescription 49
4 English legal history 5
11 Choice of law 50
5 The scheme of this book 7
12 Jurisdiction 50
2 The English law of contract 9
6 Scots land law 51
Anthony Speaight QC
William Frain-Bell
1 Introduction 9
1 Introduction 51
2 Scope of the law of contract 9
2 Rights: real and personal 51
3 What is a contract? 9
3 Classification of property 51
4 Intention to create legal relations 10
4 Land ownership 51
5 Consideration 10
5 Sale of land and buildings 52
6 ‘Agreement’ 11
6 Land registration 53
7 Terms of a contract 12
7 Title conditions: servitudes and real burdens 53
8 Exclusion clauses and the prevention of unfair terms 14
8 Access rights 55
9 Standard forms of contracts 15
9 Tenements 55
10 Misrepresentation 15
10 Boundary walls and support 55
11 Variation, novation, and assignment 16
11 Nuisance 55
12 Performance and breach 17
12 Other restrictions on heritable property 56
13 Rights for those who are not contracting parties 18
13 Leases 56
14 Agency 19
15 Limitation under the Limitation Act 1980 20

3 The English law of tort 21 Part B: Statutory framework


Claire Packman 7 Statutory authorities in England and Wales 59
1 Introduction 21 James Strachan QC
2 Negligence 21 1 Local government 59
3 The Defective Premises Act 1972 26 2 Other statutory bodies 64
4 Nuisance 27 3 Statutory undertakers: connections to services 66
5 The rule in Rylands v Fletcher 28 4 Private streets 68
6 Trespass 29 5 Grants 69
7 Breach of statutory duty 29 6 Housing associations and societies 70
8 Inducing breach of contract/wrongful interference 7 Special premises 70
with contract 29
9 Limitation periods 29 8 Statutory authorities in Scotland 73
10 Remedies 30 Graham A. Dunlop
11 Apportionment of liability 31 1 Introduction: public administration in Scotland 73
12 Conclusion 31 2 Connections to sewerage and water services 74
3 Private streets and footpaths 76
4 English land law 33 4 Grants 76
Martin Dixon 5 Registered social landlords 76
1 Land law and conveyancing distinguished 33 6 Special considerations 76
2 The extent and meaning of ‘land’ and intrusions upon it 36
3 Easements 38 9 Construction legislation in England and Wales 79
4 Restrictive covenants 40 Christopher Miers, Martin Edwards,
5 Landlord and tenant 41 And Frank Newbery
6 Surveys of property to be purchased 43 1 Building Acts and Regulations 79
7 Mortgages 43 2 The Building Regulations 2010 79
v
vi Contents

3 Control of building work other than by the local 6 The building owner’s rights 158
authority 84 7 Boundary structures in Scotland 158
4 Exemptions from control 84
5 Other controls under the Building Act 1984 84 15 Health and Safety law affecting architects 159
6 Local legislation in Inner London 85 Simon Tolson
7 Local legislation outside Inner London 85 1 Introduction 159
8 Other national legislation 85 2 A brief history 160
9 Technical harmonisation and standards 87 3 What architects need to know: key areas 161
10 Fire safety: historical background 88 4 Existing health and safety position 165
11 Fire safety and the Building Regulations 2010 90 5 Essential health and safety
12 Fire safety and amendments to Building Regulations 90 touchstone summary 170
13 Fire safety: guidance documents 92 6 Application to particular situations 171
14 Fire safety: alternative design guidance documents 96 7 Conclusion 171
15 Fire safety: local legislation in Inner London 98
16 Fire safety: local legislation outside Inner London 98
17 Fire safety: other national legislation 99 Part C: Building contracts
18 Fire safety on construction sites 102
16 Introduction to procurement methods in
19 Future legislation 104
construction 175
10 Building Regulations in Scotland 105 Simon Plunkett
Peter Anderson 1 Introduction 175
1 Introduction 105 2 Complexity 175
2 Outline of Building (Scotland) Act 2003 105 3 Client expertise 175
3 Building (Procedure) (Scotland) Regulations and 4 Commercial drivers 175
subsequent amendment 112 5 Other factors affecting choice of
4 Building (Forms) (Scotland) Regulations procurement method 176
2005 and subsequent amendments 113 6 Procurement options 176
5 The Building (Fees) (Scotland) Regulations 7 Common pricing mechanisms 178
2004 and subsequent amendment 113 8 Which contract? 178
6 Building (Scotland) Regulations 2004 and 9 Conclusion 178
subsequent amendments 113
17 The JCT Standard Building Contract 181
7 Other national legislation affecting building 120
Thomas Crangle
8 Building standards in Scotland: current legislation 120
1 Articles of Agreement 181
11 Planning law in England and Wales 121 2 Section 1: definitions and interpretation 183
Andrew Fraser-Urquhart QC 3 Section 2: carrying out the works 183
1 Introduction 121 4 Section 3: control of the works 195
2 Local planning authorities; or who is to deal with 5 Section 4: payment 199
planning applications? 123 6 Section 5: variations 207
3 The meaning of ‘development’ 124 7 Section 6: injury, damage, and insurance 209
4 Control of development in general 125 8 Section 7: assignment, performance bonds and
5 Buildings of special architectural or historical guarantees, Third Party Rights, and collateral
interest – listed buildings 130 warranties 210
6 Urban Development Corporations; Simplified 9 Section 8: termination 211
Planning Zones 131 10 Section 9: settlement of disputes 212
7 Enforcement of planning control 132 11 The Schedules 213

12 Planning law in Scotland 135 18 The NEC4 Engineering and Construction


Alasdair Burnet Contract and related Architects’ forms 215
1 Introduction 135 Theresa Mohammed
2 Planning Authorities 136 1 Introduction 215
3 Meaning of Development 136 2 NEC4 Professional Services Contract 215
4 Control of development 137 3 The parties’ main responsibilities 217
5 Listed buildings 139 4 Quality management 217
6 Enterprise Zones, Simplified Planning Zones and 5 Payment 217
Business Improvement Districts 140 6 Compensation events 217
7 Enforcement of planning control 140 7 Rights of material 218
8 The implementation of the 2019 Act 141 8 Liabilities and insurance 218
9 Termination 218
13 Public procurement under European Union law 143 10 Contract data 218
Zena Prodromou 11 Comparison with RIBA Standard Professional
1 The procurement regime 143 Services Contract 2018 219
2 The Public Sector Directive 144
3 The Utilities Directive: a brief overview 151 19 The FIDIC contract 221
4 The Concessions Directive: brief overview 152 Jeremy Glover
5 The Defence Directive: brief overview 152 1 Introduction 221
2 The FIDIC forms 221
14 Party walls 155 3 The content of the FIDIC Rainbow Suite –the
Graham North standard clauses 222
1 The Party Wall etc. Act 1996 155 4 Claims 223
2 Definitions 156 5 The engineer’s duties 223
3 Notices 157 6 The road to dispute avoidance 224
4 The surveyors 157 7 The FIDIC Golden Principles 224
5 The award 158 8 Building Information Modelling 224
Contents vii

20 Other standard forms of building contract 225 2 Litigation in England and Wales 257
Rupa Lakha 3 Litigation in Scotland 258
1 Introduction 225
2 ACA Forms of Contract 225 25 Arbitration 259
3 ICC forms of contract 227 Melanie Willems
4 RIBA forms of contract 228 1 What is arbitration? 259
5 IChemE forms of contract 228 2 The relevance of arbitration law to architects 259
6 IMechE/IET forms of contract 229 3 The purpose of this chapter 259
7 ACE Forms of Contract 230 4 The Arbitration Act 1996 260
8 CECA Forms of Contract 230 5 The importance of deciding whether a process is
9 Building contracts in Scotland* 230 or is not ‘arbitration’ 260
6 The advantages and disadvantages of arbitration
21 Contractor and sub-contractor collateral compared with litigation in court 261
warranties and third party rights 233 7 The arbitration agreement 263
Matthew Cocklin 8 The jurisdiction of the arbitration tribunal 263
1 The privity rule 233 9 Who decides where the tribunal has jurisdiction? 264
2 What is a collateral warranty? 233 10 The composition of the arbitration tribunal 265
3 Contracts (Rights of Third Parties) Act 1999 233 11 The number of arbitrators 265
4 Why are collateral warranties/third party rights so 12 The qualifications of arbitrators 265
important? 234 13 Appointment of the tribunal in multiparty disputes 265
5 Who needs the benefit of collateral warranties/ 14 Prescribing the arbitration procedure 265
third party rights? 234 15 Other provisions which may be found in
6 JCT 2016: who should provide collateral arbitration agreements 266
warranties/third party rights? 235 16 How to commence arbitration proceedings 266
7 JCT 2016: key clauses of Contractor collateral 17 Arbitration procedure or rules 266
warranties 239 18 The general duty of the parties 266
8 JCT 2016: sub-contractor collateral warranties 240 19 Definition of the issues 266
20 The exchange of information and evidence 267
22 The Construction Act Payment Rules 241 21 Evidence of fact and expert evidence 267
Jessica Stephens QC And Jonathan Schaffer-Goddard 22 The arbitration hearing 268
1 Introduction 241 23 The award 268
2 The background to the legislation 241 24 Costs 269
3 To which contracts does the HGCRA apply? 241 25 The power of the tribunal in the case of a party’s
4 Contracts excluded from the payment provisions 242 default 269
5 The payment provisions in detail 242 26 Arbitration procedures found in construction
6 The right to suspend performance for non-payment 245 industry cases 269
7 ‘Pay when paid’ clauses 246 27 The role of the courts in arbitration proceedings 270
8 Interest on late payment of debts 246 28 Powers to enforce the arbitration agreement –
‘staying’ of court proceedings in favour of arbitration 270
29 The court’s powers exercisable in support of the
Part D: Building dispute resolution arbitration process 270
30 Enforcement of arbitration awards 271
23 Adjudication 249 31 The court’s powers to supervise the arbitration process 271
Matthew Thorne 32 Appeals on points of law 272
1 What is adjudication? 249 33 The architect as arbitrator 272
2 To which contracts does it apply? 250 34 The architect as expert witness 273
3 Excluded construction contracts 250
4 The terms required by the HGCRA 250 26 International arbitration 275
5 Contractual adjudications 250 Tony Dymond And Raeesa Rawal
6 Notice of adjudication 251 1 Introduction 275
7 The ‘dispute’ 251 2 Factors relevant to the choice of international
8 Multiple disputes 251 arbitration 276
9 Does the dispute arise ‘under’ the contract? 251 3 The agreement to arbitrate 276
10 Appointment of an adjudicator 252 4 Procedure in international arbitration 277
11 The referral notice 252 5 Interim measures in international arbitrations 278
12 Procedure after the referral notice 252 6 Evidence in international arbitration 279
13 The response to the referral notice 252 7 International arbitration awards – recognition,
14 Confidentiality 253 challenges, and enforcement 280
15 Resignation, revocation, and abandonment 253 8 Costs in international arbitration 280
16 The decision 253
17 Fees and costs 254 27 Mediation 283
18 Enforcement 254 Sheena Sood And Anna Braden
19 Ineffective defences to enforcement proceedings 1 What is mediation? 283
in the TCC 254 2 Background 283
20 Jurisdictional defences to enforcement 3 Agreeing to mediate 283
proceedings 254 4 The correct time to mediate 284
21 Natural justice defences to enforcement 5 Selecting a mediator 284
proceedings 255 6 Costs of the mediation 284
22 Severance 255 7 Confidentiality and privilege 284
23 Getting a final answer 255 8 Preparation for the mediation 285
9 The mediation 285
24 Litigation 257 10 Settlement 285
Anthony Speaight QC 11 Advantages and disadvantages 285
1 Methods of dispute resolution 257 12 Online mediation 286
viii Contents

28 Building dispute resolution in Scotland 287 34 Professional disciplinary proceedings 347


Robert Howie QC James Hatt
1 Arbitration in Scotland 287 1 Introduction 347
2 Adjudication in Scotland 289 2 Disciplinary proceedings under the ARB and
RIBA rules – introduction 347
3 ARB disciplinary proceedings 348
Part E: The architect in practice 4 RIBA disciplinary proceedings 350
5 What you can do 351
29 Legal organisation of architects’ offices 295
Murray Armes 35 Architects’ professional indemnity insurance 353
1 Managing an architectural business 295 James Leabeater QC
2 Partnership 295 1 Why be insured? 353
3 Limited liability partnerships 298 2 Some basic insurance principles 353
4 Companies 298 3 Professional indemnity insurance policies 354
5 Premises and persons 302 4 Risk management 355
6 Insurance 304
7 Scottish postscript 304 36 Copyright and design protection 357
Clive D. Thorne
30 Architects’ contracts with clients 309 1 Copyright 357
Sarah Lupton 2 Protection for architectural works under the Act 359
1 The appointment 309 3 Qualification for protection 359
2 Agreement of appointment 310 4 Publication 360
3 Termination 310 5 Ownership 360
4 Ownership 311 6 Exceptions to infringement of architects'
5 Professional Services Contracts for use by architects 311 copyright 361
6 Speculative work and tendering for architects’ services 313 7 Infringement 361
7 Appointments required by statute 314 8 Licenses 362
8 Scottish appointments* 314 9 Remedies for infringement 364
10 UK Design Law 365
31 Architects’ collateral warranties 315 11 EU Design Law 366
Matthew Cocklin 12 Moral Rights 366
1 Architects and collateral warranties 315 13 Law of copyright in Scotland and Northern Ireland 366
2 The obligation to provide collateral warranties/
third party rights 315 37 Data protection 367
3 The terms of collateral warranties: Hazel Grant
CIC/ConsWa/P&T 316 1 Introduction 367
4 The terms of collateral warranties: 2 Overview of Data Protection Law 367
CIC/ConsWa/F 318 3 Enforcement 371
5 Practical advice 319 4 Application of the law: common scenarios 371
32 Architects’ responsibility for the work of others 321 38 Architects’ registration 375
Bart Kavanagh And Christopher Miers Sarah Lupton
1 Introduction 321 1 The nature of professionalism in architecture 375
2 To whom does an architect owe a duty? 321 2 Architects' registration 375
3 Responsibility for the work of others 322 3 Eligibility for registration 376
4 Minimising the risks 324
39 Professional conduct of architects 379
33 Architects’ liability 327 Sarah Lupton And Peter Anderson
James Cross QC 1 Codes of professional conduct 379
1 Introduction 327 2 ARB code of conduct 379
2 Other professional liability 327 3 RIBA Code of Professional Conduct. 382
3 Liability for professional negligence 330 4 Statement of professional conduct of the Royal
4 Scope of the obligation of reasonable care Incorporation of Architects in Scotland (RIAS) 386
and skill 331
5 Breach of the obligation of reasonable care and Table of Statutes and Statutory Instruments 389
skill: pre-construction work stages 335
Table of Cases 392
6 Breach of the obligation of reasonable care and
skill: construction work stages 337 Table of Legislation 397
7 Damages 339
8 Sharing liability for professional negligence Index 401
with others 340
9 When liability for professional negligence is
barred by lapse of time 344
10 Liability in Scots law 344
Foreword

When the first edition of this book was published in 1973, the The breadth of the subject matter is impressive: in addition to
intention was to provide a concise, comprehensive, and digest- a general introduction to the principles of law, the topics cov-
ible explanation of the law for use by architects in practice. It ered include substantive contract, tort and land law, Scots Law,
succeeded. Now in its tenth edition, nearly half a century later, it standard forms of contract, dispute resolution, and specific areas
is the standard text of choice for architectural students and prac- relevant to the professional rights and obligations of architects,
titioners alike. It is easy to understand its popularity. Although such as copyright and data protection. Each section is a model
many of the legal principles of interest to architects are of gen- of clarity and precision. The modest size of the book belies the
eral application to other professionals, the terminology, forms, wealth of material contained within. I welcome this latest edition
and procedures used in the construction industry raise particular as a valuable source for architects in practice.
issues of law and construction that require careful analysis
against the relevant statutory and regulatory framework. This Mrs Justice O’Farrell DBE
work draws together a diverse range of topics, each compiled Judge in Charge, Technology and Construction Court
by a contributor with specialist expertise, including barristers,
solicitors, and architects.

ix
Editor’s preface

Welcome to the 10th edition of the Architect’s Legal an experienced judge during a recent hearing in the Technology
Handbook. As has been its hope since the first edition, the and Construction Court:
aim of this book remains to provide, within the compass of a We do not have certificates any more. That is all out of date.
single volume, a statement of the law relevant to an architect Nowadays we have notices.
in practice.
As well as comprehensive updates to all chapters, important new
No one lawyer could write with authority about so many dif- additions have also been made to the book:
ferent aspects of the law. Each chapter is contributed by an
expert in the particular field. Our authors come from a range of (a) Chapter 9, on construction legislation, has been much
backgrounds – barristers, solicitors, academics, and architects. expanded to consider the new legal environment in respect
of fire safety following the tragedy at Grenfell Tower in
The book covers the law of the whole of Britain. In space terms, June 2017;
the law of England and Wales occupies pride of place, but Scots (b) A new Chapter 20 covers various additional standard
law is also covered in respect of the many areas of law where it form contracts, including the ACA, RICA, ICC, IChemE,
is different. In this regard, we must express our gratitude to Roy IMechE, ACE, and CECA forms;
Martin QC, who advised us as to Scottish authors, but who sadly (c) A new Chapter 32 concerns architects’ responsibility for the
passed away during the course of compilation of this edition. In work of others;
many fields, the law is the same throughout Britain, by reason (d) A new Chapter 34 covers architects’ disciplinary proceed-
either of Westminster statutes or of EU directives. ings under the codes of professional conduct that govern the
practice of an architect;
The structure of the book remains consistent with previous (e) In addition to the expansion of Chapter 36 on Copyright
editions: and Design Protection, an important new Chapter 37 covers
Data Protection, in light of the introduction of the General
A. General principles of law; Data Protection Regulation (GDPR) from May 2018 and the
B. The statutory framework: this part of the book encompasses Data Protection Act 2018 (DPA).
the statutory authorities, construction, regulations, planning
law, public procurement regulations, party wall legislation, An effort has been made in this edition to minimise the usage of
and health and safety law; the masculine for contexts in which the reference could, in fact,
C. Building contracts: this covers procurement methods, the be to either gender. However, the development of gender-neutral
commonly used standard forms of building contract, and language, which has become almost standard in most walks of
Construction Act payment rules; life, has not been so easy in the legal world. Its culture has
D. Building dispute resolution: this includes litigation, arbitra- inevitably been affected by the Interpretation Act, which sets out
tion, adjudication, and mediation; a number of space-saving standard usages for statutes including,
E. The architect in practice: this part of the book focusses on ‘words importing the masculine gender include the feminine’.
architects’ registration and professional conduct, contracts Furthermore, the adoption in common parlance of ‘they’ as a per-
with clients and collateral warranties, responsibility for sonal pronoun for the singular as well as the plural has not come
the work of others, liability in negligence, and disciplinary so easily to judges and lawyers, for whom correctness of gram-
proceedings. It also covers other aspects of the law relevant mar and exactitude of language are values of importance to good
to an architect, such as copyright, data protection, and quality legal work. Both drafters of standard contracts and legal
insurance. textbook writers have, at any rate, until very recently, regarded
it as normative for ‘he’ to connote in the reader’s ear ‘he or she’.
Over the period since the last edition of this work, the legal So, where necessary, we ask the indulgence of readers.
framework of architectural practice has undergone significant
changes. A decade ago, an architect’s regular practice might well This book is not intended to turn architects into fully fledged
have been projects undertaken by traditional procurement, with legal advisers. What we hope is that it will identify for archi-
payment to the contractor on the basis of certificates. Today, the tects the legal issues affecting their work and alert them to the
same firm’s practice may relate to projects on design and build circumstances in which legal advice is necessary. Unrealistic
contracts let by employers who want the architect to switch as many of us may consider the law’s standard to be, the hard
its obligations by a ‘novation’ to the contractor, to achieve a reality is that judges expect architects either to know a good deal
single point of responsibility for every aspect of activity. The of law themselves, or else regularly to call on legal advice. In
extent of change was reflected with deliberate exaggeration by Rupert Morgan v Jervis (2003), the Court of Appeal held that an

xi
xii Editor’s preface

architect might commit a negligent breach of duty if he or she been ‘fireproof’ if he had taken legal advice; but he had not, so
failed to inform a client when a Construction Act withholding he was not, and a heavy judgment against him for professional
notice was needed. negligence was the result.

It was a similar story in West Faulkner Associates v London Anthony Speaight QC


Borough of Newham (1994). An architect’s interpretation of Matthew Thorne
‘regularly and diligently’ in the JCT contract was different from 4 Pump Court, Temple, London
that of the judges. The Court of Appeal said he would have
Acknowledgements

Acknowledgement is given to the following bodies for permis- NEC/ICE Publishing


sion to use sample documents and statutory publications: Royal Incorporation of Architects in Scotland
Royal Institute of British Architects
Architects’ Registration Council of the United Kingdom Scottish Building Contracts Committee
British Property Federation
British Standards Institution
Building Employers’ Confederation Information provided in this document is provided ‘as is’, with-
Construction Industry Council out warranty of any kind, either express or implied. Every effort
Her Majesty’s Stationery Office has been made to ensure accuracy and conformance to standards
JCT Contracts accepted at the time of publication. The reader is advised to
Office for Official Publications of the European Communities research other sources of information on these topics.

xiii
Contributors
Editors Matthew Thorne – Barrister, in practice at 4 Pump Court,
Anthony Speaight QC – Barrister, in practice at 4 Pump Court, Temple, London, and member of Inner Temple. He is on the
Temple, London. Bencher of Middle Temple. His publications committee of the Technology and Construction Bar Association,
include The Law of Defective Premises (co-author) and the chairman of Junior TECBAR, and a member of the Society of
Butterworths Professional Negligence Service (contributor). Construction Law and Professional Negligence Bar Association.
Anthony is a past member of the Council of the Society of He is ranked in the legal directories as a leading junior in
Construction Law, past chairman of the Editorial Board of Construction and Professional Negligence. He has been a co-
Counsel, Journal of the Bar of England & Wales, and past author of LexisPSL Adjudication and is the author of Becoming
Chairman of the Bar Council’s Access to the Bar Committee. a Barrister. He is an accredited Adjudicator.
He acts as a supervisor of dissertations at the King’s College
London Centre of Construction Law. He is an accredited
Adjudicator and trained Mediator.

Contributors Tony Dymond – Partner, Debevoise & Plimpton LLP,


International Dispute Resolution Group, and Co-Chair of the
Murray Armes, BA (Hons), DipArch, MA, MSc (Constr Asia Arbitration Practice.
Law), RIBA, FCIArb, MAE – A Chartered Architect, Chartered
Arbitrator, Adjudicator, Expert Witness, Dispute Board Member, Martin Edwards, BSc (Hons) Arch, DipArch, RIBA, AAE,
and CEDR accredited Mediator. Murray is the founder of Sense MIFireE – Chartered Architect with over 35 years’ experience
Studio, a London-based architectural practice specialising in the in a wide spectrum of building in the UK and abroad; he joined
avoidance and resolution of international construction disputes. Probyn Miers in 2013. He has been instructed as an Expert
Murray has wide ranging experience in the construction industry, Witness in cases involving defective design and construction
spanning over 35 years including many types of construction and the performance of architects and contractors; he has also
projects and disputes in the UK, Europe, Middle and Far East, acted as Single Joint Expert. His extensive expertise on the
Africa, and Central Asia. He is on ADR panels run by the CIArb, analysis of spread of fire and on fire safety has positioned
RIBA, RICS, CEDR, CMC, and also on the FIDIC President’s Martin to address complicated negotiations with Fire Brigades
List of international adjudicators. and Local Authorities over the fire strategies for large buildings;
he has reported on fatal fires for criminal proceedings. Martin
Anna Braden – Senior Associate at specialist international currently continues his role at Probyn Miers as a permanent
construction and insurance law firm Beale & Co, specialises in consultant.
professional negligence claims and construction disputes in the
UK and internationally. She has experience with all areas of Andrew Fraser-Urquhart QC, MA (Cantab) – called to the
dispute resolution, including international arbitrations, litigation, Bar in 1993, having previously been employed by the Bank of
adjudication, and mediation. England. He practises from Francis Taylor Building where he
specialises in Town and Country Planning, Local Government,
Matthew Cocklin, LLB, LLM, MSc, FCIArb – Solicitor, Partner and Judicial Review. He has extensive experience in both of
at Devonshires Solicitors LLP; Construction, Engineering and planning inquiries and Local Plan work.
Procurement Group. Joined Devonshires in 2013 after a career
at Mott MacDonald, becoming a partner in 2015. Acts for all Jeremy Glover, BA (Hons) – solicitor and accredited
groups in the construction sector with particular emphasis on Adjudicator, Jeremy has been a partner at Fenwick Elliott LLP
adjudication, arbitration, litigation, and mediation. Contributes since 2002. He specialises in construction, engineering, and
to industry and legal publications. Winner of the Society of energy law both at home and abroad. Lead editor of Building
Construction Law Hudson Prize 2012. Contract Disputes: Practice and Precedents and co-author of
Understanding the FIDIC Red and Yellow Books, the 3rd Edition
Thomas Crangle is a barrister and adjudicator practising from of which was published in December 2018.
4 Pump Court. He specialises in construction and engineering,
energy, and infrastructure disputes in the UK, the Middle East, Hazel Grant – Partner and head of Privacy at Fieldfisher,
and the Far East. London. She read law at Cambridge and qualified as a solicitor
in 1992. She has advised on privacy issues for over 20 years,
James Cross QC – Barrister at 4 Pump Court. Called to the Bar for clients across many sectors including the public sector,
in 1985 after graduating in law from Magdalen College, Oxford professional services, IT, and leisure. Hazel has set professional
(where he was also a lecturer in law), James has been a QC qualification exams in privacy (for the International Association
since 2006 and has an extensive and wide-ranging commercial of Privacy Professionals) as well as been a long time editor and
practice. Recommended in both Chambers UK and the Legal contributor to the Encyclopaedia of Data Protection and Privacy
500 as a Leading Silk for Construction, Professional Negligence (Thomson Reuters).
and Property Damage work, James has particular expertise in
construction and engineering, PFI/PPP contracts (including UK James Hatt – Barrister practising from 4 Pump Court, a leading
Government contracts), insurance, property damage ,and product construction and commercial Chambers, in areas of law includ-
liability claims. ing construction and energy disputes, professional negligence,
and professional discipline.
Professor Martin Dixon, MA PhD – Professor of the Law
of Real Property, Fellow of Queens’ College University of Bart Kavanagh, MA (Arch), LLM, Dip Int Arb, RIBA, FCIArb,
Cambridge, Honorary Bencher of Lincoln’s Inn, General MAE – a Chartered Architect, Barrister (non-practising), and
Editor, The Conveyancer & Property Lawyer. Author (with Associate Director of Probyn Miers. With over 35 years’ experi-
S Bridge and E Cooke), Megarry & Wade, The Law of Real ence in architectural practice, he has worked extensively in the
Property. commercial, airport, retail, and residential sectors. In dispute

xiv
Contributors xv

resolution, he has been appointed as an expert witness in over expert reviews on a wide range of technical problems in con-
120 cases. He has been cross examined in the High Court and in struction, he has given Expert Evidence in Court and has been
international arbitrations, has presented evidence in adjudication a key participant in several mediations. He is well-versed in
proceedings, and frequently participates in mediations. He has BIM (Building Information Modelling) procedures and emerg-
written numerous articles on matters related to dispute resolution ing conventions.
and is the author of ‘Avoiding & Resolving Disputes’, published
by the RIBA. Graham North, FRICS MClArb – a Chartered Building
Surveyor and Director of Anstey Horne, specialises in party
Rupa Lakha – a partner at Charles Russell Speechlys LLP wall matters and boundary issues generally; past chairman of
specialising in construction law. Rupa acts for developers and the Boundaries & Party Walls Practice Panel of the RICS and
contractors, focusing on project advisory work and all forms Building Surveyors’ Division of the City of London Branch of
of dispute resolution. Rupa has been ranked as ‘a rising star at the RICS. He has updated and edited Anstey’s Party Walls and
partner level’ in Who’s Who Legal: Construction 2019: Future The Party Wall Surveyors Manual by RICS books. In 2007,
Leaders. he was awarded the Michael Barratt Memorial Medal by the
RICS for his outstanding contribution to Party Wall matters. He
James Leabeater QC, MA (Oxon) – Barrister practising from lectures regularly to the property profession and for RICS and
4 Pump Court, Temple, London, whose practice includes con- RIBA Branches.
struction, professional negligence and insurance law. James has
years of experience of acting on claims against architects, and of Claire Packman – a barrister practising at 4 Pump Court,
issues that arise in relation to architects’ professional indemnity specialising in construction and the professional liability of
insurance, in the UK and around the world, both in Court and construction professionals such as architects, surveyors and engi-
in arbitration. neers. She is ranked as a leading junior in Legal 500, Chambers
& Partners and Chambers Global for Construction, Professional
Professor Sarah Lupton, MA, DipArch, LLM, FCIArb, Carb, Negligence and International Arbitration (Construction and
RIBA, – holds a personal chair at Welsh School of Architecture Engineering). She is an elected member of the Council of the
and is a partner in Lupton Stellakis. She lectures widely on SCL (Society of Construction Law) and a contributing author to
subjects relating to construction law, and acts as arbitrator, the LexisNexis Adjudication KnowHow.
adjudicator and expert witness in construction disputes. She is a
member of several industry and professional committees, and is Simon Plunkett – Partner in Pinsent Masons LLP with 25 years’
chair of the Construction Industry Council Liability Panel. Sarah experience of providing risk management and dispute resolution
is the author of many books, including a series on the JCT and advice in the construction, infrastructure and energy sectors.
RIBA standard form building contracts and the fifth edition of Accredited mediator and solicitor advocate with Higher Rights
Cornes and Lupton’s Design Liability in Construction. Sarah of Audience (England and Wales).
is co-author (with Manos Stellakis) of ‘Which Contract?’, and
of series of books on the use of performance specification, and Zena Prodromou, Ptychio, LL.M., PhD –Senior Associate
on legislative controls. Sarah is currently the external examiner at Quinn Emanuel Urquhart & Sullivan LLP in Brussels. She
for the MSc in Construction Law and Dispute Resolution at the specialises in EU competition and regulatory law, including the
British University in Dubai, and for the Architects’ Professional application of public procurement and state aid rules; interna-
Examination Authority in Scotland. tional arbitration and litigation; and private international law. She
is featured in the arbitrator rosters held by various international
Christopher Miers, BA, DipArch, MSc(Constr Law), RIBA, institutions and regularly publishes on EU law and international
FCIArb, MAE – Chartered Architect, Chartered Arbitrator dispute resolution. She is an affiliated member of the Institute for
and the founder/ MD of Probyn Miers (1998), a UK team European Law at the University of Leuven since September 2019.
of Architects in forensic analysis and ADR with offices in
London and Dubai. He is widely appointed for his expertise in Raeesa Rawal – Associate, Debevoise & Plimpton LLP,
International Dispute Avoidance and Resolution as an Arbitrator, International Dispute Resolution Group.
Adjudicator, Mediator, Dispute Board member, and as Expert
Witness. Past Chairman of the Society of Construction Law, Jonathan Schaffer-Goddard – a barrister at 4 Pump Court, a
he sits on JCT Council as a representative of the RIBA. He is leading construction and commercial Chambers, and specialises
on the panels of Mediators, Adjudicators and/or Arbitrators of in construction, IT, and shipping disputes.
the DRBF (past international President), RICS, CIArb, CEDR,
CIOB, and Resolex, and he is on the FIDIC President’s List. Sheena Sood – Senior Partner at specialist international con-
struction and insurance law firm Beale & Co, advises on a
Theresa Mohammed, LLB, MA – Solicitor, Partner at inter- wide range of complex construction disputes across the globe,
national law firm Trowers & Hamlins in Dispute Resolution advising architects and major construction consultants. She has
& Litigation. Theresa specialises in construction and engineer- been involved in a diverse range of professional negligence and
ing disputes and won Best Woman in Construction Law at the construction disputes, where she is praised for her approach and
European Women in Construction and Engineering Awards specialist knowledge of the industry. She also assists clients with
2017. Theresa works on a wide range of construction disputes professional regulatory issues and through health and safety
acting for contractors, subcontractors, and employers and has investigations. She is a regular columnist for industry publica-
developed expertise in high value and complex domestic litiga- tions and speaker at construction conferences.
tion. Theresa also regularly contributes to industry publications
and is National Chair of the National Association of Women in Jessica Stephens QC – a barrister at 4 Pump Court with a
Construction. practice specialising in construction and construction-related
professional negligence, energy, infrastructure, and shipbuilding.
Frank Newbury, BA, BArch, RIBA, MAE – Chartered
Architect with over thirty years’ experience of architectural prac- James Strachan QC, MA (Oxon) – a Barrister at Law practis-
tice. A team member of Probyn Miers. He has been appointed as ing from 39 Essex Chambers, London specialising in public and
an Expert Witness as principal expert on dispute resolution and administrative law, planning and environment, local govern-
litigation involving architects and contractors on sensitive cases ment, human rights, and financial services. He was appointed
involving alleged professional negligence in the design and/or as a Deputy Judge High Court Judge in 2018. He served on the
administration of construction projects. Frank has undertaken Attorney General’s Counsel to the Crown from 2003, and the
xvi Contributors

Welsh Assembly’s Government Panel of Counsel from 2009, before calling to the Scottish Bar in 1997, taking silk in 2012. He
until his appointment as Queen’s Counsel in 2013. has a civil and commercial practice, including contract, property,
professional liability, cross-border issues, and arbitration. His
Clive Thorne – Partner at McCarthy Denning in London, spe- commercial experience includes complex contractual, construc-
cialising in Intellectual Property and IT disputes. He also prac- tion, and property disputes, shareholders’ litigation, directors’
tises as an arbitrator and is a Fellow of the Chartered Institute fiduciary duties, and professional negligence. He is a Fellow of
of Arbitrators. He read law at Trinity Hall, Cambridge and the Chartered Institute of Arbitrators (FCIArb).
was admitted as a Solicitor in 1977. He is admitted in and has
practised in Hong Kong, and is also admitted as a Barrister and Alasdair Burnet, BA LLB – is an Advocate in Terra Firma
Solicitor in Victoria, Australia. He is the co-author of ‘A User’s Chambers, a leading planning, property, and administrative
Guide to Copyright’ and ‘A User’s Guide to Design Law’. law chambers in Edinburgh. His principal areas of practice
are planning and property law. He has appeared in a num-
Simon Tolson, BA (Hons), FCIArb – Solicitor, Chartered ber of high profile cases and public inquiries including the
Arbitrator and Senior Partner of Fenwick Elliott LLP, special- Edinburgh Tram Inquiry and in the UK Supreme Court in
ised in construction and engineering law for over 30 years, with Elsick Development Co Ltd v Aberdeen City and Shire SDPA
particular emphasis on dispute resolution. He is ranked amongst [2017] UKSC 66. He is a graduate of Oxford and Edinburgh
the top construction solicitors, in Chambers & Partners UK, The Universities and has been a Standing Junior to the Scottish
Legal 500, Who’s Who Legal, and The Legal Experts guide. Government since 2012.

Melanie Willems – Head of International Arbitration in the Graham Dunlop, BA LLB LLM – is an Advocate in Terra
London office of Haynes and Boone LLP, has specialised in this Firma Chambers, a leading planning, property, and administra-
area for over 27 years. She is experienced in all forms of alternative tive law chambers in Edinburgh. His principal areas of practice
dispute resolution (including expert determination, mediation, and are in property, planning, and employment law. He has appeared
adjudication). She has extensive experience in ad hoc proceedings in a number of high profile cases, including the Edinburgh Tram
and the major international rules, such as ICC, LCIA, UNCITRAL, Inquiry. He sits as a legal member of the First-tier Tribunal for
ICSID, and standard form contract rules. Melanie has been rec- Scotland (Housing & Property) Chamber and is on the panel of
ognised among the leading international arbitration lawyers in preferred Counsel to the Commission for Equality and Human
London by major directories. She is an ex-President of the Society Rights.
of Construction Arbitrators, a Fellow of the Chartered Institute of
Arbitrators, sits as an arbitrator, and speaks fluent French. William Frain-Bell, MA LLB, FCIArb – is a Chartered
Arbitrator and a practising Advocate in Scotland and a member
Scottish Contributors of Terra Firma Chambers in Edinburgh. He has a wide ranging
civil practice with a particular interest in arbitration, construc-
Peter Anderson, LLB (Hons) – Solicitor and Solicitor Advocate; tion disputes, land, and property-related disputes. He is a gradu-
for many years, Senior Litigation Partner at Simpson & ate of St Andrews and Aberdeen Universities. William is also
Marwick WS, Edinburgh; honorary Legal Advisor to the Royal a member of the Bar of England & Wales and is a member of
Incorporation of Architects in Scotland from 1991 to 2018; pres- Thomas More Chambers.
ently Consultant, Levy and McRae Solicitors Glasgow; part-time
Judge in the Sheriff Courts Scotland from 2003 to date; part-time Robert Howie, QC, LLB – Advocate.
Tribunal Judge, Criminal Injuries Compensation Appeal Tribunal
from 1998; member Competition Appeal Tribunal from 2017; Catriona MacLeod, LLB (Hons) – prior to becoming an advo-
Chair Institute of Chartered Accountants of Scotland Discipline cate, Catriona was a solicitor for several years in private practice
Tribunal, 2002 to date. (commercial property) and the public sector (property, planning,
and roads). Called to the bar in 2007, she practices in property,
Andy Bowen QC MA (Oxon), LLM (Lond) – qualified as a public, and commercial law and is also a tutor in public law in
solicitor (1989) and barrister (1993) in England and Wales Edinburgh University school of Law.
Part A
General
principles of law
1
Introduction to English law
ANTHONY SPEAIGHT QC

1 The importance of law specialist legal advice is needed. He or she should then advise
the client to obtain legal advice. Alternatively, the architect can
1.01 Every civilised human society has had a concept of law. instruct a barrister directly.
The role of law within such a society is often expressed by the
phrase ‘the Rule of Law’. A distinguished academic lawyer,
Professor Sir Neil MacCormick, recently explained the notion 2 The place of English law
in this way:
2.01 There are two principal legal systems in the western world.
The Rule of Law is a signal virtue of civilised societies. … One is the so-called civil law system, which prevails in most
This gives significant security for the independence and dig- parts of continental Europe. It has its origins in Roman law and
nity of each citizen. Where the law prevails, you know where is today founded on written codes. The other is usually known
you are, and what you are able to do without getting yourself as the common law system. This originated in England dur-
emboiled in civil litigation or in the criminal justice system. ing the Middle Ages. Today, it is the basis of law in Canada,
(N MacCormick, Rhetoric and the Rule of Law, OUP, 2005) Australia, New Zealand, Hong Kong, Singapore, and almost
all former British territories. It is even the basis of law in the
The Rule of Law operates through the existence of many indi- United States of America. The international character of English
vidual rules. In highly developed communities, these rules have law is not often appreciated by non-lawyers, but is sufficiently
grown into a complex body of laws. Such laws are the subject alive for cases from other common law jurisdictions to guide
of this book. English courts on those occasions, which are, admittedly, rare,
when English case law is silent on a point. The courts of other
common law jurisdictions more frequently follow English deci-
Architects and the law sions. A Commonwealth Law Conference held every three years,
1.02 It is an essential feature of the concept of the Rule of at which the leading lawyers from remarkably diverse national
Law that its application should be universal: everybody must backgrounds discuss legal issues together, serves to reinforce the
be subject to the law. It follows that the law must apply to an bonds of the common law world.
individual whether or not he or she is aware of the law. Hence
the well-worn maxim that ‘ignorance of the law is no excuse’. 2.02 Today, English law is chosen as the applicable law for
many commercial contracts for activities outside Britain. A
1.03 This has a practical consequence for those who practise in well-drafted contract with any international dimension will
any profession – in addition to the skills particular to that profes- specify the law which is to govern it: English law has become
sion, they must also become acquainted with those parts of the a popular choice in many parts of the world The High Court
law which are relevant to the work of their profession. All who in London is also a popular forum for disputes which do not
offer a service to others and claim expertise to do what they offer necessarily have a connection with Britain: in 2018–19, some
have a responsibility, to society in general and to their clients in 75% of its work was categorised as ‘international’. London
particular, to know the law. That applies to architects, quite as is also a significant centre for arbitrations: it is believed that
much as to any other profession. Hence this book. more international arbitrations take place in London than in
any other city in the world.
1.04 In the case of an architect, the relevant fields of law are
notably those of contract, especially the standard forms of build- The legal systems of the United Kingdom
ing contract, and the various statutory regulations, such as the
Building Regulations, planning law, health and safety law, and 2.03 Within the United Kingdom, there are two traditions of
the like. An architect will also want to know about the areas law and three principal legal jurisdictions. English law prevails
of law which affect him or her personally. When can they be in the jurisdiction which is constituted by England and Wales.
sued? How can they sue for fees? When is copyright in their The English common law system is also the basis of the law
drawings protected? How should they insure? What is the legal in Northern Ireland, but Northern Ireland has its own statutory
relationship between architect and employer? An architect is not provisions and also its own courts. Scotland has not only its own
expected to know all the law in these areas personally. But he courts, but also its own law and legal traditions. It had its own
or she is expected to ensure that the client does not suffer from system at the time of the Union in 1707, and always retained it.
the absence of such legal knowledge. The architect is expected Some aspects of Scots law are based on Roman law, and thus
to know enough law to be aware of the circumstances in which it reflects to some extent the features of the civil law system.

3
4 Introduction to English law

2.04 It is a little unsatisfactory that the term ‘English law’ is the future. Such precedents are binding on every court with
regularly used to refer to a jurisdiction which covers Wales as jurisdiction inferior to the court which gave the decision; even
well as England, but the direction for Wales in terms of law is courts of equal or superior jurisdiction seldom fail to follow an
currently uncertain. On the one hand, it might be fair for us to earlier decision. Since 1966, the House of Lords and now the UK
speak of the law which Welsh judges and lawyers have played, Supreme Court have regarded themselves as free to depart from
and today play, a part in forming as ‘English and Welsh law’, their previous decisions, but have done so on only a handful of
rather than ‘English law’. On the other hand, as the National occasions.
Assembly for Wales enacts a growing volume of law specific to
Wales, there is a call for Welsh law to be recognised as a distinct
thing of own, and for the development of Wales as a separate
Legislation
legal jurisdiction, in the same way as Northern Ireland. In 2013, 3.06 Legislation – the written or enacted law – comprises the
the Welsh Government published a report on a consultation on a statutes enacted by Parliament and statutory instruments made
separate legal jurisdiction for Wales, without firmly advocating by ministers under powers conferred by statute. Primary legisla-
its adoption at the present time. For the moment, writers like tion, that is, Acts of Parliament, takes precedence over all other
me can only express the hope that we do not cause offence by sources of law.
continuing to use the traditional terminology.
3.07 Over the course of the 20th century, it became increasingly
2.05 The one unifying feature of the legal system of the United common for Parliament to delegate the power to make the details
Kingdom today is the Supreme Court, which is the final court of law to ministers in the form of secondary legilsation, often
of appeal for all three jurisdictions. It usually has 12 Justices, of entitled Regulations. Some such powers require an affirmative
whom two are by tradition always Scots, and one has recently resolution of both Houses of Parliament to take effect; others
been from Northern Ireland. There is also currently one Justice merely allow Parliament, if it chooses, to annul the statutory
who is a Welshman. Prior to October 2009, the role of final instrument. Local authorities are also empowered within spe-
court of apeal was performed by the Judicial Committee of the cific competences to make rules binding on citizens known as
House of Lords. by-laws.

2.06 In consequence of this divergence between the legal tra- 3.08 The courts are required to interpret Acts in accord with
ditions and laws of Scotland on the one hand, and the other the wording employed. They may not question or even discuss
parts of the United Kingdom on the other, throughout this book the validity of the enactment. Rules have been established to
there will be separate sections discussing certain particular fea- help them interpret ambiguities: there is a presumption that
tures of Scots law. Parliament in legislative matters does not make mistakes, but
in general, this principle does not apply to statutory instruments
unless the governing Act says anything to the contrary. The
3 Sources of English law courts may decide whether rules or orders are made within the
powers delegated to the authorised body ordered to make them,
3.01 English law may be conveniently divided into two main or whether they are ultra vires (outside the body’s power).
parts – unwritten and written – and there are several branches By-laws must not only be intra vires, but also reasonable.
of these.
European Union law
Common law
3.09 On 1st January 1973, the United Kingdom became a
3.02 Common law – the unwritten law – includes the early cus- member of the the European Communities, which evolved into
tomary laws assembled and formulated by judges, with modifica- the European Union. On 31st January 2020, the country left
tions of the old law of equity. Common law therefore means all the EU. During the period of the UK’s membership, it was
other than enacted law, and rules derived solely from custom and a party to a series of treaties by which it undertook to give
precedent are rules of common law. It is the unwritten law of the effect both to the contents of the treaties and to law made by
land because there is no official codification of it. the institutions of the EU. That law comprised Regulations,
whose terms were required to be given directly binding effect
3.03 The basis of all legal argument and decision in the English in all member states, and Directives, which required mem-
courts is founded upon the application of rules announced in ear- ber states in their own way to enact domestic law to achieve
lier decisions and is called stare decisis (let the decision stand). specified results. Parliament achieved compliance with these
From this has evolved the doctrine of judicial precedent, now a international obligations of the UK by enacting the European
fundamental characteristic of common law. Communities Act 1972. Section 2(1) of the 1972 Act provided
that all directly applicable provisions of the treaties establishing
3.04 It is essential for the operation of a system of law based the European Communities should become part of English law;
on previous cases that well-authenticated records of arguments so, too, would all existing and future Community secondary
and decisions be available to all courts and everyone required legislation. Decisions of the European Court of Justice on the
to advise on the law. In the 18th and early 19th centuries, there principles affecting EU instruments were to be given effect by
were many private publishers of reports of judgments. In 1865, domestic courts.
a semi-official Incorporated Council of Law Reporting was
established, whose hard copy volumes of reports of the most 3.10 Following the 2016 referendum, Parliament enacted the
important decisions continue to this day. There are now also European Union (Withdrawal) Act 2018, which was amended
computerised law libraries, of which one is free – the British and by the European Union (Withdrawal Agreement) Act 2020.
Irish Legal Information Institute located at http://www.bailii.org. Their combined effect has been to repeal the 1972 Act, but then
immediately to bring s.2(1) back into effect with only limited
3.05 Legally, the most important part of a judgment is that modifications. This new phase of EU law, which includes all
where the judge explains the principles on which he or she has new law emanating from the EU, is to last only until the end of
based the decision. A judgment is an authoritative lecture on a the Implementation Period under the Withdrawal Agreement. At
branch of the law; it includes a ratio decidendi (the statement of the time of writing, this was to be 31st December 2020. Upon
grounds for the decision) and one or more obiter dicta (things the end of the Implementation Period, there is to be a freezing
said by the way, often not directly relevant to the matters at of EU law. That frozen law will remain part of domestic law as
issue). It is the ratio decidendi which creates precedents for EU-derived law, unless and until modified by Parliament.
English legal history 5

The European Convention the Convention is accorded some standing in English law, with-
on Human Rights out derogating from the supremacy of Parliament. This has been
achieved by enacting that legislation should, so far as possible,
3.11 In 1950, a number of western European countries adopted a be interpreted in accordance with Convention rights. If this is
Convention for the Protection of Human Rights and Fundamental impossible, a court may make a declaration of incompatibility.
Freedoms (now invariably referred as the European Convention
on Human Rights). It was a symbolic response both to the
horrors of Nazism in the recent past and to the curtailment of 4 English legal history
freedom in the communist states of eastern Europe. A novel
feature of this Convention was the creation of a European Court
of Human Rights, in which individual citizens could present
The origins of the common law
grievances against their governments. 4.01 One cannot understand some parts of English law, espe-
cially land law, without an awareness of its history. The seeds of
3.12 For many years the Convention and the Court had no stand- custom and rules planted in Anglo-Saxon and earlier times have
ing within the United Kingdom beyond the fact that the United developed and grown gradually into a modern system of law. The
Kingdom government had, by a treaty, undertaken to accept Normans interfered little with common practices they found, and
them. Enthusiasts for the Convention saw it as potentially some- almost imperceptibly integrated them with their own mode of
thing which might play a role similar to that of the United States life. William I did not regard himself as a conqueror, but claimed
constitution. But any form of entrenchment of fundamental rights to have come by invitation as the lawful successor of Edward the
in the United Kingdom is hard to reconcile with the democratic Confessor – whose laws he promised to re-establish and enforce.
doctrine of the supremacy of Parliament, of which a facet is the
principle that no parliament can bind its successor. Eventually, a 4.02 The Domesday Book (1086), assembled mainly by itin-
mechanism was adopted in the Human Rights Act 1998 whereby erant judges for taxation purposes, provided William I with
6 Introduction to English law

a comprehensive social and economic survey of his newly 4.08 During the early history of the Court of Chancery, equity
acquired lands. The feudal system in England was more univer- had no binding rules. A Chancellor approached his task in a dif-
sally applied than it was on the Continent – a result, perhaps, ferent manner from the common law judges; he gave judgment
of the thoroughness of the Domesday survey. Consequently, in when he was satisfied in his own mind that a wrong had been
England, feudal law was not solely a law for the knights and done, and he would order that the wrong be made good. Thus,
bishops of the realm, nor of some parts of the country alone: the defendant could clear his own conscience at the same time.
it affected every person and every holding of land. It became The remedy for refusal was invariably to be imprisoned until he
part of the common law of England. came to see the error of his ways and agree with the court’s rul-
ing. It was not long before a set of general rules emerged in the
4.03 To the knowledge acquired from Domesday, the Normans Chancery Courts which hardened into law and became a regular
applied their administrative skills; they established within the part of the law of the land.
framework of the feudal system new rules for ownership of
land, new obligations of loyalty to the administration under the 4.09 The consequence of the rules of equity becoming rigid
Crown, and reorganized arrangements for control of the people was that the country had two parallel courts systems offering
and for hearing and judgment of their disputes. These were the different remedies and applying different rules. The existence of
true origins of our modern legal system. separate courts administering the two different sets of rules led
to serious delays and conflicts. By the end of the 18th century,
4.04 Ultimate ownership of land in England is still, in theory, the courts and their procedures had reached an almost unbeliev-
in the Crown. The lord as ‘landowner’ merely held an ‘estate’ able state of confusion, mainly due to lack of coordination of the
or ‘interest’ in the land, directly or indirectly, as tenant from the highly technical processes and overlapping jurisdiction. Charles
king. A person holding an estate of the Crown could, in turn, Dickens describes, without much exaggeration, something of
grant it to another person, but the ownership still remained in the troubles of a litigant in Chancery in the case of ‘Jarndyce v
the Crown. The tenant’s ‘interest’ may have been of long or Jarndyce’ (Bleak House).
short duration, and as varied as the kinds of services that might
be given in return for the ‘estate’. In other words, many differ-
ent estates and interests in land existed. Tenure and estate are
Victorian reforms
distinct. ‘Tenure’ refers to the relation of the landlord to his 4.10 Nineteenth-century England was dominated by a spirit of
overlord, at its highest level to the king. ‘Estate’ refers to the law reform, which extended from slavery to local government.
duration of his interest in the land, and has nothing whatever to The court system did not escape such reform. The climax came
do with the common use of the word. with the passing of the Judicature Acts of 1873 (and additional
legislation in the years that followed) whereby the whole court
4.05 English law, as a result, has never used the concept of system was thoroughly reorganized and simplified. The Act also
ownership of land, but instead has concentrated on the fact of brought to an end the separation of common law and equity; they
‘possession’, mainly because ownership can refer to so many were not amalgamated, and their rules remained the same, but
things and is ill-fitted to anything so permanent and immovable henceforth the rules of both systems were to be applied by all
as a piece of land. A person’s title to land in England is based on courts. If they were in conflict, equity was to prevail.
being able to prove that he or she has a better right to possession
of it than anyone else who claims it. 4.11 The Judicature Act 1873 established a Supreme Court of
Judicature (which is not to be confused with the present day
4.06 In the reign of King Henry II (1154–1189), the ‘king’s UK Supreme Court created in 2009). This consisted of two
justice’ began to be administered not only in the King’s Court, main parts:
where the sovereign usually sat in person and which accompa-
nied him on his travels about the country, but also by justices 1 The High Court of Justice, with three Divisions; all courts
given commissions of assize directing them to administer the of Common Law; and Equity. As a matter of convenience,
royal justice systematically in local courts throughout the whole cases concerned primarily with common law questions
kingdom. In these courts, it was their duty to hear civil actions being heard in the Queen’s Bench Division; those dealing
which previously had been referred to the central administra- with equitable problems in the Chancery Division; and the
tion at Westminster. It was these judges who created the com- Probate, Divorce, and Admiralty Division with the three
mon law. On completion of their circuits and their return to classes indicated by its title.
Westminster, they discussed their experiences and judgments 2 The Court of Appeal – hearing appeals from decisions of
given in the light of local customs and systems of law. Thus, a the High Court and most appeals from County Courts.
single system common to all was evolved; it was judge-made in
the sense that it was brought together and stated authoritatively
by judges, but it grew from the people in that it was drawn
Modern reforms
directly from their ancient customs and practices. To this day, 4.12 By the Courts Act 1971, there was a modest re-organisation
the year of Henry II’s death, 1189, is regarded by the English of the divisions of the High Court. A Family Division was cre-
common law as marking the start of legal history. ated to handle child cases as well as divorce and matrimonial
property disputes, and the Crown Court was created in place of
a confusing array of different criminal courts. During the last
Equity decades of the 20th century, the work of the County Courts was
4.07 In the Middle Ages, these common law courts failed to progressively extended, with the financial limit of their jurisdic-
give redress in certain types of cases where redress was needed, tion being progressively lifted.
either because the remedy the common law provided (i.e. dam-
ages) was unsuitable or because the law was defective in that 4.13 By the Constitutional Reform Act 2005, a new UK Supreme
no remedy existed. For instance, the common law did not rec- Court was established. It started to operate in October 2009. As
ognise trusts, and at that time there was no way of compelling a mentioned above, it replaces the House of Lords as the final
trustee to carry out his obligations. Therefore, disappointed and appeal court. It also hears challenges in respect of the jurisdic-
disgruntled litigants exercised their rights of appeal to the king tion of the Scottish Parliament, the National Assembly for Wales,
– the ‘fountain of all justice’. In due course, the king, through and Northen Ireland Assembly.
his Chancellor (keeper of his conscience, because he was also
a bishop and his confessor), set up a social Court of Chancery 4.14 Finally, mention should be made of a judicial body which
to deal with them. plays no part in determining UK cases, but whose decisions
The scheme of this book 7

are accorded the greatest respect in English courts. That is the 4 The fourth section deals with dispute resolution. The
Judicial Committee of the Privy Council. This body is composed default method of finally resolving disputes in most spheres
either wholly or mostly of the most senior UK judges. Its work is of activity is litigation, but in the construction world,
to hear appeals from courts in various parts of the world, where there are a number of alternatives, which are frequently
the constitutions of the countries provide for a right of appeal used. Many construction contracts, especially international
to the Privy Council. ones, contain an arbitration clause, by which the parties
agree to be bound by the decision of a private dispute
resolution mechanism: for many years, arbitration was the
5 The scheme of this book most common mode of determining construction disputes.
Today, however, the most common method is adjudication,
5.01 There are five main sections of the book: which provides a quick decision that is binding for only a
temporary period. By the 1996 Act, a right to adjudication
1 In the first section, the reader is offered the general prin- is now compulsory in almost all construction contracts.
ciples of the law. This introductory chapter is immediately Of growing popularity, too, is mediation, which refers to
followed by chapters setting out the principles of the two consensual meetings by parties with a neutral facilitator:
areas of English law of the greatest importance to architects, the success rate in achieving a settlement at mediations is
namely contract and tort. A third area of basic English law high. Separate chapters deal with each of these methods of
of relevance to architects, namely land law, is also covered dispute resolution.
in an early chapter. There are separate chapters providing 5 The final section of the book concerns the architect in
an introduction to Scots law and to Scots land law. practice. It covers the contracts which architects make with
2 The second section is concerned with the statutory and regula- their own clients for the provision of their professional
tory framework. Statutory authorities are described. There fol- services, and the collateral warranty contracts that archi-
low chapters on statutory regulations in the fields of planning tects enter with non-clients to provide them with a cause
and construction regulations. Regulations on public procure- of action against the architect if his professional work was
ment and party wall law are also dealt with in this section. faulty. There follows a chapter on the liability of architects
3 The next main section of the book deals with what is almost when faulty professional services are alleged. That is
certainly the legal subject of greatest day-to-day impor- followed by the chapter on professional indemnity insur-
tance to architects, namely building contracts. This section ance to cover architects against such risks. An architect’s
includes discussion of standard forms. Further chapters deal copyright in his own drawings is dealt with in the chapter
with sub-contracting, collateral warranties, and finally, the on the distinct area of the law of copyright. Finally, this
payment rules imposed by the Housing Grants Construction section deals with architects’ registration and professional
and Regeneration Act 1996. conduct.
2
The English law of contract
ANTHONY SPEAIGHT QC

1 Introduction before the objectionable event occurs, they will have agreed
what their legal obligations to one another shall be in certain,
1.01 The purpose of this chapter is to give an overview of the defined circumstances. So, for instance, if the claimant engages
law of contract: to show both how it relates to other areas of the defendant plumber to install a new sink, and it leaks; or the
the law, and to describe the general principles on which the claimant retains the defendant architect to design a house which
English law of contract operates. Although most of the examples falls down; or employs the defendant builder to build a house
and cases discussed are from areas with which architects will and it is not ready on time, the extent of the defendant’s liability
be familiar, the principles they illustrate are, for the most part, in a contract claim will depend on the terms and conditions of
general. This chapter covers, in a few pages, material which, if the contract between them. There may, in some circumstances,
fully discussed, would fill many long books. The treatment is be an identical or similar liability in tort as well, for the two are
necessarily selective and condensed. not mutually exclusive, but the conceptual distinction remains.

2 Scope of the law of contract 3 What is a contract?


2.01 Whilst the criminal law, in which a court action is brought 3.01 A contract is an agreement made between two or more
by the state, is concerned with punishments, the focus of the persons that is binding in law and is capable of being enforced
civil law is on putting things right. Civil cases are brought by by those persons in a court or other tribunal (such as an arbitral
one citizen against another with a view to obtaining a remedy. tribunal). The people who made the contract are described as
To that end, it determines the rights and liabilities which exist being party or ‘privy’ to it, and they are said to enjoy ‘privity
between parties in particular circumstances. The parties to a civil of contract’. This expression means that the parties are drawn
action are known as ‘claimant’ (until recently the claimant was into a close legal relationship with each other that is governed
called ‘plaintiff’) and ‘defendant’. The remedies available are by the agreement they have made. That legal relationship cre-
various: the court may award ‘damages’ as a means of compen- ates rights and obligations between the parties; but it binds only
sating the loss suffered by the claimant, or it may declare what them. Under the English common law, those who are not privy
the rights of the parties are, or, in certain circumstances, it will to the contract, who are often, slightly misleadingly, called ‘third
order a party to do or to refrain from doing something. parties’, cannot claim its benefits, nor be held liable to pay its
burdens. This doctrine of privity of contract has been modified
2.02 Two of the most important areas of the civil law are con- by the Contracts (Rights of Third Parties) Act 1999, which is
tract and tort. In certain factual contexts they can overlap, and in discussed later in this chapter. However, the Act’s provisions
recent years their overlap has caused the courts great problems, can be excluded if the parties so choose, and it is the almost
but they are conceptually distinct, and it is important to under- invariable practice for contracts in the construction industry and
stand the distinction. many other commercial fields so to exclude the Act. Therefore,
its practical effect is proving less than might have been expected.
2.03 Claimants sue defendants in tort when they consider them-
selves wronged by something the defendant has done or failed 3.02 Usually, the agreement will contain a promise or set of
to do. Often the claimant and the defendant will have been promises that each party has made to the other: this is known
strangers to each other before the objectionable act or omission as a bilateral contract, because each party promises to do some-
occurs. For example: the defendant carelessly runs the claim- thing. For example, X promises to build a house for Y, and Y
ant over; the defendant’s bonfire smoke ruins the claimant’s promises to pay X for doing so. Sometimes, only one party will
washing; the defendant tramples across the claimant’s field; the make a promise to do something if the other party actually does
defendant writes a scurrilous article about the claimant in the something stipulated by the former. For example, X promises to
local newspaper. All these wrongs are torts, indeed the label pay £100 if Y completes and returns a marketing questionnaire
‘tort’ is an archaic word for ‘wrong’. Each of the torts listed to X. Such a contract is known as an unilateral contract, because
above have particular labels, respectively negligence, nuisance, the promise is one-sided. Although X has promised to pay in the
trespass, and defamation. The law of torts is considered in stipulated circumstances, Y is under no obligation to complete
Chapter 3. and return the marketing questionnaire; but if he or she does,
the court or arbitral tribunal will recognise a binding agreement
2.04 On other occasions, the claimant and defendant are parties that X will pay £100. Although one often talks of a ‘written’ or
to a contract. In this case they will not be strangers to each other: ‘formal’ contract, it is not really the piece of paper which itself

9
10 The English law of contract

is the contract – the piece of paper merely records what the terms is thus the other half of the bargain or, as lawyers used to say,
of the contract are. the ‘quid pro quo’, meaning ‘something for something else’. In
a unilateral contract, the ‘something else’ is the performance
3.03 There are a few types of contract which must be made or by the party who wants to receive the promised benefit. In a
evidenced in writing: this is the case for contracts relating to the bilateral contract, often the promise of one party is exchanged
transfer of land and contracts of guarantee. For most other types for the promise of the other party. The court has defined con-
of contract, there is no requirement for a written document at sideration like this:
all, and an oral contract is just as binding in law. In practice, of
course, when there is a dispute, proving later what was orally An act or forbearance of one party, or the promise thereof, is
agreed at the outset is more difficult. That difficulty is avoided the price for which the promise of the other is bought, and
if there is documentary evidence of what was agreed. Where the promise thus given for value is enforceable.
there is a written contract, it will usually be hard for a party to (Dunlop v Selfridge [1951] AC 847 855)
persuade a court that there are additional orally agreed terms.
It is increasingly common for written contracts to contain an
‘entire contract’ clause, providing that nothing outside the writ-
Adequacy of consideration irrelevant
ten document is part of the binding arrangements. 5.02 Although consideration must be given for value, this sim-
ply means that there must be some intrinsic value, no matter
how small. It can be as small as a single peppercorn, which has
Contracts under seal become a favourite device of property professionals when wish-
3.04 Some contracts are made by deeds. This is sometimes called ing to create a binding lease or other disposition of land without
‘under seal’. In former times, deeds were made by melting seal- actual payment. The value of the consideration can be quite
ing wax onto the paper and then making an imprint on the wax, disproportionate to the other half of the bargain that it supports.
whilst still soft, by pressing an image of a coat of arms, often In Midland Bank Trust Company v Green [1980] Ch 590, a farm
by a signet ring. Later, the common way to create a deed was by worth £40,000 was sold by a husband to his wife for just £500:
affixing a small red piece of paper, about the size of a postage £500 was held to be good consideration. The court will not inter-
stamp. Today, none of that is required: any document can be fere with the level of consideration, because to do so would be to
made into a deed simply by the parties signing a declaration that adjudicate on the question of whether it was a good or bad deal
it is made as a deed. There are two principal legal consequences for one of the parties. Freedom of contract has been a guiding
of making a contract as a deed. One is that the normal require- principle of English law. The commercial aspects of a contract,
ment for consideration to pass both ways does not apply: the the bargain, are thought best left for the parties to decide.
seal provides the consideration for the contract (see below). The
other important consequence, and often the reason why parties in
the construction world choose this method of contracting, is that Consideration must move
the limitation period for making a claim pursuant to a contract from the promisee
under seal is 12 years, instead of the usual six (see paragraphs
14.01–14.02). 5.03 If A says to B, ‘I promise to pay you £100 if it rains on
Tuesday’, there is not a contract. B will have done nothing to
deserve or earn the windfall of £100. There is similarly no con-
Basic requirements for establishing tract if X says to Y, a local charity, ‘I promise to donate to you
whether there is a contract £1000 if Z builds a front wall in my garden’. Although in this
latter case, X will receive a benefit if Z should build the wall,
3.05 To determine whether there is a contract, the court or again, it is the case that the promisee, Y, will have done nothing
arbitral tribunal will look for three essential elements: first, the to earn the money. These examples illustrate the principle that
intention of the parties to create legal relations; second, whether consideration must move from the promisee.
there was in fact agreement between the parties; and third,
whether there was consideration for the agreement passing both 5.04 On the other hand, if the builder, Z, promises to the home-
ways. Each of these aspects requires further scrutiny. owner, X, to build a wall in X’s garden if X makes a donation
of £1000 to the local charity, and if X agrees, there is a contract.
This illustrates the principle that, although consideration must
4 Intention to create legal relations move from the promisee, it need not move to the promisor.
4.01 ‘If you save me my seat, I’ll buy you a drink.’ ‘OK.’ Such
a casual exchange has all the appearances of an agreement, but Consideration must not be past
if the thirsty seat-saver tried to claim the drink through a court,
he or she would probably be disappointed: the law will not 5.05 The general rule is that an act which has already been per-
enforce a promise if the parties did not intend their promises formed cannot provide consideration to support a contract sub-
to be legally binding. Similarly, one hears of people making sequently entered into. Suppose A gives B £1000 at Christmas,
a ‘gentlemen’s agreement’, where honour dictates the actions and at Easter, B agrees to build a wall for A ‘in consideration
between the parties along the lines of ‘I’ll see you right; if there of the £1000’. A cannot sue B if he does not build the wall, for
is anything you need, it will be done’. However, a moral obliga- there is no element of bargain, and no consideration supports the
tion is not enough. promise to build the wall. Also, a past agreement to do some-
thing cannot usually be used as consideration for a new promise.

5 Consideration 5.06 As so often, there can be grey situations. An example of


the outer limits of the application of the principle is provided
5.01 It is convenient to deal with consideration next. A simple by the unusual case, Williams & Roffey Bros. & Nicholls
one-way promise – ‘I’ll paint your ceiling’ – without more, is (Contractors) Ltd [1990] 1 All ER 512. There, a main contrac-
not a contract, because there is nothing to be done in return. A tor had contracted to complete the building of some housing
contract requires something to move both ways. That something units by a certain time but it became clear that he was unlikely
is called consideration. In the simplest case, one party will per- to do so because the sub-contractor was in financial difficulties.
form a service, such as painting a ceiling, in consideration of The main contractor, who would be liable for liquidated dam-
which the other will pay a price. With the exception of contracts ages under his contract with the employer if the project was
under seal, English contract law demands that there must be late, promised to pay the sub-contractors more money to ensure
consideration for the promise to be enforceable. Consideration completion on time. The Court of Appeal held that that promise
‘Agreement’ 11

was enforceable because assurance to the main contractor that they would pay £100 to anybody who used the smoke ball
the sub-contractor would continue and complete its work on three times a day as directed and still caught flu. The unfortu-
time was an additional benefit, and so amounted to consideration nate claimant caught flu despite using the smoke ball, and not
(even though the sub-contractor was already contractually bound unnaturally, felt she was entitled to the £100 offered. The Court
to do the work by that time). of Appeal held that the company’s advertisement constituted
an offer to contract, and by purchasing the smoke ball, the
claimant had accepted the offer, so that a contract was created.
6 ‘Agreement’ Accordingly, the claimant successfully extracted her £100 from
the company.
6.01 The existence of agreement between the parties to a con-
tract is, in practice, the most troublesome of the three essential 6.06 Not all pre-contractual negotiations are offers to contract.
ingredients. In deals of any complexity, there will be exploratory negotiation
before the shape of the final contract begins to emerge, and it
6.02 The inverted commas around ‘agreement’ in the heading will not be until a late stage that legal analysis will recognise
above are intentional. The law of contract does not peer into the an ‘offer’ in the law’s meaning of that concept. Such proposals
minds of contracting parties to see what they really intended to preceding an offer are known as invitations to treat. In the con-
contract to do; it contents itself with taking an objective view struction industry, an invitation to tender document will usually
and, on the basis of what the parties have said and done and be an invitation to treat, rather than an offer.
the surrounding context in which they did so, the courts decide
what the parties should be taken to have intended. The court 6.07 An offer must be sufficiently certain in its meaning and
asks whether, in the eyes of the law, they should be considered comprehensive in its extent that, if accepted, everything required
to have been in agreement. for a valid contract will be present. It must, therefore, deal with
every matter that the parties regard as essential for the particu-
6.03 To perform this somewhat artificial task, the courts use lar contract. However, in practice, the court’s requirements are
a standard analytical framework. Its ingredients can be stated limited. For example, courts will have no problem with an offer
simply: offer and acceptance in which the term as to price is a ‘fair and reasonable price’:
that is because, with the aid of expert evidence from quantity
surveyors, a court can make a determination of what a fair price
Offer is. On the other hand, ‘I offer to negotiate a satsifactory arrange-
6.04 An offer is a promise, made by the offeror, to be bound by ment with you’ is not capable of being an offer in law, the reason
a contract if the offeree accepts the terms of the offer. The offer being that even if the other party responded ‘I accept’, there is
matures into a contract when it is accepted by the other party. no yardstick by which a court could resolve a later dispute as to
A proposal does not have to contain the word ‘offer’ for the law whether a party had performed its obligation.
to recognise it as an offer in the legal sense. A jobbing builder’s
‘estimate’ is likely to be an offer: if accepted, the builder will
be obliged to complete for the price quoted. Acceptance
6.08 The acceptance of the offer can be by word – written or
6.05 The offer can be made to just one person (the usual case), oral – or by conduct. A court will be likely to find acceptance
or it can be made to a group of people, or even to the world by conduct if a party, who has received an offer, starts to behave
at large. The case of Carlill v Carbolic Smoke Ball Company as if a contract is in place, for instance, if a building contractor
[1892] 2 QB 484, [1893] 1 QB 256 is famous with all first turns up on site and commences work. Acceptance must be com-
year law students as the classic instance of an offer to all the municated or made known to the offeror. Silence is not sufficient
world. The defendant company manufactured a device called to accept an offer, because neither assent nor dissent has been
a carbolic smoke ball, which was intended to prevent its users communicated by the offeree. A court is always concerned with
from catching flu. They advertised it with the promise that whether the outwardly observable communications or actions
objectively manifest acceptance of an offer.

6.09 An acceptance must be unequivocal, and it must be a


complete acceptance of every term of the offer. ‘I accept your
terms, but only if I can have 42 days to pay instead of 28’ will
not be an acceptance, for it purports to vary the terms of the
offer. Instead, the law regards it is a counter-offer. Like the
original offer, a counter-offer may be accepted, be rejected, or
be withdrawn. A counter-offer is always deemed to be a rejec-
tion of the original offer: in consequence, the original offer can
no longer be accepted. In the old case of Hyde v Wrench [1840]
3 Beav 334, the defendant Wrench offered to sell some land to
the plaintiff for £1000. On 8 June, Hyde said he would pay £950.
On 27 June, Wrench refused to sell for £950, and on 29 June,
Hyde said he would pay £1000 after all. Wrench refused to sell.
It was held that there was no contract. Hyde’s counter-offer on
8 June had destroyed the initial offer of £1000, and by 29 June,
it was too late for Hyde to change his mind.

6.10 Sometimes an offer will specify a particular method of


acceptance. For instance, A will ask B to signal his accept-
ance by signing a copy letter and returning it within 21 days.
Ordinarily, B can only accept by complying with that method
of acceptance. However, sometimes the court will decide that
an equally effective method of acceptance will suffice if it is
clear that both parties understood that there was acceptance and
assumed there was a contract.
12 The English law of contract

Revocation of offer and the postal rules Much as courts and arbitral tribunals wish to acknowledge com-
mercial realities, they cannot escape from the need for certainty
6.11 An offer can be withdrawn or revoked up until such time of terms if a contract is to have any meaning. The crucial, central
as it is accepted. An acceptance is of course final – otherwise, feature of contract, namely that objectively viewed meeting of
people would constantly be pulling out of contracts because parties’ minds, either exists or it does not exist. The transition
they had had afterthoughts. Since an offer can be both revoked from a stage when it does not exist to the stage when it does
by its maker and destroyed by a counter-offer, yet matures into exist surely has to happen at a moment in time – hence, the
a contract when it is accepted, it can be crucial to decide when need for a predictable tool to fix that moment at which partiues
these events occur. become bound.
6.12 An acceptance is generally effective when it is received by
the offeror, but if the acceptance is made by posting a letter, then Letters of intent
the acceptance takes effect when the letter is posted. Revocation 6.18 It has become increasingly common for parties to send let-
by post takes effect when the letter is received by the offeree. ters which are referred to as, and sometimes expressly headed as,
The working of these rules is neatly exemplified by the case of ‘letters of intent’. These letters are often used where an employer
Byrne v Van Tienhoven [1880] 5 CPD 344. There, the defend- wishes to get works on site started before the parties have final-
ants made an offer to the claimants by letter on 1 October. The ised negotiating a contract. The letter may say something such
letter was received on 11 October and immediately accepted by as ‘We intend to place a contract with you for these works and
telegram. Meanwhile, on 8 October, the defendants had thought request that you start on site’. A party may hope, thereby, to
better of their offer and sent a letter revoking it. This second avoid a binding contract coming into effect. But such a hope
letter did not reach the claimants until 20 October. There was a is likely to be disappointed. In Arcadis v AMEC [2019] BLR
binding contract because the acceptance took effect before the 27, it was stated that, at any rate, if work on site had begun,
revocation. The result would have been the same even if the the court was strongly likely to find the existence of a contract.
acceptance had been by letter and the letter had arrived with the However, such contract will not necessarily include all the terms
defendants after 20 October. that a party might wish for. In the Arcadis case, a designer had
requested a cap on its liability, to which the other party was not
Battle of the forms opposed, but since the design work was carried out on a letter
of intent without the cap being clearly agreed, the contractor
6.13 These mostly Victorian rules about offer and acceptance had to go all the way to the Court of Appeal to avoid unlimited
may seem rather irrelevant to modern commercial transactions, liability for defective work without any cap at all. The lesson
but there is one context in which they regularly appear: this is for parties is that it is much better to make a proper agreement
the so-called ‘battle of the forms’, which takes place when two before work starts.
contracting parties both deal on their own standard terms of
business, typically appearing on the reverse of their estimates,
orders, invoices, and other business stationery. 7 Terms of a contract
6.14 The typical scenario is as follows. A supplier sends an
estimate on its usual business form, with its standard terms and
Express terms
conditions on the reverse, and a note saying that all business is 7.01 The most obvious terms of a contract are those which the
done on its standard terms. The purchaser sends back an order parties expressly agreed. In cases where there is an oral contract,
purporting to accept the estimate, but on the back of its accept- there may be conflicting evidence as to what actually was said
ance are its standard terms, which are doubtless more favour- and agreed , but with the written contracts, with which architects
able to it than the supplier’s. The supplier sends the goods, and will most often deal, identifying the express terms is usually
the purchaser pays for them. Is there a contract, and if there is, less problematic. Save in exceptional circumstances, parties
whose standard terms is it on? will be bound by the document that they have signed, even if
they have not bothered to read it, or to appreciate its contents.
6.15 The purchaser’s ‘acceptance’ and order is not a true accept- One issue may be determining whether an ancillary document
ance, because it does not accept all the terms of the vendor’s is a contract document: a well-drafted agreement will list what
offer: rather, it purports to substitute the purchaser’s standard other documents are part of the contract. Where there are sev-
terms. So, the purchaser’s order is, in legal terms, a counter- eral documents which form the contract, they are sometimes
offer, and this is accepted – in this example – by the vendor’s not consistent: another feature of a well-drafted agreement is to
conduct in sending the goods. So, the purchaser’s terms govern list the priority of the various contract documents in the event
the contract. of inconsistency. It should be noted at this stage that things
said or written prior to making a contract may affect the par-
6.16 If there are long, drawn-out negotiations as to quantities, ties’ legal obligations to one another, even though they are not
prices, and so on, all on business stationery containing standard terms of the contract. This matter is discussed in the section on
terms, at the end of which a delivery or performance of works misrepresentation.
occurs, then the contract is likely to be deemed to have been
made on the terms of the last communication. So, the battle of 7.02 The Supreme Court has discussed the approach which is to
the forms can be said to be won by whoever fires last. The result be taken to interpreting the text of a contract on several recent
can sometimes appear to be rather a matter of luck. occasions. It was distilled by Lord Neuberger in Arnold v Britton
[2015] UKSC 36 thus:
6.17 The courts have tried, on occasion, to substitute a rather
less mechanical analysis of offer and acceptance, looking at the meaning has to be assessed in the light of (i) the natural and
negotiations as a whole. In many construction and commercial ordinary meaning of the clause, (ii) any other relevant provi-
cases in which protracted and complex negotiations result in a sions of the [agreement], (iii) the overall purpose of the clause
situation considered to be binding by the parties, pin-pointing and the [agreement], (iv) the facts and circumstances known
a defining moment when an offer and an acceptance was made or assumed by the parties at the time that the document was
ignores the modern commercial reality. In Butler Machine Tool executed, and (v) commercial common sense, but (vi) disre-
Co Ltd v Ex-Cell-O Corporation (England) Ltd [1979] 1 WLR garding subjective evidence of any party's intentions.
401 at 405, Lord Denning said, ‘our traditional analysis of offer,
counter-offer, rejection, acceptance and so forth is out of date’, In practice, the tension is very often between what is asserted
but if that was ever so, it quickly slipped back into fashion. to be in line with commercial common sense and the literal
Terms of a contract 13

meaning of the words used. Where this is so, Lord Neuberger unlikely today to be sufficient to justify the implication of a term
stressed that commercial common sense should not ‘be invoked which does not meet the tests set out above.
to undervalue the importance of the language’, and that a court
will be very slow to reject the natural meaning of a term because
it appeared to be an imprudent one.
Terms implied by statute
7.09 For architects, there are two important statutes which may
Implied terms automatically incorporate terms into their contracts. By the Sale
of Goods Act 1979, there are standard terms as to quality and
7.03 Implied terms are likely to catch out the unwary. There are fitness for purpose implied into every commercial contract for
three types of implied term: those implied by the court, those the sale of goods, unless the contract specifically provides differ-
implied by custom, and those implied by statute. ently. The principally relevant sections are set out in Extract 2.1.
This potentially applies to contracts for the supply of materials
Terms implied by the court to a building site. For consumer contacts, the relevant statute is
the Consumer Rights Act 2015, which by s.9 and s.10, contains
7.04 With unfortunate frequency, contracting parties discover similar implied terms.
too late that their contract has failed to provide for the events
which have happened. One party will wish that the contract had
included a term imposing liability on the other in the circum-
stances that have turned out, and will try to persuade the court
Extract 2.1 Sale of Goods Act 1979, as amended
that such a term in its favour should be implied into the contract,
by Sale and Supply of Goods Act 1994
saying, in effect, that the court ought to read between the lines
of the contract and find the term there. 14.(1) Except as provided by this section and section 15 below and sub-
ject to any other enactment, there is no implied term about the quality or
7.05 There are some particular terms in particular types of fitness for any particular purpose of goods supplied under a contract of
contract that the courts will, as a matter of course, imply into sale.
contracts of a particular kind. For instance, in a construction (2) Where the seller sells goods in the course of a business, there is an
contract, the court will usually imply a term that the employer implied term that the goods supplied under the contract are of satisfactory
will cooperate with the contractor. There is currently an ongo- quality.
ing debate amongst lawyers and judges whether there is an (2A)For the purposes of this Act, goods are of satisfactory quality if they
implied term that a contract will be performed with good faith: meet the standard that a reasonable person would regard as satisfactory,
the debate not only concerns whether, and if so, when, such taking account of any description of the goods, the price (if relevant) and
a term should be implied, but also, if there is such a term, all the other relevant circumstances.
whether it makes any difference. More certain is the proposi- (2B) For the purposes of this Act, the quality of goods includes their state
tion that, if a contract creates an exercise of discretion for a and condition and the following (among others) are in appropriate cases
party, the discretion must be exercised in good faith, rationally, aspects of the quality of goods –
and consistently with the contractual purpose, and must not be (a) fitness for all the purposes for which goods of the kind in question
exercised arbitrarily or capriciously ; this was authoritatively are commonly supplied,
confirmed by the Supreme Court in Braganza v BP Shipping (b) appearance and finish,
[2015] UKSC 17. (c) freedom from minor defects,
(d) safety, and
7.06 More frequently, there will be no authority on the particular (e) durability.
type of term which it is sought to imply. English law imposes (2C) The term implied by subsection (2) above does not extend to any mat-
strict constraints on the exercise of what Sir Thomas Bingham ter making the quality of goods unsatisfactory –
MR called the ‘intrusive’ and ‘extraordinary’ power to imply (a) which is specifically drawn to the buyer's attention before the con-
terms into a commercial contract (Philips Electronique v B Sky tract is made,
B [1995] EMLR 472). In Marks & Spencer plc v BNP Parisbas (b) where the buyer examines the goods before the contract is made,
Securities [2016] AC 742, the Supreme Court reiterated the which that examination ought to reveal, or
classic criteria: (c) in the case of a contract for sale by sample, which would have been
apparent on a reasonable examination of the sample.
for a term to be implied … (2) it must be necessary to give (3) Where the seller sells goods in the course of a business and the buyer,
business efficacy to the contract, so that no term will be expressly or by implication, makes known –
implied if the contract is effective without it; (3) it must be (a) to the seller, or
so obvious it goes without saying; (4) it must be capable of (b) where the purchase price or part of it is payable by instalments and
clear expression (5) it must not contradict any express term the goods were previously sold by a credit-broker to the seller, to that
of the contract. credit-broker,
any particular purpose for which the goods are being bought, there is an
7.07 Sometimes, parties will argue for an implied term to fill in implied term that the goods supplied under the contract are reasonably fit
the gaps in an otherwise incomplete agreement, or in situations for that purpose, whether or not that is a purpose for which such goods are
where the parties have opposing arguments as to what was, in commonly supplied, except where the circumstances show that the buyer
fact, agreed. In those situations, the court is likely to say that does not rely, or that it is unreasonable for him to rely, on the skill or judg-
there was no contract, and it is not the court’s role to make the ment of the seller or credit-broker.
contract for the parties.

Terms implied by custom


7.08 The custom of a particular type of business is relevant in 7.10 The Supply of Goods and Services Act 1982 contains
construing the express terms of a contract. In certain fields, trade implied terms applicable to commercial contracts for the supply
custom has, on occasion, been sufficiently well-established for of services. That covers, in effect, all building contracts, and all
the courts to imply into a contract a term in accordance with contracts between an architect and client. The most important
such custom: this has occurred, for instance, in marine insurance. of these terms is that the supplier, whether building contractor
But whilst the Technology and Construction Court will bring or architect, will provide the service with reasonable care and
the considerable specialist experience of its judges into play in skill. The main relevant sections are set out in Extract 2.2. This
interpreting construction contracts, the custom of the industry is potentially applies to the architect’s own contract with the client.
14 The English law of contract

Again, in the case of consumer contracts, there are similar terms In respect of other losses, which, in most cases, means economic
implied by the Consumer Rights Act 2015. losses, section 2(2) subjects the validity of a term or notice
excluding or restricting liability resulting from negligence to the
test of reasonableness.

Extract 2.2 Supply of Goods and Services


8.03 This test of reasonableness is that the term should be fair
Act 1982 (as amended)
and reasonable having regard to the circumstances which were
known, or ought to be known, to the parties when the contract
12. – The contracts concerned. was made. In the Yakeley Associates case mentioned above, the
(1) In this Act a (‘relevant contract for the supply of a service’ ) means, Court of Appeal upheld a decision that the cap of £250,000
subject to subsection (2) below, a contract under which a person (‘the satisfied the test of reasonableness: at the time the architect was
supplier’) agrees to carry out a service, other than a contract to which engaged, this figure represented the estimated cost of building
Chapter 4 of Part 1 of the Consumer Rights Act 2015 applies. the house which was the subject of the professional services. On
… the other hand, in a computer case, Pegler v Wang [2000] BLR
13. – Implied term about care and skill. 218, the Technology and Construction Court held that a term,
In a relevant contract for the supply of a service where the supplier is acting which the customer had little choice but to accept, was unreason-
in the course of a business, there is an implied term that the supplier will able, despite evidence that almost all computer suppliers inserted
carry out the service with reasonable care and skill. a similar exclusion term.
14. – Implied term about time for performance.
(1) Where, under a relevant contract for the supply of a service by a sup- 8.04 Section 3 of the Act is one of the most important parts of
plier acting in the course of a business, the time for the service to be carried the Act, which applies to whenever a contract is made on one
out is not fixed by the contract, left to be fixed in a manner agreed by the party’s standard written terms of business. Although UCTA has
contract or determined by the course of dealing between the parties, there is been on the statute book for over 40 years, it remains unclear
an implied term that the supplier will carry out the service within a reason- whether general standard forms of contract, such as JCT, NEC,
able time. or ICE forms, will be treated as a party’s standard written
(2) What is a reasonable time is a question of fact. terms. In British Fermentation Products Ltd v Compair Reavell
15. – Implied term about consideration. Ltd, machinery was supplied under a contract on a standard
(1) Where, under a relevant contract for the supply of a service, the con- form published by the Institution of Mechanical Engineers
sideration for the service is not determined by the contract, left to be deter- which excluded liability for defects in the machine if the sup-
mined in a manner agreed by the contract or determined by the course of plier’s efforts at repair were unsucessful. The Technology and
dealing between the parties, there is an implied term that the party contract- Construction Court held that the contract should not be treated
ing with the supplier will pay a reasonable charge. as on the supplier’s standard terms, since there was no evidence
(2) What is a reasonable charge is a question of fact. that the supplier invariably or usually used that form, leav-
16. – Exclusion of implied terms, etc. ing open the question of what would be the decision is there
(1) Where a right, duty or liability would arise under a relevant contract was such evidence. In African Export-Import Bank v Shebah
for the supply of a service by virtue of this Part of this Act, it may (subject Exploration [2016] EWHC 311, the Commercial Court inclined
to subsection (2) below and the 1977 Act) be negatived or varied by express against regarding what it called a ‘neutral’ trade body standard
agreement, or by the course of dealing between the parties, or by such usage form as one party’s standard written terms, but again side-
as binds both parties to the contract. stepped having to make a direct decision by holding that there
… was no evidence that the bank in question regularly used the
particular standard form.

8.05 Where it applies, section 3 provides that, unless a party can


prove that a contractual term was reasonable within the meaning
8 Exclusion clauses and the of section 11 (see above), a party in breach of contract cannot
prevention of unfair terms exclude or restrict its liability for that breach of contract, nor can
a party claim to be entitled to render incomplete, significantly
8.01 A contracting party, particularly a contracting party with different, or defective performance of its obligations or, even
a dominant position relative to the other, may try to include in worse, no performance at all. Section 13 provides that a party is
the contract terms which are extremely advantageous to him not permitted to make its liability or enforcement of its liability
in the event that he is in breach of some principal obligation subject to onerous conditions or to restrict rights and remedies
under the contract. The commonest way to do this is to limit, of the other party.
or completely exclude, liability in certain circumstances. For
example, in Moores v Yakeley Associates Ltd [2000] 3WLUK
644, an architect entered into a contract for his services on
Consumer contracts: the
SFA/92 with £250,000 inserted as a maximum cap on liability. Consumer Rights Act 2015
Some exclusion and limitation clauses can be so unfair to weaker 8.06 In 1993, an EU Directive introduced a requirement on
contracting parties that the common law strove to find ways of member states to enact a set of restrictions on unfair terms in
confining their impact; and more recently, statute has introduced consumer contracts. These were initially given effect in domestic
significant controls. The law in this area has now developed to law by two successive instruments called the Unfair Terms in
the point where one can consider commercial contracts quite Consumer Contracts Regulations. As from October 2015, these
separately from consumer contracts. rules have been assimilated into a slightly wider enactment, the
Consumer Rights Act 2015. This Act has valuably tidied the law
Commercial contracts: the Unfair by bringing provisions affecting consumer contracts, which were
originally in UCTA, into the same place as the law implementing
Contracts Terms Act 1977 EU consumer law.
8.02 The Unfair Contracts Terms Act 1977 (‘UCTA’) was the
first substantial statutory control on exclusion and limitation 8.07 A consumer is a natural person acting outside his or her
clauses. Originally it applied to all types of contracts , but since trade or profession: a limited company can never be a consumer
October 2015, it no longer has application to consumer con- within this Act. The other party is called the trader. The Act
tracts. It prohibits outright the exclusion of liability for causing applies to contracts to supply goods, contracts to supply services,
death or personal injury as a result of negligence (section 2(1)). and contracts to supply digital content. Every building contract
Misrepresentation 15

and every architect’s contract will be within the Act’s scope, if are made, and the place for promises is therefore in the contract
the client is a consumer. itself. An opinion which is honestly held and honestly expressed
will not constitute an actionable misrepresentation. It does not
8.08 In all such contracts, a term is not binding to the extent that make sense to talk of an opinion being false or untrue, so the
it would exclude the trader’s liability arising under a number of expression of an opinion cannot be a misrepresentation. But a
substantive provisions which it sets out. These include those in statement, ‘I believe such and such …’, can be a representation
respect of breach of the terms as to description, quality, or fit- of the fact that the speaker holds the opinion , so, there can a
ness for purpose, etc., of goods inserted into contracts to supply misrepresentation if the representor does not actually hold the
goods, or under rules on delivery of goods or the passing of risk. belief. Bowen LJ explained:
Also covered are clauses which impose penalties on consumers,
which allow the trader to change the service or goods that it The state of a man’s mind is as much a fact as the state of
supplies, to interpret or change the terms of the contract at its his digestion. It is true that it is very difficult to prove what
discretion, or to terminate the contract early. The wide potential the state of a man’s mind at a particular time is, but if it can
impact of modern consumer law was demonstrated by Zealander be ascertained it is as much a fact as anything else. A mis-
v Laing Homes Ltd. (2000) 2 TCLR 724. This concerned the representation as to the state of a man’s mind is, therefore, a
standard NHBC Buildmark Agreement, which some people, statement of fact.
at least, might have thought a consumer-friendly document. (Edgington v Fitzmaurice [1885] 29 ChD 459 at 483.)
Despite such claims, the court held that the arbitration created a
significant imbalance for the consumer. 10.04 A somewhat more surprising line of authority holds that
‘mere puff’ or sales-speak does not constitute a representation.
Hence, describing land as ‘uncommonly rich water meadow’
9 Standard forms of contracts was held not to constitute a representation in Scott v Hanson
[1829] 1 Russ & M 128. But the courts today are rather less
9.01 Many of the contracts with which architects are involved indulgent to exaggerated sales talk and if it can be established
are standard form contracts. A later chapter deals at length that effusive description of a vendor’s product is actually
with one such contract, the JCT Standard Form of Building untrue, it seems that the courts would today be more likely to
Contract. The use of such contracts has a number of advan- hold that to be a misrepresentation than would their nineteenth-
tages. A great deal of experience has gone into drafting these century predecessors.
contracts so that many pitfalls of fuzzy or uncertain wording
can be avoided. And where the words used are open to different 10.05 Silence generally does not constitute a representation. A
interpretations, it may well be that case law has definitively vendor is generally under no obligation to draw to the attention
settled their meaning. In effect, the user of a standard term of the purchaser the defects in what is being sold, and even tacit
contract enjoys the benefit of other peoples’ earlier litigation in acquiescence in the purchaser’s self-deception will not usually
sorting out exactly what obligations the standard terms impose. create any liability. However, if the representor makes statements
The effects of well-litigated and well-established terms and about a certain matter, he or she must not leave out other aspects
conditions also have an impact on third parties. Insurers in of the story in such a way that what he or she says is mislead-
particular will know where they stand in relation to a contract ing as a whole: so although a total non-disclosure may not be a
on familiar terms, and therefore, the extra premiums inevitable misrepresentation, partial non-disclosure may be.
on uncertain risks can be avoided.

9.02 One potential problem with standard form contracts can Reliance
be minimised if it is appreciated that, just as tinkering with
10.06 To create any liability, the representee must show that the
a well-tuned engine can have catastrophic consequences, so
misrepresentation induced him or her to enter into the contract
‘home-made’ modifications of standard form contracts can have
– the misrepresentation must have been material. Therefore, if
far-reaching effects. Many of the provisions and definitions used
the misrepresentee knew that the representation was false, or if
in standard form contracts interlink, and modifying one clause
he or she was not aware of the representation at all, or if he or
may have unforeseen and far-reaching ramifications. If parties
she knew of it but it did not affect their judgement, then he or
to a standard form contract want to modify it because it does
she will have no grounds for relief. But the misrepresentation
not seem to achieve exactly the cross-obligations they want to
need not be the only, nor even indeed the principal reason why
undertake, it is advisable to take specialist advice.
the misrepresentee entered into the contract.

10 Misrepresentation The three types of misrepresentation


10.01 Pre-contractual negotiations often cover many subjects 10.07 Three types of misrepresentation should be identified. One
which are not dealt with by the terms (express or implied) of occurs if the representor making the misrepresentation made it
the eventual contract. In some circumstances, things said or done knowing it was untrue, or recklessly, not caring whether it was
before the contract is made can lead to liability. true or false: this is termed a fraudulent misrepresentation.
The second occurs if the representor made the false state-
ment believing that it was true, but had taken insufficient care to
Representations and misrepresentations ensure that it was true: this is a negligent misstatement.
10.02 A representation is a statement of existing fact made by The third occurs if the misrepresentor had taken reasonable
one party to the eventual contract (the representor) to the other care to ensure that it was true, and did believe that it was true:
(the representee), which induces the representee to enter into the this is an innocent misrepresentation.
contract. A misrepresentation is a representation which is false. The available remedies vary depending on the type of
Two elements of the definition need elaboration. misrepresentation.

Statement of existing fact Remedies for misrepresentation


10.03 The easiest way to grasp what is meant by a statement of 10.08 This is a difficult area of the law, and the finer details
existing fact is to see what is not included in the expression. A of the effects of the Misrepresentation Act 1967 are still not
promise to do something in the future is not a representation of entirely clear. The summary which follows is no more than
fact – such a statement is essentially the stuff of which contracts an outline.
16 The English law of contract

10.09 Traditionally, the basic remedy for misrepresentation was arise leading them to wish to make modifications to the original
rescission, which is the complete termination and undoing of plan. Accordingly, any sensibly drafted building contract, other
the contract. This obliges the misrepresentor to restore the rep- than the very simplest, will include provision for the details
resentee to the position he or she would have been in had the of the work to be modified during the course of the project.
contract never been made. Amongst such arrangements will be provisions for appropriate
adjustment of the price, by reference to bills of quantities or the
10.10 Rescission is not available if the misrepresentee has, with like. Variations to the works under such provisions may involve
knowledge of the misrepresentation, affirmed the contract. A either adding or omitting work. There is a limit to how far such
long lapse of time before the misrepresentee opts to rescind is varied work provisions can be used. An employer cannot omit
often taken as affirmation. Rescission is not available if a third work from the specification of the contractor, in order to award
party has, since the contract was made, acquired for value an that work to a different contractor. Nor may additions or omis-
interest in the subject matter of the contract. Nor is it available, sions be used to make so profound a change to the work to be
almost by definition, if it is impossible to restore the parties to performed as wholly to alter the character of the contract.
the status quo before the contract was made.
11.02 Provisions for varying the works must be distinguished
10.11 The court now has a general power to grant damages in from a variation of the actual contract. The former is an opera-
lieu of rescission (Misrepresentation Act 1967, section 2(2)), tion of the original contract, whilst the latter is the making of a
and may award damages to the victim of a negligent or innocent fundamental change to the original contract. Consistent with the
representation even where the misrepresentee would rather have guiding principle of freedom of contract, parties who have made
the contract rescinded instead. a contract may choose to change it; or to discharge it altogether.
Such a variation of the original contract may be made at any
10.12 The victim of a fraudulent misrepresentation may sue for time, but it is of the essence that the parties make an agreement
damages as well as claim rescission. The measure of damages to do so. In a sense, that is self-evident, but in practice, making a
will be to put the victim in the position he or she would be in if variation of a contract is not always straigtforward. If there were
the mis-statement had never been made. more than two parties to the original contract, all the original
contracting parties must agree to the new version of the contract.
10.13 The victim of a negligent misrepresentation may also
recover damages (section 1) as well as rescission. In the case 11.03 An issue which has troubled courts in recent years has
of an innocent misrepresentation, there is no right to damages, been the efficacy of clauses providing that any variation to the
but, as already explained, the court may, in its discretion, award original contract must be made in a particular manner – usu-
damages in lieu of rescission. ally the requirement is that it be in writing. Such ‘No Oral
Modification’ clauses have become more common recently.
10.14 The complications of the law on misrepresentation are There is no problem if the parties subsequently follow the agreed
compounded by the availability of damages for the tort of neg- procedure for variations, but what has happened on occasions is
ligent misstatement. In general, if a person who has a special that one party claims that the other has orally agreed to a varia-
expertise in an area negligently makes an incorrect statement of tion of contract, whilst the other disputes such conversation. One
fact to a person relying upon the maker, there is an action for view, which had support from judges in the Court of Appeal,
damages. The law of negligence is discussed in the next chapter. was that, since there is freedom of contract, and since contracts
There will be many instances in which an actionable misrepre- can be made orally, the parties can always validly make an oral
sentation is also an actionable mis-statement. variation of their contract, no matter what they may have agreed
at the outset in a written, formal contract. The issue has recently
been resolved by the Supreme Court. In Rock Advertsing v MWB
Entire contract clauses Business Exchange [2018] UKSC 24, the Court held that, whilst
in theory, parties are free at any time to agree anything, parties
10.16 The frequency with which actions for misrepresentation can make an effective agreement (in their original contract) that
may be brought has been reduced in recent years by the growing any modification will be effective only if made in such manner
popularity of a device in contract drafting known as an entire as they prescribe. Broadly speaking, the practical consequence
contract clause. Such clauses, in their simplest form, state that is that No Oral Modification clauses are effective. However, it
the contract contains the entire terms which the parties have remains possible that if, in addition to making an oral agreement
agreed; if that is as far as they go, they may do no more than to modify an original contract, a party unequivocally assures
clarify the extent of the four corners of the contract documen- the other that it will treat the oral modification as valid, that
tation. More often, however, the wording of the clauses goes party may be held estopped from subsequently asserting to the
on to say that that no pre-contract representations have been contrary.
relied upon in the decision by the parties to make the contract.
If drafted in that form, the courts will hold that parties are
excluded from later asserting reliance on a representation; and Novation
since reliance is essential to any claim for misrepresentation, the 11.04 A variation of a contract may go to the extent of removing
result is the exclusion of misrepresentation claims. Such clauses one of the original parties and substituting a fresh party. Such
have the benefit of limiting the scope for later disputes, but they variations are called novations.
can produce deeply unfair results for parties who have had less In recent years, novations have become common in the con-
advice in the pre-contract drafting stage, and who fail to secure struction industry. This has been a reflection of the attraction
inclusion in a contract as contractual terms of all the assurances to employers of having a single person to sue in the event of a
which have been given during negotiations. defect. Just as, for decades, employers have liked the arrange-
ment of a single main contractor, who is contractually responsi-
ble to them for the defective work of every specialist contractor
11 Variation, novation, through the up-and-down arrangement of sub-contracting by a
and assignment main contractor, so they have found novations to be a conveni-
ent way of sucking all the professionals under the main con-
Variation of contracts and varied work tractor as well. It has always been straightforward for a main
contractor under a design and build contract to be made respon-
11.01 It is in the nature of construction projects that the parties sible for the design work of professionals which it engages ,
cannot easily specify every detail at the outset. Even if they but the employer often itself wishes to have a strong role in the
attempt to do so, there is every likelihood that circumstances will design, and so itself deals with architects and engineers prior
Performance and breach 17

to letting the design and build contract. Moreover, purely as a who has provided a service in the event of it transpiring that the
matter of the sequence of activity, a design and build contract service was performed defectively. Such a transfer of the benefit
necessitates the drafting of Employer’s Requirements before a of a contract is usually referred to as an assignment.
contract can be executed, and that drafting is likely to involve
input from design professionals. Accordingly, employers today 11.08 Assignment is different to novation in that it does not
sometimes require their design professionals to agree, as part of require the agreement of both the parties to the original contract.
their original contracts of engagement that, if and when a design In the common case of the trader assigning a debt, there is no
and build main contract is executed with a contractor, the need to secure the agreement of the slow-paying customer ; that
professionals will execute a novation so that their contracts of customer simply receives a letter from the finance company tell-
engagement are transformed from contracts with the employer ing him or her that the debt must now be paid to it. The same
into contracts with the contractor. Typically, such novation can happen with the right to sue an architect. The architect may,
documents are drafted such that the contractor is to be liable for instance, have designed an extension for a home-owner. A
to the employer not only for future work by the professional, couple of years later, that owner may wish to sell. The pro-
but is also responsible for any past defective work. It is also spective purchaser may want as much protection as possible in
a feature of such arrangements that the professionals cease to respect of the remedies available in the event of defects appear-
be liable to the employer for defective work by them during ing in the property, and so may seek, and receive, a document
the period when they were working directly for the employer, from the seller assigning the right to sue the architect. That can
and very possibly before the contractor had been selected, and be perfectly legally effective without any agreement from the
become, instead, liable to the contractor for defective work in architect.
that period.
11.09 Assignments are subject to a number of limitations. Firstly,
11.05 Novation extinguishes the contractual relationship it is only the benefit of a contract which can be assigned; the
between the original contracting parties: so it is axiomatic burden cannot be assigned. So, the architectual firm engaged
that both the original contracting parties must be parties to to provide services in relation to the building of an extension
the novation agreement. Equally clearly, the incoming party cannot, at its own whim, transfer the right to provide those
can become liable only if it is a party to the novation. So, a services to another firm. The client will doubtless have selected
novation always requires all three parties to make the new the original firm for its good reputation ; it would cause outrage
agreement. Since the novation is itself a contract, considera- if one architect could transfer a job to any other without any
tion is required to make it contractually effective. This may consent from a client.
be deemed to be supplied by the benefit conferred by the new A second limitation is that the person to whom the benefit
party’s agreement to take on burdens and the outgoing party of a contract is assigned must have have genuine interest in
agreeing to release the remaining party from any outstanding receiving it. If the assignee of the benefit of a contract with
liabilities , but the uncertainties whether everybody involved an architect is buying a property designed by that architect,
will, in fututre, accept that there has been the requisite consid- then the assignee will be regarded as having a valid interest.
eration, may be removed by making the novation by a deed. However, English law has traditionally frowned on trafficking
Accordingly, in a well-ordered project, one typically finds that in litigation. If, hypothetically, some commercial enterprise
all three parties execute a deed of novation. Frequently, a draft were to tour a newly-built housing estate, offering owners a
of this deed (with the name of the contractor for the time being small sum to buy up the benefit of their contracts of purchase
left blank) is appended to the original contracts of engagement so that if any of the houses should, in due course, develop
with the professionals, so that there can be no quibbling about defects the commercial enterprise could claim, and retain, dam-
the terms of the novation that the professionals will be required ages representing the cost of repair, a court might well hold the
to execute. assignments invalid. That said, in the modern era, assignments
of causes of action have come to be regarded less unfavourably
11.06 The well-ordered procedures described above are not a by courts: it has been recognised that assignments can some-
feature of all novations. Novations may be enountered in cir- times benefit consumers.
cumstances other than the appointment of a design and build
contractor. One such common situation is that of a company 11.10 Assignments can be validly effected with few formalities.
reorganisation. An architect may be engaged by one company, They should be made in writing, but a simple letter signed just
and start work with it. Then the project may be taken over by by the assignor suffices. A notice must be given to the party who
another company. If the architect starts to receive instructions owes the benefit of the original contract, that is, the slow-paying
from the new company, to invoice the new company, and to be customer or the architect in the above examples, before a claim
paid by the new company, a court may well conclude that there can be made.
has been a novation from the first company to the second, so
that, if there is defective work, the architect can be sued by the
second company. 12 Performance and breach
12.01 All the topics considered so far have been concerned
Assignment with matters up to and including the creation of a contract
– matters generally of greater interest to lawyers than to busi-
11.07 Another way of moving contractual liabilities from one ness people or to architects. But both lawyers and architects
person to another is by an assignment. The theory of English have a close interest in whether or not a party fulfils its
law is that the benefit of a contract is an item of property. The obligations under a contract and, if it does not, what can be
most obvious example is the right to be paid a sum of money. done about it.
A trading company which wishes to raise money quickly can
transfer to a financial institution the right to receive a debt from
a slow-paying customer in return for the immediate payment to The right to sue on partial
the trader of a percentage of the debt. Such ‘factoring’ arrange-
ments are a common feature of commercial life, in which the
performance of a complete contract
percentage of the face value of the debt which the trader receives 12.02 Many contracts take the general form of A paying B to
usually reflects a commercial assessment of the likelihood of the perform some work or to provide some service. It is unusual
debtor eventually paying. In the same way, the law recognises for the party contacted to perform the work or provide the
the possibility of the transfer of other types of benefit under a service to do nothing at all; the usual case will be that much of
contract, including the benefit of being able to sue a professional the contracted work is performed, but some part of it remains
18 The English law of contract

incomplete, undone, or improperly performed. This situation categorised as ‘warranties’. The Sale of Goods Act adopts this
needs to be considered from both sides. We begin with examin- language. Such rigid categorisation, however, has rather fallen
ing whether the incomplete performer can sue his paymaster if out of favour, with courts preferring to confine the right to
no money is forthcoming. treat a contract at an end as turning on whether the breach has
deprived the innocent party of substantially the whole benefit
12.03 The general rule of contract law is that a party must per- which it was intended should be obtained from the contract.
form everything which he or she contracted to do. At common These tests for when a party will have a right to treat a contract
law, the consequence is that, in a contract between A and B, A as at an end are sufficiently uncertain that almost all well-
must perform all its obligations before it can claim from B for drafted contracts contain detailed, express terms governing
non-performance of B’s obligation. It followed that at common the circumstances in which an innocent party can terminate
law, a building contractor had no right to any payment until it a contract.
had completed its contract works. Unsurprisingly, it therefore
became the almost invariable practice for contractors offering to 12.08 In all the circumstances described above, the innocent
perform works of any scale to require a contractual term for peri- party has a choice as to whether or not to treat itself as dis-
odic or stage payments. Today, statute has intervened to create a charged. It may prefer to press for performance of the contract
right to periodic or stage payments in most cases: the Housing so far as the other party is able to perform it, or it may accept
Grants, Construction and Regeneration Act 1996 requires this in the ending of the contract and restrict itself to a remedy in
any contract for works expected to last more than 45 days, unless damages. But once made, the election cannot unilaterally be
the contract is with a residential occupier. changed, unless the matter which gave rise to it is a continuing
state of affairs which therefore continues to provide the remedy
12.04 An example of the common law rule was provided by afresh. Normally, the innocent party, such as a contractor whose
Bolton v Mahadeva [1972] 1 WLR 1009. There, the claimant job is cancelled, will accept the situation and confine itself to
agreed to install a hot water system for the defendant for a suing for damages, which are often its lost profit. But in theory,
lump-sum payment of £560. The radiators emitted fumes, and at any rate, in situations where performace does not require
the system did not heat the house properly. Curing the defects active cooperation from the defaulting party, the innocent party
would cost £174. The defendant was held not liable to pay the can go ahead with the performance of its contract and claim
claimant anything. the price.

12.05 There is an important exception to this rule, even for entire


contracts. If the party performing the works has ‘substantially 13 Rights for those who are
performed’ its obligations, then it is entitled to the contract
sum subject only to a counter-claim for those parts remaining not contracting parties
unperformed. In Hoenig v Isaacs [1952] 2 All ER 176, there
was a lump-sum contract for the decoration and furnishing of Privity of contract
the defendant’s flat for the price of £750. When the claimant
13.01 Contractual rights of their nature are enjoyed by contract-
left, one wardrobe door needed replacing, and one shelf was too
ing parties. Those who are not parties to a contract, that is, those
short and would have to be remade. The Court of Appeal held
who the law describes as outside the ‘privity of contract’, do not
that, although ‘near the border-line’ on the facts, the claimant
enjoy rights arising from the contract. Practical problems from
had substantially performed his contractual obligations and was
time to time arise from this concept of privity of contract.
therefore able to recover his £750, subject only to the deduction
For example, a piling sub-contractor may insert piles of
of £56, being the cost of the necessary repairs.
only half the specified depth. In consequence, a few years
later, the completed building may show signs of instability. The
employer will have a cause of action against the main contrac-
Remedies against the tor. But suppose the main contractor has gone into insolvent
incomplete performer liquidation in the meantime, or was only ever a special purpose
12.06 The flip-side of the situation of suing on an incom- company set up by a consortium, which included the piling
pletely performed contract is suing the incomplete performer. company, and now has no assets. The employer considers that,
Obviously, incomplete performance or misperformance gives to as a matter of common sense and fairness, the piling company
the other party, who has so far performed its obligations as they ought to pay compensation. But under the up-and-down theory
fall due, a right to damages, to put it in the position it would of contractual liability, the employer’s right of action lies
have been in had the contract been performed. However, in the only against the main contractor company, which is unable
realities of commercial life, employers or clients are likely to be or unwilling to litigate against the piling company under the
severely prejudiced if their sole right is one for eventual award sub-contract.
of damages when the slow-performing contractor or professional Or take another case: a Mr Smith engages a builder to erect
finally completes its obligations. In some circumstances, another an extension to the family home. A couple of years later, he and
remedy will be available to the aggrieved employer, enabling it his wife get divorced, and as part of the post-divorce financial
to treat the contract as at an end. arrangements, the family court orders the matrimonial home to
be transferred to Mrs Smith. Then, defects in the extension come
12.07 One situation in which an innocent party may treat a to light. The person who has a contactual cause of action with
contract as at an end is where the other party commits a breach the builder is Mr Smith, but he, smarting from losing his home,
which ‘goes to the root of the contract’, or deprives the party declines to assist by suing.
of, substantially, the whole benefit the contract was intended
to confer: the law calls this a ‘repudiatory breach’. Another The Contracts (Rights of
situation with a similar result is where one party evinces an
intention not to continue to perform its side of the contract:
Third Parties) Act 1999
the law calls this a ‘renunciation’. A third situation in which an 13.02 In order to address such problems, Parliament enacted the
innocent party is entitled to inform the other that the contract Contracts (Rights of Third Parties) Act 1999. Its general aim was
is at an end, is if a breach is committed which, whilst not so to give the innocent parties in the above examples a direct right
fundamental as to amount to a repudiation, is deemed by the of action against the defaulting party – to the employer against
law to be of a term of sufficient import to justify the exercise the piling sub-contractor in the first example, and to Mrs Smith
of such a right. A term which is so categorised has tradition- against the builder in the second. The Act applies to contracts
ally been called a ‘condition’, with other, less significant terms made after 11 May 2000.
Agency 19

13.03 By section 1, the third party will have a right to enforce a in minimising the number of people who will have the right to
term in the contract made for his or her benefit if: sue them. In practice, in almost all contracts in the construction
industry, one finds a term stating that the 1999 Act is excluded.
1 the term in the contract expressly says that he or she may The same is true in many other sectors of commercial life.
enforce that term; or Accordingly, although in theory the Act was one of the most
2 if he or she is expressly identified in the contract by name, radical reforms to the law of contract since medieval times, its
class, or description (even if not in existence at the time the practical effect has been much smaller than expected. For the
contract is made), and the term purports to confer a benefit construction industry, it has had relatively little practical impact.
on him or her.

An example of the first kind would be a contract term which


Collateral warranties
says that X’s next-door neighbours can claim compensation from 13.08 Rather than press contractors to agree to the application
the builder for any damage to their property while the works are of the Act, in practice, employers seek to secure protection for
carried out on X’s land. An example of the second kind would be those who may be prejudiced by the privity of contract limitation
a contract term which says that compensation is payable by the on the right to sue by what are called ‘collateral waranties’. This
builder to the next-door neighbours for any damage caused while expression is used to refer to an agreement made between a con-
the builder carries out works on X’s land, but does not specifi- tractor or a professional and a person other than the employer,
cally provide for the next-door neighbours to make a claim. A under which the contractor or professional promises (or ‘war-
less clear-cut situation is where the builder has contracted not to rants’) that the services which it is contracted to perform under
cause a nuisance to X’s neighbours while carrying out the works, its contract with the emoployer will be carried out in accordance
but says nothing about compensation or other remedy. It is in with that main contrtact. In consequence, if the work performed
such a situation that the distinction between the law of contract is defective, the other party to the collateral warranty can sue
and the law of tort seems to have become blurred. the contractor or professional in just the same circumstances as
the employer could.
13.04 The third party will not be put in a better position than
the contracting parties, and so can only exercise its right in 13.09 An issue is whether such collateral warranty agreements
accordance with and subject to the terms and conditions of the are supported by sufficient consideration to be congtractually
contract. Where there are exclusions and limitations, they will enforceable. This can be overcome by providing that the con-
apply to the third party just as much as the contracting parties. tractor/professional gives the warranty to the third party in con-
And just as a contracting party has to mitigate its loss where the sideration of receiving its main contract. But in practice, parties
other party is in breach of contract, so, too, will a third party often remove any doubts on this score by executing the collateral
have to mitigate its own loss. Also, the third party’s right will warranty as a deed. In a project of any scale, the architect may
be subject to any defence or set-off that the party against whom well be asked, as condition of its appointment, to execute col-
the term is enforced would have against the other contracting lateral warranties with the funders, with parent companies, and
party. Additionally, the third party can also expect its right to be with the prospective occupier of the building.
subject to counterclaims and set-offs which the other contracting
party has against the third party under any separate relationship.
For example, if C can sue B for the price of work done under 14 Agency
the contract between A and B, B can counterclaim for damages
suffered under a separate contract between C and B the previous 14.01 For A to act as an agent for P as the principal, means
year, when C bodged that job. Of course, the rights of set-off that A acts as P’s representative. A’s words or actions will cre-
will be subject to the express terms of the contract. ate legal rights and liabilities for P, who is therefore bound by
what A does, just as if P had said or done those things itself.
13.05 However, the statutory scheme only takes effect subject to The agent’s actions might have consequences for P in contract,
the contract between the parties: the party’s freedom of contract is or tort, or some other area of the law, but in this chapter, it is
preserved (except in the case of a subsequent variation to the con- naturally only with contractual liabilities that we are concerned.
tract where the original terms conferred a benefit on a third party In general, if A, as P’s agent, properly contracts with C, then the
which is enforceable by the statutory scheme). For this reason, a resulting contract is a contract between P and C. A is not privy
third party will not have the right to enforce a term of someone to the contract, and can neither sue or be sued upon it.
else’s contract if, on a proper interpretation of the contract, the
contracting parties did not intend that term to be enforceable by 14.02 The legal obligations between the principal and agent may,
the third party (see section 1(2) of the Act). It is thus possible to but need not, itself be the subject of a contract – the contract of
provide an express term conferring a benefit on a third party, but agency. For instance, A may be rewarded by a percentage com-
precluding the third party from enforcing that benefit, or simply mission on any of P’s business which A places with C. If A does
to contract out of the statutory provisions altogether. not receive commission, A may wish to sue P, and A will do so
under the contract of agency. That is a matter between P and A,
13.06 If the original contracting parties choose not to include a and of no interest to C. It is governed by the rules for contracts
term excluding the Act, and so allow the Act to apply to their of agency. These rules, just a specialized sub-set of the rules of
contract, they do face statutory limitations on their ability sub- contract generally, will not be further discussed here.
sequently to alter that arrangement. The normal freedom to vary
a contract is restricted where the third party has communicated
its assent to the benefit/right to the person against whom the
Creation of agency
benefit/right would be enforced (called ‘the promisor’), or if the 14.03 The commonest way to create an agency is by an express
promisor is aware that the third party has relied on the term, or appointment. Generally, no formalities are necessary: the
where the promisor could reasonably have foreseen that the third appointment may be oral or in writing. To take an example,
party would rely upon and has, in fact, relied upon the term. the employees of a trading company are frequently expressly
In those situations, a variation can take effect only if either the appointed by their contract of employment to act as the agents
third party consents, or the court makes an order waiving this on of the company and to place and receive orders on its behalf.
the ground that the third party cannot be located or is mentally
incapable of giving consent. 14.04 A relationship of agency may also arise by ‘estoppel’. If
P, by words or conduct, leads C to believe that A is P’s agent,
13.07 The ability to exclude the Act has been popular with con- and C deals with A on that basis, A cannot escape the contract
tractors of almost every kind, who see their interests as lying by saying that, in fact, A was not his or her agent. In these
20 The English law of contract

circumstances, P will be stopped, or ‘estopped’, from making upon it. This, of course, would have to be the case, for really
that assertion. in these circumstances, there is no agency operating at all. But
it is important to remember that ostensible authority may fix a
14.05 A third way in which a relationship of agency may be cre- principal with liability when the agent is acting outside his or
ated is by ‘ratification’. If A, not in fact being P’s agent, purports her express or implied authority.
to contract with C on P’s behalf, and P then discovers the con-
tract, likes the look of it, and ratifies and adopts it, then at law, A 14.10 The position of the agent is more complex. If the agent
is deemed to be P’s agent for the purposes of that contract. The purported to contract as agent for a named principal, then the
precise working of the rules of ratification are rather involved. agent cannot sue on the contract. On the other hand, if the name
of the principal is not disclosed, the agent can sue upon the
contract as if it were his or her own.
Authorisation
14.06 The effect of an agent’s words or actions will depend on 14.11 Turning now to the liability of an unauthorised agent to
whether or not the agent was authorised by his or her principal be sued by C, the position depends on what the agent thought
to say or do them. The agent’s authority will usually be an actual was the true position between him or herself and P. If A knows
authority, that is, an authority which has expressly or impliedly all along that he or she does not have P’s authority to enter into
been granted by the principal. But the scope of the agent’s the contract, then upon discovery of the true situation, C can sue
authority may, most importantly, be enlarged by the addition of A, although for the tort of deceit, rather than under the contract.
his ostensible authority.
14.12 If, on the other hand, A genuinely thought that he or she
14.07 Ostensible authority is another manifestation of the opera- was authorised by P to enter into the contract, A cannot be sued
tion of estoppel. If P represents to C that his or her agent, A, has by P for deceit – after all, A has not been deceitful, merely mis-
an authority wider than, in fact, has been expressly or impliedly taken. Instead, C has an alternative remedy. The court will infer
granted by P to A, and in reliance on that representation, C the existence of a collateral contract by A (as principal) with C,
contracts with P through A, then P will be stopped (‘estopped’) under which A warranted that he had P’s authority to contract.
from denying that the scope of A’s authority was wide enough This is a quite separate contract to the non-existent contract
to include the contract that has been made. An architect is likely which C thought it was entering into with P, but from C’s point
to be held to have ostensible authority on behalf of the client. of view, it is just as good, for now C can sue A instead. This is
referred to as a claim for breach of warranty of authority.

The agent acts within the


scope of authority 15 Limitation under the
14.08 The agent may tell C that P exists and name P. Or, A may
Limitation Act 1980
tell C that he or she has a principal, but not name him or her. 15.01 An action for breach of contract must generally be com-
Or – still less communicative – A may not tell C that he or she menced within six years. Time begins to run – the six years
has a principal at all, so that as far as C is concerned, C is con- starts – when the contract is breached. This may mean that the
tracting with A directly. Depending on which of those situations claimant can sue before any real physical damage has been
has occurred, the legal position is as follows: experienced. Suppose the defendant is an architect who has, in
breach of contract, designed foundations for a building which are
1 Principal is named: This is, in a sense, the paradigm inadequate, and it is clear that, in ten-to-twenty years’ time, the
example of agency in action. A drops out of the picture alto- building will fall down if remedial works are not carried out. The
gether, the contract is between P and C, and A can neither claimant can sue straight away. Of course, although no physical
sue nor be sued on the P–C contract. damage has yet occurred, there has been economic loss, because
2 Existence of principal disclosed, but not the identity: The the defendant has got out of the contract a building worth much
general rule is the same as in case 1. less than what he or she paid for it, and it is obviously right that
3 Neither name, nor existence of principal disclosed to C: he or she should be able to sue straightaway.
This case is described as the case of the undisclosed prin-
cipal. The rule here is somewhat counter-intuitive: both the 15.02 The exception to this rule is that a claimant may sue on a
agent and the principal may sue on the contract, and C may contract contained in a deed up to twelve years after the contract
sue the agent, and, if and when C discovers the identity, the was breached. It is for this reason that building contracts – which
principal. may take more than six years from inception to completion – are
frequently made under deed.
The agent acts outside the
15.03 The law on limitation periods is to be found in the
scope of his authority Limitation Act 1980. The law on limitation periods for suing
14.09 The position as regards the principal is clear. The princi- on a tort is different and more complicated, and is explained in
pal is not party to any contract, and can neither sue nor be sued Chapter 3.
3
The English law of tort
CLAIRE PACKMAN

1 Introduction Acts or omissions which any moral code would censure can-
not in a practical world be treated so as to give a right to every
1.01 The law of tort deals with conduct that causes harm to a person injured by them to demand relief. In this way rules of
party’s personal, proprietary, or financial interests. It is the law law arise which limit the range of complaints and the extent
of wrongdoing, and its purpose is to compensate (or sometimes of their remedy.
to prevent in the first place) interference with personal, propri-
etary or, occasionally, non-physical interests (such as a person’s
reputation or financial position). The law of tort provides a sys- 2 Negligence
tem of loss distribution and regulates behaviour within society.
2.01 Negligence is the most well-known tort and is concerned
1.02 The difference between obligations in contract and in tort with the careless infliction of harm or damage. It has three
was explained as follows by Jackson LJ in Robinson v PE Jones essential elements, namely: (a) the existence of a legal duty of
(Contractors) Limited [2012] QB 44. Contractual obligations care; (b) a breach of that duty; and (c) consequential damage.
spring from the consent of the parties and the common law
principle that contracts should be enforced. Tortious duties are
imposed by law, as a matter of policy, in specific situations.
The legal duty to take care
Contractual obligations are negotiated by the parties and then 2.02 The concept of the duty of care identifies and limits the
enforced by law, because the performance of contracts is vital class of people to whom another may be liable for negligent acts.
to the functioning of society. Tortious duties are imposed by law There is no single test which can be applied to novel claims in
(without any need for agreement by the parties) because society negligence to determine whether or not a duty of care exists. The
demands certain standards of conduct. traditional approach to defining the situations that give rise to
a duty of care was based upon a process of incremental exten-
1.03 Architects will usually have both contractual and tortious sion by analogy with existing cases, rather than on the basis of
obligations to their clients. Architects may find themselves fac- a general principle, and this remains the preferred approach in
ing claims in tort alone in some circumstances, for example most cases: see Robinson v Chief Constable of West Yorkshire
where an architect has provided free advice or services to a [2018] AC 736.
friend or neighbour, where loss is suffered by a party who relied
on the architect but was not the contracting party (for example, 2.03 The first notable attempt to set out a principled approach
another company within the same group or a subsequent pur- occurred in Donoghue v Stevenson (above). The plaintiff, who
chaser), and in cases where the limitation period has expired in was given a bottle of ginger beer by a friend, alleged that she
contract but not in tort. had become ill after drinking it because the bottle contained a
decomposed snail. As the plaintiff had no contractual relation-
1.04 There are a number of different torts, the most well-known ship with the seller (as her friend had bought it), she attempted
of which are negligence, nuisance, and trespass. A general to sue the manufacturer in tort. The House of Lords held that
definition is difficult because it is impossible to fit the various a manufacturer of bottled ginger beer (or other articles) did
separate torts into a single system of classification. The best that owe the ultimate purchaser or consumer a legal duty to take
one can say is that torts are legally wrongful acts or omissions. A reasonable care to ensure that it was free from a defect likely to
factual situation may give rise to actions in a variety of overlap- cause injury to health. Therefore, in principle, the plaintiff had a
ping torts, for example, it is common to see claims brought in cause of action against the ginger beer’s manufacturer. However,
negligence and nuisance. the main significance of the case is contained in Lord Atkin’s
description of the general concept of the duty of care:
1.05 To be actionable, it is not enough that an act or omission
as a matter of fact harms another person’s interests in some The rule that you are to love your neighbour becomes in law,
way. The wrong must also interfere with some legal right of you must not injure your neighbour: and the lawyer’s ques-
the complaining party. The various categories of tortious rights tion, who is my neighbour? receives a restricted reply. You
provide the basis for assessing when actionable interference has must take reasonable care to avoid acts or omissions which
occurred and when a legal remedy is available. But the law does you can reasonably foresee would be likely to injure your
not go so far as to protect parties against all forms of morally neighbour. Who, then, in law is my neighbour? The answer
reprehensible behaviour; Lord Atkin described, in the landmark seems to be – persons who are so closely affected by my act
case Donoghue v Stevenson [1932] AC 562 at 580: that I ought reasonably to have them in contemplation as

21
22 The English law of tort

being so affected when I am directing my mind to the acts or likely to be coterminous with the implied contractual duty to
omissions which are called in question. take reasonable care in the provision of services under their con-
tract (see, for example, Storey v Charles Church Developments
2.04 This became known as Lord Atkin’s ‘neighbour’ principle Ltd [1996] 12 Const LJ 206), the contents of the parties’ contract
and was initially criticised as being too broad. In time, however, may create stricter contractual duties than are owed in the gen-
it became accepted, and remains today the central concept to an eral law of negligence or, alternatively, the circumstances of the
understanding of the tort of negligence. parties’ relationship may, in extreme situations, lead to the crea-
tion of wider tortious duties than have been created by the con-
2.05 In the 1970s, as a result of two House of Lords cases, tract of retainer (see, in the context of a surveyor’s negligence
Dorset Yacht Co Ltd v Home Office [1970] AC 1004 and Anns action, Holt v Payne Skillington [1995] 77 BLR 51 and, in an
v Merton London Borough Council [1978] AC 728, the law engineering context, Kensington and Chelsea and Westminster
appeared to develop so that, if there was a reasonable foresee- AHA v Wettern Composites Ltd (1984) 1 Con LR 114 and Hart
ability of harm to the plaintiff, there would be liability unless Investments Ltd v Fidler [2007] EWHC 1058 (TCC)).
there was some public policy reason to negate it (the Anns
‘two-stage test’). This approach was at first applied with enthu-
siasm. However, increasingly, it appeared to many judicial eyes
Breach of duty
to herald an unwarranted potential extension of liability into 2.11 In general, a person acts in breach of a duty of care when
situations previously not covered by the tort of negligence. As behaving carelessly. As Alderson J stated in Blyth v Birmingham
a result, there followed a steady retreat from the acceptance of Waterworks Company [1856] 11 Ex 781:
a general principle of liability back to the traditional emphasis
on existing case analogy and the incremental approach to the Negligence is the omission to do something which a reason-
extension of liability situations. able man, guided upon those considerations which ordinarily
regulate the conduct of human affairs, would do, or doing
2.06 Further attempts to set out a test for the imposition of a duty something which a prudent and reasonable man would not do.
of care resulted in the development of a ‘three-stage test’ involv-
ing a consideration of (a) foreseeability of damage; (b) the rela- 2.12 The standard of care required, then, is that of the reasonable
tionship of neighbourhood or proximity between the parties; and and prudent person: the elusive ‘man on the Clapham omnibus’.
(c) an assessment of whether the situation was one in which the The standard of reasonable care and skill is not a standard of per-
court considered it fair and reasonable in all the circumstances fection. It does not make an architect the insurer or guarantor that
to impose a legal duty (Smith v Eric S Bush [1990] AC 831). In the work has been properly done. Proving an error is not in itself
Henderson v Merrett Syndicates Ltd [1995] 2 AC 145, the House sufficient to show that there has been a failure to exercise reason-
of Lords emphasised the central importance of the concept of an able skill and care. A claimant must establish actual negligence.
‘assumption of responsibility’ to the question of whether or not
a duty of care in negligence is owed by one party to another. 2.13 The standard applied is objective in that it does not take
account of an individual’s particular weaknesses. However,
2.07 The relationship between the assumption of responsibility where people hold themselves out as having a special skill or
approach, the incremental approach, and the three-stage test has being a professional (such as an architect), the standard of care
recently been clarified in a number of Supreme Court cases which expected of them is higher than one would expect of a layperson.
make clear that the three-stage test is not to be applied, and that They are under a duty to exercise the standard of care in their
assumption of responsibility and the incremental approach are activities which could reasonably be expected from a competent
preferred: see Michael v Chief Constable of South Wales [2015] member of that trade or profession, whatever their actual level
AC 1732; Robinson v Chief Constable of West Yorkshire [2018] of experience or qualification.
AC 736; NRAM Ltd v Steel [2018] 1 WLR 1190; Playboy Club
London Ltd v Banca Nationale di Lavoro [2018] 1 W.L.R 4041. 2.14 In the case of architects (as with other professionals) the
In most cases concerning architects, the question of whether a test is whether there is a responsible body of architects that
duty of care was owed will depend on whether or not there was could have acted as the architect being criticised has (see Nye
a voluntary assumption of responsibility. Saunders v Bristow [1987] 37 BLR 92 per Stephen Brown LJ
at 103), although this is not a rigid rule (see Bolitho v City &
2.08 As for the scope of the duty, in South Australia Asset Hackney HA [1998] AC 232, HL), and is not applicable where
Management Corp v York Montague Ltd [1997] AC 1, the House it is not necessary to consider professional expertise to decide
of Lords emphasised the need to consider whether the scope of the alleged acts of incompetence (see Royal Brompton Hospital
the duty of care (whether in contract or tort) was sufficient to NHS Trust v Hammond (No.7) (2001) 76 Con LR 148). In gen-
embrace the kind of damage complained of in a particular case. eral, the duty owed by construction professionals is unaffected
The starting point in the assessment of damages should therefore by the relative experience or inexperience of their clients (see
be a consideration of whether the loss for which compensation Gloucestershire Health Authority v Torpy [1997] CILL 1281;
was sought was of a kind or type for which the tortfeasor ought but see J Jarvis & Sons Ltd v Castle Wharf Developments Ltd
fairly to have accepted responsibility. [2001] Lloyd’s Rep PN 308). In contrast, however, there are
also circumstances where the law accepts a lower standard of
care from people, such as at times of emergency or dilemma (or
Relationship to any duties outside the field of professional negligence, generally in the level
of care expected from children).
existing in the law of contract
2.09 As well as emphasising the importance of the concept of 2.15 The value of the concept of ‘reasonable care’ lies in its
an assumption of responsibility to establishing a duty of care in flexibility. What will be considered by a court as ‘reasonable’
negligence, Henderson v Merrett also decided that concurrent depends on the specific facts of a particular case. In general, the
duties of care in the tort of negligence may be owed by one party assessment of reasonableness involves a consideration of three
to another even if a contract already existed between them. Thus, main factors: (a) the degree of likelihood of harm; (b) the cost
even if an architect has a contract with his client, he will also and practicability of measures to avoid it; and (c) the seriousness
owe the client a concurrent duty of care in the tort of negligence of the possible consequences. The application and balancing of
(but see 2.39 to 2.44 below, where this is discussed further). these factors will vary from case to case.

2.10 Although, generally, the nature of any tortious duty to take 2.16 While precedents may not help in establishing what is rea-
reasonable care against causing damage to the other party is sonable on different facts, the developing case law on architect’s
Negligence 23

negligence does contain some general statements on the standard can play as important a role in deciding where responsibility for
of care expected which may be of more general application: see, losses should fall (on the professional, his client, or a third party)
for example, Freeborn v De Almeida Marcal [2019] EWHC as any easily definable rules or principles of law.
454 (TCC), in which it was held that any architect who did not
provide a written brief to a client would be in breach of his
duty of care, save in exceptional circumstances. In The Wagon Economic loss
Mound (No. 2) [1967] 1 AC 617, crude oil escaped from a ship
onto the surface of the water in Sydney Harbour. It subsequently (a) Introduction
caught fire and caused substantial damage to a wharf and two 2.21 Economic loss is a category of non-physical damage and
ships. However, notwithstanding expert evidence that the risk consists of financial losses (such as lost profits or the cost of
of the oil catching fire had been very small, it was held that the remedying defects). It is distinguished from damage to the
defendants were negligent in not taking steps to abate what was person or to other property (i.e. property other than that under
nevertheless a real risk and one which, if it occurred, was very construction). Unfortunately, as well as being an area of the
likely to cause substantial damage. utmost practical importance for architects, the concept of a duty
of care to prevent economic loss is also one of the more demand-
Damage must be caused by the breach ing aspects of the law of tort.

2.17 In order to establish liability in negligence, it is necessary 2.22 The tort of negligence originally developed as a cause of
to prove that the careless conduct has caused actual damage. action for someone who had been physically injured by the
There are three requirements in this process. The first is that, careless acts of another. It quickly developed into a remedy for
on the balance of probabilities, there must, as a matter of fact, careless damage to property. However, the attempt, from about
be a connection between the negligent conduct and the damage the 1960s (associated with the developing concept of a general
(causation in fact). If there are competing causes of a claimant’s principle of liability in negligence described above), to extend its
loss, the claimant must establish as a minimum that the cause ambit to economic losses generally has been largely unsuccess-
of which he or she complains materially contributed to the loss ful. Today, economic loss is sometimes recoverable in the tort
(see the decision of the House of Lords in IBA v EMI and BICC of negligence, but it requires a claimant to prove the exceptional
(1980) 14 BLR 1 at 37). The second is that the harm or damage circumstances necessary in order to establish that a defendant
caused is of a kind that was a foreseeable consequence of such owed a duty not to cause such damage. This long-standing
conduct (causation in law). The third overarching requirement reluctance to recognise a duty of care to prevent economic loss
is that the breach of duty be the ‘dominant and effective’ cause has been largely based on what is referred to as the ‘floodgates’
of the loss. This latter test really represents the application argument – the concern that it would widen the potential scale
of judicial common sense to cases which satisfy the first two of liability in tort to an indeterminable extent.
requirements, but nevertheless involve losses which should not
be recognised as caused as a matter of law by the relevant breach
of duty under consideration. (b) Distinguishing consequential
and pure economic loss
2.18 Foreseeability of harm therefore plays a role in all three
constituents of the tort of negligence: duty of care, breach, and 2.23 There is no general freestanding liability for economic
damage. In certain respects, this makes a separate consideration loss which is disassociated from physical damage. However,
of these individual constituents artificial. However, foresee- economic loss consequential to damage to property is treated
ability of damage has a slightly different application when separately and is generally recoverable. So, if damage is caused
considering the causation of actionable damage. In assessing to a neighbouring property as a result of negligence, the busi-
the existence and breach of a duty of care, it is the reasonable ness owner of the neighbouring property would have no bar in
foreseeability of a risk of some damage that is being considered. principle for a consequential claim for loss of profit in addition
Foreseeability of the occurrence of a particular kind of damage to the cost of repairs. The distinction between such ‘consequen-
does not affect the existence of this duty or the assessment of tial’ economic loss and ‘pure’ economic loss is not always clear.
carelessness, but it does dictate whether the damage that has Perhaps the best illustration is provided by the case of Spartan
been caused is actionable in law. Steel and Alloys Ltd v Martin & Co. (Contractors Ltd) [1973]
1 QB 27. In this case, the defendants negligently cut off an elec-
2.19 If the kind of damage actually caused was not foreseeable, tricity cable which supplied the plaintiff’s factory. As a result,
there is no liability in negligence. However, as long as the kind some of the plaintiff’s molten metal that was being worked
of damage is reasonably foreseeable, there will be potential upon at the factory was damaged, causing the plaintiff to make
liability, even if the factual manner in which it was caused was a smaller profit on its eventual sale. Production was also delayed
extremely unusual and unforeseeable in itself. In Hughes v Lord generally at the factory, and the plaintiff lost the opportunity to
Advocate [1963] AC 837, workmen left a manhole overnight make profits on this lost production. It was held that although
covered by a tent and surrounded by paraffin lamps, but other- the economic loss caused by the general delay in production was
wise unguarded. The eight-year-old plaintiff ventured into the not recoverable (being pure economic loss), the lost profit from
tent, fell down the manhole, dragged some of the lamps down the molten metal actually in production at the time of the power
with him and thereby caused an explosion which caused him to cut was recoverable as it was immediately consequential to the
be severely burned. The House of Lords held that although the physical damage to the molten metal itself. This was because
manner of the explosion was highly unusual, the source of the economic loss immediately consequential to damage to property
danger and kind of damage that materialised (i.e. burns from is recoverable in negligence.
the lit paraffin) were reasonably foreseeable, and therefore the
workmen were liable. (c) Liability for negligent statements
2.20 As noted above, however, it is sometimes simplistic to view 2.24 The first exception to the general rule of there being no duty
the law of causation as simply a consideration of the first two to avoid causing pure economic loss was provided in the area
requirements outlined in paragraph 2.17 above. The courts may of negligent mis-statement and the line of authorities following
apply a less precise test of judicial common sense to distinguish Hedley Byrne & Co. Ltd v Heller & Partners [1963] AC 465.
between the effective cause of a loss from conduct which merely In this seminal case, the defendants gave a favourable financial
provides the occasion for it (as applied by the Court of Appeal reference to the plaintiff’s bankers in respect of one of the
in Galoo v Bright Grahame Murray [1994] 1 WLR 1360). plaintiff’s clients. The plaintiff relied on this incorrect reference
Ultimately, this factor reflects the reality that judicial policy and, as a result, suffered financial losses when the client became
24 The English law of tort

insolvent. The House of Lords held that a defendant would be their Lordships held that it would be anomalous in principle if
liable for such negligent mis-statements if: (a) there was a ‘spe- someone involved in the construction of a building should be in
cial relationship’ based upon an assumption of responsibility any different position from the manufacturer of bottled ginger
between the parties; (b) the defendant knew or ought to have beer or any other chattel.
known that the plaintiff was likely to rely upon his statement;
and (c) in all the circumstances, it was reasonable for the plain- 2.31 The second main justification was that innovation in the
tiff so to rely on the defendant’s statement. law of consumer protection against defects in the quality of
products should be left to Parliament, especially in the light of
2.25 In accordance with the retreat from an acceptance of a the remedies provided by the Defective Premises Act 1972 in the
general principle of liability in negligence and, in particular, its case of residential dwellings (for which see Section 3 below).
extension to economic loss generally, the circumstances where
the courts will now recognise the required ‘special relationship’ 2.32 This latter justification is less convincing, since most deci-
may have narrowed since the 1970s. In Caparo v Dickman sions in this field, including Donoghue v Stevenson itself, can be
[1990] 2 AC 605, the House of Lords held that auditors of viewed as essentially judicially created consumer-protection law
a company’s financial reports did not owe a duty of care to in any case. However, it does illustrate the influence of judicial
prospective share purchasers to avoid negligent mis-statements policy in the court’s approach to the recognition of a duty of care
because, unlike a company’s existing shareholders, the parties in novel situations. Further, although Murphy v Brentwood has
were not in a relationship of sufficient proximity. Liability for certainly simplified the law in this area, there remain recognised
economic loss caused by negligent mis-statement was to be exceptions to the general rule against the existence of a duty of
restricted to situations where the statement was given to a known care to prevent economic loss in negligence.
recipient for a specific purpose of which the maker of the state-
ment was aware.
(e) Exceptions to Murphy v Brentwood
2.26 This represented a narrow interpretation of the Hedley 2.33 First, the position in respect of economic loss consequential
Byrne principle consistent with the revival of the incremental to physical damage and negligent mis-statements remains unaf-
approach to liability discussed in paragraph 2.02 above. fected by the decision (see paragraph 2.23 above).

2.27 Liability for negligent mis-statement may be of relevance 2.34 In addition, in Murphy v Brentwood, their Lordships recog-
to architects when giving their clients advice, for example, nised that damage to a building caused by defects in a discrete
in relation to cost estimates or which builders to use. In Nye part of it could, in certain circumstances, be recoverable in tort.
Saunders v Bristow [1987] 37 BLR 92, although there was no Under the pre-Murphy v Brentwood ‘complex structure theory’,
allegation of defective work, the architect was found to be in the individual parts of a building (such as the foundations, walls,
breach of a Hedley Byrne-type duty by not advising his client or roof) could be treated as distinct items of property. Therefore,
as to the possible effect of inflation on his estimate for the cost liability for damage caused to, say, the roof, by a defect in the
of proposed works. foundations, could be justified by treating the building as a com-
plex structure and depicting the damaged roof as a separate piece
of damaged property. This analysis was proposed as a means of
(d) Liability for negligent conduct reconciling the post-Anns v Merton recognition of liability in
2.28 In contrast to the position with negligent statements, the negligence for defective premises with the established principle
attempt in a number of leading cases since the 1970s to extend that there is no tortious liability for defective products.
liability for pure economic loss to negligent conduct has largely
failed. The initial momentum for such an extension was pro- 2.35 In Murphy v Brentwood, their Lordships rejected the com-
vided by Anns v Merton, which concerned structural damage plex structure theory and viewed the damaged house as a single
in a building that had been caused by defective foundations. piece of property (i.e. not a complex structure). However, they
The House of Lords allowed the recovery in tort of the pure have left open the possibility of liability in the normal way
economic loss caused by the need to carry out repairs so that the where the item within a building that causes the damage is a
property was no longer a threat to health and safety. distinct one (perhaps a faulty electrical fuse box which causes a
fire) and is built or installed by a separate party from the builder.
2.29 However, in its decisions in Murphy v Brentwood District If damage is caused by such a ‘non-integral’ part of the build-
Council [1991] 1 AC 398 and Department of the Environment v ing, it may be considered as damage caused to separate property
Thomas Bates & Sons Ltd [1991] 1 AC 499, the House of Lords (which, under normal principles, would be actionable damage in
overruled Anns v Merton. The facts of Murphy v Brentwood also negligence). For further discussion of this limited exception, see
concerned a house which had been built on improper founda- Broster v Galliard [2011] EWHC 1722 (TCC), which reviews
tions, allegedly because of the Council’s negligence in passing treatment of the issue in Bellefield Computer Services Ltd v E
the building plans. It was held that the Council did not owe a Turner & Sons Ltd [2000] BLR 97, Payne v Setchell [2002]
duty in tort to the owner or purchaser of property in respect of PNLR 7, and Linklaters v McAlpine [2010] EWHC 1145 (TCC).
the costs of remedying such defects in the property. The repair
costs were held to be pure economic loss and irrecoverable, 2.36 This concept is illustrated by the case of Nitrigin Eireann
whether or not the defects amounted to a threat to health or Teoranta v Inco Alloys [1992] 1 All 854. The defendants had
safety. manufactured and supplied the plaintiff’s factory with some
alloy tubing in 1981 that had developed cracks by 1983. It was
2.30 There were two main reasons for the decision in Murphy held that although the cracked tubing in 1983 constituted pure
v Brentwood. First, it was considered established law that, in economic loss (because, at this time, there was no damage to
tort, the manufacturer of a chattel owed no duty in respect of other property), damage to the factory caused by an explosion
defects that did not cause personal injury or damage to other in 1984 (itself caused by the continuing weakness in the tubing)
property. Thus, in Donoghue v Stevenson (see paragraphs 2.02 did give rise to a cause of action in negligence. The structure of
and 2.03 above), the defendant was not liable in tort for the the factory surrounding the tubing was considered to be separate
diminution in value of the bottle of ginger beer by reason of property and therefore this damage was not pure economic loss.
the presence of a decomposed snail in it. Mrs Donoghue could
only recover damages against the manufacturer in respect of the 2.37 Two other bases for liability in negligence for defective
physical harm caused to her by drinking it. Therefore, the defec- premises had been thought to have survived the decision in
tive house in Murphy v Brentwood was effectively considered Murphy v Brentwood, although their application in practice is
analogous to the bottle of ginger beer in Donoghue v Stevenson: extremely unlikely. First, Lord Bridge suggested that there may
Negligence 25

be a duty to prevent economic loss where the defective build- the authorities towards the liability of a simple builder compared
ing is so close to its boundary that, by reason of its defects, the with that of a ‘design and build’ contractor or a construction
building might cause physical damage or injury to persons on professional. The former does not carry out any design function
neighbouring land or the highway. This approach was applied (and would therefore not normally be considered liable in tort
in Morse v Barrett (Leeds) Ltd (1993) 9 Const LJ. However, for any defects in the building itself, on the basis of Murphy v
finding liability in these circumstances would appear to contra- Brentwood), whereas the design and build contractor or con-
dict the reasoning in the rest of their Lordships’ judgments in struction professional might well be liable on Hedley Byrne
Murphy v Brentwood. It is submitted that the better view is that principles.
the cost of repairing such defects would still be irrecoverable in
negligence, as it amounts to pure economic loss. This was the 2.43 This apparent dichotomy was grappled with at first instance
approach taken in George Fischer Holding Ltd v Multi Design in Payne v John Setchell Ltd [2002] BLR 48. Here it was held
Consultants Ltd (1998) 61 Con LR 85 at 109–111 and in Thomas that, ordinarily, construction professionals (such as architects)
v Taylor Wimpey Developments Ltd [2019] EWHC 1134 (TCC). and building contractors might both only be under a duty of care
in tort to take reasonable care against causing their contractual
2.38 Second, there is the anomalous case of Junior Books v clients personal injury or damage to property other than the
Veitchi & Co. [1983] 1 AC 520, which the House of Lords building/item of work that is the subject matter of their services.
could not bring itself to overrule in addition to Anns v Merton. Thus, the dichotomy was resolved in this case by a finding that
In Junior Books, the defendants were specialist floor sub-con- neither the contractor nor the construction professional should
tractors who were engaged by main contractors to lay a floor owe a duty of care in the ordinary course of events in respect
in the factory of the plaintiff, with whom they had no formal of defects in quality in the product of their work or services.
contract. The floor subsequently cracked up, and the plaintiff This wrongly appears to rest upon the assumption that Murphy
sued for the cost of relaying it. The House of Lords held that, v Brentwood is authority for the proposition that a building con-
on the particular facts of the case, there was such a close rela- tractor can never owe his client a duty of care in tort in respect
tionship between the parties that the defendants’ duty of care of the quality of his work. However, Murphy v Brentwood did
to the plaintiff extended to preventing economic loss caused not directly decide this point; rather, it dealt with the responsibil-
by defects in their laying of the floor. This decision at first ity in tort of a local authority in respect of such defects.
appears completely contradictory to the reasoning in Murphy v
Brentwood, although some of their Lordships sought to explain 2.44 The better position in the light of Henderson v Merrett
it as a special application of the Hedley Byrne principle. One is that, if a building contractor can be taken on the facts of a
view is that Junior Books will continue to be considered as an particular case to have assumed responsibility toward his client
anomalous case decided very much on its own facts, and not for his work, a tortious duty in respect of the quality of that
one that establishes, as a matter of principle, a further category work may arise (for support for this proposition, see Bellefield
of exceptions from the main decision in Murphy v Brentwood. Computer Services Ltd v E Turner & Sons Ltd [2000] BLR
96 per Schieman LJ at 102). The approach in Payne v John
Setchell was not followed by Judge Toulmin CMG QC in
(f) The effect of Henderson v Merrett Ove Arup & Partners International Ltd v Mirah Asia-Pacific
2.39 The ambit of the duty of care in cases of economic loss Construction (Hong Kong) (No. 2) [2004] EWHC 1750 (TCC).
was considered in Lord Goff’s landmark speech in Henderson v
Merrett Syndicates Ltd [1994] 3WLR 761. Here, the House of 2.45 The matter was finally directly addressed by the Court of
Lords unanimously held that a concurrent duty of care was owed Appeal in Robinson v PE Jones (Contractors) Limited [2012]
in tort by managing agents to Lloyd’s names, notwithstanding QB 44, where it was held that, absent assumption of responsibil-
the existence of a contractual relationship between them. The ity, concurrent tortious duties which are co-extensive with the
decision therefore established that concurrent duties in tort may contractual duties do not arise in respect of construction work
exist between parties in a contractual relationship. carried out by a contractor. Without assumption of liability, tor-
tious duties are limited to personal injury and damage to prop-
2.40 In addition to characterising the basis of such liability as erty. In that case, the builder had not assumed responsibility, and
being the voluntary assumption of responsibility by one party to its role under an ordinary building contract was distinguished
another, Lord Goff also interpreted the Hedley Byrne principle from the relationship with a professional. Jackson LJ stated as
as applying to the provision of professional services generally, follows:
whether by words or actions. Thus, at p. 776 of his judgment
he concludes: It is perhaps understandable that professional persons are
taken to assume responsibility for economic loss to their
the concept provides its own explanation why there is no clients. Typically, they give advice, prepare reports, draw
problem in cases of this kind about liability for pure economic up accounts, produce plans and so forth. They expect their
loss: for if a person assumes responsibility to another in clients and possibly others to act in reliance upon their work
respect of certain services, there is no reason why he should product, often with financial or economic consequences.
not be liable in damages for that other in respect of economic When one moves beyond the realm of professional retainers,
loss which flows from the negligent performance of those it by no means follows that every contracting party assumes
services. It follows that, once the case is identified as falling responsibilities (in the Hedley Byrne sense) to the other par-
within the Hedley Byrne principle, there should be no need to ties co-extensive with the contractual obligations. Such an
embark upon any further enquiry whether it is “fair, just and analysis would be nonsensical.
reasonable” to impose liability for economic loss

2.41 This represented a major conceptual extension of the cat-


(g) Continuing evolution of the law
egory of conduct in which the courts might recognise a duty to 2.46 Finally, in the light of Henderson v Merrett, it should
prevent causing economic loss. be emphasised that Murphy v Brentwood does not shut off
the possible recognition of new categories of relationships in
2.42 The tension between the decisions in Murphy v Brentwood which a non-contractual duty to avoid causing economic loss
and Henderson v Merrett has become most clear in the case of will be recognised. For example, in Punjab National Bank v de
liability in tort for defective building works. Prior to Henderson Boinville [1992] 1 WLR 1138, the Court of Appeal held that
v Merrett, the authorities did not contemplate builders, or design- (a) the relationship between an insurance broker and his client
ers, or other construction professionals owing duties of care in was a recognised exceptional category of case where such a
respect of economic loss. A difference of approach emerged in duty existed; and (b) it was, on the facts of the case, a justified
26 The English law of tort

extension of this category to hold that a broker owed a like duty 8 Where there is an assumption of responsibility between an
to a non-client where the broker knew that the insurance policy architect and his client or third party, the architect may owe
was to be assigned to this person, and that he had been involved a duty of care to prevent causing purely economic losses
in instructing the broker in the first place. as a result of careless statements (via negligent designs,
certification, or advice) and in relation to the provision of
his services in general: see Burgess v Levonjarn above.
(h) Gratuitous services 9 An architect may also, in appropriate circumstances, owe
2.47 Where work is done free of charge, but in a professional, his client or a third party a personal duty of care – distinct
as opposed to an informal, or social context, the recipient of from the responsibility assumed by the firm or company
the services will still be a client in the professional sense, even for which he works (in the light of Merrett v Babb [2001]
if not contractually. The performance of services in such a pro- 3 WLR 1, which was a case where a surveyor was found to
fessional context is likely to amount to a voluntary assumption have owed his client a personal duty of care in respect of a
of responsibility, and a duty of care will arise. There will be valuation report prepared for mortgage purposes and signed
no positive obligation to carry out services, but those services in his personal capacity).
that are carried out must be done with reasonable skill and
care. This can extend to supervision and budgeting as well as
design work: see Burgess v Levonjarn [2017] EWCA 254, in 3 The Defective Premises Act 1972
which Hamblen LJ explained: ‘She did not have to provide
any such services, but to the extent that she did so she owed 3.01 Section 1 of the Act provides:
a duty to exercise reasonable skill and care in the provision of
those services.’ ‘1 A person taking on work for the provision of a dwelling
(whether the dwelling is provided by the erection or by the
conversion or enlargement of a building) owes a duty –
(i) Conclusion
(a) if the dwelling is provided to the order of any person, to
2.48 In summary, as far as the particular position of profes- that person; and
sional architects is concerned, the consequences of the landmark (b) without prejudice to paragraph (a) above, to every person
decisions in Murphy v Brentwood and Henderson v Merrett are who acquires an interest (whether legal or equitable) in
probably as follows: the dwelling;
1 Duties of care in tort will be owed by architects to their to see that the work which he takes on is done in a workmanlike
clients in relation to economic losses of a similar nature or, as the case may be, professional manner, with proper materi-
and extent as that created by any contract between the als and so that as regards that work the dwelling will be fit for
parties. habitation when completed.’
2 Economic loss claims by third parties (i.e. those not in a
contractual relationship with the architect) for defective 3.02 All building professionals, including architects, can be ‘per-
work will not succeed unless there is a Hedley Byrne rela- sons taking on work’ pursuant to the Act if the work undertaken
tionship or voluntary assumption of responsibility. is concerned with a dwelling. The duty created by the Act is
3 However, potential Donoghue v Stevenson-type liability for owed to the person for whom the dwelling is provided, although
personal injury or damage to other property remains: for the main purpose for the Act was to confer a right of action on
example, if a piece of roofing falls off a building because subsequent owners of the dwelling which they would otherwise
of an architect’s negligent design and breaks a person’s leg not have. Although not specified under the Act, the appropriate
or dents their car (whether or not that person is the owner remedy for breach of its duty is damages. The duty cannot be
of the building or a client). avoided by exclusion clauses.
4 The principle at 3 above extends to make an architect
potentially liable to subsequent owners of a building in 3.03 The person or company undertaking the work is liable not
respect of damage caused to other property or the person by only for their own work, but also for the work of independent
latent defects in the building attributable to his negligence sub-contractors employed by them if they are engaged in the
(see Baxall Securities Ltd v Sheard Walshaw Partnership course of their business. The reference to a ‘dwelling’ implies
[2002] BLR 100; Pearson Education Ltd v The Charter that the Act is limited to property capable of being used as a
Partnership Ltd [2007] EWCA Civ 130). residence. However, the Act does not apply to remedial work to
5 Given the limited scope for recovery for economic loss by an existing building. Further, liability under the Act is limited to
third parties, potential liability pursuant to the Defective a period of 6 years after the completion of the work concerned.
Premises Act 1972 will remain of interest (see below). This special limitation period provides a major restriction on the
6 It is submitted that, in practice, liability between an archi- potential significance of the Act.
tect and a third party for economic loss will be hard to
establish, absent particular circumstances demonstrating 3.04 There has been some discussion of whether the Act imposes
a positive assumption of responsibility: for unsuccessful a triple statutory duty (to ensure that (a) work is done in a work-
attempts against engineers in a construction project context, manlike manner; (b) with proper materials; and (c) as regards
see Galliford Try Infrastructure Ltd v Mott McDonald Ltd that work the dwelling will be fit for human habitation) or a
[2008] EWHC 1570 (TCC) and Sainsbury’s Supermarkets single duty, under which fitness for habitation sets the standard.
Ltd v Condek Holdings Ltd [2014] EWHC 2016 (TCC), In Thompson v Clive Alexander & Partners [1993] 59 BLR 77,
in which the court indicated that a claim by an employer it was held that allegations of defective work alone on the part of
against a construction professional appointed by the design an architect were not capable of amounting to a breach of the
and build contractor would rarely succeed. Act. It was held that the provision regarding fitness for habita-
7 An important factor to consider when analysing whether tion was the measure of the standard required in performance
a duty of care in respect of economic loss exists between of the duty pursuant to section 1(1), and that trivial defects
a construction professional and a non-client third party were not intended to be covered by the statute. In Harrison v
(say the contractor or a sub-contractor) are the terms of Shepherd Homes [2011] EWHC 1811 (TCC), Ramsey J found
the contract between the professional and his client (see, reluctantly that he was bound by the Court of Appeal’s decision
for example, Bellefield Computer Services Ltd v E Turner in Alexander v Mecouris [1979] 1 WLR 1270 to conclude that
& Sons Ltd) and the contractual matrix, generally (see there was a single duty. This approach restricts the potential
Henderson v Merrett, Riyad Bank v Ahli Bank and Galliford reach of the Act in the case of defective works, since fitness for
Try Infrastructure Ltd v Mott McDonald above). habitation is a high hurdle.
Nuisance 27

3.05 Notwithstanding these restrictions, it is likely that liability described at paragraph 4.04(a) above, damage is presumed once
under the Act will continue to be of significance for architects the encroachment is proved. In (b), there must be proof of actual
and other building professionals in the future. Although the deci- or prospective physical damage. Therefore, in both these cases,
sion in Murphy v Brentwood limited liability in negligence for the requirement of damage is an objective test which does not
pure economic loss caused to third parties by defective property, involve a further examination of the surrounding circumstances.
such pure economic loss is still recoverable under the Defective In nuisances of the kind at (c), however, there is no objective
Premises Act 1972. Typically, claims against architects involve standard applied by the courts. Whether the acts complained of
a large proportion of purely economic losses, therefore, in cases amount to the unreasonable use of land is a question of degree.
where there has been no assumption of responsibility, there may The nuisance needs to amount to a material interference with
still be a remedy under the Act. the use of other land that an average person (with no particular
susceptibilities or special interests) would consider unreasonable
in all the circumstances of the particular case. The essence of
4 Nuisance this kind of nuisance is something coming onto or encroaching
onto the claimant’s land (see Hunter v Canary Wharf Ltd [1997]
4.01 The tort of nuisance is concerned with the unjustified AC 655 and Anglian Water Services v Crawshaw Robins & Co
interference with a party’s use of land. Many activities can be [2001] BLR 173).
annoying to others, but whether they are actionable in law as a
nuisance depends, as in the case of the tort of negligence, on a 4.06 The duration and timing of the acts complained of is a rel-
consideration of all the circumstances of the case and the proof evant factor in this balancing of neighbours’ interests. So, too,
of consequential actionable damage. Although most nuisances is the character of the locality. In Sturges v Bridgman [1879]
arise out of a continuing state of affairs, an isolated occurrence 11 ChD 852 at 856, Thesiger LJ put it as follows:
can be sufficient if physical damage is caused.
whether anything is a nuisance or not is a question to be deter-
4.02 There are two varieties of actionable nuisance; public and mined, not merely by an abstract consideration of the thing
private. A public nuisance is one that inflicts damage, annoyance itself, but in reference to its circumstances: what would be a
or inconvenience on a class of persons or persons generally. It is a nuisance in Belgrave Square would not necessarily be so in
criminal offence and only actionable in tort if an individual mem- Bermondsey; and where a locality is devoted to a particular
ber of the public has suffered some particular kind of foreseeable trade or manufacture carried on by the traders or manufactur-
damage to a greater extent than the public at large, or where some ers in a particular and established manner not constituting a
private right has also been interfered with. The House of Lords public nuisance, judges would be justified in finding that the
has confirmed the existence of the common law crime of a public trade or manufacture so carried on in that locality is not a
nuisance in R v Goldstein [2006] 1 AC 459. Examples of public private or actionable wrong.
nuisances can include selling food unfit for human consumption,
causing dangerous obstructions to the highway, and (by way of 4.07 The conduct of the defendant may also be a relevant fac-
statutory nuisances) water and atmospheric pollution (see East tor. In Hollywood Silver Fox Farm Ltd v Emmett [1936] 2 KB
Dorset District Council v Eaglebeam [2007] Env LR D9). 468, the defendant maliciously encouraged his son to fire shot-
guns on his own land, but as near as possible to the plaintiff’s
4.03 A private nuisance is an unlawful act which interferes with a adjoining property in order to disrupt the plaintiff’s business of
party’s use or enjoyment of land or of some right connected with breeding silver foxes. Although the defendant was entitled to
it. Traditionally, interference with enjoyment of land in which shoot on his own land, the court held that he was nevertheless
the claimant had some kind of proprietary interest was one of creating a nuisance. The court held that the defendant’s intention
the defining characteristics of a private nuisance. However, in to alarm the plaintiff’s foxes was a relevant factor in reaching
Khorasandjian v Bush [1993] QB 727, a majority of the Court this conclusion, and specifically limited the injunction granted
of Appeal granted an injunction against the defendant to prevent against the defendant to prevent the making of loud noises so
him telephoning the plaintiff at her mother’s home (in which as to alarm the plaintiff’s foxes. Similarly, it is a nuisance if
she was staying as a mere licensee with no proprietary interest). people deliberately use their land in a manner which they know
This decision may, in time, be seen as the precursor of a wider will cause an unreasonable interference with another’s, whether
concept of actionable nuisance amounting to a general tort of or not they believes that they are entitled to do the act or have
harassment, and possibly the beginning of a tort of invasion of taken all reasonable steps (short of not doing the act itself) to
privacy. At present, however, it is submitted that the decision is prevent it amounting to a nuisance.
best seen as a narrow extension of the availability of an action in
private nuisance to interference with the enjoyment of premises 4.08 Traditionally, it was accepted that outside this kind of
at which the plaintiff lives, whether or not pursuant to a propri- conduct, nuisance had an uncertain overlap with the tort of
etary interest in the property itself. It is possible, however, that negligence. There were some situations in which it involved
the requirement for a claimant to have a legal interest in land negligent behaviour, and others where this was not considered a
before making a claim in nuisance may have been further eroded requirement for liability. As Lord Reid rather confusingly put it
by Article 8 of the Human Rights Act 1998 (see McKenna v in The Wagon Mound (No. 2) [1967] 1 AC 617:
British Aluminium Ltd, The Times, 25 April 2002 and Marcic v
Thames Water Utilities Ltd [2002] 2 All ER 55). It is quite true that negligence is not an essential element in
nuisance. Nuisance is a term used to cover a wide variety of
4.04 A private nuisance consists of a party doing some act tortious acts or omissions and in many negligence in the nar-
which is not limited to his own land, but affects another party’s row sense is not essential … although negligence may not be
occupation of land, by either: (a) causing an encroachment onto necessary, fault of some kind is almost always necessary and
the neighbouring land (for example, when trees overhang it or fault generally involves foreseeability.
tree roots grow into the neighbouring land); (b) causing physi-
cal damage to the land or buildings (such as when there is an 4.09 It is now established that liability in nuisance is not strict
emission of smoke or other fumes which damage his neighbour’s and that foreseeability of damage is a necessary ingredient
crops or property); or (c) causing an unreasonable interference (see Leaky v National Trust [1980] QB 485 and Arscott v Coal
with a neighbour’s enjoyment of his land (such as causing too Authority [2005] Env LR 6, CA). However, the requirement of
much noise or obnoxious smells to pass over it). foreseeability of damage does not necessarily imply the need
for negligent conduct, but may sometimes only be relevant to
4.05 The actual or prospective infliction of damage is a necessary what kind of damage will be actionable. Further, the concept
ingredient of an actionable nuisance. In a nuisance of the kind of ‘fault’ in nuisance is better viewed as unreasonable conduct
28 The English law of tort

(which is the essence of the tort), and may not always amount is the rule as stated by Blackburn J in Rylands v Fletcher [1866]
to negligent conduct (in the sense used in the tort of negli- LR 1 Ex 265 at 279:
gence. In Northumbrian Water Limited v Sir Robert MacAlpine
Limited [2014] EWCA Civ 685, the Court of Appeal set out We think that the true rule of law is that the person who for
three important principles that it derived from Cambridge Water his own purposes brings on his land and collects and keeps
v Eastern Counties Leather plc [1994] 2 AC 264 and Transco there anything likely to do mischief if it escapes must keep it
Plc v Stockport MBC [2003] 2 A.C. 1. The first is that although in at his peril, and, if he does not do so, is prima facie answer-
liability in nuisance has traditionally been regarded as strict, able for all the damage which is the natural consequence of
in the sense that it does not depend on proof of negligence, if its escape.
the defendant's user of his land is reasonable, he will not be
liable for interference with his neighbour's enjoyment of his 5.02 In the House of Lords, the rule was limited to apply only to
land. The second is that, unless the case can be brought within the ‘non-natural user’ of land. The courts have failed to clarify
the scope of the rule in Rylands v Fletcher, the defendant is precisely what non-natural user of land consists of and in what
not liable for damage caused by an isolated escape, i.e. one particular circumstances the rule should apply. However, it has
that is not intended or reasonably foreseeable. The third is that been applied to water, fire, explosives, poison, and, in Hale v
foreseeability of harm of the type suffered by the plaintiff is Jennings Brothers [1938] 1 All ER 579, to a seat becoming
necessary for the defendant to be liable in damages for nui- detached from a high-speed fairground roundabout. In general,
sance. Northumbrian Water’s claim failed because the escape the rule is applicable where a person brings onto his land some-
of concrete and the consequent damage to its sewer were thing that is ‘dangerous’, in the sense that if the thing escapes
unforeseeable. from the land, it would be likely to cause either personal or
physical damage.
4.10 Although, increasingly, the distinction between negligence
and nuisance has become blurred (and in practice they have to 5.03 There are various specific defences available to Rylands v
a large extent become assimilated), they are not synonymous in Fletcher liability, namely (a) that the escape of the dangerous
principle. The following points should be emphasised: (a) where thing was caused by an Act of God; (b) that it was caused by
the nuisance is the interference with a natural right incidental to the independent act of a stranger (though not an independent
land ownership (such as the right to obtain water from a well) contractor), or the claimant himself; (c) that the claimant has
then liability is strict; (b) the act complained of may constitute consented to the dangerous thing being kept on the defendant’s
the required ‘unreasonable user’ of land to constitute a nuisance land; and (d) that the dangerous thing has been stored pursu-
without necessarily amounting to ‘negligent’ behaviour; (c) ant to some statutory duty (in which case, negligence must be
economic loss is generally recoverable in nuisance; (d) some established on the part of the defendant).
kinds of damage recognised and protected in nuisance (such as
creating an unreasonable noise or smell, or harassment, such as 5.04 The tendency of the courts to adopt a restrictive interpre-
in Khorasandjian v Bush above) would not amount to action- tation of what was considered ‘non-natural use’ of land, and
able damage in the tort of negligence; and (e) the remedy of an therefore to limit the application of Rylands v Fletcher, was
injunction is available to prevent an anticipated or continuing considered in Cambridge Water Co. Ltd v Eastern Counties
nuisance, but not to prevent someone acting negligently. Leather plc [1994] 2 AC 264. In its first consideration of the rule
for over half a century, the House of Lords took the view that
the rule should be seen as no more than an extension of the law
5 The rule in Rylands v Fletcher of nuisance to cases of isolated escapes from land.

5.01 An example of strict liability in tort (which does not require 5.05 Although the House of Lords considered that the concept
the proof of negligence or intent on the part of the wrongdoer) of non-natural user had been unjustifiably extended by the
Limitation periods 29

courts, a restrictive interpretation of the rule was nevertheless liability for any breach of its provisions; (d) that on the balance
confirmed, as it found that foreseeability of harm of the relevant of probabilities his injury, loss or damage was caused by the
type was a prerequisite to liability under the rule (as in the case breach of statutory duty; and (e) that there has been a breach of
of nuisance). In an approach reminiscent of the House of Lords’ the relevant statutory duty by the defendant.
attitude in Murphy v Brentwood to economic loss, the imposition
of no-fault liability for all damage caused by operations of high 7.02 Some statutory duties are akin to the duty of care in the tort
risk was considered a more appropriate role for parliamentary, of negligence and are based upon what is considered to be rea-
not judicial, intervention. sonable behaviour in all the circumstances of the case. Others,
notably in the field of health and safety in the workplace, impose
5.06 As in the case of nuisance, it has been held that it is argu- strict liability for damage caused in certain circumstances. The
able that a claimant need not have a proprietary interest in Consumer Protection Act 1987, in response to an EEC directive,
the land affected to bring a claim under the rule in Rylands v even extended statutory strict liability in certain circumstances
Fletcher (see McKenna v British Aluminium Ltd, The Times, into the field of defective domestic consumer products (the very
25 April 2002). However, unlike the tort of nuisance, pure eco- area which gave birth to Lord Atkin’s ‘neighbour principle’ in
nomic losses are irrecoverable under this rule (see Anglian Water Donoghue v Stevenson).
Services v Crawshaw Robins & Co [2001] BLR 173 at para 149).
7.03 As far as architects are concerned, the most important
5.07 In Transco Plc v Stockport MBC [2004] 2 AC 1, the House statutory duties are those imposed by the Defective Premises
of Lords confirmed that the rule was still applicable. Lord Act 1972 (which has been discussed above) and the Occupier’s
Bingham defined the question as being whether the defendant Liability Acts of 1957 and 1984. These impose duties on the
has done something which he recognises, or ought to recognise, occupiers of land (which can include an architect, if supervising
as being quite out of the ordinary in the place and at the time a building project) in respect of consensual and non-consensual
when he does it. He thought, however, that little was gained (and visitors to the land, not unlike those owed at common law in the
unnecessary confusion perhaps caused) by considering whether tort of negligence. There is probably no automatic civil liability,
the use is proper for the general benefit of the community. The however, for breaches of the Building Act 1984 and its associ-
rule was applied in LMS International Ltd v Styrene Packaging ated Building Regulations.
& Insulation Ltd [2005] EWHC 2065 in a case involving the
escape of fire.
8 Inducing breach of contract/
6 Trespass wrongful interference
with contract
6.01 Trespass to the person involves an interference, however
slight, with a person’s right to the security of his or her body. 8.01 It is possible that in exercising a contract administration
It can be of three varieties: (a) a ‘battery’, which is caused by function (in certifying payments, for example) an architect could
unlawful physical contact; (b) an ‘assault’, which is where the be accused by a disappointed contractor (or conceivably, an
innocent party is caused to fear the immediate infliction of employer) of the tort of inducing a breach of contract or wrong-
such contact; and (c) ‘false imprisonment’, which involves the ful interference with contract.
complete deprivation of liberty without proper cause for any
period of time. 8.02 In order to succeed in such an action, a claimant would,
however, have to establish more than just an error or a neg-
6.02 The tort of trespass to land involves any unjustifiable entry ligent error in the certification process – it would need to be
upon land in possession of another, however temporary or minor established that the architect had deliberately misapplied the
the intrusion. It is also a trespass to leave, place or throw any- relevant provisions of the building contract with the intention
thing onto another party’s land, although if the material passes of depriving the contractor/employer of a benefit to which they
onto that party’s land pursuant to the defendant exercising his would otherwise have been entitled (see Lubenham Fidelities
own proprietary rights, it is a nuisance. Unlike nuisance or neg- & Investment Co Ltd v South Pembrokeshire District Council
ligence, trespass is actionable without proof of damage, although [1986] 6 Con LR 85).
if consequential harm or losses are thereby caused, damages are
recoverable. Ignorance of the law or the fact of trespass provides
no defence for a trespasser. 9 Limitation periods
6.03 As far as architects and building professionals are con- 9.01 To protect against the risk of stale claims being litigated
cerned, even the smallest infringements may be actionable. Thus, as a matter of public policy, the law imposes time limits within
setting foot without permission on land adjoining the property which causes of action must be commenced if they are to remain
where work is being conducted will constitute a trespass, as will actionable. The law aims to give claimants a reasonable opportu-
allowing equipment or other material to rest against, hang over, nity to bring claims, and defendants the assurance that the threat
fall upon or be thrown over adjoining land. However, it should of liability will not be eternal, and that any claim that they may
be emphasised that trespass is only a civil wrong which involves have to face will not be so old as to prejudice the fairness of
no automatic criminal liability in the absence of aggravating any proceedings. The two statutes that govern these time limits
circumstances (such as criminal damage). are the Limitation Act 1980 and the Latent Damage Act 1986.

9.02 For tortious actions, section 2 of the Limitation Act


7 Breach of statutory duty 1980 provides a prima facie limitation period of six years from
the accrual of the cause of action. However, in personal injury
7.01 Breach of a duty imposed by statute may lead to civil cases the period is three years. Therefore, when damage is an
liability in tort. There is a vast array of statutory duties covering essential ingredient in liability (such as in negligence), time
a wide variety of activities. In any particular case, however, in begins to run from the date that actionable damage occurs.
order to establish civil liability for breach of the statutory duty, If further damage occurs subsequently, then in respect of the
the claimant must prove: (a) that he is part of the class of persons additional damage, time will run from this later date. If there
intended to be protected by the statute; (b) that the loss or dam- is a trespass, libel, or other act which in itself amounts to an
age he has suffered is of a kind intended to be prevented under actionable tort, time begins to run from the date of the act itself.
the statute; (c) that the statute does not expressly exclude civil In the cases of continuing torts (such as nuisance or trespass),
30 The English law of tort

therefore, the limitation period begins on each repetition of the 9.08 In an architect’s negligence context, Ramsey J considered
wrong. In calculating whether the limitation period has expired, the issue in Oxford Architects v Cheltenham Ladies’ College
the date on which the cause of action accrues is normally [2006] EWHC 3156 and followed the Court of Appeal in Abbott
excluded, and the date on which the action is commenced is (above) in applying Pirelli. He gave the following example,
included. which made clear that the relevant date was the date of physi-
cal damage, even if it predated Practical Completion under the
9.03 However, these prima facie limitation periods may not building contract:
be applicable in certain exceptional circumstances. In relation
to personal injuries cases, section 33 of the Limitation Act It is convenient to take a simple example such as that in
1980 provides the court with a general discretion to disap- Abbott. An architect negligently designs a lintel. Before
ply the primary limitation period of three years if it considers Practical Completion it cracks. There is then relevant physical
it reasonable to do so. Further, section 32 provides that in a damage. The Architect issues an instruction to the contractor
case where either: (a) there has been fraud by the defendant; to remove the defective lintel and replace it with a new prop-
or (b) any fact relevant to the claimant’s cause of action has erly designed one. That will be a variation and the employer
been deliberately concealed from him by the defendant; or (c) will incur a liability to pay for remedial works. That will be
the action is for relief from the consequences of mistake, the economic loss, if indeed there has not already been such loss.
limitation period shall not begin to run until the claimant has If the Architect is negligent in reviewing the design at that
discovered this fraud, concealment, or mistake, or until he or stage then a new cause of action will accrue based on that
she could, with reasonable diligence, have done so. In building negligent review of the design.
cases, section 32 may become relevant where a party deliber-
ately conceals negligent design or construction work by building However, whatever the position in relation to economic loss,
over and hiding defects. following Abbott the relevant date is the date of physical dam-
age. Although an employer does not obtain possession of the
9.04 The common law rule that the cause of action in negligence building until Practical Completion, I consider that there is a
accrues when damage is caused creates serious difficulties in complete cause of action in negligence as against an Architect
construction cases. Often, damage which is caused in the process at that stage. The College could, for instance, have brought an
of building works is not discovered until some time after the action in negligence against the Architects for the allegedly
building is completed. However, in Pirelli General Cable Works negligent design during the course of the works to recover the
v Oscar Faber [1983] 2 AC 1, the House of Lords held that a additional sums which they were liable to pay the contractor
cause of action for negligent advice by an engineer in connec- in terms of remedial works or other costs.
tion with the design of a chimney accrued when damage, in the
form of cracks in the chimney, first occurred. The fact that they 9.09 As a result of tension between Pirelli and Murphy, this
may only become reasonably discoverable some time later was important area of the law is still in an unsatisfactorily unclear
held not to be relevant. This approach left open the possibility state. It is sensible for limitation purposes to assume that time
of claimants becoming statute barred before they had a means runs from physical damage.
of knowing that a cause of action actually existed.

9.05 The perceived injustice of this rule was addressed in the 10 Remedies
Latent Damage Act 1986. The Act modifies the limitation period
for claims other than for personal injuries in the tort of negli- 10.01 The principal remedies in tort are the provision of dam-
gence. The period should be either six years from the date that ages and the granting of an injunction. The general aim of an
the cause of action accrued (on the basis of the Pirelli test for the award of damages is to compensate the claimant for the damage
time of damage) or, if this expires later, three years from the time and losses sustained as a result of the tort. In principle, damages
the claimant knew certain material facts about the damage. This are intended to put the claimant into the same position as he
latter period is subject to a longstop provision expiring 15 years would have been in if the tort had not occurred. This restitution-
from the date of the negligent act or omission. ary principle is inappropriate where personal injury has been
caused, and so, in these cases, the courts apply a more general
9.06 Regrettably, this has not entirely clarified matters. There principle of what is fair and reasonable in all the circumstances.
remains the question of what constitutes damage in the first However, damages are recoverable only in respect of losses actu-
place. In Pirelli, the House of Lords decided (save, possibly, ally sustained, and the claimant is under a duty to mitigate his
in a case where a defect was so serious that the building was losses by taking all reasonable steps to limit them.
effectively predisposed to subsequent physical manifestation of
damage) that there was actionable damage only when there were 10.02 In addition, a claimant may recover damages only in
actual cracks in the chimney. The Court of Appeal confirmed the respect of losses that are reasonably foreseeable consequences
correctness of this approach, at least in cases where there is some of the defendant’s tort (reasonable foreseeability has already
physical manifestation of the relevant damage, in Abbott v Will been discussed in relation to the existence and breach of duty).
Gannon & Smith Ltd [2005] BLR 195. The difficulty with this Further, as also referred to above, the law does not always
proposition is reconciling it with the House of Lords’ decision recognise a duty of care to prevent certain kinds of loss (such
in Murphy v Brentwood. As we have seen, there, it was held as pure economic loss, or nervous shock, or embarrassment
that damage of the kind which occurred in Pirelli was really caused by an invasion of privacy). Thus, for all of these rea-
economic loss, not physical damage, and therefore no longer sons it is not unusual for a claimant’s actual losses suffered as
recoverable. However, their Lordships also, rather confusingly, a result of a tort to be greater than those that are compensated
approved the previous decision in Pirelli, which suggests that in law.
if there is liability in negligence for defectively constructed
buildings (which could now probably only be pursuant to a 10.03 The remedy by way of injunction is aimed at preventing
Hedley Byrne relationship, or one where damage is caused by a loss and damage, rather than compensating for it. It operates to
non-integral item in the building) the time for the accrual of the prevent an anticipated tort or restrain the continuance of one
cause of action for limitation purposes starts at the time physical (such as in the case of continuing torts like nuisance or trespass).
damage first occurs. An injunction will be available where the threatened tort is such
that the claimant could not be compensated adequately in dam-
9.07 In practice, in defective building cases, the courts have ages for its occurrence. Injunctions are of two varieties: first,
tended to apply this ‘manifestation of physical damage’ test for ‘prohibitive injunctions’, which order a party not to do certain
deciding when a cause of action in tort accrues. things that would otherwise constitute a legal wrong; second,
Conclusion 31

‘mandatory injunctions’, in which the court directs a defendant 11.03 Further, section 1 of the Civil Liability (Contribution) Act
positively to do certain things to prevent a tort being committed 1978 provides:
or continued.
Subject to the following provisions of this section, any person
liable in respect of any damage suffered by another person
11 Apportionment of liability may recover contribution from any other person liable in
respect of the same damage (whether jointly with him or
11.01 More than one person can be responsible for the same otherwise).
damage. Claimants are under a duty in tort to take reasonable 11.04 Thus, between themselves, defendants are also able to
care of their own safety. If the claimant is the only cause of apportion blame and restrict their relative contribution to the
the damage, then he or she will not succeed in a tortious action claimant’s damages. This may take the form of an apportion-
against another person. If the claimant and one or more other ment of blame at the trial of the matter or the commencement of
persons are at fault, then damages are apportioned, pursuant to separate proceedings (called Part 20 proceedings) by a defendant
the Law Reform (Contributory Negligence) Act 1945, accord- against another party who is said to be jointly or wholly to blame.
ing to the court’s assessment of the relative degree of fault of Of course, if two or more persons are responsible for the claim-
the parties. ant’s damage, the claimant may seek a remedy against either or
both of them under the doctrine of joint and several liability.
11.02 In assessing this relative responsibility, the court con-
siders both the causative potency of the parties’ actions (i.e.
how important was each party’s role as a matter of fact to 12 Conclusion
the ensuing damage) and their relative moral blameworthi-
ness (for example, if one party to a road traffic accident is 12.01 The above has, no doubt, given some indication of the
drunk at the time, that party is likely to be apportioned more complex ever-changing nature of the law of tort and its rel-
of the blame). Contributory negligence applies to liability in evance to the everyday activities of professional architects.
negligence, nuisance, the rule in Rylands v Fletcher, trespass, Unfortunately, given the restrictions on space, this chapter is
under the Occupier’s Liability Acts, and other breaches of unavoidably limited in its scope and introductory by nature. The
statutory duty. above is based upon the law as at 1 March 2019.
4
English land law
MARTIN DIXON

1 Land law and conveyancing ‘title register’ to land, the land registry can be checked online
by anyone for a very modest fee. Such a check is useful to
distinguished identify, for example, who owns a client’s land or neighbouring
land before detailed work is undertaken. In due course, many of
1.01 This chapter is intended to give an impression of those the aspects of the conveyancing process will be accomplished
aspects of land law that are relevant to architects, either in paper-free and electronically.
their professional capacity as designers of buildings for clients,
as tenants of their offices or as prospective purchasers of land
for redevelopment. At the outset, however, it is necessary to Title to land
distinguish ‘land law’, as such, from ‘conveyancing’. Land law 1.03 Title to land in England and Wales is either ‘unregistered’
is concerned with the rights of a landowner in, or over, his own or ‘registered’, although the latter is now far more common and
land, and also with the rights that others may have over that is the norm. Registered land now comprises over 85% of all
land. The landowner’s right of ownership of their land is often land by area. With effect from 1 December 1990, all land (or
expressed by saying that they have an ‘estate’ in the land (i.e. more accurately, title to land) in England and Wales must be
a ‘title’, which may be either freehold or leasehold), while the ‘registered’ consequent on a dealing with it, such as a transfer of
rights of others in that land (or technically, in that ‘estate’) are ownership or a mortgage or the granting of certain leases. After
often described by saying that they have ‘proprietary interests’ this ‘first registration’, the title remains registered in all circum-
(‘property interests’ or just ‘interests’) in it. By way of contrast, stances and for all future transactions. Thus, ‘unregistered title’
the law of conveyancing is concerned with the mechanics of the will largely disappear over time, save for those parcels of land
creation and transfer of estates and interests in and over land, where ownership may never be transferred or voluntarily regis-
usually, but not necessarily, pursuant to a contract between a tered (e.g. church land, some local authority land, some Crown
seller and purchaser. Typically, an owner of an estate in land land). The Land Registry estimates that virtually all transferable
(being either ‘the owner’ under a freehold or lease) will transfer titles will be registered by 2021, and today, unregistered land is
that estate to a purchaser, with the sale/purchase being subject found usually only in rural areas or with land that has not been
to existing interests in the land and, possibly, creating new ones. dealt with for many years. The Land Registration Act 2002 has
An architect need not concern himself with the procedures and greatly speeded up the process of registration, and owners of
mechanics of conveyancing, for in the normal course of events, substantial parcels of land – such as local authorities – are being
such matters will be entrusted to a property professional such as encouraged voluntarily to first register their land (that is, without
a solicitor or licensed conveyancer. Indeed, it would be impru- there being any dealing with it), and many are taking advantage
dent to attempt a conveyancing transaction without professional of lower fees and free assistance from the Land Registry. For
advice. Nevertheless, a certain amount must be said about title the architect, as with others interested in the precise details of
to land in England and Wales (being estates) and the methods land ownership and the existence of obligations affecting land,
that exist to protect other persons’ property interests in that land. the achievement of widespread registration of title greatly assists
the development process.
1.02 Many of the concepts that underlie English land law are
ancient, and this is reflected in the curious terminology that 1.04 For the moment, however, some land of unregistered title
is associated with the subject. However, the law was greatly still exists, and a brief understanding of it is required. Architects
simplified and restructured in 1925 by a series of important may well find themselves being asked to deal with derelict or
statutes. These, and later statutes building on them, form the dilapidated land, and there is a chance that this will be unreg-
foundation of modern land law and, generally, were designed to istered if it has not been dealt with prior to 1 December 1990.
facilitate the easy transfer of land so that it could be used to its In unregistered conveyancing – being land where the title is not
full economic potential. As part of this continuing development, recorded on a register maintained by HM Land Registry – the
a major reforming statute came into force on 13 October 2003; landowner will be either a freeholder or a leaseholder: i.e. have
the Land Registration Act 2002 has replaced, in full, the Land the equivalent of near absolute ownership (freehold: the owner-
Registration Act 1925. Although primarily designed to simply ship of mines and minerals, for example, might be with another),
the conveyancing process, the Land Registration Act 2002 also or have such ownership for a precise amount of time under a
simplifies the methods by which rights in or over land are ‘regis- lease from the freeholder (e.g. a 125-year residential lease of an
tered’ in an online, fully searchable land register administered by apartment flat). On the sale of the freehold, or upon an assign-
HM Land Registry. Although professional advice should always ment (sale or transfer) of a lease, the seller’s proof of title is
be sought to appreciate the importance of matters entered on a found in the title deeds to the property (which may be held by

33
34 English land law

a lender if there is a mortgage) and the purchaser’s solicitors 1 Where the equitable interest over the land about to be pur-
will investigate these title deeds to satisfy themselves on behalf chased qualifies as a ‘land charge’ under the Land Charges
of their client that the seller does indeed have title to the land. Act 1972, and the interest is registered as a land charge
The purchaser’s solicitors will investigate and verify all dealings in the appropriate manner. This system of registration is
with the land revealed by these deeds going back to the first entirely separate from that pertaining to registered land.
valid conveyance of it more than 15 years old. That conveyance It means that if the equitable interest is a land charge (and
is known as ‘the root of title’ and is the proof of title required this is defined in the Land Charges Act 1972) and is not
by the purchaser (Law of Property Act 1969, section 23). In registered, it cannot affect a purchaser of the land even if
addition, a physical inspection of the land is always desirable he or she knew about it, provided no fraud is involved.
in order to discover any other person’s interests in the land that 2 Where the equitable interest over the land about to be pur-
might not be revealed by the title deeds: e.g. ancient rights of chased does not qualify as a land charge, the purchaser is
way, shared sewers, rights of light, etc. So, with unregistered bound only if he or she had ‘notice’ of the equitable interest.
land, the title of the vendor will be investigated (by documentary Such notice may be ‘actual’ (as where the purchaser is told
and physical inspection), a root of title produced, and, following or sees that an equitable interest exists), ‘constructive’ (as
a successful completion of the sale, the purchaser’s solicitor will where a reasonable purchaser would have realised from the
apply for ‘first registration’ of title. Thereafter, the land becomes available facts that such an interest existed: e.g. a path is
and remains registered land. visible) or ‘imputed’ (as where the purchaser’s agent (i.e.
solicitor) has actual or constructive notice). In the absence
1.05 Other persons’ rights in unregistered land (i.e. interests) of such notice, the purchaser cannot be affected by the
are either ‘legal’ or ‘equitable’ in character. This distinction was equitable interest and may use the land without regard to it.
once of great significance, and although it is now unnecessary to Note, however, that the number of equitable interests that
explain in detail why some rights are ‘legal’ and some ‘equita- depend on the ‘doctrine of notice’ for their validity against a
ble’, its origins lay in the type of interest at issue and the manner purchaser is very limited. The majority of equitable interests
in which the interest was first created. Fortunately, usually it qualify as ‘land charges’.
will be readily apparent whether any given interest in the land is
‘legal’ or ‘equitable’. The relevance of the distinction today lies
in the effect that legal or equitable interests in unregistered land
Land charges under the Land
have when the title (the freehold or leasehold estate) to that land Charges Act 1972
is transferred to another person, such as on sale. So, legal rights 1.06 As noted above, most equitable interests in unregistered
are ‘binding on all the world’, regardless of whether a purchaser land are registrable as land charges under the Land Charges
of land (freehold or leasehold) knows of them or not. This means Act 1972. This has nothing to do with registered land, although
simply that a purchaser of the land (or any new owner) is bound the land charge registers are maintained by HM Land Registry.
to give effect to the interest. Most easements (such as a right of Some of the most important of these registrable equitable inter-
way or right to light) and most mortgages are legal rights, and ests from an architect’s point of view are:
a purchaser of unregistered land cannot escape them by saying
that he or she did not know of their existence, even if they were 1 Estate contracts: i.e. contracts for the sale of land or of any
not discovered from the title deeds or inspection of the land. interest in land, including contracts to grant leases, options
By contrast, equitable rights are binding on a purchaser only in to purchase land (i.e. a standing offer by a landowner to
certain circumstances, although they will always be binding on sell), and rights of pre-emption (i.e. rights of first refusal
a person who received land by way of gift or under a will. The should a landowner decide to sell).
circumstances in which equitable interests over unregistered land 2 Restrictive covenants (being promises not to use the land
will bind a purchaser are either: for certain purposes, such as building, or trade, or business
Land law and conveyancing distinguished 35

and see paragraph 4.01 below), except those found in a lease Freeholds and very many (but not yet all) leaseholds may
(for which special rules exist) and those entered into before be registered as titles. As long as the land is registered, and
l926 (to which the law of ‘notice’ applies). the postcode or address is known, it is now possible for
3 Certain types of easement (such as rights of way or light), any person to do an online search of the land register for
being those not originally created by a deed (a formal a nominal sum (https://www.gov.uk/search-property-infor
document) or those that endure only for the life of a given mation-land-registry), which will reveal the name of the
person. Note, however, that most easements are created owners, the existence of any mortgage, some (but not all)
by deed and are therefore ‘legal’ and are effective without other interests affecting the land, and often the price paid
registration. by the current owners.
2 The Register of Title is conclusive as to the nature of the
Registration of these land charges ensures that the interest will title to the land and the title is guaranteed by the indemnity
be enforceable against all persons who come into possession or (compensation) provisions of the system. There is no need
ownership of the unregistered land, regardless of any question to check the title deeds (which may well no longer exist)
of notice. If the interest is registrable but not actually regis- and the doctrine of notice and the idea of land charges have
tered, it will be void (i.e. unenforceable) against purchasers of no application. If, for any reason, the Register is not a true
the land, regardless of whether they know of it. This will be so reflection of the title (that is, there has been some mistake
even if the sum paid by the purchaser is only a fraction of the leading to the registration), it may, in certain limited cir-
true value of the property (Midland Bank Trust Co. Ltd v Green cumstances, be ‘altered’ on application to the Registrar or
[1981] AC 513). Land charge registration suffers from a serious the court, but the circumstances in which this is permitted
defect in that registration of the charge is not made against the are narrowly drawn. Any person suffering loss as a result
land itself, but against the name of the landowner who created of a qualifying alteration (called a ‘rectification’) may be
the charge, even if that was many years ago. Consequently, entitled to compensation out of public funds. This is an
in order to search the Land Charges Register (e.g. to find any insurance system, and fault does not need to be proved.
binding interests before completing a purchase), it is necessary Note also that, because it is the Register of Title itself that
to discover the names of all the persons who have owned the is conclusive, if an erroneous Search Certificate is issued
land. This is done by looking at the title deeds. However, it is that fails to disclose an entry on the Register, a purchaser
only obligatory for the seller to provide the title deeds back to will still be bound by the interest protected by the entry,
a good root of title, which may be only 15 years old. It is often although they may be entitled to an indemnity because of
impossible, therefore, to discover the names of all relevant land- the mistake. Such errors are very rare, and architects should
owners (i.e. going back to 1925, when land charge registration be aware that if there is a mismatch between the register of
was introduced). Nevertheless, because registration of the land title and a client’s understanding of what ‘their’ land is, or
charge ensures that it is binding, purchasers will still be bound their rights over someone else’s land, it is the register that
by it, even though they could not have discovered it because prevails.
they did not know the name against which to search! Under the 3 An intending purchaser of registered land (including a per-
Law of Property Act 1969, compensation is payable for any loss son proposing to take a significant interest in the land, such
suffered in these cases. It is worth remembering that any person as a bank lending on mortgage or a person paying for an
may search the Land Charges Register, and that an Official option to purchase) will take the following steps:
Certificate of Search is conclusive in favour of a purchaser, (a) Inspect the Register. The Register of Title is a public
actual or intending, and this will be useful in respect of potential document and may be inspected by any person on pay-
development projects. There is, in addition, one clear advantage ment of the appropriate fee. This may be done infor-
in undertaking a search of the land charges register: a Certificate mally online, as noted above, but an Official Search
of Search is conclusive. Thus, if a Certificate of Search does not should be obtained before any offer to purchase or lend
reveal a registered land charge, the purchaser will take free of it, is made or any contract signed. Usually, the property
provided that he or she searched against the correct name, even professional employed by the purchaser/transferee will
if the charge was actually registered. Note also, as mentioned obtain the Official Search. Of course, architects may
above, that even an unregistered land charge (i.e. one that should identify owners of land for themselves even if the land is
have been registered but is not) is enforceable against someone not yet up for sale (e.g. as having development potential)
who is not a purchaser. Thus, a person receiving the land by gift, by means of the online search process.
or under a will, or even a squatter, is bound by all land charges (b) Inspect the land itself, because the Register is not con-
– registered or not. clusive on all matters. Certain rights – called ‘interests
that override’ – will not appear on the Register, but they
are automatically binding on any transferee of the land
Registered land (including a purchaser) by force of statute, irrespec-
1.07 Registered land is quite different from land of unregistered tive of whether the transferee knew about them. These
title, and the overwhelming majority of titles now fall within the include certain types of legal easements, legal leases of
system of registered land. In a relatively short time, registered 7 years or less, local land charges (see paragraph 1.08
land will be the only type of land that is commonly transferred below) and the rights of persons (including squatters)
by sale or gift or on death. It has many advantages over unregis- in actual occupation of the land (provided the actual
tered land in terms of certainty about estates and interests in the occupation is discoverable on a reasonable inspection
land and in respect of ease of transactions. The system is now of the land or the interest of the occupier is known of
governed by the Land Registration Act 2002. by the transferee). The existence of ‘overriding inter-
ests’ can be a trap for the unwary because a person may
1 The actual title (the ‘estate’) to the land is itself registered gain protection, in the sense of being able to enforce
and identified by a unique title number, eliminating the need their interest against a transferee, by virtue of being in
for title deeds. The only significant exception are ‘short’ ‘discoverable actual occupation’ of the land over which
leases, being leases for seven years or less that are not cur- the right exists: Williams & Glyn ’s Bank Ltd v Boland
rently registered as titles (although they are still perfectly [1981] AC 487. Consequently, a proper inspection of
valid). Details of most (but not all) interests affecting the the land is vital, and questions should be asked of any
land will also appear on the Register, and such ‘encum- person who is, or appears to be, in occupation of the
brances’ are registered against the title itself and not against land. An intending new owner should not assume that
the name of the landowner at the time the encumbrance was those persons currently occupying the land will be con-
created. Transfer of the land is effected by registering the tent to vacate. If necessary, the written consent of such
purchaser or transferee as the new ‘registered proprietor’. persons to the proposed transaction should be obtained,
36 English land law

and this should be a matter of priority for the property minerals under his land, although all gold, silver, coal and
professional engaged to manage the transaction. The petroleum are vested in the Crown and certain other mineral
consequences of failing to do this can be fatal to any rights (e.g. shale gas deposits) might be vested in a former
proposed development of the land. owner depending on how the land was first conveyed.
4 Rights above the land to such height as is necessary for
Local land charges the ordinary use and enjoyment of land and the structures
upon it (Baron Bernstein v Skyviews & General Ltd [1978]
1.08 Irrespective of whether the land is registered or unregis- QB 479 at 488). Thus, the flight of building cranes over a
tered, there are certain rights that are registrable quite separately neighbouring property may be a trespass, and this should be
in a register kept by all local authorities (e.g. District Councils remembered when considering developments requiring such
and Unitary Authorities). Starting in the summer of 2018, machinery.
responsibility for administering these local registries is being 5 Intangible rights, such as easements (e.g. such as rights of
transferred to HM Land Registry, and this will streamline the way or rights to light), profits (such as a right to take fish or
system when it is complete. The matters entered on these reg- fruit from another’s land), and restrictive covenants (rights
isters are known as ‘local land charges’, and they are regulated to prevent activities on another’s land).
by the Local Land Charges Act 1975, which came into force
in 1977. These charges are registered by reference to the land
which they affect and not against the name of the landowner, Trespass
and should not be confused with land charges under the Land 2.02 Any unjustifiable intrusion (i.e. without permission or with-
Charges Act 1972. Registration of a local land charge constitutes out right) by one person upon ‘land’ in the possession of another
actual notice of it to all persons for all purposes. A local land is a trespass – a ‘tort’. It is likewise a trespass to place anything
charge is, however, enforceable even if not registered, but a on or in the land in the possession of another (e.g. by driving
purchaser of land burdened by an unregistered local land charge a nail into his wall or propping a ladder against his house). It
will be entitled to compensation from the local authority. Local is a popular misconception that to be actionable as a tort, the
land charges are numerous and of considerable practical impor- trespass must involve damage to the claimant’s property. Even if
tance. A search of the local land charges register is vital before no damage is done, the court may restrain the trespass by injunc-
proceeding to deal with the land, either by way of purchase or tion, binding immediately. See, for example, Anchor Brewhouse
development. They include: Developments Ltd v Berkley House (Dockland Developments)
Ltd [1987] 2 EGLR 173, where the trespass arose out of building
1 Preservation instructions as to ancient monuments. works on land adjacent to that of the claimant. Consequently,
2 Lists of buildings of special architectural or historic interest. if construction work is likely to necessitate an incursion on
3 Planning restrictions. to neighbouring land in some way – e.g. to erect scaffolding,
4 Drainage schemes. inspect drains, or because a crane jib will swing over that
5 Charges under the Public Health and Highway Acts. land – then the client must come to an arrangement with the
neighbouring landowner, unless the client can prove some right
1.09 As a matter of general good practice, architects will be to enter on the land (such as under the Access to Neighbouring
well-advised to find out from the client what adverse rights (if Land Act 1992). Such permission will usually take the form
any) affect the client’s property before undertaking any scheme of a ‘contractual licence’, being a temporary permission, often
of work. It is particularly important that they discover the granted in return for a payment or other consideration (paragraph
existence of any easements, restrictive covenants, or local land 2.04). But if a permanent incursion is contemplated – e.g. by
charges, because these may significantly affect a development the overhanging eaves of a building, the footings of a garage,
plan. For example, the existence of a neighbour’s right to light or or the line of a boundary wall – it may be better to negotiate an
right of way, or ability to enforce a building restriction (a restric- easement (see paragraph 3.01).
tive covenant), can radically affect any plans for development,
as might any local land charges registered against the land. If 2.03 In the absence of any easements, restrictive covenants, or
necessary, the client may have to engage the services of a prop- other binding agreements (e.g. a contract between landowner and
erty professional to make the relevant enquiries. Importantly, the neighbour), a person is generally free, as a matter of private law,
grant of planning permission does not take priority over these to build anywhere on his own land. Necessarily, of course, there
interests, and a client may be prevented from developing their may be planning issues and other related matters that restrict
land by these encumbrances even if the development is author- this in practice. Note, however, that in some circumstances, the
ised by planning permission. Ignoring such restrictions can be process of development may give rise to a claim by a neighbour
very expensive: see The Alexander Devine Children's Cancer in ‘nuisance’, such as where there is an unjustifiable interfer-
Trust v Millgate Developments Ltd. and Housing Solutions ence with a neighbouring landowner’s use and enjoyment of his
Ltd. [2018] EWCA Civ 2679, where a developer was ordered own land through excessive noise or dust (see Hunter v Canary
to demolish a block of thirteen affordable properties for which Wharf Ltd [1997] AC 655).
planning permission existed, but which had been built in viola-
tion of a neighbour’s restrictive covenant.
Licences
2.04 As noted above, a neighbour may give another person per-
2 The extent and meaning of mission to use his land by means of a ‘contractual licence’, and it
‘land’ and intrusions upon it is convenient at this point to discuss licences generally. A licence
is permission to do something on land that would otherwise be
2.01 ‘Land’ in English law includes not only the soil, but also: a trespass. For example, in the absence of an easement of way,
a contractual licence permitting the passage and re-passage of
1 Any buildings, parts of buildings, or similar structures. construction traffic over neighbouring land might be required for
2 Anything permanently attached to the soil (so-called, some developments. There are several types of licence, of which
‘fixtures’ [see paragraph 5.03], which may include garden only two need be considered here. First, there is a ‘bare licence’,
plants, greenhouses, and even garden statues). i.e. permission to enter land, given quite gratuitously without
3 Rights under the land. It has never been settled how far any counter-benefit for the landowner giving the permission. It
down the rights of a landowner extend, though it is com- is revocable at any time by the licensor/landowner and, on such
monly said that they extend to the centre of the earth. revocation, the licensee becomes a trespasser, although the licen-
Certainly they go down as far as the limits of economic see is entitled to a reasonable time to enable him or her to leave
exploitation. A landowner is therefore entitled to the the land once notice of termination has expired. The second type
The extent and meaning of ‘land’ and intrusions upon it 37

of licence is the contractual licence mentioned above. This is a 1 KB 666), they do not purport to fix the exact boundary.
licence that is granted for some counter-benefit, usually a fee. Where the ‘plan line’ is for purposes of identification only,
Whether a contractual licence can be revoked depends upon the topographical features and other evidence may be used to
interpretation and meaning of the contract under which it was find the exact line. Likewise, Ordinance Survey maps do
given. If a licence is either expressly, or by necessary implica- not purport to fix private boundaries and it is the practice of
tion, irrevocable during its agreed duration (e.g. the erection of the Survey to draw the boundary line down the middle of a
scaffolding on a neighbour’s land for 6 months), the licensor boundary feature (e.g. down the middle of a ditch) regardless
will be unable to prevent the licensee from going on to the land of where the boundary line actually runs in law. If the title
for the purpose of the licence. Any attempted revocation of the deeds do refer to an Ordinance Survey map, then that map
licence can be prevented by the grant of an injunction or, in will be conclusive in so far as it defines the general bound-
appropriate circumstances, by a decree of specific performance, ary. Again, however, unless the context makes clear, this
that is, an order forcing the licensor to permit the licensee to may simply indicate the general line, not its precise course.
enter (Verrall v Great Yarmouth Borough Council [1981] QB In the case of registered land, the plans used by the Land
202). If a licence is silent as to the duration or terms on which Registry are based on the Ordinance Survey maps, but once
it can be revoked, a court may supply such terms as is reason- again, the boundaries on them are regarded as general and
able, having regard to the circumstances in which the licence are not intended to be fixed precisely by the plan. A little-
was granted (Parker, the 9th Earl of Macclesfield v Hon Jocelyn used procedure – unlikely to gain popularity even under the
Parker, 2003). Importantly, a licence is personal to the land- new law – exists by which the boundary of registered land
owner who gives it: in other words, if the land changes hands, may be defined exactly, and where this has been done, the
the licence will not continue unless the new owner re-gives it plan on the Register is clearly noted as being definitive.
expressly or by necessary implication. Being personal, licences (c) A boundary of unregistered land may be proved by show-
are never land charges (unregistered land) or entered on the title ing 12 or more years’ undisturbed possession of the land
of registered land (registered title). Consequently, an architect enclosed by the boundary. This may extend to possession
should not assume that a licence will continue if there is a of a boundary wall (Prudential Assurance v Waterloo Real
change in ownership of the land to which it relates. Estate [1999]).
(d) A boundary of registered land may be proved by showing at
least 10 years’ undisturbed possession of the land enclosed
Easements by the boundary, but such boundary is only conclusive when
2.05 If a landowner has an easement over adjacent land – such an application is made to the Land Registry and the register
as a right of way – any interference with it by the owner of the of title is amended accordingly. This may extend to posses-
burdened land (the ‘servient’ land) will not constitute a trespass, sion of a boundary wall (Prudential Assurance v Waterloo
but will be a ‘nuisance’. However, not every interference with an Real Estate [1999]). Such an application may, of course,
easement will amount to a nuisance. If the easement is a positive precipitate a dispute with the person who is currently reg-
(or ‘active’) one, being one which allows the person entitled istered as owner of the land.
to the benefit of it to do something on the burdened land (e.g.
to use a right of way by foot or vehicle), the interference will
constitute a nuisance only if it prevents the practical and sub-
2 Orders of competent authorities
stantial enjoyment of the easement. If the easement is negative Establishment of boundaries by orders of statutory authorities is
(or ‘passive’), being one which allows the person entitled to the now largely historical. Under the Enclosure Acts, the Tithe Acts,
benefit of it to prevent the use of the burdened land in a certain and certain Agricultural Acts, awards defining precise boundaries
way (e.g. a right of light, being the prevention of building), the could be made. These may still be relevant in some rural areas.
interference will be actionable only if it substantially interferes Similarly, of course, a boundary may be fixed by judicial deci-
with the enjoyment of the right. (On positive and negative ease- sion, e.g. in an action for trespass or for the recovery of land or
ments, see paragraph 3.03.) in respect of adverse possession.

Boundaries 3 Legal presumption


2.06 A boundary has been defined as an imaginary line that In the absence of clear definition by the above methods, certain
marks the confines or line of division of two contiguous parcels rebuttable presumptions apply, being ‘default’ rules that will
of land (Halsbury’s Laws of England [4th edn], vol. 4, paragraph operate unless contrary evidence is available.
831). Boundaries are fixed in one of three ways: (a) by proven
acts of the respective owners; (b) by statute, or by orders of (a) Hedges and ditches. It is presumed that a person excavating
authorities having power to do so; or (c) in the absence of either a ditch will not dig into his neighbour’s land, but that he
of these, by legal presumption. Note, however, that as Lord will dig at the very edge of his own property, making a bank
Hoffmann said in Alan Wibberley Building Ltd v Insley (April on his side of the ditch with the soil that he removes. On
1999), ‘[b]oundary disputes are a particularly painful form of top of that bank, a hedge is usually planted. He is, therefore,
litigation. Feelings run high and disproportionate amounts of owner of both the hedge and the ditch. This presumption
money are spent’. While it is true, therefore, that the law on applies only where the ditch is known to be artificial, but
boundaries should be as clear as possible, the best approach is it is readily applicable in cases of doubt, including cases
to agree matters such as the precise line of a boundary before where reference is made to a plan or Ordnance Survey map
development takes place and thus avoid resort to law. defining general boundaries (Alan Wibberley Building Ltd
v Insley [1999]).
(b) Fences. It is said that there is a presumption that a wooden
1 Proved acts of the parties fence belongs to the owner of the land on whose side the
(a) The parties may expressly agree on the boundaries. This is posts are placed, on the basis that a landowner will use
by far the best approach, particularly where new develop- his land to the fullest extent (and display the better side of
ment is concerned. It is best to have the agreement formally the fence to his neighbour!). Likewise, it is often said that
drawn up by a solicitor or licensed conveyancer. nails are ‘driven home’. These presumptions are, however,
(b) The boundaries may be defined by the title deeds. These may, unsupported by authority and must be regarded as uncertain.
in turn, refer to a plan or to an Ordinance Survey map. As Most modern plans mark the fence owned by the property
far as plans are concerned, the boundary lines are usually in question by the indication of a ‘T’ on the plan.
‘for the purposes of identification only’ and, unless the con- (c) Highways. The boundary between lands separated by a
text makes clear (as was the case in Fisher v Winch [1939] highway or a private right of way is presumed to be the
38 English land law

middle line of the highway or private right of way. There village is unlikely to enjoy an easement of way over land at
is no such presumption with railways. The bed of a railway the other. In addition, the use must be related to the land or
will be the property of Network Rail, or its successors. an activity connected with the land itself, bearing in mind
(d) The seashore. The boundary line between the seashore and the normal use of the land (be it residential, commercial,
the adjoining land is (unless usage to the contrary is proved) or agricultural). Personal benefits cannot be easements,
the line of the median high tide between the ordinary spring although the issue is fact-dependent (see Regency Villas
and neap tide (Attorney General v Chambers [1854] 4 De Title Ltd v Diamond Resorts (Europe) Ltd [2018] UKSC
GM & G 206 at 218). Prima facie, the seashore belongs to 57), and the wisest course is to seek advice to see if a use
the Crown, although rights for private individuals to utilise is, or could be, an easement in law.
the seashore can exist by grant or historic long use (Lynn 3 The two tenements must not be owned and occupied by
Shellfish Ltd v Loose [2016] UKSC 14). the same person. Hence, a tenant can have an easement
(e) Rivers and streams. If a river or stream is tidal, the soil of over land occupied by his landlord, because although both
the bed of the river or stream belongs to the Crown, or the tenements are owned by the same person, they are not also
Duchies of Cornwall or Lancaster, where appropriate. As a occupied by him.
general rule, the boundary between the bed of a tidal stream 4 The easement claimed must be ‘capable of forming the
and adjoining land is the line of medium high water mark. If subject matter of a grant’, i.e. of being created by deed.
the river or stream is non-tidal, it is assumed that adjoining This means that the right alleged to be an easement must
owners own land to the middle of the flowing water, known be sufficiently well defined, certain, and limited in scope
as the ‘thalweg’ (although this may not be the middle of the to qualify as an easement. So, although there are well-
river itself). established categories of easements – rights of way, rights
(f) Walls. If the division between two properties is a wall, and to light, rights of support – the list is not closed. New rights
the exact line of the boundary is not known, in determin- can become recognised as being capable of being ‘granted’,
ing the ownership of the wall, certain presumptions apply. hence, of being easements. Modern examples include the
Party walls outside London and Bristol (for the situation in right to use a letterbox, the right to park a car on adjoining
London and Bristol, see Chapter 14) are subject to rights at land and cross it with shopping trolleys, the right to locate
common law. The usual, but by no means necessary, pre- a television aerial (and hence a satellite dish) on a neigh-
sumption is that the party wall is divided longitudinally into bour’s land, the right to display signs, the right to moor
two strips, one belonging to each of the neighbouring own- boats, the right to use paths in a park for pleasure and not
ers, but where each half is subject to a right (an easement) simply for getting from one place to another, and, in some
of support in favour of the other. If one owner removes circumstances, a right to use recreational facilities such as a
his building, he is obliged to waterproof the exposed party golf course. Against this, certain rights cannot exist as ease-
wall. (See Chapter 14 for the complicated procedures nec- ments: e.g. a right to a view; to privacy; to a general flow
essary when changes to party walls are contemplated in of air (as distinct to a flow through an air duct); to have a
London.) Extensions to existing buildings can bear only on property protected from the weather; and a general right to
the half of the wall belonging to the owner of the building light (as opposed to as right through a defined aperture).
being extended, unless the consent of the adjoining owner
is obtained. Note also that a former party wall can come 3.03 It is often said that easements may be either positive or
under the exclusive ownership of one of the neighbours, negative, although there is no consequence in the distinction. A
consequent upon the relevant period of undisturbed adverse positive (or ‘active’) easement is one which enables the domi-
possession, plus registration, in the case of registered title. nant owner to do some act upon the servient tenement, e.g. walk
or drive along a right of way. A negative (or ‘passive’) easement
allows the dominant owner to prevent the servient owner from
3 Easements doing something on his land, e.g. a right to light, which restricts
the servient owner’s ability to build. Some easements do not
3.01 Easements are rights that one owner of land may acquire readily fall into either category, e.g. a right of support for a
over the land of another. They should be distinguished from building, and the distinction is merely descriptive.
other similar rights such as (i) profits, i.e. rights to take some-
thing from another’s land, e.g. to cut grass or peat, or to shoot 3.04 Easements may be acquired in a number of ways:
or fish; (ii) natural rights, e.g. rights of support of land (but not
of buildings as that is a true easement); (iii) public rights, e.g. 1 By express grant or reservation. A landowner may, by deed
rights of way over a highway or rights of common; (iv) restric- (or written contract if the easement is to be equitable),
tive covenants (paragraph 4.01); and licences (paragraph 2.04). expressly grant an easement over his land in favour of a
neighbouring landowner. Equally, if a landowner is selling
3.02 The essentials of an easement are: off part of his land, he may expressly grant an easement in
the purchaser’s favour (burdening the land he retains), or
1 There must be a dominant and a servient tenement, where expressly reserve to himself an easement (burdening the
a ‘tenement’ is a plot of land held by a freeholder or lease- land sold) in the documents that carry out the sale. Both
holder. The dominant tenement is the land benefited by the express grant and reservation are common when a plot is
easement, and the servient land is the land burdened. Note, divided into sub-plots and sold to different purchasers, as
therefore, it is impossible for someone occupying land as with a green-field housing development. The Land Registry
only a mere licensee to be party to the creation of an ease- is willing to offer advice to persons developing large estates
ment (although a licensee may utilise, or be subject to, as to the most effective way of expressly creating easements
an existing easement as agent of the dominant or servient over the sub-plots as they are sold or leased.
owner, as the case may be). Consequently, a developer seek- 2 By implied reservation. This occurs when the parties to a
ing an easement over neighbouring land should ensure that transaction concerning land (e.g. a sale or lease) have not
they are dealing with the freehold owner. If the occupier is expressly mentioned easements in the documents carrying
a tenant, any easement they grant is likely to last only for so out the transaction. So, if a landowner sells off part of his
long as their own tenancy and is unlikely to be permanent. land and retains the rest, he may fail to reserve expressly
2 The easement must benefit (or ‘accommodate’) the domi- any easements burdening the part sold (for the benefit of
nant tenement to which it will become attached. So, the part he retains). However, in two situations, easements
although the two plots need not be contiguous or adjacent, may be implied in his favour – meaning that they will be
they must be sufficiently close for the dominant tenement to treated as if they were deliberately reserved for the benefit
be benefited by the easement. A landowner at one end of the of the land retained. These are easements of necessity and
Easements 39

easements necessary to give effect to the common inten- of occupation’ – meaning that the owner occupied one
tions of the parties. An easement of necessity in this context part and a different person occupied another part, per-
means an easement without which the vendor’s retained haps under licence – it seems that the alleged right does
land cannot be used at all. For example, if he retains land not have to be ‘continuous and apparent’. Again, an
to which there is no access, an easement of necessity will example will make matters clearer. So, X, a freeholder,
be impliedly reserved over the land that he has sold for the permits Y, a tenant of another part of X’s land, to drive
benefit of the land he retains. An easement in the common over that part of X’s land that X himself occupies. X
intention of the parties means an easement which both then sells and conveys to Y (or any other person) the
parties accepted should exist as being required to put into land of which Y has hitherto been a leaseholder. On
effect a shared intention for the use of the land retained at conveyance, Y acquires a full easement to drive over
the time of sale. Such an implied reservation can be difficult X’s land (International Tea Stores Co. v Hobbs [1903]
to prove, but a rare example is Peckham v Ellison (1999), 2 Ch 165). The precise overlap between Wheeldon and
concerning access via a rear pathway. s.62 has not been worked out, for these cases are few
3 By implied grant. In similar fashion to the above, if a pur- and far between. It is imperative, therefore, for a seller
chaser buys land from a seller (the seller again retaining of land to exclude the effect of section 62 LPA 1925 in
certain land), and no easements are expressly granted to the any conveyance to which he is party – just in case. The
purchaser for the benefit of the land sold, easements may same is true of the rule in Wheeldon v Burrows above.
be implied in favour of the land sold, burdening the land 4 By prescription. Long use by a claimant of a ‘right’ over the
retained. This can occur in the following circumstances: defendant’s land (‘nee vi, nee clam, nec precario’ – without
(a) Easements of necessity, which in this context mean ease- force, secrecy, or permission) can give rise to an easement.
ments without which the purchaser cannot enjoy the land An easement by prescription can only be claimed by one
at all. An easement of necessity does not exist merely freehold owner against another and, with certain excep-
because it would be useful or convenient. The parties tions, ‘user’ must be shown to have been continuous over
should, ideally, expressly create easements, and implied the relevant period. The rules concerning prescription are
easements of necessity are not a safety net for a failure complicated (and unsatisfactory), but essentially, there are
to specify required easements. three methods of acquiring easements by prescription: (a) at
(b) Easements necessary to give effect to the common common law; (b) under the doctrine of ‘lost modern grant’;
intentions of the parties: for example, where the shared and (c) under the Prescription Act 1832.
intention of seller and purchaser is that a dwelling shall (a) At common law, an easement can be acquired by pre-
be built on the land sold, but no easements permitting scription only if it can be proved to have been used
access by construction traffic are expressly granted from time immemorial (which the law sets at 1189!). In
(Stafford v Lee). Again, however, it is always better to fact, use for 20 years before the claim is made would
consider what easements are required and to have them normally be accepted. However, a claim can always be
expressly created. defeated by showing that the alleged right could not
(c) Easements within the rule in Wheeldon v Burrows [1879] have existed since 1189. For example, there can be no
12 ChD 31. This is best explained by an example. A land- prescriptive right to light under this head for a building
owner owns two adjacent plots, X and Y. He does certain that was constructed ‘only’ in 1585. Hence, ‘pure’ com-
things on plot Y for the benefit of X that would amount mon law claims are rare.
to an easement if X and Y were separately owned: e.g. (b) The doctrine of lost modern grant was invented because
he walks over plot Y to get to plot X. This is sometimes of the ease with which it was possible to defeat a claim
called a ‘quasi-easement’. When he sells off plot X, to prescription at common law. Where the origin of an
retaining plot Y, the purchaser of plot X will acquire an alleged easement cannot otherwise be accounted for,
easement to do those acts over plot Y (walk across it) then, provided that there has been upwards of 20 years’
which the common owner had hitherto done, providing use of the right, the court will presume that the right
the quasi-easement was ‘continuous and apparent’, i.e. was lawfully granted and that the document making the
discernible on a careful inspection of the land; necessary grant has been lost. Of course, this is a complete fiction,
for the reasonable enjoyment of plot X; and had been but the presumption can be rebutted only by evidence
and was, at the time of the grant, used by the grantor for that the existence of such a grant was impossible, for
the benefit of plot X. Consequently, the seller finds his example, that at no time was the servient land owned
retained land burdened by an easement for the benefit of by a legal person capable of granting an easement.
the land sold. Therefore, when selling land (but retaining (c) The Prescription Act 1832 laid down time periods for
part), a person should ensure that this rule is excluded. prescription in general and for rights of light in par-
Failure to exclude the rule can result in the retained land ticular (the latter are discussed in paragraph 3.08). The
being affected by easements which may impact on its use. Act provides that uninterrupted use for 20 years before
(d) Under the statutory ‘general words’ of section 62 of the some action by the dominant owner for confirmation of
Law of Property Act 1925. By virtue of this statutory an easement, or by the servient owner for a declaration
provision, there will pass on every conveyance of land that a right does not exist, means that the claim cannot
(meaning a transfer by deed or registered disposition be defeated merely by showing that the claimed ease-
only), unless a contrary intention is shown, all ‘liberties, ment cannot have existed since 1189. The Act further
privileges, easements, rights and advantages whatsoever provides that user without interruption for 40 years prior
appertaining to or reputed to appertain to the land’. The to a court action gives an absolute and unchallengeable
somewhat unexpected and dramatic effect of this section easement. In both cases, user must be of right, i.e. nee
is very similar to that of Wheeldon v Burrows (above). vi, nee clam, nec precario. ‘Interruption’ is important
It is treated separately because originally the conditions because, if a person wishes to establish an easement by
for Wheeldon and s.62 were thought to be different, but prescription, he must not acquiesce in the interruption of
as a result of Platt v Crouch ([2003] EWCA Civ 1110) his right for one year by the owner of the property over
and Wood v Waddington ([2015] EWCA Civ 538), it is which he wishes to establish the easement. Any period
clear that they overlap very considerably. The differences during which the owner of the land over which the ease-
are that s.62 operates only if there is legal conveyance ment is claimed could not give consent to establishing
of land (as there nearly always will be), whereas as an easement (e.g. because he was an infant or a lunatic)
Wheeldon would operate also in the unusual circum- must be added to the 20-year period. This is part of the
stances of their being an equitable conveyance. Further, fiction that such rights are ‘granted’ by somebody, so
where prior to the sale, the relevant land was in ‘diversity cannot exist if there was nobody to grant them!
40 English land law

Extinguishment of easements decision about whether enough light is left for ordinary
purposes after building work depends on observation
3.05 Apart from an express release by deed (i.e. deliberate and light measurement. The so-called ‘45° rule’ from the
agreement between the owners of the dominant and servient centre of a window can do no more than help the judge
land), the most important method of extinguishing an easement make up his mind, although a reduction of more than
is when the dominant and servient tenements come into the 50% of previous light suggests that too much light has
same ownership and possession. For example, acquisition and been denied. It should also be noted that if light could
occupation by an owner of his neighbour’s land, or consolida- be obtained from an existing but blocked skylight, then
tion of several plots into a development block, will extinguish this must be counted as an available alternative source in
all easements previously existing between them. Consequently, determining whether there is enough light for ‘ordinary
any subsequent development of the land that involves re-splitting purposes’.
the land into plots (either the same original plots or differently) (b) Under the Prescription Act 1832, as amended by the
may require new easements to be created expressly: e.g. as to Rights of Light Act 1959, it is provided that an absolute
water pipes, data cables, air ducts, rights of way and support, right of light can be obtained after 20 years’ uninter-
etc. It is possible for an easement to be extinguished by abandon- rupted use (the 1959 Act provided a temporary extension
ment, but this is difficult to prove and should not be relied on. of the period to 27 years due to the then abundance of
In Dwyer v Westminster City Council ([2014] EWCA Civ 153), bomb-damaged sites and the slow pace of redevelop-
non-use of an easement of way for 40 years did not amount to ment). The 1959 Act provides that a local land charge
abandonment, and the servient owner was required to re-instate may be registered (see paragraph 1.09), indicating the
the right of way. presence of a theoretical wall of stated dimensions in
such a position as would prevent an adjoining owner
Types of easement from claiming a prescriptive right of light. This useful
provision avoids landowners having to erect screens and
3.06 As noted above, the ‘list’ of easements is not closed, and hoardings (subject to planning permission: Chapter 11)
new types of easement will be required as the uses of land to prevent a right of light being acquired over their land!
change and as construction methods develop. The following are Instead, they can register a local land charge that has the
examples of common types of easement: same effect as if the light had been blocked by a wall or
screen, so preventing the neighbour’s 20-year use.
1. Rights of way. A right of way, whether acquired expressly,
impliedly, or by prescription, may be limited as to both
frequency and type of use, e.g. a right obtained for passage 4 Restrictive covenants
by horse and cart in the nineteenth century will not extend
to passage for many caravans if the dominant tenement has 4.01 A restrictive covenant is a binding obligation that restricts
become a caravan park. It is a matter of construction of the an owner of servient land (burdened land) in the use and enjoy-
easement (i.e. an interpretation of what it means) whether ment of that land. The covenant must be made for the benefit
the easement gives a right to pass on foot or with vehicles of dominant land (benefited land) belonging to the covenan-
or whether it includes the right to stop and park. A ‘general’ tee, being the person who may enforce the covenant. Typical
easement will usually encompass these rights on the basis examples are covenants not to build above a given height or in
that the grantor of the easement (he who first created it) a given place, or a certain number of buildings, or covenants
cannot ‘derogate from his grant’ by claiming at a later date restricting the use of the land to given purposes: e.g. no trade
that some lesser use was intended. If some limitation to a or business permitted. Although to some extent superseded by
general easement of way was intended, it should have been planning controls, restrictive covenants still have a valuable
made clear at the time the easement was created. role to play, particularly in preserving the character of housing
2. Rights of support. Although the natural right of support for estates and other homogenous developments. In particular, it is
land by other land has been distinguished from an easement important to appreciate that the granting of planning permis-
(paragraph 3.01), it is possible for one building to acquire sion does not remove any restrictive covenants. So, permission
an easement of support against another after a period of to build is meaningless if a neighbour has a covenant against
20 years’ prescriptive use (i.e. in the absence of any express building which he or she refuses to release: see The Alexander
grant of right). The only way of preventing this would be for Devine Children's Cancer Trust v Millgate Developments Ltd.
the owner of the alleged supporting building to seek a decla- and Housing Solutions Ltd. [2018] EWCA Civ 2679 for the
ration during the 20 years that the supported building has no expensive cost of ignoring a restrictive covenant. The essentials
right to support. It should be noted that where two detached of a restrictive covenant are:
buildings adjoin on separate plots, an easement cannot be
acquired requiring a person who removes his abutting wall 1 that it is, in substance, negative: a covenant that requires a
to weatherproof the exposed flank wall of the remaining landowner to spend money is not negative (e.g. a covenant
building (unless the wall is a party wall: paragraph 2.05). to fence or repair is not negative);
3. Rights of light. 2 that it is made between the covenantor (the person making
(a) To a considerable extent, the law relating to rights of the promise, whose land is burdened) and the covenantee
light has been rendered of secondary importance by (the person who can enforce the promise) for the benefit of
daylighting regulations under planning legislation and the covenantee’s land;
related planning controls (Chapter 11), but a knowledge 3 that the original parties intended the burden of the covenant
of the law of easements is still required. There is no to run with the covenantor’s land so as to bind not only the
such thing as easement of light generally, but only in covenantor, but also his successors in title (e.g. purchasers
respect of some definite opening, such as a window from the original covenantor). Consequently, subject to
or skylight. The owner of the dominant tenement has proper registration of the covenant (below 4.02), all subse-
a right only to such amount of light as is necessary quent owners of the burdened land can be prevented from
for ‘ordinary purposes’. Many years’ enjoyment of an carrying out the prohibited use.
exceptionally large amount of light does not prevent
an adjoining owner from building so as to reduce light: 4.02 A restrictive covenant is an equitable interest in land and
for example, see Ambler v Gordon [1905] 1 KB 417, therefore requires registration to be effective against all sub-
where an architect claimed that he had already enjoyed sequent owners (unless the covenant is contained in a lease,
and needed more light for his studio than for ordinary for which different rules apply). If the land is unregistered, the
office purposes, but the court dismissed the claim. The covenant must be registered as a land charge. However, if – as
Landlord and tenant 41

is more likely – the burdened land is registered, a restrictive alter, or repair premises, or a landlord who requires evidence to
covenant must itself be registered by entering a Notice (usually recover damages from a tenant who has failed to observe a prom-
an Agreed Notice) against the servient land on its Register of ise (covenant) for repair, regard must be had first to the express
Title. These matters will usually be dealt with by the solicitor or terms of the lease, and the client’s solicitor should be asked to
property professional at the time the covenant was first created. advise on the meaning and extent of the terms. The following
If a restrictive covenant complies with the requirements listed general remarks, except where otherwise stated, introduce the
in paragraph 4.01 and is properly protected by registration, it law only in so far as the lease itself does not make any express
will bind the covenantor’s successors in title. The rules on the provision.
passing of the benefit of restrictive covenants are complex and
need not be considered here, save to say that it is very likely
that a successor in ownership to the land benefited will be able The doctrine of waste and
to enforce the covenant against the person now owning the land repairing obligations
burdened. In other words, restrictive covenants affect both bur-
dened and benefited land long after they were first created. There 5.02 ‘Waste’ consists of an act or omission that causes or is
is, in consequence, a procedure for their removal (see paragraph likely to cause a lasting alteration to the nature of the land or
4.04 below). The usual remedy for infringement of a restrictive premises. A tenant of land for more than one year is, apart from
covenant is an injunction to restrain further breaches, or an order statute and any terms of the lease, liable for ‘voluntary waste’
to remove a prohibited development, but the court may give (any positive act such as pulling down or altering the premises)
damages either in addition to or in lieu of these remedies. A cli- and ‘permissive waste’ (any omission, such as allowing the
ent who has the benefit of a restrictive covenant (i.e. the right to premises to fall into disrepair). In practice, however, the great
enforce it) must be aware that they might not, ultimately, be able majority of leases will contain clear repairing covenants going
to prevent the prohibited conduct if the court thinks that they can beyond these obligations. Normally, the landlord is responsible
be adequately compensated in damages instead. Likewise, the for external repairs and the tenant for internal repairs, although
owner of burdened land should not assume that an application this may be different in longer leases. In any event, in respect
to discharge the covenant will be successful or that the remedy of a lease of a dwelling house or flat for less than seven years
against them will ‘only’ be damages. The court looks unfavour- (excluding some leases granted to local authorities and other
ably on those who deliberately ignore binding covenants. public sector bodies), the landlord is obliged to keep the exte-
rior and general structure in repair and to keep in repair and
4.03 Architects should request that their clients obtain confirma- working order all installations relating to heating and ameni-
tion that there are no restrictive covenants applying to a site that ties: Housing Act 1985, section 11. There is, in addition, an
could affect the proposed design and use of a building, or indeed obligation in respect of these leases that the premises are fit for
whether a building can be constructed at all. An architect must human habitation at the start and throughout the lease: Homes
proceed with caution as, for example, a simple covenant ‘not (Fitness for Habitation) Act 2018. Finally, there is a third
to carry on any trade or business’ on the land may effectively type of waste: ‘ameliorating waste’, being some change that
destroy a development, whether or not planning permission is improves the value of the landlord’s interest (his ‘reversion’).
required or has been given. Although the point has never been The courts are very unlikely to restrain acts of ameliorating
tested in court, an architect who continued to act for a client in waste by the tenant, precisely because they add value to the
designing a building that was known by both of them to contra- landlord’s interest.
vene a restrictive covenant could be liable jointly with his client
for the tort of conspiracy, i.e. of agreeing to do an unlawful act. Fixtures
5.03 Prima facie, anything that is attached to the land becomes
Discharge of restrictive covenants part of the land and, therefore, the property of the landowner.
4.04 Many restrictive covenants imposed in former years are no If, therefore, a tenant attaches something to the land, it will
longer of real benefit to the owners of adjoining lands and may presumptively become the property of the landlord. However,
indeed be anti-social or in conflict with reasonable redevelop- two questions arise. First, is the addition to the land in truth
ment proposals. Consequently, power is given to the Property a ‘fixture’, in the sense that it has become part of the land, or
Chamber of the First Tier Tribunal by section 84 of the Law does it remain a ‘chattel’ – the personal property of the tenant?
of Property Act 1925, as amended by section 28 of the Law Second, even if it is a fixture, is it of a kind that, for special
of Property Act 1969, for the discharge or modification of any reasons, a tenant may remove at the end of the lease?
covenant if the Tribunal is satisfied that, among other things,
changes in the neighbourhood make the covenant obsolete, or 1 Fixture or chattel? In deciding whether something attached
that the restriction does not now secure practical advantages to the land is a fixture or a chattel, two matters are
of substantial value to the person entitled to its benefit, or is considered:
contrary to public policy (which may include planning policy). (a) How is the thing attached to the land? If it is attached
Compensation may be awarded to the person entitled to enforce so that it can be removed readily without damaging
the covenant if it is discharged or modified. However, it is not the fabric of the land or the buildings on it, it may be
enough to secure the discharge or modification of a covenant that regarded as a chattel and therefore as the property of the
development would add amenity to the land or to the neighbour- tenant. This is the ‘degree of annexation’ test. For exam-
hood. Some reason why the private law rights of others should ple, something resting on the land by its own weight is
be overridden must be found, and the fact that planning permis- likely to be a chattel: a usual garden ornament and even
sion has been given is not, of itself, enough. a temporary housing structure (e.g. a Portakabin) may
fall into this category: Elitestone Ltd v Morris [1997]
1 W.L.R. 687.
5 Landlord and tenant (b) Why is the thing attached? This is the ‘purpose of
annexation’ test and can override the ‘degree’ test. If the
thing is attached to the land simply because it cannot
Landlord and tenant covenants otherwise be used or enjoyed as a chattel (e.g. a dentist’s
5.01 The vast majority of leases with which architects are chair bolted to the floor or a tapestry fixed to a wall),
concerned on behalf of their clients, particularly of trade and then it remains a chattel. Conversely, if the thing is
business premises, are the subject of formal agreements defin- attached in order to improve the land permanently, then
ing precisely the respective rights and obligations of the parties. it is a fixture. So, a garden ornament forming part of
Whether the architect’s client is a tenant who wishes to rebuild, an integrated garden design may well be a fixture as
42 English land law

an object intended to form part of the land and which Exception to tenant’s
increases its value. repairing obligations
2 Tenant’s fixtures. Even if the thing is a fixture, a tenant who
has attached it may be able to remove it at the end of his 5.06 The tenant is usually not liable for any damage that can be
lease under special rules. In the case of non-agricultural said to be a result of ‘fair wear and tear’, but it is the tenant’s
leases, the tenant may remove trade, domestic, and orna- responsibility to prove that a bad state of repair is covered by
mental fixtures before the expiry of the tenancy. The tenant the exception. In general terms, the phrase means that the ten-
must make good any damage to the premises occasioned ant is not responsible for damage resulting from exposure to the
by the removal of the fixtures. If the lease is of agricultural natural elements or reasonable use of the property. However,
land, tenants can remove all fixtures that they have attached although not liable for direct damage due to fair wear and tear
within 2 months of the lease expiring. The landlord has the (e.g. a slate blown off a roof), the tenant could be liable for any
option to purchase them if he or she wishes. consequential damage that then occurs (e.g. water damage to the
interior). It is often the case, therefore, that tenants will carry
out minor repairs for which they are not technically liable in
Alterations and improvements order to prevent wider disrepair for which they would be liable.
5.04 In the absence of any term in the lease regulating the mat-
ter, the tenant should obtain the landlord’s consent to do any Dilapidations
alterations. This is because any alteration to the premises will
constitute waste (voluntary or ameliorating) and are likely to be 5.07 If asked to prepare a schedule of dilapidations, an architect
a breach of the terms of the lease. It is common for a lease to should first find out from his client’s solicitor the terms of the
contain an express condition that no alterations shall be made lease, so that he is clear which portions of the building come
without the landlord’s consent, although, in most cases, such within the repairing covenant. These are the only portions he
consent may not be unreasonably withheld where the alteration need examine. As some tenant’s fixtures are removable by the
constitutes an improvement: Landlord and Tenant Act 1927, tenant, only dilapidations to landlord’s fixtures need usually be
section 19. Whether a proposed alteration is ‘an improvement’ catalogued. (Note, however, because of the difficulties of assess-
is a question of fact to be considered from the tenant’s point of ing ownership of fixtures, it is often wise to examine dilapida-
view. It should be noted that it is the tenant’s responsibility to tions on anything that is at all doubtful.) Estimates of the cost of
prove that the landlord’s consent is being unreasonably with- making good dilapidations are often required. Unless an architect
held, that the landlord may object on aesthetic, artistic, and even has much experience of this kind of work, it is advisable to
sentimental grounds, and that although the above Act forbids involve a quantity surveyor or similar professional. When land-
the taking of any payment as a condition of giving consent, the lord and tenant cannot agree about the extent of the damage or the
landlord may reasonably require the tenant to pay the landlord’s extent of responsibility for making them good, their dispute may
legal and other expenses (including architect’s and surveyor’s have to be resolved in the courts or by arbitration. In such cases,
fees), plus a reasonable amount for any diminution in the value the schedule of dilapidations becomes evidence, and it is there-
not only of the leased premises, but also of any adjoining prem- fore important that it is very clearly written. Where the parties
ises of the landlord. agree to appoint an architect or surveyor to prepare a schedule
of dilapidations, then, by analogy with the cases on valuations,
if no reasons for the conclusions in the schedule are given, and
Repairing covenants generally it was made honestly and in good faith, it cannot be set aside by
5.05 Architects are frequently asked to prepare a ‘schedule of the courts, even though it turns out to be mistaken: Campbell v
dilapidations’ at the start, during, or at the end of a lease. This Edwards [1976] 1 WLR 403. If reasons are given for the conclu-
will be used as a basis of assessing the extent of the repairing sions in the schedule and they are fundamentally erroneous, it
obligations of the parties under the lease. The importance of may be set aside: Burgess v Purchase & Sons (Farms) Ltd [1983]
initial schedules is that, in the absence of any covenant to do Ch 216. When making an inspection for a schedule, the possibil-
works as a condition of the grant of the lease, any repairing ity that matters might come to court should be borne in mind.
covenant must be interpreted with reference to the original con-
dition of the premises. Thus, the original condition, as detailed Consents
in the schedule, is crucial. The extent of repairing obligations
turns on the words used in the lease. For example, often, the 5.08 It must be emphasised that what has been stated is always
tenant’s obligation is to ‘repair, keep in repair, and deliver the subject to the express wording of the lease and also to the many
premises in repair at the end of the term’ which encompasses statutory provisions for the protection of tenants of certain types
an on-going obligation throughout the lease and an obliga- of premises, particularly houses, flats, and other dwellings.
tion to leave the premises in much the same condition as they Architects should remember that a client’s tenancy may come at
were found. The actual meaning of ‘repair’ – or rather, what the end of a long line of underleases, and the consent of supe-
is a ‘disrepair’, so as to trigger the repairing obligation – can rior landlords may be required for any work that the client has
vary according to the circumstances of each case, including requested. The client’s solicitor should be consulted to determine
the length of the lease, purpose of the lease, and location the existence of any superior landlords.
of the property. So, ‘repair’ may include the replacement or
renewal of parts of a building, but not renewal of the whole or Enforcement of repairing covenants
substantially the whole of the premises. A common repairing
obligation placed on tenants and found in leases of houses or 5.09 Under the Leasehold Property (Repairs) Act 1938, as
flats is to ‘keep and deliver up premises in good and tenant- extended by the Landlord and Tenant Act 1954, a landlord cannot
able repair’, and (in the absence of a countervailing obligation forfeit the lease (i.e. force its early termination) or even begin
of the landlord, such as in premises of low rent) the covenant an action for damages in respect of a tenant’s failure to observe
can include an obligation to put the premises into repair (even a repairing covenant unless the landlord has first served on the
if they were in disrepair by the omissions of another), as well tenant a notice under section 146 of the Law of Property Act
as to keep them in repair. The quality of such repair must be 1925 clearly specifying the alleged breach of covenant. If the
such ‘as having regard to the age, character and locality of the tenant serves a counter-notice within 28 days, the landlord cannot
premises would make it reasonably fit for occupation by another take any action without the consent of the court. Architects are
reasonably minded tenant of the same class’ (Proudfoot v Hart frequently asked to produce a schedule of defects and dilapida-
[1890] 25 QBD 42 at 55). tions to accompany a section 146 notice (see also paragraph 5.06).
Business tenancies – architects’ offces 43

6 Surveys of property to be purchased statutory code for the enforcement of leasehold covenants.
This has a number of consequences, and the architect should
6.01 Architects are often asked to inspect property for clients discuss this fully with his solicitor. In particular, architects
who intend to purchase it or take a lease. A physical inspection should note that if they take an assignment of a lease from
of the property is required, bearing in mind the proposed use and an existing tenant, they are likely to be taking on all the
taking into account all defects and dilapidations. obligations of the original tenant. Secondly, if the architects
assign the lease, they are likely to be required to guarantee
6.02 It is important to note that if defects are not observed and performance of the leasehold covenants by the person to
noted, the architect may be held to be negligent. For example, whom they assign. Thirdly, there are some circumstances
where a surveyor failed to report that the timbers of a house were where a landlord can make the giving of his or her consent
badly affected by death-watch beetle and worm, he was held to assignment dependent on the fulfilment of stringent con-
liable in negligence to the purchaser of that property (Phillips ditions, even if these are not reasonable. For leases granted
v Ward [1956] 1 WLR 471). The measure of damages in such a before 1 January 1996, different rules apply, and enquires
case is the difference between the market value of the property should again be made of the solicitor handling the matter.
with the defect and the purchase price paid by the client. It is
not the difference between the market value with the defect and Protection of business tenants
the value of the property as it would have been if it had been as
described (Perry v Sidney Phillips & Son [1982] 1 WLR 1297). 8.02 Part II of the Landlord and Tenant Act 1954 (as amended
by Part I of the Law of Property Act 1969 and the Regulatory
Reform (Business Tenancies) (England and Wales) Order 2003),
Hidden defects provides a substantial measure of protection to occupiers of
6.03 It is often wise, particularly when investigating old prop- business premises by providing, in effect, that the tenant may
erty, to open up and inspect hidden portions of the building. If continue in occupancy indefinitely, unless the landlord satisfies
this is not done, the limitations of the investigation should be the court that a new tenancy ought not to be granted for certain
clearly pointed out to the client, who should be asked to take a defined statutory reasons (paragraph 8.03). Note, however, that
decision as to whether the expense of opening up is worthwhile. by following the correct procedure, the parties to an intended
The client must, of course, be informed of the probability or oth- business lease can opt out of the protection provided by the Act
erwise of, for example, rot or beetle infestation. If rot or similar before commencement of the tenancy. In that case, the lease is
is discovered, and it was not mentioned in the survey, and the governed by ordinary principles and terminates after the original
architect did not recommend opening up to check, the architect period of the lease has expired.
is almost certainly negligent.
If the parties have not agreed to opt out of the Act, the ten-
ant may apply for renewal of the lease by serving a notice
7 Mortgages on the landlord, which the landlord can oppose (after serving
a counternotice) by proving one of the recognised grounds.
7.01 It is not proposed to discuss this subject in detail, but Similarly, a landlord may seek to terminate the tenancy at the
architects should remember that alteration to premises will alter end of the original lease (or thereafter) and prevent renewal
the value of the mortgagee’s (i.e. the lender’s) security. For this by serving notice on the tenant (not more than 12 months
reason, most mortgages contain covenants requiring the bor- or less than 6 months before the intended termination date),
rower to obtain the mortgagee’s consent to any proposed works. but the court may grant renewal unless one of the specified
As with leases, there may be several lenders who have advanced grounds are established without the tenant having to serve a
different amounts at different times, and these will rank in order notice requesting this. The court will settle the terms of any
of their priority. The architect should ask the client whether renewed tenancy.
the property is mortgaged and request the client to obtain any
necessary consents. 8 .03 There are a number of reasons that might prevent the grant
of a new tenancy to the tenant; i.e. different circumstances that
the landlord can rely on to recover the premises at the end of
8 Business tenancies – architects’ offces the original lease. The first three, if proved, conclusively prevent
the tenant gaining a new tenancy, the latter four give the court
8.01 This review of business tenancies can be in outline only, a discretion to deny a tenancy.
and it is written from the point of view of architects as tenants
of office premises. Three preliminary matters of importance 1 If, on termination of the existing tenancy, the landlord
should be noted: intends to demolish or reconstruct the premises and could
not reasonably do so without possession of the whole, a new
1 An architect should be careful if a lease includes an abso- tenancy will be denied, and the tenant must quit. Since the
lute right for the landlord to forfeit the lease (i.e. terminate 1969 Act, this does not prevent a new tenancy of the whole
it early) in the event of bankruptcy. It is difficult – if not or part of the premises if the landlord will be able to do
impossible – to raise finance from institutional lenders on the work without seriously ‘interfering’ with the tenant’s
the security of such a lease, because the value of the archi- business.
tect’s interest in the land is precarious. 2 If the landlord proves that he or she intends to occupy the
2 Care should be taken to check the wording of covenants premises for his or her own business, or as a residence, a
concerning assignment (transfer of the lease to another) new tenancy will be denied. Since 1969, landlords may suc-
or sub-letting (creation of a sub-lease, with the architect cessfully resist a new tenancy if they intend the premises to
becoming landlord of the occupier). The immediate lease be occupied by a company in which they have a controlling
offered to the architect and any superior lease (as where interest.
the architect’s landlord is a tenant of the freeholder) should 3 If the landlord proves the premises are part of a larger hold-
be inspected. Particularly, the architect should examine the ing, for which a substantially larger rent could be obtained
circumstances in which the landlord can give or refuse his than for the individual parts, a new tenancy of the part will
consent to assignment or underletting. be denied.
3 For leases granted on or after 1 January 1996, the Landlord 4 If the tenant fails to keep the premises in repair, the court
and Tenant (Covenants) Act 1995 has introduced a new may deny a new tenancy.
44 English land law

5 If there are persistent delays in paying rent, the court may The 15 year term can accommodate rent reviews at the current
deny a new tenancy. standard pattern of three or five years.
6 If there are breaches of covenant, the court may deny a new
tenancy.
7 If the landlord is willing to provide suitable alternative 9 Estoppel
accommodation on reasonable terms, the court may deny a
new tenancy. 9.01 It will not usually be the case that architects will have many
dealings with their client’s neighbours. Such matters will usually
It should be noted, however, that this area of the law is complex, be dealt with by the client or the client’s solicitor, and this is
and often subject to clarifying litigation. It is prudent for the by far the best option. However, circumstances may arise where
architect – as with all tenants of business premises – to seek the architect enters discussions about rights or interests affecting
specialist advice. either the client’s or the neighbour’s land: e.g. discussions about
the route of a new access way, the extent of overhanging eaves,
drainage channels, etc. In such cases, the architect must take
Compensation care not to make representations concerning the client’s land that
8.04 If the court cannot grant a new tenancy for any of the first could later be held to be binding on the client: e.g. as to the route
three reasons above, the tenant will be entitled to compensation of the access. Although it is difficult to prove an ‘estoppel’ – i.e.
calculated under a formula set by the legislation. that the architect has represented something about the client’s
land that the client is later held to – the architect should always
make it clear that any agreement or offer with a neighbouring
New tenancy landowner is subject to written confirmation and should not be
8.05 If the landlord is unable to rely successfully on any of the relied on by the neighbour until such confirmation is given. This
above grounds, a new tenancy of the business premises can be is very important, as the courts will enforce an estoppel against
granted. The court will fix the terms of the tenancy, including a person making such a representation, and this can have serious
the rent and length, provided this does not exceed 15 years. consequences for the viability of the development.
5
Introduction to Scots law
CATRIONA MACLEOD

1 Scots law: a distinct legal system and eighteenth centuries, whose authors are known as the
Institutional Writers, and which still have an authoritative status
1.01 Although the modern Scottish Parliament was not estab- in Scots courts and are not infrequently cited to this day. The
lished until 1999, Scotland has always had a separate legal Institutional Writers (such as Craig, Stair, Mackenzie, Forbes,
system independent of English law. Scots law was expressly Erskine, and Bankton) found a language and a structure within
preserved by the Treaty and Acts of Union in 1707, which gave the Roman law that they used and adapted.
rise to the United Kingdom. While it has not been immune to
the influence of English law, which is part of the Common Law 2.03 Following the Act of Union in 1707, the UK Parliament
tradition, it has tended to have more in common with the legal passed legislation applicable to Scotland. Often, Scottish legisla-
traditions of continental Europe, known as the Civilian tradition. tion was no more than an adapted version of the English model.
Wide-ranging legislative reform specific to Scotland often had
1.02 Peculiar though it may seem to maintain separate systems to compete for parliamentary time. Another effect of union was
of law within the relatively small geographical area of mainland that a right of appeal developed to the Judicial Committee of the
Britain, the differences north and south of the border should House of Lords, which often failed to recognise the differences
not be underestimated. In some respects, the differences of that existed between the legal systems and tended, historically, to
approach are fundamental; concepts that are second nature to apply English law. Increasingly, English cases came to be cited
a lawyer in Aberdeen can seem very alien to his contemporary in the Scottish courts and, although they were never binding,
in Birmingham (and vice versa). It is not simply the case that they were (and are) considered persuasive.
Scotland has its own set of procedural rules and a different court
structure (which is discussed below). It has different roots, and 2.04 Over the centuries, Scotland has been influenced by both
this means that the substance of the law is often different. the Common Law and the Civil Law, and it is because of this
that it is known as a ‘mixed legal system’, like South Africa,
1.03 The differences are more apparent in some areas of law Louisiana, and Sri Lanka in that regard.
than others; in fields that are heavily statute based, such as
intellectual property, there is often little practical difference.
Often the ultimate answers to legal questions and the outcome 3 Modern context: devolution
of disputes will be similar, although the legal landscape might
vary along the way. It would be both untenable and undesirable 3.01 Following devolution, the Scottish Parliament was officially
to have different legal systems within the United Kingdom that opened on 1 July 1999 in Edinburgh. In terms of the Scotland
could produce widely differing practical results (although that Act 1998, the Scottish Parliament has the power to legislate on
is not to say it has never happened!). all matters except those specifically reserved to Westminster.
This is not to say that Scots law is the same as English law
where reserved matters are concerned; only that the power to
2 Historical context legislate resides with the UK Parliament.

2.01 In mediaeval Scotland, the religious courts, known as the 3.02 General reserved matters include the constitution, foreign
canon courts, were influential. It is through the influence of affairs, and defence. Specific reserved matters are more wide
canon law that Roman law came to be increasingly applied by ranging. It is worth noting that these include a number of com-
the secular courts in the fourteenth century. Although it might mercial matters, including business associations, employment
seem odd to have turned to a legal system that was applied in the law, insolvency, and intellectual property. Regulation of the
first six centuries AD, its comprehensive and analytical approach profession of architect is also a reserved matter.
proved itself to have considerable utility and modern relevance.
Many Scots lawyers also attended university on the continent 3.03 Since 1999, a vast amount of new legislation has been
and were there exposed to the influence of Civil Law. passed, and the opportunity has been taken to implement fun-
damental reform in certain areas, for example, as regards the
2.02 While it might be said that in England the Common Law system of land tenure and the bankruptcy regime. There is now a
developed on a case-by-case basis, in Scotland there was a greater degree of flexibility and parliamentary time within which
tendency to regard the law as a comprehensive and logical to design Scottish solutions that are sensitive to and fit in with
system. This is apparent in many works from the seventeenth the broader scheme of Scots law.

45
46 Introduction to Scots law

3.04 The Scottish Parliament comprises 129 members (MSPs). A 5 Scotland and human rights
Government is formed which is known as the Scottish Executive.
This comprises MSPs in the capacity of Ministers and the 5.01 An important aspect of modern Scots law concerns human
offices of Lord Advocate and Solicitor General, led by the First rights. The European Convention for the Protection of Human
Minister. Together, they are known as the Scottish Ministers. Rights and Fundamental Freedoms (‘ECHR’) was incorporated
Since May 2007, the Executive (now rebranded the Scottish into domestic law by the Scotland Act 1998. The Scottish
Government) has been formed by the Scottish National Party. Ministers and, through the Lord Advocate, the prosecuting
authorities, cannot act in a way that is contrary to the rights set
3.05 Devolution has not altered the level of representation that out in the ECHR. This has resulted in a very large number of
Scotland has within the UK Parliament. MSPs and MPs now coex- challenges being brought before the courts, particularly in the
ist. This means that Scottish MPs still have an influence over leg- fields of immigration and criminal law. It has also had a wide-
islation on English issues, while English MPs have no influence ranging impact on various aspects of private law. The signatories
over Scottish devolved matters. As a result, there is now a process of the ECHR are the members of the Council of Europe, not the
known as ‘English votes for English laws’ which constitutes a European Union. This means that it is not directly affected by
set of procedures in the House of Commons whereby legislation Brexit. There is, however, currently an absence of clarity of what
which affects only England requires the support of a majority of will happen with ECHR after Brexit.
English MPs representing English constituencies. Following the
electoral victory of the Scottish National Party, an independence
referendum was held in 2014 on the question of Scotland’s future 6 Categorisation of Scots law
within the union. The people of Scotland voted to remain in the
United Kingdom. Following that result, the SNP have indicated 6.01 Perhaps the principal division in the legal system is
the potential for another independence referendum to be held between public law and private law. Public law concerns the
due to Britain voting to leave the European Union (‘Brexit’). It relationships between individuals and the state; it includes
remains to be seen whether devolution in Scotland will inevitably criminal law, immigration and all aspects of judicial review and
lead to complete independence. administrative law. As well as the more ‘traditional’ crimes,
criminal law also comprises many statutory offences in the field
of health and safety.
4 Scotland and European law
6.02 Private law concerns the relationships between individuals
4.01 In 1973, Britain became a member of the European and other legal persons such as companies and partnerships. It is
Economic Community, now known as the European Union often referred to, by lawyers and laypeople alike, as ‘civil law’.
(‘EU’). As a consequence, certain forms of European law Private law, or civil law, has traditionally been subject to the
became directly applicable in Scotland. Currently, parts of the threefold classification of ‘persons’, ‘things’, and ‘actions’, fol-
various European treaties, along with a type of legislation known lowing the taxonomy of Roman law. Specific branches of private
as regulations, create legal rights and obligations that are directly law include contract; unjustified enrichment; delict; property;
enforceable in Scottish courts. European directives do not have trusts; intellectual property; the law of agency and partnership;
the same effect, and require implementation in the form of family law; company law; and bankruptcy/insolvency.
domestic legislation. At the present time, therefore, legislation
must be interpreted in a way that is compatible with Community 6.03 There is no distinction in Scots law between Law and
law, and the courts cannot give effect to any provision that is Equity. General equitable concepts are recognised as part of the
contrary to it. The Scotland Act 1998 specifically provides that general law.
it is not competent for the Scottish Parliament to legislate in
any way that is incompatible with Community law. The issue
of Brexit will affect the current position: The European Union 7 Sources of Scots law
(Withdrawal) Act 2018 will convert EU law into UK law on ‘exit
day’, After ‘exit day’ EU law continues to be applicable during
the implementation period which is the transitional period after
Legislation
exit day. After Implementation completion day (31 December 7.01 The primary source is legislation. Legislation is created by
2020) only existing EU law will be applicable, and new EU either the Scottish Parliament or the UK Parliament. Primary
laws will not affect the UK (the European Union (Withdrawal) legislation takes the form of statutes; secondary legislation takes
Act 2020 inserted provisions to allow the continuation of the the form of statutory instruments and by-laws, issued by Ministers
UK to be subject to EU legislation during the ‘transitional or or local authorities pursuant to delegated authority. Legislation
implementation period’ which comes to an end on 31 December passed by the UK Parliament may apply in whole, in part, or not
2020 (s.1A, s1B). The Scotland Act is to be amended to remove at all to Scotland. If it applies solely to Scotland, or if it has been
the requirement to act compatibly with EU law (provisions have passed by the Scottish Parliament since 1999, this is denoted in
been inserted relating to ‘retained EU law (s 30A Scotland Act the title, e.g. the Requirements of Writing (Scotland) Act 1995 and
1998)’ [amendment not yet in force at time of writing]). These the Freedom of Information (Scotland) Act 2002. For statutes
points are subject to any provisions made in any Brexit deal for that are not wholly applicable, the scope can be found in the sec-
exiting the EU (which is still in process at the time of writing). tion of the statute called ‘extent’. As discussed above, European
Regulations have the same status as legislation. Copies of legisla-
4.02 The European Court of Justice (the ECJ) in Luxembourg has tion can be ordered or downloaded from the website of the Office
the ultimate say in questions of interpretation of community law. of Public Sector Information (www.opsi.gov.uk).
It does not have a truly appellate function; rather, the domestic
courts (at any level) can refer a question of interpretation to it.
The Scottish courts are also currently bound to give effect to
Case law
relevant decisions of the ECJ, which comprises judges from each 7.02 The decisions of certain courts are binding on other courts.
member state. The position will change after Implementation This means that much of the law is effectively ‘judge-made law’.
completion day. Under the European Union (Withdrawal) Act To understand what the law is on a particular point, it may be nec-
2018 (s.6), from ‘Implementation completion day’ the UK courts essary to analyse previous decisions on the same point and extract
will no longer be bound by new decisions of the ECJ. The posi- from them the legal principle. English judgments are not binding
tion has been altered by the European Union (Withdrawal) Act in Scotland, although they have varying degrees of persuasiveness
2020 which inserts provisions for the continuation of the ECJ to depending on how the judgment ranks within the English court
bind the UK until the end of the Implementation period on 31 system. Decisions of the Supreme Court in Scottish appeals are
December 2020, subject to certain provisos. binding in Scotland. As noted above, decisions of the ECJ are
The court structure 47

currently binding on Scottish courts at all levels. Decisions of the Justice of the Peace. Justice of the Peace courts replaced the
European Court of Human Rights in Strasbourg currently must District courts.
be taken into account, so far as relevant. Scottish decisions are
reported in an official series called the Session Cases and also
in Scots Law Times and various other legal reports. Unreported
Sheriff Courts: criminal
decisions since 1998 can be accessed through a database on the 8.03 Scotland is divided into six sheriffdoms (e.g. the Sheriffdom
website of the Scottish Courts Service (www.scotcourts.gov.uk). of Glasgow and Strathkelvin), each of which has a number of
individual sheriff courts hearing both criminal and civil business.
Criminal cases may be brought in the sheriff court in all matters
Authoritative writings with the exception of murder, rape, and treason, although more
7.03 The works of the Institutional Writers (paragraph 2.02) serious assaults, culpable homicide, and serious sexual assaults
are still binding in the courts today. Despite their vintage, it is do not tend to be tried in the sheriff courts. Depending on the
not uncommon, when a question of legal novelty arises today, seriousness of the charges, a trial may take place either before a
to find Stair or Erskine cited in court as the basis for a ‘new’ single sheriff or before a sheriff sitting with a jury composed of
legal argument. 15 members of the public.

7.04 Roman law also exists as a persuasive source, even today;


there are numerous instances where it has been cited in the last Sheriff Appeal Court
decade and it remains a resource for the more imaginative (or
8.04 The Sheriff Appeal court was established in 2015 as part of
perhaps desperate!) lawyer searching for a basis for his or her
Lord Gill’s civil reforms. The Sheriff Appeal court has appellate
argument.
jurisdiction in summary criminal cases including bail appeals.
An appeal on a point of law can be taken from the Sheriff Appeal
Court to the High Court of Justiciary against any decision of the
8 The court structure Sheriff Appeal Court in criminal proceedings, but only with the
permission of the High Court.
Criminal courts
8.01 The structure of the criminal court system is set out below.
In criminal matters in Scotland, the wrongdoer is known as the High Court of Justiciary
‘accused’. The prosecuting authority is the Crown Office and 8.05 The most serious crimes are tried in the High Court of
Procurator Fiscal Service. All prosecutions are brought in the Justiciary. It has jurisdiction over crimes committed throughout
name of the Lord Advocate. the whole of Scotland. It sits permanently in Edinburgh, Glasgow,
and Aberdeen. It also sits on a temporary basis in other larger
towns and cities. The High Court is presided over by Scotland’s
Justice of the Peace Courts most senior judges: the Lord Justice-General and the Lord Justice-
8.02 In very minor cases, criminal proceedings are brought Clerk (currently Lord Carloway and Lady Dorrian). Trials are
in the Justice of the Peace court before a lay magistrate: a conducted before a single judge sitting with a jury of 15.
48 Introduction to Scots law

Court of Criminal Appeal the Court of Session. From now on, civil appeals to the Sheriff
Appeal Court will be heard by a bench of three Appeal Sheriffs
8.06 When the High Court of Justiciary sits as an appeal court, sitting in Edinburgh, although procedural business, routine
it is known as the Court of Criminal Appeal. Appeals are gener- appeals, and appeals from small claims and summary causes
ally heard by a bench of three judges, although a larger bench may be dealt with by a single Appeal Sheriff in the local sher-
(of five, seven, or even nine) may be convened if an earlier iffdom. Judgements of the Sheriff Appeal Court will be binding
judgment is to be departed from. There is generally no appeal to throughout Scotland.
the Supreme Court in criminal cases. However, if a question of
compatibility with European Law or human rights has arisen, or 8.13 The Sheriff Appeal Court can remit an appeal from the
a question has arisen whether an act of the Scottish Parliament Sheriff to be considered by the Inner House of the Court of
is within legislative competence or within devolved competence, Session, but only if the Sheriff Appeal Court considers that the
there can, in certain circumstances, be an appeal to the Supreme appeal raises a complex or novel point of law. A statutory right
Court. However, once the point of law has been decided, the of appeal (in certain cases) from the Sheriff Principal to the
Supreme Court must remit the case back to the High Court for Inner House, is unaffected. It is necessary for a party to have the
the case to be concluded. permission of either the Sheriff Appeal Court or the Inner House
of the Court of Session before there can be any further appeal.
Civil courts
8.07 The structure of the civil court system is set out below. In The All Scotland Sheriff
Scotland, legal proceedings are referred to as ‘actions’, and the Personal Injury Court
respective parties are known as the pursuer and defender.
8.14 The All Scotland Sheriff Personal Injury Court is a new
8.08 As a generality, actions are initiated by a document called sheriff court with the jurisdiction of all of Scotland (as opposed
an initial writ, or a summons, which is served upon the defender. to its own sheriffdom only). There is the right to a jury trial in
Defenders are then obliged to lodge written defences if they wish the All Scotland Sheriff Personal Injury Court. It has jurisdiction
to defend the action. The system dictates that parties’ respective in Personal Injury (‘PI’) cases exceeding £5000, workplace-
cases ought to be finalised in written form before any evidential related PI actions exceeding £1000, and PI cases remitted to the
hearing takes place in court; the scope of the written case then All Scotland court by a sheriff. This court functions at the same
defines the parameters of the evidence that may ultimately be level as any other sheriff court within the civil justice system.
led. This is designed to ensure that parties have ‘fair notice’ of
the case against them and that they cannot be ambushed. Once Court of Session
the cases are set down in writing, parties may wish to debate
legal issues before a judge. However, if the legal issues are 8.15 The Court of Session is the supreme civil court in Scotland.
straightforward or if they cannot be resolved without leading It is permanently based in Edinburgh, in Parliament Square. It
evidence, a trial of the facts will be required. In civil cases this comprises around 30 judges at any one time, known as Lords
is called a ‘proof’, and it takes place before a single sheriff or Ordinary (the same judges that comprise the High Court of
judge. It is inevitable that, as parties go through the process of Justiciary), and is presided over by the Lord President and the
refining their cases in writing, many actions settle without ever Lord Justice-Clerk.
getting close to a court; others might settle at the very door of
the court itself, on the morning of a proof. 8.16 The Court of Session is divided into the Outer House,
for first instance business, and the Inner House, where it hears
appeals. In the Outer House, preliminary business, debates and
The Scottish Land Court proofs are usually heard by a single judge. The Outer House
8.09 The Scottish Land Court deals with disputes between deals with cases at first instance with a monetary value of more
landlords and tenants in relation to agricultural tenancies and than £100,000. Occasionally, jury trials can happen in civil
crofting. cases, where a single judge will sit with a jury of 12 (unlike the
criminal juries of 15) to determine disputed issues of fact. Civil
jury trials are still relatively rare.
The Court of the Lord Lyon
8.10 The Court of the Lord Lyon deals with matters of heraldry. 8.17 Much could be said about legal procedure generally, but
for present purposes it is worthwhile to note that separate proce-
dures exist for commercial actions and personal injuries actions,
Sheriff Courts: civil respectively. Designated commercial judges now exist in the
8.11 The scope of actions that may be raised in the Sheriff Court Outer House, and their aims are to achieve speedy resolution of
is relatively wide ranging and, in particular, there is no financial issues in a commercially responsive way, avoiding protracted
limit on the value of claims that may be raised there. The sheriff litigation. The whole ethos of the commercial court is quite dif-
court has exclusive jurisdiction up to a value of £100,000. There ferent from ordinary actions: the most striking visible sign of this
are rules which set out the circumstances in which a particular is that advocates do not wear wigs and gowns.
sheriffdom will have jurisdiction. There is also the new office of
summary sheriff who deal with smaller value civil cases. Sheriffs 8.18 Appeals in the Inner House are generally heard by a Bench
are not bound by the decisions of other sheriffs. Appeals from of three judges, although a larger Bench can be convened.
the decision of a sheriff lie either to the sheriff principal (in some
circumstances), the Sheriff Appeal court, or are remitted to the UK Supreme Court (formerly
Inner House of the Court of Session (see paragraph 8.16).
constituted as the House of Lords)
8.19 Appeals in civil matters lie ultimately to the Supreme Court
Sheriff Appeal Court (with the permission of the Inner House or of the Supreme
8.12 The Sheriff Appeal Court was established in 2015 as part of Court itself). They are heard before a bench of five Justices.
Lord Gill’s civil reforms. The new court, which is presided over The Justices are predominantly English, although there are usu-
by Appeal Sheriffs, removes business from the Court of Session. ally two Scottish Justices, and business is generally arranged
The new civil appellate structure largely brings an end to the so that at least one Scottish judge can sit on Scottish appeals.
appeal from a Sheriff at first instance to a Sheriff Principal and Importantly, Lord Reed has been appointed as the next President
the virtually unrestricted right of appeal to the Inner House of of the Supreme Court, with effect from January 2020. Lord Reed
Limitation of actions/prescription 49

formerly served as a judge in Scotland in both the Outer and damages. Legal advice should always be sought regarding the
Inner House of the Court of Session. appropriate remedy.

9.06 General principles aside, particular types of contract have


The legal profession developed substantial bodies of law. Construction contracts are
8.20 A Scottish lawyer is either a solicitor, an advocate, or very much a speciality in their own right. Another important
a solicitor-advocate. Solicitors and solicitor-advocates are example is the employment contract, which is likewise in a
regulated by the Law Society of Scotland, whereas advocates category of its own.
are members of a different professional body, the Faculty of
Advocates. In practical terms, solicitors deal directly with clients
and carry out a variety of legal services, including direct repre- Agency
sentation in the sheriff court. Solicitors can become accredited 9.07 The law of contract cannot be considered without refer-
specialists in 24 different areas of the law, including construction ence to the principles of agency. Once a person is appointed as
law, planning law, and environmental law. a party’s agent, with authority to act on his or her principal’s
behalf, it is possible for the agent to enter into contracts on
8.21 Only advocates and solicitor-advocates have rights of audi- behalf of that principal. A partner in a firm is the agent both of
ence in the Court of Session, the High Court of Justiciary, and the partnership and of the other partners.
the Supreme Court. When advocates appear in court, they are
still required, for the time being at least, to wear the traditional
court dress of wig and gown. Advocates are broadly equivalent Partnership
to English barristers and traditionally specialise in the prepara- 9.08 A partnership in Scotland has separate legal personality, in
tion of written pleadings, oral advocacy in the supreme courts, the same way that a company does. It is defined as ‘the relation
and the provision of legal opinions. which subsists between persons carrying on a business in com-
mon with a view to profit’. As such, it may sue and be sued in
8.22 Subject to certain exceptions, advocates must be instructed the firm name, although the partners may also be sued together
through a Scottish solicitor. This rule has been relaxed recently, in their capacity as individuals. Each partner is liable jointly
and certain professionals, including architects registered by and severally for the debts of the firm and any wrongful acts of
the Architects’ Registration Board and members of the Royal the other co-partners. The general law of partnership was codi-
Institute of Chartered Surveyors and the Royal Town Planning fied in the Partnership Act 1890, although it is now possible to
Institute, can instruct an advocate directly. form a limited liability partnership under the Limited Liability
Partnerships Act 2000.
9 Branches of Scots law
Delict
9.01 The following paragraphs are intended as a brief introduc-
tion to some of the main areas of private law with which archi- 9.09 Whereas the law of contract is concerned with obligations
tects may come into contact. assumed voluntarily, the law of delict is concerned with the
redress of legal wrongs which occur without justification. It is
broadly equivalent to the English law of tort. It encompasses
Contract the law of negligence; in general terms, A will be liable to B if
9.02 A contract arises when two or more parties agree to be A owes a duty of care to B, has failed to exercise ‘reasonable
bound. It can exist only when there is consensus between care’, and B has suffered harm as a result. The law of delict also
the parties as to its essential terms and a mutual intention to includes professional negligence; in order to succeed, a pursuer
be legally bound, which is referred to as consensus in idem. must prove that the professional said to have been negligent was
Contracts may be constituted verbally or in writing, but contracts guilty of such failure, as no professional of ordinary skill would
for the creation, transfer, extinction, or variation of an interest be guilty of if acting with ordinary care.
in land require to be in writing. The requirements for formal
validity of written contracts are set out in the Requirements of Property law
Writing (Scotland) Act 1995.
9.10 In this area, the differences between Scotland and
9.03 There is no requirement in Scotland that a contract must England are vast. Central to the law of property is a divi-
include consideration. In other words, a party may undertake to sion between ‘real’ rights and ‘personal’ rights; a real right
perform an obligation gratuitously and still be bound under the is a right directly in and to a piece of property which can
law of contract. be enforced against anyone who interferes with it, whereas a
personal right is simply a right against an individual who, if
9.04 A situation can become rapidly complex when a web of he fails to perform, can be sued for damages. Ownership of
contracts and sub-contracts exists among a number of par- land is a real right, as is the interest of a tenant under certain
ties. For example, the building of a new house might involve leases. In contrast to the law in England, ownership is abso-
contractual relationships among the client and the architect; lute, and the concept of a beneficial ownership has no place in
the client and the main contractor; the main contractor and Scots law. Moreover, there is no division in Scotland between
various sub-contractors. On 26 February 2018, the Contract leasehold and freehold property.
(Third Party Rights) (Scotland) Act 2017 came into force, which
provides a statutory basis for third parties to be granted rights 9.11 A sub-set of property law is intellectual property law, con-
under a contract governed by Scots law. Parties in Scotland can cerning copyright, designs, patents and trade marks. The differ-
now, therefore, grant third party rights, but retain the ability to ences between Scotland and England in this area are not so great,
change those rights in the future (provided that they comply with and therefore no more will be said about them here.
sections 3 to 6 of the Act). The granting of third party rights
under a contract in Scotland was previously governed by the 10 Limitation of actions/
common law principle of jus quaesitum tertio.
prescription
9.05 If one party is in breach of his or her contractual obliga-
tions, this may entitle the other party either to withhold perfor- 10.01 The rules of limitation/prescription of actions in
mance or to declare that the contract is at an end and sue for Scotland are contained in the Prescription and Limitation
50 Introduction to Scots law

(Scotland) Act 1973. In very general terms, there is a three- provide which country’s law applies to the contract and is to
year limitation period in relation to actions for damages govern disputes.
arising out of personal injuries and a five-year prescriptive
period for many other types of action, including contractual
claims. The rules are not straightforward, and legal advice 12 Jurisdiction
should always be sought.
12.01 The rules regarding when the Scottish courts will have
jurisdiction are contained in the Civil Jurisdiction and Judgments
Act 1982 and subsequent European regulations. Most commonly
11 Choice of law (but not exhaustively), unless parties have agreed otherwise, the
Scottish courts will have jurisdiction if a defender is domiciled
11.01 The question of whether Scots law will apply in any there; if the contract in question was to have been performed
given situation is determined by private international law. in Scotland; or if the harmful event in question occurred in
Usually, in a contractual situation, parties will expressly Scotland.
6
Scots land law
WILLIAM FRAIN-BELL

1 Introduction 2 Incorporeal heritable property, e.g. rights over land and


buildings, such as leases or servitude rights (discussed fur-
1.01 When it comes to land law, the Scots and English legal ther below).
systems are markedly different. This is true both at a conceptual 3 Corporeal moveable property, e.g. a car or furniture.
level and as regards the way in which property is marketed 4 Incorporeal moveable property, e.g. contractual right to
and transferred. The landscape of Scots property law was itself receive payment of a debt.
altered dramatically by the coming into force of three pieces of
legislation: the Abolition of Feudal Tenure (Scotland) Act 2000, 3.03 These distinctions are important because there are differ-
the Title Conditions (Scotland) Act 2003, and the Tenements ent rules for transferring the different types of property. This
(Scotland) Act 2004. These were the product of a comprehen- chapter is concerned only with heritable property, i.e. the first
sive programme of reform coordinated by the Scottish Law two categories.
Commission. The aim was not to produce a complete codifica-
tion; rather, the statutory innovations left parts of the common Accession: heritable and
law largely intact and now coexist alongside it.
moveable property
3.04 It should be noted that corporeal moveable property can
2 Rights: real and personal become heritable by the operation of the doctrine of acces-
sion. This occurs when a moveable thing (e.g. a central heat-
2.01 Reference was made in Chapter 5 to the traditional dis- ing system, a fitted kitchen, or heavy machinery) has become
tinction in Scots law between the laws of persons, things, and permanently attached to the land and ‘accedes’ to the land. The
actions. Property law is the law of ‘things’. People hold rights determining factor is the degree of physical connection. These
in ‘things’, e.g. the right of ownership in a house. There are items are often referred to as ‘fixtures’. The sale of a house
two categories of rights: real rights and personal rights. The would therefore include fixtures (unless otherwise specified), but
real rights are finite in number. They include the ultimate right it will not include moveable items, such as curtains and furniture
of ownership; a right in security (such as a standard security (unless otherwise specified).
held by a bank); servitude (e.g. a right of access over another’s
land); and lease. 3.05 The value of premises for rating or security purposes can
often depend on what plant and machinery is counted as part of
2.02 A real right is a right in and to the thing itself. A personal the heritable property.
right is simply a right against another person to make him do
something or refrain from doing something, e.g. the contrac-
tual right to payment of a debt. Whereas a real right can be 4 Land ownership
enforced against any person who interferes with it, a personal
right can be enforced only against one person or a defined class 4.01 As noted above, ownership is one of the real rights. This
of people. means that the rights of owners transfer to their successors and
can be enforced against anyone who interferes with the exercise
of the right.
3 Classifcation of property
3.01 Property can be classified as corporeal or incorporeal.
Abolition of feudal tenure
Corporeal things are tangible and have a physical presence, such 4.02 Historically, Scotland had a system of feudal land owner-
as a field or a car. Incorporeal things are simply rights, e.g. the ship whereby all land was ultimately held by the Crown. The
right of land ownership itself or a servitude right of access. ‘owner’ of land at any given time was not the ultimate owner,
but a ‘vassal’ owning the dominium utile, while the feudal
3.02 A further distinction is between heritable and moveable superior held the dominium directum. This often enabled the
property, which roughly equates to the distinction between land feudal superior to retain control over the use of the land, impose
and everything else that is not land. These distinctions give rise provisions relating to maintenance, retain rights of pre-emption,
to a fourfold classification of property: reversion, or redemption and, in some cases, to extract annual
payments known as feu duty. In many ways, the system operated
1 Corporeal heritable property, e.g. land and buildings. like a rudimentary (private) town planning system.

51
52 Scots land law

4.03 On 28 November 2004, this system was abolished by the as an undivided whole. Common ownership frequently occurs
Abolition of Feudal Tenure (Scotland) Act 2000. On that date when a husband and wife buy a house together. It also occurs
every estate of dominium utile automatically became outright in flatted properties or office blocks where the shared areas are
ownership vested in the current proprietor. At the same time, all in common ownership.
rights to extract feu duty were also abolished.
4.07 Subject to certain restrictions contained in the Matrimonial
4.04 No more is said of the feudal system here; it is noted Homes (Family Protection) (Scotland) Act 1981, a pro indiviso
because the change was both radical and recent and many older owner is entitled to convey his or her own share of the prop-
deeds bear reference to it. Much of the utility of the feudal sys- erty to a third party. Any pro indiviso owner is also entitled
tem lay in the mechanisms it provided for the private control and at any time to have the property physically divided or, if this
regulation of maintenance and development of properties. This is not possible, sold, and the proceeds divided. Where parties
has been preserved largely by reforming the law of real burdens. cannot agree, an action for division and sale may be raised
in court.
Terminology: no freehold or leasehold
4.05 The distinction between freehold and leasehold (and
Divided ownership
commonhold) ownership has no place in the Scottish system. 4.08 A piece of land may be divided into what are known as
Certainly, land may be owned or it may be leased (often, in the separate tenements, which can be held by different owners.
commercial context, for long periods) but beyond that, the ter- Salmon fishings are such a separate tenement, as are the rights
minology has little meaning in Scotland. In contrast to England, to gather oysters or the rights to minerals. Since 2004, certain
Scots law has long recognised the enforceability of positive sporting rights (e.g. to shoot and hunt) previously held by feu-
covenants that run with the land and are enforceable against suc- dal superiors have been preserved as separate tenements. These
cessive owners of property, e.g. maintenance covenants, in the kinds of rights often have significant commercial value, as they
form of real burdens. Accordingly, the necessity for leasehold could effectively veto certain developments that are adverse to
ownership did not arise. enjoyment of the rights.

Shared ownership 5 Sale of land and buildings


4.06 It is possible for land to be held in common or jointly by
two or more persons. Both types are known as pro indiviso 5.01 The transfer of land is a two-stage process: the contractual
ownership, meaning that the property is owned by both parties stage and the conveyancing stage.
Title conditions: servitudes and real burdens 53

The contract: missives 7 Title conditions: servitudes


5.02 A contract for the transfer of heritable property must be and real burdens
constituted in writing. An oral contract is not effective for this
purpose. This usually involves the conclusion of missives, which 7.01 ‘Title condition’ has a statutory meaning that was intro-
take the form of a series of offers and qualified acceptances that duced by the Title Conditions (Scotland) Act 2003. The main
flip back and forth between solicitors until the bargain is finally examples of title conditions are servitudes and real burdens.
concluded. During this stage, the purchaser’s solicitor under- These are the primary mechanisms for creating encumbrances
takes a full examination of the title and, as well as determining on land; they serve many useful functions in regulating various
the extent of the property and considering issues such as build- issues, including use, maintenance, upkeep, and access. It is
ing consent and planning permission, should flag up any title important for purchasers and developers alike to be aware of
conditions or servitudes burdening (or benefiting) the property the scope and extent of any encumbrances affecting a property.
(discussed further below). Architects and developers may wish to consider how prospective
plans might be affected and whether it may become necessary to
5.03 When newly built properties are sold off by a developer, negotiate for variation or discharge of a real burden or servitude.
the missives are generally in a form prescribed by the developer. It is best to address such matters at as early a stage as possible,
These are notoriously weighted in favour of the seller, and clients to avoid any subsequent delay once a development is under way.
should be advised to take legal advice before agreeing to them.

5.04 When a building is less than ten years old, the missives
Nature: running with the land
typically state that it is covered by a guarantee issued by the 7.02 Both servitudes and real burdens are ‘real’ in the sense
National House Builders’ Council (NHBC). If a builder is not that they run with the land. In essence, they are ‘attached’ to
NHBC registered, an architect may be asked to produce a certi- the lands that they respectively burden and benefit and, once
fication of supervision, stating that it has been built in a proper constituted, apply to all successive proprietors indiscriminately.
and workmanlike manner, in accordance with building regula- The defining feature is that they actually benefit the land itself
tions and planning permission. and only inadvertently benefit the owners. In this way they differ
from contractual rights, which do not extend beyond the original
5.05 Conclusion of the contract does not mean that ownership contracting parties.
passes. It means that the purchaser now has the right to insist
upon delivery of a conveyance, and the seller can insist on pay-
ment of the price.
Real burdens
Defned
The conveyance: disposition 7.03 A real burden is an encumbrance on land constituted in
5.06 The next stage is the granting of a disposition by the seller. favour of the owner of other land in that person’s capacity as
The purpose of this is to convey the land from the seller to the owner of that other land. The encumbered land is known as
purchaser. It must be probative, which usually means that it must the ‘burdened property’ and the other land as the ‘benefited
be witnessed. However, since 2006, it has been possible for an property’.
electronic document authenticated by a digital signature to be
effective for the transfer of an interest in land. 7.04 There are two principal kinds of burdens. An ‘affirmative
burden’ imposes an obligation to do something, e.g. to main-
5.07 A form of personal guarantee known as warrandice will tain a road or build a boundary wall. A ‘negative burden’ is an
be either expressly included or implied in dispositions of herit- obligation to refrain from doing something, e.g. building above
able property. This is a personal guarantee of title by the seller a certain height or using the property for commercial purposes.
(although it does not cover every risk and, in particular, is not A burden cannot provide the right to enter another property or
a guarantee against defects in the condition of the property). make use of it, unless such a requirement is ancillary to another
burden, e.g. a right to access a property to inspect maintenance
5.08 The real right of ownership is not actually transferred work that is required by an affirmative burden. Subject to that
until the disposition is registered in the Land Register, even if limited exception, rights to do something on another property
consideration has been made. The Automated Registration of or access another property are now the domain of servitudes,
Title to Land (Electronic Communications) (Scotland) Order not real burdens.
2006 permits the electronic registration of transactions affecting
land. Registration has always been pivotal in Scotland for the 7.05 A check on the titles should reveal any real burdens which
transfer of ownership. Accordingly, there is no equivalent to the could affect design, and legal advice should be sought in that
English concept of ‘beneficial ownership’. regard.

6 Land registration Community burdens


7.06 Where properties in a common scheme, e.g. a housing
6.01 The Land Registration (Scotland) Act 1979 introduced a estate or business park, are all subject to the same burdens which
new system of land registration, superseding the Register of are mutually enforceable, these are called ‘community burdens’.
Sasines. Every transfer of land is now registered in the Land Where the property deeds are silent, the 2003 Act steps in to pro-
Register, which is administered by the Keeper of the Registers vide default rules for decisions to be taken by a majority for the
and is fully accessible to the public. Every registered property carrying out of maintenance, enforcement, variation, discharge,
has its own title sheet and title plan, which is part of a larger and the appointment of a manager.
mapped index. A land certificate is issued, based on the title
sheet. Entries on the title sheet are conclusive of the location and
extent of property (albeit this does not stop disputes arising as to
Manager burdens
what a boundary entry in fact is in reality). Registration carries 7.07 A manager burden is a real burden which makes provi-
a guarantee that the position on the register is correct (although, sion for conferring on a specified person the power to act as
exceptionally, the Keeper can register a title under exclusion of a manager of related properties. This is typically utilised by
guarantee). It can be changed only by a formal process known developers, to deal with the initial years of a housing or other
as ‘rectification’, in very limited circumstances. development.
54 Scots land law

Other types Enforceable by whom?


7.08 Other special types of burden include conservation burdens; 7.16 A real burden is enforceable by an owner of the benefited
rural housing burdens; maritime burdens; economic development property but also by certain lessees and the holder of a proper
burdens; and health care burdens. In these circumstances, there liferent, provided that person has an interest to enforce it. The
is no benefited property as such; rather, the burden is granted spouse or civil partner of any of these persons, provided they
in favour of a conservation body, the Scottish Ministers, a rural have occupancy rights within the meaning of the Matrimonial
housing body, a local authority, the Crown, or a National Health Homes (Family Protection) (Scotland) Act 198l, has an equal
Service Trust, as the case may be. right to enforce them. Community burdens are enforceable by
the majority of proprietors or, where appointed, by a manager on
their behalf. The special types of burden noted above (paragraph
Creation 7.08) are enforceable by the relevant official body.
7.09 A real burden is created by a deed granted by the owner
of the burdened property. This is usually a disposition or a deed
of conditions. The deed must set out the terms of the burden Enforceable against whom?
and identify the benefited property. To take effect, it must be 7.17 An affirmative real burden (i.e. an obligation to do some-
registered against both the benefited property and the burdened thing, e.g. maintain a stair) can be enforced only against the
property. owner of the burdened property. Negative or ancillary burdens
are different and can be enforced against not only the owner, but
7.10 Community burdens must define the community affected. also any tenant or any other person having use of the property.
They apply to all units within it.

7.11 The existence of any burden will always be evident from Variation or discharge
a search of the title of a burdened property. Determining the 7.18 Discharge is by registration of a deed of discharge, granted
benefited property is not so simple, although the benefit of any by the owner of the benefited property, in the Land Register.
new burdens created since 28 November 2004 will be evident A separate procedure exists for termination of burdens over
from the Land Register. 100 years old, by the registration of a notice without objection.
Where private agreement is not possible, the Lands Tribunal for
7.12 The benefit of older burdens will not necessarily be Scotland has the power to determine applications for variation
apparent. When various properties were conveyed as part of or discharge of real burdens, as well as any question of validity,
a common scheme, or when a property was sub-divided, the applicability, enforceability, or interpretation. If an order is made
deeds would often impose real burdens but remain silent as to varying or discharging a real burden, it can order the applicant to
the properties that were to benefit from them. This gave rise pay compensation to the owner of the benefited property.
to complicated rules for the existence of implied enforcement
rights. For common schemes, any such rights were extinguished 7.19 In relation to affirmative burdens, applications can be made
by the 2003 Act and re-stated in a simplified form. Accordingly, only by the owner of the burdened property. As regards negative
many properties that were part of a common scheme may or ancillary burdens, applications can be made by the owner of
have enforcement rights that are not apparent on the face of the burdened property, but also by the tenant or any person hav-
the Land Register. The land tenure reform legislation (part of ing use of the property. This gives rise to a potential disadvan-
which brought about the abolition of the feudal system of land tage for developers who are faced with troublesome real burdens
ownership in Scotland on 28 November 2004) provided that the encumbering a prospective site. They are not in a position to
above type of real burden would automatically survive beyond make an application for variation or discharge, even when they
feudal abolition. However, this was an interim measure, and have a concluded contract or option. Here the position differs
the real burdens in question only subsisted until 28 November from England, because they must wait until they have obtained
2014, unless the owners of benefited properties had registered use of the site (for negative burdens), or obtained ownership (for
statutory ‘preservation notices’ in the appropriate property reg- affirmative burdens), or rely on the seller to make the application
ister (either the Land Register or Registers of Sasines) before on their behalf. None of the options is satisfactory.
that date.

Servitudes
Abolition and reallocation
of feudal burdens Defned
7.13 When the feudal system was abolished, all burdens 7.20 A servitude is an encumbrance on land or houses whereby
enforceable by feudal superiors in that capacity were abolished. the owner of the burdened property must allow certain use to be
Of these, it is worth noting the categories of ‘facility conditions’ made of it by the owner of the benefited property. The closest
and ‘service conditions’. Facility conditions are typically con- parallel in England is the law of easements. A typical example
cerned with the management and maintenance of common facili- is a servitude of pedestrian or vehicular access.
ties, such as private roads or boundary walls. Service conditions
bind the owner of burdened property to permit services, such 7.21 Where servitudes have been created otherwise than in
as water or electricity, to be supplied to the benefited property. a registered deed, there is a restricted number of recognised
Other burdens tended to preserve the amenity of neighbouring types. These include servitudes of building support, stillicide
properties by regulating the use or development of the burdened (eavesdrop), access, the taking of fuel (peat and turf), and the
property. drawing or conducting of water. For servitudes created by deed,
the categories are no longer closed. This paves the way for the
7.14 Feudal facility and service conditions, although no longer recognition of new types of servitude, e.g. a servitude of park-
enforceable by the feudal superior, are now enforceable by all ing. The restriction is that there must be some actual benefit
benefited proprietors. to the neighbouring property, not simply a benefit to its owner
personally.
7.15 Other burdens remain in existence only if the feudal supe-
rior ‘re-allotted’ the benefit to a specified neighbouring property 7.22 The law now expressly recognises a servitude for the lead-
by statutory notice and registration in the Land Register. ing of pipes, cable, or wire over or under land for any purpose.
Nuisance 55

Creation traditional tenements but also office buildings, new flatted devel-
opments, and houses divided into flats. Unless the title deeds
7.23 Servitudes can be created by a deed which is registered provide otherwise, the Tenements (Scotland) Act 2004 provides
against both the benefited and burdened properties in the Land a default regime for determining who owns what and how the
Register. They can also be acquired by positive prescription building is to be maintained and repaired.
through possession over a period of 20 years. It remains pos-
sible for servitudes to be created by implication when a piece
of land is divided into different parts and sold. Accordingly, it is Tenements
not always obvious from the Land Register whether a servitude
exists. Common parts, the roof, and the solum
9.02 By default, any shared ‘close (entrance and passageway)’,
Enforcement lift, path, outside stair, fire escape, rhone, pipe, flue, conduit,
cable, tank, and chimney stack is owned in common by the flats
7.24 As one of the real rights, a servitude is enforceable against that use it or are served by it. The roof is owned by the top flat.
anyone in the world who interferes with it. Parties should there- The solum and airspace is owned by the ground flat. The top flat
fore be alive to the possibility that they may be interdicted (as is, however, allocated the part of the airspace extending to the
in injuncted in England) along with the owner if they interfere highest point of the roof. This ensures that there is no difficulty
with a servitude when undertaking preliminary work on a site with the installation of dormer windows.
they do not own.
9.03 There is a statutory prohibition on interfering with support,
Renunciation, prescription, shelter, or natural light for other flats. This replaces the old com-
mon law of common interest.
variation, and discharge
7.25 A servitude can be expressly renounced by the benefited Repairs and maintenance
proprietor. It can also be extinguished by negative prescription.
This occurs if it is not used for a continuous period of twenty 9.04 In many cases, there will be a property management or fac-
years. toring scheme. The Act provides a default management scheme
which applies where the deeds do not provide otherwise.
7.26 As with real burdens, an application may be made to the
Lands Tribunal for variation or discharge of a servitude by any- 9.05 There is a general definition of ‘scheme property’ which
one against whom the servitude may be enforced. This is wider includes not only common property, but all the potential ‘big
in effect than the corresponding provision for real burdens. It ticket items’ which are owned individually: the roof, solum,
would include a developer who has a concluded contract or foundations, external walls, gable walls, and also any load-
option but does not yet own the site (or indeed made any use bearing walls. It provides a majority decision-making process
of it). whereby maintenance of these items can be arranged and the
costs apportioned. The general rule is for equal division of costs.
The scheme also provides for decisions to be taken about routine
8 Access rights maintenance cleaning, painting, and gardening. A manager may
also be appointed and a common insurance policy arranged.
Private access Emergency repairs can be instructed by any owner, and the costs
are recoverable from the other owners.
8.01 Within towns, the roads are adopted by local authorities,
and therefore problems ensuring access are less likely to arise. 9.06 Under the Civic Government (Scotland) Act 1982, councils
For rural properties, it is very important to check that a servitude also have power to light common stairs and passages and to
of access exists. The difficulty is that it may not be apparent require common areas to be kept clean and properly decorated.
from the title sheet, as it may have been established by implica- Fire authorities have power to deal with fire hazards in com-
tion or prescription. mon areas.

Public rights of way


10 Boundary walls and support
8.02 A public right of way can exist as a footpath or road from
one public place to another. It is established either by posi- 10.01 Where neighbouring properties, not forming part of a
tive prescription (continuous use for 20 years) or by statutory tenement, share a boundary wall, the respective parties each
creation. own their own half of the wall, up to the mid-point. They have
reciprocal duties of support, founded on the doctrine of common
Public right to roam interest. Each must therefore maintain his or her part of the wall
to support the other.
8.03 Very broad access rights for the public were created by the
Land Reform (Scotland) Act 2003. The public now has the right 10.02 Where walls are not shared, there is no positive obliga-
to cross all land (subject to certain exceptions), although motor- tion to provide support to a neighbouring property. However, if
ised vehicles cannot be used. Separate rights exist to access something is done to undermine existing support, e.g. excavating
land for recreational, educational, and other limited purposes. in a way that threatens the foundations of a neighbour’s property,
Exceptions include buildings, schools, land on which building then liability in damages can arise. Any proposed work that
work is being carried out, private gardens, and golf courses. might threaten support could be interdicted.
The Act imposes reciprocal duties on users and landowners to
act responsibly.
11 Nuisance
9 Tenements 11.01 The doctrine of nuisance is part of the law of delict that
can provide a useful remedy in property disputes. The principle
9.01 Many properties are made up of a number of different units is that a person cannot interfere with his or her neighbour’s
sharing common areas, such as the stair or lift. These include comfortable enjoyment of their property. Nuisance will depend
56 Scots land law

on the circumstances and the environment, but can include loud connected. The community registers its interest in a register,
noise or foul smells. If a nuisance has existed without challenge which is maintained by the Keeper of the Registers of Scotland.
for a period of 20 years or more, it cannot be objected to. The right to buy is then activated when the land comes to be
marketed or sold. Crofting communities were also given rights
to buy certain land. The Community Empowerment (Scotland)
12 Other restrictions on Act 2015 introduced further rights of community acquisition
heritable property that can force land sales from private owners in certain circum-
stances and also allow public sector assets to be taken over by
12.01 Numerous other restrictions, both statutory and otherwise, communities. The Land Reform (Scotland) Act 2016 gave the
may affect the owner of heritable property. power to the Scottish Government to force a sale of private land
to community bodies in order to further sustainable development
in the absence of a willing seller.
Statutory restrictions
12.02 The full ambit of statutory restrictions is beyond the scope Repairs and maintenance
of this chapter. Obvious examples are the Town and Country
Planning Acts and the statutes and regulations governing com- 12.06 At present, under the Civic Government (Scotland) Act
pulsory purchase. A number of uses are not permitted except 1982, a local authority can go ahead and instruct repairs to prop-
under licence (sale of alcohol, gaming, sex shops, tattooing, and erty in the interests of health and safety or to prevent damage. It
skin piercing etc). has the power to recoup costs. Under the Housing (Scotland) Act
2006, a local authority also has the power to serve repair notices
12.03 The Public Health (Scotland) Acts prohibit the carrying on on persons having control of property, to require certain repairs
of a large number of activities, defined as statutory nuisances, to be carried out when property is in a state of serious disrepair.
on various kinds of properties. A proprietor is also subject to
the building regulations administered by the appropriate local
authority in respect of any building operations he may wish to
Occupiers’ Liability (Scotland) Act 1960
carry out. 12.07 Occupiers of property are obliged to take reasonable care
to see that persons entering their premises do not suffer injury
12.04 Under the Nature Conservation (Scotland) Act 2004, there because of the state of the premises. A failure which causes an
are restrictions over certain uses and development of land that accident can result in liability to pay damages.
is designated as a Site of Special Scientific Interest or where a
nature conservation order is in place. Various activities in rela-
tion to rivers and lochs, including the discharge of pollutants, 13 Leases
are regulated by the Water Environment and Water Services
(Scotland) Act 2003 and the Water Environment (Controlled 13.01 A proprietor may lease his or her property to another in
Activities) (Scotland) Regulations 2005. Rights to enter property return for payment of rent. The law of leases is a specialised
are conferred by the Housing (Scotland) Act 2006 in relation area, and advice should be sought. Commercial leases, in par-
to maintenance, repair, and the licensing of houses in multiple ticular, can be complex, for example in relation to rent review
occupancy. clauses. There are also numerous statutory provisions regulating
leases, restricting rents, and providing security of tenure. In the
context of private residential tenancies, the Housing (Scotland)
Right to buy Act 2006 imposes a statutory code of landlords’ repair and main-
12.05 The Land Reform (Scotland) Act 2003 gave rural com- tenance obligations. Separate frameworks exist for agricultural
munities a right to buy land with which the community is tenancies and crofting land respectively.
Part B
Statutory
framework
7
Statutory authorities in England and Wales1
JAMES STRACHAN QC

1 Local government Agencies with Local Enterprise Partnerships responsible for


Enterprise Zones, reforms to the planning system, the creation
of greater financial autonomy for local government and the
Introduction: relevant local introduction of elected police commissioners. It also devolved
government authorities responsibility for certain policy areas under city “devolution
1.01 Local government in England and Wales, outside London, deals” between central Government and local authorities under
was completely reorganised on 1 April 1974, when the Local specific arrangements. This process has been continued by the
Government Act 1972 came into force and this remains one of Conservative Government that came into power in 2015 which
the most important statutes setting out local authority powers has also required directly-elected mayors in those areas where
and duties. The pattern of local authorities, following this and substantial powers have been devolved.
subsequent local government legislation, is now simpler than it
1.04 In London, the Local Government Act 1985 abolished
was before 1974, but Greater London (reorganised in 1965 by
the Greater London Council and redistributed its functions
the London Government Act 1963) is administered differently,
among the 32 London boroughs, the City of London and new
and there are also differences which exist between England and
specialised representative bodies (e.g. the London Fire and
Wales. These three parts of the country should therefore now be
Civil Defence Authority). Housing became the responsibility of
considered separately.
the boroughs and the City. The Greater London Authority Act
1999, as now amended by the Greater London Authority Act
1.02 Local government in England and Wales consists of 2007, established the Greater London Authority (GLA), which
administration by locally elected bodies constituted as corpora- is composed of the London Assembly and the Mayor of London.
tions and subject to powers conferred and duties imposed by The London Borough Councils and the Common Council of the
Parliament and the Welsh Assembly (where applicable). Local City of London remain, although some of their responsibilities
authorities are subject to the direction, control and supervision and functions have been affected by the creation of the GLA.
of the Government or, to the extent that Parliament or Welsh
Assembly has legislated for that direction, control and supervi- 1.05 In England outside the London area, the country was divided
sion in statute or in other legislation. among six metropolitan areas (West Midlands, Merseyside,
Greater Manchester, West Yorkshire, South Yorkshire, and
1.03 The Labour Government elected in 1997 carried out a Tyne and Wear) and the ‘ordinary’ counties. Between 1974 and
reform of local government in England and Wales. The Local 1985 in the metropolitan areas there was a metropolitan county
Government Act 2000 gave local authorities general powers for each area, and a varying number of metropolitan districts,
to promote the well-being of their community; established each with a council, within each county. Since 1985 the met-
executive and scrutiny arrangements within local government; ropolitan counties have been abolished and their functions
modernised the laws relating to the conduct of members; and redistributed to the metropolitan districts and specialised repre-
changed some of the local government election procedures, sentative bodies.
subject to the Local Government and Public Involvement
in Health Act 2007 and the Local Democracy, Economic 1.06 Outside the metropolitan areas the structure originally
Development and Construction Act 2009. The Government of comprised 38 counties (each with a county council) and approxi-
Wales Act 1998 devolved certain powers from Westminster to mately 390 districts (each again with a council). However, fol-
the National Assembly for Wales. Many of the provisions of lowing the recommendations of the former Local Government
that legislation have now been replaced by the Government Commission, a number of the former county councils have been
of Wales Act 2006, as amended by the Wales Act 2017, with abolished in favour of new unitary authorities, which combine
certain powers now exercisable by the Welsh Ministers. The the functions of county and district councils. In other non-metro-
Coalition Government that came into power in 2010 instituted politan counties, two tiers of government were retained, although
further significant changes in local government administration in some cases large cities have been given unitary status with
through the Localism Act 2011, including the replacement of the county and district councils retaining their responsibilities
the well-being power for local authorities in England with a for the remaining parts of the area. The Electoral Commission
general power of competence in its place, abolition of regional has the powers of the former Local Government Commission
spatial strategies and the replacement of Regional Development for England to review and make changes for effective and

1 This chapter draws heavily on the chapter written for the first edition by Professor J. F. Garner.

59
60 Statutory authorities in England and Wales

convenient local government under the Parties, Elections and Local Government (Democracy) (Wales) Act 2013 and the Local
Referendum Act 2000 and the Local Government and Public Government (Wales) Act 2016.
Involvement in Health Act 2007. The 2007 Act enabled two-tier
areas to propose a single unitary authority area, and a number of
county councils have sought such change to create single unitary General characteristics
authorities, such as Wiltshire Council and Cornwall Council in of local authorities
existence from 1 April 2009.
The Local Democracy, Economic Development and 1.09 The essential characteristic of every local authority under
Construction Act 2009, as amended by the Cities and Local this complicated system is that it is governed by a council
Government Devolution Act 2016, now enables the Secretary elected on a wide franchise by local government electors at
of State to establish either an economic prosperity board 4-year intervals, normally on the first Thursday in May. In dis-
(EPB), or a combined authority (such as now exists for Greater tricts, one-third of the councillors retire every year on three out
Manchester, West Yorkshire, the Tees Valley or the West of of four years: but a non-metropolitan district may resolve that
England). EPBs or a combined authority may be created for the all their members shall retire together. In counties, all members
whole of two or more local government areas to exercise specific retire together every fourth year. In parishes and communities,
authority functions, so giving effect to the principles of local councillors are elected for a four year term. Some changes have
authority devolution and “devolution deals”. been made to the system of election of councillors by the Local
The Secretary of State may provide for a directly elected Government Act 2000 and now the Local Government and
mayor and for functions of mayoral combined authority to be Public Involvement in Health Act 2007. Under this legislation
exercisable by the mayor, including the functions of a police district councils may be subject to schemes for whole-council
and crime commissioner for that area. The mayoral combined elections, or elections by halves or thirds, and power is given
authorities of Greater Manchester, the Liverpool City Region to change the date of local elections to the date of a European
and the West of England have been given the equivalent powers Parliamentary general election. The term of office for an elected
exercised by the Mayor of London to produce spatial develop- mayor is 4 years.
ment strategies for their areas. The Secretary of State has various
powers under the 2009 Act, the Localism Act 2011 and the Cities 1.10 Local authorities are legal persons with corporate status,
and Local Government Devolution Act 2016 to delegate local capable of suing and being sued in the courts, entrusted by
public functions to permitted authorities and to make regula- Parliament with a range of functions over a precisely limited
tions about structural and boundary arrangements in relation to geographical area. Each local authority is subject to the doc-
local authorities with the consent of the local authorities them- trine of ultra vires – this means that a local authority is not
selves. The Localism Act 2011 also allows specified persons or entitled to act beyond its powers. It can only lawfully perform
voluntary community bodies to express an interest in providing those functions that are within the powers conferred on it by
specified local authority services which must be considered by Parliament or other legislative body, and only in such a manner
a local authority and may only be rejected on grounds specified as has been prescribed if the requirements are mandatory. On the
by the Secretary of State. The Broads Authority established other hand, within such powers, each local authority is its own
by the Norfolk and Suffolk Broads Act 1988 and a number of master. In the two-tier or three-tier system there is no question
National Park Authorities established under the Environment Act of an appeal from the lower-rank authorities (the district or the
1995 exercise specific duties in respect of the Broads and desig- parish) to the higher rank (the county council) or from the par-
nated National Parks respectively. National Park Authorities are ish to the district. If the individual authority has acted within its
the planning authority for the relevant National Park. statutory powers, its decision is final, except in cases laid down
by Parliament, where (as in many planning situations) there may
1.07 In addition, rural parishes which existed before 1974 have be a right of appeal to a Minister of the central government (see
been allowed to continue, subject now to Part 4 of the Local Chapter 11) or the courts. A local authority’s powers include the
Government and Public Involvement in Health Act 2007 right to do things for which there is express or implied authority
(amending the Local Government Act 1972). Some of the pre- and things which can fairly be regarded as reasonably incidental
1974 district councils have been re-formed with parish council to the discharge of their functions (as now reflected in s.111 of
status. As an additional complication, district councils have been the Local Government Act 1972). If, however, a local authority
allowed to apply for a charter giving themselves the status of has overstepped the limits of its legal powers, a private citizen
a borough, although this is solely a ceremonial matter. Some who is aggrieved may apply to the courts for an order quashing
parishes have been allowed to call themselves ‘towns’ and have a local authority decision, requiring the local authority to keep
appointed ‘town mayors’, again with no real legal significance. within its powers or prohibiting the local authority from acting
The parishes (‘communities’ in Wales) have very few substantial unlawfully. Thus, a ratepayer in Fulham successfully obtained
functions, but may provide and maintain recreation grounds, bus an order against the borough council, requiring the council to
shelters, and roadside seats. The Chairman and Vice-Chairman stop spending ratepayers’ money on the provision of a service
of a parish council must now be chosen from elected, as com- for washing clothes for members of the public, when the council
pared with appointed, councils. New parishes within an area may only had statutory powers to provide a service to enable mem-
arise as a result of community governance reviews. bers of the public to wash clothes themselves (Attorney General
v Fulham BC [1921] 1 Ch 440). The court can also grant an
1.08 In Wales there are no metropolitan areas. The former injunction or make a declaration.
structure of 8 counties divided into 37 districts, with councils
at each level, was abolished on 1 April 1996, since when all 1.11 The Local Government (Contracts) Act 1997 sets out statu-
local administration has been undertaken by 22 new unitary tory powers for a local authority to enter into contracts. Local
authorities (11 counties and 11 county boroughs) under the authorities were granted wide general powers under section 2 of
Local Government (Wales) Act 1994. The Government of Wales Part I of the Local Government Act 2000 to do anything which
Act 1998 provided for the devolution of certain powers from they consider likely to achieve the promotion or improve-
ministers to the National Assembly for Wales and this is now ment of the economic, social or environmental well-being of
subject to the Government of Wales Act 2006 which separates their area. This well-being power now only applies to local
the executive and legislative functions of the Assembly and authorities in Wales and must be exercised having regard to
Welsh Ministers. In effect, the Welsh Assembly and Welsh local well-being plans published under the Well-being of Future
Ministers have taken over the responsibilities that the Secretary Generation (Wales) Act 2015. Local authorities in England have
of State for Wales previously exercised in Wales and local been granted a new general power of competence under the
government measures taken in Wales include those under the Localism Act 2011. This now enables them to do anything that
Local Government (Wales) Measures in 2007 and 2011 and the an individual may generally do, subject to the limits set by the
Local government 61

provisions within the Localism Act 2011 and other legislation. Executive Arrangements and Committees
Local authorities are required to perform a significant number
of other specific duties by various pieces of legislation affecting 1.15 Part 2 of the Local Government Act 2000, as amended by
its functions which are too numerous to list here. In the exer- the Local Government and Public Involvement in Health Act
cise of their functions, local authorities are subject to the public 2007, previously required each local authority in England and
sector equality duty in the Equality Act 2010. They must have Wales to adopt one of the three specified forms of ‘executive
due regard to the need to eliminate discrimination, harassment, arrangements’ or alternative arrangements permitted by regula-
victimisation or any other conduct that is prohibited under the tions. These dealt with the creation and operation of an executive
Equality Act 2010 and to advance equality of opportunity and for the authority where certain of the authority’s functions are
foster good relations between persons who share a relevant the responsibility of the executive.
protected characteristic under that Act and those who do not
share it. Under the Legislative and Regulatory Reform Act 1.16 This structure continues to apply to local authorities in
2006, the Regulation Enforcement and Sanctions Act 2008 and Wales, subject to the Local Government (Wales) Measures Act
the Deregulation Act 2015, when exercising specified regulatory 2011 which (amongst other things) removes the ability to operate
functions (such as planning enforcement), a local authority must alternative arrangements and provides for the designation of one
also have regard to the principle that the regulatory function of the council officers as head of democratic services. Executive
should be carried out in a way which is transparent, accountable, arrangements must provide for the appointment of overview and
proportionate and consistent and it should be targeted only at scrutiny committees to monitor and review the performance of
cases in which action is needed. the authority’s functions and the local authority must prepare a
constitution, with its standing orders and code of conduct, and
keep it up to date.
Human Rights
1.17 In England, the Localism Act 2011 introduced a new
1.12 The enactment of the Human Rights Act 1998 has added a Part 1A into the 2000 Act providing for greater flexibility. Local
significant new dimension to the statutory duties of local authori- authorities may operate either one of two types of executive
ties. The basic purpose of the Act is ‘to give further effect to arrangements (a directly elected mayor and a cabinet executive,
rights and freedoms guaranteed under the European Convention or a leader of the council and a cabinet executive), or a commit-
of Human Rights’. Of particular relevance to local authorities, tee system or other permitted arrangement.
the Act provides that it is unlawful for a public authority to act
in a way which is incompatible with any Convention right and 1.18 The Local Government Act 2000 (as amended and sup-
that legislation has to be read and given effect to in a way which plemented by relevant legislation respectively for England and
is compatible with the Convention rights. Wales) sets out the functions that are, and are not, and may (but
do not have), to be the responsibility of the executive of the
Freedom of Information council. In particular, the functions of town and country plan-
ning; licensing and registration; health and safety at work; elec-
1.13 Local authorities, like other public bodies, are now subject tions; community governance; pensions and by-laws are (among
to the requirements of the Freedom of Information Act 2000 others) expressly stated not to be executive responsibilities. Such
(FOIA) and the Environmental Information Regulations 2004 functions will generally continue to be dealt with by the system
(SI 2004/339l) (EIR). This legislation gives important rights established under the Local Government Act 1972.
to the public to obtain information held by local authorities
(subject to certain specified statutory exemptions) which may 1.19 In practice this will mean decisions are normally taken
be particularly relevant to the local authority’s decision-making pursuant to committee system. Committees, consisting of named
in respect of development applications. Where a local authority councillors, are usually considerably smaller in membership than
refuses a request for information under the FOIA or the EIR, the council as a whole and are entrusted with specified func-
there is a right to pursue a complaint with the Information tions of the council. There are no general rules, but a council
Commissioner, and thereafter a right of appeal against an of, say, 48 members may place about 12 councillors on each of
Information Commissioner’s decision notice to the First-Tier its committees. Recently there has been a tendency to streamline
Tribunal (General Regulatory Chamber). For further details of committee organisation, leaving more routine matters to the
these rights, see: the Information Commissioner’s website www. discretion of officers. Thus, every county council will generally
ico.gov.uk; and that of the Tribunal: https://www.gov.uk/courts have a planning committee and a finance committee, and most
-tribunals/first-tier-tribunal-general-regulatory-chamber district councils will have a planning committee and licensing
committee, although details will vary from authority to author-
ity. Every matter requiring a council decision within the terms
Offcers of reference of a particular committee is first brought before the
1.14 All local authorities are alike in that they employ officers committee. The committee then considers the matter and either
and other staff to carry out their instructions, while the elected recommends a certain decision to the council, or may itself
members assembled in council make decisions as to what is to make the decision. Whether the committee decides on behalf of
be done. Officers of the authority – chief executive, solicitor, the council depends on whether the council has delegated to the
treasurer, surveyor, architect, planning officer, and many others – committee power to take the decision on its behalf, either in that
play a large part in the decision-making process: they advise the particular matter, or in matters of that kind, or falling within a
council on the courses of action open to them, and also on the particular class.
consequences of taking such actions. When a decision has been
taken, it is then the duty of appropriate officers of the council 1.20 Section 101 of the Local Government Act 1972 confers on
to implement it: to notify persons concerned and to take any all local authorities power to arrange for any of its functions
executive decisions or other action necessary to give effect to the (except levying a charge or raising a loan) to be discharged
main decision. It is sometimes said that the officers give advice by a committee, a sub-committee, or an officer. However, this
and take action, while the council decides all matters of policy; does not authorise the delegation of any function to a commit-
although basically true (for statutes almost invariably confer the tee comprising only one member: R v Secretary of State for the
power to exercise discretion on the authority itself) this does Environment, exp. London Borough of Hillingdon [1986] 2 All
not clarify what happens in practice. ‘Policy’ is incapable of ER 273.
precise definition. What is policy for some local authorities in
some circumstances may be regarded as routine administration 1.21 Proceedings in committee are normally held in public and
by other authorities in different circumstances. tend to be informal. Officers attend, volunteer advice, and often
62 Statutory authorities in England and Wales

take part in the discussion, although any decision is taken on the enable allegations to be investigated and decisions to be made
vote or assent of the councillors present. Council meetings and after taking into account the views of at least one independ-
meetings of specified committees, such as the licensing commit- ent person. The authority has no power to suspend, expel or
tee, are more formal; the press and members of the public are disqualify a member for breach of its code, but can make find-
entitled to be present, unless they have been excluded by special ings of a breach and require an apology to be issued or other
resolution of the council passed because of the intention to dis- steps to be taken which are proportionate to the breach: see eg
cuss exempted information, such as facts regarding individual R(Taylor) v Honiton Town Council [2016] EWHC 3307(Admin);
council employees (Local Government (Access to Information) and R(Harvey) v Ledbury Town Council [2018] EWHC 1151
Act 1985); and proceedings are conducted in accordance with (Admin). A monitoring office for each authority must establish
the council’s standing orders. Officers do not speak at a council and maintain a register of interests of members which is available
meeting unless their advice is expressly requested, and as much for inspection and published on its website. Members must notify
business consists of receipt of reports from committees, discus- the monitoring officer of any disclosable pecuniary interest (as
sion tends to be confined to more controversial topics. defined in the Localism Act 2011) and this will affect the mem-
ber’s ability to participate in meetings that relate to that interest.
1.22 Because of the presence of the press and public, party poli- Certain interests which might lead to a member being subject
tics tend to be more obvious at council meetings. Sometimes in to violence or intimidation may be withheld from publication.
committee, members from opposing political parties will agree, Criminal offences are created under section 34 of the Localism
and members of a single party may disagree with one another. In Act 2011 if a person, without reasonable excuse, fails to comply
recent years, however, there has been a tendency for authorities with obligations in relation to specified interests set out in the
to be more closely organised on party political lines. When this 2011 Act.
occurs, ‘group’ meetings may be held preceding the committee
meetings. Thus on important matters, decisions at committee
meetings can be ‘rubber stamps’ of decisions already taken at
Offcers’ powers
the group meeting of the political party in power on the council. 1.26 Local authorities are required to appoint such officers as
It has been held that it is legitimate, when deciding how to vote, they think necessary for the proper discharge of the authority
for a councillor to have regard to party loyalty and party policy, of its functions and every such appointment must be on merit.
provided they do not ‘dominate so as to exclude other consid- All discretionary powers are conferred on a local authority in
erations or deprive the councillor of real choice: R v Waltham the first instance, but decisions may also now be made pursu-
Forest London Borough Council, ex p. Baxter [1988] 1 QB 419. ant to the Executive arrangements described above; and under
However, the Local Ombudsman’s finding of maladministration section 101 of the Local Government Act 1972, every local
where members of a planning committee were heavily influ- authority has wide powers to delegate any of its discretionary
enced by party political loyalty, which was not material to the decisions to any of its officers; a power which is often used,
planning application before them, was upheld by the court: R v especially in planning. But there must always be a clear del-
Local Commissioner for Administration in the North and North egation before an officer can decide on behalf of the authority.
East England, exp. Liverpool City Council (2000) 2 LGLR 603. Therefore, when an officer of a council who was asked for
information as to the planning position in respect of a particular
1.23 The law relating to the conduct of members was radically piece of land carelessly gave the wrong information, saying that
overhauled by the Local Government Act 2000. Part III of that planning permission was not required, it was held by the courts
Act created a statutory scheme for ethical regulation of mem- that the council were not bound by this statement. It could not be
bers. The Secretary of State directed that all local authorities taken as the decision of the council, as the officer had no power
must develop their own codes of conduct, although the Secretary to act on their behalf in that case: Southend-on- Sea Corporation
of State produced a model code and the mandatory provisions of v Hodgson (Wickford) Ltd [1961] 2 All ER 46. This decision is
it had to be included in the local authority’s code. Each member still good law in circumstances where powers have not been
was under a duty to comply with the authority’s code. Ethical expressly delegated to the officer concerned (see e.g. Western
issues were to be considered by the local authority’s standards Fish Products Ltd v Penwith DC [1979] 77 LGR 185 and now
committee, but complaints about conduct of members could be R v East Sussex County Council, ex p. Reprotech (Pebsham) Ltd
made to the Standards Boards for England and Wales which [2002] UKHL 8; [2003] 1 WLR 348).
would generally investigate complaints through local authority
Ethical Standards Officers. However council members were no 1.27 Local authorities do not stand outside the common law in
longer subject to the former surcharge provisions which rendered respect of acts of negligence by their officers and employees.
them potentially personally liable for Council decisions. However, the House of Lords has held that a local authority
is not generally liable in negligence to owners or occupiers
1.24 The system contained in Part III of the 2000 Act now only of buildings for failings in the authority’s enforcement of the
applies to Wales, with the Welsh Assembly having made a code Building Regulations concerning the defective construction of
of conduct for Wales. Each member of a relevant authority in those buildings: Murphy v Brentwood District Council [1990]
Wales is under a duty to comply with that authority’s code; 2 All ER 908. Local planning authorities are also not liable
and each relevant authority (other than a community council) for negligence in the grant of planning permission: see Strable
must establish a standards committee. The Public Services v Dartford Borough Council [1984] JPL 329; Lam v Brennan
Ombudsman for Wales may issue guidance on investigations [1997] 3 PLR 22; but cf Kane v New Forest District Council
relating to standards and will conduct investigations into alle- [2001] EWCA Civ 878 . Officers enjoy some statutory immunity
gations of non-compliance. The Welsh Ministers can make from personal liability.
regulations about investigations. There is a system of adjudica-
tion tribunals whose panel members are appointed by the Welsh 1.28 An alternative non-judicial method by which an aggrieved
Ministers to decide on breaches of the relevant code of conduct individual may seek redress against a local authority’s actions
and the imposition of sanctions. The Welsh Assembly has also or inaction in England is to make a complaint to the Local
promulgated a Code of Conduct for qualifying employees. Government and Social Care Ombudsman under the Local
Government Act 1974 (as amended) (see www. lgo. org.uk).
1.25 In England, Chapter 7 of Part I of the Localism Act Complaints in relation to social housing in England are dealt
2011 made new provisions for standards for local authorities in with by the Housing Ombudsman under the Localism Act 2011.
England and abolished the Standards Board for England. Every If the ombudsman finds that a complainant has suffered injustice
local authority must have a code of conduct consistent with as a consequence of maladministration by the local authority,
7 specified core principles. Breaches of that code are matters he or she may publish such a finding and recommend a suitable
for the relevant local authority pursuant to arrangements which remedy (which can include financial compensation). The local
Local government 63

authority are obliged to have regard to the report, but they cannot Mayor must prepare and publish a ‘spatial development strategy’
be compelled in law to implement the Ombudsman’s recommen- (SDS). He is empowered to direct the local planning authority of
dations to alleviate the injustice. a London Borough Council to refuse an application for planning
There is a separate Public Services Ombudsman for Wales permission of a prescribed description in any particular. He must
under the Public Services Ombudsman (Wales) Act 2019 in monitor the implementation of the SDS and monitor the UDP
Wales (see www.ombudsman.wales) which, in addition to inves- of each London Borough Council so that it is in accordance
tigating administration by local authorities, also covers com- with the SDS. Similarly, within the metropolitan areas outside
plaints concerning the Health Service, the Welsh Administration London, the metropolitan district councils fulfil both local plan-
and Social Housing. ning and mineral planning functions.

1.31 For non-metropolitan areas where there is a unitary author-


Finding the right offcer ity, those unitary authorities are the local planning authority for
1.29 Architects in the course of their professional business are all purposes within its area.
obliged to have dealings with numerous local authority officials.
Table 7.1 shows the purposes for which a permission, licence, 1.32 For non-metropolitan areas where there is a two-tier local
or certificate may have to be obtained from the local authority government structure, the vast majority of development control
identifying the officers initially responsible (see Chapters 9 and functions are vested in the districts.
11). But first of all it is essential to ascertain the authority in
whose area the site lies. 1.33 In Wales, the local planning authority is the county council
or the county borough council. All local planning authorities
and the National Parks Authority within Wales are required to
Local government: distribution prepare and maintain unitary development plans for their areas.
of planning functions
1.30 Within Greater London, the London Borough Council (or, 1.34 Within the national parks, the functions formerly vested
as the case may be, the City of London) is both the local plan- in the Planning Board in the Peak District and Lake District
ning authority and the mineral planning authority. The London Parks, and elsewhere in the county planning authority, now vest
in the National Parks authority for that area (section 4A, Town
and Country Planning Act 1990). In relation to tree preservation
Table 7.1 Responsibilities
of local authority officers
and replacement (sections 198 to 201, 206 to 209, and 211 to
Subject matter Officer Local 214) and the powers under section 215 (power to require proper
authority maintenance of land) the district planning authority whose
area includes that part of the Park has concurrent jurisdiction
Planning Planning officer or surveyor DC (section 4A(2)).
Building regulations Building inspector or surveyor DC
Development in a private Surveyor CC 1.35 Within the Norfolk and Suffolk Broads, the Broads
street Authority is the sole district planning authority for non-county
Surface water sewerage Engineer SU matters (Town and Country Planning Act 1990, section 5).
Sewer connections Engineer SU
Blocked sewers Engineer SU 1.36 Overlooking this general structure, the Secretary of State
Housing grants; housing Environmental health officer/ DC for Housing, Communities and Local Government has wide-
generally practitioner or (sometimes) ranging supervisory powers. There is a right of appeal to the
surveyor Secretary of State from all adverse development control deci-
Height of chimneys or Environmental health officer/ DC sions and enforcement notices, although not from the issue of
other clean air matters practitioner breach of condition notice. The Secretary of State may remove
Petroleum licensing; most Petroleum inspector (often CC or DC
jurisdiction from the local planning authority in particular cases
other licensing environmental health officer
by calling a planning application in for determination (Town and
or surveyor)
Country Planning Act 1990, section 77). The Secretary of State
Regulated entertainment Licensing officer*
also oversees the making and adoption of development plans,
licences
with powers to prevent adoption of such plans (although these
Alcohol licences Licensing officer*
powers are rarely exercised).
Late Night Refreshment Licensing officer*
licences
1.37 The basic feature of planning control in England and Wales
is the requirement for planning permission for “development”
Key: CC, county council; DC, district council; SU, sewerage undertaker
as defined in section 55 of the Town and Country Planning Act
Notes 1990. Development ordinarily consists of either building opera-
A company operating under the Water Act 1989, whose functions may be exercised tions or a material change in the use of the land. Applications
by the district council under an arrangement with the sewerage undertaker. for planning permission are generally determined in accordance
London. In Greater London, in all cases (except for liquor licences) the responsible with the plan-led system where there is a presumption that
authority is the London Borough Council or the Common Council of the City. such applications will be determined in accordance with the
Planning. In planning matters the authority given above should be contacted in development plan, unless material considerations indicate oth-
the first instance, although the county council may ultimately make the decision. erwise. This plan-led system has been radically overhauled by
Roads. In the counties highway functions are commonly administered by district the Planning and Compulsory Purchase Act 2004, the Planning
or divisional surveyors, responsible to the county surveyor but stationed locally Act 2008 and the Localism Act 2011 under which the former
often at district council offices. system of local plans, structure plans, or unitary development
In the case of trunk and special roads (motorways) the highway authority is the plans for unitary authorities, and Regional Planning Guidance /
Secretary of State for Transport, but the local county surveyor acts as his agent Regional Spatial Strategies have been replaced by a new system
at local level. Highways England is the executive agency of the Department for of: Local Development Schemes which specify which documents
Transport responsible for the maintenance and operation of roads for the Secretary
are “development plan documents” that form part of the statutory
of State is the highway authority. Maintenance of urban roads may be claimed
by the DC.
development plan for an area; and “neighbourhood plans” where
Under the Local Government (Miscellaneous Provisions) Act 1982, several they have been made for a neighbourhood area..
activities are made subject to licensing (e.g. acupuncture, tattooing, take away food
shops, etc.). These provisions are administered by the district council. 1.38 Local Development Schemes are prepared by local plan-
*Under Licensing Act 2003. ning authorities. They set out a programme for the production
64 Statutory authorities in England and Wales

of specified “local development documents”. Local development to challenge a local authority in relation to the delivery of
documents can be either “development plan documents” or services and the requirement on local authorities to maintain a
“supplementary planning documents”. Only “development plan list of assets of community value and the importance of social
documents” will form part of the statutory development plan value when considering best value. The Public Services (Social
and these are required to go through the process of independent Value) Act 2012 requires authorities in England to consider how
examination before adoption. These “development plan docu- the procurement of services will improve the economic, social
ments” should set out the local planning authority’s policies on and environmental well-being of an area. The Local Government
the development of use and land in its area. This will ordinar- (Wales) Measure 2009 as amended in Wales in the system of
ily be in a document referred to as the Local Plan. There will improvement authorities.
usually be separate development plan documents to deal with
waste and mineral developments prepared by the relevant local 1.43 From 1974 to 1989 the provision and maintenance of
authority (usually the County Council outside London or in sewers and sewerage disposal, together with water supply
metropolitan areas). More detail on the workings and formula- and distribution and the prevention of river pollution, was the
tion of local development schemes in England is provided in the responsibility of special authorities: the ten regional water
Government’s national planning policy: the National Planning authorities (nine in England, one in Wales). Under the Water Act
Policy Framework and the Government’s online Planning 1989 the water industry was privatised and as a consequence the
Practice Guidance. sewerage functions of the former water authorities have passed
to successor companies, which are in most instances also respon-
1.39 The Localism Act 2011 created the concept of “neighbour- sible for water supply, except in those areas where this was
hood plans” which form part of the statutory development plan formerly the responsibility of statutory water companies which
for the neighbourhood area where they have been made. A remain in existence. The Secretary of State for the Environment,
neighbourhood plan must be prepared by a qualifying body for Food and Rural Affairs is responsible for controlling the water
a prescribed neighbourhood area and it is subject to independent industry in England. The Welsh Assembly has taken over many
examination and then a local referendum before it is treated as of those functions for Wales under devolved arrangements.
being made. Water and sewerage undertakers are forbidden from causing
river pollution, the prevention of which is now the responsibility
1.40 Special provision is made in respect of development affect- of the Environment Agency in England and Natural Resources
ing statutorily listed buildings and designated conservation areas Wales in Wales, along with the obligations articulated in the
under the Planning (Listed Buildings and Conservation Areas) Water Environment (Water Framework Directive) (England
Act 1990. Buildings of special architectural or historic inter- and Wales) Regulations 2017 . The successor companies are
est may be listed under section 1 of that Act. There are over constituted under the regime of the Companies Acts and are
500,000 listed buildings in England and Wales. Listed building appointed by the Secretary of State to act as water and/or sewer-
consent for specific works affecting listed building may need to age undertakers.
be obtained under section 10 of that Act. In addition, when con-
sidering whether to grant planning permission for development
which affects a listed building or its setting, special regard must 2 Other statutory bodies
be paid to the desirability of preserving the building or its setting
or any features of special architectural or historic interest which
it possesses under section 66 of that Act. Conservation areas are
Historic England and Cadw
areas designated by a local planning authority of special archi- 2.01 The Historic Buildings and Monuments Commission for
tectural or historic interest the character and appearance of which England, previously known as ‘English Heritage’ but now known
it is desirable to preserve or enhance under section 69 of that as ‘Historic England’, was established under section 32 of the
Act. Certain works require specific consent. In addition, when National Heritage Act 1983. It is an executive non-departmental
considering whether to grant planning permission in respect of public body sponsored by the Department of Culture, Media and
buildings or other land in a conservation area, special attention Sport. As a body corporate, its commissioners are appointed by
must be paid to the desirability of preserving or enhancing the the Secretary of State for Culture, and commonly serve a four
character or appearance of that area under section 72 of that Act. year term, subject to a maximum of 5 years. Its functions include
The approach both to “designated heritage assets” such as statu- making grants in relation to historic buildings and conservation
torily listed buildings and conservation areas and “undesignated areas, acquiring historic buildings, acquiring or becoming the
heritage assets” is the subject of national policy in England in guardian of ancient monuments, and undertaking archaeologi-
the National Planning Policy Framework. cal investigation and publishing the results. It may prosecute
for offences under the Ancient Monuments and Archaeological
Areas Act 1989 or under the Planning (Listed Buildings and
Local government: other functions Conservation Areas) Act 1990. Within Greater London, it has the
1.41 Outside London, county councils are responsible for fire power, concurrently with the London Boroughs, to take enforce-
services, main and district highways, refuse disposal, and a few ment action against breaches of listed building control (Planning
other functions. Outside the metropolitan areas county councils (Listed Buildings and Conservation Areas) Act 1990, section 45).
are also responsible for education and welfare services, which
in the metropolitan areas are the responsibility of the district 2.02 Its duties are, so far as practicable in exercising its func-
councils. tions: to secure the preservation of ancient monuments and
historic buildings in England; to promote the preservation and
1.42 All district councils are responsible for housing, refuse enhancement of the character and appearance of conservation
collection, drainage, clean air and public health generally (but areas situated in England; and to promote the public’s enjoy-
not sewerage and water supply), development control, parks ment and advance their knowledge of ancient monuments and
and open spaces, and building controls, etc. A district council historic buildings situated in England (section 33 of the National
may also (by arrangement with the county council) undertake Heritage Act 1983).
the maintenance of urban roads (other than trunk roads), bridle-
ways, and footpaths within its district. Detailed provisions as 2.03 Historic England plays an important role in the listing
to the tendering of services by local authorities are now set out of buildings. Although ultimate responsibility for deciding
in the Local Government Act 1999, the Local Government Act which buildings should (and should not) be listed rests with the
2003, the Localism Act 2011 and the Public Services (Social Secretary of State, Historic England may compile lists of build-
Value) Act 2012 in England in the best value regime for local ings of special architectural or historic interest for the Secretary
authorities. These provisions now include the community right of State’s approval, and must be consulted by him before he
Other statutory bodies 65

compiles, approves, adds to or modifies any such list (Planning functions previously carried out by: the National Rivers Authority;
(Listed Buildings and Conservation Areas) Act 1990, section 1). the Waste Regulation Authorities; HM Inspectorate of Pollution;
and certain functions of the Secretary of State in relation to
2.04 Historic England must be consulted by the planning author- radioactive substances, ‘special category effluent’ and sludge.
ity on a range of applications, including: the demolition in whole The Environment Agency has functions with respect to pollution
or part, or the material alteration, of a listed building in Greater control, water resources, environmental duties with respect to
London; development likely to affect the site of a scheduled mon- sites of special interest and flood defence.
ument or development likely to affect any Grade I or Grade II reg-
istered garden or park of special historic interest: Article 18 and 2.11 Its principal aim in discharging its functions, as set out
Schedule 4 of the Town and Country Planning (Development in section 4 of the Environment Act 1995, is ‘so to protect or
Management Procedure) (England) Order 2015 (SI 2015/595). enhance the environment, taken as a whole, as to make the con-
tribution towards attaining the objective of achieving sustainable
2.05 Historic England publishes a wide range of advice on the development’, in which regard the Agency receives guidance
care of historic buildings, such as Listed Buildings and Curtilage from Ministers on the extent of the contribution the Agency is
(2018), Conservation Principles, Policies and Guidance (2018), expected to make.
The Setting of Heritage Assets (2017) and Managing Significance
in Decision-Taking in the Historic Environment (2015). Early 2.12 The Agency must be consulted by the planning authority on
consultation with Historic England will often be useful. any application for development involving: mining operations;
the carrying out of works or operations in the bed of, or within
2.06 The functions under the Planning (Listed Buildings and 20 metres of the top of a bank of, a main river which has been
Conservation Areas) Act are conferred on the Welsh Government notified to the local planning authority by the Agency as a main
in respect of Wales. The equivalent heritage advisory body to river; culverting or controlling the flow of any river or stream;
Historic England for Wales is Cadw: see http://cadw.gov.wales/. the refining or storage of mineral oils or derivatives; the deposit
Consultation requirements in Wales in respect of applications of refuse or waste; use of land as a cemetery; fish farming; (with
affecting heritage assets are set out in the Town and Country certain minor exceptions) the retention, treatment or disposal
Planning (Development Management Procedure) (Wales) Order of sewage, trade waste, slurry or sludge; and, other than for
2012 (SI 2012/801). minor development, land in area within Flood Zones 2 or 3, or
Flood Zone 1 if it has critical drainage problems and has been
notified by the Agency; and land of more than 1 hectare: Town
Natural England and the and Country Planning (General Development Procedure) Order
Natural Resources Wales 1995, Article 10.
2.07 Section 1 of the Natural Environment and Rural
Communities Act 2006 established Natural England, an inde- 2.13 The functions carried out by the Environment Agency in
pendent body replacing English Nature and the Countryside England were previously carried out by the Environment Agency
Agency. Nature conservation functions previously exercisable Wales in Wales, but are now carried out Natural Resources
in respect of Wales by the Nature Conservancy Council, then Wales. They are largely mirrored by those carried out by the
the Countryside Council for Wales, were transferred to Natural Scottish Environment Protection Agency for Scotland.
Resources Wales on 1 April 2013.

2.08 These two bodies are responsible for the establishment,


Sports Council for England and
maintenance and management of nature reserves, the notifica- Sports Council for Wales
tion and protection of (SSSIs), the provision of advice for the 2.14 The Sports Council for England and the Sports Council
Secretary of State or the Welsh Assembly on the development for Wales, known respectively as ‘Sport England’ and ‘Sport
and implementation of policies for, or affecting, nature conserva- Wales’ are the government agencies responsible for developing
tion in their areas, the provision of advice and the dissemination a world-class community sport system in England and Wales.
of knowledge about nature conservation in their areas, and the They must be consulted by local planning authorities on an
commissioning or support of research which is relevant to their application for development which is likely to prejudice or lead
functions. They also advise on any endangered animal or plant to the loss of the use of land being used as a playing field, or
which should be added to, or removed from, the lists of protected is on land which has been used as a playing field at any time in
species. The general purpose of Natural England is to ensure that five years before the making of the planning application where
the natural environment is conserved, enhanced and managed for the land remains undeveloped, or on land which is allocated for
the benefit of present and future generations. playing field use, or involves replacement of a grass pitch with
an artificial surface: see Article 18 and Schedule 4 of the Town
2.09 Natural England or Natural Resources Wales must be and Country Planning (Development Management Procedure)
consulted by planning authorities before permission is granted (England) Order 2015 (SI 2015/595) and the Town and Country
for development of land in a SSSI, or in any consultation area Planning (Development Management Procedure) (Wales) Order
around a SSSI, or for development which is likely to affect 2012 (SI 2012/801).
a SSSI or major development in an area of particular natural
sensitivity or interest which may be affected: see Article 18 and
Schedule 4 of the Town and Country Planning (Development Health and Safety Executive
Management Procedure) (England) Order 2015 (SI 2015/595) 2.15 The Health and Safety Executive (HSE) was established
and the Town and Country Planning (Development Management by section 10 of the Health and Safety at Work etc Act 1974.
Procedure) (Wales) Order 2012 (SI 2012/801). Consultation The HSE must be notified of development within an area which
areas defined by English Nature may extend up to a maximum has been notified to the local planning authority by the HSE
of 2 kilometres from the boundary of the SSSI. because of the presence within the vicinity of toxic highly reac-
tive, explosive or inflammable substances, where the develop-
The Environment Agency and ment involves residential accommodation, or more than 250m2
of retail space, or more than 500m 2 of office space, or more
Natural Resources Wales than 750m2 of industrial processes, or it is likely to result in a
2.10 The Environment Agency was established under the material increase in the number of persons working within the
Environment Act 1995 as a body corporate, and has inherited notified area.
66 Statutory authorities in England and Wales

3 Statutory undertakers: 3 The general rule does not permit a communication directly
with a storm-water overflow sewer (section 106(2)(c)).
connections to services 4 Where separate public sewers are provided for foul and for
surface water, foul water may not be discharged into a sewer
3.01 When starting to design a building for a client, any architect provided for surface water, and surface water may not, with-
is obliged at an early stage to consider the availability of mains out the consent of the sewerage undertaker, be discharged
services and the rights of the client as landowner regarding the into a sewer provided for foul water (section 106(2)(b)).
various statutory undertakers: sewer and highway authorities, It is particularly important that an architect should know
water, gas, and electricity supply undertakings, and possibly whether the undertaker’s sewerage network is designed on
the water undertaker if it is proposed to use a water course as the separate system, as he or she may in turn have to pro-
a means of disposing of effluent from the building. The legal vide a separate drainage for the building being designed.
provisions regulating these matters are discussed below. 5 The right is subject to section 106A of the 1991 Act in respect
of a sustainable drainage system which required approval
Sewers under Schedule 3 to the Flood and Water Management Act
2010.
3.02 Sewers are generally channels (artificial or natural) used
for conveying effluent (i.e. waste liquids - clear water, surface
water from covered surfaces, land or buildings, foul water, or Procedure
trade effluent) from two or more buildings not within the same 3.06 A person wishing to connect his or her sewer or drain to a
curtilage. Curtilage is normally, in non-technical terms, equiva- public sewer must give the sewerage undertaker written notice
lent to the natural boundaries of a particular building; thus the of the proposal, and the undertaker may within 21 days of such
curtilage of an ordinary dwelling house would often include the notice refuse to permit the making of the communication if the
garage, the garden and its appurtenances, and any outbuildings. mode of construction or condition of the drain or sewer does not
By contrast, a conduit which takes effluent from one building satisfy the standards reasonably required by the undertaker, or is
only or from a number of buildings all within the same curtilage, such that the making of the communication would be prejudicial
is in law a ‘drain’ (see the Public Health Act 1936, the Water to their sewerage system (section 106(4) of the Act), but they
Industry Act 1991 and the Building Act 1984). This distinction may not so refuse for any other reason. Any dispute with the
is important, as a landowner never has any legal right to let his undertaker under these provisions may be settled by way of an
effluent flow into a drain belonging to another person (even if application to Ofwat, the Water Services Regulation Authority.
that other person is a local authority) unless he has acquired such
a right by at least 20 years’ use or as the result of an agreement 3.07 Alternatively, where proposals have been served on the
with the other person. The same rule applies to a private sewer; undertaker, the undertaker may within 14 days of service give
but if the conduit to which he proposes to drain his effluent is notice that it intends to make the communication to the public
a public sewer, he will have certain valuable rights to use it. sewer itself (section 107 of the Act) if no agreement was entered
into under section 104 of the Act which provided for that per-
3.03 All public sewers are vested in (i.e. owned by) the sewerage son to make the communication. The private landowner is then
undertakers. A sewer is a public sewer if it existed as a sewer obliged to permit the undertaker to do the work of making the
(regardless of who constructed it) before 1 October 1937, or if house drains or sewer connect with the public sewer, and has to
it was constructed by a local authority after 1 October 1937 and bear the sewerage undertaker’s reasonable expenses so incurred.
before 1 April 1974, or by a water authority before 1 November The undertaker is not obliged to make the communication until
1989, or by a sewerage undertaker after 1 November 1989 and its reasonable estimate of the cost has been paid, or security for
was not designed to serve only property belonging to a local such payment has been given. Disputes over the reasonableness
authority (e.g. a council housing estate), or if it has been adopted of any charge and security for the charge may be referred to
as a public sewer since 1 October 1937 (see Water Act 1989 and Ofwat for determination.
Water Industry Act 1991).
3.08 When making the communication, the undertaker (or the
Rights to connection private owner if allowed to do the work him- or herself) has
power as necessary to break open any street (section 107(6) of
3.04 By section 106 of the Water Industry Act 1991, the owner the Act).
or occupier of any premises in the area of a sewerage undertaker,
or the owner of any private sewer which drains premises, has
a right to cause his or her own drains or private sewer to com- Approval of drainage
municate with the public sewers or public lateral drains (which 3.09 The arrangements proposed to be made for the ‘satisfac-
satisfy sewer standards) of that undertaker and to discharge foul tory provision’ for drainage of a building (except those relating
and surface water from his premises to it. Connecting sewers or to sustainable drainage requiring approval under Schedule 3 to
drains from the premises to the public sewer must be constructed the Flood and Water Management Act 201) must be approved by
at the expense of the landowner concerned. Sometimes – but not the district council or London Borough Council at the time when
often – the sewerage undertaker may itself construct ‘laterals’, or the building plans are considered under the Building Regulations
connecting drains leading from the main sewer to the boundary (see Building Act 1984, section 21 and Chapter 9). Disposal of
of the street to which house drains may be connected. the effluent may be to a public sewer, or to a cesspool or private
septic tank, and in the case of surface water, to a highway drain
There are a few exceptions to this general rule: or a watercourse or to the sea. In this instance it should be noted
that the powers remain with the district council and have not
1 No substance likely to injure the sewer or to interfere with been transferred to the sewerage undertaker.
the free flow of its contents, or to affect prejudicially the
treatment and disposal of its contents; no chemical refuse 3.10 If there is no existing main sewer into which the prop-
or waste stream or liquid of a temperature higher than erty could be drained, the owner or occupier (usually with the
43 degrees Celsius which is dangerous, the cause of a owners, etc., of other premises) may requisition the sewerage
nuisance or injurious or likely to cause injury to health; no undertaker to provide a public sewer or lateral drain, under
petroleum spirit or calcium carbide, may be caused to flow section 98 of the Water Industry Act 1991. They must then sat-
into a public sewer (Water Industry Act 1991, section 111). isfy conditions specified by the undertaker, the most important
2 The general rule does not apply to trade effluents of which is likely to be that those requisitioning the sewer shall
(section 106(2)(a)). undertake to meet any ‘relevant deficit’ of the undertaker in
Statutory undertakers: connections to services 67

consequence of constructing the sewer. This section applies only from the sewerage undertaker (see Water Industry Act 1991,
to sewers to be used for domestic purposes. section 118). This is done by the owner or occupier of the
premises serving on the undertaker a ‘trade effluent notice’
under section 119. This must specify (in writing) the nature or
Highway drains composition of the proposed effluent, the maximum quantity
3.11 Landowners have no legal right to cause their drains (or to be discharged in any one day, and the highest proposed rate
sewers) to be connected with a highway drain, and this applies of discharge of the effluent. This notice (for which there is no
equally to surface water drains taking effluent from roads and standard form) is then treated by the undertaker as an application
paved surfaces on a private housing estate. Such drains may, in for their consent to the proposed discharge. No effluent may then
accordance with the statutory provisions outlined above, be con- be discharged for a period of 2 months (or such less time as may
nected with a public sewer, but if it is desired to connect with a be agreed by the undertaker).
drain or sewer provided for the drainage of a highway and vested
in the highway authority, the consent of the highway authority 3.19 A decision, when given by the undertaker, may be a
must first be obtained. The highway authority will normally be refusal to permit the discharge or a consent. A consent may be
the county council or unitary authority. given subject to conditions as to a number of matters ‘includ-
ing a payment by the occupier of the trade premises of charges
3.12 A public sewer may be used to take surface water from a for the reception and disposal of the effluent’, as specified in
highway, but that does not affect its status as a public sewer, section 121 of the Water Industry Act 1991. These conditions
nor does the fact that house drains may in the past have been may be varied (not more frequently than once every two years)
connected (probably unlawfully) with a highway drain convert by direction given by the sewerage undertaker (section 124).
such highway drain into a public sewer (Rickarby v New Forest The owner or occupier of trade premises has a right of appeal
RDC [1910] 26 TLR 586). It is only to public sewers that drains to Ofwat, the Water Services Regulation Authority, against a
or sewers may be connected as of right. refusal of consent to a discharge, against the conditions imposed
in such a consent, or against a direction subsequently given vary-
ing the conditions (Water Industry Act 1991, sections 122 and
Water Discharges into Rivers or the Sea 126). On appeal, the Authority may review all the conditions,
whether or not they have been appealed against, and substitute
3.13 If it is desired to discharge waste, poisonous, noxious for them any other set of conditions or annul any of the condi-
or polluting matters, or trade or sewage effluents into inland tions (section 122(3)).
freshwaters, coastal waters or relevant territorial waters an
environment permit must be obtained from the Environment 3.20 In practice, however, it is frequently desirable for an
Agency in England or Natural Resources Wales in Wales under industrialist’s professional advisers to discuss disposal of trade
the Environmental Permitting (England and Wales) Regulations effluent with the officers of the sewerage undertaker, with a
2016. Permits may be granted subject to conditions. view to an agreement being entered into between the owner of
the premises and the undertaker under section 129 of the Water
3.14 If a person causes or knowingly permits the discharge of Industry Act 1991. This will avoid the need to serve a trade efflu-
any poisonous, noxious or polluting matter or any waste matter ent notice, and better terms can often be obtained by negotiation
or trade effluent or sewage effluent into a watercourse without than by the more formal procedure of the trade effluent notice.
the permission of the Environment Agency, he or she commits The contents of any such agreement becomes public property, as
a water discharge activity offence under regulation 38 of the a copy has to be kept at the sewerage undertaker’s offices and
2016 Regulations. made available for inspection and copying by any person (Water
Industry Act 1991, section 196).
3.15 ‘Trade effluent’ has the meaning in section 221 of the
Water Resources Act 1991 as meaning “any liquid, including
particles of matter and other substances in suspension in the Water supply
liquid” “which is discharged from premises used for carrying 3.21 The water supply authority will be the local water under-
on any trade or industry, other than surface water and domestic taker (a company appointed for a designated area of England
sewage, and for the purposes of this definition any premises and Wales by the Secretary of State (see Water Industry Act
wholly or mainly used (whether for profit or not) for agricul- 1991, section 6), but where before 1989 supply was made by
tural purposes or for the purposes of fish farming or scientific a statutory water company, this may remain in existence. The
research or experiment shall be deemed to be premises used for statutory water companies may have their own private Acts of
carrying on a trade.” Parliament regulating their affairs. Readers dealing in practice
with a particular water undertaking should ascertain whether
3.16 Private landowners have at common law no legal right to there are any local statutory variations.
discharge their sewage or other polluting matter in to the sea;
indeed, as the Crown originally owned the foreshore between
high and low tides, they might not have any legal right to take Rights to connection: domestic premises
their drain or sewer as far as the water. 3.22 If the owner or occupier of premises which consist in the
whole or any part of a building, or any premises on which any
3.17 There must also be no nuisance caused as a consequence, person is proposing to erect any building or part of a building,
and no breach of any requirement in respect of licensable marine within the area served by a water undertaker wishes to have
activities under the Marine and Coastal Access Act 2009. If a supply for domestic purposes, he or she may serve a notice
effluent discharging into the sea does cause a nuisance, any requiring the undertaker to connect a service pipe to those prem-
person harmed can take proceedings for an injunction and/or ises to provide a supply of water for domestic purposes (Water
damages, as in Foster v Warblington UDC [1906] 1 KB 648, Industry Act 1991, section 45).
where guests at a banquet were poisoned from oysters taken
from a bed which had been affected by sewage. 3.23 The obligation is to provide a connection. The undertaker
is only required to lay that part of the service pipe serving the
Trade Effuent Discharges premises which leads from the main to the boundary of the street
into a Public Sewer in which the main is laid or to the stopcock; the laying of the
remainder is the responsibility of the owner or occupier. If the
3.18 Where it is intended to discharge trade effluent as defined supply pipe passes through any property belonging to another
above into a public sewer, consent must first be obtained owner, consent must be obtained in the form of an express
68 Statutory authorities in England and Wales

easement or a licence (see Chapters 2 and 4). Any breaking up for a separate supply for industrial purposes or for conveying
of streets must be effected by the undertakers and not by the gas in bulk, or if they could be connected to any such main by a
owner requiring the supply. pipe supplied and laid by the owner or occupier of the premises.

3.24 Where a notice has been served under section 45, the
undertaker is under a duty to make the connection. This must
Electricity supply
generally be done within 21 days of the service of the connection 3.30 The Electricity Act 1989 provided for the privatising of
notice or, where it is necessary for the person serving the notice the generation and supply of electricity. Ofgem, the Gas and
to lay any part of the service pipe, within 21 days of the date on Electricity Markets Authority, is authorised to license persons to
which notice is given stating that the pipe has been laid. Work generate, transmit, distribute and supply electricity or participate
carried out by the undertaker will be done at the expense of the in the operation of an electricity interconnector, in designated
person requesting the connection, and the undertaker may make areas (1989 Act, section 6).
it a condition of installation that a meter is installed, and may
insist that the plumbing of the premises is compatible with such 3.31 Under section 16 of the 1989 Act, a licensed electricity
a meter (section 47). distributor for an area is under a duty to make or give a connec-
tion to premises where requested by the owner or occupier. The
3.25 Once a connection has been made, the undertaker is under owner or occupier must serve a notice requiring the distributor
a duty to provide a supply of water. The undertaker will have to offer terms, specifying the premises, the date by which the
an excuse for not providing a supply if such failure is due to connection should be made, and the maximum power which may
the carrying out of ‘necessary works’ (Water Industry Act 1991, be required. Where such a request necessitates the provision of
section 60). electrical lines or plant by the public electricity supplier, the sup-
plied may require any expenses reasonably incurred in providing
3.26 This assumes, of course, that the water main in the nearest the supply to be paid by the consumer requesting the supply
street is within a reasonable distance from the house or other (Act 1989, section 19). Any dispute arising out of the above
premises to be served. Where the main is not readily avail- obligations may be referred by either the consumer or supplier
able, the owner of the premises may serve a requisition on the to Ofgem for resolution (Act 1989, section 23).
undertaker requiring them to extend their mains (Water Industry
Act 1991, sections 41–43A). Where such a notice is served the
water undertaker may require the owner to undertake to pay an
Electronic Communications
annual sum, not exceeding the amount (if any) by which the 3.32 The Telecommunications Act 1984 provided for the priva-
water charges payable for the use during that year of that main tisation of British Telecommunications. Today consumers can
are exceeded by the annual borrowing costs of a loan of the obtain communication services from a wide variety of licensed
amount required for the provision of main. Such payments may operators. The terms for the provision of communications ser-
be levied for a maximum of 12 years following the provision of vices depends upon: (1) the licence conditions regulating the par-
the main (Water Industry Act 1991, section 42). Provided those ticular communications company, as approved by Ofcom under
conditions have been satisfied, the water undertaker must extend the Communications Act 2003, the Telecommunications Act
their main within a period of three months (Water Industry Act 1984 and the Wireless Telegraphy Act 2006, and (2) the standard
1991, section 44). contracts offered by the specific company supplying the service.

Rights to connection: non- Construction of mains


domestic premises 3.33 All the utility undertakings have inherent powers to negoti-
ate on terms with private landowners for the grant of easements
3.27 Owners or occupiers of premises requiring a supply of or ‘wayleaves’ to enable them to place mains, cables, wires,
water for industrial or other (non-domestic) purposes or for apparatus, and so on over or under privately owned land. They
premises not including the whole or any part of a building, must also have powers to break open public streets for the purpose
come to terms for a supply with the undertakers or, failing agree- of constructing mains. Water and sewerage undertakers (Water
ment, according to terms determined by Ofwat (Water Industry Industry Act 1991, Schedule 6), gas transporters (Gas Act 1986,
Act 1991, sections 55 and 56). Schedule 3), electricity suppliers (Electricity Act 1989, Schedule
16) and licensed communications operators (Digital Economy
Gas supply Act 2017) all have statutory powers enabling them to place
such mains and apparatus in private land, without the consent
3.28 Following the privatisation of the gas industry in 1986, the of the landowner or occupier concerned, on payment of proper
privileges previously conferred on the British Gas Corporation compensation. Private persons have no such compulsory rights,
have been abolished, and gas is now supplied by a number of although rights may be compulsorily acquired for an oil or other
different companies. Under the Gas Act 1995 and subsequent pipeline under the Pipelines Act 1962.
legislation, Ofgem - the Gas and Electricity Markets Authority
- may grant licences: (1) to public gas transporters, authorising 3.34 All the utility undertakers can also be authorised, without
them to carry gas through pipes to any premises in their author- the consent of the landowner, to place their mains, apparatus,
ised area and to convey gas to any pipeline system operated by etc., on ‘controlled land’ (land forming part of a street or
another transporter; (2) to gas interconnectors; and (3) to gas highway maintainable or prospectively maintainable at public
suppliers and shippers, authorising them to supply gas to speci- expense) or in land between the boundary of such a highway
fied premises. A person may not hold licences for both the public and any improvement line prescribed for the street (New Roads
transport and the supply of gas (sections 6–7). and Street Works Act 1991, Part III).
3.29 If owners or occupiers of premises require a supply of gas
for any purpose (not necessarily domestic), they may serve a 4 Private streets
notice on the public gas transporter for the area specifying the
premises, and the day on which it is desired the service shall 4.01 It is not within the scope of this chapter to describe the
begin – and a reasonable time must be given (Gas Act l986, whole law governing the making up of a private street by county
section 10, as amended by the Gas Act 1995). The transporter councils at the expense of the frontagers to such a street, but
must comply with such a request, but only if the premises are the special rules that regulate the construction of a building in a
within 23 metres of any of their mains, not being a main used ‘private street’ are outlined.
Grants 69

Defnition private street, and they should advise the client to consult his
or her solicitor in any difficult case, or where the exact legal
4.02 A private street may or may not be a highway (i.e. any way, position is not clear.
footpath, bridlepath, or carriageway over which members of the
public have rights to pass and repass). The word ‘private’ does
not mean that it is necessarily closed to the public (although it 5 Grants
may be), but that the street has not been adopted by a highway
authority, and therefore it is not maintainable by them on behalf 5.01 There are circumstances in which a building owner is able
of the public at the public expense. It must also be a ‘street’. to obtain a grant from the local authority (in this case, the dis-
This does not mean, that every country road is a street; it has trict council) for some alteration or extension of his dwelling
been said that are considered below. All statutory provisions considered here
concern dwelling-houses (or flats and so on), but it may be pos-
‘what one has to find before one can determine that the high- sible in development areas and enterprise zones to obtain grants
way in question is a street, is that the highway has become for industrial development.
a street in the ordinary acceptation of that word, because by
reason of the number of houses, their continuity and their 5.02 Up until July 2003, grants were available pursuant to the
proximity to one another, what would be a road or highway Housing Grants, Construction and Regeneration Act 1996. From
has been converted into a street’. 18 July 2003 that Act was substantively repealed and replaced
(Attorney General v Laird [1925] 1 Ch 318 at p. 329) by the Regulatory Reform (Housing Assistance) (England and
Wales) Order 2002.
Advance payments code
5.03 Under the Order, for the purpose of improving living condi-
4.03 As a general principle, before a new building may be tions in their area, local authorities may provide direct or indirect
erected in a new street, the developer must either pay to the assistance to a person for the purposes of enabling him or her:
local authority or secure to their satisfaction (by means of a
bond or mortgage, etc.), a sum equivalent to the estimated cost, (a) to acquire living accommodation;
apportioned to the extent of the frontage of the proposed build- (b) to adapt or improve living accommodation;
ing to the private street, of carrying out street works to such an (c) to repair living accommodation;
extent that the street would be adopted by the highway authority (d) to demolish buildings comprising or including living
(the advance payments code – Highways Act 1980, section 219). accommodation;
‘Street works’ means sewering, levelling, paving, metalling, (e) where buildings comprising or including living accommo-
flagging, channelling, making good, and lighting. The standards dation have been demolished, to construct buildings that
required are not specified in the legislation, but clearly they must comprise or include replacement living accommodation.
not be unreasonably stringent. In general, the standard prevailing
for similar streets in the authority’s district is required. 5.04 Assistance may be provided in any form and may be subject
to conditions, including as to repayment or making a contribu-
Section 38 of Highways Act 1980 tion towards the assisted work. Examples of possible conditions,
such as to eligibility and payment are given in the guidance.
4.04 The need to pay or give security in advance of the build- Before imposing a condition as to repayment or contribution the
ing work being started can be avoided if an agreement has been authority must have regard to the ability of the person to make
entered into with the local authority under section 38 of the the repayment or contribution. The primary methods of assistance
Highways Act 1980, pursuant to an exception from the general will be grants or loans, although other forms of assistance, such as
principle contained in section 219(4)(d) of that Act. discounted materials, or access to a tool hire scheme, may also be
provided. A mandatory grant remains available for the provision
4.05 Under section 38, the local authority may enter into an of facilities for a disabled person in a dwelling. Applicants must
agreement with the developer of land on either side or both be 18 years old and are means tested. There is a maximum level
sides of a private street; the authority can agree to adopt the of grant. For further information, see the terms of the above Order.
street as a highway maintainable at public expense when all the
street works have been carried out to their satisfaction, and the
developer agrees to carry them out within a stated time. If the Agriculture
works are not so carried out, the local authority can still use their 5.05 Under the Hill Farming Act 1946 and Livestock Rearing
statutory powers to carry out the works (or to complete them), Act 1951, a grant may be obtained from the Minister of
at the expense of the frontagers; it is therefore customary for the Agriculture, Fisheries and Food towards the cost of improving
developer to enter into a bond for its performance with a bank a dwelling as part of a scheme prepared with ‘a view to the
or an insurance company. rehabilitation of livestock rearing land’.

4.06 Such an agreement takes the street, or the part of the street
to which the agreement relates, outside the operation of the Conversion of closets
above general principles. The developer can then sell building 5.06 A grant not exceeding half the cost may be claimed towards
plots or completed houses ‘free of road charges’ to purchasers. the expenditure incurred by the owners of a dwelling in convert-
Though the street may not have been made up at the time of ing an earth or pail closet to a WC, either pursuant to a notice
purchase, the purchaser is protected, as the developer has agreed served by the authority, or where it is proposed to undertake
to make up the street; if it fails to carry out its promise, the local the work voluntarily. In the latter case the grant is payable at
authority will be able to sue on the bond and recover sufficient the local authority’s discretion (Building Act 1984, section 66).
to pay for street works’ expenses without having to charge
them to the frontagers. If the authority should proceed against
the frontagers, they in turn normally have a remedy against the Clean air
developer and on the bond, but this may depend on the terms 5.07 Where a private dwelling (an expression which includes
of their purchase. part of a house) is situated within a smoke control area, a grant
may be claimed from the local authority amounting to 70% of
4.07 Architects are not necessarily professionally concerned in the expenditure reasonably incurred in adapting any fireplace or
such matters, but it is suggested that it is their duty to be aware fireplaces in the dwelling to enable them to burn only ‘author-
of the potential expense to the client of building in an unmade ised fuels’ such as gas, electricity, coke, or specially prepared
70 Statutory authorities in England and Wales

solid fuels (Clean Air Act 1993, section 25 and Schedule 2). A association can improve existing council-owned houses, or
similar grant may be obtainable for certain religious buildings there is an acquisition of land by the local authority, which can
(section 26). then be sold or leased to the association for building houses; or,
with the consent of the Secretary of State for the Environment,
Historic buildings the authority may make grants or loans on to the association
to enable them to build houses. They may be able to obtain a
5.08 In the case of a building of historic or architectural inter- grant from the Homes England (or in Wales from the Welsh
est, whether or not it is 'listed' as such (under section 1 of the Government) towards the expenses of forming and running the
Planning (Listed Buildings and Conservation Areas) Act 1990), a association (Housing Act 1988, section 50). Registered housing
grant towards the cost of repair or maintenance may be obtained associations may also be able to obtain grants from the Secretary
from the local authority under section 57 of the 1990 Act, but of State where the associations’ activities have incurred a liabil-
such grants are entirely discretionary and no amounts are speci- ity for income or corporation tax (Housing Act 1988, section 54).
fied in the legislation. Grants and loans are also available from
Historic England for the maintenance and repair of buildings
of outstanding historical or architectural interest. The power to Housing Corporation loans
make such payments is found in sections 3A and 4 of the Historic 6.03 These provisions depend on the goodwill of the local
Buildings and Ancient Monuments Act 1953. Normally, Historic authority; a housing association cannot insist on being given
England only make payments for the maintenance and repair assistance. As an alternative, an association may be able to get
(excluding routine work) of outstanding Grade I or II build- help by ways of loans for obtaining land and general advice from
ings. Historic England do not normally make payments towards Homes England or the Welsh Government..
repair schemes costing less than £10,000. Further information on
potential funds available in respect of historic buildings may be
obtained from the Heritage Funding Directory, website: www. Setting up a housing association
heritagefundingdirectory.org. Where grants are given they are 6.04 In practice people proposing to form a housing society
generally at the rate of 40% of approved expenditure. A similar would be well advised to obtain advice from Homes England and
scheme is administered in Wales. those proposing to set up an association should get in touch with
the National Housing Federation website: www.housing.org.uk.
Airport noise
5.09 Under the Civil Aviation Act 1982, section 79, a grant may 7 Special premises
be obtained from the manager of the aerodrome for a building
‘near’ a designated aerodrome towards the cost of insulating 7.01 If architects are designing any kind of building, they must
it, or any part of it, against noise attributable to the use of the take into account the controls exercised under town and coun-
aerodrome. The details of such grants are specified in schemes try planning legislation (Chapter 11) and under the Building
approved by the Secretary of State for Transport, and further Regulations (Chapter 9); and he must consider the question of
particulars are obtainable from the Secretary of State or usually sewerage and mains services and the other matters discussed in
from the relevant airport operator. this chapter. But if their building is of a specialised kind, or is
to be used for some specialised purpose, additional controls may
Water supply have to be considered; the more usual types of special control
are outlined below.
5.10 The local authority has a discretionary power to make a
grant towards all or any part of the expenses incurred in the pro-
vision of a separate service pipe for the supply of water for any Premises for Sale & Supply of Alcohol
house which has a piped supply from a main, but which does not 7.02 Premises for the retail sale of alcohol, such as a public
have a separate service pipe (Housing Act 1985, section 523). house, restaurant or hotel, must be licensed by the local author-
ity under the Licensing Act 2003. The suitability of the prem-
ises for the proposed use, including the ability to comply with
6 Housing associations relevant conditions, may be relevant. Applications will normally
and societies be granted unless the local authority raises an objection to the
proposal. The licensing authority will advertise and consult upon
6.01 A housing association may be formed on a charitable basis applications, taking advice from the police, the officer of the
for provision of houses for those in need, or for special groups of local fire brigade, an environmental health officer, and the local
persons, such as the elderly or handicapped, in a specified area. planning authority. Each licensing authority is required to pro-
Such an association may also be constituted by an industrial firm duce a statement of licensing policy which should be examined
for housing its employees, or by a group of persons proposing when making such applications. An appeal against an adverse
to build its own homes by voluntary (or part voluntary) and decision of the licensing authority lies to the magistrates’ court.
co-operative labour. Frequently such associations are strictly
housing societies having acquired corporate personality by regis-
tration with the Registrar of Friendly Societies. However, a hous-
Theatres and cinemas
ing association (which may be incorporated as a company under 7.03 The Licensing Act 2003 also now covers the licensing of
the Companies Acts, or by other means) which complies with the provision of regulated entertainment including theatres and
the provisions of the Housing Acts (see definition in section 1 of cinemas, whereas previously such controls were all contained in
the Housing Associations Act 1985) and, in particular, does not either the Theatre Act 1968 and the Cinemas Act 1985.
trade for profit, is entitled to be considered for certain benefits
under the Housing Acts. Tenants of a housing association who
have occupied their homes for at least five years will have a right
Hotels
to purchase the dwelling under Part V of the Housing Act 1985. 7.04 Hotels are no longer under specific fire certificate obliga-
tions that previously existed under the Fire Precautions Act
1971. However hotels, as with other premises, are under a gen-
Benefts eral duty to ensure so far as reasonably practicable the safety
6.02 First, the association may be able to obtain ‘assistance’ of employees, and are under a general duty in relation to non-
from the local housing authority in whose area they propose employees to take such fire precautions as may reasonably be
to build. This may mean making arrangements so that the required in the circumstances to ensure premises are safe. There
Special premises 71

is also a duty to carry out a risk assessment: see Regulatory of section 5 (see the Clean Air (Emissions of Grit and Dust from
Reform (Fire Safety) Order 2005 (SI 2005/1541). Furnaces) Regulations 1971). In addition, a furnace of a type to
which the section applies (section 14: see 1993 Act), may not
be used in a building unless the height of the chimney serving
Shops and offces the furnace has been approved by the local authority (1993 Act,
7.05 Shops, offices, and railway premises where persons other section 15).
than close relatives of the employer are employed to work are
in some cases subject to control by the district council, under
the Offices, Shops and Railway Premises Act 1963, provided
Petroleum
the time worked at the premises exceeds 21 hours a week 7.11 A premises used for keeping petroleum generally must
(sections 1–3). The Act provided for such matters as cleanliness, be subject to a valid storage certificate issued by the petro-
temperature within rooms, ventilation, lighting, and the provi- leum enforcement authority; otherwise the occupier is guilty
sion of WCs (if necessary for both sexes), washing accommoda- of an offence (Petroleum (Consolidation) Regulations 2014 SI
tion, and so on. The standards specified were detailed, but many 2014/1637). The petroleum enforcement authority in England
of the provisions have been repealed and superseded in relation and Wales is generally the county council; in Greater London or
to “workplaces” by the requirements of the Health and Safety at a metropolitan county, it is the fire and rescue authority. There
Work Act and the relevant regulations made pursuant to that Act, are exceptions for the storage of up to 30 litres of petrol in suit-
such as the Workplace (Health, Safety and Welfare) Regulations able portable metal or plastic containers or a demountable fuel
1992 (SI 1992/3004). Fire requirements are now governed by the tank, or where storage of up to 275 litres of petrol occurs but
Regulatory Reform (Fire Safety) Order 2005 (SI 2005/1541), the petroleum enforcement authority is notified and the general
under which there are general duties to take such fire precautions requirements of such storage are met. Detailed conditions are
as may reasonably be required in the circumstances to ensure usually imposed when a storage certificate is granted. Petroleum
premises are safe. storage certificates are usually renewable each year at a fee.

Factories Food premises


7.06 The Factories Act 1961 imposed special control over certain 7.12 If any part of the premises is used for a business involv-
specialised constructional matters in a factory (as defined in ing food, the more stringent provisions of the Food Safety and
Factories Act 1961, section 175); there wass no special control Hygiene (England) Regulations 2013 (SI 2013/2996) made
over plans (other than the normal controls of the planning legis- under the European Communities Act 1972 and under the Food
lation and the Building Regulations), but if the requirements of Safety Act 1990 must be observed. Premises used as a slaugh-
the Act were not met in a particular factory, the occupier or (in terhouse or a knacker’s yard for the slaughter of animals need
a tenement factory) the owner would be liable to be prosecuted to be approved by the Food Standards Agency under various
for an offence. Many of these requirements related to the use and regulations.
fencing of machinery, keeping walls and floors clean, and so on,
and as such they are not of direct concern to the architect. Whilst
some of the Act remains in for, it has largely been replaced by
Miscellaneous
the requirements in the Health and Safety at Work Act 1974 and 7.13 In England, licences from the district council are also
regulations made under it. required for the use of premises as a shop for the sale of pet
animals, board for cats or dogs, hiring out horses, breeding dogs,
7.07 The fire certificate legislation for factories, as with offices or keeping or training animals for exhibition under the Animal
and shops, has now been changed by the Regulatory Reform Welfare (Licensing of Activities Involving Animals) (England)
(Fire Safety) Order 2005. Regulations 2018 SI 2018/486. In Wales such licences are
necessary under other legislation such as the Pet Animals Act
7.08 The effluent from a factory’s sewers or drains may well be 1951, the Animal Boarding Establishments Act 1963, and the
‘trade effluent’ and will then be subject to the special control of Riding Establishment Acts 1964 and 1970. Childrens Homes,
the Environmental Permitting Regulations 2017 and the Water Independent Hospitals and Care Homes are subject to registra-
Industry Act 1991, Chapter III. tion requirements in England and Wales. In all these cases the
suitability or otherwise of the premises for the particular purpose
7.09 Under the Clean Air Act 1993 factories are subject to may be an issue in the grant or refusal of the licence.
several constructional controls operating quite independently of
the Building Regulations, but administered by the same local 7.14 Caravan sites used for human habitation also need a licence
authorities (district councils). Thus any furnace installed in a in addition to planning permission (Caravan Sites and Control
building which will be used to burn pulverised fuel, or to burn of Development Act 1960, Part 1), and detailed conditions as to
any other solid matter at a rate of 45.4 kg per hour or more, hygiene and sanitary requirements are customarily imposed. In
or any liquid or gaseous matter at a rate of 366.4 kW or more, many districts it will also be necessary to obtain a licence from
must be provided with plant for arresting emissions of grit and the council if premises are to be used as a sex shop or for the
dust which has been approved by the local authority or has been practice of tattooing or acupuncture or electrolysis or ear-pierc-
installed with plans and specifications submitted to and approved ing (Local Government (Miscellaneous Provisions) Act 1982).
by the local authority (Clean Air Act 1993, section 6).
7.15 Premises serving late night refreshment, including take-
7.10 Limits are set by regulations for the rates of emission of grit away food shops, will require a licence from the local authority
and dust, and there are certain exemptions from the provisions under the Licensing Act 2003.
8
Statutory authorities in Scotland
GRAHAM A. DUNLOP

1 Introduction: public recently, a number of those services have been reorganised into
national bodies such as Scottish Water and Police Scotland.
administration in Scotland
1.03 Certain decisions of local authorities and other bodies
1.01 Prior to the Scotland Act 1998, local government and pub- are subject to judicial review. The topic of judicial review is
lic administration arrangements within Scotland largely derived a specialised area of law. In brief terms, the Court of Session
from legislation emanating from Westminster. The Scotland (in Edinburgh) is entitled to consider whether a decision
Act 1998 devolved many government functions, previously of a public authority is unlawful. The Court does not con-
controlled by the UK government, to the Scottish Government. sider the merits of the decision. Rather, the Court considers
The creation of legislation defining the statutory powers and whether or not a decision was made in accordance with any
duties for these functions is devolved to the Scottish Parliament. prescribed procedure and was reached lawfully. This requires
Historically, Scotland has always retained a separate judiciary local authorities to reach decisions which are not perverse or
and legal system, following the 1707 Act of Union. Scotland’s illogical, or otherwise wrong in law. In reaching a decision,
legal system has continued to provide authoritative decisions on public bodies should have regard to relevant matters and not
the interpretation and application of the powers and duties of take into account irrelevant considerations. A person seeking
statutory authorities in Scotland. Regulation of the architectural to challenge a decision of a local authority or other body by
profession is reserved to Westminster. Devolved matters relevant judicial review proceedings should first exhaust all statutory
to architectural practice in Scotland include: rights of appeal.
Local Government
Housing Local authorities – administration
Planning and building control
Inland waterways 1.04 Local authority elections in Scotland are to be held every
Licensing four years from 2021. Since 2007, Scottish Councillors (gen-
Environmental Protection erally referred to within local authorities as ‘members’) have
Built Heritage been remunerated. Members may be independent, but are gener-
Natural Heritage ally a member of one of the main recognised political parties.
Roads Members sit on decision-making committees and panels. In
practice, certain decisions will be delegated to employed offic-
Legislation in devolved matters that existed prior to the ers by virtue of a scheme of delegation. Accordingly, whilst a
1998 Act continues to remain in force unless amended or planning application for a major housing development will be
repealed. Functions previously exercised by the Secretary of determined by a Committee of elected members, an application
State for Scotland in relation to matters now devolved are exer- for development of a single house will be determined by an
cised by the Scottish Ministers. employed planning officer. Local authorities appoint officials,
often referred to as chief officers, and other less senior offic-
ers and staff to enable them to carry out their functions. A few
Local authorities – general officials require to be appointed as a statutory requirement,
1.02 The Local Government etc. (Scotland) Act 1994 created due to their roles being a statutory function. Local authorities
32 unitary local government authorities in Scotland. In general have discretion in the matter of their internal organisation.
terms, the unitary authorities inherited and exercised for their The most senior chief officer, responsible for coordinating the
area all functions previously fulfilled by the regional, district, various functions of a local authority, is generally titled Chief
and islands councils. The authorities also inherited the property Executive, and will be supported by Directors and Heads of
and liabilities of the former authorities. The unitary authorities Service.
are responsible for services which had previously been regional In the context of a professional architect’s point of view,
council functions, such as education provision, and for services the key officials will be within the departments or services
which were a district council function such as housing. responsible for development, planning, and building standards.
Following local government re-organisation, separate admin- The local authority is the planning authority for approval of
istrative arrangements were made for a limited range of public development in their area in terms of the Town and Country
services and functions which had previously been delivered Planning (Scotland) Act 1997. Similarly, the local authority is
by the regional councils and served more than one of the new also responsible for planning enforcement arising from breaches
unitary local government areas, such as water provision. More of planning control. The local authority is responsible under

73
74 Statutory authorities in Scotland

Both national parks have local development plans setting out


the various planning policies. Loch Lomond & the Trossachs
National Park is also the planning authority with responsibility
for development management, including determining develop-
ment proposals. Cairngorms National Park also produces a local
development plan identifying what development may or may
not be acceptable. However, planning applications for develop-
ment are determined by one of the five local authorities whose
geographical areas lie within the Cairngorms National Park. The
Cairngorms National Park is consulted on planning applications
for development.

Other relevant bodies


1.09 In addition to the bodies discussed above, architects
involved in development proposals may have involvement with
Historic Environment Scotland; Scottish Natural Heritage; and/
or the Scottish Environment Protection Agency.
Historic Environment Scotland is a non-departmental public
body responsible for properties of national importance, includ-
ing listed buildings. It is a statutory consultee where proposed
the Building (Scotland) Act 2003 and Building Regulations for development affects certain listed buildings and world heritage
building warrants and enforcement of building control. sites, such as the New Town of Edinburgh.
Scottish Natural Heritage (SNH) was established in accord-
1.05 As indicated above, the significant decisions made by ance with the Natural Heritage (Scotland) Act 1991. Its respon-
local authorities are determined by the elected members. The sibilities include designating areas of land to conserve and
most significant decisions are taken by all members sitting as enhance the natural heritage. SNH is consulted by planning
the full Council, but generally, decisions by members are more authorities in planning applications for development where there
likely to be made by a committee with a particular mandate, may be an impact on the natural environment caused by devel-
e.g. planning. Whilst all Councils vary in the structure of com- opment, such as impact on wildlife. It may suggest necessary
mittees, it is common for each service to be represented by at mitigation, which will be imposed in any planning conditions.
least one committee, such as planning and development or child The Scottish Environment Protection Agency (SEPA) is
protection. A Convenor (or Chair) is appointed to each com- a further non-departmental body of the Scottish Government
mittee. Convenors tend to have a detailed understanding of the which has responsibilities relating to environmental protection
particular service the committee represents and will have regu- in Scotland. SEPA is a statutory consultee in large scale devel-
lar contact with the employed officers in the particular service. opment proposals where there is a risk of pollution or flooding,
Limited decision-making by members is made under a separate and regularly offers advice on matters such as sustainable urban
statutory framework such as Licensing Boards. drainage. SEPA also has statutory functions in relation to dis-
charge of sewage and other effluent. SEPA regulates the use of
1.06 In general, committees are composed of elected council septic tanks for domestic properties not connected to the public
members only. Employed officials are present at committee sewerage network.
meetings to give advice when required, but without the right
to vote. Often committees will be presented with an executive
report prepared by employed officials. The report may contain 2 Connections to sewerage
recommendations on the decision to be taken. Members are not
obliged to follow any recommendations. and water services
2.01 The principal legislation for sewerage and water services is
Scottish Water the Sewerage (Scotland) Act 1968 (as amended) and the Water
1.07 The Water Industry (Scotland) Act 2002 established a sin- (Scotland) Act 1980 (as amended).
gle body known as Scottish Water. Scottish Water is a publicly
owned company operating in accordance with the statutory Sewers
framework in the Water Acts. It provides public water and sew-
erage functions in Scotland, and is controlled by a Board which 2.02 The Sewerage (Scotland) Act 1968 (as amended) narrates
includes members appointed by Scottish Ministers. The Water the powers and obligations of Scottish Water in respect of sewer-
Services etc. (Scotland) Act 2005 established a Water Industry age functions. The 1968 Act provides definitions of ‘drains’ and
Commission for Scotland. The Commission works with Scottish ‘sewers’. Drains are defined as pipes (or drains) within the curti-
Water to agree the costs to be levied on persons wishing to con- lage of premises used for draining buildings and yards within the
nect to the water and sewerage networks. In order to connect same curtilage. Sewers are defined as all pipes (except ‘drains’)
to the public water supply and sewerage treatment in Scotland, used for draining buildings and yards appurtenant to buildings.
it is necessary to contact Scottish Water. Within Scotland there
remain a considerable number of properties that rely on private 2.03 Public sewers are vested in Scottish Water, as are (pre-
water supplies (such as boreholes and springs) and private sew- 2002) private sewers under agreement with Scottish Water.
erage (such as septic tanks). There are separate statutory arrange- Junctions to public sewers are vested in Scottish Water. If a
ments for domestic and non-domestic properties. private drain is connected to a public sewer, it is the responsi-
bility of Scottish Water to maintain the junction. Private Sewers
and Sustainable Urban Drain (SUD) systems created since April
National Parks 2002 vest in Scottish Water.
1.08 The National Parks (Scotland) Act 2000 led to the creation
of two national parks in Scotland being: (1) Loch Lomond & 2.04 Scottish Water is obliged to provide public sewers as may
the Trossachs; and (2) the Cairngorms. The 2000 Act aims to be necessary for draining their area of domestic sewage, surface
conserve and enhance the natural heritage of the national parks, water, and trade effluent. It has to take public sewers to such
including promoting sustainable use of the natural resources. point(s) as will enable owners of premises to connect their drains
Connections to sewerage and water services 75

(or private sewers) at a reasonable cost. The responsibility for be possible to obtain a connection subject to the supply being
installing drains in individual premises is that of the proprietor. technically possible and the person seeking the supply meet-
ing the cost There remain, in Scotland, many properties which
2.05 Scottish Water has powers to construct, close or alter sew- either are unable or unwilling to be provided with a water
ers and sewage treatment works. It is obliged to provide an supply and rely upon private water supplies, such as boreholes
equally effective replacement sewer for any person deprived by and springs, noted above. ‘Reasonable Cost’ is the subject of a
any closure of a sewer. Scottish Water has the power to take over statutory formula in terms of regulations made under the Water
the responsibility of private sewage treatment works or SUDs, Acts. The various costs of establishing a private connection
which may give rise to a right to compensation to be paid to are agreed annually and published in a scheme following dis-
the owner(s). cussion between the Water Industry Commission and Scottish
Water. Prior to establishing a permanent water supply, Scottish
2.06 Where Scottish Water is not under an obligation to provide Water may be able to provide a temporary supply arrangement
sewers for new premises in accordance with section 1 of the to enable water for building purposes, such as mixing building
1968 Act, it may enter into an agreement with the developer. The materials.
agreement may stipulate how the works are to be undertaken,
and arrangements may be entered for Scottish Water to take over 2.14 The arrangements for obtaining a non-domestic water sup-
the responsibility for the sewers; sewerage treatment works; and ply were subject to significant legislative reform following the
SUD systems. Water Services etc. (Scotland) Act 2005. Since the 2005 Act,
Scottish Water acts as the wholesaler of water services, but does
2.07 The 1968 Act makes provision requiring Scottish Water to so through arrangements with third party organisations who act
empty a domestic septic tank on being requested to do so by the as licensed water supply providers. The arrangement is similar to
owner or occupier. The duty arises where it would be reasonably the competition arrangements which exist between suppliers of
practicable to empty the tank. Scottish Water may insist upon domestic gas and electricity. In 2019, there were approximately
payment for the service. 20 licensed providers competing for a share of the non-domestic
water supply market. Whilst Scottish Water can provide an
estimate of capacity for any new connections, the arrangements
Drains for a new connection must be made through one of the licensed
2.08 Any owner of premises is entitled to connect his or her providers. Scottish Water publishes the list of licensed provid-
drains or private sewers or private SUD systems to a public ers who can be contacted to establish which provider best meets
sewer on giving the sewerage authority 28 days’ notice. Scottish the needs of the particular non-domestic supply. Mixed-use
Water may refuse permission, or grant it subject to conditions. developments will therefore require separate arrangements with
There is a right of appeal to the Scottish Ministers. Scottish Water and also a licensed provider. One of the licensed
providers, Business Stream, is a Scottish Water-owned company.
2.09 Where permission is granted allowing connection of a Under the 1980 Act, Scottish Water remain obliged to provide
drain or sewer to a public sewer, the owner is required to notify infrastructure for non-domestic development, subject to financial
Scottish Water of his or her intention to commence works. A contributions, except where new waterworks would give rise to
minimum of three days’ notice is required. Scottish Water is unreasonable expenditure which would endanger existing sup-
entitled to supervise the works. ply obligations, or endanger future domestic supply obligations.

2.10 Scottish Water or the local authority may serve a notice 2.15 In terms of the 1980 Act, persons erecting new buildings
requiring defects in private drains and sewers to be remedied are obliged to make adequate provision, to the satisfaction of
within a reasonable period. The period may be reduced to the local authority, for a supply of wholesome water for the
48 hours where immediate action is required. The works may be domestic purposes of persons occupying or using the building.
undertaken where the notice is not complied with, and the cost In fulfilment of the duty, the local authority will consult Scottish
of remedying the defect(s) may be recovered from proprietors. Water. Scottish Water is subject to the oversight of the Scottish
Ministers. Where Scottish Water fails to discharge its statutory
2.11 Sewage discharged into a public sewer must not be of such duties, including failure to provide an adequate supply, the
a nature as to cause damage to the sewer or, through mixture Scottish Ministers may investigate the compliant. The Scottish
with other sewage, cause a nuisance. Statutory nuisances in Ministers have powers to require a local inquiry to be heard and
terms of the Environmental Protection Act 1990 are enforced to impose requirements upon Scottish Water.
by the local authority.
2.16 Scottish Water’s powers under the 1980 Act include the
power to lay mains. This power may be exercised in, under, and
Trade effuent over road and land. Scottish Water may also grant a third party
2.12 The discharge of trade effluent into public sewers and the power to lay mains and other pipes in, under, and over land
other disposal and treatment of trade effluent is regulated by the and roads. The power of Scottish Water to inspect and maintain
1968 Act (as amended). New discharges can be made only with the apparatus is also conferred by the 1980 Act.
the consent of Scottish Water. Application for consent is made
by serving a trade effluent notice on the authority, which must 2.17 The procedure for obtaining a new water supply varies on
specify the nature of the effluent, the maximum daily quantity, whether the supply is domestic or non-domestic. In either case,
and the maximum hourly rate of discharge. The application contact should first be made with Scottish Water to establish if
has to be determined within three months. Consent may be the new development can technically be provided. Where the
granted subject to conditions. Consent lasts for a minimum of development is domestic, it will be necessary to provide designs
2 years and survives a change of ownership of the premises. The to Scottish Water as part of the formal application process.
1968 Act provides a right of review and a right of appeal against Where the supply is to new, non-domestic premises, contact
a decision relating to a consent. should be made with a licensed provider.

Water supply Gas, electricity, and telephones


2.13 The Water (Scotland) Act 1980 (as amended) requires 2.18 On these topics, reference should be made to Chapter 7,
Scottish Water to provide a supply of wholesome water where as what is said there applies also in Scotland. The Gas Act
that supply can be provided practicably at a reasonable cost. 1986 applies with minor modifications in Scotland as in England.
Where a supply cannot provided at a reasonable cost, it may Likewise, the Electricity Act 1989 applies with small
76 Statutory authorities in Scotland

modifications. The Building (Scotland) Regulations 2004 require 6 Special considerations


that buildings are designed and constructed with oil or gas
storage (or tanks) that will inhibit fire from spreading to the 6.01 Special controls and regulatory regimes apply to a variety
storage/tanks. of premises, sites and structures. Examples include:

3 Private streets and footpaths Premises licensed for the sale of alcohol
6.02 In terms of the Licensing (Scotland) Act 2005, a premises
3.01 The principal Act relating to roads in Scotland is the Roads licence is required where the premises will be used for the sale
(Scotland) Act 1984. Trunk roads, such as Motorways, are the of alcohol. Licensing boards comprising members of the local
responsibility of the Scottish Ministers. Public roads are the authority determine the application for a premises licence.
responsibility of the local authority in which the public road is Specialist advice should be sought from a solicitor when seeking
located. The 1984 Act defines roads as ways over which there a premises licence.
is a public right of passage, by any means. A road includes the
verge of the road and any bridges or tunnels. It also includes a 6.03 The application process includes consideration of the fol-
public footway which can be used only by foot (i.e. pavement). lowing: (1) the licensing objectives under the 2005 Act (which
Footpaths arise where there is a public right of passage by foot includes preventing crime and disorder; protecting and improv-
without being associated with a carriageway. ing public health; and preventing public nuisance); (2) the loca-
tion and character of premises, including the nature of activities
3.02 Public roads are roads entered by local councils in their ‘list and persons likely to use the premises; and (3) the existing
of public roads’ and are roads which those authorities are bound provision of similar premises and whether granting the licence
to maintain. Private roads are roads which are not public roads. would lead to overprovision. Where a premises licence is sought,
The authorities can require frontagers to make up and maintain statutory certificates in relation to planning, building control, and
a private road. When a road has been properly made up, the food hygiene must be presented.
frontagers may require the roads authority to add the road to the
list of public roads for that authority.
Other licensed premises
4 Grants 6.04 The Gambling Act 2005 replaced a variety of outdated
enactments. Under the 2005 Act, there are different types of
4.01 Local authorities have powers, under Part 2 of the Housing licences required, namely operating licences; premises licences;
(Scotland) Act 2006, to assist in the maintenance and improve- and personal licences. Operator licences and personal licences
ment of private sector housing in their authority area. The are outwith the scope of this book.
assistance available includes advice and guidance, but more sig-
nificantly, may also include grants or loans. The local authority 6.05 There are five different types of premises licences, includ-
has discretion in determining the types of assistance available, ing ‘Betting Premises Licence’. The principal considerations
subject to two mandatory requirements. in determining the application are (1) the Code of Practice; (2)
First, that a local authority must provide assistance where guidance from the Gambling Commission; (3) Consistency with
the owner of a house has been served with a notice under the licensing objectives; and (4) the licensing board’s statement of
2006 Act requiring work to be undertaken to the house. The type licensing policy.
of work prescribed in the 2006 Act is drafted in wide terms and
includes, for example, ‘improvement, repair or maintenance of 6.06 In terms of the Theatres Act 1968, as amended, no prem-
a house’. ises may be used for the public performance of any play unless
Secondly, a local authority must provide assistance for adap- licensed by the local authority. In terms of the Cinemas Act
tations or reinstatement works to a house to make the house suit- 1985 (as amended), no premises may be used for exhibiting
able for a disabled resident. The 2006 Act provides that grants films unless licensed by the local authority. The Cinematograph
(i.e. financial assistance) are mandatory for most work which is (Safety) (Scotland) Regulations 1955 (as amended) make
required to adapt the house for disabled use. detailed provision for the design and construction of premises
and relevant fittings.
4.02 In terms of section 233 of the Housing (Scotland) Act
1987, a local authority may provide grant assistance to install a 6.07 Premises may be licensed by the local authority for a range
separate service pipe for water supply. Section 233 applies where of different activities, including public entertainment, indoor
the house is connected to the mains supply but does not have sports entertainment, and late hours catering in terms of the
a separate service pipe. Section 15 of the Social Security Act Civic Government (Scotland) Act 1982 (as amended). There
1990 provides that grants may be made available for the thermal is a licensing scheme for sex shops in terms of section 45 and
insulation of buildings, and other measures designed to reduce Schedule 2 of the 1982 Act.
energy wastage in buildings. The Home Energy Assistance
Scheme (Scotland) Regulations 2013 are made in accordance Sports grounds
with the 1990 Act and provide the detail of eligibility and criteria
for obtaining grant assistance. 6.08 The Safety of Sports Grounds Act 1975 makes provision
for safety at sport grounds. Local councils are responsible for
issuing safety certificates for designated sports grounds. The
5 Registered social landlords Fire Safety and Safety of Places of Sport Act 1987 extended
regulation to all stands with covered accommodation for more
5.01 Registered social landlords (RSLs) are regulated under than 500 spectators.
the terms of the Housing (Scotland) Act 2010. The 2010 Act
introduced a new independent regulator, the Scottish Housing Care Homes
Regulator. The Regulator monitors the performance of RSLs
and local authorities in providing housing. A RSL requires to 6.09 The former statutory regimes differing between nursing
meet statutory criteria under the 2010 Act include not trading homes and residential homes are no longer relevant, and all
for profit and having the purpose of providing, constructing, or homes are now known as ‘care homes’. Care homes can pro-
managing housing available for letting. vide residential as well as nursing care. They may be owned
Special considerations 77

and operated by the public sector or private sector. The Care operations. Involvement in the design of permanent, temporary
Inspectorate (in Scotland) both registers and inspects care homes. and protective works, the scheduling of works, the organisation
of working practices, etc. involves the potential for causing
accidents and for liability, direct and indirect. Reference should
Workplaces be made to Chapter 15.
6.10 Health and safety legislation raises many design issues
in relation to workplaces of all kinds. The traditional regime
has been substantially updated by regulations made under the
Fire Safety
Health and Safety at Work Act 1974, in fulfilment of direc- 6.12 The Fire (Scotland) Act 2006 requires persons in control
tives. For example, the Workplace (Health, Safety and Welfare) of most non-domestic premises to identify fire safety risks.
Regulations 1992 impose requirements in respect of ventilation, The 2006 Act requires employers to carry out an assessment of
temperature, lighting, room dimensions, layout of workstations, the workplace in relation to the risks to employees from harm
design, and materials of all surfaces, floors, windows, and doors, caused by fire, and to take such fire safety measures are as nec-
washing facilities, and sanitary facilities. The 1992 Regulations essary. Schedule 2 of the 2006 Act details fires safety measures
also make provisions requiring accommodation for storing such as detection systems and measures for securing escape
clothing and changing, and rest facilities, including facilities for from premises.
pregnant women and nursing mothers.
Houses in multiple occupation
Construction sites 6.10 The Housing (Scotland) Act 2006 requires that properties
6.11 Architects should be aware of the extensive health and let for multiple occupation by three or more unrelated persons
safety legislation relating to construction sites and engineering have to be licensed by the local authority.
9
Construction legislation in England and Wales
CHRISTOPHER MIERS, MARTIN EDWARDS, AND FRANK NEWBERY1

1 Building Acts and Regulations 2.02 Building Regulation 4(1)(a) requires that building work
shall be carried out so that –
1.01 Planning legislation is largely concerned with development
policy and, in relation to the external appearance of a building, (a) it complies with the applicable requirements contained in
with safeguarding the amenity of neighbours and the general Schedule 1 (see 2.08 below); and
public (see Chapter 11). But obtaining planning permission is (b) in complying with any such requirement, there is no failure
only the first legal hurdle. The architect is then faced with con- to comply with any other such requirement.
trols over the construction and design of buildings.
In England and Wales the basic framework of control is found 2.03 Regulation 3(2) defines a material alteration as one which
in the Building Act 1984 and in the Building Regulations made would result in an existing building not meeting the require-
under it. An important feature of the present system of building ments of Schedule 1, Parts A, B, and M, relating respectively to
control is that there are two alternative means of control – one by structure, fire safety (except B2 internal fire spread – linings),
local authorities operating under the Building Regulations 2010, and access and facilities for disabled persons, either:
and the other by a system of private certification which relies on
‘approved inspectors’ operating under the Building (Approved (a) where previously it had; or
Inspectors etc.) Regulations 2010. (b) making it more unsatisfactory than it was before in respect
of those particular requirements.
1.02 The Building Act 1984 applies in England and Wales,
but does not extend to Scotland or to Northern Ireland. The 2.04 Regulation 5 defines what constitutes a material change of
Building Regulations 2010 are made under this Act, which also use of a building and Regulation 6 requires that, where there is
contains provisions linked to the deposit of plans for Building a material change of use of the whole of a building, such work
Regulations purposes and provisions relating to existing build- must comply with certain listed parts of Schedule 1. See para-
ings. In Northern Ireland, the Building Regulations (Northern graph 11.02 below for how this applies to fire safety.
Ireland) 2012 (as amended) applies; for Scotland, see Chapter 10.
There may also be additional provisions in local Acts, and the 2.05 Building Regulation 7 requires that building work must be
local authority must say, if asked, whether a local Act applies carried out with adequate and proper materials, and in a work-
in its area. Some sections of the old London Building Acts have manlike manner. This regulation has its own distinct Approved
been incorporated/amended by the Building (Inner London) Document and has been expanded recently (see 2.10 below).
Regulations 1987 and may be applicable to some inner London
buildings (see section 6). For additional provisions in local Acts 2.06 Since 2010, these Regulations have been modified by a
outside London, see section 7. Finally, there may be relevant series of Building Regulations &c. (Amendment) Regulations
provisions in national Acts (see section 8). (‘BR(A)R’), affecting, in particular, the scope and content of
the Building Regulations Schedule 1 requirements (as listed
1.03 Sections 1–9 of this chapter give an account of construc- in 2.02 below). Notable examples of these amendments are
tion legislation as a whole. Sections 10–19 are focussed more BR(A)R 2012, which modified Part K; BR(A)R 2015, which
particularly on fire safety legislation, which has been undergoing modified Part M and added Part Q; BR(A)R 2016, which added
substantial reappraisal and amendment since the Grenfell Tower Part R; and BR(A)R 2018, which modified Part B and expanded
disaster of June 2017. Regulation 7. These amendment regulations are summarised and
listed in DCLG Circulars 03/2012, 04/2016, 01/2015, and 02 and
03/2018. These Circulars and many others are accessible from
2 The Building Regulations 2010 the gov.uk/government/collections/building-regulations-circulars
web page. The legislation.gov.uk website includes an electronic
2.01 The Building Regulations 2010 contain the technical and text of the Building Regulations 2010, which is progressively
procedural rules governing building control by local authorities. modified and/or annotated in accordance with successive post-
The Building (Approved Inspectors etc.) Regulations 2010 set 2010 amendments.
out the procedures to be adopted by an approved inspector (see
section 3 of this chapter).

1 In previous editions, this chapter was contributed by Oliver Palmer, and was then updated for the ninth edition by Martin Edwards and Murray Armes.
The present update reproduces the text of these earlier editions where still appropriate.

79
80 Construction legislation in England and Wales

2.07 The following information is current at the time of writ- PART K: PROTECTION FROM FALLING, COLLISION,
ing, but the latest versions of legislation texts and advice on AND IMPACT (as modified by the 2015 amendment
the gov.uk website should be checked where current details regulations)
are critical. K1. Stairs, ladders and ramps.
K2. Protection from falling.
K3. Vehicle barriers and loading bays.
Technical requirements: Schedule 1 K4. Protection against impact with glazing.
2.08 These requirements are as listed in Schedule 1 of the K5. Additional provisions for glazing in buildings other
Building Regulations 2010, subject to additions and modifi- than dwellings.
cations by subsequent Amendment regulations. The require- K6. Protection against impact from and trapping by doors.
ments’ contents are not reproduced here; current versions are PART L: CONSERVATION OF FUEL AND POWER (as
quoted fully in the latest editions of the Approved Documents sub-categorised in four Approved Documents)
(which can be downloaded without charge from official web- L1A. Conservation of fuel and power in new dwellings.
sites such as gov.uk/government/collections and planningpor- L1B. Conservation of fuel and power in existing dwellings.
tal.co.uk). L2A. Conservation of fuel and power in new buildings other
The following is a list of requirement headings as current than dwellings.
at the time of writing. These headings are reproduced by the L1B. Conservation of fuel and power in existing buildings
Part titles and subdivision headings of the Approved Documents. other than dwellings.
PART M: ACCESS TO AND USE OF BUILDINGS (as
PART A: STRUCTURE expanded by the 2015 amendment regulations)
A1. Loading. M1. Access and use of buildings other than dwellings.
A2. Ground Movement. M2. Access to extensions to buildings other than dwellings.
A3. Disproportionate Collapse. M3. Sanitary conveniences in extensions to buildings other
PART B: FIRE SAFETY (The below requirements are treated than dwellings.
separately in two volumes of the Approved Documents, one M4(1). Category 1: Visitable dwellings.
for dwellings, and one for buildings other than dwellings.) M4(2). Category 2: Accessible and adaptable dwellings.
B1. Means of warning and escape. M4(3). Category 3: Wheelchair use dwellings.
B2. Internal fire spread (linings). PART N: GLAZING – SAFETY IN RELATION TO
B3. Internal fire spread (structure). IMPACT, OPENING, AND CLEANING
B4. External fire spread. N1. Protection against impact.
B5. Access and facilities for the fire service. N2. Manifestation of glazing.
(The 2019 editions of the Part B Approved Documents N3. Safe opening and closing of windows etc.
add a further section heading ‘Regulations: 6(3), 7(2) and N4. Safe access for cleaning windows etc.
38’.) PART P: ELECTRICAL SAFETY
PART C: SITE PREPARATION AND RESISTANCE TO P1: Design and installation of electrical installations.
CONTAMINANTS AND MOISTURE PART Q: SECURITY – DWELLINGS (added by the
C1. Site preparation and resistance to contaminants. 2015 amendment regulations)
C2. Resistance to moisture. Q1: Unauthorised access.
PART D: TOXIC SUBSTANCES PART R: PHYSICAL INFRASTRUCTURE FOR HIGH-
D1. Cavity insulation. S P E E D E L E C T R O N I C C O M M U N I C AT I O N S
PART E: RESISTANCE TO THE PASSAGE OF SOUND NETWORKS (added by the 2016 amendment regulations)
E1. Protection against sound from other parts of the build- R1: In-building physical infrastructure.
ing and adjoining buildings.
E2. Protection against sound within a dwelling-house etc. 2.09 The Building Regulations require that all ‘building work’
E3. Reverberation in the common internal parts of buildings must be carried out in accordance with the requirements of
containing flats or rooms for residential purposes. Schedule 1, but there are important limitations on the require-
E4. Acoustic conditions in schools. ments. Building Regulation 8 (Limitation on requirements) states
PART F: VENTILATION that nothing need be done other than the works necessary to
F1. Means of ventilation. secure reasonable standards of health and safety for persons in
PART G: SANITATION, HOT WATER SAFETY, AND and about buildings, or others affected by buildings. This limi-
WATER EFFICIENCY tation does not apply to Parts E, L, and M, or to the particular
G1. Cold water supply. requirements G2, H2, and J7.
G2. Water efficiency.
G3. Hot water supply and systems. 2.10 There is also a supporting Building Regulation 7 (Materials
G4. Sanitary conveniences and washing facilities. and workmanship). This currently implements the Construction
G5. Bathrooms. Products Regulation, an EU-wide harmonisation measure which
G6. Food preparation areas. has been in force since 2013 and is the basis of ‘CE’-marking,
PART H: DRAINAGE AND WASTE DISPOSAL as an indicator of approved product quality. Regulation 7 was
H1. Foul water drainage. expanded in 2018 mainly to correct a perceived deficiency of
H2. Wastewater treatment systems and cesspools. clarity and control over materials specification in relation to
H3. Rainwater drainage. fire risk following the Grenfell Tower disaster. This expan-
H4. Building over sewers. sion of Regulation 7 was coordinated with amendments to the
H5. Separate systems of drainage. Approved Document guidance to Part B (Fire Safety). See fire
H6. Solid waste storage. safety sections 12 and 13 below. The ‘CE’-marking provisions of
PART J: COMBUSTION APPLIANCES AND FUEL Regulation 7 are likely to be reviewed in the course of the UK’s
STORAGE SYSTEMS transition away from shared EU law and standards.
J1. Air supply.
J2. Discharge of products of combustion.
J3. Warning of release of carbon monoxide.
Approved documents
J4. Protection of building. 2.11 The status and use of the Approved Documents (‘AD’) is
J5. Provision of information. laid down in sections 6 and 7 of the Building Act 1984. The pur-
J6. Protection of liquid fuel storage systems. pose of the documents is to give practical guidance with respect
J7. Protection against pollution. to the requirements of any provision of the Building Regulations.
The Building Regulations 2010 81

The documents may be approved by the Secretary of State or by Nature of approval


some other body designated by him.
2.16 Before considering the procedural requirements in detail,
2.12 There is an AD for each of the Schedule 1 ‘Parts’ as listed several important matters must be emphasised: discretion of
above. These provide more specific guidance and/or limiting local authorities, breach of Building Regulations, enforcement
criteria that will be expected to meet the requirements. The and dispensation, and relaxation of requirements.
current ADs all refer to other non-statutory material, including
British Standards and certificates issued by the British Board of Discretion of local authority
Agrément. The ADs are intended to give designers a consider-
able amount of flexibility. Specific details within the documents 2.17 Section 16 of the Building Act 1984 provides that the
do not have to be followed if the requirements can be met in local authority must pass the plans of any proposed work unless
some other way, although in practice, any alternative to their they are defective, or show that the work would contravene any
guidance should be pursued only with caution, rigour, and due of the Building Regulations, or unless some other provision
consultation with the approving authority. of the Act requires or authorises it to reject the plans. ‘Plans’
The ADs are revised and republished from time to time, include drawings, specifications, and information in any form
usually in response to new technologies, advancing health (section 126 of the Act).
and safety concerns, or progressively heightening standards. When considering whether the work does show a contraven-
An example is the AD guidance to Part L, where successive tion, it should be borne in mind that the Building Regulations
editions have generally prescribed ever-increasing minimum require only compliance with the Requirements in Schedule 1,
levels of thermal insulation. At the time of writing it is not the guidance in the relevant Approved Document (see para-
planned that Parts L and F will be substantially revised in late graphs 2.05–2.07).
2020 to pave the way for a 2025 ‘Future Homes Standard’ Where the building notice procedure is followed (see
aimed at improving domestic energy efficiency. Whilst the paragraph 2.23), the local authority may specify, in writing,
AD guidance may thus frequently be updated, the Schedule such plans as it requires to discharge its functions (Building
1 requirements can mostly remain unaltered as general state- Regulation 13[3]). Note that these plans will not be treated as
ments of purpose. having been deposited, and they will not be passed or rejected.
Where the full plans procedure is followed (see paragraph
2.13 Sections 6 and 7 of the Building Act 1984 define the legal 2.24), the submission must include two sets of plans together
status of the ADs. Failure to comply with their recommendations with further information, as relevant, regarding thermal ele-
does not involve civil or criminal liability, but they can be relied ments, energy status, change of use, building above existing
on by either party to any proceedings for alleged contravention sewerage, and whether the Regulatory Reform (Fire Safety)
of the Building Regulations. Thus, if an architect proves that he Order 2005 will apply (Building Regulation 14). Some local
has complied with the requirements of an AD in any proceedings authorities may decline to register plans if they are incomplete
which are brought against him, he can rely on this as ‘tending to in these respects.
negative liability’. Conversely, his failure to so comply may be The time limit for passing or rejecting the plans begins to
relied on by the claimant as ‘tending to establish liability’, and run from the date they are deposited (not the date they are reg-
the onus will be on the architect to establish that he has met the istered). If the plans are defective, they can be passed subject to
functional requirement in some other way. conditions (enabling the plans to be passed in stages), and work
In Rickards v Kerrier District Council [1987] CILL 345, in can be started within two days of the deposit.
an appeal against enforcement proceedings under section 36 of The local authority, under its duty to enforce the Building
the Building Act 1984, the High Court had to consider the Regulations, also has discretion to decide whether or not to
application of section 6. The judge held that the burden of inspect building work in progress, and it must give proper consid-
proving non-compliance with the Regulations was on the local eration to the question. Architects should, however, bear in mind
authority, but if they established that the works did not comply that local authorities do not thereby become liable for ensuring
with an AD, then the evidential burden shifted to the appellant compliance with the Building Regulations. Current English law
to show that the requirements of the Building Regulations had on this issue was established by Murphy v Brentwood District
been met. Council (1991). In a departure from earlier decisions (notably
Anns v Merton (1978)), it was held that the Council, who had
approved a defective foundation design, was not liable for the
Procedural rules cost of remedial work. Underlying principles include the view
2.14 Subject to a number of exemptions (see section 4), the that a public authority is not obliged to safeguard commer-
requirements of Part II of the Building Regulations must be met cial interests from pure economic loss – even if that loss has
where a person intends to carry out ‘building work’ or make a been incurred by remedying dangers to health or safety, which
‘material change of use’ that is subject to the control of the local Building Control is intended to prevent. A more recent case, R
authority. The procedural requirements of Part V (see paragraphs (Gresty) v Knowsley MBC (2012) appears to confirm Building
2.23–2.24 below) must also be met, and the work must comply Control ‘immunity’ in this respect. It was found, in this case,
with the relevant technical requirements of Schedule 1 of the that despite having approved defective foundations under a new
regulations. house extension, Building Control had neither any contractual
obligation, nor (following Murphy) any common law duty to the
Building work is defined in Building Regulation 3, and the householders to compensate them for necessary repairs.
related requirements are set out in Regulation 4. It follows that an architect exercising reasonable skill and
‘Material change of use’ is defined in Building Regulation 5, and care must produce designs in the knowledge that Building
the related requirements are set out in Regulation 6. Control approval does not shield the employer from loss conse-
‘Local authority’ is defined in section 126 of the Building Act quent upon design defects, or designers from responsibility to
1984. the employer for such defects. Current RIBA advice is that, irre-
spective of any received Building Control approval, an architect
The building work or the material change of use may be controlled must take care independently to design in compliance with the
by the local authority (see paragraph 2.22), or other than by the Building Regulations themselves.
local authority e.g. by an Approved Inspector (see section 3).
Breach of Building Regulations
2.15 The Building Regulations 2010, as amended, are not a
self-sufficient code, and other legislation (and non-statutory 2.18 Section 35 of the Building Act 1984 provides that a contra-
documents) must be referred to (see sections 5–8 and 15–18). vention of the Building Regulations is an offence. The position
82 Construction legislation in England and Wales

appears to be that the local authority can take enforcement action and Local Government (now the MHCLG) and obtainable from
if there is an event to which a procedural regulation attaches a the gov.uk/ government/ publications website.
requirement. An example would be commencement of build-
ing work without a building notice being given or full plans
deposited.
Control of building work by
Building Regulations 16 and 17 require the person carrying the local authorities
out building work to give notice of the commencement and com- 2.22 Unless the developer wishes to employ an approved inspec-
pletion of certain stages of the work, and for the local authority tor (see section 3) the general rule is that anyone intending to
to provide certificates upon satisfactory completion of that work. carry out ‘building work’ or make a ‘material change of use’
The local authority may give notice if the Building Regulations must give a building notice (Building Regulations 12 and 13,
have been contravened, whereupon the person carrying out and paragraph 2.23) or submit full plans (Building Regulations
building work must, within a reasonable time, take action to 12 and 14, and paragraph 2.24 below).
achieve compliance, and must notify the local authority when the Whichever procedure is adopted, the work may be inspected
correction is complete. Under Regulation 18, a local authority by the local authority’s building control officer, who may
may, with due consideration, issue a ‘regularisation certificate’ test any building work to establish whether it complies with
for building work commenced without prior submission of the Regulation 7 or any applicable Requirements of Schedule 1, and
required notice or plans. who may also take such samples of materials to be used in the
work as may be necessary to establish whether they comply with
Enforcement the provisions of the regulations (Building Regulation 18(3)).
Building work is defined in Regulation 3 to mean:
2.19 Section 36 of the Building Act provides that, without
prejudice to its right to take proceedings under section 35, the (a) the erection or extension of a building;
local authority can, by notice (a ‘section 36 notice’), require (b) the provision or extension of a controlled service or fitting
the offending work to be removed or corrected, but it has only in or in connection with a building;
12 months from the date it was completed in which to do (c) the material alteration of a building, or a controlled service
so, and cannot do so at all if the work is in accordance with or fitting, as mentioned in paragraph (2);
plans which were passed or not rejected within the time limit. (d) work required by Regulation 6 (requirements relating to
However, this does not prevent an application for an injunction material change of use);
(with the consent and in the name of the Attorney General) to (e) the insertion of insulating material into the cavity wall of a
remove or correct the work, but the court can order the local building;
authority to pay the owner of the work such compensation as (f) work involving the underpinning of a building;
it thinks just. (g) work required by Regulation 22 (requirements relating to a
change of energy status);
2.20 The person on whom a section 36 notice is served has (h) work required by Regulation 23 (requirements relating to
a right of appeal to the magistrates’ court, and an important thermal elements);
procedure is provided by section 37 of the Building Act. (i) work required by Regulation 28 (consequential improve-
Under section 37, the recipient of a section 36 notice may ments to energy performance).
notify the local authority of his intention to obtain, from a
‘suitably qualified person’, a written report about the matter As set out above, a material change of use is defined in Building
to which the section 36 notice relates. The expert’s report Regulation 5 to mean one which would result in a relevant
is then submitted to the local authority and, in light of that change of occupancy, or where the result would no longer belong
report, the authority may withdraw the notice and pay the to one of the seven Classes of building which are exempted
expenses reasonably incurred in obtaining the report, which under Schedule 2.
will relate to technical matters. If the local authority rejects A material alteration is defined in Regulation 3(2) as one
the report, it can then be used as evidence in any appeal which would result:
under section 40 of the Building Act, and if the appeal is
successful, the appellant would normally recover the costs of (a) in a building or controlled service or fitting not complying
obtaining the report as well as his other costs: Building Act with a relevant requirement where previously it did; or
1984, section 40(6). (b) in a building or controlled service or fitting which, before
the work commenced, did not comply with a relevant
requirement, being more unsatisfactory in relation to such
Dispensations and relaxations a requirement.
2.21 Section 8 of the Building Act conferred on the Secretary
of State the power to dispense with or relax any Building For these purposes a ‘relevant requirement’ means the follow-
Regulations requirement ‘if he considers that the operation of ing from Schedule 1: all requirements of Part A (structure); fire
(that) requirement would be unreasonable in relation to the par- safety requirements B1, B3, B4, and B5; all requirements of
ticular case’. Sections 9 and 10 of the 1984 Act laid down the Part M (access to and use of buildings).
procedure for application for relaxation. It applies whether the
building notice or full plans procedure has been followed. The
power has since been delegated to local authorities (Building
Building notice procedure
Regulation 11). 2.23 The procedure is governed by section 16 of the Building
If the local authority refuses the application, the applicant has Act 1984, and Building Regulations 12 and 13. It is not avail-
a right to appeal to the Secretary of State within one month. If able, and full plans must be deposited if: the Regulatory Reform
the local authority fails to give a decision within two months, (Fire Safety) Order 2005 applies to the building work, or the
section 39 of the Building Act 1984 provides that the application building will front onto a private street, or requirement H4
is deemed to be refused, and the applicant may appeal forthwith. (Building over sewers) will apply (Building Regulation 12, parts
For more detailed information see A Guide to Determinations (3), (4) and (5)).
and Appeals – Sections 16(10)(a), 39 and 50(2) of the Building There is no legally prescribed form for the notice, but it
Act 1984, published in 2011 by the Department for Communities must be signed by or on behalf of the person intending to carry
The Building Regulations 2010 83

out the work, and it must contain or be accompanied by the Applications for determination
information listed in Building Regulation 13. Local authorities
usually provide their own standard hardcopy and/or web-entry 2.25 If there is a dispute between a local authority and the
forms for this purpose. The local authority is not required to person proposing to carry out the work as to whether the plans
accept or reject the notice and has no power to do so. However, comply with the requirements of the regulations, section 16(10)
the authority may ask for any plans and information it needs of the Building Act 1984 provides for that person to apply to the
to enable it to discharge its building control functions and may Secretary of State for a determination. The current application
specify a time limit for their provision. These plans will not form on the gov.uk website stipulates a fee, i.e. half of the local
be treated as having been deposited, and the local authority authority’s plan charge, excluding VAT, subject to a minimum
has no power to pass or reject them. Information may also be limit of £100 and an upper limit of £1,000.
required in connection with the linked powers under the Act However, the application can only be made where full
(see section 5 of this chapter). Once the notice has been given plans procedure has been followed, after the plans have been
with the required charge, the work can start, provided the deposited, and before the work to which the application relates
authority is given at least two days’ notice (Building Regulation has been started. For more detailed information, see A Guide
16[1][a] and [b]). to Determinations and Appeals – Sections 16(10)(a), 39 and
A building notice ceases to have effect after three years if the 50(2) of the Building Act 1984, published by Department for
building work or building change to which the notice relates has Communities and Local Government in 2011.
not commenced (Building Regulation 13[5]).
Completion certifcates
2.26 Local authorities will issue completion certificates under
Full plans procedure the conditions set out in Building Regulation 17, i.e. princi-
2.24 The advantage of this procedure, if the developer wishes to pally when the notified building work has been satisfactorily
adopt it (or the building notice procedure is not available, see completed.
paragraph 2.23), is that the local authority cannot take any action Take note, however of paragraph 17(4), which states ‘A
under section 36 of the Building Act 1984 if the work is carried certificate given in accordance with this regulation shall be
out in conformity with the plans as passed. evidence (but not conclusive evidence) that the requirements
The procedure is governed by section 16 of the Building specified in the certificate have been complied with’ (empha-
Act and Building Regulation 12 (Giving of a building notice or sis added). See previous comments under ‘Discretion of local
deposit of plans) and 14 (Full plans). Again, there is no legally authority’ regarding responsibility for compliance and recent
prescribed form, but the deposited plans must be signed by or case law.
on behalf of the person intending to carry out the work, and
they must contain or be accompanied by the information listed Unauthorised building work
in Building Regulation 14. Again, local authorities normally
provide their own standard hardcopy and/or web-entry forms for 2.27 Where building work has been carried out without approval,
this purpose. Once the plans have been deposited (whether or not and notice was not given, the owner may apply for a regularisa-
they have been passed or rejected) with the required charge, the tion certificate (Building Regulation 18). A regularisation cer-
work can start, provided the authority is given at least 2 days’ tificate will be issued if the completed work complies with the
notice (Building Regulation 16(1)(a) and (b)). The charge which Building Regulations.
may be made is governed by the Building (Local Authority
Charges) Regulations 2010.
The local authority must pass or reject the deposited plans
Effciency and information requirements
within five weeks unless the period is extended, subject to the 2.28 The Building Regulations have the following further
written agreement of the depositor and the local authority dur- requirements for efficiency and information:
ing the five week period, to take it to two months (Building
Act 1984 clause 16(12)). Both times run from the date when Part 6, Energy Efficiency Requirements, regulations 21–28.
the plans are deposited, with the appropriate charge. Where These regulations identify buildings to which energy efficiency
for any reason the authority has not given notice of passing requirements will apply, acceptable calculation methods, refer-
or rejecting the plans within the time limit, it must refund any ence to Schedule 1 Part L (Conservation of fuel and power),
plan charge paid. and the requirements and procedure for obtaining energy
If the local authority does reject the plans, it must give its performance certificates. (Regulations 29–33 concerning
reasons and, ideally, it will do so in sufficient detail (and in suf- energy performance certificates were transferred to the Energy
ficient time) for the depositor to make the necessary changes. Performance of Buildings Regulations 2012 by BR(A)R 2016.)
The deposit of the plans is of no effect after three years Part 7, Water Efficiency, regulations 36 and 37. A person
if, within that period, the local authority gives formal notice performing building or conversion works which form a new
to that effect and the work has not started (section 32 of the dwelling must calculate the occupants’ consumption of whole-
Building Act). (Note that the lapse is not automatic as for a some water according to a government-approved calculation
building notice.) method, and must notify the local authority that a specified limit
Plans will usually be deposited with the local authority in is not exceeded.
whose area the intended work will be carried out. However, the Part 8, Information to be Provided by the Person Carrying
individual local authorities co-ordinate their services regionally Out Work. Regulation 38 applies where Schedule 1 Part B (Fire
and nationally through the Local Authority Building Control safety) applies to the building. The person carrying out the work
(LABC). This runs a Partner Authority Scheme (PAS) which must provide information adequate for maintaining fire safety to
enables plans to be deposited with the local authority of your the ‘responsible person’ identified under the Regulatory Reform
choice to be handled by LABC, together with the local authority (Fire Safety) Order 2005 (regulation 38). Regulations 39 and
in the area in which the intended work is to be carried out. It also 40 similarly require the person carrying out the work to provide
runs the Local Authority National Type Approval Confederation the building owner with information adequate to maintain ven-
(LANTAC) scheme, which enables standard designs to be tilation systems and keep consumption of fuel and power to a
approved for nationwide use. reasonable level.
84 Construction legislation in England and Wales

3 Control of building work other The above Class definitions incorporate limitations on floor
area and use. Whether or not buildings or works are included
than by the local authority among the above Classes, Building Regulations Schedule
1 Part L (Conservation of fuel and power) and/or Part P
3.01 Part II of the Building Act enables the person intending to (Electrical Safety) may nonetheless apply. Current and more
carry out the work to appoint an approved inspector to take over detailed guidance on these exemptions can be found on the
from the local authority the responsibility for ensuring compli- ‘planning portal’ website.
ance with the Building Regulations. Building Regulations Schedule 1, with its associated
It also enables approved public bodies to supervise their own Approved Document guidance, also incorporates some limita-
work, but currently this applies only to the Metropolitan Police tions or differences of degree in applicability according to a
Authority. non-exempt building’s purpose and/or dimensions.

Approved Inspectors 4.03 In addition to the exemptions from the technical require-
ments, there are some exemptions from the procedural require-
3.02 The procedures for ensuring compliance with the Building ment to give a building notice or deposit full plans. These
Regulations are governed by Part II of the Building Act are allowed under self-certification and ‘competent persons’
1984 and the Building (Approved Inspectors etc.) Regulations schemes, which are recognised under Schedule 3 of the Building
2010 and amendments. Section 49 of the Building Act defines an Regulations, or according to the categories and guidance set out
Approved Inspector, authorised under the Building Act to carry on the gov.uk ‘Competent person schemes’ web page (https://
out building control work in England and Wales, as a corporate www.gov.uk/building-regulations-competent-person-schemes).
body approved by the Secretary of State (or by a body desig- These exemptions principally cover specialist works undertaken
nated by him for that purpose) or as an individual (not a firm) by accredited skilled tradesmen.
approved by a designated body.
As effective from 2013 (announced in a DCLG Divisional
Circular of 21 December 2012), rules governing Approved 5 Other controls under the
Inspectors’ insurances were simplified, and restrictions were
lifted on the types of dwellings that they were empowered to Building Act 1984
inspect.
The Secretary of State has, since 2014, designated the 5.01 Local authorities exercise a number of statutory public
Construction Industry Council Approved Inspectors Register health functions in conjunction with the process of building con-
(CICAIR) as the body to receive all applications from corporate trol. These provisions are commonly called the ‘linked powers’
bodies and individuals for Approved Inspector status and for because their operation is linked with the authority’s building
deciding on the applications. control functions in checking deposited plans or considering a
The MHCLG has more recently issued revised guidance for building notice. The most important of these linked powers are
insuring Approved Inspectors, including a two-tier structure described below.
(MHCLG Circular Letter of 1 November 2019).
Building over sewers and drains
3.03 CICAIR maintains the registers of all corporate and indi-
vidual inspectors, and listings are available on its website. The 5.02 Sections 199 and 200 of the Water Industry Act 1991 state
Approved Inspector’s charges are negotiable on a case-by-case that sewerage undertakers must keep a map showing the loca-
basis. There is also an Association of Consultant Approved tion of all public sewers and supply a copy to local authorities
Inspectors (‘ACAI’) with industry and government links, a for public inspection. The map distinguishes among public sew-
website, and a membership list. ers those with respect to which a vesting declaration has been
made, but which has not yet taken effect, and those subject to
3.04 Recent case law at the time of writing indicates that an agreement as to future declaration. Where separate sewers
Approved Inspectors have a degree of immunity from profes- are reserved for foul and surface water, this must be clearly
sional liability comparable to that of local authority Building shown. These four groups of sewers and drains are to be shown
Control departments (see 2.17 above). Architects working with on the map.
Approved Inspectors must therefore take care to assess inde-
pendently whether proposed works comply with the Building 5.03 Section 18 of the Building Act 1984, which governed build-
Regulations. ing over sewers, was repealed in 2001. Instead, Requirement H4
(Building over sewers) of Schedule 1 to the Building Regulations
now applies, and Building Regulation 14(3)(b) requires the
4 Exemptions from control depositing of full plans, including particulars of the precautions
to be taken in building over a drain, sewer, or disposal main.
4.01 Section 4(1) of the Building Act 1984 grants exemption Building Regulation 15 requires the local authority to consult the
from building control to certain types of statutory undertakers’, sewerage undertaker and ‘to have regard to its views’.
civil aviation, and atomic energy buildings. Note, however, that
school buildings are no longer exempt, further to amendment
following the Sustainable and Secure Buildings Act 2004.
New buildings and drains
5.04 Following the repeal in 2001 of subsections 21(1) and (2) of
4.02 There are further exemptions in Building Regulation 9 the Building Act 1984, this section is no longer a linked power.
(Exempt buildings and work), detailed in Schedule 2 to the Instead, Part H (drainage and waste disposal) of Schedule 1 of
Building Regulations: the Building Regulations now applies.
In Chesterton RDC v Ralph Thompson Ltd [1947] KB 300,
Class 1 – Buildings controlled under other legislation; the High Court held that the local authority is not entitled to
Class 2 – Buildings not frequented by people; reject plans on the ground that the sewerage system, into which
Class 3 – Greenhouses and agricultural buildings; the drains lead, is unsatisfactory. What the local authority must
Class 4 – Temporary buildings; consider is the drainage of the particular building only.
Class 5 – Ancillary buildings;
Class 6 – Small detached buildings; 5.05 Under section 21(3) of the Building Act, the local author-
Class 7 – Extensions consisting of a conservatory, porch or ity can determine the method of disposal from a drain – a
carport. connection to a sewer or discharge to a cesspool or some other
Other national legislation 85

place – provided that, in the case of a sewer, it satisfies certain must not be used for the storage of inflammable materials or for
conditions. A drain is defined as being used for the drainage of the purpose of human habitation. Hoardings over seven feet in
one or more buildings within the same curtilage and a sewer height are dealt with in Section 30(5), and any such structure
(which may be private or public) as being used for the drainage which is in place for three years or more requires the approval
of buildings within two or more curtilages. of the district surveyor as to its structural stability.
Under section 22 of the Building Act, the local authority can
determine whether a building shall be drained separately into a
sewer or ‘in combination’ with two or more other buildings, by 7 Local legislation outside
means of a private sewer discharging to the sewer, if it appears
to the authority that the buildings may be drained more economi-
Inner London
cally or advantageously in this way. However, it can only do
7.01 Sections 89 and 90 of the Building Act 1984 recognise the
this when the relevant drains are first laid, not in respect of any
existence of local legislative provisions applying to construction
building for whose drainage plans have previously been passed
and require the local authority to keep a copy of those provi-
by it, unless the owners agree.
sions at its offices for inspection by the public at all reasonable
times, free of charge.
Provision of exits, etc.
7.02 Until recent reforms, there have existed many local provi-
5.06 Section 24 of the Building Act required the local authority sions enforceable in accordance with the above Section, but the
to reject plans if the entrances and exits of buildings for use trend has been towards achieving nationwide uniformity. See
by large numbers of the public were unsatisfactory. Whilst not section 17 below regarding the Regulatory Reform (Fire Safety)
repealed, this has, in effect, been superseded by the requirements Order 2005.
of Building Regulations Part B (Fire safety) and associated
Approved Document guidance. 7.03 An account of residual elements of local building leg-
islation in all categories for the nation at large is beyond the
Water supply scope of this chapter. Architects should take care to find out if
special local legislative provisions are applicable to a particular
5.07 The effect of section 25 of the Building Act is that drawings project.
of a house deposited with the local authority are to be rejected,
unless ‘there is put before (the local authority) a proposal which
appears to it to be satisfactory for providing the occupants with 8 Other national legislation
a supply of wholesome water sufficient for their domestic pur-
poses’, and, if possible, the water is to be from a piped supply. 8.01 Many general statutes contain further provisions affecting
the construction of buildings, although this may not be apparent
Height of chimneys from the titles of the Acts concerned. There are also numerous
Statutory Instruments made under powers conferred by many
5.08 Section 73 of the Building Act enables the local authority, of these Acts. In this section, some statutory rules which affect
when a building (‘the taller building’) is being erected or raised the bulk of building developments will be considered. This list
to a height greater than an adjoining building, to require any does not claim to be exhaustive, nor does it cover all the relevant
chimney of the adjoining building within 6 feet of the taller sections. See sections 10–18 below for a more detailed summary
building to be raised to the height of the taller building. of fire safety legislation, including the Regulatory Reform (Fire
Section 16 of the Clean Air Act 1993, a linked power, Safety) Order 2005.
requires the local authority to reject plans unless it is satisfied
that the height of any chimney will be sufficient to prevent, as 8.02 Certain requirements are dealt with automatically on the
far as practicable, the smoke, grit, dust, or gases from becoming deposit of drawings under the Building Regulations or, in some
prejudicial to health or a nuisance (see also paragraphs 8.03, cases, at the same time as the application for planning permis-
8.04). sion. The following are some of the more important provisions
that are relevant at that stage.
The responsibility for the enforcement of the various Acts
6 Local legislation in Inner London will fall on a variety of different bodies, not all of which are
departments of the local authority.
6.01 Inner London consists of the City of London and the
twelve London Boroughs of Camden, Greenwich, Hackney,
Hammersmith, Islington, Kensington and Chelsea, Lambeth, The Clean Air Act 1993
Lewisham, Southwark, Tower Hamlets, Wandsworth, and 8.03 Among other things, this Act controls the height of chim-
Westminster (London Government Act 1963, Schedule 1, first neys on industrial premises, types of installation, and the treat-
twelve listed boroughs). ment of offensive fumes from appliances. Sections 14 and 15 of
the 1993 Act require the approval of the local authority for the
6.02 Until 1986, the London Building Acts and by-laws formed height of a chimney serving a furnace, and approval may be
a code of control which governed the design, construction, and granted subject to conditions as to the rate and/or quality of
use of buildings in the area and differed from that which oper- emissions from the chimney. There is a right of appeal to the
ated elsewhere. On 6 January 1986, the Building (Inner London) Secretary of State.
Regulations 1985 came into effect, repealed the by-laws, applied
most of the national regulations, and amended the London 8.04 Similarly, section 16 of the Act provides that, in other cases,
Building Acts. On 1 June 1987, the Building (Inner London) the local authority must reject plans of buildings other than
Regulations 1987 came into effect and applied the remaining residences, shops, or offices unless the height of the chimney as
national regulations. shown on the drawings will, so far as practicable, be sufficient
Some original parts of the London Building Acts persisted in to prevent fumes from being a nuisance or a health hazard. The
force beyond 1987. Section 20, regarding fire safety of tall or factors to be considered are the purpose of the chimney, the posi-
large buildings, and Section 21, regarding uniting of buildings, tion and description of nearby buildings, level of neighbouring
were both repealed in 2013. ground, and other relevant matters. These provisions represent
Section 30 is still in force, and applies to consents for tem- an important negative control. Again, there is a right of appeal
porary buildings. Section 30(3) states that temporary buildings to the Secretary of State.
86 Construction legislation in England and Wales

Highways Act 1980 Construction sites are subject to the Construction (Design
and Management) (‘CDM’) Regulations 2015. This supersedes
8.05 The Act contains several provisions of interest to architects. preceding CDM legislation under which construction safety
They include highway authorities’ powers in respect of street issues would commonly be delegated to a third party ‘CDM co-
widening and setting building frontage lines (sections 73 and ordinator’. The 2015 legislation replaces this role with that of
74), means of access (sections 124 and 184), building over high- ‘Principal Designer’, intending that CDM management should
ways (section 177), precautions against accidents, including the be better integrated with a project’s central design and admin-
depositing and removal of a skip on a highway (sections 139, istration processes.
140, and 168), and powers in respect of adopting privately con- The CDM regulations set out procedures for predicting health
structed roads for maintenance at public expense (section 38). and safety risks, sharing relevant information, monitoring par-
Some of these provisions may be enforced by the highway ticipants’ obligations, and producing adequate records.
authority, others implemented by conditions attached to plan- The Principal Designer might typically be the architect or
ning consents (see Chapter 11). The Act’s provisions in respect other type of lead designer, performing this role as a distinct
of ‘New Streets’ (sections 186–202) were repealed in 1991. The and additional professional service. Subject to possessing and
New Roads and Street Works Act was introduced in the same exercising suitable skills, a ‘design and build’ contractor can
year. act as both the ‘Principal Designer’ and ‘Principal Contractor’
within a project’s CDM framework.
8.06 Section 73 requires the highway authority’s consent, where Work at height is covered separately by the Work at Height
an improvement line has been prescribed, to the erection of a Regulations 2005.
building and the making of any permanent excavation in front The Workplace (Health, Safety and Welfare) Regulations
of the improvement line. This may be granted with conditions. 1992 require employers to ensure, as far as is reasonably practi-
There is a right of appeal against a refusal of consent or its cable, the health, safety and welfare of their employees at work.
granting subject to conditions. The regulations, which expand on these duties, include require-
ments for ventilation, lighting, sanitary conveniences, washing
8.07 Section 74 requires the highway authority’s consent to the facilities, drinking water, etc. (see Chapter 15).
erection of a new building (but not a boundary wall) in front of The existence of asbestos in older buildings continues to be
the building line. This may be granted with conditions or for a a matter of health and safety concern. Earlier 2006 regulations
limited time. were replaced by The Control of Asbestos Regulations 2012,
conforming to more restrictive European standards. For all non-
8.08 Section 124 enables the Secretary of State, by order, to domestic premises, the building owner has a duty to manage
authorise the highway authority to stop up a private access to the handling or containment of any asbestos by ascertaining
the highway if he or she considers that the access is likely to its location and extent, assessing the risk it presents, planning
cause danger to, or interfere unnecessarily, with traffic on the appropriate action, and maintaining adequate records. Measures
highway. However, the order can only be made where no access required to deal with asbestos can incur substantial cost and
to the premises from the highway is reasonably required, or time, and architects should be mindful of this when a design will
where another reasonably convenient means of access is avail- require alteration or demolition of existing building construction.
able or will be provided. There is an objection procedure and The Health and Safety Executive (HSE) is responsible
compensation may be payable. for enforcing these regulations. The HSE’s business plan for
2019/2020 indicates that it will be especially proactive in
8.09 Sections 139 and 140 require precautions to be taken where scrutinising the role and performance of designated Principal
a person is carrying out works in the street such as the planking Designers.
and strutting of drainage works and shoring up any building
adjoining a street. Stringent safety precautions must be observed
in relation to builder’s skips. They must not be placed on the Party Wall etc. Act 1996
highway without the authority’s consent. This may be granted 8.13 The Act, which came into force on 1 July 1997, drew on the
subject to conditions. sections of the London Building Act dealing with party walls,
Section 168 provides that if, in the course of carrying out which it replaced. It applies to the whole of England and Wales
building work in or near the highway, an accident gives rise to (except the four Temples) to provide a national framework for
the risk of serious bodily injury to a person in the street, the preventing and resolving disputes between neighbouring owners
owner of the land is guilty of an offence. Hoardings and scaf- in respect of party walls and similar matters. It deals with three
folding in or adjoining the highway require a licence from the main issues: construction of new walls on boundaries between
highway authority. adjoining owners’ land (section 1); carrying out works to, or
repair of, a party wall and the rights of the owner (section 2);
8.10 Section 177 requires a license from the highway authority and excavation near to neighbouring buildings (section 6). See
for the construction and subsequent alteration of buildings or Chapter 14 for procedures.
parts of buildings over highways maintained at public expense.
This may be granted subject to conditions, and may be registered
as a local land charge (see Chapter 4). Environment Acts 1995/1999
8.14 The Act is administered by the Environment Agency.
8.11 Section 184 enables a building owner to initiate proposals Matters of concern to the Agency include contaminated land,
to create a new means of access to his property to be constructed flooding, and the disposal of effluents.
at his own expense for, for example, a vehicle crossing to a Contaminated land may, on the advice of the Agency, be
garage. In certain circumstance, the authority may, on its initia- subject to planning conditions. It is also subject to Building
tive, construct the crossing at the owner’s expense. Regulations Schedule 1, Part C, requirement C1 (Preparation of
site and resistance to contaminants) and its associated Approved
Health and Safety at Work etc. Document guidance.
Act 1974 and CDM Regulations Flooding may also, on the advice of the Agency, be subject
to planning conditions to limit possible obstructions to flows
8.12 The Act and the regulations made pursuant to it contain (which may be contaminated by sewage). The Part C Approved
provisions relating to health and safety during the construction Document also provides guidance regarding potential flooding
process and in the workplace, and the design (which includes in relation to buildings and their groundworks.
specification) should take account of these requirements (see Effluent disposal is unlikely to be subject to planning condi-
also Chapter 15). tions (except perhaps in the case of major projects), but the
Technical harmonisation and standards 87

consent of the Agency to outfalls is required (except for infiltra- Buildings (England and Wales) Regulations 2012, with subse-
tion systems) and may be subject to conditions. The Building quent amendments.
Regulations Schedule 1 Part H requirements for drainage and The Licensing of Houses in Multiple Occupation (Mandatory
waste disposal may be relevant. Conditions of Licences) (England) Regulations 2018 impose
additional and more detailed requirements for minimum floor
areas and other features of HMOs. The MHCLG has published a
Clean Neighbourhoods and summary of current powers and requirements relating to HMOs
Environment Act 2005 in Houses in Multiple Occupation and residential property
8.15 Section 54 of the Act contains provisions for the prepara- licensing reform [/] Guidance for Local Housing Authorities
tion of plans for the management and disposal of site waste. The (current edition December 2018 at time of writing), obtainable
Regulations make provisions for the circumstances under which through the gov.uk website.
a plan must be prepared, the enforcement power to the local
authority, and the penalties for any offences.
Part 8 made provisions for the establishment of the Special classes of building
Commission for Architecture and the Built Environment 8.18 The legislation dealt with so far is, in one sense, of general
(‘CABE’). CABE was merged into the Design Council in 2011, application. The architect dealing with the design and con-
and the relevant sections 87–89 of the Act duly repealed. struction of specialised types of building may find that special
Section 94 of Part 8 gives the Secretary of State the power controls apply. All these specialised provisions are extremely
to provide financial or other assistance to persons promoting complex, and space does not permit any detailed examination
education or high standards in architecture and the design and of them. They range from premises (such as nursing homes and
management of the built environment. schools) to special risks (such as cinemas and the keeping of
radio-active substances) (See Chapter 7).
Equality Act 2010
8.16 The Equality Act 2010 has replaced the preceding Disability The Licensing Act 2003
Discrimination Act 1995 (except in Northern Ireland). 8.19 The Act governs the operation of entertainment premises
The Act requires reasonable adjustments to be made in rela- and premises where alcohol is sold. Application for a licence
tion to buildings’ accessibility, in effect extending the obligations must be made to the local authority Licensing Committee,
already imposed by Building Regulations Schedule 1, Part M which would normally include representatives of the local
(Access to and use of buildings). The Act’s scope and relation- area’s planning, police, fire, health/safety, and environmental
ship with Part M is explained in a DCLG circular letter dated authorities.
9 December 2011 and accessible via the gov.uk web pages.
This states The licensing objectives are –
The Equality Act requires reasonable adjustments to be made (a) the prevention of crime and disorder;
in relation to accessibility. In practice, this means that due (b) public safety;
regard must be given to any specific needs of likely build- (c) the prevention of public nuisance; and
ing users that might be reasonably met. Compliance with the (d) the protection of children from harm.
requirements of Part M does not therefore signify compliance
with the much broader obligations and duties set out in the Apart from sale of alcohol, The Licensing Act applies to enter-
Equality Act. This is a source of frequent misunderstanding. tainment venues which accommodate:
New building works are, however, exempt from the Act for a (a) plays – both performance and rehearsal;
10-year period, as long as the Part M provisions applicable at (b) the showing of films (or any exhibition of moving pictures);
the time of the works are complied with. (c) indoor sporting events;
Insofar as the Act applies, the duty to make reasonable adjust- (d) outdoor boxing and wrestling matches. No other form of
ments in relation to accessibility is set out in paragraph 2 of both outdoor sport would be regulated by the Act;
Schedule 2 (in relation to public authorities and service provid- (e) music: both the performance of live music and the playing
ers); Schedule 8 (in relation to employers); and Schedule 15 (in of recorded music;
relation to associations). (f) performance of dance;
The Equality Act may, through these provisions, have a
significant effect upon the design of renovation or remedial where the entertainment takes place in the presence of an audi-
building works. ence and is provided for their entertainment.
The Licensing Authority may stipulate additional provi-
Housing Act 1985/2004 sions for the welfare and safety of the staff and customers of
the licensed premises. This may have a significant effect on
8.17 These Acts contain provisions relating to the fitness of the design of the premises, and the architect should consult
dwellings, including houses in multiple occupation, and some the licensing authority at an early stage in the design. See
environmental health authorities use their wide-ranging powers Chapter 7 for further detail.
to seek to impose requirements that the Building Regulations
have dropped (such as minimum ceiling heights and venti-
lated WC lobbies) or have chosen not to introduce. The Act is
enforced by environmental health officers and negotiation seems
9 Technical harmonisation
to be the best policy. and standards
The Housing Act 2004, which replaces certain parts of the
1985 Act, was brought into force in November 2004, and it The Construction Products
replaces the existing housing fitness standard with a Housing
and Safety Rating System and the introduction of a scheme to
Regulation (EU) 305/2011
license higher-risk Houses in Multiple Occupation (‘HMO’). The 9.01 The previous Construction Products Directive (1989) was
Act also introduced the requirement for Home Information Packs replaced by the Construction Products Regulation (‘CPR’),
to be produced by sellers or estate agents. This requirement was with effect from June 2013. This European Union regulation
suspended in 2010, except that Energy Performance Certificates is adopted and enforced under the (UK) Construction Products
are still required, now subject to The Energy Performance of Regulations 2013.
88 Construction legislation in England and Wales

The Regulation is intended to harmonise standards of product and 52 livery company halls were destroyed, as were courts,
quality and performance so as to facilitate free movement of gaols and civil administration buildings …’
building products between and throughout EU countries includ-
ing the UK. 10.02 Following the Great Fire, in 1666, An Act for rebuilding the
It sets out the procedures relating to ‘CE’ quality marking and Citty of London decreed ‘… That all the outsides of all Buildings
establishes basic requirements in respect of: in and about the said Citty be henceforth made of Bricke or Stone
or of Bricke and Stone together …’ Party walls and external
● mechanical resistance and stability; walls were to be 1–2½ bricks thick. Timber buildings were effec-
● safety in case of fire; tively excluded from the capital. Over the following 350 years,
● hygiene health and environment; the London Building Acts, and then the national Building
● safety and accessibility in use; Regulations, were developed on the basis of masonry buildings.
● protection against noise;
● energy economy including heat retention; 10.03 Fire safety regulation and guidance have continued to be
● sustainable use of natural resources. influenced by real fire events, and historically, both have been
revised after major fire incidents, particularly where there have
The CPR is cited in the Approved Document guidance to been fatalities.
Building Regulation 7 governing materials and workmanship.
The CPR is of concern principally to product manufacturers
and distributors, but may concern architects or other construction Fires in the modern era infuencing
specifiers to the extent that ‘CE’ certification may be a stand- fre safety regulation and advice
ing requirement for some employers or categories of product.
Knowsley Heights fire, 5 April 1991
Requiring ‘CE’ conformity would also attest to the specifier’s
reasonable skill and care in the event of any subsequent alleged
10.04 A recently over-clad, concrete-cored, 11-storey block of
failure related to the product. ‘CE’ conformity also enables con-
flats suffered a deliberately ignited fire started in a rubbish com-
sistency of design and replication of details and specifications
pound at ground level. The fire spread in the cavity between the
where buildings of intentionally similar purpose and appearance
cladding and the concrete walls of the building. The remedial
(such as for a retail franchise) are to be erected in different
works involved the removal of the ground floor cladding to
European countries.
diminish the risk of arson attack and the introduction of hori-
At the time of writing, it is unclear whether or to what degree
zontal cavity barriers at each floor level to inhibit fire spread
law and standards in the EU and UK will remain integrated, and
within the cavity.
what the status of ‘CE’ marking in the UK will eventually be.
10.05 Consequently, the provision of cavity barriers was recom-
mended at each compartment wall and floor behind rainscreen
10 Fire safety: historical cladding in residential and institutional buildings in Approved
background Document B Fire safety (‘ADB’) 1992. Additionally, the ‘Class
0’ recommendations for the exterior surface of the cladding were
10.01 On 2 September 1666, ‘a most dreadfull Fire’, originating applied to the cavity face of the cladding in ADB 1992.
in a bakery in Pudding Lane, raged for four days, destroying
the City of London from the Tower in the east to Fetter Lane, 10.06 ADB 1992 also recommended that in a building with a
beyond the city walls to the west. ‘13,200 houses, 87 churches storey at more than 20m above ground level, insulation material

Samuel Rolle’s ‘The burning of London in the year 1666’ (London, 1667) Credit: Museum of London
Fire safety: historical background 89

used in the external wall construction should be of limited com- or to be proven through full-scale testing not to pose an
bustibility. However, this recommendation was less demanding unacceptable level of risk in terms of fire spread. The BRE
than its predecessor, ADB 1985, which advised that the entire full-scale fire tests were developed to become BS 8414-1:
external wall should be constructed of materials of limited com- 2002 and BS 8414-2: 2005 – Fire performance of external
bustibility if the building was more than 15m in height. cladding systems.

10.07 The Knowsley Heights fire also motivated research at the 10.15 BRE report (BR 135) Fire performance of external ther-
Building Research Establishment (BRE), carried out in 1994. mal insulation for walls of multi-storey buildings was revised
BRE developed a large-scale fire test method, known as ‘A test in 2003 to incorporate the knowledge gained, and revised again
for assessing the fire performance of external cladding systems’, in 2013 to address new technologies in cladding and external
submitted to the government in 1996. This was the forerunner of wall systems.
the BS 8414 large-scale fire tests.
10.16 In response to the Garnock Court fire, in the revised ADB
Sun Valley Poultry fire, 6 September 1993 2000, provision of cavity barriers was recommended at the edges
of cavities around window, door, and other openings in the exter-
10.08 During the 1990s, there were at least 30 fires in the UK nal wall construction in all buildings.
involving composite panels, both internal and external.
10.17 However, in ADB 2000, the scope of the limited com-
10.09 Polystyrene-cored composite panels had become widely bustibility recommendation was narrowed from the insulation
used for internal partitioning within the food industry, particularly material used in the external wall construction to only the
cold storage. The large, refrigerated Sun Valley Poultry factory insulation material used in ventilated cavities in the external
had ceilings of metal-faced composite panels with cores of insu- wall construction. The critical building height that triggered
lating EPS and PUR polymeric foam, and walls of composite the limited combustibility recommendation was reduced to 18m
panels with EPS, PUR, and Rockwool cores. Two firefighters high, rather than 20m high.
died when the EPS-cored steel ceiling panels, which were secured
in place with polypropylene fixings, collapsed on top of them. 10.18 The 2006 revision of ADB, together with the intro-
duction of the Regulatory Reform (Fire Safety) Order (see
10.10 Lessons learned from the Sun Valley fire and other related, Section 17 below), was the output of a major overhaul of fire
but non-fatal, incidents led to the inclusion of Appendix F, Fire safety legislation.
behaviour of insulating core panels used for internal structures,
in ADB 2000. 10.19 In subsequent years, concerns were expressed in the con-
struction and fire sectors about timber-framed housing and the
10.11 Appendix F: Fire behaviour of insulating core panels used hazards presented (a) on building sites, when the timber was
for internal structures stated: exposed during the construction period; and (b) when fire spread
in the voids between the double stud external and compartment
Fire fighting walls of completed buildings.
3 When compared with other types of construction techniques,
these panel systems therefore provide a unique combination 10.20 ADB was not revised to address timber frame construc-
of problems for firefighters, including: tion site or cavity fires, nor the increased use of combustible
plastic components and other ‘modern methods of construc-
• hidden fire spread within the panels; tion’, which include off-site, pre-fabricated sub-assemblies
• production of large quantities of black toxic smoke; and components (door sets, timber I-beams, prefabricated
and chimneys, and dormers), panellised systems (e.g. timber and
• rapid fire spread leading to flashover. steel frame), floor and roof cassettes, ‘volumetrics’ (large
These three characteristics are common to both polyure- modules fully fitted out on-site), ‘pods’ (prefabricated room-
thane and polystyrene cored panels, although the rate of fire sized modules, normally bathrooms or kitchens) and composite
spread in polyurethane cores is significantly less than that of cladding panels.
polystyrene cores, especially when any external heat source
is removed. 10.21 In 2012, news came from the Middle East about outbreaks
In addition, irrespective of the type of panel core, all sys- of spectacular exterior fires involving new-build skyscraper
tems are susceptible to: blocks clad with aluminium-faced polyethylene-cored composite
cladding panels. Similar fires occurred in the recessed balconies
• delamination of the steel facing; of a re-clad 18-storey social housing block in Roubaix, France
• collapse of the system; (2012), with one fatality, in Melbourne (2014), and again in
• hidden fire spread behind the system. Dubai (2015).

Garnock Court fire, 11 June 1999 10.22 There were significant UK fire events during this time,
notably the Lakanal House fire of 3 July 2009 in which six peo-
10.12 A fire started in a flat on the fifth floor of a 14-storey ple died, which involved high pressure laminate (HPL) cladding
residential housing block in Scotland. The fire broke out of a panels. Following the 2013 Inquest, the Coroner recommended
window and ignited PVC window frames and GRP window to government that ADB should be reviewed to provide clear
surrounds, which formed a ribbon of combustible material up guidance on Part B4 (external fire spread).
the height of the building. The flames reached the 12th floor ten
minutes later. An elderly resident died in the fire. 10.23 However, the 2006 ADB guidance was not substantively
revised until 2018, despite the nature of construction evolving
10.13 Following the Garnock Court fire, a parliamentary inquiry rapidly in the interim.
was undertaken to investigate the potential risk of fire spread in
buildings by way of external cladding systems. The report was Grenfell Tower fire, 14 June 2017
published early in 2000.
10.24 A fire at Grenfell Tower, London on 14 June 2017 led to
10.14 The committee concluded that all external cladding sys- the death of 72 people; the greatest loss of life as the result of
tems should be required either to be entirely non-combustible, a fire in the UK in modern times.
90 Construction legislation in England and Wales

10.25 The fire commenced in the kitchen of a fourth-floor The Building (Amendment)
apartment in the 24-storey residential block and spread to the Regulations 2018
external cladding, which had recently been refurbished and
over-clad with a rainscreen system of aluminium-faced poly- 12.03 The Building (Amendment) Regulations 2018 came into
ethylene-cored panels over polyisocyanurate (PIR) insulation force in England on 21 December 2018. These Regulations do
boards. The fire spread rapidly up the façade and around to the not apply to any building in Wales.
other facades, engulfing the building and spreading internally
to most areas. 12.04 The Building (Amendment) Regulations 2018 contain
detailed and prescriptive technical requirements, conspicuously
10.26 Lines of internal fire compartmentation proved ineffective, unlike the broad functional requirements of Schedule 1 to the
and many residents who initially remained within the single- Building Regulations 2010.
staircase building in accordance with the planned stay-put policy
were unable to escape. 12.05 Paragraph 6 is added to Building Regulation 2, interpret-
ing and defining ‘external wall’ to include any voids within
10.27 A public inquiry to investigate the causes of the fire, the wall, any external decorative finish, any windows or doors,
the performance of the building in the fire, and other associ- and any roof over 70° to the horizontal, if adjoining accessible
ated issues continues at the time of writing this edition of the accommodation.
Architect’s Legal Handbook.
12.06 Paragraph 4 is added to Building Regulation 7, containing
10.28 The Grenfell Tower fire led to a widespread review of fire the following definitions:
safety of tall residential buildings and to an independent review
of building regulations and fire safety, which was published on (a) a “relevant building” means a building with a storey (not
17 May 2018. including roof-top plant areas or any storey consisting
exclusively of plant rooms) at least 18 metres above
10.29 Revisions to Building Regulations and associated guid- ground level and which—
ance have followed, as further reviewed below. (i) contains one or more dwellings;
(ii) contains an institution; or
10.30 The 2018 amendments to the Building Regulations (iii) contains a room for residential purposes (excluding
2010 and to ADB, and publication of the new ADB 2019 stem any room in a hostel, hotel or boarding house); and
directly from the Grenfell Tower fire. (b) “above ground level” in relation to a storey means above
ground level when measured from the lowest ground level
adjoining the outside of a building to the top of the floor
11 Fire safety and the Building surface of the storey.
Regulations 2010 The measures of the Building (Amendment) Regulations 2018,
which effectively ban the use of combustible cladding in external
11.01 Fire safety is covered principally by Part B of Schedule walls, apply to ‘relevant buildings’.
1 to the Building Regulations.
12.07 A new paragraph (k) is added to Building Regulation 5
11.02 Where there is a material change of use of the whole of (meaning of material change of use), to include:
a building, Building Regulation 6 requires some components of ‘… a building described in regulation 7(4)(a), where previ-
Schedule 1 Part B to be applied in respect of fire safety. They ously it was not’.
include in all cases, B1 (means of warning and escape), B2 This means any residential or institutional building that is
(internal fire spread – linings), B3 (internal fire spread – struc- extended up to over 18m high to the top storey, or any building
ture), B4(2) (external fire spread – roofs), B5 (access and facili- of that height which is converted for residential or institutional
ties for the fire service), and, in the case of a building exceeding use, is deemed to have undergone a material change of use, and
15m in height, B4(1) (external fire spread – walls). the same requirements apply to its external walls as for a new-
build ‘relevant building’.
11.03 Building Regulation 12(3) requires that a person intend-
ing to carry out building work in relation to a building to which 12.08 A new paragraph 3 is added to Building Regulation 6:
the Regulatory Reform (Fire Safety) Order 2005 applies, or will
apply after the completion of the building work, shall deposit (3) Subject to paragraph (4), where there is a material change
full plans with the local authority or Approved Inspector. of use described in regulation 5(k), such work, if any, shall be
carried out as is necessary to ensure that any external wall,
11.04 Building Regulation 38 requires the person carrying or specified attachment, of the building only contains materi-
out the building work shall give fire safety information to the als of European Classification A2-s1, d0 or A1, classified in
‘Responsible Person’ not later than the date of completion of accordance with BS EN 13501- 1:2007+A1:2009 entitled
the work, or the date of occupation of the building or extension, “Fire classification of construction products and building
whichever is the earlier. (See Section 17 Regulatory Reform elements. Classification using test data from reaction to fire
[Fire Safety] Order 2005 below.) tests” (ISBN 978 0 580 59861 6) published by the British
Standards Institution on 30th March 2007 and amended in
November 2009.
12 Fire safety and amendments (4) Paragraph (3) does not apply to the items listed in
to Building Regulations regulation 7(3).

12.01 The amendments that specifically refer to fire issues 12.09 A new paragraph 2 is added to Building Regulation 7:
are the Building Regulations &c. (Amendment) Regulations
2012 and the Building (Amendment) Regulations 2018. (2) Subject to paragraph (3), building work shall be carried
out so that materials which become part of an external wall,
12.02 The Building Regulations &c. (Amendment) Regulations or specified attachment, of a relevant building are of European
2012 made minor changes to the requirements at completion of Classification A2-s1, d0 or A1, classified in accordance with
building works, more onerous for non-domestic buildings than BS EN 13501-1:2007+A1:2009 entitled “Fire classification
for family houses. of construction products and building elements. Classification
Fire safety and amendments to Building Regulations 91

using test data from reaction to fire tests” (ISBN 978 0 580 Wales
59861 6) published by the British Standards Institution on
30th March 2007 and amended in November 2009. 12.17 The Building Act 1984 was amended by the Welsh
Ministers (Transfer of Functions) (No. 2) Order 2009.
12.10 “Specified attachment” means—
12.18 The National Assembly for Wales passed the Domestic
i. a balcony attached to an external wall; Fire Safety (Wales) Measure 2011, and it received Royal
ii. a device for reducing heat gain within a building by approval on 7 April 2011. The Measure included a require-
deflecting sunlight which is attached to an external wall; ment to provide automatic fire suppression systems (usually
or sprinklers, but also water mist and other suppression systems)
iii. a solar panel attached to an external wall. on completion or occupation of a new residence, a conversion
to a residence, a subdivision, or amalgamation of a residence. A
12.11 These paragraphs make it clear that henceforth, external ‘residence’ included any:
cladding panels, external finishes, and other materials in or
attached to the external wall construction (with the exceptions (a) dwelling-house;
listed in paragraph 3) of a new, extended, or materially altered, (b) flat;
residential, or institutional ‘relevant building’, over 18m high to (c) care home;
the top storey, must be either European Class A2-s1, d0, or A1. (d) residential accommodation for pupils or students of a
school, college, university, or other educational institution;
12.12 These European classes replace the national classifications (e) room or group of rooms within a building, intended to be
‘limited combustibility’ and ‘non-combustible’, terms derived used for living and sleeping; and
from BS 476, with the slightly more demanding European (f) the common parts of a building containing one or more
classes to BS EN 13501-1:2007 as amended 2009. residences.
The substantive provisions of the Measure did not come into
12.13 However, there are exceptions to the Building Regulation force immediately.
7(2) requirements, listed in Regulation 7(3):
12.19 The power to make building regulations applying to Wales
(3) Paragraph (2) does not apply to— was transferred to Welsh Ministers from 31 December 2011. A
(a) cavity trays when used between two leaves of masonry; Building Regulations Advisory Committee for Wales was estab-
(b) any part of a roof (other than any part of a roof which lished, the counterpart of the English body.
falls within paragraph (iv) of regulation 2(6)) if that
part is connected to an external wall; 12.20 In addition to amendments applicable in the UK, Statutory
(c) door frames and doors; Instruments amending the Building Regulations in Wales were
(d) electrical installations; made in 2013 (3 times), 2014, 2015, 2016 (twice), 2017, and
(e) insulation and water proofing materials used below 2018 (twice).
ground level;
(f) intumescent and fire stopping materials where the inclu- 12.21 The Building Regulations &c. (Amendment No. 3)
sion of the materials is necessary to meet the requirements and Domestic Fire Safety (Wales) Regulations 2013 inserted
of Part B of Schedule 1; Regulation 37A into the Building Regulations 2010 in relation
(g) membranes; to Wales: a requirement to fit automatic fire suppression systems.
(h) seals, gaskets, fixings, sealants and backer rods; The Amended Building Regulations came into force on 30 April
(i) thermal break materials where the inclusion of the materi- 2014 in relation to:
als is necessary to meet the thermal bridging requirements (i) care homes;
of Part L of Schedule 1; or (ii) rooms for residential purposes (excluding hotels, hostels,
(j) window frames and glass. prisons, and hospitals).

12.14 The fire classification requirements for external wall mate- The amended Building Regulations came into force on 1 January
rials in tall residential and institutional ‘relevant buildings’ are 2016 in relation to dwellinghouses and flats.
more demanding and more widely applicable than previously
advised in Approved Document B Fire Safety 2006, Volume 12.22 The Building (Amendment) (Wales) Regulations
2 Buildings other than dwellinghouses, amended 2007, 2010, 2017 extended the requirement to fit automatic fire suppression
and 2013 (‘ADB 2006’) and they are mandatory requirements, systems to residential hostels, i.e. not Youth Hostels or back-
not merely recommendations as previously, in ADB 2006. packers’ hostels.

12.23 The Building Regulations &c. (Amendment) (Excepted


12.15 Unlike ADB, the new Building Regulations 6(3) and 7(2) Energy Buildings) (Wales) Regulations 2018 extended the require-
do not accept as compliant external walls of a ‘relevant build- ment to fit automatic fire suppression systems to ‘excepted energy
ing’ containing combustible insulation or cladding meeting the buildings’, which were not previously under Welsh control.
performance criteria given in the BRE Report Fire performance
of external thermal insulation for walls of multi storey buildings 12.24 The requirement for automatic fire suppression in residen-
(BR 135) for cladding systems using full scale test data from tial buildings was a major divergence from building control in
BS 8414-1: 2002 or BS 8414-2: 2005. All materials (other than England, where sprinkler installations are only a requirement in
the specific exemptions listed in Regulation 7(3)) must be clas- buildings over 30m high to the top storey level, although encour-
sified A2-s1, d0, or A1, to BS EN 13501-1: 2007 (amendment aged in other buildings.
A1: 2009).
The Building (Amendment) (Wales) Regulations 2019
12.16 The Building (Amendment) Regulations 2018 accept
neither desktop study reports from fire specialists, nor a fire 12.25 The Building (Amendment) (Wales) Regulations
engineered approach to BS 7974, as options for demonstrat- 2019 came into force in Wales on 13 January 2020.
ing compliance with Part B4 (1) of Schedule 1 to the Building
Regulations 2010 regarding a ‘relevant building’, although these 12.26 The regulations amend the requirements against the exter-
approaches were previously accepted by Building Control bodies nal spread of fire and prohibit the use of combustible materials
prior to the Grenfell Tower fire. in the external walls of certain buildings over 18m in height.
92 Construction legislation in England and Wales

12.27 The Building (Amendment) (Wales) Regulations 2019 are 13.07 Also close to the front of each volume of ADB 2019 is
very similar to the Building (Amendment) Regulations 2018 in Table 0.1, Classification of purpose groups, ‘promoted’ from
England (see above). The discernible differences include the Appendix D in ADB 2006. The Purpose Groups are exactly
following: the same as in Appendix B, Table B4, Minimum periods of fire
resistance, correcting an anomaly in ADB 2006.
(a) Regulation 2(6)(b) only includes balconies and solar pan-
els as ‘specified attachments’, not shading devices (brises 13.08 The broad arrangement of sections: Introduction, Parts B1
soleils) as in England; to B5, and Appendices will be familiar to architects who know
(b) Regulation 2(7) does not apply in relation to excepted ADB 2006, but the precise order of contents has changed.
energy buildings in Wales;
(c) In Regulations 6(3) and 7(2), the reference to BS EN Technical recommendations of ADB 2019
13501-1 is updated to 2018.
England
ADB Volume 1: Dwellings (2019)
13 Fire safety: guidance documents
13.09 ADB 2019, Volume 1 now includes recommendations for
Approved Document B (Fire Safety) (2019) flats in addition to houses. As a result, the document has sacri-
ficed the brevity of its 2006 predecessor. It has almost doubled
13.01 Approved Document B (‘ADB’) applies to Part B (Fire in size and is scarcely less bulky than Volume 2.
safety) of Schedule 1 to the Building Regulations as amended.
The current edition of ADB in England is the 2019 edition, 13.10 Part B1, regarding means of escape in dwellinghouses,
which came into force on 30 August 2019. Like the other ADs, is generally similar to ADB 2006, but paragraph 2.7 adds new
it is freely available online at https://www.gov.uk/government/ guidance on passenger lifts.
collections/approved-documents.
13.11 Part B1 regarding means of escape in blocks of flats,
13.02 The 2006 edition of ADB was published in two volumes: paragraph 3.3 advises:
Volume 1, Dwellinghouses; and Volume 2, Buildings other than
dwellinghouses (including flats). The 2019 edition of ADB, 3.3 Provisions are recommended to support a stay put evacu-
Volume 1 deals with Dwellings, including blocks of flats, while ation strategy for blocks of flats. It is based on the principle
Volume 2 concerns all other types of building covered by the that a fire is contained in the flat of origin and common escape
Building Regulations. The logic for this change is not explained routes are maintained relatively free from smoke and heat. It
in ADB 2019, but ADB 2019 is now consistent with Approved allows occupants, some of whom may require assistance to
Documents L and M, which are published in 2 or more volumes: escape in the event of a fire, in other flats that are not affected
Dwellings and Buildings other than dwellings. to remain.
Sufficient protection to common means of escape is neces-
13.03 The Summary of the main changes states that there are sary to allow occupants to escape should they choose to do so
no (technical) changes in the advice from the previous ADB or are instructed/aided to by the fire service. A higher standard
2006 edition, including all amendments. However, there were of protection is therefore needed to ensure common escape
very significant amendments in November 2018 and further routes remain available for a longer period than is provided
amendments in December 2018 and April 2019, so the architect in other buildings.
should read the text of the published advice carefully. ADB
2019 has been re-written, and is generally in plainer, simpler 13.12 The principle of the ‘stay-put’ or ‘defend in place’ evacu-
language than its predecessor. However, this makes any subtle ation strategy was not explained in previous editions of ADB.
changes from ADB 2006 less obvious to discern. The ‘stay-put’ evacuation strategy has been normal in blocks of
flats constructed since 1962 and overwhelmingly has worked
13.04 The main changes, as described in ADB 2019, are: satisfactorily in the vast majority of fires in blocks of flats. (See
‘Fire safety in purpose-built blocks of flats’, Local Government
• The design of blocks of flats has moved from volume Association (2012), Appendix A1, paragraph A1.27 et seq.)
2 to volume 1. However, the ‘stay-put’ evacuation strategy is dependent on
• Guidance on the design of sprinkler systems has been effective compartmentation, which failed at both Lakanal House
consolidated to a new Appendix E. and Grenfell Tower.
• European fire classifications are provided within the
main body of the document with transposition to a 13.13 Guidance concerning common escape routes in blocks
national classification provided in Appendix B. of flats appears substantively unchanged, despite post-Grenfell
• The guidance on external stairs has been consolidated. lobbying. Under paragraph 3.27 and Diagram 3.7, a single
• Fire safety information (under regulation 38) has been escape route and a single common stair are acceptable, subject
moved from an appendix into a new section. to provision of a protected lobby or corridor, 7.5m maximum
• The guidance on insulating core panels has moved travel distance in that protected lobby or corridor, and provision
from an appendix into the Wall and ceiling linings of smoke ventilation in the lobby or corridor next to the stair in
section. accordance with paragraphs 3.50–3.53.
• The guidance on fire dampers and ventilation systems
has been consolidated. 13.14 Paragraph 3.51b.iii was corrected in September 2019 to read:

3.51 Smoke vents should comply with one of the following.


13.05 No sooner than ADB 2019 was published, it was cor-
rected, in September 2019. The old version was removed and a. They should be located on an external wall with minimum
replaced on the Planning Portal website. The corrected issue is free area of 1.5m2.
superficially indistinguishable from the first issue, but note that b. They should discharge into a vertical smoke shaft, closed
the up-to-date version has an index at the end. Attention is drawn at the base, that meets all of the following criteria.
to the corrected items in the detailed review below. …

13.06 At the beginning of each volume, before even the iii. The smoke shaft should be constructed from a class
Contents pages, there is a summary of the provisions of Building A1 material. All vents should either be a fire doorset
Regulations 2010 (as amended 2018), Regulations 3–7. (see Appendix C, Table C1, item 2.e for minimum fire
Fire safety: guidance documents 93

resistance) or fitted with a smoke control damper achiev- (a) BS 9251 for residential buildings; and (b) BS EN 12845 for
ing the same period of fire resistance and designed to non-residential buildings and for residential buildings outside
operate as described below. The shaft should be vertical the scope of BS 9251.
from base to head, with a maximum of 4m at a maximum
inclined angle of 30 degrees. 13.27 Former Appendix F: Fire behaviour of insulating core
panels used for internal structures is omitted, but much abridged
13.15 Under Part B2 and paragraph 4.10, brief advice is given recommendations are included in Section 6, paragraph 6.11.
on the fire behaviour of insulating core panels used internally,
much briefer than the advice in Appendix F in Volume 2 of ADB 13.28 New Appendix F: Standards referred to updates the refer-
2006, which has largely been left out. ences to include:
13.16 In September 2019, the guidance in relation to double- BS 8414-1: 2015+A1: 2017 Fire Performance of external clad-
skinned insulated roof sheeting was corrected. Diagram 5.2a, ding systems;
with the associated text in paragraph 5.14, was amended to BS 8414-2: 2015+A1: 2017 Fire Performance of external clad-
remove ‘with a thermoplastic core’. This aligned the text with ding systems.
ADB 2006 (as amended).

13.17 Part B3, Diagram 8.1, adds graphically a recommendation 13.29 New Appendix G: Documents referred to updates the
for cavity barriers at the bottom of cavity walls, not included in references to include:
ADB 2006, Diagram 33.
BRE report (BR 135) Fire performance of external thermal
13.18 Part B3 of ADB 2019, Volume 1, does not include the insulation for walls of multi-storey buildings 2013;
advice in ADB 2006, Volume 2, Section 11 regarding car parks,
although car parks are very often included in blocks of flats. DCLG Fire Performance of Green Roofs and Walls 2013.
The first UK fatality as the result of a car park fire occurred
in a block of sheltered flats over a semi-basement car park in ADB Volume 2: Buildings other than dwellings (2019)
Bristol in 2006. The recommendations for car parks are included
in ADB 2019, Volume 2, Section 11, substantially unchanged 13.30 The major changes in ADB 2019 principally consist
since 2006. of revisions to Part B4 External fire spread, and particu-
larly to Section 12: Resisting fire spread over external walls
13.19 Part B3, paragraph 7.4, recommends sprinklers for blocks (Section 10 in ADB 2019, Volume 1), consistent with the
of flats with a floor more than 30m above ground: the same Building (Amendment) Regulations 2018.
advice as in ADB 2006, paragraph 8.14.
13.31 Part B4 begins by reiterating Requirements B4 (1) and
13.20 The new Part B4 and Section 10 Resisting fire spread over (2) of Schedule 1 to the Building Regulations regarding exter-
external walls are substantively the same as the new Part B4 nal walls and roof respectively. Then Regulation 7, including
and Section 12 in Volume 2, which are reviewed under Volume new (2018) paragraphs 7(2), 7(3), and 7(4), is reproduced in
2 below. its entirety, confirming the ban on combustible materials in
the external walls of ‘relevant buildings’ with a storey 18m
13.21 Appendix A defines Key terms used in Building Regulations above ground level, other than for the stated exceptions. (See
and ADB. It has been brought forward (from Appendix E in ADB section 12 above for details.) In ‘relevant buildings’, Class A1
2006) and given greater prominence. The Building Regulations or A2-s1, d0 materials are obligatory.
(as amended 2018) definitions of ‘Dwelling’, ‘External wall’,
and ‘Specified attachment’ are included, as are new or simpli- 13.32 The reason for excluding hostels, hotels and boarding
fied definitions of ‘Fire alarm system’, ‘Fire damper’, ‘Fire and houses (places where people sleep and may be unfamiliar with
smoke damper’, and ‘Self-closing device’. ‘Concealed space or the building) from the list of ‘relevant buildings’, to which the
cavity’ in ADB 2006 becomes ‘cavity’, and ‘Fire door’ becomes ban on combustible cladding applies, is not stated. However, a
‘fire doorset’. ‘Thermoplastic material’ is brought in from the government consultation paper published in June 2018 stated
previous Appendix A in ADB 2006. that hotels have different evacuation strategies from residential
buildings and the risks are lower. Hotels are likely to have simul-
13.22 Definitions in ADB 2006 omitted in ADB 2019 include taneous or phased full evacuation strategies. Blocks of flats usu-
‘Class 0’, ‘Material of limited combustibility’, ‘Non-combustible ally have a ‘stay-put’ or ‘defend-in-place’ evacuation strategy,
material’, ‘Occupancy type’, and ‘Smoke alarm’. where the residents stay in their dwellings unless instructed to
leave by the fire service.
13.23 Appendix B, Performance of materials, products and
structures, (formerly Appendix A) is slimmer than its predeces- 13.33 Under ‘Intention’ on page 92, sub-paragraph b. includes
sor, principally because of the omission of sub-sections on ‘Non- specified attachments to external walls (i.e. balconies, brises
combustible materials’, ‘Materials of limited combustibility’, soleils, solar panels) in the recommendations to limit the rate of
and ‘Internal linings’, including ‘Class 0’. external fire spread.

13.24 Appendix B, paragraph B10 explains that ADB uses 13.34 In September 2019, the guidance in relation to double-
European ‘Reaction to fire’ classes as in BS EN 13501-1 (and skinned insulated roof sheeting was corrected. Diagram 8.2a,
no longer national classes). However, Table B1 sets out transpo- with the associated text in paragraph 8.28, was amended to
sitions of European classes to national classes, referring to BS remove ‘with a thermoplastic core’. This aligned the text with
476-7 and BS 476-11. ADB 2006 (as amended).

13.25 In Appendix B, the Tables regarding fire resistances are 13.35 New paragraph 12.3 accepts, other than for a tall residen-
numbered Tables B3 and B4. (formerly Tables A1 and A2 in tial or institutional ‘relevant building’ as described in Regulation
ADB 2006). 7(4), following the provisions of paragraphs 12.5 to 12.9 or
meeting the performance criteria given in the BRE Report Fire
13.26 There is a new Appendix E concerning sprinklers, in lieu performance of external thermal insulation for walls of mul-
of paragraphs 0.16–0.18 of ADB 2006. This begins by tabulat- tistorey buildings (BR 135) for external walls using full-scale
ing all the recommendations regarding sprinklers in ADB 2019. test data from BS 8414-1: 2015 or BS 8414-2: 2015 as means
Regarding the design of sprinkler systems, ADB 2019 refers to: of compliance with Building Regulations.
94 Construction legislation in England and Wales

13.36 New paragraph 12.4 recommends taking attachments to 13.48 The second note to paragraph 12.11 confirms that the
the external wall into consideration regarding the risk of external requirement in Regulation 7(2) is limited to materials achiev-
fire spread. ing either European classification Class A2-s1, d0, or Class
A1. Therefore, only materials achieving ‘limited combustibil-
13.37 New paragraph 12.5 refers to new Table 12.1 for recom- ity’ (to BS 476: Part 11: 1982) can not be deemed to meet the
mendations regarding the external surfaces of walls. Table 12.1 requirement.
recommends that the external wall surfaces of ‘relevant build-
ings’, regardless of the proximity of the boundary, should be 13.49 New paragraph 12.13 explains the exemptions in
constructed of materials having a reaction to fire performance Regulation 7(3) for certain components found in external walls
of A2-s1, d0, or better. Also, inconspicuous in an unnumbered and specified attachments.
note, there is the advice that buildings with a top occupied storey
above 18m should additionally meet the provisions of paragraph 13.50 New paragraph 12.14 explains that when a building
12.6. (see below). is altered to become a ‘relevant building’ (as described in
Regulation 7(4), then under Regulations 5(k) and 6(3)), the
13.38 Table 12.1 also recommends that external wall surfaces construction of the external walls and specified attachments must
of other buildings should be Class B-s3, d2 if either less than be investigated and, where necessary, work must be carried out
1m horizontally from the relevant boundary, or if over 18m to ensure that they only contain materials achieving European
high above ground level. The external parts of tall buildings Class A2-s1, d0, or Class A1.
from ground level to 18m high should be Class C-s3, d2 if
the building is more than 1m from the boundary. There are no 13.51 New paragraph 12.15 emphasises that provisions of
provisions for buildings both less than 18m high and more than Regulation 7 apply in addition to the Requirements of B4.
1m from the boundary. These recommendations of Table 12.1
do not differ from those of Diagram 40 in ADB 2006, save that 13.52 Sub-paragraph 12.16a states that, for a ‘relevant build-
references to national Class 0 and other national classifications ing’, membranes used as part of the external wall construction
are withdrawn. There is no graphic equivalent of Diagram 40 in should achieve a minimum classification of European Class
ADB 2019. B-s3, d0. There are already breather membranes and water-
proofing membranes on the market that meet (and better) this
13.39 New paragraph 12.6 recommends: requirement.

12.6 In a building with a storey 18m or more in height … any 13.53 There is no definition of the term ‘membranes’ and no
insulation product, filler material (such as the core materials guidance as to whether it includes vapour control layers (VCLs).
of metal composite panels, sandwich panels and window Achieving a VCL that meets the recommendation would be
spandrel panels but not including gaskets, sealants and simi- problematic, as VCLs are generally composed of polyethylene,
lar) etc. used in the construction of an external wall should be essentially the same material as the cores of the composite pan-
class A2-s3, d2 or better. els involved in the external cladding fires.

13.40 The scope of buildings in this recommendation is all 13.54 Sub-paragraph 12.16d confirms that window frames and
buildings with a storey 18m or more in height, not just ‘relevant glass (including laminated glass) are exempted from Regulation
buildings’. 7(2). However, for a ‘relevant building’, window spandrel panels
and infill panels must comply with Regulation 7(2).
13.41 Note the additional text (in bold) in comparison with ADB
2006, paragraph 12.7. There is no longer any ambiguity regard- 13.55 Sub-paragraph 12.16e states that there is no minimum
ing the cores of external cladding panels. They are included in performance for thermal break materials, but they should not
the recommendation. span two compartments, and they should be limited in size to the
minimum required to restrict the thermal bridging.
13.42 Class A2-s3, d2 is a direct equivalent of the old national
classification ‘limited combustibility’. Note that when a classifi- 13.56 Sub-paragraph 12.16f states that shop front signs and simi-
cation includes ‘s3, d2’, this means that there is no limit set for lar additions are not ‘specified attachments’ to which Regulation
smoke production and/or flaming droplets/particles. Only insu- 7(2) applies.
lation and cladding products meeting European Classifications
A2-s1, d0 (minimal smoke production and no flaming droplets) 13.57 Sub-paragraph 12.16g states that consideration should be
or A1 suffice for ‘relevant buildings’. given to other attachments to the external wall that could impact
on the risk of fire spread over the wall. There is no specific
13.43 New paragraph 12.7 refers to the DCLG publication ‘Fire recommendation.
Performance of Green Roofs and Walls’.
13.58 New Section 19: Fire safety information, replaces former
13.44 New paragraph 12.8 recommends that cavity barriers are Appendix G. It begins:
provided in accordance with Section 9.
19.1 For building work involving the erection or extension of
13.45 New paragraph 12.9 recommends, for masonry external a relevant building (i.e. a building to which the Regulatory
cavity walls, that the provisions of Table 12.1 apply to the Reform (Fire Safety) Order 2005 applies or will apply), or
surfaces that face into the external wall cavities. However, the the relevant change of use of a building, fire safety informa-
more onerous provisions of Building Regulation 7(2) prevail in tion should be given to the responsible person at one of the
the case of ‘relevant buildings’. following times.

13.46 New paragraphs 12.10 and 12.11 explain Building a. When the project is complete.
Regulations 7(1) and 7(2). b. When the building or extension is first occupied.

13.47 The first note to paragraph 12.11 explains that the institu- This introduces a definition of ‘relevant building’, i.e. ‘a
tional and residential buildings under the definition of ‘relevant building to which the Regulatory Reform (Fire Safety) Order
building’ include student accommodation, care homes, sheltered 2005 applies, or will apply after the completion of building
housing, hospitals, and dormitories in boarding schools. work’, which differs from that in Building Regulation 7(4).
Fire safety: guidance documents 95

13.59 There are two methods of measurement of height in ADB 13.69 Section 2 in ADB Volume 1, Part B1, provides guidance
2019 (as there were in ADB 2006). The height of the building on residential automatic fire suppression systems. At the begin-
is measured as shown in Appendix D, Diagram D4: the vertical ning of the Section, Building Regulations 37A and 37B are
difference between mean ground level and mean roof level. This reproduced.
is the height which applies to paragraph 12.5 and Table 12.1
regarding external surfaces of walls and cladding. 13.70 Section 2, paragraph 2.3 recommends that, where an auto-
matic fire suppression system is required, it should be designed
13.60 The height of the floor of the top storey above ground and installed in accordance with BS 9251: 2014 Sprinkler
is measured as shown in Appendix D, Diagram D6: the height systems for domestic and residential occupancies – Code of
of the building from the ground level on the lowest side of the practice or equivalent.
building to the finished floor level of the top storey. This is
the measurement of height applicable to new paragraph 12.6, 13.71 Section 2, paragraph 2.5 advises that there are many
which advises that the external wall insulation and cores of alternative or innovative fire suppression systems available, but
cladding panels in a building with a storey 18m or more above such systems should be designed and tested for use in domestic
ground level should be Class A2-s3, d2, or better. It is also the buildings and should be fit for their intended purpose.
threshold height of a ‘relevant building’, as defined in Building
Regulation 7(4), with its more demanding requirement of Class 13.72 Section 2, paragraph 2.8 advises that other, less common
A2-s1, d0, or Class A1 for materials of external walls and speci- arrangements for means of escape (for example, residences
fied attachments. entered above or below accommodation level, or residences
containing galleries or open plan layouts) are acceptable where
13.61 All, or nearly all, of the new recommendations in the automatic fire suppression is provided. Guidance on these less
2019 edition of ADB apply only to tall (>18m) residential common layouts is given in BS 9991: 2011 (Fire safety in the
or institutional ‘relevant buildings’ only. It begs the question design, management and use of residential buildings – Code of
whether the recommendations should extend to other building practice – revised in 2015) and NHBC / BRE Open Plan Flat
types and to less tall buildings. Layouts: Assessing life safety in the event of fire (2009).

13.73 Appendix E was amended in 2019 to define ‘External


Property Protection wall’ as in Regulation 2(6) of the Building (Amendment) (Wales)
13.62 Although primarily concerned with life safety, ADB Regulations 2019.
2019, paragraph 0.7 also makes reference to property protec-
tion, in addition to life safety, citing the RISC Authority Design 13.74 Appendix F provides guidance on the maintenance of
Guide for the fire protection of buildings by the Fire Protection residential automatic fire suppression systems.
Association (FPA).
13.75 The remaining guidance in ADB Volume 1 (Wales) is
13.63 In 2015, the RIBA, RISC Authority, and FPA published similar, but not identical, to that of ADB 2006, 2010 amendment,
a revised version of ADB (Volume 2) 2006 Buildings other before the advice in England and Wales diverged.
than Dwellinghouses, incorporating Insurers’ Requirements For
Property Protection.
ADB Volume 2 Buildings other
13.64 In addition to reproducing the text of ADB Volume 2, the than dwellinghouses in Wales
guidance is targeted at reducing property damage and minimis-
ing business interruption. It contains sections relating to com- 13.76 ADB Volume 2 in Wales was amended in 2010, 2013,
posite panels, fire safety engineering solutions, and advice on 2016, and 2019.
arson prevention.
13.73 The 2013 amendments to ADB Volume 2 in Wales
13.65 The 2015 edition adds additional guidance on buildings reflected the changes due to the introduction of Regulation 37A
with combustible structural elements, such as timber frame (Fire suppression systems) into the Building Regulations.
buildings, on modern methods of construction and on external Section 2: Automatic Fire Suppression Systems, paragraph 2.4
fire spread. There is advice on roof-mounted photovoltaic solar recommended that, where an automatic fire suppression system
panels and charging points for electric vehicles. A new Appendix is required, it should be designed and installed in accordance
J contains additional guidance on penetrations of external walls, with:
and on breather membranes, cavity trays, air bricks, and waste
water outlets: components where plastic materials have been a) for dwellings and residential buildings, BS 9251: 2005 Sprinkler
implicated in recent fire events. systems for domestic and residential occupancies – Code of
practice or equivalent technical standard.
b) for non-residential buildings, or dwellings and residential
Wales buildings outside the scope of the relevant technical stand-
13.66 In Wales (as previously in England), since 2006, ADB has ard, the requirements of BS EN 12845: 2009 or equivalent
been published in two volumes: Volume 1, Dwellinghouses; and technical standard.
Volume 2, Buildings other than dwellinghouses. The guidance
on flats remains in Volume 1. Section 2, paragraph 2.7a advised that, for the purposes of
meeting the requirements of Regulation 37A relating to resi-
13.67 The current edition of ADB Volume 1 in Wales is the dential buildings, the 20m height limit stated in BS 9251 may
2006 edition, incorporating 2010, 2016, and 2019 amendments. be disregarded.
The current edition of ADB Volume 2 in Wales is the 2006 edition, Section 2, paragraph 2.8 gave advice on water supplies for
incorporating 2010, 2013, 2016, and 2019 amendments. non-residential automatic fire suppression systems designed and
installed to BS EN 12845. (Water supply advice is in paragraph
0.18 of the General Introduction of ADB Volume 2 in England.)
ADB Volume 1 Dwellinghouses in Wales A new Appendix H provided guidance on the maintenance of
13.68 The 2016 amendments to ADB Volume 1 in Wales residential automatic fire suppression systems.
reflected changes due to the introduction of Regulation 37A (Fire Otherwise, Section 2 of ADB Volume 2, 2013, contained sim-
suppression systems) into the Building Regulations. ilar advice to Section 2 of ADB Volume 1, as described above.
96 Construction legislation in England and Wales

13.74 ADB Volume 2 in Wales was amended in 2016. Diagram 40, Provisions for external surfaces or walls, is
Section 2: Automatic Fire Suppression Systems, paragraph included, largely unchanged except for the title note: ‘where
2.4, updated the standard for fire sprinkler systems in domestic Regulation 7(2) applies, it prevails over the provisions in
and residential occupancies to BS 9251: 2014, but was otherwise this diagram’. Diagram 40 also retains reference to national
unchanged. Classification Class 0.
Section 3: Means of escape from flats in ADB Volume 2, Part There is a new footnote:
B1 was also amended in 2016.
The advice in paragraph 3.16 on approaches to planning a ‘3 Where a mixed-use building includes Assembly and Recreation
multi-storey flat was revised, and recommendations were added Purpose Group(s) accommodation, the external surfaces of walls
regarding extension of an existing un-sprinklered apartment should meet the provisions in Diagram 40c.’
building to include a storey more than 4.5m above ground level.
A note was added to paragraph 3.24 regarding building man- 13.79 Paragraphs 13.9–13.14, inclusive, are under the new head-
agement, and the possible addition of fire suppression system in ing ‘Regulation 7 – Materials and Workmanship’. The major
the common areas of flats if there were concerns related to fire change comes in Paragraph 13.10:
safety management.
Regulation 7(2) applies to any building with a storey at least
13.75 ADB Volume 2 in Wales was further amended in 2017. 18m above ground level (as measured in accordance with
Section 7: Wall and Ceiling linings, Table 10 Classification of Diagram C6) and which contains one or more dwellings; an
linings, has an additional Note 5, which accepts wall coverings institution; or a room for residential purposes (excluding any
which conform to BS EN 15102: 2007 Decorative wallcover- room in a hostel providing temporary accommodation to those
ings – roll and panel form products, which achieve at least Class who are ordinarily resident elsewhere, hotel or a boarding
C-s3, d2 and are bonded to a Class A2-s3, d2 substrate. house). It requires that all materials which become part of
Section 7: Table 11 Limitations applied to thermoplastic an external wall or specified attachment achieve European
rooflights and lighting diffusers in suspended ceilings and Class Class A2-s1, d0 or Class A1, other than those exempted by
3 plastic rooflights, accepts Euroclass D-s3, d2 as an equivalent Regulation 7(3).
of national Class 3. There is also new guidance on the minimum Note 1: The above includes student accommodation, care
separation distance between small diffuser panels or rooflights of homes, sheltered housing, hospitals and dormitories in board-
less than 1m2 area, and a new explanatory Diagram 27A. ing schools.
Note 2: The requirement in Regulation 7(2) is limited to
13.76 ADB Volume 2 in Wales was again amended in 2019. This materials achieving European classification Class A2-s1, d0
is the current version and has been in effect since 29 January or Class A1. Therefore materials achieving limited combus-
2020. tibility cannot be deemed to meet the requirement using an
alternative classification method.
13.77 After B4: The Requirement, the whole of amended (2019)
Regulation 7 is reproduced. 13.80 Other provisions in the amended guidance are consistent
Regulation 7(4)(a) describes ‘relevant building’ subtly dif- with ADB 2019 in England.
ferently from the Building (Amendment) (Wales) Regulations Appendix E is amended to define ‘External wall’ and
2019, as follows: ‘specified attachment’, as in Regulation 2(6) of the Building
(Amendment) (Wales) Regulations 2019.
a ‘relevant building’ means a building with a storey (not
including roof-top plant areas or any storey consisting
exclusively of plant rooms) at least 18 metres above 14 Fire safety: alternative design
ground level and which— guidance documents
(i) contains one or more dwellings;
(ii) contains an institution; or Alternative approaches
(iii) contains a room for residential purposes (excluding
14.01 There are other codes or guides that provide alternative ways
any room in a hostel providing temporary accom-
of achieving compliance with the requirements of the Building
modation to those who are ordinarily resident else-
Regulations, some of which are devised for specific building types.
where, hotel or boarding house);
This section summarises several that are relevant to fire safety.
13.78 There is a new re-written Section 13: Construction of
external walls. HTM 05 ‘Firecode’ documents
Paragraph 13.4 states that the BR 135 route to compli-
ance (based on BS 8414 testing) is not applicable to buildings 14.02 The Department of Health has prepared a set of guidance
described in Regulation 7(4), i.e. ‘relevant buildings’. documents on fire precautions in health care buildings, under
Paragraph 13.5 states that the external surfaces of walls the general title of ‘Firecode’, taking into account the particular
should meet the provisions in Diagram 40, but where Regulation characteristics of these buildings.
7(2) applies, that regulation prevails over the provisions in the
diagram. There is a cross-reference to paragraph 13.10. 14.03 Health Technical Memorandum (HTM) 05-02, Guidance
Paragraph 13.6, Insulation Materials/Products, is largely in support of functional provisions for healthcare premises (Fire
unchanged from previous advice, but notes that, where safety in the design of healthcare premises) (2015), should be
Regulation 7(2) applies, that regulation prevails over all the used for the design of new hospitals and similar health care prem-
provisions in this paragraph. Paragraph 13.6 has not been ampli- ises, and major new extensions to existing healthcare premises.
fied to explicitly include ‘… core materials of metal composite
panels, sandwich panels and window spandrel panels’, as in 14.04 The specialised nature of some health care premises
ADB 2019 in England. Instead, there is a new Note 1: demands a different approach to the provision of means of
escape, from much of that embodied by the guidance in ADB.
Whilst the guidance above applies to any insulation product, The concept of ‘progressive horizontal evacuation’ (PHE) is to
filler material (not including gaskets, sealants and similar) provide means of escape by evacuating patients horizontally
etc. used in the construction of an external wall, consideration into adjoining compartments, or sub-divisions of compartments.
should be given to the choice of material used for any other The object is to provide a place of relative safety within a short
parts of an external wall or attachments to the wall which distance, from which further evacuation can be made, if neces-
could impact on the risk of fire spread over the wall. sary, but under less time pressure.
Fire safety: alternative design guidance documents 97

Building Bulletin 100: Design for fire safety in schools (2007) ‘occupancy characteristic’ and the ‘fire growth rate’. The effect
of introducing sprinklers, or water mist, is always to lower the
14.05 Building Bulletin 100: Design for fire safety in schools fire growth rate by one integer. As the Risk Profile changes from
2007 (BB 100) provides fire safety design guidance for schools A1 (the lowest risk) to C3 (the highest acceptable risk), the rec-
in England and Wales. The guidance applies to nursery schools, ommended coverage and sophistication of the fire detection and
primary and secondary schools, including sixth form colleges, alarm system increases.
academies and city technology colleges, special schools, and
pupil referral units. 14.14 The risk-based approach of BS 9999 can permit signifi-
cant flexibility of design compared to the General (Approved
14.06 Arson is a particular problem for schools. According to Document B) approach.
government statistics for the years 2000–2005, 56% of school
fires were classified as ‘non-accidental’, with the majority of 14.15 The fire safety procedures described in BS 9999 require
these likely to have been arson. management throughout the life of the building. Staff should be
trained to handle incidents and operate effective and tested emer-
14.07 BB 100 addresses both the life safety needs and property gency plans. Under BS 9999, evacuation lifts that are designed,
protection, providing guidance on the design of school buildings specifically designated, and managed for the purpose, can be
to reduce arson and property loss through fire. used to evacuate people safely and effectively.
14.08 BB 100 acknowledges the important role of sprinklers. On 14.16 Advice on insulating core panels used in external clad-
1 March 2007, the government announced a policy on sprinklers ding (and internal structures) is given in Section 7: Designing
and their value as a measure against the risk of fire and arson. the building structure, sub-clause 34.3, Insulating core panels.
Sprinkler systems installed in buildings can significantly reduce It is clearly directed at the metal-faced polymeric foam-cored
the degree of damage caused by fire and can reduce the risk to life. composite panels common in the 1990s and early 2000s:
BS 9999 Fire safety in the design, management and use of When compared with other types of construction techniques,
buildings – Code of practice (2017) insulating core panel systems provide a unique combination
of problems for fire-fighters, which can include:
14.09 British Standards provide a useful source of information
that can be used to provide an alternative to the design guidance
given in ADB. BS 9999 is applicable to non-residential buildings • hidden fire spread within the panels;
of intermediate size and complexity. • production of large quantities of black toxic smoke;
• rapid fire spread leading to flashover.
14.10 In 2008, BS 9999 superseded nine earlier British Standards,
all parts of BS 5588, but not Part 1 – Residential buildings. (BS These three characteristics are common to both polyure-
5588-1 was subsequently replaced by BS 9991.) thane and polystyrene cored panels. The rate of fire spread
in polyisocyanurate cores is significantly less than that of
14.11 The Foreword of the current edition, BS 9999: standard polyurethane or polystyrene cores, especially when
2017 explains: any external heat source is removed.

The concept behind the development of BS 9999 and BS This text is closely based on Appendix F in ADB Volume 2
7974 is that technical guidance on fire safety is provided at (2006 as amended), save that where ADB advised that the rate of
three different levels. This permits a design approach to be fire spread in polyurethane cores is significantly less than that of
adopted that corresponds to the complexity of the building polystyrene cores, BS 9999 advised that the rate of fire spread in
and to the degree of flexibility required. The three levels are polyisocyanurate cores is significantly less than that of standard
as follows: polyurethane or polystyrene cores.
a) General approach. This level is applicable to a majority 14.17 Further advice on external fire spread is given in Clause
of building work undertaken within the UK. In this case 35, particularly sub-clause 35.5, External fire spread over the
the fire precautions designed into the building usually fol- external faces of buildings, but this is also closely based on ADB
low the guidance contained in the documents published Volume 2 (2006 and amendments).
by the relevant government departments to support legis-
lative requirements. BS 9991 Fire safety in the design, management, and use of
b) Advanced approach. This is the level for which BS residential buildings – Code of practice (2015)
9999 is provided.
The provisions of this document allow a more trans- 14.18 First published in 2011, BS 9991 is the equivalent guid-
parent and flexible approach to fire safety design through ance to BS 9999, but for residential buildings only.
use of a structured approach to risk-based design where
designers can take account of varying physical and 14.19 The Introduction of the current edition BS 9991:
human factors. Many of the measures recommended in 2015 explains:
BS 9999 are based on fire safety engineering princi-
ples, although it is not intended as a guide to fire safety The provisions for means of escape for flats or maisonettes
engineering. are based on the assumptions that:
c) Fire safety engineering. This is the level for which BS
7974 is provided. a) provided that the building is well managed and corridors/
This level provides an alternative approach to fire stairways are kept clear, fire is more likely to occur within
safety and can be the only practical way to achieve a the flat or maisonette than in the common parts (e.g. not
satisfactory standard of fire safety in some large and com- in a stairwell);
plex buildings, and in buildings containing different uses. b) there can be no reliance on external rescue (e.g. a portable
ladder);
14.12 BS 9999 is based on risk analysis and is derived from c) the flat or maisonette will have a high degree of compart-
performance-based fire engineering principles. mentation and therefore there will be a low probability
of fire spread beyond the flat or maisonette of origin, so
14.13 BS 9999 categorises the potential for fire risks to people, in most fires simultaneous evacuation of the building is
property, and businesses. The ‘Risk Profile’ is based on the unlikely to be necessary; and
98 Construction legislation in England and Wales

d) where fires do occur in the common parts of the building, b) allow the safety levels for alternative designs to be
the materials and construction used in such areas will compared;
prevent the fire from spreading beyond the immediate c) provide a basis for selection of appropriate fire protection
vicinity (although in some cases communal facilities exist systems;
which require additional measures to be taken). d) provide opportunities for innovative design; and
e) provide information and assessment methods to support
In purpose-built blocks of flats, special provisions are made the design, construction, management and operation of
to ensure that a fire is contained within the flat of origin and buildings.
that common escape routes and stairways remain relatively
free from smoke and heat in the event of a fire within a Fire is an extremely complex phenomenon and gaps exist
dwelling. For this reason, the general fire strategy is a stay in the available knowledge and technology. This British
put strategy. Standard is intended to provide a framework for a flexible
but formalized approach to fire safety design by which an
14.20 Advice on external fire spread is given in Clause 18, par- adequately fire safe building can be constructed while allow-
ticularly sub-clause 18.2, External fire spread over the external ing for the inevitable uncertainties in the development of a fire
faces of buildings. Generally, this is based on ADB Volume and the response of the building and occupants to it. It also
2 (2006 and amendments), but in a significant revision of the sets out a reporting methodology which allows for the design
advice, sub-clause 18.2 states: to be readily assessed by approvals bodies.

External walls should either meet the performance criteria 14.26 BS 7974 is a fire engineering standard and should be
given in BRE Report BR 135 … for cladding systems using applied by qualified fire engineers, rather than architects.
full scale test data from BS 8414-1 or BS 8414-2, or meet the
following recommendations.
a) The external surfaces of walls should meet the provisions
15 Fire safety: local legislation
in Figure 17. in Inner London
b) In a building with a storey 18 m or more above ground
level, any cladding material, insulation product, filler 15.01 The few remaining sections of the London Building Acts
material (not including gaskets, sealants and similar), etc., that are still in force are usually administered by the local build-
used in the external wall construction should be of limited ing control in the person of the chief officer acting as a District
combustibility. (emboldened for emphasis) … Surveyor. Regarding fire safety, the more important of these
c) Cavity barriers should be provided in accordance with remaining sections of the Act are summarised below.
Clause 19.
d) External balconies that are enclosed should be constructed Fire safety – precautions against fre
and separated from other enclosed balconies with com-
partmentation and fire-resisting construction in accord- 15.02 Sections 20 and 21 were previously residual parts of the
ance with Annex D. London Building Acts (Amendment) Act 1939. Section 20 dealt
with precautions against fire in buildings of excess height or
14.21 The recommendation for any cladding material to be of cube (i.e. volume), and Section 21 with the uniting of buildings.
limited combustibility was additional to the advice in paragraph Sections 20 and 21 were repealed by the Building (Repeal of
12.7 of ADB Volume 2 (2006 and amendments). Provisions of Local Acts) Regulations 2012, with effect from
9 January 2013.
14.22 The recommendations concerning enclosed balconies
were new and were not included in ADB Volume 2 (2006 and Temporary buildings
amendments).
15.03 Section 30 of the London Building Acts (Amendment)
BS 7974 Application of fire safety engineering principles to the Act 1939 applies to consents for the erection or retention of
design of buildings – Code of practice (2019) temporary buildings and structures that are not covered by the
Building Regulations 2010. Examples include marquees, flag
14.23 First published in 2001, a revision of the standard came poles, flue pipes, and free-standing boundary walls greater than
into effect on 31 March 2019. 1.83 metres (6 feet) high. Section 30(3) states that temporary
buildings must not be used for the storage of inflammable
14.24 BS 7974 is intended to provide a framework for the materials or for the purpose of human habitation. Hoardings
application of fire safety engineering principles to the design over seven feet in height are dealt with in Section 30(5), and
of buildings. any such structure which is in place for three years or more
requires the approval of the district surveyor as to its structural
14.25 The Introduction to BS 7974 states: stability.

For most buildings, the recommendations in existing design


codes such as BS 9991 and BS 9999 are generally adequate.
Fire safety – means of escape
Where they are not, this British Standard can be used for 15.04 Part V/Section 34 were repealed by the Regulatory Reform
developing and assessing fire safety engineered proposals. (Fire Safety) Order 2005 (RRFSO): see section 17 below. Means
A fire safety engineering (FSE) approach that takes into of escape are now all dealt with by Part B1 of Schedule 1 to the
account the total fire risk management package specific to the Building Regulations.
building can often provide a more fundamental and economi-
cal solution than design codes. It might in some cases be the
only viable means of achieving a satisfactory standard of fire 16 Fire safety: local legislation
safety in some large and complex buildings.
FSE can have many benefits. The use of this British
outside Inner London
Standard is intended to facilitate the practice of FSE and, in
16.01 Although the Building Act 1984 and Building Regulations
particular, to:
made under it were intended to provide a national code of build-
a) provide the designer with a disciplined approach to fire ing control, there were many provisions in local Acts which
safety design; imposed additional controls on the construction of buildings.
Fire safety: other national legislation 99

16.02 The Regulatory Reform (Fire Safety) Order 2005 (RRFSO) ● the Health and Safety Executive for nuclear installa-
repealed many sections of these local Acts that dealt with fire tions, ships and construction sites;
safety. ● the Ministry of Defence fire service for premises occu-
pied by armed forces;
16.03 The Building (Repeal of Provisions of Local Acts) ● the Local Authority for sports grounds and grandstands;
Regulations 2012 repealed remaining provisions of local Acts ● Her Majesty’s Inspectorate for Crown Premises.
concerning safety requirements in underground and multi-
storey parking places, and/or fire precautions in high buildings 17.06 Article 27(1) of the RRFSO permits the inspector to do
and large storage buildings in Merseyside, West Midlands, anything necessary for the purpose of carrying out the RRFSO.
Cheshire, Isle of Wight, South Yorkshire, Greater Manchester, Articles 29, 30, and 31 provide for Alterations, Enforcement,
Kent, Derbyshire, Humberside, Avon, Cumbria, Hampshire, and Prohibition Notices. These Notices are graduated in severity,
Staffordshire, Lancashire, Surrey, Bournemouth, Leicestershire, in that each of these notices is stiffer than the preceding notice.
Hereford, Worcester, Poole, Berkshire, and Cleveland. The Alterations Notice requires the specified risk to be
reduced or eliminated, but the Responsible Person can make a
16.04 Where an Approved Inspector is responsible for com- proposal of their own liking. There appears to be no provision
pliance with the building regulations, the Building (Approved for a time limit on the remedial works.
Inspectors etc.) Regulations 2010 require him/her to consult the The Enforcement Notice has a deadline (not less than 28
Fire Authority where a local Act requires. days’ notice) and may include directions as to the measures
considered necessary to remedy the failure.
The Prohibition Notice prohibits or restricts the use of the
17 Fire safety: other premises until the specified matters have been remedied. It may
national legislation also include direction as to the measures which will have to be
taken to remedy the matters specified.
The Regulatory Reform (Fire Article 32 relates to Offences and Penalties, Articles 33 and
34 relate to Defence, and Article 35 relates to Appeals.
Safety) Order 2005 (RRFSO)
17.01 The RRFSO repealed or revoked much other legisla- 17.07 The RRFSO was modified in 2018 to make a fire inspec-
tion concerning fire safety, including the whole of the Fire tor, or any person authorised by the Secretary of State, the
Precautions Act 1971, the Smoke Detectors Act 1991, the enforcing authority for prisons and certain other custodial
Fire Certificate (Special Premises) Regulations 1976, the premises, irrespective of whether they are owned or occupied
Fire Precautions (Workplace) Regulations 1997, and the Fire by the Crown.
Precautions (Workplace) (Amendment) Regulations 1999. The
RRFSO also repealed parts of the Building Act 1984, the London
Building Acts (Amendment) Act 1939, the Health and Safety
Fire Safety Risk Assessment guides
at Work etc. Act 1974, the Safety of Sports Grounds Act 1975, 17.08 To assist the Responsible Person to carry out a fire risk
the Fire Safety and Safety of Places of Sport Act 1987, and the assessment, in 2006 and 2007, HM Government (DCLG) pub-
Management of Health and Safety at Work Regulations 1999. lished a series of 12 Fire Safety Risk Assessment guides for
various different building types and functions:
17.02 The RRFSO reformed the law relating to fire safety in Offices and shops; Factories and warehouses; Sleeping
non-domestic premises. The RRFSO replaced fire certification accommodation; Residential care premises; Educational prem-
under the Fire Precautions Act 1971 with a general duty to ises; Small and medium places of assembly; Large places of
ensure, so far as is reasonably practicable, the safety of employ- assembly; Theatres, cinemas and similar premises; Open air
ees; a general duty, in relation to non-employees, to take such events and venues; Healthcare premises; Animal premises and
fire precautions as may reasonably be required in the circum- stables; Transport premises and facilities.
stances to ensure that premises are safe; and a duty to carry out
risk assessments. 17.09 The guides are intended for all employers, managers,
occupiers and owners of the premises.
17.03 The person who must carry out the Fire Risk Assessment
is the ‘Responsible Person’, defined in Article 3 of the RRFSO. 17.10 The guides provide recommendations and guidance for use
The Responsible Person will be one of the following: an when assessing the adequacy of fire precautions in existing, less
employer, if he controls the workplace; an occupier; an owner; complex premises, rather than new premises. There is advice on
any others that have a contract that gives them control over fire compliance with fire safety law, carrying out a fire risk assess-
safety measures, e.g. installer/maintainer of fire alarms. There ment, and the general fire precautions that should be in place.
may be more than one Responsible Person, and they are obliged
to cooperate with each other. Housing – Fire Safety: Guidance on fire safety provisions for
certain types of existing housing (2008)
17.04 The Risk Assessment must take account of all the risks to
which building occupants and persons in the immediate vicin- 17.11 The Housing Act 2004 brought in a new system of regula-
ity of the premises may be exposed. The Risk Assessment must tion for fire safety in existing residential premises. In July 2008,
be recorded and reviewed on a regular basis to keep it up to Housing – Fire Safety: Guidance on fire safety provisions for
date. Article 18 of the RRFSO requires the Responsible Person certain types of existing housing was published by the Local
to appoint one or more ‘Competent Persons’ to assist him in Authorities Coordinators of Regulatory Services (LACoRS).
undertaking the fire prevention and fire protection measures, The document contains guidance for landlords and fire safety
unless he or an employee has sufficient training and experience enforcement officers.
or knowledge.
17.12 The guidance on fire safety in residential accommodation
17.05 The RRFSO provides for the enforcement of the Order, includes single household occupancy buildings, but also shared
for appeals, offences, and connected matters. houses, bedsit-type houses in multiple occupation (HMOs),
The enforcing authorities are – buildings converted into self-contained flats, flats in multiple
occupation and back-to-back houses. The LACoRS guide was
● the local Fire and Rescue authority for all except for the not intended to address purpose-built blocks of flats. (A clarifica-
following specific cases: tion note on the guidance was issued in March 2009.)
100 Construction legislation in England and Wales

Fire safety in purpose built blocks of flats (2011) 17.18 Immediately after the Grenfell Tower fire, the government
instigated a nationwide audit of the cladding panels of existing
17.13 Fire safety in purpose built blocks of flats was first pub- high-rise housing blocks, to ensure that any similar risks were
lished by the Local Government Group in July 2011. The docu- identified. On 18 June 2017, the DCLG wrote to local authority
ment is a guide to ensuring adequate fire safety in purpose-built and housing association landlords, asking them to:
blocks of flats, regardless of age.
● identify all their residential tower blocks over 18 metres in
17.14 Part C concerns the law governing fire safety in blocks of height;
flats. Paragraph 25.1 explains that: ● identify those with aluminium external cladding and whether
the panels were made of Aluminium Composite Material
When a block of flats is designed and constructed, Building (ACM), so they could be submitted for testing;
Regulations make requirements in respect of various fire ● provide more information about their tower blocks; and
safety measures. However, there is no ongoing control for the ● check they had robust fire assessments for their stock, with
maintenance of these measures under Building Regulations; attention to the Local Government Association’s guidance,
the regulations have no further effect until there are propos- ‘Fire Safety in purpose-built blocks of flats’.
als for alterations. After the block is occupied, control of
fire safety is transferred to the Housing Act 2004 and the 17.19 Over the following two years, there followed a series of
Regulatory Reform (Fire Safety) Order 2005. 22 Advice Notes addressed to landlords, owners and residents
of high-rise residential buildings. Advice Note 1 was issued
17.15 The key points of Part C are: on 30 June 2017, and Advice Note 22 was issued on 18 July
2019. These Advice Notes have now all been superseded and
● Material alterations to existing blocks of flats, including the advice consolidated in the MHCLG ‘Advice for Building
alterations to individual flats, are controlled under the Owners of Multi-storey, Multi-occupied Residential Buildings’
Building Regulations 2010, and need to be approved by a (Jan 2020).
building control body, otherwise an offence is committed.
● All residents of flats need to be made aware of the importance 17.20 The first 12 Advice Notes concerned the testing of ACM
of maintaining in place the fire safety measures required by cladding panels, then of entire external wall cladding systems.
legislation at the time of construction of the block. Alterations Annex A to Advice Note 1 explained the screening test and the
by residents within their own flats may not only put those resulting placement of the core material of the ACM cladding
residents at risk, but also other residents in the block. in one of three categories related to the three types of ACM
● Even if the block satisfied earlier legislation, proposed panel available:
alterations must be considered in the light of the current
Building Regulations; it is not sufficient to carry out altera- ● Category 1 means that the result met the definition of ‘mate-
tions on the basis of the earlier legislation. rials of limited combustibility’.
● Under the Housing Act 2004, the housing authority must ● Category 2 means that the result did not achieve the defini-
inspect properties if they become aware of significant fire tion of Category 1, but did have some limited flame retardant
hazards. Housing authorities have powers of entry for this properties.
purpose. ● Category 3 means that the result did not achieve the defini-
● The housing authority may make requirements for improve- tion of ‘materials of limited combustibility’, nor have flame
ments in fire precautions. In the event of serious risk, the retardant properties. Commonly, the core in this category
housing authority has the power to take emergency remedial comprised polyethylene (PE) without the addition of flame
action. retardant. (This was the type of ACM panel at Grenfell
● The RRFSO applies to all parts of a block of flats, other than Tower.)
within the individual flats.
● The RRFSO imposes duties on persons who may include 17.21 Examples of each of the three categories of ACM
freeholders, landlords, managing agents, and contractors cladding were subjected to large-scale testing based on BS
who maintain fire safety measures, and those who carry out 8414, in combination with one of two types of insulation: (a)
fire risk assessments. combustible polyisocyanurate foam (PIR) and (b) non-com-
● All fire safety measures must be adequately maintained. bustible stone wool insulation, to reproduce generic external
● An offence is committed if inadequate fire safety measures wall rainscreen cladding systems with cavities behind the
place people at risk of death or serious injury in case of fire. cladding and cavity barriers to inhibit the spread of fire within
the cavities. A seventh test was added with the commonly
17.16 The guide comments on an overlap of legislation between used combination of Category 2 ACM panels with phenolic
the Housing Act 2004 and the RRFSO 2005: foam insulation.
29.1 It is obvious … that there is overlap between the 17.22 The results of the tests are reproduced after paragraph
Housing Act and the (RR)FSO. The Housing Act applies to 4.11 of MHCLG ‘Advice for Building Owners of Multi-storey,
the common parts and the flats themselves, while the common Multi-occupied Residential Buildings’ (Jan 2020):
parts also fall within the scope of the (RR)FSO. A further
complexity is that the safety of the common parts from fire
can sometimes rely on fire safety measures within the flats, Aluminium Composite Insulation
into which there is no power of entry by the fire and rescue Material (ACM) with …
authority, or power to make requirements under the (RR)FSO. PIR Foam Phenolic Foam Stone Wool
However, there is such a power under the Housing Act.
Unmodified polyethylene Test 1 failed n/a Test 2 failed
filler*
17.17 An amendment was published by the Local Government
(Cat 3 in screening tests)
Association in May 2012. This deleted incorrect advice concern- Fire retardant polyethylene Test 3 failed Test 7 failed Test 4 passed
ing fire-resistant flat entrance doors in existing single stairway filler*
blocks with corridor or lobby access. (Cat 2 in screening tests)
Limited combustibility Test 5 passed n/a Test 6 passed
Government building safety programme and advice notes filler*
(Cat 1 in screening tests)
Aluminium Composite Material (ACM) cladding panels
Fire safety: other national legislation 101

17.23 *The MHCLG referred to the core of the ACM panels as panels with stone wool insulation, the equivalent of ACM Test
‘filler’, linking to the advice of ADB 2006, paragraph 12.7: ‘In 4. In the test, this external wall system achieved the perfor-
a building with a storey 18m or more above ground level any mance criteria in BR 135, so complying with paragraph 12.3
insulation product, filler material (not including gaskets, sealants of ADB 2019.
and similar) etc. used in the external wall construction should be
of limited combustibility.’ 17.30 Then, on 15 November 2019, a fire in a block of student
flats in Bolton, converted from offices, spread over the HPL
17.24 The government’s Expert Panel’s advice was summarised cladding, completely destroying the sixth (top) floor of the
(in January 2020) as follows: block. The building had seven storeys, but was reportedly just
under 18m high to the floor level of the top storey. However,
1.21.1. ACM cladding (and other metal composite material if this is the case, on the top storey over 18m above the lowest
cladding) with unmodified polyethylene filler (category 3 in adjacent ground level, it should have had cladding of Class B-s3,
screening tests) presents a significant fire hazard on resi- d2 external surface classification, and below 18m, the cladding
dential buildings at any height with any form of insulation should have been Class C-s3, d2, in order to comply with para-
and action to remediate unsafe wall systems and remove graph 12.6 and Diagram 40 of ADB 2006.
unsafe cladding should be taken as soon as possible. …
1.21.2. ACM cladding (and other metal composite material 17.31 The government’s Expert Panel’s advice was summarised
cladding) with fire retardant polyethylene filler (category (January 2020) as follows:
2 in screening tests) when used with rigid polymeric
foam insulation presents a notable fire hazard on residen- 1.21.3. High Pressure Laminate (HPL) systems using Class
tial buildings over 18m or buildings at any height with C-s3, d2 or D-s3, d2 HPL panels on residential buildings
residents who need significant assistance to evacuate of 18m or more to the height of the top occupied storey
(particularly where horizontal, phased evacuation is in or buildings at any height with residents who need signifi-
place) based on the evidence currently available. Action cant assistance to evacuate (particularly where horizontal,
to remediate these unsafe wall systems should be taken phased evacuation is in place) would not meet the func-
as soon as possible. tional requirements of the Building Regulations, and that
these systems should be remediated. …
17.25 Note that the advice reproduced above regarding Category 1.21.4. Building owners with HPL systems of any class used
3 ACM cladding applies to residential buildings at any height, with combustible insulation on residential buildings of
and the advice regarding Category 2 ACM cladding applies 18m or more to the height of the top occupied storey or
additionally to buildings at any height with residents who need buildings at any height with residents who need signifi-
significant assistance to evacuate, particularly where progressive cant assistance to evacuate (particularly where horizontal,
horizontal evacuation is the strategy, i.e. hospitals. MHCLG phased evacuation is in place) should seek professional
‘Advice for Building Owners’, paragraph 1.5 concludes: ‘The advice and take appropriate remedial action.
need to assess and manage the risk of external fire spread applies
to buildings of any height.’ 17.32 The advice of sub-paragraph 1.21.3 is more demanding
from the recommendations of ADB 2019, Table 12.1, which (like
17.26 The 2018 amendment to the Building Regulations and its predecessor ADB 2006) accepts class C-s3, d2 external wall
revised advice in ADB 2019 apply only to new residential ‘rel- surfaces from ground level to 18m high for tall buildings (other
evant buildings’ over 18 metres tall to top floor level, or where than ‘relevant buildings’) 1m or more from the site boundary
building work is carried out on existing buildings of 18 metres and has no recommendation for buildings less than 18m high
or more tall that make them ‘relevant buildings’. Post-Grenfell, and more than 1m from the boundary.
there were widespread concerns about fire safety in less tall
buildings. Subsequent residential fires in 2019 included a balcony
fire in Barking, a timber-frame fire in Crewe, a timber-frame and
Balconies
timber-cladding fire in Worcester Park and an HPL cladding fire 17.33 On 9 June 2019, a severe fire, believed to have been
in Bolton. None of these buildings was over 18 metres tall to top started by a barbeque, rapidly consumed the timber-clad balco-
floor level, so the new legislation did not apply. nies of a block of flats in Barking, destroying 20 flats and dam-
aging 10 others. Fortunately, the walls of the flats themselves
17.27 The other ten Advice Notes, 13–22, dealt with concerns were of brick and block, so no one within was injured.
arising directly or indirectly from the Grenfell Tower fire and
from the other serious, but non-fatal, fires occurring post-Gren- 17.34 The flats were 5 storeys high over a semi-basement car
fell: external wall insulation (EWI) systems; non-ACM cladding park, but the top floor was well below 18m above ground level,
panels; flat entrance doors; partial cladding; spandrel panels; so the ADB guidance for tall buildings did not apply.
smoke control systems; balconies; and high pressure laminate
(HPL) cladding panels. These subjects are all incorporated in 17.35 The balconies had a steel structure, but their floors and
MHCLG ‘Advice for Building Owners of Multi-storey, Multi- balustrades were constructed in timber, and it was a heat-treated
occupied Residential Buildings’ (Jan 2020). timber only achieving Class D to BS EN 13501. Untreated tim-
ber is generally acceptable from ground level to 18m high for
High Pressure Laminate the external wall surfaces of all buildings other than ‘relevant
buildings’ under ADB 2019, Table 12.1. With fire protective
(HPL) Cladding Panels treatments, timber can achieve Class B, which is acceptable at
17.28 HPL panels are manufactured from wood or paper any height for external wall surfaces of all buildings other than
fibre, layered with resin, and bonded under heat and pressure. ‘relevant buildings’.
Standard HPL cladding typically has a Class D reaction to fire
performance. HPL panels with fire retardant chemicals added 17.36 There was no prescriptive recommendation for balcony
are sometimes referred to as ‘FR grade’ and typically achieve materials in ADB 2006 when the building was designed, and
Class B-s1, d0. there is none in ADB 2019 other than for ‘relevant buildings’.
The structure and cladding of balconies of an 18m tall ‘relevant
17.29 BRE, on behalf of government, conducted a large-scale building’ have to comply with Building Regulation 7(2), i.e. be
BS 8414 test in July 2019 with FR grade HPL Class B-s1, d0 classified as A1 or A2-s1, d0.
102 Construction legislation in England and Wales

17.37 The advice in MHCLG ‘Advice for Building Owners of Following sub-paragraphs (2) to (7) then set out further require-
Multi-storey, Multi-occupied Residential Buildings’ (Jan 2020) ments and precautions pursuant to the above.
includes:
7.1. External walls of buildings, of any height, should not HSG 168 Fire safety in
assist the spread of fire, in accordance with the func- construction (2010)
tional Requirement B4 of Schedule 1 to the Building
Regulations. Balconies made with combustible materials 18.04 This guide is published by HSE and can be obtained as a
are a potential source of rapid fire spread on the external free download from the HSE website. It refers explicitly to the
wall of residential buildings. … superseded 2007 CDM Regulations, but remains relevant and
7.3. The view of the Expert Panel is that the removal and helpful in respect of the current 2015 CDM Regulations.
replacement of any combustible material used in balcony
construction is the clearest way to prevent external fire 18.05 In addition to the CDM Regulations, the RRFSO
spread from balconies and therefore to meet the intention 2005 applies. General fire precautions are required, as for exist-
of building regulation requirements and this should occur ing completed buildings.
as soon as practical.
18.06 Paragraph 332 states:
17.38 The advice is applicable to all buildings, irrespective of
the height of the building. 332 Under CDM, there is a requirement for every contractor
carrying out construction work and any person who controls
17.39 Earlier fires in Dubai and France have involved fire spread the manner in which this is carried out, to ensure suitable and
from balcony to balcony. Experience from the Middle East and sufficient steps to ensure the risk of injury from fire or explo-
UK indicates that balcony fires are often due to barbeques or sion that might arise from such work is prevented or reduced,
smoking. ‘Advice for Building Owners’ gives guidance on the so far as is reasonably practicable. Such steps to be taken
management of residents’ use of balconies: include the provision of adequate GFP (general fire precau-
tions) … measures to enable persons on the construction site
7.9. The fire risk on balconies can also be increased due to the to safely and promptly escape from a fire or explosion and
use of balconies as storage. A significant number of balcony reach a place of safety.
fires start from the unsafe disposal of smoking materials and
the misuse of barbeques. Building owners may have existing 18.07 Appendix 3 is a ‘Summary of basic precautions for all
policies in place as to what can and cannot be stored and used sites and additional precautions for higher risk sites’.
on balconies by residents and may wish to review these in the There is advice for all construction and additional recom-
light of the materials used in the balcony construction. They mendations for high risk, such as timber frame buildings.
may also wish to communicate with residents to develop their Considerations comprise:
understanding of these risks. Planning; Reduce amount of combustible material; Storage;
Rubbish disposal and housekeeping; LPG, acetylene or other
17.40 Balconies have a variety of configurations. They can be fuel types; Hot works; Ignition sources (smoking, plant and
completely open, or partially or fully enclosed (‘winter garden’). equipment, electrical, security/arson, site fires); Temporary
They can be cantilevered or free-standing, self-supported. They accommodation; General fire precautions; Means of escape; Fire
can be projecting or recessed. The behaviour of fires on balco- alarms; Fire-fighting equipment; Compartmentation/ stopping
nies is not yet fully understood, and further guidance will be (fire) spread; and Emergency procedures.
forthcoming: a British Standard is in preparation.

Fire Prevention on Construction


18 Fire safety on construction sites Sites (9th edition, 2015)
18.08 The ‘Joint Fire Code’, or more fully, Fire Prevention on
Construction (Design and Construction Sites: the Joint Code of Practice on the Protection
Management) Regulations (2015) from Fire of Construction Sites and Buildings Undergoing
Renovation, is published by Construction Industry Publications
18.01 See paragraph 8.12 above for a general outline of this leg-
Limited and the Fire Protection Association, with the support
islation and what has changed in relation to its 2007 predecessor.
of the Association of British Insurers, the Chief Fire Officers
The following current CDM regulations are of particular rel-
Association, London Fire Brigade, and the Contractors Legal
evance to fire safety.
Group, and is amended from time to time. There is also a check-
list version, designed to enable the user to establish if adequate
18.02 CDM Regulation 29 requires:
and comprehensive fire precautions are in place, using a tick
box-based form.
Prevention of risk from fire, flooding or asphyxiation
29. Suitable and sufficient steps must be taken to prevent, 18.09 The Joint Fire Code is principally directed at construction
so far as is reasonably practicable, the risk of injury to a site staff during the construction phase, but also to designers and
person during the carrying out of construction work arising specifiers in the design and procurement phases.
from—
(a) fire or explosion. 18.10 Compliance with the Joint Fire Code is frequently a con-
tractual obligation under JCT contracts.
18.03 CDM Regulation 30 covers Emergency Procedures;
Regulation 31 covers Emergency Routes and Exits. This is fol- 18.11 On larger projects, insurers will normally require compli-
lowed by: ance with at least the standards set out in Fire prevention on
construction sites – Joint Code of Practice.
Fire detection and fire-fighting
32.(1) Where necessary in the interests of the health or safety 18.12 Contents of the Joint Fire Code comprise:
of a person on a construction site, suitable and sufficient fire-
fighting equipment and fire detection and alarm systems must Design phase; Construction phase; Liaison with the emergency
be provided and located in suitable places. services; Emergency procedures; Fire protection; Temporary
Fire safety on construction sites 103

covering materials; Portable fire extinguishers; Site security Colindale fire, 2006
against arson; Temporary buildings; Site storage of Flammable
liquids and LPG; Acetylene; Hot work; Electricity and gas; 18.22 On 12 July 2006, there was a serious fire at a timber
Waste materials; Plant and vehicles; Stored materials; Smoking; framed development under construction in Colindale, London
High-rise construction sites; and Large timber frame structures. NW9. Plasterboard had not yet been installed over the timber
frame.
18.13 The Joint Fire Code is aligned with HSG 168 Fire Safety
in Construction Work. 18.23 The six-storey timber frame residential block was fully
alight about ten minutes after ignition. The Fire Brigade reported
18.14 Section 9, Fire protection, recommends early installation full structural collapse within 20 minutes, shortly after the
and completion of fire protection measures such as escape stairs, Brigade arrived on site. The first crews reported radiated heat
compartmentation, fire doors, fire-stopping, fire protection to to be so intense that it was not possible for them to approach
steelwork, firefighting shafts, lightning conductors, automatic nearer than 50m to the burning building.
fire detection systems, and sprinkler installations.
18.24 The huge exposed fire load, the high surface area of
18.15 Section 23, Large timber frame structures, addresses timber, and the virtually unrestricted airflow contributed to the
the fire risks to and from the timber frame under construction, inferno. Flames leapt 19m horizontally to set fire to a similar
requiring 20m of separation between the timber frame and tem- block which was approaching completion. This block had a
porary buildings and fuel stores. rendered finish, but the radiant heat from the burning timber
frame set it alight. The fire also set fire to the roof of a more
distant, traditionally built hall of residence building belonging
Separation distances to Middlesex University.
BR 187 External fire spread: building separation and bound-
ary distances (2nd edition, 2014) Peckham fire, 2009

18.16 First published in 1991 and revised in 2014, BR 187 is 18.25 On 27 November 2009, at 0430 GMT a fire broke out
cited in ADB Volume 2. at a timber framed construction site at Carisbrooke Gardens in
Peckham. At the height of the blaze, there were 30 fire engines
18.17 BR 187 is concerned with the possibility that fire might and over 150 fire fighters tackling the fire. The whole of the
spread from a burning building to adjacent buildings. site was on fire, and the fire also affected two nearby blocks of
maisonettes and a pub.
18.18 The Introduction to BR 187 explains:
18.26 There were five such fires in timber frame buildings under
Most accidental fires start as small fires which initially present construction in London in the same number of years.
a very small hazard to adjacent buildings. However, as a fire
grows, windows in the burning building will break and other 18.27 The DCLG Analysis of fires in buildings of timber framed
openings in the external envelope may develop; this provides construction, England, 2009–10 to 2011–12 found that:
the potential for fire to spread to adjacent buildings by con-
tact with flames and hot gases from the openings, thermal Fires in timber framed dwellings under construction had on
radiation or by burning brands (burning debris from the fire) average larger areas of damage compared to dwellings of no
drifting in the wind. special construction. Out of total fires in timber framed dwell-
… Burning debris from a fire at high level in a tall build- ings under construction, 24% of these resulted in damage of
ing also has the potential to spread fire to lower parts of the an area of more than 100 m2 compared to 4% for dwellings
building if the material falls onto balconies or is blown into a of no special construction.
room through open windows. Burning debris may also ignite
items such as vehicles at ground level. The main concern here
is that a brand could provide a pilot ignition source for materi-
Design guide to separating distances
als on an adjacent building that has been heated by thermal during construction. For timber frame
radiation from the fire. buildings. (Version 3.3, 2017)
If a fire is allowed to develop, as windows in the com-
partment break, more air can enter the compartment allow- 18.28 This Design guide was first published by the UK Timber
ing the fire to grow until it is limited either by the amount Frame Association in 2011. UKTFA prepared guidance on fire
of fuel, availability of air or the extent of the compartment. risk assessments to determine the impact of a timber frame
Thermal radiation from the external openings in the burning construction site fire on neighbouring buildings. The Guide was
compartment, and from flames leaving the compartment, will revised by the Structural Timber Association in 2017.
then heat surfaces on adjacent buildings. This has the poten-
tial, especially if burning brands are present, to ignite the 18.29 The Design guide is intended primarily to be used during
surface(s) of an adjacent building. If left unchecked the fire the design phase of construction projects and forms the basis
could then propagate from building to building and develop for establishing the site fire risk assessment plan. It introduces
into a large urban fire. separating distance tables, with worked examples, technical
background, and risk mitigation advice.
18.19 While the risk of fire spread between buildings cannot be
eliminated completely, the aim of calculating building separation 18.30 If the radiant heat falling on the receiving building would
distances is to ensure that ignition of a building adjacent to a fire cause ignition, the Design guide suggests mitigation methods,
is sufficiently delayed to allow the Fire Service to arrive on site including:
and take preventative action.
a. Adopt a more fire resistant timber frame specification;
18.20 BR 187 describes a number of methods for calculating b. Changing the emitter footprint and / or orientation to avoid
building separation distances. risk mitigation requirements;
c. The use of build process to construct the final and perma-
18.21 BR 187 was directed initially at fires in completed build- nent building outer cladding;
ings, but could equally apply to incomplete buildings. d. Adopt non combustible podium structures to reduce the
timber frame height.
104 Construction legislation in England and Wales

18.31 Early completion of internal compartmentation can also 19 Future legislation


reduce the ‘emitter length’ and hence, the radiant heat impinging
on the neighbouring building(s). 19.01 The government has asked HSE to establish a new build-
16 Steps to fire safety: Promoting good practice on construc- ing safety regulator in the wake of the Grenfell Tower disaster
tion sites (Version 4.3, October 2017) and following recommendations in the ‘Building a Safer Future’
report by Dame Judith Hackitt.
18.32 This good practice guide was first published by the UK
Timber Frame Association in 2008. The Guide was revised by 19.02 Major new fire safety legislation, including a Building
the Structural Timber Association in 2017. Safety Act and a Fire Safety Act, is anticipated imminently.

18.33 The Foreword explains that because, during the construc- 19.03 This may include reduction of the critical 18m building
tion phase, timber frame and structural timber buildings are more height threshold down to 11m and also mandatory requirements
vulnerable, it is therefore critical that suitable and proportionate for sprinklers in buildings less than 30m tall.
steps are taken to manage the risk from fire, and that these are
planned during the design and pre-construction phase, and then
19.04 Architects should be alert for impending changes to the
implemented fully during the construction process.
regulatory regime, and in particular, take note of any future
18.34 The 16 steps are broadly similar to issues raised in HSG publications by HSE and/or MHCLG.
168 and the Joint Fire Code.
19.05 Architects should take note of the guidance already
18.35 The Principal Designer should review and implement published in MHCLG ‘Advice for Building Owners of Multi-
relevant steps 1–3. Subcontract Designers should support storey, Multi-occupied Residential Buildings’ (Jan 2020). See
the Principal Designer in managing fire safety. The Principal Section 17, paragraphs 17.18–17.40 above. Much of the advice
Contractor should review and implement relevant steps 4–16. may be incorporated in future regulations or guidance.
10
Building Regulations in Scotland
PETER ANDERSON

1 Introduction 2 Outline of Building


1.01 Building control and the building standards system in
(Scotland) Act 2003
Scotland are based on the Building (Scotland) Act 2003, and
the Building (Scotland) Regulations 2004 with frequent, usually 2.01 A number of Regulations and Orders are introduced under
annual, revisions. Whilst only one part of the larger regulatory the Act. In addition, the Scottish Building Standards Agency was
scene, they are a very important part. Anyone trying to compare set up as an executive agency of the Scottish Executive in June
the Scottish building standards system and English building con- of 2004 and was re-integrated into the Scottish Government in
trol must bear the above in mind, so that there is a comparison April 2007, as the Building Standards Division (‘BSD’) of the
of like with like wherever possible. Directorate for the Built Environment, where it acts on behalf of
Scottish Ministers under the Act. In that capacity, the BSD has
1.02 This chapter is intended to describe the main provisions issued: (1) Domestic and Non-Domestic Technical Handbooks,
of the Building (Scotland) Act 2003 and procedures laid down which provide guidance as to compliance with the Building
under it, as well as the various Statutory Instruments associated Regulations; (2) a Procedural Handbook (now in its 3rd edition),
with it. It is impossible in the scope of this work to review the which provides advice on procedures under the Act and has a
detail of each of the Building Regulations. The object of each of number of very useful flow charts covering most of the proce-
the Regulations has, therefore, been briefly stated and reference dures arising under the Act and its regulations; (3) a Certification
made to those provisions which have been amended. Handbook giving advice regarding the setting up of certification
schemes under section 7(2), or individual applications under
1.03 The Regulations are amended very regularly and frequently, section 7(1) of the Act; (4) model forms to supplement those
typically annually since 2007, when major amendments to the included in the Forms Regulations; (5) guidance on such matters
previous system were first fully set out. This chapter does not as continuing requirements and staged warrants; and (6) direc-
attempt to update each of the original provisions and it is vital tions on such matters as electrical installations and structural
that a search against specific regulations should always be car- design together with other house-keeping matters, such as cor-
ried out before projects are progressed. rections and erratum to Handbooks and Forms.

1.04 Notably, following the Grenfell Tower tragedy and the final 2.02 The Act is composed of six Parts, with six Schedules. The
report of Dame Judith Hackitt released on 17 May 2018, there Parts consist of: Part 1 (Building Regulations: Sections 1–6)
was a separate Scottish Government review into fire safety. covering the making of building regulations, relaxations,
That report by Dr Paul Stollard – Review Panel on Building guidance and assessments; Part 2 (Approval of Construction
Standards (Fire Safety), published on 29 June 2018 – recognised Work etc.: Sections 7–24) covering building warrants, their
that since 2005, Scottish Building Regulations required cladding administration, and those involved; Part 3 (Compliance and
and insulation on new high rise domestic buildings taller than Enforcement: Sections 25–27), covering enforcement, which
18 metres to be made of non-combustible materials, or to pass is by the local authority; Part 4 (Defective and Dangerous
a stringent fire test. The Review did conclude that a stronger Buildings: Sections 28–30) which provides local authorities with
system of verification of fire safety engineering solutions for new powers in relation to defective buildings, which bolster and
complex buildings was desirable and made recommendations for partly replace the powers they already have under section 87 of
a minimum of two stairways as a means of escape if the building the Civic Government (Scotland) Act 1982 (as amended) and
was more than 18 metres tall. It also proposed that automatic reintroduces the powers it had under the 1959 Act in rela-
fire suppression systems should be required for all Houses in tion to dangerous buildings; Part 5 (General: Sections 31–56)
Multiple Occupancy where used for ‘care’ and for large HMO’s covering miscellaneous matters including procedures, forms,
(more than 10 occupants). It appears that the position in England fees, appeals, Crown application, penalties, corporate liability,
and Wales will be very similar to that in Scotland. It is likely that civil liability, and interpretation; and Part 6 (Supplementary:
there will be continuing changes and clarifications to technical Sections 57–59) covering, among other things, commencement
guidance and a certification regime in due course. procedures.

105
106 Building Regulations in Scotland

completed buildings (regulations 10(2), 13, 14, and 15). This


means that, where other parts of the Act require compliance with
the Building Regulations, or persons are required to certify such
compliance, these operational standards are covered along with
the more expected building standards.

Building Regulations
2.04 The Building Standards, which are set out in Schedule 5 to
the Building Regulations and incorporated by Regulation 9, are
drafted as expanded functional standards so that they should not
need to be changed to accommodate technical or design innova-
tions. The statutory requirement is to comply with these regula-
tions. One of the problems is that of unauthorised minor works.
The system requires a ‘building warrant’ before most works can
be carried out, however the category of those works requiring
to comply with the Building Regulations, but not requiring a
building warrant, which is set out in Schedule 3 to the Building
Regulations, has been expanded. It should be noted, however,
that while these works do not require a building warrant, they
do still require to comply with the Building Regulations. This
could present problems in the sale and purchase of property
where the missives require an undertaking regarding compliance
with statutory requirements. Exhibition of a building warrant
completion certificate (now to have been accepted by the veri-
fier, more of which later) will only address those works, which
were subject to a building warrant, and not other works, which
did not need such a warrant.

Conversion
2.05 There are two categories of building (Domestic and Non-
Domestic), each with its own set of guidance. The system has
the concept of ‘conversion’ with those changes, which consti-
tute conversion, being set out in Schedule 2 to the Building
Regulations, and the regulations, which apply in relation to
such conversions, being set out in Schedule 6 to the Building
Part 1 (Building Regulations) Regulations. Schedule 6 has two paragraphs. The first sets out
(Sections 1–6) those standards with which every ‘conversion’ must comply,
while the second sets out those standards which are to be met
Scope of Regulations only so far as reasonably practicable, as long as they are no
2.03 The Act, at section 1, has increased the purposes for which worse than they were before the conversion.
Building Regulations can be made to include ‘furthering the
achievement of sustainable development’ and has added to Continuing requirements – Verifer
the list of matters in relation which regulations can be made:
suitability for use by disabled persons, security, and reuse of 2.06 The Act, at section 22, allows continuing requirements to
building materials. ‘Sustainability’ was redefined in the Building be imposed with a Building Warrant or with the acceptance of
(Scotland) Amendment Regulations 2011, with a definition intro- a late-submitted completion certificate (under section 17(4) of
duced into Schedule 5 of the Building (Scotland) Regulations the Act) where necessary, to avoid the purposes of any provi-
2004 as follows: sion of the Building Regulations being frustrated. For example,
acceptance of a moveable platform for cleaning widows could be
A Statement of Sustainability. made subject to a continuing requirement that adequate access
7.1 Every building must be designed and constructed in and hard standing are provided, and kept clear, and properly
such a way that – maintained thereafter. The BSD also issued guidance on staged
warrants, in which they suggest that for projects involving ‘shell’
(a) with regard to a dwelling, a level of sustainability speci- and ‘fit-out’ works, separate building warrants, each with their
fied by the Scottish Ministers in respect of carbon dioxide own completion certificates, could be issued, but subject to a
emissions, resource use, building flexibility, adaptability continuing requirement under the ‘shell’ building warrant that
and occupant wellbeing is achieved; the building is not occupied or used until the ‘fit-out’ works are
(b) with regards to a non-domestic building, a level of sus- complete.
tainability specified by the Scottish Ministers in respect
of carbon dioxide emissions is achieved; and
(c) A statement of the level of sustainability achieved is Technical guidance
affixed to the dwelling or non-domestic building. 2.07 Because the Building Regulations are drafted in general
terms, they provide no practical guidance as to how to comply
The provision does also explain limitations of this sustainability with them. Under section 4 of the Act, Scottish Ministers, nor-
standard, particularly in relation to alterations and extensions, mally acting through the BSD, may issue guidance documents
conversions of building, and other categories. providing practical guidance on the requirements of the Building
Reference should be made to paragraph 5(2) of Schedule Regulations. This guidance may be withdrawn, fresh guidance
1 to the Act as to the subject matter of Building Regulations. may be issued, or the existing guidance revised by notice with
The Building Regulations now include obligations relative no need for any parliamentary procedure or reference to the EU.
to making completed demolition sites safe, protecting the This should allow such guidance to be changed quickly, as the
works, clearing footpaths, and securing unoccupied and partly need arises. Under section 5 of the Act, failure to comply with
Outline of Building (Scotland) Act 2003 107

the guidance does not, of itself, give rise to civil or criminal requirements relative to the building are being complied with;
liability. It is sufficient for the applicant to show that its propos- and (iv) the building has any defects, which would entitle the
als meet the requirements of the Building Regulations, even if authority to serve a defective building notice on the owner. This
they adopt means which are different from those set out in the section has not yet been implemented.
guidance. However, following the guidance can have its benefits
as, under section 5 (2) of the Act, proof of compliance with the
guidance can be treated as tending to negative liability for a Part 2 (approval of construction
breach of the Building Regulations. This should be contrasted work, etc.) (Sections 7–24)
with the standing of approved codes of practice for Health and
Safety Regulations made under the Health & Safety at Work Act Verifers and approved certifers
1974, where a breach of the relevant provision of the code can of design and of construction
be used as proof of contravention of the relevant requirement,
or prohibition subject to proof of compliance by another means. 2.12 The Act identifies three persons: verifiers; approved certi-
fiers of design; and approved certifiers of construction.

Technical handbooks
Verifers
2.08 The guidance is produced in two Technical Handbooks:
one for domestic buildings and one for non-domestic buildings. 2.13 Verifiers have the duty to administer the granting of build-
The two Handbooks are organised into seven sections, the first ing warrants, amendments to those warrants, the staging of
section being a general interpretive section numbered ‘0’ and work under those warrants, and the acceptance of completion
providing guidance on the Building Regulations, except for certificates. Verifiers are appointed by Scottish Ministers under
Regulation 9, and the following six sections numbered 1–6, section 7(l)(a) of the Act. Scottish Ministers are to consider any
corresponding to the six sections of Schedule 5 to the Building potential verifier’s qualifications; competence; accountability
Regulations, incorporated into the Building Regulations by to the public; and impartiality before making any appoint-
Regulation 9, which set out the required building standards and ment (Part VI of the Procedure Regulations). At present, all
which correspond with the six essential requirements of the 32 Scottish local authorities have been appointed as verifiers
Construction Products Directive (Structure; Fire; Environment; within their own areas. Such appointment is subject to the provi-
Safety; Noise; and Energy). The two technical handbooks are sions of section 7 of and Schedule 2 to the Act. Within Schedule
regularly updated, and the most recent version as at the date of 2, there is a provision (paragraph 9) prohibiting verifiers acting
this chapter is dated 2019, relevant for applications for building as such in relation to buildings in which they have an interest
warrants submitted on or after 1 October 2019 and to building unless authorised to do so by a direction from Scottish Ministers.
work which does not require a warrant commenced from that Verifiers need not necessarily be local authorities, but at present
date. there are no plans to involve any other bodies. Verifiers are
subject to regular audit by Scottish Ministers, which is being
2.09 The Guide for Practitioners – Conversion of Traditional carried out on their behalf by BSD, and the outcome of those
Buildings (Part 1: Principles and Practice & Part II: Application audits can be viewed on BSD’s website. BSD also maintain a
of the Building Standards) prepared by Historic Scotland in register of verifiers.
conjunction with Scottish Building Standards Agency (now
Building Standards Division), was issued by Scottish Ministers Certifers
under section 4 (1) of the Act to come into effect under
section 4(2) of the Act with the same status as the other two 2.14 Section 7 provides for Scottish Ministers appointing per-
Technical Handbooks. Where building works, subject to the sons, or approving schemes entitling persons, to act as approved
Building Regulations, are being carried out to historic buildings, certifiers of design and as approved certifiers of construction.
this guide gives guidance, on a par with that in the Technical So far, only schemes have been approved. Reference should be
Handbooks, as to compliance with those Regulations. There made to the Certification Handbook, available from the BSD
is also a Technical Handbook, issued under section 4 of the website, if you should be considering setting up such a scheme,
Act, on conservatories, providing guidance on how to meet the and to the links to the operating schemes, available on the BSD
Building Regulations for simple conservatories. In addition, website. These schemes are subject to audit by BSD, on behalf
BSD issues further guidance, which does not have the status of of Scottish Ministers, and operate their own internal audit both
Technical Guidance, but which is meant to assist in meeting the of certifiers and of the approved bodies who employ the certi-
functional standards set out in Regulation 9. For example, there fiers. Scottish Ministers, through the BSD and their website,
are Accredited Construction Details (Scotland), which show one maintain a public register of approved certifiers of design and
way, but not the only way, to address issues of air infiltration and of construction which can be checked to ensure that a person
heat-loss through junctions in the fabric of the building. holding themselves out as an approved certifier is approved and
for what they are approved.
Relaxations
2.10 Provisions allow, at section 3 of the Act, for the relaxation
Works requiring a building warrant
of any particular provision within the Building Regulations on 2.15 Under section 8 of the Act, a building warrant is required
the Scottish Ministers own initiative, in relation to a type of for: construction or demolition; or the provision of services, fit-
building, or upon an application from any person relative to tings or equipment in, or in connection with a building to which
a particular building. However, because the standards set by the Building Regulations apply, or to any conversion except for
Building Regulations are drafted as functional standards, it is those works mentioned above, which require to comply with
not expected that there will need to be many such relaxations. the Building Regulations, but do not require a building warrant.

Building Standards assessments Application for building warrant


2.11 Section 6 imposes an obligation on local authorities, if 2.16 The application for building warrant is submitted to the ver-
requested by the owner of a building, to carry out a Building ifier who must grant a building warrant if, but only if, satisfied
Standards assessment of that building. Assessing the extent to that the work, demolition or provision of services etc. will be
which: (i) the building complies with the Building Regulations carried out in accordance with the Building Regulations (includ-
applicable at the time of assessment; (ii) there is any unau- ing the building operations requirements mentioned above),
thorised work to the building; (iii) any applicable continuing that nothing in the drawings specifications etc. submitted with
108 Building Regulations in Scotland

issue such a certificate which is false or misleading in a material


particular. The applicant also commits a criminal offence where
they knowingly or recklessly make an application for a building
warrant that contains a statement which is false or misleading in
a material particular. It is therefore important, where advising
applicants who are not technically expert, to ensure that they take
expert advice before completing the application.

Approved certifcation schemes


2.20 The Scheme covers all of Section 1 of Schedule 5 to the
Building Regulations, and therefore the certifier has to be in a
position to be satisfied on all aspects of the structural design
,whenever and by whomsoever designed. This has been a prob-
lem in relation to staged works and in relation to contractor
designed aspects of the works. The solution, in relation to staged
warrants, is for the certificate to make clear which stage is cov-
ered, and when the amendment for the next stage is applied for,
the accompanying certificate will not only certify the new work,
but will also confirm the effects of the new stage on the previ-
ous works, thus maintaining a certificate for all of the structural
works. In relation to contractor-designed structure, such as roof
trusses or connection details, which, at the time of the warrant
the application indicates that the works or services etc., when application, are not designed, the certificate is to include a per-
completed in accordance with those plans, specifications, etc., formance specification for those items, and when the detailed
will fail to comply with the Building Regulations, or where the design is produced, then the certifier is to confirm that it meets
application is for a conversion that after the conversion is com- the performance specification (see model form Q). There have
pleted, it will comply with the Building Regulations (but only also been two new schemes relative to Section 6 (Energy) of
to the extent set out in Schedule 6 to the Building Regulations). Schedule 5 to the Building Regulations, one for domestic build-
ings, the other for non-domestic buildings.
Amendments to building warrants
and staged building warrants Offences under section 8
2.17 The Act contains provisions on amendment to building 2.21 In relation to the carrying out of work, provision of ser-
warrants and for staged building warrants. This should allow vices, etc., and conversion requiring a building warrant there
verifiers and applicants to agree appropriate stages with further are two offences: (1) carrying out such activity without a build-
work beyond that stage being contingent upon an amendment to ing warrant; or (2) where building warrant has been granted,
the building warrant incorporating the further stage of the works. carrying out such activity not in accordance with that building
In addition, a building warrant will not be granted for exten- warrant: and there are three categories of potential offenders: (a)
sions or alterations to existing buildings where, in relation to the person actually carrying out such activity (‘person carrying
compliance with the Building Regulations, the existing building out the activity’); (b) the person on whose behalf such activity is
complies, but will not with the extension or alteration, or where carried out (‘person instructing the activity’); and (c) the owner
the existing building fails to comply, but will fail to a greater of the building within which, or in relation to which, such activ-
degree with the extension or alteration. ity is carried out where they are not already a person in category
(a) or (b) above (‘owner’).
Limited-life buildings
2.18 The Act has provisions relative to buildings with a limited
Section 8 defences
life and also providing that any building warrant is granted 2.22 Each of these persons has different statutory defences to
subject to any conditions within it and subject to the works etc., the two different offences. Where the activity is being carried
which are the subject matter of the building warrant, being car- out without a building warrant: (i) the person carrying out the
ried out in accordance with the Building Regulations. The Act activity has a defence where, before the activity commenced, the
does, at section 14(6), create the specific statutory offence of person instructing the activity or the owner gave him or her rea-
occupying or using a building after the expiry of its limited life sonable cause to believe that a building warrant had been granted
(other than for demolition) knowing the period has expired, or for such activity; and (ii) the owner has a defence where, whilst
without regard as to whether it has expired or not. In addition the activity is being carried out, he or she did not know, and had
to the powers of enforcement given under section 27 of the Act no reasonable cause to know, that the activity was being carried
(Building Warrant Enforcement), the Act gives the local author- out. In such circumstances, the person instructing the activity
ity power to seek to prevent or restrain such actual or appre- has no statutory defence.
hended occupation or use by applying for an interdict.
2.23 Where a building warrant has been obtained for the activ-
ity, but the activity is being carried out not in accordance with
Approved certifers of design that building warrant, the person instructing the activity and the
2.19 In addition to submitting the plans specifications etc. to owner, where appropriate, each has a defence where, at the time
satisfy the verifier as to the matters noted above, the applicant of the alleged offence, they did not know and had no reason-
can also submit a certificate from an approved certifier of design. able cause to know that the activity was being carried out not
Such a certificate should certify that the part of the design for in accordance with the building warrant. In such circumstances,
which the certifier is approved to certify and the proposed method the person carrying out the activity has no statutory defence.
of working both comply with the Building Regulations. The veri-
fier must treat such a certificate as conclusive evidence as to what
it certifies and, other than satisfying themselves as to the validity
Consequences
and the scope of the certificate, the verifier need make no further 2.24 Any person instructed to carry out an activity for which
enquiries. It is a criminal offence knowingly or recklessly to a building warrant is required should, before starting, require
Outline of Building (Scotland) Act 2003 109

confirmation from the person instructing such activity, or the The verifier can either accept or reject that certificate and must
owner of the building in relation to which such activity is accept it if, after reasonable enquiry, it is satisfied as to the mat-
instructed, as appropriate, that a building warrant covering the ters certified in it.
proposed activity is in place. The person instructed to carry out
such activity should also have a copy of the building warrant
and associated plans, specifications, and documents and should
‘Relevant person’ under section 17
insist that, in carrying out the proposed activity, he or she should 2.29 The ‘relevant person’ is one of three different persons: (1)
not be required to breach either the building warrant or the the person carrying out the work for themselves, as where, for
Building Regulations. The building contract documents should, example, it is the tenant where he does the work himself; or (2)
therefore, not conflict with building warrant plans, specifications the person for whom the work is carried out where it is carried
and documents. out by others, as where, for example, it is the tenant where he
gets a builder to do the work for him; or (3) the owner, but
2.25 The person instructing the activity and the owner, where only where the owner does not fall within categories (1) or (2)
appropriate, will need to ensure that, where the proposed activ- above, and where neither (1) or (2) above submit the certificate.
ity requires a building warrant, one is obtained, and they have The completion certificate is only effective once the verifier has
procedures in place, in relation to the implementation of the accepted it. Thus, where no one has submitted a completion
building warrant, where they might have reasonable cause to certificate, the owner can be obliged to submit it.
suspect that the implementation may not be in accordance with
the building warrant, to ensure that such implementation is in
accordance with the building warrant. In this regard you should
Approved certifers of construction
note that, where the owner of the building, in relation to which 2.30 The relevant person can submit, with the completion certifi-
such activity is to be carried, is not the applicant for the build- cate, certificates from approved certifiers of construction certify-
ing warrant, the verifier is required to notify them of the issue ing that the specified construction complies with the Building
of the building warrant. Regulations. These certificates are treated, by the verifier, as
conclusive evidence of what they certify.
2.26 The owner of such a building should, therefore, have pro-
cedures in place to ensure that a building warrant is obtained
for any activities requiring such a warrant, and both the person
Offences under sections 19 and 20
instructing such activity and the owner of the building should 2.31 The relevant person submitting the completion certificate
have procedures to ensure that it is being carried out in accord- and any certifiers of construction issuing certificates of construc-
ance with that building warrant. tion are guilty of an offence if they, knowingly or recklessly,
submit or issue, as appropriate, such a certificate which is false
or misleading in a material particular. In relation to the com-
Liability of applicant pletion certificate, this means that, where the ‘relevant person’
2.27 The applicant for a building warrant commits an offence has insufficient knowledge or understanding of how building
where they knowingly or recklessly make a statement, in their warrant works were carried out, it would be advisable for that
application, which is false or misleading in a material particular. relevant person to consult with those who do before submitting
The Act does not stipulate who can make the application, but the the completion certificate.
model form A of the model forms includes a declaration

1. That the work will be carried out in accordance with build- Unauthorised occupation or use
ing regulations, and in accordance with the details supplied 2.32 It is an offence to occupy or use any building, except for
above and with any necessary accompanying information construction, which is the subject of a building warrant, except
(including annexes to this application, drawings, and specifi- where it is only for alteration, without an accepted completion
cations), (see note 6 [this covers matters relating to building certificate or without consent from the verifier for the tempo-
operations]) 2. Iam/we* are the owner of the building/That the rary occupation or use of the building. The offence is commit-
owner of the building is aware of this application 3. [Where ted where the above noted exceptions do not apply, and the
the warrant involves a specified conversion] That after con- person, knowingly or without regard to whether a completion
version the building as converted will comply with building certificate has been accepted, occupies or uses the building. The
regulations*. local authority, should they so wish, can apply to a court for
an interdict to restrain or prevent such actual or apprehended
The applicant will therefore need to be in a position, contractu- occupation or use.
ally, to ensure that the works are carried out in accordance with
the declaration and, where they are not technically competent,
will need to receive undertakings, from those acting for them Building Standards assessments
who are, that the declaration is being implemented. Finally, there and completion certifcates for
is a further consequence of carrying out works without a build-
ing warrant, which will be dealt with in more detail later when
works without a building warrant
discussing the completion certificate. 2.33 The Act introduces a right, in section 6, for the owner of
a building, requiring the local authority to carry out a ‘Building
Standards assessment’ of a building if so requested by the owner.
Completion certifcate Under section 15, a building warrant can be applied for at any
2.28 There is no application for a completion certificate. Instead, time before a completion certificate has been accepted, notwith-
the ‘relevant person’ must submit a completion certificate when standing that it is an offence to start work without a building
the work, or the conversion, in respect of which the building warrant. However, the Building Regulations applicable to any
warrant was granted, is complete. The certificate may be signed building warrant are those applicable at the time of applica-
by the ‘relevant person’ or their duly authorised agent, but tion for the building warrant, even if the works were carried
remains the relevant person’s certificate, even if signed by their out earlier. In addition, under regulation 7(2) of the Procedure
agent. That certificate must certify that the works were carried Regulations, the verifier is entitled, in such circumstances,
out, or conversion was made, in accordance with the building to require the works to be opened up to establish that they
warrant and the works or services, fittings, or equipment which have been built in accordance with the plans submitted. Under
are, or the converted building which is, the subject of the build- section 17(4), where works or a conversion requiring a building
ing warrant, comply or complies with the Building Regulations. warrant have been carried out without a building warrant, then
110 Building Regulations in Scotland

the ‘relevant person’ must submit a completion certificate, which applied for before that date. If, by that date, the owner has not
can only be accepted if the verifier is, after reasonable enquiry, complied with the notice, the owner is guilty of an offence, and
satisfied as to the matters certified. Such a certificate certifies the local authority can carry out the work necessary to make the
compliance with the Building Regulations, and where it is sub- building comply. The local authority does not need a warrant
mitted under section 17(4), where there is no preceding building for such work, but must register a completion certificate in the
warrant, the applicable Building Regulations are those applicable buildings register (which will show up on a search). The local
at the time the completion certificate is submitted. In addition, authority may withdraw the notice, or waive or relax any of its
any such late submission of a completion certificate with no requirements, but this does not preclude the issue of a further
preceding building warrant attracts, under the Fees Regulations, notice.
a 125% building warrant fee. Under section 41 of the Act, where
a completion certificate is submitted under section 17 of the Act 2.38 Section 25 of the Act is to be used to enforce the display
(or a building warrant is applied for, or building works are car- of energy performance certificates (EPCs) in public buildings as
ried out pursuant to a building warrant), the verifier may require required under the Energy Performance of Buildings Directive.
materials tests to be made, which could include tests of combina- In addition, the Climate Change (Scotland) Act 2009 contains
tions of materials or of the whole building and, under regulation further powers regarding changes to existing buildings.
46 of the Procedure Regulations, may require the exposure of
concealed parts of the structure to establish compliance with the
Building Regulations. Continuing requirement and building
warrant enforcement notices
Building Standards Register 2.39 The local authority can, under section 26 of the Act, serve a
‘continuing requirements enforcement notice’ requiring an owner
2.34 Section 24 of the Act requires local authorities to keep a to comply with continuing requirements imposed by the verifier
Building Standards Register covering its own geographical area. under section 22 of the Act or by the Building Regulations under
This register is in two parts. Part I contains the basic data on section 2 of the Act. Failure to comply with such a notice is an
any building warrants relative to a particular works or conver- offence, and the local authority may carry out such work as is
sion, including any applications and amendments for warrant, necessary to comply with the notice and recover the reasonably
any completion certificates submitted and their acceptance or incurred expenses of such work from the owner.
rejection, and any energy performance certificates and notices
issued relative to those works or conversion (including any 2.40 The local authority can also, under section 27 of the Act
issued under the Housing (Scotland) Act 2006). Part II contains serve a ‘building warrant enforcement notice’ requiring the
the relevant documents. Building Standards assessments, when relevant person (in this case: (i) the person doing the work for
introduced, will not be recorded on the register, but if any themselves; or (ii) the person for whom the work is being done;
enforcement notices are issued as a result of any assessment, or (iii) the owner, where not (i) or (ii), and where (i) or (ii) can-
they will. The register is public, with Part I being in electronic not be found, or no longer have an interest in the building) to
form, but access to some of the documents lodged in Part II obtain a building warrant (where the work is being carried out)
may be restricted where there are issues of security or privacy. or to submit a completion certificate (where it has been com-
pleted without a building warrant), and, where the works have
Part 3 (compliance and not been carried out in accordance with a building warrant, to
secure compliance with, or obtain an appropriate amendment to,
enforcement) (sections 25–27) the building warrant. Failure to comply with such a notice is an
2.35 Verifiers mainly administer the provisions within Part 2 of offence, and the local authority may carry out such work as is
the Act, while the main body responsible for implementing the necessary to comply with the notice and recover the reasonably
provisions in Part 3 is the local authority. incurred expenses of such work from the owner.

2.41 It is therefore important when purchasing property to check


Building regulations compliance notice that all the relevant building warrants are in place and that com-
2.36 Building warrants, completion certificates, and the other pletion certificates have been submitted and accepted in relation
provisions in Part 2 of the Act relating to the approval of to all building warrants, as a failure to do so could leave the
building works are concerned with actual building works (new new owner with an obligation to pay the building warrant fee
or alterations) or conversions, but not with existing buildings +25% and to meet the standards of the Building Regulations
(except where they are affected by such works or conversions). applicable at the time of submission of the completion certificate
(and not when the works were carried out). In addition, until
2.37 Under section 25, Scottish Ministers can, where they that completion certificate is accepted, they could be prevented
consider buildings of any description to which the Building from occupying or using the building. All of the above notices
Regulations apply, ought to comply with a provision of those are either served on the owners of the relevant buildings or, in
regulations, direct all or particular local authorities, or a par- relation to the building warrant enforcement notice, on the rel-
ticular local authority, to secure that such buildings comply with evant person, who is likely to be the owner. The local authority
that provision, but only for certain specified purposes. Those can carry out such works as is necessary to comply with such a
purposes fall into three main categories, which, in general terms, notice, including demolition of the works, and recover the costs,
are: (i) health, safety, welfare, and convenience; (ii) furthering less any proceeds from the sale of the materials arising from the
the conservation of fuel and power; and (iii) furthering the demolition, from the person on whom the notice was served.
achievement of sustainable development. It is, however, the local
authority, on the direction of Scottish Ministers, who serves the Part 4 (defective and dangerous
notice (known as a ‘building regulations compliance notice’) on
the owners of the specified buildings. The notice must specify buildings) (sections 28–30)
the provision of the regulations to be met, the date after which
the building should comply, any particular steps to be taken,
Defective buildings
and the date on which the notice takes effect. Any work carried 2.42 Section 28 empowers the local authority to serve a notice (a
out under such a notice must still comply with the provisions ‘defective building notice’) on owners requiring them to rectify
of Part 2 of the Act (Building Warrant granted and Completion specified defects, which require rectification in order to bring
Certificate accepted), but the local authority can vary the date the building into a reasonable state of repair having regard to
by which the building must comply where a building warrant is its age, type, and location.
Outline of Building (Scotland) Act 2003 111

Dangerous buildings Offences and liability (sections 48–51)


2.43 Sections 29 and 30 deal with buildings which constitute a 2.48 These sections cover statutory offences by persons and
danger to persons in or about them, or to the public generally, in corporate bodies, criminal liability of trustees, and civil liability.
relation to which the local authority can issue notices (‘danger- Section 48 sets the level of fines on summary conviction for an
ous building notices’). offence under the Act (not exceeding level 5 on the standard
scale [at present £5000]). Offences under sections 14(6), 21(5),
2.44 The provisions in Part 4 go into detail regarding action to be and 43(1), which all relate to illegal occupation of premises, can
taken to bring defective buildings up to the required standard and be subject to indictment, with an unlimited fine on conviction.
to make dangerous buildings safe, the powers of local authori- Section 49 extends liability for offences committed by corporate
ties to carry out emergency work to dangerous buildings and to bodies, local authorities, Scottish partnerships, and unincorpo-
recover the cost from the owner, and with regard to purchasing rated bodies from those bodies to include those persons within
such buildings where owners cannot be found, and the selling those bodies in positions of authority and control who consent
of materials from buildings demolished by the local authority. or connive in the offence or where such offences are attribut-
able to their neglect. Section 50 provides specific defences for
trustees etc.
Part 5 (general) (sections 31–56)
2.45 This part of the Act covers a number of administrative 2.49 The Act, at section 51, includes for civil liability. These are
details and should be referred to if it is required to check whether specific statutory provisions and expressly do not exclude delict-
the powers contained in the Act have been properly used or to ual liability (that is, common law non-statutory or contractual
make use of provisions within the Act. For example, any notices liability) arising due to breach of a duty of care or negligence.
served by a local authority need to comply with section 37, and The statutory civil liability arises where there is a breach of a
any appeals under the Act need to comply with the provisions duty imposed by the Building Regulations which causes damage
in section 47. In addition, where scheduled monuments or listed except in so far as the regulations provide otherwise and subject
buildings are involved, section 35 sets out special procedures to any defences provided within those regulations. ‘Damage’ is
which are to be followed. defined to include death or physical injury.

2.50 However, the definition is silent as to whether it includes


Entry, inspection, and tests financial loss, what is often referred to as ‘pure economic loss’,
(sections 39–41) as opposed to financial recompense for physical damage, both
2.46 These sections give the local authority powers to enter to person (death or injury) and to buildings.
buildings and carry out inspections and tests relative to
Part 3 (Compliance and Enforcement) and Part 4 (Defective Crown rights – removal of Crown immunity
and Dangerous Buildings) and allow, at section 41, Scottish
Ministers to require the testing of materials by those applying 2.51 The commencement of Section 53 of the Building
to them for a relaxation. The same section allows verifiers to (Scotland) Act 2003 to remove Crown immunity from building
require those applying to them for a building warrant, or carry- regulations came into force on 1 May 2009. This was effected
ing out work under a building warrant, or submitting a comple- by The Building (Scotland) Act 2003 (Commencement No.2 and
tion certificate, to carry out a materials test. It is these powers Transitional Provisions) Order 2009.
which allow the verifier to require such tests as sound tests. The
tests are to be carried out at the expense of the applicant. Powers 2.52 Exemptions. A Section 104 Order under the Scotland Act
to require testing, arising under this section, are included in the 1998 to deal with reserved matters (The Building (Scotland) Act
Procedure Regulations (Regulation 61). 2003 (Exemptions for Defence and National Security) Order
2009) gave exemption from the Building (Scotland) Act and
Scottish building standards system for buildings used or to be
Appeals (section 47) used for defence or national security purposes. In addition, The
2.47 In addition to setting out those decisions or notices which Building (Scotland) Amendment Regulations 2009 amends the
can be appealed to the Sheriff within 21 days of the date of the Building Regulations to include within Schedule 3 additional
decision or notice (such appeal being final), this section also work types that do not require a building warrant. These are
provides that certain decisions are deemed to have been made if works to: the Scottish Parliament; Her Majesty’s private estate;
they are not made within certain time limits. Those time limits and prisons or buildings where persons may be legally detained
are specified in the Procedure Regulations (Regulation 60). (such as police or court cells or secure mental institutions) where
Where the verifier has not made a ‘first report’ (see Procedure work does not increase floor area by more than 100m2.
Regulations later in this chapter) on a building warrant, or
amendment to warrant, application within three months, or 2.53 Amendments to the Procedure Regulations (The Building
where the verifier has, but has not made a decision on the appli- (Procedure) (Scotland) Amendment Regulations 2009). These
cation within 9 months of that report, or such longer period as Regulations: (i) amend the interpretation of ‘fire authority’ to
is agreed between the verifier and the applicant (or the owner), recognise the different enforcing authorities for Crown build-
then the application is deemed to have been refused (subject to ings; (ii) amend Regulation 58 to reference specific Crown build-
any periods required for considering relaxations or making con- ings being a prison, a building where a person may be lawfully
sultations being disregarded). Where the verifier has not made detained or lawfully held in custody, the Scottish Parliament, or
a decision on an application to extend the period for demolition a building owned by Her Majesty in her private capacity; and
of a ‘limited-life’ building within one month of that application, (iii) widen the public access to all documents on the Building
then it is deemed to have been refused, and where a completion Standards Register except those that the local authority are satis-
certificate has not been accepted or rejected within 14 days of fied would raise genuine security concerns.
its submission, or such longer period as agreed between the veri-
fier and applicant, then it is deemed to be rejected. Except that 2.54 In addition, the Scottish Government have produced
where the completion certificate is submitted for work requiring Procedural Guidance for Crown Buildings.
a building warrant, but carried out without such a warrant (see
section 17[4] of the Act), as the certificate must be accompanied
with the same drawings and information as if it were a build-
Interpretation
ing warrant application, the time limits in relation to a building 2.55 Section 55 covers the meaning of ‘building’, and
warrant application apply. section 56 covers most of the other definitions.
112 Building Regulations in Scotland

Schedules applicant to a reduction in the fee properly payable (reference


should be made to the Fees Regulations for details).
2.56 These relate to matters in regard of which regulations may
be made, verifiers and certifiers, procedure regulations, powers 3.04 When the application is received, the verifier shall forth-
of entry, inspection and testing, evacuation of buildings, and with consider the application. However, where the application
modification of enactments. is submitted without the specified plans, except where it is an
application for a staged warrant or the verifier is satisfied that
3 Building (Procedure) the plans submitted sufficiently describe the proposed works,
the verifier must advise the applicant of the specified plans still
(Scotland) Regulations and required and accept the application on condition that the appli-
subsequent amendment cant submits the missing plans within 42 days of the applicant’s
receipt of that advice. This provision allows application to be
made without all the details, with such details being submitted
Interpretation 42 days later, with the applicable regulations being those in
3.01 Part I of the Procedure Regulations deals with citation, force at the date of application. In addition, a warrant is valid for
commencement, and interpretation, and includes a provision 3 years from the date it is granted, such validity being subject to
allowing the submission of documents by electronic transmission further extension, at the discretion of the verifier, if applied for
where the recipient has, in advance, accepted such transmission. before the expiry of the warrant. This has allowed warrants to be
Thus, where the verifier or local authority has made provision applied for immediately prior to the coming into force of more
for such electronic transmission, building warrant applications onerous regulations with very little detail in the application and
can be made electronically. for the works under that warrant not to be built for many years
thereafter, when the regulations current at that time may be very
Applications for warrant different to those under which the warrant is granted.

3.02 Part II of the Procedure Regulations deals with applications 3.05 Any extension to the duration of a warrant allowed under
for warrant. The following is a précis of the arrangements. The Regulation 19, if granted by the verifier, can, if the verifier sees
applicant, whose identity is not restricted, must lodge the appli- fit, be subject to any work carried out during the further period
cation with the verifier in writing or, where the verifier allows of validity being compliant with the Building Regulations appli-
electronic transmission, in electronic form, on the appropriate cable at the time the extension is granted (regulation 19(5)). In
form which, in the case of an application for building warrant, addition, where a warrant relates to multiple subjects the verifier
is not one of the statutory forms. However, the BSD provides may require that separate applications are made in respect of
‘Model Forms’ (available on their website) which should, nor- such multiple subjects as the verifier thinks fit (regulation 19(6)).
mally, be the basis for any form produced by the verifier. It can
be signed by the applicant or on behalf of the applicant, by his 3.06 The verifier shall: if the application complies with the
or her agent (or, where it is an electronic submission, authen- requirements of the Procedure Regulations and satisfies the
ticated by an electronic signature). The application should be matters set out in section 9 of the Act, grant the building war-
accompanied by the principal plans specified in Schedule 2 to rant; or, within three months of receipt of the application, send
the Procedure Regulations and, where the submission is not a report to the applicant or the applicant’s agent, identifying
in electronic form, a copy of each of the plans together with what further information is required and anything which is not
the appropriate fees. The plans are to be to such scale as the in accordance with section 9(1) of the Act (the ‘first report’); or,
verifier may require. If a direction relaxing any regulation has after giving the applicant or agent 14 days’ notice of any grounds
already been given by Scottish Ministers, this should accom- for refusal and an opportunity to be heard, refuse the application.
pany the application. The model form application for building Such application or its refusal is sent to the local authority for
warrant now has a question regarding security matters, as the registration in the building standards register.
2009 amendments to the Regulations provide for the restriction
of access to such information as referred to in ‘Note 4’ in the 3.07 Part II contains further provisions in relation, amongst other
Model Form A. things, to: staged warrants; warrants for conversions; late appli-
cations under section 15 of the Act; consultation; demolition
3.03 There is an alternative to giving the verifier all of the (where period for demolition must be stated); and limited life
detailed information referred to above. An approved certifier of buildings (including the requirement that it must be demolished
design can provide a certificate saying that particular aspects and removed from the site before the expiry of that limited life).
of the work will comply with the Building Regulations. Such a
certificate, once it is proved to be valid, is conclusive evidence 3.08 Part III covers reference to Scottish Ministers for views
as to what it certifies, and no further enquiry by the verifier is under section 12 of the Act. Parts IV and V cover applications
necessary. The certificate must be issued by an approved certi- to Scottish Ministers for a direction under section 3(2)(a) or 3(2)
fier of design employed by an approved body operating under (b) of the Act to relax, or dispense with, a particular provision
an approved scheme. The current scheme providers, in relation of the Building Regulations, or to vary such a direction under
to design, are SER Ltd, under whose scheme compliance of section 3(4)(c). Part VI sets out the qualities to be considered
building structures with section 1 (structure) of Schedule 5 to when appointing a verifier.
the Building Regulations is certified, BRE Certification Ltd,
under whose scheme compliance of non-domestic buildings with 3.09 Part VII covers procedures relative to certification of design
section 6 (energy) of Schedule 5 to the Building Regulations is and of construction. Any scheme will need to comply with these
certified, and RIAS Services Ltd, under whose scheme compli- requirements. However, these requirements are mainly relevant
ance of domestic buildings with section 6 (energy) of Schedule to the scheme providers, and members of the scheme should
5 to the Building Regulations is certified. The information on the refer to the scheme itself for their obligations, as any scheme
certificate should match that on the building warrant application must comply, otherwise it will not be approved. However, the
form in respect of the location of the project, the description requirements relative to the promotion of good practice regula-
of the works and, where there is a staged warrant, the descrip- tion 36(3) and the requirements regarding the maintenance of
tion of the stage of work applicable. The applicant must also records in regulation 37 should be noted.
provide enough information in respect of the certified work to
assist in any site inspections the verifier may wish to make. The 3.10 Part VIII covers the procedures in relation to completion
submission of such a certificate with the application entitles the certificates. The completion certificate is to be submitted in
Building (Scotland) Regulations 2004 and subsequent amendments 113

prescribed form (Form 5, 6, or 7, as appropriate, in the Schedule 5 The Building (Fees) (Scotland)
to the Forms Regulations). The regulations set out what should
be covered in the submission and what should accompany the Regulations 2004 and
form. The 2007 Amendment Regulations introduce the require- subsequent amendment
ment to submit an energy performance certificate where required
under the Building Regulations and permits the submission of 5.01 These Regulations set the fees charged by verifiers for build-
a single completion certificate for multiple dwellings where the ing warrant submissions, including submissions after work has
work is to existing dwellings in the same ownership (such as already started, and for submissions of completion certificates
work for a local authority or social landlord). The regulations without any building warrant (where a surcharge applies). They
make further provisions, which have been covered earlier in this also set out the discounts available when parts of a submission for
chapter, regarding completion certificates for works carried out a building warrant are covered by a certificate from an approved
without a building warrant. certifier of design (as such design does not need to be checked by
the verifier) and the discounts available when a completion certifi-
3.11 Parts IX and X cover notices by local authorities and cate is submitted with one or more certificates from approved certi-
general procedures for local authorities and verifiers. Part IX fiers of construction. The verifier is to be informed of the proposed
requires local authorities to enter in the building standards use of such certificates when the building warrant application is
register any notices issued by them under Parts 3 (Compliance made. Where such certificates are not, in fact, submitted, the fee
and Enforcement) and 4 (Defective and Dangerous Buildings) otherwise applicable will become due. There is a zero fee for
of the Act, including any waiver, or relaxation of any require- work to improve the suitability of a dwelling for use by a disabled
ment contained in those notices, or any withdrawal, or the occupant (such work is already required for most non-domestic
quashing of such notices. The building standards register can buildings under the Disability Discrimination Act). The fees are
therefore be a useful source of information on an existing build- set out in a table in the schedule to the Fees Regulations, and are
ing. Part X covers procedures to be followed by verifiers and based on the estimated value of the work (which is an estimate
local authorities relative to a number of matters. Some of these, of the commercial cost or, where there are special circumstances
such as deemed determination, have already been mentioned in such as self-build, what would be the cost on a commercial basis).
the commentary on the appropriate parts of the Act. However, However, the cost is only of that work subject to the Building
Regulation 57, which is amended by the 2007 Amendment to Regulations and does not include such items as decorating or floor
the Procedure Regulations, should be noted. This lists what coverings not required to comply with the Building Regulations.
should be included in Parts I and II of the Building Standards
Register and is a useful checklist of information, most of
which should be available for public inspection (parts of Part II 6 Building (Scotland)
may be restricted). Part I should include: list of applications, Regulations 2004 and
submissions, and decisions; particulars of energy performance
certificates, certificates from approved certifiers, and of notices subsequent amendments
issued under Parts 2 and 3 of the Act; and particulars of all
other documents submitted to the local authority for regis- 6.01 The Regulations, as amended, consist of 17 regulations.
tration on the Building Standards Register. Part I should be Regulation 2 provides the definitions to a number of terms
available in electronic form on line and therefore should be used in the regulations. Careful note should be taken of the
freely available. However, the information in Part II, which definitions of ‘domestic’, ‘residential’, and ‘dwelling’. Whilst
includes drawings, specifications, and other technical informa- the actual definitions should be examined, in general terms, a
tion, may be restricted, for privacy or security reasons; the ‘domestic building’ is equivalent to a ‘dwelling’ plus common
2009 Amendments to the Procedure Regulations have amended areas, a ‘dwelling’ is residential accommodation for a family or
Regulation 58 to make further provisions regarding security, less than six persons living together as a single household, and a
and if a copy of any of the available documents is requested, ‘residential building’ is a building, other than a ‘domestic build-
the local authority is entitled to charge for such provision ing’, having sleeping accommodation. These definitions apply
(Regulation 8 of the Fees Regulations). only to the Building Regulations (although they can be shared
by the Act and other regulations under the Act), and care should
be taken when using similar terms in different legislation (thus
4 Building (Forms) (Scotland) houses subject to licensing, under other legislation, as Houses in
Multiple Occupation [covered later in this chapter] can be clas-
Regulations 2005 and sified as either domestic or non-domestic, principally depending
subsequent amendments on the number of occupants).

4.01 Section 36 of the Building (Scotland) Act 2003 gives 6.02 Regulation 3 provides for certain types of building, ser-
Scottish Ministers power to make Regulations prescribing vices, fittings, and equipment, as set out in Schedule 1 to the
the form and content of any application, warrant, certificate, Regulations, to be exempt from regulations 8–12, subject to the
notice, or document authorised or required to be used under exceptions stated in the schedule. Schedule 2 to the Regulations
or for the purposes of the Act. Where such a form is used, it sets out what changes in occupation or use of a building consti-
must be used in the form set out in the Forms Regulations, or tute conversion, and Schedule 6 sets out the extent to which, in
in a form as close to it as circumstances permit. The Forms a conversion, particular standards require to be complied with.
Regulations contain, in a schedule, 16 prescribed forms, which
include notes as to their completion. However these forms do 6.03 Regulation 5 and Schedule 3 to the regulations set out the
not cover all circumstances where forms may be needed, and work which, while it does require to meet the standards set out
BSD have published a number of ‘Model Forms’ (available in regulations 8–12, does not, subject to the exceptions and
on the BSD website), which cover a number of circumstances conditions, require a building warrant. Though this work does
not covered by the statutory forms. These forms are intended not require a building warrant, it still requires to comply with
for use by verifiers and local authorities to assist in compos- the Building Regulations. This work, as it does not require a
ing their forms covering the same subject. They therefore building warrant or a completion certificate, will not feature on
give an indication of the general information to be expected, the building standards register.
but anyone needing to use such a form should check with the
relevant verifier or local authority as to actual forms required 6.04 Regulation 8(1) requires all work carried out to meet the
to be used. standards set out in regulations 9–12 to be ‘carried out in a
114 Building Regulations in Scotland

technically proper and workmanlike manner, and materials Section 1: Structure


must be durable and fit for their intended purpose’. Regulation (Standards 1.1 and 1.2)
8(2) requires materials, services, fittings, and equipment used
to meet such standards to be, so far as reasonably practicable, 1.1 Structure
sufficiently accessible to enable any necessary maintenance or
repair work to be carried out. This fitness for purpose standard Every building to be designed and constructed so that the applied
applies only to work required to comply with the building stand- loadings, taking account of the ground, will not lead to collapse
ards, but that breach of this regulation could give rise to civil of the whole or part of the building, deformations rendering the
liability under section 51 of the Act. building unfit for the intended purpose, unsafe, or causing dam-
age to other parts of, or fittings in, the building, or impairment
6.05 Regulation 9 and Schedule 5 are the heart of the Building to the stability of any part of another building.
Standards system, as they set out what must be achieved in Means of escape from fire
building work. The standards are set out in full in Sections l–6 Flowchart for assessing appropriate method for compli-
of Schedule 5 to the Regulations, with associated guidance on ance with Standards taken from Building Standards Division
compliance in sections 1–6 of the Technical Handbooks (both of the Directorate of the Built Environment of the Scottish
Domestic and Non-Domestic versions). The sections relate Governments consultation on proposed changes to the Means
directly to the ‘Essential Requirements’ of the Construction of Escape.
Products Directive. Schedule 5 and the 66 expanded functional
standards (arranged within six sections) will be covered later in 1.2 Disproportionate collapse
this chapter.
Every building to be designed and constructed so that, in the
6.06 Regulations 10, 13, 14 and 15 contain provisions regard- event of damage occurring to any part of the structure of the
ing demolition, protective works, clearing of footpaths, and the building, the extent of any resultant collapse will not be dispro-
securing of unoccupied and partly completed buildings, which portionate to the original cause.
were previously contained in separate Buildings Operation This section (Standards 1.1 and 1.2) is covered by the certifi-
Regulations. By bringing these regulations within the Building cation scheme operated by SER Limited, discussed earlier in this
Regulations, compliance with them becomes an obligation under chapter, under which approved certifiers of design can certify
the building warrant and is included in the completion certificate. that particular applications for building warrant comply with
this section of Schedule 5 to the building regulations. Under this
6.07 The amendment regulations of 2006 introduced a new scheme, the certifier must certify compliance of all of the design
Regulation 17. This regulation, on continuing requirements, was with the requirements of section 1 (structure).
introduced to implement the terms of Article 9 of the Energy
Performance of Buildings Directive regarding the inspection of Section 2: Fire (Standards 2.1–2.15)
air-conditioning systems.
The following paragraphs give a brief description of the In relation to these standards, every building is to be designed
expanded functional standards as amended in 2006, 2007, 2008, and constructed so that, in the event of an outbreak of fire within
and 2009 and brought into force in May 2009. (Amendment that building, the requirements set out below, against each of
2008 makes only a definitional change to Schedule 5 and these standards, are met (with Standards 2.12, 2.13, and 2.14
Amendment 2009 mainly amends Schedule 3.) However, this is applying to every building), each standard being subject to the
only meant to guide readers to the appropriate part of the regu- limitations stated.
lations and the relevant Technical Handbooks which should be In relation to fire, these standards should be read along with
consulted for more detailed information and guidance. the provisions of Part 3 of the Fire (Scotland) Act 2005 and any
regulations and guidance issued under that Act.
Schedule 5 to the Building Regulations
2.1 Compartmentation
6.08 This schedule contains the expanded functional standards.
That is, the standards describe the functions a building should Fire and smoke are to be inhibited from spreading from the
perform, such as, in Fire, ‘providing resistance to the spread compartment of origin until occupants have had time to leave
of fire,’ and are an expanded and more detailed form of the and any fire containment measures initiated.
previous building standards regulations. They are arranged
into 6 sections: 1 (Structure); 2 (Fire); 3 (Environment); 4 Limitation
(Safety); 5 (Noise) and 6 (Energy), corresponding with the six Not applicable to domestic buildings.
essential requirements of the Construction Products Directive
(1: Mechanical Resistance & Stability; 2: Safety in case of 2.2 Separation
Fire; 3: Hygiene, Health and the Environment; 4: Safety in
Use; 5: Protection against Noise; 6: Energy, Economy and Heat Where a building is divided into more than one area of different
Retention). Each of the standards includes, where appropriate, occupation, it must inhibit fire and smoke from spreading from
limitations on the standards contained in them. Two Technical the area of occupation where the fire originated.
Handbooks (regularly updated) have been provided by Scottish
Ministers giving guidance on how to comply with these regula- 2.3 Structural protection
tions. One handbook is for where the buildings are domestic,
and one is for where they are non-domestic. The Regulations The load-bearing capacity of the building must continue to
define a ‘domestic building’ as a dwelling or dwellings and any function until all occupants have escaped, or been assisted to
common areas associated with the dwelling, while ‘dwelling’ is escape from the building, and any fire containment measures
defined as a unit of residential accommodation occupied: by an have been initiated.
individual or individuals living together as a family; or by not
more than six individuals living together as a single household. 2.4 Cavities
Following such guidance is not mandatory, but compliance with
the applicable requirements set out in this Schedule 5 (subject The unseen spread of fire and smoke within concealed spaces in
to any relaxation) is mandatory. its structure and fabric is to be inhibited.
Building (Scotland) Regulations 2004 and subsequent amendments 115
116 Building Regulations in Scotland

2.5 Internal linings constructed in such a way that specific requirements are met,
as set out below, in brief, (subject to the limitations). Standards
The development of fire and smoke from the surfaces of the 3.5–3.9 deal with drainage as detailed below.
walls and ceilings within the area of origin is to be inhibited. Standards 3.11 and 3.12 relate to ‘liveability’ and ‘lifetime
homes’ and issues of sustainability and convenience. There
2.6 Spread to neighbouring buildings needs to be provision, on one level, of an enhanced apartment
and kitchen, and an accessible toilet, which taken with improved
The spread of fire to neighbouring buildings is to be inhibited. circulation spaces (under Standard 4.2) will assist in creating
homes that can be lived in even when mobility is impaired, pro-
2.7 Spread on external walls moting both sustainability and lifetime homes. A requirement for
a space for drying clothes has also been re-introduced to assist
The spread of fire on the external walls of the building is to be
in sustainability.
inhibited both where the fire originates within the building and
where it originates from an external source.
3.1 Site preparation – harmful
2.8 Spread from neighbouring buildings and dangerous substances
Where the fire originates in a neighbouring building, the spread There is not to be danger to the building nor threat to health of
of fire to the building is to be inhibited. people in or around the building due to presence of harmful or
dangerous substances.
2.9 Escape Limitation
The occupants, once alerted to the outbreak of fire, are to be Not applicable to removal of unsuitable materials (topsoils
provided with the opportunity to escape from the building before etc.) on site of temporary (under five-year intended life)
being affected by fire or smoke. non-dwellings.

2.10 Escape lighting 3.2 Site preparation – protection


Illumination is to be provided to assist in escape. from radon gas
There is not to be a threat to the health of people in or around
2.11 Communication the building due to emission and containment of radon gas.
The occupants are to be alerted to the outbreak of fire.
3.3 Flooding and ground water
Limitation
There is not to be a threat to the building or the health of the
Only applies to a dwelling, residential building, or enclosed
occupants due to flooding and the accumulation of ground water.
shopping centre.

2.12 Fire Service access 3.4 Moisture from ground


There is not to be a threat to the building or the health of the
Every building to be accessible for fire appliances and fire ser-
occupants due to moisture penetration from the ground.
vice personnel.

2.13 Fire Service water supply 3.5 Existing drains


No building to be constructed over an existing active drain.
Every building to be provided with a water supply for use by
the fire service.
Limitation
Not applicable where not reasonably practicable to re-route
Limitation
existing drain.
Not applicable to domestic buildings.

2.14 Fire Service facilities 3.6 Surface water drainages


Every building to be designed and constructed to provide facili- Every building and hard surface within the curtilage of a build-
ties to assist fire-fighting and rescue operations. ing to be designed and constructed with a surface water system
which has facilities for separation and removal of silt, grit, and
pollutants and ensures disposal of surface water without threat-
2.15 Automatic life safety fre ening the building and the health and safety of people in and
suppression systems around the building.
Fire and smoke to be inhibited from spreading through the build-
ing by the operation of an automatic life safety fire suppression 3.7 Wastewater drainage
system. Every wastewater drainage system serving a building to be
designed and constructed to ensure removal of wastewater from
Limitation building without threatening health and safety of people in and
Only applies to enclosed shopping centres, residential care build- around the building and: (a) provide facilities for separation and
ings, high-rise domestic buildings, or whole or part of sheltered removal of oil, fat, grease, and volatile substances; (b) where
housing complex. reasonably practicable, discharge to be to public sewer or public
wastewater treatment plant and, where not, to a private waste-
Section 3: environment water treatment plant or septic tank.
(standards 3.1–3.26) Limitation
In Standards 3.1–3.4 and 3.10–3.26, every building (every Facilities for separation and removal of oil, fat, grease, and
dwelling in the case of Standard 3.11) must be designed and volatile substances not required for dwellings.
Building (Scotland) Regulations 2004 and subsequent amendments 117

3.8 Private wastewater treatment 3.17 Combustion appliances


systems – treatment plants – safe operation
Every private wastewater treatment plant or septic tank serv- Each fixed combustion appliance installation is to operate safely.
ing a building must be designed and constructed to ensure the
safe temporary storage and treatment of wastewater prior to
discharge.
3.18 Combustion appliances – protection
from products of combustion
3.9 Private wastewater treatment Any component part of each fixed combustion appliance instal-
systems – infltration systems lation shall withstand heat generated from its operation without
any structural change impairing the stability or performance of
Every private wastewater treatment system serving a building the installation.
must be designed and constructed so that the disposal of waste-
water to ground is safe and is not a threat to the health of people
in and around the building. 3.19 Combustion appliances
– relationship to
3.10 Precipitation combustible materials
There is not to be a threat to the building or the health of occu- Any component part of each fixed combustion appliance installa-
pants from moisture due to precipitation penetrating to inner tion not to cause damage to the building in which it is installed
face of the building. by radiated, convected, or conducted heat, or from hot embers
expelled from the appliance.
Limitation
Not applicable where effects of moisture penetration from out- 3.20 Combustion appliances – removal
side are no more harmful than effects from building use.
of products of combustion
The products of combustion to be carried safely to the external
3.11 Facilities in dwelling air without harm to the health of any person through leakage,
The size of any apartments or kitchen is to ensure the welfare spillage, or exhaust, and not to permit the re-entry of dangerous
and convenience of all occupants and visitors, and an accessible gases from the combustion process of fuels into the building.
space is provided to allow safe, convenient, and sustainable dry-
ing of washing.
3.21 Combustion appliances –
Limitation air for combustion
This standard only applies to dwellings. Every fixed combustion appliance installation to receive air for
combustion and the chimney to operate so that the health of
3.12 Sanitary facilities persons within the building is not threatened by the build-up of
dangerous gases as a result of incomplete combustion.
Sanitary facilities to be provided for all occupants of, and visi-
tors to, the building, allowing convenient use with no threat to
the health and safety of occupants or visitors. 3.22 Combustion appliances
– air for cooling
3.13 Heating Every fixed combustion appliance installation to receive air for
The building to be capable of being heated and maintain heat cooling so that it will operate safely without threatening the
at temperature levels that will not threaten the health of the health and safety of persons within the building.
occupants.

Limitation
3.23 Fuel storage – protection from fre
This standard only applies to dwellings. Every oil storage installation, incorporating oil storage tanks
used solely to serve a fixed combustion appliance installation
providing space heating or cooking facilities in a building, or
3.14 Ventilation each container for the storage of woody biomass fuel, to inhibit
The air quality within the building is not to be a threat to the fire from spreading to the tank, or to the container, and its con-
health of the occupants or to the capacity of the building to resist tents from within, or beyond, the boundary.
moisture, decay, or infestation.
Limitation
This standard does not apply to portable containers.
3.15 Condensation
There is not to be a threat to the building or the health of the
occupants due to moisture caused by surface or interstitial
3.24 Fuel storage – containment
condensation. The volume of every woody biomass fuel storage to be such
as to minimise the number of delivery journeys and every oil
Limitation storage installation, incorporating oil storage tanks used solely
This standard only applies to dwellings. to serve a fixed combustion appliance installation providing
space heating or cooking facilities in a building, to reduce
the risk of oil escaping from the installation, contain any oil
3.16 Natural lighting spillage likely to contaminate any water supply, groundwater,
Natural lighting to be provided to ensure that the health of occu- watercourse, drain, or sewer, and permit any spill to be dis-
pants is not threatened. posed of safely.

Limitation Limitation
This standard only applies to dwellings. This standard does not apply to portable containers.
118 Building Regulations in Scotland

3.25 Solid waste storage 4.6 Electrical fxtures


Accommodation for solid waste storage provided, which permits Electric lighting points and socket outlets are to be provided
access for storage and for the removal of its contents and does to ensure health, safety, and convenience of occupants of, and
not threaten the health of people in or around the building or visitors to, the building.
contaminate any water supply, ground, or surface water.
Limitation
Limitation Standard applies only to domestic buildings where electricity
This standard applies only to a dwelling. is available.

3.26 Dungsteads and farm effuent tanks 4.7 Aids to communications


There not to be a threat to the health and safety of people from Every building is to have aids to assist those with hearing
the construction or location of dungsteads or effluent tanks. impairment.

Limitation
Section 4: safety This standard does not apply to domestic buildings.
The standards in this section require every building to be
designed and constructed so that the requirements set out below
are met.
4.8 Danger from accidents
Standards 4.1 and 4.2 provide enhanced access rela- People in and around the building are to be protected from injury
tive to buildings and within buildings, both domestic and caused by fixed glazing, projections, or moving elements on the
non-domestic. building; fixed glazing is not to be vulnerable to breakage where
there is a possibility of impact by people in or around the build-
ing, both faces of windows and rooflights are to be cleanable
4.1 Access to buildings without threat to cleaner of severe injury from a fall; safe and
All occupants and visitors to be provided with safe, convenient, secure access to roof and safe operation of manual controls for
and unassisted means of access to the building. ventilation and electrical fixtures are required.

Limitation Limitation
No need for wheelchair access to the entrance of a single house Provision of safe and secure access to roof does not apply for
where not practicable to do so, or to a common entrance of a domestic buildings.
domestic building, without a lift, where no dwelling entered off
that entrance storey. 4.9 Danger from heat
Protection is to be provided for people in or around the building
4.2 Access within buildings from the danger of severe burns or scalds from the discharge of
In non-domestic buildings, safe, unassisted, and convenient steam or hot water.
access is to be provided throughout; in residential buildings,
wheelchair access is also to be provided to a proportion of bed- 4.10 Fixed seating
rooms; in domestic buildings, safe and convenient access is to
be provided within common areas and to each dwelling; and in Where there is fixed seating for an audience or spectators, a
dwellings, safe and convenient means of access to be provided number of level spaces for wheelchairs to be provided propor-
throughout, and unassisted access to, and throughout, at least tionate to the potential audience or spectators.
one level.
Limitation
Limitation This standard does not apply to domestic buildings.
No need for wheelchair access to bedrooms not on entrance
storey in non-domestic building without lift, or to dwellings on 4.11 Liquifed petroleum gas storage
upper storeys of a building without a lift.
Every liquified petroleum gas storage installation, used solely to
serve a combustion appliance providing space, or water heating,
4.3 Stairs and ramps or cooking, is to be protected from fire spreading to any liquified
Every level to be reached safely by stairs or ramp. petroleum gas container and not to permit the contents of any
such container to form explosive gas pockets in the vicinity of
any container.
4.4 Pedestrian protective barriers
Every sudden change of level that is accessible in, or around, the Limitation
building is guarded by pedestrian protective barriers. Not applicable to such storage used with portable appliances.

Limitation 4.12 Vehicle protective barriers


Standard does not apply where guarding would obstruct the use
of the area so guarded. Every building accessible to vehicular traffic should have every
change in level guarded.

4.5 Electrical safety Sections 5: noise


The electrical installation is not to threaten the health and safety
in or around the building, or to become a source of fire. 5.1 Resisting sound transmission
to dwellings using appropriate
Limitation constructions
Not applicable for installations for buildings covered by Mines
and Quarries Act 1954, Factories Act 1961, or for works of Every building must be designed and constructed in such a
undertakers covered by the Electricity Act 1989. way that each wall and floor separating one dwelling from
Building (Scotland) Regulations 2004 and subsequent amendments 119

another, or one dwelling from another part of the building, or Limitation


one dwelling from a building other than a dwelling, will limit Not to apply to process and emergency lighting, communal areas
the transmission of noise to the dwelling to a level that will of domestic buildings, or alterations in dwellings.
not threaten the health of the occupants of the dwelling or
inconvenience them in the course of normal domestic activities, 6.6 Mechanical ventilation
provided the noise source is not in excess of that from normal
domestic activities. and air conditioning
The form and fabric of the building to minimise use of mechani-
Limitation cal ventilation or cooling systems for cooling and, in non-
Not to apply to fully detached houses, roofs, or walkways with domestic buildings, installed ventilation and cooling systems,
access solely for maintenance, or solely for the use, of the resi- are energy efficient and capable of being controlled to achieve
dents of the dwelling below. optimum energy efficiency.

Section 6: energy Limitation


Not to apply to buildings not using fuel or power for ventilating
The main changes to this section arise due to the implementation or cooling internal environment.
of the Energy Performance of Buildings Directive.
6.7 Commissioning building services
6.1 Carbon dioxide emissions
Energy supply systems and building services, which use fuel or
Energy performance is to be calculated with methodology, which power for heating, lighting, ventilation, and cooling the internal
is asset based, conforms with Energy Performance of Buildings environment, and for heating water, are to be commissioned to
Directive, and uses UK climate data, and that energy perfor- achieve optimum energy efficiency.
mance is capable of reducing CO2 emissions.
Limitation
Limitation Not to apply to major power plants serving National Grid, process
Not to apply to alterations and extensions, conversions, stand- and emergency lighting components, heating solely for frost protec-
alone buildings (non-domestic and ancillary to domestic) of less tion, or energy supply systems used solely for industrial and com-
than 50m2, not heated (other than for frost protection) or cooled mercial processes, leisure, and emergency use within a building.
buildings, or buildings with intended life of under two years.
6.8 Written information
6.2 Building insulation envelope Occupiers of the building are to be provided with written
Insulation envelope is to be provided to reduce heat loss. information by the owner on operation and maintenance of
building services and energy supply systems and, where any
Limitation air-conditioning system is subject to Regulation 17 (continuing
Not to apply to non-domestic buildings, communal parts of requirements relative inspection and provision of advice relative
domestic buildings; and buildings ancillary to dwellings (other to air-conditioning systems), stating a time-based interval for
than conservatories), which are not heated (other than for frost inspection of the system.
protection).
Limitation
Not to apply to major power plants servicing the National Grid,
6.3 Heating system buildings not using fuel or power for heating, lighting, ventilat-
The installed heating and hot water service systems are to be ing, and cooling the internal environment and heating the water
energy efficient and capable of being controlled for optimum supply services, the process and emergency lighting components
energy efficiency. of a building, heating solely for frost protection, lighting, ven-
tilation and cooling systems in domestic building, and energy
Limitation systems used solely for industrial and commercial processes,
Not to apply to buildings where fuel or power is not used leisure use, and emergency use within a building.
for controlling internal environment temperature or heating is
provided only for frost protection, or to secondary heating in 6.9 Energy performance certifcates
domestic buildings provided by individual solid fuel or oil-
fired stoves or open fires, gas or electric fires, or room heaters An energy performance certificate (EPC) for the building is to be
(excluding electric storage or panel heaters). affixed to the building. The EPC is to be defined in The Energy
Performance of Buildings (Scotland) Regulations as amended.
The energy performance certificate is to be displayed in a promi-
6.4 Insulation of pipes, ducts, and vessels nent place within the building.
Temperature loss from heated pipes, ducts, and vessels and tem-
perature gain to cooled pipes and ducts to be resisted. Limitation
Not to apply to buildings not using fuel or power for controlling
Limitation temperature of internal environment or non-domestic buildings
Not to apply to buildings not using fuel or power for heating and stand-alone buildings ancillary to dwellings of less than
or cooling of internal environment or water services, unheated 50m2 area or conversions, alterations and extensions with an
parts or whole buildings (other than for frost protection), area of less than 50m2, or buildings with intended life of less
pipes, ducts, or vessels forming part of an isolated industrial than two years. The obligation to prominently display the EPC
or commercial process, and cooled pipes or ducts in domestic is to apply only to buildings, which can be visited by the public,
buildings. of floor area over 1000 m2 occupied by public authorities, and
institutions providing public services.
6.5 Artifcial and display lighting
6.10 Metering
The artificial or display lighting installed is energy efficient
and capable of being controlled to achieve optimum energy Each part of a building designed for different occupation is to
efficiency. be fitted with fuel consumption meters.
120 Building Regulations in Scotland

Limitation ● The Building (Scotland) Amendment Regulations 2015.


Not to apply to domestic buildings, communal areas of build- ● The Building (Scotland) Amendment Regulations 2014.
ings in different occupation, or district or block heating systems ● The Building (Scotland) Amendment Regulations 2012 (SSI
(where each of the parts designed for different occupation are 2012/209).
fitted with heat meters), or heating fired by solid fuel or biomass. ● The Building (Scotland) Amendment Regulations 2011.
● The Building (Scotland) Amendment Regulations 2010.
● The Building (Scotland) Amendment Regulations 2009.
Technical Handbooks ● The Building (Scotland) Amendment Regulations 2008.
6.09 There are two Technical Handbooks, one covering domes- ● The Building (Scotland) Amendment Regulations 2007.
tic buildings (as defined in the building regulations) and one ● The Building (Scotland) Amendment Regulations 2006.
covering non-domestic buildings (that is all buildings which ● The Building Standards Advisory Committee (Scotland)
are not domestic). There is also the Guide for Practitioners – Regulations 2004.
Conversion of Traditional Building, issued by Historic Scotland, ● The Building (Scotland) Regulations 2004.
and guidance on conservatories produced by BSD, which have
already been mentioned. The Technical Handbooks, the Guide Building (Scotland) Procedural
for Practitioners, and the guidance on Conservatories are issued
by Scottish Ministers under section 4(4) of the Act to provide ● The Building (Miscellaneous Amendments) (Scotland)
practical guidance with regard to the requirements of the build- Amendment Regulations 2017.
ing regulations, and their status is as set out in sections 4 and ● The Building (Miscellaneous Amendments) (Scotland)
5 of the Act, as discussed above. Regulations 2017.
● The Building (Miscellaneous Amendment) (Scotland)
Regulations 2013.
7 Other national legislation ● The Building (Scotland) Amendment Regulations 2011.
affecting building ● The B uilding (Proc e dure ) (Sc otla nd) A me n dm ent
Regulations 2009.
7.01 A building warrant and planning consent are normally ● The B uilding (Proc e dure ) (Sc otla nd) A me n dm ent
required before most construction work. However, they are not Regulations 2007.
necessarily the only statutory consents required. There is a wide ● The Building (Procedure) (Scotland) Regulations 2004.
range of statute covering construction, some requiring licences,
others requiring only compliance, and some only relevant Building (Fees)
when the construction is operated for a particular purpose. It
is therefore important to understand to what use any particular ● The Building (Fees) (Scotland) Amendment Regulations
construction is to be put, as it is not much use constructing a 2008.
building which complies with the building regulations if it can- ● The Building (Fees) (Scotland) Amendment Regulations
not be put to the use for that which it was designed. The list 2007.
below (although not completely exhaustive) applies in Scotland. ● The Building (Fees) (Scotland) Regulations 2004.

7.02 Certain legislation is mentioned in the Technical Handbooks Building (Forms)


as relevant to the standards set out in the appropriate section of
Schedule 5 to the Building Regulations. The web version and ● The Building (Miscellaneous Amendments) (Scotland)
the CD-ROM version, when read on a computer connected to Amendment Regulations 2017.
the internet, both have hypertext links to copies of the relevant ● The Building (Miscellaneous Amendments) (Scotland)
legislation. Regulations 2017.
● The Building (Miscellaneous Amendment) (Scotland)
Regulations 2013.
8 Building standards in Scotland: ● The Building (Scotland) Amendment Regulations 2011.
current legislation ● The Building (Forms) (Scotland) Amendment Regulations
2007.
Building (Scotland) Act ● The Building (Forms) (Scotland) Amendment Regulations
2006.
● The Building (Scotland) Act 2003 (Charging Orders) ● The Building (Forms) (Scotland) Regulations 2005.
Regulations 2014.
● The Buildings (Recovery of Expenses) (Scotland) Act 2014. Energy Performance Regulations
● The Building (Scotland) Act 2003 (Commencement No.
2 and Transitional Provisions) Order 2009. ● The Building (Energy Performance of Buildings) (Scotland)
● The Building (Scotland) Act 2003 (Exemptions for Defence Amendment Regulations 2016.
and National Security) Order 2009. ● The Energy Performance of Buildings (Scotland) Amendment
● The Building (Scotland) Act 2003 (Commencement No. 1, Regulations 2013.
Transitional Provisions and Savings) Order 2004. ● The Energy Performance of Buildings (Scotland) Amendment
● The Building (Scotland) Act 2003. (No. 3) Regulations 2012.
● The Energy Performance of Buildings (Scotland) Amendment
Building (Scotland) Regulations Regulations 2012 (SSI 2012/190).
● The Energy Performance of Buildings (Scotland) Amendment
● The Building (Miscellaneous Amendments) (Scotland) (No. 2) Regulations 2012 (SSI 2012/208).
Amendment Regulations 2017. ● The Energy Performance of Buildings (Scotland) Regulations
● The Building (Miscellaneous Amendments) (Scotland) 2008.
Regulations 2017. ● The Energy Performance of Buildings (Scotland) Amendment
● The Building (Miscellaneous Amendment) (Scotland) Regulations 2008.
Regulations 2013. ● The Energy Performance of Buildings (Scotland) Amendment
● The Building (Scotland) Amendment Regulations 2016. (No 386) Regulations 2015.
11
Planning law in England and Wales
ANDREW FRASER-URQUHART QC

Note arising out of the use of the land for a particular purpose. The
essential exercise in planning judgement is to properly assess
Throughout this chapter, the Town and Country Planning Act the weight to be given to all these different factors when arriv-
1990 is referred to as ‘TCPA 1990’. ing at the fundamental judgement as to whether or not planning
permission ought to be granted.

1 Introduction The Main Acts


1.01 Town and country planning control over the development 1.03 Following major reforms in 2004, there are now two prin-
of all land (including buildings) in England and Wales is an cipal Acts on the subject. The first is TCPA 1990. It contains
administrative process deriving from the Town and Country 337 sections (although some are now only to be referred to as
Planning Act 1947. See Chapter 12 for the position in Scotland. part of the transitional process to the procedure in the 2004 Act)
It has operated since 1 July 1948, and was brought about (to and 17 Schedules and came into operation on 24 August
mention no other matter), for the simple reason that in England 1990. Associated with this principal Act are three further Acts
and Wales, there is a limited amount of land for an increasing related to planning, namely the Planning (Listed Buildings
number of people who wish to live and work upon it and who, and Conservation Areas) Act 1990, the Planning (Hazardous
increasingly, call for more space both for working and for lei- Substances) Act 1990, and the Planning (Consequential
sure. Thus, the pressure on a limited amount of land is great, Provisions) Act 1990. These four Acts are defined (TCPA 1990,
and is getting greater. section 336(l)) as ‘the Planning Acts’.
The reader should also be aware that, as well as the major
1.02 By way of the most basic introduction, activity which changes brought about in 2004, the Planning and Compensation
falls within the definition of ‘development’ requires planning Act 1991 also amended the TCPA 1990. It is therefore impera-
permission. Unless the ‘development’ in question falls into tive to consult an appropriate loose-leaf or online resource to
a defined class for which that permission is deemed to be see TCPA 1990 as it currently stands, rather than the original
granted, the way in which planning permission is obtained in Queen’s Printer’s version.
England and Wales is described as ‘plan-led’. For each area, After a very long gestation period, from 1997, in 2004,
there is something known as the development plan (which, Parliament enacted the Planning and Compulsory Purchase
confusingly enough, does not consist of a single document Act 2004. This introduced major reforms into the system of
or plan, but instead, of an interlocking series of documents ‘development plans’, but left broadly unchanged the fundamen-
and plans). By law, applications for planning permission must tal principles by which the content of those development plans
be decided in accordance with that development plan ‘unless bears upon the decision about whether or not to grant planning
material considerations indicate otherwise’. ‘Material consid- permission for any particular development.
erations’ can consist of any matter which properly relates to
the desirability, in land use terms, of permitting a particular 1.04 Planning control over land development is rooted in central
development. They may, for example, consist of statements government policy. Accordingly, attention is drawn to the vari-
of central government planning policy. Equally, they might ous statements of that policy. They are contained in a published
consist of the fact that a development which would be con- document, the National Planning Policy Framework, and an
trary to the development plan would nevertheless bring about online resource, the National Planning Practice Guidance. In
some particular benefit in terms of, say, the improvement of Wales, central government advice is provided by the Planning
the environment, or the creation of jobs, or any such matter Policy Wales document.

121
122 Planning law in England and Wales

Planning control process which form at least part of the development plan. The architect
must also be able to identify any policies which are ‘saved’, for
1.05 As noted above, the planning control process is a two- the time being, from the old system of county structure plans
part process involving, on the one hand, the making of devel- and local plans. It is also imperative to identify the ‘emerging’
opment plans (that is, blueprints for the future) that seek to policy documents which may carry considerable weight in the
show what the state of affairs will be when all foreseeable planning process, even though they have not completed the com-
development (or non-development) in the area covered by the plicated formal statutory process of adoption. Fortunately, this
plan has been achieved. The other prong of the process is the information is usually readily available from either the planning
day-to-day control over the carrying out of development through department of the relevant local authority or from its website.
the medium of a grant or a refusal of planning permission for It is assumed for the purpose of this chapter that all the
development. All this is a highly simplified statement of the requisite development plan documents and saved policies have
entire complicated and sophisticated process of town planning been identified and are in operation. Accordingly, attention in
control as it functions today. succeeding paragraphs is given to the day-to-day process of
development control through the medium of grants or refusals
1.06 In the ultimate analysis, all this control is done by the min- of planning permission for development.
ister for town and country planning, by whatever name he or she
may be known. At the moment, ‘he’ is known as the Secretary
of State for Housing, Communities and Local Government, but 1.08 Moreover, it should be made clear at the start that this chap-
this does not alter the fact that one minister of the Crown is, by ter is written primarily for the guidance of architects; it is delib-
law, rendered responsible, ultimately, for the way in which all erately slanted in the direction of architects. An effort has been
town planning control is carried out in England and Wales. For made to pick out from the surging cauldron of town planning
his actions, he is answerable to Parliament. Thus the control is controls some of the more important controls, and particularly
exercised, in the ultimate analysis, in accordance with the town those that would affect an architect seeking to organise develop-
and country planning policies of the central government for the ment on behalf of a client. Thus the chapter does not purport to
time being in power at Westminster. deal with control over advertisements, caravans, mineral work-
ings, or hazardous substances.
1.07 In this chapter, no attention is given to the first prong of
the process, namely the making, approving, and bringing into 1.09 Accordingly, there will be found in succeeding paragraphs
operation of development plans. The 2004 Act was primarily a brief statement on local planning authorities (paragraphs 2.08
aimed at improving the system by which this came about. The onwards) and what they can do when faced with an applica-
architect must, however, be able to identify which of the suite tion for planning permission for development (paragraph 4.11).
of local authority documents are those known as ‘Development Development itself is treated in some detail (paragraph 3.01)
Plan Documents’. As the name suggests, those are the documents though, maybe, not in all the detail into which the expression
Local planning authorities; or who is to deal with planning applications? 123

breaks up once it is investigated. The method of making plan- (a) a national park declared under the National Parks and
ning applications is dealt with, as are the consequences of a Access to the Countryside Act 1949;
refusal or a grant of permission subject to conditions (paragraph (b) an area of outstanding natural beauty (‘AONB’) declared
4.04). Special reference is made to buildings of special architec- under the same Act of 1949;
tural or historic interest (paragraph 5.01) because these are mat- (c) an area designated as a conservation area under
ters which, although standing outside the main stream of town section 69 of the Planning (Listed Buildings in
planning control, are nevertheless highly important matters to a Conservation Areas) Act 1990;
developer and to any architect advising it. (d) an area specified for the purposes of the Wildlife and
There is a brief reference (paragraph 6.01) to the special con- Countryside Act 1981, section 41(3);
cepts in the planning field of urban development areas and cor- (e) the Broads as defined in the Norfolk and Suffolk Broads
porations, and of simplified planning zones. There is reference Act 1988; and
to the enforcement of planning control over the development of (f) a World Heritage Site.
land (paragraph 7.01) or, in other words, there is a statement 2 comprise ‘or ‘Article 2(4) land’ (as defined in Article 2(4)
on what happens if a person does indeed carry out development GPO 2015) which land includes:
without getting the appropriate planning permission in advance. (a) land in a National Park;
(b) in the Norfolk and Suffolk Broads (as defined above);
1.10 The length of this chapter has been limited. This means and
that it has not been possible in every instance to put in all the (c) in land outside a national park but within an area
qualifications, exceptions, reservations, and so forth which, in a (specified in Article 2(4)) as set out in paragraph 2(2)
more categorical statement, would necessarily be appended to of Schedule 1, Part 3, of the aforesaid 2015 Order.
the general statements set out in the paragraphs which follow.
If the development site is on Article 2(3) land or Article 2(4)
land, then the amount of ‘permitted development’ (see paragraph
2 Local planning authorities; 2.06) allowed on the site is constricted by the GPO 2015. Copies
or who is to deal with of the GPO 2015 are obtainable online (see paragraph 2.02). Any
such land falls within what are nowadays called ‘sensitive areas’,
planning applications? and the relaxation of development control brought about by the
General Development (Amendment) Order 1981 was denied to
2.01 The first thing an architect seeking to carry out development them – and is still denied to them by the GPO 2015.
must do is to inspect the site of the proposed development. It is
most important nowadays to discover: 2.06 Fifth, the architect must ascertain whether the development
site is in an Urban Development Area (see paragraph 6.02);
1 whether it is a cleared site; or in an Enterprise Zone (see paragraph 6.10); or in a Simplified
2 whether it contains a building and, if it does, whether that Planning Zone (see paragraph 6.14). If the site is in any one of
building is a building of special architectural or historic these areas or zones, then the normal constraints of development
interest (see paragraph 5.01). control (e.g. the need to obtain, from a local planning authority,
planning permission for development (see paragraph 2.10) are
2.02 Second, the architect must consider carefully the definition relaxed (see paragraphs 6.01, 6.11, and 6.14).
of ‘development’ in TCPA 1990 (section 55) and the possible
effect of the Town and Country Planning (Use Classes) Order 2.07 All these are preliminary matters about which the archi-
1987 (SI 1987 No. 764) (‘the 1987 Order’). Many building tect should become fully informed at the outset. In this chapter
operations and changes of use do not constitute development, by it will be assumed, for the moment, that the architect is dealing
virtue of the definitions and provisions of this section and the with a cleared site (or, at least, a site not containing anything
1987 Order. If they do not, then nothing in the Planning Acts in the nature of a special building), and that the development
applies to them. ‘Development’ is considered in paragraph 3.01 he or she wishes to carry out is development that can be dealt
below. Copies of the 1987 Order and its two amending orders with under the general run of town planning control and does
of 1992 (SI 1992 Nos 610 and 657) are available at http://www. not attract any additional, i.e. special, control. (The special
legislation.gov.uk/. control over development which is going to occupy the site
of an existing building of architectural or historic interest
2.03 Third, the architect must examine closely the type of devel- is dealt with later.) For the moment, it is assumed that the
opment which is sought to be carried out. Is it development development which the architect is considering is a straight-
which can be dealt with in the normal run of planning control, forward building development not subject to any special form
or will it be subject to some additional control over and above of control, but only to general town planning control under
the normal run? It certainly will be if it happens to be develop- TCPA 1990.
ment of land occupied by a building of special architectural or
historic interest (paragraph 5.01) which has been listed by the
Secretary of State. Which authority?
2.08 This being the case, the next thing which the architect must
2.04 Fourth, the architect must investigate, generally, the consider is the local government authority to whom the applica-
Town and Country Planning (General Permitted Development) tion for planning permission is to be made. It must be made to
(England) Order 2015 (SI 2015/596) (‘GPO 2015’). It will be the local planning authority.
necessary to do this sort of investigation in order to ascertain
whether the development is ‘permitted development’ under the 2.09 The local government system in England and Wales was
GPO 2015 because, if it is, it gets automatic planning permis- completely reorganised as from 1 April 1974 under the provision
sion, and there is no need to make any application to a local of the Local Government Act 1972. It was further reorganised
planning authority (see paragraph 4.02). as from 1 April 1986 by the Local Government Act 1985, which
abolished the Greater London Council and the six metropolitan
2.05 When considering the GPO 2015, the architect must satisfy county councils (but not the metropolitan counties themselves)
himself whether the site for the development does, or does not: of Greater Manchester, Merseyside, South Yorkshire, Tyne and
Wear, West Midlands, and West Yorkshire respectively. The most
1 comprise ‘Article 2(3) land’ (as defined in Article 2(3) and recent change was the introduction in the mid-1990s of a series
paragraph 1 of Schedule 1 GPO 2015), which land includes of ‘unitary’ authorities that took the functions of both district
land within: and county council in their areas.
124 Planning law in England and Wales

2.10 After all the foregoing reorganisations, the system (outside appropriate parts of these provisions to the matter in hand to
Greater London) provided for local government to be discharged ascertain if that which it is sought to do is, in law as well as in
either at three separate tiers, namely: fact, development.

1 by 34 non-metropolitan county councils popularly called 3.02 Putting the matter quite briefly, development consists of:
‘shire’ county councils;
2 by 264 district councils (36 metropolitan district councils if 1 the carrying out of operations (that is to say, building, min-
they happen to be in a metropolitan county and 238 ‘shire’ ing, engineering, or other operations); or
district councils if they happen to be in a ‘shire’ county) 2 the making of any material change in the use of land
some of which have borough status; and (including buildings on land).
3 by parish councils;
or by one of the 47 Unitary Authorities. It will be seen that the big cleavage in the definition is between
the carrying out of operations, on the one hand, and the making
2.11 In Greater London, local government is carried out by each of a material change of use, on the other.
of the 32 London borough councils plus the Corporation of the
City of London. These authorities are the local planning author- What is an operation?
ity for their borough, but the Greater London Authority has the
right to be consulted on major applications and has the right, 3.03 If the definition of what constitutes development is
in certain circumstances, to direct that planning permission be important, it may be said that the definition of what does not
refused on such major applications in the event the application constitute development is equally important. Section 55 TCPA
conflicts with the mayor’s strategic policies. 1990 contains quite a list of operations and uses which do not
amount to development. If that which the architect seeks to do
2.12 The county councils and the district councils and the uni- falls within this particular list, then he or she need worry no
tary councils are all local planning authorities, and thus current more about TCPA 1990 or any part of it. In particular, purely
nomenclature speaks of the ‘county planning authority’, the internal works or works which do not materially affect the exter-
‘district planning authority’, and the ‘unitary planning author- nal appearance of a building are not development (remembering,
ity’. A purchaser or a developer of land must, at the very start, of course that this exception most definitely does not apply to
ascertain which is the local planning authority for the purpose Listed Buildings!).
of whatever it wishes to do.
What is a change of use?
2.13 All applications for planning permission will go to the
district planning authority or the unitary planning authority 3.04 The list of specific exceptions in section 55 of TCPA
except (in the area of a shire district council) when the applica- 1990 must be read with the 1987 Order, which contains
tion relates to a ‘county matter’ (see TCPA 1990, Schedule 1, 15 classes of use. If that which the architect seeks to do is, in
paragraph 1) in which event the application is to be made to the fact, a material change of use, then if the existing use is any one
shire county council (see paragraph 2.14). of those specified in the 1987 Order, and if the change of use
will still leave the use within the same use-class, the proposed
2.14 The instances of ‘county matters’ when, in a shire county, change of use will not, in law, constitute development. In short,
the application for planning permission goes in the first place a use may switch around without planning permission, provided
not to the district planning authority but to the county planning its total manoeuvring does not take it out of its use-class as set
authority, are (TCPA 1990, Schedule 1, paragraph 1): out in the 1987 Order.

1 applications relating to mineral mining, working, and devel- 3.05 However, since the case of City of London Corporation
opment (including the construction of cement works) (TCPA v Secretary of State for the Environment and Watting Street
1990, Schedule 1, paragraph 1(1)(a)–(h) inclusive); Properties Ltd (1971) 23 P and CR 169, it is clear that, on grant-
2 applications relating to development straddling the bound- ing planning permission, a local planning authority may impose
ary of a national park (TCPA 1990, Schedule 1, paragraph such conditions as would prevent any future change of use, not-
1(1)(i)); and withstanding that any such change would not constitute devel-
3 applications in England relating to waste disposal matters opment of land by virtue of the provisions of the 1987 Order
(TCPA 1990, Schedule 1, paragraph 1(1)(j)) and Town and section 55(2)(f) of TCPA 1990. In effect, the local planning
and Country Planning (Prescription of County Matters) authority may remove from a developer the right to make a
(England) Regulations 2003 (SI 2003 No. 1033) which does change of use, even if that change of use would not normally
not apply to Greater London. (because of the Use Classes Order) need planning permission.

2.15 Parish councils are not local planning authorities, but, even 3.06 For the purpose of removing all doubt, section 55(3) of
so, have the right (if they have claimed it) to be consulted by the TCPA 1990 specifically states that merely using a single dwell-
district council about planning applications for development fall- ing house as two or more separate dwelling houses does involve
ing within the area of the parish council (TCPA 1990, Schedule making a material change of use, and it is ‘development’ needing
1, paragraph 8). planning permission before it can take place. Thus, the architect
may carry out, at ground level or above, internal building opera-
2.16 In Greater London, the 32 London boroughs (each for tions (not affecting the exterior elevations) on a single house in
its own borough) with the Common Council (for the City order to adapt it for use as two houses. Such building operations
of London) are all local planning authorities (TCPA 1990, will not need planning permission. However, when it comes to
section 1(2)). inaugurating the use of the former single house as two houses,
this change of use will call for planning permission, which may
or may not be granted.
3 The meaning of ‘development’
3.07 If the architect has any doubts as to whether that which
3.01 The question as to whether that which the architect seeks to the client seeks to do is or is not ‘development’, he or she can
carry out is or is not development is a potentially difficult one. apply (1990 Act, section 192) to the local planning authority for
The meaning of ‘development’ is defined in section 55 TCPA a certificate of lawfulness relating to any proposed use or devel-
1990, and it is a question of taking the relevant provisions of opment of land. Such a certificate relating to any existing use
this Act, working carefully through them, and then applying the or development can be made under section 191 of TCPA 1990.
Control of development in general 125

In either case, there is a right of appeal to the Secretary of State 11 A to C Heritage and demolition
for Housing, Communities and Local Government (hereinafter 12 A to B Development by local authorities
referred to as ‘the Secretary of State’) against the decision of 13 A to D Water and sewage
the authority (TCPA 1990, section 195). 14 A to O Renewable energy
15 A to B Power-related development
16 A to E Communications
4 Control of development in general 17 A to M Mining and mineral exploration
18 A to B Miscellaneous development (under private Acts or
4.01 Once the architect is satisfied that that which is sought to be at amusement parks)
done is indeed development, but is not an Enterprise Zone (see 19 A to T Development by the Crown or for national security
paragraphs 6.09–6.11 of this chapter) nor a Simplified Planning purposes
Zone (see paragraphs 6.12–6.15 of this chapter), he or she must
next ascertain whether it falls within the privileged category of
‘permitted development’. This will require investigation of the Other than permitted development
GPO 2015.
– the planning application
Permitted development 4.04 If the proposed development does not fall within any of
the classes of permitted development above mentioned, then a
4.02 The GPO 2015 contains a number of separate classes of formal application for planning permission will need to be made
development which are categorised as permitted development, (section 57 TCPA 1990). Sections 58 and 62 TCPA 1990 require
that is, they comprise development for which a grant of plan- an application for planning permission for development to
ning permission is automatically given by virtue of the GPO be made in accordance with the Town and Country Planning
2015 itself (TCPA 1990, sections 58, 59 and 60). If development (Development Management Procedure) (England) Order 2015
falls within any one of these classes of permitted development, (SI 2015 No. 585) (‘DMP Order 2015’). The requisite form on
there is no need to make any application to any local planning which the application is lodged can be obtained from the local
authority for planning permission for the development. If the planning authority.
development is not permitted development, then a formal appli-
cation must be made (TCPA 1990, sections 58 and 62). 4.05 When making an application for planning permission
for development, reference must further be made to the Town
4.03 It is to be stressed that the GPO 2015 is a most important and Country Planning (Environmental Impact Assessment)
document, particularly for smaller scale development where Regulations 2017 (SI 2017 No. 571). These regulations provide,
the architect may be advising without the benefit of a specialist in broad terms, that if a development is likely to have significant
planning consultant or solicitor. The classes of permitted devel- environmental impacts (a term which includes such matters as
opment are spread across 19 Parts in Schedule 2 GPO 2015, as the effect on the landscape, or on air quality, or on ecology) the
follows: planning application cannot be decided until the local planning
GPO 2015 authority has received and assessed so-called ‘Environmental
Information’. This must include an Environmental Statement,
prepared by the developer, which sets out the nature of the
Part Class Permitted development development, the effect it is likely to have, and the measures
1 A Development within the curtilage of a dwelling which are proposed to deal with such effects.
house. The enlargement, improvement, or other A failure to comply with these regulations (which are detailed
alteration of a dwelling house and complex) will render any planning permission liable to be
1 B The enlargement of a dwelling house consisting of quashed by the High Court on an application for judicial review.
an addition or alteration to its roof Such a legal challenge is an obvious tactic for person opposed to a
1 C Any other alteration to the roof of a dwelling development. While the regulations are most likely to be ‘in play’
house in a large development when the architect may well be part of a
1 D The erection or construction of a porch outside any team advising the developer, even a smaller-scale development
external door of a dwelling house with particular effects may trigger the application of the regula-
1 E The provision within the curtilage of a dwelling tions. Furthermore, the architect will need to be aware of the
house, of any building or enclosure, swimming effects of the Conservation of Habitats and Species Regulations
or other pool required for a purpose incidental 2017 (SI 2017 No. 1012) (‘Habitats Regulations 2017’) which
to the enjoyment of the dwelling house, or the impose particular controls on development which have a signifi-
maintenance, improvement, or other alteration of cant effect on the habitat of particular protected species.
such a building or enclosure
1 F The provision within the curtilage of a dwelling 4.06 Although the application for planning permission will for-
house of a hard surface for any purpose incidental mally be made to a local planning authority, it will often be the
to the enjoyment of the dwelling house case that a good deal of ‘negotiation’ relating to the application
1 G The installation, alteration, or replacement of a will take place between the applicant’s architect and officers of
chimney, flue, or soil and vent pipe on a dwelling the local planning authority.
house
1 H The installation, alteration, or replacement of a 4.07 Case law from the House of Lords (see R v East Sussex
satellite antenna on a dwelling house or within the County Council ex p. Reprotech (Pebsham) Ltd [2002] UKLR
curtilage of a dwelling house, subject to a limit of 8) makes plain, however, that it is almost impossible for the
two such antennas discussions with a planning authority during such negotiations
2 A to F Minor operations to be binding on the local planning authority when the formal
3 A to V Changes of use decision comes to be made. Nevertheless, such discussions are
4 A to E Temporary buildings and uses a sensible, if not essential, part of the process and can save a
5 A to C Caravan sites and recreational campsites good deal of time and money.
6 A to E Agricultural and forestry
7 A to N Non-domestic extensions, alterations etc 4.08 Once that process has been undertaken, a formal application
8 A to N Transport-related development for planning permission can be made on a form provided by the
9 A to E Development related to roads local planning authority. It is now required that the application
10 A Repairs to services be accompanied by a ‘Design and Access Statement’. This is a
126 Planning law in England and Wales

document in which the architect is likely to take the primary 4.15 If the application for planning permission is refused, or is
responsibility and which must set out, in some reasonable detail, granted subject to conditions unacceptable to the applicant for
the basis on which the architect has formed his or her views as planning permission, there is a right of appeal to the Secretary
to the type of design appropriate to the area and the nature of of State within 6 months of the authority’s decision (TCPA 1990,
the design and access proposed. sections 78 and 79). Planning appeals under section 79 and
Schedule 6 to TCPA 1990 (and the Town and Country Planning
4.09 Fees are payable to local planning authorities in respect of (Determination of Appeals by Appointed Persons) (Prescribed
applications for planning permission, applications for approval Classes) Regulations 1997 (SI 1997 No. 420)) are determined
of matters reserved in an outline planning permission, or applica- by an inspector appointed by the Secretary of State, unless the
tions for consent to display advertisements. The amount of the Secretary of State decides to ‘recover’ the appeal for his own
fees is set out in Schedule 1 to the Town and Country Planning determination. The inspector appointed to determine an appeal
(Fees for Applications, Deemed Applications, Requests and Site may hear the arguments of the various parties under one of three
Visits) (England) Regulations 2012 (SI 2012 No. 2920) (‘Fees alternative procedures: written representations, an informal hear-
Regulations 2012’). ing, or a public local inquiry. When deciding which procedure
to use, the inspector must take into account the criteria speci-
4.10 A reduced planning fee is payable, in certain circum- fied under section 319A of TCPA 1990 (see Annexe K of the
stances, where an application is made for a scheme which has Planning Inspectorate’s ‘Procedural Guide’). On making the
been slightly altered from a scheme for which permission was appeal, the appellant must identify the procedure they consider
refused, when the alterations are made in order to overcome most appropriate, having regard to the same criteria. Neither
the problems which led to the refusal (Regulation 9, Fees party can demand a public local inquiry, although the Inspector
Regulations 2012). frequently decides to hold such an inquiry.

4.16 The procedure at appeal determined by an inspector at an


Deciding the planning application inquiry is found in the Town and Country Planning Appeals
4.11 The central principle in deciding planning applications is (Determination by Inspectors) (Inquiries Procedure) Rules 2000
set out in the important section 38(6) of the 2004 Act, which (SI 2000 No. 1625) and Annexe of the Planning Inspectorate’s
is in the following terms: ‘If regard is to be had to the devel- ‘Procedural Guide’. Procedure for inquiries where the Secretary
opment plan for the purpose of any determination to be made of State will make the final determination is dealt with in the
under the planning Acts the determination must be made in Town and Country Planning (Inquiries Procedure) Rules 2000
accordance with the plan unless material considerations indi- (SI 2000 No. 1624) and Annex G of the ‘Procedural Guide’.
cate otherwise.’ The ‘development plan’ is a suite of documents In either case, the public inquiry is a formal, legalistic,
which includes the local planning authorities Development Plan process. It is most usual to use specialist advocates to present
Documents and any relevant neighbourhood development plans the case. Evidence is presented in the form of a ‘proof of evi-
(see section 38(3) of the 2004 Act). dence’ from each witness, with the rules requiring that proofs
be exchanged, usually 4 weeks before the inquiry. Witnesses are
4.12 Put simply, section 38(6) means that if the proposed subject to cross-examination, and detailed submissions will be
development is in accordance with the development plan, a made to the inspector in the last stages of the inquiry.
presumption in favour of granting planning permission would
exist. If it was not in accordance with the development plan, 4.17 For cases of lesser complexity, the matter may be dealt
then good reasons would need to be shown as to why the with by an informal hearing, which are governed by the Town
development should be permitted. Thus, if a developer sought and Country Planning (Hearings Procedure) (England) Rules
to put houses on a site allocated in the development plan for 2000 (SI 2000 No. 1626) – see also Annexe E of the Planning
housing, there would need to be significant reasons as to why Inspectorate’s ‘Procedural Guide’. In such cases, each party
permission should not be granted. If, on the other hand, the prepares a written statement of its case and attaches any relevant
site for this proposed housing was allocated in the develop- documents. There is then a hearing before the inspector which
ment plan for employment uses, then there would need to be takes the form of a round-table discussion. Such hearings do not
good countervailing reasons as to why it should be permitted. have the formality of public inquiries, and it is not unreasonable
These good reasons are described in the statutory language as to suggest that the degree of scrutiny of a case is less than that
‘material considerations’. which is achieved by a full public inquiry. However, the savings
in costs to be achieved if this route is pursued can be consider-
4.13 Material considerations might, for example, include the fact able, and the choice of appeal method (the parties being allowed
that a particular development, while contrary to the development to express a preference, but not to have the final decision as to
plan, would generate considerable employment opportunities method of appeal, which rests with the Secretary of State) can
or would cause the removal of what was previously an ‘eye- be a difficult and important one.
sore’. Further, while the development plan for the purposes of
section 38(6) is only the plan which has been formally adopted, 4.18 For the smallest cases, there is the written representations
if a later, revised, plan is at an advanced stage of the statutory process. As the name suggests, the process involves the submis-
consultation process, the provisions of that forthcoming develop- sion of written statements to the Inspector who will consider
ment plan would be a material consideration. them and, having inspected the site, come to a decision. This is
dealt with in the Town and Country Planning (Appeals) (Written
4.14 However, the most important material considerations are Representations Procedure) Regulations 2000 (SI 2000 No.
perhaps the provisions of the NPPF and the NPPG. If there are 1628) – see also Annexe D of the Planning Inspectorate’s
no relevant policies in the development plan, or those which do ‘Procedural Guide’.
exist are ‘out of date’, then the NPPF applies a tilted planning
balance which requires permission to be given for the applica- 4.19 In any planning appeal, a planning inspector may order one
tion unless the adverse effects of it ‘significantly and demonstra- party to pay the legal and other costs of any other party (see PPG
bly’ outweigh the benefits. Different considerations will apply on Appeals at paragraphs 27–34). Costs can be awarded where
to decision-making to applications for development in green there has been ‘unreasonable’ behaviour by a party, and the
belts, Areas of Outstanding Natural Beauty, and the like, and for unreasonable behaviour has resulted in the other party incurring
development affecting heritage assets. These are matters of con- unnecessary or wasted expense.
siderable technical complexity, and if the architect is confronted
with such a situation, he or she might be well advised to take 4.20 As an alternative to the consideration of planning applica-
specialist planning or legal advice tions by the local planning authority, the Secretary of State has
Control of development in general 127

power under TCPA 1990, section 77 to ‘call in’ the application, specifications, then again there is an appeal against such refusal
with the result that the Secretary of State him or herself makes to the Secretary of State (see paragraph 4.16).
the decision. This power is generally only used for the most
major developments which would have effects outside the area 4.24 It will be seen that, for an applicant who does not own land
of the local planning authority where the development would and who wonders how much he or she ought to pay for it, the
take place. Where a decision is ‘called in’, a public inquiry is making of an outline application to test the position vis-à-vis the
held, so the Secretary of State, when deciding, has the benefit local planning authority is a useful arrangement. It is not neces-
of advice from the inspector. The Heathrow Terminal 5 Inquiry sary for the applicant to go into details and incur the expense
gives an indication of the scale and length which such inquiries thereby involved. All they wants to know before they make their
can reach. However, it must be noted that despite the length and bid for the land is whether, if they are able to buy the land, they
complexity of these inquiries, and the considerable resources will then be able to develop it in anything like the manner they
which the parties necessarily spend on them, the Inspector’s have in mind. To get to know this, all that they need do is make
report is not binding upon the Secretary of State. It is not an outline planning application.
at all uncommon for the Secretary of State to disagree with
the conclusions the Inspector reaches and to go against the 4.25 Sadly, this effective and convenient procedure is increas-
recommendations. ingly constricted, particularly in larger schemes, by the opera-
Following the determination of the Secretary of State, there tion of the Environmental Assessment Regulations considered
is a further appeal under section 288 of TCPA 1990. However, at paragraph 4.05 above. The difficulty lies in the fact that if
such an appeal can only be made on point of law, and the courts an application is too ‘outline’, the environmental impact may
are hostile to challenges which simply seek to undermine the be impossible to properly assess. How, for example, can the
planning judgement made by the Secretary of State (or the impact on the landscape of a development be properly assessed
inspector). Those contemplating bringing such an appeal are when that development has not been designed? In the case of R
well advised to take specialist legal advice as to the possibility v Rochdale MBC ex p. Tew [1999] 3 PLR 74, an outline appli-
of success as, once the High Court is reached, the normal rule cation for a proposed mixed use residential and business park,
is that ‘costs follow the events’, and unsuccessful litigants will where the submitted plan was ‘illustrative only’ and did not
be likely to pay not only their own legal costs, but those of even define which areas would be business premises and which
the Secretary of State in defending the decision. Furthermore, would be housing, was granted outline permission. The level
a strictly applied deadline of six weeks from the date of the of the detail on the plan was thought to be quite sufficient for
Secretary of State’s decision letter ensures that those wishing an outline application. The planning permission was, however,
to challenge a decision in the High Court must move quickly quashed on an application for judicial review, because the plan
to begin the procedure. was insufficiently detailed to be a proper foundation for the
Environmental Assessment.
Outline permission 4.26 The common solution to this problem is the ‘Masterplan’;
4.21 If the architect knows exactly what he or she wants to do a plan is drawn up which, while leaving some flexibility in mat-
by way of building operations, a complete detailed application ters of detailed design, shows definitely the location of internal
for planning permission can be put in. But it may be that the roads, the location and density of different types of development,
architect wants, in the first place, to ‘test the temperature of the and the main design features. The developer can then offer to
water’, that is, to see what are the chances of getting planning submit to a condition on the outline planning permission that
permission at all for, say, a block of offices 20 storeys high. If the development will be in accordance with the Masterplan. The
the architect wishes to do this, then he or she can save time, Environmental impact of the scheme set out in the Masterplan
trouble, and expense by putting in an application (TCPA 1990, can then be properly assessed, and a lawful outline permission
section 92) for outline planning permission, so that the principle can be granted.
of having a block of offices 20 storeys high may be tested. If
it is approved, then it will be necessary for the architect, later
on, within the period (if any) specified in the grant of outline Notices re planning applications
planning permission and before any development begins, to 4.27 Notice of the making of any application for planning
put in detailed plans and specifications for the approval of the permission to develop land must be given to the owner of
local planning authority, these being what are called ‘reserved the land and to any tenant of an agricultural holding, any
matters’, that is, matters reserved, at the stage when the local part of which is comprised in the land (TCPA 1990, section 65;
authority is granting the planning application in outline, for later DMP 2015, Article 13 and Schedule 2). Any application for
and further consideration. planning permission must be accompanied by a certificate
indicating the giving of notice to owners and agricultural
4.22 An outline application should make it clear that it is an tenants (DMP 2015 Article 14). If the appropriate certificate
application in outline and nothing more. Thus any plans and is not included with the planning application, then the local
drawings which accompany it should be clearly marked as planning authority ‘shall not entertain’ the application (TCPA
being by way of illustration only. Although the architect will be 1990, section 65(5)).
required to provide so-called ‘parameter plans’ setting out the
basic details of the scheme, at the stage of applying for outline
permission, architects should not fetter themselves as to the styl-
ing of development. All the architect wants at the outline stage is
General publicity
to know whether or not he or she can, under any circumstances 4.28 In addition to the foregoing personal or private publicity
at all, have planning permission to do the sort of thing desired. deriving from the notices referred to in the previous para-
If permission is received, then the architect must return, in due graph, there must be what can be called general publicity by
course, to the local planning authority with detailed plans and newspaper advertisement for all planning applications (TCPA
specifications so that the authority may consider these detailed 1990, section 65; DMP 2015 Article 15). Thus the owners and
matters. occupiers of neighbouring land will be informed, provided they
keep a sharp eye open for newspaper planning advertisements,
4.23 If the outline application for planning permission is refused, of any application to carry out development so that they may
there is a right of appeal against that refusal to the Secretary give their views and opinions to the local planning authority
of State within 6 months. Similarly, if the outline application before a decision is arrived at. Such views and opinions must
is granted but, later on, the local authority refuses to approve be considered by the local planning authority (TCPA 1990,
reserved matters, that is, refuses approval of detailed plans and section 71).
128 Planning law in England and Wales

Site notices because the legislation under which all this control functions is
town planning legislation.
4.29 Moreover, a site notice, exhibited on the site where the
development is to take place, may have to be given (Article 4.33 A local planning authority in attaching conditions must
13 DMP 2015). Those instances in which a site notice may ensure that the conditions fairly and reasonably relate to the
have to be posted are referred to in TCPA 1990, section 65 and development. The authority is not at liberty to use its powers
Article 13 DMP 2015, and (so far as listed buildings and con- for an ulterior object, however desirable that object may seem
servation areas are concerned) in the Planning (Listed Buildings to be in the public interest. If it mistakes or misuses its power,
and Conservation Areas) Act 1990, sections 67 and 73, and the however bona fide, the court can interfere by the making of an
Planning (Listed Buildings and Conservation Areas) Regulations injunction – per Lord Denning in Pyx Granite Co. Ltd v Ministry
1990 (SI 1990 No. 1519). of Housing and Local Government [1958] 1 QB 554, CA.

Local authority procedure 4.34 Suppose one of the conditions attached to a grant is improper
and thereby unlawful; does this invalidate the entire planning per-
4.30 On receipt of an application for planning permission, the mission, or can the unlawful condition be severed from the rest,
local planning authority must consider the matter and, generally leaving the planning permission intact, but shorn of the improper
speaking, give a decision within eight weeks, unless an exten- condition? There have been several cases on this particularly dif-
sion of time is agreed (DMP 2015, Article 34). In the event that ficult point, and the most authoritative guidance was offered in
the authority classifies the development as ‘major development’, Kent County Council v Kingsway Investments (Kent) Ltd [1971]
a period of 13 weeks is applicable. The decision as to whether AC 72. It would appear from the decisions of the courts that the
or not to so classify an application is one for the discretion of question of whether or not a planning permission is to be held
the local planning authority. The authority will probably need wholly bad and of no effect, by reason of the invalidity of some
to consult the appropriate county council (Article 21) and may condition attached to it, is a matter which should be decided on the
also have to consult any parish council within whose area the basis of common sense and with particular inquiry as to whether
proposed development is going to take place. the valid condition is fundamental or trivial.
The authority may grant the application, may refuse it, or
may grant it subject to conditions (TCPA 1990, 1990 section 70). 4.35 The views of the Secretary of State on attaching conditions
Whatever it does, the authority must state its reasons for hav- to a grant of planning permission are set out at paragraph 54–55
ing so decided (DMP 2015 Article 35). Where the decision is NPPF and in the PPG on ‘Use of planning conditions’, to which
to grant planning permission, only summary reasons need to be reference can be made with advantage (see the Bibliography at
given. If, however, permission is refused, full reasons for refusal the end of the book).
must be provided. This is to enable the unsuccessful applicants
to challenge the decision of the local planning authority if the 4.36 Paragraph 55 of the NPPF sets out five tests that a planning
applicant decides to appeal to the Secretary of State, as may be condition must meet:
done within a period of six months (TCPA 1990, section 78;
DMP 2015 Article 37), or to allow those who might be aggrieved 1 Necessary;
by the grant of planning permission to consider whether further 2 Relevant to planning;
legal action (by way of an application for judicial review) should 3 Relevant to the development to be permitted;
be pursued. 4 Enforceable;
If no decision is given within the appropriate period, the 5 Precise; and
applicant may appeal (again, within six months) to the Secretary 6 Reasonable in all other respects.
of State as if he or she had been faced with a refusal (TCPA
1990, section 78; Development Procedure Order 1995, Article These requirements reflect the test for legal validity of a plan-
37). This is known as an appeal on the grounds of ‘non-deter- ning condition developed by the House of Lords in Newbury DC
mination’. In such a case, which usually arises in circumstances v Secretary of State for the Environment [1978] 1 W.L.R. 1241,
where the local planning authority knows it intends to refuse the 1248 (and approved by the Supreme Court in Aberdeen City
application but has not properly formulated its reasons for doing and Shire Strategic Development Planning Authority v Elsick
so, the local planning authority will subsequently formulate Development Company Ltd [2017] P.T.S.R. 1413), namely that
‘putative’ reasons for refusal. The subsequent appeal will usually a condition must be:
consist of an examination of those putative reasons for refusal.
1 Imposed for a planning purpose and not for any ulterior
Conservation areas purpose;
2 Fairly and reasonably relate to the development to be per-
4.31 If the site of the development is within a conservation mitted by the permission; and
area designated under the Planning (Listed Buildings and 3 Not so unreasonable that no reasonable planning authority
Conservation Areas) Act 1990, sections 69 and 70, then the local could have imposed it.
planning authority, in considering the application, will have to
pay attention to sections 71, 72, 74, and 75 of that Act and to 4.37 One particularly important type of condition is the so-called
any directions given to them by the Secretary of State as to the Grampian condition. This provides that certain things may not
manner in which they should consider applications for develop- happen (such as the commencement of the development or the
ment within areas of special architectural or historic interest. occupation of the first dwelling in it) may not occur until certain
Development in a conservation area must ‘preserve or enhance’ other steps have been undertaken, including on land not controlled
the appearance of the Conservation Area, and detailed design by the applicant (for example the construction of a new road junc-
will invariably be expected from the architect to demonstrate tion). Such conditions are entirely lawful, but the Secretary of
that this condition is complied with. State in PPG, on ‘Use of planning conditions’ at paragraph 009,
has made clear that such a condition should not be imposed if
Conditions there is no reasonable prospect of it being complied with during
the lifetime of the permission (now three years).
4.32 The local planning authority, in granting planning permis-
sion, may attach such conditions as it thinks fit (TCPA 1990
1990, section 70); but this does not mean that it can attach any Section 106 agreements
conditions it likes; not at all. The conditions must be fit, that is 4.38 TCPA 1990, section 106 provides that a developer may
to say, fit, meet, and proper from a town planning point of view, enter into either a unilateral undertaking or an agreement with
Control of development in general 129

the local planning authority (both referred to as a ‘planning obli- or within two years of the final approval of any reserved matter,
gation’) so as to offer some planning benefit as part of a package whichever of these two periods happens to be the longer. The
involving the grant of a planning permission. Most unusually in outline planning permission is granted up to 24 August 2005, the
English law, a section 106 undertaking or agreement binds both requirement is that development must be begun within 2 years
the current and any future owner of the land. A typical example of the final approval of any reserved matter.
of a section 106 obligation is that a developer might offer, as
part of a package which led to grant of planning permission for a
supermarket, to pay for the upgrading of the road junction giving
Starting development
access to the site of the new supermarket. 4.44 When is a project of development to be regarded as having
been begun? This is an important question. TCPA 1990 provides
4.39 The Secretary of State has offered guidance as to the the complete answer in section 56 by providing that a project
proper use of section 106 agreements (see NPPF paragraph of development is begun on the earliest date on which a mate-
56 and PPG on ‘Planning Obligations’). The central principle rial operation in connection with the development is started. A
is that planning permission cannot be ‘bought’ by means of ‘material operation’ will include, among other things, the dig-
a section 106 obligation. Instead, the benefits to be conferred ging of a trench which is to contain the foundations of a build-
by means of the section 106 obligation must be related to the ing. Thus, only a trivial amount of labour needs to be spent in
development being proposed. Usually, a section 106 obligation order to ensure that development has been begun and that a town
is used to provide benefits which overcome a problem caused planning permission has been embarked upon.
by the development, which problem would, without mitiga-
tion, provide a reason to refuse planning permission. The use Abandoning development
of section 106 obligations are therefore subject to tests, both
in legislation (regulation 122 Community Infrastructure Levy 4.45 A ticklish question has always been: can a planning permis-
Regulations 2010) (SI 2010 No. 948) and in policy (NPPF sion be lost through non-use? Can it be abandoned? In Pioneer
paragraph 56). Aggregates (UK) Ltd v Secretary of State for the Environment
[1985] AC 132, a decision of the House of Lords, it was held
that there was no legal principle that a planning permission
Other controls could be abandoned by the act of a party entitled to the benefit
4.40 It should be remembered that obtaining planning permis- of the permission.
sion for development may not necessarily be the end of the
matter. Certain specialised forms of development, e.g. devel- Completion notices
opment relating to the display of advertisements (TCPA 1990
1990 sections 220–225 and the Town and Country Planning 4.46 Having begun its development, a developer cannot unduly
(Control of Advertisements) (England) Regulations 2007 (SI delay the completion of the development. If the developer is
2007 No. 783)) or to the creation of caravan sites (Caravan dilatory, it is open to the local planning authority to serve it with
Sites and the Control of Development Act 1960, Part I, and ‘a completion notice’ requiring the completion of his develop-
the ‘Planning Policy for traveller sites’ issued by the Secretary ment within a certain period (TCPA 1990, sections 94 and 96).
of State), are subject to additional control over and above the A completion notice will declare that the relevant planning
general run of town planning control. permission will cease to have effect on such date as may be
specified in the notice, but this date may not be earlier than
4.41 Moreover, the architect must never forget that town plan- 12 months from the date of the notice. A completion notice will
ning control is a control which functions entirely without not take effect unless and until it is confirmed by the Secretary
prejudice to the long-established control of building operations of State, who may substitute a longer period for completion.
through the medium of building by-laws created under a code Any person served with a completion notice may demand to be
of law relating to public health and dating back to the Public given an opportunity of being heard by an inspector appointed
Health Act 1875, and even before. Irrespective of town plan- by the Secretary of State. Of course, a local planning authority,
ning control, such detailed matters as the thickness of walls, the having served a completion notice, may for good and sufficient
opening of exit doors in public places in an outward and not an reason be prevailed upon to withdraw it; the law authorises such
inward direction, the provision of means of escape in case of fire withdrawal.
– all these are matters which are entirely separate from the sort
of control over development which is discussed in this chapter. Revoking or modifying
planning permission
Duration of permission 4.47 It should be remembered that a planning permission, once
4.42 Nowadays, any developer obtaining planning permission given, ensures a right to develop for the benefit of all persons
must remember that, unless the permission itself specifies oth- for the time being interested in the land, subject to any limita-
erwise, permission will last for only three years. Permissions tion of time contained in the grant of planning permission itself
which last for three years are those which were secured by or imported into the matter by TCPA 1990, as mentioned in
applications made after 24 August 2005. Permissions secured paragraph 4.34. This, however, is subject to the right of a local
by applications made before this date will have a time limit of planning authority to revoke or modify a planning permission by
five years. This is to prevent, among other things, an accumula- means of an order made by the authority and confirmed by the
tion in the records of local planning authorities of quantities Secretary of State (TCPA 1990, sections 97–100 and 102–104).
of planning permissions granted from time to time over a long Before confirming the order, the Secretary of State must afford
period of years and never acted upon. This had been going on the owner and the occupier of the land affected by the order an
for a long time, but was brought to an end by provisions in the opportunity of being heard by the Secretary of State’s inspector.
Town and Country Planning Act 1968, now sections 91 to 96 of There are certain revoking or modifying orders which, being
TCPA 1990. unopposed and unlikely to give rise to claims for compensation,
can be made by the local planning authority without need for
4.43 If that which is obtained is an outline planning permission confirmation by the Secretary of State.
granted between 1 April 1969 and 24 August 2005, the submis-
sion of detailed plans and specifications for the reserved matters 4.48 If the local planning authority wish to make a revocation or
necessary to bring the outline permission to full fruition must modifying order, they must remember to do so before buildings
be done not later than three years from the grant, while the authorised by the planning permission in question have been
development itself must be begun within five years of the grant started. If they fail to do so, the revocation or modification may
130 Planning law in England and Wales

not affect so much of the building operations as have already 1990). It may be granted (like a planning permission) with or
been carried out. Compensation may become payable on the without conditions (section 17 PLBCA 1990). The application
revocation or modification of a previously granted planning for listed building consent is made to the local planning author-
permission (TCPA 1990, sections 115, 117, and 118). ity, and the procedure is given in sections 10 to 16 of the PLBCA
1990 and in the Planning (Listed Buildings and Conservation
Areas) Regulations 1990 (SI 1990 No. 1519). A grant of listed
5 Buildings of special building consent will last for only three years, following the gen-
eral reduction in the duration of permissions brought about by
architectural or historical the 2004 Act. If planning permission for development has been
interest – listed buildings granted, or if an application for planning permission has been
duly made, and if there is a building (unlisted) on the site, the
developer may, since 13 November 1980, apply to the Secretary
of State for a certificate that the Secretary will not list any such
Listing building for at least five years (section 6 PLBCA 1990 and see
5.01 Lists of special buildings are compiled under section 1 of Amalgamated Investment and Property Co. Ltd v John Walker
the Planning (Listed Buildings and Conservation Areas) Act and Sons Ltd [1976] 3 all ER 509 SA). This is a most useful
1990 (‘PLBCA 1990’) by the Secretary of State or the Historic provision when the architect feels that a building standing on the
Buildings and Monuments Commission for England (established development site is potentially a ‘listable’ building.
under the National Heritage Act 1983). Once a building is
listed, it is no longer possible for a local authority to make (as 5.09 In deciding whether or not to grant listed building consent
hitherto) a building preservation order for it; in lieu, PLBCA with respect to a special building, the local planning authority
1990 provides a different kind of protection (see further, para- must pay ‘special regard’ to the desirability of preserving the
graphs 5.07 and 5.8). building or its setting and of preserving any features of special
architectural or historic interest which the building possesses
5.02 The owner of such a special building need not be consulted (sections 16 and 72 PLBCA 1990). Notwithstanding this, it must
before it is listed; he or she is merely told what has occurred. be remembered that the grant of planning permission is one thing,
However, the statutory list of special buildings must be kept and the grant of listed building consent is another. Merely because
open by the Secretary of State for free public inspection. planning permission is granted for development, it does not fol-
Similarly, a local authority must also keep open for free public low that listed building consent will be given to remove some
inspection any portion of the list which relates to their area. obstructive listed building to allow such development to go for-
ward. The planning permission, once granted, will (as explained
5.03 To damage a listed building is to commit a criminal offence in paragraph 4.42) last, generally speaking, for 3 years. During
punishable with a fine up to level 3 on the Standard Scale (cur- that time, views and opinions about a listed building may change;
rently £1000) and a daily penalty of up to one-tenth of that scale views and opinions about architecture do tend to fluctuate. During
(section 59 PLBCA 1990) (see further, paragraph 5.11). the first years of the planning permission, it may be impossible to
get the requisite listed building consent to demolish some obstruc-
5.04 A local authority may carry out works urgently neces- tive listed building. Later on, different opinions about preservation
sary for the preservation of an unoccupied listed building after may prevail, or pressure to carry out development may become
giving the owner seven days’ notice (sections 54, 55, 60, and stronger. Thus, different considerations, in the view of the authors,
76 PLBCA 1990). A local authority may make a loan or a grant apply when a local planning authority is considering whether it
towards preserving buildings of special historic interest (whether should grant planning permission for development and when it is
listed or not) under section 57 of PLBCA 1990. considering whether it should grant listed building consent for the
demolition of a listed building in order to allow planned develop-
5.05 In deciding whether to list a building or not, the Secretary ment to go forward.
of State may now take into account not only the building itself,
but also its relationship to other buildings and the desirability of 5.10 If listed building consent is refused, there is a right of appeal
preserving features associated with the building, but not actually to the Secretary of State after the style of the appeal against
forming part of the building. Thus, it is not solely the building refusal of planning permission (sections 20 and 21 PLBCA
that is to be considered, but the entire setting of the building 1990 and regulation 8 of the Planning (Listed Buildings and
(PLBCA 1990, section 1). Conservation Areas) Regulations 1990 (SI 1990 No. 1519)).

5.06 When speaking of a building, it must be remembered that 5.11 It is an offence to demolish, alter, or extend a listed building
the law is so framed as to give protection to any object or struc- so as to affect its character as a building of special architectural
ture fixed to a building or forming part of the land on which or historic interest without first getting listed building consent
the building stands, and comprised within the curtilage of the (sections 7 to 9 PLBCA 1990; see also Britain’s Heritage v
building (section 1 PLBCA 1990 and see Watts v the Secretary Secretary of State and Others [the Peter Palumbo case] [1991]
of State for the Environment [1991] JPL 718). 1WLR 153). It is also an offence to fail to comply with any
conditions attached to such consent. The penalty for each of
these offences is (on summary conviction) an unlimited fine,
Listed building consent or imprisonment for six months, or both, and on conviction on
5.07 There is no provision for the owner of a special building to indictment, a fine of an unlimited amount or imprisonment for
appeal against the listing of the building. Once the building is two years or both. It is, however, a defence to prove that any
listed, the whole of the protective provisions of Part I of PLBCA works carried out on a listed building were urgently necessary
1990 automatically swing into operation. The consequence of this in the interests of safety or health, or for the preservation of the
is that while (as already explained in paragraph 4.04) it is neces- building and that notice in writing of the need for the works was
sary to get planning permission for any kind of development, if given to the district planning authority as soon as was reasonably
the site of the development happens to be occupied in whole or in practicable (section 9 PLBCA 1990).
part by a listed building, then the development simply cannot take
place unless an additional form of consent, known as ‘listed build- 5.12 If the owner is faced with a refusal of listed building
ing consent’, is first obtained (sections 7, 8, and 9 PLBCA 1990). consent, and can demonstrate that in its present state, the listed
building has become incapable of reasonable beneficial use,
5.08 Listed building consent must be obtained in order to demol- then he or she may serve a listed building purchase notice on
ish, alter, or extend a listed building (sections 7, 8, and 9 PLBCA the local planning authority requiring the authority to purchase
Urban Development Corporations; Simplifed Planning Zones 131

the building (sections 32 to 36 PLBCA 1990 and the Planning building preservation notice that failed to be followed by the
(Listed Buildings and Conservation Areas) Regulations 1990 (SI listing of the building.
1990 No. 1519)).
5.17 Certain buildings of undoubted architectural and historic
interest do not come within the protection of listing at all. These
Listed building enforcement notices are:
5.13 If unauthorised works to a listed building are carried out,
then the local planning authority, in addition to taking proceed- 1 Ecclesiastical buildings in use for church purposes (but not
ing for the commission of a criminal offence, may serve a ‘listed the parsonage house, which is capable of being listed);
building enforcement notice’ upon the owner, requiring full 2 A building included in the Schedule of monuments compiled
reinstatement of the listed building (section 38 PLBCA 1990). and maintained by the Secretary of State under ancient
There is a right of appeal against the notice to the Secretary of monuments legislation.
State (sections 39 to 41, 64, and 65 PLBCA 1990 and Town and
Country Planning (Enforcement Notices and Appeals) Regulations Buildings in conservation areas
2002 (SI 2002 No. 2682)). Penalties are provided in the case of
non-compliance with the terms of the listed building enforcement 5.18 In addition to the special protection given to listed build-
notice. The guilty person is liable to an unlimited fine on summary ings, as described above, section 74 of the PLBCA 1990 gives
conviction or conviction on indictment (section 43 PLBCA 1990). protection to all buildings if they happen to be in a conservation
These penalties are recoverable from the owner of the land who is area designated under section 69 PLBCA 1990.
in breach of the notice, and this may include a subsequent owner.
So, purchasers of a listed building must be careful to ascertain,
before they buy, whether there are any listed building enforcement
6 Urban Development Corporations;
notices outstanding in respect of the building. Simplifed Planning Zones
5.14 A local authority is authorised to acquire compulsorily any Urban development areas
listed building which is not properly preserved (sections 49 to
50 PLBCA 1990). This power may not be exercised until at
and corporations
least 2 months after the service on the owner of the building of 6.01 The Secretary of State is empowered to designate an area
a repairs notice specifying the work considered necessary for of land as an ‘urban development area’ and to establish an Urban
the proper preservation of the building. An owner faced with the Development Corporation to encourage re-development. An
possibility of having the listed building compulsorily acquired Urban Development Corporation is a limited life body tasked
cannot appeal to the Secretary of State, but, curiously enough, with a broad remit to secure the regeneration of their area. The
he or she can, within 28 days, appeal to the local magistrates’ rationale behind Urban Development Corporations was origi-
court to stay the proceedings under the compulsory purchase nally articulated on 14 November 1980 by the then Minister for
order. If the court is satisfied that reasonable steps have been Local Government and Environmental Services, Mr Tom King,
taken for properly preserving the building, then the court may MP, who declared
order accordingly. Against the order of the magistrates, there is
a further appeal to the Crown Court. We shall shortly be bringing forward Orders under powers
in the [Local Government, Planning and Land] Act to set up
5.15 If a listed building is compulsorily acquired, then the com- Urban Development Corporations as single-minded agencies
pensation to be paid to the owner will, in general, disregard the to spearhead the regeneration of the London and Merseyside
depressive effect of the fact that the building has been listed. docklands and to introduce the bold new experiment of enter-
On the other hand, if it is established that the building has prise zones, where business can be freed from such detailed
been allowed deliberately to fall into disrepair for the purpose planning controls.
of justifying the redevelopment of the site, then the PLBCA
1990 provides for the payment of what is called ‘minimum com- In the 1980s, Urban Development Corporations were estab-
pensation’. This means that the compensation will be assessed lished for Trafford (Manchester), The Black Country, Teesside,
at a price which disregards any profit which might have accrued Tyne and Wear, Cardiff Bay, Leeds, Bristol, Sheffield, and
to the owner from the redevelopment of the site. Against any Wolverhampton.
direction in a compulsory purchase order providing for the pay-
ment of this minimum compensation there is a right of appeal 6.02 These Urban Development Corporations were all wound
and, again, this is to the local magistrates’ court, with a further upon in the mid-1990s. However, in February 2003, the govern-
appeal to the Crown Court (section 50 PLBCA 1990). ment re-endorsed the idea of Urban Development Corporations
to drive development. Since that time, Urban Development
Corporations have been established in the Thurrock Thames
Building preservation notices Gateway, East London, and West Northamptonshire.
5.16 Are there any means today of protecting a building which
is not a listed building, but which appears to the local planning 6.03 The statutory objectives of the Urban Development
authority to be of special architectural or historic interest? The Corporations include:
answer is yes. Although the district planning authority can no
longer make a building preservation order, it can serve on the ● bringing land and buildings into effective use;
owner of the building a building preservation notice, which gives ● encouraging the development of existing and new industry
temporary protection for 6 months, during which time the build- and commerce;
ing is protected just as if it were listed (section 3 PLBCA 1990). ● creating an attractive environment; and
The object of this is to give time for consideration by the local ● ensuring that housing and social facilities are available to
planning authority and the Secretary of State, or indeed by any- encourage people to live and work in the area.
body else, as to whether the building should, in fact, be listed.
If, at the end of 6 months, the Secretary of State will not make Urban Development Corporations are empowered to deal with
any such listing, then the building preservation notice automati- matters of land assembly and disposal, planning, housing, and
cally ceases, and the local planning authority may not serve a industrial promotion.
further building preservation notice within the next 12 months.
Moreover, compensation may become payable to the owner of 6.04 An Urban Development Corporation is not an elected
the building for loss or damage caused by the service of the body. It is appointed by the Secretary of State and comprises a
132 Planning law in England and Wales

chairman and a deputy chairman, together with not fewer than powers were added to the original 1990 Act by the Planning and
five, nor more than eleven, other members as the Secretary of Compensation Act 1991.
State may see fit to appoint. In making these appointments, the
Secretary of State must consult such local government authori-
ties as appear to him or her to be concerned with the regenera-
Time limits
tion of the urban development area, and the Secretary of State 7.02 If development consisting of building or other operations
must have regard to the desirability of appointing persons having is carried out without planning permission and if the authori-
special knowledge of the locality where the area is situated. ties allow four years to elapse without doing anything about
the matter (i.e. without taking action by issuing an enforcement
6.05 Urban Development Corporations have a term set for seven notice, as to which see paragraphs 7.06 to 7.08 below), then such
to ten years, with a review after five years, and are funded by development becomes validated automatically for town planning
the Ministry of Housing, Communities and Local Government. purposes, and no enforcement action can be taken thereafter. It
Urban Development Corporations may, by order made by the may be said at once that nothing in TCPA 1990 interferes with
Secretary of State (and subject to annulment by either House this state of affairs so far as building development is concerned.
of Parliament), become the local planning authority for its
own area, thereby taking over all the planning control duties 7.03 However, so far as development involving only a change of
of any local government planning authority functioning within use of land is concerned, the equivalent time limit is ten years
the urban development area. Historically, extensive planning from the date at which the change of use occurred. In order to
powers were bestowed on Urban Development Corporations. take advantage of this time limit, a developer must be able to
However, the planning powers of the new Urban Development demonstrate that the unlawful use has gone on continuously for
Corporations are intentionally not as broad as the first generation over ten years before the date of issue of any enforcement notice.
of Urban Development Corporations; second generation Urban
Development Corporations do not have powers in relation to
determining the overall level of development or the location and
Certifcates of lawful use
distribution of development. Rather, these Urban Development 7.04 Until the Planning and Compensation Act 1991, devel-
Corporations have been invested with development control opment in respect of which the time limit for enforcement
powers for strategic planning applications in support of their had expired was regarded as being ‘established’, but was not
objectives and purposes. Domestic and routine applications will regarded as lawful. This bizarre situation led to great difficulty in
be left to the local authority. assessing the lawfulness of development on land where there had
previously been an ‘established’, but not ‘lawful’ use, and was
6.06 It will be observed that, each time an Urban Development swept away by TCPA 1990, section 191 (as inserted into TCPA
Corporation is established, there is bound to be a consequential 1990 by the 1991 Act). Henceforth, all development in respect
diminution of the planning control powers of any local govern- of which the time limit for enforcement has expired is lawful.
ment planning authority functioning within the urban develop-
ment area over whose regeneration it is the responsibility of the
Urban Development Corporation to preside. Accordingly, it will
not be surprising to find that the establishment of any Urban
Development Corporation, and the demarcation of the boundaries
of any urban development area, are matters which will be eyed
critically by any local government authority out of whose area
the urban development area is to be carved. On this, it may be
mentioned that the London borough of Southwark petitioned the
House of Lords to have the boundaries of the London Dockland
Development Corporation redrawn. The petition failed.

6.07 The trend to delegate planning powers to Urban


Development Corporations seems to be on the wane; in recent
years, Corporations in, for example, Sheffield and Leeds, have
had the transfer of planning powers to them revoked.

Simplifed Planning Zones (SPZs)


6.08 By the enactment of the Housing and Planning Act 1986,
Part II, Simplified Planning Zones were created. Simplified
Planning Zones are now dealt with in sections 82–87 and 94, and
Schedule 1, paragraph 9, and Schedule 7 to the TCPA 1990, and
in the Town and Country Planning (Simplified Planning Zones)
Regulations 1992 (SI 1992 No. 2414). The NPPF and PPG do
not treat with Simplified Planning Zones, so there is not extant
central government planning policy relevant to the exercise of
these powers. Simplified Planning Zones will be established by
local planning authorities by means of a new system of Simplified
Planning Zone Schemes (it is the word ‘Scheme’ which is the
really important part of this expression), each of which will
specify types of development permitted in a zone. A developer
will be able to carry out such development without making an
application for planning permission and paying the requisite fee.

7 Enforcement of planning control


7.05 A developer may now apply under TCPA 1990,
7.01 The enforcement of planning control is dealt with in section 191 for a ‘certificate of lawful use or development’.
sections 171A–196C TCPA 1990. Important new enforcement This is obtained from the local planning authority, and there is
Enforcement of planning control 133

a right of appeal to the Secretary of State if one is refused. The 7.10 Once an Enforcement Notice has been served, the local
certificate makes it clear that the use in question, though origi- authority may follow it with a Stop Notice, which brings all
nally instituted without planning permission, is now lawful and building operations or changes of use to a halt under a penalty,
immune from enforcement action. for breach of the notice, of an unlimited fine (TCPA 1990,
section 187).
Enforcement Notices 7.11 A Stop Notice may also be served following an enforcement
7.06 Enforcement action is by way of Enforcement Notice notice which relates, not to building or other operations, but to
served by the local planning authority upon the owner and occu- any material change in the use of land (TCPA 1990, section 183).
pier of the land to which it relates (see, generally, TCPA 1990, If a Stop Notice is so served, it must be served within 12 months
Part VII, and T and CP (Enforcement) (Inquiries Procedure) of the change of use occurring. But a Stop Notice on a change
Rules 2000 (SI 2000 No 2686)). Briefly, the notice must state of use can never be served when the change of use is change
exactly what the alleged breach of planning control is and the of use of a building into use as a dwelling house (TCPA 1990,
steps required to remedy the breach. There is an appeal to the section 183(4)).
Secretary of State against the notice, and the appeal must now
state not only the grounds of the appeal, but the facts on which 7.12 There is no appeal against a stop notice. Such a notice is
it is based. The penalty for non-compliance with an Enforcement dependent entirely on the enforcement notice with which it is
Notice is an unlimited fine (TCPA 1990, section 179). associated. If, on appeal, the Enforcement Notice fails, so does
the Stop Notice. In this instance, compensation is payable under
7.07 Architects should note that a local planning authority is TCPA 1990 in certain (but not all) cases for loss or damage
never obliged to serve an Enforcement Notice whenever there arising from the Stop Notice (TCPA 1990, section 186). Thus,
has been a breach of planning control. The authority always has a local authority will be inclined to think twice before serving
a discretion which it must be expected to exercise reasonably, a Stop Notice.
as must any public authority holding discretionary powers. What
the authority have to consider is whether, notwithstanding the Temporary Stop Notices
breach of planning control, it is expedient to take enforcement
action, and on this, the authority must have regard not only to 7.13 Local authorities may also issue temporary Stop Notices
the provisions of the relevant development plan, but also to ‘any where there is a breach of planning control, and it is ‘expe-
other material considerations’. Sharing information special pro- dient’ that the breach is stopped immediately (TCPA 1990,
visions will apply if there has been an attempt at ‘concealment’ section 171E). Temporary Stop Notices have effect from the time
by the landowner or occupier. they are displayed on the land in question, however they are
only effective for, at most, 28 days (TCPA 1990, section 17IE).
7.08 Should an Enforcement Notice be served, the land owner or A temporary Stop Notice cannot prohibit the use of a building
occupier has the right to appeal on a number of grounds, includ- as a dwelling house or an activity which has been carried out for
ing on the basis that planning permission should be granted for 4 years prior to the notice (TCPA 1990, section 17IF). A local
whatever is going on on the land. It may also be claimed that the authority cannot issue a second or subsequent temporary Stop
development (whether it be operational development or a mate- Notice; rather, it must take enforcement action (TCPA 1990,
rial change of use) has become, due to the expiry of the time lim- section 17IF). Temporary Stop Notices are subject to similar
its referred to above, immune from enforcement action. Finally, enforcement and compensation provisions as Stop Notices
it may be suggested that the steps which the notice requires to (TCPA 1990, sections 171G to H).
be taken are excessive, or that the period allowed for compliance
is too short. The appeal will be determined by the Secretary of Injunctions
State following an inquiry, and there is a right of appeal to the
High Court on point of law under section 289 of TCPA 1990. 7.14 TCPA 1990, section 187B enables local planning authorities
That right is not, however, unfettered: the landowner/occupier to seek injunctions in respect of actual or apprehended breaches
must show at a preliminary hearing that there is an arguable of planning control. The use of injunctions by local planning
case that the Secretary of State has made an error of law before authorities is on the increase, and developers tempted by the
permission to bring the appeal will be granted. apparent slowness of the statutory enforcement proceedings to
step outside the law should beware. It is for the local planning
authority, not the court, to determine whether it is necessary
Stop Notices or expedient to restrain an actual or apprehended breach of
7.09 The legal pitfalls associated with an Enforcement Notice planning control. An injunction can be sought irrespective of
have, in the past, sometimes led a developer to ‘spin out’ the whether the local planning authority has exercised any of its
appeal procedure while getting on in the meantime with his build- other enforcement powers and irrespective of whether there are,
ing development. There is an appeal to the High Court on a point for example, pending applications for planning permission. The
of law from the Secretary of State’s decision in an enforcement court’s consideration will simply be limited to an assessment
notice appeal, and there are further appeals (on points of law) of whether the circumstances of the case are such that only an
to the Court of Appeal and to the House of Lords. This is still injunction will actually be effective to stop the breach of plan-
the position, but TCPA 1990 prevents a building developer from ning control taking place.
continuing its building operations while the protracted appeals
procedure is working itself out. There is no longer the possibility Guidance
of (quite lawfully) finishing the building before the appeal to, and
in, the House of Lords is concluded. The Stop Notice procedure 7.15 The NPPG on enforcement gives detailed information on
prevents this from happening (TCPA 1990, section 183). the enforcement notice, stop notices, and injunctions.
12
Planning law in Scotland
ALASDAIR BURNET

1 Introduction special provisions apply to proposals for development of build-


ings or land within a conservation area designated as such by
1.01 By virtue of the Scotland Act 1998, town and country plan- the planning authority or the Scottish Ministers. For demolition
ning is a devolved matter on which the Scottish Parliament has of a building in such an area, a consent known as conservation
power to legislate. The principal statute in Scotland is the Town area consent is required. Similarly, many development proposals
and Country Planning (Scotland) Act 1997 (‘the 1997 Act’), will be subject to environmental considerations and may require
which is an Act of the UK Parliament. The 1997 Act has been environmental impact assessments or appropriate assessments in
subject to significant amendment by two recent Acts of the relation to their potential impact on protected areas.
Scottish Parliament: the Planning etc. (Scotland) Act 2006
(‘the 2006 Act’) and the Planning (Scotland) Act 2019 (‘the 1.05 There are also a considerable number of statutory instru-
2019 Act’). Many of the provisions of the 2019 Act are still to ments dealing with planning matters. These are regulations or
come into effect. The section numbers given below are from the orders made by the Scottish Ministers (or, prior to devolution,
1997 Act (as amended), unless otherwise stated. the Secretary of State) under powers granted by provisions in the
principal Acts. They cover a wide variety of issues including: the
1.02 There are some specific differences in the statutory provi- extent of permitted development rights (i.e. development granted
sions applicable to Scotland and England. However, those dif- planning permission by the terms of the order and not requir-
ferences aside, Scots planning law and procedure is generally ing an application for planning permission); the procedure for
similar to, and often identical with, that of England. To that making and determining planning applications; the fees for such
extent, Chapter 11 is commended to the Scots reader. This chap- applications; the rights and procedures in relation to appeals
ter is also subject to the same caveats in relation to the extent of against decisions on applications; the specification of classes
its scope and the focus of its attention as set out in Chapter 11. or changes of use not involving development; the enforcement
of planning control; and other miscellaneous matters such as
1.03 The legislative framework and general approach to plan- the making of tree-preservation orders. References in pre-1998
ning matters in Scotland is very similar to that in England. There legislation to Ministers of the Crown, such as the Secretary of
is a ‘plan-led’ system with a ‘development plan’ (comprising State, are now to be read so as to include Scottish Ministers.
several different documents) being prepared and adopted by the Reference will be made here to the Scottish Ministers rather than
relevant planning authorities to set out their policies and indicate the Secretary of State as in the original measure.
what types of development are likely to be acceptable where.
Decisions on planning applications are then determined ‘in 1.06 Scottish Government policy on planning is an important
accordance with’ the development plan ‘unless material consid- material consideration in determining planning applications.
erations indicate otherwise’. Whether a proposed development It was formerly found in National Planning Policy Guidelines
requires planning permission depends on whether it constitutes (NPPGs) and Scottish Planning Policies (SPPs). Most of the
‘development’ in terms of the definition in section 26 of the SPPs and NPPGs have now been consolidated into a single
1997 Act (see section 3 of this chapter). As in England, the two Scottish Planning Policy (SPP), the latest version of which
main aspects of ‘development’ are the carrying out of building, was published in 2014. The Scottish Government also pub-
engineering, mining or other ‘operations’ in, over, or under lish a National Planning Framework and advice in circulars
land; or the making of any ‘material change in the use’ of any and planning advice notes (PANs). As part of the reforms
building or land. proposed in the 2019 Act, SPP is to be included in the next
National Planning Framework (NPF4), and the NPF itself will
1.04 In relation to buildings that are listed as being of special become part of the development plan. Government circulars
architectural or historical interest, particular provisions of the give guidance on how it envisages its policies and procedures
Planning (Listed Buildings and Conservation Areas) (Scotland) should be implemented. Important circulars include Circular
Act 1997 (as amended) apply. In addition, under the same Act, 5/2013 on Schemes of Delegation and Local Reviews; 4/2013

135
136 Planning law in Scotland

on Planning Appeals; 3/2013 on Development Management


Procedures; 3/2012 on Planning Agreements; 1/2012 on
Permitted Development; 10/2009 on Planning Enforcement;
3/2011 on Environmental Impact Assessments; 4/1998 on the
Use of Conditions in Planning Permissions; 1/1998 on Use
Classes; and 1/2004 and 2/2013 on Fees. The full list and cop-
ies of the circulars can be found on the Scottish Government
website.

1.07 The legislation governing planning in Scotland is presently


undergoing other significant changes, as the 2019 Act is brought
into force and regulations made, and to be made, under it are the
subject of consultation and implementation. The main changes
are described in section 8 below. In the interim, regard should be
had to the fact that not all of the new laws have been published
and brought into force, and that this is a continuing process.
The legal position on such matters will require to be reviewed
by the interested practitioner to ascertain the up-to-date position.

2 Planning Authorities
2.01 Scottish Ministers have executive responsibility for the
Scottish Planning system. Their responsibilities include initiat-
ing new legislation, taking ministerial responsibility for the
activities of the Directorate for Planning and Environmental
Appeals (DPEA), drawing up national policies, issuing guidance
on policy matters, preparing the National Planning Framework,
approving strategic development plans, and potentially interven-
ing in the preparation of local development plans, deciding some
applications of national importance and determining appeals
against a range of planning decisions (normally by delegating
them to a ‘reporter’ – which is the equivalent of an ‘inspector’
in England).

2.02 In relation to the preparation of the development plan for


an area, there are four strategic development planning authorities
in Scotland. One for each of Scotland’s four main city regions:
Glasgow and Clyde Valley; Aberdeen City and Shire; Edinburgh
and South East Scotland; and Dundee, Perth, Angus, and North 3.02 Building operations include demolition, rebuilding, struc-
Fife. These planning authorities have been responsible for the tural alteration, and additions (section 26(4)). Section 26(2) sets
preparation of strategic development plans, but not for the deter- out operations which do not involve development. These include
mination of planning applications. works affecting only the interior of the building and which do
not materially affect the exterior and the use of buildings or land
2.03 A system of unitary local authorities has been in place in within the curtilage of a dwelling house for a purpose incidental
Scotland since 1996. These local authorities are the relevant to the enjoyment of the dwelling house. The use as two or more
planning authorities for the preparation of local development separate dwelling houses of a building previously used as a
plans and for the determination of planning applications within single dwelling house involves a material change in the use of
their area. Planning permission is sought from the local author- the building and each part of it (section 26(3)). The operation
ity as the planning authority. In addition to the local planning of a marine fish farm after a prescribed date (generally, 1 April
authorities, there are two National Park Authorities in Scotland. 2010) is also ‘development’.
Within its area, the Loch Lomond & The Trossachs National
Park Authority has full planning powers, including deciding 3.03 Some operations that require planning permission are
planning applications, while there is an agreement whereby governed by legislation other than the 1997 Act. These include
the Cairngorm National Park Authority can seek to determine developments that relate to matters that are not devolved, such
planning applications which have been made to one of the local as the energy and transport sectors. For example, planning per-
authorities within its area. The Scottish Ministers also still retain mission may be granted as part of the consideration of major
power to give directions requiring applications to be referred to developments under the Electricity Act 1989, or for road-related
them for determination. This is the power to ‘call in’ an applica- development under the Roads (Scotland) Act 1984.
tion (section 46).
3.04 In relation to change of use, the Town and Country
Planning (Use Classes) (Scotland) Order 1997 (S.I. No. 3061)
3 Meaning of Development specifies 11 classes of use under these headings: Class 1, Shops;
Class 2, Financial, professional and other services; Class 3,
3.01 As noted above, section 26(1) of the 1997 Act defines Food and drink; Class 4, Business; Class 5, General industrial;
‘development’ as the carrying out of building engineering Class 6, Storage or distribution; Class 7, Hotels and hostels;
mining or the operations in and over or under land, or the Class 8, Residential institutions; Class 9, Houses; Class 10,
making of any material change in the use of any building or Non-residential institutions; Class 11, Assembly and leisure. A
land. However, certain changes of use do not constitute devel- change of use which does not involve a change from one class
opment by virtue of the provisions of the Town and Country to another is not development. For instance, a change from
Planning (Use Classes) (Scotland) Order 1997 (S.I. No. 3061) retailing goods in a building to using it as a travel agency is not
as amended. Such changes do not therefore require planning development requiring permission, because both activities come
permission. within Class 1, Shops. Incidental uses do not require permission
Control of development 137

merely because they fall within a different class. The statutory the applicant intends to undertake. Details of the procedures to
classification of uses is not exhaustive; an activity may fall out- be followed are given in the DMPR and explained in Circular
with any of the 11 classes. 3/2013 on Development Management Procedures. Such applica-
tions are often also subject to processing agreements whereby
3.05 In cases of doubt, it is possible to apply for a ‘certificate the applicant and the authority agree a timetable for the produc-
of lawfulness’ of an existing or proposed use or development tion and processing of information and the taking of a decision.
(sections 150 and 151), and there is provision for an appeal to For larger applications or those in sensitive or protected areas,
the Scottish Ministers against a refusal or failure to give a deci- the applicant will also need to consider whether an environmen-
sion in relation to such application. tal impact assessment is required, and may request a ‘screening
opinion’ from the authority as to whether such assessment is
3.06 The 2006 Act introduced a hierarchy of development with required. A design and access statement may also be required
‘national development’ being identified as such in the National (DMPR Regulation 13).
Planning Framework, ‘major development’ being defined in
the Town and Country Planning (Hierarchy of Development) 4.03 Informal negotiation frequently takes place between the
(Scotland) Regulations 2009, and ‘local development’ being all applicant’s representatives and planning officers with a view
other development. In terms of the 2009 Regulations, a ‘major to arriving at details for a proposal which the officers would
development’ includes any development to which Schedule 1 of find acceptable and recommend for approval to the planning
the Environmental Impact Assessment Regulations applies, or committee; ordinarily, comments or opinions expressed by an
housing development of over 50 houses, any office block with a officer do not bind the authority, unless the officer was exercis-
gross floor space over 10,000 square metres, or the development ing delegated powers or, possibly, that the statement was about
of any site in excess of 2 hectares. As set out below, different a matter on which the authority had represented that the officer
regimes for the granting of planning permission can apply to the had power to make a binding decision.
different types of development.
4.04 An application for permission may contain full details
and plans of the development and be referred to as a ‘full’ or
4 Control of development ‘detailed’ planning application. Alternatively, what is termed
‘Planning Permission in Principle’ (formerly ‘outline permis-
4.01 Once it is established that a proposed change involves sion’) may be sought (section 59[1]). Where permission in prin-
‘development’ within the meaning of the 1997 Act, an appli- ciple is sought, only brief details of the proposed development
cation for planning permission will be required unless the require to be provided, as subsequently, further application(s)
proposal is ‘permitted development’. Permitted development for approval of matters specified in conditions (‘AMSC’ appli-
is development which is granted permission automatically by cations) (formerly a ‘reserved matters’ applications) will be
virtue of the Town and Country Planning (General Permitted required. ‘AMSC applications’ contain the details that have not
Development (Scotland)) Order 1992 (S.I. No. 223) as amended been given at the initial stage and often concern issues such as
(see section 31), which provides for almost 100 classes of devel- the siting, design, or external appearance of the development,
opment covered by 24 Parts (Schedule 1). The Parts indicate the means of access, or the landscaping of the site. By impos-
general descriptions of groups of classes. Part 1, for instance, ing a condition, the authority may also reserve other matters for
covers development within the curtilage of a dwelling house; its subsequent approval (Inverclyde District Council v Inverkip
Part 2, minor operations; Part 3, changes of use; Part 6, agricul- Building Co. Ltd 1983 SLT 563). Where approval is sought
tural buildings and operations; Part 8, industrial and warehouse purely for the principle of development, drawings and illustra-
operations, and so on. A full explanation of ‘permitted devel- tions submitted should be marked as indicative only.
opment’ is found in Article 3. The Order does not authorise
development contrary to a condition imposed by a permission 4.05 The Applicant requires to notify the application to the own-
granted otherwise than by the Order. Directions restricting ers of the land to be developed and agricultural tenants at the
permitted development may be issued (Article 4). Where a time of submission. The applicant must submit with the appli-
proposed development does not fall within the classes of per- cation a certificate that he has given the requisite notice with
mitted development, an application for permission requires to details, or that he has been unable to do so. After the application
be made (sections 32 and 33). Detailed procedure is set out in is validated, the local authority notifies neighbouring landown-
the 1997 Act and the Town and Country Planning (Development ers (DMPR Regulation 18). Generally, neighbouring land is
Management Procedure) (Scotland) Regulations 2013 (S.S.I. land which is conterminous with or within twenty metres of the
2013/155) (‘the DMPR’). boundary of the land to be developed.

4.02 If the decision on whether or not to grant planning permis- 4.06 An application must be made on a form obtainable from
sion is to be made by the local authority, the norm used to be that the authority. It must describe the development. In the case of
all decisions were taken by the local councillors through the rel- an application for planning permission, in principle there must
evant planning committee. However, the 2006 Act introduced a be a plan sufficient to identify the relevant land. In relation to
requirement for local authorities to publish a ‘scheme of delega- any other application, such other plans and drawings as may be
tion’ that specified how they would decide planning applications necessary to describe the development must be submitted. It is
and allowed them to delegate the determination of applications essential that the description of the proposed development in the
for ‘local’ scale developments to planning officers, while still application accurately describes the development, failing which,
requiring ‘major’ or ‘national’ scale developments to be decided even although the nature of the application may be clear from
by the Council’s Planning Committee. Since the introduction of the plans, any grant of permission may be challenged. In order to
the hierarchy of developments, applications for ‘local’ develop- be accepted and validated, the application requires to be accom-
ment are often delegated to an appointed person (i.e. an indi- panied by such information as is required by the authority and
vidual planning officer). ‘National’ or ‘major’ developments, must be accompanied by the appropriate fee (DMPR Regulations
on the other hand, cannot be delegated. They also require pre- 9–12 and 14, Raymoyle Developments Limited v Scottish Borders
application consultation with the community (section 35A–C), Council [2020] CSIH 9). Fees payable in respect of various
and the authority can refuse to determine them if they decide that applications are found in the Town and Country Planning
the consultation has been inadequate (section 39). An applicant (Fees for Applications and Deemed Applications) (Scotland)
requires to submit a ‘proposal of application notice’ (‘PAN’) at Regulations 2004 (S.I. No. 219), as amended.
least 12 weeks before such an application and give a copy of
such notice to every community council. The PAN must give an 4.07 The DMPR also provides (in Regulation 25 and Schedule
indication of the proposed development and the consultation that 5) who must be consulted before any grant of permission.
138 Planning law in Scotland

This depends on the nature of the development and whether 4.12 Refusal of an application is subject to a right of appeal
there are implications for the body concerned. The list to the Scottish Ministers in relation to applications that have
includes the roads authority, the Scottish Ministers, the water not been determined under a Scheme of Delegation. Such
and sewerage authority, Scottish Natural Heritage, the appeal must be made within three months of the decision
Scottish Environmental Protection Agency, and the Health and (section 47(1)). Appeal may also be taken against what is termed
Safety Executive. The Ministers may issue directions about a ‘deemed refusal’, namely where an application has not been
consultations. determined within the designated time limit, which is generally
two months from receipt of an application for a local develop-
4.08 In relation to the determination of a planning applica- ment or four months from the receipt of an application for a
tion, the authority must have regard to the provisions of the major or national development, or any alternative time limit that
development plan and to any other material considerations has been agreed between the parties (section 47(2)).
(section 37[2]). Section 25 provides that a determination shall The right of appeal applies to the refusal of an application
be made in accordance with the development plan unless mate- for detailed planning permission, planning permission in prin-
rial considerations indicate otherwise. There is, accordingly, a ciple, or AMSC. The Ministers’ obligation to determine appeals
statutory presumption that the development plan will govern is ordinarily delegated to officials known as reporters, although
the decision unless material considerations indicate otherwise. they may recall for their own determination particular cases.
Where a proposal is in accordance with the development plan, Appeals by statutory undertakers are reserved for determination
the principle of development should be taken as established. by the Ministers. Appeals may be dealt with by the holding of a
Under the 1997 Act, the development plan was originally the public inquiry or, in the vast majority of cases, by way of written
approved structure plan and adopted local plan. The 2006 Act’s submissions. Procedural rules governing appeals determined by
amendments introduced strategic development plans to replace public inquiry and written submissions are found in the Town
structure plans and local development plans to replace local and Country Planning (Appeals) (Scotland) Regulations 2013
plans. In the four regions around Aberdeen, Dundee, Edinburgh, (S.S.I. 2013/156).
and Glasgow respectively, planning authorities were grouped Any determination of an application in respect of a local
into strategic development plan authorities (‘SDPAs’) which development by a planning officer is subject to the right to seek
were obliged to prepare SDPs (1997 Act, Part 2, as amended); a ‘review’ by a Local Review Body of the local authority, but
the Aberdeen City and Shire SDP; the Dundee, Perth, Angus, does not provide a right to appeal to Scottish Ministers unless
and North Fife SDP (‘TAYplan’), the Edinburgh and South-East the officer and the authority have failed to determine the appli-
Scotland SDP, and the Glasgow and Clyde Valley SDP. The cation within the specified time limits. A local review body is
Ministers were entitled to approve, modify or reject the SDPs usually made up of three councillors, and there are regulations
(section 13). The development plan then comprised the strategic setting out how such review is to be conducted (Town and
development plan and local development plan, in those SDPA Country Planning (Schemes of Delegation and Local Review
areas, and the relevant local development plan alone outwith Procedure)(Scotland) Regulations 2013 (S.S.I. 2013/157)). It
those areas. The definition of the development plan (section 24) has been clarified that although the Local Review Body consid-
was also extended to include any supplementary guidance that ers the Report of Handling produced by the planning officer, it
had been adopted by the strategic development plan authority should approach the determination of the merits of the planning
or the local planning authority in relation to its plan follow- application de novo and not merely consider the reasonableness
ing the necessary consultation and other approval procedures of the officer’s decision (Carroll v Scottish Borders Council
(section 22). [2015] CSIH 73).
Despite some lobbying in favour of it, the 2019 Act has not
4.09 Provisions introduced into the 1997 Act by the 2019 Act are introduced a third party right of appeal against the grant of plan-
set to change the system again. They remove the need for strate- ning permission. An aggrieved party therefore cannot challenge
gic development plans but introduce Regional Spatial Strategies; the planning merits of a decision to grant of planning permis-
remove the possibility of supplementary planning guidance that sion, but may challenge it in the Court of Session on the basis
is part of the development plan; revise the procedures for prepar- that the decision is unlawful, either by judicial review if it is a
ing the next National Planning Framework (NPF4) and elevate decision of the local planning authority, or statutory appeal if it
its status to being part of the statutory development plan, and is a decision of the Scottish Ministers.
introduce ‘local place plans’ prepared by community bodies at a
local level. The composition of the development plan for an area 4.13 An application may be granted, refused, or granted subject
in the future will therefore look quite different to the present, but to such conditions as the authority thinks fit (section 37(1)).
the current components of the development plan will continue In the case of refusal or conditional grant, the reasons for the
in effect until replaced. decision must be given. As noted earlier, a refusal may be
appealed, as may a conditional grant, if the applicant objects to
4.10 Material considerations are not defined and extend to all a condition. The power to impose conditions is found not only
matters relating to the use and development of the land which in section 37(1) but also in section 41, which allows the imposi-
the law does not regard as irrelevant. What is ‘material’ depends tion of conditions regulating the development or use of any land
on the nature and circumstances of the proposal. It will generally under the applicant’s control (whether or not it is part of the
include government policy and guidance, such as found in SPP, application site) or requiring that works be carried out there if
relevant public representations, consultation responses, the effect expedient for the purposes of or in connection with the author-
on the natural and man-made environment, including the design ised development. Conditions may also provide for the removal
and the external appearance. A replacement local development of buildings or works authorised by the permission. Conditions
plan, particularly if it is at an advanced stage of preparation, may be imposed which depend on the actions of a third party.
even though it has not yet been adopted, is also relevant. So long The applicant cannot lawfully be required to secure that such
as it is a relevant material consideration, the weight to be given action is taken, but a condition can require that no development
to a material consideration in reaching a decision on whether shall proceed until the specified action has been taken (often
or not to grant planning permission is entirely a matter for the referred to as a ‘Grampian condition’).
planning judgment of the authorised decision taker.
4.14 A planning condition must have a planning purpose, fairly
4.11 Where permission is sought in respect of subjects in a con- and reasonably relate to the permitted development, and not be
servation area, special attention must be paid to the desirability so unreasonable that no planning authority could have imposed
of preserving or enhancing the area’s character or appearance it. Guidance is given in the Circular 4/1998 on the Use of
(section 64 of the Planning (Listed Buildings and Conservation Planning Conditions, which states that a condition should only
Areas) (Scotland) Act 1997). be imposed where it is necessary, relevant to planning, relevant
Listed buildings 139

to the proposed development, enforceable, precise, and reason- be begun (as explained above) within two years of the approval
able. A condition should not qualify the permission so as to make of the last AMSC (section 59). The authority currently has the
it substantially different in character from what was sought. A power to vary these time limits by direction, but the amendments
condition requiring any consideration for the grant of permission made by the 2019 Act will once again specify that such varia-
cannot be imposed without statutory authority. tion of the time limits should be imposed by way of condition
attached to the planning permission in principle.
4.15 In an appeal against a condition, the condition may be
deleted or modified. A more onerous condition may be imposed 4.20 While there is no rule that a permission can be abandoned
by the reporter, or he or she may refuse permission, although by the actings of a party entitled to its benefit, after its imple-
the appeal is only against the imposition of the condition mentation, its further implementation may be rendered physi-
(section 47(1)). Where a reporter’s decision is appealed to the cally impossible by another development.
Court of Session, the court has no power to sever an invalid
condition from the rest of the permission if it goes to the root 4.21 Where permission is subject to a condition that develop-
of the permission; if a condition is held to be invalid, the entire ment must begin before the expiry of a particular period; the
permission may fall (BAA v Secretary of State for Scotland development has been begun but not completed within that
1979 SC 200). period; and the authority considers that it will not begin within
a reasonable period of time, it may serve a completion notice
4.16 Section 42 of the 1997 Act allows an applicant to apply stating that the permission will cease to have effect at the end of
for permission without compliance with a condition to which a stated period of not less than 1 year (section 61). The authority
a planning permission previously granted was subject. This is may withdraw a notice. The notice must be confirmed by the
often referred to as an application to ‘vary’ the permission or the Ministers before it takes effect. If it takes effect, then, at the
conditions attached to it, but in reality, it is a new application end of the period, the permission becomes invalid (section 62).
that leaves the original permission unaffected (Pye v Secretary of
State for the Environment [1999] PLCR 28). In considering such 4.22 Section 65 empowers an authority to revoke or modify a
an application, the planning authority will normally only look permission if it appears expedient to do so. The authority must
at the effect of not requiring the condition to be complied with, have regard to the development plan and other material con-
and will not re-visit the principle of development on the site. siderations. The power may be exercised before the operations
have been completed, or the use has been changed, as the case
4.17 Section 75 of the 1997 Act, like section 106 of the English may be. In relation to operations, the revocation does not affect
Planning Act, provides that an authority may enter into an what has already been carried out. Procedure is dealt with in
agreement with any person interested in land in their area for sections 66 and 67. The authority may also make an order requir-
the purpose of restricting or regulating the development or ing discontinuance of use or alteration or removal of buildings
use of the land, and the existence of such agreement may be or works (section 71). Compensation is likely to be payable if a
regarded as a material consideration when determining an appli- planning permission is revoked (sections 76 and 83).
cation for planning permission. Such an agreement or planning
obligation may include necessary or expedient incidental and
financial provisions; for instance, the applicant may agree to 5 Listed buildings
make payment in respect of the cost of providing infrastructure
required by the development. A provision for an applicant to 5.01 Practitioners should also be aware of the potential effect
enter a unilateral undertaking as in England has also now been on any development on listed buildings and conservation areas.
introduced in Scotland. However prior to the coming into force There are some 47,000 listed buildings in Scotland. Statutory
of the 2019 Act there was no power for a Scottish authority to provisions in respect of buildings of special architectural and
impose the equivalent of a community infrastructure levy or seek historical interest are found in the Planning (Listed Buildings
contributions for community infrastructure where there was no and Conservation Area) (Scotland) Act 1997 as amended (the
direct relationship between the development and the need for the ‘Listed Buildings Act’). Lists of such buildings are, since 2015,
infrastructure (Elsick Development Company Limited v Aberdeen compiled by Historic Environment Scotland. Any object or
City and Shire Strategic Development Planning Authority [2017] structure fixed to a listed building and any object or structure
UKSC 66). The 2019 Act has now introduced the possibility of within its curtilage which, though not fixed to it, forms part of
community infrastructure levies being introduced in Scotland, the land may be treated as part of the building. The desirabil-
but further details of how they might work are awaited. ity of preserving such objects or structures on the ground of
architectural or historical interest may be taken into account
4.18 While a grant of planning permission authorises the particu- in considering whether to list a building. Similarly, in deciding
lar development to be carried out, it will often be necessary to whether to list a building, Historic Environment Scotland may
apply separately for other authority such as a building warrant have regard not only to the building itself but also any respect
from the local authority before carrying out the development. in which its exterior contributes to the architectural or historic
interest of any group of buildings of which it forms part. Since
4.19 In terms of the 1997 Act, a permission has a duration of 2015, there is now right of appeal to Scottish Ministers against
three years unless the grant specifies otherwise. That means that a decision to list a building. It is available to the owner, tenant,
development must be begun not later than the expiration of three or occupier of the building.
years or the appropriate period beginning with the date of the
permission (section 58). Section 27 sets out detailed provisions 5.02 A listed building may not be demolished, altered, or
for the purpose of determining when development is taken to extended in any manner which would affect its character as a
have begun, which is generally on the earliest date on which building of special architectural or historic interest without writ-
any material operation comprised in the development is started. ten consent (‘Listed Building Consent’) (section 6). Conditions
That includes any construction work in the course of erection may be attached (section 7). A listed building may not be
of a building, any demolition work and, commonly, the digging demolished within three months of notice of the proposal being
of a trench for the foundations of the buildings: any one of the given to Historic Environment Scotland, following the grant of
specified operations suffices to begin the development (City of Listed Building Consent (section 7[2]). Listed Building Consent
Glasgow DC v Secretary of State for Scotland 1993 SLT 268). is required in addition to any necessary planning permission.
Where planning permission in principle has been given, applica- Applications for consent are made to the planning authority
tion for approval of matters specified in conditions must be made (section 9). Procedure is set out in sections 9 to 16 of the Listed
within three years of the date of the permission in principle (sub- Buildings Act and the Planning (Listed Building Consent and
ject to certain qualifications), and the development itself must Conservation Area Consent Procedure) (Scotland) Regulations
140 Planning law in Scotland

2015 (S.S.I. 2015/243). The planning authority is required to do not do so, then the notice ceases, and no further notice can
consult Historic Environment Scotland before granting various be served for 12 months.
specified listed building or conservation area consent includ-
ing and permission in relation to a Grade A or Grade B listed
building (Regulation 7). The Ministers may call an applica- 6 Enterprise Zones, Simplifed
tion in for determination by them. Listed Building consent is Planning Zones and Business
granted on condition that works permitted by it shall begin Improvement Districts
within a specified period. If none is specified, the works must
commence within three years of the grant of consent (section 6.01 The Ministers may, by order under Schedule 32 to the
l6). Listed Building consent may be granted subject to condi- Local Government Planning and Land Act 1980, designate an
tions; e.g., requiring the preservation of particular features of Enterprise Zone. This has the effect of granting permission for
the building, the remedying of damage caused by the works, development of any class specified in the scheme (1997 Act,
and re-construction following execution of the works using, sections 2 and 55). Planning permission so granted will be
where practicable, original materials with interior alterations as subject to the conditions, if any, specified in the scheme. The
specified (sections 14(1) and 15(1)). Specified details may also Enterprise Zone Authority may direct that any such permission
be reserved for subsequent approval (section 15(2)). shall not apply to a specified development or to specified classes
of development either generally or within a specified area. This
5.03 In reaching a decision on an application for consent, the has only been used in limited circumstances.
authority or the Ministers must have special regard to the desir-
ability of preserving the building or its setting, or any features 6.02 There is also the possibility of creating a Simplified
of special architectural or historic interest which it possesses Planning Zone. The adoption or approval of such a scheme has
(section 14(2)). Accordingly, these are considerations which the effect of granting permission for development specified in
should be addressed when the development is formulated. the scheme or for development of any class so specified. Such a
These are, of course, different considerations from those which permission may be unconditional or subject to conditions speci-
apply to an application for planning permission for an unlisted fied in the scheme (section 49). The planning authority has the
building, but in an application to develop a listed building or power to make or alter such schemes. The types of conditions
its setting, the same requirement applies; special regard is to which may be specified are set out in section 51. Such a scheme
be had to the desirability of preserving the building or its set- has effect for a period of 10 years. It appears unlikely that any
ting (section 59). new Simplified Planning Zones will be created, as the 2019 Act
proposes to remove the obligation on planning authorities to
5.04 There is a right of appeal against a refusal of consent or create and keep under review such areas. It does, however, pro-
a grant subject to conditions. Where consent is refused but the pose to introduce new areas called Masterplan Consent Areas
building and land cannot reasonably be used beneficially in their (sections 54A–54F).
existing state, a Listed Building Purchase Notice may be served
on the authority requiring them to purchase it (section 28). It is
an offence to execute or cause to be executed any works for the 7 Enforcement of planning control
demolition of a listed building or for its alteration or execution
in a manner which would affect its character as a building of 7.01 The relevant provisions are found in Part VI of the 1997 Act
special architectural or historic interest unless there is Listed (sections 123–158). Where there has been a breach of planning
Building consent for those works (section 8). Failure to comply control, i.e. development without planning permission or breach
with a condition under such a consent is also an offence and of a condition, then, if the development consists of building or
punishable by fine or imprisonment. Defences are provided in other operations, no enforcement action may be taken after the
section 8(3) where works are urgently necessary in the interests end of four years from the substantial completion of the opera-
of health and safety, or for preservation of the building, although tions. In the case of a change of use, the period is ten years,
there are then specific criteria which require to be met. beginning with the date of the breach. It is possible, as noted
earlier, to apply for a certificate of lawfulness of an existing or
5.05 The authority may serve a Listed Building Enforcement proposed use or development (sections 150 and 151).
Notice where works have been or are being executed to a listed
building in contravention of section 8 (see section 34). It is an 7.02 Before enforcement action is taken, where it appears to the
offence not to comply with such a notice (section 39). Where authority that there may have been a breach of planning control,
after the period for compliance specified has elapsed, a required it may serve on the owner, or occupier, or any person using the
step has not been taken, the person who is ‘for the time being land or carrying out operations on it, a Planning Contravention
owner of the land’ is guilty of an offence. Defences are available, Notice requiring the giving of information about operations on
including not having been served with the notice or not being and use of the land (section 125). Non-compliance with such a
aware of its existence (section 39(4)). There is a right of appeal notice is a criminal offence (section 126).
against a notice (section 35).
7.03 Where it appears to the authority that there has been a
5.06 The planning authority or the Ministers may use a compul- breach of planning control, it may serve an Enforcement Notice
sory purchase order to acquire a listed building in need of repair, on the owner or occupier of the land (section 127). The notice
after service of a repairs notice (section 42). Where reasonable must specify the matters considered to be a breach of planning
steps have been taken for properly preserving the building, the control and the step(s) required to remedy the breach or any
sheriff may halt the compulsory purchase. Compensation provi- consequent injury to amenity. It should also specify a period for
sions are found in sections 44 and 45. compliance (section 128). An appeal may be made against such a
notice (sections 130–133), although the previous power to grant
5.07 There are provisions enabling the authority to protect a planning permission as a result of such appeal was removed by
building which is not listed but which appears to them to be the 2006 Act.
of special architectural or historic interest and to be in danger
of demolition or alteration in such a way as to affect its char- 7.04 Where the authority considers it expedient that any activity
acter as a building of such interest. They may serve a Building specified in an enforcement notice as one which it requires to
Preservation Notice on the owner (section 3). It remains in force cease should do so before the expiry of the period for compli-
for six months. The effect is that the building is protected as if it ance, it may, upon serving the Enforcement Notice or afterwards,
were listed. During that period, Historic Environment Scotland serve a Stop Notice prohibiting the activity (section 140). Such a
can consider whether to list it. If, at the end of the period, they notice may not be served where the enforcement notice has taken
The implementation of the 2019 Act 141

effect. A stop notice cannot prohibit the use of any building as 3. Revised procedures for preparing the next National Planning
a dwelling house nor any activity which has been carried out Framework (NPF4), which will encompass Scottish Planning
for a period of more than four years ending with the service of Policy and will be elevated in status to being part of the
the notice. There is no right of appeal against a Stop Notice. It statutory development plan.
stands or falls with the relative Enforcement Notice. 4. The introduction of ‘local place plans’ prepared by com-
munity bodies at a local level.
7.05 An authority may, where a condition attaching to a plan- 5. The introduction of Masterplan Consent Areas in place of
ning permission has not been complied with, serve a Breach of Enterprise Zones, Simplified Planning Zones, and Business
Condition Notice on any person carrying out the development Improvement Districts.
or on any person having control of the land (section 145). The 6. The introduction of a requirement to notify major applica-
notice requires that the conditions specified be complied with. tions to local Councillors, MSPs, and MPs.
The notice should specify the steps to be taken or the activities 7. The option for local authorities to require permission for the
which should cease to secure compliance. The period for compli- use of houses for short-term holiday lets.
ance must be not less than 28 days. 8. The possibility of controlling the duration of planning
permission by the imposition of planning conditions is
7.06 Finally, an authority may seek to restrain or prevent a reinstated.
breach of planning control by applying to the court for an inter- 9. The period in which a repeat planning application for simi-
dict (section 146). lar development on the same site is excluded is increased
from two to five years.
7.07 Official guidance on enforcement matters is found in
Circular 10/2009 on Planning Enforcement. 8.02 The Scottish Government intends to bring into force further
provisions of the 2019 Act and regulations to be made under
it. These will relate to, inter alia, NPF and local development
8 The implementation plan preparation procedures and contents; and the creation of
of the 2019 Act masterplan consent areas. They may also lead to the introduc-
tion of community infrastructure levies, although that is far
8.01 The 2019 Act introduces amendments to the 1997 Act and, from certain, as, while the power to make regulations to create
in some instances, resurrects elements of the system that were such schemes is introduced in the 2019 Act, the relevant section
in place prior to the amendments made by the 2006 Act. The has not yet come into force and is, quite unusually, subject to
main changes include: a ‘sunset clause’ whereby the power to make such regulations
will lapse if it is not used within 7 years, i.e. by 24 July 2026.
1. The introduction of a defined statutory ‘purpose’ of plan-
ning; namely ‘to manage the development and use of land 8.03 More detailed information and treatment in respect of
in the long term public interest’ with special emphasis in Scottish planning law may be found in Rowan Robinson et al.,
that context being placed on anything which contributes to Scottish Planning Law & Procedure (2001, W Green & Son),
sustainable development or achieves ‘national outcomes’. and the more recent and concise text, Collar, Planning (4th edn,
2. Revised procedures for preparing the development plan 2016, W Green & Son). The principal statutes, statutory instru-
including: the abolition of strategic development plans and ments, and official guidance, together with articles on selected
the introduction of Regional Spatial Strategies; the removal planning topics, are published in loose-leaf format in the Scottish
of supplementary planning guidance that is part of the Planning Encyclopaedia (four volumes, regularly updated, W.
development plan; the review of Local Development Plans Green & Son). The vast majority of relevant legislation, regu-
and the National Planning Framework to take place every lations, circulars, and guidance can be found on the Scottish
ten years, rather than every five years. Government or planning authorities’ own websites.
13
Public procurement under European Union law
ZENA PRODROMOU

1 The procurement regime the fundamental freedoms as well as the general principles of
law enshrined under the Treaty on the Functioning of the EU
(‘TFEU’), provided that the contracts in question bear a cross-
The relevant EU legislation border EU interest.
1.01 EU law defines public procurement as the process by which
one or more public contracting authorities choose and award
contracts to private economic operators for the provision of
Aims of the EU procurement regime
desired supplies and/or services as well as for the execution of 1.05 The EU procurement regime seeks to contribute towards
desired works, irrespective of whether these works, supplies, or the creation of the common market, eliminating any barriers in
services are intended for a public purpose. the movement of goods and the provision of services across the
Union. This means that contracting authorities may not impose
1.02 Public procurement under EU law is primarily regulated procedural or substantive barriers or any other measures with an
by a set of Directives EU Member States are required to imple- equivalent effect that frustrate economic operators’ right to sub-
ment in their domestic legislation. The relevant Directives (as mit tenders to calls from throughout the EU. Contracting authori-
of March 2019) are: ties are, in fact, bound to assess any such tenders submitted from
operators from across the EU pursuant to the doctrines of equal
● the Public Sector Directive (2014/24/EU), concerning the treatment, transparency, proportionality, non-discrimination,
award of public works and contracts, public supply con- and mutual recognition. All in all, the EU procurement regime
tracts, and public service contracts, which is incorporated essentially seeks to promote competition on the merits.
into UK law by Statutory Instrument 2015 No. 102;
● the Utilities Directive (2014/25/EU), concerning procure- 1.06 Next to these general principles, the EU’s revised procure-
ment procedures applicable to contracting entities operating ment regime equally (i) takes in common societal goals, includ-
in the water, energy, transport, and postal services sectors, ing environmental protection, social responsibility, innovation,
which is incorporated into UK law by Statutory Instrument combating climate change, employment, public health, and other
2016 No. 274; and social and environmental considerations; (ii) promotes electronic
● the Concessions Directive (2014/23/EU), concerning public procurement and auctions; and (iii) seeks to ensure that all public
procurement by means of a concession agreement, which is purchasing represents value for money.
incorporated into UK law by Statutory Instrument 2016 No.
273.
The importance of EU procurement
These three directives are collectively referred to as the ‘2014 rules for architects
Procurement Directives’. 1.07 EU public procurement rules are practically significant for
architects in two main respects:
1.03 Moreover, procurement in certain economic fields is subject
to sector-specific legislation. By way of example: For architects employed in the public sector: EU public procure-
ment rules create certain obligations for contracting authorities,
● the Defence Directive (2009/81/EC) regulates the award- architects employed by which may be under a contractual duty
ing of certain contracts in the fields of defence and security, to carry out in their capacity as the public body’s agents. By
incorporated into UK law by Statutory Instrument 2011 No. way of example, architects may be liable for indemnification
1848; and where the contracting authority is compelled to pay damages for
● Regulation 1370/2007/EC governs the award of public infringements of the rules.
contracts for certain public passenger transport services by
rail and road. For architects in the private sector: Architects may take advan-
tage of the EU public procurement rules, which allow them to
1.04 The award of contacts that fall outside the scope of the participate freely in tenders across the EU and indeed in an
aforementioned pieces of secondary EU legislation (i.e. contracts equal, transparent, non-discriminatory and proportionate fashion.
not subject to the said Directives and Regulation) may nonethe- Moreover, architects may seek redress before national as well as
less be subject to obligations under primary EU law based on EU bodies for infringements of EU public procurement rules.

143
144 Public procurement under European Union law

EU procurement rules and Brexit ● for tenderers: They will no longer have a right to: (i) access
procurement procedures across the EU on the basis of the
1.08 Of course, application of the EU public procurement rules TFEU and the respective Directives outlined above; and
in, and vis-à-vis, the UK will depend on the outcome of the (ii) seek redress before the European Commission and EU
Brexit negotiations. However, a few points may already be Courts.
made:
First, it is worth bearing in mind that the relevant EU pro- Third, while the UK may still be able to agree a limited form of
curement rules have been transposed into national law. Hence, Free Trade Agreement (FTA) with the EU by the end of the tran-
the respective provisions shall remain in place unless and until sition period (i.e. December 2020), it seems unlikely this will
the UK government decides to amend or repeal them. include any specific provisions on public procurement. Based
Second, the key changes anticipated in the event of Brexit on the current status of negotiations the most likely post-Brexit
without a deal are: option is that UK will rely on the Government Procurement
Agreement (‘GPA’) under the World Trade Organisation
● for contracting authorities: UK notices will no longer be (‘WTO’).
publicised through the OJEU (i.e. new UK e-notification
service will need to be established);

2 The Public Sector Directive Public contracts


2.03 ‘Public contracts’ are contracts for pecuniary interest con-
Relevant Defnitions cluded in writing between one or more economic operators and
one or more contracting authorities concerning the execution
Contracting Authority of works, the supply of products, or the provision of services.
2.01 Under the Public Sector Directive, ‘contracting authorities’
are defined as the state, regional or local authorities, bodies gov- Public works contract
erned by public law, or associations formed by one or several of
such authorities, or one or several of such bodies governed by pub- 2.04 A ‘public works contract’ is a public contract concerning:
lic law that extend a request for a public contract. The term encom-
passes the ‘central government authorities’ listed in Annex I of the ● the execution, or both the design and execution, of works
Directive; as well as ‘sub-central government authorities’, namely related to one of the activities within the meaning of
various competent regional and local contracting authorities. Annex II of the Directive (including, inter alia, construc-
tion, site preparation, building of complete constructions
or parts thereof and civil engineering, construction of
Economic operators highways, roads, airfields and sport facilities, renting of
2.02 The Directive defines ‘economic operators’ as any natural construction or demolition equipment with operator);
or legal person or public entity or group of such persons and/or ● the execution, or both the design and execution, of a work;
entities, including any temporary association of undertakings, ● the realisation, by whatever means, of a work corresponding
which offers the execution of works and/or a work, the supply to the requirements specified by the contracting authority exer-
of products, or the provision of services on the market. cising a decisive influence on the type or design of the work.
The Public Sector Directive 145

The ‘works’ referred to means the outcome of building or civil ● contracts awarded by one contracting authority to another
engineering works taken as a whole which is sufficient in itself contracting authority, or to an association of contracting
to fulfil an economic or technical function. authorities on the basis of exclusive rights as per Article 11;
● certain public contracts between entities within the public
sector as detailed under Article 12;
Public supply contract ● contracts for the provisions of research and development
2.05 A ‘public supply contract’ is a public contract having as its services except those listed under Article 14.
subject-matter the purchase, lease, rental, or hire-purchase, with
or without an option to buy, of products. It may incidentally
include sitting and installation operations. Contracts excluded based on their value
2.11 Moreover, the Public Sector Directive does not apply
Public services contract to contracts the estimated value of which (net of VAT) at the
relevant time does not exceed the following thresholds (as of
2.06 A ‘public services contract’ is a public contract concerning
March 2019):
the provision of services. Annex XIV provides a list of social
and other specific services subject to the Directive.
● €5,548,000 (£4,789,505) for public works contracts;
● €144,000 (£124,313) for supply and services contracts
Mixed cases awarded by central government authorities and design con-
2.07 For mixed contracts that combine works, supplies, and/ tests organised by such authorities;
or services in a single agreement, the main subject-matter is ● €221,000 (£190,785) for supply and services contracts
determined by the element with the higher value or by the awarded by sub-central contracting authorities and design
part of the contract that is the most essential to meet the need contests organised by such authorities; and
as follows: ● €750,000 (£647,463) for public service contracts for social
services, as well as for the
● types of services listed in Annex XIV.
Situations Criteria to determine the type of contract

Works + Supplies Main subject of contract


A number of clarifications are necessary in this connection.
Works + Services Main subject of contract
Services + Supplies Highest value First, the aforementioned thresholds apply irrespective of the
contract’s subject-matter.
Second, the relevant thresholds change on a regular basis, gener-
ally every two years, and can be regularly checked on the
Procurement Document Commission’s website.
2.08 The term ‘procurement document’ concerns any document Third, the ‘relevant time’ for calculating the contract’s value
produced or referred to by the contracting authority to describe is the date on which the contract notice is sent to the
or determine elements of the procurement or the procedure Official Journal of the European Union (‘OJEU’). This
including: (i) the contract notice; (ii) the prior information date generally corresponds to the time when the contract-
notice, where used as a means for calling a competition; (iii) ing authority forms the intention to seek offers in relation
the technical specification; (iv) the descriptive document; (v) to the contract.
proposed conditions of contract; (vi) formats for the presentation Fourth, a contracting authority must not separate contracts or
of documents by candidates/tenderers; and (vii) information on otherwise use value calculation methods with the intention
generally applicable conditions. of avoiding the Directive’s application.
Fifth, the ‘estimated value’ is the sum the contracting authority
expects to pay for the contract. In determining this amount
Scope of application contracting authorities must, where appropriate, take into
2.09 The Public Sector Directive generally applies whenever account:
a contracting authority seeks offers in relation to a proposed ● any form of options;
public supply, works, and/or services contract. Certain con- ● any renewals of the contract; and
tracts are, nonetheless, excluded from the Directive’s scope ● any prize of payment awarded by the contracting
of application on the basis of either their subject-matter or authority to the economic operator.
their overall value. Moreover, depending on the nature of the respective ser-
vices contracts authorities must also factor in:
● the premium payable and other forms of remuneration
Contracts excluded based for insurance services;
on their subject-matter ● the fees, commissions payable, as well as interest and
other forms of remuneration for banking and general
2.10 The following categories of contracts are excluded from the
financial services;
Directive’s scope due to their subject matter:
● fees, commissions payable, as well as any other forms
of remuneration for design contracts.
● contracts expressly covered by the Utilities Directive as
described under Article 7;
● contracts expressly covered by the Defence Directive as Fifth, for public works contracts, the estimated value must take
detailed under Article 15; into account both the cost of the works and the total esti-
● contracts related to the provision and/or exploitation of pub- mated value of the supplies and services made available to
lic communications networks and/or electronic communica- the contractor by the contracting authority necessary for
tions services as elaborated under Article 8; executing the said work.
● contracts awarded pursuant to international rules and/or by Sixth, if the contract is split into lots, the general rule is that
an international organisation as explained under Article 9; the value of the purchase is the combined value of all lots.
● contracts related to a number of services enumerated under Seventh, special provisions apply for public supply and/or ser-
Article 10, the most important of which, for current pur- vice contracts intended for renewal (Article 5(11)) and sup-
poses, concerns the acquisition and/or rental of land, build- ply contracts for the leasing, hire, rental, or hire purchase
ings, or immovable property; of products (Article 5((12)).
146 Public procurement under European Union law

Different types of procedures for the difficulties, provided that the duration of such contracts does
award of a public works contract not exceed three years; (iii) concerning commodity market
supplies; and (iv) for purchases on particularly advanta-
2.12 The Public Sector Directive lays down the following five geous terms such as in the context of winding-up/insolvency
different types of procurement procedures: proceedings.
● Where the tender concerns a public service contact awarded
1 The Open Procedure, whereby the contracting authority following a design contest;
issues a call for competition and any interested economic ● Where the tender concerns a contract for new works or ser-
operator may submit a tender. vices in the context of a basic project, the original contract
2 The Restricted Procedure, whereby only those economic for which has been already entrusted to the same economic
operators selected by the contracting authority on the basis operator.
of their responses to the prior information notice are invited
to submit tenders. The open procedure
3 The Negotiated Procedure, whereby the contracting
authority negotiates the terms of the contract with one or ● Issue contract notice.
more economic operators pre-selected by it on the basis of Time limits to respond:
their responses to the prior information notice.
● 35 days;
4 The Competitive Dialogue Procedure, whereby the con-
tracting authority discusses and defines the award’s speci- ● Accelerated – 15 days;
fications with economic operators pre-selected by it on the ● Reductions available for e-procurement.
basis of their responses to the prior information notice. ● Submission of expression of interest/receipt of tenders.
5 The Innovation Partnership, whereby the contracting
authority negotiates ideas to develop innovative works, sup- ● Elimination of unsuitable tenderers on the basis of the applicable
plies or services aimed at meeting a need for which there is exclusion and selection criteria.
no suitable existing product on the market with economic ● Evaluation of bids on the basis of the most economically
operators pre-selected by it on the basis of their responses advantageous tender and appointment of preferred bidder.
to the contract notice. ● Observe 10/15 day standstill period.

2.13 The Public Sector Directive prioritises the open and ● Issue contract award notice.
restricted procedures. Conversely, the negotiated and competi-
tive dialogue procedures are only available where:
The restricted procedure
1 The needs of the contracting authority cannot be met with-
out adaptation of readily available solutions; ● Issue contract notice.
2 The call concerns design or innovative solutions; Time limits to respond:
3 The contract cannot be awarded without prior negotiations
● 30 days.
due to specific circumstances, such as its nature, complex-
ity, legal/financial make-up, and/or risks attached thereto; ● Accelerated – 10 days;
4 The contracting authority faces difficulties in estab- ● Reductions available for e-procurement.
lishing with sufficient precision the requisite technical
● Submission of expression of interest/receipt of completed pre-
specifications;
qualification questionnaires (PPQs).
5 Contracting authorities have received only irregular or
unacceptable tenders in response to previous calls following ● Evaluation of PPQs and elimination of unsuitable candidates on the
the open or restricted procedure. basis of the applicable exclusion and selection criteria.
● Scoring of PPQs and pre-selection of maximum five qualifying
The Public Sector Directive foresees an additional exception bidders and issuance of invitation to tender (ITT).
which allows for recourse to the negotiated procedure even Time limits to respond:
without prior publication where: ● 30 days.
● No tenders or no suitable tenders or no requests to par- ● Accelerated – 10 days.
ticipate or no suitable requests to participate have been ● Reductions available for e-procurement.
submitted in response to previous calls following the open ● Evaluation of bids on the basis of the most economically
or restricted procedure, provided that the contract’s initial advantageous tender and appointment of preferred bidder.
conditions have not been substantially altered;
● The desired works, supplies, or services can only be supplied ● Observe 10/15 day standstill period.
by a particular economic operator because: ● Issue contract award notice.
● The contract concerns the creation/acquisition of a
unique work of art or artistic performance;
● Competition is absent for technical reasons;
● This is dictated by the need to protect exclusive rights, The negotiated procedure
including intellectual property rights. ● Issue contract notice.
● There is extreme urgency previously unforeseen and, in any
event, non-attributable to the contracting authority. Time limits to respond:
● 30 days;
2.14 The negotiated procedure without prior publication is also ● Accelerated – 10 days;
available in the following instances:
● Reductions available for e-procurement.
● Where the tender concerns public supply contracts: (i) where
the products involved are manufactured purely for research, ● Submission of expression of interest/receipt of completed pre-
experimentation, study, or development; (ii) concerning the qualification questionnaires (PPQs).
partial replacement of supplies and/or installations, or where ● Evaluation of PPQs and elimination of unsuitable candidates on the
a change of supplier would create practical and technical basis of the applicable exclusion and selection criteria.
The Public Sector Directive 147

● Scoring of PPQs and pre-selection of maximum three qualifying


● technical specifications drawn, in order of preference, from
bidders and issuance of invitation to tender (ITT).
(i) national standards transposing European standards; (ii)
European Technical Assessments; (iii) common technical
● Time limits to respond: specifications; (iv) international standards; (v) other techni-
● 30 days; cal reference systems established by the European stand-
● Accelerated – 10 days; ardisation bodies; or (vi) when any of those do not exist,
national standards, national technical approvals, or national
● Reductions available for e-procurement. technical specifications relating to the design, calculation,
● Submission of bids and contract negotiations. and execution of the works and use of the supplies accom-
● Evaluation of bids on the basis of the most economically panied by the term ‘or equivalent’;
advantageous tender and appointment of preferred bidder. ● performance/functional requirements referred to above
assessed on the basis of technical specifications;
● Observe 10/15 day standstill period.
● a combination of performance/functional requirements and
● Issue contract award notice. technical specifications as per the above.

A number of clarifications are necessary in this connection:


The competitive dialogue First, any functional requirements must be sufficiently precise
to allow tenders to determine the contract’s subject-matter.
● Issue contract notice
Second, technical specifications shall not refer to a specific make
● Time limits to respond: or source, or a particular process which characterises the
● 30 days. products or services provided by a specific economic opera-
● Submission of expression of interest/receipt of completed pre-
tor, or to trade marks, patents, types, or a specific origin
qualification questionnaires (PPQs).
or production with the effect of favouring or eliminating
certain undertakings or certain products.
● Evaluation of PPQs and elimination of unsuitable candidates on the Third, where reference is made to a specific European, inter-
basis of the applicable exclusion and selection criteria. national, or national standard, a tender cannot be rejected
● Scoring of PPQs, and pre-selection of maximum three qualifying on the grounds that it does not comply with that standard,
bidders, and issuance of invitation to tender (ITT). so long as the tenderer proves that its offer satisfies, in an
● Submission of bids and dialogue. equivalent manner, the technical requirements defined by
the specification in question. Similarly, tenderers will be
● Evaluation of bids on the basis of the most economically able to rely on appropriate national or European stand-
advantageous tender and appointment of preferred bidder. ards to show that they satisfy performance or functional
● Observe 10/15 day standstill period. requirements.
● Issue contract award notice. Fourth, contracting authorities may require that economic
operators provide a test report from a conformity assess-
ment body or a certificate issued by such a body as means
of proof of conformity with requirements or criteria set out
The innovation partnership in the technical specifications, the award criteria, or the
contract performance conditions. Certificates from different,
● Issue contract notice.
yet equivalent conformity assessment bodies shall also be
Time limits to respond: accepted. Other appropriate means of proof, such as techni-
● 30 days. cal dossiers, may also be accepted.
Fifth, tenderers may also submit variants to the specifications
● Submission of expression of interest/receipt of completed pre-
provided that: (i) the relevant procurement documents
qualification questionnaires (PPQs).
expressly allow so; and (ii) these are linked to the contract’s
● Evaluation of PPQs and elimination of unsuitable candidates on the subject-matter.
basis of the applicable exclusion and selection criteria.
● Scoring of PPQs, pre-selection, and issuance of invitation to 1 or Labels
more innovation partners.
2.16 Contracting authorities may also require a specific label as
● Negotiation for the development of innovative product (multiple
a means of proof that the proposed works, services, or supplies
mini-tenders) and further reduction of innovation partners based on
actually correspond to the required environmental, social, or
exclusion/selection criteria.
other related characteristics set out by the contracting authority,
● Invite partners to submit final tenders. provided that the following conditions are fulfilled:
● Evaluation of bids on the basis of the most economically
advantageous tender and appointment of preferred bidder. ● the label requirements must only concern criteria linked
to the contract’s subject-matter and must be appropriate to
● Observe 10/15 day standstill period. define the contract’s characteristics;
● Issue contract award notice. ● the label requirements must be based on objectively verifi-
able and non-discriminatory criteria;
● the labels must be established in an open and transparent
Key steps in the procurement process procedure in which all relevant stakeholders, including
government bodies, consumers, social partners, manufactur-
Technical specifcations and labels ers, distributors, and non-governmental organisations, may
participate;
Technical specifications
● the labels must be accessible to all interested parties;
● the label requirements must be set by a third party over
2.15 Technical specifications lay down the characteristics
which the economic operator applying for the label cannot
required of the advertised work, service, or supply, and may take
exercise a decisive influence.
any the following forms:
Labels equivalent to the ones specified under the relevant pro-
● performance or functional requirements, including environ- curement documents shall also be accepted. Other appropriate
mental characteristics; means of proof, such as technical dossiers, may also be accepted.
148 Public procurement under European Union law

Publication and transparency ● Type of procedure;


2.17 A basic tenet of the EU public procurement regime is ● Relevant time-limits and submission instructions
transparency, such that allows all interested economic operators Time-frame N/A
across the EU to participate in each procurement process and Other comments Following its publication, substantial changes may
submit their offers. This general principle translates into con- not be implemented to the contract notice unless the
crete obligations imposed upon contracting authorities, including relevant time-limits are extended
the duties to:

● advertise tenders at the OJEU following a standard format, Contract award notices
including any modifications and changes thereto;
● make all relevant procurement documents publicly available Aim Inform about the results of the procurement process
and fully accessible, free of charge, to any interested party Mandatory? Yes
also through electronic means; Standard Form https://simap.ted.europa.eu/documents/10184/99173/
● inform candidates as soon as possible of their decisions EN_F03.pdf
concerning the conclusion of a framework agreement; the Content ● Contract’s subject-matter (including CVP codes);
award of a contract; or admittance to a dynamic purchasing ● Conditions for participation, including relevant
system as well as the respective grounds therefore; legal, economic, financial, and technical
● provide further information on the reasons of their decision- information;
making within 15 days from the receipt of a written request ● Type of contract;
therefore.
● Type of procedure;
2.18 With particular regard to the obligation to advertise tenders, ● Date of contract conclusion;
the Public Works Directive establishes the three following types ● Number of tenders received and information on
of standard documents: (i) prior information notices; (ii) contact the successful tenderer;
notices; and (iii) contract award notices.
● Value of successful tender;
● Details of competent review body and applicable
Prior information notices deadline
Time-frame 30 days after public contract conclusion
Aim Alerts the market to future contracts
Mandatory? No
Standard Form https://simap.ted.europa.eu/documents/10184/99173/
EN_F01.pdf The three sets of criteria to
Content ● Contract’s subject-matter (including CVP codes); determine the winning tender
● Brief description of the procurement, i.e. nature 2.19 Contracting authorities must define the criteria on the basis
and extent of desired works/supplies/services; of which the advertised contract is to be awarded in the respec-
● Estimated dates for the publication of the tive procurement documents. More specifically, there are three
contract notice types of criteria used to determine the winning tender:
Time-frame Between 35 days and 12 months prior to the
publication of the Contract notice or invitation to Exclusion grounds, namely grounds on the basis of which
candidates potential candidates are cut out from the procurement
Other comments For restricted procedures and competitive procedures process;
with negotiation, sub-central contracting authorities Selection criteria, namely criteria relevant for determining
may use a prior information notice as a call for whether the various economic operators are qualified to
competition, provided that the cumulative conditions carry out the public contract in question;
foreseen under Article 48(2) are met. Should this be Award criteria, namely criteria seeking to ascertain the pro-
the case, the notice should also include the following posal capable of delivering the expected results in the best
information: possible way.
● Conditions for participation, including relevant
legal, economic, financial, and technical 2.20 It is worth highlighting that in the event of incomplete
information; or erroneous submissions, contracting authorities may request
the economic operators concerned to supplement, clarify, and
● Type of contract;
complete the respective information and/or documentation
● Type of procedure; within appropriate time limits with a view to ascertaining the
● Contract value; existence of the aforementioned criteria. In so doing, contract-
ing authorities are bound by the principles of equal treatment
● Relevant time-limits and submission instructions
and transparency.

Contract notices Exclusion of tenderers


Aim Initiates the procurement procedure 2.21 The Public Sector Directive sets out two clusters of exclu-
Mandatory? Yes sion grounds: mandatory exclusion grounds and optional exclu-
Standard Form https://simap.ted.europa.eu/documents/10184/99173/ sion grounds.
EN_F02.pdf
Content ● Contract’s subject-matter (including CVP codes);
Mandatory exclusion grounds
● Contract value;
2.22 Contracting authorities must exclude from the procure-
● Conditions for participation, including relevant
ment procedure any economic operator who infringes or has
legal, economic, financial, and technical
infringed the law or who has demonstrated highly reprehen-
information;
sible professional behaviour on the basis of the following
● Type of contract; grounds:
The Public Sector Directive 149

Exclusion ground (mandatory) Derogations from the general


Selection of tenderers
rule 2.25 The contracting authority may rely on the following criteria
for the selection of the most appropriate tenderer: (i) suitability
● Conviction (by final judgment) ● Overriding reasons relating to purse the professional activity; (ii) economic and financial
for: to public interest (i.e. public capacities; and (iii) technical and professional abilities.
● Participation in criminal health, environment) In setting out any of the aforementioned selection criteria
organisation; the contracting authority must, nonetheless, abide to certain
● Corruption; principles, namely:
● Fraud;
● the relevant criteria must be related and proportionate to the
● Terrorism; size and nature of the contract in question and be determined
● Money laundering; and in light of the specific needs of each contract;
● Child labour and/or human
● the criteria must be set out in a specific way and be formu-
trafficking
lated simply and clearly;
● Failure to appropriately pay taxes ● Same as above; and ● the contracting authorities must apply the selection criteria
and social security contributions ● Proportionality (i.e. minor in line with the principles of transparency, equal treatment,
and non-discrimination; and
amounts due and/or ● the criteria must be designed in such a way so that economic
economic operator mal- operators, including small and medium-sized enterprises, are
informed of his obligations) not deterred from participating in the tender.

The aforementioned general categories of selection criteria may


Optional exclusion grounds translate into a number of specific requirements:
2.23 Moreover, contracting authorities may also exclude from
participation in procurement procedures (depending on the General selection Specific requirement
national transposition of the Directive) economic operators on criterion
the basis of the following additional grounds:
Suitability to pursue ● Enrolment in one of the official
professional activity professional or trade registers kept in the
Exclusion grounds (optional) relevant Member State;
● Non-compliance with environmental, social, or labour law; ● Official authorisation to perform a certain
type of service (i.e. engineers, architects);
● Bankruptcy or being subject to insolvency proceedings;
● Valid professional insurance certificate
● Serious professional misconduct affecting the operator’s integrity;
Economic and financial ● Minimum yearly turnover not exceeding
● Distortion of competition (i.e. collusion with other tenderers; capacity twice the estimated contract value,
involvement in the preparation of the procurement procedure); including certain minimum yearly
● Severe conflicts of interest; turnover;
● Significant deficiency in carrying out previous public contracts; ● Information on annual accounts showing
ratio between assets and liabilities;
● Failure to provide information to verify absence of exclusion
grounds; and ● Appropriate level of professional risk
indemnity insurance
● Exerting undue influence on the decision-making process
Technical and ● Appropriate human and technical resources
professional ability to carry out the contract to the requisite
quality standard;
General comments on exclusion ● Experience of the contract to carry out the
2.24 Two key clarifications need to be made regarding applica- contract to the requisite quality standard
tion of the exclusion grounds: (i.e. sufficient references from previous
customers);
First, contracting authorities may exclude economic operators at ● Necessary skills, efficiency, experience,
any time during the procurement process. and reliability to provide the service or
Second, economic operators may provide evidence showing they execute installation or work
are reliable, despite their conviction and/or the fulfilment
of any of the optional grounds for exclusion by means of:
(i) proof of compensation paid or undertaken to be paid
for any damage caused; (ii) their active collaboration with Contract award
investigating authorities; and (iii) undertaking concrete
technical, organisational, and personnel measures appropri-
Award criteria: the ‘most economically
ate to prevent further criminal offences, in which case, the advantageous tender’
contracting authority may decide not to exclude them from 2.26 According to the Public Sector Directive, contracting authorities
the process. shall base the award of public contracts on the ‘most economically
150 Public procurement under European Union law

advantageous tender’. This criterion may be assessed on the basis cost analysis using a cost-effectiveness approach, such as life-cycle
of either of the three following methods: (i) pure price analysis; (ii) costing analysis; or (iii) best price-quality ratio analysis.

Price analysis Cost analysis Best price-quality ratio analysis

Analysis takes into Analysis takes into account all costs throughout the contract’s Analysis takes into account various factors
account only the proposed life-cycle including: including:
price: the bid with the
lowest price wins the ● Acquisition costs (i.e. purchase, installation, initial training); ● Price;
contract ● Operational and maintenance costs (i.e. energy and ● Quality
consumables); ● Technical merit;
● End-of-life costs (i.e. recycling, disposal); ● Aesthetic and functional characteristics;
● Environmental costs (i.e. emissions, greenhouse, climate ● Accessibility;
change mitigation), provided their monetary value can be
● Social, environmental, and innovative
determined and verified
characteristics
● Organisation, qualification, and experience;
● After-sales service and technical assistance

2.27 Contracting authorities are obliged to specify in the the performance of a public contract upon the condition that the
procurement documents the methodology applicable to each contractor engages a given number of long-term unemployed.
contract as well as the respective weighting to be attributed to However, this condition does not concern the contractor’s eco-
each of the qualitative criteria, where relevant. These conditions nomic, financial, or technical capacity to carry out the work,
may not be modified during the evaluation process. Similarly, provide the service, or supply the goods and therefore does not
criteria not mentioned in the contract notice, or the contract, or form part of the criteria applied by the contracting authority in
descriptive documents may not be used. Moreover, the contract- selecting the tenderer.
ing authority is obliged to apply any chosen criteria objectively Moreover, any performance conditions must comply with the
and uniformly towards all bidders. fundamental EU principles of equality and non-discrimination.
It would be against EU law if it appeared on the facts of the
case that the performance conditions imposed by a contract-
Abnormally low tenders ing authority could only be fulfilled by national firms or that it
2.28 When the financial offer of a tender seems to be abnormally would, in any event, be more difficult for tenderers coming from
low, the contracting authority shall require in writing certain other member states to fulfil the same condition.
clarifications from the tenderer concerning, inter alia: the eco- When a contracting authority awards a public contract on the
nomics of the manufacturing process, the service provided, or basis of the offer which is most economically advantageous, it
the chosen construction method; any particular circumstances may take account of tenders which offer variations on the per-
that have allowed the tendered to obtain supplies or to subcon- formance conditions specified in the contract documents if they
tract tasks at favourable conditions; compliance with applicable meet the minimum requirements and the contracting authority
EU and national environmental, social and labour law-related has explicitly stated so in the contract documents.
obligations enshrined under Article 18(2); and the possibility of
the tendered obtaining state aid.
This means that the contracting authority may not automati- Contract modifcation
cally reject a tender simply because it appears to be abnormally 2.30 By way of derogation to the general rule, Article 72 of
low. Conversely, the authority is obliged to allow contractors the Public Works Directive stipulates the circumstances under
the opportunity to provide relevant clarifications and to evaluate which a contract may be modified without a new procurement
these. Following this process, the contracting authority: shall process. Permissible grounds for modification include the exist-
reject tenders non-compliant with the social considerations ence of suitable ‘clear, precise and unequivocal’ review clauses
foreseen under Article 18(2); and may reject tenders where the in the contract; a need for additional supplies or services where
justifications offered do not adequately explain the low price a change of supplier is impossible and would cause significant
and/or costs proposed. inconvenience, or a need for additional deliveries due to unfore-
Where a contracting authority establishes that a tender is seen circumstances (both subject to 50% maximum increase in
abnormally low because the tenderer has obtained state aid, the initial contract value); where a new supplier replaces the existing
offer may be rejected on that ground alone only after there has supplier because of insolvency, genuine restructuring; and where
been a consultation with the tenderer, following which tenderers the amendment, irrespective of its value, is not substantial.
prove unable to demonstrate, within a reasonable time limit fixed
by the contracting authority, that the aid was granted in a way
which is compatible with EU rules. Contract termination
2.31 Contracting authorities may terminate a public contract
Contract performance in the course of its implementation for any of the following
reasons:
Performance
2.29 A contracting authority may stipulate conditions relating to ● the contract has been substantially modified such that a new
the performance of a public contract, provided that those con- procurement procedure is necessary;
ditions are indicated in the contract notice and/or the contract ● at the time of the award, the contractor fulfils one of the
documents. These conditions may include social and environ- exclusion grounds recognised under the Directive and/or
mental considerations. A distinction must be made between a national law;
contractual condition requiring the successful contractor to coop- ● the contract should not have been awarded to the contractor
erate with some policy objective of the contracting authority, and in view of a serious infringement of EU law obligations as
the criteria for the selection of contractors or for the award of the declared by the Court of Justice of the European Union in a
contract. By way of example, a contracting authority may attach procedure pursuant to Article 258 TFEU.
The Utilities Directive: a brief overview 151

Moreover, standard contract termination grounds (such as failure ● the negotiated procedure with prior call;
to fulfil obligations) may also apply, depending on the contract’s ● the competitive dialogue procedure; and
exact provisions. ● the innovation partnership procedure.

However, unlike the Public Works Directive, it does not con-


Close of contract dition application of the negotiated or competitive dialogue
2.32 The public contract is closed as soon as the contracting procedures upon certain requirements, and it does not otherwise
authority has formally accepted the final deliveries/provided prioritise the open and/or restricted models. Contracting authori-
services/concluded work and has paid the related invoices. ties may also apply the negotiated procedure without prior call
for competition on the same grounds as under the Public Works
Directive. The respective timelines to respond to the authorities’
3 The Utilities Directive: calls are stipulated under Articles 45 to 49 per relevant procure-
a brief overview ment procedure.

Introduction Transparency and information


3.01 The Utilities Directive applies similar rules to those under 3.06 Contracting authorities are under the obligation to observe a
the Public Works Directive to contracts for certain works, sup- number of publication and transparency requirements such as: (i)
plies, or services entered into by entities operating in the water, publish the contract notice in the OJEU, including with the infor-
energy (gas, heat, and electricity, coal, oil, and gas exploration/ mation detailed in Annex XI of the Utilities Directive; (ii) make
extraction) and transport sectors. The types of works covered all the concession-related documents electronically available;
by the Utilities Directive are listed out under Annex I and (iii) publish the award notice in the OJEU no later than 30 days
include, inter alia, construction of buildings, highways, roads, after the contract’s conclusion; and (iv) publish the setting up
airfields, sport facilities and water projects, site preparation, and of a qualification system. Contracting authorities may also issue
demolition. periodic indicative notices giving the market advance warning
of contracts intended to put out over the coming 12 months.
Contracts excluded based
on their subject-matter Utilities procurement: the relevant stages
3.02 The following types of contracts are excluded from the 3.07 Specification: the contract’s characteristics must be defined
Directive’s ambit due to their subject-matter: (i) contracts related in the procurement documents on the basis of specific techni-
to the lease/acquisition of land or other immovable property cal and functional requirements and may include, by way of
(although related financial services contracts are caught); (ii) example, quality levels, environmental and climate performance
contracts for broadcasting programme material and broadcasting levels, design for all requirements and conformity assessment,
time; (iii) contracts for voice telephony, telex, radiotelephony, safety, marking, and labelling. The tenderer may prove his/her
paging, and satellite services; (iv) contracts for legal services, proposal meets the respective requirements in an equivalent
including arbitration and conciliation; (v) contracts related to manner.
defence or national security, or which are subject to international
commitments; (vi) employment contracts; and (vii) contracts for 3.08 Selection: at first instance, the contracting authority
research and development (other than contracts for the exclusive reviews whether any tenders are to be excluded on the basis of
benefit of the utility for its own use, on condition that the service a series of reasons similar to those foreseen under the Public
is wholly funded by the utility). Works Directive. Non-excluded tenderers are then assessed
on the basis of their professional and technical ability and
3.03 Other types of contracts excluded from the Directive’s appli- their economic and financial standing. These criteria must be
cation include: (i) contracts awarded for the purposes of resale or applied non-discriminatorily and proportionately. The Utilities
lease to third parties; (ii) contracts and design contests awarded Directive allows contracting authorities to limit participation
or organised for purposes other than the pursuit of a covered in contract award procedure to candidates that are registered
activity or for the pursuit of such an activity in a third country; on a ‘qualification system’. This is a unique feature under the
(iii) service contracts awarded on the basis of an exclusive right; Utilities Directive under which economic operators interested in
(iv) contracts awarded by certain contracting entities for the pur- contracting with the authority may apply to be listed as potential
chase of water and the supply of energy/fuel for the production provided providers. The authority then decides on whether to
of energy; and (v) contracts intended to enable an activity directly accept the operators’ application on the basis of predefined and
exposed to competition in markets in which access is unrestricted. published qualification criteria. Following this process, a pool
of potential candidates is formed out of which the contracting
authority may decide whom to invite to bid or negotiate with
Contracts excluded based on their value for a specific contract. The setting up of a qualification system
3.04 The Utilities Directive applies to contracts the value of must be advertised in the OJEU and must be advertised annu-
which is equal or higher than: ally if this is to operate for more than three years. Qualification
systems can be set up and managed by third parties on behalf
(a) €5,548,000 (£4,789,394) for works contracts; of contracting authorities.
(b) €443,000 (£382,426) for supply and service contracts and
design contests; and 3.09 Award: the contact must be awarded on the basis of objec-
(c) €1,000,000 (£862,855) for the social services contracts tive criteria, including environmental, social, or innovation-
specified under Annex XVII. related criteria, provided that these are linked to the contract’s
subject-matter.

Procurement Models 3.10 Performance: contracting authorities may lay down special
3.05 The Utilities Directive sets forth the same procurement conditions related to contract performance, including economic,
models as under the Public Works Directive, namely: innovation-related, environmental, social, or employment-related
considerations, provided these are linked to the contract’s
● the open procedure; subject-matter and form part of the call for competition and the
● the restricted procedure; respective procurement documents.
152 Public procurement under European Union law

Contract modifcation and termination Procurement models


3.11 Articles 89 and 90 respectively govern the modification and 4.04 Interestingly, the Concessions Directive does not set forth
termination of concession contracts in line with the equivalent any model procurement procedures. Conversely, the Concessions
requirements set out under the Public Works Directive. Directive merely stipulates the general principles that should
govern the procurement process, such as equal treatment, non-
discrimination, and transparency as well as combat against fraud,
Other provisions favouritism, corruption, distortion, or competition.
3.12 The Utilities Directive also introduces provisions related to
framework agreements, dynamic purchasing systems, electronic
auctions, and design contests.
Transparency and information
4.05 With particular regard to the transparency requirement,
contracting authorities are, inter alia, under the obligation to:
4 The Concessions Directive: (i) publish in the OJEU the concession notice in line with the
brief overview information detailed in Annex V of the Concessions Directive,
as well as any other information that might be useful, subject to
the exceptions foreseen under Article 31(4) and (5); (ii) make all
the concession-related documents electronically available; and
Introduction (iii) publish the concession award notice in the OJEU no later
than 48 hours after the contract’s actual award. Moreover, the
4.01 Special rules apply to concession contracts, namely ‘con- Concessions Directive is conditioned by only a small number of
tracts for pecuniary interest by means of which one or more con- time-limits, which are set forth under Article 39.
tracting authorities or contracting entities entrusts the execution
of works, or the provision and the management of services, to
one or more economic operators (…) the consideration of which
Concession Procurement:
consists in the right to exploit the works or services or in that the relevant stages
right together with payment.’ 4.06 The Concessions Directive breaks down the respective
The main feature of a concession is that the concessionaire procurement process to the following stages:
assumes an operating risk of economic nature related to the
exploitation of the relevant work or services such that it is pos- 4.07 Specification: the contract’s characteristics must be defined
sible they will not recoup the investments made and the costs in the concession documents on the basis of specific techni-
incurred in the course of the operation. cal and functional requirements and may include, by way of
example, quality levels, environmental and climate performance
Scope of application levels, design for all requirements and conformity assessment,
safety, marking, and labelling. The tenderer may prove his/her
4.02 The Concessions Directive applies to contracts whose value proposal meets the respective requirements in an equivalent
is equal or greater to €5,548,000 (£4,789,394), provided that manner.
their subject-matter is not captured by the exclusions stipulated
under Articles 10–14. The value of a concession shall be the 4.08 Selection: at first instance, the contracting authority reviews
total turnover of the concessionaire generated over the dura- whether any tenders are to be excluded on the basis of a series
tion of the contract, net of VAT, as estimated by the contracting of reasons similar to those foreseen under the Public Works
authority or the contracting entity, in consideration for the works Directive. Non-excluded tenderers are then assessed on the basis
and services being the object of the concession, as well as for of their professional and technical ability and their economic
the supplies incidental to such works and services. On certain and financial standing. These criteria must be applied non-
occasions, though, the estimated value of the concession contract discriminatorily and proportionately.
pre-procurement may be different than the estimated value at the
time of the award. Hence, if the value of the award at the time 4.09 Negotiation: the contracting authority may hold negotia-
of the award is 20% or more higher than the estimated value tions with candidates and tenderers, so long as these discussions
pre-procurement, a new valuation is necessary. In any event, do not alter the concession’s subject-matter, award criteria, and
the estimated concession value must be calculated on the basis minimum requirements.
of an objective method, taking into account a number of criteria
listed under Article 8(3). 4.10 Award: the contract must be awarded on the basis of objec-
tive criteria, including environmental, social, or innovation-
Special features of the Concessions related criteria, provided that these are linked to the contract’s
subject-matter.
Procurement Regime
4.03 Another important element is that concessions contracts are
of limited duration and cannot be left open-ended. Moreover, the
Contract modifcation and termination
Concessions Directive subjects concession contracts for the pro- 4.11 Articles 43 and 44 respectively govern the modification and
vision of social and other specific services listed under Annex IV termination of concession contracts in line with the equivalent
to a special regime, whereby contracting authorities are subject requirements set out under the Public Works Directive.
only to a sub-set of the generally applicable obligations. Equally,
the Concessions Directive allows member states to reserve the
right to participate in concession award procedures to sheltered 5 The Defence Directive:
workshops and economic operators whose main aim is the brief overview
social and professional integration of disabled or disadvantaged
persons or may provide for such concessions to be performed 5.01 The Defence Directive applies, inter alia, to the procure-
in the context of sheltered employment programmes, provided ment of arms, munitions, war materials, as well as works and
that: (i) at least 30 % of the employees of those workshops, services, including architectural services, for specific military
economic operators, or programmes are disabled or disadvan- purposes. The applicable value thresholds, as of March 2019, are
taged workers; and (ii) relevant provisions have been made to €5,548,000 (£4,789,394) for works and €443,000 (£382,426) for
the procurement documents. all other supplies and services.
The Defence Directive: brief overview 153

5.02 The Defence Directive contains a number of features reflect- from entering into the contract with the successful tenderer. This
ing the specific needs of procurement in the defence and security removes the need for the claimant to apply for interim protection
markets. By way of example: (i) the negotiated procedure can be separately. If proceedings are issued, the automatic suspension
used as a standard procedure (albeit publication of tender notices will remain in force until such time as the proceedings are deter-
is required); (ii) candidates can be required to put in place meas- mined, discontinued, or otherwise disposed of. If the contract-
ures to ensure the protection of sensitive information; and (iii) ing authority wishes to insist on awarding the contract, it must
member states can request guarantees to ensure that armed forces make an application to the court for the automatic suspension
are delivered in time, especially in times of crisis or conflict. to be lifted.

6 The Remedies Directives


Post-contractual remedies
Overview 6.07 After the contract has been entered into, there are essen-
tially two remedies available:
6.01 The EU legal framework on remedies is set out under
Directive 89/665/EEC concerning public works contracts and 6.08 Damages: the claimant is entitled to claim its bid-costs
Directive 92/13/EEC concerning utilities contracts (referred alto- and a proportion of lost profit on the contract, depending on
gether as the ‘Remedies Directives’). Both of these Directives its chances of being awarded the contract, but for the breach.
have been amended by Directive 2007/66/EC. The said Directives There are a number of procedural and technical obstacles fac-
provide for certain general procedural rules, leaving the details ing any claimant, but damages awards have been made by the
and more specific procedural aspects to national law. courts, and many post-award challenges settle before reaching
final judgment; and
Standing to bring proceedings 6.09 A declaration of ineffectiveness/ineffectiveness order: the
6.02 The Remedies Directives provide that redress is avail- ineffectiveness remedy is an exceptional remedy that gives
able to any economic operator that has or has had an interest courts the power to set aside concluded contracts by making
in obtaining a particular contract and that risks, or has risked, an order rendering unenforceable all future rights and obliga-
being harmed by an alleged violation of the applicable procure- tions under the contract and imposing fines on the contracting
ment rules. This means that all economic operators that have authority.
expressed an interest in participating in a contract award proce- The grounds for a declaration of ineffectiveness are (i) a com-
dure – or might have done so if the contract had been advertised plete failure to advertise a contract or framework agreement in
– have the right to benefit from the available remedies. However, the OJEU (an illegal direct award); (ii) a failure to comply with
Member States may require that the person seeking the review the equal treatment and transparency obligations when conduc-
must have previously notified the contracting authority of the ing the tender process, combined with a failure to observe the
alleged infringement and of his intention to seek review. debrief and standstill requirements prior to awarding the contract
(an aggravated OJEU breach); or (iii) a failure properly to award
an above threshold call-off contract under a dynamic purchasing
Competent body system (a dynamic purchasing breach).
6.03 In the UK, the competent judicial body to hear procurement There are special time limits for seeking a declaration of inef-
cases is the High Court. fectiveness/ineffectiveness order. As regards a claim under the
first ground, proceedings must be brought either within 30 days
of the publication of any contract award notice or otherwise
Time-limits within months of the day after the date on which the contract
6.04 The general rule is that proceedings must be brought within is entered into. If the claim is brought on the second or third
30 days of the ‘date of knowledge’, defined as the point at which grounds, it must be brought within 30 days of any valid award
the claimant knew or ought to have known of the infringement. notice or otherwise within months of the contract being entered
The courts will, however, retain judicial discretion to extend into (the publication of a contract award notice is irrelevant).
the period within which proceedings must be brought, up to a Conversely, the Remedies Directives do not provide for the
maximum of 3 months. There is a separate time-bar provision power to set aside a contract entered into in breach of EU public
where the claimant is seeing a declaration of ineffectiveness. procurement rules. Such contracts may, nonetheless, be held out
as unenforceable on the basis of public policy grounds as a mat-
ter of national contract law.
Types of remedies available
6.05 The Remedies Directives provide for two types of remedies:
(i) pre-contractual; and (ii) post-contractual ones.
Redress before the European
Commission and the EU Courts
Pre-contractual remedies 6.10 Economic operators may also lodge complaints alleg-
ing infringements of EU public procurement rules before the
6.06 An unsuccessful tenderer may request, during the tender European Commission. In the event the European Commission
process and in any event before the contract has been awarded, accepts the complaint, it may call the relevant contracting
a national court to: authority and corresponding Member State to justify the con-
duct under review, rectify the infringement, or suspend the
● set aside any unlawful decision taken in the process; or award procedure. Where the European Commission is not sat-
● amend unlawful tender documentation (e.g. discriminatory isfied with the explanations and/or actions of the contracting
specification, unlawful selection, or award criteria); and/or authority, it may institute infringement proceedings against
● make an award in damages for loss or damage suffered as a the corresponding Member State before the Court of Justice
consequence of the breach. of the EU. Economic operators may have a right to intervene
in these proceedings.
Where proceedings are raised before the contract has been
entered into, the contracting authority is automatically suspended
14
Party walls
GRAHAM NORTH

1 The Party Wall etc. Act 1996 Section 1 Building along the line of junction of the boundary
which is not currently built on other than to the extent
1.01 The Party Wall etc. Act 1996 came into force in 1997 and of a boundary wall (not being the wall of a building).
extended the party wall legislation previously applying to Section 2 Carrying out works to a party structure/party wall/
London and set out in Part VI of the London Building Acts party floor/party fence wall, such as underpinning,
(Amendment) Act 1939 to the rest of England and Wales. demolishing and rebuilding, raising, removing chim-
ney breasts, cutting into install beams, injecting a
1.02 The Act sets out a procedure for notices to be served if damp-proof course, columns, etc.
certain works are proposed. An adjoining owner can consent Section 6 (a) Excavating or excavating to construct new foun-
or dissent (and, in the case of a Party Structure and Excavation dations within 3 metres of an adjoining building
Notice, will dissent by failing to respond) which gives rise and to a greater depth than the foundations of
to a dispute. When this happens, surveyors are appointed to that adjoining building or structure.
resolve the dispute by making an award which sets out who (b) If one is excavating or excavating to construct
the owners are and the manner in which the works will be foundations within 6 metres of an adjoining
carried out. Notices must be served if one is carrying out the building or structure and to a depth which would
following works: intersect a 45° line drawn downwards from next
door’s footings.

For a 3-metre notice.

155
156 Party walls

For a 6-metre notice.

1.03 Before the Act was passed, a party wall outside of London
was defined as being severed vertically through its centre. One
could carry out works to one’s own half of the wall, but not to
the neighbour’s side unless consent was given. In some cases,
this provided difficulties if the party wall required underpinning
or had to be raised for its full thickness.

2 Defnitions
2.01 The Party Wall etc. Act now gives two definitions for a
party wall:

1 Section 20(a): a wall which forms part of a building and


stands on lands of different owners to a greater extent than
the projection of any artificially formed support on which
the wall rests.
2 Section 20(b): so much of a wall not being a wall referred
to in section 20(a) above as separate buildings belonging to
different owners.

Figure 14.3 and 14.4 illustrate these definitions.

Party wall, as defined by section 20(a).


The surveyors 157

these notices relate cannot start even after these periods if an


award is yet to be agreed and published to the owners.
A notice is served on any owner who has an interest in their
property of greater than 12 months. A building owner must be
someone who has an interest in the land and is ‘desirous of
exercising rights’ under the Act. A building owner can also be
someone who has contracted to purchase an interest in the land
or signed an agreement for a lease, as long as this is for greater
than 12 months.
It is vitally important that any notice served contains the cor-
rect information. Failure to include these details on the notice
could render the notice invalid. Thereafter, any matter or award
agreed by the surveyors following the service of a defective
notice could also be invalid.

3.03 An adjoining owner has 14 days in which to dissent or con-


sent to the works described in a Party Structure and Excavation
Notice, otherwise he or she will be deemed to have dissented
by default. Thereafter, a dispute arises, and surveyors must be
appointed to settle the matter by an award.
The parties can agree to the appointment of one surveyor,
known as the ‘agreed surveyor’, a role which the surveyor can
fulfil because of the surveyor’s statutory responsibility to act
impartially. Alternatively, the adjoining owner can appoint their
own surveyor. If there is no agreed surveyor, but a surveyor
appointed for each of the building and adjoining owners, then
their first duty is to select a third surveyor who will adjudicate
on any matter in dispute between the surveyors and, in some
instances, between the owners.

3.04 If an adjoining owner fails to respond to a notice, then a


written request must be made to him or her, either by the build-
ing owners or their surveyor if given due authority, to appoint
a surveyor within 10 days. If the adjoining owner ignores this
request, then the building owners are in a position to appoint a
Party wall, as defined by Section 20(b). *This section was written by
surveyor for the adjoining owner.
William Frain-Bell.
4 The surveyors
2.02 A party structure can be a party wall, party floor, parti-
tion, or other structure separating buildings or parts of buildings 4.01 The surveyor can be any person who is not a party to the
approached solely by separate staircases or separate entrances. A matter. No specific qualifications are required, but it is important
party fence wall is a wall which does not form part of a building to ensure that if such an appointment is accepted, one has the
but stands astride the boundary. knowledge and experience required. The appointment is personal
to the individual.

3 Notices 4.02 It is the surveyors’ duty in their award to determine the


right for the works to be carried out, the time and manner of
3.01 The Act sets out the steps that must be followed if one is executing this work, and any other matter arising out of or inci-
intending to carry out any of the works referred to above. This dental to the dispute, including the costs of making the award.
involves the service of notice, commonly known as a Party
Structure Notice, Line of Junction Notice, or an Excavation 4.03 If the surveyors are unable to agree, then an approach can
Notice, and the notice must state: be made to the third surveyor who will make a decision in the
form of an award. Submissions to the third surveyor are nor-
● The name and address of the building owner. mally in writing once the third surveyor has confirmed that he
● The nature and particulars of the proposed works. or she is able to accept the appointment.
● The date on which the proposed works will begin. Information sent to the third surveyor should include copies
of each surveyor’s letter of appointment from the owner, copies
In respect of an Excavation Notice, it must also be accompanied of the notices, and evidence that the third surveyor has been
by plans and sections showing: selected. An outline of the matters in dispute should be given
along with supporting arguments.
● The site and depth of any excavation the building owner
proposes to make. 4.04 One of the most important aspects of the award will be the
● If the building owner proposes to erect a building or struc- Schedule of Condition taken of the adjoining property or land.
ture, its site. This is normally in a written form and can be supplemented
with photographs.
A Line of Junction Notice must describe the intended wall. If the adjoining owner’s surveyor fails to respond within ten
days to a written request from the building owner’s surveyor, or
3.02 A Party Structure Notice must be served at least two months does not act effectively, then the building owner’s surveyor can
before the works are due to start, and in respect of an Excavation proceed ex parte, and this will be as effectual as if he or she had
and Line of Junction Notice, one month before. Works to which been the agreed surveyor.
158 Party walls

5 The award unnecessary inconvenience to any adjoining owner or occupier


(section 7(1)). It is incumbent upon building owners to ensure
5.01 Once the award is agreed, it is published to the owners, who that they take all reasonable measures to minimise any incon-
have 14 days in which to appeal against the award in the country venience to an adjoining owner.
court if they feel it has been made improperly or incorrectly.
The Act does not say that once the award is published to the 6.04 It is vitally important that the procedures are followed.
owners, that the building owner must wait 14 days before the Failure to do so can lead to legal action from the adjoining
works can start, although some awards will make that a condi- owner and subsequent delays to the works.
tion. If an adjoining owner wishes to appeal against an award,
and in the meantime, the building owner’s works commence, 6.05 Where an adjoining owner may be vulnerable if the build-
then the adjoining owner must lodge an appeal and also obtain ing owner does not honour his or her obligations, for example,
an injunction to prevent the works from proceeding further. if a party wall is to be demolished and rebuilt, but the building
Legal advice must be sought at this stage. owner disappears prior to reconstruction, the adjoining owner
The surveyors decide who pays the fees for agreeing the can request security for expenses. The request for such security
award and any other costs arising from it. In the majority of must be in writing and made before the works commence. The
cases, it is the building owner who will bear the fees for the amount of security will vary depending upon the extent of the
surveyors appointed, because the works will be for the building works which may be necessary if the adjoining owner has to
owner’s benefit. complete them. However, the security requested should not be
If there are works which are necessary to a party wall on so much that to provide the money, a building owner would be
account of defect or want of repair, then the costs of such works prohibited from commencing the works.
will be defrayed by the building owner and the adjoining owner Security for expenses is usually provided as a financial
with regard to the use which each of the owners make of the deposit in an account from which the money can only be
structure or wall concerned and the cause of the defect. returned upon the signatures of two of the three surveyors
appointed. If there is no requirement to use the security, then
the money is released to the building owner with any interest
6 The building owner’s rights which may have accrued.

6.01 Section 8 grants building owners, their servants, agents, and 6.06 The standard forms for notices, awards, letters of appoint-
workmen the right to enter the land of an adjoining owner for ment, etc. are in various publications, including the RICS
the purpose of executing any works under this Act. This could Guidance Note, the RIBA Guidance Note, and the Party Wall Act
include the erection of scaffolding over the adjoining owner’s Explained, published by the Pyramus and Thisbe Club.
land and buildings, although details of the access will be agreed
by the surveyors beforehand.
If an adjoining owner fails to give such access to the building 7 Boundary structures in Scotland
owner, or to the surveyors, if they need to carry out an inspec-
tion, to take a Schedule of Condition, for example, then that 7.01 ‘Party wall’ is not a term of art in Scotland. The Party Wall
owner would be guilty of an offence and liable on summary etc. Act 1996 does not extend to Scotland. North of the border,
conviction to a fine imposed by the courts. the common law, property titles and local by-laws regulate mutual
boundary wall questions and other questions about ‘joint owner-
6.02 The Act does not permit a building owner to install special ship’, ‘common ownership’, and ‘common interest’. The common
foundations on an adjoining owner’s land unless the adjoining law developed an elaborate doctrine of ‘common interest’, nota-
owner’s consent is obtained. Special foundations are defined as bly in relation to flats in different ownership within the same tene-
foundations in which assemblage of beam or rods is employed ment building, which has now been codified by the Tenements
for the purpose of distributing any load. This type of founda- (Scotland) Act 2004. Proprietors now have a statutory duty to
tion is becoming more common where basements are being maintain their own parts of the building so as to ensure that they
excavated and the party walls are underpinned. continue to provide support and shelter their properties within the
The Act also permits a building owner to chase into an tenement, e.g. to maintain walls, partitions, floors, and ceilings
adjoining owner’s wall to install a flashing or other weather- and to carry out repairs. The Tenements (Scotland) Act 2004 also
proofing of a wall erected against the adjoining owner’s wall now provides a default management scheme for the maintenance
(section 2(2)(j)). of many parts of a tenement building, including external walls,
gable walls, and load-bearing walls. Where neighbouring proper-
6.03 In the event of damage being caused to the adjoining own- ties, not forming part of a tenement, share a boundary wall, the
er’s land or property, an adjoining owner can either insist that the general rule is that each owns half of the wall up to its mid-point.
building owner makes good that damage, or can request payment Each owner has an obligation at common law, based on common
in lieu. The amount of any money to be paid to the adjoining interest, not to undermine the support of the other half. Where
owner in this situation is to be determined by the surveyors. it is proposed to carry out works on or adjacent to boundary
As far as the award is concerned, it is the building owner who structures or adjoining property and, in the case of buildings in
is responsible for making good or paying for the damage, not the multiple ownership, where it is proposed to carry out operations
contractor. It is for the surveyors to determine what damage has which may affect the stability of the building or interface with
been caused and the extent of remedial work necessary. services, legal advice should be taken. The same applies where
Building owners are not permitted to exercise any rights con- there is a question about maintenance or repairs to the common
ferred upon them in such a manner or at such time as to cause parts of a building or a development of several buildings.
15
Health and Safety law affecting architects
SIMON TOLSON

1 Introduction Principal contractor’s duties to consult and engage with


workers
1.01 Health and Safety should be a fundamental consideration 14. The principal contractor must—
for all architects and designers. It should be part of everyday
working both with activities inside the design office and on (a) make and maintain arrangements which will enable the
every project on site. principal contractor and workers engaged in construction
Whenever we ponder on health and safety, the inevitable work to cooperate effectively in developing, promoting
image is of the busybody with a clipboard telling you what you and checking the effectiveness of measures to ensure the
can and cannot do. Let’s be honest, it does not get great press! health, safety and welfare of the workers; …
But there is a sound argument that the Health and Safety at Work (c) ensure that those workers or their representatives can
Act 1974 (‘HSWA’) has done more to revolutionise how we go inspect and take copies of any information which the prin-
about our lives, and our working lives in particular, than any cipal contractor has, or which these Regulations require
other piece of legislation in the second half of the 20th century. to be provided to the principal contractor, which relate to
the health, safety or welfare of workers at the site, except
1.02 Construction remains a disproportionately dangerous indus- any information—
try where the need to make improvements to health and safety
is still pressing, despite the very substantial progress made in (i) the disclosure of which would be against the interests
recent years. Added to that has been the complexity in the UK, of national security;
from late February 2020, of one of the greatest public health (ii) which the principal contractor could not disclose
challenges of our time namely working during a pandemic and without contravening a prohibition imposed by or
attempting viable construction activity with the Severe Acute under an enactment;
Respiratory Syndrome Coronavirus-2 (SARS-CoV-2) (‘C-19’) (iii) relating specifically to an individual, unless that indi-
for short upon us. At its highest point, some 65 per cent of UK vidual has consented to its being disclosed;
sites by value had closed down. (iv) the disclosure of which would, for reasons other
than its effect on health, safety or welfare at work,
1.03 C-19 means a fortiori everyone needs to assess and manage cause substantial injury to the principal contractor’s
the risks of C-19 as well as other risks of the construction pro- undertaking or, where the information was supplied
cess itself and how they sit together. An employer has a duty of to the principal contractor by another person, to the
care and a legal responsibility to protect workers, their employ- undertaking of that other person;
ees, and others who might be affected by their business from risk (v) obtained by the principal contractor for the purpose
to their health and safety (HSWA). Employers must do whatever of bringing, prosecuting or defending any legal
is reasonably practicable to achieve this. This obligation applies proceedings.
to employees of contractors, sub-contractors, and others who
Accordingly, in the light of Regulation 14(c), subcontractors and
would normally be expected on a typical building site.
workers on a building site can ask to have copies of materials
held by the principal contractor relating to health and safety for
1.04 The Architect also has a duty of care to ensure, so far as is
that site. The contractor can refuse these requests if the requests
reasonably practicable, that the health and safety of other people
relate to an individual, or it would cause substantial injury to
is not put at risk. They are bound by the express and implied
the principal contractor, or the documents are being obtained for
terms of contracts of employment and other contracts for the
bringing prosecuting or defending legal proceedings.
personal performance of work or services, including the implied
Any request of the principal contractor to provide details of
duty of trust and confidence.
the provisions which it has in place for dealing with C-19 would
not seem to fall within any of these exceptions, and the main
1.05 Employers are under a duty under the Equality Act 2010
contractor should provide the information if asked. No doubt,
(EqA) not to discriminate against employees/workers with pro-
architects will ask.
tected characteristics, and they have a duty under the EqA to
make reasonable adjustments for the disabled.
1.07 Regulation 15 imposes on all contractors, at all levels of
main and sub-contracting, a duty to ensure work is carried out
1.06 Regulation 14 of the Construction (Design and Management)
‘as far as reasonably practicable’ without risks to health and
Regulations 2015 imposes specific separate duties on the
safety:
Principal Contractor:

159
160 Health and Safety law affecting architects

Duties of contractors recognise potential risks and to balance the level of obligation
15 (2) A contractor must plan, manage and monitor construc- upon different types of employer. While not excusing impecuni-
tion work carried out either by the contractor or by workers osity, it made allowances for small employers who did not have
under the contractor’s control, to ensure that, so far as is the means to implement sometimes expensive safety measures,
reasonably practicable, it is carried out without risks to health while making implied demands upon larger employers who had
and safety. the financial means to do so.

1.08 This means those on site, or planning to be, need to think 2.05 While all of this legislation had some impression upon
about the risks they face and do everything reasonably practica- working conditions, it still relied upon a ‘voluntarist’ approach
ble to minimise them, recognising the unique overarching added from employers to implement it and effectively left them to their
complication in 2020 that one cannot completely eliminate the own devices, save for a few state regulations such as machine
risk of C-19 on site, one merely can manage the risk it adds to guards in factories.
construction activity so as to avoid the opportunity for the virus The inadequacies of this approach were all too apparent. By
to spread. Following a concerted effort by Build UK to support the end of the 1960s, around 1000 people per year died as a
members to increase their output while complying with the result of workplace accidents, and by 1970, there were still five
Construction Leadership Council led Site Operating Procedures, million workers without any kind of safeguards under the law.
the Secretary of State for Housing, Communities, and Local Something needed to be done.
Government, Robert Jenrick published a written ministerial
statement making it clear that for the 12 months from May 2020, 2.06 In 1970, Alfred Robens (or Baron Robens of Woldingham,
local planning authorities in England should not refuse requests as he was formally known) was appointed to investigate and
to extend working hours on construction sites up to 9:00pm, propose a solution to the issue of improving workplace health
Monday to Saturday, without very compelling reasons to allow and safety. In 1972 he published his report, and what he pro-
for the slower pace of working safely with C-19 measures like posed was radical.
self-distancing, masks/facial coverings, respirators, and regular The Report recommended at paragraph 178 that ‘health and
hand washing. In some cases, such as in areas without residential safety at work legislation should apply explicitly for the protec-
properties, 24-hour working may be justified. tion of the general public as well as workpeople’. The Report
Data from the Office of National Statistics (ONS) also reveals a concern for the public who are not involved in the work
revealed in May 2020 a higher rate of coronavirus-related operations, for example the ‘public in the thoroughfare alongside
deaths when compared to many other sectors, and that among construction operations or persons living in the neighbourhood
low-skilled construction workers rates were highest, no doubt as of premises where hazardous substances are stored or used’.
operatives cannot work from home and must be on site. Lessons must be learnt from the experience of accidents, and the
experience must be used to promote good practice and judgment.

2 A brief history 2.07 The Robens Committee recommendations were substan-


tially enacted in the Health and Safety at Work, etc Act 1974
2.01 Since many of us will recall from our school days those (‘HSWA’), which received Royal Assent on 31 July 1974. In
images and tales told of the workhouses and of working condi- January 1975, the Health and Safety Commission and its enforc-
tions in general, it is hard to believe that the very first piece of ing body, the Health and Safety Executive (HSE) were set up.
health and safety legislation dates back to the early nineteenth
century and the Health and Morals of Apprentices Act of 1802. 2.08 The Report has four main areas of recommendations: first,
The Act required that no child under the age of nine was to be for changes in the nature of health and safety offences; second,
employed in cotton mills, with a maximum day of 12 hours for to extend health and safety legislation to provide protection of
all those under 16. Throughout the nineteenth century, workers’ the public as well as protection of those at work; third, on policy,
existences were, to quote the seventeenth century philosopher in regard to sanctions and enforcement; and fourth, for the set-
Thomas Hobbes, ‘nasty, brutish and short’. ting up of new administrative bodies, the Health and Safety
Executive and the Health and Safety Commission, with a range
2.02 Even with the good intentions of the 1802 Act, it was not of new powers and functions.
effectively enforced, as it lacked an independent body to make
sure these minimum standards were being met, and instead relied 2.09 The Robens Report started from a general view that the
on the good will of the mill and factory owners. In spite of this, prescriptive approach of the old legislation was ineffective and
we can see the first tentative steps towards what we take for unsatisfactory. One criticism of the old approach was that it had
granted today. resulted in too much law, spread around too many disparate
regulations. A second criticism was that the law was difficult
2.03 The common law took a turn toward employee rights in to comprehend.
the workplace with the 1837 case of Priestly v Fowler [1837] The HSWA was not a moment too soon in its coming, the
150 All ER 1030, which established a common law duty of Construction Industry had long been identified as the one of the
care of employers towards their employees. This principle was most dangerous in the UK. Only farming is more dangerous.
enshrined in legislation in the Employers Liability Act 1880, He proposed to abolish the myriad of inspectorates and con-
which gave legal protection to workers for accidents caused solidate it down into one, overarching inspectorate with control
by their employers’ negligence. This was replaced by the over all areas of health and safety regulation.
Workman’s Compensation Act 1897, which introduced payments
for workers in certain industries who were injured ‘out of and in 2.10 As a result of the Robens report, HSWA was enacted in
the course of employment’. 1974 and implemented almost all of Robens’ recommenda-
tions. The effect of HSWA can be seen plainly from the data.
2.04 This perhaps is best demonstrated in the case of Edwards Sometimes they say that statistics do not tell the whole story, but
v National Coal Board (1949) 1 All ER 743 (CA), which intro- on this occasion they appear to paint a pretty clear, lucid picture:
duced the concept of ‘reasonable practicability’, which has been In 1974, there were 651 fatal injuries and 336,722 non-fatal
transported to later legislation, including the HSWA. This is the workplace injuries reported. In 2018/19 there were 147 fatal
idea that employers must balance the time and expense neces- injuries and 69,208 non-fatal workplace injuries reported. This
sary to implement safety measures against the potential effect of represents a fall of 77% in fatal workplace injuries, and a 79.5%
taking such measures. fall in non-fatal injuries.
This effectively implied the need for employers to undertake These statistics go some way to signifying the efficacy of
risk assessments within the workplace environment in order to the new approach. The legislation has saved hundreds, possibly
What architects need to know: key areas 161

thousands of lives through avoidable workplace accidents and for England and Wales, Regulation 38, that ‘The person carrying
improved working conditions for millions more. out the work shall give fire safety information to the responsible
person not later than the date of completion of the work, or the
date of occupation of the building or extension, whichever is the
3 What architects need earlier.’ For those not familiar with the term ‘Responsible per-
to know: key areas son’, the meaning of ‘Responsible Person’ is detailed in Article
(3) of the Regulatory Reform (fire safety) Order 2005.
3.01 Architects, by definition, need to be concerned with health
and safety. After all, any new or refurbished building has to be 3.07 Architects designers, building contractors, developers, and
designed with health and safety in mind. Whether it is mechani- the owners of buildings are responsible for ensuring that suitable
cal and/or electrical services, fire escape routes, or selection of designs, building techniques, and materials are used.
materials, health and safety is an imperative that needs to be
carefully considered. However, it is not only about the building’s Fire safety
safety standards, but also about the process.
3.08 A brief word on fire safety is necessary before devot-
3.02 UK architectural education under the Architects Act 1997, ing most attention in the remainder of this chapter to non-fire
and specifically as set by the Architects Registration Board specific health and safety law and regulation more widely. For
(ARB), has the responsibility for prescribing the qualifications further detail on fire safety and related legislation, see chapter 9.
and practical experience required for entry into the profession
on the UK Register of Architects and therefore includes, in 3.09 This Chapter does not address fire safety in any detail, save
broad terms, the legislative framework for ensuring the health, to say here that the Regulatory Reform Fire Safety Order 2005
safety, and welfare of both construction workers and building (RRFSO) is highly controversial and will not likely be with us
users, in terms of health and safety regulations and building much longer in its current form, particularly following its expo-
regulations. The ARB sets prescription criteria which are held sure in light of the Grenfell fire disaster in June 2017. The major
in common by the RIBA for the purposes of RIBA validation of change in the legislation was that it brought in the concept of
architectural courses in the UK. The ARB prescription criteria risk assessment rather than prescriptive codes. It was introduced
for qualification at Parts 1, 2, and 3 are themselves derived from under Tony Blair’s governments and shifted the responsibility
specific criteria for architectural training set out in Article 46 of for fire inspection from the fire brigade to the local council. It
EU Directive 2005/36/EC on the recognition of professional ended the practice of routine fire inspections and with it, under-
qualifications (still applicable, for now, post Brexit. After the mined the safety of the people of this nation.
withdrawal date of 31 December 2020, UK nationals will be
deemed third country nationals, and Directive 2005/36/EC will 3.10 In London, until the RRFSO became law in October 2006,
not apply to them. This means that the recognition of UK nation- London building regulations were once specialised as applied
als in an EU-27 Member State will be governed by the national to buildings at a greater height than 30m, and to buildings
policies and rules of that Member State). Every architect should, of the warehouse class or used for the purposes of trade or
for example, be aware that preparing a fire safety strategy for a manufacture exceeding 7100 cubic metres in extent. The repeal
building is a requirement of Building Regulations. of sections 20 and 21 of the London Building Acts 1930 to
1939 soon after the RRFSO (they were repealed by the Building
3.03 The specific criteria for architectural training include the (Repeal of Provisions of Local Acts) Regulations 2012 with
following requirements: effect from 9 January 2013) have all occurred since the last edi-
tion of this book. It was said by many to be a blow to fire safety
‘The graduate will have the skills to prepare designs that will standards, removing the ‘final card’ that a district surveyor and
meet building users’ requirements and comply with UK legisla- brigade could use in London, and ended independent oversight
tion, appropriate performance standards and health and safety by the local fire authority.
requirements. (GC10.3)’
3.11 The health and safety requirements specific to
‘The graduate will have knowledge of the fundamental legal, Section 20 buildings included designing in and provisioning for
professional and statutory responsibilities of the architect, and fire compartmentation, automatic sprinkler installations and other
the organisations, regulations and procedures involved in the fire suppression systems, smoke ventilation to above ground
negotiation and approval of architectural designs, including land stories, special fire precautions for car parks and loading bays,
law, development control, building regulations and health and special measures for other areas of high fire risk, and provision of
safety legislation. (GC11.1)’ additional facilities and information for the fire and rescue services.

‘A successful candidate for the Professional Practice Examination 3.12 The RRFSO is the statutory instrument for England and
will demonstrate an understanding of building regulations, Wales that obligates those responsible for property (except
approved documents and standards, guidance and processes individual domestic dwellings) to conduct a fire risk assess-
(PC3.3) and health and safety legislation and regulations (PC3.6).’ ment and take reasonable steps to mitigate any risks identified.
It replaced the fire certification required under the now repealed
3.04 However, the RIBA itself has highlighted that it is notice- Fire Precautions Act 1971 and repealed the Fire Precautions
able that there is no explicit reference within the criteria to (Workplace) Regulations 1997. Fire Certificates are no longer
design for fire safety as a specific element of technical design necessary (and those previously in force now have no legal status).
and regulatory compliance, this being evident from the October In addition to the statutory instrument, a set of sixteen guides
2017 submission from the Royal Institute of British Architects exist to assist business owners, including guidance on conducting
to the Call for Evidence by the Independent Review of Building a fire safety risk assessment for a variety of different types of
Regulations and Fire Safety. premises, ranging from transportation to entertainment, industrial
to healthcare.
3.05 Plainly, the design and layout of a building, in conjunction
with the materials used and style of construction, play a key role 3.13 The three reasons for the RRFSO were said at the time
in preventing the spread of flames and smoke and in allowing the to be:
safe evacuation of people from the premises in the event of a fire.
1 To simplify, rationalise, and consolidate existing fire safety
3.06 Every architect should also know that ‘it is a legal require- legislation for buildings into a consolidated collection of
ment of the Building Regulations 2010 approved document B regulations.
162 Health and Safety law affecting architects

2 To bring together fire safety legislation with health and heart of a reformed building safety system. The new regulator
safety law and reduce prescriptive requirements. will be responsible for implementing and enforcing a more strin-
3 To put the responsibility for fire safety on the ‘Responsible gent regulatory regime for buildings in scope, providing stronger
Person’ (owner/occupier/employer/landlord) as a conse- oversight of safety and performance of all buildings, and increas-
quence of the findings in the ‘Fire Risk Assessment’, which ing the competence of those working on building safety.
the Responsible Person has a legal responsibility to create.
3.19 The Independent Review and the proposals focus on fire
3.14 On any objective analysis, the RRFSO is widely believed and structural safety for buildings in scope, but the Building
to be a failure: see, for example, the RIBA Statement on Design Safety Regulator will also work with industry and other regula-
for Fire Safety, dated 5 July 2017, being its feedback to the tors to strengthen the safety and performance of other build-
government consultation at the time on changes to Building ings. The scope of the more stringent regulatory regime will
Regulations which have had a profound effect on fire safety and apply to all multi-occupied residential buildings of 18 metres or
health and safety design, and can and has led to loss of life, more in height, or more than six storeys (whichever is reached
damage, and destruction of buildings, equipment, and stock. The first) from the outset but will, in due course, also extend to
recent November 2019 hall of residence fire at the Cube, Bolton, include other premises, based on emerging risk evidence. The
and the notable part played in it by high pressure laminate (HPL) more severe regime will, importantly, apply throughout the
and timber cladding components on the building certainly bring lifecycle of new builds. It will also apply at the occupation
in to question the quality of the design review processes in the stage to existing buildings in scope, following a suitable transi-
era up to Grenfell. tion period. For buildings within scope of the more stringent
In relation to the design of flats, for example, the RRFSO regime, the Building Safety Regulator – working with exist-
does not impose obligations regarding fire prevention within ing local regulators – will oversee a new duty-holder regime
the actual flats themselves, only the common parts. Fire safety operating over a building’s whole life span. This duty-holder
within the flats is covered by the Housing Act 2004, which gives regime will place greater responsibility on those designing
local Environmental Health Officers the power to issue notices and constructing buildings to explain how they are managing
with respect of fire hazards inside a flat. Dame Judith Hackett safety risks and demonstrating to the regulator that the build-
has already indicated that the overlap and mismatch of the Fire ing is safe to be occupied. Architects will need to be on top
Safety Order and Housing Act 2004 make it ‘significantly more of these changes.
challenging to ensure that there is a sufficient holistic focus on
the fire safety of all occupied buildings’. 3.20 Alongside the new Building Safety Regulator, the
Government will strengthen the oversight and enforcement of
3.15 The key feature of the RRFSO is that it places responsi- the existing construction products’ regulatory regime by estab-
bility for fire safety of premises on those individuals who are lishing a new national Construction Products regulatory role.
responsible for those premises in some way. Previously, the
local fire safety officer would define their requirements for fire 3.21 The Building Safety Regulator will also oversee and
safety and firefighting equipment. In practical terms, a business enforce (including through criminal sanctions) the safety and
owner should employ a suitably qualified person to carry out performance of all buildings and be responsible for oversight of
their duties on their behalf; in the case of building design, this the competence and performance of building control profession-
will normally involve the architect. However, it seems design als and the building control bodies in which they work.
and build contractors often rely on Approved Inspectors or Local
Authority building control departments to do the checking and
‘policing’, and that is simply beyond their resource constraints.
System of duty holders
Dame Hackett has, in the meantime, stated that the current 3.22 Under the Government’s BSR proposals, there will be a
regulatory system for ensuring fire safety in high-rise buildings new system of duty-holders with clear responsibilities at each
is ‘not fit for purpose’. Sir Martin James Moore-Bick’s enquiry stage of a building’s lifecycle, designed to provide more answer-
will, in due course, no doubt shed more light. ability to end-users. The five duty-holders during the design and
construction phase mirror those under the CDM Regulations
2015: the Client, Principal Designer, Principal Contractor, any
The Building Safety Regulator (‘BSR’) Designer (including anyone who prepares or modifies a design),
3.16 The newly created ‘Building Safety Regulator’ will mark and any Contractor (including anyone who manages or controls
a new chapter in fire safety and oversight of the design and construction work).
management of buildings, with a strong focus on ensuring the
new regime for higher-risk buildings is enforced effectively
and robustly. This Regulator will also have the power to apply
The three gateways
criminal sanctions to building owners who do not follow the 3.23 During the planning, design, and construction phases, new
new regime. builds subject to the stricter regime will need to pass through
three ‘Gateways’, during which they will be evaluated by the
3.17 On 2 April 2020, the UK Government published a raft of Building Safety Regulator. The information submitted during
proposals for a reformed building safety regulatory system in its headway through all three Gateways will form part of what is
response to the Building a Safer Future consultation (Response), termed the ‘golden thread’ of digitally stored data, which will
which ran from 6 June 2019 to 31 July 2019. be updated and made accessible throughout the lifecycle of the
The April 2020 Ministry of Housing, Communities and Local building.
Government publication: A reformed building safety regulatory
system Government response to the ‘Building a Safer Future’ 3.24 Gateway one will have to be passed before planning per-
consultation explains the changes proposed. mission has been granted, and will concentrate on fire safety
The measures proposed by the Government will be set out issues, such as emergency fire vehicle access and whether there
in more detail in the yet to be published Building Safety Bill, are adequate water supplies available in the event of a fire.
but the Response gives a clear indication as to what we can
expect in the Bill and will be of interest to all involved in the 3.25 The intention is for Gateway two to be passed prior to the
development, design, construction, ownership, and management start of construction. However, the Building Safety Regulator
of buildings. will be allowed to permit a staged approach to construction to
prevent delay on a project (e.g. by permitting piling works) if
3.18 The Government intends to deliver on these objectives by certain information required to pass Gateway two on a complex
establishing a new, national Building Safety Regulator at the build remains outstanding.
What architects need to know: key areas 163

At Gateway two, the Client will be obliged to submit vari- the new regime is expected to work for existing buildings during
ous information to the Building Safety Regulator in order to the course of 2020.
demonstrate how the building meets applicable regulations and
sufficiently manages safety risks. The Building Safety Regulator
may seek additional information from the Client or reject an
Going forward
application to progress through Gateway two outright. As a 3.30 Prior to announcement of the Government’s Response,
result, the Government states that Gateway two will be a ‘hard considerable progress had already been made in building and
stop’ before the Building Safety Regulator gives permission fire safety in the UK, and it is notable that on the same day
for construction to begin although, as noted above, a staged the new measures were announced, the latest non-ACM clad-
approach may be permitted. It should be interesting to see the ding testing results were released by the Building Research
detail as to how they envisage the staged approach to work when Department showing that none of the materials tested (includ-
the legislation is published. ing high pressure laminate (HPL), timber, zinc, copper, and
Building professionals need to be aware that during construc- aluminium honeycomb cladding) behaved in the same manner
tion, the Building Safety Regulator will still have the power to as ACM.
issue ‘stop’ and ‘improvement’ notices as construction works If enacted, the current proposals will clarify and, in all likeli-
proceed. Failure to respond to an improvement notice may lead hood, increase the liability for architects, designers, engineers,
to the regulator issuing a stop notice, which would require some and contractors responsible for ensuring the fire safety and
or all work on site to cease. structural integrity of a building. Nonetheless, the majority of the
measures, particularly the new system of duty-holders, are likely
3.26 Gateway three will have to be passed before occupation of to be widely welcomed in the construction industry.
the building is permitted, although the current proposals state
that the Building Safety Regulator will be allowed to permit
partial occupation before the building is completed. At Gateway
Non-fre-related health and safety
three, the Client will be required to submit various information 3.31 Construction sites can, of course, be dangerous places
on the final, as-built building (including updated, as-built plans). for reasons other than fire safety, and the implementation and
The Client, Principal Designer, and Principal Contractor will be proper management of adequate and suitable health and safety
required to produce and sign a final declaration confirming that measures is vital in the construction industry to reduce the risk
to the best of their knowledge the building complies with the of accidents and sickness.
building regulations.
3.32 Fines imposed for breach of these statutory duties are
escalating, and in certain circumstances it is possible for an
The Accountable Person and individual to be imprisoned for up to two years or face worse
Building Safety Manager sanctions for breach of duties imposed under the Health and
3.27 Once Gateway three is passed, a new duty-holder for the Safety at Work, etc., Act 1974 (‘HSWA’).
occupation phase, the ‘Accountable Person’, will be responsible The maximum sentence for health and safety offences
for taking the appropriate steps and actions to mitigate and man- depends on the date that the offence was committed and the
age the fire and structural risks in their buildings. court that passes sentence. This is because the Health and Safety
The Accountable Person will be the individual, partnership, (Offences) Act 2008 increased penalties for some offences
or corporate body with the legal right to receive funds through committed post 16 January 2009 (by increasing the maximum
service charges or rent from leaseholders and tenants in the fine and introducing imprisonment for certain offences), and
building. Any person or company may find itself designated an section 85 of the Legal Aid, Sentencing and Punishment of
Accountable Person if they subsequently take ownership of the Offenders Act 2012 (which came into force on 12 March 2015)
property. As a result, identifying the Accountable Person could had the effect of increasing the level of most fines available for
be quite complex, given some of the ownership structures of magistrates’ courts to an unlimited fine (previously £20,000 for
buildings caught by the new regime, though the Response states most health and safety offences).
that the Government will provide comprehensive guidance in
due course. 3.33 As described above, the starting place for the current law
The Accountable Person will be responsible for appointing on health and safety matters is the Robens Report in 1972. This
a Building Safety Manager and ensuring the Manager has the was the immediate precursor to the HSWA.
resources necessary to report on and manage various aspects of
a building’s safety, including engaging with residents on the safe Construction’s safety record
management of their buildings through the implementation of a
Resident Engagement Strategy, which will be reviewed by the 3.34 The construction industry’s record is getting steadily bet-
Building Safety Regulator. ter. The number of fatal injuries to workers in construction in
2018–2019, at 30, is the lowest number on record. Over the last
3.28 As with the construction phase, the Building Safety five years that number has ranged between 30 and 47, whereas
Regulator will have the power to issue a ‘compliance’ notice, in early years, it was measured in the hundreds.
which will require remedial action to be taken. The Response Of the main industrial sectors, construction, agriculture,
states that the breach of any of ‘compliance’, ‘stop’, or ‘improve- and waste and recycling consistently have the highest injury
ment’ notice will be a criminal offence under the proposals, and accident rates. The HSE fatal injuries in Great Britain
although it gives no guidance at this stage as to what the ‘penal- 2019 study sets out the main kinds of fatal accident for work-
ties’ may be for a breach. ers. No surprises that falls from heights lead, followed by being
struck by a vehicle and being struck by a moving object.
The most dangerous vocations within construction are scaf-
Existing buildings under the new regime folding and roofing, and even with all the safety and technical
3.29 Current multi-occupied residential buildings above 18m guidance around scaffolding, it is still classed as one of the most
or six storeys in height will fall under the new, more stringent dangerous jobs in Britain.
regulatory regime, and the Accountable Person will be required Broadly, since the Building (Safety, Health and Welfare)
to obtain a Building Registration Certificate at Gateway three in Regulations 1948, health and safety on construction sites, or the
a similar way to that required for new builds. The Government is lack of it, has thus unsurprisingly been the subject of intermittent
expected to set out further details on how the transition period to legislation over the last 72 years or so.
164 Health and Safety law affecting architects

The Construction (Design and 2007. Importantly, unlike its predecessors, CDM 2015 applies
Management) Regulations to a domestic client, too, and saw this threshold lowered to
include projects of a smaller size within the ‘notifiable’ band. It
3.35 The Construction (Design and Management) Regulations contains a more detailed (and crucially lowered) project notifica-
(‘CDM’) are probably the next most important regulatory area tion threshold (30 days and 20 or more operatives on any one
for the construction professional and are invoked via a Statutory day, or 500 person days [i.e. 30 days with 16.66 (17) workers
Instrument, therefore forming part of UK delegated legislation. or 250 days with 2 workers]).
They are based on a European ‘Construction Sites Directive’, The client can, however, agree with the principal designer
EU Directive 92/57/EEC (OJ L245, 26.8.92). that the latter will perform the client’s duties. Consultant archi-
tects should be aware that they may be required to take on the
3.36 The CDM Regulations place legally enforceable collective responsibilities of the principal contractor, a contractor, and a
duties on all those involved with a construction project to plan, designer, particularly on smaller projects or where its capabili-
control, and coordinate their work, and cooperate with others to ties extend to contractor-type roles. CDM 2015 thus applies to
ensure the effective management of risks to health and safety of domestic clients (that is, those not acting in the course or fur-
anyone affected by the construction and subsequent operation of therance of business, whether for profit). However, they include
the building. They also identify specific duty holders and their provisions easing a domestic client’s compliance burden.
responsibilities. One of the underlying reasons for some of the changes in
approach and language in CDM 2015 was the government’s
3.37 Failure to comply with CDM can result in prosecution in desire to follow more closely the requirements of the Temporary
the criminal courts, leading to significant penalties, both finan- or Mobile Construction Sites Directive (Directive 92/57/ECC).
cial and reputational. Increasingly, companies look carefully at There is no exclusion or modification where the client is an
the safety record of potential business partners, and requests for unincorporated association, a group of volunteers, a charity, or
details of any safety convictions have become standard on tender a sports club.
questionnaires. The damage caused to a business’ reputation by
a criminal conviction could last longer than the initial financial 3.42 Other key changes made by the CDM 2015 include abol-
outlay. In the construction industry, it is common to require that ishing the role of CDM Co-ordinator. A principal designer must
organisations submit their health and safety policy as part of the now co-ordinate the pre-construction phase, further enhancing
tender documentation when bidding for work. the role of the client. The gradual shift of placing key health and
safety responsibility on the client continues. Another feature is
3.38 Understanding CDM 2015 is essential for anyone involved simplifying how parties assess competence, including organisa-
in or advising on construction, development, or redevelopment tional competence.
work in the UK. At the advent of CDM in 1994, construction
output in the UK was £41 billion per annum and contributed 3.43 The RIBA has produced a checklist of all the information
5.6% of GDP (in 2019, it was more than £110 billion per annum architects are likely to need, particularly when fulfilling the role
and contributed 7% of GDP) yet it was an industry with a poor of Principal Designer, on this link titled CDM 2015 Tools for
safety record that needed improving. Architects: see https://www.architecture.com/knowledge-and-re
The CDM were radical in their focus of attention on the sources/resources-landing-page/cdm-2015-tools-for-architects
project team, and their efforts directed on the health and safety
aspects of the project, to improve the planning and management 3.44 However, whilst the former CDM Regulations 2007 were
of projects, to facilitate the early identification of hazards, and published with an Approved Code of Practice (ACoP), CDM
to place responsibilities and efforts where they can most benefit 2015 is not accompanied by an ACoP, and in May 2016, the HSE
health and safety. decided that the CRM Regulations 2015 will not be supported
by an ACoP in any event.
3.39 Like many things, they have changed and developed over
time. The history of CDM goes back over 25 years, with the 3.45 The introduction of CDM legislation saw a string of
Construction Design and Management Regulations 1994. The prosecutions by the HSE. The HSE keeps an online register of
1994 version was replaced by the Construction (Design and enforcement, information on notices, and convictions for Great
Management) Regulations 2007, which aimed to clarify and Britain: see https://www.hse.gov.uk/enforce/convictions.htm.
improve the regulations which they superseded and came into These prosecutions and publications gave meat to the bones
force on 6 April 2007. The CDM Regulations 2007 were in of the Regulations by showing the type of incident that would
turn superseded by the Construction (Design and Management) be prosecuted and the effect of health and safety issues on the
Regulations 2015, which came into force on 6 April 2015, and normal contractual relationship. Several Crown Court cases have
form a key part of the current health and safety legislation affect- provided a stark reminder of the serious potential consequences
ing all construction and engineering projects, including work for for company directors found in breach of health and safety leg-
domestic households. islation. In extreme cases, company directors are imprisoned for
gross negligence manslaughter following the death and serious
3.40 The CDM Regulations 2015 are aimed at redressing the injury of operatives/employees working at height.
areas in which the original legislation was either inadequate or In terms of the prosecutions, the HSE, in its early days, fol-
incomplete, in much the same way that other areas of practice lowed the spirit of the legislation and focused upon the ‘client’
have changed or developed over time. In a similar fashion, as target, but at the same time held the designer responsible,
architects (and others) who pilot drones to survey and measure in some cases, for failing to warn the client adequately of his
sites must, since 30 November 2019, not own or use a drone/ responsibilities. The case law that has developed highlights the
unmanned aerial vehicles (UAV) weighing more than 250g and increasing importance of architects being thoroughly familiar
less than 20kg unless they are registered with the Civil Aviation with and adhering to health and safety legislation. In terms
Authority, and they must not be flown until a free online test of the amendments to the standard forms of contract, these
has been passed by the pilot. One cannot fly above 400 feet in have increased the grounds for extensions of time and loss and
altitude or 500 metres from the controller and must ensure the expense for the contractor arising from the performance of the
drone is always in line of sight: see the CAA Drone Code. officeholders for health and safety purposes. See JCT DB 2016,
clause 3.16, by which each Party undertakes to the other that in
3.41 The key change from CDM 2007 is that CDM 2015 now relation to the Works and site, he will duly comply with appli-
applies to projects that were not previously caught by CDM cable CDM Regulations.
Existing health and safety position 165

4 Existing health and them informed of any risks that need to be controlled during the
construction phase.
safety position
Health and Safety at Work Act 1974 Liability under the Act and Regulations
4.01 Before 1974, approximately 8 million employees had no 4.06 Breaches of the HSWA or of the regulations brought in by
legal safety protection at work. As outlined above, the HSWA it (the Workplace (Health, Safety and Welfare) Regulations 1992,
provides the legal framework to promote, stimulate, and encour- or the ‘HSW Regulations’) give rise to criminal liabilities which
age high standards of health and safety in places of work and may lead to sentences of unlimited fines and/or a maximum
on construction sites. It protects employees and the public from term of imprisonment not exceeding 2 years. They cover a wide
work activities. range of basic health, safety, and welfare issues and apply to
most workplaces (except those involving construction work on
4.02 The HSWA enacted a system progressively to replace the construction sites). New sentencing guidelines were introduced
older law, which had grown up piecemeal and which addressed on 1 February 2016 and introduced higher fines and prison sen-
only certain types of workplaces or processes (such as under the tences for anyone who breaches the CDM regulations.
Factories Act 1961 and the Offices, Shops and Railway Premises
Act 1963). The old system had left other workplaces uncovered 4.07 The policy of the HSE in enforcing the HSW Regulations
by the legislation, and the HSWA provided the framework for has been to prosecute and fine an organisation rather than an
a system of regulations applying generally to all workplaces, individual, although that has been changing, and individuals
employers, and employees. It also extended to many self- are now being prosecuted and imprisoned. However, the HSE’s
employed persons and to others such as manufacturers, design- enforcement policy emphasises the importance of prevention
ers, and importers of articles to be used at work. over prosecution. Codes of practice are regularly issued with
the relevant HSW Regulations, and these are used to flesh out
4.03 Examples of the regulations which were brought in under the Regulations concerned. Breach of the codes is not, in itself,
the new policy were those then covering the protection of eyes breach of the HSW Regulations, but the codes are admissi-
(the Protection of Eyes Regulations 1974; now regulation 4 of ble in criminal and, indeed, in civil proceedings to determine
the Personal Protective Equipment at Work Regulations 1992), whether or not there has been a breach of the HSW Regulations.
noise (the Noise at Work Regulations 1989; now the Control Compliance with the relevant code raises the (rebuttable)
of Noise at Work Regulations 2005), the use of lead (the presumption that the HSW Regulations themselves have been
Control of Lead at Work Regulations 1980; now the Control of complied with.
Lead at Work Regulations 2002), the use of asbestos (Control
of Asbestos at Work Regulations 1987; now the Control of 4.08 At the time of writing there have been 95 prosecutions
Asbestos Regulations 2012), the control of industrial major haz- under CDM since the latest version came into force in 2015.
ards (Control of Industrial Major Accident Hazard Regulations 46 of those prosecutions occurred in 2018, which also saw the
1984; now the Control of Major Accident Hazards Regulations largest fine to date under CDM 2015 (£800,000) and the first
2015), and the control of substances hazardous to health (Control prison sentence. This was in 2018, and the Manchester-based
of Substances Hazardous to Health Regulations 1988; now the property developer was sentenced to eight months in prison for
Control of Substances Hazardous to Health Regulations 2002). breaches under CDM. The primary breach was under part 4 of
the regulations for the stability of structures. This was a serious
case, involving the uncontrolled partial collapse of a structure.
Structure of the Act There were 305 prosecutions under the previous CDM
4.04 Sections 2–4 and 6 place general duties on employers, the 2007 version, with the largest fine being £1.5m in a
self-employed, persons otherwise in control of premises, and 2016 prosecution.
designers, manufacturers, importers, or suppliers of articles for While that is more prosecutions overall compared to CDM
use at work. The duties imposed on the client/employer are not 2015, prosecutions under the 2015 version only really started
absolute (in that the words ‘so far as is reasonably practicable’ hitting the courts in 2016, as cases take time to prepare.
commonly preface the obligations) although there is a heavy It seems there were only eight prosecutions under CDM 1994,
burden to prove that he or she has discharged his duty. which, as far as trends go, certainly shows that there has been a
Section 6 refers to the duties of designers, together with those huge increase in action taken by the HSE in more recent years.
who manufacture and import or supply an article for use at work. The average fine resulting from prosecutions under CDM 2015 is
The general obligation is: about £71,000 currently.

To ensure, so far as is reasonably practicable, that the article 4.09 In the context of civil liability, there are two potential
is so designed and constructed that it will be safe and without limbs: first, the tort of breach of statutory duty, which is a
risks to health at all times when it is being set, used, cleaned ‘strict’ liability in the sense that it is not qualified by what is
or maintained by person at work. reasonable in the context of the profession at large (although the
statutory duties in the Regulations themselves are usually quali-
The structure of the HSWA is, therefore, divided into general fied by statements such as ‘so far as is reasonably practicable’);
obligations under the Act itself and more specific obligations and, second, the tort of negligence, which arises from common
under the existing body of regulations. standards becoming established in the profession of which the
reasonable architect is deemed to have knowledge and breach
of, which thereby renders the architect liable.
Buildings and construction sites
4.05 The HSE has, in a number of cases, applied the general 4.10 Breach of the provisions of the HSWA does not itself give
obligation in relation to buildings and construction sites. This of rise to a civil action for breach of statutory duty. However, if
itself is not surprising, given the CDM 2015 duties of designers, there is a breach of the HSW Regulations, this may enable a
Regulation 11 concerning the principal designer’s health and claimant to cite the breach as a basis for a civil claim, depending
safety obligations in the pre-construction period, and Regulation upon whether the specific HSW Regulations allow such a claim
13 duties of a principal contractor in relation to health and and whether the claimant’s interest is intended to be protected by
safety at the construction phase, during which the principal the Regulations. Under the CDM 2015 Regulations, for example,
designer must also liaise with the principal contractor, keeping regulation 12 provides that the construction phase of any project
166 Health and Safety law affecting architects

cannot commence until the construction phase plan is drawn up 4.16 The current CAR12 came into force on the 6 April 2012 and
(during the pre-construction phase) and before the construction replaced the Control of Asbestos at Work Regulations 2006,
site is set up. The construction phase plan is a health and safety the Asbestos (Licensing) Regulations 1983, and the Asbestos
management document for the project. It will include details of (Prohibitions) Regulations 1992. The CAR12 comprise more
the work that is being done, the project team, and emergency than an update to previous asbestos regulations. The revised
arrangements. Thus, unless a compliant construction phase plan Regulations came as a result of the European Commission’s
has been prepared, this can give rise to civil liability without the view that the regulations of 2002 and 2006 had not fully imple-
need to prove negligence or breach of contract. mented the EU Directive on exposure to asbestos. The CAR12
imposes a duty in relation to ‘nondomestic premises’ to man-
4.11 Inevitably, the influence of the Regulations will affect age asbestos risk and are discussed in greater detail later in the
the law of negligence in setting specific legal standards in the chapter.
context of health and safety. A failure to meet those standards
may represent a breach of duty in negligence, even if the mat- 4.17 The former CAR06 set out the licensing requirements for
ter in question is not specifically covered by the Regulations. work with asbestos and required any business carrying out high
Therefore, liability is not restricted merely to claims based upon risk work with Asbestos Containing Materials (‘ACMs’) to hold
breach of statutory duty but also, indirectly, in the tort of neg- a licence before they can undertake such work. This effectively
ligence. In addition, the requirement for employers to carry out created two categories of work with asbestos: (a) licensed work,
risk assessments is likely to be of significance when considering to which all the requirements applied; and, (b) non-licensed
questions of foreseeability at common law. work, which is exempt from certain requirements, including
notification, medical examinations, and registers of work (also
known as health records).
Relevant regulations
4.12 There are a large number of health and safety regulations 4.18 However, in 2006, a complaint was made to the European
in addition to the CDM Regulations and Control of Asbestos Commission alleging under-implementation of Article 3 of
Regulations which, while not necessarily specific to the con- Directive 2003/18/EC, which was designed to strengthen protec-
struction industry, certainly affect the work of some architects tion for maintenance workers. As a result of its investigation, the
on refurbishment projects. Many of these regulations apply to Commission issued a reasoned opinion in 2011 relating to the
the duties of employers in the workplace. As such, the architect omission of the terms ‘non-friable’ and ‘without deterioration of
must have a general knowledge of these when designing such non-degraded material’ from Regulation 3 of CAR 2006, which
workplaces in order to avoid risks to the health of employees exempts ‘low risk’ work with asbestos from certain duties in the
and generally to allow them to be safe. These regulations include regulations. In the Commission’s view, the omission of these
those set out below. terms had the effect of widening the scope of the exemption.
CAR 2012 subsequently made the changes required to comply
with the reasoned opinion, but avoided inappropriately extend-
Control of Asbestos Regulations ing the application of the UK requirement to hold a licence to
2012 (CAR12) short-term, low-risk work. CAR12 achieved this by de-coupling
the exemption for licensing from the other exemptions and
4.13 Asbestos is a naturally occurring mineral and was used in separately defining the work for which a licence is required. The
the UK extensively for about 150 years until the late 1990s. It detail is beyond the scope of this book.
was versatile, abundant, and ideal as a fireproofing and insu-
lation material and, as a result, was used for many different 4.19 These changes in CAR12 resulted in more clearly defining
purposes, and heavily in construction before the health hazards three categories of work with asbestos:
it posed were fully understood in the late 1920s. Although the
importation, supply, and use of asbestos have now been banned (i) Licensed work – this is work where the concentrations of
(for blue and brown asbestos since 1985; for white asbestos asbestos fibres in the air during work activity are likely
from 1999) and much of the material has been removed, it is to exceed specified limits or involve specific ACMs. This
still present in a large number of buildings. includes large-scale asbestos removal and building refur-
Following the prohibition on import, supply, and use of bishment/demolition work, and can only be carried out by
asbestos, and improved working conditions, the risks for many licensed contractors, and to which all requirements apply;
workers in new build have been virtually eliminated. A formal (ii) Notifiable non-licensed work – this is work where concen-
ban on the use of all types of asbestos is now in place and trations of asbestos fibres during work activity are unlikely
extends to all European Member States. However, building to exceed specified limits, and the activity is sporadic and of
maintenance workers and tradespeople remain at significant low intensity. It does not need to be carried out by licensed
risk, as they may be unknowingly exposed to asbestos-con- contractors but is subject to the specific requirements (a)–
taining materials that remain in place in buildings. Asbestos (c), as outlined above; and
remains the single greatest cause of work-related deaths in the (iii) Non-licensed work – this work is where the concentrations
UK. of asbestos fibres in the air during work activity are likely
The time between exposure and disease varies widely. It is to be low, and covers such activity as maintenance and
a grim statistic that around 20 tradespeople die each week from small-scale asbestos work, and does not therefore require
asbestos-related disease. notification. This work is exempt from the requirements to
notify, carry out medical examinations, and keep registers
4.14 Refurbishment, alteration, and demolition projects are of work.
affected by asbestos in buildings. Material condition and type
are key factors in the danger presented. 4.20 An instructive case illustrating how an architect can get
in to trouble and be prosecuted in this area through negligence
4.15 Asbestos removal is a specialised function. Proper decon- is R v Dilwyn Roberts Penseiri/Architects Ltd (2012), where
tamination facilities are needed for the workforce, and a dedi- a practice was prosecuted after contractors were potentially
cated transit route must be provided to an enclosure kept under exposed to dangerous asbestos mineral fibres during construc-
negative pressure. Airlocks must be in place at the enclosure for tion work at Aberystwyth Rugby Club. Dilwyn Roberts Penseiri/
air movement control and to permit those working to carry out Architects Ltd failed to pass on vital information about the pres-
preliminary decontamination procedures. Asbestos waste must ence of asbestos insulation board to the contractors before they
be double-bagged in labelled asbestos bags and properly stored removed soffits from an end wall at the clubhouse. The situation
in lockable skips on the transit route. came to light during a routine inspection of the work by an HSE
Existing health and safety position 167

inspector, who found remains of damaged asbestos insulation working at height. It reported on 26 February 2019: Report:
boards on the gable end of the clubhouse. A subsequent HSE Staying Alive: Preventing Serious Injuries and Fatalities While
investigation found that Dilwyn Roberts Penseiri/Architects Ltd Working at Height. The APPG report makes four key recom-
had been appointed to design and oversee the work at the club- mendations to reduce fall numbers:
house and to act as the Construction, Design and Management
Co-ordinator (CDM 2007 applied) for the project. Although an (i) The introduction of an enhanced reporting system through
asbestos survey was commissioned by the rugby club and sent RIDDOR, which, at a minimum, records the scale of a fall,
to the architects, this was never shown to the contractors, even the method used and circumstances surrounding it.
though it clearly identified the presence of asbestos insulation (ii) Appointing an independent body to allow confidential,
board. When the work was tendered, the practice prepared the enhanced, and digital reporting of all near misses and acci-
pre-construction information and advised that an asbestos survey dents that do not qualify for RIDDOR reporting to be shared
had identified asbestos cement in the soffits, but not the asbes- with government and industry and inform Health & Safety
tos insulating board. Unlike asbestos cement products, asbestos Policy.
insulation board requires removal by licensed companies under (iii) Extending the Working Well Together: Working Well at
strictly controlled conditions. When the building contractor Height safety campaigns to industry outside of the construc-
removed the soffits on the end wall, it had not recognised the tion sector.
material as asbestos boards. Dilwyn Roberts Penseiri/Architects (iv) Adopting an equivalent system to Scotland’s Fatal Accident
Ltd, pleaded guilty and was fined and ordered to pay costs. Inquiry process across the UK.

4.21 Construction Design and Management Co-ordinators (as 4.26 It is to be noted you are working at height if you:
with the ‘Principal Designer’ under CDM 15 where there is more
than one contractor) are required to identify and collect pre- ● Work above ground/floor level;
construction information for projects. It should contain all infor- ● Could fall from an edge, through an opening or fragile
mation relevant to the health and safety of people engaged in, surface; or
affected by the work, or using the building as a future workplace. ● Could fall from ground level into an opening in a floor or a
hole in the ground.
Work at Height Regulations So, architects should think before scaling a ladder up a scaffold
2005 (WAHR) or taking a hoist.
4.22 The purpose of the Work at Height Regulations 2005
(WAHR) is to prevent death and injury caused by a fall from 4.27 Work at height does not include a slip or a trip on the level,
height. Employers and those in control of any work at height as a fall from height has to involve a fall from one level to a
activity must make sure work is properly planned, supervised, lower level, nor does it include walking up and down a perma-
and carried out by competent people. Falls from height are one nent staircase in a building.
of the greatest causes of injuries and death in the UK. Operatives
also have duties to each other. Workplace (Health, Safety and
4.23 The 2005 WAHR create a distinct regulatory regime for
Welfare) Regulations 1992
working at height, and prosecutions are regularly brought 4.28 These Regulations extend the duties of employers into areas
under the more general HSWA or the Construction (Design not previously the subject of specific statutory provisions, such
and Management) Regulations. Recent corporate prosecutions as hospitals, schools, universities, hotels, and court houses.
show significant sentences for both fatal and non-fatal incidents,
including the 2016 prosecutions of both Tesco Stores Ltd and 4.29 They form part of what is known as the ‘six pack’, a group
Tesco Maintenance Ltd for an incident in which an employee of the following six regulations: the Management of Health
fell 30 feet through a skylight, but suffered only minor injuries. and Safety at Work Regulations; the Display Screen Equipment
The companies were fined £200,000 and £300,000 respectively, Regulations; the Manual Handling Operations Regulations;
plus costs. Fines of this type are a firm reminder of the fact that the Personal Protective Equipment at Work Regulations; the
health and safety offences are concerned with failures to manage Provision and Use of Work Equipment Regulations; and the
risks, and do not require proof that the offence caused any actual Workplace Health, Safety and Welfare Regulations.
harm. Both cases are important reminders to employees work-
ing in the construction, manufacturing, and similar industries to 4.30 These Regulations cover a wide range of basic health,
take reasonable care of their own health and safety, as well as safety, and welfare issues and apply to most workplaces (with
the health and safety of others. The obligation to minimise risk the exception of those workplaces involving construction work
includes a duty to take reasonable care for your own safety and on construction sites, those in or on a ship, or those below
health. The message is stark: adopting a highhanded attitude to ground at a mine). They are amended by the Health and Safety
personal risk will not be tolerated. While this may at first seem (Miscellaneous Amendments) Regulations 2002, the Work at
harsh, it is worth bearing in mind that assumption of unnecessary Height Regulations 2005, and the Construction (Design and
personal risk in high-risk workplaces often has potential conse- Management) Regulations 2015.
quences for others – for example, the risk of potential injury or
death from falling tools or materials. 4.31 Just because the regulations do not apply to construction
sites does not detract from their importance. Architects have a
4.24 Work at height guidance was overhauled in 2014 in the legal duty to make clients aware of their responsibilities and
hope that the incidence of falls could be reduced ‘by giving give due regard to health and safety in their design work. The
simple and clear advice and tackling the myths that can confuse designer must also provide adequate information about the
employers’. Despite this, falls from height and falling objects health and safety risk of the design to those who need it and
from height remain one of the main causes of fatal accidents cooperate with the planning supervisor and, where appropriate,
at work; particularly in the construction industry, where they other designers involved in the project. For example, in accord-
account for 49% of total fatal accidents, according to HSE ance with EU regulations for now in transition until the end
statistics. of 2020 (see The Health and Safety [Amendment] [EU Exit]
Regulations 2018), these are designed to ensure that European
4.25 In 2018, an all-party parliamentary group (APPG) was set Union-derived health and safety protections will continue in
up to seek industry responses on a number of questions around domestic law after the UK leaves the EU.
168 Health and Safety law affecting architects

4.32 Thus, the construction of floor and traffic routes should be is no alternative, and that if such work goes ahead, then the
suitable for their purpose. There should not be holes, slopes, necessary PPE and training must be provided. More than simply
unevenness, or slippery surfaces that would present risks to any providing the equipment, employers need to make sure that it
person’s safety. There should be effective drainage where neces- is always available when needed, that it is in suitable working
sary. The requirement for floors not to be slippery is contained condition, that clear instructions are given, and that its use is
in Reg. 12 (2) of the Workplace (Health, Safety and Welfare) clearly enforced.
Regulations, 1992. This is an exacting and absolute standard,
which overrides the normally quoted i.e. ‘so far as is reasonably 4.40 Section 9 of the Regulations makes it clear that under no
practicable’. circumstances should there be any charge to an employee requir-
ing PPE equipment (an issue during the C-19 pandemic), and
4.33 The Regulations require that the workplace, equipment, that the employer should provide all the necessary equipment for
devices, and system shall be maintained in an efficient state, in free. The equipment must also be regularly checked for damage
efficient working order, and in good repair. Thus: and effectiveness, with special attention being paid to specific
requirements, such as the use-by dates of hard hats.
● Adequate lighting, heating, ventilation, and workspace (and
keep them in a clean condition); 4.41 The employer’s obligations relate to the suitability of pro-
● Staff facilities, including toilets, washing facilities, and tective clothing to be worn by employees. In the case of Fytche
refreshment; and v Wincanton Logistics plc [2004] UKHL 31, the Claimant, Mr
● Safe passageways, i.e. to prevent slipping and tripping Fytche, was a Heavy Goods Vehicle driver who collected milk
hazards. from farms at night. He was provided with steel-cap safety boots.
There was a small hole in his right boot where the steel-cap met
4.34 Specifically, the Regulations specify suitable provision for the sole. He suffered frostbite one night in the little toe of his
the ventilation, temperature, lighting, cleanliness, and removal right foot. He claimed from his employer, alleging amongst
of waste materials, sufficient working area, and suitable worksta- other things, that the employer was in breach of Regulation 7(i)
tion provision. There are a number of provisions relating to the of the 1992 Regulations, which imposed an absolute duty on
condition of floors, windows, skylights, doors, gates, escalators, the employer to keep personal protective equipment in efficient
sanitary conveniences, and washing facilities. Where the work- working order and good repair. The claim was dismissed.
place is a building, the regulations now require the workplace to The Decision (by a majority of 3:2) found Mr Fytche was
be appropriate for the use to which it is to be put. provided with steel toe caps on his boots because his employers
considered there was a sufficient risk of heavy things falling on
4.35 Regulation 11 covers workstations – they must be suitable his feet. The boots were therefore PPE, and there was nothing
for both the work to be done and the person doing the work, to suggest that they failed any of the tests of suitability. They
there must be a suitable seat, if appropriate, and a footrest must fitted and were appropriate for conditions in milk parlours and
be provided if needed. Workstations outside must, where reason- so on. The hole in one of the boots did not create a second-
ably practicable, protect the worker from adverse weather and ary risk or increase overall risk. The secondary or overall risk
be easy to evacuate in an emergency. must be a risk in the course of employment. Mr Fytche was not
expected to do anything requiring him to have waterproof boots,
4.36 Regulation 12 states that every floor and the surface of all and therefore the hole created no such risk. If there had been a
traffic routes within a workplace must be suitably constructed weather risk against which the boot should have protected him,
and should be kept as free as possible from any obstructions that then he would have been able to recover, but the Claimant did
could cause slips, trips, or falls. not suggest that he should have been given PPE to protect him
against the weather. On the assumption that the hole was present
when Mr Fytche was issued with his boots, there was therefore
Personal Protective Equipment no breach of Regulation 4.
Regulations 2002 Regulation 7 provides that every employer should ensure that
4.37 The Personal Protective Equipment Regulations were intro- any personal protective equipment provided is maintained in an
duced to the UK in 1992 and updated in 2002. These regulations efficient state, in efficient working order, and in good repair. Mr
explain the duties employers have regarding the provision and Fytche argued that the boot, which had developed a hole, was
use of PPE equipment. For example, employers must ensure not in good repair and that therefore there was a breach. The
that protective equipment is provided free of charge, that staff court held that regulation 7(1) of these Regulations imposed an
are trained on how to use it, and that equipment is maintained, absolute duty on employers to make sure protective equipment
repaired, and replaced when needed. With C-19 PPE, availability was kept in good condition. However, that duty only applied to
for operatives has been brought sharply in to focus like never risks against which the equipment was supposed to protect the
before. employee. In this case, steel toe-capped boots were provided
to the employee to protect his feet from falling objects. A tiny
4.38 It is up to each individual company to make sure these hole in the boots caused the employee to sustain frostbite, but
regulations are followed and carried out, not just to comply with the employer was not liable for this injury, as the boots were not
the law (which is only the minimum requirement) but also to intended to protect the employee from that type of harm.
ensure that their most important assets are protected. One of the
key ways of doing this is with personal protective equipment, Manual Handling Operations
or PPE, as it is commonly known.
Regulations 1992 (MHOR)
4.39 Regulation 4 of the 1992 Act states: 4.42 The MHOR impose obligations on an employer to avoid a
manual handling operation where there is a risk of injury from
Every employer shall ensure that suitable personal protective such an operation. MHOR were slightly amended by the Health
equipment is provided to his employees who may be exposed and Safety (Miscellaneous Amendments) Regulations 2002
to a risk to their health or safety while at work except where (SI 2002 No 2174), with effect from 17 September 2002. The
and to the extent that such risk has been adequately controlled Regulations define manual handling as:
by other means which are equally or more effective.
any transporting or supporting of a load (including the lifting,
The accompanying guidance clarifies that work which endan- putting down, pushing, pulling, carrying or moving thereof)
gers health and safety should only be carried out when there by hand or bodily force.
Existing health and safety position 169

The load can be an object, person, or animal. Architects and Architectural Technicians have been on screens
and off drawing boards for 20 years or so since the advent of
4.43 The MHOR 1992 set out a clear ranking of measures for CAD and bespoke modelling software, these Regulations apply
dealing with risks from manual handling, these are: to all those staff.
The employer must ensure that all display screen equipment
● First – avoid hazardous manual handling operations so far which may be used for the purposes of the employer business
as is reasonably practicable; meets the requirements set out in the Regulations. The employer
● Second – assess any hazardous manual handling operations is under an obligation to make a risk assessment of workstations
that cannot be avoided; and used by employees of the relevant risks to health and safety
● Third – reduce the risk of injury so far as is reasonably from the operation and reduce the risks to the ‘lowest extent
practicable. reasonably practicable’. Employers must ensure that employees
take regular and adequate breaks from looking at their screens.
4.44 The employer’s duty is to take steps to reduce the risk of Employees are entitled to ask their employer to pay for yearly
injury to the lowest level reasonably practicable (Regulation 4(1) eye tests by a qualified optician.
(b)). It also requires an employer to make an assessment of the Employers must provide their computer users with adequate
manual handling to be carried out and provide information to the health and safety training for any workstation they work at. This
employee as to the type of load to be lifted. entails showing employees how to properly adjust their chairs
and desks (if adjustable) and the correct way to sit and work at
4.45 The Court of Appeal case of Swain v Denso Marston their workstations.
(2000) ICR 1079 is illustrative of how the Regulations work It requires employers to plan the activities of their ‘users’ so
(see also Sloan v The Governors of Rastrick High School [2014] that there are periodic interruptions in their work on the display
EWCA Civ 1063). An injury was suffered by the claimant when screen equipment. There must be appropriate eye and eyesight
stripping down part of the conveyor system at his employer’s tests for the employees.
premises. To replace bearings, he had to remove various com-
ponents and then the roller itself. Unexpectedly, the roller was
solid metal, weighing about 20 kilograms, and he suffered a
Provision and Use of Work Equipment
crush injury to his right hand when the roller was released. Regulations 1998 (PUWER)
There had been no relevant risk assessment, notwithstanding 4.51 The PUWER place duties on people and companies who
that the employer had a health and safety officer. The conveyor own, operate or have control over work equipment. PUWER also
system was described as ‘specialised plant and machinery’, and places responsibilities on businesses and organisations whose
an assessment would have considered whether repairs and non- employees use work equipment, whether owned by them or not.
routine maintenance should be carried out by the employer’s PUWER requires the risks to people’s health and safety from
staff or the manufacturer, and would have considered the manual equipment that they use at work to be prevented or controlled.
handling tasks involved in repairs and maintenance. The Court The Regulations cover a wide range of equipment, including
held that there was ‘no systematic assessment under the control those found in an office environment, such as 3D printers, photo-
of either an outside consultant or the health and safety officer copiers, scanners, plotters, and binding machines, and potentially
(even if part of the task was delegated to a person who was an drones and robotics, and require employers to ensure that equip-
experienced employee).’ ment provided for employees to use at work is:
4.46 These above three requirements should not be read conjunc- ● Suitable for the intended use;
tively so that breach of any of them could be enough to make ● Safe for use, maintained in a safe condition;
the employer liable. ● Used only by people who have received adequate informa-
tion, instruction, and training; and
4.47 In assessing whether a task involved a risk of injury, and ● Accompanied by suitable safety measures, e.g. protective
in assessing whether it was ‘reasonably practicable’ for an devices, markings, warnings.
employer to avoid his employees being subjected to that risk, it
was necessary to look at the particular activity in context (see In addition to the requirements of PUWER, lifting equipment is
Koonjul v Thameslink Healthcare Services NHS Trust (CA) also subject to the requirements of the Lifting Operations and
[2000] PIQR P123). Lifting Equipment Regulations (LOLER).
4.48 In determining whether the manual handling operations 4.52 ‘Work equipment’ is defined widely, to include anything
involve a risk of injury, and in determining appropriate steps from a pair of pliers to robotic welding machines. There is an
to reduce the risk, regard must be had to such things as the obligation on the employer and on others having ‘control’ of
employee’s suitability to the tasks he or she is carrying out, the work equipment to ensure that work equipment is used only
employee’s clothing, the results of any risk assessment that has for the operations for which, and under conditions for which,
been carried out under the Management of Health and Safety it is suitable. If the equipment has a health risk, the employer
at Work Regulations 1999, and the employee’s knowledge and (or relevant person) must restrict its use and maintenance
training. to specific persons. In 2015, a robot grabbed a worker at a
Volkswagen plant in Germany, crushing and killing him. This
4.49 The importance of an employer giving careful consid- tragic, though uncommon incident has drawn attention to the
eration to the type of tasks it will be asking its employees to growing dangers of robotics and artificial intelligence (AI),
carry out is clear. It is not enough to consider the tasks in their now that robotics in construction are increasing, with super-
own right. The employer will have to address the individual sized 3D printers and robots used for some bricklaying and
employee’s suitability to a task, which is an onerous burden for masonry operations.
the employer.
4.53 The PUWER 1998, as amended by the Health and Safety
Health and Safety (Display Screen (Miscellaneous Amendment) Regulations 2002, are supported by
an Approved Code of Practice (ACOP) and additional free guid-
Equipment) Regulations 1992 and 2002 ance is readily available from HSE. While the ACOPs are not
4.50 The Health and Safety (Display Screen Equipment) law, they were made under section 16 of the Health and Safety
Regulations 1992 (amended 2002) apply to all display screen at Work Act (HSWA) and so have a special status, as outlined
equipment (DSE) including computer screens. Given that most in the introduction to the PUWER ACOP:
170 Health and Safety law affecting architects

Following the guidance is not compulsory and you are free and extend the general duties contained in HSWA and introduce
to take other action. But if you do follow the guidance you a general duty on employers to carry out risk assessments.
will normally be doing enough to comply with the law. Health
and safety inspectors seek to secure compliance with the law 4.59 The basic obligation under these Regulations requires
and may refer to this guidance as illustrating good practice. employers to carry out a ‘suitable and sufficient’ assessment of
the risks to the health and safety of employees to which they
are exposed while at work. The assessment must also consider
Lifting Operations and Lifting Equipment the risks to the health and safety of other people not in their
Regulations 1998 (LOLER) employment, but arising out of their business.
4.54 The LOLER replaced the former Construction and Use
(Lifting) regulations of 1961, which required each piece of 4.60 Section 3 of the Regulations places a duty on all employers
lifting equipment to undergo an overload test every four years. to make (and record, if they have more than five employees) a
These old regulations were replaced because certain types suitable and sufficient assessment of the risks to the health and
of lifting equipment are prone to damage during conventional safety of their employees, to which they are exposed at work.
overload tests. LOLER inspections, which involve a thorough Employers must ensure that there are proper control measures
examination each year, are much less intensive, and therefore do in place to avoid these risks wherever possible. Where it is not
not affect the lifespan of this lifting equipment. As they are able possible to avoid risk, steps must be taken to reduce them, so
to be performed more regularly, they are also better to ensure the far as is reasonably practicable. The purpose of the assessment
performance of lifting equipment. is to identify measures the employer needs to take to comply
with law.
4.55 LOLER places duties on people and companies who own,
operate, or have control over lifting equipment. This includes 4.61 Since 27 October 2003, these Regulations enabled employ-
all businesses and organisations whose employees use lifting ees to bring civil claims against their employers where they are
equipment, whether owned by them or not. In most cases, lift- in breach of duties imposed by these Regulations. It will remain
ing equipment is also work equipment, so the Provision and the case that it is not possible for non-employees to bring such
Use of Work Equipment Regulations (PUWER) will also apply civil claims. This right to bring civil claims will mean that a
(including inspection and maintenance). breach of the Regulations by architects, as employers, can give
All lifting operations involving lifting equipment must be rise to civil liability without the need to prove negligence or
properly planned by a competent person, appropriately super- even a breach of contract.
vised, and carried out in a safe manner.
LOLER is supported by the Safe use of lifting equipment:
Approved Code of Practice (ACOP).
5 Essential health and safety
LOLER also requires that all equipment used for lifting is touchstone summary
fit for purpose, appropriate for the task, suitably marked, and,
in many cases, subject to statutory periodic ‘thorough examina- 5.01 A Client/Employer must make arrangements that, so far as
tion’. Records must be kept of all thorough examinations, and is reasonably practicable, result in the construction project being
any defects found must be reported to both the person responsi- able to be carried out without risks to the health or safety of any
ble for the equipment and the relevant enforcing authority. person affected by the project.

4.56 The Regulations therefore impose duties on employers, 5.02 A Main Contractor (likely to be the ‘Principal Contractor’
self-employed persons, and certain people having control of under CDM) must:
lifting equipment to ensure that the equipment is engineeringly
robust, stable, sited, positioned and installed correctly, exam- (i) Ensure, so far as is reasonably practicable, the health, safety,
ined, inspected, marked, and organised, and, in respect of which, and welfare at work of all its employees;
records are held and maintained. Anyone who hires or loans (ii) Ensure, so far as is reasonably practicable, that persons not
equipment has a responsibility for ensuring that the equipment in its employment who may be affected thereby are not
is regularly examined by a competent person. thereby exposed to risks to their health or safety (this would
include sub-contractors);
4.57 The client, who may also be an employer, will rely upon (iii) Review, update, and revise, from time to time, the construc-
the architect or engineer to advise him whether and what assess- tion phase plan, so that it ensures that construction work is
ments are required and the hazards which must be identified in carried out, so far as is reasonably practicable, without risks
the workplace. He will also rely upon his consultants to advise to health and safety;
him how to avoid any such hazards, and thereby to avoid any (iv) Plan, manage, and monitor the construction work to ensure
potential liability under the Regulations, for example, if in an that, so far as is reasonably practicable, it is carried out
urban environment, a heavy steel or glazing unit or pod has to without risk to health and safety;
be unloaded at great radius distance from a mobile crane that
may be near the safe limit for the reach. According to the HSE, 5.03 All levels of Sub-Contractor must:
lifting operations should be planned on a case-by-case basis.
Routine lifting operations, such as the use of forklift trucks in a (i) Ensure, so far as is reasonably practicable, the health, safety,
factory, only require minimal planning, whereas uncommon and and welfare at work of all its employees;
complex lifting operations should be planned more thoroughly in (ii) Ensure, so far as is reasonably practicable, that persons
accordance to the LOLER ACOP by a competent person. not in its employment who may be affected thereby are not
thereby exposed to risks to their health or safety (this would
include its own sub-sub-contractors);
Management of Health and Safety (iii) Plan, manage, and monitor the construction work to ensure
at Work Regulations 1999 that, so far as is reasonably practicable, it is carried out
4.58 These Regulations impose duties on employers and employ- without risks to health and safety.
ees concerning formal risk assessments, formal management
control systems, health surveillance, procedures for serious and 5.04 Accordingly, a legal obligation is owed not only to one’s
imminent danger, job specific training, and so on. They further own employees, but also to others to ensure that as far as
implement the major provisions of an EU health and safety practicable, they are not placed at risk to their health or safety.
directive – the Framework Directive. The regulations supplement That obligation would include, for example, complying with
Conclusion 171

Government Guidance regarding C-19, and ‘social distancing’, attend site until such time as a main contractor could comply
in so far as that is possible on a site. with the requirements to provide a safe working environment.

6 Application to particular 7 Conclusion


situations 7.01 One thing is clear: clients do not need to be made to be con-
6.01 For as long as C-19 considerations remain, there will be vinced of the commercial and economic arguments to establish
heightened concern amongst Architects as with others involved health and safety as a lead criterion in the selection of contrac-
in any project about the health and safety of site operatives and tors and successful project outcomes. That is so now more than
whether it is safe for them to work on certain building sites in ever before. If anything, this promotes leaner and smarter ways
cramped congested sites. As at May 2020, what is and what of working, which technology and artificial intelligence will
is not ‘safe’ in the context of the Government advice will be accelerate. There is, therefore, a need to educate construction
dependent on individual facts in each case. Simply because clients in matters of health and safety management and broader
providing a ‘safe working environment’ would be inconvenient, issues of construction procurement. The CDM Regulations
or more costly, or delay work on a project, is most unlikely to require designers to inform clients of their health and safety
pass any objective test of ‘not reasonably practicable’. duties under the regulations.

6.02 The current Guidance is clear. If the work cannot safely 7.02 A strategic theme in the Help Great Britain Work Well
be done within these current guidelines at the time of going to Strategy (2016) is Keeping Pace with Change: anticipating and
print, then the work should not take place. This may require a tackling new health and safety challenges is an imperative for
highly detailed analysis of how work might take place. Not only all our sakes, as C-19 has further underscored. Control can be
must all the other listed criteria regarding PPE, handwashing, handed over in some respects: autonomous and unmanned tech-
toilet, welfare, canteen, etc. facilities be met in the light of the nology is already at our doorstep, hand held devices take the
Guidance, but the question of how a particular worker can access temperature of those entering site. Autonomous (self-driving,
and exit each of his or her particular work locations safely and driverless, or unmanned) vehicles are on construction sites, doz-
work, while all the time maintaining all effort with ‘social dis- ers, excavators, load-carriers and haul trucks, as are unmanned
tance’, must be addressed. What C-19 does is add another level aerial systems such as drones, equipped with powerful tech-
of complexity to health and safety on site and in planning, such nology including RADAR, lasers, cameras, global positioning
activity of which the architect must be cognisant. system computers, AI, and 3D maps. Autonomous vehicles can
sense, monitor, and navigate their site environment. They can
6.03 If there are differences in view about whether something be remotely controlled or operate without human supervision or
can be done safely within the guidelines or not, then details need input. They might even be safer, and humans doing less danger-
to be kept, and evidence held for future justification, if ever ous things is to be welcomed, but there have been deaths by
needed. It seems, for example, extremely unlikely that any Court robots in auto manufacturing, and parties must learn from other
would conclude that a sub-contractor had been unreasonable, and areas how to design out risk as we adopt and use more technol-
in breach of contract, if it was able to justify its decision not to ogy. Nothing stands still.
Part C
Building contracts
16
Introduction to procurement
methods in construction
SIMON PLUNKETT

1 Introduction end of the spectrum, there are many ‘one-off procurers’ with
no previous experience. The client’s level of experience will be
1.01 Selecting the most appropriate procurement strategy for a an important factor in the process of choosing an appropriate
construction project of any significant size is unlikely to be as procurement method. The paying party’s attitude to risk and the
straightforward as many might think. The aim should be to pro- level of responsibility it wishes to retain will also be relevant to
vide a suitable contractual framework which takes into account the suitability of any procurement method. This attitude to risk
the complexity of the project, the expertise of the procuring is often directly related to the client’s expertise. For example,
party, and the commercial drivers behind the project. But, of an experienced client may be prepared to take a more ‘hands on’
course, there is a huge range of construction projects, and many approach to a project and carry more of the risk, with the aim
different ways of procuring construction works and services have of reducing the price to be paid. Certain procurement methods
developed as a result. lend themselves to this approach better than others. Similarly,
there are other approaches which can be adopted to insulate an
inexperienced or risk averse client from responsibility and risk.
2 Complexity
3.02 Whilst a professional client experienced in construction
2.01 Construction projects range from the very small and simple projects may be willing to take on more responsibility, a ‘one-
(e.g. those where sole traders carry out straightforward extension off’ client is likely to look for a contractual arrangement that
works for residential occupiers), to the very large and com- places as much responsibility and risk with the delivery team as
plicated (e.g. state-sponsored infrastructure projects involving possible. There are many different procurement models that can
multiple parties, which utilise innovative design and advanced achieve this to a greater or lesser extent, and the final choice of
engineering). The former can often be procured using a simple route will not be governed by this consideration alone – many
contract; the latter most certainly cannot, and are more likely to other factors will come into play.
be procured using a great many inter-related contracts governing
the roles and responsibilities of the parties involved. 3.03 A further relevant question will be whether even the expe-
rienced client has the internal resources to manage the project,
2.02 Where the project is large, complicated, or requiring or whether a third party will need to be appointed to perform the
innovation, there is likely to be a commensurate increase in management function on the client’s behalf. A client who wishes
the complexity of the procurement. There are likely to be more to retain control of the project will have to be prepared to allo-
interested parties, including funders, client, tenants, multiple cate the time or in-house expertise to manage the project. It may
specialist contractors, and consultants, all of whose positions be more appropriate for a client that does not have the neces-
will need to be taken into account in the contractual matrix. In sary expertise or resources to relinquish a degree of control and
such circumstances, it is inevitable that the procurement method appoint an experienced professional to perform the traditional
will need to be sophisticated enough to provide for multiple, client role. Among all these questions, one thing is for sure:
often competing, interests. management of a construction project will be key to its success,
and a failure to recognise this will have a significant impact.
2.03 Provision will also need to be made for the risks inherent in
the complexities of the project. For example, the construction of
a city centre rail system will involve specific risks, such as those 4 Commercial drivers
associated with ground conditions, site access, land acquisition,
and obtaining consents. In the process engineering sector, there 4.01 One also needs to consider the commercial drivers of a
are likely to be demanding performance specifications to be met project and the fact that most clients and other stakeholders will
and liabilities for failing to achieve them. Risks such as these want a high-quality project completed as quickly and cheaply as
will be allocated by the project contracts, describing the roles of possible. Sadly, however, the elements of this ‘trinity’ of high
the parties and how they should interact. quality, high speed, and low price are fundamentally incompati-
ble. Procurement in construction is often, therefore, about finding
the right balance between these objectives and deciding where
3 Client expertise priorities lie. Questions need to be put and answers sought. More
often than not, in the commercial world, the answers come from
3.01 Projects are often procured by experienced clients, such as a cold, financial calculation: does it make financial sense to pay
public authorities or major developers. However, at the other more for a construction if it means an earlier completion date

175
176 Introduction to procurement methods in construction

and therefore an earlier income stream? Does it follow that pay- will be complete at an early stage, so that variations to the works
ing more for a state-of-the-art design means that higher rents can are going to be limited, and therefore initial pricing is more
be commanded as a result? These sorts of commercial drivers accurate. It will also be looking to have direct contracts with key
will have an impact on the chosen procurement method. Some participants in the design and construction of the project and the
procurement methods are better suited to getting a project to an right to step into the shoes of the client in circumstances where
early start on site and therefore an earlier finish, while others are there may be uncertainty as to the client’s ability to complete the
designed to engage all parties together to ensure a high-quality project in question. This will inevitably add layers of complex-
product – perhaps at the expense of speed. ity to a procurement, as the funder’s rights vis à vis the project
participants need to be recorded in direct contractual agreements
4.02 It can be seen, then, that choosing a procurement method and other security instruments.
is often a challenging exercise, involving the consideration of
such things as the size and complexity of the project, the client’s
experience and attitude towards risk, and the tension between
Ability to change design
the three client objectives of high quality, speed of completion, 5.05 The question of whether and the extent to which the design
and low price. When one factors in the plethora of other relevant should be allowed to change during the construction phase is
considerations, it is not surprising that the choice of procurement an important factor in choosing the correct procurement route
route is seldom an easy one to make. Nor is it surprising that his- because of the consequential impact this is likely to have on cost
tory is littered with examples of where the procurement choice and time to completion. Where the design is not complete before
made for a project turned out to be the wrong one, resulting in it the works are commenced, clearly, a procurement route that is
being a painful experience for at least some of the participants. flexible enough to allow for changes to the design is required.
The same is true where the nature of the site may determine
whether design changes are required as the project progresses.
5 Other factors affecting choice For example, works to existing buildings often uncover features
of procurement method that were not known at the original design stage and which will
necessitate changes to the design.
Design responsibility
5.01 The question of who is to take responsibility for the design
How important is a fxed price?
of the project is fundamental. The ‘traditional’ approach to 5.06 The importance to the client of obtaining a fixed price from
construction is to engage a team of professional consultants, led the contractor will depend on the client’s ability to pay for any
by the architect, to design a building and then appoint a build- price increases and/or a funder’s willingness or otherwise to
ing contractor to construct in accordance with that completed back a project where the price is uncertain. Other factors (such
design. Where a project is to be designed by a professional team as completion by a certain date) may take priority, in which case
in this way, the contractor can be brought on board at a later the client may be prepared to pay more to achieve this.
stage and then merely employed to build to the specification
or employer’s requirements. The works are therefore designed 5.07 For price certainty, a client should be looking to issue a
as the first stage, and thereafter the client invites contractors to tender package which specifies the works in terms of quality and
tender for the works according to the design. This arrangement quantity at tender stage. However, in practice, whilst most clients
can be perceived to have advantages for the client, most notably require some element of price certainty, it must be recognised
in terms of control of costs. It ought to be easier for contractors that unless the scope of works is very accurately defined and the
to price works accurately if their tender is based on a completed risks of the project are minimal and predictable, it is unlikely to
design. However, the result is that there are several points of be the case that a particular price can be guaranteed. However, a
responsibility and a need to manage the relationship between the tight specification does at least allow the selection of a procure-
professional team and the contractor. This is sometimes viewed ment route which only provides for price increases in circum-
as placing an onerous burden on the client, and there may be stances which are closely controlled by the contract provisions.
a risk of responsibilities for build issues ‘falling between the
cracks’ and remaining with the client. 5.08 It may also be the case that scope and risks are far from
clear at the outset, in which case a client is going to have to
5.02 The other extreme is to hand the entire design and build accept that he or she is likely to have to pay the outturn cost
obligation to a contractor who is then engaged to carry out plus margin. For example, this may be the case where urgent
the works to accord with a relatively brief statement of the work, such as repairs after fire or water damage, are required,
employer’s requirements. In reality, most building contracts and where the scope of the work cannot be ascertained until the
today represent a ‘hybrid’ of the two approaches, whereby a pro- work has been commenced.
fessional team is initially employed to work up the design of the
project on the client’s behalf, and the contractor is then required
to develop the design or to design discrete, specialist parts of
How important is the time
it, before the professional team’s appointment is transferred to for completion?
the design and build contractor who then takes on responsibility 5.09 For some clients, early completion is key, e.g. where the
for the whole of the design and build. The theory here is that financial gains to be had are greater, the earlier the project is
the contractor has a far clearer picture of what is required to be completed. In such circumstances, the contract may provide that
built than with the traditional approach, before becoming solely the contractor is incentivised to work efficiently either by ‘car-
responsible to the client for doing so. rot’, or ‘stick’, or both, i.e. by way of bonus payments for early
completion and/or damages for late completion.
Funding
5.03 The impact and influence of funders on the choice of pro- 6 Procurement options
curement route should not be underestimated, and it is usually
prudent to get the funder’s views as early as possible. Traditional
5.04 The client’s objectives will be numerous and competing, 6.01 The traditional procurement route, as its name suggests,
whereas a funder’s only real concerns are the protection of its was, until relatively recently, the most widely used in the UK.
financial stake and the return on its investment. A funder is As touched on above, at its most basic, the traditional route is
likely, therefore, to want the security of knowing that the design where the client appoints a professional team to carry out the
Procurement options 177

design. Once the design is complete, the client invites contrac- should it need to pass down liability for any negligence on their
tors to tender for the works. The main contractor will then often part. Thus, the client’s recourse in the event of any defect in
sub-contract the works, particularly specialist packages. The cli- either the design or the works will be against the contractor. It is
ent will have a direct contractual relationship with the contractor then up to the contractor to recover further down the contractual
and all of the professionals. The client will usually enter into chain, where appropriate.
direct contractual relationships with key sub-contractors under
separate collateral warranties or direct agreements to provide it 6.08 It is sometimes said that contractors approach design
with direct rights against those sub-contractors. from a different perspective to an architect, putting cost above
aesthetics with the result that design and build projects can be
6.02 This method can be suitable for all clients, experienced or uninspiring. Notwithstanding this view, design and build has
otherwise. As the design is fixed at an early stage, it gives the grown in popularity as a procurement route since it was origi-
client some degree of certainty as to price. Tenders are priced nally used in the 1980s. It is undeniably suitable for projects
on a fixed design and can therefore be required to be lump sum/ where aesthetics are not an issue and has been found to work
fixed price. well on repeat projects.

6.03 Because the contractor is working to a completed design,


there is a greater prospect of the contractor completing on time.
Two-stage tendering
The employer and the architect should also be able to work 6.09 This approach is used where the time from inception
closely together to arrive at designs which mirror the client’s to completion needs to be short – something which can be a
precise requirements, which can then be implemented by a con- major downfall of the traditional route. Two-stage tendering
tractor closely supervised by the architect, thereby resulting in usually involves appointing a preferred contractor at the first
better quality. However, in complex projects, early involvement stage through a competitive tender process. The invitation to
of the contractor and the specialist sub-contractors can be desir- tender usually requests certain deliverables, e.g. a construction
able, because they can bring their expertise to bear on questions programme and method statement, preliminaries prices, and
of ‘buildability’ and other design issues. overheads and profit margins. Lump sums for preconstruction
services and design fees may also be required.
6.04 A traditionally procured project may take longer to com-
plete from inception, because work does not start on site until 6.10 At second stage, the employer and the preferred contrac-
the design has been finalised. Another potential disadvantage is tor negotiate a fixed price for the works, as the scope becomes
that the client has no single point of responsibility when issues clearer. In theory, at least, the element of competition is main-
arise. The two-stage process can also mean that the lines of tained by the fact that the unsuccessful first-stage tenderers may
responsibility can become blurred. This is particularly so where be willing and able to step in to pick up the main second-stage
the contractor undertakes elements of the design. The lack of works packages.
communication and the fact that the design team and the con-
struction team approach the project from a different professional 6.11 In two-stage tendering, the design process can overlap with
perspective can also hinder smooth running of the project. This the construction works meaning that the construction phase
is because the contractor is arguably not on board sufficiently should be shorter. The involvement of the contractor at an early
early to advise on the buildability of the architect’s design. There stage also promotes a better understanding of the project among
can be arguments from the construction team that the design is the parties. The contractor is available during the design stage
not adequate or complete, and therefore the contractor may say to advise on the buildability of the architect’s design. However,
it has been prevented from completing the works as required. given that the tenderers are narrowed down (usually to one) fol-
In the event of a dispute, it may be difficult to determine which lowing the first stage, there is less competition during the second
party, designer, or contractor, is responsible. stage, and this may mean that the client does not ultimately
achieve the best price.
Design and build
6.05 In design and build contracts, the contractor carries out (or
Construction management
at least assumes contractual responsibility for) both the design 6.12 Under the construction management procurement route, the
and the construction works. As a result, many major contractors client enters into direct trade contracts and appointments with
have their own internal design capability. all of the other parties who are providing works and services,
but also appoints a construction manager to manage the project.
6.06 Commonly, the client will have prepared a basic design or
outline specification (or appointed an architect to do so), and this 6.13 Construction managers administer the trade contracts and
will be given to the contractor to develop. The client will prepare appointments on the client’s behalf. Their only role is this
employer’s requirements setting out the basic design requirements, management role. They do not provide any other services, and
and the contractor will prepare the contractor’s proposals for meet- are only responsible to the client for the performance of their
ing those requirements. In the building contract, the contractor construction management function. However, this is likely to
will take responsibility for the design and for ensuring it meets include assisting the client in the event there are problems with
the client’s requirements. Often, the client will appoint the profes- any of the other works and services.
sional team in the first instance, and these appointments will then
be novated to the contractor once it is on board. Novation gives 6.14 Proponents of construction management argue that it has
the contractor the ability to ensure that the professionals comply the advantage of speed, as design and works can move forward
with their appointments, and rights in the event that they do not. in parallel, and that the construction manager can drive up qual-
On novation, the professionals will give collateral warranties to ity for the client. On the flip side, there is inherent uncertainty
the client, thereby maintaining a direct contractual link and giving as to the time for completion and price, and if the project goes
some protection in the event of contractor insolvency. awry, there may be multiple points of responsibility for the client
to investigate and prove.
6.07 While the administrative burden of novating the profes-
sionals and providing warranties back to the client is seen as a
disadvantage of this procurement route, it does mean that the
Management contracting
contractor becomes the client’s single point of responsibility to 6.15 With management contracting, the client appoints the
the client in respect of the design and the construction, whilst designers and a management contractor, who then lets the works
the contractor has a direct contractual route to the professionals to various works contractors. The management contractor is paid
178 Introduction to procurement methods in construction

a fixed fee plus the actual or ‘prime’ cost of his on-site manage- additional payment. It is an approach which is suitable where
ment staff and of the works contractors. It enables a quick start the scope of works is well-developed at the time of contracting.
on site, as the design need not be particularly detailed when the
management contractor is engaged. It also tends to promote a
speedy completion, as the management contractor should be able
Measurement contracts
to effect very good supervision and management of the works 7.02 A measurement contract might be selected by a client who
on site, and the contract may contain incentives to him to secure needs an early start on site at the expense of price certainty. In
early completion. This advantage is derived from the fact that such contracts, the contractor usually provides rates and prices
the contractor is involved from an early stage, working with the for labour and materials against an indicative bill of quantities
design team and developing the programme. in order to give an indication of the likely final price for the cli-
ent. However, the price ultimately paid is assessed by measuring
6.16 The management contractor’s relationship with the client is the amount of the actual work done on the basis of the agreed
that of a consultant rather than a contractor. Whilst letting works rates and prices.
packages as and when required by the programme can speed up
the process, the price is subject to adjustment until all packages 7.03 In extreme circumstances, where there is insufficient time
have been let, meaning price certainty for the client may only to prepare even an approximate bill of quantities, a measurement
come at a late stage. contract may be based on drawings and schedules of rates. This
exposes the client to the risk of price uncertainty and for that
reason, is rarely recommended.
Partnering/framework agreements
6.17 Under a framework agreement, the client engages a sup- 7.04 Measurement contracts have been developed to include
plier that it intends to appoint to carry out a number of projects target cost mechanisms where contractors are incentivised by
over a period of time. The framework agreement sets out the ‘pain-gain’ provisions, under which they share costs savings or
principal terms and conditions, and then the client can simply overruns in agreed proportions.
call off each project without the need to re-tender. The call-off
of each project may be no more than a simple purchase order, as
the detail is already agreed in the framework agreement. There
Cost reimbursable/prime cost
is usually no obligation on the client to instruct any works and 7.05 This type of contract is again used mainly where a quick
no guarantees as to volume. start on site is required and the design is not sufficiently devel-
oped to allow the contractor to price the works. The contractor
6.18 As well as reducing tendering costs, the purpose of framework will be paid the prime cost of labour, plant, and materials. The
arrangements is to encourage construction teams to stay together contractor is also paid an additional fee for carrying out the
from project to project and make the most of what they have works. This can either be variable or fixed as a percentage of the
learned from working together on a number of similar projects. prime cost. A variable fee will usually be some form of target
fee where the contractor benefits from keeping the prime cost
6.19 The framework agreement approach typically promotes down, thereby discouraging inefficiency.
‘partnering’ and collaboration by including provisions designed
to encourage the parties to work together in a manner requiring
openness and a spirit of mutual trust and respect. This idea rather 8 Which contract?
obviously only works well where all parties buy into the ethos.
8.01 The decision as to which procurement route to use will
naturally lead to consideration of which contract to select. Whilst
Public Private Partnership (PPP) professional appointments, warranties, and other related con-
6.20 In PPP projects, private-sector resources are used to deliver tracts are often bespoke documents, the building contract itself
works and services that were traditionally provided by the public is usually based on one of the industry standard forms, of which
sector. For example, between 1992 and 2016, successive UK there are many, including those in the Joint Contracts Tribunal
governments procured a large number of projects under the (JCT) and the New Engineering Contract (NEC) suites. These
Private Finance Initiative (PFI) across a range of sectors, includ- are the two suites most often used in the UK, and are discussed
ing transport, energy, and health. A typical PFI structure involved in Chapters 17 and 18 respectively. Each drafting body issues
a funder providing finance to the private sector for the construc- traditional, design and build, framework, construction manage-
tion of a capital asset, which would then be subject to a long- ment, and management contracting editions with numerous dif-
term operating and maintenance contract, during which period ferent pricing approaches.
the public sector would pay a unitary charge for use of the asset.
8.02 There is a tendency in the industry for parties to favour
6.21 In October 2018, the UK government abolished the use of a particular form, or at least a particular edition of that form.
PFI and its successor, PFI2, for new public sector infrastructure This is not entirely unreasonable, as it is crucial that the par-
projects, whilst signalling its commitment to the use of PPP ties understand the contract they are using and how it operates.
where it delivered value and genuinely transferred risk to the An ill-informed decision to switch to an unfamiliar form of
private sector. However, whilst the private sector remains keen contract may well lead to failures in contract administration. It
on PPP, private sector involvement in public projects is a politi- is, however, always sensible to consider carefully which form
cally sensitive issue, and it is by no means clear how future PPP of contract would best meet the competing considerations that
projects will be structured. will be relevant to the project. For example, it would be wholly
inappropriate to propose the use of the NEC Option A contract
(which is a fixed-price contract by reference to an activity sched-
7 Common pricing mechanisms ule) where the parties have never used the NEC contract before,
a prompt start on site is of the utmost importance, and the scope
of works is far from clear.
Lump sum/fxed price
7.01 In a lump-sum or fixed price contract, the price is deter-
mined before the works start on site, and the agreed amount is 9 Conclusion
written into the contract. The price is subject to change only
where variations are instructed or where events occur which are 9.01 Often, a client or contractor will favour a particular form
at the client’s risk and which give rise to a pre-agreed right to of contract. A decision will be taken about which form is used,
Conclusion 179

and the parties work backwards from that to determine the pro- the constructions of the works, which may be considered to be a
curement route. While familiarity with a contract form has its good thing until the client who requires flexibility for late design
advantages, it is fundamental to the success of a project that the changes realises that there is little scope for varying the works
parties take a step back and ask some basic questions about what except at great cost. Similarly, the traditional procurement route
the client is trying to achieve. may allow the contractor to price accurately, but this is very
likely to increase the time from inception to completion of the
9.02 A failure to recognise the significance to the client of a project. This would not be a good thing for a developer with
demanding specification, completing on time, or keeping to the tenants waiting to take occupation.
budget can mean that the contract chosen does not adequately
provide a mechanism for achieving those objectives. 9.04 Time spent considering the options and making the right
choice of procurement route is likely to save time and cost in
9.03 A design and build contract, for example, will mean that the long run and may well increase the prospects of achieving a
there is a single point of responsibility for both the design and high quality outcome.
17
The JCT Standard Building Contract
THOMAS CRANGLE

The text discussed in this chapter is that of the JCT Standard 3 The introduction of a mechanism that allows notified sums
Building Contract 2016 edition. This chapter is a commentary (plus interest) to be automatically recovered as a debt where
on the text of the Standard Building Contract and also sets out no pay less notice is served;
in full those clauses that are considered to be of particular rel- 4 The introduction of a time limit by which the Architect
evance to architects. must assess a claim for loss and expense. Whereas there
Although the commentary below remains relevant to earlier was previously no time limit, the architect must now make
versions of the Standard Building Contract, the contractual an assessment within 28 days of the initial claim being
wording has undergone considerable changes over the years made and then within 14 days of any updated details being
(particularly between the 1998 and 2005 editions). Considerable provided. There is also a slightly stricter time limit for the
care should therefore be taken to ensure that the wording of the contractor to notify claims for loss and expense;
clause is identical when considering any case law applying to 5 Whereas previously the employer was required to obtain
earlier editions, as changes in the wording of a given clause may insurance for existing structures, the form now provides
well alter how it should be interpreted. Readers are also referred for alternative arrangements, such as the provisions of that
to earlier editions of this work. insurance by a superior landlord; and
The Standard Building Contract is available in three ver- 6 The 2016 edition introduces provisions for security to
sions: (1) With Quantities; (2) Without Quantities; and (3) With be provided in the form of performance bonds or parent
Approximate Quantities. Where the version With Approximate company guarantees. The form is to be agreed between the
Quantities is used, the quantities are to be remeasured. parties, and no standard form is included.
Since the last version of this book was published, two new
editions of the Standard Form have been issued, in 2011 and
2016. The key changes introduced in the 2011 edition were: 1 Articles of Agreement
1 Changes to the payment provisions in order to implement 1.01 The first part of the form, which contains the Articles of
the payment regime introduced by the Local Democracy, Agreement, has four elements: the front page, the Recitals,
Economic Development and Construction Act 2009. These the Articles, and the Contract Particulars. Their purpose is to
are by far the most far-reaching changes made in the establish the fundamental terms of the contract. The front page,
2011 edition; when completed, identifies the parties and the date upon which
2 Giving effect to the contractor’s statutory right, introduced the contract is made. The Recitals (the twelve statements com-
by the 2009 Act, to recover costs and expense arising out of mencing with the word ‘Whereas’) record the nature of the
the exercise of its existing right to suspend the performance intended works, identify the documents in which those works
of the works for non-payment; are described (the Bills of Quantities [if used] and Contract
3 The incorporation of revised terrorism cover provisions; and Drawings), and provide for the Activity Schedule and the
4 Making the provisions on extension of time consistent with Information Release Schedule as options. They also provide
those for the recovery of loss and expense in respect of the for a Contractor’s Designed Portion of the intended works, if
discovery of antiquities. applicable.
It is important that the particular set of drawings which are
The changes introduced in the 2016 edition are relatively minor intended to comprise the Contract Drawings are clearly identi-
by comparison. Those that are likely to be of significance to fied, and, where there is a Contractor’s Designed Portion, that
Architects are: the documents comprising the Employer’s Requirements and
the Contractor’s Proposals are also properly identified and are
1 The introduction of a common valuation date so that sub- checked for inconsistencies. Last minute changes often occur,
contractors and sub-sub-contractors can be paid quicker and and care should be taken to ensure that the documentation is
do not have to wait until the next upstream valuation to be correct before the contract is executed.
paid;
2 Whereas previously, the frequency at which valuations 1.02 The Articles state shortly the substance of the parties’ agree-
were to be carried out decreased following practical com- ment. Articles 1 and 2 define the basic contractual obligations
pletion from every one month to every two months, the of the parties. The contractor agrees to carry out and complete
2016 edition maintains the one month frequency throughout the works in compliance with the Contract Documents (defined
the length of the contract; in clause 1.1 as the Contract Drawings, the Contract Bills, the

181
182 The JCT Standard Building Contract

Articles of Agreement, the Conditions, and [where applicable] the nominee by giving notice within seven days. If the contrac-
the Employer’s Requirements, the Contractor’s Proposals, and tor chooses to do so, a contractual dispute resolution procedure
the Contractor’s Designed Portion Analysis). The employer, in applies. Any replacement Architect is bound by final decisions
consideration, agrees to pay the contractor the Contract Sum at of his predecessor.
the times and in the manner specified in the conditions. These
Articles provide the bedrock for the remainder of the contract: 1.05 Articles 7, 8, and 9 contain dispute resolution procedures.
they identify the contract as a lump-sum contract, with the con- Under Article 7, either party has the right to refer any dispute
tractor being paid in accordance with the issue of Architect’s or difference arising under the contract to adjudication, to which
Certificates (see clauses 4.9 to 4.15). the rules of the statutory Scheme for Construction Contracts will
apply (with certain modifications set out in clause 9.2).
1.03 Article 3 identifies the Architect or Contract Administrator.
In this chapter, the term ‘the Architect’ will be used to describe 1.06 Paragraph 6 of the Supplemental Provisions, which are
both functions. Article 4 identifies the Quantity Surveyor, and found in Schedule 8 to the Conditions and which incorporate
Articles 5 and 6, the CDM Co-ordinator and Principal Contractor the Achieving Excellence in Construction principles, provides
respectively, for the purposes of the CDM Regulations, if they an alternative dispute resolution procedure of direct, good faith
are other than the Architect and the contractor. negotiations between senior executives of each party who are
named in the Contract Particulars. This procedure is, as it must
1.04 Clause 3.5.1 requires that if either the Architect/Contract be, subject to either party’s right to refer any dispute to adjudi-
Administrator or the Quantity Surveyor cease to hold their cation at any time.
contractual post, the employer comes under a duty to appoint
a replacement. If the employer fails to do so, they will be in 1.07 The arbitration agreement is contained in Article 8, if the
breach of contract. The employer is required to nominate a parties elect to apply it, in which case they must make a posi-
replacement as soon as reasonably practicable and in any event tive election in the Contract Particulars. The application of the
within 21 days. The contractor normally has a right to object to arbitration procedure is subject to the unfettered right to refer a
Section 2: carrying out the works 183

dispute to adjudication at any time. Where arbitration is selected, 1.14 In deciding whether the agreement should be made as a
disputes ‘arising out of or in connection with’ the contract may deed or not, the key factor is that if it is made as a deed, the
be referred to arbitration in accordance with clauses 9.3 to 9.8 limitation period for bringing actions is 12 years from the date
of the 2016 edition of the CIMAR rules, subject to certain of the breach of contract (see section 8 of the Limitation Act
exceptions. 1980); otherwise it is six years (see section 5 of the Limitation
Act 1980).
1.08 The main exception is that matters in connection with the
enforcement of decisions of an adjudicator cannot be referred to
arbitration, and any adjudication enforcement proceedings should
Conditions
be brought in the Technology and Construction Court. Disputes
under or in respect of the Construction Industry Scheme or VAT
are also excluded from the arbitration provisions. 2 Section 1: defnitions and interpretation
1.09 If legal proceedings are brought against a party, that party 2.01 The purpose of this section is to provide a list of definitions
may apply to stay those proceedings if their subject-matter is of the main terms used in the contract (clause 1.1) and a number
covered by a valid arbitration clause. It must make the appli- of interpretation clauses (clauses 1.2–1.12). All listed definitions
cation before taking any step in the proceedings to answer commence with capital letters and are of general application
the substantive claim, but should first acknowledge service throughout the contract, whereas particular definitions applicable
of those proceedings. The court must then stay the proceed- only to a particular section or clause are found in those particular
ings – it has no discretion (see section 9(4) of the Arbitration locations. The following interpretation clauses are of particular
Act 1996). significance.

1.10 Article 9 provides for the English courts otherwise to have 2.02 Clause 1.6 excludes the effect of the Contracts (Rights
jurisdiction over any dispute or difference between the parties of Third Parties) Act 1999, but the exclusion is now limited
arising out of or in connection with the contract. because of the inclusion of rights for purchasers, tenants, and
funders provided for by clauses 7A and 7B.

Contract Particulars 2.03 Clause 1.7 requires all notices and communications
referred to in the contract to be in writing and encourages the
1.11 There follow the Contract Particulars, which are divided into parties to agree a communications protocol as soon as possible
two – Part 1: General; and Part 2: Third Party Rights and Collateral to provide for their effective transmission. This is particularly
Warranties. In conjunction with section 7 of and Schedule 5 to the important where there is a Contractor’s Designed Portion. Key
Conditions, Part 2 enables the grant of third party rights to named notices (relating to termination and to the grant of third party
or identified purchasers, tenants, and funders. rights) are required to be hand delivered or sent by recorded
or special delivery post. In the absence of a communications
1.12 Architects should ensure that the Contract Particulars are protocol, all other notices may be given or served by ‘any
carefully completed. It is not unknown for this to be overlooked. effective means’ to a specified address, or to the last known
Care should be taken to follow the format and instructions, as principal business address, or to the registered or principal
there are pitfalls for the unwary. In Temloc v Errili Properties office of a company.
(1987) 39 BLR 30 an entry of the word ‘nil’ was made in respect
of liquidated damages. Did this mean that there were to be no 2.04 Clauses 1.09 and 1.10 are important clauses which con-
damages for delay payable at all, no matter how late was com- cern the effect as between employer and contractor of interim
pletion? Or did it mean that damages for delay were not to be and final certificates issued by the Architect and the action that
at a pre-agreed rate, but were left to be assessed, on the basis of needs to be taken in order to challenge a final certificate before
the actual loss that could be proved, subject to the common law it becomes conclusive: see paragraph 5.18 below.
rules on recovery? The Court of Appeal held that it meant that
there were to be no damages for delay at all. Obviously, parties
should try to avoid creating uncertainties of this character. 3 Section 2: carrying out the works
1.13 The Articles conclude with a space for the appropriate 3.01 Section 2 contains a series of key clauses relating to the
attestation clause under hand or as a deed. If the contract is to carrying out of the works and sets out the central obligations of
be executed by an individual as a deed, following the Law of both parties in order to achieve their completion.
Property (Miscellaneous Provisions) Act 1989, there is no longer
any requirement that it be executed under seal (although the use of
a seal will not invalidate it). The instrument must make it clear on The position of the Architect
its face that it is intended to be a deed and must be signed by the 3.02 The Architect is the employer’s agent, with authority to
individual in the presence of a witness who attests the signature exercise those powers conferred on him or her by the contract.
(or if it is signed at the individual’s direction in his presence, it As such, the Architect is both entitled and obliged to protect
must be attested by two witnesses). Further, the instrument must the employer’s interests. Formerly the courts took the view
be delivered as a deed by the signatory or by a person author- that, because of the grave disadvantages which would be suf-
ised to do so on his behalf. If the contract is to be executed by fered by the contractor if the Architect failed to certify properly
a company, the Companies Act 1989 provides that a document or otherwise exercise in a proper manner his functions under
executed by a company which makes it clear on its face that it the contract, the Architect was, to some extent, in an inde-
is intended to be a deed has effect upon delivery as a deed, and pendent ‘quasi-judicial’ position, and immune from actions for
it is presumed to be delivered upon execution, unless a contrary negligence by either party when performing functions requiring
intention is proved. A document may be executed by a company the exercise of his independent professional judgement and
by affixing its seal but, irrespective of whether or not the company the application of his mind fairly and impartially between the
has a seal, a document signed by a director and the secretary of parties. However, in Sutcliffe v Thackrah [1974] AC 727, it
the company, or by two directors, or by a single director whose was held that an architect was liable to his employer for negli-
signature is attested by a witness and expressed to be executed by gently over-certifying in interim certificates, and the House of
the company, has the same effect as if executed under the common Lords said that the Architect enjoyed no such ‘quasi-judicial’
seal of the company (see section 44 of the Companies Act 2006). immunity.
184 The JCT Standard Building Contract

3.03 In Pacific Associates v Baxter [1990] QB 993, the Court of 3.05 This duty to act fairly is often extremely difficult for an
Appeal held that an engineer (and by analogy an architect) could employer client (who is paying the Architect’s fees) to appreci-
not be sued by the contractor for negligently issuing a certificate ate, but is essential to the correct functioning of the contract.
for the contractor’s payment. The decision turned on the fact However, the fact that the Architect must act fairly and impar-
that the contractor could challenge the certificate (by going to tially in administering the contract does not mean that he or she
arbitration) and recover any further sums to which they were may not consult with the employer on matters within the sphere
entitled from the employer. If there is no challenge mechanism of his or her independent duty, but obliges the Architect when
(which there is in the JCT family of contracts), there might exist making a decision to make up his or her own mind, doing their
the possibility that an architect may be liable to a contractor for best to decide in accordance with the contract terms, interpreted
negligent under-certification. against the background of the circumstances prevailing at the
Similarly, it is likely that an employer will not be under a time of entering into the contract. The Architect should then
duty to ensure that the Architect discharges his duties correctly. certify or give a decision accordingly, whether or not he or
In Hiap Hong & Co Pte Ltd v Hong Huat Development Co (Pte) she thinks it will please the employer. It is in this way that the
Ltd [2001] 17 Const LJ 530, the Singapore Court of Appeal held Architect must act in an independent manner.
that the Architect was under a duty to act independently. He was
not subject to the instructions of either employer or contractor
and had to reach his own decisions. He was not an agent of
Liability for design
the owners. The control exercised over the Architect by the 3.06 It is thought that, provided the contractor carries out the
owner was limited to acts that were performed by the Architect work strictly in accordance with the contract documents, it
on the owner’s behalf (such as the instruction of variations to is not responsible if the works prove to be unsuitable for the
the works), but this did not include the Architect’s certification purpose which the employer or architect had in mind. The
duties, which require the exercise of fair and independent profes- Architect is responsible for the integration of the design of any
sional judgement: see also Scheldebouw BV v St James Homes Contractor’s Designed Portion of the works with the design
Ltd [2006] BLR 113. of the works as a whole, and may direct the contractor to that
effect (clause 2.2.2). It is not otherwise the Architect’s function
3.04 The Architect must, at all times, adhere to the requirements to direct the contractor in the way it shall carry out the works,
of the contract. Thus, for example, it is wrong to permit a con- save where the Conditions expressly give him this power, for
tractor to carry out work to a standard lower than that required example his power to issue instructions requiring a variation:
by the contract, because the Architect discovers that the contrac- see Section 5.
tor has tendered low. It is also wrong to insist on a standard of
work higher than the contract standard because the employer 3.07 Under clause 2.3.1, the Architect must give written consent,
demands it. Architects are reminded that, quite apart from what not to be unreasonably delayed or withheld, to the substitution of
the courts have explained as their role under the building con- any specifically described materials or goods by the contractor.
tract, the RIBA Code of Professional Conduct requires all mem-
bers and students of the RIBA to act impartially in all matters of 3.08 Clause 2.3.3 provides that, where and to the extent that
dispute between the building owner and the contractor, and to approval of the quality of materials or goods or of the standards
interpret the conditions of the building contract even-handedly of workmanship is a matter for the opinion of the Architect, such
as between the parties. quality and standards shall be to his reasonable satisfaction. It

Materials, goods, and workmanship

2.3 .1 All materials and goods for the Works, excluding any CDP Works, shall, so far as procurable, be of
the kinds and standards described in the Contract Bills. Materials and goods for any CDP Works
shall, so far as procurable, be of the kinds and standards described in the Employer's Requirements
or, if not there specifcally described, as described in the Contractor’s Proposals or documents
referred to in clause 2.9.4. The Contractor shall not substitute any materials or goods so described
without the Architect/Contract Administrator’s consent, which shall not be unreasonably delayed or
withheld but shall not relieve the Contractor of his other obligations.

.2 Workmanship for the Works, excluding any CDP Works, shall be of the standards described in
the Contract Bills. Workmanship for any CDP Works shall be of the standards described in the
Employer’s Requirements or, if not there specifcally described, as described in the Contractor’s
Proposals.

.3 Where and to the extent that approval of the quality of materials or goods or of the standards of
workmanship is a matter for the Architect/Contract Administrator’s opinion, such quality and stand-
ards shall be to his reasonable satisfaction. To the extent that the quality of materials and goods or
standards of workmanship are neither described in the manner referred to in clause 2.3.1 or 2.3.2
nor stated to be a matter for such opinion or satisfaction, they shall in the case of the Contractor’s
Designed Portion be of a standard appropriate to it and shall in any other case be of a standard
appropriate to the Works.

.4 The Contractor shall upon the request of the Architect/Contract Administrator provide him with rea-
sonable proof that the materials and goods used comply with this clause 2.3.
Section 2: carrying out the works 185

may be that the Architect can, and perhaps should, take account Administration of the contract
of the price of the works in deciding whether or not he or she
is reasonably satisfied: Cotton v Wallis [1955] 1 WLR 1168. 3.15 Clauses 2.8–2.12 are concerned with matters of contract
Under clause 1.9.1, the final certificate is conclusive evidence administration, namely the custody and issue of the contract
that the quality of materials or standard of workmanship are to and other documents. The Architect is closely involved in these
the reasonable satisfaction of the Architect only where they are matters, and is, from the execution of the contract, obliged
expressly required to be so, but not where it is merely implicit to provide or release a series of documents and schedules
that those matters are for the approval of the Architect (thus to the contractor. Clauses 2.9.1.2 and 2.9.2 in particular are
negating the effect of Crown Estates v John Mowlem & Co. significant: these clauses require the contractor to supply the
Ltd (1994) 70 B.L.R. 1 (CA), which was decided on previous Architect with his master programme for the execution of the
wording). works and to update it to take account of extensions of time
granted under clause 2.28.1. This master programme does not,
however, impose any obligation beyond those imposed by the
Possession of the site contract documents (clause 2.9.3) and is not itself a contract
document.
3.09 Clauses 2.4–2.6, which are concerned with possession and
use of the site, should be read in conjunction with clauses 2.26–
3.16 By clause 2.10, the Architect must determine the ground
2.28 (Adjustment of Completion Date), 2.30–2.32 (Practical
level information required to set out the works, and provide
Completion, Lateness and Liquidated Damages), and clauses
drawings containing that information to the contractor. Unless
4.23–4.26 (Loss and Expense).
the Architect, with the employer’s consent, instructs that any
errors arising from inaccurate setting out by the contractor are
3.10 The form gives the option of having either a single
not to be amended, the contractor must amend them at its own
Date for Completion of the Works or for several Dates for
cost. If the Architect does instruct that the errors need not be
Completion of Sections. Where the option of having Sections
amended, an appropriate deduction in respect of the errors is to
is chosen, different dates may be including for giving posses-
be made from the contract sum.
sion of particular Sections to the contractor. Where Sections are
adopted, it is important that each Section is clearly defined in
3.17 By clause 2.11, where, at the time of the contract, the
the contract in order to minimise the risk of disputes over what
employer has provided the contractor with an Information
work has to be carried out in order to achieve the completion
Release Schedule (see the fifth recital to the Articles of
of each Section.
Agreement), the Architect is required to provide information
to the contractor in accordance with the dates set out in the
3.11 If possession of the site cannot be given on the date for
schedule, subject to a proviso that the employer and contractor
possession, the employer is in serious breach of contract,
may agree to vary those times. If all the information required
and the contractor is entitled to claim damages. Giving pos-
by the contractor is not covered by the Information Release
session is a matter of fact. It was held in Whittal Builders v
Schedule, then the Architect is required, by clause 2.12, to
Chester Le Street DC (1988) 40 BLR 82 that giving posses-
provide such information, by way of further drawings, details,
sion in stages was a breach of this term. However, there will
and instructions, when it is reasonably necessary to do so. The
be no breach where the parties have agreed different dates
Architect is obliged to act with reasonable diligence and to use
of possession for different Sections and possession of each
reasonable care and skill in the provision of such information:
Section is given by the date required. They may also agree
London Borough of Merton v Leach (1985) 32 BLR 51.
that the employer can delay the giving of possession by up to
six weeks (clause 2.5), without affecting his right to recover
3.18 Whether further drawings or details are reasonably nec-
liquidated damages.
essary is to be judged objectively, and the Architect may be
under an obligation to provide particular further information
3.12 Once the contractor has possession of the site, it is deemed
even where there has been no request from the contractor (see
to retain it for the purpose of works insurance until practical
Royal Brompton Hospital NHS Trust v Hammond (No. 9) [2002]
completion. If the employer takes partial possession (pursuant
EWHC 2037 (TCC)).
to clause 2.33), then practical completion is deemed to have
occurred in respect of that part. The employer is not otherwise
3.19 Clauses 2.13–2.20 deal with errors, discrepancies and
entitled to take possession of any part of the works.
divergences in and between the contract and related documents,
and require the contractor to report a number of such occur-
3.13 The employer may, however, with the contractor’s consent,
rences to the Architect, who is required to issue instructions
use or occupy the site of the works before practical completion
to resolve the difficulty. In general, the cost involved is borne
without taking possession of it (clause 2.6), as long as he or she
by the party responsible for the preparation of the document
notifies the works’ insurers and receives confirmation that the
in question.
insurance will not be prejudiced. As such early use or occupation
does not amount to the taking of possession, it will not preclude
3.20 Under clause 2.13 (unless otherwise expressly stated in
the employer from claiming liquidated damages for late comple-
respect of any specified item or items), the contract bills are
tion. Guidance on what constitutes use or occupation for the
to have been prepared in accordance with the principles of
purposes of clause 2.6 can be found in Imperial Castelli: SpA v
the Standard Method of Measurement (SMM). If they have
Cola Holdings [2002] C.I.L.L. 1904.
not been so prepared, this constitutes an error, which must
be corrected (clause 2.14.1). By virtue of clause 2.14.3,
3.14 Clause 2.7 governs the position where the employer wishes
the correction is to be treated as though it was a variation
to carry out certain work itself (or by persons it has employed,
required by the Architect. SMM expressly requires contract
engaged, or authorised) while the contractor is engaged on the
bills fully and accurately to describe the work. For example,
works. Where this work is described in the bills, the contractor is
if in carrying out work it becomes clear that excavation of
obliged to permit the employer to carry the work out, but where
rock is necessary and that the bills should have stated that
it is not, the contractor is required to give its consent, which
excavation would be required, it seems that the contractor
must not be unreasonably delayed or withheld. For the mean-
will become entitled to extra payment for all such excavation
ing of ‘work not forming part of this Contract’, see Henry Boot
(see Bryant & Son Ltd v Birmingham Hospital Saturday Fund
Construction Ltd v Central Lancashire New Town Development
[1938] 1 All ER 503).
Corporation (1981) 15 BLR 1.
186 The JCT Standard Building Contract

Supply of Documents, Setting Out etc.

Contract Documents

2.8 .1 The Contract Documents shall remain in the custody of the Employer and shall be available at all rea-
sonable times for inspection by the Contractor.

.2 Immediately after the execution of this Contract the Architect/Contract Administrator, without charge to
the Contractor, shall (unless previously provided) provide him with:
.1 one copy, certifed on behalf of the Employer, of the Contract Documents;
.2 two further copies of the Contract Drawings; and
.3 two copies of the unpriced bills of quantities.

.3 The Contractor shall keep upon the site and available to the Architect/Contract Administrator or his
representative at all reasonable times a copy of each of the following documents, namely: the Contract
Drawings; the unpriced bills of quantities; the CDP Documents (where applicable); the descriptive
schedules or similar documents referred to in clause 2.9.1.1; the master programme referred to in
clause 2.9.1.2; and the drawings and details referred to in clauses 2.10 and 2.12.

.4 None of the documents referred to in this clause 2.8 or provided or released to the Contractor in
accordance with clauses 2.9 to 2.12 shall be used by the Contractor for any purpose other than this
Contract, and the Employer, the Architect/Contract Administrator and the Quantity Surveyor shall not
divulge or use except for the purposes of this Contract any of the rates or prices in the Contract Bills.

Construction information and Contractor’s master programme


2.9 .1 As soon as possible after the execution of this Contract, if not previously provided:
.1 the Architect/Contract Administrator, without charge to the Contractor, shall provide him with any
descriptive schedules or similar documents necessary for use in carrying out the Works (excluding
any CDP Works), together with any pre-construction information required for the purposes of regula-
tion 10 of the CDM Regulations; and
.2 the Contractor shall without charge provide the Architect/Contract Administrator with his master
programme for the execution of the Works identifying, where required in the Contract Particulars, the
critical paths and/or providing such other details as are specifed in the Contract Documents.

.2 Within 14 days of any decision by the Architect/Contract Administrator under clause 2.28.1 or of agree-
ment of any Pre-agreed Adjustment, the Contractor shall provide him with an amendment or revision of
the master programme that takes account of that decision or agreement, with the details referred to in
clause 2.9.1.2.

.3 Nothing in the descriptive schedules or similar documents, or in the master programme or any amend-
ment or revision of it, shall however impose any obligation beyond those imposed by the Contract
Documents.

.4 In relation to any CDP Works, the Contractor, in addition to complying with regulations 11,12 and 18 of
the CDM Regulations, shall without charge provide the Architect/Contract Administrator with copies of:
.1 such Contractor's Design Documents, and (if requested) related calculations and information, as are
reasonably necessary to explain or amplify the Contractor’s Proposals; and
.2 all levels and setting out dimensions which the Contractor prepares or uses for the purposes of car-
rying out and completing the Contractor's Designed Portion.

.5 The Contractor's Design Documents and other information referred to in clause 2.9.4.1 shall be pro-
vided to the Architect/Contract Administrator as and when necessary from time to time in accordance
with the Contractor’s Design Submission Procedure set out in Schedule 1 or as otherwise stated in
the Contract Documents, and the Contractor shall not commence any work to which such a document
relates before that procedure has been complied with.

Levels and setting out of the Works


2.10 The Architect/Contract Administrator shall determine any levels required for the execution of the Works
and, subject to clause 2.9.4.2, shall provide the Contractor by way of accurately dimensioned drawings
with such information as shall enable the Contractor to set out the Works. The Contractor shall be
responsible for, and shall at no cost to the Employer amend, any errors arising from his own inaccurate
setting out. With the Employer’s consent, the Architect/Contract Administrator may instruct that such
errors shall not be amended and an appropriate deduction shall be made from the Contract Sum for
those that are not required to be amended.
Section 2: carrying out the works 187

Information Release Schedule


2.11 Except to the extent that the Architect/Contract Administrator is prevented by an act or default of
the Contractor or of any of the Contractor’s Persons, he shall ensure that the information referred
to in the Information Release Schedule is released at the time stated in that schedule. The
Employer and the Contractor may agree to vary any such time, such agreement not to be unreason-
ably withheld.

Further drawings, details and instructions


2.12 .1 Where not included in the Information Release Schedule, the Architect/Contract Administrator
shall from time to time, without charge to the Contractor, provide him with such further drawings
or details as are reasonably necessary to explain and amplify the Contract Drawings and shall
issue such instructions (including those for or in regard to the expenditure of Provisional Sums)
as are necessary to enable the Contractor to carry out and complete the Works in accordance
with this Contract.

.2 The further drawings, details and instructions shall be provided or given at the time it is reasonably
necessary for the Contractor to receive them, having regard to the progress of the Works, or, if in the
Architect/Contract Administrator’s opinion practical completion of the Works or relevant Section is
likely to be achieved before the relevant Completion Date, having regard to that Completion Date.

.3 Where the Contractor has reason to believe that the Architect/Contract Administrator is not aware
of the time by which the Contractor needs to receive such further drawings, details or instructions,
he shall, so far as reasonably practicable, notify the Architect/Contract Administrator suffciently in
advance as to enable the Architect/Contract Administrator to comply with this clause 2.12.

Notice of discrepancies etc.

2.15 If the Contractor becomes aware of any such departure, error, omission or inadequacy as is referred
to in clause 2.14 or any other discrepancy or divergence in or between any of the following docu-
ments, namely:
.1 the Contract Drawings;
.2 the Contract Bills;
.3 any instruction issued by the Architect/Contract Administrator under these Conditions;
.4 any drawings or documents issued by the Architect/Contract Administrator under any of clauses 2.9
to 2.12; and .
.5 (where applicable) the CDP Documents,
he shall immediately give notice with appropriate details to the Architect/Contract Administrator, who
shall issue instructions in that regard.

Discrepancies in CDP Documents


2.16 .1 Where the discrepancy or divergence to be notifed under clause 2.15 is within or between the CDP
Documents other than the Employer’s Requirements, the Contractor shall send with his notice, or
as soon thereafter as is reasonably practicable, a statement setting out his proposed amendments
to remove it. The Architect/Contract Administrator shall not be obliged to issue instructions until he
receives that statement, but, when issued, the Contractor shall comply with those instructions and,
to the extent that they relate to the removal of that discrepancy or divergence, there shall be no addi-
tion to the Contract Sum.

.2 Where the discrepancy is within the Employer’s Requirements (including any Variation of them issued
under clause 3.14) the Contractor’s Proposals shall prevail (subject to compliance with Statutory
Requirements), without any adjustment of the Contract Sum. Where the Contractor’s Proposals do
188 The JCT Standard Building Contract

not deal with such a discrepancy, the Contractor shall notify the Architect/ Contract Administrator of
his proposed amendment to deal with it and the Architect/Contract Administrator shall either agree
the proposed amendment or decide how the discrepancy shall be dealt with; that agreement or deci-
sion shall be notifed to the Contractor and treated as a Variation.

Divergences from Statutory Requirements


2.17 .1 If the Contractor or Architect/Contract Administrator becomes aware of any divergence between the
Statutory Requirements and any of the documents referred to in clause 2.15, he shall immediately
give the other notice specifying the divergence and, where it is between the Statutory Requirements
and any of the CDP Documents, the Contractor shall notify the Architect/Contract Administrator of
his proposed amendment for removing it.

.2 Within 7 days of becoming aware of such divergence (or, where applicable, within 14 days of receipt
of the Contractor’s proposed amendment), the Architect/Contract Administrator shall issue instruc-
tions in that regard, in relation to which:

.1 in the case of a divergence between the Statutory Requirements and any of the CDP Documents,
the Contractor shall comply at no cost to the Employer unless after the Base Date there is a
change in the Statutory Requirements which necessitates an alteration or modifcation to the
Contractor’s Designed Portion, in which event such alteration or modifcation shall be treated as
an instruction requiring a Variation of the Employer’s Requirements; and
.2 in any other case, if and insofar as those instructions require the Works to be varied, they shall
be treated as instructions requiring a Variation.

.3 Provided the Contractor is not in breach of clause 2.17.1, the Contractor shall not be liable
under this Contract if the Works (other than the CDP Works) do not comply with the Statutory
Requirements to the extent that the non-compliance results from the Contractor having carried
out work in accordance with the documents referred to in clauses 2.15.1 to 2.15.4 (other than an
instruction for a Variation in respect of the Contractor’s Designed Portion)

3.21 By clause 2.17, the contractor is required to give written Extensions of Time
notice to the Architect of any divergence it finds between the
statutory requirements and the documents referred to in clause 3.23 Clauses 2.26–2.29 make provision for extensions of time
2.15. The Architect is required to issue instructions in relation to to be given to the contractor through delay caused by ‘Relevant
the divergence, and this instruction will be treated as an instruc- Events’, as defined in clause 2.29. When it becomes reasonably
tion requiring a variation under clause 3.14. It is probably also apparent that the progress of any section of the works is being or
the contractor’s implied duty to bring to the Architect’s atten- is likely to be delayed from any cause whatever, the contractor is
tion any obvious errors in the Architect’s design, of which the obliged to give notice forthwith to the Architect of the material
contractor has actual knowledge. circumstances identifying (clause 2.27.1):
3.22 Clauses 2.24 and 2.25, which deal with unfixed materials 1. The cause or causes of the delay.
and goods on and off site, should be read in conjunction with 2. Any event which is in his opinion a ‘Relevant Event’.
clauses 4.16 and 4.17. The position as to materials and goods
intended for the works is as follows: The giving of a timely notice by the contractor is not a condi-
tion precedent to an entitlement to an extension of time. Thus,
1 As soon as materials or goods are delivered to or placed on a failure to comply with the notice provisions (whether as to
or adjacent to the works, they must not be removed without timing or content) will not preclude the contractor from being
the Architect’s consent (clause 2.24). granted an extension (see Walter Lilly & Co Limited v Mackay
2 Provided that the materials or goods have not been prema- [2012] BLR 503). However, in practice, it will usually be in
turely delivered to site and are adequately protected against the contractor’s interests to give a timely notice and sufficient
weather and other risks, the Architect is bound to certify information to allow the Architect to make an informed decision.
them for payment (clause 4.16.1.2).
3 As soon as materials or goods are paid for, property in them 3.24 Clause 2.27.2 requires the contractor to give particulars of the
passes to the employer (clause 2.24). expected effects of the event causing delay, and an estimate of the
4 As soon as materials or goods are incorporated into the extent of delay in completion of any section of the works beyond
works, property in them passes to the owner of the land by the completion date resulting from that particular event (whether
operation of law, whether the goods are paid for or not. or not the delay will be concurrent with a delay resulting from
5 Pre-fabricated materials or goods which are off site may be any other relevant event). This information should be included in
certified for payment provided they were contained in a list the notice where possible, and alternatively, it should be given in
annexed to the contract bills and certain conditions have writing as soon as possible after the issue of the notice.
been met by the contractor (clause 4.17).
6 If off site materials are certified and paid for, property in 3.25 It is clear that the contractor is required to give full particu-
them passes to the employer (clause 2.25). lars and details of the delay, even if the delay is the contractor’s
Section 2: carrying out the works 189

Adjustment of Completion Date

Related defnitions and interpretation

2.26 In clauses 2.27 to 2.29 and, so far as relevant, in the other clauses of these Conditions:
.1 any reference to delay or extension of time includes any further delay or further extension of time;
.2 ‘Pre-agreed Adjustment’ means the fxing of a revised Completion Date for the Works or a Section by
the Confrmed Acceptance of a Variation Quotation or an Acceleration Quotation;
.3 ‘Relevant Omission' means the omission of any work or obligation through an instruction for a
Variation under clause 3.14 or through an instruction under clause 3.16 in regard to a Provisional
Sum for defned work.

Notice by Contractor of delay to progress


2.27 .1 If and whenever it becomes reasonably apparent that the progress of the Works or any Section is
being or is likely to be delayed the Contractor shall forthwith give notice to the Architect/ Contract
Administrator of the material circumstances, including the cause or causes of the delay, and shall
identify in the notice any event which in his opinion is a Relevant Event.

.2 In respect of each event identifed in the notice the Contractor shall, if practicable in such notice or
otherwise in writing as soon as possible thereafter, give particulars of its expected effects, including
an estimate of any expected delay in the completion of the Works or any Section beyond the relevant
Completion Date.

.3 The Contractor shall forthwith notify the Architect/Contract Administrator of any material change in
the estimated delay or in any other particulars and supply such further information as the Architect/
Contract Administrator may at any time reasonably require.

Fixing Completion Date


2.28 .1 If, in the Architect/Contract Administrator's opinion, on receiving a notice and particulars under
clause 2.27:

.1 any of the events which are stated to be a cause of delay is a Relevant Event; and
.2 completion of the Works or of any Section is likely to be delayed thereby beyond the relevant
Completion Date,

then, save where these Conditions expressly provide otherwise, the Architect/Contract Administrator
shall give an extension of time by fxing such later date as the Completion Date for the Works or
Section as he then estimates to be fair and reasonable.

.2 Whether or not an extension is given, the Architect/Contract Administrator shall notify the Contractor
of his decision in respect of any notice under clause 2.27 as soon as is reasonably practicable and
in any event within 12 weeks of receipt of the required particulars. Where the period from receipt
to the Completion Date is less than 12 weeks, he shall endeavour to do so prior to the Completion
Date.

.3 The Architect/Contract Administrator shall in his decision state:

.1 the extension of time that he has attributed to each Relevant Event; and .
.2 (in the case of a decision under clause 2.28.4 or 2.28.5) the reduction in time that he has
attributed to each Relevant Omission.

.4 After the frst fxing of a later Completion Date in respect of the Works or a Section, either under
clause 2.28.1 or by a Pre-agreed Adjustment, but subject to clauses 2.28.6.3 and 2.28.6.4, the
Architect/Contract Administrator may by notice to the Contractor, giving the details referred to in
clause 2.28.3, fx a Completion Date for the Works or that Section earlier than that previously
so fxed if in his opinion the fxing of such earlier Completion Date is fair and reasonable, having
regard to any Relevant Omissions for which instructions have been issued after the last occasion
on which a new Completion Date was fxed for the Works or for that Section.

.5 After the Completion Date for the Works or for a Section, if this occurs before the date of practical
completion, the Architect/Contract Administrator may, and not later than the expiry of 12 weeks after
the date of practical completion shall, by notice to the Contractor, giving the details referred to in
clause 2.28.3:
190 The JCT Standard Building Contract

.1 fx a Completion Date for the Works or for the Section later than that previously fxed if in his
opinion that is fair and reasonable having regard to any Relevant Events, whether on reviewing a
previous decision or otherwise and whether or not the Relevant Event has been specifcally noti-
fed by the Contractor under clause 2.27.1; or
.2 subject to clauses 2.28.6.3 and 2.28.6.4, fx a Completion Date earlier than that previously
fxed if in his opinion that is fair and reasonable having regard to any instructions for Relevant
Omissions issued after the last occasion on which a new Completion Date was fxed for the
Works or Section; or .
.3 confrm the Completion Date previously fxed.

.6 Provided always that:


.1 the Contractor shall constantly use his best endeavours to prevent delay in the progress of the
Works or any Section, however caused, and to prevent the completion of the Works or Section
being delayed or further delayed beyond the relevant Completion Date;
.2 in the event of any delay the Contractor shall do all that may reasonably be required to the satis-
faction of the Architect/Contract Administrator to proceed with the Works or Section;
.3 no decision of the Architect/Contract Administrator under clause 2.28.4 or 2.28.5.2
shall fx a Completion Date for the Works or any Section earlier than the relevant Date for
Completion; and
.4 no decision under clause 2.28.4 or 2.28.5.2 shall alter the length of any Pre-agreed Adjustment
except in the case of a Variation Quotation where the relevant Variation is itself the subject of a
Relevant Omission.

Relevant Events
2.29 The following are the Relevant Events referred to in clauses 2.27 and 2.28:

.1 Variations and any other matters or instructions which under these Conditions are to be treated as,
or as requiring, a Variation;

.2 Architect/Contract Administrator's instructions:

.1 under any of clauses 2.15, 3.15, 3.16 (excluding an instruction for expenditure of a Provisional
Sum for defned work), or 5.3.2; or .
.2 for the opening up for inspection or testing of any work, materials or goods under clause 3.17 or
3.18.4 (including making good), unless the inspection or test shows that the work, materials or
goods are not in accordance with this Contract;

.3 deferment of the giving of possession of the site or any Section under clause 2.5;

.4 compliance with 3.22.1 or with Architect/Contract Administrator’s instructions under clause 3.22.2;

.5 the execution of work for which an Approximate Quantity is not a reasonably accurate forecast of the
quantity of work required;

.6 suspension by the Contractor under clause 4.14 of the performance of his obligations under this
Contract;

.7 any impediment, prevention or default, whether by act or omission, by the Employer, the
Architect/Contract Administrator, the Quantity Surveyor or any of the Employer's Persons,
except to the extent caused or contributed to by any default, whether by act or omission, of
the Contractor or of any of the Contractor’s Persons;

.8 the carrying out by a Statutory Undertaker of work in pursuance of its statutory obligations in relation
to the Works, or the failure to carry out such work;

.9 exceptionally adverse weather conditions;

.10 loss or damage occasioned by any of the Specifed Perils;

.11 civil commotion or the use or threat of terrorism and/or the activities of the relevant authorities
in dealing with such event or threat;

.12 strike, lock-out or local combination of workmen affecting any of the trades employed upon the Works
or any of the trades engaged in the preparation, manufacture or transportation of any of the goods
Section 2: carrying out the works 191

or materials required for the Works or any persons engaged in the preparation of the design for the
Contractor’s Designed Portion;

.13 the exercise after the Base Date by the United Kingdom Government of any statutory power which
directly affects the execution of the Works;

.14 force majeure.

own fault. Obviously, more than one notice under these clauses 3.31 Under clause 2.28.4, if the Architect has already exercised
may be served during the currency of the contract. the power to grant an extension, he or she may fix a completion
date which is earlier than the previously extended completion
3.26 It was held in Balfour Beatty Building Ltd v Chestermount date if he or she thinks it fair and reasonable to do so, having
Properties Ltd (1993) 62 BLR 1 that where the works are regard to variations requiring the omission of work which have
delayed as a result of the contractor’s fault, so that the original been issued after the last occasion on which an extension of
completion date has passed, the Architect still has power on the time was granted. This is, however, subject to the proviso that
happening of a Relevant Event to re-fix the completion date. The (under Clause 2.28.6.3) no completion date can be fixed earlier
appropriate way to do this is to take the original completion date than the date for completion stated in the Contract Particulars.
and add the number of days which the Architect regards as fair Thus, the Architect is entitled to reduce a previously granted
and reasonable in all the circumstances, even if the effect of this extension of time if work is subsequently ordered to be omitted,
is that the new completion date has already passed before the thereby reducing the amount of the contractor’s commitments
happening of the Relevant Event. It would be wrong in princi- and justifying an earlier completion date, but he or she cannot
ple to re-fix the completion date by starting at the date of the rewrite the contract. RIBA Publications Ltd publishes a form of
Relevant Event and adding days to that date. ‘Notification of Revision to Completion Date’.

Architect’s action Duty of Architect to review


3.27 On receipt of the contractor’s notice, particulars and esti-
after practical completion
mate, the Architect must first decide whether the contractor is 3.32 When practical completion has occurred, provision is made
entitled to an extension of time in principle (i.e. whether the for the Architect finally to review the position as regards exten-
delay is caused by a Relevant Event as defined by clause 2.29) sions of time. This must be done within 12 weeks after practical
and secondly, whether the occurrence of the Relevant Event will, completion (clause 2.28.5). The Architect may fix a later com-
in fact, cause delay beyond the completion date. Having decided pletion date than that previously fixed and in so doing take into
these two points, the Architect grants an extension of time, if account all Relevant Events, whether or not specifically notified
he or she thinks that it is fair and reasonable to do so, by fix- by the contractor. It is also open to the Architect to fix an earlier
ing a new completion date which is notified to the contractor in completion date, having regard to omissions which have occurred
writing. The notice must state the extension of time which the since the last occasion when an extension of time was granted.
Architect has attributed to each Relevant Event. Alternatively, he or she may simply confirm the previously fixed
completion date. It is important for the Architect to carry out an
3.28 In making the decision, the Architect must consider a num- overall review with knowledge of all the relevant facts and with
ber of different matters, including the effect of other causes of time to make a care full-assessment of the contractor’s entitlement.
delay, whether they are or are not Relevant Events, and action
taken by the contractor both to prevent delay and in the event
of delay: clause 2.28.6.
Relevant events
3.33 The first six of the Relevant Events are also Relevant
3.29 Where delay is caused by two events, one of which is a Matters falling within clauses 4.23 and 4.24, which entitle the
Relevant Event and the other is not, and both events occur at contractor to claim the reimbursement of direct loss and expense
the same time, and their effects are felt at the same time, there is incurred by it. Hence, notices of delay and applications for
concurrent delay. In those circumstances, the contractor remains reimbursement are likely to be combined in the case of these
entitled to an extension of time, and no reduction should be Relevant Events/Matters. Only some of the Relevant Events
made on account of the fact that an event that is not a Relevant require any comment.
Event has also caused the delay (see Walter Lilly & Co Limited
v Mackay [2012] BLR 503). True concurrency is a relatively rare
occurrence. It is more likely to occur at the beginning of a project Clause 2.29.4
(for example where the employer does not give possession of the 3.34 This Relevant Event relates to the discovery of Antiquities
site (a Relevant Event), but the contractor is unable to mobilise and was introduced in the 2011 edition of the form.
in any event due to lack of resources (not a Relevant Event)).

3.30 The Architect must either issue a new completion date or Clause 2.29.6
notify the contractor of the decision not to do so, as soon as 3.35 Clause 4.13 allows the contractor to suspend performance
is reasonably practicable and in any event within 12 weeks of of the works if the employer fails to pay it in full (pursuant to
receipt of the required particulars, or (where there are fewer than the contract and subject to the giving of withholding notices).
12 weeks to completion) no later than the completion date (using This gives effect to s.112(4) of the Construction Act, and such
his best endeavours). a suspension is not to be construed as a failure to proceed
192 The JCT Standard Building Contract

diligently with the works, but entitles the contractor to an exten- Clause 2.29.9
sion of time.
3.38 Exceptionally adverse weather conditions require quite
unusual severity: it will frequently be necessary to establish this
Clause 2.29.7 with the aid of weather charts covering a considerable period.
3.36 This sub-clause creates a wide-ranging Relevant Event in Note that the definition includes exceptional extremes of heat
respect of acts of prevention or events of default committed by and dryness, as well as the more normal British weather; such
the employer or any other person for whom the employer is extremes can, of course, have a serious effect on progress. An
contractually responsible. Such acts or events will only amount earlier version of the form used the term ‘inclement’ rather than
to a Relevant Event to the extent that the contractor or those ‘adverse’ and was discussed in Walter Lawrence v Commercial
for which he is contractually responsible have not caused or Union Properties (1984) 4 Con. L.R. 37, in which it was estab-
contributed to them. lished that it was the weather itself that had to be exceptionally
inclement. It is not enough that the delay caused by the weather
is exceptional. The relevant time for determining whether or
Clause 2.29.8 not the weather conditions are exceptional is when the work
3.37 This sub-clause covers delay caused by statutory undertak- was actually carried out and not when it was planned to be
ers in performing their statutory obligations, usually the lay- carried out.
ing of gas, water, and electricity mains. Where the contractor
has no choice but to employ these statutory undertakers, it is Clause 2.29.10
thought unjust that it should be penalised for their delay. This
sub-clause does not apply where the statutory undertaker is 3.39 Loss from specified perils (defined in clause 6.8): these
carrying out work extending beyond its statutory obligations contingencies are very wide, and in some instances may be due
pursuant to a contract with the employer or the contractor (see to an act of negligence on the part of the contractor, at any rate
Henry Boot Construction Limited v Central Lancashire New in their underlying causes.
Town Development Corporation (1981) 15 BLR 1). It also does
not apply where the statutory undertaker is exercising a statu- Clause 2.29.13
tory decision-making power as opposed to carrying out physical
works affecting the site (see Walter Lilly & Co Limited v Clin 3.40 This clause will tend to reduce the scope of the immediately
[2018] BLR 321.) following ‘force majeure’ Relevant Event.

Practical Completion, Lateness and Liquidated Damages

Practical completion and certifcates

2.30 When in the Architect/Contract Administrator's opinion practical completion of the Works or a
Section is achieved and the Contractor has complied suffciently with clauses 2.40 and 3.23.4,
then:
.1 in the case of the Works, the Architect/Contract Administrator shall forthwith issue a certifcate to
that effect (‘the Practical Completion Certifcate');

.2 in the case of a Section, he shall forthwith issue a certifcate of practical completion of that Section
(a ‘Section Completion Certifcate');
and practical completion of the Works or the Section shall be deemed for all the purposes of this
Contract to have taken place on the date stated in that certifcate.

Non-Completion Certifcates
2.31 If the Contractor fails to complete the Works or a Section by the relevant Completion Date,
the Architect/Contract Administrator shall issue a certifcate to that effect (a ‘Non-Completion
Certifcate’). If a new Completion Date is fxed after the issue of such a certifcate, such fxing
shall cancel that certifcate and the Architect/Contract Administrator shall where necessary issue
a further certifcate.

Payment or allowance of liquidated damages


2.31 .1 Provided:

.1 the Architect/Contract Administrator has issued a Non-Completion Certifcate for the Works or a
Section; and
.2 the Employer has notifed the Contractor before the date of the Final Certifcate that he may
require payment of, or may withhold or deduct, liquidated damages,
the Employer may, not later than 5 days before the fnal date for payment of the debt due under the Final
Certifcate, give notice to the Contractor in the terms set out in clause 2.32.2.
Section 2: carrying out the works 193

Clause 2.29.14 the Contract Particulars. The issue of a certificate under clause
2.31 is a condition precedent to the employer’s right to deduct
3.41 The meaning of the term ‘force majeure’ is difficult to state liquidated damages (see Ramac Construction v Lesser [1975]
exactly, but very broadly, the words extend to special circum- 2 Lloyd’s Reports 430).
stances quite outside the control of the contractor, arising from
a cause which is unforeseeable, but inevitable. Such happenings 3.45 The certificate is, it seems, required in order to ensure that
will not, by their very nature, have been dealt with elsewhere in the Architect has properly considered any contractor’s notices
the contract. The effect of inundations and epidemics are exam- of delay given under clause 2.27 and has granted all extensions
ples of events which are probably within this clause. Financial of time to which the contractor is entitled. Under clause 2.28,
difficulties experienced by the contractor are equally clearly not provision is made for reassessment of the need for extension
within this definition. Because of the specific inclusion of speci- of time throughout the contract period. Clause 2.32.3 provides
fied perils and government interference earlier in the Relevant for the situation where, after liquidated damages have been
Events, it is probable that ‘force majeure’ requires to be given a deducted, a later completion date is fixed under clause 2.28.5.1.
restrictive definition in these Conditions. In such circumstances, the employer would be obliged to pay or
repay to the contractor amounts in respect of the period up to
Practical completion, lateness such later completion date. Clause 2.32.3 does not state whether
and liquidated damages the employer must pay interest on any damages repaid, and it is
unclear at present what is the correct interpretation of the clause
3.42 Clause 2.30 provides for the issue of a certificate of practi- in this respect.
cal completion when, in the opinion of the Architect, practical
completion of the works or of a section of the works has been 3.46 Clause 2.32 provides two methods by which the employer
achieved, and the contractor has sufficiently complied with may recover liquidated damages that are due: either as a debt
clauses 2.40 (as built contractor’s design drawings) and 3.23.4 (clause 2.32.2.1) or by deduction from monies due to the con-
(health and safety file information). The certificate signifies that tractor (clause 2.32.2.2). The latter method now requires notice
all the necessary construction work has been done without any to be given to the contractor (under clause 4.13.4 or clause
obvious defects, but does not exclude the existence of latent 4.15.4), to ensure compliance with section 111 of the HGCRA
defects. 1996.

3.43 Clause 2.31 obliges the Architect to issue a certificate of


non-completion in the relevant circumstances, whether or not Meaning of practical completion
the employer intends to deduct (or call for the payment of) 3.47 The term ‘practical completion’ is not defined in the con-
liquidated damages. tract, but it has been said (by Lord Dilhorne in Westminster City
Council v Jarvis Limited [1970] 1 All ER 943 at 948) that it does
3.44 Clause 2.32 gives the employer the right to deduct or not mean the stage when the work ‘was almost but not entirely
claim liquidated and ascertained damages at the rate stated in finished’, but ‘the completion of all the construction work that

Defects

Schedules of defects and instructions

2.38 If any defects, shrinkages or other faults in the Works or a Section appear within the relevant
Rectifcation Period due to materials, goods or workmanship not in accordance with this Contract or
any failure of the Contractor to comply with his obligations in respect of the Contractor’s Designed
Portion:
.1 such defects, shrinkages and other faults shall be specifed by the Architect/Contract Administrator
in a schedule of defects which he shall deliver to the Contractor as an instruction not later than
14 days after the expiry of that Rectifcation Period; and

.2 notwithstanding clause 2.38.1, the Architect/Contract Administrator may whenever he considers it


necessary issue instructions requiring any such defect, shrinkage or other fault to be made good,
provided no instructions under this clause 2.38.2 shall be issued after delivery of a schedule of
defects or more than 14 days after the expiry of the relevant Rectifcation Period.
Within a reasonable time after receipt of such schedule or instructions, the defects, shrinkages and
other faults shall at no cost to the Employer be made good by the Contractor unless the Architect/
Contract Administrator with the Employer’s consent shall otherwise instruct. If he does so otherwise
instruct, an appropriate deduction shall be made from the Contract Sum in respect of the defects,
shrinkages or other faults not made good.

Certifcate of Making Good


2.39 When in the Architect/Contract Administrator’s opinion the defects, shrinkages or other faults in the
Works or a Section which he has required to be made good under clause 2.38 have been made good,
he shall issue a certifcate to that effect (a ‘Certifcate of Making Good’), and completion of that mak-
ing good shall for the purposes of this Contract be deemed to have taken place on the date stated
in that certifcate.
194 The JCT Standard Building Contract

has to be done’. Such completion is subject to defects which or grounds for withholding payment. Under the 1963 JCT Form,
may thereafter appear and require action under clause 2.38. In it has been held that no certificate under clause 22 of that form
the same case in the Court of Appeal, Salmon LJ said: (the equivalent clause to clause 2.32) could be issued after the
issue of the final certificate (Fairweather v Asden Securities
I take these words to mean completion for all practical pur- [1980] 12 BLR 40). It is thought that the position is the same
poses, i.e. for the purpose of allowing [the employer] to take under subsequent editions.
possession of the works and use them as intended. If “com-
pletion” in Clause 21 [Clause 2.4 of the 2005 Form] means
completion down to the last detail, however trivial and
Advantage of liquidated damages
unimportant, then Clause 22 [Clause 2.32 of the 2005 Form] 3.52 If there is no provision for liquidated damages, ascertain-
would be a penalty clause and as such unenforceable. ment of the loss suffered by reason of non-completion can
involve the parties in long and costly proceedings and be dif-
Neither explanation is binding as to the meaning of the words for ficult for the employer to prove. Where the parties have made
the purposes of considering whether the contractor has reached and agreed a genuine and commercially justifiable pre-estimate
the stage of practical completion. However, it is suggested that of damages, such proceedings are avoided, and the parties have
the Architect can issue the certificate despite very minor defects greater certainty. The rate agreed, described here as ‘liquidated
(applying the de minimis principle: HWNevill [Sunblest] Limited damages’, will be given effect to by the courts without enquiring
v Wm Press & Son Limited [1982] 20 BLR 78) if: into the actual loss suffered.

1 Reasonably satisfied that the works accord with the contract;


and
Liquidated damages and
2 There is adequate retention; and penalties distinguished
3 The employer will not suffer loss due to disturbance or 3.53 In circumstances where the liquidated damages are con-
otherwise; and strued as a penalty, the contractor can have the agreed rate of liq-
4 He or she obtains a written acknowledgement of the exist- uidated damages set aside and make the employer prove and be
ence of any defects and an undertaking from the contractor limited to his actual loss. It is therefore extremely important that
to put them right. If the defects are other than trivial, the liquidated damages should be stated in the Contract Particulars
views of the employer should first be obtained. in such a way that they cannot be construed as being a penalty.
This is particularly likely to happen, as it did in Bramall &
More recently, it has been reiterated that practical completion Ogden Ltd v Sheffield City Council (1985) 29 BLR 73, where the
means completion for all practical purposes. What that requires liquidated damages provision is sectional, but sectional comple-
in practice depends on the nature and scope of the works and tion is not required by the contract.
any contractual definition. Snagging items that can properly be
regarded as de minimis will not prevent practical completion 3.54 In order to ensure that a sum entered for liquidated dam-
from being certified (see Walter Lilly & Co Limited v Mackay ages is enforceable and is not struck down as a penalty with the
[2012] BLR 503). See also Mears Limited v Costplan [2019] effect that the employer would have to prove his actual losses
EWCA Civ 502 arising from late completion, the specified sum must be one that
It goes without saying that the Architect must exercise the is commercially justifiable and not ‘out of all proportion to any
above discretion with extreme care. legitimate interests’ of the employer in enforcing the completion
date (see Cavendish Square Holding BV v Tala El Makdessi
Form of certifcate [2015] UKSC 67).
3.48 This is not prescribed by the contract, but it should be clear
and definite. The RIBA issues suitable forms. Delay partly employer’s fault
3.55 At common law, an employer who was partly responsi-
ble for delay could not rely on a liquidated damages clause.
Effect of certifcate of practical However, under clause 2.28, extensions of time may be granted
completion in respect of Relevant Events which include delay caused by
3.49 The practical completion certificate has the following the employer’s fault, and, provided such extensions are properly
important effects: granted, the right to liquidated damages is preserved.

1 It marks the date when the employer re-takes possession of 3.56 Failure to grant proper extensions of time in respect
the site (subject to clauses 2.6 and 2.33). of such Relevant Events as arise through the employer’s
2 It fixes the commencement of the Rectification Period (as fault will disentitle him from claiming liquidated damages.
stated in the Contract Particulars). In Percy Bilton Ltd v Greater London Council [1982] 2 All
3 It fixes the commencement of the period for the final adjust- ER 63 (HL), it was held that delay caused by the bankruptcy
ment of the contract sum (clause 4.5). of a nominated sub-contractor (for which no provision for
4 It gives rise to the right of release of the first half of the extension is made by clause 2.28) did not arise through any
retention percentage (clause 4.20.3). fault of the employer, so he was not disentitled from claiming
5 It marks the time for release of the contractor’s obligation liquidated damages.
to insure under Schedule 3 Option A where this applies.
6 It marks the end of the contractor’s liability for liquidated
dam ages under clause 2.32. Partial possession by employer
3.57 Clauses 2.33 to 2.37 bring forward clauses previously
3.50 The employer’s remedies for defective work are not lim- found in clause 18 of the 1998 edition. They provide for the
ited to those contained in clause 2.38 (requiring the contractor situation where, before the works are completed, the employer,
to make good defects). It may additionally sue for damages for with the contractor’s consent, takes possession of part or
breach of contract: HWNevill (Sun Blest) Ltd v Wm Press & Son parts of the works. They include provisions as to practical
Ltd (1982) 20 BLR 78. completion, defects, insurance, and retention percentage for
application to each part analogous to those which apply to the
Procedure whole, and for a proportionate reduction of any liquidated dam-
3.51 The requisite clause 4.13.4 or clause 4.15.4 notice should ages payable. The appropriate Contract Particulars entry (refer-
set out the amount that is proposed to be withheld and the ground ring to clause 2.32.2) must be completed so as to allow the
Section 3: control of the works 195

proper operation of clause 2.37, otherwise liquidated damages complied with, others can be employed to do the necessary work
will not be enforceable. In Bramali & Ogden Ltd v Sheffield and the cost deducted from the Retention Percentage. Further,
City Council (1985) 29 BLR 73 (a case on the 1963 edition), until defects have been made good, the Architect need not and
the Appendix had been completed so as to allow a sum in should not issue his Certificate of Making Good. The second
damages for each incomplete dwelling. This was held to be half of the Retention Percentage will not be released, and issue
inconsistent with Clause 16(e) (equivalent to clause 2.37). of the Final Certificate, with the protection it usually affords to
If possession is given in sections, the Architect must apply the contractor (see clause 1.10), may be delayed. The power of
clauses 2.33 to 2.37 strictly and has no power, without the determination under clause 8.4 is not designed to be exercised
parties’ consent, to issue a certificate of practical completion after practical completion, and the remedies set out above ought
for an average date of completion. to be sufficient to make it unnecessary to attempt to rely on
clause 8.4.
Duty to complete in sections
3.58 Clause 2.33 does not impose any duty or right for to
Irremediable breach
complete in sections. Equally, if the contractor is delayed and 3.65 The Architect may require a defect to be remedied in an
therefore subject to the deduction of liquidated damages, it is instruction or in the schedule, but then find that the relevant
not entitled to any contra-credit for having completed some defect cannot be remedied except at a cost which is unreason-
of the work before the contractual completion date, although able in comparison with the nature of the defect and the loss
an employer’s unreasonable refusal of an offer of partial to the employer resulting from it. If the employer consents, the
possession might limit its entitlement to recover liquidated Architect may issue the Certificate of Making Good under clause
damages. If sectional completion is required, the provisions 2.39, having made an ‘appropriate’ deduction from the Contract
of the Contract Particulars for Sectional Completion must be Sum by the amount certified for payment in respect of the works
completed. not properly carried out (clause 2.38). This deduction will usu-
ally be the amount by which the works are reduced in value by
reason of the unremedied defect.
Defects
3.59 The Contract Particulars require a Rectification Period to
be stated. In default, the contract specifies the period to be six
Defects appearing after the expiry
months. If any defects, shrinkages, or faults (due to materials or of the defects liability period
workmanship not in accordance with the contract, or any failure 3.66 If defects appear after the issue of the Certificate under
by the contractor to comply with its obligations in respect of clause 2.39, the Architect can no longer issue instructions under
the Contractor’s Designed Portion) appear within this period, clause 2.38, but such defects will still amount to a breach of
the Architect should list these in a schedule of defects. This contract by the contractor. As such, the employer is entitled to
must be delivered to the contractor no later than 14 days after damages, and the Architect should adjust any further certificate
the end of the Rectification Period. The contractor must then, to reflect the effect on the value of the works. In accordance with
within a reasonable time, make good these defects at its own common law rules as to mitigation of damages, the contractor,
cost. An alternative procedure is to allow the defects to remain if it is reasonable to do so, should be given the opportunity of
and make a deduction from the contract sum. This must be the rectifying the defects. A Final Certificate should not be issued if
subject of an architect’s instruction issued with the consent of the defects remain unremedied (see clause 1.10).
the employer.

3.60 The Architect also has power at any time before issu- 4 Section 3: control of the works
ing the comprehensive schedule of defects to issue instruc-
tions requiring the contractor to make good particular defects 4.01 The scope of this section extends over a number of different
(clause 2.38.2). In practice, the Architect may wish to leave the matters, the most important of which for present purposes are
delivery of a schedule of defects as late as possible in order Access and Representatives (clauses 3.1 to 3.6) and Architect/
to ensure that all defects are captured in the schedule, using Contract Administrator’s Instructions (clauses 3.10 to 3.21).
the clause 2.38.2 procedure until then. The Architect is not
entitled to issue instructions for the making good of defects
under clause 2.38.2 after the schedule of defects under clause Access and Representatives
2.38.1 has been issued. 4.02 In the absence of express provision, doubts might arise as
to the Architect’s right of access to the site, since the contractor
3.61 After all such defects, shrinkages, or faults have been made is entitled as against the employer to free and uninterrupted pos-
good, the Architect should issue a Certificate of Making Good: session of the site during the progress of the works. Therefore,
clause 2.39. Its issue acts as a trigger for the Final Certificate clause 3.1 reserves to the Architect and his or her authorised
timetable (clause 4.26.1) and the final release of Retention representative an express right of access to the works. There is a
(clause 4.20.3). similar right of access in relation to workshops and other places
in the possession of the contractor or a sub-contractor where
Meaning of defects work is being prepared for incorporation in the works. This right
is subject to such reasonable restrictions by the contractor and
3.62 For the contractor’s obligation as to standards of workman- sub-contractor as are necessary to protect any proprietary right
ship, materials, and goods, see clauses 2.1 and 2.3. Defects are, in the work for the contract. The provisions relating to sub-con-
generally, work, materials, and goods which are not in conform- tractors do not, of course, directly affect the obligations of the
ity with the contract documents. They do not include a failure sub-contractors, but the contractor would be liable in damages to
by the Architect to design the works, for example. the employer if the employer could establish loss flowing from
failure by the contractor to ensure that the appropriate terms
3.63 It is, in general, no excuse for a contractor to say that the were included in the sub-contracts.
Architect or the Clerk of Works ought to have observed bad
work during site inspections. 4.03 The person-in-charge on site is the contractor’s agent to
receive instructions. To avoid confusion, he or she should be
Architect’s remedies named.

3.64 A notice under clause 3.11 can be given for non-compliance 4.04 The note to clause 3.3 makes it clear that, in order to
with an instruction to make good defects. If the notice is not avoid any risk of confusion between the different roles of
196 The JCT Standard Building Contract

Section 3 Control of the Works

Access and Representatives

Access for Architect/Contract Administrator


3.1 The Architect/Contract Administrator and any person authorised by him shall at all reasonable times
have access to the Works and to the workshops or other premises of the Contractor where work is
being prepared for this Contract. When work is to be prepared in workshops or other premises of a
sub-contractor the Contractor shall by a term in the sub-contract secure so far as possible a similar
right of access to those workshops or premises for the Architect/Contract Administrator and any
person authorised by him and shall do all things reasonably necessary to make that right effective.
Access under this clause 3.1 may be subject to such reasonable restrictions as are necessary to
protect proprietary rights.

Clerk of works
3.4 The Employer shall be entitled to appoint a clerk of works whose duty shall be to act solely as
inspector on behalf of the Employer under the Architect/Contract Administrator's directions and the
Contractor shall afford every reasonable facility for the performance of that duty. If any direction is
given to the Contractor by the clerk of works, it shall be of no effect unless given in regard to a matter
in respect of which the Architect/Contract Administrator is expressly empowered by these Conditions
to issue instructions and unless confrmed in writing by the Architect/Contract Administrator within
2 working days of the direction being given. Any direction so given and confrmed shall, as from the
date of issue of that confrmation, be deemed an instruction of the Architect/Contract Administrator

individuals involved in the contract, neither the Architect/ 3 The replacement is bound to follow any certificate, opinion,
Contract Administrator nor the Quantity Surveyor should be decision, approval, or instruction given or expressed by his
appointed as the Employer’s representative. or her predecessor, except and insofar as that predecessor
would have been able to disregard or overrule it.
4.05 Clerks of works are to act ‘solely as inspector’. They are
not the Architect’s agent to give instructions, and it will be a 4.08 Clause 3.6 restates the contractor’s primary and entire
source of confusion and dispute if they purport to do so. If the responsibility for carrying out the works in accordance with
clerk of works gives ‘directions’, they are to be of no effect the contractual Conditions, unaffected by any supervision or
unless and until converted into Architect’s Instructions by the inspection by the Architect or clerk of works or by the issue by
Architect within two working days. Such directions can lead the Architect of any certificate, whether in respect of an interim
to uncertainty on the part of the contractor. It is suggested that payment or otherwise.
the clerk of works should be discouraged from giving direc-
tions unless absolutely essential. However, if directions are to
be given, the problems will be minimised if they are given in
Sub-contracting
writing and the Architect immediately confirms, amends, or 4.09 The increasingly complicated provisions for nominations of
rejects them. If the clerk of works gives ‘directions’ in regard sub-contractors and suppliers which developed through earlier
to a matter in respect of which the Architect is not empowered editions of the JCT forms have now all disappeared since the
to issue instructions, and the contractor follows that direction, 2005 edition. The only involvement of the employer in the selec-
it may be that the Architect can sanction that ‘direction’ under tion of sub-contractors is through the listing process contained
clause 3.14.4. in clause 3.8. The Architect’s only involvement in the process is
the giving of consent to sub-contracting of the whole or part of
4.06 In Kensington and Chelsea and Westminster Area Health the works (clause 3.7.1), which consent is not to be unreasonably
Authority v Wettern Composites (1986) 31 BLR 57, it was held delayed or withheld.
that the employer was responsible for the contributory negli-
gence of the clerk of works, because the clerk of works was
his employee. Responsibility for his acts was not borne by the
Architect/Contract
Architect, even though he was acting under the direction and Administrator’s instructions
control of the Architect. 4.10 Clauses 3.10–3.13 govern the Architect’s authority to give
instructions and the contractor’s duty, subject to certain condi-
4.07 Clause 3.5 is designed to ensure continuity in the con- tions, to comply with those instructions. Clauses 3.14–3.16
tractual posts of Architect/Contract Administrator and Quantity specify the Architect’s authority to vary or postpone the works,
Surveyor. The clause protects the contractor from the whims of and clauses 3.17–3.21 concern the Architect’s authority to control
the employer in that: work, workmanship, goods, or materials which are found to be not
in accordance with the contract. The wording of clauses 3.14–3.21
1 The employer is obliged to give the contractor notice of the is clear, and those clauses do not here call for separate comment.
identity of any replacement in either role.
2 The contractor may object to the nominated replacement, 4.11 The contractor must comply with the Architect’s instruc-
which objection may be accepted by the employer or tions. Failure to do so gives rise to the employer’s right under
decided by an adjudicator. clause 3.11 to have work carried out by others, and in some
Section 3: control of the works 197

Architect/Contract Administrator’s instructions

Compliance with instructions

3.10 The Contractor shall forthwith comply with all instructions issued to him by the Architect/Contract
Administrator in regard to any matter in respect of which the Architect/Contract Administrator is
expressly empowered by these Conditions to issue instructions, save that:
.1 where an instruction requires a Variation of the type referred to in clause 5.1.2, the Contractor need
not comply to the extent that he notifes a reasonable objection to it to the Architect/ Contract
Administrator;

.2 where an instruction for a Variation is given which pursuant to clause 5.3.1 requires the Contractor
to provide a Variation Quotation, the Variation shall not be carried out until the Architect/Contract
Administrator has in relation to it issued either a Confrmed Acceptance or a further instruction
under clause 5.3.2;

.3 in the Contractor's opinion compliance with any direction under clause 2.2.2 or any instruction
issued by the Architect/Contract Administrator injuriously affects the effcacy of the design of the
Contractor's Designed Portion (including the obligations of the Contractor to comply with regulations
11, 12 and 18 of the CDM Regulations), he shall within 7 days of receipt of the direction or instruc-
tion give notice to the Architect/Contract Administrator specifying the injurious effect, and the direc-
tion or instruction shall not take effect unless confrmed by the Architect/Contract Administrator.

Non-compliance with instructions


3.11 Subject to clause 3.10, if within 7 days after receipt of a notice from the Architect/Contract
Administrator requiring compliance with an instruction the Contractor does not comply, the Employer
may employ and pay other persons to execute any work whatsoever which may be necessary to
give effect to that instruction. The Contractor shall be liable for all additional costs incurred by the
Employer in connection with such employment and an appropriate deduction shall be made from the
Contract Sum.

Instructions other than in writing


3.12 .1 Where the Architect/Contract Administrator issues an instruction otherwise than in writing, it shall
be of no immediate effect but the Contractor shall confrm it in writing to the Architect/ Contract
Administrator within 7 days, and, if he does not dissent by notice to the Contractor within 7 days
from receipt of the Contractor's confrmation, it shall take effect as from the expiry of the latter 7 day
period.

.2 If within 7 days of giving an instruction otherwise than in writing the Architect/Contract Administrator
confrms it in writing, the Contractor shall not be obliged to confrm it and it shall take effect as from
the date of the Architect/Contract Administrator's confrmation.

.3 If neither the Contractor nor the Architect/Contract Administrator confrms such an instruction in the
manner and time stated but the Contractor nevertheless complies with it, the Architect/ Contract
Administrator may at any time prior to the issue of the Final Certifcate confrm it with retrospective
effect.

Provisions empowering instructions


3.13 On receipt of an instruction or purported instruction the Contractor may request the Architect/ Contract
Administrator to notify him which provision of these Conditions empowers its issue and the Architect/
Contract Administrator shall forthwith comply with the request. If the Contractor thereafter complies
with that instruction with neither Party then having invoked any dispute resolution procedure under this
Contract to establish the Architect/Contract Administrator’s powers in that regard, the instruction shall be
deemed to have been duly given under the specifed provision.

Instructions requiring Variations


3.14 .1 The Architect/Contract Administrator may issue instructions requiring a Variation.

.2 Any instruction of the type referred to in clause 5.1.2 shall be subject to the Contractor’s right of
reasonable objection set out in clause 3.10.1.

.3 In respect of the Contractor’s Designed Portion, any instruction requiring a Variation shall be an
alteration to or modifcation of the Employer’s Requirements.
198 The JCT Standard Building Contract

.4 The Architect/Contract Administrator may sanction in writing any Variation made by the Contractor
otherwise than pursuant to an instruction.

.5 No Variation required by the Architect/Contract Administrator or subsequently sanctioned by him


shall vitiate this Contract.

Postponement of work
3.15 The Architect/Contract Administrator may issue instructions in regard to the postponement of any
work to be executed under this Contract.

Instructions on Provisional Sums


3.16 The Architect/Contract Administrator shall issue instructions in regard to the expenditure of
Provisional Sums included in the Contract Bills or in the Employer’s Requirements.

Inspection – tests
3.17 The Architect/Contract Administrator may issue instructions requiring the Contractor to open up
for inspection any work covered up or to arrange for or carry out any test of any materials or goods
(whether or not already incorporated in the Works) or of any executed work. The cost of such opening
up or testing (including the cost of making good) shall be added to the Contract Sum unless provided
for in the Contract Bills or unless the inspection or test shows that the materials, goods or work are
not in accordance with this Contract.

Work not in accordance with the Contract


3.18 If any work, materials or goods are not in accordance with this Contract the Architect/Contract
Administrator, in addition to his other powers, may:
.1 issue instructions in regard to the removal from the site of all or any of such work, materials or goods;

.2 after consultation with the Contractor and with the agreement of the Employer, allow all or any of
such work, materials or goods to remain (except those which are part of the Contractor’s Designed
Portion), in which event he shall notify the Contractor to that effect but that shall not be construed
as a Variation and an appropriate deduction shall be made from the Contract Sum;

.3 after consultation with the Contractor, issue such instructions requiring a Variation as are reasonably
necessary as a consequence of any instruction under clause 3.18.1 and/or of any notifcation under
clause 3.18.2 (but to the extent that such instructions are reasonably necessary, no addition shall
be made to the Contract Sum and no extension of time shall be given); and/or

.4 having due regard to the Code of Practice set out in Schedule 4, issue such instructions under
clause 3.17 to open up for inspection or to test as are reasonable in all the circumstances to
establish to the reasonable satisfaction of the Architect/Contract Administrator the likelihood or
extent, as appropriate to the circumstances, of any further similar non-compliance. To the extent
that such instructions are reasonable, whatever the results of the opening up, no addition shall
be made to the Contract Sum but clauses 2.28 and 2.29.2.2 shall apply unless the inspection
or test shows that the work, materials or goods are not in accordance with this Contract.

Workmanship not in accordance with the Contract


3.19 Where there is any failure to comply with clause 2.1 in regard to the carrying out of work in a proper and
workmanlike manner and/or in accordance with the Construction Phase Plan, the Architect/ Contract
Administrator, in addition to his other powers, may, after consultation with the Contractor, issue such
instructions (whether requiring a Variation or otherwise) as are in consequence reasonably necessary.
To the extent that such instructions are reasonably necessary, no addition shall be made to the Contract
Sum and no extension of time shall be given.

Executed work
3.20 In respect of any materials, goods or workmanship, as comprised in executed work, which under
clause 2.3 are to be to the reasonable satisfaction of the Architect/Contract Administrator, the
Architect/Contract Administrator, if he is dissatisfed, shall give the reasons for such dissatisfaction
to the Contractor within a reasonable time from the execution of the unsatisfactory work.

Exclusion of persons from the Works


3.21 The Architect/Contract Administrator may (but shall not unreasonably or vexatiously) issue instruc-
tions requiring the exclusion from the site of any person employed thereon.
Section 4: payment 199

circumstances can result in the employer having the right to writing if the Architect in fact issues an oral instruction. Instructions
determine the contractor’s employment (see clause 8.4.1.3). should be given in clear terms. The RIBA publishes a common form
for the giving of instructions, which should be used.
Power to issue instructions
Site meeting minutes
4.12 The Architect, by clause 3.10, can only issue instructions
where express power is given to him or her to do so. In some 4.17 Sometimes the Architect and the contractor expressly agree
instances, the employer’s consent is required. The most impor- that site meeting minutes are to operate as the confirmation of
tant powers for the issue of instructions relate to: oral instructions contemplated by clause 3.12.2. If there is no
express agreement as to the status of the minute, in each case it
1 Clause 2.10 (levels). must be decided whether in fact it was intended that the minutes
2 Clause 2.15 (discrepancies in documents). should act as written confirmation of the instructions. Significant
3 Clause 2.16 (discrepancies in CDP documents). factors to take into account would be: (1) the authorship of the
4 Clause 2.17 (divergence between statutory requirements and minutes; (2) whether they are accepted by all parties as a true
documents). record of the meeting; and (3) whether they were circulated
5 Clause 2.38.1 (defects, shrinkages or other faults). after the meeting to give the recipients the opportunity to object.
6 Clause 2.38.2 (rectification of defects).
7 Clause 3.4 (instructions to clerk of works). 5 Section 4: payment
8 Clause 3.14.1 (variations) – subject to right of reasonable
objection in clause 3.14.2. Clauses 4.1–4.5: contract
9 Clause 3.15 (postponement of work).
10 Clause 3.16 (expenditure of provisional sums). sum and adjustments
11 Clause 3.17 (opening up and tests). 5.01 Unless there is a case for rectification, the parties are bound
12 Clause 3.18.1 (removal of work, materials and goods not in by any errors incorporated into the contract sum. Rectification
accordance with the Contract). is available either where: (1) the contract does not give effect
13 Clause 3.18.3 (variation instructions following clauses to a prior concluded agreement; or (2) when the contract was
3.18.1 and 3.18.2). executed, the parties had a common intention that they expressed
14 Clause 3.18.4 (inspections and tests). to each other which, by mistake, the contract does not accu-
15 Clause 3.19 (workmanship not in accordance with the rately record (see FSHC Group Holdings Limited v GLAS Trust
Contract). Corporation Limited [2019] EWCA Civ 1361).
16 Clause 3.21 (exclusion of persons from the works).
17 Clause 3.22 (antiquities). 5.02 Clause 4.3 provides a detailed guide as to how the contract
sum is to be adjusted by way of variation agreements, deduc-
4.13 The Architect will not usually be able to vary the works tions, and additions so as to produce the final account. Clause
simply to have them carried out by a different contractor (see 4.5 provides a timetable for the production of the final account
Commissioner for Main Roads v Reed & Stuart Pty [1974] by way of provision by the contractor of all necessary material
12 BLR 55). Variation instructions to omit works can only be within six months of the date of issue of the Practical Completion
issued if the omitted works are no longer to be carried out at Certificate, and for the production of a final account within three
all. In principle, in the absence of an architect’s instruction, the months thereafter. Subject to the Architect’s decision on matters
contractor is not entitled to extra payment for any increased of principle, the final account will be prepared by the quantity
costs due to variations (although by clause 3.14.4, the Architect surveyor. In Tameside Metropolitan Borough Council v Barlow
may sanction in writing any variation made by the contractor Securities Group Services Ltd [2001] BLR 113, the Court of
otherwise than pursuant to an instruction). Merely permitting Appeal held that it was a pre-condition of the Architect’s duty
the contractor to alter the proposed method of construction at to provide a final account that the contractor should provide him
the contractor’s request does not ordinarily amount to a vari- with all the necessary documentation to do so pursuant to the
ation, although such permission may amount to a variation in requirements of (the predecessor of) clause 4.5.1.
the design or quality – or both – of the works (see Simplex
Concrete Piles v Borough of St Pancras [1980] 14 BLR 80). 5.03 Clause 4.4 provides for adjustments to the Contract Sum to
be included in interim certificates as soon as their amount has
4.14 If the contractor does not comply with any instructions been ascertained.
properly given by the Architect, the Architect may give writ-
ten notice to the contractor to comply. If compliance is not
achieved within seven days, clause 3.11 allows the employer Clauses 4.5–4.14: certifcates
to employ others to carry out and complete the works. The and payments
employer may obtain an interim injunction to prevent the con- 5.04 Clause 4.5.1 states that the Contract Sum is exclusive of
tractor from refusing access to the site for persons whom the VAT and requires the employer to pay the VAT properly charge-
employer has employed to carry out works necessary in respect able in respect of any payment made under the contract. Clause
of an instruction with which the contractor has not complied: 4.5.2 caters for the situation where the supply of goods and ser-
Bath and North East Somerset District Council v Mowlemplc vices to the employer becomes exempt after the date of tender.
[2004] BLR 153.
5.05 Tax is a complex subject, and one wholly outside the scope
4.15 Under clause 3.13, the contractor may request the Architect of this chapter. On any point of difficulty, architects should take
to specify in writing the provision of the Conditions which advice from an accountant, a solicitor, or a barrister specialising
empowers the issue of an instruction. If the Architect specifies in tax matters.
a provision and the contractor then obeys the instruction, the
instruction is deemed to be empowered by the provision in the
contract specified in the Architect’s answer. If the contractor Interim Certifcates and payments
is not satisfied with the Architect’s answer, the matter may be 5.06 The Architect is under a duty to issue interim certificates
referred to adjudication or arbitration. at monthly intervals following the date specified in the Contract
Particulars, stating the amount due to the contractor and the basis
Form of instructions on which that sum has been calculated. If he or she certifies an
excessive amount, he or she may be liable to the employer in
4.16 By clause 1.7.1 all instructions are to be in writing, but note damages (see Sutcliffe v Thackrah [1974] AC 727). By clause
the elaborate provisions in clauses 3.12.1–3.12.3 for confirmation in
200 The JCT Standard Building Contract

Interim payments – due dates

4.8 During the period up to the due date for the fnal payment fxed under clause 4.26.3, the monthly due
dates for interim payments by the Employer shall in each case be the date 7 days after the relevant
Interim Valuation Date.

Interim Certifcates and valuations


4.9 .1 The Architect/Contract Administrator shall not later than 5 days after each due date issue an Interim
Certifcate, stating:

.1 the sum he considers to be or have been due to the Contractor at the due date, calculated in
accordance with clauses 4.14 and 4.15; and
.2 the basis on which that sum has been calculated.

.2 Interim valuations shall be made by the Quantity Surveyor whenever the Architect/Contract
Administrator considers them necessary for ascertaining the sum due in an Interim Certifcate.

Contractor’s Payment Applications and Payment Notices


4.10 .1 In relation to any interim payment the Contractor may not later than its Interim Valuation Date or, in
the case of the fnal payment, may at any time prior to issue of the Final Certifcate make an applica-
tion to the Quantity Surveyor (a ‘Payment Application’), stating the sum that the Contractor considers
to be due to him at the relevant due date as fxed in accordance with clause 4.8 or 4.26.3, and the
basis on which that sum has been calculated.

.2 If a Payment Certifcate is not issued in accordance with clause 4.9.1 or 4.26.1, then:

.1 where the Contractor has made a Payment Application in accordance with clause 4.10.1, that
application is for the purposes of these Conditions a Payment Notice; or
.2 where the Contractor has not made a Payment Application, he may at any time after the last
date for issue of the Payment Certifcate give a Payment Notice to the Quantity Surveyor, stating
the sum that the Contractor considers to have become due to him under clauses 4.14 and 4.15
or clause 4.26.2 at the relevant due date and the basis on which that sum has been calculated.

Interim and fnal payments – fnal date and amount


4.11 .1 Subject to clause 4.11.4, the fnal date for payment of each interim payment and the fnal payment
shall be 14 days from its due date.

.2 Subject to any Pay Less Notice given by the paying Party under clause 4.11.5, the paying Party shall
pay the sum stated as due in the Payment Certifcate on or before the fnal date for payment.

.3 If a Payment Certifcate is not issued in accordance with clause 4.9.1 or 4.26.1, but a Payment
Notice has been or is then given, the Employer shall, subject to any Pay Less Notice under clause
4.11.5, pay the Contractor the sum stated as due in the Payment Notice.

.4 Where a Payment Notice is given under clause 4.10.2.2, the fnal date for payment of the sum
specifed in it shall for all purposes be regarded as postponed by the same number of days as the
number of days after the last date for issue of the Payment Certifcate that the Payment Notice is
given.

.5 Where:

.1 the Employer intends to pay less than the sum stated as due from him in a Payment Certifcate
or Payment Notice; or
.2 if the Final Certifcate shows a balance due to the Employer, the Contractor intends to pay less
than the sum stated as due,

the Party by whom he payment is stated to be payable shall not later than 5 days before the fnal
date for payment give the other Party notice of that intention in accordance with clause 4.12.1 (‘Pay
Less Notice’). Where a Pay Less Notice is given, the payment to be made on or before the fnal date
for payment shall not be less than the amount stated as due.

.6 If either Party fails to pay a sum, or any part of it, due to the other Party under these Conditions by
its fnal date for payment, he shall, in addition to any unpaid amount that should properly have been
Section 4: payment 201

paid, pay the other Party simple interest on that amount at the Interest Rate for the period from the
fnal date for payment until payment is made.

.7 Any such unpaid amount and any interest under clause 4.11.6 shall be recoverable as a debt.
Acceptance of a payment of interest shall not in any circumstances be construed as a waiver either
of the recipient’s right to proper payment of the principal amount due or of the Contractor’s rights to
suspend performance under clause 4.13 or terminate his employment under section 8.

Pay Less Notices and general provisions


4.12 .1 A Pay Less Notice given by either Party shall specify the sum he considers to be due to the other
Party at the date the notice is given and the basis on which that sum has been calculated. Such
notice:

.1 (where it is to be given by the Employer) may be given on his behalf by the Architect/Contract
Administrator, Quantity Surveyor or Employer’s representative or by any other person who the
Employer notifes to the Contractor as being authorized to do so but, in the case of a payment
for which a Payment Certifcate is not issued in due time, may not be given until the Contractor
has in respect of the payment given a Payment Notice;
.2 (where it is to be given by the Contractor) shall be sent to the Employer, with a copy to the
Architect/Contract Administrator.

.2 In relation to the requirements for the issue of Payment Certifcates and the giving of Pay Less
notices, it is immaterial that the amount then considered to be due may be zero.

.3 The Employer’s fduciary interest in the Retention referred to in clause 4.17 shall not prevent him
exercising any right under this Contract to withhold or deduct from a sum due to the Contractor, sub-
ject to clause 4.11.5, even if that sum includes any Retention due for release under clause 4.19.

Contractor’s right of suspension


4.13 .1 If the Employer fails to pay a sum payable to the Contractor in accordance with clause 4.11 (together
with any VAT properly chargeable in respect of that payment) by the fnal date for payment and the
failure continues for 7 days after the Contractor has given notice to the Employer, with a copy to
the Architect/Contract Administrator, of his intention to suspend the performance of his obligations
under this Contract and the grounds for such suspension, the Contractor, without affecting his other
rights and remedies, may suspend performance of any or all of those obligations until payment is
made in full.

.2 Where the Contractor exercises his right of suspension under clause 4.13.1, he shall be entitled to
a reasonable amount in respect of costs and expenses reasonably incurred by him as a result of
exercising the right.

.3 Applications in respect of any such costs and expenses shall be made to the Architect/Contract
Administrator and the Contractor shall with his application or on request submit such details of
them as are reasonably necessary for ascertaining the amount in question.

Interim Payments – calculation of sums due


Gross Valuation
4.14 The Gross Valuation for each interim payment shall, subject to any agreement between the Parties
as to stage payments, be the total of the amounts referred to in clauses 4.14.1 and 4.14.2, less
the deductions referred to in clause 4.14.3, each calculated as at the Interim Valuation Date:
.1 The total values of the following which are subject to Retention:

.1 work properly executed by the Contractor (including work so executed for which a value has
been agreed pursuant to clause 5.2.1 or which has been valued under the Valuation Rules and
work for which there is a Confrmed Acceptance of a Variation Quotation), but excluding any
amounts referred to in clause 4.14.2.4;
.2 Site Materials, provided they are adequately protected against weather and other casualties and
are not on the Works prematurely; and
.3 Listed Items (if any) for which the conditions set out in clause 4.16 are satisfed;
those values shall be adjusted, where appropriate, in accordance with any applicable
Fluctuations Provision or any Acceleration Quotation for which there has been Confrmed
Acceptance and, where there is an Activity Schedule, the value of the work in each activity
202 The JCT Standard Building Contract

to which it relates shall be a proportion of the price stated for the work in that activity equal
to the proportion of the work in that activity that has then been properly executed;

.2 the total of the following which are not subject to Retention:

.1 any amounts to be included in accordance with clause 4.4 as a result of payments made or
costs incurred by the Contractor under clause 2.6.2, 2.21, 2.23, 3.17, 6.5, 6.10.2 or 6.10.3,
6.11.3, 6.12.2 or 6.20;
.2 any amounts payable under clause 4.13.2;
.3 the amount of any loss and/or expense to which the Contractor is entitled under clause 4.20.1
or 5.3.3 or by a Confrmed Acceptance;
.4 where Insurance Option B or C applies or to the extent that the work is under clause 6.13.5.3
to be treated as a Variation, any amounts in respect of reinstatement work under clause 6.13.4;
and
.5 any amount payable to the Contractor under any applicable Fluctuations Provision, other than by
means of an adjustment made under clause 4.14.1;

.3 the following deductions:

.1 any amounts deductible under clause 2.10, 2.38, 3.11, 3.18.2, 6.12.2 or 6.19.2; and
.2 any amount allowable by the Contractor under clause 6.10.2 or under any applicable
Fluctuations Provision, other than by means of an adjustment made under clause 4.14.1.

4.9.1, following practical completion, the interval between 5.10 The amendments to the HGCRA 1996 introduced by the
interim certificates increases to two months, until and including Local Democracy, Economic Development and Construction Act
the later of the expiry of the Rectification Period and the issue 2009 are reflected in clauses 4.10 and 4.11, which include a default
of the Certificate of Making Good. payment mechanism. If the contractor makes a payment applica-
tion on or before the Interim Valuation Date setting out the sum it
5.07 The issue of the certificate is a condition precedent to considers to be due to it as at the due date, and the Architect fails
the contractor’s right to payment: Henry Boot Ltd v Alstom to issue an interim certificate by the required time, then the effect
Combined Cycles Ltd [2005] 1 WLR 3850. In the event, how- of clause 4.10.2.1 is that the contractor’s application becomes a
ever, of non-issue of a certificate, a failure to issue an interim Payment Notice. The effect of such a notice is that, unless the
certificate on time or at all creates a dispute or difference, so employer then serves a Pay Less Notice no later than five days
enabling an adjudicator to review the position and decide that before the final date for payment (in accordance with clause
the contractor is entitled to receive an interim payment as if the 4.11.5), then the sum stated in the contractor’s application will be
certificate had been issued. In the 2016 form, interim payment payable whether or not that reflects the true valuation of the works.
regime remains the same up to the final payment, and the distinc-
tion previously made between interim payments before and after 5.11 An interim application for payment must be sufficiently
practical completion has been removed. clear in its intention so as to amount to reasonable notice to
the employer that the period for him to issue a Pay Less Notice
5.08 The 2016 form has introduced the concept of an Interim has been triggered (see Caledonian Modular Ltd v Mar City
Valuation Date, which is defined by clause 1.1 as the date speci- Developments [2015] EWHC 1855 (TCC)).
fied in the Contract Particulars. The works are valued as at the
Interim Valuation Date for the purposes of interim payments. If 5.12 If the contractor has not made a payment application by the
no date is specified, the first Interim Valuation Date will be one Interim Valuation Date, and the Architect does not issue a timely
month after the Date of Possession. The due dates for interim interim certificate, then clause 4.10.2.2 allows the contractor to
payments fall seven days after the Interim Valuation Date (clause issue a Payment Notice at any time after the expiry of the period
4.8). The Architect must then issue interim certificates not later for the Architect to issue an interim certificate. The employer
than five days after the due date. The interim certificate serves as will then have to pay the sum notified in the contractor’s Interim
the payment notice required by section 110A of HGCRA 1996. Payment Notice unless it gives a timely Pay Less Notice (clause
The interim certificate must state the sum the Architect considers 4.11.3). However, in this scenario, the final date for payment is
to be or to have been due at the due date (calculated in accord- postponed by the number of days after the expiry of the time for
ance with clauses 4.14 and 4.15) and the basis on which that issuing an interim certificate the contractor gives the Payment
sum has been calculated. Notice (clause 4.11.3). So, if the contractor’s Interim Payment
Notice is given three days after the deadline for the Architect
5.09 Clause 4.15 identifies the component parts of the interim issuing an interim certificate, then the final date for payment will
payment which are the gross valuation of the work carried out, be postponed by three days.
less: (1) the aggregate retention; (2) the cumulative total of an
advance payment due for the repayment; (3) the sums identified 5.13 Similarly, where an interim certificate is issued by the
as due in previous certificates; and (4) sums previously paid Architect in accordance with clause 4.9.1, then the employer
by the employer under the default payment mechanism (dis- must pay the amount stated in the certificate unless it gives a
cussed in further detail below), to the extent they have not been timely Pay Less Notice in accordance with clause 4.11.5.
reflected in an earlier certificate.
Section 4: payment 203

5.14 This default payment mechanism can have serious Final certifcate
consequences for the employer. If no interim certificate is
issued by the Architect and no Pay Less Notice is given by 5.15 The responsibility for issuing this certificate is a very sig-
the employer, then the employer will have to pay the amount nificant one, and the Architect should not issue it unless satisfied
demanded by the contractor, which may be an amount far that the contract has been fully complied with. The Architect
in excess of the proper valuation of the works at that stage. must re-consider the whole of the contractor’s performance
Whilst the position can be corrected in later interim certifi- under the contract and its right to payment, notwithstanding the
cates, the mechanism can cause serious cash flow difficul- inclusion or otherwise of sums in interim certificates. The final
ties for the employer, and if the contractor is or becomes certificate must be issued within two months of the latest of the
insolvent before any overpayment can be clawed back, the following events (clause 4.26.1):
employer may never be able to recover the overpayment. The
default payment mechanism can therefore have draconian 1. The end of the Rectification Period.
consequences, which makes it of the utmost importance that 2. The issue of the Certificate of Making Good under clause
the Architect issues interim certificates as required and does 2.39.
so on time (see S&T [UK] Limited v Grove Developments 3. The date upon which the Architect sent to the contractor a
Limited [2019] BLR 1). copy of any statement and ascertainment to which clause
The timetable for interim payments is illustrated in the dia- 4.25 refers (final adjustment of Contract Sum).
gram below.
In each case, where the contract provides for work sections, the
Contractor’s Payment reference is to the last such event.
Application (Optional)
Timing: On or before Interim 5.16 The form of the final certificate is governed by clause
Valuation Date 4.26.2. Note that the final certificate may show a balance in
favour of the employer if monies have been over-paid in earlier
certificates. This is a difference in wording to that governing
interim certificates, which only appears to contemplate a bal-
ance being due to the contractor. It is not necessary to hold back
payment from earlier certificates merely to keep something in
Interim valuation date reserve for the purposes of the final certificate, although it is
Timing: see Contract Particulars often considered prudent. RIBA Publications Ltd publishes a
form of Final Certificate.

5.17 Clauses 4.11.5 contain provisions for the giving of a Pay


Less Notice similar to those that apply to interim payments if the
party from whom payment is due intends to pay a sum less than
that notified, which are similar to those that apply in respect of
Due Date interim payments (see paragraphs 5.10–5.14 above). There is a
Timing: 7 days after Interim right to interest, at 5% above current Bank of England base rate,
Valuation Date in the event of late payment (clause 4.11.6).

Effect of fnal certifcate


5.18 The final certificate is not merely the last certificate; it is, if
properly issued in accordance with the contract, a document of
Architect’s Interim Certificate considerable legal importance. Subject to certain qualifications,
Timing: No later than 5 days after it is conclusive evidence of the following matters:
Due Date (12 days after Interim
Valuation Date 1. Where the quality of materials, or goods, or the stand-
ards of workmanship are expressly stated to be for the
approval of the Architect, they are to his reasonable
satisfaction, but not that the materials or goods or work-
manship comply with any other contractual requirement
(clause 1.9.1.1).
Contractor’s Payment Notice
2. All the terms of the contract which require an adjustment
(Optional – if no application)
Timing: Any time after deadline for
to be made of the contract sum have been complied with
interim certificate) (clause 1.9.1.2).
3. All and only such extensions of time as are due under clause
have been given (clause 1.9.1.3). Therefore, no further
extensions of time may be granted after the final certificate
has been issued. If the contractor wishes to take issue with
the extensions already granted, then it can only do so by
Employer’s Pay Less Notice commencing adjudication, arbitration, or court proceedings
Timing: No later than 5 days before (as the case may be) within the required time limit.
Final Date for Payment 4. The reimbursement of direct loss and/or expense, if any, to
the contractor, pursuant to clause 4.21, is in final settlement
of all claims arising out of the occurrence of the Relevant
Matters referred to in clause 4.22 (clause 1.9.1.4).

5.19 The exceptions to the conclusivity of the final certificate


Final Date for Payment are, in summary, the following:
Timing: 14 days after due date
(but postponed if contractor gives 1. Where proceedings of any sort have been commenced by
Payment Notice) either party before the issue of the final certificate, the final
204 The JCT Standard Building Contract

certificate becomes subject to the terms of any decision, 1 The contractor must provide reasonable proof to the
award, judgment, or settlement of such proceedings, or Architect that the property in the items has vested in it,
settlement of matters in issue in such proceedings (clause so that upon payment, property in them can pass to the
1.9.2). employer.
2. Where proceedings of any sort are commenced by either 2 The contractor must also provide reasonable proof that the
party within 28 days after its issue, the final certificate is items are insured against Specified Perils for the period
then conclusive save only in respect of the matters to which from the transfer of property to the contractor until their
the proceedings relate (clause 1.9.2.1). delivery to the works.
3. Fraud (clause 1.9.1). 3 If the items are off-site, they must be set apart or visibly
4. Accidental inclusion or exclusion of items or arithmetical and individually marked, identifying the employer and their
error (clause 1.9.1.2). destination as the works.
4 If the goods are ‘uniquely identified Listed Items’ (e.g.
5.20 Clause 1.9.2.2 provides that, where the parties receive an a boiler from a specified supplier), the contractor must
adjudicator’s decision after the issue of the Final Certificate, provide a bond in favour of the employer from a surety, if
if one of the parties wishes to seek a final determination over- required to do so in the Contract Particulars.
turning that decision in court or arbitration proceedings, that 5 If the goods are ‘Listed Items which are not uniquely identi-
party may commence such proceedings within 28 days of the fied’ (e.g. a quantity of bricks) the contractor must in any
adjudicator’s decision. It does not mention the evidential effect event provide a bond from a surety.
of the Final Certificate. It is probably intended to mean that the
Final Certificate (as confirmed or amended by the adjudicator’s
decision) does not have conclusive effect, provided that legal or
Retention
arbitration proceedings are commenced within 28 days after the 5.26 The purpose of retention is to provide the employer with
adjudicator’s decision. security for the contractor’s due performance of its obligations
in relation to the quality of the work. The percentage of retention
is now 3%, unless a different rate is included in the Contract
Gross Valuation and interim certifcates Particulars. The retention percentage may be deducted in respect
5.21 The amount to be included in interim certificates is defined of work or sections of work which have not reached practical
by clauses 4.14 and 4.15. Clauses 4.14.1 and 4.14.2 deal with completion (clause 4.19.1), and half that percentage may be
matters which are and are not subject to retention respectively. deducted in respect of work which has reached practical com-
The principal item in clause 4.14.1.1 is the total value of work pletion (clause 4.19.2). When the Certificate of Making Good is
properly executed by the contractor. This means that the amounts issued, it has the effect of releasing the retention in respect of
certified should take into account adjustments for variation, price the works, or that part of them to which that certificate relates.
fluctuations, and defects. RIBA Publications Ltd publishes forms
of interim certificate and direction and a statement of reten-
tion. Clause 4.14.1.1 includes provisions for where a Variation
Rules on treatment of retention
Quotation is accepted, and further that the prices to be used 5.27 The retention rules are contained in clauses 4.17 and 4.19.
in the valuation should be ascertained from a priced Activity They provide a precise regime for the treatment of retention
Schedule (if one is used). monies, but complications can arise when the employer does
not pay retention monies into a separate bank account, whether
5.22 Clause 4.14.1.2 requires the total value of unincorporated because the contractor does not request it or because its request
materials and goods to be included in interim certificates, is ignored. Complications can also be experienced where sub-
subject to certain conditions. By clause 2.24, where such contractors have interests in part of the retention monies.
materials and goods have been paid for, by inclusion of their
value in an interim certificate, property in them passes to the 5.28 Under clause 4.17.1, the employer holds the retention mon-
employer. ies as fiduciary on trust for the contractor. In Wales Construction
Ltd v Franthom Property Ltd (1991) 53 BLR 23, the Court of
5.23 Clause 4.14.2 deals with materials which are not subject Appeal held that (the equivalent of) clause 4.18.1 had the effect
to retention. Broadly, retention is to be deducted where the of requiring the employer to place the retention monies in a sep-
contractor had some responsibility for the matters in question, arate bank account if required to do so, and clause 4.17.3 makes
so that the employer’s interests have to be protected by making this an express requirement except where the employer is a local
the deduction. There will be no retention in instances where the authority. The intention is that the retention money should be
employer’s interests do not require such protection: thus, for set aside as a separate fund to be used only for the purpose of
example, ascertained additions to the Contract Sum are not sub- providing the employer with security against the making good
ject to retention (see clause 4.14.2.1), nor are amounts of direct of defects, and the purpose of making the employer a trustee is
loss and/or expense payable to the contractor and included in to protect the retention money against his liquidation. It is not
interim certificates (see clause 4.14.2.2). available for the employer to use as working capital.

5.24 Clause 4.14.3 provides for there to be deducted from the 5.29 If, however, no actual separate fund is set up, in the event
Gross Valuation sums which are deductible from the Contract of the employer’s liquidation, there will be no effective trust,
Sum by reason of contractor defects, omissions, or errors. and therefore the contractor will have to prove for its retention
monies along with the employer’s general creditors (MacJordan
Construction Ltd v Brookmount Erostin Ltd [1991] 53 BLR 1),
Valuation of off-site materials so it is important to ensure that the exercise of setting up a
separate fund is carried out. If the employer fails to do this, the
5.25 Clause 4.16 deals with certification in respect of prefab- court will grant a mandatory injunction enforcing the obligation
ricated goods and materials not on site. If goods and materials before liquidation, but the Court of Appeal considered that it
are not on site, the employer has less protection in the event of would be unlikely to do so after liquidation, as to do so might
the contractor’s insolvency, and in certain other circumstances, constitute a preference under the insolvency legislation. If the
than if they are on site. If the employer wishes to pay for goods case involved a solvent employer, but an insolvent contractor,
before their delivery to site, it must list those goods and annex and the employer had failed in its contractual obligation to set
the list to the Contract Bills (‘the Listed Items’). The contrac- the retention monies aside, the court would treat the fund as hav-
tor must then fulfil certain conditions if it desires to be paid for ing been set aside, so as to prevent the employer from relying
those goods in interim valuations: on his own breach of contract. However, the court will not grant
Section 4: payment 205

an injunction compelling the employer to set aside the retention 5.34 All that is required under clause 4.20 is that direct loss
money in a separate fund where the employer has a claim against and/or expense arises because ‘regular progress of the works’
the contractor for a greater amount which is deductible from the is ‘materially affected’ or because giving possession of the site
retention monies (see clause 4.13.2 and Henry Boot Building Ltd has been deferred under clause 2.5. There is no requirement
v The Croydon Hotel and Leisure Co Ltd [1985] 36 BLR 41). that progress be delayed, nor that the whole of the works be
affected. It could apply, for example, where the contractor is
5.30 Where clause 4.18 is applied by the Contract Particulars, it obliged to bring extra operatives on site, or where the contrac-
entitles the contractor to provide a Retention Bond from a surety tor is disrupted, resulting in a loss of productivity of a certain
approved by the employer in order to procure the release to it trade.
of monies that would otherwise be retained by the employer.
5.35 It should be noted that any possible overlap between the
operation of clause 4.20 and clauses 5.1 to 5.10 (Variations) is
Clauses 4.20–4.23: loss and expense precluded by clause 5.10.2.
caused by matters materially affecting
regular progress of the works Notice
Nature of clauses 4.20–4.23 5.36 Clause 4.21 requires the contractor to give notice in writ-
5.31 Clause 4.20 entitles the contractor to claim direct loss ing to the Architect stating that it has incurred, or is likely to
and/or expense arising as a result of the regular progress of incur such loss and expense. Once a notice has been given, the
the works (or part of them) being materially affected by any of loss and expense must be ascertained from time to time by the
the list of matters contained in clause 4.22 or by deferment of Architect or quantity surveyor. Under clause 4.21.1, the notifica-
possession under clause 2.5. This is a carefully restricted list of tion must be given as soon as the likely effect of the Relevant
circumstances under which the contractor may obtain payment. Matter on progress, or in the case of a deferment of possession,
However, there is a broad ‘catch-all’ clause (clause 4.22.5) to the likely nature and extent of any loss and/or expense arising
the effect that any impediment, prevention or default by the becomes (or should have become) reasonably apparent to the
employer (or those for whom it is responsible) will entitle the contractor. By clause 4.21.1, the contractor must also provide
contractor to claim under the clause, except to the extent that its initial assessment of the loss and/or expense incurred and
the contractor (or those for whom it is responsible) have con- any further amounts likely to be incurred, together with such
tributed to the default. By clause 4.24, the provisions of clauses information reasonably necessary to allow the Architect or
4.20–4.23 are without prejudice to any other rights and remedies Quantity Surveyor to ascertain the loss and/or expense. The
which the contractor may possess, and therefore the provisions initial assessment and supporting information must be provided
of clause 4.20 do not preclude any claim by the contractor for with the notification or as soon as reasonably practicable there-
damages for breach of contract, negligence, misrepresentation, after. Clause 4.21.3 then imposes on the contractor an ongoing
etc. Thus, the contractor may pursue a claim for damages, even obligation to update its assessment and information at monthly
if a claim under clause 4.20 fails (Fairclough v Vale of Belvoir intervals until all information reasonably required to allow the
Superstore [1991] 56 BLR 74), or may even make a claim under total amount to be ascertained has been provided.
clause 4.20 in order to obtain prompt reimbursement, and later
claim damages for breach of contract, taking into account the 5.37 Once an application for loss and/or expense has been made,
amount awarded under clause 4.20 (London Borough of Merton the Architect or Quantity Surveyor then has an important duty to
v Leach [1985] 32 BLR 51 at 108). fulfil. Clause 4.21.4 requires that they notify the contractor of the
ascertainment of loss and/or expense within 28 days of receipt
5.32 The word ‘direct’ means damages which flow naturally of the initial assessment and information and within 14 days of
from the breach without other intervening cause and indepen- each subsequent update.
dently of special circumstances (Saint Line Ltd v Richardson
[1940] p4060 2 KB 99), and excludes claims for consequential 5.38 Unlike the notice provision concerning a claim for an
loss (Cawoods v Croudace [1978] 2 Lloyd’s Reports 55). It extension, which contains materially different wording, it
therefore includes damages arising in the ordinary course of is widely thought that the requirement of a notice and the
things, as in the first limb of Hadley v Baxendale (1859) 9 Ex. provision of adequate supporting information is a condition
3421. In general, the computation of the amount of direct loss precedent to the contractor’s entitlement to recover loss and/
and/or expense should follow the lines for computation for or expense under this clause (see Walter Lilly & Co Limited
ordinary damages for breach of contract, although a claim under v Mackay [2012] BLR 503). Although the wording of clause
clause 4.20 is not a claim for breach of contract as such: see 4.20 has changed since Walter Lilly was decided, it is likely
Wraight Ltd v PH & T (Holdings) Ltd (1980) 13 BLR 26. In F. that, at the very least, the provision of a timely notification
G. Minter v Welsh HTSO (1980) 13 BLR 1, the Court of Appeal and information reasonably necessary to allow the Architect or
held that under an earlier version of the clause, the contractor Quantity Surveyor to ascertain the loss and/or expense incurred
could claim, as part of his direct loss and/or expense, the amount is a condition precedent to the contractor having any right to
of finance charges he incurred in financing the principal sum recover loss and/or expense. That is because, even under the
claimed as direct loss and/or expense. current wording, the right to loss and/or expense under clause
4.20.1 is expressed to be ‘subject to … compliance with the
5.33 The word ‘ascertain’ means ‘to find out for certain’, rather provisions of clause 4.21’.
than ‘to make a general assessment’ (McAlpine v Property and
Land Contractors Ltd [1995] 76 BLR 59), but there is room Claims generally
for the exercise of judgment in the ascertainment of loss and
expense (How Engineering Services Ltd v Lindner Ceilings Ltd 5.39 The term ‘claim’ has no exact meaning, but for present
[1999] 64 Con LR 67). Ascertaining the loss and/or expense to purposes it may be considered to be any request for payment by
which the contractor is entitled is therefore an important duty of the contractor other than in respect of the original contract price.
the Architect. It is not necessary to attempt too fine a distinction Any such claims fall under one of the following categories:
between what amounts are to be regarded as ‘loss’ and ‘expense’
respectively (McAlpine v Property and Land Contractors Ltd 1 A right to payment arising under a clause of the contract.
[1995] 76 BLR 59), and there is widely thought to be a brought 2 A claim for damages for breach of contract.
overlap between the two terms. 3 Any other claim arising under neither 1. nor 2.
206 The JCT Standard Building Contract

Loss and Expense

Matters materially affecting regular progress

4.20 .1 If in the execution of this Contract the Contractor incurs or is likely to incur direct loss and/or
expense as a result of any deferment of giving possession of the site or part of it under clause 2.5
or because regular of the Works or any part of them has been or is likely to be materially affected by
any Relevant Matter, he shall, subject to clause 4.20.2 and compliance with the provisions of clause
4.21 be entitled to reimbursement of that loss and/or expense.

.2 No such entitlement arises where these Conditions provide that there shall be no addition to the
Contract Sum or otherwise exclude the operation of this clause 4.20 or to the extent that the
Contractor is reimbursed for such loss and/or expense under another provision of these Conditions.
4.21 .1 The Contractor shall notify the Architect/Contract Administrator as soon as the likely effect of a
Relevant Matter on regular progress or the likely nature and extent of any loss and/or expense aris-
ing from a deferment of possession becomes (or should have become) reasonably apparent to him.

.2 That notifcation shall be accompanied by or, as soon as reasonably practicable, followed by


the Contractor’s initial assessment of the loss and/or expense incurred and any amounts
likely to be incurred, together with such information as is reasonably necessary to enable
the Architect/Contract Administrator or Quantity Surveyor to ascertain the loss and/or
expense incurred.

.3 The Contractor shall thereafter, in such form and manner as the Architect/Contract
Administrator may reasonably require, update that assessment and information at monthly
intervals until all information reasonably necessary to allow ascertainment of the total
amount of such loss and expense has been supplied.

.4 Within 28 days of receipt of the initial assessment and information and 14 days of each subsequent
update of them the Architect/Contract Administrator or Quantity Surveyor shall notify the Contractor
of the ascertained amount of the loss and/or expense incurred, each ascertainment being made
by reference to the information supplied by the Contractor and in suffcient detail to enable the
Contractor to identify differences between it and the Contractor’s assessment.

Relevant Matters
4.22 The following are the Relevant Matters:
.1 Variations (excluding those where loss and/or expense has been agreed by Confrmed Acceptance
of a Variation Quotation but including any other matters or instructions which under these Conditions
are to be treated as a Variation);

.2 Architect/Contract Administrator's instructions:

.1 under clause 3.15 or 3.16 (excluding an instruction for expenditure of a Provisional Sum for
defned work);
.2 for the opening up for inspection or testing of any work, materials or goods under clause 3.17
(including making good), unless the cost is provided for in the Contract Bills or unless the
inspection or test shows that the work, materials or goods are not in accordance with this
Contract;
.3 in relation to any discrepancy or divergence referred to in clause 2.15;
.4 in respect of any notifcation of reasonable objections under Supplemental Provision 9, para-
graph 9.4;
.5 given under Supplemental Provision 9, paragraph 9.6 where a Names Specialist is insolvent;

.3 compliance with clause 3.22.1 or with Architect/Contract Administrator’s instructions under clause
3.22.2;

.4 the execution of work for which an Approximate Quantity is not a reasonably accurate forecast of the
quantity of work required;

.5 any impediment, prevention or default, whether by act or omission, by the Employer, the Architect/
Contract Administrator, the Quantity Surveyor or any Employer’s Person, except to the extent caused
or contributed to by any default, whether by act or omission, of the Contractor or any Contractor’s
Person.
Section 5: variations 207

Amounts ascertained – addition to Contract Sum


4.23 Any amounts from time to time ascertained under clause 4.23 shall be added to the Contract Sum.

Reservation of Contractor’s rights and remedies


4.24 The provisions of clauses 4.20 to 4.23 shall not limit or affect any other rights and remedies of the
Contractor.

5.40 If a claim comes within 1., the Architect must follow what- Thus, the Architect cannot, without the contractor’s agreement,
ever procedure the contract prescribes, according to the clause require work that is the subject matter of a prime cost sum to
relied on by the contractor. The Architect need not consult the be carried out by the contractor, and cannot omit work from
employer, although he or she may do so if desirable. If the the contractor’s scope in order to have it carried out by another
claim falls within 2., the Architect has no formal role under the contractor. Instructions to omit work may only be issued if they
contract in relation to it. He or she should consult the employer are no longer to be carried out at all (Commissioner for Main
and should not include in a certificate any sum in respect of such Roads v Reed & Stuart Pty [1980] 12 BLR 55; Amec Building
a claim without the employer’s agreement, as the contract gives Ltd v Cadmus Investments Co Ltd [1996] 51 Con LR 105 at
the Architect no power to certify in respect of a contractual claim 125–128). Nor can the Architect instruct variations after practi-
for damages. Other, non-contractual, claims may be made, such cal completion.
as a claim for damages in tort, a restitutionary claim, or a claim
to an ex gratia payment. In relation to these, the Architect should
only act as directed by the employer. Prime costs, provisional sums,
and approximate quantities
6 Section 5: variations 6.04 Prime cost sums are pre-estimates of expenditure which
it is known will be incurred when the contract is entered into.
6.01 Clauses 5.1–5.10 are concerned with: Where work can be described, but the quantity of work required
cannot be accurately determined, an estimate of the quantity
1. Defining what constitutes a variation (clauses 5.1–5.5); and is to be given. This is identified as an approximate quantity.
2. Laying down the rules for valuing variations (clauses A provisional sum represents a sum which is included to meet
5.6–5.10). unforeseen contingencies (which may not arise). More detailed
definitions of these terms are set out in SMM. An instruction to
They should be read in conjunction with clauses 3.14 and 3.16, expend a provisional sum is valued in the same way as a vari-
which respectively give the Architect power to issue instruc- ation (clause 5.2.1.3).
tions requiring a variation (subject to the contractor’s right of
reasonable objection set out in clause 3.10.1), and require the
Architect to issue instructions in regard to the expenditure of Valuation rules
provisional sums. 6.05 Clause 5.2 sets out the method for valuing all:

Defnition of variation 1 Variations, whether instructed or sanctioned by the Architect


or treated as such by the Conditions;
6.02 Clause 5.1 defines the word ‘variation’ in wide terms. Not 2 Work executed in accordance with an instruction as to the
only does it include alterations in the design, quality, or quan- expenditure of provisional sums;
tity of the work itself (clause 5.1.1), but also, by clause 5.1.2, 3 Work for which an approximate quantity has been included
the imposition by the employer of, or alterations or omissions in the contract bills.
of, obligations or restrictions in relation to such matters as site
access, working space, working hours, and work sequence.
Disputes frequently arise between employer and contractor as 6.06 There are, in effect, four methods by which variations may
to whether work constitutes a variation, and such disputes were be valued:
frequently referred to arbitration. The Architect’s decision as
to what constitutes and does not constitute a variation will be 1 The value may be agreed at any stage by the employer and
subject to the adjudication process. contractor.
2 Absent such agreement, the value is to be determined by
the quantity surveyor in accordance with the rules contained
Limits on the Architect’s powers in clauses 5.6–5.10.
6.03 Despite the apparent breadth of the Architect’s powers 3 As an alternative, employer and contractor may agree a
to order variations, it is generally thought that he or she can- different method of valuation.
not order variations of such extent or nature as to alter the 4 In any event, a different method applies to variation instruc-
nature of the works as originally contemplated. Nor is the tions in respect of which a Variation Quotation has been
Architect entitled to include work wholly outside the scope of formally accepted by the Architect (see clause 5.2.2): see
the original contract within a variation instruction (Blue Circle paragraphs 6.19 to 6.25 below.
Industries PLC v Holland Dredging Co (UK) Ltd [1987] 37 BLR
40). The Architect’s powers are limited to those given by the 6.07 The rules set out in clauses 5.6–5.10 cover seven different
Conditions, which he or she has no power to vary or waive. situations:
208 The JCT Standard Building Contract

1 The execution of additional or substituted work which can adjustment (clause 5.6.3). Preliminary items defined by SMM
properly be valued by measurement (clauses 5.6.1.1–5.6.1.3). consist broadly of overhead items which the contractor will
2 The execution of work for which an approximate quantity incur, such as plant, site establishment, etc.
is included in the Contract Bills, provided that the work has
not been altered or modified other than in quantity (clauses 6.11 Rule 3: where work is omitted from the Contract Bills, the
5.6.1.4 and 5.6.1.5). valuation of the omission is to be determined by the rates and
3 The omission of work set out in the Contract Bills (clause prices for such work in the Contract Bills, except where it is
5.6.2). CDP work, in which case clause 5.8 is applicable (clause 5.6.2).
4 The execution of additional or substituted work which can-
not properly be valued by measurement (clause 5.7). 6.12 Rule 4: where additional or substituted work is incapable
5 Valuations relating to the Contractor’s Designed Portion of valuation by measurement, clause 5.7 requires it to be valued
(clause 5.8). at day-work rates. Subject to any special agreement, the quantity
6 Variations effecting a substantial change in the conditions surveyor must carry out the valuation in accordance with the rules
under which other work is executed (clause 5.9). laid down in clause 5.7, but the Architect is not bound to follow
7 Finally, a residual provision for a fair valuation (clause the quantity surveyor’s valuation. The responsibility for valua-
5.10). tion rests ultimately with the Architect, who may, in a particular
case, take the view that the quantity surveyor has failed to apply
6.08 Rule 1 governs three different scenarios relating to the the rules laid down correctly in principle. The Architect may, for
similarity or dissimilarity of additional or substituted work to example, consider that varied work should have been valued at bill
work originally set out in the Contract Bills: rates, whereas the quantity surveyor has valued it at ‘fair’ rates.
At least in matters relating to certification, the Architect is not
bound to accept the quantity surveyor’s opinions or valuation (R B
1 The rates and prices set out in the Contract Bills determine Burden Ltd v Swansea Corporation compliance; [1957] 3 All ER
the valuation where the additional or substituted work: 243). Note that the quantity surveyor has no authority to vary the
(a) is of similar character to; and terms of the contract; his or her function is confined to measur-
(b) is executed under similar conditions as; and ing and quantifying (John Laing Construction Ltd v County and
(c) does not significantly change the quantity of the work District Properties [1982] 23 BLR 1).
set out in the Contract Bills.
2 The rates and prices set out in the Contract Bills form the 6.13 Rule 5 concerns the valuation of CDP work (clause 5.8),
basis for determining the valuation, with a fair allowance which imports the provisions of a number of the other valuation
for difference in conditions or quantity, where (a) above clauses into such a valuation.
remains true, but either (b) or (c) do not.
3 The work is to be valued at fair rates and prices where it 6.14 Rule 6 deals with what might be termed indirect varia-
is of dissimilar character to work set out in the Contract tions, where a variation which directly affects one aspect of the
Bills. This rule of valuation (clause 5.6.1.3) is, in practice, work also has indirect effect upon another aspect. For example,
probably the most difficult to apply. It is necessary to decide the Architect may require work to be carried out in a different
first whether it applies and then, if it does, how to apply sequence from that envisaged, resulting in certain finishing
it. It seems that one must look at the position at the time trades being obliged to work in parts of the building which are
of acceptance of the tender and consider the character of not fully watertight. In such circumstances, the contractor would
the work then priced and the conditions under which the be entitled to be paid as if the indirectly-affected work were
parties must have contemplated that it would be carried itself the subject of a variation (clause 5.9).
out. If the character of the various works or the conditions
under which they were to be carried out differ, then this rule 6.15 Rule 7 provides a ‘fall back’ method of valuing a variation
applies. The following, it is thought, may be examples of its to produce a fair result where none of the other methods can be
application: material changes in quantities; winter instead of applied, by simply providing for a fair valuation (clause 5.10).
summer working; wet instead of dry; high instead of low;
confined working space instead of ample working space. 6.16 Clause 5.10.2 excludes additional payment under the
If it does apply, it is necessary to look at its effect, which Valuation Rules for items which the contractor would be able to
must vary according to circumstances. In some cases, a ‘fair claim as loss and/or expense under any other provision of the con-
valuation’ may result in no or very little change from bill tract. The policy of the JCT form is, save in the case of Variation
rates. Indeed, the wording of this sub clause is so wide that Quotations, to have separate and distinct regimes governing
the payment of less than bill rates might be justified. Note, variations on the one hand, and loss and/or expense on the other.
however, that a claim under clause 5.6.1.3 must be sharply
differentiated from a claim for loss and expense.

6.09 Rule 2: in the case of Approximate Quantities, there are Errors in the bills
two alternatives: 6.17 The contractor may have made errors in pricing its tender
on the basis of the bills of quantities, either by totalling figures
1 The rate or price for the Approximate Quantity determines incorrectly or by inserting a rate for a particular item which is
the valuation where the Approximate Quantity is a reason- manifestly excessive or too low. The parties are precluded from
ably accurate forecast of the quantity of work required disputing the total contract sum by the wording of clause 4.2.
(clause 5.6.1.4). Where a particular item is priced manifestly too low, contractors
2 Where that is not so, the rate or price for the Approximate sometimes argue that, if work the subject of the uneconomic
Quantity forms the basis for determining the valuation, rate becomes the subject of variation, it should be valued at an
with a fair allowance for the difference in quantity (clause economic rate and not at the bill rate. In the absence of any claim
5.6.1.5). for rectification being sustainable, it is thought that the bill rate
should prevail, and it is probable that the Architect would be in
6.10 Measurement of variations under Rules 1 and 2 above breach of duty to the employer were he or she to agree to adopt
is to be carried out in accordance with SMM, with allowance the economic rate without the employer’s express agreement.
to be made for any percentage or lump sum adjustments in Thus, a variation will not save the contractor from its own error
the Contract Bills, and preliminary items are also subject to in underestimating its tender.
Section 6: injury, damage, and insurance 209

Clause 5.3: Variation instruction – 6.25 Paragraph 2 of Schedule 2 makes provision for an
contractor’s Variation Quotation Acceleration Quotation. This applies where the employer
wishes to investigate the possibility of achieving practical
6.18 Clause 5.3 provides an alternative to the traditional method completion before the Completion Date for the works or for
of valuing in accordance with the other valuation rules in any section. The Architect will then invite proposals from the
Section 5. It is for the Architect in the first instance to decide contractor in that regard, and the contractor may either provide
whether he or she wishes clause 5.3 to be applied. If so, this an Acceleration Quotation setting out the details required by
must be specified in the instruction. If the Architect does, the paragraph 2.1.1 or explain why it would be impracticable to
clause 5.3 method will apply, unless within seven days the accelerate the Completion Date. The provisions for submission,
contractor states in writing that it disagrees with the application acceptance, and non-acceptance are the same as those for a
of clause 5.3 to the instruction. If the contractor does that, then, Variation Quotation.
provided the Architect issues a further instruction for the vari-
ation to be carried out, it will be valued in accordance with the
rules in clauses 5.6–5.10. Deemed variation
6.26 This term is frequently used to denote an occurrence which
6.19 At the heart of the clause 5.3 method of valuation is what entitles (or is alleged to entitle) the contractor to extra payments
is called a ‘Variation Quotation’, which is a quotation to be even though the requirements of clause 5 have not been com-
provided by the contractor. Much of the detail of the operation plied with. There are two principal occurrences which often give
of this method of valuation, which was previously included in rise to a deemed variation:
the body of the conditions, is now found in Schedule 2. The
commentary at paragraphs 6.20 to 6.25 below is therefore based 1 The bills of quantities are inaccurate and fail to record
upon the provisions of Schedule 2. correctly the quantity of work actually required, in which
circumstance the contractor is entitled to extra payment
6.20 Architects should not seek to employ the Variation under clause 2.14.1, which provides for such errors to be
Quotation procedure in the following situations, to which it is corrected, and clause 2.14.3, which provides for such cor-
inappropriately suited because of its complexity and because of rection to be treated as a variation.
the amount of time required to operate it: 2 Misstatements or inaccuracies in the bills of quanti-
ties may constitute an actionable misrepresentation for
● A variation instruction which requires virtually immediate which the contractor is entitled to damages under the
compliance; Misrepresentation Act 1967.
● A variation which amounts to a minor amendment or correc-
tion to information in the contract documents.
7 Section 6: injury, damage,
6.21 If the valuation system is to work properly, the Architect’s and insurance
variation instruction must give the contractor sufficient infor-
mation upon the basis of which to provide a quotation. The
note in Schedule 2 suggests that the information should be in a Contractor’s liability under clauses
similar format to that provided at tender stage. If the contractor 6.1–6.6 in respect of personal injury
considers that the information provided is insufficient, then it and injury or damage to property
has the right within seven days to request further information:
paragraph 1.1. The contractor is allowed 21 days from receipt 7.01 Clause 6.1 requires the contractor to indemnify the
of the instruction or the further information in which to provide employer against liability, claims, losses, and expenses, etc.
the quotation: paragraph 3.1. arising from the death of or personal injury to any person
occasioned in the carrying out of the works. However, to the
extent that the death or injury is due to any act or neglect of the
6.22 The Variation Quotation must not merely provide a price
employer, any employer’s person, or any statutory undertaker,
for the variation. It must give the value of the entire adjustment
there will be an apportionment of liability between employer
to the contract sum, including the effect on any other work, any
and contractor.
adjustment to the time required for completion of the works, any
sum by way of ‘direct loss and expense’ under clause 4.23, and
7.02 Clause 6.2 deals with damage to property other than the
a fee for preparing the quotation: paragraph 1.2.
works themselves. It requires the contractor to indemnify the
employer against liability etc. arising from damage to property,
6.23 On receipt of the quotation, the employer must choose
real or personal, occasioned by the carrying out of the works.
whether or not to accept it. If it decides to accept it, the Architect
It differs from clause 6.1 in that the onus is implicitly on the
must do so on its behalf within seven days by giving the con-
employer to show that the injury or damage was due to neg-
tractor an instruction to that effect referred to as a ‘Confirmed
ligence, breach of statutory duty, omission, or default on the
Acceptance’ containing specified information: paragraph 4.
part of the contractor or any contractor’s person.
6.24 The alternative course is for the employer not to accept
7.03 In clause 6.2, ‘property real or personal’ excludes the
the quotation. This may happen for two different reasons. One
works, work executed, or site materials before the issue of the
is simply that the employer considers the contractor’s price to
Practical Completion Certificate or the determination of the
be excessive. In that case, the Architect must instruct that the
contractor’s employment if earlier (clause 6.3.4). In a case of
variation is to be carried out in any event and to be valued in
sectional completion (clause 6.3.4.1) or partial possession by
accordance with the normal valuation rules: paragraph 5.1.1. The
the employer (clause 6.3.4.2), the completed section or part falls
other reason is that, having seen the cost or delay implications,
within the definition ‘property real or personal’.
the employer decides that it does not want to have the varied
work carried out after all. In that case, the Architect should
7.04 If Option C applies (insurance of existing structures), then
instruct the contractor that the varied work is not to be carried
the indemnity also excludes loss or damage to any property
out: paragraph 5.1.2. Whatever the reason for the non-acceptance
caused by a Specified Peril, which is required to be insured under
of the quotation, the contractor is entitled to be paid a fair and
that clause. The decision in Ossory Road (Skelmersdale) Limited
reasonable fee for preparing it: paragraph 5.2.
v Balfour Beatty Building Limited [1993] CILL 882 confirmed
210 The JCT Standard Building Contract

that where the contractor negligently damaged an existing struc- Options A or B. Option A requires the contractor to take out the
ture, and such damage was caused by a Specified Peril (fire), the policy; Option B the employer. Option C relates to works to exist-
contractor would not be liable to the employer for loss or dam- ing buildings. It requires the employer to take out a joint names
age suffered by, or for third party claims against, the employer. insurance policy covering the existing structures and the new works.
This approach was affirmed by the Court of Appeal in Scottish If the employer is unable to obtain such a joint names policy (for
& Newcastle Plc v GD Construction (St Albans) Ltd [2003] example, because it is a tenant of the building) the form now pro-
BLR 131, which held that the effect of requiring the employer vides for alternative arrangements to be put in place. Subcontractors
to take out joint names insurance with the contractor was that are entitled to the benefit of the insurance (clause 6.9.1).
the parties allocated to the employer the risk of loss or dam-
age by a fire caused by the negligence of a sub-contractor. The
employer must look to his insurers for reimbursement: see also
Clauses 6.15–6.20: CDP insurance
Co-operative Retail Services Ltd v Taylor Young Partnership & and the Joint Fire Code
Others [2002] BLR 272. 7.13 Clause 6.15 requires the contractor, where there is a
Contractor’s Designed Portion of the contract, to take out and
7.05 Clause 6.9.1 provides protection for sub-contractors from maintain professional indemnity insurance in an amount and for
liability to the employer for loss or damage to the works or a a period (normally six years from practical completion) which
relevant section by one of the Specified Perils, in the form either the parties have agreed and stated in the Contract Particulars.
of their recognition as a co-insured in the Joint Names Policy The contractor must produce evidence of such insurance to the
required by that clause, or by the inclusion in such policy of a Architect when the employer reasonably requests it to do so
waiver by the insurer of any right of subrogation against sub- (clause 6.15.3). If such insurance ceases to be available at com-
contractors: see The Board of Trustees of the Tate Gallery v mercially reasonable rates, the contractor is under an obligation
Duffy Construction Ltd [2007] BLR 216. to notify the employer (clause 6.16).
7.06 In addition to its liability under clause 6.2, the contractor 7.14 The parties may decide that the Joint Fire Code (the ‘Joint
must, as an incident of its duty to complete, make good damage Code of Practice on the Protection from Fire of Construction
to the works. This would apply, for example, to damage caused Sites and Buildings Undergoing Renovation’) applies. If so,
by vandalism or theft occurring before practical completion (pro- clause 6.18 places a duty upon each of the contractor and
vided it was not caused by the employer’s negligence or default employer to comply with the same, and to ensure the compli-
and was not within the risks accepted by the employer where ance of those for whom they are responsible. In the event of
Options B or C are selected). The contractor’s plant, equipment, a breach of the Code, the relevant insurers may specify the
and unfixed goods and materials are at his risk. Goods and mate- remedial measures to be carried out, and the contractor is
rials, when certified, remain at his risk. obliged to carry them out, if necessary under an instruction
from the Architect by way of a variation. If the contractor fails
Clauses 6.4 to 6.6: insurance against to carry out the necessary works, the employer may pay others
personal injury or property damage to carry them out and may deduct the cost from the contract
sum (clause 6.19.2).
7.07 Clause 6.4.1 requires the contractor to take out and main-
tain insurance in respect of claims arising under clauses 6.1 and
6.2 (see above).
8 Section 7: assignment,
7.09 Clause 6.5.1 requires the contractor, if instructed to do performance bonds and
so by the Architect, to take out insurance in the names of the guarantees, Third Party Rights,
contractor and employer in respect of liability, loss, claims, etc.
for damage to property caused by collapse, subsidence, heave, and collateral warranties
vibration, weakening or removal of support or lowering of
ground water arising out of the actual execution of the works. 8.01 Clause 7.1 prevents either party from assigning the contract
This is subject to a number of exceptions, which include damage or any rights under it except:
caused by the contractor’s own negligence, design errors, injury
for which the employer should insure (under Option C if appli- (a) With the other’s written consent; or
cable), and inevitable damage which is a reasonably foreseeable (b) To allow the employer, on or after practical completion of
consequence of undertaking the work. If such insurance is taken the works or of a section, to grant a limited right to bring
out, the contractor should deposit the policy with the Architect proceedings in the employer’s name to enforce any of the
or, if directed to do so, the employer (clause 6.5.2). contract terms made for the employer’s benefit (clause 7.2).
The parties must have stated in the Contract Particulars that
7.10 The amount spent by the contractor in taking out or main- clause applies, so as to cater for employers who wish to
taining the clause 6.5.1 insurance is added to the contract sum transfer an interest in the subject matter of the contract on
(clause 6.5.3). achieving practical completion.

7.11 Clause 6.4.2 and clause 6.5.3 (read in conjunction with 8.02 At law, a party may assign the benefit of a contract on
clause 6.12) impose an obligation on the contractor, when giving notice of the assignment to the other party, but may not
required to do so by the employer, to provide proof to the assign the burden without the other party’s consent. This clause
Architect of the continuing existence of the insurance referred prohibits either party making any assignment without the written
to in those clauses. If the contractor fails to take out such insur- consent of the other, save as stated. The rationale behind this is
ance, the employer may do so and recover the cost of so doing to ensure that the original contracting parties are not brought into
from the contractor (clause 6.12.2). direct contractual relations with third parties with whom they
may not wish to contract. The House of Lords held in Linden
Garden Trust Ltd v Lenesta Sludge Disposals Ltd [1993] 3 All
Clauses 6.7 to 6.10: ER 417 that any purported assignment would be invalid under
Insurance of the works this clause, and therefore not effective to transfer any rights of
action under the contract. This is emphasised by the fact that
7.12 These clauses provide for all-risks insurance of the works. clause 1.6 expressly excludes the effect of the Contracts (Rights
There are three alternatives, one of which may be stated in the of Third Parties) Act 1999, save as is permitted by clauses 7A
Contract Particulars to apply. Two are to be used for new works: and 7B.
Section 8: termination 211

8.03 The remainder of Section 7 covers the grant of Third Party purpose of clause 8.4 is to confer on the employer additional
Rights, performance bonds and guarantees, and the giving of col- and alternative rights by which it may determine the contractor’s
lateral warranties, which are of importance as between employer employment, without having to prove that the contractor has
and contractor, but do not justify commentary in this chapter. repudiated the contract. However, having regard to clause 8.2.1
(which requires that notice should not be given unreasonably or
vexatiously), there is sometimes uncertainty as to whether the
9 Section 8: termination circumstances which exist justify determination of the contrac-
tor’s employment (see J M Hill & Sons Ltd v London Borough
9.01 Section 8 concerns the termination of the contractor’s of Camden (1982) 18 BLR 31, CA and John Jarvis Limited v
employment under the contract. The general clauses (clauses Rockdale Housing Association Ltd (1986) 36 BLR 48, CA, on
8.1–8.3) define the meaning of insolvency for the purpose of the corresponding provisions in clause 8.9).
the Conditions, cover the giving of notice of termination, and
set the termination provisions apart from any other contractual 9.07 Under clause 8.6, the employer is entitled to determine the
rights and remedies of either party, e.g. termination for repudia- contractor’s employment on discovery of corrupt practices by
tory conduct by the other party. Clause 8.3.2 provides for the the contractor, and in this case there is no requirement for an
reinstatement of the contractor’s employment if the parties so architect’s notice of default.
agree, irrespective of the grounds of termination.
Insolvency
9.02 The basis of the section is that the contractor’s employment
9.08 Earlier editions of the standard form provided for automatic
may be terminated by either party either because of a specified
termination of the contractor’s employment in the event of its
default by, or the insolvency of, the other, or because the whole
insolvency. This is no longer so. If the contractor makes any
or substantially the whole of the works are suspended for speci-
proposal, gives notice of any meeting, or becomes the subject
fied reasons beyond the control of either party for a continuous
of any proceedings or appointment relating to any of the mat-
period which is stated in the Contract Particulars. In addition, the
ters referred to within the definitions of insolvency contained
employer is entitled to terminate the contractor’s employment
in clause 8.1, it must immediately inform the employer in writ-
because of an offence of corruption committed by the contractor.
ing (clause 8.5.2). The employer then has a right under clause
8.5.1 to determine the employment of the contractor by notice.
Whether or not it chooses to do so, clause 8.5.3 sets out certain
Clauses 8.4 to 8.8: automatic consequences of the insolvency:
Termination by employer
9.03 These clauses make provision for the following possibilities: 1 The employer’s obligation to make any further payment or
release of retention ceases to apply and is replaced by the
1 Discretionary termination by the employer in event of cer- taking of an account (clauses 8.7.3 and 8.7.4).
tain defaults by the contractor, including insolvency. 2 The contractor’s obligation to carry out the works (and the
2 Automatic suspension of the works and accounting provi- design of the CDP) is suspended.
sions in the event of insolvency. 3 The employer is entitled to protect the site, the works, and
3 The consequences following termination by the employer of site materials.
the contractor’s employment. In any event, if the contractor is a company in liquidation,
the liquidator has a statutory right to disclaim the contract if
Termination on notice it is unprofitable, which is likely to be the case (section 178,
Insolvency Act 1986).
9.04 The employer is entitled to terminate the contractor’s
employment in the circumstances specified in clause 8.4, subject Rights of parties after
to the Architect having given notice specifying the default and
the default having continued for 14 days after receipt of that termination by the employer
notice. Notices must, by virtue of clause 8.2.3, be in writing 9.09 Clause 8.7 governs the rights of the parties after termination
and be given by actual, special, or recorded signed for delivery. by the employer. In summary, the position is that:
Normally there must be two notices, a notice of default by the
Architect and a notice of termination by the employer, although 1 The employer is entitled to have the work completed by
clause 8.4.1.3 (refusal or neglect to comply with a written notice/ others and to take possession of the site and to use all con-
instruction) requires a total of three notices. Where the right to tractor’s, plant, equipment, and materials on site (subject to
terminate under clause 8.3 arises, the employer has a period of obtaining necessary third party consents e.g. from those who
21 days to give notice of the decision to terminate. have hired equipment to the contractor) (clause 8.7.1).
2 The employer is entitled to request and to take an assign-
9.05 It was held in West Faulkner Associates v London Borough of ment of contracts for the supply of materials and of sub-
Newham (1995) 74 BLR 1, a case on the JCT 63 clause which is in contracts, although such assignments may not be effective
similar terms to clause 8.4.1.2, that ‘regularly and diligently’ meant where the con tractor is insolvent (clause 8.7.2.3).
that a contractor must perform its duties in such a way as to achieve 3 The contractor is obliged, on receiving written notice from
his contractual obligations. The clause applies both before and after the Architect (but not before), to remove all temporary
the Date for Completion has passed. It requires a contractor to plan buildings, plant, tools, equipment, goods, and materials
work, to lead and manage its workforce, to provide sufficient and belonging to it or those for whom it is responsible (clause
proper materials, and to employ competent tradesmen so that the 8.7.2.1).
works are fully carried out to an acceptable standard, and that all
time, sequence, and other provisions of the contractor are fulfilled. 9.10 Typically, the employer will engage a replacement con-
The Architect will be in breach of contract if he or she fails to serve tractor to complete the outstanding work. Under clause 8.7.3,
a notice under the clause if an ordinarily competent architect would the employer is not bound to make any further payments to
have done so in the same circumstances. the contractor whose employment has been terminated. Upon
completion of the works and making good defects, an account
9.06 At common law, a party is entitled to treat a contract as will be taken, normally by the Architect but otherwise by the
repudiated and therefore, at an end if the other party so con- employer (clause 8.7.4), which is in effect a final account as
ducts itself as to show no intention to carry on with the contract between employer and contractor. If the employer has, in fact,
(see Universal Cargo Carriers v Citati [1957] 2 QB 401). The got the work completed for less than it would have had to pay
212 The JCT Standard Building Contract

the contractor, the contractor is in principle entitled to be paid circumstances would have thought it unreasonable or vexatious
the difference, but if (as is far more likely in practice) the work to give the notice.
has cost more than the contractor would have charged, the
contractor is obliged to pay the difference to the employer. In
addition, the Architect must certify the amount of direct loss and/
Clause 8.10: insolvency of employer
or damage caused to the employer for which the contractor is 9.16 Clause 8.10.2 provides that the employer must inform the
liable, whether caused by the termination or otherwise, and this contractor immediately in writing if it makes any proposal, gives
will be taken into account (clause 8.7.4.1). notice of any meeting or becomes the subject of any proceed-
ings or appointment relating to any of the matters referred to
within the definitions of insolvency contained in clause 8.1. The
Clauses 8.9–8.10: termination contractor has the right to terminate its employment by notice in
by contractor the event of the employer’s insolvency (see clause 8.10.1), and
9.11 These clauses, which should be compared with clauses 8.4 its obligations to carry out and complete the works (and CDP
and 8.5, entitle the contractor to determine its own employment design) are in any event suspended.
in certain circumstances. Clause 8.9.1.1 provides for determina-
tion for non-payment of amounts properly due in relation to Clause 8.11: termination by either party
an interim payment (or the VAT thereon); clause 8.9.1.2 deals
with interference with or obstruction of the issue of certificates; 9.17 Either party may, before practical completion, terminate
clause 8.9.1.3 deals with failure to comply with clause 7.1 the contractor’s employment, where the works have been sus-
(prohibition against assigning without consent). Clause 8.9.2 pended for the relevant continuous period agreed and stated in
deals with suspension of the work for a period in excess of that the Contract Particulars, by reason of one of the events speci-
which the parties have agreed. The procedure is in two stages: fied in clause 8.11.1. These are events which are not the fault of
first, a notice of specified default or suspension event from the either party. If, in fact, loss or damage to the works occasioned
contractor, then, if the default or event continues for 14 days by a Specified Peril has been caused by the negligence of the
from receipt of the notice, a notice of termination may be given. contractor, or one of those for whom it is responsible, it is dis-
As with a termination by the employer, once the right to give entitled from giving such notice. This includes the negligence
a notice of termination arises, the contractor has a period of of sub-contractors. Again, care should be taken to ensure that
21 days within which to give that notice. the periods provided in the Contract Particulars are reasonably
sufficient.

Clause 8.9.1.1: non-


payment of certifcates Clause 8.12: rights of parties
9.12 If the employer intends to pay less than the sum specified after determination
in a payment certificate or payment notice, it must give the 9.18 Clause 8.12 governs the rights and obligations of the par-
requisite notice under clause 4.11.5, otherwise it must pay the ties after termination under clauses 8.9 to 8.11 (and two other
amount certified or notified. Thus, the employer is entitled to circumstances). In summary:
exercise any contractual right of deduction or set off to which it
is contractually entitled (see, for example, clause 2.32), provided 1 The contractor is to remove its temporary buildings, plant,
it gives a valid and timeous pay less notice. If the contractor etc. from the site with all reasonable dispatch and ensure
disagrees with the sum stated in the pay less notice, its remedy that its sub-contractors do the same (clause 8.12.2.1).
in such a case is to refer to adjudication; if it terminates the 2 If there is a Contractor’s Designed Portion, the contractor
contract, it risks a finding that it was not entitled to do so if the must provide the employer with copies of the relevant docu-
pay less notice was validly given. ments (see clause 8.12.2.2).
3 The contractual payment and retention provisions cease to
Clause 8.9.1.2: obstruction apply (see clause 8.12.1).
4 The contractor is to prepare (or to provide the documents
of certifcates necessary for the employer to prepare) a final account as
9.13 Interference with or obstruction of the issue of certificates between contractor and employer, including the amounts
by the employer includes preventing the Architect from perform- referred to in clause 8.12.3.
ing his or her duties, directing the Architect as to the amount to 5 The employer shall pay the amount properly due to the
be given in his or her certificate, or as to the decision which he contractor (assuming that it is likely that there will be such
or she should reach, in respect of matters which are within the a balance in such circumstances) within 28 days of the
sphere of the Architect’s duty to exercise independent profes- submission of the account (see clause 8.12.5).
sional judgement.

10 Section 9: settlement
Clause 8.9.2: continuous suspension
of disputes
9.14 This clause relates to suspension of the works for the
continuous period the length of which has been agreed and 10.1 Section 9 must be read in conjunction with Articles 7, 8, and
included in the Contract Particulars. Care must be taken to 9. The dispute resolution procedures of the JCT form now provide
ensure that the periods in the Contract Particulars are reason- four separate but overlapping methods of dispute resolution:
ably sufficient. The contractor must be careful not to give
notice of a specified suspension event when one of those for 1 Mediation (clause 9.1).
whose actions or omissions it is responsible has been negligent 2 Adjudication (Article 7 and clause 9.2).
or in default. 3 Arbitration (Article 8 and clauses 9.3–9.8).
4 Litigation (Article 9).
9.15 In John Jarvis Ltd v Rockdale Housing Association Ltd
(1986) 36 BLR 48, the Court of Appeal held that notice under To these must be added the good faith negotiations between
the predecessor of clause 8.9.2 was not given ‘unreasonably senior executives available under paragraph 6 of Schedule 8 if
or vexatiously’ unless a reasonable contractor in the same selected to apply in the Contract Particulars.
The Schedules 213

10.02 Mediation and the mandatory imposition of the Housing 10.08 Clause 9.5 sets out some of the powers of the arbitrator,
Grants, Construction and Regeneration Act 1996 into almost all which are:
construction contracts (and now including those not in writing),
which allows for adjudication so as to enable disputes arising 1 To rectify the contract so as to reflect the true agreement
during the course of the contract to be provisionally determined made by the parties.
in a quick process, pending final review by the courts or in 2 To direct measurements and valuations that he or she thinks
arbitration. It has been, and remains, extremely successful; desirable in order to determine the rights of the parties.
whilst there have been a significant number of decisions of the 3 To ascertain and award any sum that he or she thinks should
Technology and Construction Court concerning adjudication have been included in any certificate.
enforcement, the amount of satellite litigation concerning adju- 4 To open up, review, and revise any certificate, decision,
dication has recently receded, and they represent a very small opinion, requirement, or notice (subject to clause 1.10,
minority of the disputes referred to adjudication. The available which concerns the effect of the final certificate).
evidence also indicates that very few adjudicators’ decisions are 5 To determine all matters in dispute submitted to him or her.
reconsidered in substantive litigation or arbitration.
10.09 The award of the arbitrator is final and binding on the
10.03 The overruling of Northern Regional Health Authority v parties (clause 9.6) subject to applications for determination of
Derek Crouch Construction Co Ltd [1984] QB 644 by the House questions of law (clause 9.7.1) and rights of appeal on questions
of Lords in Beaufort Developments Ltd v Gilbert-Ash (Northern of law (clause 9.7.2) under sections 45(2)(a) and 69(2)(a) of the
Ireland) Ltd (1998) 88 BLR 1, has allowed parties to challenge Arbitration Act 1996.
decisions and interim certificates of the Architect in proceedings
other than arbitration. The parties now have a genuine tactical
choice as to whether to litigate or arbitrate.
Article 9: litigation
10.10 The parties have an unfettered choice under the contract
10.04 The full scope of the adjudication, arbitration, and litigation to dispense with arbitration altogether, and have disputes finally
processes are dealt with elsewhere in this book. The following determined by court proceedings. This is a tactical and com-
text is an overview of these complementary and developing areas. mercial decision to be made by the parties at a very early stage
in the contractual process. Litigation has certain advantages over
arbitration:
Article 7 and clause 9.2: adjudication
10.05 Article 7 gives the parties the substantive right to refer 1 Cases are heard by judges with considerable experience
‘any dispute or difference arising under this Contract’ to adju- of construction litigation, usually in the Technology and
dication. Clause 9.2 now provides that the procedural rules Construction Court.
governing a dispute referred to adjudication shall be those of 2 Judges have a full range of preliminary remedies available
the Scheme for Construction Contracts. Clause 9.2.1 allows to them, e.g. the power to grant injunctions.
the parties to select the identity of the adjudicator and/or the 3 Questions of law and fact may be appealed directly to the
nominating body. Clause 9.2.2 applies where the dispute referred Court of Appeal.
includes consideration of whether an instruction issued under 4 Apart from standard Court fees no further fees are payable.
clause 3.18.4 (instructions to open up for inspection or to test) 5 Co-defendants and third parties may be joined in the same
is reasonable in all the circumstances. In that situation, clause action. If some of the works are sub-contracted and there is
9.2.2 requires the adjudicator to have appropriate expertise and potential for a dispute to involve more than two parties, that
experience in the specialist area or discipline relevant to the may be a reason for choosing litigation over arbitration.
instruction in dispute, where practicable. If the adjudicator does
not have the appropriate experience or expertise, clause 9.2.2.2 10.11 Against this, arbitration offers flexibility in the way that
requires the appointment of an independent expert to advise, and the matters are to be decided and (unless there is an appeal to
report in writing to, the adjudicator. the court) privacy. However, architects should be slow to advise
their clients to litigate before exploring other avenues of dispute
resolution. In Paul Thomas Construction Ltd v Hyland [2002]
Article 8 and clauses 9.3–9.8: arbitration 18 Const LJ 345, the claimant started proceedings after refusing
10.06 The parties have to make a positive choice whether or not to participate in adjudication and generally not co-operating.
to include the arbitration provisions as part of their agreement, Indemnity costs were awarded against the claimant.
otherwise litigation will be their preferred method of final dis-
pute resolution. Note the broad scope of the dispute or difference
which may be referred to arbitration as opposed to adjudication: 11 The Schedules
any dispute or difference between the Parties of any kind what- 11.01 The Schedules to the 2016 form comprise the following:
soever arising out of or in connection with this Contract.
1 Contractor’s Design Submission Procedure. This fol-
Article 8 provides that this excludes adjudication enforcement lows clause 2.9.3 of the Conditions and provides for the
disputes and one other (minor) category of dispute. Not only is submission to the Architect of copies of the Contractor’s
the wording of Article 8 in itself very wide as to what disputes Designed Portion for the purpose of marking it as
may be referred to arbitration, a decision of the House of Lords either in accordance with or not in accordance with the
has held that agreements to arbitration will be interpreted very Contract.
widely, and the parties to an arbitration agreement will be taken 2 Variation and Acceleration Quotation Procedures: these
to have consented to all disputes arising out of their commercial follow clause 5.3 and have been considered in paragraphs
relationship to be referred to arbitration except to the extent they 6.19 to 6.25 above.
have expressly excluded particular types of dispute (Fiona Trust 3 Insurance Options: these have been considered in paragraph
v Privalov [2007] 4 All ER 951). 7.12 above.
4 Code of Practice: this sets out a procedure to assist in the
10.07 The arbitration is to be conducted in accordance with the fair and reasonable operation of clause 3.18.4, i.e. where
JCT 2016 edition of the CIMAR rules, although the parties can the Architect issues an instruction for the opening up for
agree to include any subsequent amendments. inspection or testing of work which is considered not to be
214 The JCT Standard Building Contract

in accordance with the contract. It sets out fifteen criteria 6 Forms of Bonds in respect of advance payment (clause 4.7),
for the Architect to consider in issuing instructions pursuant Listed Items (clause 4.16), and the Retention Bond (clause
to that clause. 4.18).
5 Third Party Rights. This follows clauses 7A and 7B of 7 Fluctuations Option A.
the Conditions. It confers certain rights as against the 8 Schedule 8 is designed, in conjunction with Recital 8, to
contractor on named or identified Purchasers, Tenants, and incorporate the Achieving Excellence in Construction prin-
Funders. ciples into the form.
18
The NEC4 Engineering and Construction
Contract and related Architects’ forms
THERESA MOHAMMED

1 Introduction Architects, Designers, Project Managers, Supervisors, and other


Consultants. The contract can be used on construction projects
1.01 The NEC suite of contracts are designed to stimulate good using the other NEC forms or for non-NEC projects.
project management and to deliver projects, particularly large It is divided into a Schedule of Options, Core Clauses,
and high value projects on time and on budget. The contracts Main Option Clauses, Resolving and Avoiding Disputes, and
are written in plain language and the procedures introduced by Secondary Option Clauses.
this form serve to compel the parties to actively communicate,
record, and manage risk. 2.02 The agreement commences with the Schedule of Options.
It should be noted that, under options W1 and W2, the parties
1.02 The NEC family of contracts current at the date of the previ- must select a dispute resolution option which may be either the
ous edition of this book were known as NEC3. Since then, the appointment of an adjudicator under the NEC form of adjudica-
NEC form has undergone further revision, in June 2017, and the tor’s appointment used when the Housing Grants, Construction
revised suite of documents are now known collectively as the and Regeneration Act 1996 (as amended) does not apply or the
‘NEC4’, which have all adopted gender neutral language. There adjudication procedure when the Housing Grants, Construction
have also been changes of nomenclature such as the Employer is and Regeneration Act 1996 (as amended) does apply. Under
now the Client and Works Information is now Scope. The forms both options, the reader should carefully note that under W1
have been updated and others added including a Professional (10) and W2 (11),
Services Subcontract, a Professional Services Short Contract,
a Professional Service Subcontract, a Term Service Contract, a the Adjudicator’s decision is binding on the Parties unless and
Design Build Operate Contract and, in 2018, an Alliance Contract. until revised by the tribunal and is enforceable as a matter of
contractual obligation between the parties and not as an arbi-
1.03 The NEC4 suite, like this form of contract generally, tral award. The Adjudicator’s decision is final and binding if
espouses the concept of modern project management, collabo- neither party has notified the other within the times required
ration, frequent communication, and the early identification of by this contract that it is dissatisfied with a decision of the
risk. These concepts will be familiar to Architects but do entail Adjudicator and intends to refer the matter to the tribunal.
greater resource and administration than other forms of construc-
tion contract. Given the serious impact of this provision, Architects would be
well advised to highlight it to their insurers and pay particular
1.04 The RIBA in 2018 released the Standard Professional attention to the specified time limit at W1.4 (2) and W2.4 (2)
Services Contract, the Concise Professional Services Contract, in the event that disputes arise and are referred to adjudication.
the Domestic Professional Services Contract, the Sub-consultant
Professional Services Contract, and the Principal Designer
Professional Services Contract. For details on professional
Option X2 – Changes in the law
services contracts for use by Architects, readers should refer to 2.03 This provision provides that a ‘change in the law of the
section 5 of Chapter 30. project’ is a ‘compensation event’ if it occurs after the Contract
Date.
1.05 The purpose of this chapter is to consider the provisions
of the NEC4 Professional Services Contract and make any rel-
evant comparisons to the RIBA Standard Professional Services Option X7 – Delay damages
Contracts. The NEC itself has produced commentary that com- 2.04 This provision confirms that the Consultant will pay
pares NEC3 and NEC4, clause by clause, published by ICE delay damages at the rate stated in the Contract Data from
Publishing in 2017. the Completion Date for each day until Completion. If the
Completion Date is adjusted, this provision also entitles the
Consultant to repayment of the damages with interest. The
2 NEC4 Professional commercial viability of a project can be dramatically altered by
Services Contract provisions that address delay damages. The value of the damages
must be considered carefully by any Architect who may have a
2.01 The NEC4 Professional Services Contract is intended liability to pay them in terms of the affect they will have on the
for use for a wide range of professional services including profitability of the work and whether they could be paid during

215
216 The NEC4 Engineering and Construction Contract

the currency of the works without starving the consultancy of ‘Other than the Parties or a beneficiary, no person can enforce
funds, doubtless causing further delay. any of the terms of the contract under the Contracts (Rights of
Third Parties) Act 1999’.
2.05 Further, given the impact on construction works of events
such as the coronavirus pandemic and the anticipated delays 2.14 The Contracts (Rights of Third Parties) Act 1999 extends
caused by adapting sites to facilitate social distancing and infec- rights to those third parties in general, provided that they can
tion control, it would be prudent to specifically address how establish that the contract was made ‘for their benefit’: see
risks like this will be shared by the parties. Chapter 21. The wording here is more restrictive, in that the
beneficiaries need to be identified in the Contract Data.
Option X8 – Undertaking to Others 2.15 The importance of this provision is that it extends rights to
2.06 Under X8.1, ‘the Consultant gives undertakings to Others particular beneficiaries that are stated in the Contract Data. In
as stated in the Contract Data’. An important point to note is that doing so, this extends the risk of claims that can be made and
the Consultant should not offer anything more than it is obligated should be approved by your insurer before agreement.
to provide under the contract and should be aware that in provid-
ing undertakings, it is expanding the class of potential claimants Option Z – Additional
entitled to make contractual claims against it. As such, any under-
taking should be provided in full to insurers before it is agreed. conditions of contract
2.16 This is self-explanatory and, briefly, will cover additional
Option X9 – Transfer of rights conditions (amendments) to the contract.

2.07 Option clause X9.1 provides, ‘The Client owns the


Consultant’s rights over material prepared for this contract by Core clauses
the Consultant except as stated otherwise in the Scope. The 2.17 These include the following:
Consultant obtains other rights for the Client as stated in the
Scope and obtains from a Subcontractor equivalent rights for Clause 10.1: ‘The Parties and the Service Manager shall act as
the Client over the material prepared by the Subcontractor. The stated in this contract.’
Consultant provides to the Client the documents which transfer Clause 10.2: ‘The Parties and the Service Manager act in a spirit
these rights to the Client’. of mutual trust and co-operation.’ An obligation of good faith
will not generally be implied under English law and, unless
2.08 The rights to all ownership of copyright material pro- there is a specific additional obligation linked to this provision,
duced by the Consultant pursuant to the contract vest in the it will be challenging to try and argue that it has been breached.
Client. It should also be noted that the Consultant is required However, it is considered that statements of intent such as this
to obtain equivalent rights for the Client that it obtains from its create a positive working relationship and encourage teamwork.
Subcontractor. This provision should potentially be amended to
make clear that the Consultant will not be held liable for any Clause 11.2(1): ‘The Accepted Programme is the programme
misuse, variation, or use of the material contrary to the purpose identified in the Contract Data or is the latest programme
for which it was intended under the contract. accepted by the Service Manager. The latest Programme
accepted by the Service Manager supersedes previous Accepted
Programmes.’ This highlights the importance of accurately
Option X11 – Termination by the Client completing the ‘Contract Data’, as clarity as to the relevant
2.09 Option clause X11.1 provides that the Client may terminate programme is crucial under any contract, but particularly this
the Consultant’s obligation to provide the Service for a reason form of contract.
not identified in the Termination Table by notifying the Service Clause 11.2(2): ‘Completion is when the Consultant has
Manager and the Consultant.
● done all the work which the Scope states he is to do by the
2.10 Clause X11.2 then provides a formula for such a termina- Completion Date and
tion, which is P1, and the amounts due are A1 and A3, as set ● corrected Defects which would have prevented the Client
out under clause 93 of the contract. from using the service or Others from doing their work’.
2.11 The financial consequences of any termination should be Clause 11.2(12): ‘To Provide the Service means to do the work
worked out and assessed before the contract can be agreed, necessary to complete the service in accordance with this con-
particularly for provisions that allow the client to terminate the tract and all incidental work, services and actions which the
Consultant’s obligations ‘at will’ without having to evidence contract requires.’ This provision should be referred to your
default. insurers before it is agreed, as it extends the obligations of the
Consultant to services that may not be specifically addressed
Option X18 – Limitation of liability by the contract and therefore increases the Consultant’s risk
and liability.
2.12 This clause outlines the limitations of the Consultant’s
liability to the Client in respect of indirect and consequential
loss and defects and should be carefully considered in conjunc- Interpretation of the law
tion with the Contract Data and approved by insurers before
2.18 Clause 12.2 states: ‘This contract is governed by the law
agreement. Further, it contains an express provision that con-
of the contract’. This wording reflects the fact that the NEC4
firms that the Consultant is not liable to the Client for a matter
is intended to be used within the United Kingdom and inter-
unless details are notified before the end of the liability date.
nationally. However, Architects may consider it prudent, if the
contract is in the United Kingdom, to amend this clause to read
Option Y (UK) 3 – The Contracts ‘This contract is governed by the laws of [England and Wales],
[Northern Ireland] or [Scotland]’, depending on which jurisdic-
(Rights of Third Parties) Act 1999 tion is relevant and so as to ensure that this reflects the appli-
2.13 This provides that ‘A beneficiary may enforce a term of the cable law of any other contracts entered into for this project.
contract stated in the Contract Data under the Contracts (Rights A surprising number of disputes are generated by inconsistent
of Third Parties) Act 1999’. However, it also provides that drafting of contracts on large international projects and having a
Compensation events 217

conflict of applicable law will introduce unnecessary confusion Instructions to stop or not to start work
and risk as to which law is determinative.
3.03 By clause 34.1, ‘The Service Manager may instruct the
2.19 Clause 12.4 then states: ‘This contract is the entire agree- Consultant to stop or not to start any work. The Service Manager
ment between the Parties’. This provision should be amended if subsequently gives an instruction to the Consultant to:
there are other agreements, documents, contracts or representa-
tions that you wish to rely on or need to be incorporated to ● re-start or start the work or
understand the full Scope of the Service. ● remove the work from the Scope.’

It should be noted that an instruction to stop or not start work


Acceptance is classified as a compensation event pursuant to clause 60, and
2.20 Clause 14.1 provides: ‘The Service Manager's acceptance that if the Service Manager changes this decision, this is also
of a communication from the Consultant or of the work does not classified as a compensation event for which additional costs and
change the Consultant’s responsibility to Provide the Service’. time could be claimed.
This clause suggests that any change to the provision of the
Service will not be effective if just communicated to the Service 4 Quality management
Manager. The precise obligations of each party and whether or
not they have been varied is a key area of dispute, so it is vital
to follow the proper contractual processes (clauses 16 and 60) Correcting defects
if you are requesting to change the Scope or consider that you 4.01 Clause 41.1 provides that ‘until the defects date, the Service
are being asked to. Manager and the Consultant notifies the other as soon as they
become aware of a Defect. At Completion the Consultant noti-
Early warning fies the Service Manager of the Defects which have not been
corrected. The Client’s rights in respect of a Defect which the
2.21 A key feature of this contract is the early warning process, Service Manager has not found or notified by the defects date
whereby the Consultant and the Service Manager give an early are not affected’.
warning as soon as either becomes aware of any matter which
could 4.02 Clause 41.2 entitles the Service Manager to assess the cost
to the Client of having the Defect corrected by other people, and
● Increase the total of the Prices; the Consultant pays this amount.
● Delay Completion;
● Delay meeting a Key Date;
● Impair the usefulness of the service to the Client; or 5 Payment
● Affect the work of the Client, a Client’s contractor, or
another consultant; and 5.01 By clause 50.1, ‘The Service Manager assesses the amount
● Any matter that could increase the Consultant’s total cost. due at each assessment date. The first assessment date is decided
by the Service Manager to suit the procedures of the Parties and
The warnings are recorded on the Early Warning Register it not later than the assessment interval after the starting date.
(save for matters already notified as compensation events), Later assessment dates occur at the end of each assessment
and meetings are held to try to address how the impacts of the interval until:
issues raised can be avoided or reduced and any advantageous
solutions. ● four weeks after the defects date
● the Service manager issues a termination certificate’.
3 The parties’ main responsibilities 5.02 The NEC4, at clause 50.3, identifies what is required as
part of the application for payment, and clause 51 confirms the
The Consultant’s main responsibilities time period for the certification of payment. Interest is payable if
a certified payment is late or payment is late because of a default
3.01 By clause 20.2, ‘The Consultant’s obligation is to use the
of the Service Manager and is assessed from the date by which
skill and care normally used by professionals providing services
the late payment should have been made until the date when the
similar to the services’. This kind of provision is commonplace,
late payment is made.
but is usually key for insurers, and it will be important to scru-
tinise any amendments made to it.
6 Compensation events
Time
6.01 Clause 60.1 provides 15 different ‘compensation events’
3.02 By clause 31.3, ‘Within two weeks of the Consultant that may be added to by inclusion in the Contract Data. Those
submitting a programme for acceptance the Service Manager which could particularly affect the Architect are:
notifies the Consultant of the acceptance of the programme or
the reasons for not accepting it. A reason for not accepting a (4) The Service Manager gives an instruction to stop or not
programme is that: to start any work or to change a key date.
(5) The Client or Others do not work within the time shown
● the Consultant’s plans which it shows are not practicable, on the Accepted Programme or within the conditions
● it does not show the information which this contract stated in the Scope.
require, (6) The Service Manager does not reply to a communication
● it does not represent the Consultant’s plans realistically or from the Consultant within the period required by the
● it does not comply with the Scope.’ contract.
(7) The Service Manager changes a decision which the
If the Service Manager does not respond within the stipulated Service Manager had previously communicated to the
timeframe, the Consultant may notify the Service Manager Consultant.
of that failure. If the failure continues for a further week, it (8) The Service Manager withholds an acceptance (other than
will be treated as acceptance by the Service Manager of the acceptance of a quotation for acceleration) for a reason
programme. not stated in the contract.
218 The NEC4 Engineering and Construction Contract

(9) An event which is a Client's liability stated in these ● Additional Client’s liabilities stated in the Contract
conditions of contract. Data’.
(10) The Service Manager notifies the Consultant of a cor-
rection of an assumption which the Service Manager
stated about a compensation event. Insurance cover
(11) A breach of contract by the Client which is not one of 8.02 The ‘Insurance Table’ provides for ‘Liability of the
the other compensation events of the contract. Consultant for all claims made against it arising out of the
(12) An event which Consultant's failure to use the skill and care normally used by
professionals providing services similar to the service’. The
• stops the Consultant completing the whole of the
amount is limited to the amount stated in the Contract Data and
service or
the wording of this provision and the amount stipulated should
• stops the Consultant completing the whole of the
be approved by your insurers before it can be agreed.
service by the date for planned Completion shown
on the Accepted Programme,
8.03 It should be noted that, for the purposes of clause 87.1, the
and which ‘cap’ on liability specifically excludes the following:

• neither Party could prevent, ● delay damages, if Option X7 applies;


• an experienced consultant would have judged at ● Consultant’s share, if option C applies;
the Contract Date to have such a small chance of ● an infringement by the Consultant of the rights of Others
occurring that it would have been unreasonable to (e.g. breach of copyright);
have allowed for it and ● loss or damage to third party property and death of or bodily
• is not one of the other compensation events stated injury to a person other than an employee of the Consultant.
in the contract.
(13) The Consultant corrects a Defect for which it is not
liable under the contract. 9 Termination
(14) The Service Manager gives an instruction correcting
information provided by the Client. 9.01 Clause 90 sets out the grounds of termination, and clause
(15) The Service Manager notifies the Consultant that a 90.2 provides that a party may terminate for a reason identified
quotation for a proposed instruction is not accepted. in the Termination Table.

6.02 Clause 61.3 stipulates that if the Consultant does not notify The Consultant may terminate if the Client has not paid an
a compensation event within eight weeks of becoming aware that amount due under the contract within thirteen weeks of the date
the event has happened, the Prices, the Completion Date, or a Key that the Consultant should have been paid.
Date are not changed. Therefore, it is crucial that this timeframe
is observed unless the event arises from the Service Manager giv- By virtue of clause 91.3, the Client may terminate if the Service
ing an instruction or notification or changing an earlier decision. Manager has notified that the Consultant has not stopped one of
the following defaults within four weeks of the date when the
6.03 Clause 64 provides the procedure for the assessment of Service Manager notified the Consultant of the default:
compensation events by the Service Manager.
● substantially hindered the Client or Others (R14);
● substantially broken a health or safety regulation (R15).
7 Rights of material
Under clause 90.4, the project may be stopped if an event occurs
which stops the Consultant completing the services or stops the
The parties’ use of material Consultant from doing so on the Accepted programme, this is
7.01 It is expressly stated by clause 70.1 that the ‘Client has forecast to delay completion by more than 13 weeks, and is an
the right to use the material provided by the Consultant for the event which neither party could prevent and which an ‘expe-
purpose stated in the Scope’. These rights can be expanded by rienced consultant’ would have judged at the contract date to
Option Clause X9 (see paragraph 2.07 above). have such a ‘small chance of occurring that it would have been
unreasonable for him to have allowed for it’.
7.02 Clause 70.2 makes clear that the ‘Consultant has the right
to use material provided by the Client only to Provide the
Service’. 10 Contract data
7.03 However, the Consultant is permitted to use the material 10.01 It is emphasised that the completion of the Contract data
for other work absent any provision to the contrary. Clause 70.3 should not be overlooked. The pre-amble to Part One (page
provides that ‘The Consultant may use the material provided by 54) states that ‘Completion of the data in full, according to the
him under this contract for other work unless stated otherwise Options chosen, is essential to create a complete contract’.
in the Scope’.
10.02 Clause 8, Indemnity, Insurance and Liability, will require
particularly careful consideration with your insurers before
8 Liabilities and insurance agreement. It will be important to confirm that the insurance
obtained corresponds precisely to what is required under the
8.01 By clause 80.1, ‘The following are the Client’s liabilities. contract and the Scope that has been agreed to.

● Claims and proceedings from Others and compensation and


costs payable to Others which are due to:
Part 2 – Data provided by the consultant
● the unavoidable result of the service or 10.03 The NEC4 does not set out a schedule of services
● Negligence, breach of statutory duty or interference with equivalent to the RIBA stages of services (Stages A to L).
any legal right by the Client or by any person employed As a consequence, care must be taken in identifying accu-
by or contracted to it except the Consultant. rately those services which the Architect intends to perform
● A fault of the Client or any person employed by or con- under the contract. It will often be considered prudent to
tracted to it, except the Consultant. retain the industry-accepted, traditional RIBA ‘work stages’ in
Comparison with RIBA Standard Professional Services Contract 2018 219

identifying those services or to identify them with a similar level Architect to keep records which are available to the Client on
of particularisation. request, and the costs incurred in relation to tenders.

11 Comparison with RIBA Copyright and Licence


Standard Professional 11.08 Intellectual property rights, including the copyright in the
drawings and documents produced in performing the Services,
Services Contract 2018 Copyright, and Licence set out at clause 6.1 remains with the
Architect and additionally asserts the Architect’s right to be
11.01 In 2018, the RIBA published the Standard Professional identified as the author of the work.
Services Contract, the Concise Professional Services Contract
2018, the Domestic Professional Services Contract, the Sub- 11.09 The Architect always retains ownership of the copyright
Consultant Professional Services Contract, and the Principal material but gives the Client, at clause 6.3,
Designer Professional Services Contract 2018. This was intended
to replace SFA/99 (Rev 2004), which has now been withdrawn. a licence to copy and use such of the drawings and documents
See Chapter 30 for further information in this regard. for which all fees and other amounts properly due have been
paid, only for purposes related to the construction of the
11.02 All the contracts contain helpful guidance notes on what Project or its subsequent use or sale, but they may not be used
to consider when completing the Contract Details and the for reproduction of the design for any part of any extension
Schedule of Services. The intention behind these publications is of the Project or any other project without the Architect's/
to simplify the form of appointment and, like NEC4, set it out Consultant's written consent.
in easy-to-read, ‘user friendly’ terms. The contracts are written
in clear language and are colour-coded. 11.10 An advantage it has over NEC4 is that it is specifically
provided in clause 6.7 that ‘the Architect/Consultant shall not be
11.03 As would be expected in a suite of contracts, they contain liable to the Client for any use of the drawings and documents
similar provisions, so the more salient terms are highlighted as other than for the purpose for which they were prepared and
follows: provided by the Architect/Consultant’.

The RIBA Standard Professional 11.11 Further, at clause 6.2, ‘no part of any design by the
Services Contract 2018 Architect/Consultant may be registered under the Registered
Designs Regulations 2001 by the Client without the written
11.04 This form of contract is suitable when the Architect/ consent of the Architect/Consultant’.
Consultant undertakes a commission for architectural services on
projects whereby the Client commissioning the project appoints
the Architect/Consultant. Architect/Consultant’s liability
11.12 Clause 7 seeks to limit legal action or proceedings arising
Architect/Consultant’s responsibilities out of or in connection with the Contract whether in contract,
11.05 Clause 3.1 provides that: tort for negligence or breach of statutory duty, or otherwise
to 6 years for a simple contract or 12 years if the contract is
In the performance of the Services, and discharging all the executed as a deed. The date when time starts to run is stipulated
obligations under the Contract, the Architect/Consultant to be from the earlier of the date of Practical Completion or the
will exercise the reasonable skill, care and diligence to be date of completion of the last Services.
expected of an Architect/Consultant experienced in the provi-
sion of such services for projects of a similar size, nature and 11.13 There is a time limit on the bringing of claims under NEC4
complexity to the Project. Notwithstanding anything that may which is addressed by Option X18, with specific reference to a
appear elsewhere to the contrary, whether under this Contract liability date. Under the SPSC, by contrast, it is stated at clause
or otherwise, the Architect/Consultant's duties and obligations 7.1 that:
shall be deemed to be subject to the exercise of such reason-
able skill, care and diligence and nothing contained in this No action or proceedings arising out of or in connection with
Agreement or elsewhere shall be construed as imposing on the Contract whether in contract, in tort, for negligence or
the Architect/Consultant any greater duty that the exercise of breach of statutory duty or otherwise shall be commenced
such reasonable skill, care and diligence. after the expiry of 6 or 12 years, depending on how the
Contract is executed, from the date of Practical Completion
This is an attempt to limit the duties of the Architect to that of or the date of completion of the last Services, whichever is
reasonable skill, care, and diligence, and this is expressed to the earlier.
withstand statements to the contrary within the agreement or any
other documents. However, it would still be sensible to inter- 11.14 The SPSC 2018, like the NEC4, has a ‘net liability’ clause
rogate any amendments or any documents that are associated at clause 7.3. In common with the NEC4, it seeks to limit liabil-
with the Project that confer any obligations on the Architect, as ity at clause 7.2 to the amount of the Architect’s professional
there could be scope for legal argument as to the effectiveness indemnity insurance specified in the Contract Details. The agree-
of such attempted limitations. ment also contains a provision at clause 7.2 that seeks to limit
the liability for loss or damage to the amount of the Architect/
Consultant’s professional indemnity insurance and stipulates
Fees and expenses
that no employee of the Architect/Consultant shall be personally
11.06 Clause 5 identifies that the fees for performance of the liable for any negligence, default, or any other liability arising
Services and/or any additional services shall be calculated in from the performance of the Services.
accordance with that clause and as specified in the Contract
Details. 11.15 Further, the drafting of the provisions at clause 7 anticipate
that the Architect’s liability is further limited to such sum as
11.07 Clauses 5.1 to 5.10 are more precise than under the NEC4 agreed by the parties or such sum adjudged by the court as to be
regarding the terms on which fees are calculated, adjusted to the proportion of the loss to the Client caused by the Architect’s
allow for items such as loss and expense, reductions in the failure to exercise reasonable skill, care, and diligence in the
Construction Cost, extra work or expense, the requirement of the performance of its duties under the Contract.
220 The NEC4 Engineering and Construction Contract

Suspension or termination The RIBA Concise Professional


11.16 The grounds for suspension and termination under SPSC Services Contract 2018
are broadly in line with NEC4. 11.23 The concise form of contract is of use when the
The Client may suspend or terminate performance of any or Architect/Consultant undertakes a simple commercial project
all of the Services upon seven days’ written notice and stating of any value where the building works are being carried out
the reason for doing so in accordance with clause 9.1. pursuant to a separate form of building contract. As this is a
The Architect/Consultant may suspend or terminate perfor- concise version of the contract discussed above, no further
mance of any or all of the Services and other obligations under commentary is required.
the Contract by giving at least seven days’ written notice and
identifying the specified grounds detailed at clauses 9.2.1–9.2.5
which include the Client’s failure to pay fees, the Clent being The RIBA Domestic Professional
in material or persistent breach of its obligations and where the Services Contract 2018
Architect/Consultant is prevented or impeded in performing the
Services, force majeure, and any other reasonable ground. 11.24 The RIBA Domestic Professional Services Contract is for
use when the Architect/Consultant is engaged by a consumer
11.17 Clause 9.4 provides for the situation whereby a notice of Client relating to works in the Client’s own home. This form
suspension or termination arises from a default and confirms largely resembles the standard and concise forms, but a key dif-
that if the default is remedied, performance of the Services and ference is that, at clause 10, the parties need to have stated in
other obligations shall resume within a reasonable period. Where the Contract Details that adjudication applies if they seek to use
the default is not remedied, the Contract shall be ended by the that form of dispute resolution.
non-defaulting Party giving at least seven days’ written notice.
11.25 The adjudication process and the benefits of it are dis-
11.18 Where the Services are suspended by either Party and not cussed in Chapter 23. It is important that if the Architect/
resumed within six months, the Architect/Consultant has the Consultant wishes to have that form of dispute resolution
right to treat performance of the Services as ended on giving at available, it needs to be set out in the Contract Details. On
least seven days’ further written notice to the Client. balance, it would usually seem sensible for its inclusion from
the Architect/Consultant’s perspective, as it is likely that it will
11.19 The agreement may be terminated immediately by notice be the Architect or Consultant that will be a potential referring
from either party in the event that the other Party becomes bank- party, chasing payment in any dispute. Further, as this is a con-
rupt, or is subject to a receiving or administration order, and/or tract for a domestic project, the disputes may be of a relatively
goes into liquidation, and/or becomes insolvent, and/or makes any modest value that will not justify the costs or time of arbitration
arrangements with creditors. Upon termination, as stipulated at or litigation.
clause 9.8, a copy of any drawings and documents produced pur-
suant to the Services and not previously provided by the Architect/
Consultant to the Client shall be delivered to the Client by the The RIBA Sub-Consultant Professional
Architect/Consultant, subject to the terms of the licence under Services Contract 2018
clause 6.3 and payment of any outstanding fees and other amounts 11.26 The RIBA SCPSC is for use when the Architect/Consultant
due plus the reasonable expenses of the Architect/Consultant. desires or is required to appoint a sub-consultant to carry out some
of its services. It is of course essential that the contract terms are
Dispute resolution compatible and limited in the same way as the agreement or what
is termed the Head Agreement between the Architect/Consultant
11.20 Under SPSC clause 10.2, it is made clear that either Party and the Client. The provisions at clause 9 that address suspension
pursuant to its statutory rights may give notice at any time of and termination confirm that if the Head Agreement is terminated
its intention to refer a dispute to adjudication. The nominating for any reason, then the performance of all Services under this
body and the relevant adjudication rules are specified in the Agreement shall immediately terminate.
Contract Details.

11.21 It is also noted at clause 10.5 that the Adjudicator may The RIBA Principal Designer Professional
allocate between the Parties the costs relating to the adjudica-
Services Contract 2018
tion, including the fees and expenses of the Adjudicator.
11.27 The RIBA PDPSC is for use when the Architect is
11.22 Clause 10.8 provides for arbitration as an alternative to appointed Principal Designer under the CDM Regulations 2015,
litigation. It is stipulated that any arbitration is subject to the this form being suitable for simple, commercial projects of any
Construction Industry Model Arbitration Rules (CIMAR) current value. Again, the format falls into line with the other forms in
at the date of the referral. this series, so no further analysis needs to be provided here.
19
The FIDIC contract
JEREMY GLOVER

1 Introduction (i) Conditions of Contract for Construction for Building


and Engineering Works Designed by the Employer: The
1.01 You might well ask what a chapter on the FIDIC form Construction Contract (the new ‘Red Book’). In 2001, a Red
of contract is doing in a legal handbook for architects. Surely, Book subcontract was introduced;
the FIDIC contract conditions apply to duties of engineers, not (ii) Conditions of Contract for Plant and Design-Build for
architects? The answer is quite simple: for international contrac- Electrical and Mechanical Plant and for Building and
tors, the most common form of contract is FIDIC, or at least a Engineering Works, Designed by the contractor: The Plant
contract largely borrowed from the FIDIC form. Therefore, it is and Design/Build Contract (the new ‘Yellow Book’). A
highly probable that if you are asked to advise on an appropriate Yellow Book subcontract finally followed in 2019;
form of contract for an international project, you will need to (iii) Conditions of Contract for EPC/Turnkey Projects: the EPC
be aware of the FIDIC form; equally, if architects are working Turnkey Contract (the ‘Silver Book’);
abroad, perhaps administering the project, they may well find (iv) A short form of contract (the ‘Green Book’).
themselves operating under some form of the FIDIC conditions.
In December 2016, at the FIDIC International Users’ Conference 2.03 The FIDIC Forms also contain Guidance for the Preparation
in London, Simon Worley, a member of the FIDIC Red Book of Particular Conditions, which includes notes on the preparation
Update Task Group, commented that: ‘The Red Book has been of tender documents and also highlights some of the key points
and is used in more countries around the World than any other which, if missed, could lead to difficulties during the project.
form of contract —160+’.
2.04 In December 2017, FIDIC introduced a Second Edition
1.02 The FIDIC organisation was founded in 1913 by France, of the Rainbow Suite, but only for the Red, Yellow, and Silver
Belgium, and Switzerland. The UK did not join until 1949. Books. An Emerald Book for tunnelling contracts based on the
The original FIDIC contract, or ‘Red Book’, was based on the 2017 version was introduced in May 2019. FIDIC said that it
detailed design being provided to the contractor by the employer. wanted:
It applied to civil engineering and infrastructure projects. This
led to the development of the ‘Yellow Book’ for mechanical and (i) To ‘reinforce the role of the Engineer’;
electrical works, which had an emphasis on testing and com- (ii) To achieve ‘clarity, transparency and certainty’; and
missioning, and so was more suitable for the manufacture and (iii) To address ‘issues raised by users over the past 17 years
installation of plant. arising out of the use of the 1999 Suite’.

2.05 The most immediate difference is the size of the new edi-
2 The FIDIC forms tions. The contracts have doubled in size. The 1999 Yellow
Book was 63 pages long, and is now 119 pages (or 126 pages,
2.01 In 1994, FIDIC established a task force to update its if you include the appendices with the Dispute Boards). As well
contract forms in the light of developments in the international as being far longer, the FIDIC 2017 Rainbow Suite is, in many
construction industry. The key considerations included: respects, far more detailed and prescriptive.

(i) The role of the engineer and in particular the require- 2.06 FIDIC is also keenly aware of the need to develop new
ment to act impartially in the circumstances of being contract forms in order to adapt to changing conditions. Since
employed and paid by the employer; the original publication of the 1999 suite of contracts, FIDIC has
(ii) The desirability for the standardisation of the FIDIC also introduced the following:
forms;
(iii) The simplification of the FIDIC forms in light of the (i) Conditions of Contract for Construction for Building
fact that the FIDIC conditions were in English, but and Engineering Works Designed by the Employer, for
were often used by those whose language background bank-financed projects only (the ‘Pink Book’ or ‘MDB’
was other than English; Form). This was not updated in the 2017 Second
(iv) The new contracts would be suitable for use in both Edition Suite.
common law and civil law jurisdictions. (ii) Conditions of Contract for Design, Build and Operate
Projects 2008 (the ‘Gold Book’). The Gold Book
2.02 This led to the publication of four new contracts, known as can also be seen as a bridge between the 1999 and
the Rainbow suite, in 1999: 2017 Editions of the Rainbow Site, as the origin of

221
222 The FIDIC contract

some of the changes made in 2017 is clearly signposted to architects, as they may often find themselves working under
in the 2008 Form. similar obligations, and is dealt with in more detail below in
(iii) Dredgers Contract (the ‘Blue Book’): 2nd Edition 2016. Section 4.
The Blue Book is intended for dredging and reclama-
tion work and ancillary construction, and the employer 3.07 Clause 4 is by far the longest sub-clause and covers the
undertakes the design of the project. contractor’s general obligations, including, in the ‘Red Book’,
(iv) Consultant Model Agreements, (the ‘White Book’): 5th the requirement that in respect of contractor designed works: ‘it
Edition 2017. The White Book is an agreement to be shall, when the works are completed, be fit for such purposes for
used by the employer and its consultant. which the part is intended as are specified in the Contract’. This
is an absolute duty. In other words, the absence of negligence in
the design will not be a defence for the contractor.
3 The content of the FIDIC Rainbow
Suite –the standard clauses 3.08 In the ‘Silver Book’, clause 5 deals with design responsibil-
ity. Given the turnkey nature of the contract, the intention is to
3.01 In keeping with the desire for standardisation, all of the con- make the contractor responsible for the integration of the design
tract forms include General Conditions together with guidance for and the construction of the works. Clause 5.1 notes that:
the preparation of the Particular Conditions and a Letter of Tender,
Contract Agreement and Dispute Adjudication Agreements. ‘The Contractor shall be responsible for the design of the
works and for the accuracy of the Employer’s Requirements
3.02 From a practical point of view, the key to reading and (including design criteria and calculations). Any data received
understanding the FIDC form is to understand its structure. The by the Contractor, from the Employer or otherwise shall not
1999 FIDIC form has 20 clauses, which are perhaps best viewed relieve the Contractor from his responsibility for the design
as chapters covering the key project topics. Those clauses are and execution of the works.’
as follows:
3.09 There is a difference between the design obligations of
the contractor under the Rainbow suite and the consultant who
Clause 1 – General provisions; enters into a White Book agreement. Sub-clause 3.3.1 of the
Clause 2 – The employer; White Book notes that the consultant shall: ‘have no other
Clause 3 – The engineer or employer’s representative; responsibility than to exercise the reasonable skill, care and
Clause 4 – The contractor; diligence to be expected from a consultant experienced in the
Clause 5 – Design (‘Silver Book’), or Nominated subcontractor provision of such services for projects of similar size, nature and
(‘Red Book’); complexity.’ Whilst, sub-clause 3.3.2 says that:
Clause 6 – Staff and labour;
Clause 7 – Plant, materials and workmanship; To the extent achievable using the standard of care in sub-
Clause 8 – Commencement, delays and suspension; clause 3.3.1 and without extending the obligation of the
Clause 9 – Tests on completion;
consultant beyond that required under sub-clause 3.3.1, the
Clause 10 – Taking over;
consultant shall perform the Services with a view to satisfy-
Clause 11 – Defects liability;
ing any function and purpose that may be described in [Scope
Clause 12 – Tests after completion;
Clause 13 – Variations and adjustments;
of Services].
Clause 14 – Contract price and payment;
Clause 15 – Termination by employer; The reason for this may be that when the contractor carries out
Clause 16 – Suspension and termination by contractor; design work, it is in a design and build fashion.
Clause 17 – Risk and responsibility;
Clause 18 – Insurance; 3.10 Clause 6 has particular importance in relation to person-
Clause 19 – Force majeure; nel. The contractor must not only engage labour and staff, but
Clause 20 – Claims, disputes and arbitration. must also make appropriate welfare arrangements for them. This
clause is more wide-ranging and detailed in the Pink Book.

3.03 Following the approach of the ‘Gold Book’, in the 3.11 Clause 8 makes provision for Commencement, Delay, and
2017 Second Edition, there is a slightly different order, with the Suspension. Sub-clause 8.3 sets out the manner in which the
insurance clause having been moved to clause 19, while clause contractor should provide programmes showing how the contrac-
17 has been renamed ‘care of the works and indemnities’, and tor proposes to execute the works. The programming information
the force majeure clause has been replaced with a new clause required under the 2017 Edition has become far more detailed
18, headed ‘exceptional events’. and prescriptive.

3.04 Further, in the 2017 Second Edition, there are 21 clauses, 3.12 Clause 12 deals with measurement and evaluation.
with clause 20 dealing with claims, disputes and arbitration. Measurement is a central feature of clause 12, and is the basis
The most important clauses are discussed below. ultimately upon which payment to the contractor is calculated.
Sometimes called a ‘measure and value’ type of contract, the
3.05 Clause 2 addresses the role of the employer. Sub-clause 2.4 arrangements in place in the Red Book proceed on the basis that
renders it mandatory upon the employer, following request from the the works are to be measured by the engineer. Those quantities
contractor, to submit reasonable evidence of its financial arrange- and measured amounts of work are then to be paid for at the
ments and any material change to those arrangements. Failure to rates and prices in the contract, or else on the basis of adjusted
submit such evidence provides the contractor with the entitlement rates or entirely new rates (if there is no basis for using or alter-
to suspend work, ‘or reduce the rate of work’, unless and until the ing contract rates for the work).
contractor has received that reasonable evidence. In addition, sub-
clause 2.5 of the 1999 Form requires the employer to give notice 3.13 Clauses 15 and 16 deal with termination by the employer
and particulars to a contractor if it considers that it is entitled to and suspension and termination by the contractor, while clauses
any payment under any clause of the contract. The same principle 17–19 deal with risk and responsibility. This includes, at sub-
applies to the 2017 Edition, but it is now a part of clause 20. clause 17.6, the exclusion of the liability of both contractor and
employer: ‘for loss of use of any works, loss of profit, loss of
3.06 Clause 3 deals with the position of the engineer or any contract or for any indirect or consequential loss or dam-
employer’s representative. This may be of particular interest age which may be suffered by the other party in connection
The engineer’s duties 223

with the contract’. This includes a cap on the liability of the over a certain period of time, it can become difficult to pinpoint
contractor to the employer – something which was new to the the exact start of the 28-day period.
1999 FIDIC form. In the 2017 Edition, contractor’s indemni-
ties now include an indemnity, carved out of the overall cap 4.06 Sub-clause 20.1 is a time-bar clause or condition prec-
on liability, in relation to ‘the design of the Works and other edent which potentially provides the employer with a complete
professional services which result in the Works not being fit defence to any claim for time or money by the contractor not
for purpose’. started within the required time-frame. In England and Wales,
following the House of Lords case of Bremer Handelgesellschaft
3.14 Finally, clause 20 deals with claims, disputes, and arbitra- mbH v Vanden Avenne Izegem NV [1978] 2 Lloyd’s Rep,
tion. The way the FIDIC form operates when it comes to making 113 such clauses are binding only if the language of the clause
claims merits further discussion. in question is clear. Here, sub-clause 20.1 expressly makes it
clear that:

4 Claims If the contractor fails to give notice of a claim within such


period of 28 days, the Time for Completion shall not be
How does the employer make a extended, the contractor shall not be entitled to additional
claim under the 1999 FIDIC form? payment, and the employer shall be discharged from all liabil-
ity in connection with the claim.
4.01 As indicated above, sub-clause 2.5 provides details as to
how the employer is to make a claim. The key features of this 4.07 Further, the courts have confirmed their approval for con-
sub-clause are: dition precedents, provided that they fulfil the conditions laid
out in the Bremer case: in Multiplex Construction v Honeywell
(i) If the employer considers itself entitled to either any pay- Control Systems [2007] EWHC 447 (TCC), Jackson J held that:
ment or an extension of the Defects Notification Period, it
shall give notice and particulars to the contractor. contractual terms requiring a contractor to give prompt notice
(ii) The notice relating to payment should be given as soon of delay serve a valuable purpose; such notice enables matters
as practicable after the employer has become aware of the to be investigated while they are still current. Furthermore,
event or circumstance which gives rise to the claim. such notice sometimes gives the employer the opportunity
(iii) The employer must also provide substantiation, including to withdraw instructions when the financial consequences
the basis of the claim and details of the relief sought. become apparent.
(iv) Once notice has been given, the engineer shall make a
determination in accordance with sub-clause 3.5. 4.08 However, perhaps even FIDIC itself has recognised the
(v) The employer cannot make any deduction by way of setoff potentially harsh consequences of the strict time limits within
or any other claim unless it is in accordance with the engi- sub-clause 20.1. In the Second Edition, there is a new sub-clause
neer’s determination. 20.2.5, which gives the Engineer an element of discretion in
deciding whether or not there are circumstances which justify
4.02 The employer must give notice ‘as soon as practicable’ the late submission.
after becoming aware of a situation which might entitle it to
payment. Following the Privy Council case of NH International 4.09 Given the potential consequences of failing to submit a
(Caribbean) Ltd v National Insurance Property Development timely claim, with the FIDIC form, as indeed with any construc-
Company Ltd (Trinidad and Tobago), [2015] UKPC 37, this is tion contract:
a strict time limit.
(i) Parties should take care when concluding contracts to check
4.03 Sub-clause 2.5 is therefore, in many ways, a ‘contractor- any time-bar clauses governing claims they might make.
friendly’ clause, which is designed to prevent an employer from (ii) Parties should appreciate the risks they then run of not mak-
summarily withholding payment or unilaterally extending the ing a claim (even if to maintain goodwill) unless the other
Defects Notification Period. party agrees to relax the requirements or clearly waives
them. This is perhaps especially the case where time-bar
clauses, if cautiously operated, may generate a proliferation
In what circumstances can a contractor of claims.
make a claim under the 1999 Form? (iii) Remember that the courts see the benefits of time-bar pro-
visions and support their operation. A tribunal might bar
4.04 A different set of rules apply to the contractor. Under clause an entire claim for what seems like a technical reason, by
20.1, the contractor has a duty to notify the employer of an which time it will usually be too late to make a new, compli-
entitlement to additional time or money. The key features of the ant claim.
sub-clause are that: (iv) Indeed, even where the contract contains a clause such as
sub-clause 20.2.5 of the Second Edition, potential claimants
(i) The contractor must give notice of time or money claims should not necessarily rely upon the other party already
as soon as practicable, and not later than 28 days after the having the information they are required to provide.
date on which the contractor became aware, or should have
become aware, of the relevant event or circumstance.
(ii) Any claim to time or money will be lost if there is no notice 5 The engineer’s duties
within the specified time limit.
(iii) Supporting particulars should be served by the contractor 5.01 Obviously, the engineer is not a party to the construction
and the contractor should also maintain such contemporary contract, having a separate contract with the employer. Under
records as may be needed to substantiate claims. the White Book, sub-clause 1.16.1 states: ‘In all dealings under
the Agreement the Client and Consultant shall act in good faith
4.05 The 28-day deadline does not necessarily start on the and in a spirit of mutual trust.’ This obligation is not found in
date of the claim event itself, but on the date the contractor the Rainbow suite. Under English Law, there is no implied duty
objectively should have become aware of the event. While it is of good faith.
relatively easy to identify the claim event in the case of a single
event, such as the receipt of an instruction, when, however, the 5.02 One of the notable features of the Second Edition is the
claim event is a continuous event, such as unforeseeable weather increased workload given to the engineer. In the context of the
224 The FIDIC contract

2017 editions, engineers must be particularly careful to act within 6.03 FIDIC have also reinforced the Advance Warning provi-
the time limits set out in the contract. If they do not, the numer- sions, previously tucked away within the 1999 Edition. There is
ous deeming provisions to be found within the contract will come now a specific sub-clause 8.4 requiring all parties, including the
into play, and the employer may well find that it has inadvertently engineer, to make the others aware of any event likely to cause
approved something it might have preferred not to have. delay or increased cost.

5.03 There have been significant changes in the engineer’s role


as the FIDIC form has developed. In the 1999 form, the express 7 The FIDIC Golden Principles
reference in the 1987 edition to the engineer’s impartiality was
replaced with the following: 7.01 One of FIDIC’s main current concerns is that, whilst the
1999 Rainbow Suite is the most widely used set of construction
Whenever carrying out duties or exercising authority, speci- contracts globally, the FIDIC contracts are frequently amended
fied in or implied by the Contract, the engineer shall be to such an extent that their fundamental characteristics can
deemed to act for the employer. seem to be lost. FIDIC wanted to prevent parties from using the
Particular Conditions of Contract to fundamentally change the
5.04 Under the 2017 Edition, by contrast, when making a risk allocation and therefore the very nature of a FIDIC contract.
determination, the engineer is required by sub-clause 3.7 to act
‘neutrally’. 7.02 FIDIC has sought to address this through the adoption in
the 2017 Edition of the following Five Golden Principles:
5.05 Sub-clause 3 essentially provides a two-step process for the
resolution of claims before the engineer. While the engineer is GP1: The duties, rights, obligations, roles and responsibilities of
expressly the agent of the employer: all the Contract Participants must be generally as implied in
the General Conditions, and appropriate to the requirements
(i) Under the first stage, the engineer’s duty is to ‘endeavour of the project.
to reach agreement’ between the parties; if that fails, then GP2: The Particular Conditions must be drafted clearly and
(ii) The engineer is obliged to make ‘a fair determination’. unambiguously.
GP3: The Particular Conditions must not change the balance
5.06 So, what is a fair determination? In England and Wales, of risk/reward allocation provided for in the General
there has been considerable debate about the role of the engineer. Conditions.
Rix LJ, in Amec Civil Engineering Ltd v Secretary of State for GP4: All time periods specified in the Contract for Contract
Transport [2005] CILL 2288, summarised the obligations of the Participants to perform their obligations must be of reason-
engineer (or indeed the architect) in such circumstances. He said able duration.
that the engineer or architect must: GP5: All formal disputes must be referred to a Dispute
Avoidance/Adjudication Board (or a Dispute Adjudication
(i) ‘Retain his independence in exercising [his skilled profes- Board, if applicable) for a provisionally binding decision as
sional] judgment’; a condition precedent to arbitration.
(ii) ‘Act in a fair and unbiased manner’ and ‘reach his decisions
fairly, holding the balance’ ; 7.03 These Golden Principles are not incorporated as a formal
(iii) If the engineer hears representations from one party, the part of the General Conditions, although FIDIC introduced a
engineer must give a similar opportunity to the other party short, separate Guide in June 2019. They are in the Guidance
to answer what is alleged against it; and Section where FIDIC ‘strongly recommends’ that drafters of the
(iv) ‘Act fairly and impartially’, where fairness is ‘a broad and PCC abide by the Five Golden Principles. Currently, therefore,
even elastic concept’ and impartiality ‘is not meant to be a they are no more than an expression of FIDIC’s intent, albeit an
narrow concept’. important statement of intent that can be seen in many of the
changes made to the Second Edition.

7.04 This is likely to be an area which is developed when FIDIC


6 The road to dispute avoidance comes to consider a Third Edition of the Rainbow Suite.
6.01 The prescriptive nature of the 2017 Edition appears to be
part of a trend towards setting out greater detail in express terms. 8 Building Information Modelling
The apparent justification for this is to introduce more clarity and
transparency and, therefore, more certainty, all of which should 8.01 Something else which may be addressed in any third edition
lead to fewer disputes. If a contract sets out, step by step, what is building information modelling (BIM), which has only been
each party must do, as well as the consequences of failing to take addressed to a limited degree in the 2017 Edition. There is no
that step, then compliance is expected, and any consequences of specific mention of BIM in the General Conditions, just a special
non-compliance are the risk and responsibility of the relevant Advisory Note within the Special Provisions which deals with the
party (in theory at least). This does mean that there are increased use of BIM. The Advisory Note indicates that FIDIC are going to
financial and resource burdens of contract administration for all prepare two documents – a ‘Technology Guideline’ and a ‘Definition
parties to the project, including consultants, which will have to of Scope Guideline Specific to BIM’, which are intended to provide
be tackled at the earliest stages in a potential project. further detailed support for the use of BIM on projects that use the
FIDIC form. When FIDIC do produce the guideline document,
6.02 A more obvious example of the increased focus on dispute perhaps in the form of an agreement or FIDIC BIM Protocol, it
avoidance comes with the re-naming of the Dispute Board as would be prudent to see if it is ISO 19650 compliant.
the Dispute Adjudication and Avoidance Board (or DAAB).
The changes introduced are far wider than the simple change of
name and, if adopted, there is a valuable role to be played by 9 Further information
the Dispute Board and Board members. Sub-Clause 21.3 permits 9.01 It is not within the scope of this book, of course, to provide
the Parties to make a joint request at any time to the DAAB, a full commentary of the FIDIC form. If you need further infor-
except during the period when the Engineer is carrying out a mation about the FIDIC form, the FIDIC website – www.fidic.
determination, to ‘provide assistance and/or informally discuss org – provides a valuable starting point and a generous amount
and attempt to resolve any issue or disagreement’. of free information.
20
Other standard forms of building contract
RUPA LAKHA

1 Introduction The main forms are accompanied by contract and pricing


Guides. Some international editions have been produced, and a
1.01 This chapter discusses standard forms of building contract BIM protocol has been developed for use with PPC2000.
issued by other bodies, such as the Association of Consultant
Architects (‘ACA’), the Royal Institute of British Architects PPC2000
(‘RIBA’), and the Institution of Civil Engineers (‘ICE’), focus-
ing on those contracts which are more commonly used and have 2.03 When launched, PPC2000 was unusual in being the first
become prevalent in the market. standard form multi-party partnering contract intended to cover
the entire procurement process. Together with ACA’s TPC2005
1.02 As well as these contract suites, there are a number of Term Partnering Contract, it has been widely adopted in both
other standard forms, but it is beyond the scope of this book public and private sector projects and has been used as the basis
to comment on every standard form available in the construc- of major frameworks.
tion industry, including older or outdated editions. Readers are
referred to previous editions of this work for information on 2.04 The other main partnering forms are the JCT Constructing
historic contract forms. Excellence Contract (JCT-CE), produced in collaboration with
Constructing Excellence, the ICE Contract with its Partnering
Addendum (now ICC Partnering Addendum August 2011), and
the collaborative and more commonly adopted NEC form of
2 ACA Forms of Contract contract (Option X12, the NEC Partnering Option). NEC4ALC
now also adopts a single, multi-party contract to procure the
ACA suite of Partnering project. However, these forms do not adopt the PPC2000 two-
Contracts, PPC2000, TPC2005, stage approach to early contractor and subcontractor procure-
ment, which is a key feature of PPC, and allows the parties to
SPC2000 and Guides withdraw from the contract if the values profile is unsatisfactory
2.01 The ACA, the national professional body representing (Section 3.1.3).
architects in private practice throughout the UK, publishes
a range of standard forms regularly used in the construction 2.05 The focus of PPC2000 is on collaborative working rather
industry. Their suite of Partnering and Alliance contracts are one than contractual penalties. The contract seeks to establish early
of the few UK standard forms for these types of contracts with and active engagement of a Partnering Team, usually made up
PPC2000 (Amended 2013), ACA Standard Form of Contract of the Client, the contractor (Constructor), consultants, and any
for Project Partnering (‘PPC2000’), one of the most commonly specialist sub-contractors (Specialists). Other parties may enter
used of the ACA suite. This is a one-off contract. the Partnership Agreement as the project progresses by entering
into the Joining Agreement that accompanies the form. This
2.02 The other ACA partnering forms are: feature of PPC2000 exposes all parties to claims from all other
parties.
(a) TPC2005 (Amended 2008) – ACA Standard Form of
Contract for Term Partnering, which is a multi-party 2.06 As set out from almost the beginning of the Partnership
contract providing a basis for term partnering and can be Agreement, this contract expressly demands that parties work
used for term works and services in any jurisdiction; in ‘mutual cooperation to fulfil their agreed roles and respon-
(b) SPC2000 (Amended 2008) – ACA Standard Form of sibilities’. Clause 1.3 of the Partnering Terms states that ‘The
Specialist Contract for Project Partnering, which covers Partnering Team shall work together and individually in the
contracts with specialist sub-contractors and enables them spirit of trust, fairness and mutual cooperation for the benefit
to join the project partnering team under the PPC2000. The of the Project, within the scope of their agreed roles, expertise
SPC2000 works back to back with PPC2000 and is aimed and responsibilities’. This ethos of ‘working together and indi-
to involve sub-contractors in project design from an early vidually’ is also repeated in ensuring access and transparency in
stage; relation to the exchange of information (clause 3.1).
(c) SPC2000 Short Form (Issued 2010) – ACA Standard Form
of Specialist Contract for Project Partnering; and 2.07 It is clear that this form of contract is not intended to be
(d) STPC2005 (Issued 2010) – ACA Standard Form of Specialist signed and then forgotten about; it requires active involvement.
Contract for Term Partnering. As demonstrated from its risk management process through to

225
226 Other standard forms of building contract

its dispute resolution structure, this form of contract is likely 2.16 Where the parties agree on a traditional procurement route,
to be most effective with an experienced Client where the par- it is usual for the architect to act as the Lead Designer. However,
ties have an established, long-term relationship and/or are fully where the contract is procured on a design and build basis
committed to and educated in the partnering ethos. To that end, and parties have elected in the Partnering Agreement for the
the Client will have some work to do in developing the Brief Constructor to be the single point of responsibility to the Client
before the PPC2000 is entered into, and it is likely that an for design and construction, there is potential for the Constructor
architect’s input will be necessary from the outset. This could to accept design responsibility for a design process where he has
be covered by a letter of intent until parties are ready to enter potentially restricted input. However, this should be considered
into the PPC2000. alongside the process for variations as set out in clause 17.

2.08 Pre-construction phase activities include joint design review


and development whereby the Constructor can comment and Delivering the partnership ethos
offer alternative solutions, second stage supply chain tender-
ing to encourage repricing of the works where needed, joint 2.17 The PPC2000 imposes express obligations on the parties to
risk management, advance agreement of a construction phase take action to achieve the best outcome for the project:
programme identifying contractual deadlines for the parties and
the contract administrator, and direct employer attendance at ● The Core Group is to meet regularly to ‘stimulate the pro-
key meetings. gress of the Project’ (clause 3.3);
● The design development and process is to have the objective
2.09 The structure and content of the PCC partnering forms is of ‘achieving best value’ (clause 8.1);
similar and includes the use of KPIs, targets and incentives to ● Each Partnering Team member is to do ‘all that it can … for
motivate and improve performance, relatively strict time limits the benefit of the Project’ (clause 4.2);
(for example, in the time that the Client’s Representative is ● The Partnering Team is to implement the processes for
required to respond to certain Contractor requests), and options establishing relationships with Specialists so that, inter alia,
for a project bank account. they ‘establish and demonstrate best value to the Client’
(clause 10.1);
2.10 The most recent amendments to this suite are those needed ● Clause 18.1 requires the Partnering Team to ‘analyse and
to comply with the CDM Regulations 2015 changes, the changes manage risks in the most effective ways’;
to the Housing Grants, Construction and Regeneration Act 1996 ● The Partnering Team is to work together and individually to
required for all contracts entered into from 1 October 2011, and ‘provide best value to the Client’ (clause 23.2).
payment changes for contracting authorities.
The following highlights some key areas of the contract to Whilst the intention behind the drafting is apparent, the ability
be considered. to measure these provisions and therefore enforce them may be
less clear.

Price Duty of care and warranties


2.11 The cost build up is critical to the PPC2000 form, which 2.18 The parties are to use reasonable skill and care as appropriate
is facilitated by the two-stage process. The Constructor is paid to their respective roles, expertise, and responsibilities, and a duty
according to the Pricing Framework, albeit costs are to be of ‘reasonable skill and care’ for each member of the Partnering
kept on an open book basis throughout and there is an Agreed team in respect of their roles and responsibilities (Clause 22).
Maximum Price in place.
2.19 However, the standard of care must be considered in the
2.12 Having emphasised achieving ‘best value’, the contract context of the contract as a whole. How does, for instance, one
enables Incentives for all Partnering Members where cost sav- measure the express obligation to achieve ‘best value’ when
ings are made. The mechanism and levels of the Incentives are ultimately it is still only subject to the duty to exercise reason-
to be agreed by the Core Group and put forward to the Client able skill and care?
for approval, and may supplement other incentives and KPIs set
out in the contract. 2.20 The risk profile for the Constructor may be different. In
addition to potentially being the single point of design respon-
sibility, the Constructor can also adopt a fitness for purpose
Design Process and Responsibility obligation in the Partnering Terms. This is notwithstanding the
duty of reasonable skill and care owed to the Constructor by
2.13 Clause 8 sets out the design process. The Lead Designer the other Parties.
and Design Team are to develop the design with the ‘objective
of achieving best value for the Client’. How one determines if 2.21 Similarly, whilst the parties are to proceed ‘regularly and dili-
that objective is met is discussed further below. gently’ with the Partnership Timetable and the Project Timetable,
the Constructor must also use ‘best endeavours at all times to
2.14 The partnering ethos requires parties to work together to minimise any delay or increased cost to the Project’ (clause 18.3).
develop and integrate the design, therefore hopefully facilitat-
ing better design interface. However, the primary obligation 2.22 However, the Partnering Terms give the option to amend the
to coordinate the design development process both pre- and warranties owed between the parties. There is also provision for
post-commencement of the works rests with the Lead Designer. a net contribution type clause, the relevant proportions of which
Depending on the form of procurement for the contract, this role are to be agreed between the parties.
is likely to be taken up by the architect.

2.15 Amongst other duties, the Lead Designer will provide the Risk
Constructor with design information. If neither the Constructor
nor the Specialist have contributed to that design and they 2.23 PPC2000 aims to provide a system whereby risk is divided,
consider that design to be contrary to the Project Agreement, or managed, and reduced between the parties in a transparent way.
not in the best interests of the Project, the Constructor can raise There is an express obligation on Partnering Team members to
objections within a specified timeframe. This begins a consulta- actively assess and manage risk throughout the different stages
tion process. of the project (clause 18.1). This is reflected in:
ICC forms of contract 227

● The use of two timetables. The Partnering Timetable governs contract published by the Institution of Civil Engineers (‘ICE’).
pre-construction activities and the Project Timetable governs The Association for Consultancy and Engineering (‘ACE’), and
construction activities. If completed collaboratively by the Civil Engineering Contractors Association (‘CECA’) co-sponsor
Partnering Team with realistic and logical timescales, they the ICC suite of contracts, which adopt a traditional construction
can be an effective way to assist project management; contract structure and tend to be favoured by the engineering
● The establishment and function of the Core Group (clauses industry.
3.3–3.6);
● The responsibilities of the Client Representative (clause 5.1); 3.02 This chapter focuses on the ICC Design and Construct
● The Early Warning System (clause 3.7); and Version 2018, as it is the most recently updated of the suite and
● The Risk Register. The parties have a template risk register arguably, the more commonly used.
to complete which again means that parties can tailor the
way risks specific to the project are properly managed. Of
course, parties will need to invest the time and focus in the ICC Design and Construct
early stage of the project to benefit fully. Version – June 2018
3.03 This lump sum design and build contract is a revision of
ACA suite of Alliance Contracts the earlier August 2011 edition. The ICC Design and Construct
FAC-1 and TAC-1 2011 Guidance Notes refer to the ICC Design and Construct as
a radical departure from the ICC Measurement Version August
2011. Unlike the ICC Measurement Version 2011, which fol-
FAC-1 - Framework Alliance Contract lows the traditional route, but provides for Contractor design for
part of the Works, the ICC Design and Contract 2018 allocates
2.24 FAC-1 is a multi-party overarching contract which can inte-
all aspects of design and construction risk to the Contractor,
grate related projects and can be combined with a range of two
including design originally provided by the Employer. The ICC
party construction forms, such as JCT, NEC, ICC, and PPC. It
Design and Construct Version 2018 allows no re-measurement of
was published in 2016 to address a lack of alliancing forms in the
the works, and the only cap on liability is a limit on the amount
UK market and adopts collaborative processes to help employers
of Liquidated Damages (Clause 10.8).
and their supply chain obtain better results from their framework.
3.04 It adopts a typical construction contract structure:
2.25 Parties can create an alliance comprising the employer, the
Alliance Manager, and any combination of consultants, con-
● Contents and index;
tractors, and suppliers, with the facility to add members. The
● Infrastructure Conditions of Contract, which generally fol-
members establish objectives, determine how they will achieve
low the project time line (definitions, subcontracting, provi-
improved value through supply chain collaboration, and manage
sion of information, Engineer’s role, the parties’ roles and
risks and avoid disputes through a shared risk register. There is
risk, time, performance, variations and change, payment,
flexibility to include specified legal requirements and the option
termination, insurance and dispute resolution, and a few sup-
to adopt BIM to achieve improved value.
plementary clauses which address Milestones, Sustainability,
and Employer supplied materials);
TAC-1 – Term Alliance Contract ● Form of Tender;
2.26 TAC-1 launched in 2017, is based on the TPC2005 part- ● Appendix which incorporates the contract particulars;
nering form and follows the FAC-1 structure. It operates as a ● Form of Agreement for execution by the parties;
self-contained multi-party contract which, like FAC-1 allows the ● Optional clauses, addressing tax and the CDM Regulations
parties to establish an alliance, its members and objectives, how 2015;
they will achieve improved value and avoid disputes. ● Form of bond; and
● Price Fluctuation provisions.

Architectural appointment
Information and design risk
2.27 The ACA publishes two forms of architectural appointments,
ACA SFA 2012 – ACA Standard Form of Agreement for the 3.05 Clause 4 (The Contract and Provision of Information)
Appointment of an Architect, updated from the original September primarily allocates risk to the Contractor. For instance, the
2008 version, and a shorter form of appointment, ACA98 – The Contractor is deemed to have inspected the Site and to have
Appointment of a Consultant Architect for Small Works. ‘obtained for himself all necessary information as to risks, con-
tingencies and other circumstances which may affect his tender’
2.28 The ACA form is less commonly used than the RIBA form (Clause 4.5). The Contractor is responsible for the Employer’s
of appointment. It is based on its predecessor, SFA/99, and was design (Clause 4.8) and for the interpretation of all information
updated in 2012, which has served both architects and employers obtained relevant to the Site or to risks, whether obtained by the
well since its inception as SFA/92. It has been updated to include Contractor or provided by the Employer (Clause 4.10).
the Housing Grants, Construction and Regeneration Act 1996
and Bribery Act 2010 amendments and includes model letters 3.06 Under clause 6.3, the Contractor must exercise the skill,
for each kind of project to assist architects and their employers care and diligence appropriate to an experienced professional
to agree on contract terms. consultant in the design of the Contractor Designed Portion.

ACA form of Building Agreement


and Subcontract Engineer’s role and collaboration
2.29 These less popular contract forms have undergone a number 3.07 In addition to the usual monitoring obligations and author-
of revisions, although the ACA Building Agreement 1982, Third ity to issue instructions (Clause 5), the Engineer has a number of
edition 1998 was last revised in 2003. key functions under this form of contract. The Engineer has sig-
nificant authority to determine and/or influence the outcome of
3 ICC forms of contract problems as they arise on the project (discussed further below).
To temper this, the Engineer is required to act impartially where
3.01 From 1 August 2011, the Infrastructure Conditions of required by the Contract to decide any matter as between the
Contract (‘ICC’) replaced the longstanding ICE forms of parties (Clause 5.4).
228 Other standard forms of building contract

3.08 Despite the traditional contract structure and approach to provision is made for Contractor design of specified parts of
risk allocation, Clause 6.1 (Collaboration and early warning) the Works). As one would expect, this form does not allo-
operates in a similar way to NEC’s co-operation provision cate risk for all aspects of design and construction to the
and the partnering ethos of the PPC2000, and requires the Contractor;
Contractor, Employer, and Engineer (on the Employer’s behalf) ● Ground Investigation Version – August 2011;
to ‘collaborate in a spirit of trust and mutual support in the ● Term Version – August 2011;
interests of the timely, economic and successful completion of ● Minor Works Version – August 2011;
the Works’. ● the ICC Partnering Addendum August 2011,

3.09 In addition to this, the ‘early warning’ mechanism in clause as well as various Guidance Notes.
6.1 requires the Contractor and Engineer to give notice to the
other ‘as soon as they become aware of any matter’ likely to 3.17 Note that in October 2011, an amendment sheet was pub-
affect design, cause delay, or lead to additional cost. This is lished to clarify the payment provisions in the 2011 versions
required irrespective of whether the Contract gives an entitle- of the ICC suite, both to address the changes to the Housing
ment to claim as a result of the relevant matter. Grants, Construction and Regeneration Act 1996 and concerns
that certain payment provisions did not comply with the Act.
3.10 The intention of Clause 6.1 is to require the parties to
meet and consider remedial action at an early stage. Clause
6.1(a) requires the Engineer to arrange a meeting between 4 RIBA forms of contract
appropriately authorised persons (presumably representatives
of the parties) within 7 days of an ‘early warning’ notice being 4.01 The Royal Institute of British Architects (‘RIBA’) publishes
given, and to consider measures to mitigate delay and additional a range of contract forms and appointments for both commercial
cost. Where the Contractor and the Engineer (on behalf of the and domestic (non-commercial) projects. Its two main construc-
Employer) agree actions or measures to deal with the relevant tion contract forms are the RIBA Concise Building Contract
matter, these are to be agreed in writing and become binding 2018, suitable for simple, small-to-medium-sized commercial
on the parties. building work, and the RIBA Domestic Building Contract
2018, suitable for work to a home, including renovations, exten-
3.11 Whilst on one hand the clear intention of this clause is early sions, maintenance, or new buildings.
risk management in a collaborative manner, there is potential
for tension between this process and the terms of Clause 13.1 4.02 Both forms were originally launched in 2014 and were
(Notice of Claims). Clause 13.1 requires the Contractor to give recently updated in February 2018. Amongst other things, the
notice within 28 days of becoming aware of the facts giving recent updates address the changes to the CDM Regulations
rise to a claim for additional payment or time, and states that 2015, specification of a level of PI insurance for the Contractor
‘failure to give timely notice shall disentitle the contractor from Design option, greater guidance on insurance and dispute
any compensation or allowance of additional time’, except to the resolution, simplified options in relation to programming, and
extent determined by the Engineer. inclusion of a contract checklist. They anticipate project admin-
istration by an architect or contract administrator.

Dispute resolution 4.03 The RIBA Standard Professional Services Contract


2018 is a professional appointment for architectural services
3.12 The ICC forms offer the full range of alternative and other form. It anticipates a traditional form of procurement, is intended
dispute resolution procedures. Although the parties can adjudi- for use on commercial projects, and has been updated to provide
cate at any time, parties are also able to refer disputes to the for novation or the option for the architect/consultant to ‘walk
Engineer who is required to decide the outcome of the dispute away’ from the project if a design and build procurement route
within the relatively limited timescale of 14 days from the refer- is undertaken. The architect’s liability is limited to the project
ral (clause 19.1). Unless challenged in writing within 28 days in question, and a net contribution clause is included. In addi-
of the date of the decision and setting out the grounds for the tion, there are Domestic, Concise, Sub-consultant, and Principal
challenge, the Engineer’s decision is binding. Designer forms of appointment.

3.13 Where challenged, the Engineer’s decision remains binding


until revised by any settlement agreement, adjudication decision, 5 IChemE forms of contract
or arbitration award. The Engineer’s award can be enforced up
until the point of revision. 5.01 The Institution of Chemical Engineers (‘IChemE’) is a
global professional engineering institution for professionals
3.14 Conciliation or mediation (Clause 19.3) and arbitration involved in the chemical, biochemical, and process industries.
(Clause 19.6) are also included as dispute resolution options. It publishes forms of contract for use on both international and
UK projects.
ICC Target Cost Version - June 2018 5.02 There are three main UK IChemE forms (Red Book: Lump
3.15 Under this contract, the Contractor is paid an agreed fixed Sum; Green Book: Cost Reimbursable; and Burgundy Book:
or ‘target’ cost plus fee, with cost savings below the target Target Cost) and a subcontract (Yellow Book), with accompany-
cost and expenditure above the target cost (gain or loss) shared ing guides for contract preparation. They are colour-coded based
according to an agreed percentage. ACE states that this contract on their pricing and procurement method, in a similar way to the
has been produced to meet industry demand. However, the NEC FIDIC forms. There is also a professional services agreement,
Target Cost and Partnering forms are likely to be more com- the Silver Book, 1st edition, 2017 and a minor works contract,
monly used than the corresponding ICC forms. Orange Book, 3rd edition, 2018.

5.03 The IChemE forms are ‘turnkey’ contracts, whereby the


Other ICC forms project is intended to be handed over to the employer in fully
3.16 The other main forms in the ICC suite include: operational order. Although the forms are used for the procure-
ment of infrastructure projects generally, they are designed for
● Measurement Version – August 2011, for use where the and primarily used in the chemical and process engineering
design is provided by the Employer (although as advised, industries – chemical, food production and pharmaceutical – for
IMechE/IET forms of contract 229

technical- and performance-based process plants. Accordingly, with a detailed procedure prescribed for the investigation and rec-
these forms include a very thorough testing procedure both dur- tification of any failures. An Acceptance Certificate must be given
ing and post-completion, and liability for defects is excluded where performance tests are undertaken (Clause 36) and there
following the (sometimes lengthy) defects liability period and are further detailed provisions dealing with the Defects Liability
issue of the Final Certificate. Period, rectification, and making good defects (Clause 37). After
expiry of the relevant Defects Liability Period for the Plant or sec-
5.04 As one would expect with contracts intended for the con- tion of works, the Project Manager must issue the Final Certificate
struction of operational plant, the IChemE forms are result- and which, subject to fraud, constitutes conclusive evidence ‘for all
performance-based, rather than traditional work-based construc- purposes and in all proceedings whatsoever between the Purchaser
tion forms. The forms contemplate that the Contractor may carry and the Contractor’ that the Contractor has completed the works
out innovative design work in view of the likely nature of the and made good in accordance with the contract. This places a
project. This may involve different approaches to pricing under potentially considerable burden on the Project Manager.
the one form of contract, such that elements of the works under
the lump sum Red Book, for example, can be priced as provi- Design
sional sums or on a reimbursable basis.
5.11 The Red Book contemplates that Special Conditions may be
5.05 The three main IChemE forms (the Red Book, Green Book, included, giving the Purchaser the option, exercisable when the
and Burgundy Book) adopt a relatively typical construction Contractor has completed the design work on a section covered
contract structure: by a provisional sum, of agreeing a price for that section to be
incorporated in the lump sum price for the works. The emphasis is
● Contents and introductory notes; on completion and sign off, both in terms of testing and payment,
● Agreement for execution by the parties; as the works proceed. It is also contemplated that provision is
● General Conditions of Contract, which generally follow made for third parties providing technology licences to check the
the project time line (definitions, Contractor and Purchaser Contractor’s design, provide guarantees, performance test and com-
responsibilities, Contract co-ordination, price, statutory mission, and provide training in respect of elements of the works.
obligations, subcontracting, Project Manager’s role and other
representatives, time, variations, claims, inspection and pre-
installation testing, site and materials, insurance, completion Liability
and site clearance, performance tests and acceptance, final
certificate, payment, termination and dispute resolution); 5.12 In general, the IChemE forms contain more exclusions of
● Guidance on compiling the contract and contractual issues; liability in favour of the Contractor than are usually found in
● Performance test flowcharts; and construction contracts. This reflects the potential liability for
● Various sample certificates: completion, take over, accept- significant costs in the event of failure, such as the daily cost of
ance, and final certificate. a power or process plant shutdown.

5.13 Although fitness for purpose obligations are imposed on


IChemE Red Book, 5th edition, 2013 the Contractor (Clause 3.4), the Contractor’s aggregate liability
5.06 As the more commonly used IChemE contract, the Red is capped at the amount specified in the contract (Clause 45.3).
Book is the focus of the commentary on the IChemE suite in this Clause 45.2 also operates as an ‘exclusive remedies’ clause for
chapter. This fixed price/lump sum contract has the contractor both parties whereby, except in the case of termination of the
assume the risk of additional costs, except in respect of speci- contract under Clause 44 (Termination for Contractor’s Default)
fied events. or repudiation, the liability of each party is limited to the dam-
ages and remedies expressly provided for in the contract. This
provision is, as one would expect, subject to liability imposed by
Co-operation and good faith consumer protection legislation and arising from personal injury
or death caused by the Contractor’s negligence.
5.07 The parties and the Project Manager are required to co-
operate with each other in discharging their respective obliga- IChemE Green Book, 4th edition, 2013
tions (Clause 2.1). Clause 2.2 requires the parties alone to ‘deal
fairly, openly and in good faith with each other’ and to disclose 5.14 This is a cost-reimbursable contract with no specified fixed
such information as the other party may reasonably need in order price and risk of cost escalation borne by the Employer. The
for each party to exercise their rights and perform their obliga- Contractor may claim certain costs incurred in performing the
tions under the contract. works, subject to specified exceptions.

IChemE Burgundy Book,


Testing and rectifcation
2nd edition, 2013
5.08 Inspection and testing is a theme of the IChemE forms. 5.15 This is a target cost contract with the usual ‘gain/pain share’
Clause 22 of the Red Book anticipates inspection and testing arrangements: the final cost above or below the target is shared
prior to installation of plant and materials. For this purpose, between the parties. The target cost can be set at the outset or
the Project Manager is to have access at all times to any place after the scope of work is better known.
where work under the contract is being carried out, including
off site manufacture. IChemE Yellow Book, 4th edition, 2013
5.09 Upon completion of any part of the Plant (as it is described in 5.16 These are the back-to-back subcontracts which correspond
the Specifications, and including software), further inspection and to the other contract forms and cater for the design, supply, site
tests are carried out under Clause 32 in accordance with the pre- construction, erection, and/or installation and testing of equip-
scribed quality assurance system (Schedule 6). The Plant may be ment relevant to the main contract plant.
taken over by Sections (Clause 33), and the Take Over Certificate
is issued after completion of any minor outstanding items. 6 IMechE/IET forms of contract
5.10 Where specific guarantees are given in respect of the perfor- 6.01 The Institution of Mechanical Engineers (‘IMechE’) and
mance of any Plant, performance tests are undertaken (Clause 35) the Institution of Engineering and Technology (‘IET’) publish
230 Other standard forms of building contract

a range of contract forms specifically for use where electrical GC/Works Suite
and mechanical work and consultancy is required in respect
of a construction project. They are used by utility companies 8.02 These very employer-friendly government forms are still
and suppliers of specialist electrical and mechanical plant, occasionally referred to in relation to public sector and engineer-
and are favoured for use in renewable energy projects in ing projects. However, its last major update was in 1998 (as the
the UK. government now favours NEC contracts), so it is substantially
out of date.
6.02 There are three model forms of contract conditions (MF/1,
MF/2, and MF/3), a form of appointment (MF/4), and three DOM/1 and DOM/2 sub-
commentaries which accompany them. The use of the three contracts (2018 Editions)
contract forms depends on the type of plant and equipment
involved, and whether design and installation is involved, as 8.03 These are domestic sub-contract forms which were updated
well as supply. in 2018, replacing the 2011 editions and ensuring their compat-
ibility with the JCT 2016 forms. DOM/1 is for use with the JCT
● The MF/1 (Revision 6) (2014 edition) is a form of contract Standard Building Contract 2016 (SBC 2016) and DOM/2 is for
for the design, supply, and installation of electrical, elec- use with the JCT Design and Build Contract 2016 (DB 2016).
tronic, and mechanical plant for both UK and international They are published in two parts: Articles of Agreement and Sub-
projects. Contract Conditions.
● The MF/2 (Revision 1) (1999 edition) form is for supply
only of electrical, electronic, or mechanical plant in both CIC Forms of Contract
UK and international projects. Revisions to take account of
1999 UK legislative changes are included by way of inserts 8.04 The Construction Industry Council (‘CIC’), which repre-
to the form. sents professional bodies, research organisations and specialist
● The MF/3 (Revision 1) (2001 edition) is a form of simple business associations in the construction industry, has a CIC
supply contract for electrical and mechanical goods in the Consultant Conditions – 2nd edition, November 2011 form.
UK. It publishes other forms, including a form of novation and col-
● The MF/4 (2003 edition) is a form of appointment for an lateral warranties. The consultant appointment is intended for
engineering consultant and is for use in connection with both use by architects and other consultants.
UK and international projects.
LOGIC Forms of Contract
7 ACE Forms of Contract 8.05 LOGIC (Leading Oil and Gas Industry Competitiveness)
is a part of Oil & Gas UK, which supports efficient working
7.01 In addition to managing the ICC forms of contract with practices in the United Kingdom Continental Shelf. LOGIC sup-
CECA, the ACE publishes a range of contracts, including ACE ports a suite of ten standard contract forms that are available for
2017. The main contracts in this suite are: use throughout the oil and gas industry. They are currently being
reviewed and updated.
● ACE Professional Services Agreement 2017 and vari-
ous useful Schedules of Services (e.g. Civil and Structural
Engineering, Mechanical Electrical, and Public Health 9 Building contracts in Scotland*
Engineering) for use with the Professional Appointment. It
is accompanied by the ACE Sub-Consultancy Agreement 9.01 The standard forms of building contract issued by the Joint
2017. Contracts Tribunal are drafted with the law of England and
● ACE Short Form 2015 appointment for use where there is Wales in mind. Where the works in question are to be carried
a clear description of the services. out in Scotland, those forms are unlikely to be appropriate, and
recourse should be had to the standard forms of building contract
The latest additions to the ACE suite are: which are issued by the Scottish Building Contracts Committee
(‘SBCC’). These make allowance for the different legal back-
● ACE Professional Services Agreement Advisory, ground in Scotland in the context of which the contract made
Investigatory and other Services 2019, which updates between the parties will have to operate. The currently applica-
and replaces ACE Agreement 2: Advisory, Investigatory ble suite of SBCC contracts is that which was drawn up to take
and Other Services: 2009. It adopts the same style and account of the 2009 Act and issued in 2011.
relevant ‘core’ clauses from the ACE Professional Services
Agreement 2017. For use in all UK jurisdictions, it is for 9.02 In framing its standard form contracts, the SBCC tries to
the appointment of a Consultant to undertake any type of keep as much of the material which appears in any given JCT con-
Services in the built and natural environment, except where tract in its Scottish counterpart as possible. In consequence, not
the Client appointing the Consultant intends to employ a only are most of the provisions of the Scottish Building Contract
Contractor to construct or install permanent works designed of 2011 common to that document and the 2011 JCT Standard
by the Consultant as part of the Services. Form of Building Contract, but authority drawn from English law
● ACE Professional Services Consumer Agreement 2019, on the parallel provisions of the co-relative JCT form is frequently
which replaces ACE Agreement 5 (Homeowner). It is for cited and founded on in cases arising out of SBCC ones. In this
the appointment of a Consultant by a ‘consumer’ client and section, it is proposed only to call attention to some of those areas
recognises current UK consumer legislation. of concern to the architect where the law of Scotland, as declared
in its courts, has produced either results different from those
obtaining in England in similar circumstances or differences in
8 CECA Forms of Contract emphasis on matters which end in a common result.

8.01 In addition to various policy publications and co-sponsor- 9.03 Previous SBCC forms sought to achieve a large measure
ship of the ICC forms, the CECA publishes a range of civil engi- of congruence between its forms and those of the JCT by the
neering industry specific forms of Subcontract and Schedules inclusion in the formal contract document, which took the place
of Dayworks. Some are intended for use with the ICC contract of the Articles of Agreement in the JCT regime, of a provision
forms. to the effect that the contract should be governed by the terms
of the chosen JCT form as those stood amended by such of the
Building contracts in Scotland* 231

JCT Amendments as the parties may have selected and by the Ltd 1997 SLT 10, a case decided in the context of very similar
provisions of the Scottish supplement appended to the contract provisions in the SBCC Management and Works Contracts. In
as Appendix I thereof. That method has now been abandoned. that case, the contract’s provisions were judicially stigmatised
The Scottish Building Contract is now a single document which as being ‘wholly ineffective to achieve what may have been the
repeats much of the parallel JCT wording. Its terminology is intended purpose of the draftsman’, because they did not serve
noticeably anglicised, but occasionally it resorts to Scottish to create a trust or other property right in specific assets of the
legal terminology. The Scottish amendment of the original JCT management contractor. At best, for the contractor, it can only
drafting is now less obvious, but traces of it can still easily be make use of the clause to sue the employer for specific imple-
seen in parts of the contract such as the clause of consent to ment of the obligation to set up a trust in the retention monies
registration for preservation and execution which would be quite (see Fairclough Scotland Ltd v Jamaica Street Ltd, 30 April
meaningless in an English contract, but in Scotland is capable of 1992, unreported) – and that remedy is apt to be stultified if the
producing results nearly as dramatic as its name would suggest. employer becomes insolvent in the interim, or, pleading dispute
Of course, there is no rule of law which prevents the parties from about his right to set off monies, insists on putting the matter to
making amendments of their own to the terms of the SBCC con- arbitration or adjudication.
tract, and that is frequently done. Architects contemplating such
alterations should, however, consider whether, in the context of 9.07 There are also other areas (of perhaps more immediate con-
Scots law, those changes will have the effect which they may cern to the architect than the trust obligations of the employer in
know from experience they would have in England and Wales. relation to retention monies) in which the Scottish courts have
taken a different approach from that followed south of the bor-
9.04 To enable the consent to registration clause to have effect, der. A significant example arises in relation to the hierarchy pro-
it is necessary to ensure that the contract is formally executed in visions of the JCT Standard Form Building Contract, whereby
the correct way. It is therefore necessary for an architect oversee- any provisions in the bills of quantities inconsistent with those
ing the parties’ entry into a building contract in the standard form of the JCT standard form are subordinated to that form. Of late
terms to have regard to the requirements of Scots law regarding years, a practice appears to have grown up in Scotland whereby
the execution of a formal self-proving contract, and ensure that the formal contract is not executed, but the contract is allowed
they are complied with, not least through the completion of the to rest on the bills of quantities and the form of lender referring
formal testing clause, which is called for after the words ‘in thereto, duly accepted, which incorporates the terms of the JCT
witness whereof’, which appear at the end of the contract, just form, including the hierarchy clause. The bills will frequently
before the schedule thereto. Those requirements vary depending amend the Conditions heavily, and, with a view to circumvent-
on the status of the executing party, but will, for the most part, be ing the hierarchy clause, will preface those amendments with a
found in the Requirements of Writing (Scotland) Act 1995. In the term to the effect that ‘Notwithstanding the provisions of [the
newly re-named ‘Articles of Agreement’ will be found the clauses hierarchy clause] of the said Conditions, the amendments and
which declare the governing law of the contract and the chosen modifications detailed hereunder shall apply’.
mode of dispute resolution. The pre-printed text of the Articles The perils of adopting this practice were highlighted in Barry
is in conditional form, the critical condition being whether the D. Trentham Ltd v McNeil 1996 SLT 202, where that term was
type of dispute resolution procedure selected by the parties in implicitly held to be ineffective to prevent the hierarchy clause
the Contract Particulars makes the clause being examined opera- from operating to strike down any inconsistent clause in the
tive in the case of the particular contract which the parties have bills, albeit that it might be quite evident that all the special
entered. It is therefore essential to read the Articles in association clauses of the contract drawn with the particular project in mind
with the Contract Particulars, as the latter have been completed were to be found with bills. It is suggested that, in the light of
by the parties in order to see what selection has been made and the Trentham case, and the prior decision which it followed, it
which clauses apply as a result in the contract in view. It should be would be unwise for an architect who wished to amend the JCT
noted in this connection that, unlike some previous standard form or SBCC Forms to carry out that exercise in the contract bills:
contracts, under the 2011 form, the ‘default’ position ,which will the better course would seem to be to secure the execution of
obtain if contrary entries are not made in the Contract Particulars, a formal contract in amended terms, and to number among the
is that disputes will be resolved by court proceedings. A conse- amendments the necessary changes to the hierarchy clause itself.
quence of this reversal from the previous dispensation is that
there now appears an express prorogation of the jurisdiction of 9.08 Certification, too, is an area in which the Scottish courts
‘the Scottish courts’, though, curiously, that prorogation does not have not always taken the same line as their English counter-
take the form of an exclusive jurisdiction clause, thus opening the parts. As in England, architects, when acting as certifier, are
way to disputes about the convenient forum in which to sue when regarded as exercising a quasi-judicial office in which they
parties subject to English jurisdiction are involved (cf., Babcock should resist interference from the employer. They are expected
Marine (Clyde) Ltd v HS Barrier Coatings Ltd [2019] B.L.R. to take care not to exceed their jurisdiction in that office and to
495). It is thought that the designation of the ‘Scottish courts’ avoid issuing certificates which they have not been given com-
means that only in cases with a value above the privative limit petence by the parties’ contract to issue (cf. Amec Mining Ltd
of the sheriff court is recourse to the Court of Session competent, v The Scottish Coal Company Ltd, 6 August 2003, unreported).
but in any dispute, any sheriff court in Scotland can be selected If they do issue such certificates, they will be invalid. On the
as the forum. Lastly, the Articles provide that the contract will be other hand, the Court of Session has made it clear that in cases
governed by the law of Scotland. where an adjudicator has determined a matter relevant to some
task which an architect has to perform, or to a decision which
9.05 It should not be assumed from this that all differences he or she has to take in the course of the relevant certifying
between English and Scottish law have been accounted for in functions, the architect cannot disagree with the adjudicator, but
the SBCC Forms: they have not. One major area of difficulty must rather give effect to the determination, albeit that, if new
which arises in Scotland with the terms of a JCT form, which information has come to light since the date of the determina-
are unamended by the counterpart SBCC Form, concerns the tion, the architect is entitled to make use of that information in
trust fund sought to be created over the contractual retention updating the effects of the adjudicator’s decision. If, therefore,
monies by Clause 4.18 of the 2011 Contract. Whatever may be an adjudicator has decided that a given sum is payable in respect
the position in England, these provisions are not, in Scotland, of work in an interim certificate, the architect is bound by that
sufficient to create a trust over the retention monies in favour decision until such time as it may be overridden by court action
of the contractor on which he can rely in the event of the insol- or arbitration. This holds true not only in relation to subsequent
vency of the employer. The practical failure of these provisions interim payment certificates, but in relation to the issue of
from the point of view of the contractor was graphically illus- the final certificate as well (Castle Inns (Stirling) Ltd v Clark
trated by the decision in Balfour Beatty-Ltd v Britannia Life Contracts Ltd 2006 S.C.L.R. 663).
232 Other standard forms of building contract

A further complication about final certificates is also high- dealing with a six-year limitation period. It should be recalled
lighted by the same case. An adjudicator’s award which is that, in Scotland, the operative doctrine in the building con-
issued after the final certificate has itself been issued becomes tract context will be prescription rather than limitation, and
final under clause 1.9.4 of the 2011 form if it has not been chal- more importantly, that prescription strikes after five years in
lenged within 28 days of its issue. Under clause 1.9.3, a final a breach of contract or implement of contract case, not six.
certificate does not become conclusive evidence for 60 days Complexities can attend the ascertainment of the date when the
after its issue. In consequence, a final certificate can, in effect, period of prescription commenced running. Recent decisions
be amended by a subsequent contrary adjudicator’s decision on of the courts in building cases, particularly those concerned
a matter covered by the certificate, because the 28 days elapse with defects noticed long after the completion of the building,
without the adjudicator’s decision being challenged and thereby have come as an unpleasant surprise to building owners, most
becoming final before the 60 days have run their course. In such notably a Supreme Court case which overruled 25 years’ worth
a case, a court challenge to the final certificate by the victor in of contrary Scottish cases criticised as having been unduly
the adjudication made before the elapse of the 60 days is bound generous to building owners. The full implications of this are
to succeed at least to the extent of securing the re-writing of still being worked out, but the decision in Midlothian Council v
the final certificate in so far as that is necessary to cause the Bracewell Stirling [2019] CSOH 29 (a professional negligence
certificate to reflect the adjudicator’s decision. case about defects), in which time was held to have begun to
run when the contractor was paid an interim payment can fairly
9.09 It also behoves the architect to pay close attention to the be said to have caused consternation among building owners.
insurance provisions of the JCT contracts. In Clauses 6.7–6.13 of, Given the potential consequential effects of that case on rights
and schedule Part 3 to, the 1998 Standard Form, provisions are of contribution when third party notices are raised by members
made as to the allocation of responsibilities to insure the works of the professional team or contractors, that consternation is
and existing structures as between the employer and contractor. likely to spread throughout the industry to the extent that it
Over the past ten years or so, the predecessors of these provisions has done work in Scotland which may become the subject of a
have given rise to not a little litigation in Scotland, including defects action. Such importance has the issue of prescription,
two cases which reached the House of Lords. The net effect of assumed that the safest course for the architect concerned about
that litigation is in certain circumstances to prevent the employer the possibility of the issue arising in connection with a project
from suing the contractor or a sub-contractor for damage wrought is promptly to seek legal advice in light of the circumstances
by the latter either to the works themselves or to the building in which obtain in the individual case in question. It is always
which the works are taking place. In light of recent decisions in necessary to be alive to the risk that valuable legal rights may
England concerning the liability of a project manager for failing be lost through prescription. It should be remembered that the
to check that the appropriate insurances were in place, it is sug- ways in which prescription may be stopped from running are
gested that the employer’s architect in Scotland who fails so to very limited – acts amounting to a ‘relevant claim’ or ‘relevant
check is likely to be at risk of liability to the client if the applica- acknowledgement’ within the meaning of the Prescription and
tion in the circumstances of the case in question of the above- Limitation (Scotland) Act 1973 are called for. A reference to
mentioned House of Lords cases restricting the scope of the duty adjudication, it is thought, is not a ‘relevant claim’. The safest
of care owed to the employer by the contractor or sub-contractor course is usually simply to sue in court, if needs be, by way
precludes that client from recovering his losses from the contrac- of recourse to the declarator ad ante procedure, for, saving one
tor or sub-contractor the fault of which had brought them about. rather unlikely case, an action served on the person against
whom the claim is asserted is always a ‘relevant claim’.
9.10 Time-bar is a further matter which is prone to give rise to
difficulty, particularly when the client is English and used to *This section was written by Robert Howie QC.
21
Contractor and sub-contractor collateral
warranties and third party rights
MATTHEW COCKLIN

1 The privity rule parties to the underlying contract, including the party providing
services (e.g. an architect) or carrying out work (e.g. a contrac-
1.01 There is a general common law rule, known as the ‘privity tor and sub-contractor) and a third party who has an interest
rule’ or ‘privity of contract’, that a contract may only be enforced in the proper performance of that underlying contract (e.g. the
by the parties to that contract. The privity rule can cause particular employer, purchasers, tenants, and funders).
problems in relation to construction work because, often, the party
who suffers loss and damage caused by defects will not have a 2.03 Like any contract, a collateral warranty must be signed
contractual link with the perpetrator of the defect. For example: or executed by the parties. The person giving the collateral
warranty is known as ‘the warrantor’. The person to whom the
(a) if a contractor employs a specialist sub-contractor, only the collateral warranty is given is known as ‘the beneficiary’. Under
contractor will have a contractual right of recourse against the terms of a collateral warranty, the warrantor warrants to the
the sub-contractor, not the building owner; beneficiary that it has complied with its professional appoint-
(b) if a contractor is employed to design and build a devel- ment, building contract, or sub-contract, as applicable. Whilst
opment, only the design and build contractor will have a the collateral warranty is collateral to such contracts, it is a
contractual right of recourse against the architect, not the contract in its own right (like any other contract).
building owner; and
(c) if a developer employs a contractor to build a block of flats, 2.04 Collateral warranties in favour of third parties, such as
only the developer will have a contractual right of recourse funders, purchasers, and tenants, tend to be bespoke, usually to
against the building contractor under the building contract, not suit the requirements of particular employers. As they reallocate
the purchasers, or tenants of flats, or the developer’s funder. risk among the parties, they are often the subject of extensive
negotiation. Non-standard warranties can vary greatly in scope
In each example, the law will treat the party suffering the loss and complexity, with some drafted to be more favourable to ben-
and damage as a third party. The first two examples can be eficiaries and some to warrantors. They can also be known by a
particularly problematic if the contractor becomes insolvent. In variety of names such as ‘Duty of Care Agreement’, or simply
that case, a claim for damages may only succeed if the employer ‘Warranty Agreement’, and can be drafted as deeds or simple
can establish a contractual link with the sub-contractor and/or contract letter form agreements. As tailor-made warranties can
professional team employed by the insolvent contractor. be very diverse, and negotiating them can lead to extensive argu-
ment before a development is begun, a number of standard forms
1.02 These problems can, however, be surmounted: a collat- have been drafted. The Joint Contracts Tribunal (‘JCT’) publishes
eral warranty and the Contracts (Rights of Third Parties) Act standard form of collateral warranties for use with the JCT suite
1999 are the principal means of overcoming the privity rule. of contracts. Section 6 of this chapter considers the 2016 suite.
These are generally encountered by architects in two scenarios:
first, architects are frequently asked to provide collateral warran- 3 Contracts (Rights of Third
ties/third party rights in relation to their own professional ser-
vices. This is considered in further detail in Chapter 31. Second, Parties) Act 1999
architects may be expected to advise their clients and ensure that
all necessary collateral warranties/third party rights are obtained 3.01 The Contracts (Rights of Third Parties) Act 1999 came into
from other professionals, contractors, and sub-contractors. This force in May 2000. The Act confers on a third party ‘a right to
chapter will focus on this second scenario, having first generally enforce a term of the contract’ where either the contract contains
looked at collateral warranties/third party rights. an express term to that effect or where the contract purports to con-
fer a benefit on that third party. In both cases, the third party must
be expressly identified in the contract by name, class, or descrip-
2 What is a collateral warranty? tion, but need not be in existence at the time of the contract. The
third party must, however, be capable of being ascertained with
2.01 A collateral warranty is a separate contract, which runs along- certainty. Accordingly, a general reference to ‘purchasers of the
side, and is usually supplemental to, another contract. Usually, a building when completed’ would be enforceable.
collateral warranty creates a direct contractual link, or relation-
ship, between two parties where none would otherwise exist. 3.02 A ‘right to enforce a term of the contract’ means the right
to all of the remedies which would have been available to a third
2.02 Collateral warranties are extensively used on construction party through the courts if it had been a party to the contract,
projects. They take the form of a tripartite contract between the but subject to the terms of the contract, including any relevant
233
234 Contractor and sub-contractor collateral warranties

exclusions of liability or restrictions in the contract. In other involved in the construction process were held to owe fairly wide
words, contractual damages are recoverable but the parties can duties of care to all those who might reasonably be expected to
agree that recovery is excluded or capped. be affected by their negligent actions. This duty of care protected
tenants and purchasers of developments. Therefore, parties who
3.03 The Act also states that where a third party has a right to needed to be protected from negligent and defective building
enforce a term of a contract, the parties may not, without the design or work were advised that they had some legal protection
consent of that party, ‘rescind the contract, or vary it in such a under the tort of negligence without needing any direct contrac-
way as to extinguish or alter his entitlement under that right’ in tual link with the builders and designers.
certain circumstances. This can be excluded by agreement, or by
the courts, or the arbitrator in defined circumstances. 4.04 The cases of D & F Estates Ltd and Others v The Church
3.04 The third party’s rights will be subject to all defences and Commissioners of England and Others [1988] 49 BLR 1,
set-offs that would have been available to the contracting party Murphy v Brentwood District Council [1991] 1 AC 398,
had the third party been a party to the original contract, unless and other subsequent authorities, dramatically altered the
the parties provide otherwise in the contract. established legal position relating to defective buildings and
negligence, so that a contractor would not be liable in tort to
3.05 This legislation means that there is no need for separate col- successive owners of a building (i.e. those with no contractual
lateral warranties in favour of funders, purchasers, and tenants. link to the contractor) for any defects in the building itself. It
The relevant rights can be granted by a clause included in the was held that the cost of rectifying defects was economic loss
original consultancy agreement or building contract. Those rights and that this type of loss was not ordinarily recoverable in the
can be subject to exclusions and restrictions. In other words, tort of negligence. The builder would only be liable in tort if
the contractual damages which would otherwise be recoverable any defect caused personal injury or damage to other property
by the third party potentially include losses other than the cost (i.e. something other than the building). The principles govern-
of repair, but these can be subject to agreements that recovery ing liabilities in tort are discussed in more detail in Chapter 3.
is excluded or capped, that it is subject to ‘net contribution
clauses’, and so on. Sub-contracts, too, can include a clause 4.05 The decisions in D & F Estates and Murphy left third par-
enabling the employer to pursue the sub-contractor directly. ties legally exposed. As a result, collateral warranties became
increasingly important as the only means of protection for third
3.06 The initial reaction of most of the contract producing bodies parties who were otherwise prevented from recovering losses
to the Act was to exclude any third party rights wholesale. This suffered due to defective building work. It has now become
sweeping approach was eventually superseded by a more careful common practice for employers, purchasers, tenants, funders,
and reflective use of the benefits that the Act has to offer. It is freeholders, and others to require contractors, sub-contractors,
now increasingly accepted that third party rights are a simpler and professional consultants with whom they do not have a con-
and more straightforward way of vesting rights in purchasers and tractual link to provide collateral warranties or, as noted above,
tenants avoiding the extensive problems created by the need to third party rights pursuant to the Act, to enable them to recover
secure the execution of collateral warranties by parties who may directly for any defects and other losses arising from their work.
have finished their work or with whom the employer may be in
dispute. In contrast, banks’ and funders’ lawyers are more dubious 4.06 Although more recent decisions of the House of Lords (St
about the use of third party rights in place of collateral warranties Martins Property Corporation Ltd v Sir Robert McAlpine Ltd
because of the provision of ‘step-in rights’ where obligations and [1994] AC 85) and of the Court of Appeal (Darlington Borough
not just rights are imposed on the third party bank or funder in Council v Wiltshier Northern Ltd [1995] 1 WLR 68 and Sir
certain circumstances. Accordingly, it is still common to see col- Alfred McAlpine Ltd v Panatown Ltd [1998] 88 BLR 67) may
lateral warranties in their favour. For purchasers and tenants, both enable contractual claims to be pursued on behalf of subse-
methods of granting them rights are in common use, although the quent purchasers of a defective building (even though the pur-
rights granted are essentially the same under both routes. chaser has no contractual link with the contractor), the extent
of the comfort afforded by these decisions is so imprecise that
3.07 The JCT 2016 suite of contracts permits the warrantor to
employers are usually still advised to ask for collateral warran-
either confer third party rights in accordance with the Act (the
ties on behalf of purchasers, tenants, and funders.
rights being identified in a schedule to the contract) or execute
collateral warranties.
4.07 In addition, the courts have tried to avoid the draconian
effects of the decisions in D & F Estates and Murphy by further
4 Why are collateral warranties/ developing the law of negligent misstatement under which profes-
sionals who give negligent advice can still be held liable for pure
third party rights so important? economic loss even to persons with whom they have no contract.
The leading authority is Hedley Byrne & Co v Heller and Partners
4.01 The legal doctrine of privity of contract means that remedies [1964] AC 465, and the doctrine has been extended in cases such
for the improper performance of obligations under a contract are as Henderson v Merrett Syndicates Ltd [1995] 2 AC 145.
– subject to the existence of collateral warranties and third party
rights pursuant to the Act – limited to the parties to that contract.
4.02 It was a desire to circumvent the legal problems that stem
5 Who needs the beneft
from the law of privity of contract that led to the development of of collateral warranties/
the tort of negligence, as set out in the famous case of Donoghue third party rights?
v Stevenson [1932] AC 562. That case established the ‘neigh-
bour’ principle, which obliges a party to take care to avoid acts
which it can reasonably foresee are likely to injure its neighbour. Employers
‘Neighbours’ were defined as being those so closely affected by a 5.01 Employers require collateral warranties/third party rights
party’s act that that party ought to have had them in contemplation from the contracting industry in their favour in two different
when carrying out the act in question. ‘Injury’ initially meant phys- circumstances. They are:
ical harm, but the courts came to extend it to financial loss. A duty
of care in negligence is owed only to neighbours, but there is no (a) to supplement and reinforce their direct contractual rights. For
need for neighbours to be contractually linked to create a liability. example, the employer may seek collateral warranties from
certain sub-contractors and suppliers in respect of materials
4.03 For many years, the tort of negligence applied to cases of and workmanship supplied or carried out by them, even though
defective buildings. The leading case was Anns v Merton London the employer has contractual rights against the main contractor.
Borough Council [1978] AC 728. Builders, architects, and others The main advantage to the employer of obtaining collateral
JCT 2016: who should provide collateral warranties/third party rights? 235

warranties in such circumstances is that if such workmanship dependent on the consent of a neighbouring landowner, that
or materials were to prove defective, or the main contractor neighbouring landowner may require a collateral warranty from
becomes insolvent, proceedings could be brought directly those involved in the construction process to ensure that, should
against the party responsible in addition/alternative to the con- any damage occur to the neighbour’s property or should the neigh-
tractor. Whether this supplemental protection is required will bour’s business be disrupted as a result of the works, the neigh-
be a matter for the employer to decide on a project-by-project bour would be able to recover from those responsible any costs
basis. As demonstrated by the demise of Carillion in 2018, no incurred in repairing the damage. Collateral warranties may also
contractor is immune from insolvency; and be required where a developer lets a development to a tenant who
(b) where, but for the collateral warranty, the employer may carries out fitting-out works. In such circumstances, the developer
have no enforceable contractual right for the design and may require a collateral warranty from the tenant’s designer and
construction work. This is most commonly the case where fit-out contractor to ensure such works are performed correctly.
specialist sub-contractors carry out design work in connec-
tion with the development, but the main contractor has no
responsibility for such design. Equally, an employer would 6 JCT 2016: who should
also require collateral warranties if management contract-
ing is used to procure the development. Otherwise, the
provide collateral warranties/
employer may be left without any remedy, since the man- third party rights?
agement contractor’s liability for works contractors’ short-
comings is limited by the terms of the management contract. 6.01 Exactly which contractor or sub-contractor should provide
In this situation, there is a much greater obligation on the warranties depends upon the form of contractual procurement
architect to ensure that the correct collateral warranties are used. The Joint Contract Tribunal (JCT) publishes a suite of
in place. If they are not, the employer may be left without building contracts and related agreements for the forms of pro-
any contractual remedy at all in respect of parts of the curement most commonly used in the commercial development
design of the development where the architect has agreed sector in the United Kingdom. The current suite of contracts is
that such design will be carried out by the sub-contractor. the 2016 suite, principally comprising:

Purchasers (a) Standard Building Contract: this is published in three


versions: With Quantities (Q), Without Quantities (XQ),
5.02 Purchasers cannot generally sue vendors for defects in the and With Approximate Quantities (AQ). The contract is
development in the absence of express contractual undertakings intended for larger projects where most of the works have
from the vendor. A purchaser from an original employer would already been designed or detailed by the Employer and the
have no direct contractual link with those involved in the con- Contractor is provided with drawings and either bills of
struction process unless the benefits of the construction contracts quantities (Q and AQ) or a specification or works schedules
and the various consultancy agreements were assigned to the (XQ) to define the quantity and quality of the work.
vendor. Usually, this will not be possible without the prior consent (b) Intermediate Contract: this is published in two versions:
of the contractor or consultants. Sometimes, the building contract IC where the Contractor is not required to design any of
may be amended so that the contractor is obliged to consent to the the Works and ICD (with contractor’s design) where the
assignment in advance of it. Purchasers from original developers Contractor is required to design part(s) of the works. The
were specially mentioned in D & F Estates and Murphy as having contract is intended for use where:
no rights in negligence against contractors for any defects aris- (i) the proposed works are simple and involve normal, rec-
ing in any building purchased. As a result, purchasers will often ognised basic industry trades and skills, without build-
require collateral warranties to ensure that they are protected. ing service installations of a complex nature or other
specialist work; and
Tenants (ii) the works, or the majority of the works, have been
5.03 A prospective tenant of a new development may require designed or detailed by the Employer with drawings and
collateral warranties if the lease is to be granted on a full repair- bills of quantities, a specification or work schedule to
ing basis, so that the landlord accepts no liability for defects in adequately define the quantity and quality of the work.
the building and the tenant becomes liable to carry out repairs (c) Design and Build Contract: This is intended for use where
at its own cost. With full repairing leases it is desirable that the the Employer has defined its requirements and the Contractor
tenant obtains collateral warranties from those involved in the is required to design the works in accordance with the
construction process in order that the tenant can recover, via a Employer’s Requirements and then carry out the works.
direct contractual link, repair costs from those responsible. Even (d) Prime Cost Building Contract: this is a cost-reimbursable
where the landlord does accept some liability for defects in the contract. It is intended for use where an early start is
building, tenants will usually also want a collateral warranty required but it is not possible, in the time available, to
from the design and construction team in order to protect them- define the extent and nature of the work with sufficient
selves against insolvency of the landlord developers. accuracy to obtain a firm lump sum price or use a remeas-
urement contract. It was originally intended for projects
Funders involving uncertainties. For example, projects involving
repair or reinstatement after fire or other damage to existing
5.04 Where a bank or institution provides finance for a develop- structures and for alterations and repairs to old buildings.
ment and takes a legal charge over the property to be developed, (e) Construction Management Contract: this is intended for
the funder will be concerned that on completion, it is free of use where the Employer wishes to utilise the services of a
defects and is of a sufficient quality and value to provide adequate Construction Manager to manage the procurement of a pro-
security for the loan. Without a collateral warranty, a funder will ject. The Construction Manager provides a consultancy and
have no direct contractual relationship with any of those involved management service including the provision of site facilities
in the design and construction of the development. A funder will and the negotiation and contract administration of Trade
usually want any collateral warranty to contain ‘step-in’ rights Contracts. A professional team designs the works and acts as
so that, should the employer/borrower default under the funding cost consultant whilst the construction work is undertaken by
agreement, or act in such a way that would enable the contractor trade contractors which each enter into contracts direct with
to terminate the building contract, the funder could ‘step-in’ and the Employer. The Construction Manager is not a party to the
take over the completion of the development. appointments of the professional team or the Trade Contracts.
(f) Management Building Contract: this is intended for
Other third parties large scale projects that require an early start on site where
5.05 Collateral warranties may be required in a number of general designs describing the scope of work have been
other circumstances. For instance, where development work is prepared on behalf of the Employer but where:
236 Contractor and sub-contractor collateral warranties

(iii)detailed design is still required, some of which may be The contracts contemplate that the collateral warranties will
of a sophisticated or innovative nature, requiring propri- take the particular forms published by the JCT. As an alterna-
etary systems or components designed by specialists; and tive to collateral warranties, the contracts each contain, where
(iv) it will not be possible to prepare full design information selected, third party rights, which are provided in the schedules
before construction work commences. to the respective contracts. For example, the Standard Building
Contract provides third party rights for Funders and Purchasers
The Management Contractor manages the project for a fee and and Tenants whereas the Standard Building Sub-Contract addi-
provides the necessary site facilities. All construction work is tionally provides third party rights for the Employer.
undertaken by specialist contractors, which are employed by the
Management Contractor pursuant to sub-contracts.
6.03 The contract forms detailed above can be illustrated dia-
6.02 Each form of contract in the JCT 2016 suite provides for
grammatically as follows:
collateral warranties or third party rights pursuant to the Act.

Standard Building Contract/Intermediate Contracts/Prime Cost Contract

Purchaser or
Employer Funder
Tenant

Professional
Team

Contractor

Sub-
Contractors

Key

Building contracts, sub-contracts and professional appointments

Collateral warranties/third party rights to building contracts and sub-contracts (considered in detail in
this chapter)

Collateral warranties/third party rights to professional appointments (considered in detail in Chapter


31)

Design and Build

Purchaser or
Employer Funder
Tenant

Contractor

Professional Sub-
Team Contractors

Key

Building contracts, sub-contracts and professional appointments

Collateral warranties/third party rights to building contracts and sub-contracts (considered in detail in
this chapter)

Collateral warranties/third party rights to professional appointments (considered in detail in Chapter


31)
JCT 2016: who should provide collateral warranties/third party rights? 237

Construction Management Contracting

Purchaser or
Employer Funder
Tenant

Construction
Manager

Trade
Contractors

Professional
Team

Key

Building contracts, sub-contracts and professional appointments

Collateral warranties/third party rights to building contracts and sub-contracts (considered in detail in
this chapter)

Collateral warranties/third party rights to professional appointments (considered in detail in Chapter


31)

Management Contracting

Purchaser or
Employer Funder
Tenant

Professional
Team

Management
Contractor

Works
Contractors

Key

Building contracts, sub-contracts and professional appointments

Collateral warranties/third party rights to building contracts and sub-contracts (considered in detail in
this chapter)

Collateral warranties/third party rights to professional appointments (considered in detail in Chapter


31)
UNDERLYING CONTRACT
238

SBC/Q SBC/ IC ICD DB PCC CM/A CM/TC MC MWC


XQ SBC/AQ

COLLATERAL WARRANTY Standard Intermediate Design Prime Cost Construction Construction Management Management Works
Building Building Contract and Build Building Management Management Trade Building Contract Contract
Contract and Intermediate Contract Contract Appointment Contract
Building Contract with
Contractor’s Design

CWa/F Contractor Collateral ✔ ✔ ✔ ✔


Warranty for a Funder
CWa/P&T Contractor Collateral ✔ ✔ ✔ ✔
Warranty for a Purchaser
or Tenant
SCWa/E Sub-Contractor Collateral ✔ ✔ ✔ ✔
Warranty for an
Employer
SCWa/F Sub-Contractor Collateral ✔ ✔ ✔ ✔
Contractor and sub-contractor collateral warranties

Warranty for a Funder


SCWa/P&T Sub-Contractor Collateral ✔ ✔ ✔ ✔
Warranty for a Purchaser
or Tenant
CMWa/F Construction Manager ✔
Collateral Warranty for a
Funder
CMWa/P&T Construction Manager ✔
Collateral Warranty for a
Purchaser or Tenant
TCWa/F Trade Contractor ✔
Collateral Warranty for a
Funder
TCWa/P&T Trade Contractor ✔
Collateral Warranty for a
Purchaser or Tenant
MCWa/F Management Contractor ✔
Collateral Warranty for a
Funder
MCWa/P&T Management Contractor ✔
Collateral Warranty for a
Purchaser or Tenant
WCWa/F Works Contractor ✔
Collateral Warranty for a
Funder
WCWa/P&T Works Contractor ✔
Collateral Warranty for a
Purchaser or Tenant
MCWC/E Management Works ✔
Contractor/Employer
Agreement
JCT 2016: key clauses of Contractor collateral warranties 239

7 JCT 2016: key clauses of beneficiaries. To achieve this the words from ‘In the event of
breach …’ in Clause 1.1 to the end of the Clause, including both
Contractor collateral warranties Clauses 1.1.1 and 1.1.2, should be deleted, as should clause 1.2.
7.01 This section comments on the Standard Forms of Contractor
collateral warranty: CWa/P&T and CWa/F. Joint liability and contribution clauses
7.07 A further limitation on the beneficiary’s right to claim
The warranty itself damages from the Contractor applies in the case where the
7.02 Most forms of warranty start by imposing a contractual Contractor is not the only person responsible for the defect.
obligation on the warrantor in favour of the beneficiary. Such a CWa/P&T contains a net contribution clause, which limits the
warranty in a contractor collateral warranty usually refers to the liability of the warrantor to the proportion of the costs incurred
terms of the main contract. Clause 1 of CWa/P&T states: by the beneficiary which it would be fair for it to pay, having
regard to its own and the other parties’ share of the blame. The
The Contractor warrants as at and with effect from practical relevant clause is Clause 1.3, which applies only where so stated
completion of the Works … that he has carried out the Works in the Warranty Particulars and which states:
… in accordance with the Building Contract.
.3 the Contractor’s liability to a Purchaser or Tenant under
7.03 This wording reflects the fact that such warranties are this Agreement shall be limited to the proportion of the
intended to be given or at least to be enforced after practical Purchaser’s or Tenant’s losses which it would be just and
completion. Under this wording, the Contractor’s liability under equitable to require the Contractor to pay having regard to
the warranty to the third party will be the same as its obligations the extent of the Contractor’s responsibility for the same, on
under the Building Contract to the Employer. The Contractor’s the following assumptions that the Consultant(s) (as defined
obligations under Standard Building Contract, Design and Build in the Building Contract):
Contract, and Intermediate Building Contract (IFC) are similar
.1 has or have provided contractual undertakings to the
in that the contractor has an absolute duty to complete the con-
Purchaser or Tenant as regards the performance of his
tract works in accordance with the contract and specification.
or their services in connection with the Works in accord-
This position contrasts with a consultant’s obligations under
ance with the terms of his or their respective consultancy
consultancy appointments and warranties, which are usually
agreements and that there are no limitations on liability
limited to a duty to exercise reasonable skill and care in the
as between the Consultant and the Employer in the con-
performance of his duties.
sultancy agreement(s); and
.2 have paid to the Purchaser or Tenant such proportion of
the Purchaser’s or Tenant’s losses as it would be just and
Economic and consequential loss equitable for them to pay having regard to the extent of
7.04 Under the law of negligence, losses which are deemed to their responsibility for the Purchaser’s or Tenant’s losses.
be purely economic are generally not recoverable, as noted in
7.08 This clause operates by ‘assuming’ that the Consultant(s)
Section 4 above. Under contract law, however, such ‘economic’
and Contractor have a legal liability to the beneficiary, even if
loss can be recoverable. Therefore, if an employer suffers a
the beneficiary has not obtained collateral warranties from those
loss of profit, a loss of rent revenue, or a diminution in value
other parties. The purpose of the clause is to entitle the court to
in his property due to a breach of contract by a contractor, he
calculate what percentage of the blame should be apportioned
can claim such loss from the contractor in contract. Contractors
to those other parties. This is a calculation which the court is
have resisted the imposition of such all-embracing liability in
used to making under the Civil Liability (Contribution) Act
collateral warranties.
1978 where, for instance, two drivers negligently contribute to
causing the same crash. Clause 1.3 is simply intended to cap
7.05 As a result of this, Clause 1.1 of CWa/P&T (but not CWa/F)
the damages for which the Contractor is liable. It is a significant
contains two possible alternative drafting options that require
limitation on the value to a beneficiary of the CWa warranties.
amendment or deletion from the text of the printed form in order
to select the option which is to apply. The options are as follows:
Deleterious material clauses
(a) to restrict the Contractor’s liability to reasonable costs of
repair, renewal and/or reinstatement of the Works only to 7.09 Most forms of collateral warranty to funders, purchasers,
the exclusion of all other losses suffered or incurred by the and tenants contain provisions related to excluded materials.
beneficiary as a result of the Contractor’s breach of Clause Clause 2 of the CWa warranties contain such provisions whereby
1. If this is to be adopted, then the Warranty Particulars in the Contractor warrants that materials will not be used except in
the main JCT Contract need to state that Clause 1.1.2 does accordance with good practice guidelines:
not apply. Clause 1.2 then provides that the contractor is
not liable for any losses incurred other than repair costs as he has not used and will not use materials in the Works other
referred to in Clause 1.1.1; or than in accordance with the guidelines contained in the edition
(b) to make the Contractor liable for the costs of repair incurred of the publication ‘Good Practice in Selection of Construction
by the beneficiary and (subject to cap) such other liability Materials’ (British Council for Offices) current at the date of
for damages which would otherwise be recoverable by the the Building Contract.
beneficiary in accordance with common law principles
including loss of profit, loss of rent revenue, etc., as outlined Step-in rights
above to a maximum amount in respect of each breach of
Clause 1. If this option is to be adopted, then the warranty 7.10 Where a warranty is to be provided to a funder or fund-
particulars need to state that Clause 1.1.2 does apply and ing institution, it is common for the warranty to contain step-in
the amount of the cap needs to be stated. rights. Clauses 5–7 of CWa/F enable the Funder to step into the
Employer’s shoes, should the Employer behave in such a way as
7.06 The CWa/P&T does not contemplate making the Contractor would enable the Contractor to terminate the Building Contract.
responsible for costs of repair and in addition to impose fur- This is most likely to occur if the Employer encounters financial
ther unlimited liability for damages for breach of contract, difficulties and is unable to pay the Contractor. Step-in provi-
but without a cap. It is, however, the preferred route for most sions such as these permit the fund to take on the duties, rights,
240 Contractor and sub-contractor collateral warranties

and responsibilities of the Employer. Again, the effect of these Contract. For this reason, Clause 13 appears in CWa/F (Clause
provisions is elaborated in Section 5. 9 in CWa/P&T) which states that:

the Contractor shall have no liability under this Agreement for


Insurance clauses delay under the Building Contract unless and until the Funder
7.11 Contractors’ warranties will not usually contain insurance serves notice pursuant to Clause 5 or Clause 6.4 [the ‘step-in’
clauses unless the contractor is to be responsible for some ele- provisions]. For the avoidance of doubt the Contractor shall
ments of the design of the works. Where such design obliga- not be required to pay damages in respect of the period of
tions exist, they are often required to be backed by professional delay where the same has been paid to or deducted by the
indemnity insurance. The relevant clause of the CWa warranties Employer.
is Clause 5 in CWa/P&T and Clause 9 in CWa/F.
This provision is acceptable to most funders, purchasers, and
7.12 It is important to ensure that the insurance will be avail- tenants, if properly advised.
able up to the limit stated in the Warranty Particulars for any
one claim, rather than up to that limit for all claims unless the Assignment
Warranty Particulars provide for an aggregate limit.
7.17 When developments are sold, or some other change of
7.13 The insurance clauses contain provisions requiring the ownership takes place, it is common for the potential pur-
Contractor to maintain the insurance for a certain period to be chaser to request that any existing warranties are assigned to
stipulated in the Warranty Particulars. This time limit should be that purchaser. Under common law, the benefits of a contract
at least as long as the Contractor’s liability under the warranty, can be assigned unless there is an express prohibition against
which is either 6 years or 12 years – see Clause 8 of CWa/P&T. assignment in the contract. Sometimes, the warrantor may
require that assignments be permissible only with the war-
7.14 The clauses state that insurance shall be maintained so rantor’s consent, which shall not be unreasonably withheld.
long as it is available at commercially reasonable rates. This Alternatively, the warrantor may only allow the assignment
allows the Contractor to cease maintaining insurance if insurance of the warranty a limited number of times, for example twice,
premiums rise to an exorbitant level or if restrictions on level or to purchasers or tenants of a specified part of the develop-
are imposed by insurers. However, the warranty also requires ment. CWa/ P&T and CWa/F contemplate assignment without
the Contractor to notify the beneficiary if such insurance is no consent, but only on two occasions. The client should be
longer available. advised that, without some ability to assign the warranty at
least once or twice, the marketability of a development may
be adversely affected, as potential future purchasers may be
Limitation put off if they are unable to obtain the comfort of the relevant
collateral warranties.
7.15 Most standard forms of warranty allow for the execution
of a warranty as either a simple contract or as a deed. Where a
warranty is signed as a simple contract, consideration is required 8 JCT 2016: sub-contractor
(see, for example, the consideration recital immediately before collateral warranties
Clause 1 of the CWa warranties), and the limitation period for
the warranty will run for six years from the date of any breach 8.01 The JCT 2016 suite includes published forms for the Sub-
of the warranty. Where a warranty is executed as a deed, no Contractor Collateral Warranty: for a funder (SCWa/F) – and for
consideration is required, and the limitation period will run for a purchaser or tenant – (SCWa/ P&T). These have been produced
12 years from any breach. For this reason, beneficiaries tend for use with the Standard Building Contract, Design and Build
to favour the execution of warranties as deeds, although the Contract, and Intermediate Building Contract.
method of execution of the warranty should reflect that of the
underlying contract to ensure that the warrantor’s liability under 8.02 The drafting broadly follows the forms of main contractor
the warranty lasts for a similar period as his liability under the collateral warranty with similar provisions in relation to net
contract. In addition to this cut-off period provided by the law contribution and caps on liability for costs other than the costs
on limitation, it is common to see clauses in warranties which of repair under SCWa/P&T. SCWa/F includes step-in rights
limit the liability of the warrantor to a specific period of time, for the Funder if the main contractor’s employment under the
often calculated as a certain number of years following practi- Building Contract is terminated. The Employer is by passed by
cal completion. For example, Clause 8 in CWa/P&T, as noted the step-in provisions.
above, provides for a cut-off after 6 or 12 years to reflect whether
a deed has been used or not. The advantage of such a clause to 8.03 Enabling clauses in relation to these sub-contractor collat-
a contractor is that it provides a fixed period under which the eral warranties are included in the JCT forms of main contract.
contractor will be liable and the contractor knows exactly when The Standard Building Contract at Clauses 7E provides for sub-
its liability under the warranty will end. As drafted, however, it contractor’s warranties in favour of Purchasers, and Tenants/
does not affect its tortious liability. Funders, and the Employer respectively, and simply requires
the contractor to deliver the collateral warranties within 21 days
from receipt of the Employer’s notice identifying the relevant
Delay sub-contractor, type of warranty, and beneficiary. References are
7.16 If a contractor is in delay in completing the works under made to the standard form which is to be delivered subject only
the Building Contract, the Employer’s remedy lies in liquidated to amendments proposed by the Sub-Contractor and approved by
and ascertained damages, which may be deducted from mon- the Contractor and the Employer approval not to be unreason-
ies due to the Contractor in accordance with the provisions of ably withheld or delayed.
the Building Contract. Plainly, the Contractor does not want to
create an alternative remedy for delay which might otherwise 8.04 Securing sub-contractors’ collateral warranties presents a
by-pass the provisions for liquidated and ascertained damages huge logistical challenge on a major multi-let construction pro-
contained in the Building Contract by giving a collateral war- ject. The costs entailed in obtaining such collateral warranties,
ranty which, under the terms of Clause 1, would give funders, particularly after practical completion, are huge, and there are
purchasers, and tenants a claim for unlimited damages for very few reported examples of such collateral warranties being
failure to complete the Works in accordance with the Building relied on in practice.
22
The Construction Act Payment Rules
JESSICA STEPHENS QC AND JONATHAN SCHAFFER-GODDARD

1 Introduction recommendations were implemented by the HGCRA and the


Scheme. The original provisions were discussed in the previous
1.01 This chapter concerns the Payment Rules which are set out edition of this book.
in sections 109–113 of the HGCRA1 and Part II of the Scheme2.
Architects need to be aware of the practical effects of this legis- 2.02 In 2004, Sir Michael was asked to undertake a review of
lation, which has had a huge impact on contracts in the construc- the working of the Act. This led to the production of reports on
tion industry, and take this into consideration when: adjudication and payment, and consequently, provisions in the
Local Democracy, Economic Development and Construction Act
(a) negotiating their own terms of appointment with their 2009, which amended the HGCRA.
clients;
(b) advising clients on the forms of building contract which 2.03 As well as setting out a statutory mechanism of notices for pay-
may be used to employ the Contractor; and ment and subsequent payment, the HGCRA grants important provi-
(c) acting as Contract Administrator during the course of sions regarding a party’s entitlement to payment. These include:
the building works, particularly when either advising the
employer about issuing payment and pay less notices or (a) the right to payment by instalments for contracts lasting
when issuing the payment and pay less notices on behalf of 45 days or more;
the employer as the ‘specified person’ under the HGCRA. (b) the ability of a party to suspend performance if it has not
been paid within a specified period;
1.02 Architects need to appreciate when the Scheme applies and (c) the outlawing of “pay when paid” clauses, except in specific
be able to explain its impact to clients who may not be aware circumstances.
of the legislation, which applies to construction professional
appointments as well as construction contracts. 2.04 The HGCRA requires construction contracts to include
terms which give effect to these provisions. In the absence of
1.03 The majority of bodies involved in the drafting of standard express terms that are compliant with the HGCRA, the provi-
forms of building contracts have ensured that their building sions of the Scheme are implied into the contract.
contracts have been amended to incorporate the provisions of
the HGCRA, as have the professional bodies responsible for the 2.05 The Scheme’s provisions are therefore default provisions. It
various standard forms of professional appointment. is always necessary to consider whether the construction contract
complies with the HGCRA in order to determine whether the
1.04 This chapter sets out the law as it applies to contracts relevant provisions in the Scheme are to be incorporated into it.
entered into after 1 October 2011 in England and Wales. For If a construction contract does not comply with the provisions
contracts entered into before that date, the reader should consult relating to payment, then it is only the non-compliant provi-
the previous edition of this work. sions within the construction contract which are replaced by
the relevant payment provisions within the Scheme, and not the
entirety of the Scheme’s payment provisions.
2 The background to the legislation
3 To which contracts does
2.01 The background to the legislation is set out in a report
published by Sir Michael Latham following a review of the the HGCRA apply?
contracting arrangements in the construction industry. The
Report ‘Constructing the Team’ made a number of recommenda- 3.01 Sections 104–107 of the HGCRA identify the requirements
tions that were aimed at curing payment disputes. Some of the with which a ‘construction contract’ must comply before the
payment provisions apply. Section 104(1) essentially defines a
‘construction contract’ as a contract to carry out ‘construction
operations’, which in turn are defined in section 105(1). Subject
1 Housing Grants Construction and Regeneration Act 1996 (as amended
to limited exceptions (see below), most building or construc-
by the Local Democracy, Economic Development and Construction Act
2009), referred to throughout this chapter as ‘the HGCRA’.
tion contracts will be caught by the HGCRA (see, Chapter 23).
2 Scheme for Construction Contracts (England and Wales) Regulations 1998 Importantly, section 104(2) extends the definition of a construc-
(SI 1998 No. 649), referred to throughout this chapter as ‘the Scheme’. tion contract to include:

241
242 The Construction Act Payment Rules

(a) architectural, design, or surveying work in relation to con- for those components to be installed in the building as well,
struction operations; or i.e. supply only contracts. In addition, the section also excludes
(b) the provision of advice on building, engineering, interior works which are of a wholly artistic nature.
or exterior decoration, or on the laying out of landscape in
relation to construction operations. 4.04 A residential occupier is a person who is having construc-
tion works carried out on their house or flat which they occupy
3.02 Members of the design and professional team are granted or intend to occupy. The definition does not extend to the con-
the same rights to payment (and adjudication) as those granted struction work being carried out on a block of flats one of which
to contractors or sub-contractors by section 104(1). is owned by the contracting party. Nothing prevents an architect
agreeing with a client who is a residential occupier that payment
3.03 If an architect engages sub-consultants, the architect must terms which comply with the HGCRA should be expressly incor-
ensure that the sub-consultant appointments comply with the porated into the appointment.
HGCRA and that the payment mechanism is complied with.
4.05 The list of construction contracts that have been excluded
3.04 Architects are frequently appointed to design the complete by the Secretary of State is extensive, and reference should be
building, right down to the interior furnishings which are to be made to the relevant statutory instruments (the Construction
installed within it. The Act only applies to an architect’s services Contracts (England and Wales) Exclusion Order 1998 No.
relating to ‘construction operations’ and will not catch other 648). However, it is worth noting that the following have been
services. The potential for different regimes to apply in respect excluded:
of different services is not desirable and is avoided by expressly
agreeing and recording satisfactory terms. (a) the power of highway authorities to adopt by agreement
roads under section 38 of the Highways Act;
3.05 It is the location of the construction operations that attracts (b) the power of highway authorities to enter into agreement as
the provisions of the HGCRA. The payment provisions do not to the execution of work under the Highways Act 1980;
apply to a construction contract which states that the law of the (c) planning agreements under section 106, which is an agree-
contract is English if the construction work is to be carried out ment imposing planning obligations on the land owner, and
somewhere other than the UK. The provisions of the HGCRA section 106A, which is a modificational discharge of plan-
would, however, apply to a construction contract which specifies ning obligations, or section 299A, relating to Crown planning
the law of the contract to be, for example, Dutch, if the actual obligations, of the Town and Country Planning Act 1990;
work is to be carried out in the UK, a not-uncommon situation (d) agreements to adopt sewer, drainage, or sewage disposal
with construction work at docks or harbours. Where UK archi- work under section 104 of the Water Industry Act 1991;
tects are commissioned by foreign clients for buildings which (e) construction contracts under the Private Finance Initiative;
are to be built abroad, the HGCRA does not apply, as the ‘con- (f) finance agreements such as contracts for insurance, etc;
struction operations’ take place abroad. (g) development agreements where the agreement includes a
provision for the grant or disposal of a parcel of land upon
3.06 Previously, the HGCRA required that the contract be in which the principal construction operations are to take
writing (section 107(1)). However, s.107 has now been repealed, place.
with the result that oral contracts are now caught.

5 The payment provisions in detail


4 Contracts excluded from 5.01 Sections 109 to 113 of the HGCRA deal with the parties’
the payment provisions right to payment in connection with a construction contract. In
summary these rights are:
4.01 Contracts specifically excluded from the ambit of the
HGCRA are: (a) the right for a party to be paid by stage payments where the
specified duration of the works (or agreed estimated dura-
(a) contracts of employment (section 104(3)); tion of the works) is 45 days or more;
(b) matters identified in section 105(2); (b) the right to be informed of the amount to be paid in any
(c) contracts with a residential occupier (section 106(1)); and stage payment, and when that money is due for payment;
(d) any other contract excluded by order of the Secretary of State. (c) the right to be given notice if it is intended that any payment
be withheld;
4.02 Contracts of employment are contracts of service or appren- (d) the right to suspend performance if payment is not made
ticeship between an employer and an individual employee. This within the specified time;
would appear to be relatively straightforward. However, dif- (e) making ‘pay when paid’ clauses ineffective except where a
ficulties arise where self-employed architects or technicians are third party is insolvent.
working in the architect’s office; are they an employee or are
they a sub-consultant? Various tests are applied by the courts to 5.02 The standard forms of appointment and the standard forms
determine the type of contract that exists between the employer of construction contract include these rights within them, but it
and the employee. A detailed discussion of such matters is is necessary to consider these provisions if:
beyond the scope of this chapter, and legal advice should be
sought on the particular facts of a case as it arises. (a) The contract has been further amended; or
(b) The contract has been specially drafted for the project con-
4.03 The matters specifically excluded from the definition of cerned; or
‘construction operations’ primarily relate to drilling and min- (c) An informal agreement has been reached between the client
ing of minerals, oil, or natural gas; nuclear processing, power and the contractor, for example an exchange of letters or
generation, or water supply and treatment industries; or the reference to terms and conditions of contract within various
chemical, pharmaceuticals, oil, gas, steel, or food and drink written documents.
industries. The section also excludes contracts for the manufac-
ture or delivery to site of various building materials, plant and 5.03 In these circumstances, it will be necessary to ascertain
machinery, or components for heating, ventilation, power supply, whether the terms and conditions of the contract comply with
drainage, sanitation, water supply, fire protection, or for security the provisions of the HGCRA and, if they do not, which part or
or communication systems, where the contract does not include parts of the Scheme apply.
The payment provisions in detail 243

Payment by instalments purposes of section 110(1)(b) there is no final date. The final
date remains seven days after the issue of the certificate. The
5.04 A party to a construction contract is entitled to payment by fact that a date is set by reference to a future event does not
instalments only if the contract specifies that the duration of the render it any the less a final date.
work is to be 45 days or more or if it has been agreed by the
parties, or if it is estimated that the work will be of a duration 5.10 There have not been any reported decisions on s.110(1A)–
greater than 45 days. When calculating the duration of the work, (1D), and so it remains to be seen whether this decision remains
Christmas Day, Good Friday, or other bank holidays should good law.
not be included, but weekends are included within the 45-day
period. The same method of calculation should be adopted when
determining notice periods under the Scheme.
Payment notices and pay less notices
5.05 If the duration of the work exceeds the 45-day period, then 5.11 The purpose of sections 110, 110A, 110B, and 111, which
the HGCRA requires that the parties agree the amounts of the provide for payment notices and pay less notices, is best summed
payments, and the intervals at which or circumstances in which up by Coulson J (as he then was) in Systems Pipework Ltd v
they become due. If the parties fail to agree the intervals at Rotary Building Services Ltd [2017] EWHC 3235 (TCC):
which, or the circumstances in which, stage payment become
due, then paragraphs 2–4 of Part II of the Scheme will apply. Prior to [HGCRA]… There was a perceived problem in the
construction industry that employers and main contractors
were failing properly to answer sub-contractors' claims for
Dates for payment payment. Because they were not specifically obliged to do
so, they often delayed in giving any answer at all and, even
5.06 The HGCRA has always required that every construction when they did, they would offer only vague reasons for non-
contract provides an adequate mechanism for determining what payment. One of the beneficial effects of the 1996 Act is that
payments become due and when. Section 110 HGCRA now paying parties are now required to identify early on what (if
includes a negative definition of an ‘adequate mechanism’. anything) they say is due and why.
Sections 110(1A)–1(D) outlaw provisions that make payment
conditional on the performance of obligations under another con- 5.12 Sections 110A and 110B of the HGCRA set out the statu-
tract or a decision by any person as to whether obligations under tory requirements for the contractual mechanisms for giving
another contract has been performed. This extends the prohibi- notice. Section 110A requires a payment notice by either the
tion on ‘pay when paid’ clauses. On one interpretation, it could payer or the payee, while section 110B requires a payee’s notice
include the situation where a main contractor is not paid under in default of a payer’s notice. Taking these in turn:
the main contract for works carried out by a subcontractor, but
the subcontractor seeks payment under the subcontract, however 5.13 Section 110A(1) specifies that the contract must require, no
section 110(1C) appears designed to exclude that. later than 5 days after the payment due date (i.e. the date under
s.110), either (a) the payer or specified person to give a notice
5.07 While a construction contract must provide a final date for to the payee (‘Payer’s Payment Notice’), or (b) the payee to
payment in relation to any sum which becomes due, the parties give a notice to the payer or specified person (‘Payee’s Payment
are free to agree how long the period is to be between the date Notice’).
on which the sum becomes due under the contract and the final
date for payment. 5.14 The provision for a specified person to give notice on behalf
of the payer is of special relevance to Architects when acting as
5.08 If the parties do not agree an adequate mechanism, the a contract administrator: they must be aware of what notice is
provisions of paragraphs 2–7 of Part II of the Scheme will apply. to be given on behalf of the payer and when.

5.09 Under the pre-2011 HGCRA, the issue of what might 5.15 A valid Payer’s Payment Notice or Payee’s Payment Notice
constitute an adequate mechanism was discussed in the case of must specify: (a) the sum that is considered to be due as at the
Alstom Signalling Ltd v Jarvis Facilities Ltd. The parties had payment due date (which may be zero), and (b) the basis on
agreed that the applications for payment and payments made which that sum is calculated (ss.110A(2) and (3)).
under their sub-contract would be linked to the payment cycle in
a separate main contract between Alstom and Railtrack. The final 5.16 Where a contract requires that the Payment Notice be given
date for payment of a sum due under the sub-contract between by the Payer, but in default, no such notice is in fact given,
the parties was 7 days after the date of issue of the Railtrack s.110B allows the payee to give a Payee’s Payment Notice in
certificate under the main contract. HHJ Humphrey Lloyd had the form required by s.110A(3). The effect of the payee serv-
no difficulty in deciding that the payment mechanism in the main ing a notice in accordance with s.110B, is that: (i) a payment
contract did constitute an adequate mechanism for determining notice has been given for the purposes of the statutory scheme
what payments become due under the sub-contract, stating: (s.111(1)); and (ii) the final date for payment (set pursuant to
s.110(1)) is postponed by the same number of days as the num-
I find myself at a loss to understand why Schedule F does not ber of days between the date on which the notice under s.110B
comply with section 110 of the Act in terms of an adequate was given and the date by which the notice under s.110A was
mechanism to determine when a payment was due for the meant to be given.
purposes of section 110(1). The subcontract was made by
reference to the main contract, both formally and finan- 5.17 The operation of s.110B is demonstrated in the following
cially. Conventionally it seems that Alstom was to issue a example: the contract requires that the payer give notice under
certificate within 14 days of the receipt of an application s.110A: If the Payment Due Date is A, and the final date for
(see for example, its letter of the 13 June 2003). Clause 2.6 payment is B, but on day A+5, the payer has not given the payee
said that payment would be made within seven days of the a Payment Notice pursuant to s.110A, then on day A+6, or any
Railtrack certificate being issued in accordance with Annex day after that, the payee may serve a notice pursuant to s.110B.
Fl. There was therefore certainty as to the final date for pay- If the payee serves that notice on day A+11, there are then six
ment – seven days of the Railtrack certificate. This satisfies days between the last day on which the s.110A notice should
section 110(1)(b). The fact that Railtrack, probably in breach have been served and the day on which the s.110B notice was
of its contract with Alstom, might fail to issue its certificate served. Therefore, if the original final date for payment under
in accordance with Annex Fl does not mean that for the the contract was B, the new date is B+6.
244 The Construction Act Payment Rules

5.18 There is no sanction imposed if the paying party fails to to this is the ‘final payment’, i.e. the balance of the contract
serve a section 110A notice. price due after deduction of all instalment payments which have
become due under the contract. The ‘final payment’ becomes due
5.19 Once a valid notice has been given, whether given pursu- by the later of (a) 30 days following completion of the works or
ant to a provision of the contract or s.110B, then, subject to any (b) the making of a claim by the receiving party.
valid pay less notice (see below), the payer must pay the notified
sum (s.111(1)) by the final date for payment. 5.31 Architects may encounter these provisions as payer, as
payee, or as a contract administrator (specified person on behalf
of a payer). If payee, Architects would be advised to ensure that
Pay less notices their appointments allow them to make the application for pay-
5.20 The right to withhold payment at common law arises ment (under s.110A(1)(b)), rather than being reliant upon the
by either set-off or abatement. Set-off allows a paying party employer or its project manager certifying their fees.
to deduct monies owed by the payee (under the same or
closely related contracts) from sums due to the receiving party. 5.32 The Courts have had several opportunities to consider
Abatement is the withholding of money as the result of a breach the new payment notice and pay less notice scheme under
of contract which reduces the value of the work done by that HGCRA since they came into force in 2011. In doing so, they’ve
party. The most common form of abatement is for defective answered important questions that arise from the operation of
work. the scheme.

5.21 Section 111 prevents the payer from exercising its right to
set off or abate the sums due to the payee unless it has given a Pay less notices apply to both
valid notice to the receiving party specifying the amount pro- fnal and interim payment
posed to be withheld and the grounds for withholding payment
5.33 In Adam Architecture Ltd v Halsbury Homes Ltd [2017]
(s.111(3)). This is called a ‘pay less notice’.
EWCA Civ 1735, the Court of Appeal considered the applica-
tion of s.111 to final payments. The claimant architects entered
5.22 A pay less notice must specify the sum that the payer con-
into a contract, governed by HGCRA, with the defendant
siders to be due on the date the notice is served (which may be
property developer. The contract was on the 2012 edition of
zero) and the basis on which it is calculated (s.111(4)).
the RIBA Conditions of Appointment for an Architect. After
termination of the contract, the architects enclosed an invoice
5.23 A pay less notice under s.111(3) must be given prior to ‘the
for the work already completed. The property developer did
prescribed period before the final date for payment’ (which must
not pay the invoice and did not issue a pay less notice under
either be agreed by the parties in the contract, or absent express
s.111. The architects succeeded at the adjudication, but when
agreement, is set by the Scheme at seven days before the final
seeking to enforce in the High Court, the Judge ruled that there
date for payment) (s.111(5)(a) and s.111(7)).
was no obligation to issue a pay less notice in respect of a final
account. The architects appealed successfully. Giving judg-
5.24 If a payee’s notice has been given (either under s.110A(1)
ment for the Court, Jackson LJ held that s.111 applied to all
(b) or s.111B), then a pay less notice must postdate that pay-
payments which are ‘provided for by a construction contract’
ment notice.
and not just interim payments. Therefore, on presentation by
the contractor (in this case an architect), the requirement under
5.25 If (and only if) a valid pay less notice has been issued, then
s.111 to serve a pay less notice continues – and failure to do
the payer can pay the lesser sum specified by the pay less notice.
so will require the paying party to pay the full amount stated
to be due.
5.26 Whether or not a pay less notice has been given, the payer
must make a payment by or before the final date for payment
(being the date specified by the parties in accordance with Formalities for valid payment
s.110(1) or otherwise the date specified by the Scheme). and pay less notices
5.27 If the payer specifies an amount to be owing (either by a 5.34 In the High Court and then Court of Appeal decisions in
payer’s notice (s.110A(1)(a)) or by a pay less notice (s.111(3))) Grove Developments v S&T [2017] EWHC 123 (TCC) [2018]
which is less than the payee considers to be owing, the payee EWCA Civ 2448, the Courts have considered the conditions for
may commence an adjudication (s.111(8)). If the adjudicator validity of a pay less notice. Prior to the certification of practi-
finds that more than the sum specified in the payer’s notice/ cal completion, S&T (contractors) sent Grove (employer) an
pay less notice should be paid, the payer is required to pay the interim application for payment. The amount sought was £14
additional amount (s.111(8) and s.111(9)). million more than the previous interim payment. This was not
a final account, but was, in reality, the contractor’s substantive
5.28 The parties are entitled to agree the timetable and periods final claim.
when the due date and final date may occur after the relevant Grove responded to S&T with its own detailed assessment
period for which payment is to be made. The parties are also of S&T’s valuation as a separate payment notice, but that notice
entitled to agree the timetable for service of the various notices, was contractually out of time. Grove subsequently provided
with the exception of the section 110(A) payer’s or payee’s S&T with a pay less notice, which referred back to its invalid
notice, which must always be served not later than five days payment notice to substantiate ‘the basis on which the sum was
after the date on which a payment became due. calculated’.
It will be recalled that a pay less notice must ‘specify – (a)
5.29 If the construction contract does not comply with these the sum that the payer considers to be due on the date the notice
provisions of the HGCRA, then paragraphs 4–8 of the Scheme is served, and (b) the basis on which that sum is calculated’.
will apply. Paragraph 4 of the Scheme provides that the due date One of the questions for the Court to determine was whether
shall occur on the later of either: or not a payless notice was valid where it referred back to a
document previously provided rather than providing the calcu-
(a) the expiry of seven days following the relevant period; or lations again.
(b) the making of a claim by the payee. The Court of Appeal refused to draw a bright line that would
prevent a pay less notice from referring back to a document pre-
5.30 The Scheme provides that the final date for payment is viously provided in specifying the basis of calculation.
17 days after the date the payment becomes due. The exception In his judgment, Lord Justice Jackson said:
The right to suspend performance for non-payment 245

It is neither tenable to say that reference to other documents Court of Appeal considered a contractor’s termination account.
is always permissible nor to say that such reference is never No pay less notice had been served, and the employer was
permissible. … it is a question of fact and degree in each case liable to pay the full amount stated to be due in the contractor’s
whether the purported Pay Less Notice achieved the requisite termination account. The employer paid the sum stated and com-
degree of specificity. menced an adjudication seeking declarations as to the true value
of the termination accounts. The contractor tried but failed to
In the High Court, the judgment of Coulson J (approved of by stop the ‘true value’ adjudication. Jackson LJ said:
the Court of Appeal) had made clear that:
the employer’s failure to serve a Pay Less notice (as held by
A pay less notice will be construed by reference to its back- the previous adjudicator) had limited consequences. It meant
ground, in order to see how a reasonable recipient would have that the employer had to pay the full amount shown on the
understood it. The court will be unimpressed by nice points contractor's account and argue about the figures later. The
of textual analysis, or arguments which seek to condemn the employer duly paid that sum, as ordered by the previous adju-
notice on an artificial or contrived basis. dicator. The employer is now entitled to proceed to adjudica-
tion in order to determine the correct value of the contractor's
This decision may well increase satellite litigation – with par- claims and the employer’s counter-claims.
ties arguing over the adequacy of notices given by reference to
another document or documents. 5.40 It was unclear for a while whether this applied only
to disputes about the final payment. This was resolved in
5.35 The courts have also considered whether or not payment S&T (UK) v Grove Developments [2018] EWHC 123 (TCC),
notices and pay less notices are required to be in writing. In [2018] EWCA Civ 2448, which concerned an interim applica-
Strathmore Building Services Ltd v Greig (t/a Hestia Fireside tion for payment. The Court of Appeal considered whether the
Design) ([2001] 17 Const LJ 72) it was decided that while employer could commence a separate adjudication seeking a
sections 111 and 115 (Service of notices) of the HGCRA do decision as to the ‘true’ value of the interim application. The
not expressly provide that a pay less notice (and by inference, answer (contrary to the position in ISG and Estura) was a
presumably a payment notice as well) must be in writing, the resounding ‘yes’: an employer could, having paid the amount
references in section 115 to ‘any notice or other document’ notified under the contractor’s payment notice, commence an
indicated that it was clearly intended such a notice should be in adjudication to determine the true value of the work carried
writing. Therefore, oral notice will not suffice, and payment and out. The parties reached a compromise before this decision
pay less notices should always be provided in writing. was appealed to the Supreme Court.

5.41 Therefore, the situation now is that if the employer fails to


Determining the ‘true value’ after failing serve a valid payment or pay less notice in respect of either an
to serve a payment or pay less notice interim or final application for payment, the contractor’s appli-
cation is unchallenged and must be paid; however, provided
5.36 Since the last edition of this work was published, the Courts that the employer has paid that sum, it may commence a true
have had to grapple with the question of whether an employer who value adjudication and recover any overpayment made. The
has failed to serve a valid payment or pay less notice can seek statutory scheme of notices and payment on notices can now be
a determination of the ‘true value’ in a subsequent adjudication. properly understood as being concerned with cashflow, rather
than final determination of what sums are due to the contractor.
5.37 In ISG Construction v Seevic College [2014] EWHC 4007
(TCC), Edwards-Stuart J held that such an employer had no
right to a ‘true value’ adjudication, finding that the employer’s 6 The right to suspend
failure to serve a notice in time meant that the employer ‘must be performance for non-payment
taken to be agreeing the value stated in the application, right or
wrong’. Subsequently, in Galliford Try Building v Estura [2015] 6.01 If a party has not received a sum stated to be due under the
EWHC 412 (TCC), the Court clarified that the employer’s failure contract, in full, by the final date for payment, that party has the
to submit a payment or pay less notice did not mean that the right to suspend the performance of its contractual obligations
employer was taken to have agreed to the value of the works at until payment has been made.
any date other than the relevant valuation date and, importantly,
that there was nothing to stop the Employer from ‘challenging 6.02 This must be regarded as one of the most powerful sanc-
the value of the work on the next application, even if he is con- tions available to a party seeking payment. Prior to the HGCRA,
tending for a figure that is lower than the (unchallenged) amount any suspension of performance by a party carried with it the
stated in the previous application’. potential risk of being regarded as repudiation of the contract,
for which the suspending party could be liable for damages.
5.38 Following these decisions, the phenomenon of the ‘smash Suspension continues to be risky and any provision permitting
and grab’ claim (where the contractor submits a large pay- suspension must be strictly complied with.
ment notice at or towards the end of works but before a final
account) became commonplace. If no effective pay less notice 6.03 The HGCRA stipulates that the right to suspend perfor-
was served, the Employer consequently became liable to pay the mance may not be exercised without first giving the defaulting
full amount stated, and could not (following ISG and Estura) party at least seven days’ notice of the intention to suspend for
challenge that by way of an adjudication to determine the ‘true non-payment (s.112(2)). The notice must state the ground(s)
value’ of the work done. This became something of a trap for the upon which it is intended to suspend the performance. The right
unwary. Since there is often a lengthy period of delay between to suspend performance ceases when the party in default makes
the conclusion of the works and the final account, and the final payment in full of the amount due.
account is often a costly process, the last interim payment is
often effectively the final account; an overpayment could not 6.04 The 2011 amendments enhance the right to suspend by
be corrected in subsequent interim payments, and there was no expressly providing that: all or part of the works can be sus-
longer an incentive for the contractor to comply with the final pended (s. 112(1)); a suspending contractor can recover costs
account provisions. and expenses which would include demobilisation and remo-
bilisation (s. 112(3A)); and a contractor has an entitlement to
5.39 However, that situation has now changed following a series an extension of time for consequential delays caused by the
of decisions. In Harding v Paice [2015] EWCA Civ 1231, the suspension (s. 112(4)).
246 The Construction Act Payment Rules

7 ‘Pay when paid’ clauses final date for payment. Interest can be claimed on late payment
if there is an express term in the contract, or under the Late
7.01 The HGCRA renders ineffective any clause in a construc- Payment of Commercial Debts (Interest) Act 1998.
tion contract which makes receiving payment conditional upon
the payer receiving payment from a third party. The exception 8.02 A provision for interest on late payments is often provided
to this is where the client becomes insolvent. In those circum- in contracts of appointment. The RIBA form of appointment
stances, a ‘pay when paid’ clause in a contract would be effec- S-Con-07-A, by way of example, contains a clause that stipulates
tive. Advice should be sought should insolvency impact a project interest is to be paid at 5% over the Bank of England dealing rate
on which an architect is engaged. current at the date the payment becomes overdue, in the event
of a bill not being paid within 28 days.
7.02 The ‘pay when paid’ clause may have been rendered ineffec-
tive by the HGCRA, but there have been attempts in contracts to 8.03 If the appointment contains no express entitlement to
circumvent its effect by means of a ‘pay when certified’ clause. interest on late payment of debts, then the architect will have
These clauses have probably been outlawed by section 110(1A)(b). to rely on the statutory provisions, which entitle him to claim
interest on the outstanding debt from the final date for payment,
8 Interest on late payment of debts either agreed by the parties or as determined under the Scheme.
The rate of interest that can be claimed is set by the Secretary
8.01 The final matter to consider in relation to payment is the of State. It is currently fixed at 8% over the Bank of England
architect’s entitlement to interest if payment is not made by the dealing rate.
Part D
Building dispute
resolution
23
Adjudication
MATTHEW THORNE

1 What is adjudication? Distinctive features


1.06 Adjudication has three important and distinctive features:
1.01 Adjudication is a procedure for obtaining a speedy and (i) speed; (ii) temporary finality; and (iii) enforceability.
impartial determination on a construction dispute. The decision
of the adjudicator is not final, but it is enforceable and tempo- 1.07 Speed: Adjudication is designed to be a fast process, by
rarily binding unless and until the dispute is finally resolved by which an adjudicator is nominated, arguments and evidence
litigation, arbitration, or agreement. are presented, and a decision is given, all in quick succes-
sion. To this end, the construction contract must provide a
1.02 Because it is a quick and cost-effective way of resolving timetable designed to secure the appointment of an adjudicator
differences and maintaining cash-flow, it is frequently used dur- within 7 days of a party giving notice of its intention to refer
ing the course of a project, as well as after completion. a dispute to adjudication. It must require the adjudicator to
reach a decision within 28 days of referral. This period can
Mandatory nature be extended in only two situations: (i) the adjudicator can
extend it by up to 14 days with the consent of the party who
1.03 Adjudication is a process brought about by the Housing referred the dispute; (ii) after the reference, the parties can
Grants, Construction and Regeneration Act 1996 1 (‘HGCRA’) agree a longer period.
following a report on the UK construction industry by Sir
Michael Latham in 1994. 1.08 Temporary finality: in Bouygues (UK) Ltd v Dahl-Jensen
(UK) Ltd [2000] BLR 522, Chadwick LJ confirmed that deci-
1.04 The HGCRA makes the right to commence an adjudica- sions were ‘not finally determinative’, but ‘provide a speedy
tion mandatory. Subject to limited exceptions, ‘construction method by which disputes under construction contracts can be
contracts’ (as defined by the HGCRA) must give the parties to resolved on a provisional basis’. In other words, they are tempo-
the contract the right to refer disputes to adjudication and must rarily binding, unless and until one of the parties seeks to reopen
contain terms which the HGCRA specifies. This right cannot the dispute in litigation or arbitration, or if the parties reach an
be excluded by agreement and, if a construction contract does agreement. This is often referred to as ‘temporary finality’.
not contain the required provisions, the adjudication provisions
contained in the Scheme for Construction Contracts (England 1.09 Enforceability: the decision is enforceable notwithstanding
and Wales) Regulations 1998/649, as amended in 2011 (‘the the fact that it is provisional. It is also likely to be enforceable
Scheme’) will apply. If a construction contract does contain notwithstanding the fact that it contains errors of fact or law.
the required provisions, it may also contain other provisions If a party fails to comply with a decision, it will usually be
regulating the adjudication, provided those other provisions are compelled to do so by the Technology and Construction Court,
not inconsistent with the provisions required by the HGCRA. pending any final dispute resolution.
1.05 Parties to contracts which are not ‘construction contracts’, 1.10 Speed and the possibility of enforcement despite error have
and which are therefore not covered by the HGCRA, may ‘opt resulted in adjudication being referred to as a ‘quick and dirty’
in’ and agree that their disputes shall be resolved by adjudi- procedure. As the Court of Appeal has said, the need to have
cation. In that event, subject to the precise terms agreed, the the ‘right’ answer has been subordinated to the need to have an
procedure will be the same as or similar to the procedure under answer quickly: Carillion Construction Ltd v Devonport [2006]
the HGCRA. BLR 15. Adjudication is, nevertheless, a popular procedure in
the construction industry, and parties often accept the adjudica-
tor’s decision and do not seek to challenge it by subsequent
litigation or arbitration.
1 The HCGRA was amended by the Local Democracy, Economic
1.11 The Courts have consistently stressed the uniqueness of
Development and Construction Act 2009, which came into force on 1
November 2011. The as-amended HCGRA applies to construction con-
adjudication. It is not the same as arbitration (which is a final
tracts entered into after that date and this 10th Edition consequently deals dispute resolution process, like litigation, and is regulated by the
with those statutory provisions now in force and applicable to contracts Arbitration Act 1996). Nor is it the same as expert determination
entered into after that date. Those seeking to research points under the (which is a final dispute resolution process with a very different
un-amended provisions are respectfully referred to the previous edition. procedure and decided by an expert).

249
250 Adjudication

2 To which contracts does it apply? 3.04 The HGCRA applies only to construction operations in
England, Wales, Scotland, or Northern Ireland; and the pre-
2.01 Whilst other contracts could incorporate a similar procedure sent (amended) wording applies only to contracts made from
voluntarily, section 108 of the HCGRA gives the mandatory 1 November 2011. Readers are referred to previous editions of
right of adjudication to parties to a ‘construction contract’. The this work for information on contracts executed prior to that
first question that arises, therefore, is what is a construction date. See also Chapter 22, section 4.
contract?

2.02 The answer lies in sections 104 and 105 of the HGCRA, 4 The terms required by the HGCRA
which set out an unfortunately complex definition. Further infor-
mation about these sections is given below but, in broad terms: 4.01 Unless the contract fulfils the requirements of section 108 of
(i) a contract concerned with works of construction is likely to the HGCRA, the provisions of the Scheme apply as implied
be a construction contract; and (ii) many contracts with profes- terms of the contract (section 114(4)). What, then, are the
sionals, including architects, are also construction contracts. section 108 requirements?

2.03 By virtue of section 104 of HGCRA, a ‘construction con- 4.02 By section 108, a construction contract must include pro-
tract’ is an agreement for (a) the carrying out of construction vision in writing so as to: (i) enable a party to give notice at
operations; (b) arranging for the carrying out of ‘construction any time of its intention to refer a dispute to adjudication; (ii)
operations’ by others; and (c) providing one’s own or another’s provide a timetable with the object of securing the appointment
labour for the carrying out of ‘construction operations’. In of an adjudicator and the referral of the dispute to him within
addition, agreements in relation to ‘construction operations’ for seven days of such notice; (iii) require the adjudicator to reach
architectural, design, or surveying work, and agreements for the a decision within 28 days or such longer period as is agreed
provision of advice on building, engineering, interior or exterior by the parties after the reference; (iv) allow the adjudicator to
decoration, or the laying out of landscape are also construction extend the 28-day period by up to 14 days with the consent of
contracts. Thus, contracts with construction professionals are the referring party; (v) impose a duty on the adjudicator to act
construction contracts, provided they relate to ‘construction oper- impartially; (vi) enable the adjudicator to take the initiative in
ations’. Contracts of employment are not construction contracts. ascertaining the facts and the law; (vii) provide that the adjudica-
tor’s decision is binding until the dispute is finally determined
2.04 Section 105(1) then gives a list of ‘construction operations’. by legal proceedings, arbitration, or agreement; (viii) permit the
Broadly speaking, the list includes the operations which an adjudicator to correct the decision so as to remove a clerical or
architect or a layman would consider to be construction opera- typographical error; and (ix) provide that the adjudicator and his
tions. However, section 105(2) contains a long and complicated or her employees or agents shall not be liable for acts or omis-
list of operations which are not to be considered as ‘construc- sions in the discharge or purported discharge of the adjudicator’s
tion operations’. For the most part, they are operations which functions, unless the act or omission is in bad faith.
are unlikely to concern architects, for example: (a) drilling
for or extracting oil or natural gas; and (b) extracting miner- 4.03 Contractual terms dealing with adjudication may be set
als. However, architects should note that the following are not out in the contract itself or may be incorporated into it by refer-
construction operations: (i) manufacturing or delivering to site ence. Many organisations have standard terms which regulate
various types of equipment and materials under a contract which adjudications and which can be incorporated by reference. If
does not provide for their installation; and (ii) various operations there are contract terms which fully satisfy the requirements
connected with sculptures, murals, and other artistic works. of section 108 and which are not, in any respect, inconsistent
with it, they will govern the adjudication. If the contract does
2.05 Architects concerned with the question whether a particular not fully satisfy the requirements of section 108, or contains
contract is or is not a construction contract will need to consider terms which are, in any respect, inconsistent with it, the Scheme
the detail in sections 104 and 105 before providing an answer. applies and replaces the express terms in their entirety. All of
the contractual adjudication terms are void, not simply the term
which contains the inconsistency: Yuanda (UK) Co Ltd v WW
Gear Construction Ltd [2010] EWHC 720 (TCC).
3 Excluded construction contracts
4.04 The fact that terms are in a standard form is no guarantee
3.01 The adjudication provisions in the HGCRA do not currently that they do satisfy the requirements of section 108. For instance,
apply to two categories of construction contracts: (i) construc- GC/Works adjudication provisions used to provide that the adju-
tion contracts with a residential occupier (section 106 of the dicator’s decision would be valid notwithstanding the fact that
HGCRA); and (ii) specific types of contracts identified in the it was issued late. That was inconsistent with section 108. As
Construction Contracts (England and Wales) Exclusion Order a result, the GC/Works adjudication provisions failed in their
1998 (SI 1998 No. 648) (the ‘Exclusion Order’). entirety, and adjudication was regulated by the Scheme: Aveat
Heating Ltd v Jerram Falkus Construction Ltd [2007] EWHC
3.02 Construction contracts with residential occupiers: a con- 131 (TCC).
struction contract with a residential occupier is a contract which
principally relates to operations on a dwelling which one of the 4.05 The risk of inconsistency with section 108 has resulted
parties to the contract occupies, or intends to occupy, as his or in some standard forms and some organisations concerned
her residence. Nevertheless, even though not mandatory, many with adjudication using the Scheme provisions and not a
residential occupiers do instruct works on contractual terms that bespoke set of rules; see, for instance, the JCT 2005, 2011, and
include adjudication provisions, thereby incorporating adjudica- 2016 contracts and the TECBAR Adjudication Rules 2012.
tion by their agreement.

3.03 The Exclusion Order: at present, a number of different 5 Contractual adjudications


contracts are excluded, for instance some contracts with the
Highways Agency and with NHS Trusts; some contracts entered 5.01 Most standard form contracts include or incorporate terms
into under the private finance initiative; and finance and develop- providing for adjudication. Bespoke contracts may also do so. It
ment agreements as defined. Architects concerned with the ques- follows that there may be a contractual entitlement to adjudicate
tion whether a particular contract is or is not excluded, wholly even if the HGCRA does not apply: see Treasure & Sons Ltd v
or in part, should consider the specific provisions. Dawes [2008] BLR 24.
Does the dispute arise ‘under’ the contract? 251

6 Notice of adjudication may simply remain silent for a period of time, giving rise to the
same inference.
6.01 A construction contract must enable a party to give notice
‘at any time’ of its intention to refer a dispute to adjudica- 7.04 There may be a dispute notwithstanding the fact that there
tion: section 108(2) of the HGCRA. Such a notice is known is no valid defence, with the result that the claim is, in one sense,
as a ‘notice of adjudication’. It must identify the dispute and indisputable. On the other hand, there will not be a dispute if the
the nature of the redress sought and, by doing so, defines the claim has already been decided by an adjudicator (or arbitrator
scope of the dispute for the purpose of the adjudication. It thus or court) and is for that reason indisputable.
establishes the limits of the adjudicator’s jurisdiction and must
be carefully drafted; its importance cannot be over-emphasised.
8 Multiple disputes
6.02 Where the Scheme applies (whether incorporated
expressly by the contract or implied due to non-compliance 8.01 Parties to a construction contract frequently find that more
with section 108), this prescribes certain requirements for the than one dispute arises between them. However, the traditional
contents of the notice of adjudication. By paragraph 1 of Part I view is that only a single dispute can be referred to an adjudica-
of the Scheme, the notice must set out (a) the nature and a brief tor at any one time, because section 108 of the HGCRA concerns
description of the dispute and parties involved; (b) details of the reference of ‘a dispute’ to adjudication: TSG v South Anglia
where and when the dispute arose; (c) the nature of the redress Housing [2013] EWHC 1151. It is said that this must at least be
sought; and (d) the names and addresses of the parties to the the case when the Scheme applies because the Scheme contains
contract. a provision which would be unnecessary if there were a right to
refer multiple disputes; i.e. the provision in paragraph 8(1) of the
6.03 The notice can be given at any time. This means that it Scheme, which provides that with the consent of the parties, the
can be, and often is, given while the works are being carried adjudicator may adjudicate at one time on more than one dispute.
out. It is therefore be a useful tool to resolve disputes which
would otherwise sour the working relationship of the parties or 8.02 It follows that, absent consent, an adjudicator will gener-
bring the contract to a premature end; and it can be important in ally have no jurisdiction to deal with multiple disputes. Want of
maintaining cash flow for contractors or sub-contractors where jurisdiction on this basis is not infrequently raised as a defence
disputes as to payment arise. Equally, the notice can be given in enforcement proceedings.
after the works have been completed and even while litigation
or arbitration is proceeding. 8.03 In practice, the inability to refer multiple disputes should
not cause a problem. The Courts have taken a wide view as to
6.04 Determining the appropriate moment to refer a dispute will the meaning of ‘dispute’ so that, for example, an application
often also bring considerations of strategy into play. A referring encompassing issues as to variations, extensions of time, and
party will need to ensure it has properly prepared and obtained other matters will often all fall within the same ‘dispute’: David
the necessary evidence for its case. Responding parties should McLean Housing Ltd v Swansea Housing Association Ltd [2002]
also be alive to the possibility of ‘ambush’: a referring party BLR 125. It will ultimately be a question whether, on the facts,
may spend considerable time preparing a case for adjudication a claim comprising of separate elements can fairly be described
and, having served the notice of adjudication, the tight timeta- as a single dispute. In this regard,
ble imposed by the HGCRA then operates and limits the time
available for the responding party to prepare an answer to the The courts have adopted a robust approach to this point and
claim. It is also not unheard of for a party to refer a dispute to have utilised what has been called a ‘benevolent interpretation
adjudication shortly before a holiday period in order to gain a of the notice’ to conclude that whilst there may have been a
strategic advantage. number of issues in the adjudication in question, there was
only one underlying dispute.
Michael John Construction Ltd v Golledge [2006]
EWHC 71
7 The ‘dispute’
8.04 Moreover, when the Scheme applies, the adjudicator can
7.01 Since, by section 108(1), only a ‘dispute’ can be referred deal with multiple disputes with consent. Further, there is noth-
to adjudication, it follows that there must be a dispute before a ing to stop a party giving a separate notice of adjudication in
notice of adjudication can be validly given. This is particularly respect of separate disputes.
relevant where, for example, parts of a referral to adjudication
have never in fact been raised before. A responding party may
complain that insufficient time has passed since a claim was 9 Does the dispute arise
made to it (if indeed any claim had been previously made at ‘under’ the contract?
all), or that the adjudication expands from a narrow issue into
previously untouched terrain. 9.01 The right provided by the HGCRA is a right to refer dis-
putes ‘arising under the contract’: section 108(1).
7.02 Whether a dispute exists is accordingly not as straight-
forward as one might think, and the Courts have considered a 9.02 Similar provisions in arbitration agreements are given a
number of different tests. wide interpretation on the basis that the parties ‘are likely to
have intended any dispute arising out of the relationship into
7.03 The test now settled upon is to ascertain whether the dispute which they have entered or purported to enter to be decided by
has ‘crystallised’. Thus, mere notification of a claim by one party the same tribunal’: Fiona Trust v Privalov [2007] UKHL 40).
to the other does not automatically and immediately give rise to
a dispute. A dispute does not arise unless and until it emerges 9.03 The position is somewhat less clear in respect of adju-
that the claim is not admitted (see Amec Civil Engineering v dications. In Hillcrest Homes v Beresford [2014] EWHC 280,
Secretary of State for Transport [2004] EWHC 2339). This is HHJ Raynor QC found a claim for misrepresentation under the
heavily fact-dependent. There may, for example, be an express 1967 Misrepresentation Act did not arise under the contract.
rejection of the claim. There may be discussions between the By contrast, in ISG v Castletech [2015] EWHC 1443 Edwards-
parties from which objectively it is to be inferred that the claim Stuart J held that a restitutionary claim for failure of considera-
is not admitted. The respondent may prevaricate, thus giving rise tion did arise under the contract. It remains to be seen how the
to the inference that it does not admit the claim. The respondent Court will deal with other situations which arise.
252 Adjudication

10 Appointment of an adjudicator 11.05 The referral notice cannot go beyond the confines of
the dispute identified in the notice of adjudication. It can, and
10.01 Section 108(2) of the HGCRA requires the contract to in practice it should, give full details of the way the referring
provide a timetable with the object of securing the appointment party puts its case in respect of that dispute. It must be carefully
of an adjudicator and the referral of the dispute to the adjudicator drafted. The referring party might not be permitted to put in
within seven days of the notice of adjudication. The method by further documents at a later stage.
which the appointment is secured will depend on the particular
terms of the contract or, in default of any or sufficient terms, on
the provisions of the Scheme. 12 Procedure after the
referral notice
10.02 Typically, the contract will specify a nominating body
to identify a particular adjudicator. Alternatively, the contract 12.01 The adjudicator will generally look to issue directions
may state who is to be the adjudicator. If it does neither and the for the adjudication process fairly quickly after receipt of the
Scheme applies, the referring party may ask any ‘adjudicator referral notice.
nominating body’ (i.e. any organisation which holds itself out
as a body which will select an adjudicator) to make the appoint- 12.02 By virtue of section 108(2) of the HGCRA, the construc-
ment. There are many such bodies. tion contract must enable the adjudicator to take the initiative
in ascertaining the facts and law but, save for its requirements
10.03 In order to begin the adjudication process, the referring as to the time within which the adjudicator’s decision has to be
party will therefore need to follow the contract or Scheme reached, it does not impose any further procedural requirements.
requirements, making a request to the relevant adjudicator or However, the adjudicator’s ability to take the initiative neces-
nominating body. The request should be accompanied by the sarily includes the ability to give directions for the conduct of
notice of adjudication and should be made on the same day as the adjudication. This may also be expressed in the contract or
the notice of adjudication. in a set of procedural rules which the contract incorporates. It is
expressed in regulation 13 of the Scheme.
10.04 The adjudicator must act impartially. A person who
is biased cannot be appointed. Whilst the HGCRA does not 12.03 The parties may make representations to the adjudicator
expressly require that the adjudicator be independent of the par- about what directions should be given. The adjudicator should
ties, the Scheme prohibits an employee of a party from acting consider whether or not the adjudication can be completed
as adjudicator, and any decision tainted with apparent bias is within the statutory time limit and, if not, should inform the
unlikely to be enforced. The person requested or nominated as parties and seek consent to an extension.
adjudicator should disclose any connection with the parties to
the dispute: see, for example, paragraph 4 of the Scheme. This 12.04 In practice, the adjudicator will usually give directions for
enables the parties to object to the appointment and may result the service of a written response to the referral notice. Because
in the referring party having to restart the appointment process. of the tight time constraints, this is likely to be required within
a very short period. One week is not unusual. The directions
10.05 There is no appointment until the person requested or might also allow for the submission of a reply by the referring
nominated as adjudicator has agreed to act. The person first party and/or the submission of other documents or arguments.
suggested may refuse or be unwilling to act. If that occurs, the The requirements of natural justice must be satisfied but, subject
appointment process must be restarted. In practice, the proposed to that, the adjudicator has a full discretion as to how the dispute
adjudicator is unlikely to agree to act unless the referring party will be handled.
expressly agrees to pay his or her fees and expenses. Other terms
may also be demanded; e.g. that both parties, not just the refer- 12.05 The adjudicator will have to decide whether there should
ring party, expressly accept liability for fees and expenses and/ be an oral hearing; if so, its date and length; and whether fur-
or terms concerning the conduct of the adjudication. ther directions are required covering a potentially broad range
of matters such as expert evidence, site visits, or testing to be
carried out.
11 The referral notice
11.01 Section 108(2) of the HGCRA also requires the contract to 13 The response to the
provide a timetable with the object of securing the appointment referral notice
and referral of the dispute to the adjudicator within 7 days of
the notice of adjudication. This requirement will be fleshed out 13.01 The responding party’s answer to the claim raised comes
by the terms of the contract or, in default of any or sufficient in the form of a ‘response’. There are not usually any specific
terms, by the Scheme. requirements as to form or content, but the responding party
should answer the claim as fully and clearly as is reasonably
11.02 Typically, referral is by means of a document known as possible. Unless otherwise required by the adjudicator, the
the ‘referral notice’. This is usually drafted in a similar form to responding party should also serve all additional documents on
a points of claim, setting out the parties, contract, details of the which it relies at the same time.
project, and legal and factual arguments in support of the claim.
13.02 It will be recalled that the adjudicator only has jurisdiction
11.03 The requirement to ‘refer’ the dispute within seven days to consider the ‘dispute’ referred. Difficult questions arise if the
of the notice of adjudication has been interpreted as requir- responding party seeks to raise counterclaims (or cross-claims),
ing receipt of the referral notice by the adjudicator within that set-offs, and matters which abate (i.e. reduce) a claim. If these
period: Aveat v Jerram Falkus [2007] EWHC 131. do not form part of the same dispute, they will be outside the
adjudicator’s jurisdiction.
11.04 Where the Scheme applies, paragraph 7 requires the refer-
ral notice to be accompanied by copies of, or relevant extracts 13.03 In this regard, the courts will generally seek to avoid inter-
from, the construction contract and such other documents as the preting a notice of adjudication in a way which would exclude
referring party intends to rely upon. It must be also served upon defences otherwise open to a responding party: Pilon v Breyer
every other party to the dispute. In practice, even where the [2010] EWHC 837. Moreover, where the responding party’s
Scheme does not apply, the same requirements are likely to arise. claim arises from the same exercise referred to the adjudicator,
The decision 253

such as where the dispute concerns an interim valuation, an 15 Resignation, revocation,


award to the responding party in respect of that valuation is
part of the same dispute: Workspace Management v YJL [2009] and abandonment
EWHC 2017.
15.01 The adjudicator is obliged to carry out a fair and impar-
13.04 Whilst a response should put forward all matters upon tial determination in the time provided by the HGCRA (or such
which the defendant relies to show that it is not obliged to pay longer period as is agreed). If a fair decision is not possible
what is claimed, due account must be taken of the provisions in within the time available, the adjudicator should ask the parties
sections 109–113 of the HGCRA and, in particular, the need for to agree to extend it. If they refuse to give an extension, the
an effective pay less notice before a payment under a construc- adjudicator should resign: Balfour Beatty v Lambeth BC [2002]
tion contract can be withheld: see section 111. A responding BLR 288. Continuing in such circumstances would be a breach
party will not usually be able to rely on matters which should of the rules of natural justice.
have been, but were not the subject of a valid pay less notice:
Letchworth v Sterling [2009] EWHC 1119. 15.02 The adjudicator should also resign if the dispute referred
to adjudication is the same as one on which a previous adjudica-
13.05 The responding party may have its own jurisdictional chal- tion decision has already been given, since an adjudicator cannot
lenges to the claim, for instance, that the HGCRA does not apply rule on the same dispute more than once: see Balfour Beatty
to the contract in question; that there is no ‘dispute’ within the v Shepherd Construction [2009] EWHC 2218. Indeed, where
meaning of the GCRA; or that, for some reason, the adjudicator the Scheme applies, paragraph 9(2) expressly provides that the
has not been validly appointed. adjudicator must resign if the dispute referred is the same or
substantially the same as a dispute previously referred to and
13.06 In challenging jurisdiction, the party raising the challenge decided by an adjudicator.
(‘the challenger’) has, in theory, a number of options.
15.03 Whether an adjudicator is entitled or obliged to resign
13.07 The challenger could ignore the adjudication and raise in other circumstances depends on the contractual terms which
the challenge in subsequent enforcement proceedings. This is govern the adjudication. If the Scheme applies, an adjudicator
not advisable: the challenge may fail, and the challenger will is entitled to resign at any time on giving written notice to the
have lost the ability to put forward a defence on the merits of parties.
the claim. Alternatively, it could participate in the adjudication
without raising the challenge. That, too, is inadvisable: there is 15.04 As to revocation and abandonment, the referring party is
a substantial risk that the challenger will be held to have waived generally entitled unilaterally to withdraw or discontinue any
the right to raise the challenge later. head of claim in the adjudication: Midland Expressway Ltd v
Carillion Construction Ltd [2006] BLR 325. Indeed, a referring
13.08 The challenger could ask the adjudicator to rule on the party can even unilaterally withdraw the entire dispute: Jacobs
challenge and could agree to be bound by the decision. Since v Skanska [2017] EWHC 2395. Moreover, when the Scheme
the adjudicator may not be a lawyer, or may reach the wrong applies, paragraph 11(1) provides that the parties may at any
conclusion in any event, this route will usually be inadvisable. time agree to revoke the appointment of the adjudicator.

13.09 The challenger can seek a declaration from the court that 15.05 The adjudicator’s entitlement to fees and costs in the
the adjudicator has no jurisdiction. This may be appropriate in event of resignation, revocation, or abandonment depends on
some cases but, unless and until the declaration is granted, the the contractual terms governing the adjudication, including any
adjudication is likely to proceed, and a defence on the merits can additional terms agreed when the adjudicator was appointed.
only be raised if the challenger participates in the adjudication.
15.06 In most circumstances, there will be nothing to prevent a
13.10 The best course will usually be for the challenger to raise fresh adjudication being commenced after a resignation, revoca-
the challenge, together with any defence on the merits, in the tion, or abandonment, unless the further adjudication was unrea-
response, but without agreeing to be bound by the decision on sonable and oppressive: Jacobs v Skanska [2017] EWHC 2395.
jurisdiction. This approach may result in the adjudicator, if the
challenge is well founded, declining to act further. If this option 16 The decision
is selected by the challenger, it is important to make it clear,
preferably in the response itself, that the challenge is maintained, 16.01 The decision must be made within 28 days of referral;
even if the adjudicator decides that it is not well-founded and within 42 days if the referring party has agreed to an exten-
continues to act. It is also prudent to include similar jurisdic- sion of up to 14 days requested by the adjudicator; or within
tional reservations in other correspondence. This preserves the any longer period which the parties have agreed: HGCRA
challenger’s right to resist later enforcement proceedings on the section 108(2)(c) and (d).
ground that the adjudicator lacked jurisdiction.
16.02 If the adjudicator fails to reach a decision within the rel-
evant period, the decision is a nullity: Cubitt Building Interiors
14 Confdentiality Ltd v Fleetglade Ltd [2006] EWHC 3413. However, a decision
reached within the relevant period may be valid even if it is not
14.01 Adjudication, unlike arbitration, is not generally confiden- communicated to the parties until afterwards; but only if it is
tial. However, where the adjudication is conducted in accordance sent to the parties forthwith: Cubitt, above. By contrast, lengthier
with the Scheme, paragraph 18 prohibits disclosure by the adju- delays in communicating a decision, even if reached within
dicator or parties of any documents which the disclosing party the required timeframe, are likely to lead to the decision being
has indicated are to be treated as confidential. If the Scheme does unenforceable: Lee v Chartered Properties [2010] EWHC 1540.
not apply, the contract’s adjudication terms may impose more
extensive confidentiality obligations. 16.03 There is generally no obligation on an adjudicator to
give reasons for the decision, but regard should be had to the
14.02 Information or documents which are to be treated as applicable rules. Paragraph 22 of the Scheme, for example,
confidential can nevertheless be considered in any court pro- requires the adjudicator to provide reasons where requested by
ceedings concerning the adjudication, for instance enforcement one of the parties to the dispute. Where reasons are required, a
proceedings. brief statement of reasons will generally suffice to show that the
254 Adjudication

adjudicator has dealt with the issues referred and what his or her 18.03 Attempts to prevent enforcement have been a growth
conclusions are on those issues: Carillion v Devonport [2005] industry since the HGCRA came into force, but these do not
EWHC 778. This does not require every single argument of fact often find favour with the Court. ‘It should only be in rare cir-
and law to be detailed: it is enough if the adjudicator deals with cumstances that the courts will interfere with the decision of an
those arguments which are sufficient to establish the route by adjudicator’: per Chadwick L.J. in Carillion Construction Ltd
which the decision is reached: Balfour Beatty v Shepherd [2009] v Devonport Royal Dockyard Ltd [2006] BLR 15. Enforcement
EWHC 2218. can be resisted on the ground that the adjudicator had no juris-
diction or exceeded his jurisdiction and on the ground that there
16.04 Section 108(3A) of the HGCRA requires the contract to was a breach of the rules of natural justice, both dealt with
include provision in writing permitting the adjudicator to correct further below.
the decision ‘so as to remove a clerical or typographical error
arising by accident or omission’. In the absence of such provi-
sion, the Scheme will apply. 19 Ineffective defences to
enforcement proceedings
16.05 Adjudicators are not entitled to exercise a lien which
would have the effect of delaying delivery of the decision in the TCC
pending payment of their fees: Cubitt Building Interiors Ltd v
Fleetglade Ltd [2006] EWHC 3413. 19.01 Enforcement cannot be resisted on the ground that the
adjudicator (i) came to the wrong decision on the facts or made
factual errors in his decision; (ii) made an error of law; or (iii)
17 Fees and costs made a procedural error (C&B Scene Concept v Isobars [2002]
EWCA Civ 46; Urang v Century Investments [2011] EWHC
17.01 A distinction should be drawn between the adjudicator’s 1561). The only caveat to this is where, as a result, the deci-
fees and disbursements on the one hand and the parties’ costs sion was outside the adjudicator’s jurisdiction or was made in
and expenses on the other. breach of the rules of natural justice (see below). Mistakes by
the adjudicator are unlikely to have this result.
17.02 As to the adjudicator’s fees, no specific provision is
made in the HGCRA. Where the Scheme applies, paragraph 19.02 It will not normally be possible to raise a counterclaim,
25 provides for the adjudicator to be paid such reasonable cross-claim, or set-off as a defence in enforcement proceedings.
amount as he or she has reasonably incurred. In practice, an The general rule is subject to two exceptions: if permitted by the
adjudicator will almost always ensure that satisfactory terms terms of the contract, or if permitted on a proper interpretation of
with regard to fees and disbursements are in place before accept- the adjudicator’s decision: Squibb Group v Vertase [2012] EWHC
ing the appointment. If the contract does not cover this, as a 1958. Thus, it may be possible to set-off an entitlement to liqui-
minimum, the referring party will be required to accept liability dated damages if that entitlement follows logically from the adju-
for the fees before acceptance. In fact, the contract may make dicator’s decision or if the adjudicator’s decision has not decided,
the parties jointly and severally liable for fees and/or may enable either expressly or by implication, that there is such an entitlement:
the adjudicator to apportion liability for them between the par- Balfour Beatty Construction v Serco [2004] EWHC 3336 (TCC).
ties. Moreover, participation in adjudication may give rise to a
contract between the adjudicator and the parties by which they 19.03 Stays of execution are typically sought either if the judg-
come under an implied obligation to be jointly and severally ment debtor has a yet-undetermined cross-claim or if the finan-
liable to pay reasonably incurred fees and expenses: Linnett v cial position of the judgment creditor makes a stay appropriate.
Halliwells LLP [2009] EWHC 319. Since cross-claims can rarely be relied upon as a defence in
enforcement claims, they will not generally give rise to a stay
17.03 As to the parties’ costs, the adjudicator has no general of execution: Interserve Industrial v Cleveland Bridge [2006]
power to make any order as to the parties’ respective costs of EWGC 741, and the former argument is thus likely to fail. A
the adjudication. No such power is provided by the HGCRA or stay of execution is likewise generally unlikely to be granted
the Scheme. There are, however, two routes by which an adju- merely because the judgment debtor raises a dispute as to the
dicator can properly make such an order. First, the parties may financial soundness of the judgment creditor. Nevertheless, it is
expressly or impliedly grant such jurisdiction to the adjudicator: likely to be granted if the judgment creditor is insolvent; and,
Northern Developments v J&J Nichol [2000] BLR 3. Second, by even if insolvency cannot be proved, it may be granted if (a)
section 108A of the HGCRA, the adjudicator will be entitled to the creditor is likely to be unable to repay the judgment sum;
make a cost award if the parties have so agreed in writing after (b) it had not been in this financial position when the relevant
the giving of notice of intention to refer the dispute to adjudica- contract was made; and (c) its financial position was not due to
tion: Enviroflow v Redhill [2017] EWHC 2159. the judgment debtor: Wimbledon v Vago [2005] EWHC 1086.

18 Enforcement 20 Jurisdictional defences to


enforcement proceedings
18.01 If the losing party does not voluntarily honour the deci-
sion, the successful party will need to enforce it. Proceedings in 20.01 Jurisdiction depends first on whether the adjudication is
the Technology and Construction Court (‘TCC’) are the best and statutory, under the HGCRA, or contractual; i.e. arising from
speediest method of enforcement. A claim form and an applica- contractual terms which enable an adjudication which is outside
tion for summary judgment have to be issued. The procedure in, the ambit of the HGCRA. If it is statutory, the adjudicator will
and requirements of, Section 9 of the TCC Guide should be fol- have jurisdiction only if there is a construction contract which is
lowed. Generally, directions will be issued within three working within the definition in the HGCRA and which is not excluded
days of an application notice, and an enforcement hearing will by HGCRA or any exclusion Order (discussed above). Further,
ordinarily be held within around 28 days of the directions. The the adjudicator will have jurisdiction only if validly appointed
Pre-Action Protocol for Construction and Engineering Disputes and if there is a dispute which arises under the contract. If the
does not apply to such enforcement proceedings and thus does adjudication is contractual, jurisdictional limits will depend on
not delay matters. the contract, not on the provisions of the HGCRA.
18.02 A winding-up petition is an alternative but, it is thought, 20.02 The adjudication may also be outside the adjudicator’s
a less satisfactory method of enforcement. jurisdiction because (a) the adjudicator did not decide it in time;
Getting a fnal answer 255

(b) more than one dispute was referred; (c) the same dispute had a fair opportunity to answer or deal with are common. Such
been the subject of an earlier adjudication decision; (d) one or complaints arise more frequently in adjudication than in arbi-
more of the parties to the adjudication was not in fact a contract- trations, because the HGCRA subordinates the need to have the
ing party; or (e) the adjudicator decided a dispute which was not ‘right’ answer to the need to have an answer quickly: Carillion
the dispute set out in the notice of adjudication. Construction Ltd v Devonport [2006] BLR 15. For that reason, a
breach of this rule of natural justice must be material: Cantillon
20.03 If a defence based on lack of jurisdiction is to be raised, Ltd v Urvasco Ltd [2008] EWHC 282 (TCC). Arguments
the objecting party should ensure that it has not accepted the typically deployed include suggestions that the adjudicator has
jurisdiction of the adjudicator or waived its right to object addressed a matter or new material outside the scope of the
(paragraph 13.10 above). Parties are well-advised to reserve original dispute, has failed to address a matter in issue, has
their position on jurisdiction from the outset and make clear their failed to consider material adduced, has misused his or her
specific concerns on an ongoing basis: Aedifice v Shar [2010] own knowledge, or the knowledge or advice of others, without
EWHC 2106. affording the parties an opportunity to make submissions, or
has taken into account material adduced late in the process
by one party without affording the other party proper time to
21 Natural justice defences to consider and respond. Despite this plethora of arguments, such
enforcement proceedings challenges rarely find favour with the Courts. A rare example
of a successful challenge was in Beumer v Vinci [2016] EWHC
21.01 In this context, the relevant rules of natural justice are that 2283 where, unknown to the responding party (sub-contractor),
(i) the tribunal should be unbiased; and (ii) a party should know the adjudicator was also conducting a simultaneous adjudication
the case it has to answer and have a fair opportunity to answer involving the referring party (main contractor) and the project
it. In adjudication, there will also be a contractual duty to act employer, and in those two adjudications, the main contractor
impartially: section 108(2) of the HGCRA requires such a duty was advancing inconsistent positions. The Court held that the
to be imposed on the adjudicator. sub-contractor ought to have been informed of the information
made available to the adjudicator in the other adjudication and
21.02 In theory, bias can be established in two ways: either (i) to have known about the inconsistencies in the two cases being
by proving that the adjudicator was actually biased; or (ii) by advanced by the main contractor.
proving that the circumstances would lead a fair minded and
informed observer to conclude that there was a real possibil-
ity that the adjudicator was biased: Amec v Whitefriars [2004] 22 Severance
EWCA Civ 1418. The fair-minded observer must be assumed to
know all relevant, publicly available facts; must be assumed to 22.01 If lack of jurisdiction or breach of the rules of natural
be neither complacent nor unduly sensitive or suspicious; and justice invalidate part but not all of the adjudicator’s decision,
must be assumed to be perspicacious and able to distinguish it is possible that the bad can be severed from the good and the
between what is and what is not relevant: Lanes v Galliford Try good enforced: Cantillon Ltd v Urvasco Ltd [2008] EWHC 282
[2011] EWCA Civ 1617. (TCC).
21.02 Proof of either actual or apparent bias will rarely be pos- 22.02 That is generally so where more than one dispute has been
sible but, for example, in Glencot v Barrett [2001] BLR 207, the referred (either because permitted by the contract or because the
adjudicator was present during negotiations between the parties, parties have agreed that the adjudicator would have such power)
acted as a mediator, and had private communications with them. and the Court is thus able to sever one dispute from another.
There was thus an arguable case of bias.
22.03 It may also be the case where distinct elements of one dis-
21.03 A strand of law coming under the broad category of bias pute are clearly separate and where one element is not dependent
concerns pre-determination, where the decision-maker has, or on the other but, failing this, the entire decision will be unen-
has given the impression that, he or she has, already reached forceable: Lidl v RG Carter [2012] EWHC 3138.
a concluded decision before being in possession of all the rel-
evant evidence and arguments: see Lanes. This might arise if an
adjudicator has determined a dispute between an employer and 23 Getting a fnal answer
main contractor, and the same issues then arise for considera-
tion by the same adjudicator in a subsequent claim by the main 23.01 A party dissatisfied with the adjudicator’s decision can
contractor to pass the losses down to a sub-contractor: Pring v commence legal proceedings or, if the contract contains an
Hafner [2002] EWHC 1775. Alternatively, it might arise where arbitration clause, an arbitration, to obtain a final decision on
an adjudicator issues a decision before the end of the adjudica- the dispute. In some cases, the prospect of further proceedings
tion process: see John Sisk v Duro Felguera [2016] EWHC 81. leads to a settlement, which modifies the decision. There is,
however, no obligation on either party to take matters further,
21.03 Complaints by the losing party to the effect that the and in practice, the adjudicator’s decision is often accepted and
adjudicator’s decision is based on a point which it did not have thus becomes the final decision on the dispute.
24
Litigation
ANTHONY SPEAIGHT QC

1 Methods of dispute resolution 2 Litigation in England and Wales


1.01 It is in the nature of human life that from time to time 2.01 Construction litigation in England and Wales usually takes
there are disagreements. Sometimes such disputes can be sorted place in the Technology and Construction Court (the ‘TCC’).
out by agreement; or be ruled upon by an agreed decision- The TCC is a specialist division of the High Court. There are at
maker. But if they cannot, the parties have to resort to some any one time about a half a dozen permanent TCC judges who
outside agency. In earlier times and in more primitive socie- sit in London. In addition, there are some 20 Circuit Judges
ties, that agency tended to be the ruler – a feudal lord, a tribal based in other major cities who sit as TCC judges when the
chief, or possibly the king. In all modern societies, the outside need arises in their area. The modern TCC was created in 1998.
agency provided for dispute resolution takes the form of a Previously, there had been a similar arrangement under which
court system. a number of judges had the less than meaningful designation
of ‘Official Referees’. The TCC is presided over by a High
1.02 Litigation is the process of dispute resolution before a Court judge. The first appointee to this position was Mr Justice
court. In many spheres of activity, litigation is almost the Dyson, who had been a distinguished construction practitioner
invariable mode of dispute resolution. But in the construction at the Bar, and who, as Lord Dyson, later held the second
world today, it is not the only, nor even the most common, highest judicial office in the land, Master of the Rolls. The
process. Many construction contracts, especially international standing of the TCC has risen further in recent years as result
ones, contain an arbitration clause, by which the parties agree of initiatives introduced under the inspiration of a subsequent
to be bound by the decision of a private dispute resolution presiding judge, Mr Justice Jackson, whose name was known to
mechanism: for many years, arbitration was the most com- many architects as one of the co-authors of the most authorita-
mon mode of determining domestic construction disputes. tive legal textbook on professional negligence. In recent years,
Arbitration differs from litigation in that it takes place in the judicial make-up of the London court has developed from
private, and that the decision-maker, often an architect, is a situation in which only a few cases were heard by a High
appointed by agreement of the parties. On the other hand, Court judge to a system in which several High Court judges
the actual nature of the proceedings is similar to litigation: are hearing TCC cases almost full-time. The TCC has recently
the hearing is preceded by formal pleadings and exchange of been brought under an umbrella embracing other commercial
documents, and witnesses give evidence on oath. Arbitration is and similar courts called the Business and Property Courts of
discussed in the following chapter. Today, arbitration has been England and Wales. This new administrative arrangement has,
overtaken in popularity by adjudication, around which there has to date, made little difference to the activity of the TCC, whose
developed a substantial body of law of its own. Adjudication prestige amongst construction lawyers is today as high as it
is similar to arbitration in that the decision-maker may well be has ever been.
an architect, but the procedures are far more summary, and the
decision is binding for only a temporary period. By legislation 2.02 All citizens have the right to conduct their own cases in
enacted in 1996, a right to adjudication is now compulsory in court, but construction disputes are normally matters of such
almost all construction contracts. Such is the attraction of a complexity that litigants in person are almost always at a real
quick decision that not only is adjudication today being used disadvantage to parties who are legally represented. In prac-
with great frequency, but it is relatively unusual for adjudica- tice, almost all litigants in the TCC are represented. Unless a
tor’s decisions to be challenged in subsequent litigation or party is acting in person, the administrative aspects of litiga-
arbitration. What is often the subject of court proceedings is tion, such as issuing the claim form, must be undertaken by a
the question whether an adjudicator’s decision is enforceable: member of a profession which has been approved to act as a
the grounds on which a successful challenge can be made are ‘litigator’. Although barristers can today obtain authorisation
few, but parties anxious not to pay often try to make out an to act litigators, and although solicitors can acquire the right
argument for non-enforcement. Of growing popularity, too, is to act as higher court advocates, in practice in the High Court,
mediation, which refers to consensual meetings by parties with one finds each branch of the legal profession in its traditional
a neutral facilitator: the success rate in achieving a settlement role. Litigants who are wise will instruct a solicitor with good
at mediations is very high. Nevertheless, litigation remains the litigation experience. The solicitor almost invariably instructs a
fallback method of dispute resolution. The existence of litiga- barrister to act as advocate in the TCC. There is a corps of about
tion underpins the efficacy of the other modes. 200 barristers who have specialist experience of construction

257
258 Litigation

work. They are members of the Technology and Construction 3 Litigation in Scotland1
Bar Association. In addition to their advocacy work, they often
undertake advisory work, sometimes on the direct instruction 3.01 The court system in Scotland has been described in
of an architect. Section 8 of Chapter 5. Architects are more likely to be involved
as parties or witnesses in civil actions in the Court of Session or
2.03 The venue for lower value civil disputes is the County the sheriff court. A party commencing an action (the ‘pursuer’)
Court. There are County Courts in many cities and towns. An does so by serving a writ setting out his case (a ‘summons’ in the
architect would be likely to use a County Court if obliged to sue Court of Session or an ‘initial writ’ in the sheriff court) on the
a client for unpaid fees. In such proceedings, an architect might party being sued (the ‘defender’). The parties have fixed times
choose to act in person in relation to the administrative aspects. in which the defender lodges his or her answers (‘defences’),
The court office will provide factual information as to the proce- and they adjust their written cases in response to each other. A
dures. If, however, the response to the fees claim should be, as document called the ‘closed record’ (the latter word unusually
is sometimes the case, an allegation of professional negligence, having its emphasis on the second syllable!) is then printed
then, of course, insurers should be notified, and a full legal team which contains the final version of each party’s written case.
will certainly be required. There may then be a legal debate between the parties as to the
legal soundness of their cases, assuming that they are factually
2.04 Civil procedure has recently undergone major changes. The true, or as to the sufficiency of detail specified. Cases which can
Civil Procedure Rules, which came into force in April 1999, only be resolved by hearing evidence as to the facts come before
implemented ideas proposed by Lord Woolf. These Rules apply a single judge or sheriff for a hearing known as a proof, when
to both High Court and County Court. A significant feature of evidence is given by witnesses and speeches are then made on
the new regime is encouragement of settlement. There are likely behalf of each party. At the end of a proof, the judge or sheriff
to be penalties in the payment of higher costs to be paid to the usually does not give an immediate decision, but gives a later
other side if parties unreasonably refuse to mediate, or decline written decision. In the Court of Session, some cases may be
to accept an offer in settlement, or fail to disclose sufficient heard by a judge and jury of twelve (a ‘jury trial’) instead of
information at an early stage. In fact, considerable exchange of by a judge alone. There are also jury trials in the All Scotland
information is expected to take place even before proceedings Sheriff Personal Injury Court based at Edinburgh Sheriff Court.
are commenced. The Pre-Action Protocol for Construction and Since 1994, in the Court of Session, there has been a special
Engineering Disputes requires not only the supply in correspond- ‘fast-track’ procedure for Commercial Action, available to par-
ence of details of what parties will be saying but also an off-the- ties with business-related disputes.
record meeting. Currently there is a fresh impetus in procedural
changes aimed at reducing the high cost of dispute resolution,
including controlling the cost of disclosure of documents, the
number of which has greatly increased with the advent of email
and electronic files. 1 This section was written by Catriona MacLeod.
25
Arbitration
MELANIE WILLEMS

1 What is arbitration? important role on projects, and therefore also in any ensuing
disputes. Under a number of construction contracts, architects
1.01 Arbitration is a process whereby parties agree to refer an certify works and issue certificates (including final certificates).
existing, or future, dispute to the determination of one or more Architects also commonly act as experts in arbitration proceed-
independent persons (the arbitrator or the tribunal) in a judicial ings. Finally, an architect may also be appointed as an arbitrator.
manner. The decision of the arbitrator is expressed in an award,
which (subject to satisfying certain legal requirements relating
to the manner in which the decision is made) will be binding on 3 The purpose of this chapter
the parties and enforceable in law. English law recognises and
supports the arbitral process by providing a statutory framework 3.01 The purpose of this chapter is to provide architects with
for arbitrations, set out in the Arbitration Act 1996 (the ‘Act’). a summary of the legal framework for arbitrations and of the
arbitral process. The chapter is not intended to be a manual on
1.02 Arbitration is a consensual process. Unless the parties how to conduct an arbitration, nor is it a comprehensive refer-
have agreed to refer their dispute to arbitration, there can be no ence work on the topic. There are many substantial books which
arbitration. To explain this by an example, if a creditor claims fulfil these roles and interested readers should refer to the bibli-
that a debtor owes him money, unless the parties have agreed to ography at the end of this book for more information.
resolve their disputes in a different way, the creditor can com-
mence a court action (litigation) to recover the debt, and the 3.02 This chapter also briefly mentions the importance of other
debtor cannot prevent him from commencing the proceedings. methods for resolving disputes, such as adjudication and media-
However, the creditor could not unilaterally refer the dispute to tion, which have evolved as alternatives to both litigation and
arbitration. Parties resolve their disputes by arbitration because arbitration.
that is what they have agreed to do.
3.03 Because of the time and cost involved in resolving a detailed
1.03 As arbitration can exist only where there is an agreement construction dispute formally by way of litigation or arbitration,
between the parties, any arbitrator should comply with any proce- the parties often attempt to resolve their dispute through such
dure the parties have agreed for the arbitration. Giving the parties ‘alternative’ means of dispute resolution. Arbitration users
the possibility of procedural control, arbitration offers a flexible sometimes complain that the procedure seems akin to litigation
method of resolving disputes that fits the circumstances at hand. in court, with some procedural aspects appearing cumbersome
Further, the parties can choose the decision-maker for his or her and expensive (although, with the right arbitrator, arbitration
particular skill or expertise relevant to the matter at hand. can still offer an expeditious and efficient method of reaching a
formal decision). Pressure therefore grew for alternatives to both
litigation and arbitration. It has, of course, always been possible
for parties to resolve their disputes by negotiation and agree-
2 The relevance of arbitration ment. However, negotiating a settlement to a dispute is often
law to architects difficult, and so a number of techniques have evolved which are
designed to help the parties to achieve a negotiated settlement of
2.01 Architects are almost bound to come across arbitration at their disputes. These techniques have become known by the col-
some point during their professional careers for two principal lective name of ‘alternative dispute resolution’ or ‘ADR’. ADR
reasons. First, the standard forms of agreements used in the con- is now widely recognised as a successful method of resolving
struction industry (including the standard terms of engagement disputes cheaply and quickly. A number of construction industry
for architects) often provide that disputes will be determined standard forms incorporate ADR into their dispute resolution
by arbitration and not by the courts. Second, the construction clauses. ADR is likely to continue to be used increasingly in the
industry is a fertile source of disputes. Indeed, the construction construction industry, so it is important that architects are aware
industry has developed its own model rules for arbitration, the of the main ADR techniques.
Construction Industry Model Arbitration Rules (‘CIMAR’),
published by the Joint Contracts Tribunal. 3.04 Reference will be made to a number of standard forms and
other documents, using the following abbreviations:
2.02 An architect may also be required to give factual evi-
dence during an arbitration arising out of a project in which 1 JCT 2016: the Joint Contracts Tribunal Standard Form of
he or she has been involved. Contractually, architects play an Building Contract, 2016 edition (as subsequently amended).

259
260 Arbitration

2 RIBA 2018: RIBA Standard Professional Services Contract obligations and duties under Section 33 at the forefront of their
2018. minds throughout an arbitration.
3 CIMAR 2016: the Construction Industry Model Arbitration
Rules 2016. 4.05 The Act was generally welcomed as a substantial improve-
ment to the law of arbitration. It sets out the law in a simple and
logical manner which should make the law intelligible to all. In
4 The Arbitration Act 1996 addition to governing the relationship between arbitrators and
the courts, the Act also supplements any arbitration agreement
4.01 Arbitration in England and Wales has now been governed (which can, in practice, be very succinct, as short as simply
by the Arbitration Act 1996 (the ‘Act’) for more than two dec- referring to ‘arbitration’ in the contract) by offering a fallback
ades. It is generally thought amongst arbitration practitioners position as regards the most important procedural aspects of the
and users alike that the Act introduced a welcome reform of arbitration. However, it is important to recall that this fallback
the law relating to arbitration, which continues to be a popular position can (often) be superseded by an agreement between
alternative to litigation in the High Court. When the Act was first the parties. To illustrate this function of the Act by way of an
introduced, there was a feeling that arbitration in England was in example, parties may not have spelt out in their contract how the
danger of losing its way. In a number of arbitrations, the involve- arbitrator(s) should be appointed. If the parties have not agreed
ment of the High Court became necessary (sometimes because of how this is to occur, the procedure set out in Sections 16 and
‘tactical’ applications to the court made by a recalcitrant party to 17 of the Act will apply. Arbitration proceedings that rely heav-
the arbitration), increasing time and cost. Due to the state of the ily on the Act to fill in the procedural blanks left unaddressed in
law prior to the Act, the courts did not universally recognise that the contract are sometimes referred to as ‘ad hoc’ arbitrations.
an agreement to arbitrate between the parties should supersede
the jurisdiction of the courts, which produced judicial decisions 4.06 However, the Act only applies to arbitration agreements
seen as interfering with or (at worst) frustrating the arbitral pro- which are made or evidenced in writing (see later for com-
cess. In many cases, awards by arbitrators were challenged and ments on this requirement). The Act defines an ‘arbitration
became the subject of scrutiny by the courts, despite one view agreement’ as follows: ‘an agreement to submit to arbitration
that the courts are not meant to hear appeals from arbitrators, as present or future disputes (whether they are contractual or not’
arbitration is intended to produce a final decision. (sub-section 6(1)).

4.02 The preamble to the Act states that its purpose is to ‘restate
and improve the law relating to arbitration …’. The Act has now
firmly and formally adopted many concepts and principles found 5 The importance of deciding whether
in arbitration laws internationally, inspired by the UNCITRAL a process is or is not ‘arbitration’
Model Law for arbitration (published under the auspices of the
UN Commission for International Trade Law). These principles 5.01 The most important reason for distinguishing ‘arbitration’
include party autonomy (parties are free to decide the procedure from other decision-making or dispute-resolution processes is that
for ‘their’ arbitration), the fact that arbitration takes precedence if the process is arbitration, and, in particular, if it is governed
over litigation (so no court proceedings can be commenced if by the Act, the parties will be afforded a number of legal rights
the parties have concluded an arbitration agreement in their con- and remedies in respect of the process. Ultimately, the parties
tract), and limiting the grounds on which arbitral decisions can may seek to use the powers of the courts to enforce those rights
be challenged in the courts (which can be restricted to a serious or to obtain the remedies – subject, of course, to the role of the
procedural irregularity affecting the arbitral process). Under the courts with regard to arbitration being supportive with any judicial
Act, the role of the court is to be supportive of arbitration, and review limited to what is deemed necessary in the public interest.
judicial practice has shown that most challenges to arbitrator’s
decisions are dealt with robustly. 5.02 As one can imagine, there are a number of situations where
a third party may be called on to resolve a contractual dispute
4.03 Much of the Act reflects the three overriding considerations between others. If the agreement in question expressly describes
set out in section 1: the process as ‘arbitration’, then it will be clear that the third
party must act as an arbitrator and that, if he or she does, his or
(a) ‘The object of arbitration is to obtain the fair resolution of her decision (the award) will be enforceable in law. But even if
disputes by an impartial tribunal without unnecessary delay the agreement does not expressly refer to arbitration, the courts
or expense; might still consider the process to be an arbitration in substance.
(b) The parties should be free to agree how their disputes are It is important in practice to be clear as to the capacity of any
resolved, subject only to such safeguards as are necessary decision-maker that is appointed by the parties to a contract. For
in the public interest; and example, a third party may be charged with deciding an issue as an
(c) The court should not intervene in arbitrations save as expert (the relevant clause may refer to the third party acting ‘as
expressly provided in the Act.’ an expert, but not as an arbitrator’). In contrast with arbitration,
expert determination does not require the expert to follow a ‘judi-
4.04 The Act imposes a positive duty on any arbitral tribunal to cial process’ (such as, for example, considering submissions from
ensure that these objectives are met. Section 33 provides that both parties instead of deciding purely on the basis of the decision-
the Tribunal shall: makers own expertise) and any expert is not automatically bound
to adhere to the rules of natural justice (or ‘due process’). Unless
(a) ‘Act fairly and impartially as between the parties, giving the expert has committed fraud, his or her decision will generally
each party a reasonable opportunity of putting his case and bind the parties, even if it appears to be manifestly wrong.
dealing with that of his opponent; and
(b) Adopt procedures suitable to the circumstances of the par- 5.03 Arbitration has the following characteristics which can be
ticular case, avoiding unnecessary delay or expense, so as to contrasted from other methods of resolving disputes:
provide a fair means for the resolution of the matters falling
to be determined.’ 1 There must be a valid agreement to arbitrate. In legal terms,
an arbitration agreement must either form part of a valid,
Arbitral tribunals are required to comply with this general duty binding contract between the parties, or it must amount to
in conducting the arbitral proceedings, in their decisions on mat- such a contract itself. In other words, the parties must have
ters of procedure and evidence, and indeed in the exercise of all the relevant capacity (required by law) to make a contract,
other powers conferred by the Act. Arbitrators should have their the terms of the contract must be sufficiently clear for it
The advantages and disadvantages of arbitration compared with litigation in court 261

to be enforceable and there must be consideration, etc. All negotiations aided by an independent third party who
these issues are dealt with in respect of contracts generally does not, however, reach any decisions). In mediations,
elsewhere in this book. Arbitration agreements are consid- it is of the essence of the process that any view about
ered in more detail later. the dispute expressed by the mediator will not be binding
2 The decision made by the process will be a final and bind- on the parties. Arbitration should also be contrasted with
ing determination of the parties’ legal rights, enforceable in ‘adjudication’, which is governed by the Housing Grants
law. This is to be contrasted with, for example, an agree- Construction and Regeneration Act 1996 (see further para-
ment to engage in mediation (a form of ADR, a structured graph 5.04 below)

3 The arbitrator is obliged to act impartially. He or she should into each construction contract that does not already contain
be independent of the parties, even when appointed as the acceptable adjudication provisions. The decision of any statutory
nominee of one of them on a tribunal of three arbitrators. adjudicator is ‘interim but binding’. This means that the decision
4 Arbitrators are obliged to carry out their functions in a judi- is binding on the parties until the dispute is finally determined by
cial manner and in accordance with the rules of ‘natural jus- legal proceedings (commonly arbitration) or by agreement of the
tice’. This feature distinguishes the arbitration process from parties. The underlying principle in adjudication is sometimes
various other dispute resolution processes which are to be referred to as ‘pay first, argue later’, and is intended to assist
found in commercial contracts, such as determination by an with cash flow on ongoing projects. Any more formal dispute
expert (see above). Experts can resolve a dispute by making resolution proceedings than adjudication are meant to be post-
their own enquiries or by using their own knowledge of the poned until the end of the project – which (hopefully) will have
subject matter of the dispute. Apart from exceptional cases been completed on the basis of the adjudicator’s interim, but
(commonly found in shipping and commodities arbitrations) binding determination.
an arbitrator cannot do this.
Architects are sometimes said to be acting in an arbitral 5.05 Adjudications are meant to be completed within 28 or
or ‘quasi arbitral’ manner when considering and certifying 42 days. They are sometimes described as ‘rough justice’, since
applications for extensions of time and other claims under the proceedings are fast moving and mistakes can be made.
the building contracts, but that description is wrong. An Adjudication proved extremely popular in the industry after its
architect who carries out such valuation and certification introduction, and came to be used to resolve a large number of
functions is not acting as an arbitrator. The architect in this complex disputes (perhaps more complex than had been envis-
context has a duty to act fairly, but does not have a duty aged by the legislative). The increasing popularity of adjudica-
to act judicially. tion has led to a fall in arbitrations, and also court litigation, in
5 The arbitration tribunal must be appointed by the parties, or the construction industry. Some years ago now, complaints were
by a method to which they have consented (subject to the heard from judges in the construction courts that a significant
default appointed procedure in the Act). This emphasises the amount of their business related to arguments over the enforce-
consensual nature of the process. ment of adjudicator’s decisions, meant to be interim only. In
6 The parties to the arbitration process must be the same as recent years, there appear to have been the signs of a reversal of
the parties whose rights are being determined, and who the trend in favour of adjudication. See, further, Chapter 23 in
will be bound by the arbitration award. In most construc- respect of adjudication.
tion industry arbitrations, there will be little doubt that this
requirement has been met, although it is, of course, impor-
tant to ensure that the right corporate parties enter into any 6 The advantages and
(sub)contracts containing the relevant arbitration agreement.
disadvantages of arbitration
5.04 Statutory adjudication under the Housing Grants compared with litigation in court
Construction and Regeneration Act 1996 is compulsory for
most written construction contracts: the statute has the effect 6.01 Because arbitration is a consensual process, it follows that
of writing a mandatory adjudication procedure (the ‘Scheme’) at some point, either when they are negotiating a contract, or
262 Arbitration

later, after a dispute has arisen, the parties have chosen arbitra- of the courts. Many countries are parties to the New York
tion. A positive choice for arbitration instead of litigation is Convention on the Recognition and Enforcement of Foreign
now necessary under the JCT 2016 Standard Form of Building Arbitral Awards (1958) (the ‘New York Convention’) and
Contract. The ‘default’ position under the JCT form is now in have agreed to recognise and enforce foreign arbitra-
favour of litigation, and the parties will need to adopt arbitra- tion awards, on reciprocal basis. While a judgment of
tion instead by making appropriate amendments to the contract the English courts will often be recognised and enforced
particulars (see Articles of Agreement 8 and 9). If parties do not in many countries, there are jurisdictions who recognise
opt for arbitration, disputes which cannot be resolved amicably English arbitration awards but not English judgments.
must be determined by the courts.
Comparison with court process
Advantages 6.03 All civil cases in the High Court and the county courts are
governed by the Civil Procedure Rules (which came into force
6.02 Arbitration has a number of potential advantages over court in 1999). At the time, the Civil Procedure Rules were hailed as a
proceedings: welcome reform of civil and commercial litigation. These rules
introduced a number of features aimed at streamlining the process
1 The technical expertise of the arbitrator: arbitration enables of litigation, including the concept of a proactive judge whose
the parties to choose their decision-maker. The parties may task will be to manage the conduct of the case. They also include
feel that they would prefer technical disputes to be decided an ‘overriding objective’ which requires the parties and the courts
by an arbitrator with the relevant technical expertise. This to ensure that cases are handled justly. Parties are to be on an
is, of course, a point of particular relevance in the construc- equal footing, and expense is saved by dealing with the case in a
tion industry, where disputes about the construction process manner which is proportionate to the amount of money involved,
may often involve technical, architectural, engineering, or the importance of the case, the complexity of the issues and the
quantity surveying/valuation issues. It should be noted that, parties’ financial position. The overriding objective which applies
notwithstanding any technical expertise the arbitrator may to court proceedings is, perhaps, analogous to the general duty
have, he or she should only decide the dispute in accord- imposed on arbitral tribunals by section 33 of the Act.
ance with the evidence presented by the parties. It is often
difficult to reach agreement after a dispute has arisen, so it 6.04 Construction industry disputes of any reasonable size are
is sensible to include a list of arbitrator candidates in the generally referred to a specialist court of the High Court now
contract at the outset, before any falling out. called the Technology and Construction Court (‘TCC’). In the
2 Privacy: arbitration proceedings are private and confidential major provincial centres, TCC business tends to be dealt with
as between the parties. Proceedings in court are (in general) by designated judges, although there is no separate TCC in
open to the public. The fact that a claim form has been issued those centres. Judges in the TCC are experienced in dealing
by one party against another is a matter of public record. It with construction industry disputes. They should be well aware
is often important to parties that their ‘dirty laundry’ should of the terms of most of the standard forms of contract used by
not be aired in the public forum of the courts. It is for this the industry and should quickly grasp the technical issues which
reason that arbitration clauses are often found in partnership arise. Traditionally, the TCC court has been at the forefront of
agreements (including architectural partnerships) where it adopting innovative procedures to reduce the delay and expense
is felt that public knowledge of a dispute between partners of litigation (even before the introduction of the reforms to
could be very damaging for the partnership business. the Civil Procedure Rules). Recent appointments to the bench
3 Flexibility: as noted above, the parties can have a great deal have included some experienced and respected construction law
of control over the procedure, for example, by choosing practitioners with many years’ experience, and have helped to
their own arbitrator, fixing the venue for the hearing, and alleviate criticism regarding the quality of some judgments.
setting the timetable for the dispute to be dealt with. It is an
underlying principle of the Act that, subject to certain man-
datory requirements, the parties are free to choose their own Disadvantages
procedures for the resolution of their disputes. In litigation, 6.05 One potential disadvantage of arbitration proceedings is
the rules are determined by the court, in accordance with the lack of an effective means to deal with disputes involving
the Civil Procedure Rules. Disclosure of documents (which more than two parties. This area requires careful consideration,
is explained later in this chapter) is an example of the dif- as it can be of practical importance in the construction industry.
ference. In litigation, standard disclosure of documents is Construction disputes may arise between the employer, architect,
nearly always required. In arbitration, disclosure is subject contractor, and sub-contractor, all relating to the same subject-
to the discretion of the tribunal. matter. For example, the employer wishes to recover damages aris-
4 The ability to exclude appeals: parties are sometimes keen that, ing from a defect which is partly caused by the architect’s design
whatever the decision on a particular dispute may be, it should and partly by the contractor’s poor workmanship. Unless special
be final and binding in the sense that it is not subject to an provision is made in the arbitration agreements of all relevant
appeal. It is not possible to agree to exclude rights of appeal (sub-) contracts, by which the various parties agree that all the
from a decision of the courts but such agreements are possible separate disputes can be determined by the same arbitral tribunal,
with respect to arbitrations (see below): the parties can agree to the disputes could be heard together. Even where such special
be bound by an arbitration award even if the tribunal has made provision is made, careful drafting is still required. Unless there
a mistake as to the law or the interpretation of the contract. are effective provisions of this nature written into the arbitration
5 The duty of tribunals to adopt procedures which are suitable agreements, even if the same arbitrator is appointed to deal with
to the circumstances of the case, avoiding unnecessary delay the various disputes between the different parties, he or she does
and expense: in practice, this can mean that arbitration pro- not have power to order the various arbitrations to be heard at the
ceedings are quicker and more economical than equivalent same time unless all the parties consent (see section 35 of the Act).
proceedings in court.
6 Powers of the tribunal: the tribunal may be granted powers by 6.06 Where no provision is made for such multiparty disputes
the parties, or by the Act, which a judge does not have. For (or where the specific circumstances which have arisen have not
example, the Act gives an arbitrator a wider power to award been addressed), the party who is ‘common’ to both disputes
interest on a compound basis than is available to the court. (and therefore party to separate arbitrations) may consider
7 Enforcement: in cases involving foreign parties, it can that there is a risk of prejudice through inconsistent decisions
sometimes be easier to enforce the arbitration award in the reached by the various arbitration tribunals. For instance, a main
foreign country than would be the case with a judgment contractor who is caught in the middle in this way may not have
The jurisdiction of the arbitration tribunal 263

the certainty that any claim from the employer can be passed 7.02 Also (by sub-section (3)), where parties agree otherwise
‘down the line’ to the subcontractor on the same factual basis on than in writing by reference to terms which are in writing, they
which the employer relied against the main contractor. For that make an agreement in writing. So, for example, an oral agree-
reason, section 35 of the Act allows parties to agree that (related) ment between an architect and employer which referred to the
arbitral proceedings may be consolidated or heard together. standard CA07 would satisfy the ‘in writing’ requirement of the
Act, because the CA07 are written and contain an arbitration
6.07 Examples of agreements which provided for multiparty clause (although under the 2018 version of RIBA’s appointment
disputes can be found in the JCT forms of main contract (see conditions, arbitration must be positively chosen in item K of
Conditions, Section 9.4.2 of the JCT Standard Form of Building the Contract Details). It is also possible (and indeed occurs fre-
Contract 2016) and sub-contracts which provide for multiparty quently in the construction industry) for contracts to be formed
arbitration in certain circumstances. These standard forms seek to not orally but by conduct: for example, if a subcontractor, having
do this by reference to CIMAR 2016, which both forms of contract been sent the main contractor’s proposed terms, starts work on
adopt as the applicable rules for arbitrations arising out of those site without referring to or objecting to the proposed contract
contracts. CIMAR 2016 provides detailed rules relating to the terms, the subcontractor may be held to be bound by these terms
joinder of two arbitrations and the appointment of the tribunal. It and any arbitration clause they contain.
is beyond the scope of this chapter to summarise the relevant rules,
save as to say that similar provisions in prior editions of the JCT 7.03 Because arbitration is a consensual process, the arbitration
forms of contract were effective to allow one tribunal to hear arbi- agreement is the very foundation of the process and can (or
trations relating to the same works arising under a JCT main and should) fulfil a number of important functions:
subcontract (see Trafalgar House v Railtrack [1995] 75 BLR 55).
1 The agreement defines the types or categories of dispute
6.08 Another possible disadvantage with arbitration is that it may that can be referred to arbitration. It therefore establishes,
be less effective than litigation at dealing with the reluctant defend- and limits, the scope of the jurisdiction of the arbitration
ant. Defendants may raise a number of weak defences or coun- tribunal. For example, Clause 10.8.1 of RIBA 2018 provides
terclaims simply as a means of delaying the day when they have that any ‘dispute or difference (except in connection with
to pay their creditors. The courts provide procedures for dealing the enforcement of any decision of an Adjudicator)’ may be
with defences which are obviously weak (such as applications to referred to arbitration if arbitration has been selected by the
‘strike out’ part of a case or to ask for early determination through parties under item K of the Contract Details.
summary judgment), in addition to providing a range of sanctions 2 The agreement establishes the composition of the arbi-
which can be used to prevent one of the parties from ‘dragging its tration tribunal or the method by which the tribunal
feet’ during the litigation process. The equivalent arbitration pro- will be appointed. For example, clause 10.8.1 of RIBA
cedures and sanctions are generally less effective, simply because 2018 assumes a sole arbitrator. It provides that ‘the dispute
the arbitral tribunal does not have the same powers of the court or difference shall be referred to a person to be agreed
to impose immediate sanctions for procedural transgressions dur- between the parties or, failing agreement, within 14 days …,
ing the arbitration. However, while there may be less danger of a a person nominated by the appointing body specified in item
party’s case being rejected if a time limit in an arbitration has been K of the Contract Details’ (this could be the President of
missed (as opposed to court, where that is the ultimate sanction), RIBA, but the parties will need to take a decision as to who
arbitrators can (and often do) mark their disapproval of a party’s appoints the arbitrator). The agreement should therefore
conduct in an award of legal costs at the end of proceedings. state the number of arbitrators, their qualifications and how
Arbitrators have a wide discretion when deciding whether to award they will be appointed. Ideally, it may also contain a list of
a successful party a share of its legal costs (arguably wider than the arbitrators that are acceptable to both parties, from which
discretion of the courts), and will consider unhelpful or obstructive the tribunal can be selected once a dispute has arisen. If the
conduct during the proceedings that may have led to increased agreement fails to deal with any of these matters, the Act
costs. As regards further perceived disadvantages of arbitration, provides default provisions to fill the gaps as noted above.
there is a view that means of enforcing an arbitral award are not 3 The agreement may prescribe the procedure or rules which
as fast as the means of enforcing a court judgment. the tribunal should follow. This may be done by setting out
the procedure extensively (or specific procedural points) or,
6.09 Notwithstanding some of the drawbacks of arbitration, there more usually, by reference to some other document which
is no doubt that arbitration can be used to great advantage. Where contains the procedure. For example, the JCT Standard
the arbitral tribunal makes sensible use of procedures appropriate Form of Building Contract 2016 incorporates CIMAR 2016
to the particular circumstances of the case, some of which are (Conditions, Section 9.3). Particularly in projects involv-
explicitly provided in the established rules of arbitration (such ing international parties, the arbitration rules of the court
as the short hearing procedure and documents only procedure of arbitration of the International Chamber of Commerce
permitted by CIMAR 2016), the process can offer an efficient (‘ICC’) or of the London Court of International Arbitration
and economical way of resolving a dispute. Whatever the rela- (‘LCIA’) are a popular choice.
tive merits of arbitration when compared to litigation, a topic 4 The arbitration agreement may make other provisions in
on which it is difficult to generalise in any event since much relation to the rules of law which the arbitration tribunal
depends on the attitude of the parties and the decision-maker in will apply. In English arbitration agreements which do
question, it is clear that arbitration clauses will continue to be not involve foreign parties, this provision is not usually
incorporated into construction industry standard forms. necessary.

Each of these matters is considered below.


7 The arbitration agreement
7.01 The Act applies only where the arbitration agreement is in
writing. Section 5(2) of the Act provides that there is an agree- 8 The jurisdiction of the
ment in writing: arbitration tribunal
1 If the agreement is made in writing (whether or not it is 8.01 An award made by a tribunal which, in fact, does not have
signed by the parties); jurisdiction to determine the dispute is not enforceable and can
2 If the agreement is made by exchange of communications be set aside. Confirming the jurisdiction of the arbitral tribunal
in writing; or is therefore an important starting point: as set out below in para-
3 If the agreement is evidenced in writing. graph 8.02, where an arbitration agreement exists, the particular
264 Arbitration

dispute must fall within the scope of disputes covered by that not mentioned in the notice of arbitration (or even in existence
agreement, otherwise the tribunal will not have jurisdiction to at that time) must be referred to the tribunal either as agreed
determine that dispute. It is, of course, also open to the parties between the parties, or through service of further notices of
to agree, after the contract has been signed without an arbitration arbitration. However, if new and different disputes arise after
clause and after a dispute has arisen, that this particular dispute a first notice of arbitration, and additional notices require to be
(only) should be resolved by arbitration. In all cases, the arbitral served, all the disputes will not necessarily be determined by
tribunal can, however, only determine disputes which are actu- the same arbitral tribunal, unless the rules permit this (CIMAR
ally referred to it by the ‘notice of arbitration’ (the document 2016 give the tribunal a discretion to allow additional disputes
which begins the arbitration process), or which the parties later to be referred to the same tribunal, and the ICE Arbitration
agree should be determined by the tribunal. Procedure 2012 contains a rule allowing notices of further dis-
putes or differences).
8.02 It may be easy to determine whether there is actually an
arbitration agreement (a matter of checking the contract condi- 8.06 This is especially important where the claim may shortly
tions or other contractual documents), but what if the agreement become time barred by reason of the Limitation Act 1980,
which contains the arbitration clause never came into effect? For a ‘time bar’ being a procedural defence to a claim aimed at
example, the parties work to a letter of intent which is never having claims determined before the evidence becomes stale
converted to a binding contract, or the contract is set aside due to the passage of time. To avoid a ‘time bar’ defence, it is
because it is void, or is terminated as a result of one party’s necessary to institute formal proceedings in respect of the claim
breach? It might be thought that in any of these circumstances within the relevant time limit (which may well be six years for
there would be no arbitration agreement because the substan- breaches of contract), so a notice of arbitration will be required.
tive agreement which contains the arbitration clause does not A new claim, which is outside the scope of the original notice of
exist or is terminated. However, such a result is undesirable. It arbitration, introduced by a party after the limitation period has
is logical to assume that parties who chose to refer any disputes expired, could be defeated by a Limitation Act defence.
under the contract to an arbitrator also wanted that arbitrator to
decide whether or not the contract itself exists or is valid in the 8.07 The arbitration clause or the substantive contract may also
circumstances. Section 7 of the Act achieves this. It confirms include time limits by which claims must be notified or referred
the principle that the arbitration agreement is free-standing and to arbitration. Failure to comply with these time limits can pro-
has its own existence quite apart from the underlying contract. vide a complete defence to the claim. However, section 12 of
The Act states that ‘unless otherwise agreed by the parties, an the Act gives the court power to extend time in certain circum-
arbitration agreement which forms or was intended to form stances (described in more detail below). While time limits for
part of another agreement (whether or not in writing) shall not the assertion of claims may seem procedural or technical in
be regarded as invalid, nonexistent or ineffective because that nature, such conditions precedent have been enforced by both
other agreement is invalid, or did not come into existence or arbitrators and the courts. They are matters that can affect the
has become ineffective and it shall for that purpose be treated substantive rights of the parties. Arbitration notices served in
as a distinct agreement’. The arbitration agreement is therefore disregard of time limits or other conditions precedent to arbitra-
separate from the substantive agreement in which it may be tion are likely to have no effect.
incorporated.

8.03 A further key question is whether the dispute in question


falls within the scope of the arbitration agreement: did the par- 9 Who decides where the
ties intend for this particular dispute to go to the arbitrators? tribunal has jurisdiction?
In most construction contracts which adopt one of the standard
forms, there will be little doubt about this issue. The arbitra- 9.01 Who should decide if a party contends that the tribunal has
tion agreement in Article 8 (Articles of Agreement) of the JCT no jurisdiction to determine the dispute, for example because
Standard Form of Building Contract 2016 applies to ‘any dispute there is no arbitration agreement? Strict logic might suggest
or difference between the Parties of any kind whatsoever aris- that the tribunal cannot decide that question because, if there is
ing out of or in connection with this Contract, whether before, no arbitration agreement, there is no validly appointed tribunal.
during the progress or after the completion or abandonment of However, in practice, someone must decide this question, and it
the Works’, but subject to certain specified exceptions. It is hard seems sensible to trust the parties’ arbitral tribunal to decide on
to imagine any dispute between the employer and the contrac- its own jurisdiction, and this is confirmed by the Act.
tor relating to the particular contract which might fall outside
the scope of this arbitration clause (other than matters which 9.02 Section 30 of the Act provides that, unless otherwise
fall within the specified exceptions). Referring to all disputes agreed by the parties, the arbitral tribunal may rule on its own
‘arising under’, ‘out of’, or ‘in connection with’ the contract substantive jurisdiction, which will include questions such as (i)
ensures that the arbitration agreement should be wide enough to whether there is a valid arbitration agreement; (ii) whether the
cover claims in tort as well (such as, for example, allegations of tribunal has been properly appointed (respecting any procedure
misrepresentation or common law negligence). agreed for the purpose between the parties, with no arbitrator
suffering from a conflict of interest prevent him or her from
8.04 While a dispute may fall within the scope of the arbitra- taking up office); and (iii) what matters have been referred to
tion clause, it is also necessary to consider whether there is any arbitration in accordance with the arbitration agreement and the
preliminary step to be completed before the dispute is capable notice of arbitration. Any such ruling by the tribunal may then
of being referred to arbitration. Care should be taken when be challenged by proceedings in court, subject to the specific
considering such preliminary steps, or time limits, that are set conditions attached to such a challenge by the Act. A party who
out in arbitration agreements: they should be complied with (see wishes to object to the substantive jurisdiction of the tribunal
further paragraph 8.07 below). must raise this objection not later than the time he takes the first
step in the proceedings to contest the merits, otherwise he or she
8.05 Most arbitration clauses amount to agreements to refer will be deemed to have accepted the tribunal’s jurisdiction by
future disputes to arbitration (as opposed to agreements to participating in the proceedings before it.
refer a particular dispute to arbitration, which must be made
after that dispute has arisen). The disputes actually referred to 9.03 Any objection during the course of the arbitration that the
arbitration are (or should be) defined in the claimant’s notice tribunal is exceeding its substantive jurisdiction must be made
requesting arbitration. The notice of arbitration should describe as soon as possible after the matter alleged to be beyond the tri-
the dispute referred to in clear terms. Further, different disputes, bunal’s jurisdiction first comes to the party’s knowledge. Under
Prescribing the arbitration procedure 265

section 32 of the Act, the court may, on the application of a agree between themselves: section 21 of the Act is intended to
party, determine any question as to the substantive jurisdiction deal with situation.
of the tribunal. However, applications to the court of this kind
may only be made with the agreement of all other parties to the 11.03 Although an arbitrator may have been appointed by only
proceedings, or with the permission of the tribunal. Even then one of the parties, it is not that arbitrator’s function to act as a
the court must be satisfied that the determination of the question ‘champion’ of, or advocate for, the party who appointed him
to be put to it is likely to produce a substantial saving in costs, or her. Any suggestion of a party-appointed arbitrator openly
and that the application has been made without delay, and there favouring the party that appointed him or her would cause
is good reason why the matter should be decided by the court doubts as to the regularity of the arbitral process, and could ulti-
(and not the tribunal). mately lead to any award being challenged. The party-appointed
arbitrator must be independent of both parties and act impartially
at all times. He or she must hear the evidence, listen to the argu-
10 The composition of the ment, and then make the decision in the proper way.
arbitration tribunal
10.01 The second function of the arbitration agreement is to deal 12 The qualifcations of arbitrators
with the number of arbitrators and how they are to be appointed.
It may also deal with other matters relating to the tribunal, such 12.01 In this context, the term ‘qualification’ may cover not
as their desired qualifications and (in international agreements) only academic or other qualifications to act as an arbitrator, but
nationality of the arbitrators. Although highly desirable, it is not also any other particular quality that the arbitration agreement
essential that the arbitration agreement deals with these matters. specifies that the arbitrator should have. As regards the latter, the
If it does not, the Act will provide the missing essential ingredi- parties are free to specify what characteristics or experience the
ents. As before, in the absence of agreement between the parties arbitrator shall have, though they should be mindful of the trap
on the point, the Act provides the following: of specifying the perfect arbitrator – who may not be available
to act when a real dispute arises.
1 Section 15 of the Act provides that arbitration means a sole
arbitrator. 12.02 It is not necessary for an arbitrator to have any particu-
2 Section 16 of the Act sets out the procedure for appointing lar formal qualification (to enable him or her to take up an
the arbitrator or arbitrators. If the tribunal is to consist of appointment), but it is, of course, desirable that the arbitrator
a sole arbitrator, the parties are jointly to appoint the arbi- should have experience of acting as an arbitrator and, ideally,
trator. If the tribunal is to consist of two arbitrators, each be familiar with the legal areas that may be relevant to disputes
party is to appoint one arbitrator. In case of three arbitrators, that are likely to arise under the contract in question. Arbitrators
each party is to appoint one arbitrator and those two arbitra- appointed in construction disputes are generally experienced
tors are to appoint a third arbitrator as the chairman of the legal practitioners, or have an engineering/surveying background
tribunal. (some hold both legal and technical industry qualifications).
3 Section 17 of the Act aims to offer a solution where the
appointment process breaks down because a party does not 12.03 Where the appointing body is one which maintains a list
cooperate. It provides that where each of two parties is to of arbitrators (such as the Chartered Institute of Arbitrators, or
appoint an arbitrator and one party refuses or fails to do so, the RIBA, or the RICS) it is likely that the appointed arbitra-
the other party, after giving notice to the party in default, tor will have such experience and, in the case of the Chartered
may appoint his arbitrator as sole arbitrator. In the event of Institute, the person nominated will almost certainly be a fellow
a failure of the procedure for the appointment of the arbitral of the Chartered Institute and have undertaken further practical
tribunal, and in the absence of agreement between the par- training as an arbitrator.
ties, any party may apply to the court to exercise its powers
under section 18 of the Act. These include the power of the 13 Appointment of the tribunal
court to make any necessary appointments itself.
in multiparty disputes
11 The number of arbitrators 13.01 Multi-party disputes are a common feature of construc-
tion projects, and efforts have been made in the standard forms
11.01 While it is theoretically possible for an arbitration tribunal of contracts to provide a mechanism for these disputes to be
to be composed of any number of arbitrators, it is, however, very determined by the same tribunal. Where there is a multi-party
rare for there to be more than three. This is patently sensible for arbitration, the arbitration agreement should make particular
practical reasons, and importantly due to cost (since the parties provision for the appointment of the tribunal. For example, the
need to bear the fees of the arbitrators). Under section 15(2) of JCT 2016 forms of contract and the associated subcontract forms
the Act, unless otherwise agreed by the parties, an agreement adopt the CIMAR 2016 provisions relating to the appointment
that the number of arbitrators shall be two or any other even of the tribunal.
number shall be understood as requiring the appointment of an
additional arbitrator as Chairman of the tribunal, which avoids
the result being a ‘draw’.
14 Prescribing the
11.02 When three arbitrators are appointed, then the award of arbitration procedure
the majority of them will be binding unless the parties have
expressed a contrary intention. Although some construction 14.01 ‘Party autonomy’ is one of the underlying principles of the
industry disputes (particularly international disputes) are dealt Act. This means that, subject to certain mandatory provisions,
with by an arbitration tribunal of three arbitrators, it is most the parties are free to choose their own procedure. Typically,
common to provide that disputes be resolved by a sole arbitra- the procedure may be specified in the arbitration agreement
tor. This is the provision which is found in RIBA 2018 and (although as noted above, this is not always the case), often by
also in the JCT Standard Form of Building Contract 2016. adopting established rules of arbitration rather than setting out
Two-member arbitral tribunals have not proven popular in the the procedure at length in the contract itself. If no procedure is
construction industry, though there are procedures (notably referred to in the arbitration agreement or agreed separately by
in the shipping industry) which involve two party-appointed the parties (who, in principle, retain this freedom throughout
arbitrators and an umpire who decides if the arbitrators cannot the whole of the arbitration), then the arbitration tribunal is said
266 Arbitration

to be ‘master of its own procedure’. This is reflected in sub- 16.02 The form of notice need not be long or complex, but it
section 34(1) of the Act which provides that ‘it shall be for the is important that it should identify the matters to be referred
tribunal to decide all procedural and evidential matters, subject to arbitration in broad terms. It must also comply with the
to the right of the parties to agree any matter’. The arbitration requirements of the arbitration agreement or section 14 of the
clause in RIBA 2018 (clause 10.8.3) specifies that CIMAR Act, if the arbitration agreement is silent as to commencement.
2016 should apply to any significant claim. The arbitration notice should be served in accordance with the
provisions of the arbitration agreement or, if there are no provi-
14.02 Theoretically, leaving the procedure to be worked out by sions, the method of service that is set out in section 76 of the
an experienced arbitrator should introduce the flexibility for the Act. The notice may be served by any effective means. If a
arbitrator to ‘tailor’ the procedure to deal with the particular notice is served, addressed, prepaid, and delivered by post to the
dispute. Under the Act, the tribunal, in any event, has a positive addressee’s last known principal residence or principal business
duty to adopt appropriate procedures for the circumstances of the address or, if a body corporate, to the registered or principal
case (section 33). Most of the standard form agreements used office, it will be treated as effectively served.
in the construction industry specify the rules which will apply
(such as CIMAR 2016). These procedures present a range of
options for the parties and for the tribunal, giving the parties the 17 Arbitration procedure or rules
advantage of some certainty, and the tribunal the comfort that
if it adopts an option envisaged by the prescribed rules, then it 17.01 Once commenced, the arbitration will be conducted in
is less likely that its decision will be attacked on the grounds of accordance with the procedure or rules agreed between the par-
a serious procedural irregularity (under section 68 of the Act). ties, or failing agreement, as determined by the tribunal (being
Arbitration procedure is dealt with in a little more detail later the ‘master’ of the procedure). In either case, as already noted,
in this chapter. the tribunal must act fairly and impartially between parties, giv-
ing each party a reasonable opportunity to put its case and to
deal with that of its opponent and adopting procedures which
15 Other provisions which may be are appropriate for the circumstances of the case (section 33 of
found in arbitration agreements the Act). The objectives of the procedures in an arbitration can
be summarised as follows:
15.01 A number of other provisions may be included in
arbitration agreements. For example, the arbitration clause 1 First, to define the issues in the arbitration with sufficient
is often part of a longer dispute-resolution provision, which precision so that each side can prepare the evidence and
may require the parties to exhaust other means of resolv- argument which it will rely on to prove its case (or disprove
ing their disputes before referring the dispute to arbitration the other party’s case). The procedure should also ensure
(sometimes referred to as a ‘stepped’ or ‘tiered’ dispute reso- that neither side can be taken by surprise by evidence or
lution provision). The agreement may specify the manner in argument presented by its opponent.
which the arbitration is to be commenced, for example how 2 Second, to make appropriate provision for the exchange of
and where the arbitration notice is to be served. Also, the information and evidence relating to the matters in dispute.
arbitration clause may state whether the arbitration tribunal 3 Third, to make provision for the way in which the hearing
is obliged to apply the law strictly, or is entitled to decide itself will be conducted (if, indeed, a hearing is held).
the dispute ex aqueo et bono (meaning ‘according to equity
and good conscience’) or in the light of usages and custom 17.02 Usually the specified rules will deal with these matters,
of the industry. while allowing the tribunal some discretion as to how they are
applied. In most cases of any size, there will be a meeting with
15.02 In arbitrations involving foreign parties, the agreement the tribunal at an early stage in the proceedings when the tribu-
should refer to the applicable law, the language of the arbitra- nal will make an ‘order for directions’ (setting out, step by step,
tion, and the place of arbitration. The latter issue is of practical how the tribunal and the parties will arrive at the final hearing
importance. The law of the ‘seat’ of the arbitration governs the of all the evidence if the case cannot be resolved before then).
procedural aspects of the subsequent proceedings (for exam- In substantial cases, these directions, and the need for further
ple, what powers the arbitrators have, how an award might directions, are reviewed throughout. There is likely to be a fur-
be challenged). If the seat of the arbitration is not England ther procedural hearing, which usually takes place much nearer
and Wales, then the Act will not apply: the implications of to the trial date and serves as a check that the parties are indeed
adopting a seat other than England and Wales are beyond the ready to go into the hearing (as they ought to be).
scope of this chapter. See, further, Chapter 26 on International
Arbitration.
18 The general duty of the parties
16 How to commence 18.01 Section 40 of the Act imposes a general duty on the par-
ties to ‘do all things necessary for the proper and expeditious
arbitration proceedings conduct of the arbitral proceedings’. This includes complying
without delay with the tribunal’s directions and orders and also
16.01 It is important to know how to commence arbitration any step to obtain a decision of the court on a preliminary ques-
proceedings. A mistake in the notice of arbitration, rendering tion of jurisdiction or law.
it ineffective, may mean that a claim becomes time barred as
a result of the expiration of a limitation period (see above). If
the arbitration agreement does not specify how and when pro- 19 Defnition of the issues
ceedings are deemed to be commenced, then the provisions of
section 14 of the Act will apply. The precise mechanism will 19.01 In most cases, the parties will be required to serve on
depend on whether the arbitration agreement names a designated each other a ‘statement of case’. As the name suggests, this
arbitrator or requires either the parties to appoint the arbitrator document sets out the nature of each side’s case. The amount
or a third party to do so. The underlying principle is that arbitral of information included in the statement of case will depend on
proceedings are commenced in respect of a matter when one the circumstances of the case. Sometimes, the statement will
party serves on the other party a notice in writing requiring it (or include full submissions of fact and law, supported by copies
them) to submit that matter to the persons named, designated, or of the documents on which the party wishes to rely. The nor-
to be appointed as arbitrator. mal requirement is that the statements of case should set out,
Evidence of fact and expert evidence 267

as concisely as possible, the material facts on which the party categories, such as by file, or by simply providing relevant docu-
relies in support of its case. Generally, statements of case in ments to the other side without any list.
arbitration are more readable than formal ‘pleadings’ in court.
Good arbitration submissions tell the story convincingly without 20.05 Certain categories of documents, referred to as ‘privi-
veering off into unsupported allegations, hyperbole, irrelevan- leged documents’, need not be disclosed. For most practical
cies, or repetition. circumstances which architects are likely to come across, the
only relevant categories of privilege are legal professional
19.02 In large construction disputes, which can involve com- privilege and communications between the parties on a ‘without
plex issues of fact and substantial quantities of documents, it prejudice’ basis.
may be necessary for the parties to serve schedules providing
details of the factual matters which are in dispute (called ‘Scott 20.06 Documents covered by legal professional privilege are
Schedules’). These large disputes call for all of the skills of communications between clients and their qualified lawyers
the tribunal to devise procedures which will be appropriate and which come into existence for the purpose of either providing
enable the arbitration to proceed to a speedy conclusion. An the client with legal advice or were prepared in contempla-
experienced arbitrator should not allow a complex claim for tion of litigation or proceedings (and this includes arbitration
delay and disruption to turn into a re-staging of everything that claims). Documents produced by the lawyers, or at their request
happened on the project. Generally, in construction arbitrations, in order to collect or prepare evidence for the arbitration, are
the management of factual detail by all involved (experts, arbi- also privileged.
trators, lawyers, and witnesses) is one of the key challenges to
be addressed. 20.07 It should be noted, however, that legal professional
privilege only applies to confidential communications between
clients and their qualified lawyers (and this includes in-house
20 The exchange of information counsel) and to documents prepared by or at the request of
and evidence qualified lawyers. There are a great number of construction
industry arbitrations where lawyers are not involved, but other
consultants are engaged. Communications with such consultants
Disclosure of documents and documents prepared by them will not be covered by legal
20.01 In litigation, after the parties have exchanged their state- professional privilege (see New Victoria Hospital v Ryan (Court
ments of case, each is required to disclose to the other docu- of Appeal) 4 December 1992).
ments in its possession, custody, or control that either support
that party’s case, undermine that party’s own case or support the 20.08 The long-running litigation against the Bank of England
case of the opposing party. Prior to the introduction of the Civil concerning the collapse of BCCI has produced some changes to
Procedure Rules, it was generally necessary to disclose docu- the law of legal professional privilege (in particular the House of
ments that merely related to the issues, or documents that, once Lords in Three Rivers District Council and others (Respondents)
seen, might put the other side onto a ‘trail of enquiry’ towards v Governor and Company of the Bank of England (Appellants)
other, more fruitful documents. However, concepts of relevance [2004] UKHL 48). It is important to ensure that where legal
and the trail of enquiry have not had any place in English court advice is given, the ‘client’ is identified (in terms of a group of
procedure for some time now, and should have no place in arbi- persons within an organisation that deal with the specific matter
tration either – especially since disclosure of documents is not in issue) and that communications are kept between the ‘client’
a permanent fixture in arbitrations. and the lawyers. If documents are circulated widely, it may be
that any privilege is lost.
20.02 Disclosure of documents has never been mandatory in
arbitration proceedings. However, there has been a (perhaps 20.09 Without prejudice communications are communications
unwelcome) tendency for some arbitrators to copy the litigation between the parties or their advisers, whether or not expressly
procedures to the extent of requiring the parties to give disclo- marked ‘without prejudice’, which comprise negotiations to
sure of all their documents that fall within the test – but this settle the dispute or part of the dispute and which are intended
approach is become less common nowadays. The more modern to be made on a ‘without prejudice basis’ (in other words, on
approach in arbitration is not to require the parties to produce the basis that they should not be referred to in the arbitration).
more than the documents on which they rely, plus specific
categories of documents which may be requested by the other
party. Even then, the tribunal may decline to order a party to
produce documents requested by the other party if the request
21 Evidence of fact and
is not reasonable. For instance, a reasonable request may relate expert evidence
to any internal minutes of a meeting at which it is known that
the cause of an important defect was discussed. A potentially 21.01 One of the main tasks of the tribunal is to establish the
unreasonable request might be aimed at ‘any and all’ documents facts of the case. The way in which facts are proved will depend
or correspondence passing between the main contractor and the on the procedure adopted by the tribunal. As set out below, the
sub-contractor concerning the piling works (this should be lim- Act allows a proactive arbitrator to take a much more ‘inquisi-
ited to dates or a time period, and the specific relevance of the torial’ approach to the collection of evidence and the issues in
piling works to the claims ought to be explained). dispute as one would expect from a judge in the TCC. However,
legal proceedings in the common law tradition (and this includes
20.03 This modern approach is reflected in section 34(2)(d) arbitrations) will generally remain ‘adversarial’ in nature, with
of the Act, which leaves it to the tribunal to decide ‘whether both parties advancing their case and the decision-maker picking
any and if so which documents or classes of documents the most convincing case, rather than taking the lead from the
should be disclosed between and produced by the parties and parties by establishing the facts and the law out of his or her
at what stage’. own initiative.

20.04 The manner in which documents are disclosed is also 21.02 Subject to any agreement between the parties, section 34(2)
important. In litigation, parties are required to list all of the of the Act confers wide powers and a discretion to decide how
documents produced (which generally involves extracting them the facts will be proved on the tribunal. For example, the tribunal
from files and listing them, chronologically). Arbitrators could can decide whether to apply the strict rules of evidence as to the
impose a similar requirement but the more modern approach is admissibility, relevance or weight of any material (oral, written,
to require the parties to identify the documents by more general or other) on any matters of fact or opinion. The tribunal can
268 Arbitration

also decide whether it should take the initiative in ascertaining opening the arbitration by explaining the whole of the case to
the facts by making its own enquiries. The tribunal can decide the arbitrator and then taking the arbitrator through all of the
whether and to what extent there should be oral or written evi- relevant documents and correspondence. The claimant would
dence or submissions. Under section 37, the tribunal has the then call its witnesses of fact and expert witnesses. Each witness
power to appoint experts or legal advisers to report to it and to the would give their evidence in chief orally. The witness would
parties and to appoint assessors to assist it on technical matters. then be cross-examined by the respondent’s representative and
might then be re-examined by the claimant’s representative. The
21.03 In litigation, facts are proved by the evidence of witnesses, respondent’s representative would present its case in a similar
which is normally given mainly in writing (in the form of a wit- manner.
ness statement) and partly through oral examination, usually cross-
examination. The witness statement sets out the witness’s own 22.03 Today this ‘traditional’ approach is very rare. While the
story, while cross-examination is conducted by the opposing party’s tribunal has a duty to allow each party a reasonable opportunity
advocate with the aim of making the witness seem less credible of putting its case and dealing with that of its opponent, it is
and ‘picking holes’ in the testimony. In arbitration proceedings, quite consistent with that obligation to adopt procedures which
the tribunal has the discretion to establish the facts on the basis curtail substantially the amount of oral presentation and argu-
of documents alone, possibly supplemented by written witness ment at the hearing. Nowadays, tribunals increasingly require
statements or by oral examination of all or some of the witnesses. the parties to put in written submissions of law and take steps
to reduce the length of the oral hearing. In short, the tribunal
21.04 Because the tribunal is not bound by the strict rules of will read up on the case in advance and will use the time at the
evidence which apply in court it can admit hearsay evidence hearing to hear cross-examination of witnesses and experts, and
and decide how much weight should be given to that evidence. also frequently to question the parties on the basis of the cases
It is also becoming increasingly common for arbitral tribunals that have been advanced so far.
to take an active part in examining the witnesses that appear
before them. For instance, the arbitrator may have his or her own 22.04 Where there are significant factual disputes, it is more
questions following a review of the written witness statement, than likely that the tribunal will require the oral examination of
and these questions may not necessarily coincide with those to witnesses, even though the witnesses will have served written
be asked by the opposing party’s advocate. witness statements. The sequence in which witnesses are called
by the parties is a matter for them and the tribunal. Most com-
21.05 Construction disputes frequently raise important issues monly, the claimant calls all of its witnesses of fact and expert
which turn on opinion evidence and not just evidence of fact. witnesses and then the respondent calls all of its witnesses.
For example, if the tribunal has to decide whether an architect However, sometimes it is the case that the claimant will call all
failed to use reasonable care and skill in designing a building, of its witnesses dealing with a particular topic (whether a factual
it must first establish as a matter of fact how the building was topic or an issue of expert evidence) and the respondent will then
actually designed. Whether that design was negligent is a matter call its witnesses dealing with that particular topic. The most
of opinion. For that reason, most arbitration rules provide for the appropriate procedure varies from case to case.
possibility of expert evidence being given on matters of opinion.
Experts, although they appear on behalf of one party and will
generally advance a position that assists that party (which party
would otherwise not be relying on the expert in question), are
meant to be independent and owe a duty to the tribunal rather
than the party instructing them. Any architect who acts as expert
witness should bear this duty of independence, and impartially,
in mind.

21.06 The collection and service of expert evidence is usually


an expensive part of the arbitral process, with each party having
its own expert and the tribunal having to assess and weigh the
evidence of both experts to decide the dispute. For this reason,
the tribunal is given the power to appoint experts to report to it
and to the parties (section 37 of the Act). In those circumstances,
the parties are given a reasonable opportunity to comment on
any information, opinion, or advice offered by any such expert.

21.07 Where the tribunal permits the parties to use their own
experts, it is usually directed that the two experts meet with a
view to narrowing and defining the issues in dispute. The duties
of the expert are described below in the section referring to
the architect as expert. It is not uncommon for the tribunal to
interview both experts jointly at the hearing, to seek to explore 22.05 After the arbitrator has heard the evidence, the representa-
the areas of difference that remain following discussions directly tives of the parties will make their closing submissions. Again,
between the experts. it is common for these submissions to be put in writing, and in
more complex cases, the arbitrator may order a short adjourn-
ment to give the parties the chance to prepare their submissions
22 The arbitration hearing in the light of all the evidence which has been given and ask for
those submissions to be delivered in writing. The arbitrator may
22.01 A party may be represented in arbitration proceedings by then ask for a further short hearing to deal with any questions
a lawyer or any other person chosen by it. which he or she has on the written submissions.

22.02 The arbitration hearing is an expensive, and final, stage


in the arbitration. Work in the period leading up to the hearing 23 The award
will be intensive. In large arbitrations, a practice developed of
following the court procedure for the conduct of the hearings. 23.01 Having heard the evidence and submissions, the tribunal
Historically, this would involve the claimant’s representative then renders its decision in the form of an award. The parties are
Arbitration procedures found in construction industry cases 269

also free to agree that the tribunal may make provisional awards, arbitration with paper by disclosing a large amount of irrelevant
in advance of a final determination of the issues – a power the documents may find that it has to pay a high proportion of the
tribunal does not have in the absence of such an agreement. This costs of the other party incurred in reviewing those documents.
additional power is often necessary where the tribunal wishes
to make a provisional order for the payment of money or the 24.02 While the parties are free to make their own agreement
disposal of property. In construction disputes, the arbitrators may relating to the award of costs, they cannot agree before a dispute
be asked to order a sum due to a contractor on a provisional or has arisen that one party is to pay the whole or part of the costs
interim basis, perhaps pending determination of entitlement or of the arbitration in any event (so irrespective of the outcome of
the carrying out of further work that affects the final valuation. the arbitration). This is intended to prevent the position where,
through such an agreement, a party is dissuaded from commenc-
23.02 The parties are also free to agree the form of the final ing arbitration proceedings for fear of having to pay the other
award, but if there is no agreement, the Act provides that the party’s costs, come what may. However, the parties may agree
award should be in writing signed by all the arbitrators and shall in advance that each party is to bear its own costs.
contain the tribunal’s reasons (unless it is an agreed award or
the parties have agreed to dispense with reasons). The award is 24.03 The parties can agree what costs will be recoverable and
also required to state the seat (location) of the arbitration and what fees will be paid to the arbitrator for his services. If the
the date when it is made. parties do not agree any of these matters, then the provisions of
the Act will apply.
23.03 Unless otherwise agreed by the parties, the tribunal may
make more than one award at different times on different aspects 24.04 The Act also gives the tribunal the power (again, unless
of the matters to be determined. Typically this is done where otherwise agreed by the parties) to direct that the recoverable
the tribunal deals with issues of liability before considering the costs of the arbitration, or of any part of the arbitral proceed-
quantum of the claim. Establishing liability first is sometimes ings, shall be limited to a specified amount. This is a potentially
considered a sensible step to take because it allows the parties important provision, since it provides the tribunal with the means
to reach a commercial agreement as to quantum without the need to ensure that the parties use the most economic and efficient
to hear expert evidence on this (such as the report of a quantity procedures to bring their dispute to a point of determination.
surveyor or other valuation expert).

23.04 The tribunal also has power to award simple or compound 25 The power of the tribunal in
interest from such dates and at such rates and on such amounts
as it considers just. The ability of the tribunal to award com-
the case of a party’s default
pound interest is wider than the equivalent power of the court.
25.01 One advantage of litigation over arbitration is that the
court is better able to deal with a party in default. This is not
23.05 The requirement to provide reasons as part of the award
to suggest, however, that an arbitration tribunal is powerless to
is to allow the court to consider any appeal. Accordingly, the
deal with a party’s default. The parties have an explicit duty to
arbitrator must state all his or her findings of fact (although
comply without delay with the orders of the tribunal (see above)
need not recite all the evidence which leads to the findings)
and can agree on the powers of the tribunal in case of a party’s
and briefly state the reasoning on the issues of law. However, it
default. If there is no agreed provision, then section 41 of the
should be recalled that the court will never review an arbitrator’s
Act gives the tribunal power to dismiss a claim if there has been
findings of fact, and will only consider any potential error of
inordinate and inexcusable delay on the part of a claimant to
law if the parties have not agreed to exclude the right to appeal
pursue his claim (subject to the tribunal being satisfied on certain
on a point of law.
conditions). The Act also gives the tribunal power to continue
the proceedings in the absence of a party in default and may
23.06 All awards, whether including reasons or not, should be
make an award on the basis of the evidence before it. This is
certain (in the sense of being sufficiently clear and unambigu-
to deal with a defendant who fails to comply with the tribunal’s
ous), and final (unless clearly intended to be an interim award).
directions or to participate in the proceedings. The tribunal’s
If the reference to arbitration calls for an award in money terms,
power to make peremptory orders is supplemented by the power
then the award should be in an appropriate form to allow it to
of the court to enforce such orders (see later).
be enforced as if it were a judgment of the High Court, i.e. it
should specify precisely the sum of money found to be due and
which of the parties is to make the payment.
26 Arbitration procedures found in
construction industry cases
24 Costs
26.01 There are two sets of rules commonly used in construc-
24.01 The costs of an arbitration will include the arbitrator’s tion industry disputes because they are adopted in the standard
fees and expenses, the fees and expenses of any arbitral institu- building and civil engineering contract forms. CIMAR 2016 are
tion involved, and finally, the legal or other costs of the parties adopted by the JCT contracts and the ICE Arbitration Procedure
(including the professional fees of expert witnesses). Generally, (England and Wales), 2012 edition (the ‘ICE Procedure’) by the
the legal costs of the parties represent the largest item. The ICE contract. Both sets of rules were issued after the Act was
tribunal will deal with the allocation of costs in its award. In so enacted and take advantage of its provisions. Both also deal
doing, the tribunal has a wide discretion, but there are general expressly with many of the powers given to arbitrators and/or
rules that are likely to apply. Subject to agreeing otherwise, the the courts by the Act. CIMAR 2016 actually sets out applicable
general principle is that ‘costs should follow the event’ (loser sections of the Act in its rules.
pays) – unless it appears to the tribunal that in the circumstances
this would not be appropriate in relation to some, or all, of the 26.02 Some features of CIMAR 2016 which are worth noting
costs. For example, the tribunal might take account that the are:
claimant declined an offer to settle the claim for more than the
amount of the eventual award. Or it may be that the claimant, 1 The provisions relating to the joinder of separate arbitrations.
while the overall winner, lost on a number of issues which took 2 The arbitrator is required to consider the form of procedure
up substantial time at the hearing. As noted above, the tribunal which is most appropriate for the dispute as soon as he or
is also likely to consider any relevant conduct by the parties that she is appointed. The rules offer three options:
may have increased costs. For instance, a party that floods the (i) a short hearing procedure;
270 Arbitration

(ii) a documents only procedure; 27 The role of the courts in


(iii)a full procedure with a hearing.
3 If there is no joint decision by the parties as to which pro- arbitration proceedings
cedure shall apply, then the arbitrator shall direct which
procedure is to be followed. The rules give guidance on 27.01 There is a limit to what can be achieved by a tribunal if a
this. They state that a short hearing is appropriate where party refuses to comply with the arbitration agreement or with
the matters in dispute are to be determined principally the tribunal’s directions or award. Ultimately, resort must be
by the arbitrator inspecting work, materials, machinery, made to the courts to enforce the process. The Act provides the
etc. A documents only procedure is appropriate where the necessary ‘legal infrastructure’ for arbitration by giving the court
issues do not require oral evidence or because the sums powers to support the process not only by enforcing decisions
in dispute do not warrant the cost of a hearing. Where and awards of arbitral tribunals, but also by providing a remedy
neither of the previous two procedures is appropriate, if the arbitral tribunal ignores the fundamental requirements of
the full procedure should be adopted ‘subject to such arbitration. The powers of the court can be divided into the fol-
modification as is appropriate to the particular matters lowing general categories, as powers to:
in issue’.
4 The provisions relating to the award of costs, which flesh 1 enforce the arbitration agreement;
out the circumstances the arbitrator can take into account 2 support of the arbitration process;
when making that decision. 3 supervise the arbitration process;
4 decide points of law;
26.03 In general, the ICE Procedure allows the arbitrator the 5 consider appeals and applications to set aside the award; and
flexibility to handle the case in the manner he or she consid- 6 enforce the award.
ers to be appropriate, and is intended to take over some of
the perceived advantages of adjudication (mainly the speedy 27.02 The general policy of the Act is that if the parties have
resolution of disputes). The arbitrator may order the parties agreed that their disputes should be resolved by arbitration, then
to define their cases by delivering ‘short statements express- that agreement should be upheld. The objective of the court’s
ing their perception of the disputes or differences’. These powers is to ensure that the arbitration process runs smoothly
statements should have sufficient detail of the issues to allow and fairly. Even if the court intervenes in the arbitration process
the arbitrator and the parties to discuss them at a preliminary it is the arbitration tribunal, not the court, which resolves the
meeting (rule 6.1). The arbitrator can, however, decide the substantive dispute.
form the statements should take (see further rule 8.2). Express
provision is made for the arbitrator and the parties to consider
whether and to what extent documents should be disclosed. 28 Powers to enforce the
Further powers to order disclosure of documents are set out arbitration agreement –
in rule 8.3.
‘staying’ of court proceedings
26.04 The ICE Procedure also includes two optional procedures in favour of arbitration
which may be adopted when the parties so agree (the arbitrator
may invite the parties to agree to these procedures, but cannot 28.01 If a party to an arbitration agreement commences proceed-
order them to do so): ings in court in respect of a matter covered by the arbitration
agreement, then the Act gives the courts the power to hold that
1 There is provision for a ‘short procedure ’ (for sums which party to its agreement to arbitrate by ordering a ‘stay’ (which
do not exceed £50,000, or the where the parties agree): means a suspension) of the court proceedings. The effect of
according to this procedure each side delivers to the other the stay will be that if the party who brought the court action
and to the arbitrator a file containing a statement as to orders still wishes to pursue its claim, it will only be able to do so by
or awards sought, reasons relied upon by the parties, and arbitration.
copies of any documents relied upon. The other party then
has 14 days to respond, but counter-claims are not allowed 28.02 An application to stay court proceedings must be made
– these require a new, separate reference. Thereafter, each before the applicant has taken any step in the proceedings to
party may comment on the other party’s case within a fur- answer the substantive claim. If the applicant does take such a
ther 14-day period. The arbitrator will then make his or her step, it will waive his right to a stay.
award within a further period of 14 days. There is to be no
hearing or cross-examination. 28.03 Subject to that, section 9(4) of the Act provides that
2 There is now also an ‘expedited procedure’ (for sums up to ‘the court shall grant a stay unless satisfied that the arbitration
£250 000). Essentially, under this procedure, the arbitrator agreement is null and void, inoperative or incapable of being
will set a procedural timetable for a period not exceed- performed’ [emphasis added]. The use of mandatory words here
ing 100 days (which the parties, by agreement, but not means that the court has no discretion not to order a stay, unless
the arbitrator, may extend). This procedure will feature a the arbitration agreement itself is ineffective.
sequential exchange of statements of case with specified
periods (a defence to be served 21 days after the statement
of case, followed by a reply within 14 days) and a formal 29 The court’s powers
hearing. The arbitrator is given a variety of express pow- exercisable in support of
ers in relation to this hearing (which he or she may have
under the Act in any event) – and may take the initiative the arbitration process
as regards factual and legal matters, and questioning of
witnesses. 29.01 A number of powers exercisable by the court have already
3 There is a ‘special procedure for experts’: according to been mentioned in this chapter, for example, in relation to the
this procedure, parties submit a file containing a statement appointment of arbitrators. This power also extends to cases
of factual findings sought, a report or statement from an where an appointed arbitrator refuses to act, is incapable of
expert and any other document relied upon by the parties. acting, or dies; where an arbitration agreement provides for the
There is then a hearing for experts to express their views appointment of an arbitrator by some third party which refuses
and be examined by the arbitrator. The rules provide that no to make the appointment or does not make it within a reasonable
costs of legal representation are allowed if this procedure is time; and where two arbitrators are required to appoint a third
followed. party (or umpire) and do not appoint him or her.
The court’s powers to supervise the arbitration process 271

29.02 Again as noted above, the court may also extend time lim- of interference from the court, nonetheless, the court is con-
its for commencing arbitration proceedings under section 12 of cerned to ensure that the arbitration is conducted in accordance
the Act. This power is relevant where the terms of an arbitra- with the basic standards of fairness and natural justice. The
tion agreement provide that any claim is to be barred unless the principal means by which the court exercises this supervisory
claimant takes some step to commence the proceedings within role are through the power to remove an arbitrator or the power
a specified time. It should, however, be emphasised that the cir- to set aside an award if there is a procedural irregularity.
cumstances in which the court will extend time are limited, and
it would be unwise to assume that an extension will be granted. 31.02 Under section 24 of the Act, the court has power to
The applicant should first exhaust any available arbitral process remove an arbitrator on any of the following grounds:
for obtaining an extension of time. The court must then be satis-
fied that the circumstances are such as were outside the reason- (a) that circumstances exist that give rise to justifiable doubts
able contemplation of the parties when they agreed the provision as to his impartiality;
in question, and that it would be just to extend the time, or that (b) that he does not possess the qualifications required by the
the conduct of one party makes it unjust to hold the other party arbitration agreement;
to the strict terms of the provision in question. (c) that he is physically or mentally incapable of conducting the
proceedings or there are justifiable doubts as to his capacity
29.03 The powers of the court in relation to arbitral proceedings to do so;
are set out in sections 42–45 of the Act. Section 42 deals with the (d) that he has refused or failed –
enforcement of peremptory orders of the tribunal, section 43 with (i) properly to conduct the proceedings; or
securing the attendance of witnesses, section 44 with various (ii) to use all reasonable despatch in conducting the proceed-
powers exercisable in support of the arbitral proceedings, and ings or making an award, and that substantial injustice
section 45 with determination of preliminary points of law. has been or will be caused to the applicant.
There are a number of common themes. First, with the excep-
tion of section 43, the court’s powers are subject to any contrary 31.03 The court has also power to set aside or vary an arbitra-
agreement between the parties. That contrary agreement might tion award where one of the parties applies on the basis that the
be expressed in the arbitration rules which apply to the proceed- tribunal lacked substantive jurisdiction (section 67).
ings. Second, the powers of the court are in support of the arbitral
proceedings, so generally, the court will not exercise the power 31.04 Finally, the court can set aside, vary, or remit an award
unless the applicant has exhausted any available arbitral process back to the tribunal if there was a ‘serious irregularity’ affecting
or the application is made with the consent of the tribunal. the tribunal, the proceedings or the award (section 68). A serious
irregularity means an irregularity of a kind specified in the Act,
29.04 The range of powers included in section 44 includes the which the court considers has caused or will cause substantial
taking and preservation of evidence, making orders relating to injustice to the applicant:
property which is the subject of the proceedings, the sale of any (a) failure by the [arbitral] tribunal to comply with section 33
goods the subject of the proceedings, and the granting of an [under which it is obliged to act fairly and impartially
interim injunction for the appointment of a receiver. The under- and adopt procedures suitable to the circumstances of the
lying rationale of the powers exercisable under section 44 is particular case] …
the recognition that a party may need to take prompt action (b) the tribunal exceeding its powers …
to preserve its rights (for example by applying for an interim (c) failure by the tribunal to conduct the proceedings in
injunction), and it may be unable to secure those rights through accordance with the procedure agreed by the parties;
arbitration for the simple reason that the arbitral tribunal has not (d) failure by the tribunal to deal with all the issues that were
been constituted. put to it;
(e) any arbitral or other institution or person vested by the
29.05 The power of the court to determine a preliminary parties with powers in relation to the proceedings or the
point of law under section 45 of the Act is to be distinguished award exceeding its powers;
from an appeal against the arbitrator’s award (see later). (f) uncertainty or ambiguity as to the effect of the award;
Section 45 provides a means for the parties or the tribunal to (g) the award being obtained by fraud or the award or the way
obtain a ruling from the court on a point of law which sub- in which it was procured being contrary to public policy;
stantially affects the rights of one or more of the parties. An (h) failure to comply with the requirements as to the form of
application can only be made with the consent of all the parties the award; or
or with the permission of the tribunal. Even then, the court must (i) any irregularity in the conduct of the proceedings or in the
be satisfied that the determination of the question is likely to award which is admitted by the tribunal or by any arbitral
produce substantial savings in costs and that the application was or other institution or person vested by the parties with
made without delay. powers in relation to the proceedings or the award.
31.05 The court’s powers under sections 67 and 68 are subject to
30 Enforcement of certain conditions, such as a time limit and the need to exhaust
remedies available under the arbitral process. The right to make
arbitration awards such a challenge can be lost (see section 73) by, for example,
failing to make a timely and effective objection to the exercise of
30.01 Arbitration awards may, with leave of the court, be jurisdiction by the tribunal or to the offending conduct or action.
enforced in the same manner as a judgment of the High Court
(section 66 of the Act). Obtaining leave is almost always a pure 31.06 The issue of a serious irregularity is sometimes raised
formality unless the respondent can say that there was some by the losing party wishing to challenge an arbitration award
severe defect in the arbitration process, such as problems with (especially if any right to appeal the award on a point of law has
the arbitration tribunal’s jurisdiction. been excluded). However, section 68 was not intended, and does
not in practice operate, as a backdoor through which arbitration
awards may be challenged. As the court explained in Petroships
31 The court’s powers to supervise Pte Ltd v Petec Trading and Investment Corporation [2001]
the arbitration process Lloyd’s Rep 348, section 68 reflects the internationally accepted
view that the courts should be able to correct a serious disre-
31.01 Although the underlying principle of the Act is to allow gard of due process in any arbitration. However, the provision
the arbitration process to take its own course, with the minimum should only come into play where something extraordinary has
272 Arbitration

happened in the arbitration process, which is far removed from to significantly increase the prospect of appealing on a point of
what could reasonably be expected of arbitrators. When looking law before the court.
for a substantial injustice to one of the parties (without which
the courts will not interfere), it is not appropriate to ask what the
outcome would have been had the matter been litigated rather 33 The architect as arbitrator
than arbitrated. The parties, having chosen arbitration, should be
held to that choice in all but the truly exceptional cases. 33.01 As can be seen from the description of the law of arbitra-
tion set out in this chapter, the acceptance of the position of
arbitrator is not something to be undertaken lightly. An architect
who undertakes arbitrations should have a good working knowl-
32 Appeals on points of law edge of the law and practice of arbitrations in addition to the law
and practice of the construction industry. Furthermore, acting as
32.01 A party’s right to apply to set aside an award on the
an arbitrator can be time-consuming if the arbitration goes to a
grounds of a serious irregularity cannot be excluded by agree-
full hearing. After the hearing, the arbitrator must set aside suf-
ment (although the right can be lost by conduct), but if the
ficient time to write the award. This will involve reviewing all of
tribunal, having conducted the arbitration proceedings prop-
the evidence and the submissions made during the proceedings.
erly, reaches the wrong conclusion, it can be very difficult to
challenge the award (as noted above). In contrast, the right to
33.02 When arbitrators undertakes their appointment, they are
appeal to the courts on points of law can be excluded by agree-
entitled to such reasonable fees as are appropriate in the cir-
ment. Note, however, that neither the arbitration clause in the
cumstances’ (section 64(1) of the Act) to be paid by the parties.
JCT Standard Form of Building Contract 2005 (Conditions,
If nothing is agreed between the arbitrator and the parties when
Section 9.7) nor CIMAR 2016 exclude the right to appeal on
the arbitrator accepts the appointment, then the arbitrator usually
a point of law. If the right to appeal is not excluded, an appeal
assesses what he or she considers to be a reasonable sum for the
can only be made with the leave of the court, or the agreement
services and makes that sum, and the identity of the person who
between all parties. Leave of the court will be granted only if
is liable to pay that sum, part of the award. Recovery of the fees
the court is satisfied:
is usually dealt with by notifying the parties that the arbitration
(a) that the determination of the question will substantially award is available to be collected provided that fees are paid.
affect the rights of one or more of the parties, This is usually a sufficient incentive for the claimant to pay the
(b) that the question is one which the tribunal was asked to arbitrator’s fees (whether or not the claimant is made liable for
determine, them by the award), so that the award may be obtained and the
(c) that, on the basis of the findings of fact in the award – claimant can (if successful) proceed to enforce it.
(i) the decision of the tribunal on the question is obvi-
ously wrong, or 33.03 However, statistically, most arbitrations settle before the
(ii) the question is one of general public importance and final award. In these circumstances, the law probably is that the
the decision of the tribunal is at least open to serious arbitrator is entitled to reasonable remuneration from the parties
doubt, and in respect of the work which has been carried out, but that he
(d) that, despite the agreement of the parties to resolve the or she is not entitled to payment (either as ‘remuneration’ or
matter by arbitration, it is just and proper in all the cir- as ‘damages’ for lost opportunity) in respect of the fees which
cumstances for the court to determine the question. the arbitrator would have earned had there been a hearing and
(See section 69(3) of the Act.) final award.

32.02 In practice, in a ‘one-off’ dispute (that is, a dispute which 33.04 If there is a dispute between the arbitrator and the parties
does not relate to a standard provision in a construction agree- with regard to the level of remuneration, then there are various
ment), leave to appeal will usually only be granted in respect of ways for that to be determined by the court, depending on the
a question of law if it is apparent to the judge that the arbitrator’s circumstances of the case.
award is obviously wrong. Even then, if the judge considers that
it is possible that argument could persuade him or her that the 33.05 For these reasons, experienced arbitrators do not accept
arbitrator might be right, leave will often not be granted. In cases their appointment until the parties have accepted the arbitra-
concerning the meaning of standard terms in contracts, the judge tor’s terms of engagement. These terms usually provide that
will be likely to take a less strict approach, but leave should not both parties are jointly and severally liable for the arbitrator’s
be given, even in those cases, unless the judge considers that a fees. It is common for arbitrators and parties to agree that there
strong prima facie case has been made out that the arbitrator was should be hourly remuneration rates for preparatory reading and
wrong in the construction of the contract. When the events to interlocutory hearings and daily rates of remuneration for the
which the standard clause were applied in the particular arbitra- hearing of the arbitration itself. It is also common for ‘cancella-
tion were themselves ‘one-off’ events, the stricter criteria would, tion charges’ to be stipulated by arbitrators to protect them from
nevertheless, be applied. loss of revenue in the event that the arbitration is settled before
the award is made. Arbitrators often also require some security
32.03 Appeals from arbitration awards will therefore be infre- on account of likely fees.
quent. If an appeal is allowed, the court may confirm, vary, set
aside, or remit the award for the reconsideration of the arbitrator, 33.06 An arbitrator is generally not liable for actions taken in the
together with the court’s opinion on the question of law which capacity of arbitrator. Section 29(1) of the Act (which applies
was the subject of the appeal. notwithstanding any contrary agreement between the parties)
provides that an arbitrator is not liable for anything done (or
32.04 It should be noted, however, that the JCT Standard Form omitted to be done) in the discharge (or purported discharge) of
of Building Contract 2016 (Conditions, Section 9.7) states that his or her functions as arbitrator unless the act or omission can
the parties agree that the High Court shall have jurisdiction over be shown to have been in bad faith. The arbitrator’s position
any appeal on a point of law. It is likely that this clause will is therefore different from that of judges who, when acting in
be interpreted as an agreement between all the parties to the their judicial capacity, are immune even where they have acted
arbitration, with the effect that permission or leave of the court maliciously. The burden of proving bad faith on the part of an
will not be required (see Taylor Woodrow Civil Engineering Ltd arbitrator lies on the person alleging it and would no doubt be
v Hutchison IDH Development Ltd [1998] Con LR 1). Since a considerable burden to shift. In one case, the court held that
permission is very difficult to obtain, the effect of the provi- bad faith covered malice in the sense of personal spite or desire
sions of the JCT Standard Form of Building Contract 2016 is to injure for improper reasons.
The architect as expert witness 273

33.07 Section 24(4) of the Act provides that ‘Where the court 1 Expert evidence should be and should be seen to be inde-
removes an arbitrator, it may make such order as it thinks fit pendently produced by the expert witness, albeit that the
with respect to his entitlement (if any) to fees or expenses, or the expert is giving evidence on behalf of one of the parties
repayment of any fees or expenses already paid’. The Act does and he or she should co-operate with the party’s legal team
not deal explicitly with the position where an award has been in identifying the issues to be addressed and on the overall
set aside on the grounds of ‘serious irregularity’ caused by the structure for the report.
arbitrator’s failure to conduct the proceedings properly. Logic 2 The expert witness should present an objective unbiased
would suggest that the court would order an arbitrator to refund opinion regarding matters which fall within his or her
the fees if the circumstances were sufficiently serious. expertise.
3 An expert witness should never assume the role of advocate.
33.08 Perhaps the best advice for architects contemplating 4 Any facts or assumptions upon which the expert witness’s
accepting an appointment as an arbitrator is to ensure that they opinion is founded must be stated together with any material
are covered by appropriate professional indemnity insurance. facts which could detract from his or her concluded opinion.
5 Any photographs, survey reports, plans and any other docu-
33.09 Architects who act as arbitrators may wish to have ment upon which the expert witness has relied in his or her
their own legal advice, if the dispute raises difficult issues evidence must be provided to the other parties in the legal
of law. Section 37(1) of the Act provides that, unless the proceedings/ arbitration at the same time as expert reports
parties agree otherwise, arbitrators may appoint experts/legal are exchanged.
advisers to report to them and to the parties and to attend the 6 If the expert witness does not have sufficient data available
proceedings. However, the parties must be given a reason- to form a properly researched conclusion, this fact must be
able opportunity to comment on any information, opinion or revealed to the court/arbitrator together with an indication
advice offered. that the opinion is no more than provisional.
7 If any of the subject matter of the dispute falls outside the
33.10 It must, however, be the arbitrators, and not the legal area of the expert witness’s expertise, he or she is under a
adviser, who make decisions and are seen to make decisions, duty to inform the court/arbitrator in his report. Likewise,
even on points of law. They must not merely adopt the views it should be made clear, when under cross-examination, if
put forward by the legal adviser without considering the matter asked questions which are not within the area of his or her
themselves. expertise.
8 Where the expert witness is unable to swear on oath that the
33.11 The fees of the legal assessor are part of the fees of the report contains the truth, the whole truth, and nothing but
arbitration and are recoverable by the arbitrator from the parties the truth, this qualification must be stated in the report.
(see section 37(2) of the Act). 9 If an expert witness changes his or her mind with respect
to a material issue of the evidence after reports have been
exchanged, this change of view should immediately be com-
34 The architect as expert witness municated through the parties’ representatives to the other
side, and where appropriate to the court/arbitrator.
34.01 Experienced architects may be requested to provide expert
evidence in arbitration proceedings. The function of an expert 34.03 The Civil Procedure Rules governing court proceedings
witness is to state his or her professional opinion on the relevant state that:
issues in the arbitration. The opinion should be stated clearly,
first in a written report, which is served prior to the hearing (a) It is the duty of an expert to help the court on the matters
itself, and then orally at the hearing. Usually the expert will within his expertise.
meet his or her opposite number before the hearing to identify (b) This duty overrides any obligation to the person from whom
common ground and define the issues on which they disagree. he has received instructions or by whom he is paid.
(See rule 35.3.)
34.02 An architect needs no special training to be an expert,
since it is the expertise as an architect which is being called 34.04 The Civil Procedure Rules also require an expert to state
on. However, it is important to understand the nature of the the substance of all material instructions on the basis of which
role of the expert in the proceedings, since experts commonly the report was written. This is a major change, as previously,
believe that it is their task to advocate their party’s case, to communications between a party’s lawyer and the expert were
the extent of compromising their own opinion. Guidelines for legally privileged. It is likely that arbitrators may follow the
expert witnesses in litigation and arbitration were given by the lead given by the courts by making it clear to experts appointed
court in National Justice Compania Naviera SA v The Prudential by the parties that they have a duty to the tribunal. They could
Assurance Company Ltd (the Ikarian Reefer) [1993] 2 Lloyd’s also require the expert to summarise his or her instructions in
Reports 68 (QBD). The court advised that: the report.
26
International arbitration
TONY DYMOND AND RAEESA RAWAL

1 Introduction (i) The first is the substantive law of the contract; that is the
system of law which governs the main contract, either cho-
1.01 The preceding Chapter 25 on arbitration sets out a summary sen by the parties or determined by the arbitral tribunal.
of the legal framework and of the arbitral process for domestic (ii) The second is the arbitral law of the place of the arbitra-
arbitration in England and Wales; international arbitration is its tion, referred to as the ‘seat’ of the arbitration. The law of
closely related cousin. The purpose of this chapter on interna- the seat usually governs issues such as the interpretation,
tional arbitration is to give the reader an understanding of some recognition and enforcement of the arbitration agreement,
of the common issues and where certain differences lie. It is not interim measures, evidentiary issues, and appeals of awards.
intended to be a practical guide as to how these matters should Many states have adopted the United Nations Commission
be dealt with, since much will depend on the case in point and on International Trade Law (‘UNCITRAL’) Model Law
the relevant circumstances surrounding the matter, but some (adopted by the UN General Assembly in 1976) in whole
commentary is provided. The reader will find this chapter most or in part, which provides for many of these issues.
useful if it is read after Chapter 25, to which it makes reference. (iii) The third legal regime will be the law of the arbitration
agreement. Commonly, of course, the agreement to arbi-
trate is found in a clause forming part of the main contract,
What makes an arbitration and as such, the governing law of the contract may too be
‘international’? the governing law of the arbitration agreement. However,
this is not always the case, and parties should review the
1.02 Essentially, international commercial arbitration is founded
arbitration clause carefully to determine if it selects a dif-
on the same judicial process as that of domestic arbitration, but
ferent law.
distinguished in its widest sense by some element that transcends
(iv) The law governing the recognition and enforcement of
state boundaries, thereby making it ‘international’ and subject to
awards is the fourth legal regime. This will usually be the
other legal regimes. There is no defining criterion for what that
law of the place where a party is seeking to enforce an
international element might be. In England, the law does not
award. Each of these different legal regimes is considered in
now distinguish between domestic and international arbitration,
this chapter, with particular reference being given to those
except when it comes to enforcement of foreign awards made
aspects most relevant to disputes arising out of international
in states which are signatories to the New York Convention.
construction projects.
This is addressed later in this chapter. However, those states or
arbitral institutions which do distinguish between domestic and
1.05 In addition to the above legal regimes, any arbitration rules
international arbitrations generally do so by reference to:
drawn up or chosen by the parties to govern the arbitration or, in
default of agreement, determined by the tribunal at a preliminary
● the nature of the dispute, e.g. if it involves international
hearing once the arbitration has begun, will also impact the way
trade, or the application of international law, or the perfor-
in which the arbitration is run. These may be rules imposed by
mance of the contract in a state other than that of the nation
an arbitral institution chosen by the parties to administer their
of the contracting parties; or
arbitration.
● some factor connected to the parties, e.g. their nationalities,
or their place of residence, or business.
International construction arbitration
1.03 In France, for example, arbitration is treated as ‘interna-
1.06 In international construction projects, the use of arbitra-
tional’ if it involves the ‘interests of international trade’, but in
tion as a means of dispute resolution has a historic background,
Switzerland, it is the nationality of the parties that determines the
with arbitration clauses incorporated into the most widely used
matter. The question of whether an arbitration is ‘international’
standard forms of contract since their inception – the Conditions
therefore falls to be decided on a case-by-case basis, along with
of Contract first published by the Fédération Internationale des
the issue of what legal regimes apply.
Ingénieurs-Conseils (‘FIDIC’) in 1957.

Legal regimes relevant in 1.07 The use of arbitration clauses in international construc-
tion projects is now widespread, including in building con-
international arbitration tracts (whether or not based on FIDIC forms) and professional
1.04 Typically, there are four legal regimes that are relevant in services contracts including those for the services of archi-
international arbitration: tects. International arbitration has maintained its appeal in

275
276 International arbitration

international projects and is commonly found now at the conclu- may choose from, including the ICC Rules and The London
sion of an escalating dispute resolution procedure which very Court of International Arbitration (‘LCIA’) Arbitration Rules.
often includes mandatory intermediate steps. The FIDIC forms Finally, the courts of the seat of the arbitration may have juris-
include provision for a Dispute Adjudication Board (which diction to order a consolidation or hearing together of related
investigates and recommends provisional decisions to resolve disputes – for example, the Hong Kong courts have such a
disputes) and an amicable dispute resolution stage, (such as power, subject to the compatibility of the arbitration agree-
mediation), followed by arbitration (see, further, Chapter 19 in ments in each dispute.
respect of the FIDIC forms).
2.06 More generally, due consideration and recognition should
always be given to the implications of the choice of seat, for it
2 Factors relevant to the choice determines the supportive and supervisory role of the national
courts and any mandatory laws that shall apply to any interna-
of international arbitration tional arbitration. In Saudi Arabia, for example, the arbitral law
provides that the tribunal (or at least the Chairman if multiple
2.01 The factors which militate in favour of the choice of arbi- arbitrators are appointed) must hold a degree in Shari’ah law.
tration to resolve domestic disputes are also relevant to interna- Failure to comply with this mandatory requirement of the seat
tional disputes. Many of these factors are listed in Chapter 25, could amount to a procedural ground on which the enforcement
such as the privacy of the proceedings; the technical expertise of an Award might be refused or the Award annulled at the seat.
of the arbitrators (particularly relevant in construction arbitra-
tions, which can involve difficult technical issues and specialised 2.07 States vary in the support they give to the arbitral process
forms of contract); and the flexibility the procedure affords the and the extent to which they are prepared to interfere in that pro-
parties. For parties to an international arbitration, the flexibility cess. This is reflected in the powers which the state confers on
and the control afforded to the parties to determine their own the tribunal itself and upon the courts to supervise that process
procedure may be of greater significance than to parties to and to make ancillary orders, e.g. for the production of docu-
domestic proceedings. This is because parties involved in an ments, attendance of witnesses, or injunctions.
international project are often from distinct legal backgrounds
and are unfamiliar with the different legal procedures known
to the other party. Parties usually come from either a common 3 The agreement to arbitrate
law or civil law background; in which the role of the ‘decision
maker’, the parties’ legal representatives, and the manner and 3.01 In international arbitration, two types of arbitration agree-
method of proving or defending a case may be very different. ments are commonly seen. The first is a basic arbitration clause
in the main contract between the parties and tends to be rela-
2.02 The most common reason given for the choice of interna- tively brief, because it provides for the resolution of future, but
tional arbitration is by far the ease of enforcing an international as yet unknown disputes.
arbitration award. The New York Convention on the Recognition The second type, sometimes called ‘submission’ agreements,
and Enforcement of Foreign Arbitral Awards 1958 (the ‘New are discussed in section 3.11 below.
York Convention’) provides for the enforcement of ‘interna-
tional’ or ‘foreign’ arbitration awards in most of the major
countries of the world. There is no real global equivalent for
Institutional arbitration
the recognition and enforcement of domestic court judgments. 3.02 In large international construction projects, the parties very
The New York Convention has been important in facilitating the often sign up to an arbitration clause in the form of a model
creation of international construction projects, including secur- clause, recommended by one of the established arbitration
ing the provision of financial and economic measures requisite institutions. The parties may make provision for an institution
for such projects. to administer the arbitration and for the arbitration rules of the
institution to apply. This is known as an ‘institutional arbitra-
2.03 Another important factor is the opportunity international tion’. The advantages of an institutional arbitration include the
arbitration affords parties to contract out of a national court application of established international arbitration rules along
system and to refer a dispute to a neutral forum to which neither with trained staff to appoint the tribunal, to ensure time limits
party has any connection. This can be particularly attractive to a are observed, to review the award, and to assure the general
party, if it is wary of referring a dispute to the national courts of smooth running of the arbitration.
their contracting counterparty or the place of performance of the
contract, where the rule of law or independence of the judiciary 3.03 The ICC recommends the following sample clause, where
is not well established. the parties have chosen the ICC Court of Arbitration to admin-
ister their international arbitration:
2.04 An arbitrator’s jurisdiction derives (at least in part) from
the agreement between the contracting parties. This means that ‘All disputes arising out of or in connection with the present
arbitration may not be well suited for dealing with multi-party contract shall be finally settled under the Rules of Arbitration
disputes where these arise under separate contracts. This is very of the International Chamber of Commerce by one or more
relevant in international construction and engineering projects, arbitrators appointed in accordance with the said Rules’.
which may involve numerous parties with linked contractual
relationships and where frequently an employer may take issue This is a broad form clause and will encompass all types of
with more than one party, for example both the architect and disputes, including claims for misrepresentation and non-con-
contractor, in relation to the same dispute. tractual claims such as tort claims for professional negligence.

2.05 Multiple parties to a dispute may all agree to consoli- 3.04 There are no international arbitration institutions which
date or hear together their related disputes. Alternatively, the specialise in construction disputes, or specific international con-
parties may confer a discretion upon an arbitrator to order a struction arbitration rules. Parties therefore use the established
consolidation or hearing together of related disputes. The UK’s international institutions, such as the ICC, the LCIA, the China
Joint Contracts Tribunal (‘JCT’) has incorporated multi-party International Economic and Trade Arbitration Commission
arbitration agreements into its standard forms, but no such (CIETAC), the American Arbitration Association (AAA), the
provision has been made in the FIDIC Conditions of Contract. Singapore International Arbitration Centre (SIAC), and the Hong
Provision for multiparty arbitration is included in many of the Kong International Arbitration Centre (HKIAC). The institu-
model arbitration clauses and arbitration rules which parties tional arbitration rules of the ICC (which are widely used in
Procedure in international arbitration 277

international construction arbitrations) are referred to in greater 3.10 There are a number of important clauses which should be
detail in this chapter. included in an agreement to arbitrate:

3.05 The ICC headquarters are in Paris, but an international (i) The number of arbitrators and their method of selection. In
arbitration under the ICC Rules may have arbitrators of any large international arbitrations, the custom is to appoint a
nationality, sitting in any place and using any language. The role three-person tribunal, but this may not always be necessary.
played by the ICC Court of Arbitration is to ensure the proper The usual practice for the appointment of a tribunal is for
application of the rules; it will appoint or confirm the appoint- each party to appoint or nominate one arbitrator and for
ment of arbitrators and, in the absence of agreement between the the party-appointed or -nominated arbitrators to agree on
parties, fix the place of the arbitration. Some of the rules may be the appointment of a third arbitrator to be the chair of the
modified by the parties’ agreement, but the ICC will refuse to tribunal. In the absence of an express choice, the presump-
administer arbitrations where the parties’ agreement has modi- tion under the ICC Rules is for a sole arbitrator, unless the
fied rules that the ICC considers basic to the proper functioning Court considers the complexity of the dispute warrants the
of an ICC arbitration. appointment of a three-person tribunal.
(ii) The place or seat of the arbitration. It should be noted that
3.06 The ICC also administers the costs associated with the run- this does not mean that all arbitral proceedings have to
ning of an international arbitration, which in an ICC arbitration take place there. The tribunal usually has discretion to hold
can be significant (for a fuller explanation, see Section 8). Since proceedings at other venues.
the major arbitral institutions amend their arbitration rules from (iii) The language of the proceedings. Absent agreement of the
time to time, parties may wish to include drafting to make it parties, most arbitration rules provide the arbitrators with
clear which version they are seeking to incorporate be this the the power to decide the language of the arbitration.
version ‘in force on the date of their agreement to arbitrate’ or
‘as modified and amended from time to time’.
Submission agreement
3.07 There are many benefits that parties will derive by using 3.11 The other type of arbitration agreement commonly seen in
institutional arbitration (over ad hoc arbitration, discussed international arbitrations provides for the submission of an exist-
below). Amongst those are the administrative functions and ing dispute to arbitration, and therefore usually sets out in much
assistance that the institutions provide; they will receive filings, greater detail how the parties wish for the arbitration to proceed.
oversee the appointment and challenge of tribunal members, and This is sometimes called a ‘Submission Agreement’. It might
(at least in the case of ICC) scrutinise awards handed down by include such details as the names of the arbitrators agreed upon,
tribunals. Such benefits can be of particular value in instances of agreements reached regarding the procedure to be followed in
inexperienced or uncooperative parties (or counsel), and where the arbitration, and the venue for the arbitration.
the supervisory courts are not supportive of the arbitral process.
Pathological arbitration clauses
Ad hoc arbitration 3.12 From time to time, an agreement to arbitrate is so poorly
3.08 In principle, an ad hoc international arbitration operating drafted that it leads to a dispute over the correct interpretation
without the supervision (and associated cost) of an institution or effectiveness of the clause. The dispute can result in the
tends to be cheaper than an institutional arbitration. The parties complete failure of the agreement to arbitrate or in the unen-
are free to draft a procedure entirely suited to their particular forceability of an arbitral award. Such defective clauses are
dispute, but the risk with this approach is that the success of known as ‘pathological arbitration clauses’. The problems that
the procedure is dependent on the willingness of the parties to arise include:
cooperate in its drafting. The alternative is for the arbitration to
proceed without a formal written procedure in accordance with ● equivocal drafting as to whether binding arbitration is
directions made by the tribunal as and when required. In many intended or whether the parties are entitled to have recourse
ad hoc international construction arbitrations, parties chose to to national courts;
incorporate the UNCITRAL Arbitration Rules either as a whole ● conflicting or unclear procedures; and
or in part. The UNCITRAL Arbitration Rules are a set of stand- ● the inclusion of a reference to an arbitrator or arbitral institu-
alone arbitration rules which can be imported into an agreement tion that does not exist or refuses to act.
to arbitrate to provide many of the same benefits of certainty
over the procedure without reference to an arbitral institution or 3.13 Most national courts will usually attempt to give meaning
the associated expense. The UNCITRAL Arbitration Rules may to the defective arbitration clause, in order to give effect to the
be adapted by agreement between the parties. intention of the parties to arbitrate their dispute. Where it is
possible, a national court may discard the defective drafting if
3.09 In ad hoc international arbitrations, in circumstances where it is clear that the surviving clause represents the intention of
the parties cannot agree on the choice of arbitrator(s), the par- the parties. The ICC encounters clauses from time to time which
ties are obliged to refer the decision to an appointing authority. purport to provide for ICC arbitration, but which fail in this pur-
Provision should be made for this possibility when the arbitra- pose for lack of certainty. An example is a clause which refers
tion clause is drafted. The FIDIC forms suggest that where the an unresolved dispute between the parties ‘to the International
UNCITRAL Arbitration Rules are used, provision should be Chamber of Commerce’. Even if this clause is taken to be a
made to provide for the President of the FIDIC or a person broad reference to the ICC’s Court of Arbitration, it fails because
appointed by the President to appoint the arbitral tribunal, when it is not clear what method of dispute resolution it is intended
the parties cannot agree on its composition. Frequently, in the that the dispute be resolved by, e.g. conciliation, or mediation,
Royal Institute of British Architects (RIBA) contracts for archi- or arbitration, etc.
tects’ services, this role is filled by the President of the RIBA,
who is named as the appointer of the arbitrator. The RIBA’s list
of potential arbitrators includes individuals who are qualified as 4 Procedure in international
architects, engineers, and quantity surveyors, and some of these arbitration
are additionally qualified as lawyers. The choice of appointing
authority can be contentious, and it is worth exploring with the 4.01 The procedure for an international arbitration is derived
proposed appointing authority how it makes its appointments from the procedural rules agreed by the parties, whether set-
and the identity of the individuals on its list. tled by the parties themselves or imposed by the application
278 International arbitration

of institutional rules, or failing that, procedural rules settled closings by both sides. Oral hearings tend to be very short by
by the arbitral tribunal. In practice, the arbitral rules usually comparison with hearings before English courts, and cross-
grant a tribunal a wide discretion to devise a procedure that the examination is usually permitted, but is typically limited. Some
tribunal deems to be most appropriate for the dispute before it. arbitral rules provide that consideration should be given to
Procedural requirements may also be imposed on the parties whether an oral hearing is necessary at all, but in most cases, it
and/or the tribunal by the law of the seat of the arbitration. will be important for arbitrators to hear directly from key wit-
For example, a tribunal with its seat in England and Wales is nesses and any experts to be able to judge their credibility and
required to act fairly, impartially, and avoid unnecessary delay the weight to be given to their evidence.
or expense in accordance with section 33 of the Arbitration
Act 1996. 4.07 Hearings are usually held in private, and only the tribunal,
the parties, and their representatives are entitled to attend. After
the conclusion of the hearing, there may be further written
Commencement date submissions from the parties’ legal representatives, following
4.02 The commencement date is of particular importance if a which, the tribunal will draft its award.
challenge to the claim is raised on the basis that it is time barred
by the application of a limitation period arising under the sub- 4.08 The ICC Court of Arbitration reviews all international
stantive law of the contract. In ad hoc arbitration, the start date arbitration awards before they are published to the parties. This
is either agreed by parties or determined in accordance with the review is not on the merits of the decision, but so as to ensure
law of the seat. An ICC arbitration is commenced on the date that the tribunal has properly addressed all of the issues before
a Request for Arbitration is received by the Secretariat of the it. This is thought to give greater international acceptability to
Court in accordance with Article 4 of the ICC Rules. the award than might be the case in an award issued by an ad
hoc arbitral tribunal.
Appointment of the tribunal
4.03 If the dispute is to be referred to three arbitrators, the usual 5 Interim measures in
practice is that each party may appoint one arbitrator or, in the
case of multiple claimants or multiple respondents, they may international arbitrations
appoint jointly. The party-appointed arbitrators agree upon the
appointment of the third arbitrator. The practice varies slightly 5.01 Interim measures in international arbitration are sometimes
in an ICC arbitration. The ICC Court confirms the appoint- called ‘provisional relief’ or ‘conservatory measures’. The range
ments of the party-nominated arbitrators and the court appoints of measures sought can be wide reaching, relating to the pres-
the Chair of the tribunal unless the parties agree otherwise. ervation of evidence or party assets, or compelling a witness to
Notwithstanding that they have been nominated by a party, all attend a hearing and give evidence. A party may have recourse
arbitrators are obliged to be independent of the parties and to act to the tribunal or to a national court to grant an interim measure.
fairly and impartially in the conduct of the proceedings.
5.02 The power of a tribunal to grant an interim measure will
4.04 In an ICC arbitration, the ICC Court Secretariat will trans- turn primarily upon the terms of the arbitration agreement and
fer the case file to the tribunal once an advance on costs has been the law of the seat.
paid. The tribunal will then examine the Request for Arbitration
and the Answer to determine what, if any, further clarifications 5.03 The ICC Rules provide: ‘the Arbitral Tribunal may, at the
are required before the ‘Terms of Reference’ for the arbitration request of a party, order any interim or conservatory measure it
are drawn up. This is a procedural feature particular to the ICC deems appropriate’.
Rules. The Terms of Reference summarise each parties’ claims
and the relief sought, with sufficient detail to prevent either 5.04 There are similar provisions in the UNCITRAL Arbitration
party from introducing a new claim later on in the proceedings Rules and the LCIA Rules. The power conferred by the ICC
which falls outside the Terms of Reference, unless it has been Rules is wide ranging; it is not, for example, limited to measures
authorised by the tribunal. The Terms of Reference should also which affect property or evidence which is the subject of the dis-
include a list of the issues in dispute, so as to enable the arbitral pute. However, the tribunal may only act once the case file has
tribunal to ensure that all matters are considered in the arbitra- been provided to it by the ICC Court. There may be cause for a
tion and decided when it comes to drafting the award. Where the party to seek an interim measure before this, because it can take
list of issues cannot be agreed by the parties, it is common for time to establish the arbitral tribunal, and during that time, vital
each party to submit separate lists to the tribunal. evidence or assets could disappear, in which case a party will be
obliged to apply to the national courts for the interim measure.
4.05 After the appointment of the tribunal (and in the case of an
ICC arbitration, after the agreement of the Terms of Reference) 5.05 Typically, an order will be sought to secure assets out of
the parties typically come before the tribunal for a procedural which an award may be satisfied when a recalcitrant debtor is
meeting. At this meeting, the tribunal will usually seek to estab- deliberately dissipating assets to render itself eventually poor.
lish a timetable for the arbitration, providing for such things Difficulties with this process can arise where the parties have
as the preparation and exchange of witness statements, expert chosen a neutral seat for the arbitration where the courts of that
reports, and document production. Subsequent procedural hear- seat have no jurisdiction over the party (and their assets) against
ings may deal with issues that arise in the immediate run up to whom the interim measures are to be enforced. Necessarily then,
the main arbitration hearing or hearings, and the conduct of the the parties will have to apply to a foreign court to render assis-
arbitration hearing itself. tance to an arbitration with a seat elsewhere.

4.06 The procedure will often include written submissions 5.06 Many states permit their national courts to grant interim
known as ‘memorials’ which exhibit the evidence on which measures in support of an international arbitration. In practice,
each party intends to rely (both documentary and in the form a party may therefore have a choice as to whether an application
of witness statements). These submissions are usually presented for an interim measure is made to the tribunal or to the national
consecutively, the claimant first, followed by the respondent, courts. The appropriate course of action will depend, in each
and permission may be given for further ‘reply’ submissions. case, on the particular application, the relevant law and the relief
Common law style pleadings are sometimes used instead of sought, and the ease of enforcement. If it is necessary for coer-
memorials. Provision is usually made for short oral openings; cive action to be taken to deal with the issue, the measure must
concise oral cross-examination of witnesses, and short oral usually be pursued through the national courts. In England, the
Evidence in international arbitration 279

court will only act with the permission of the tribunal (unless the but far wider than any terms a European party would be familiar
matter is urgent), and only where the tribunal lacks jurisdiction with. A party is entitled to object to a Request to Produce in
or is unable to act effectively. accordance with limited grounds set out in the IBA Rules.

5.07 In recent years, emergency arbitration has developed as a 6.04 In recent years, parties objecting to a Request to Produce
means of obtaining urgent relief before an arbitral tribunal has have often cited the ground that the request placed an ‘unreason-
been formally constituted. Many of the leading arbitral institu- able burden’ on them to produce, as a result of the overwhelming
tions have revised their rules to incorporate provisions on emer- amount of electronic documentation falling into the category of
gency arbitration. Through this mechanism, parties are able to documents requested. This is a consequence of the electronic
apply for an emergency arbitrator to be appointed at short notice revolution in document creation, and the use of email com-
to decide on an application for urgent interim relief in a short munication. As a result, the IBA Rules were revised in 2010 so
period of time, typically ranging from a couple of days to one or as to provide greater guidance on how to address requests for
two weeks. It will be up to the subsequently constituted arbitral electronic documents. Article 3(3)(a) of the IBA Rules grants
tribunal to uphold or reverse any order issued by the emergency the tribunal the power to order the requesting party to identify
arbitrator, and it is understood that the arbitral tribunal will specific search terms or other economical means of searching for
not be bound by the decisions of an emergency arbitrator. Not the documents requested.
infrequently, however, the emergency arbitrator’s preliminary
assessment of the particular strengths and weaknesses of the
parties’ case may lead to an early settlement.
Factual witness evidence
6.05 Some civil law jurisdictions prevent a party-affiliated indi-
vidual from giving evidence as a witness of fact; this is in sharp
6 Evidence in international contrast to the common law practice which permits any person
to present evidence, including a party to the arbitration agree-
arbitration ment. International arbitration practice generally follows the
common law, though the tribunal may accord less weight to the
6.01 Under most international arbitration rules, the tribunal has evidence of a party-affiliated witness than to that of an independ-
a wide discretion to establish the facts of the case by any appro- ent witness. Generally, if a party submits a witness statement,
priate means, subject to any agreement by the parties and any the witness should be prepared to attend the arbitration and to
mandatory laws of the seat. Parties may choose to adopt (in full give oral testimony, unless the parties have agreed otherwise or
or in part) the International Bar Association Rules on the Taking the arbitral tribunal has made such a direction. Sometimes, a
of Evidence in International Arbitration (the ‘IBA Rules’). tribunal will exercise its discretion to refuse to hear a witness,
These provide the tribunal with guidance on how to deal with if it determines that it is sufficiently well informed of the facts
issues of evidence and document production. The IBA Rules through other evidence that has already been admitted.
are specifically designed to supplement the institutional arbitral
rules which apply to the conduct of the arbitration proceedings. 6.06 The IBA Rules provide that where a witness has submitted a
statement, but does not attend to provide oral testimony (without
Admissibility of evidence a valid reason), the arbitral tribunal may dismiss their evidence
(Article 4[7]). There is no such express provision in the ICC
6.02 There is very little authority on how a tribunal should Rules as to what happens when a witness fails to appear, and it
address the admissibility of evidence in an international arbi- will be a matter for the tribunal to determine what, if any, weight
tration; the UNCITRAL Arbitration Rules, the ICC Rules of should be given to the evidence contained in the statement.
Arbitration, and the LCIA Rules are silent on the matter. The
consequence is that formal rules governing the admissibility 6.07 The tribunal will usually provide the legal representatives
of evidence tend not to apply in international arbitration, and of the parties with the opportunity to cross-examine the wit-
all evidence is accepted by the tribunal, with its weight and nesses and it may put some questions directly to the witnesses
relevance assessed accordingly. itself.

Disclosure Expert witnesses


6.03 A party’s expectation of the document production or disclo- 6.08 In complex construction arbitrations, the opinion of experts
sure process will depend on whether they are from a common is often required because of the technical nature of the matters
or civil law background. A party from a civil law background in dispute.
is likely to object to the common law approach of producing all
‘relevant’ documents to an opponent’s case, on the basis that 6.09 If a party wishes to call expert evidence and the request is
it is costly and too onerous to apply. Parties who chose not to acceded to by the tribunal, the other party will be given the same
adopt institutional rules, or where such rules do not provide for opportunity. Most tribunals will provide directions for experts of
discovery (as is the case with the UNCITRAL Arbitration Rules, the same discipline to meet and to discuss any conflicting views
the ICC Rules, and the LCIA Rules), may incorporate the IBA in an attempt to narrow the issues in dispute, before each expert
Rules in whole or in part. The IBA Rules provide that the parties produces his report.
shall first submit to each other and the tribunal the documents
on which each party intends to rely. After such an exchange, any 6.10 Most national laws and arbitration rules provide that the
party may submit a ‘Request to Produce’ to the arbitral tribunal, tribunal may appoint experts to assist it on specific or techni-
in which the requesting party is required to set out: cal matters. The costs of such an appointment will generally
form part of the overall costs of the arbitration, to be paid by
● documents, or a narrow or specific requested category of the parties and not the tribunal. Therefore, if a party objects,
documents that are reasonably believed to exist and to be in a tribunal is usually cautious to appoint. The tribunal will be
the possession of another party (and are not in the possession aware that in practice, the parties will be unlikely to allow the
of the requesting party); and tribunal-appointed expert’s evidence to stand unchallenged and
● an explanation of how the documents requested are relevant will usually seek to adduce their own expert evidence. If such
and material to the outcome of the case. an appointment is made, Article 6 of the IBA Rules provides
that the terms of reference for the tribunal-appointed expert
The grounds set out in Article 3 of the IBA Rules are more should be closely defined after consultation with the parties,
restrictive than the comparative English Civil Procedure rules, and the parties should be afforded the opportunity to raise any
280 International arbitration

objections to a tribunal-appointed expert’s independence. In


Capacity The parties to the agreement were under some
practice, the tribunal should also afford the parties an opportu-
incapacity, or the agreement to arbitrate is not valid
nity to put questions to the tribunal-appointed expert during the
under the law to which the parties have subjected it or
arbitration hearing.
the law of the seat where the award was made.
Notice The party against whom the award is invoked was not
Confrontation testimony given proper notice of the appointment of the arbitrators
or of the proceedings or was otherwise unable to present
6.11 The simultaneous questioning of two or more witnesses its case.
on the same issues is increasingly being used as a technique. It Scope The award deals with matters not within the scope of
is called ‘confrontation testimony’, ‘witness conferencing’ or, the agreement to arbitrate.
in one variant, ‘hot tubbing’. It is popular where one or more Procedure The composition of the arbitral tribunal or its procedure
issues have great importance to the tribunal reaching their final was not in accordance with the agreement of the parties
determination on the merits, such as the opinion from experts or absent such agreement not in accordance with the law
on the viability of a design. Confrontation testimony enables the of the seat.
tribunal to hear immediately where the witnesses are in agree- Finality The award has not yet become binding on the parties,
ment and where their accounts differ. or has been set aside or suspended, for example the ICC
Court of Arbitration has yet to approve the award and
issue it.
7 International arbitration Arbitrability The subject matter of the difference is not capable of
awards – recognition, settlement by arbitration under the law of the country
challenges, and enforcement where enforcement is sought.
Public Policy Recognition or enforcement of the award would be
7.01 At the conclusion of an international arbitration, the tribunal contrary to the public policy of the country where
will publish its award, which will generally be immediately final enforcement is sought.
and binding. Typically, the tribunal will require payment of all
its fees and expenses before publication. The law of the seat 7.05 The grounds are relatively limited and largely concerned
may provide for certain limited rights of challenge or appeal. It with procedural irregularities that must be proved by the appli-
is common for parties to an international dispute to contract out cant, except for the last two grounds, which may only be raised
of the rights of appeal to the fullest extent possible under the law by the national court charged with recognition and enforcement,
of the seat, and many institutional rules, including those of the of its own motion. The exact procedure to be followed and the
ICC, provide for this. If prior to the conclusion of the arbitra- way in which the New York Convention is interpreted is a matter
tion the parties reach a settlement, most international arbitration for the national law and national courts of the country in which
rules provide for the tribunal (if requested by both parties), to recognition and enforcement is sought.
record the settlement in the form of an award which need not
contain reasons. 7.06 Most states support the arbitral process and construe the
bases for refusing enforcement fairly narrowly. In these states
7.02 The award, if not carried out voluntarily, may be enforced (among which the UK can be included) a refusal to recognise
by legal proceedings through the courts. There are a number and enforce an award is very rare. Other signatory states have
of regional and international treaties and conventions which perhaps embraced the spirit of the convention less wholeheart-
relate to the enforcement of awards, but the most important of edly, and their courts construe the grounds more liberally (par-
these is the New York Convention which is recognised in over ticularly the public policy ground) with the consequence that
160 countries. It requires the local courts of the contracting refusal to recognise or enforce an award is more common.
states to give effect to an agreement to arbitrate when seized
of an action in a matter covered by an arbitration agreement by
staying any court proceedings which are brought in breach of 8 Costs in international arbitration
that agreement and also to recognise and enforce awards made
in the territory of a state other than the state in which recogni- 8.01 The law of costs in international arbitration is properly to be
tion and enforcement is sought, and to awards not considered considered part of the law of the seat. In general, arbitral rules
as domestic in the state in which enforcement is sought. It has give the tribunal a broad discretion to make cost orders. Most
one principal formal requirement stipulated in Article II, that rules are silent as to how that discretion should be exercised,
the arbitration agreement be in writing. Some states will only though the LCIA rules provide that the cost award should in
enforce awards made in other contracting states – another rea- general reflect the parties’ relative success and failure.
son that care must be taken with the choice of the seat of the
arbitration. 8.02 In practice, a losing party will often be ordered to pay the
legal and other costs of the arbitration. These costs may include:
7.03 A party seeking recognition and enforcement of an award to
which the New York Convention applies, is obliged to produce ● a substantial proportion of the legal fees of the winning
to the relevant court: party;
● the fees and expenses of the arbitrators;
● the duly authenticated original award or a duly certified ● the costs of any tribunal appointed experts; and
copy thereof; and ● any costs arising out of the administering of the arbitration
● the original agreement to arbitrate or a duly certified copy by an institution.
thereof.
These costs fall to be paid by the losing party in addition to
Certified translations of the documentation are required if their own legal costs and other expenses. Where there is no
the official language of the country in which recognition and clear loser, or where the winner has succeeded on only a part of
enforcement is sought is not the language of the documentation. its claim, a tribunal is likely to make some other order for the
The court will then usually grant recognition and enforcement proportions in which the parties are to bear the costs. Tribunals
of the award. with a broad discretion may take into account any offers to settle
made by the parties when making an award of costs on the basis
7.04 The New York Convention provides, in Article 5, lim- that a party should not have to bear the costs of proceedings
ited grounds on which a court may (it is discretionary) refuse which ought not reasonably to have continued once the offer
enforcement: had been made.
Costs in international arbitration 281

8.03 Under the ICC Rules and Guidance Note on the Conduct then take these offers to settle into account when determining
of the Arbitration under the ICC Rules of Arbitration, the parties an award for costs.
may avail themselves to the ‘sealed offer’ provisions. A sealed
offer is an offer from one party to another to settle a dispute that 8.04 The cost of an institutional arbitration may be significantly
is made on a ‘without prejudice save as to costs’ basis. These greater than the costs of conducting a similar arbitration on an
sealed offers are provided only to the Secretariat of the ICC, ad hoc basis. Under the ICC Rules, the charges made by the
who will hold all correspondence relating to potential ‘sealed institution for administrative expenses, as well as the fees and
offers’ made by the parties in the course of the arbitration. When expenses of any experts appointed by the arbitral tribunal and the
the tribunal informs the Secretariat that it is ready to begin the arbitrators’ fees, are given in terms of a fixed percentage of the
process of apportioning costs, only then will the Secretariat sum in dispute on a sliding scale, so that the greater the sum in
provide this correspondence to the Tribunal. The Tribunal may dispute, the greater the overall fee, but the smaller the percentage.
27
Mediation
SHEENA SOOD AND ANNA BRADEN

1 What is mediation? organisations such as the Centre for Effective Dispute Resolution
(CEDR), Lord Woolf was commissioned in 1994 to review the
1.01 Mediation is a form of alternative dispute resolution (ADR) rules and procedure of the English civil justice system, which led
in which a neutral third-party mediator assists the parties to a to the implementation of the Civil Procedure Rules 1998 (CPR).
dispute to negotiate with each other with the aim of agreeing a Underpinning the rules is the principle of the overriding objec-
settlement of the dispute. It is a voluntary, flexible, and consen- tive, which imposes a duty on the parties to enable the courts to
sual process, with the parties maintaining control. The parties deal with cases justly and at a proportionate cost.
are free to decide whether or not to settle the dispute and can
devise their own solutions to resolution. Mediation is typically 2.02 The introduction of the CPR changed attitudes towards
confidential, allowing the parties to discuss the dispute freely mediation and the courts now actively encourage parties to
and openly, without fear of information being made public or seek alternative forms of dispute resolution to litigation. The
later used against them in subsequent proceedings if the parties Pre-Action Protocol for Construction and Engineering Disputes
are unable to resolve the dispute at mediation. introduced into the CPR stipulates that one of the objectives
of the Protocol is to make appropriate attempts to resolve the
1.02 There are several styles of mediation. The most common matter without starting proceedings and to consider the use of
form of mediation is facilitative mediation, where the mediator an appropriate form of ADR in order to do so. The third edition
will work to facilitate agreement between the parties to reach of the Technology and Construction Court (TCC) Guide sets
agreement of a dispute without providing his or her own opin- out that the TCC will give active encouragement to the parties
ion on the merits of any party’s case. Another popular form of to use ADR and will, where appropriate, facilitate the use of
mediation is evaluative mediation, where the mediator may be such a procedure. Mediation is the subject of the EU Mediation
asked to evaluate the strengths and weaknesses of the parties’ Directive (2008/52/EC) to encourage the use of mediation as a
positions and the likely outcome of the dispute in subsequent cost-effective and quicker alternative to civil litigation for cross-
proceedings. border commercial disputes.

1.03 The main objective of mediation is to reach a binding 2.03 Parties are now far more willing to mediate, and it is widely
agreement that settles either all or part of the matters in dispute. accepted as a sensible and effective form of dispute resolution.
Mediation can also be used to identify and narrow the issues in
dispute. Therefore, even if the parties are unable to resolve the
dispute at a mediation, the information gained at mediation may 3 Agreeing to mediate
be useful in subsequent negotiations or proceedings.
3.01 The first step in the mediation process is reaching agree-
1.04 Mediations can involve two parties or several different ment between the disputing parties to attempt to settle the
parties to a dispute. In construction disputes, it is common for dispute by mediation. As mediation is a voluntary, consensual
mediations to involve multiple parties. process, it can be challenging in some instances to persuade
another party to mediate. However, due to the potential cost
1.05 Mediation has a high success rate. The success of a media- consequences in litigation of unreasonably refusing to mediate,
tion and whether the parties are able to resolve their dispute at it can be difficult for a party to refuse to mediate.
the mediation usually comes down to how much preparation they
have done prior to the mediation to come to a realistic view of its 3.02 Mediation is commonly provided for in standard forms of
position in the dispute and the commercial sensitivities in play. contract. For example, the RIBA Standard Professional Services
Contract 2018 provides that the parties may agree to try and
resolve their differences though mediation without prejudice
2 Background to any other dispute resolution rights. The majority of the JCT
Suite of Contracts Edition 2016 provide that each party should
2.01 Prior to the late 1990s, mediation was infrequently used in give serious consideration to any request by the other to refer a
commercial dispute resolution. There were, however, systematic dispute to mediation if negotiation proves unsuccessful.
problems with the litigation process in England and Wales at
this time due to the significant costs, length, and delays of liti- 3.03 Bespoke contracts may also contain provision for the par-
gating a dispute. Following lobbying and campaigning for the ties to mediate, which are commonly drafted as multi-tiered
development of alternative methods of resolving disputes from dispute resolution clauses. ADR (including mediation) can be

283
284 Mediation

provided as a mandatory pre-condition to the commencement flexibility to determine the appropriate expertise required of the
of other proceedings such as litigation or arbitration (see Cable mediator, depending on the particular nature of the dispute.
& Wireless plc v Ibm Uk Ltd [2002] EWHC 2059 (Comm)),
the enforceability of which will depend on whether the ADR 5.02 The mediator’s fees may also be a factor to take into
clause is clear, unambiguous, and enforceable (SulamÉrica Cia account when selecting a mediator. Experienced mediators with
Nacional De Seguros S.A. and others v Enesa Engenharia S.A. expertise in construction disputes can typically charge between
and others [2012] EWCA Civ 638 and Emirates Trading Agency £300–500 per hour, and more for multi-party disputes. For lower
LLC v Prime Mineral Exports Private Ltd [2014] EWHC 2104 value disputes, some mediators offer fixed fees and other media-
(Comm)). tion packages.

3.04 The courts have no jurisdiction to force the parties to 5.03 Mediators in construction disputes are frequently lawyers
mediate (Halsey v Milton Keynes NHS Trust and Steel v Joy who are familiar with the legal issues in dispute in construction
and Halliday [2004] EWCA (Civ) 576). However, the Courts matters. It is also common for mediators to be construction
actively encourage the parties to consider forms of ADR and professionals, such as engineers or consultants who are familiar
stipulate that litigation should only be used as a last resort. The with the technical issues in dispute.
Practice Direction for Pre-Action Conduct and Protocols pro-
vides that the Courts may decide that there has been a failure of 5.04 There are several professional and independent bodies
compliance with the relevant pre-action protocol if a party has with lists of experienced mediators, which can provide names
unreasonably refused to use a form of ADR or failed to respond of mediators on enquiry, such as RIBA, CEDR, CIArb, RICS,
to an invitation to do so. In the event that the court decides that CIOB. If the parties cannot agree on the appointment of a media-
there has been a non-compliance with the relevant protocol, it tor, the parties can request that one of these bodies nominate
can apply cost sanctions against the party at fault (e.g. Burchell a mediator. In some mediations, an assistant or co-mediator
v Bullard [2005] EWCA Civ 358). may be required, which is increasingly common in multi-party
disputes.
3.05 When considering whether a party has unreasonably refused
to mediate, the court is likely to take into account the nature 5.05 Consideration should be given to whether the mediator is
of the dispute, the merits of the case, whether other settlement impartial, and the mediator should undertake a conflict check
methods have been attempted, whether the costs of mediation to ensure that he or she is not conflicted prior to appointment.
would be disproportionately high, delay, and the prospects of
success of the mediation (Halsey v Milton Keynes NHS Trust 5.06 Once selected, the mediator will usually send the parties a
and Steel v Joy and Halliday [2004] EWCA (Civ) 576). A party’s draft mediation agreement to be agreed in advance of the media-
silence in failing to respond to an invitation to mediate is likely tion. CEDR provides a Model Mediation Agreement (www.cedr.
to be held to be unreasonable and lead to the court awarding co.uk). The mediation agreement will usually require that each
cost sanctions against it (PGF II SA v OMFS Co 1 Ltd [2013] party has someone at the mediation present with full authority
EWCA Civ 1288). A party should be pragmatic when it receives to negotiate and settle the dispute and to bind it to the terms of
an offer to mediate from another party. any settlement agreement. If a party is a company, it is therefore
usually appropriate for a director or someone with equivalent
decision-making authority to attend the mediation and, if a party
4 The correct time to mediate has insurance, for a representative of its insurers to attend the
mediation.
4.01 Unless mediation is provided as a mandatory provision
under a contract, the parties are free to decide when to mediate,
and it can be undertaken at any stage, including before or dur- 6 Costs of the mediation
ing another more formal dispute resolution process. The parties
may disagree when the optimum time to mediate is. Generally, 6.01 The parties should give careful consideration to how the
a party will want a certain amount of initial investigation to costs of the mediation are to be paid, which is a matter for agree-
be undertaken to ascertain the facts surrounding the issues in ment between the parties and the mediator (in relation to the
dispute, which may include obtaining an expert opinion from an mediator’s fees). It is common for mediators to require that the
independent expert to form a view as to the merits of their case. mediator’s fees and expenses are to be shared equally between
This is especially true of insurance-backed disputes, as insurers the parties, but for the parties to be jointly and severally liable
frequently require a view on the merits of an insured’s case to be for his or her fees. This should be avoided if there is any doubt
undertaken prior to agreeing to attend a mediation to set suitable that one of the parties will fail to pay their share of the fees. It
reserves for the mediation. is also common for the parties to agree to bear their own costs
of the mediation, but that in the event that the dispute does not
4.02 For construction and engineering disputes, each party to settle at the mediation, and proceeds to litigation or arbitration,
the dispute is obliged by the CPR to adhere to the Pre-Action for the costs of the mediation to become ‘costs in the case’.
Protocol for Construction and Engineering Disputes prior to
initiating litigation proceedings. The Protocol culminates in a
stipulation that the parties should normally attend a Pre-Action 7 Confdentiality and privilege
Meeting. The aim of the meeting is, amongst other matters, for
the parties to consider whether, and if so how, the dispute might 7.01 The mediation agreement and the procedural rules which
be resolved without recourse to litigation. Parties frequently use govern the mediation will determine the confidentiality terms
this point to consider whether to mediate, and it is typical for of the mediation. Mediation agreements will typically provide
the parties to agree for the Pre-Action Meeting to take the form that all communications and information (subject to some
of a mediation. limited exceptions) made in, or in connection with, the media-
tion between the parties and the mediator are confidential, and
subject to without prejudice privilege, and not admissible as
5 Selecting a mediator evidence in current or future proceedings or dispute resolution.
A confidentiality clause is likely to be implied in the absence
5.01 It is common for the parties to select a mediator at the time of an express confidentiality clause (Farm Assist Limited (in
of the dispute, often on advice from their legal advisors. If a liquidation) v The Secretary of State for the Environment, Food
party’s insurers are involved, insurers may also have preferences and Rural Affairs (No.2) [2009] EWHC 1102 (TCC)). The court
for particular mediators. This provides the parties with greater may, however, permit confidential information arising out of a
Advantages and disadvantages 285

mediation in exceptional circumstances, where it is in the inter- parties to each sign the mediation agreement. It is typical for
est of justice to do so (Farm Assist, above). the parties to subsequently attend a plenary session with all the
parties and the mediator. Typically, at the plenary session, the
mediator will address the parties and set out the procedure for
8 Preparation for the mediation the mediation. The parties will then take turns to make a brief
opening statement highlighting their position in the dispute
8.01 Once appointed, the parties and the mediator will agree (the plenary session can be dispensed with if the parties or the
the procedure to be adopted. If discussions are held with the mediator considers that it would not assist the parties to resolve
mediator prior to entering into the mediation agreement, it is the dispute). The opening statement is a good opportunity to
important that those discussions are agreed to be confidential set the tone for the mediation and to address the other party
and privileged. directly in relation to the dispute. A party should consider the
opponent’s body language for signs of potential weaknesses
8.02 Typically, each party produces a case summary of its in their case. The parties may ask questions of each other and
respective positions to be exchanged between the parties and request information and/or that documentation be provided.
submitted to the mediator in advance of the mediation. A core The parties may thereafter further explore the issues in a joint
bundle of documents will usually be agreed between the parties session, in separate group sessions, or separate party meetings
to be provided to the mediator for pre-reading and to be referred with the mediator.
to at the mediation.
9.03 The mediator will continue to work with the parties to
8.03 The parties will set a date for the mediation and agree the establish the critical issues in dispute, to identify the obstacles
duration of the mediation with assistance from the mediator. to settlement, to assist each party in taking a realistic look at its
The parties will also agree a venue for the mediation. There are own position, and to consider creatively the possible solutions
dispute resolution centres available to accommodate mediations to the dispute with the aim of reaching a point at which the par-
if required, such as the International Dispute Resolution Centre ties will be able to start negotiating a settlement of the dispute.
(IDRC). Typically, each party will require their own separate
break-out rooms and a main room to accommodate all the parties 9.04 In considering and exploring offers for settlement, the medi-
and the mediator for group sessions. ator may use a number of tactics to assist the parties to reach
agreement. The mediator will likely highlight to the parties the
8.04 Depending on the size and nature of the dispute, the parties alternatives to not achieving settlement and will likely encour-
will need to consider whether there is a need for legal represen- age a party to take account of the risk of proceeding, losing, and
tation and expert evidence. In addition, if a party has insurance, paying the other parties’ costs. The courts have expressed the
it will be necessary to liaise with its insurers in advance of the view that adopting an unreasonable position at a mediation is a
mediation to ensure that they are in agreement with the strategy matter which may lead to a party which succeeds at trial being
and tactics to be employed at the mediation, have set suitable deprived of its costs (Carleton (Earl of Malmesbury) v Strutt &
reserves, and to consider whether a representative for its insurers Parker (a partnership) [2008] EWHC 424 (QB)).
is required to attend the mediation.
9.05 It is common for opening offers to be significantly far apart,
8.05 Good preparation is key to enhance the likelihood of as parties usually allow themselves sufficient bargaining room to
reaching an acceptable outcome at the mediation. Parties should negotiate. The parties should, however, be careful not to offer an
ensure that they understand the case in detail, including the amount which is too high or too low as to discourage the other
merits of their case, and should undertake a realistic assessment side that there is any possible chance of settlement. The parties
of the weaknesses of their arguments. It is important for a party should try and make reasonable and sensible offers as soon as
to be prepared to answer likely arguments raised by the other possible. The parties should approach the mediation appreciating
parties. Each party should consider what issues are important that in order to achieve a resolution of the dispute, it will involve
to them, such as whether it is key to maintain a good business a degree of compromise.
relationship with the other party.

8.06 If opening statements are going to be made at the media- 10 Settlement


tion, each party should consider who is best to deliver the state-
ments, and these should be prepared in advance. 10.1 The parties may or may not be able to agree a settlement
of the dispute at the mediation. If the parties do not settle the
8.07 A party should consider the likely possible range of set- dispute on the day of the mediation, it is increasingly common
tlement at the mediation and the worst settlement level it is for the parties to reach agreement in the following days after
prepared to accept. The parties should consider the costs it has the mediation. If the mediation is to continue after the day of
already incurred and estimates to resolve the dispute if the matter the mediation, it is important that it is agreed between the par-
does not settle at the mediation (such as resolving the dispute ties that further correspondence, discussions, and information
through litigation or arbitration) to weigh up the cost risk of not between the parties and with the mediator is confidential and
agreeing a settlement. privileged. Reaching a binding agreement at the end of the day
of the mediation is preferable in order to avoid a subsequent
8.08 It is good practice for a party or its legal advisors to prepare change in a party’s position.
a draft settlement agreement to bring to the mediation to save
time at the mediation. 10.2 Typically, a mediation agreement will provide that, if the
parties reach agreement at the mediation, the agreement must be
written down and signed before it becomes binding.
9 The mediation
9.01 The structure of the day of the mediation is flexible and 11 Advantages and disadvantages
will depend on the particular requirements of the parties and the
nature of the issues in dispute. The parties are free to decide how 11.01 The potential benefits of mediation are extensive. The
to structure the mediation with assistance from the mediator. main advantages include:

9.02 The mediator is likely to request to meet the parties sepa- ● The opportunity for a quick and relatively inexpensive way
rately at the commencement of the mediation and to require the (compared to other forms of dispute resolution) of reaching
286 Mediation

a settlement of the dispute at an early stage of the dispute, 12.03 Typically, the mediator will have an element of control
reducing potential legal costs, and the cost risk of further over the particular technology that is used during the online
proceedings. mediation. Video-conferencing software that enables parties to
● A way of facilitating communication and information create virtual ‘rooms’ in which the parties can be placed is popu-
between the parties and to gain an early understanding of lar. This allows the mediator to interact with the parties privately
your opponent’s case. in a manner that is similar to physical mediation.
● An opportunity to preserve business relationships and to
repair existing or broken relationships. 12.04 The exchange and presentation of documents during the
● The parties can agree terms of settlement which would not online mediation may be facilitated by the mediation platform
be possible through litigation or arbitration. itself or through email correspondence and e-bundles between
● The confidential nature of mediation allows the parties to the participants and the mediator. The parties should be aware
freely discuss the dispute without fear of this information of the need to ensure that adequate arrangements are in place
being made public or used against them in subsequent to securely protect information that is exchanged online during
proceedings. the mediation.
● The parties maintain control of the process and are free to
terminate the mediation at any time. 12.05 Online mediation has a number of potential advantages
over traditional mediation. Key advantages include:
11.02 Typical disadvantages of mediation are:
● The mediation can be conducted at any time and in any loca-
● There is no guarantee that a mediation will be successful at tion where an internet connection is available, enabling the
resolving a dispute. parties to conduct the mediation at their own pace.
● If the mediation is unsuccessful, it can add time and costs ● Costs of travelling to the mediation will be reduced or
to resolving the dispute. extinguished.
● There will be no costs incurred in hiring a mediation
venue.
12 Online mediation
12.06 Some of the disadvantages of online mediation are:
12.01 Modern technology can be used to conduct mediation over
the internet. Online mediation has become increasingly popular ● It can impersonal and can hinder the ability of some parties
in recent years as global disputes have become more common. to communicate as effectively as they would in a physical
meeting.
12.02 There are a variety of platforms available to parties who ● Lack of a high-speed internet connection can limit and/or
wish to conduct a mediation online. The platform(s) and soft- prevent the ability of some parties to take part in the online
ware used in the online mediation are likely to be determined by mediation.
the mediation provider. Early online mediations were carried out ● Difficulties in building rapport with both the mediator and
using email. However, the use of video-conferencing software is the other parties involved, particularly where the online
now rising. The parties may also choose to conduct the online mediation is conducted on an ‘audio only’ basis or by using
mediation on an ‘audio only’ basis. email.
28
Building dispute resolution in Scotland
ROBERT HOWIE QC

1 Arbitration in Scotland clause as properly construed, for it is a precondition of any


arbitration that there is a dispute between the parties which may
1.01 It is common to find in building contracts in Scotland be arbitrated. It has been the practice of the court to decline to
provisions for the arbitration of disputes which arise thereun- sist actions for arbitration (particularly where the demand for
der or in connection therewith. Indeed, an arbitration clause a sist is made in answer to a motion for summary decree in a
appears in the Scottish Standard Form Building Contract which court action designed to enforce one party’s claims against the
is published by the Scottish Building Contract Committee. This other) where the court is not persuaded that there exists a bona
does not mean that parties are obliged to resolve their disputes fide dispute between the parties, as opposed to a mere refusal
by arbitration when those disputes arise under that form of by A to meet a claim made upon it by B. Under the wide defini-
building contract or, indeed, any other which contains an arbi- tion which has been given to the word ‘dispute’ in the second
tration clause. Parties are at liberty to delete the pre-printed section of the new Arbitration legislation, however, it is likely
standard form of clause from their own contract or, subject to that it will no longer be possible for the court to prevent the
very broad limits, to amend the pre-printed form in any way right to demand arbitration in cases where it apprehends that
they like, and, not infrequently, some degree of modification that right is being exploited as a delaying tactic. Any difference
to standard form clauses is made by contracting parties. Where between the parties is now sufficient to create a ‘dispute’ for the
the arbitration clause is entirely deleted, the result will be that, purposes of the statutory right to a sist created by section 10 of
in the absence of some other ad hoc arrangement being made the Arbitration (Scotland) Act, 2010. But it is still necessary, if
for the resolution of any dispute which may come to arise a sist is to be secured, that the dispute in question should fall
between the parties to the contract, that dispute will have to within the purview of the arbitration clause properly construed.
be resolved in the courts in the usual way. Even when arbitra- Whether, in any given case, that requirement is met is a strictly
tion clauses are not deleted, however, it is open to parties if legal question on which advice should be taken, but in the
they wish to ignore those clauses and take their disputes to the context of Clause 9.3 of the SBCC Agreement, it should rarely
courts for resolution. This is, in fact, commonly done, as when cause much difficulty, since that clause remits to arbitration any
a dispute breaks out there are often reasons – not infrequently dispute arising under or in connection with the contract. Other
involving the need for prescription reasons to sue more than clauses, however, particularly in bespoke contracts, may give
one party – why a pursuer will prefer to bring an action in the rise to much greater difficulty.
courts rather than arbitrate.
1.04 Even where an arbitration clause appears in the contract,
1.02 Conversely, it is not necessary for a building contract to however, it is impossible to insist that a given dispute be arbi-
contain an arbitration clause in order to allow the parties to adopt trated where either of the parties seeking so to insist has waived
that mode of dispute resolution in relation to a given dispute the right to do so or has become personally barred from so insist-
if they both wish to do that. The existence or otherwise of an ing, or the right so to insist has itself prescribed. Architects, if
arbitration clause in a contract assumes importance when at the they should find themselves involved with the initial stages of
time when a dispute arises the parties are not in agreement as to a dispute as agent for the employer, should therefore be alert to
whether or not that dispute should be remitted to arbitration. If the danger of so acting – or failing to act – as to set up a plea of
there is no arbitration clause incorporated into the contract, then waiver or personal bar against their employer, a plea which may
because the basis of all jurisdiction in arbitration is consensual, serve to prevent that employer from insisting that the dispute
the party opposed to arbitration can refuse to assent to it, and be arbitrated rather than publicly canvassed in court. Since both
may effectively force its contradictor to litigate in order to secure waiver and personal bar involve questions of fact, it is not pos-
a resolution of the dispute. But if, on the other hand, such a sible to indicate in advance what conduct by the architect may
clause has been incorporated, then unless personally barred from be found to raise such a plea. It is a matter in which architects
so doing, the party insisting on arbitration can force its opponent concerned about the problem should take advice in light of the
to arbitrate as it had contracted to do, and, assuming that the circumstances of the cases which face them. Prescription of the
obligation to arbitrate has not been lost, will be entitled to the right to arbitrate through the elapse of five years since the right
sist (anglice stay) of any court proceedings about the dispute came into existence without that right being exercised or being
raised by the other party until the arbitration is completed or for the subject of a relevant claim or acknowledgement for the pur-
some reason breaks down. poses of the Prescription and Limitation (Scotland) Act 1973 is
unlikely to be a matter which will arise as an issue of immediate
1.03 This, of course, assumes that there exists a dispute between practical importance for the architect, but it has been known to
the parties and that it falls within the ambit of the arbitration happen, and should not be overlooked.

287
288 Building dispute resolution in Scotland

1.05 The time-bar issue which the architect is more likely to ‘international arbitrations’ were conducted under the provisions
encounter is a different one. It should be borne in mind that even of the UNCITRAL Model Law, and supposedly purely Scottish
if the right to arbitrate may be not lost through the passage of arbitrations were conducted under a basically common law
time, the underlying contractual rights about which the parties regime, was abolished by the 2010 Act. The parallel system
are in dispute may be being lost through the elapse of time or had not proved particularly successful in attracting international
rendered unprovable by the contractual mechanisms. It will be arbitrations to Scotland, not least on account of its ability to
recalled that in varying regards, conclusive effect is accorded engender satellite litigation with concomitant cost and delay in
the Final Certificate in the SBCC building contract if proceed- disputes about which of the parallel regimes applied to the arbi-
ings in relation to those matters it covers have not been begun tration in hand. A notable example was the arbitration about con-
before a date 60 days after the issue of the certificate in question. version of the ‘Fennica’ to enable her to switch between being
The architect should thus bear in mind that, even if the right to an ice-breaker and a pipe-laying vessel. That arbitration became
arbitration is not in danger of being prescribed, it may be that the subject of a judicial review and a satellite proof within the
recourse to arbitration or court proceedings is required promptly arbitration process about whether or not the arbitration was truly
if underlying rights sought to be arbitrated upon are not to be international for the purposes of the UNCITRAL Model Law.
destroyed by prescription or by conclusive evidence provisions The delay to the resolution of the substantive dispute between
in the contract. the parties caused by the satellite argument was of the order of
18 months! The Model Law has therefore been replaced as a
1.06 Given that, as noticed above, the jurisdiction of an arbiter statutory set of arbitration rules in Scotland.
in Scotland derives from the contract of the parties, both the
identity of the arbitral tribunal and, subject to the statutory 1.08 The former common law structure of the domestic arbitra-
default provisions on the subject, the powers that are to be tion system, with its small number of statutory additions, which
exercised by it are a matter for the consent of the parties. To was outlined in past editions of this book has likewise been
combat the obvious problem that, once they are at odds over swept away to be replaced by a fundamentally statutory law set
some dispute, the parties may fail to agree upon the identity of out in the 2010 Act. The most conspicuous casualties of this
their arbiter, the SBCC Arbitration Clause follows the common change in the law has been judicial review as a mechanism for
practice of providing that, failing agreement between the parties the supervision of arbitrations and the Stated Case procedure,
on the matter within a specified time, either party may apply to a whereby arbiters could be invited (and in some cases obliged)
nominating body to appoint an arbitrator. In practice, not many to state a case for the opinion of the Court of Session on some
arbitrators in construction disputes in Scotland are appointed point of law which the arbiters were required to decide in order
in that way; at length, agreement, howsoever reluctant, usually to resolve the dispute before them. The stated case has been
prevails. The clause provides for different possible appointing abolished and judicial review excluded as part of an avowed
bodies. When the terms of the clause are being considered at attempt to reduce the degree to which the court could become
the outset, before the building contract is entered into, it may be involved in the conduct of Scottish arbitrations. There was, in
appropriate to consider which appointing body would be most some quarters, a view that parties, and especially parties from
likely to appoint an arbiter skilled in the resolution of the kind abroad, were dissuaded from arbitrating in Scotland by the
of dispute which is apt to arise in connection with that contract. extent to which, under the former law, the court could be called
In that regard, it should not be overlooked that although a dis- upon to step in and effectively take certain decisions out of the
pute may at first sight appear to relate to one discipline, a more hands of the parties’ selected arbiter while at the same time add-
detailed consideration of it may disclose that the decisive issues ing to the cost and length of the arbitration process.
will enter another discipline, and that in consequence, a choice
between competing areas of expertise of potential arbitrators has 1.09 Another of the complaints often made about the former law
to be made in deciding what category of person would make the was that potential arbitrating parties were dissuaded from using
best potential arbitrator. The clause also gives rise to a practical arbitration in Scotland by the common law basis of the law and
problem to which architects may wish to direct their clients’ its consequent uncertainty and dissipation through court cases,
attention at the contracting stage. Many arbitrators appoint clerks some well over a century old, books, and occasional pieces of
to assist them, and usually both arbitrator and clerk charge fees disparate legislation, not all of which even included a reference
for their services. A number of arbiters proceed upon the footing to arbitration in their titles. It was scarcely surprising that in
of terms and conditions of appointment as arbitrators, governing these circumstances the lay, English, or foreign reader trying
matters such as joint and several liability for fees, and expenses, to discover what Scottish arbitration would entail would be
and the size of those fees. Theoretically, fee scales in such terms defeated by its obscurity and give up the idea of arbitrating in
and conditions form the terms of a separate ancillary contract Scotland.
between the arbiter and parties to which all consent. But in real-
ity, where the arbitrator is imposed on parties by the appointing 1.10 This criticism was somewhat misplaced in the case of
authority and that arbiter presents terms which are unacceptable international arbitration, where the Model Law applied, for it
to a party (e.g. as regards the daily rate of remuneration), it was always set out in one place, and the width of the definition
would seem to be open to some doubt what that party can do of ‘international’ arbitration employed in the 1990 Act which
to reject those terms if the arbiter is minded to insist on them. introduced the UNCITRAL Model Law to Scotland ensured that
That result appears to follow from the unqualified and uncon- it covered many building cases. If, as was not infrequently the
ditional nature of the agreement embodied in the standard form case, one party to a building contract dispute was domiciled in
to accept as arbitrator such person as the appointing authority Scotland, whilst the opposing party was domiciled in England,
may specify. To avoid it, therefore, it may be desired to amend the dispute was counted as an international one. It was only in
the standard form clause so as to render the agreement to accept relation to purely domestic arbitration that the criticism had any
the arbitrator subject to prior agreement having been reached on force. It was nevertheless sought to be met by the passage of
the terms and conditions upon which he or she will act as such. the 2010 Act, which sets out the great majority of the present
The danger in such amendment is that, unless carefully drafted, law on arbitration procedure in one statute. Though it is a mat-
it opens up the opportunity to frustrate – or at least delay – the ter unlikely to trouble the architect (save, perhaps, those who
arbitration process through dispute about ancillary questions are themselves sitting as an arbitrator), it is inevitable that, as
such as the arbiter’s fees. the years pass, the fraction of the relevant law which will be
found in the statute itself will drop, and recourse will have to
1.07 Since the last edition of this book was published, the law be made to a greater extent to law reports and the textbooks
of Scotland on arbitration has undergone major change with the for the elucidation of matters not directly addressed in the Act.
coming into force of the Arbitration (Scotland) Act, 2010.The Moreover, as is noted below, there is already a mass of material
dual structure which had existed for twenty years, whereunder in the English court cases which may have to be consulted in a
Adjudication in Scotland 289

given case, particularly in relation to appeals under rules 67–69 ‘re-inventing the wheel’. In consequence, given the substantial
of the Scottish Arbitration Rules. mass of such cases, the hope that the law is now readily avail-
able to the lay reader is perhaps an illusion. Reliance on English
1.11 The reason for this is readily seen. The 2010 Act is closely decisions in this context can already be seen in Scottish appeals
modelled on the English Arbitration Act, 1996, although there on arbitration such as Arbitration Appeal No. 1 of 2013 and
are differences between the two pieces of legislation, largely Arbitration Appeal No. 3 of 2011.
derived from the differing backgrounds of court procedure in
the two jurisdictions. Certain parts of the 2010 Act, notably 1.14 By comparison with the English literature, the number of
the obligation under section 10 to sist court proceedings where arbitration cases in the Court of Session is small, reflecting, it is
arbitration is invoked, will apply to any arbitration matter which thought, the limited number of arbitrations which have been held
comes before the Scottish courts, but the majority of the Act in Scotland since the introduction of the 2010 Act. The majority
applies only where the arbitration between the parties is ‘seated of the cases which do exist are appeals, though one case on the
in Scotland’. That is a term defined by the statute as being the recovery of documents will be found, and another on the subject
result of a decision to designate the seat as being somewhere in of anonymity and confidentiality.
Scotland which is made either by the parties themselves or by
a third party on whom they have conferred the power to make 1.15 Traditionally, privacy has been considered one of the
such a designation. In the absence of any such designation, sub- great benefits of arbitration, the procedure affording the par-
section 3(1)(b) makes it the task of ‘the court’ to decide whether ties a mechanism for resolving their dispute without exposing
the arbitration has its seat in Scotland. An arbitration which is it, or other sensitive material, to public gaze, as might happen
taking place because that course is enjoined by a statute will, if the dispute were to be litigated. To avoid undermining the
should sub-section 16(4) of the Act be brought into force, be one duty of confidentiality implicit in a submission to arbitration,
seated in Scotland. The architect is likely to be concerned with if proceedings are raised in the Court of Session in relation to
arbitration agreements in, or associated with, contracts, however, that arbitration, they will initially not be given their name, but
and in these, to avoid dispute on the subject, the safe course is a numerical designation as ‘Arbitration Application No. x’ of
to make an express designation of the seat for the purposes of the year in which the case is raised, thus disguising the names
the 2010 Act and then ensure that that designation is not contra- of the parties to the arbitration and the litigation. However,
dicted by other terms of the arbitration agreement. The danger in as Court of Session proceedings are, by virtue of seventeenth
such contradiction is that it may result in the designation being century legislation, public, unless the court order otherwise,
read only as a statement about where any hearings in the arbi- under Rule of Court 100.9, the anonymity will be withdrawn,
tration are to be held, as opposed to a choice of the jurisdiction and the proceedings will be heard in public unless the court is
which will have legal oversight of the arbitration and, absent any persuaded by any party seeking to maintain it that that anonym-
contrary provision, as to the law which will govern the arbitra- ity (and with it, private hearings) should be maintained. It is
tion, if not necessarily the substantive dispute to resolve which thought that this is not often a matter as to which there is any
recourse to arbitration is contemplated. difficulty, but as the decision in North Lanarkshire Council v
Stewart & Shields Ltd [2017] CSOH 76 demonstrates, ano-
1.12 The most important practical consequence of the location nymity in court reports is sometimes very contentious, and it
of the seat of the arbitration in Scotland is that, in terms of cannot be assumed that it will be granted. This is unlikely to
section 7 of the 2010 Act, the Scottish Arbitration Rules will be of immediate importance to the architect; more significant
apply to the conduct of the arbitration. Those rules are set out will be the provisions of Scottish Arbitration Rule 26 in those
in full in Schedule 1 to the Act. They can be divided into two cases in which it applies and the duties which it places on a
categories. Many of the rules, such as those on the power of arbi- party to an arbitrator, a party and, indirectly, others involved in
trators to require the provision of security for expenses, or their an arbitration to maintain secrecy of confidential information.
right to allocate liability for such expenses between the parties That is defined to include information not in the public domain
are known as ‘default rules’, and may be modified or disapplied about the dispute, the arbitration – including the award – and
by the parties if they so choose. Such a choice will be held to any litigation about the arbitration where an order has been
have been made if an express choice of a foreign law to govern made under section 15 for anonymity.
the arbitration is made, notwithstanding the Scottish seat of the
arbitration. Other rules, however, are declared to be mandatory 1.16 Once the arbitrators have pronounced their final interlocu-
and cannot be modified or disapplied, even by the selection of tor, they are functus officio and have no further jurisdiction over
a foreign law to govern the arbitration. These mandatory rules the parties (cf. Mowlem (Scotland) Ltd v Inverclyde Council,
are listed in section 8 of the Act and include matters such as the 1 October 2003, unreported). The award is res judicata between
right to refer matters to the court and the power of the arbiter them, but only as regards those matters which were in fact sub-
to award damages. mitted and adjudicated upon. Matters not so submitted may be
the subject of litigation, even if they might originally have been
1.13 The detail of the content of the new legislation is a matter submitted to the arbitrator.
for specialised works, but a few comments are perhaps worth
making here. First and foremost, subject to the restricted access
to the courts permitted by the legislation, the decision of an 2 Adjudication in Scotland
arbitrator is regarded by section 11 of the Act as being final and
binding upon the parties, though not third parties. Secondly, the 2.01 The Housing Grants, Construction and Regeneration Act
powers of the court to intervene in an arbitration are limited by 1996 and the legislation by which it was amended were passed
section 13 of the Act and the terms of the Scottish Arbitration by Parliament as Acts having application across the whole of
Rules. They are restricted to performing functions necessary the United Kingdom. Unsurprisingly, therefore, adjudication in
to assist the arbitrator to proceed with the arbitration, such Scotland shares much in common with adjudication in England
as citing witnesses or granting the right to recover documents and Wales: English cases are frequently cited in Scottish deci-
from third parties, and hearing the limited forms of appeal on sions on adjudication – indeed, there is scarcely a single Scottish
grounds which will be familiar from the English legislation, such case in which English authority is not cited – and, occasionally,
as jurisdictional error, serious irregularity, and error of law. In Scottish cases are relied upon in the English Courts, the reli-
relation to such appellate litigation, it has been declared by the ance on Castle Inns (Stirling) Ltd v Clark Contracts Ltd, infra,
Court of Session that in light of the similarity between the Acts in Halsbury Homes Ltd v Adam Architecture Ltd [2016] B.L.R.
of 2010 and 1996, authority from England on the parallel provi- 419 offering a recent example. But although the court has some-
sions of the English statute will be considered to be relevant to times sought to avoid differences arising between the Scots and
any decision it has to make on account of the pointlessness of English laws regarding adjudication (Gillies Ramsay Diamond,
290 Building dispute resolution in Scotland

Petitioner 2003 SLT 162), particularly in the fields of enforce- 2.04 The law governing the actual operation of an adjudication
ment and challenge of adjudicators’ awards, there are some is not dissimilar to that in England. It is thought, however, that
significant differences between the law concerning adjudication a claim for rectification of the contract or its inducement by
which obtains in Scotland and the English law with which many misrepresentation cannot be adjudicated. Nor, in cases where
readers of this work will be more familiar. damages are awarded, can the adjudicator award interest from
prior to the date of his or her decree in the absence of a spe-
2.02 From the point of view of the architect, not the least of the cial power so to do. The Interest on Damages (Scotland) Acts
significant features about adjudications in Scotland is their use 1958 and 1971, which introduced the ability to award interest
as a mechanism for the recovery of professional fees, and the from before the date of decree in damages cases, have not been
prosecution by that route of claims by employers for damages extended to adjudications.
for breach of contract on the part of members of the professional
team. It is understood that adjudications against members of the 2.05 In the normal case, the adjudicator can allocate as between
professional team are relatively more common in Scotland than the parties responsibility for payment of the adjudicator’s own
they are in England, and where English professionals undertake fees and outlays but, without special power to that effect, cannot
work on Scottish building projects, this risk must be borne in award the parties their legal expenses. In those cases where such
mind. A contract whereunder an architect agrees to act as a con- power is given (often P.F.I. contracts) and exercised, however,
tract administrator under a building contract has been held to be those expenses awarded are subject to taxation by the Auditor
a ‘construction contract’ for the purposes of the 1996 Act (Gillies of Court in exactly the same way as expenses awarded by the
Ramsay Diamond, Petitioner 2003 SLT 162; upheld on appeal, court, and it is only a taxed amount of expenses that the court
2004 SC 430), and it is thought that the same would hold true will be willing to enforce in an action to obtain payment of the
of a contract to act as a project manager for the construction or sums awarded by the adjudicator.
refurbishment of a building.
2.06 In Scotland, as well as in England, adjudicators are required
2.03 For an employer wishing to pursue a claim against the to follow the rules of natural justice, and they must decide the
architect, there are decided tactical attractions in proceeding by dispute according to the parties’ legal entitlements rather than ex
way of adjudication. Not infrequently, losses sustained by the aequo et bono. The leading case on natural justice in adjudica-
employer have been contributed to through the actions of differ- tion in Scotland is now Costain Ltd v Strathclyde Builders Ltd
ent members of the professional team as well as the contractor. 2004 SLT 102, a case which has given rise to some disquiet
Determination of the loss which is attributable to each may be among adjudicators. The case contains an extended discussion
far from easy. Where court proceedings to recoup these losses of the place of natural justice in adjudications. The case was
are raised, the ensuing action can become costly and time-con- concerned with the failure of the adjudicator to disclose to the
suming for the pursuing employer, given the likelihood that third parties, and invite their comments on, legal advice received by
party notices will be served by the defenders in order to bring him. The court held that, as well as keeping free of bias, the
the contractors and other professionals into the action, either in adjudicator had a separate and additional duty to hear both par-
order to prosecute claims for indemnity or relief against them, ties to the case on all material (including legal advice received
or to contend that those others alone are liable to the Pursuer for by the adjudicator) that might be relevant to the case in hand.
the losses. Matters may become yet more complicated for the In a case where that had not been done, it would be enough to
pursuer, for it may have to adopt such contentions for its own justify the reduction of the adjudicator’s decision that there was
protection, and may face, from some of those thus added to the a possibility of injustice arising as a result of the breach: it was
action, defences alleging matters such as limitation of liability, not necessary that actual prejudice be shown to have resulted.
the protection of a final certificate, or the benefit of a ‘net con- The adjudicator must also adhere to the statutory time limits
tribution’ clause, with potentially serious risks in relation to the for the reaching of his decision. This is now clearly the case
incurring of liability in expenses if any of these points should in relation to adjudications under the statutory scheme (Ritchie
succeed. All these problems the employer can avoid by adju- Brothers (PWC) Ltd v David Philp (Commercials Ltd) 2005 1 SC
dicating, since all the other claims among the other parties do 384), and it is thought that, absent clear wording to the contrary
not involve a dispute ‘under the contract’ between the employer in the contractual adjudication provisions, the same holds true
and architect, and so cannot fall within the jurisdiction of the for those adjudications to which the scheme does not apply. It
adjudicator. is not clear whether the adjudicator’s decision should also be
The employer can recover all losses from the architect issued within the statutory time limits, though there is author-
(assuming the latter has no ‘net contribution’ clause in the ity for the view that it should be (St Andrews Bay Development
contract of appointment) relying on the doctrine of joint and Ltd v HBG Management Ltd 2003 SLT 740). The safe course
several liability (Clydesdale Bank pic v Messrs MacLay Collier for any architect sitting as an adjudicator is to obviate that kind
& Partners 1998 SLT 1102), and leave it to the architect – or of argument at the outset by issuing the decision to the parties
the architect’s underwriters – to sue the other parties in an effort within that number of days which they have conferred upon the
to recoup the architect’s losses. Lastly, in the event of success adjudicator for the delivery of his or her decision.
in obtaining damages (particularly if the employer achieves a
level of damages which, if not what was sought, it is prepared to 2.07 By contrast with those matters, however, the question of
rest content with), it is thought that the employer can effectively retention and the compensation of competing cross-claims is an
place upon the architect in any subsequent court action pursuant area where Scots law is apt to part company from its southern
to section 108(3) of the 1996 Act, the burden of proving that he neighbour. An exclusion in a Scottish contract of rights of ‘set-
or she did not breach the contract with the employer in order off’ has been held not to prevent the taking of a plea of retention
to recover the monies paid out as damages in obedience to the in Scottish proceedings (A v B 2003 SLT 242), and the view has
adjudicator’s award. Although the matter is not uncontroversial, been expressed that, notwithstanding the prima facie restriction
it is thought that the Lord Ordinary’s remark in City Inn Ltd v of the adjudicator’s jurisdiction to single disputes, an arbiter to
Shepherd Construction Ltd to the effect that an adjudicator’s whom is referred a question such as ‘to payment of what sum
decision does not alter the burden of proof in a section 108(3) is the Claimant entitled?’ must entertain such a plea of retention
action applies only to the class of case (of which City Inn was raised in defence of the claim, and all the disputed issues, such
an example) where the claimant in the adjudication seeks, as pur- as late completion and damages (liquidated or otherwise) which
suer in the court, action to recover more than was obtained at the may underpin it (Construction Centre Group Ltd v Highland
hands of the adjudicator. (City Inn Ltd v Shepherd Construction Council 2002 SLT 1274). The same logic would seem to apply
Ltd 2002 SLT 781 at paragraph 59. This point was not chal- to pleas of compensation under the 1592 Act, though in that
lenged in the subsequent reclaiming motion (anglice appeal). case, the pre-existing liquidation of the debts said to extinguish
See 2003 SLT 885.) the sum claimed or part thereof is at least likely to make the
Adjudication in Scotland 291

entertaining of that plea a less daunting task for the adjudicator awards made by adjudicators. In Scotland, it is not necessary for
faced with the statutory time limit on the making of his decision. a party dissatisfied with an adjudicator’s decision to wait for the
opponent to attempt to enforce it and then defend the enforce-
2.08 The ability of the unsuccessful party in an adjudication to ment proceedings on whatever grounds may cause him or her to
resist enforcement of the award on the grounds of retention or be so dissatisfied. For in Scotland, an adjudicator’s decisions are
compensation of cross-claims has also given rise to some dif- subject to judicial review, and that method of challenge is not
ficulty. A plea of retention cannot, it seems, be raised to suspend infrequently resorted to (Gillies Ramsay Diamond, Petitioner,
enforcement of an award – least if it could have been pleaded above, was an example). Recent legislation means that these
before the adjudicator and was not – and it appears that the must now be raised within three months of the decision sought
position in relation to compensation is similar (Construction to be challenged. The availability of judicial review in Scotland
Centre Group Ltd v Highland Council 2003 SLT 623). The as a mode of reviewing adjudication decisions has tended to
position in relation to the compensation of debts, or rights to cause a greater resort to administrative law cases as a source of
withhold which could not competently have been put before the precedent on review than has perhaps been the case in England.
adjudicator, because, for example, they arose in the period after Thus, it has been stated that the decision of an adjudicator is
the award was made, is unclear. subject to reduction in the event that it is ‘Wednesbury unrea-
sonable’ (see Ballast plc, above), and it has been argued that
2.09 Probably the most important areas of difference between reduction is similarly available if other elements of the classical
the laws in England and Scotland in relation to adjudication con- Scottish touchstone of administrative law grounds of reduction
cern the questions of enforcement or challenge of awards. Such set out in Wordie Property Ltd v Secretary of State for Scotland
are the differences in this area that it can become an important 1984 SLT 345 are not complied with. In the reclaiming motion in
question for the adviser of a client who has received a decision Gillies Ramsay Diamond, Petitioner, the argument was advanced
from an adjudicator whether he or she should seek to challenge that, on the basis of House of Lords cases such as O’Reilly v
or enforce that decision in England or in Scotland. Provided Mackman [1983] 2 AC 287, there is no distinction between intra
that the defender is subject to the jurisdiction of the Scottish vires and ultra vires errors of law in adjudication, so that the
courts (as many main contractors and employers will be) there award should be reduced as would, say, a planning authority’s
is no necessary objection to the enforcement there of awards decision letter be, if it were disfigured by errors of law about the
made by English adjudicators in respect of English building merits of the case, even if it displayed none about jurisdictional
contacts. Such enforcement actions have already been brought in matters. A decision to that effect would have run counter to
Scotland, and, indeed, the oft-cited Homer Burgess Ltd v Chirex those made by the Court of Appeal in Bouygues Offshore (UK)
(Annan) Ltd is an early example. The main reason for seeking Ltd v Dahl-Jensen (UK) Ltd [2002] BLR 522 and C & B Scene
to enforce an English award in Scotland, it is thought, would be Concept Design Ltd v Isobars Ltd [2002] 82 Con LR 154. The
to allow a successful, but financially seriously straitened party, argument, however, was rejected, since O’Reilly and similar
faced with the prospect of cross-claims or a cross-action under cases were concerned with English public law notions rather
section 108(3) of the 1996 Act, to seek a court decree for the than contractually based jurisdictions such as adjudications, and,
monies awarded by the adjudicator which could then be enforced for cases of the latter class, the Scottish rule in arbitration cases
by diligence. was the better guide, as well as the one more consonant with the
policy of the adjudication provisions of the 1996 Act. Parliament
2.10 Whereas in England, the court has held that it will stay had provided a mechanism for undoing the effects of adjudica-
execution of the decree in circumstances of that class, it has been tors’ errors in the shape of the section 108(3) action, and it was
held in the Outer House of the Court of Session that in Scotland, unnecessary to call into existence another. Even if in England,
there is no power so to do, and that the insolvency (as opposed to the argument from O’Reilly may still be open, in Scotland, it is
liquidation) of the successful party is no ground for withholding now firmly excluded.
an immediately enforceable decree for the sum awarded by the
adjudicator. By seeking to enforce the adjudicator’s award in 2.12 Recent years have seen an increase in the number of actions
Scotland, therefore, the financially stricken sub-contractor – or of the kind envisaged by section 108(3) of the1996 Act, in which
perhaps its bankers – can secure the benefit of a perhaps fortu- parties dissatisfied with enforceable adjudicators’ awards seek
nate adjudicator’s award and avoid those protections afforded by to re-litigate the issues argued over in the adjudication, albeit
the English courts on which the opponent may hope, and expect, that the law reports sometimes do not disclose that fact (West
to be able to rely in avoiding the need to pay out ad interim to Register Street (Property) Ltd v Central Demolition Ltd [2018]
one likely to be unable to repay in the event of the payer’s suc- CSOH 98 is a recent example). It should be borne in mind that
cess in the cross-action. It is necessary to beware of jurisdiction in Scotland, unless the parties’ contract to adjudicate provides
clauses in the contract, however. Whilst these were once thought otherwise, even if the adjudicator’s decision is successfully over-
not to apply to the enforcement of adjudication awards, recently, turned in such a case, neither the award (insofar as it touches
the reverse view has held sway in Scotland, and so an English on the question of the adjudicator’s fees and expenses), nor any
jurisdiction clause may now bar recourse to this tactic (BN interest which may have been attracted by the award before it
Rendering Ltd v Everwarm Ltd [2018] CSOH 45). was honoured, will be repayable by the party who won the origi-
nal adjudication. The same is true of any award of legal expenses
2.11 By way of contrast, the second major difference between which the adjudicator may have made (Castle Inns (Stirling) Ltd,
English and Scots law in this area relates to the challenge of Petitioner v Clark Contracts Ltd 2006 SCLR 663).
Part E
The architect in
practice
29
Legal organisation of architects’ offces
MURRAY ARMES1

1 Managing an architectural defined in section 1 as ‘the relation which subsists between per-
sons carrying on a business in common with a view to profit’.
business ‘Business’ includes the practice of architecture. A single act,
such as designing a house, may make a business and, if there is
1.01 Management is a creative activity, the exercise of which a series of such acts, a business will certainly be held to exist.
is about making and maintaining dynamic cultures within and A view to profit’ requires only the intention to make a profit.
by which the objectives of people as individuals, teams, and The requirement of acting in common is important. It may be
organisations are achieved. contrasted with barristers, who are in business with a view to
The manager of an architectural business is concerned with profit but do not act in common: they merely share facilities.
three types of relationship: between the owners of the business Unlike a company, a partnership has no legal personality. It is
and their clients, between employer and employee, and between nothing more than the sum total of the individuals comprising it.
the owners of the business themselves. This chapter deals with
the third.
Responsible management of an architectural business is Formation of partnership
an essential pre-requisite for the successful management of 2.02 A partnership is a form of contract. Although many archi-
architectural projects and is part of an architect’s duty of care tects set up partnerships quite casually, it is prudent to create
enshrined in the Architects Registration Board and RIBA Codes the business formally and expressly by a deed of partnership
of Conduct. executed under seal or written articles of partnership. The exist-
Critical to the success of any business is its legal form and ence of a partnership can sometimes be inferred in law, however,
structure. The choice of the form of legal organisation is an from the behaviour of the individuals involved, even if no deed
important part of an architect’s duty. of partnership exists, and may exist even despite vigorous state-
ments to the contrary.
1.02 There are no formal restrictions in the professional codes
governing the structures under which architects carry out their
business. The Architects Act 1997 permits registered persons Importance of clarity
to practise as partnerships or companies, limited or unlimited, 2.03 Considerable importance may be attached to the existence
provided that the work of their practice, insofar as it relates to of a partnership. For example, if two architects work together
architecture, is under the control and management of a registered occasionally over several years, and a case of negligence arises,
person. The RIBA Code of Professional Conduct stated in its both may be liable if a partnership exists, even if only one of
preface that them has been negligent. If there is no partnership, however, one
of them, if not personally involved in any negligence, will be
A member is at liberty to engage in any activity, whether as safe from any claim. For instance, limited liability partnerships,
proprietor, director, principal, partner, manager, superinten- established under the Limited Liability Partnerships Act, 2000,
dent, controller or salaried employee of, or consultant to, any unlike those established under the 1890 Act, allow some, or all,
body corporate or unincorporate, or in any other capacity of the partners to enjoy limited, rather than joint and several,
provided that his conduct complies with the Principles of this liability. It can be vital to clients or suppliers of a practice to
Code and the Rules applying to his circumstances. establish whether they are dealing with a partnership or one
person. Architects are recommended on all occasions to clarify
Whilst this text is no longer present in the latest revision of the their relationship with each other in writing, particularly when
RIBA Code of Conduct (2019), there is no reason to believe the working as group practices and consortia.
underlying principle has changed.

1.03 While architects may choose to practise as sole traders, Sharing facilities and profts
to form companies or to create larger amalgamations as group 2.04 If two or more architects do not intend to practise in part-
practices or consortia, many architects still practise in partner- nership, but merely to share facilities, they must take great care
ship. The main choice for architects setting up in business is to avoid the possibility of leading others into the assumption that
usually between partnerships, limited liability partnerships, and they practise together as partners. Shared ownership of property,
companies. A partnership provides the breadth of expertise a even if accompanied by sharing of net profits, is not normally on
sole trader cannot provide without the formality of incorporat- its own evidence of the existence of a partnership. Profit-sharing
ing a registered company (see Checklist 29.3 for an outline of is, however, prima facie evidence of a partnership, but if it is
the principal differences between partnerships and companies). just one piece of evidence among others it will be weighed with
the other evidence. This is particularly important to architec-
tural practices, since profit-sharing in the form of profit-related
2 Partnership bonus payments is a common means of remunerating staff.
Nevertheless, payment by profit-sharing will not of itself make
2.01 The law of partnership is governed by the Partnership Act an employee a partner in the business, nor will sharing in gross
1890. Section numbers in the text which follows are from the returns alone necessarily create a partnership. It is important to
1890 Act. Unless otherwise specified in a partnership agreement, draft any contract of employment including any profit-sharing
the provisions of the Partnership Act will apply. Partnership is provision very carefully indeed. The relationship between the

1 In previous editions, this chapter was contributed by Graham Brown and Gordon Gibb. The present update reproduces such text where still appropriate.

295
296 Legal organisation of architects’ offces

business and the outside world is important. Individuals can be Registration Board (ARB) are permitted to practise or carry on
‘held out’ to the world as partners and the outside world will be business under the name, style, or title of ‘architect’, with the
entitled to treat them as partners. This can be done, for instance, exception of ‘landscape architects’, ‘naval architects’, and ‘golf
by listing them as partners on the firm’s notepaper. course architects’, who are outside the scope of the Act. It is
important that any person wishing to use the words ‘architect’
or ‘architects’ in their practice title or name checks their accept-
Deed of partnership ability first with ARB.
2.05 Even though there are ways of determining whether a The provisions of the Business Names Act 1985 must be
partnership exists, and the 1890 Act sets out terms which apply complied with if a partnership does not consist of the named
if partners have nothing written down, it is most important, if partners. Certain names which are set out in statutory regula-
intending partners agree they are going into a business together, tions or give the impression that the business is connected with
to set out the terms of their relationship in a deed of partnership HM Government or a local authority must gain the approval of
since the terms expressed and implied by the Partnership Act the Secretary of State. The use in a firm’s name of a retired,
can be draconian and unfair. The deed should cover the points former, or deceased partner may be permissible, provided there
outlined in Checklist 29.1. is no intent to mislead; but caution is necessary to avoid the
implication that such a person is still involved in the practice.
The 1985 Act requires businesses to disclose certain informa-
Checklist 29.1 Items to be considered for a deed of partnership
tion. The names and addresses of each partner must be promi-
nently displayed at the business premises where the public have
Note: The terms of a partnership agreement, like any other contract, may access. It is important to comply with the provisions of this
be widely varied by mutual consent of the parties. Where no provision is Act. Failure to do so is a criminal offence, or may render void
made, those of the Partnership Act 1890 will apply. Figures in brackets refer contracts entered into by the practice. The Act requires that
to relevant clauses in that Act. business documentation must contain the name of each partner.
1 Name of firm If there are more than 20 partners, however, the names of all
2 Place of business partners can be omitted from business documents if they state
3 Commencement date the address of the principal place of business and also state
4 Duration that a full list of partners’ names and relevant addresses may
5 Provision of capital be inspected there.
(a) Amount
(b) Proportion to be contributed by each partner Size of practice
(c) Distinctions between what is not partnership capital (a premium)
and capital which is partnership property (contribution to working 2.07 There are still restrictions on the size of some partner-
capital) ships. In the case of architects, these have been removed by
(d) Capital should be expressed in money terms the Partnerships (Unrestricted Size) (No.4) Regulations 1992
(e) Any special agreement for interest on capital (24(3), (4)) (amended 2002) so long as not less than three-quarters are reg-
(f) Valuation and repayments on death, etc. (42 and 43) istered under the Architects Act 1997.
(g) Rules for settlement for accounts after dissolution (44)
6 Property Types of partner
(a) What partners bring to the firm including contracts (20, 22, 24)
(b) What belongs to firm as a whole (21) 2.08 The law is not concerned with distinctions between senior
(c) What is co-owned but not partnership property and junior partners. It is up to the partners to decide how to
(d) What is individually owned but used in the business (24) share profits, but they will be shared equally unless special
7 Mutual rights and duties. If these are to be differentiated then they provision is made. The Royal Institute of British Architects
should be specified as holiday times, sabbaticals, work brought into the (RIBA) recommends strongly that all persons who are held
firm, etc. out to be partners should be described as such without further
8 Miscellaneous earnings. Whether or not income from lecturing, jour- distinction and, in particular, the term ‘salaried partner’ should
nalism, honoraria, etc. is to be paid into the firm. be avoided. The purpose of this is to ensure that all persons
9 Profits and losses. Basis for division among partners: if not equally then described as partners share in the decision-making of the busi-
specified (24(1)). Any reservations such as about guaranteed minimum ness and have access to appropriate information. Partners are
share of profits in any individual case. fully responsible for the professional conduct of the practice
10 Banking and accountants. Arrangements for signing cheques, presenta- and for keeping themselves properly informed about all part-
tion of audited accounts, etc. nership matters.
11 Employment of locum tenens. Authority for, circumstances, and terms.
12 Constitution of firm. Provisions for changes (36). Associates
13 Retirement at will. Age, fixed term or partnership for life, notice of
retirement, etc. Arrangements for consultants and for payment dur- 2.09 It is a common practice to recognise the status and contribu-
ing retirement. Repayment of capital and current accounts on death or tion of senior staff qualified or not by describing them as ‘asso-
retirement. ciates’. The title ‘associate’ is not referred to in the Partnership
14 Dissolution. Any special circumstances (see Checklist 29.3). Act, and it has no meaning in law. If it is not intended that asso-
15 Restrictions on practice. Any covenant restraining competition must be ciates be partners and share in the liabilities of the partnership,
reasonable to interests of parties and public. Areas of operation. it is unwise to use the term ‘associate partner’. Its use may also
16 Insurances. Various, including liability of surviving partners for dead contravene professional codes. If people are misled into thinking
partners’ share in firm. associates are partners, associates will find themselves liable as
17 Arbitration. Method, number of arbitrators, etc. if they were partners, holding all the obligations without any
rights or benefits.

Rights and liabilities of partners


Name of practice
2.10 Every partner has the following rights unless there is an
2.06 In naming a firm, there are a number of considerations. agreement to the contrary:
Use of the words ‘architect’ or ‘architects’ is restricted by the
Architects Act 1997 as amended. Only those persons who are 1 To take full part in management of the business
on the Register of Architects maintained by the Architects (section 24(5));
Partnership 297

2 To have an equal share in profits and capital of the business 2.15 The provisions of the Limitation Act 1980 and the Latent
(section 24(1)); Damage Act 1986 apply to breaches of contract or of duty of
3 To inspect the partnership books. These must be kept at the care in tort.
principal place of business of each firm (section 24(9));
4 To dissolve the partnership at any time by giving notice to 2.16 Partners are not liable for the criminal actions of other
the other partners (section 26(1)); partners unless they contributed to them or have knowledge of
5 By section 24(2) a firm must indemnify every partner in them. Architects may be liable, however, for breaches of their
respect of payments made and personal liabilities incurred codes of professional conduct by fellow partners.
by them in acting as necessary or in the ordinary and proper
conduct of the business of the firm; 2.17 A partnership may indemnify one or more of its partners
6 Not to have new partners added without their consent against the consequences of their liability. This device enables
(section 24(7)); members of staff to share the management of a practice without
7 Not to have the fundamental nature of the partnership busi- outlaying capital to join the equity partnership.
ness altered without their consent. The consent of a major-
ity of partners will suffice for changes in all other ordinary 2.18 A new partner entering a firm does not normally become
matters connected with the business; liable for debts, obligations, or wrongs incurred or committed
8 Not to be expelled without express agreement (section 25). before their entry (section 17(1)). If a partner retires, he or she
will still be liable for debts or obligations incurred before retire-
ment (section 17(2)). If he or she dies, their estate will be liable
for such debts or obligations. Moreover, a partner will continue
to be treated as a member of the firm, attracting the usual liabil-
ity, until notice of a change in the constitution of the partnership
is advertised (section 36).

2.19 Every partner is an agent of the practice. Any action under-


taken by any partner in carrying out the business of the practice
will bind the practice unless it is outside their authority to act for
the practice in that particular matter and the person with whom
they are dealing knows that they have no authority or does not
believe them to be a partner (section 5).

2.20 Partners must render true accounts and full information on


anything affecting the partnership or partners (section 28).

2.21 Partners are accountable to the partnership for any pri-


vate profits they receive from any partnership transaction
or from using partnership property, names, or connections
(section 29(1)).

2.22 If a partner, while still a partner, competes with the practice


Rights to which partners are not entitled without the consent of the other partners he or she must pay all
2.11 By section 24(4), there is no right to interest on capital profits made in consequence to the practice (section 30).
subscribed by a partner, although by section 24(3), there is a
right to interest on capital subscribed beyond that which was Relationship of partners one to another
agreed to be subscribed.
2.23 A practice of any size may not discriminate against partners
2.12 By section 24(6), there is no right to remuneration for act- on the basis of protected characteristics (age, disability, gender
ing in the partnership business. reassignment, marriage and civil partnership, pregnancy and
maternity, race, religion or belief, sex and sexual orientation)
pursuant to the Equality Act 2010.
Liabilities
2.13 Under English law, a partnership is a collection of indi- Dissolution of partnerships
viduals and not a corporate body. In addition to all their normal 2.24 A partnership comes to an end in any of the following ways:
individual liabilities, each partner has added responsibilities as
a member of a partnership. 1 at the end of a fixed term, if it has been so set up;
2 at the end of a single specific commission, if it was set up
2.14 Legal action may be taken against a partner jointly, or for that commission alone;
jointly and severally. By sections 9 and 10 of the Partnership 3 on the death or bankruptcy of any partner, unless the part-
Act, every partner is personally liable jointly with all other nership agreement makes provision for continuity of the
partners for all debts and obligations incurred by the firm while partnership;
he or she is a partner, as well as jointly and severally for wrongs 4 if any partner gives notice;
done by other partners acting in the ordinary course of the 5 by mutual consent; or
business of the firm or for wrongs done with the authority of 6 by dissolution by the court.
co-partners. If a partnership is sued jointly, one or more partners
may be sued at the same time. If an action is brought against a 2.25 Prior to the Finance Act 1985, there were tax benefits in
partnership jointly and severally, the partners may be sued singly cessation and re-formation of a partnership, but these have now
or together. When judgment is given against one, further action been ended.
may be brought against the others, one by one or together, until
the full amount is paid. If only some of the partners are sued, 2.26 If a partner wishes to end the firm, but is prevented by his
they may apply to the courts to have their other partners enjoined or her fellow partners, application may be made to the court
as co-defendants. for dissolution on one of the grounds shown in Checklist 29.2.
298 Legal organisation of architects’ offces

7 It has complete flexibility regarding its internal structure. It


Checklist 29.2: Grounds for dissolution of a partnership has no memorandum or articles of association and there are
no requirements for board or general meetings or decision-
Note: Figures in brackets refer to relevant clauses in the Partnership Act
making by resolution;
1890.
8 It is required to maintain accounting records, to prepare
1 By agreement of parties
and deliver audited annual accounts and an annual return to
(a) Agreement per deed. End of fixed term or of single project.
Companies House. Exemptions from audit and full account-
(b) By expiration, or notice (32). If for undefined time, any partner giv-
ing apply as for companies.
ing notice of intention (32(c)).
(c) Illness. Special provisions in deed (to avoid need to apply to courts
(35)). Membership
Note: Expulsion. A majority of partners cannot expel unless express agree-
ment in deed (25). There can be no implied consent to expel. Clarification 3.04 Any natural or legal person such as a company may be
required of arrangements in case partners fall out with each other. members of an LLP. There are no shareholders, directors, or
2 By operation of law and courts secretary. All members are required to be registered as self-
(a) Subject to express agreement, partnership is dissolved as regards all employed. Each member and the LLP itself are required to make
by death or bankruptcy of any partner (33). annual self-assessment returns to HM Revenue and Customs. A
(b) Any event making it unlawful to carry on the business of the practice minimum of two members are required, of which two are des-
such as if a partner is insane, incapable of carrying on their part of ignated members. If no members are identified as designated,
agreement, guilty of conduct prejudicial to the interests of the firm, then all members are designated. Designated members have a
wilfully and persistently breaches the partnership agreement or if statutory responsibility for certain tasks, including signing the
their conduct is such that the other partners can no longer carry on accounts, submitting the accounts to the Registrar, appointing
business with them. and removing auditors, notifying the Registrar of membership
(c) If the firm can only carry on at a loss. changes, preparing, signing, and submitting annual returns, and
(d) If, in the opinion of the courts, it is just and equitable that the firm applying for striking off the register.
should be dissolved.
3.05 All members are agents of an LLP and, as such, are obliged
to act in the interests of the LLP and to avoid conflicts of inter-
est. The internal relationships between members are unregulated,
3 Limited liability partnerships leaving the matter to a separate and private agreement between
members.
3.01 Introduced by the Limited Liability Partnership Act 2000,
limited liability partnerships (LLPs) are essentially a hybrid Agreement
between partnerships and limited liability companies. The Act is
brief and is supplemented by the LLP Regulations 2001, which 3.06 There is no statutory requirement for LLPs to have a par-
apply to LLPs certain provisions of a number of statutes, includ- ticular management structure, including for the appointment of
ing the Companies Act 2006 and the Insolvency Act 1986, as directors. This should be formulated in a private LLP agreement
amended by the Insolvency Acts 1994 and 2000. unregistered with Companies House. Such agreement describing
members’ responsibilities should cover arrangements for man-
3.02 The intention of the Act is to give the benefits of lim- agement, decision making, capital contribution requirements,
ited liability while retaining other characteristics of a tradi- distribution of profits, membership changes, dispute resolution,
tional partnership. From 6 April 2014, when the Finance Bill liquidation, termination, and changes to the agreement. If an
2014 became operative, an LLP is not taxed in the same way agreement is absent, the default provisions of the Regulations
as existing partnerships, and although the internal structure apply. These include that every member may take part in man-
is similar to a partnership, the individual members will be agement, all members are entitled to share equally in the capital
taxed as employees. Unlike a limited company, an LLP has no and profits, and no members are entitled to payment for their
memorandum or articles of association, relying instead upon business or management actions.
an agreement, similar to a partnership agreement, designed
to suit its members. An LLP is a separate legal entity. It is Liability
responsible for its assets and liabilities, and the liability of
its members are limited. But, as with companies, actions may 3.07 An LLP is financially liable to the extent of its assets and
be taken against individual members found to be negligent or members may risk losing the contributions they have made to
fraudulent in their dealings. these assets. In the event of liquidation, members are liable
LLPs are available to any ‘two or more persons associated for simply to make such contributions as they have agreed with the
carrying on a lawful business with a view to profit’ by registra- other members. Such arrangements should be included in the
tion with Companies House. LLP agreement.

3.03 A decision as to whether to adopt an LLP structure is likely 3.08 Members are liable for fraudulent or wrongful trading in
to be made primarily in regard to its position on taxation. Key the same way as are company directors and others under the
features of an LLP include: Insolvency Acts.

1 It is a body corporate, that is a legal entity distinct from its 3.09 Members are liable in tort for their negligent acts or omis-
members; sions, and the LLP will also be liable to the same extent.
2 It can own property, employ people and enter into contracts.
Debts incurred are debts of the LLP;
3 It is taxed as a partnership not as a company; 4 Companies
4 It has unlimited capacity, that is to say its activities are not
restricted; 4.01 Company law is enshrined in legislation. The Companies
5 It has members but no directors or shareholders. It has no Act 2006 applies to all existing and new companies operating in
share capital and is not subject to company law regarding the UK. The Act was implemented in stages up to and including
capital maintenance; 1 October 2009. Companies House provides full information
6 Its members have limited liability. It is liable for all its debts on the Act and guidance on the changes it makes to previous
to the extent of its assets; legislation.
Companies 299

View of the professional organisations them leave to act), or are disqualified by the court under
the Company Directors Disqualification Act 1986 or the
4.02 Under its Code of Professional Conduct, the RIBA may Articles. The company may remove a director by ordinary
hold a member acting through a body corporate or unincorporate resolution before the end of his or her term. Directors
responsible for the acts of that body. This means that for the normally retire in rotation (one-third each year) but may
purposes of suspension or expulsion from the RIBA, an architect resign by giving such notice as is required in the Articles.
who is a director of a company may be held personally liable for Directors are entitled only to such remuneration as is stated
the acts of the company. in the Articles. Companies may not loan to directors or con-
nected persons except as provided under the Act.
A separate legal persona 5 Intended location of the registered office of the company.
6 The prescribed fee.
4.03 The most fundamental principle of company law is that
a company is a distinct and separate entity in law from its 4.06 Companies House will issue a Certificate of Incorporation
members or directors. As a separate legal person, a company as evidence that the company is legally registered, and give
can own and alienate property, sue and be sued, and enter into the company a registered number. Without a Certificate of
contracts in its own right. Although a company is owned by its Incorporation, a company does not exist in law and cannot do
shareholders and governed by its directors under the supervision business.
of its shareholders, it is distinct in law from all of these. In rela-
tion to third parties, it is the company which is usually liable,
not the shareholders or directors. This is so, however large the Public and private companies
percentage of shares or debentures held by one shareholder. A 4.07 Companies, whether limited or unlimited, may be either
company may be liable in contract, tort, crime, and for matters public or private. A public company is the only sort of company
of property. Only in rare cases can directors or shareholders be permitted to offer its shares to the public. Only companies with a
held personally liable for debts and obligations of the company, minimum authorised share capital of 50,000 in sterling or 65,600
for example, if they have been fraudulent or if directors allow in euros may be public limited companies. The Memorandum of
the company to trade while it is insolvent. Association must state that the company is a public company.
An architect’s practice will normally incorporate as a private
Types of company company. The individuals (who would otherwise be partners)
are likely to be directors and shareholders.
4.04 A company may be limited (by shares or guarantee) or
unlimited. A company limited by shares is one in which the
share-holders’ liability to contribute to the company’s assets is Profts
limited to the amount unpaid on their shares. A company limited 4.08 Profits are distributed among shareholders in accord-
by guarantee is one where the shareholders are liable as guaran- ance with the rights attached to their shares. Although there
tors for an amount set out in its Memorandum in the event of the is a presumption that all shares confer equal rights and equal
company being wound up. An unlimited company is subjected to liabilities, this can be rebutted by a power in the company’s
the same rules as a limited company, except that its shareholders Articles to issue different classes of shares. An example of a
are personally liable for all its debts and obligations in event of class of share is a preference share. Holders of preference shares
the company being wound up. will be entitled to dividends before ordinary shareholders. If
there are insufficient funds, preference shareholders will be the
Formation of companies only shareholders to receive dividends. Shares are also classed
according to whether they have voting rights or not. In most
4.05 Companies are formed by registration under the Companies architectural companies, profits and dividends are small because
Act. The following must be sent to Companies House: directors are remunerated by salary under their service contracts
with the company.
1 A Memorandum of Association setting out the objects of
the company. A company’s objects are unrestricted unless
restrictions are included in its Memorandum which should Name of company
therefore be drafted carefully to comply with relevant pro- 4.09 Like partnerships, the name of a company is restricted
fessional codes. The Memorandum should contain provision by the Architects Act 1997 and the Business Names Act 1985.
for alteration as it can be changed only in certain circum- Limited companies must use the word ‘Limited’ after their name.
stances as laid down by the Companies Act 2006. It is an offence for public companies to choose names giving the
2 Articles of Association containing the regulations of the impression that they are private companies, and vice versa. The
company (subject to the Memorandum). All companies are use of a name similar to that of another company with the same
required to adopt articles of association upon incorpora- type of business may constitute an actionable tort.
tion. Model articles prescribed under the Companies Act
2006 apply to companies who choose to adopt them and 4.10 A company must state its corporate name on all business
apply by default to companies formed under the Act but documents and on its seal. It must display this name legibly on
who do not register articles of their own with Companies the outside of its business premises. Other particulars including
House. The Articles may be altered by special resolution of the place of registration, the registered number and the address
a majority of voting company members. of the registered office must be included on company business
3 A statement of initial nominal capital. documents.
4 Particulars of the director(s) and secretary. All companies
must have officers. This means at least one director for a
private company, and at least two directors and a company Size of company
secretary for a public limited company. A private limited 4.11 A company may have an unlimited number of shareholders.
company is not required to have a company secretary but
it can choose to include in its articles a requirement to do
so. Any change in the names and addresses of directors or Rights and liabilities of shareholders
secretary must be notified to Companies House. The Articles 4.12 Shareholders holding shares with voting rights have the
may require directors to have qualification shares. Anyone, right to supervise the management of the company by voting
even a corporation, may be a company director, unless they in an annual general meeting, or in such extraordinary general
are an undischarged bankrupt (though the court may give meetings as may be called. Private companies are not required
300 Legal organisation of architects’ offces

to hold an AGM unless they positively opt to do so. Decisions company available for inspection by company officers at
may be taken by written resolution. any time;
2 Directors must prepare an annual report reviewing the
4.13 Shareholders are paid dividends out of the profits of the business of the company and recommending the amount of
company, in accordance with the rights belonging to their shares. dividends to be paid;
3 The company must be audited annually if its turnover
4.14 A partnership is bound by contracts made by one of its exceeds a specified amount or if at least 10% of its share-
partners and is liable in tort for the acts or omissions of each holders request an audit;
partner. In contrast, shareholders cannot make contracts binding 4 The report and accounts must be filed with Companies
on a company, nor are they liable personally for debts or obli- House at specified times to be available for inspection by
gations of other shareholders. Shareholders are liable, however, the public;
for torts and obligations of a limited company to the amount 5 The company may elect to hold an annual general meeting
unpaid on the nominal value of their shares. Frequently, this of shareholders in each calendar year but this may be dis-
is academic. Many small limited companies only have £100 pensed with by resolution of the shareholders. Two persons
worth of share capital split into smaller proportions still. If the can constitute a quorum. Extraordinary general meetings
company is unlimited, shareholders will be liable for the debts may be convened if there is some business the directors
and obligations of the company in the event of its winding-up. consider to be of special importance;
6 The company must keep a register of directors at its regis-
4.15 When a company is dissolved by winding-up, both present tered office disclosing certain information about directors
members and those who have been members in the 12 months and their interest in the shares or debentures of the com-
preceding the winding-up are required to contribute towards the pany. Companies House must be informed of these par-
liability of the company but, for the reasons given above, this ticulars and any changes. A register of members containing
contribution is often nominal. Only in the case of a substantial similar information must also be kept by the company;
unpaid up shareholding could it assume any significance, and 7 Directors have no right to remuneration except that specified
this is likely to be most unusual. The liabilities of past company in the Articles. Remuneration of directors is normally voted
members are not so wide-reaching as those of partners. on by the shareholders at their general meetings;
8 Directors owe the company a fiduciary duty of loyalty and
good faith. They are considered trustees of company assets
Rights and liabilities of directors under their control. They must account to the company for
4.16 Under the Articles, directors are normally given the power any profits they make by virtue of their position as directors
to manage the company under the ultimate supervision of and cannot use their powers as directors except to benefit
shareholders. They may delegate the management to a manag- the company. They must always devote themselves to pro-
ing director. moting the company’s interests and act in its best interest.
Their duty of loyalty means they cannot enter into engage-
4.17 Directors are not servants or agents of a company and can ments where their personal interests might conflict with the
only bind it if some organ of the company has conferred appro- company’s interest, and they must disclose their personal
priate authority upon them. Authority for this depends on the interests in such engagements to the shareholders. This duty
Articles or by special resolution of the shareholders. A director can continue even after a director leaves the company;
may be held to have had usual authority or to have been held 9 Directors owe a duty to the company to exercise reason-
out as having authority, and this will bind the company. The able care in the conduct of the business. Such duties are
third party need not be familiar with the Articles in either case. not unduly onerous. Courts are reluctant to intervene in
A managing director can normally be expected to have authority areas involving business judgement. In some circumstances
to bind the company. directors will be expected to seek specialist advice and will
be liable if they do not. Directors will not be liable for
4.18 The Companies Acts and the Insolvency Acts prescribe a anything they have been authorised to do by shareholders.
large number of duties for directors. These include: This duty is not owed to shareholders, contractors or credi-
tors (although a director may be liable to the creditor for
1 Directors must prepare and disclose company accounts in a fraudulent or wrongful trading). Since the duty is owed to
specified form stating the financial position of the company. the company, the company itself can sue directors who have
They must keep the books at the registered office of the been negligent or in breach of their fiduciary duties.

Checklist 29.3: Differences between companies and partnerships

Partnerships Companies

1 No separate legal personality (except in Scotland). 1 Separate legal personality from its shareholders.
2 Partners have unlimited liability. 2 Shareholders are liable only to the amount unpaid on their shares but
may be liable on personal guarantees for some liabilities.
3 Partners’ interests may be difficult to transfer, subject to valuation agreement. 3 Interest of shareholders are their shares, which can be easier to transfer,
subject to restrictions in Articles and to valuation agreement. Shares
may be difficult to value.
4 May be difficult for a young architect to join a partnership, since sufficient 4 It is easier to join a company, as it does not necessarily involve buying
capital will need to have been accumulated to buy a share in the partnership in.
or to take over a retiring partner’s interest.
5 Only promotion is to become a partner, so career prospects may be limited. 5 More kinds of promotion possible, including to directorship through
employment structure. In small companies, this is a more theoretical
than practical advantage.
6 Difficult for partners to resign and subject to agreement. 6 Easy for directors to resign, but liability remains for up to 12 months.
7 Management through meetings of partners. 7 Management through Board of Directors supervised by shareholders,
meeting annually.
8 Partners share profits equally unless there is an agreement to the contrary. 8 Company profits are divided according to rights attached to the shares.
Employees are remunerated by salary, shareholders by dividends.
These can be mixed and matched.
Companies 301

9 Can be formed informally by just starting up business with another person. 9 Must be registered to come into existence, but company formation
can be quick and cost less than £100.
10 No restrictions on powers of partners, subject to agreement. 10 Company powers unrestricted, subject to limitations imposed by
Articles.
11 Each partner can bind the partnership. 11 No shareholder can bind the company, but directors can.
12 Partnership details cannot be inspected by the public. 12 Matters filed with the Registrar of Companies are open to public
inspection including Memorandum, Articles, details of directors,
secretary, and registered office.
13 Accounts need not be publicised. 13 Accounts must be filed annually with the Registrar of Companies.
14 No audit required. 14 Annual audit may be required.
15 Partnership must make annual tax returns, but partners are liable individu- 15 Company liable for all declarations and payments of tax.
ally for declaring and paying their own tax.
16 Less administration required. 16 More administration required.
17 Money can be borrowed in the names of the partners, but partnership debtors17 May raise money subject to Articles by debentures, for example, or
cannot be used as security for loans. by fixed and floating charges over assets.
18 Death or departure of a partner can cause dissolution of the partnership un- 18 Transfer of shares will not end a company’s existence.
less otherwise agreed.
19 Many ways to dissolve a partnership, including instantly by agreement. 19 A company is dissolved only by liquidation in accordance with the
Companies and Insolvency Acts or by winding-up.

Dissolution most important provisions of the company’s constitution, includ-


ing the activities which the company may carry out.
4.19 A company may be dissolved in two ways:

1 By winding-up under the Insolvency Acts. This may be Group practices


voluntary or compulsory. Once a company has been wound 4.24 Practices may group together for their mutual benefit and
up, no judgment may be enforced against it; to give better service while each retains some independence:
2 By being struck off the Register under the Companies Act.
This happens, for instance, if the company fails to file its 1 Association: the degree of association may vary consider-
annual accounts or returns. Companies may seek this form ably from simply sharing office accommodation, facilities
of dissolution themselves. They may do this to save the and expense, to a fully comprehensive system of mutual
costs of a formal liquidation. help. Beyond agreeing to a division of overhead expenses
each practice retains their profits and their normal respon-
sibility to their respective clients;
Companies versus partnerships 2 Coordinated groups: for large development projects it is
4.20 A list of the differences is set out in Checklist 29.3. The not unusual for the work to be undertaken by two or more
relative advantages and disadvantages will differ for individual architectural practices with one of them appointed to coor-
businesses. Managers need to assess the business priorities when dinate the activities of the others. Practices are liable to the
making a decision to form a company or a partnership. The size coordinating practice for torts committed in their areas of
of the business may be relevant to the decision. Smaller busi- activity. The arrangement may be constructed under head
nesses may find the paperwork and administration required for a and sub-consultancy agreements.
company too arduous. Taxation is another factor in the decision.
This is beyond the scope of this chapter. Managers should seek Single-project partnerships and group partnerships may be
professional advice from an accountant or from a local tax office. entered into on terms which are entirely a matter for individual
agreements between the parties and are similar in law to any
ordinary partnership.
Service companies
4.21 Service companies are formed to provide services to a part-
nership. The company may employ staff and hold the premises.
Consortia
It will also normally provide things such as office equipment, 4.25 Consortia are little different in law from group practices.
stationery, cars, and accountancy services to the practice. The The term normally implies the association of practices with dif-
advantages of a service company are related to the balance ferent professional skills acting as one in carrying out projects
between income and corporation tax. jointly, yet retaining their separate identities and each with their
own responsibility to the building owner. A consortium may be
formed for the duration of a single project or on a more regular
Group practices and consortia and permanent basis.
4.22 Architects’ businesses may come together to work in sev-
eral forms of association, whether for a single project or on a
more permanent basis. This chapter is not concerned with the
Diffculties
operational and management factors for and behind the choice 4.26 Any association of practices, whether permanent or tempo-
of form, but only with the legal issues. Further guidance is given rary, must be very carefully planned. If practices are to merge
in the RIBA Architect’s Handbook of Practice Management. The completely, assets should be carefully assessed (including work
creation of any association should be checked carefully with the in progress). Specific agreement is necessary on debts, including
professional indemnity insurers of each party. liabilities relating to previous contracts. These could be signifi-
cant if a pre-merger project became the subject of a professional
negligence claim.
Loose groups
4.23 These are associations in which practices or individuals 4.27 If practices are to preserve their own identities and to
pool their knowledge and experience. Such a group does not continue to practise in their own right, as well as together on
need to be registered, but some short constitution is desirable common projects, the form of agreement becomes more critical
which clearly distinguishes it from a partnership. In company and more complex. A new group or consortium, partnership, or
law a more formal ‘Memorandum and Articles of Association’ company should be created to contract with clients for com-
is necessary and is of far greater significance. It must set out the mon projects. Its agreement must resolve how far the assets of
302 Legal organisation of architects’ offces

member practices are brought in, the extent of liabilities of the Railway Premises Act 1963, but this is now subordinate to the
group, and the degree of independence retained by each member Health and Safety at Work Act 1974 (HSW Act) together with
practice to carry on its own activities. A solicitor should always regulations made under the two Acts. The HSW Act shifted the
be consulted. focus from premises to people. This chapter is concerned with
its impact on an architect as employer, employee, or occupier
of premises.
Employee Trusts
4.28 A more recent innovation is that of Employee Ownership. 5.02 The HSW Act is directed at people who work, whether
This structure enables the owners of a practice to distribute own- employer, employee, or self-employed persons, and their respon-
ership to the employees. This might, for instance, be a way for sibilities to each other and to third parties who may be affected
senior partners to retire and take some financial benefit, whilst by the work process or its results. Under the Act, employers
transferring an ongoing concern to the employees. Employee must maintain safe systems of work and keep plant and premises
ownership can help companies to retain their independence, in safe condition. Adequate instruction, training, and supervision
reward employees’ hard work, and enable outgoing shareholders must be given for the purposes of safety. This may extend to
to receive fair value for the company they have built, amongst guidance or instruction to employees visiting buildings or con-
many other benefits. It can also be used when setting up a new struction sites in the course of their employment, particularly at
business, helping to attract talented employees, and to create a times when the premises or site may be otherwise unoccupied.
positive culture. The RIBA provides detailed guidance on safety procedures with
particular reference to safety on site. Unless fewer than five peo-
4.29 Employee Ownership is facilitated by using an Employee ple are employed, an employer must prepare a written statement
Ownership Trust (EOT). A structure originated by the govern- of the business’s safety policies, organisation, and arrangements,
ment in 2014, arising from the Nuttall Report of 2012, to encour- and make this known and understood by all employees. Even if
age company owners to sell a majority stake in the company to a written policy is not required, an employer is not entitled to
its employees. The original company will be valued and then disregard the Act.
sold to the trust company by way of a share purchase agreement.
The purchase price creates a debt owed by the trust company to 5.03 Safety policy should deal with the safety responsibilities
the original shareholders. of all managers, inspection procedures, supervision, training,
research, and consultative arrangements regarding safety, fire
4.30 To incentivise shareholders to create such a trust, the drill procedure, reminders on keeping stairways and corridors
government has set up favourable tax breaks provided the trust free of obstructions, the marking and guarding of temporary
(known as a qualifying trust) is set up as follows: hazards, use of machinery, accidents, and first aid. Advice is
obtainable from the Health and Safety Executive. However,
● The EOT must have a controlling interest (i.e. more than employers should ensure that their safety policies are tailored
50%) in the company; specifically to meet the individual needs of their businesses.
● The EOT must be established for benefit of ALL employees; Anyone in a supervisory or managerial role will have specific
● The EOT must treat ALL employees on an equitable basis. health and safety responsibilities. While managers may delegate,
they retain responsibility.
4.31 There are benefits in setting up an EOT. For instance, the
original shareholders will get a guaranteed sale price, provided 5.04 Employees in turn have a duty to exercise reasonable care
the criteria are met, the sellers are able to take advantage of tax to themselves and their fellow employees, to cooperate with
breaks available at the time (currently this is exemption from their employer in carrying out statutory requirements, and not
Capital Gains Tax), and finally, an EOT can ensure a smooth to interfere with safety provisions. It is important for managers
succession whilst retaining the outgoing owners’ experience to remember that they are also employees.
and expertise. Another key benefit, especially if the EOT is set
up from the beginning, is the potential for greater employee 5.05 A number of regulations are important to the office
engagement. Finally, transferring the business to an EOT is seen environment and organisation. Central to these are the
as a more friendly and predictable process than a sale to another Management of Health and Safety at Work Regulations
organisation. 1999, containing the requirement, among other matters,
that employers and the self-employed make and maintain a
4.32 There are some pitfalls to take into account when consider- sufficient and suitable risk assessment for the purposes of
ing an EOT. The EOT must be set up to benefit all employees, identifying the measures required to be taken to comply with
but some will be better placed to take key roles in running the health and safety law. Equally important are the Workplace
business than others. Therefore, a share ownership structure that (Health, Safety and Welfare) Regulations 1992. More specific
reflects the roles and responsibilities of each employee needs to requirements are laid down in the Provision and Use of Work
be carefully defined at the outset. If this is not done, there is a Equipment Regulations 1998, the Health and Safety (Display
possibility that no one really knows who is responsible for what Screen Equipment) Regulations 1992, the Manual Handling
and that can cause serious problems. There is some evidence that Operations Regulations 1992, and the Personal Protective
EOTs work better in larger companies that are able to employ a Equipment at Work Regulations 1992. The Health and Safety
management team to oversee the trust and take on the day-to-day (First Aid) Regulations 1981 impose a duty upon employers
running of the company, while the remaining employees carry on to provide first aid equipment and facilities, to provide suit-
doing their existing jobs, but also benefit from part ownership able persons with training in first aid, and to inform employ-
of the company. ees of the arrangements they have made. The British Safety
Council Approved Code of Practice, Health and Safety (First
Aid) Regulations 1981 is approved by the Health and Safety
5 Premises and persons Commission to provide practical guidance in respect of the
regulations. Although failure to comply with the Code’s guid-
Health and Safety at Work Act 1974 ance is not in itself an offence, it is prudent to follow it. The
Control of Substances Hazardous to Health Regulations 2002
5.01 Employers are obliged under the general duty of care to (COSHH) impose a duty upon employers to ensure levels of
protect employees against personal injury in the course of their hazardous substances do not harm employees or others who
employment. They are obliged by statute to provide employees may be in contact with them. Hazardous substances used in
with healthy, safe, and decent working conditions. For office the office include ammonia, solvents (for example correction
workers, these were originally set out in the Offices, Shops and fluid), adhesives, photocopy and laser printer toner, copier
Premises and persons 303

emissions, cleaning agents, and dusts. The Electricity at Work not been suffered. Although insurance may be taken out against
Regulations 1989 require that electrical systems and equip- the possibility of damages being awarded, insurance may not
ment be maintained so far as is reasonably practical to prevent be used to protect against the results of criminal acts, such as
danger. Recommendations are provided on the frequency of fines or imprisonment under the Health and Safety (Offences)
formal inspection and electrical testing. The Health and Safety Act 2008.
Executive publishes guidance enabling the obligations imposed
by these, and other relevant regulations, to be met.
Occupiers’ Liability Acts 1957 and 1984
5.13 Occupiers owe a duty of care to all entrants on their prem-
Accidents ises. If the entrants are lawful visitors, reasonably practicable
5.06 Employers are required to notify the enforcing authority steps must be taken to make the premises safe for them and
of accidents on the premises, subject to the requirements of the to protect them against all hazards, or give sufficient notice
Reporting of Injuries, Diseases, and Dangerous Occurrences of them. Visiting workpeople such as window cleaners are
Regulations (RIDDOR), which cause the death, or the disable- responsible for their own safe working methods, but if there
ment for more than three days, of a person employed to work are particular hazards in the area in which they will be work-
on the premises. A record must be kept of all accidents as they ing, then the employer, owner, or occupier has a duty to advise
occur. In any case, this is useful as a check against the possibil- each visitor of those hazards. If it is foreseeable that persons
ity of persons making claims for accidents which did not happen unable to read warnings, such as children or blind persons,
on office premises. may be likely to get into hazardous areas, then protection must
be adequate to keep them out. A duty of care is even owed to
trespassers, although this duty is to take such care as is rea-
Employees’ right to information sonable in all the circumstances of the case to see that they
5.07 Because the HSW Act is primarily for the benefit of do not suffer injury on the premises by reason of the danger
employees, and because some employers are forgetful of their concerned. Sufficient warnings or discouragements will nor-
duties, the occupier is obliged to give employees information mally discharge the duty.
about the Act either by posting up an abstract in a sufficiently
prominent place or by giving them an explanatory booklet. 5.14 Responsibility for injury or damage arising from improper
construction or maintenance is not avoided by the transfer of
the premises to another owner (Defective Premises Act 1972).
Division of responsibility
5.08 One of the potentially confusing aspects of the HSW Act 5.15 If a landlord has a repairing obligation to tenants, then the
is the division of responsibility between owner and occupier, landlord has a responsibility to anyone who could be affected by
particularly in multi-occupied buildings. The employer, if not the the landlord’s failure to keep the premises properly maintained.
occupier, is responsible for notifying the occupier of accidents to
his or her employees and for notifying his or her own employees
of the provisions of the Act.
Fire protection
5.16 The Regulatory Reform (Fire Safety) Order 2005 (FSO) is
the most current and up-to-date legislation in respect of fire. The
Single occupation FSO has revoked all other fire regulations, including the Fire
5.09 An employer who occupies a whole building is responsible Precautions (Workplace) Regulations 1997.
for ensuring that all provisions of the HSW Act are met.
5.17 The FSO applies to most premises and covers most types
of buildings, structures, and open spaces. It requires any person
Multi-occupation who exercises some level of control in premises to take reason-
5.10 When a building is in multi-occupation, responsibility is able steps to reduce the risk from fire and ensure occupants can
divided. The owner is responsible for the fire risk assessment, safely escape if a fire does occur.
fire alarms, and signposting, and keeping free from obstruction
all exits and means of escape in the building as a whole, clean- 5.18 The main requirements of the FSO are that the responsible
ing, lighting, and safety of the common parts, washing, and sani- person is to:
tary facilities. Occupiers are responsible for the risk assessment
and all other provisions of the HSW Act within the parts of the 1 Carry out or nominate someone to carry out a fire risk
building they occupy. assessment identifying the risks and hazards;
2 Consider who may be especially at risk;
3 Eliminate or reduce the risk from fire as far as is reasonably
Enforcement practical and provide general fire precautions to deal with
5.11 To ensure that the law on health and safety is respected, any residual risk;
inspectors appointed by the enforcing authority have the power 4 Take additional measures to ensure fire safety where flam-
to enter premises to which the HSW Act applies. They may mable or explosive materials are used or stored;
inspect the premises, question anyone, or ask to see relevant 5 Create a plan to deal with any emergency and, in most
certificates or notices. It is good practice to obtain evidence of cases, document the findings; and
their identity and authority before taking anyone round. 6 Review the findings as necessary.

5.12 Inspectors have the power to make ‘improvement’ notices 5.19 Fire alarms must be tested at intervals, and occupiers are
under which the offending practice must cease or the deficiency required to take effective steps to ensure that all occupants are
must be remedied within a certain period. They also have the familiar with the means of escape and with the action to be
power to issue a ‘prohibition’ notice under which the practice taken in case of fire. Fire drills are the most effective way of
must cease or the premises must not be used until their require- doing this.
ments have been met. An appeal against a notice may be made
to an industrial tribunal. Offences under the Health and Safety 5.20 If any alterations are made to the premises, the responsible
at Work Act are criminal offences, although breaches of the person is required to review the fire risk assessment and take
regulations made thereunder can also result in civil liability. It such measures as are reasonably necessary to reduce the risk
is an offence to contravene requirements imposed by a notice. from fire and ensure occupants can safely escape in the event
The offender may be liable to a fine even though damage has of fire.
304 Legal organisation of architects’ offces

The General Data Protection (Compulsory Insurance) Act 1969 and the Employers’ Liability
Regulation 2016/679 (GDPR) (Compulsory Insurance) Regulations 1998 as amended require
that every employer who carries on business in Great Britain
5.21 The GDPR is a Europe-wide regime that replaces the Data shall maintain insurance under approved policies with authorised
protection Act, 1998. It applies to ‘controllers’ and ‘processors’. insurers against liability for bodily injury or disease sustained
A controller determines the purposes and means of processing by employees and arising out of, and in the course of, their
personal data. A processor is responsible for processing personal employment in that business. Cover must extend to an amount
data on behalf of a controller. Every organisation that processes of £5m for any one occurrence. Employers’ liability policies
personal data had to be compliant with the new rules on 25 May are contracts of indemnity. The premium is often based on the
2018. Failure to comply could render a practice liable to a fine amount of wages paid by the insured to employees during the
of up to £500,000. An architectural practice will inevitably hold year of insurance. The size of the business is immaterial. The
data about its employees, clients, suppliers and others that it col- Act also provides for employees not ordinarily resident, but who
laborates with. Compliance need not be onerous, especially for may be temporarily in Great Britain in the course of employment
small practices, but it is advisable to seek professional guidance. for a continuous period of not less than 14 days. Copies of the
To start with, privacy notices should be reviewed for compli- insurance certificate must be displayed at the place or places of
ance, and existing notices may have to be updated. GDPR gives business for the information of employees.
people more rights over their data, and it is no longer possible
to require payment for access to it. It is worth knowing that if
you willingly exchange business cards with another person, they Motor vehicles
have effectively given you permission to store their data (as have 6.06 Third party insurance cover is a legal requirement under
you!), on a client or potential client database, or CRM system, the Road Traffic Act 1988, as amended by the Road Traffic Act
as have you on their system). See, further, Chapter 37. 1991 in respect of death or personal injury to third parties or
damage to a third party’s property. Cover may be invalidated
if a car is used for purposes not covered by the policy. Cars
6 Insurance owned and operated by a practice must therefore be covered for
business use, and cars owned by employees and used by them
6.01 A practice protects itself by insurance against financial in their duties must be covered for occasional business use and
risks. Some of these are ordinary risks such as fire, and some are travel to and from a place of work, including for commuting.
eventualities that a practice is not obliged to cover but which, as
a good employer, it may wish to provide for, such as prolonged 6.07 If staff use their own cars on practice business, their cover
sickness of a member of staff. There are cases, however, when must be adequate, particularly in respect of fellow employees.
a practice is obliged by law to cover damage caused to other Their policies should be checked to ensure that they include a
persons. Varieties of insurance which cover these risks follow third party indemnity in favour of the employer, otherwise, if a
(see also Chapter 35). claim results from an incident while the car is used on practice
business, insurers may repudiate liability.
Public liability
6.02 An owner or a lessee of premises, or someone carrying on Professional indemnity
a business in premises may be legally liable for personal injury 6.08 This is the insurance necessary to cover professional people
or damage to property of third parties caused by their negligence for negligence. Such policies will normally only cover liabilities
or that of their staff. to third parties, not loss caused to a person’s own business by
reason of their negligence. Nor will they cover fraud.
6.03 Public Liability insurance is not compulsory in the UK,
but since several people may be involved in a single incident, 6.09 Every architect in every form of practice is required by
and the level of damages may be very high, it is important for the Architects Registration Board and the RIBA to be covered
cover to be: by professional indemnity insurance. The scope of the policy,
amount of the premium, and other details are matters which
1 Appropriate to status, whether owner, lessee, or occupier; must be worked out on an individual basis by the architect and
2 Extended to cover the actions of employers and employees, an experienced insurance broker, taking ARB’s requirements
not just on the premises, but anywhere while on business; into account.
3 Extended to cover overseas if employers or employees are
likely to be overseas on business. 6.10 The minimum level of cover is set at £250,000, but in
practice, this will be considerably higher where the practice
Employers' liability takes on anything other than very small projects and especially
if it works overseas.
6.04 An employer is liable for personal injury caused to an
employee in the course of employment by the employer’s neg- 6.11 In view of its importance, professional indemnity insurance
ligence or that of another member of staff, his or her agent, or is dealt with in Chapter 35.
servant. It is important to arrange insurance to cover for injuries
sustained:

1 During employment, whether on or off the employer’s


7 Scottish postscript
premises;
2 Overseas, if employees are likely to be overseas on Introduction
business. 7.01 An individual architect in Scotland can operate either as a
sole trader or, in certain circumstances, as a limited company.
Employers’ Liability (Compulsory Groups can operate as either limited companies, partnerships,
Insurance) Act 1969 limited partnerships, or limited liability partnerships.
The Partnership Act 1890, the Business Names Act 1985, and
6.05 Employers are required by statute to take out specific the Limited Partnership Act 1907 apply equally to Scottish part-
insurance to meet their obligations. The Employers’ Liability nerships. The Offices, Shops and Railway Premises Act 1963 and
Scottish postscript 305

the Health and Safety at Work Act 1974, as amended, apply in Separate legal entity
Scotland as in England.
The Architects Act 1997 (as amended) applies equally to 7.06 In Scots law, the architectural practice or firm has a separate
Scotland and to England. Care needs to be taken in the naming personality from its members. The partnership owns the funds of
the practice and in the correct use of singular/plural to ensure the partnership; the partners are not joint owners of the partner-
that the Act is complied with. ship funds. This is of importance relative to liability for debts
In many respects, the law in Scotland and England concurs and actions brought by and against the firm and its members and
in respect of the framework for establishment of an architectural for diligences, ranking in bankruptcy and compensation. The tax
practice. The essential differences are outlined below. position for a Scottish partnership is presently the same as that
in England and Wales.
A partner is not directly liable for a debt owed by the prac-
Sole traders on the business tice. A debtor to a firm cannot plead compensation on a debt due
7.02 The situation for architects practising as sole traders in by an individual partner, nor can a partner be sued for a private
Scotland is much the same as that in England, in relation to debt plead compensation on a debt due to the firm. However, a
the setting up of the business. Business naming is governed by partner suing for a private debt may be met with a plea of com-
the Business Names Act 1985 relating to the disclosure of the pensation on a debt due by the firm, while the firm sued may
proprietor’s name on business documentation and at the place plead compensation on a debt due to a partner. The principle is
of business. The taxation position for sole traders, partnerships, that a partner is not a creditor in debts due to the firm, but is a
and companies is presently the same as exercised in England and debtor in debts due by the firm.
Wales, although it could be subject to change as a result of the A firm can sue and be sued. When suing, it does so either in
additional tax-raising powers of the Scottish Parliament, if they its own name or in the names of all of the partners, indicating
are implemented in the future. that it is for a firm debt. A firm may be either a debtor or credi-
tor to any of its partners and consequently, a partner may sue,
or be sued by, the firm.
Partnerships A firm is liable for the wrongful acts or omissions of its
7.03 As in England, it is inherent in the idea of partnership that partners acting in the ordinary course of business (Kirkintilloch
association exists, and that business is carried out with a com- Equitable Co-operative Society Ltd v Livingston and others
mon view to profit. Within a partnership, the minimum number 1972 SLT 154). Further, a firm, at common law, may be liable
of partners is two. Although governed by the same statutes, on the grounds that it received gratuitously the benefit of the
there are fundamental differences between Scots and English law wrongful act of a partner.
regarding the legal status of partnerships and their relationship
with the partners themselves. The extent of partners’ liability
7.07 Every partner of a firm is jointly and severally liable for the
Firm naming debts of the firm. Further, the liability is unlimited, making the
7.04 In Scotland, a collection of individuals or partners is called partner liable to his or her last penny to the firm’s creditors if the
a ‘firm’. The name of the business is the ‘firm name’. The nature firm does not meet its debts. Partners can be held liable only when
of the firm name is important in relation to legal proceedings in the debt has been constituted against the firm. The creditor must
the Court of Session. If the firm name does not comprise the sue the firm first. If the firm has been dissolved, all the partners
names of individuals, it is required in legal proceedings to add within the jurisdiction must be sued together. The right of recovery
the names of all of the partners, up to a maximum of three. This of a debt is covered by the Prescription and Limitation (Scotland)
does not apply if the name comprises the names of persons, no Act 1973, as amended in 1984, under which the creditor has five
matter who they may be. This requirement also does not apply years from the date of the loss or transaction to raise a competent
to actions in the sheriff courts (Sheriff Courts (Scotland) Acts action in court. The right of recovery under delictual liability for
1907 and 1913, updated in 1939, 1971, and 2007). The Business professional negligence or other wrongdoing is not so restricted.
Names Act 1985 requires the name of a firm to be registered
unless it comprises only the true surnames of the partners with- Partnership property
out any additions other than their true first names or initials. If
registered, the firm must display the registration certificate in a 7.08 Partnership property is all property originally brought
prominent place at the firm’s principal place of business. Failure into the partnership stock or acquired for the purposes and in
to do so is a criminal offence. The 1985 Act also demands the the course of the firm’s business. The partners must apply this
publication of the names of the persons or corporations using the property exclusively for the purposes of the partnership. If
business name. In partnership, the names of the partners and any property has been bought with money belonging to the firm, it
former first names or surnames and nationality, if not British, of is deemed to have been bought on account of the firm. Property
the partners must appear on all business letters, brochures, and bought by partners individually, which may be loaned to the firm
business cards. by agreement, is not partnership property. Partnership property
excludes land or buildings, which must be owned by one or more
individuals or by trustees on behalf of the firm.
The relationship between partners
7.05 The contract of partnership needs no special form. It may Retiring partners
be oral, written, or inferred by the nature of the relationship. As
in any contract, the intention of the parties is relevant, inferred 7.09 A retiring partner of a firm remains liable for the debts or
by law from the whole evidence. Every partner is an agent for wrongful acts of the firm incurred or committed while he or she
the firm. His or her acts in the ordinary course of business and was a partner, irrespective of the fact that the other partners may
in signing the firm name binds the firm. have agreed to indemnify him against claims, unless the creditor
The relationship between partners is regulated by the partner- in question is party to the arrangement. Any agreed limitation
ship agreement. A partner who meets a firm debt has a right of of liability in this regard will not restrict ongoing liability for
relief against his or her co-partners and may call on them to con- professional negligence. It is of great importance to a retiring
tribute their contracted share to the loss. Terms in the contract partner that all customers and clients are directly informed of the
of partnership, if verbal or poorly prepared, can be implied from retirement or dissolution. Otherwise, he or she may remain liable
the Partnership Act, relating to the rights of sharing profits and for the debts or wrongful acts of the firm incurred or committed
the liability for losses, the right of access to the firm’s books, after his or her resignation (Welsh and another v Knarston and
and to take part in its management. others 1973 SLT 66).
306 Legal organisation of architects’ offces

New partners Termination


7.10 A new partner admitted to an existing firm does not 7.13 A partnership may terminate at the end of a fixed term, by
automatically become liable to the creditors for anything done rescission or by agreement, by notice of any of the partners, by
before he or she became a partner. This depends upon whether death or bankruptcy of a partner, or by the court. When the part-
the whole assets are handed over to a new partnership and the nership has been dissolved, the general authority of the partners
business is continued, as before, in which case the liabilities are to bind the firm is ended other than to wind up the partnership
taken over with the assets and the new partner will be liable. affairs and complete transactions unfinished at the date of dis-
If the new partner paid into the firm a sum as capital while the solution. At the winding up of the firm, all losses, including
other partners contributing their share of the going business, loss of capital, are paid out of profits, with residual payments
the new partner will not share in the firm’s previous liabilities. being made by or to the partners in proportion to the relationship
stipulated in the partnership agreement.
Assignation
7.11 A partner may assign his or her interest in the partnership,
Limited partnerships
but not to the point of making the assignee a partner, nor giving 7.14 Other than the differences noted above, in respect of the
partnership rights. A partnership agreement may provide for a degree of limitation of liability achieved, the Limited Partnership
right to nominate a partner by inclusion within a will. However, Act 1907 applies in Scotland as it does in England, with the Act
a sole heir cannot become a partner without relevant provision providing for registration of a limited partnership separately in
in both the will and the partnership agreement (Thomson v Scotland. The Registrar will advise against the use of any name
Thomson 1962 SC (HL) 28). that is the same as the name of a limited company or another
limited partnership already on the register. In addition, the names
of limited partnerships are controlled by the Business Names Act
Bankruptcy 1985. Until a limited partnership is registered, it will be regarded
7.12 In bankruptcy, the firm’s creditors must rank before the as a general partnership, with both the general and limited part-
partners against the firm’s estate. The creditors of individual ners equally responsible for any debts and obligations incurred.
partners do not have a claim on the estate of the firm, although The Act permits the creation of partnerships in which some part-
the creditors of the firm qualify for dividends from the estate of ners may limit their liability for the firm’s debts. There are two
individual partners. classes of partner within a limited partnership, being general and
The process of divesting a bankrupt of his or her estate and limited. General partners are fully liable as within a full partner-
property is sequestration, whereby the court will pass over the ship. Limited partners’ liability can be restricted to the amount
bankrupt’s property to a trustee. The trustee gathers in the assets of their initial financial contribution to the partnership. Limited
and sells them; the net proceeds (after payment of administra- partners cannot take any part in the management of the firm
tion expenses) being divided, as far as possible, amongst the without exposing themselves to full liability for the firm’s debts.
creditors, according to their various priorities, in payment or
part-payment of the debts due to them. Before sequestration, an
individual or firm may go through other stages in the process
Limited liability partnerships
of inability to meet obligations (Bankruptcy (Scotland) Act 7.15 The Limited Liability Partnership Act 2000 operates simi-
1985 section 7). ‘Practical insolvency’ is the first stage, being larly in Scotland as in England and Wales. However, the Act
a present inability to meet debts due to insufficient liquidity. provides that the incorporation document must state whether the
The second stage, or ‘absolute insolvency’, is when the indi- registered office of the limited liability partnership is to be situ-
vidual or firm’s liabilities exceed its assets. At this point, the ated in England, Wales, or in Scotland. At all times, a Scottish
firm is restricted to acting only in the interests of its creditors. registered limited liability partnership must maintain its regis-
Gifts cannot be made, nor can one creditor be favoured at the tered office in Scotland. In Scotland, in addition to the English
expense of others. Transactions, which have that effect, are provisions, a former member of a limited liability partnership or
referred to as ‘fraudulent preferences’ and may be reduced his or her trustee in bankruptcy or permanent or interim trustee
(overturned) at common law. The third stage is ‘apparent (within the meaning of the Bankruptcy (Scotland) Act 1985)
insolvency’, formerly known as ‘notour bankruptcy’, which is may not interfere in the management or administration of any
‘insolvency of a public or notorious nature’. This can be consti- business or affairs of the limited liability partnership.
tuted by sequestration. Alternatively, apparent insolvency can
be constituted by one of the following: voluntary disclosure to
creditors that payment of debts in the normal course of busi-
Companies
ness has ceased; insolvency concurring with a duly executed 7.16 Although the Companies Act covers both countries, it is
charge, the date of which has expired without payment being important to understand the effect of differing legal systems
received by the creditor; the granting of a trust deed or a decree upon legal entities within England and Scotland.
of adjudication, either for payment or in security; or by the
equalisation of diligences.
Diligence is the legal process of attaching preper to force
Registered offce
appearance in court or to allow the implementation of a judg- 7.17 The Act refers to the requirement for stating the intended
ment already pronounced. Diligence may be in the form of place of registered office. The exact address must be filed
arrestment: attaching property in the hands of a third party; or with the Registrar of Companies simultaneously with the
poinding: the attachment of moveable property, the effect of Memorandum at the time of incorporation.
which is to immobilise it. This may be followed by a judicially The registered office determines the nationality and domicile
ordered sale for the benefit of the creditor. of the company, but not its residence. The shares of a company
A firm can be sequestrated without any of the partners them- registered in Scotland are deemed to be located in Scotland,
selves being sequestrated. If an individual is sequestrated, he irrespective of the location of the share certificates. This has
or she has the right to retain certain property. This is restricted implications for capital transfer tax (death duties) in the event
to items of clothing for him or herself and family and working of the death of a shareholder.
tools or implements necessary to enable him to earn a living. The registered office may be changed at any time by a
Deliberate avoidance of the loss of assets in Bankruptcy through resolution of a board of directors, subject to notification to the
‘gratuitous alienations’ (gifts) made by the insolvent person to Registrar of Companies. However, once established, the com-
trusted others or family can be challenged under the Act of 1985, pany cannot relocate its registered office to any part of the UK
section 34. outside Scotland. As in England, the address of the registered
Scottish postscript 307

office must be indicated on letterheads and other company the borrower’s liability is unrealistically limited. To obtain such
forms and in the annual return. The principal office of the credit, personal guarantees are generally sought, with a liability
company need not be the registered office, and can be situated being confirmed for a set sum to the lender by each director,
outside Scotland, and indeed outside the UK. Thus, a ‘Scottish’ usually on a ‘joint and several’ basis. A floating charge may be
architectural practice can carry on its business almost wholly taken against personal property or the asset value of the com-
outside Scotland while still being subject to the jurisdiction of pany’s work-in-progress at the time of winding-up. Any director
the Scottish courts. unable to meet the obligations imposed as a result of personal
guarantees on the winding-up of a company could be liable to
sequestration.
Lien over shares
7.18 A company in Scotland has a common law right of reten-
tion, or ‘lien’, over its shares, whether fully or partly paid. This
Directors’ liability
may be extended or restricted if so expressed in the articles of 7.20 It is important to note that limitation of liability within a
agreement. Articles will usually provide for a lien only to be limited company does not restrict liability for negligence either
exercisable over partly paid shares (Bell S Trustee v Coatbridge as an officer of the firm or as an architect. Professional indem-
Tinplate Co (1886) 14 R (HL) 246). Unless the Articles provide nity insurance should be held by the firm to cover errors or acts
otherwise, the company cannot sell shares subject to a lien in of professional negligence. There are also circumstances where
order to satisfy a debt owed to it. a company director can be found liable to the company itself,
in relation to the payment of dividends (Flitcroft’s Case (1882)
21 Ch D 519). The Bankruptcy (Scotland) Act 1985, as amended
Floating charges in 1993, does not deal with the position of directors responsible
7.19 The Companies (Floating Charges) (Scotland) Act for the payment of dividends. Dividends must only be paid out
1961 makes exception to the rule that a lender can only acquire of company profits, not out of capital. A director who is respon-
security over moveable property after delivery, and over herit- sible for an unlawful distribution could be liable to the company
able property through registration at the Register of Sasines. for breach of duty. Redress could be sought and the full amount
The floating charge gives the creditor a preferential right over of the dividend reimbursed to the company. However, this prin-
the liquidator to recovery when the charge ‘crystallises’ on ciple would only apply if the director knows the circumstances
the winding-up of the company. It’s possible that institutional of the payment. An innocent director is not liable to repay a
credit for a limited company will be refused on the basis that dividend that has been wrongfully paid.
30
Architects’ contracts with clients
SARAH LUPTON

1 The appointment on the profession; the onus is on the architect to ensure that the
employer is made aware of all the relevant matters.
1.01 An architect has many factors to take into account when The architect must consider the position of any other archi-
considering an offer of an appointment, and it is important that tects who may have been involved in the same scheme. An
their implications are thoroughly understood before entering into employer is free to offer the commission to whomever it wishes,
a legal commitment to undertake the commission. to obtain alternative schemes from different architects, and to
The architect must be satisfied that the client has the authority make whatever arrangements for professional services it con-
and resources to commission the work; he or she must appreciate siders to be necessary. However, the architect is bound by the
the background to the proposal and understand its scope, at least codes of professional conduct and must ensure that he or she has
in outline, and be aware of any other consultants who have been, acted, and continues to act, properly and fairly in any dealings
or are likely to be, associated with the project. with other architects. Apart from the professional obligation to
The architect must be satisfied that he or she has the experi- advise the first architect, it is commercially prudent to do so.
ence and competence to undertake the work; that the office has
the necessary finance, staff, and other resources; and that the 1.03 The need to consider the position of other architects is par-
proposal will not conflict with any relevant codes of professional ticularly important in large, complex projects involving various
conduct, other commissions and commitments in the office, and consultant architects providing different, but related services,
the policy of the practice. Key matters such as the scale and especially when the arrangements for professional services
complexity of the project, and its proposed procurement route, change during the project. The scope of services and the rela-
will have a significant impact on the terms of appointment, and tionships between consultant architects and executive architects
will need to be established at an early stage. can, on occasion, be the cause of misunderstanding, and even
The preliminary negotiations between the parties often difficulties in evolving and changing circumstances. The onus is
involve the exchange of business references, especially where on the project leader to ensure that the roles, relationships, and
the architect and the potential client are previously unknown to responsibilities of everyone involved are clearly understood, but
each other. On occasions, extensive enquiries about the client it is particularly important that the architects are fully aware of
and the client’s business may be necessary. the extent of their individual duties and liabilities.
It is not unusual for architects to be invited to enter into
collateral agreements with funding bodies or other third parties 1.04 Clients sometimes seek single, all-in service appointments
as a condition of the appointment; the possible implications of for the whole range of consultancy services required. The all-in
these agreements need to be considered by the architect, and in services can be commissioned from an existing multi-discipli-
particular, it is important to ensure that any liabilities incurred nary practice or from a single-discipline consultant who engages
are covered by the architect’s professional indemnity insurance others as sub-consultants for any other specialist services that
cover. Occasionally, clients ask the architect to enter into collat- may be needed. Multi-disciplinary practices usually have their
eral agreements after the fees and terms of the appointment have own well-established forms of agreement but, in the case of the
been agreed but, if this happens, it is essential that the architect single discipline consultant offering an all-in service, care is
considers their conditions carefully, comparing them with those needed in the drafting of an agreed form of appointment. The
of the original appointment. If the proposed collateral agree- consultants concerned have to agree upon a unified approach to
ments extend the services required or increase the architect’s services, payment, conditions, and liabilities before an offer can
liabilities beyond those originally envisaged, the terms of the be made to a potential client. It is particularly important that the
appointment should be renegotiated. extent of the liabilities which may be incurred are considered in
relation to the current professional indemnity insurance of the
1.02 Any appointment offered to an architect must be considered consultants concerned and any changes that may be needed in
in relation to the requirements of the Architects Registration the extent of the cover. It is essential that the lead consultant
Board (ARB) Code of Conduct (Chapter 39), and also the offering the all-in service, and therefore being totally liable to
codes of conduct of any other professional institutions of which the client, confirms the position with its professional indemnity
the architect may be a member. The architect must be able to insurers before making the offer.
demonstrate that he or she has acted properly in obtaining the The architect often acts as the lead consultant in making an
commission and is able to carry out the work in a suitable man- all-in service offer, but occasionally the architect may act as a
ner and in accordance with the appropriate codes and standards. sub-consultant to a consultant from another discipline. Where the
An employer may not always be conscious of the constraints architect is required to act as a sub-consultant, or is appointing

309
310 Architects’ contracts with clients

another architect as a sub-consultant, consideration should be conditions of the appointment. Difficulties develop occasionally
given to the use of the sub-consultant agreement discussed when the subsequent building is substantially different from that
below. originally envisaged and where there has been a material change
in the conditions. The subsequent appointment of consultants
other than the original competition winners can be the cause of
2 Agreement of appointment serious difficulties.

2.01 Although, in law, an oral agreement may be accepted as 2.05 The form of appointment agreement should be signed by
the basis of a contract of engagement between architect and both parties and dated, each keeping a copy. If the contract is
employer, such an arrangement would not comply with the ARB to be executed as a deed, then the required formalities must be
and RIBA codes of conduct, and a formal procedure of appoint- observed. The onus is on the architect to explain the professional
ment should always be adopted at the outset. Such a procedure obligation to enter into a formal agreement before work com-
creates a clearly identifiable legal basis for the commission mences; beginning work without a clear agreement of services
and establishes a sound business approach to the relationship and charges is not only commercially unwise, it is also a breach
between the architect and the employer. The appointment may be of the codes, which could result in disciplinary action. Failure
made by either an exchange of letters or emails, or an exchange to agree and confirm the services to be given and the charges
of a formal memorandum of agreement, in each case, supported to be made is also the most common source of dispute between
by appropriate supplementary material such as conditions of architects and clients. The absence of clear and precise terms
engagement. of appointment make it hard for a conciliator, an adjudicator,
An informal exchange of letters or emails is frequently used, an arbitrator, or the courts to resolve disputes in an equitable
but it is not recommended practice. Informal exchanges are liable manner.
to misinterpretation and misunderstanding, and are often the source
of difficulties and disagreements between the parties. In particular, 2.06 The authority of the architect is strictly limited to the terms
they frequently neglect to cover matters required under the RIBA of the appointment, that is, as shown in any form of agree-
and ARB codes of conduct, for example, to define clearly the ser- ment and conditions of engagement. It is in the interests of the
vices to be provided or the provisions for termination. employer, the architect, the quantity surveyor, and other inde-
pendent consultants that these terms should be fully and clearly
2.02 Various institutions publish standard forms of agreement, understood by everyone involved. It is not unusual for the form
and their use is strongly recommended (see below). In particular, of services to be varied with changing circumstances during the
the RIBA recommends to all members that its own forms are work, but it is essential that these changes are formally con-
used where appropriate and possible (2019 Code, Principle 1: firmed in amendments to the form of agreement.
Guidance Note 2.1). The forms are self-explanatory, but it is
important that they are carefully read and fully understood by 2.07 Where the architect practices as a sole trader, or as a
both the architect and the client before signing. With ‘consumer’ partnership, the contract of engagement is usually personal
clients, it is particularly important to discuss and agree all the to the architect or the partnership. The duties cannot be del-
terms of the standard form, as otherwise, some of its terms may egated completely, but the architect is under no obligation to
become void by operation of the Consumer Rights Act 2015. carry out all the works personally. The extent to which the
architect may be prepared to delegate duties to an assistant
2.03 Where a standard form of agreement is not used, the terms is a matter of competence, confidence, reliability, and experi-
must comply with the relevant Codes of Conduct, for example, ence of both the principal and the assistant. The architect is
the ARB Code at paragraph 4.4 requires that the terms are set becoming increasingly dependent on the skill and labour of
out in writing and adequately cover: others, both within and external to the office, but will remain
responsible to the client within the terms of the appointment,
● the contracting parties; and continues to be responsible for the acts and defaults of
● the scope of the work: any subordinates. The subordinates, in turn, are responsible
● the fee or method of calculating it; to their principal and could be held liable to their employers
● who will be responsible for what; for results of their acts.
● any constraints or limitations on the responsibilities of the Where the business is conducted as an unlimited or a lim-
parties; ited company, the relationships will depend upon the form of
● the provisions for suspension or termination of the agreement; contract involved, but the ethical responsibilities between the
● a statement that you have adequate and appropriate insur- parties remain, and liability in tort continues regardless of the
ance cover as specified by the Board; form of organisation.
● your complaints-handling procedure (see Standard 10),
including details of any special arrangements for resolving
disputes (e.g. arbitration). 3 Termination
When, as occasionally happens, employers wish to use their own 3.01 Unless the appointment terms set out specific procedures
forms of agreement, attention should be drawn to the merits (as is the case with the RIBA standard forms), the contract of
of using one of the standard forms; they are more likely to be engagement between architect and client may be terminated by
comprehensive; they represent the interests of the parties in an either party at reasonable notice. Reasons for the termination
equitable manner; and are widely recognised in the industry. need not be stated, but in the event of dispute over outstand-
Where the client insists on the use of a non-standard form, its ing fees or payments, the cause of the termination would be of
terms and conditions should be compared with those of the importance to an adjudicator, an arbitrator, or a court in deter-
nearest equivalent standard form; in the case of differences, the mining a decision or an award.
form should be sent to the architect’s professional indemnity In the event of the termination of the contract, any out-
insurers, and impartial advice should be sought before enter- standing fees for work properly carried out become due to the
ing into an agreement. It is particularly important that forms of architect, but it is unlikely that the employer could be held
agreement are compatible with the requirements of the Housing responsible for any loss of anticipated profits on work not yet
Grants, Construction and Regeneration Act 1996, and the ARB carried out.
and RIBA Codes of Conduct.
3.02 Difficulties sometimes arise in connection with the use
2.04 Where a commission arises out of a recognised competi- of material prepared before the termination of the engagement
tion, the competition conditions usually form or set out the took place. The standard forms of appointment usually define
Professional Services Contracts for use by architects 311

the rights of the parties in such circumstances. In the absence that of an architect (NEC4 PSC, now in a 2017 edition): see
of any statement concerning the use of material following the Chapter 18 for a comparison between the RIBA PSC and the
termination of an engagement, it is generally assumed that if NEC4. The Joint Contracts Tribunal publish a Consultancy
the work was substantially advanced at the time of termination, Agreement (Public Sector) stated to be ‘appropriate for use by
it would be unreasonable for the employer not to be entitled to Public Sector employers who are undertaking construction works
complete the project. It is usually accepted that the employer is and wish to engage a consultant (regardless of discipline) to
entitled to a licence to use the drawings to complete the work carry out services in respect of such works’. It also publishes
effectively. The copyright, of course, remains with the architect, a version of its Homeowner/Occupier Contract, which includes
unless some other agreement is made. a form for appointment of a consultant. The most recent edi-
tion of both of these was published in 2016. The Association
3.03 In the event of the death or the incapacity of the architect, of Consultant Architects (ACA) produces two architectural
it is usually held that the employer is entitled to the use of the appointments. The ACA Standard Form of Agreement for the
drawings and other documents to complete the work, provided Appointment of an Architect (ACA SFA, the most recent edition
that payment has been made. Provision for the procedure to be being 2012) and a shorter form of appointment contract, The
adopted in such circumstances should be included in the standard Appointment of a Consultant Architect for Small Works (this
form of agreement. The death of either party to a personal con- has not been re-published since 1998, but is still available). For
tract generally dissolves the contract, but it is usually possible, international use, FIDIC publishes the Client/Consultant Model
with agreement, for a third party to assume responsibility for the Services Agreement (5th edition, 2017), commonly known as
completion of the contract. the White Book, which can be used by any discipline. FIDIC
Agreements of appointments between companies and part- also publishes Sub-Consultancy Agreement to go with the White
nerships, rather than between individuals, avoid the occasional, Book.
embarrassing technical difficulties and delays that occur in the
transfer of responsibility to others in the event of the death or 5.02 The RIBA Professional Services Contracts (PSCs) for the
incapacity of an individual. appointment of an architect have a long history in the course
of which they have, on occasion, been subject to litigation and
3.04 In the event of termination on the grounds of the bank- official comment. The use of the forms is not and cannot be
ruptcy or liquidation, the contract can be continued if both mandatory, and the parties to the contract of appointment are free
parties wish to do so and the receiver agrees, and provided that to use whatever version or form of appointment they wish and to
assurances about the payment of any fees and monies which amend the forms to suit their particular requirements. However,
may become due can be secured. The bankruptcy of the archi- the forms reflect the experience of consultants operating in all
tect can pose problems of professional indemnity insurance and fields of activity and are consistent with current legislation. The
other matters, and it is rare for arrangements to be made for an current forms have been developed in consultation with other
insolvent practitioner to continue in business other than under a sectors of the industry and carefully balance the needs of the
voluntary administration arrangement. client and architect. Guidance Note 2.1 to the 2019 RIBA Code
of Professional Conduct states that they should be used ‘where
3.05 The Housing Grants, Construction and Regeneration Act appropriate and possible’. An architect would have to have very
1996, and the RIBA standard forms of appointment, make provi- good reasons not to recommend their use or to make significant
sion for the right to suspend work in the event of non-payment amendments to them.
of fees. Non-payment of fees may be the architect’s reason for
wishing to terminate an appointment, but before doing so, it 5.03 The PSCs introduced in 2018, and revised and re-published
would be prudent for the architect to give formal notice of the in 2020, provide a series of related appointment documents for
intention to suspend work unless payment is made within a use in various situations. The forms replace the previous suites,
stated period and only then, if payment is still not forthcoming, i.e. the Standard Forms of Agreement 2010, which, in turn,
to proceed with the termination. replaced suites published in 2007 and in 1999. The new family
of standard appointment documents takes into account current
market expectations, as well as all current legislation, such
4 Ownership as the Professional Services Regulations 2009, the Consumer
Rights Act 2015, and the Construction (Design and Management)
4.01 Ownership of drawings and other documents is often cause Regulations 2015. The suite of documents comprises:
for concern. Unless the terms of the appointment provide other-
wise, correspondence and other documents exchanged between ● RIBA Standard PSC 2020;
the architect and others in connection with the approval of ● RIBA Concise PSC 2020;
plans, the running of the project, or the administration of the ● RIBA Domestic PSC 2020;
contract by the architect in his or her role as an agent normally ● RIBA Sub-consultant PSC 2020;
belong to the employer, provided that payment has been made, ● RIBA Principal Designer PSC 2020.
although in practice, it is most unusual for all these documents
to be automatically transferred to the employer. Other material, 5.04 Several additional to the suite were published in Autumn
especially design material, prepared in the architect’s profes- 2020:
sional capacity belongs to the architect, and this accounts for
the greater part of the documentation prepared in the course of ● RIBA Concise PSC 2020: Interior Design Services;
a project. ● RIBA Domestic PSC 2020: Interior Design Services (both
published in association with the British Institute of Interior
Design);
5 Professional Services Contracts ● RIBA Concise PSC 2020: Conservation Architectural
for use by architects Services;
● RIBA Domestic PSC 2020: Conservation Architectural
5.01 The RIBA Professional Services Contracts are the most Services;
widely used forms of appointment by architects and are likely ● RIBA Client Adviser PSC 2020.
to remain so, although others are available. The CIC pub-
lishes a Consultants Contract (second edition, 2011, currently An RIBA Design and Build PSC is also under preparation.
being revised), which is intended for use on larger projects
and for appointing all members of the project team. The New 5.05 The RIBA Standard Professional Services Contract 2020 is
Engineering Contract suite includes a Professional Services the key document(this replaces SFA 2010). It is suitable for
Contract for use in any consultancy appointment, including use where the architect provides services for a fully designed
312 Architects’ contracts with clients

building project of any size or complexity. It is sold as a hard RIBA Standard Professional
copy document or as an on-line, digital version. Services Contract 2020
For design build procurement, the architect may be appointed
by the client or contractor using the RIBA Standard PSC, with 5.07 The RIBA Standard PSC 2020 is published as one docu-
the Schedules of Services completed to reflect the range of ser- ment, unlike previous editions that in some cases comprised
vices that will be provided. The RIBA Standard PSC also makes several different component parts. The Standard PSC includes:
provision for novation of the appointment to the contractor by
setting out the template novation clauses that will be used. The Guidance notes;
novation will, in addition, require a supplementary tri-partite Checklist;
agreement between employer, contractor, and architect, as well Agreement;
as a new appointment to the contractor. The RIBA do not pub- Contract Details;
lish a standard form of novation agreement, instead, the RIBA Contract Conditions;
Standard PSC makes provision in Section M for identifying a Schedule of Services.
form of agreement and recommends use of the CIC Novation
Agreement: Ab Initio (2018). 5.08 The Agreement makes reference to (and therefore incor-
For smaller projects, there are two options, the RIBA porates) the Schedule of Services and the Contract terms. It
Concise PSC 2020 and the RIBA Domestic PSC 2020. The requires insertion of the name of the client body and the firm of
former is for use for a professional commission or construction architects, full details of which are set out in sections A and B of
project with simple contract terms, where the client is acting the Contract Details. The Agreement allows for execution under
for business or commercial purposes. The latter is suitable for hand or as a deed, and requires insertion of a date. The law of
consumer clients undertaking work on their own home, and is England and Wales is stated to apply (cl. 1.5).
not suitable where the client is acting in a commercial capac-
ity, for example, where a landlord is carrying out work to a 5.09 The Contract Conditions comprise two sections: a Definition
rented flat. of Terms, and the Contract Clauses. The Clauses are grouped as
Where the architect is engaged to act as Principal Designer follows:
under the CDM Regulations 2015, the RIBA Principal Designer
PSC 2020, i.e. a separate appointment, is needed for this 1 General interpretation;
role. The exception is for domestic projects, where the RIBA 2 Client’s responsibilities;
Domestic PSC 2018 includes principal designer services within 3 Architect’s responsibilities;
the same contract as a separate and distinct Schedule. 4 Assignment, sub-contracting, other client appointments,
The RIBA Sub-consultant PSC 2020 is devised for situations supplementary agreements, novation;
in which an architect wishes, or is required by the client, to sub- 5 Fees and expenses;
contract part of its services to another consultant, who becomes a 6 Copyright and licence;
sub-consultant. Alternatively, it can be used where the architect 7 Architect's liability;
acts as sub-consultant. It is not appropriate for use where the 8 Professional indemnity insurance;
client wishes to make direct appointments with consultants. The 9 Suspension or termination;
client’s consent to subcontracting is required. The form can be 10 Dispute resolution;
used as printed, regardless of the form of agreement between the 11 Information formats.
client and the main consultant.
The terminology, format, and conditions of the RIBA suite of 5.10 As well as information on the client and the architect, the
documents are consistent, but it is important that the architect Contract Details also requires entries on a wide range of matters.
should be sufficiently familiar with the differences in application Of primary importance is the Project Brief (section D),
and content of the forms in order to be able to advise clients on which should include the project description and the client’s
the selection of the form most appropriate to any given situation. statement of requirements. The fullness of the description will
It is particularly important that the architect is familiar with the depend upon how much is known at the time of execution of the
conditions and is able to explain their meaning and application Agreement, but an attempt must be made in order that the basis
to a consumer client. of the architect’s services and fees can be demonstrated. The
Project Brief is referred to throughout the Contract, for example,
the architect is required to perform the Services with regard to
Plan of Work the Project Brief (cl 3.2.1). Similarly, the Construction Cost and
5.06 The RIBA Plan of Work is used as a benchmark for clas- the Project Programme must be identified in the Details.
sifying project stages, and in the context of appointments, Other matters that must be covered in the Contract Details
is used as a way of sequencing the services to be provided, are; other client appointments, fees and services, payment, pro-
and in some cases determining points at which fees will be fessional indemnity insurance, dispute resolution, information
invoiced. The latest RIBA Plan of Work was published in formats, and supplementary agreements.
February 2020. It is available as a summary, one-page tem- Under other client appointments (section E), the parties are
plate and as a fully detailed guide (the RIBA Plan of Work required to identify ‘other consultants or services appointments
2020 Overview). This replaced the 2013 Plan, which in turn which have been or will need to be made’. This helps establish
had replaced the Outline Plan of Work 2007, and the expanded exactly what team the architect will be working with, even if not
version entitled Plan of Work Multi-Disciplinary Services by all appointments have yet been made. Fees and services (sections
Roland Phillips published in 2008. The 2020 Plan of Work F–H) relate to the services selected in the Schedule of Services,
stages are as follows: and are dealt with below. Payment (section I) requires the parties
to indicate whether payment notices will be issued monthly, at
the end of each stage, in accordance with an agreed draw down
Plan of Work stages: schedule, or another agreed method.
0 Strategic Definition; Under dispute resolution, (section K), the Details refer to
1 Preparation and Briefing;
mediation and to adjudication (noting it is a statutory right), and
2 Concept Design;
require the parties to select either arbitration or litigation as the
3 Spatial Coordination;
final dispute resolution process. Section L relates to electronic
4 Technical Design;
5 Manufacturing and Construction;
information formats and allows for identifying a BIM Protocol,
6 Handover; or specifying particular software to be used. Supplementary
7 Use. Agreements (section M) allows for the identification of any
forms of collateral warranty that may be required (e.g. to a
Speculative work and tendering for architects’ services 313

funder, purchaser, or tenant) and for a novation agreement and construed as imposing on the architect any greater duty …’ In
related warranty. In all cases there is reference to CIC standard practice, a higher or strict standard is sometimes set out in other
forms, or to alternative terms that, if used, must be attached to documents, such as a project brief, and this should help to avoid
the PSC as an appendix. the architect being held liable to this higher standard (contrary
to the result in cases such as Costain v Charles Haswell &
5.11 The Schedule of Services is split into four sections: Role Partners [2009], where engineers were held to be strictly liable
Specifications, The Services, and Other Services and Additional for their design).
Services. These are of considerable importance and merit careful
study. The Role Specifications lists the roles that the architect 5.15 As in previous versions, the RIBA PSCs offer a great deal
could undertake, and entries are required to indicate which will of protection to the architect in terms of obligation to pay fees,
be performed on the project in question, and over what work protection of copyright, and limitations on nature and extent of
stages. Roles listed comprise architect/consultant, lead designer, liability (most of these provisions are largely unchanged since
project lead, and contract administrator. There is also a place to earlier editions). However, of note is a re-drafting of the net
enter other specialist roles (which might be, e.g., project man- contribution clauses (e.g. RIBA Standard PSC cl 7.3) and the re-
ager, planning consultant, or BIM coordinator). This helps to introduction of a net contribution clause in the RIBA Domestic
ensure that a clear decision is made as to whether the architect PSC. This was removed following a judgement which had sug-
will perform these roles, and if not, that the client may need to gested it could be unfair for consumer clients, but subsequent
consider further appointments. case law has removed this constraint.
The Services schedule sets out in more detail the tasks the One of the most significant changes to the RIBA Standard
architect will perform under these roles at each Work Stage, and PSC is the introduction of provisions covering novation (cl.
for the Basic Fee. Some tasks are pre-specified (but must be 4.6–4.9, note these are only in the Standard version). These are
selected to apply), but there is provision for adding others under to cover situations where an architect transfers from the original
each role at each Stage. The Other Services allows for adding client to a new client. Although this is normally to a contrac-
further services (for example, inspections or an accessibility tor in a design build context, it could also apply if transferred
audit). If any of these may be required, this must be indicated, to a different client, e.g. a new developer. The clauses would
including the basis for charging fees (i.e. included in the Basic be relevant whether the novation was anticipated at the time
Fee, or on a time-charge or lump sum basis). of appointment or arose later. Clause 4.8 makes it clear that
there is no obligation to accept the novation, but should it go
5.12 Under section F of the Contact Details, the parties enter ahead, the contract sets out the terms of the novation agreement.
the agreed method for calculating the Basic Fee for the services These reflect exactly the terms of the CIC Novation Agreement:
described in Schedule of Services for each work stage. The Ab Initio 2018, to which the PSC refers (it also refers to the
suggested methods are specified percentage of Construction CIC matching warranty, CIC Collateral Warranty: Consultant-
Cost, fixed lump sum, time charge, and design cost per square Employer 2018).
metre (gross or net), but any other agreed method can be used.
Section F now allows for limiting the number of meetings and 5.16 Sometimes, when using an RIBA PSC, potential clients
site inspections that are included in this Basic Fee. Time charges wish to impose their own particular conditions, but the impli-
for additional fees can be entered in Section F. cations of any non-standard conditions need to be carefully
Prospective clients frequently require an estimate of the assessed. If a substantial extension to the liability or duties of
anticipated total fees likely to be involved in projects. This is the architect is likely to be incurred, appropriate additional reim-
understandable, but care is needed; difficulties often arise where bursement should be negotiated. Extensions of liability outside
fees have been forecast on the basis of a premature estimate of those of an existing professional indemnity policy should be dis-
the likely total cost of the building work. If an estimate is made, cussed with the architect’s broker or insurers before acceptance.
it is essential that the client is properly briefed on the nature of In the case of public bodies and others requiring the architect
the estimate and its limitations. Similarly, difficulties can arise to undertake to maintain professional indemnity insurance for
when a forecast of the likely duration of work is offered in the six years following completion of the works, the architect must
case of work to be charged on a time basis. insist that the undertaking is subject to the reasonable availabil-
ity of insurance cover.
5.13 Where it is very difficult to assess the scope and extent of
services required, it may be necessary to set up an appointment
to cover the feasibility and preliminary stages of the project only, 6 Speculative work and tendering
while the project brief is developed. This should, nevertheless,
be a formal arrangement, albeit for a limited scope of services. for architects’ services
5.14 At the heart of the RIBA PSCs sit the ‘Clauses’. The core 6.01 The emergence of speculative work and competitive fee
obligation is set out in clause 3.1 (all versions of the PSC), tendering has had a profound effect on the procedures of archi-
which begins: tects’ negotiations with their clients and, to some extent, their
relationships with clients. Competitive fee-tendering is common-
In the performance of the Services and discharging all the place, with official and quasi-official bodies obliged to obtain
obligations under the Contract, the Architect/Consultant competitive tenders for substantial projects, and with private
will exercise the reasonable skill, care and diligence to be clients becoming more aware of the possibilities of competitive
expected of an Architect/Consultant experienced in the provi- fee-tendering.
sion of such services for projects of a similar size, nature and
complexity to the Project … 6.02 The extent to which an architect is prepared to undertake
speculative work must depend upon many factors, such as the
The reference to ‘experienced’ was included for the first time policy of the practice, the architect’s knowledge of the potential
in the 2018 editions, to bring in the line with industry expecta- client, the nature of the proposed project, the likelihood of its
tions; not only is it what most clients expect to see, it is used success, the architect’s existing commitments, the capacity of the
in the standard terms of other professions (e.g. the new RICS office now and in the foreseeable future, the possible income and
PSCs). This is standard wording and should be acceptable to all profit from the commission if it proceeds, the extent of competi-
PI insurers. tion for the work and so on. But regardless of these conditions
More importantly, and very much to the benefit of the archi- and the fact that the architect may not be paid initially, it is
tect, is the introduction of a new ‘governing clause’, stating important (and a requirement of the Codes of Conduct) that
‘nothing contained in this as agreement or elsewhere shall be there should be a formal agreement between the architect and
314 Architects’ contracts with clients

the client defining the extent of the service to be provided by in the Act, but payment arrangements and other matters have to
the architect and the commitment of the client to the architect in be agreed between the consultant and the parties involved; if
the event of the project proceeding. In the event of the project the parties cannot agree on the appointment, the local authority
proceeding, it is usual for the architect to be reimbursed for the will make the appointment, unless the local authority is a party
initial work undertaken at risk. in the dispute in which case the Secretary of State will make
The cost of speculative work undertaken at risk by an archi- the appointment. There is no RIBA standard form to cover such
tect may be substantial, and it is important that the practice appointments, which should not be dealt with under, for exam-
should budget for non-fee-earning speculative work, as part of ple, RIBA Standard PSC 2020, but should form a separate writ-
its overheads, fixing a limit to the amount it does, and maintain- ten agreement. Advising the client regarding Party Wall Matters
ing strict record of time and costs. Where teams of design and (as opposed to the independent statutory function) is, however,
other consultants are involved in joint submissions on a specula- covered, as under Other Services in the Standard Agreement.
tive basis, it is becoming usual for the costs to be shared.
7.04 A key statutory duty is that of the adjudicator under the
6.03 Architects should be particularly wary of invitations to pre- Housing Grants, Construction and Regeneration Act 1996, acting
pare design solutions in conjunction with competitive fee tenders, in the resolution of differences or disputes between the parties
often on the basis of scant information – only rarely would such to a construction contract. The adjudicator is allowed consider-
an invitation be acceptable. Architects should also endeavour to able flexibility within the time scales of the Act in the carrying
discover details of others invited to submit fee tenders and refuse out of duties, but generally, adjudicator appointment agreements
to participate in competitive fee bidding, in which the number of are tending to follow those of conventional appointments for
tenderers or the form of competition is unreasonable. arbitrators. Payment is usually on a time basis, and it is now
As the range of possible sources of design and procurement usual for the parties to agree an appropriate rate at the time
routes widens, it is understandable that clients should increas- of appointment. Various institutions publish standard terms of
ingly make detailed enquiries about services and charges before agreement for appointment of an adjudicator, for example the
making formal appointments. The basis of comparison is often JCT and the CIC.
inadequate; architects should endeavour to ensure that clients
fully appreciate the nature of the service being offered and do
not make appointments on the basis of fee alone. Potential cli- 8 Scottish appointments*
ents are often unaware of fundamental differences between, say,
conventional design services and design by a contractor’s organi- 8.01 The Royal Incorporation of Architects in Scotland (‘the
sation; more subtle differences in design services are certain to RISA’) recommends the use of a standard form agreement such
elude them unless they are carefully explained by the architect. as the Scottish Conditions of Appointment for an Architect
The fee is determined by the service required and the cost of [SCA/2018], in the interests of both the client and the architect
providing that service; unless this is known, a fee quotation can for all types of project. The form helps ensure that the key
be little more than a guess. aspects of the service to be provided and the responsibilities of
each party are agreed at the beginning of a project, while allow-
6.04 Dissatisfaction with the approach of some large commercial ing the agreement to be tailored to meet the specific require-
organisations seeking competitive fee bids led to the prepara- ments of each appointment.
tion and publication of the RIBA-CIC Guidance for Clients
to Quality Based Selection in 1998 and the more recent CIC 8.02 The law regarding execution of documents in Scotland
Selecting The Team in 2005. Guidance can also be found in differs greatly from England. In Scotland, the starting point
Selection of Consultants: FIDIC Guidelines for the Selection of is the Requirement of Writing (Scotland) Act 1995. Under the
Consultants (2019). 1995 Act, all that is required for valid execution is that the
document is subscribed by or on behalf of the granter. If there is
more than one granter or party, the document must be subscribed
7 Appointments required by statute by each granter or party. A document is subscribed by a party
if it is signed by them. Individuals should sign their full name.
7.01 On occasion, the architect may be engaged to carry out Execution by a company requires signature by one director, the
duties required by statute; these duties may be specified in company secretary, or another authorised signatory.
detail as part of the schedule of services, or reference may be The document should be signed on the last page of the docu-
made to the relevant statute. It has to be recognised by both the ment containing an operative clause, as opposed to any schedule
client and the architect that statutory duties are non-negotiable; or annex. Alterations made to a document before it is subscribed
if, for any reason, the architect cannot or is not allowed to com- should be initialled, and in respect of alterations made after a
ply with the requirements of the legislation, the architect must document has been subscribed, the best practice is for a separate
withdraw, advising the client of the reasons for the termination instrument of alteration to be prepared, which is then subscribed
of the appointment. by all the grantors of the original document.
7.02 An appointment as a Construction (Design and The Legal Writings (Counterparts and Delivery) (Scotland)
Management) Regulations 2015 Principal Designer under the Act 2015 allows parties to a document to sign it in counterpart,
Health and Safety at Work etc. Act 1974 is probably the statu- i.e. a document can be executed in two or more duplicate inter-
tory appointment most frequently encountered. The duties are changeable parts where no individual part is subscribed by both
specified in detail in the regulations, but payment arrange- or all the parties. No formal counterpart clause is required. The
ments and other matters have to be agreed between the parties. document becomes effective if the signed counterpart is deliv-
This appointment can be dealt with using the RIBA Principal ered by each party to the other party or parties.
Designer PSC 2020.
8.03 Forms of appointment and advice are available from the
7.03 An appointment as a Surveyor under the Party Wall etc. RIAS Bookshop at 15 Rutland Square, Edinburgh EH1 2BE; Tel:
Act 1996 is concerned with the carrying out of duties as speci- 0131 229 7545; e-mail: bookshop@rias.org.uk.
fied in a disinterested and impartial manner, regardless of the
concerns of the parties. Again, the duties are specified in detail *
This section was written by William Frain-Bell, Advocate.
31
Architects’ collateral warranties
MATTHEW COCKLIN

1 Architects and collateral 2.03 The relevant provision must define the persons to whom
collateral warranties are to be given. This is where the first
warranties difficulties in negotiation usually arise. In order to maintain
maximum flexibility, the client will usually require collateral
1.01 Architects are likely to encounter collateral warranties warranties in favour of:
in two circumstances. First, as considered in Chapter 21, they
may be expected to advise their clients (the employer under the (a) any person providing finance;
building contract) on collateral warranties to be given by con- (b) any future purchaser of the project, or, where the project is
tractors and sub-contractors either to the employer or to funders, capable of being divided into separate investment units, of
purchasers, or tenants. Second, they themselves may be asked any part of the project;
to provide collateral warranties. This chapter is concerned with (c) any tenant of the project or of any part of the project;
the second of these circumstances and looks in more detail at (d) if the nature of the profit-sharing or other arrangements for
the forms of collateral warranties that an architect is likely to the project requires it, freeholders or borough councils or
encounter. other third parties who may incur a loss if the project is
negligently designed or constructed.
1.02 The second editions of the CIC/ConsWa/F (Collateral
Warranty Consultant – Funder) and CIC/ConsWa/P&T (Collateral Architects should not accept these open-ended provisions, which
Warranty Consultant – Purchaser/Tenant), published in 2018 by raise the prospect of their being required to enter into collateral
the Construction Industry Council (‘CIC’), will be used as a warranties with, say, 60 shop tenants in a shopping centre or
basis for explaining the usual terms of collateral warranties. tenants of kiosks in the lobby of a major office development. It
is appropriate that both parties look sensibly at the nature of the
2 The obligation to provide project and arrive at an equitable solution – perhaps to give col-
lateral warranties to tenants of the anchor stores only in a shop-
collateral warranties/ ping centre, or tenants who take more than a certain amount of
third party rights lettable area in the case of a multi-tenanted office development.

2.01 There is no general legal duty on anyone to agree the 2.04 There is much debate about the enforceability of a simple
terms of or to enter into a collateral warranty or provide third obligation to enter into a collateral warranty. Will the courts
party rights in favour of a third party. If collateral warranties/ order specific performance of an obligation to enter into an
third party rights are required, then the employer would be well agreement by making the architect sign it, or will they suggest
advised to ensure that there is a binding obligation imposed by that damages for breach of the contractual obligation undertaken
the terms of his consultancy agreement with the architect to by the architect is an adequate remedy for the client, so that the
grant collateral warranties/third party rights. client must show that he has suffered a loss (presumably the loss
of a funder, purchaser or tenant) because the architect has failed
2.02 In practice, architects will be presented with bespoke con- to comply with its contract? The latter is most widely held, but
sultancy agreements which endeavour to protect the client by opinions differ. In any event, applying to the courts, with all the
imposing specific obligations on the architect in relation to the costs and delays that entails, is not a satisfactory position for a
provision of collateral warranties or third party rights. What the client who has a tenant waiting to sign a lease with the client,
client needs to include, where it is anticipated that there may be provided a collateral warranty is forthcoming from the archi-
a need to call for collateral warranties, is a clause requiring the tect. It is for this reason that powers of attorney are frequently
architect to give collateral warranties to expressly identified par- inserted by clients in tailor-made consultancy agreements in
ties in accordance with a stipulated form of collateral warranty, addition to the basic obligation to provide the collateral war-
which should be attached to the consultancy agreement. If no ranty. The power of attorney authorises the client to execute the
form is stipulated and attached, the obligation is merely to enter collateral warranty on behalf of the architect if the architect, in
into a form as agreed between the parties. The clause will then breach of the contractual obligations, fails to execute it directly.
simply amount to an ‘agreement to agree’ and will be unenforce- Architects usually, and perhaps understandably, object to these
able by the client if the architect simply refuses to agree a draft. provisions, and yet they do no more than give the client rights

315
316 Architects’ collateral warranties

to enforce an obligation in circumstances where the architect is a collateral warranty to a tenant, these would probably include
in breach of contract. cost of repair of defects caused by the architect’s negligence,
additional professional fees, loss of profit, potentially business
2.05 The use of the Contracts (Rights of Third Parties) Act interruption, and the like.
1999 to obviate the need to sign a multitude of separate collat-
eral warranty documents is discussed in Chapter 21. The Act will 3.05 Losses other than the cost of repair should be excluded,
not, of course, prevent debates about the potential beneficiaries as the final sentence states. However, this is a position which
of third party rights. Nor will the Act obviate the need for debate architects may find difficult to sustain, in practice, when
about the terms of the third party rights to be granted. Therefore, under pressure from their clients. Clients, purchasers, and ten-
the issues discussed below will still arise. The Act does, how- ants argue that designers and builders can anticipate the sort
ever, provide a much simpler mechanism for the delivery of third of business losses likely to be suffered, and that liability for
party rights, thereby reducing the paper chase which exists with such losses would arise if they had contracted with the owner/
collateral warranties. It also avoids arguments about the need occupier in the usual way. Why should the architect escape this
for powers of attorney. liability simply because the architect is working for a developer
who is unlikely ever to go into occupation of the building?
Accordingly, purchasers and tenants in particular would pre-
3 The terms of collateral fer to delete Clause 2(a) in its entirety. To do so would leave
warranties: CIC/ConsWa/P&T architects completely exposed to potential open-ended liability
under the collateral warranty.
Clause 1: the warranty
Clause 2(b): contribution
The Consultant confirms to the Purchaser/Tenant that it has
exercised and will continue to exercise reasonable skill care Without prejudice to any other exclusion or limitation of lia-
and diligence in the performance of its services to the Client bility, damages, loss, expense or costs the Consultant’s liabil-
under the Appointment. ity for such costs of the repair, renewal and/or reinstatement
in question shall be further limited to that proportion thereof
3.01 Architects generally warrant that they will exercise reason- as it would be just and equitable to require the Consultant to
able skill and care in the performance of their duties. Part II of pay having regard to the extent of the Consultant’s responsi-
the Supply of Goods and Services Act 1982 reflects this basic bility for the same and on the assumptions that:
implied term. All the standard terms of engagement published
by the relevant professional bodies provide for this or something (i) all other consultants and advisers, the Contractor and all
similar. Architects do not ‘guarantee’ results; they do not war- sub-contractors involved in the Development have pro-
rant that the results of their labours will be a building which is vided contractual undertakings on terms no less onerous
‘suitable’, or which will comply with any particular performance than those set out in clause 1 to the Purchaser/Tenant in
specification or requirement. Hence, this basic warranty of rea- respect of the carrying out of their obligations in con-
sonable skill care and diligence. nection with the Development; and
(ii) there are no exclusions of or limitations of liability nor
3.02 Arguably, if, under the terms of the consultancy agreement, joint insurance or co-insurance provisions between the
the architect has assumed a higher duty of care (for example, Purchaser/Tenant and any other party referred to in this
‘the skill, care and diligence reasonably to be expected of a clause 2(b) and any such other party who is responsible
properly qualified and competent architect experienced in the to any extent for such costs is contractually liable to the
provision of like services for projects of a similar size, scope Purchaser/Tenant for the same; and
and complexity to the Project’), then this duty of care might be (iii) all the parties referred to in this clause 2(b) have paid
reflected in the collateral warranty. to the Purchaser/Tenant such proportion of such costs
which it would be just and equitable for them to pay
3.03 It should also be noted that the warranty relates to the having regard to the extent of their responsibility for
‘services’ under the consultancy agreement. If, for example, the the same.
architect has been engaged to provide design services only and
3.06 This drafting, which refers to ‘all other consultants and
not inspection services, this formulation will apply the collateral
advisors, the Contractor and all sub-contractors’, is very wide
warranty to the design services only. It is imperative, therefore,
in relation to the potential parties from whom contribution can
that any beneficiary of a collateral warranty also checks pre-
be assessed. Not all of these parties will also give collateral
cisely the definition of services under the consultancy agreement
warranties to any purchaser or tenant.
to ascertain the scope of the warranty.
3.07 The Civil Liability (Contribution) Act 1978 deals with
Clause 2(a): the exclusion of contribution between people liable in respect of any damage in
economic and consequential loss tort, for breach of contract, or otherwise. Under the provisions
of the Act, where two or more people have contributed to the
the Consultant shall be liable for the reasonable costs of same loss as a result of separately being in breach of contract,
repair, renewal and/or reinstatement of any part or parts of if one of them is sued for that loss, they can claim contribution
the Development which has or have suffered damage as a from the others. Obviously, this right of contribution will be
result of such breach to the extent that the Purchaser/Tenant much more difficult if, say, the architect has given a collateral
reasonably incurs such costs and/or the Purchaser/Tenant is or warranty, but the contractor, who may have contributed to the
becomes liable either directly or by way of financial contribu- loss, has not. Equally, if both the architect and the contractor
tion for such costs. The Consultant shall not be liable for other have given collateral warranties, but the contractor is insolvent
losses incurred by the Purchaser/Tenant. so that there is no recovery from it, then the architect is left with
the full extent of the liability.
3.04 If this limitation on the basic warranty did not appear,
then the architect would be liable to the Purchaser/Tenant for 3.08 The effect of Clause 2(b) is to try to ensure that, if there is
damages for breach of contract assessed in accordance with the a latent defect in the building, and the Purchaser/Tenant wishes
usual rules. Broadly, contractual damages cover losses which to sue, any recovery against, say, the architect is assessed on the
are reasonably foreseeable at the date the contract was entered assumption that the architect is only liable for its ‘share’ of the
into as likely to arise as a result of the breach. In the case of contribution to the loss, even if the Purchaser/Tenant is unable
The terms of collateral warranties: CIC/ConsWa/P&T 317

to recover from the contractor, who may have also contributed to the collateral warranty, when it comes to enforce them, are not
the loss, either because the contractor has not given a collateral worth anything.
warranty at all or, having done so, is insolvent, and so cannot
meet its share.
Clause 3: independent enquiry
3.09 Such clauses, when they first appeared, were resisted by The obligations of the Consultant under or pursuant to this
purchasers and tenants who find it difficult to accept that they Agreement shall not be released or diminished by the appoint-
may be able to recover only 10% of their loss because of the ment of any person by the Purchaser/Tenant to carry out any
contribution clause, notwithstanding negligence by, say, the independent enquiry into any relevant matter.
architect and breach of contract by the contractor. There is now
an acceptance that in the context of the voluntary assumption of 3.14 This provision is designed to prevent a contribution claim
contractual responsibility inherent in the giving of a collateral by the architect arising from the involvement of an independent
warranty, the principles of ‘joint and several liability’ under surveyor or even an in-house surveyor by the Purchaser/Tenant.
English law can operate unfairly, particularly in circumstances In other words, as between the architect and the Purchaser/
where one party’s contribution to the loss is significantly more Tenant, the architect cannot argue that it is liable for less than the
than another party’s contribution, but the first party cannot meet full amount of the damage suffered by the Purchaser/Tenant. The
its share of responsibility. architect is not, however, precluded from recovering a contribu-
tion from the independent surveyor employed by the Purchaser/
3.10 There are, though, doubts as to the enforceability of Tenant if that surveyor has also been negligent.
the ‘contribution clause’. In particular, there are elements of
uncertainty in terms of the assumed nature and extent of the
contractual undertakings which have been given by the other
Clause 5: deleterious materials
parties. In addition, there may be public policy issues involved The Consultant has exercised and will continue to exercise
in asking the courts to determine the potential liability by way reasonable skill, care and diligence to see that, unless author-
of contribution of a party which is not involved in the proceed- ised by the Client in writing or, where such authorisation is
ings, is not represented, and does not have an opportunity to given orally, confirmed by the Consultant to the Client in
defend itself. writing, materials specified by it for use in the Development
are in accordance with the guidelines contained in the British
Council for Offices edition of the publication Good Practice
Clause 2(c): defences of liability in Selection of Construction Materials current at the date of
The Consultant shall be entitled in any action or proceedings its specification.
by the Purchaser/Tenant to rely on any limitation or exclu-
sion in the Appointment and to raise the equivalent rights in 3.15 The architect warrants that it has exercised reasonable
defence of liability as it would have had against the Client skill and care to see that materials are specified in accordance
under the Appointment. with the Guidelines contained in the addition of the publication
Good Practice in Selection of Construction Materials (Ove Arup
3.11 The purpose of this provision is to ensure that if, for exam- & Partners) current at the date of specification. This provision
ple, the consultancy agreement contains a limitation on the archi- avoids lengthy lists of materials, which used to characterise con-
tect’s liability for negligence, that limitation is also imported sultancy agreements and collateral warranties. These provisions
into the collateral warranty and, hence, into the architect’s may be expanded by more sophisticated clients to include refer-
relationship with the Purchaser/Tenant. If it were not included, ence to their standard environmental policies. The CIC advises
then there would be a strong argument that the Purchaser/Tenant in a guidance note that the consultant should ensure that that this
could sue the architect for an unlimited amount and, potentially, provision is consistent with the deleterious materials provision
more than could be recovered from him under the consultancy in the underlying appointment.
agreement.
Clause 7: copyright
3.12 This provision allows the architect to argue, for example,
that limitation periods for breach of the consultancy agree- 3.16 This provision obliges the architect to give the Purchaser/
ment have expired and, therefore, there can be no claim by the Tenant a wide-ranging licence to copy and use those documents
Purchaser/Tenant under the collateral warranty. The provision prepared by or on behalf of the architect for any purpose related
reinforces, should reinforcement be needed, the necessity that to the premises – that is, those parts of the development which
purchasers and tenants consider the terms of the consultancy the Purchaser/Tenant has purchased or leased. The licence
agreement in order to determine the full extent of their rights extends to the copying and use of documents for an extension
under the collateral warranty. Similarly, if, for example, the but not a right to reproduce the design for an extension. It should
architect’s client requires a design detail to be produced in a also be noted that this provision refers to the licence being con-
certain way, perhaps against the advice of the architect, the ditional upon the architect having received payment of any fees
architect will have a defence to any claim brought by the cli- properly due and owing as at the date of exercise by the licence.
ent. That defence will also be available, because of Clause 2(c), In other words, the architect can argue, in circumstances where
to the architect in any claim brought by the Purchaser/Tenant. entitlement is disputed under the consultancy agreement, that no
Other ‘rights in defence of liability’ could arise through waivers, copyright licence arises.
estoppels, and so on.
3.17 The CIC has marked the provision: ‘Delete clause if
3.13 In order to close the loop, a well-advised Purchaser/Tenant Consultant does not retain copyright/amend as appropriate
would ensure that it had included, in its agreement with the according to the terms of the Appointment’. Therefore, if under
client, provisions prohibiting the client waiving, releasing or the terms of the appointment, the client (or anyone else) has
otherwise interfering with the architect in the performance of the copyright in the documents, the clause will need to reflect this.
architect’s duties, so as to give rise to a ‘defence of liability’.
Although not watertight (since the circumstances in which the Clause 8: professional
Purchaser/Tenant is likely to sue the architect are circumstances
where the developer is insolvent or cannot meet the liability), indemnity insurance
this does, at least, provide some protection to the Purchaser/ 3.18 While architects should check that their professional indem-
Tenant who, hopefully, will not then find that its rights under nity insurance corresponds with the obligation set out in the
318 Architects’ collateral warranties

collateral warranty at the date it is executed, this obligation is, 3.23 The CIC’s guidance notes recommend that, under English
after that, largely of academic interest because: law, periods not exceeding 6 years should be inserted for con-
sultancy agreements under hand and 12 years if the consultancy
(a) the obligation is probably too uncertain to be enforceable agreement is executed as a deed. It is important that such
since it is qualified by the proviso ‘provided that such insur- periods are accurately inserted to ensure that the collateral war-
ance is available at commercially reasonable rates’; and ranty does not potentially extent the limitation period under the
(b) there is no effective sanction for a breach by the architect of appointment.
the obligation to maintain professional indemnity insurance.
3.24 Even if such periods are included, there is a risk that Clause
12 will prevent claims being made against the architect by the
Clause 9: assignment Purchasers/Tenant in circumstances where the client still has a
3.19 The collateral warranty provides for two assignments to valid claim against the architect for breach of the consultancy
persons taking an assignment of the interest of the Purchaser/ agreement, and relevant limitation periods under the consultancy
Tenant. Ownership of premises does not change frequently, nor agreement have not expired. This is because, where practical
are leases often assigned, so this should meet the requirements completion is achieved, the limitation period in the collateral
of most purchasers or tenants, although the assignment will not warranty runs from the date of practical completion. Therefore,
be valid if the properly is divided up which may be a problem. if an act of negligence is committed by the architect after the
date of practical completion:
3.20 It should be remembered that an assignment does not cre-
ate new rights. It extinguishes the assignor’s rights and, from (a) during the defects liability period; or
the date of the assignment, gives the assignee the rights which (b) after the defects liability period has expired (for example,
the assignor would otherwise have had. It does not mean that if negligent advice is given by the architect in relation to a
the assignee’s limitation period starts again following an assign- defect);
ment of the collateral warranty. Similarly, it does not mean that
the assignee can recover damages which would not have been then Clause 12 may bar a claim under the collateral warranty
recoverable by the assignor. even though limitation periods may still open under the consul-
tancy agreement.
3.21 Equally, from the perspective of the Purchaser/Tenant:

(a) if the architect has agreed to provide a collateral warranty 4 The terms of collateral
in the first place, because it is thought that the size of the
interest which the Purchaser/Tenant is taking in the develop-
warranties: CIC/ConsWa/F
ment warrants this degree of protection; and
4.01 This collateral warranty contains, at Clauses 7, 8, and 9,
(b) if that Purchaser/Tenant parts with its interest after occupy-
provisions conferring ‘step-in rights’ on the funders. This entitles
ing the building for, say, two years;
the funder to ‘take over’ the appointment and to receive prior
notice of termination of the appointment by the architect. Such
then any new purchaser or tenant will still have losses if there
rights are of limited application and should only be included
are latent defects in the building caused by the architect’s neg-
where they are properly covered under agreements between
ligence. If a new purchaser/tenant does not have the benefit of
developers and their funders. The clauses warrant careful
the collateral warranty, then it may have no redress whatsoever
analysis.
in respect of those losses.
4.02 Such ‘step-in rights’ can only appear as drafted in one
Clause 10: payment collateral warranty on each project. If they are given to two or
more different parties, the architect may find itself in an impos-
The Consultant acknowledges that it has received all fees and
sible position and may receive notices from two or more parties
expenses properly due and owing it under the Appointment up
requiring the architect to contract with them. If step-in rights
to the date of this Agreement.
are to be given to more than one party, priority clauses must
be included.
3.22 The CIC has marked the provision: ‘Delete clause if not
appropriate’. The presence of this provision in the collateral
warranty is curious. Given that a properly drafted consultancy Clause 7
agreement from the client’s perspective would oblige the archi-
tect to enter into the collateral warranty when requested, it can 4.03 The funder is entitled to serve notice on the architect
only work against the architect who will also be obliged to give upon termination of the finance agreement. In order to avoid an
this acknowledgement even in circumstances where the basic argument by the developer that the architect is in breach of his
statement is untrue. The truth is that the relationship between the obligations under the appointment, it is important in such cir-
client and architect is governed by the consultancy agreement cumstances to ensure that the developer acknowledges that the
and not by the collateral warranty, which should not interfere architect is entitled to rely on notice given by the funder and,
in these issues. hence, the fact that the developer is a party to CIC/ConsWa/F,
even though it derives no benefit under it.

Clause 12: limitation


Clause 8
No action or proceedings whether in contract or in tort or in
delict or in negligence or for breach of statutory duty or oth- 4.04 The architect is required to give notice to the funder before
erwise) [sic] shall be commenced against the Consultant after terminating the appointment for breach by the developer. Again,
the expiry of … years from the date of practical completion it entitles the funder to serve notice on the architect requiring
of the relevant part of the Development under the Building the architect to act for the funder in such circumstances. The
Contract or, in the event that practical completion is not developer should ensure in these circumstances that it has proper
achieved, the date that the Consultant finishes its services for protection under the terms of its agreement with the funder
the Client under the Appointment. against improper service of notice by the funder.
Practical advice 319

Clause 9 numbers which may be given and the terms which are insured.
Therefore, an architect being asked to sign:
4.05 This requires the funder to accept liability for fees payable to
the architect, including fees outstanding at the date of service of any
(a) a consultancy agreement which contains an obligation to
notice. This clause sometimes causes difficulties with funders but,
provide collateral warranties in a stipulated form; or
of course, if a funder does not agree to meet outstanding fees, the
(b) the collateral warranty itself;
architect will simply serve further notice on the funder in respect
of breach of payment obligations under appointment. Clause 9 also
must clarify with its insurers their precise policy in relation to
provides that, if the funder nominates someone else to take over
the issue of these documents. If there is no special endorse-
the appointment – perhaps, for example, another developer – it,
ment, insurers should be questioned carefully about their
the funder, will act as guarantor for the fees; in other words, the
position to ensure that, by entering into express contractual
architect will not find itself in contract with a ‘man of straw’.
commitments with third parties, the architect is not allowing
insurers to avoid liability or is not activating one of the policy
5 Practical advice exclusions.
It is prudent to have all warranties which contain any depar-
5.01 Most professional indemnity insurance policies will contain ture from forms accepted by insurers agreed with insurers.
a specific endorsement about collateral warranties stipulating the
32
Architects’ responsibility for the work of others
BART KAVANAGH AND CHRISTOPHER MIERS

1 Introduction ● Design services;


● Technical design services;
1.01 Claims against architects often arise in relation to the ● Assistance and advice in connection with the selection of
design by others of specialist items or the level of inspection contractor;
where workmanship is found to be defective. This chapter looks ● Contract administration services;
at the potential sources of such claims, i.e. those to whom an ● Site visits;
architect might owe a duty; identifies areas of work for which, it ● Certification of the value of work carried out by the
may be claimed, the architect is responsible, despite not having contractor;
carried out the work itself; and sets out some practical steps that ● Certification of Practical Completion of the works.
may be taken to minimise the risk of spurious claims.
2.06 Ideally, the appointment agreement should identify posi-
tive undertakings, and also set out any agreed limitations to the
2 To whom does an services. In particular, many of the problems that arise between
architect owe a duty? architects and their clients relate to misunderstandings between
the parties with respect to:
2.01 Duties or obligations to others fall into two categories:
those that are generated by agreement between two or more par- (i) The scope of the technical design that the architect will
ties (see Chapter 2) and those that are owed under the common undertake. For example, in private domestic work, an archi-
law of negligence (see Chapter 3). The former is referred to as tect will often rely upon the contractor’s sub-contractors to
a contractual duty, and the latter is known as a duty in tort or design such things as the plumbing and electrical installa-
a duty of care. tions. In larger commercial projects, the detailed technical
design of major components, such as curtain and wall
2.02 Contractual obligations and duties of care in tort may facades, may be undertaken by a specialist sub-contractor.
also exist side by side. These are referred to as concurrent The limits of the design responsibility of the architect
obligations. and specialist should be made clear in the appointment.
Otherwise, a client may expect the architect to design spe-
cialist elements himself;
Employer (ii) The scope of Contract Administration duties;
2.03 Typically, the main agreement that concerns an architect is (iii) Scope of any project management duties undertaken;
his or her appointment with the Client (see, further, Chapter 30). (iv) Scope of site inspections, especially where contract
This may be the Employer, who has commissioned the project, administration or project management services have been
or it may be the Contractor, who has taken on design and build undertaken.
responsibilities and needs design consultants to enable it to fulfil
its obligations.
Contractor
2.04 In design and build (D&B) procurement, the appointment 2.07 In a traditionally procured project, an architect will gener-
of the architect may be with both: initially, an agreement with ally not have any contractual relationship with the contractor.
the Employer to prepare the Employer’s Requirements; and The parties to a construction contract are the employer and the
then being transferred to the Contractor in order to complete the contractor, and the contract imposes duties only upon those
design and produce construction information. parties. More importantly, because of the concept of privity of
contract, if either the contractor or the employer suffers a loss
2.05 The appointment agreement is a formal contract between because of a breach of a condition of the construction contract,
the employer and the architect. It sets out the obligations that any claim for compensation may only be made against the other
each party has undertaken to perform. Under a typical appoint- party to the contract. In other words, the architect will not be
ment agreement, an architect will undertake to provide, amongst directly at risk for any breach of the construction contract.
other things, the following:
2.08 However, where architects are acting as contract adminis-
● Advice to clients; trator, they will be engaged in tasks which require them to act
● The necessary skills and resources for the work; impartially between the parties to the building contract. In these

321
322 Architects’ responsibility for the work of others

circumstances, a dissatisfied Contractor will generally look to Subrogation


the Employer, who may, in turn, pursue the architect.
2.16 Subrogation is a legal doctrine that, in certain circum-
2.09 Where architects are employed by a contractor who is stances, allows a third party to enforce the rights of a party to a
undertaking a design and build contract, then they will have a contract for its own benefit. The main importance of subrogation
direct contractual relationship with the Contractor and may be to an architect is in circumstances where an employer who has
sued for a breach of any of the conditions of the appointment suffered a loss is covered by an insurance policy, which pays out
contract. to compensate him for that loss. If the loss was caused by some
fault of the architect, then the principle of subrogation may allow
the insurer to ‘step into the shoes’ of the employer to pursue the
Third parties architect under its appointment with the employer and seek to
2.10 In addition to the duties and obligations owed under the recover the money that it has paid out.
appointment, the parties may owe duties to others who are
not party to the appointment. These are known as Third Party 2.17 Rights of subrogation are commonly included in insurance
Rights and arise in several ways; most commonly through policies (see, further Chapter 35). This means that an architect
the Contract (Rights of Third Parties) Act 1999, in tort, or by whose actions cause a loss to the employer may ultimately
subrogation. find itself compelled to compensate the insurer for that loss
where the insurer has paid out under an insurance policy. The
rights and obligations under the appointment will apply equally
The Contract (Rights of Third between the architect and the insurer. Therefore, whilst they may
Parties) Act 1999 allow the insurer to seek to recover its loss from the architect,
they will also allow the architect to rely upon any terms in the
2.11 The principle of privity of contract means that a contract appointment that seek to minimise the architect’s liability to the
cannot confer rights or impose obligations on anyone who is not employer.
a party to the contract. The Contract (Rights of Third Parties)
Act 1999, however does allow some, limited, rights to third par-
ties (see, further Chapter 21).
3 Responsibility for the
2.12 It provides that a third party may enforce a term of a con- work of others
tract if the contract expressly provides that they may, or if the
term purports to confer a benefit on them. The third party must 3.01 The architect frequently has a role in respect of the design
be expressly identified in the contract by name, as a member of work being undertaken by others. For example, this may relate to
a class, or as answering a particular description. The third party the role of Lead Designer or Project Lead; or the role of architect
need not be in existence at the time the contract is entered into. commenting on the design work of specialist sub-contractors
engaged by the contractor in a D&B contract. Such other parties
2.13 Currently, the main application of this Act to the appoint- undertaking design will typically include the following:
ment of architects is as an alternative to ancillary contracts such
as collateral warrantees, which architects are routinely asked (i) Employer’s specialist consultants;
to provide. Both can provide contractual rights to subsequent (ii) Architect’s design sub-consultants;
purchasers or tenants of a property, but the incorporation of the (iii) Specialist sub-contractors;
terms of the Act provides the employer with a more streamlined (iv) Specialist suppliers;
method of providing funders and future owners or tenants with (v) The Contractor – workmanship details.
a direct contractual relationship with the architect. It should be
noted, however, that incorporation of the Act does not provide 3.02 In all such arrangements, it is key for the architect to estab-
a third party with the right to adjudication. lish in his written appointment document his role in respect of
any duties relating to the design of others and during the course
of providing the services, to be aware of that role and to take
Duties arising in tort steps to perform the role to the required standard as set out in
2.14 Duties in tort can arise in situations where there is a the contract and using reasonable skill and care.
close association between parties, where one party has special
knowledge or expertise on which the other might rely, and
particularly where there has been an assumption of responsi-
Employer’s specialist consultants
bility, as in Burgess v Lejonvarn [2018] EWHC 3166 (TCC). 3.03 On all but the smallest projects, there is likely to be a need
This may occur even between parties who may not have had for design to be carried out by other design disciplines in addi-
direct interaction. tion to the architect. Structural and building services engineering
will almost always be required, but on larger and more complex
2.15 There are several ways in which an architect may be suf- projects, specialist design consultants may number more than
ficiently closely associated with a third party to give rise to a lia- a dozen.
bility of this sort (see, further, Chapters 3 and 33). For example:
3.04 These consultants will usually be appointed directly by the
Providing an assessment of the development potential of a Employer, and the scope of their responsibilities and the terms
property, which an owner is intending to sell. Potential buyers under which they are to be undertaken will be set out in the con-
who may be given a copy of the assessment and rely on it when tract of appointment between the Employer and the consultant. If
agreeing the purchase price might seek to claim compensation any failure on the part of the consultant constitutes a breach of
if the assessment is flawed because of negligence on the part of that contract, then the Employer will have direct recourse to the
the architect. consultant to recover any losses caused by the breach.

Providing information or reassurances to a neighbour, either 3.05 The scope of services included in the architect’s appoint-
directly or through the employer, regarding the likely impact of ment and those in the appointments of the other design con-
works on the neighbour’s property. If the neighbour relies on sultants must be carefully considered and coordinated. This is
such information to allow work to proceed, which eventually necessary to avoid any gaps or overlaps between the services to
causes damage and loss, then the neighbour might seek com- be provided by different consultants, which may lead to uncer-
pensation from the architect by an action in tort. tainty and confusion about responsibilities in those areas.
Responsibility for the work of others 323

3.06 The architect should be aware that, if its own appointment portion of the works, there is often a lack of clarity regarding
is as lead designer or lead consultant, it is likely to be respon- design responsibility and liability for defects if things go wrong.
sible for the coordination of the designs produced by the other
design consultants into the overall building design. 3.14 In order to ensure that design liability is properly identi-
fied and apportioned, it is essential to select a form of contract
3.07 It sometimes happens that additional areas of design work that is expressly intended to accommodate some design by the
arise during the course of a project. This may result from contractor. There are a number to choose from. JCT SBC 2016,
additional instructions from the Employer; unforeseen site JCT MP 2016, JCT D&B 2016, and NEC4 are among those
conditions; changing circumstances; or the natural develop- suitable for major works, and JCT ICD 2016, JCT MWD 2016,
ment of the design. It is important that responsibility for any ACA Form of Building Agreement 1982 Third Edition 1998
such areas of design is clearly allocated, either to the architect (2003 Revision), and NEC4 (Short Contract) are suitable for a
or to one or more of the other design consultants, at the time range of less complex undertakings. Forms with no option for
that it arises. any design by the contractor, such as CIOB forms, should be
avoided for this purpose.
Architect’s design sub-consultants 3.15 Once a suitable form of contract has been selected, the
3.08 Although additional design or technical consultants will appropriate contract documentation must be put in place. For
usually be appointed directly by the employer, there may be example, JCT SBC 2016 stipulates that Employer’s Requirements
occasions when the employer insists on having a single point of and Contractor’s Proposals must be prepared for the contractor’s
contact with the design team and requires the architect to provide designed portions of the work.
all the additional consultancy services. This is likely to result in
the architect appointing sub-consultants. 3.16 Where a bespoke contract has been developed, or where
standard forms have been amended, it is essential that any terms
3.09 Where this occurs, the architect’s duties to the employer relating to the design liability of the contractor are clear with
will include the duties and obligations related to the sub- regard not only to their intent, but also the formalities that are
consultant’s services. The architect should ensure that the range required to bring them into operation. The parties, and their
and level of duties imposed on the sub-consultant by the sub- agents who will be responsible for administering the contract,
consultancy appointment are compatible with those imposed must be made aware of these formalities and must ensure that
by the architect’s own appointment with the employer, often they are properly observed and carried out.
referred to as being ‘back to back’. This may necessitate seek-
ing legal advice on the compatibility of the standard forms of 3.17 In Walter Lilly v McKay [2012] EWHC 1773 (TCC) it was
appointment issued by the various professional institutes. It may a requirement of the (amended) contract that the Employer must
also necessitate amendments to these standard forms or, in some notify the contractor of any work that was to be the subject of
cases, the drafting of bespoke agreements. Note that the RIBA contractor design. Several areas of work exhibited significant
publishes its Sub-Consultant Professional Services Contract design defects, but no notification had been issued to the con-
2018 to sit alongside the RIBA Standard Professional Services tractor regarding his responsibility for their design. Instead,
Contract 2018. the architect placed reliance on: the wording of specification
clauses; the active participation by specialist sub-contractors
3.10 In order to minimise the risk of disputes, the architect will with the architect in the design of certain elements; references in
need to establish that all its sub-consultants have the necessary sub-contracts to the ‘completion’ of design; and on the produc-
skills, experience, and resources to carry out the work. It is tion by sub-contractors of detail and shop drawings. The judge
important to establish that these will be available over the full decided that these various references did not amount to a clear
period that the project will be carried out. notification and found that the contractor was not responsible
for the design. He said:
3.11 Where an architect enters a sub-consultancy agreement,
it will be liable to the employer not only for any failings in The need for a clear CDP notification should not be consid-
its own performance, but also those of its sub-consultants. ered if one has to try to scrabble around for it in documents
If a sub-consultant fails to perform, then any action brought issued.
by the employer will be brought against the architect, who (Paragraph 203(d))
will need either to join the sub-consultant in the action or
to pursue the sub-consultant in a separate action. If there is 3.18 In addition, it was apparent that the contractor had sought
an arbitration agreement in place between the architect and clarification as to design responsibility and had received no
employer, or in the event of the employer commencing an response. The judge inferred from this that the architect’s lack
adjudication against the architect, it will not be possible to of response amounted to a decision not to provide notification
join the sub-consultant into the immediate proceedings, and that the work was the subject of contractor design.
the architect will have to take separate action against the
sub-consultant to recover any monies that it has to pay to [The architect’s] … ignoring of a series of letters from [the
the employer. contractor] seeking clarification as to design responsibility ...
points strongly by inference to [the architect] taking a con-
3.12 Sub-contracting out parts of the architect’s duties will nor- scious decision not to provide any such notification.
mally require the express agreement of the client. See, for exam- (Paragraph 203(e))
ple the provisions in the RIBA Standard Professional Services
Contract 2018, clause 4.2. 3.19 The decision in Walter Lilly highlights the risks involved
in relying on assumptions about the effect of various elements
of construction documentation, absent the operation of clear
Specialist sub-contractors contractual mechanisms to give them force. It demonstrates
3.13 The liability of specialist sub-contractors for the design of that, in order to be confident that responsibility for specialist
those elements of work which they are contracted to provide is design rests with the appropriate sub-contractor, rather than
often a grey area for contractors, employers, and architects alike. the architect, it is essential to have a contract with an appropri-
In full design and build contracts, the issue is usually considered ate Contractor’s Design Portion (CDP) in place and to ensure
and addressed. Where the contractor has no formal design respon- that its requirements and formalities are properly adhered to.
sibility, however, or undertakes design responsibility only for a Peripheral documents and the actions of others might appear to
324 Architects’ responsibility for the work of others

imply liability, but are unlikely to be construed as doing so by may arise where client expectations exceed what the builder
a court or other tribunal. can reasonably produce within the constraints of the given brief
and budget.
3.20 In addition to the situation described above, many claims
against architects involve misunderstandings in respect of 3.26 Secondly, where construction defects are apparent in the
the architect’s review of specialist sub-contractors’ designs. completed work, or where the client is dissatisfied with the
Typically, review by an architect of drawings developed tech- standard of workmanship achieved, and where the contractor
nically by a specialist sub-contractor will be limited to those is no longer in existence: In this situation, a client may seek to
aspects of the design that fall within the architect’s competence; recover damages from the architect on the grounds that, even
it will not address specialist technical matters. The situation though the defects were caused by the contractor, the architect
where a specialist sub-contractor seeks to pass on responsibility ought to have noticed the defects as they occurred and instructed
for a technical failure in its design, by referring to the review and the contractor to correct them.
‘approval’ of its drawings by the architect, should be avoided
by making the limitations on the scope of any such review clear 3.27 The Architect’s Job Book gives guidance with respect to
both in the architect’s appointment and in the specialist sub- site visits, the associated general principles, the appropriate
contract documents. frequency, and the way in which they should be organised and
structured. A more detailed analysis of what should be provided
3.21 Where an architect has undertaken to comment on specialist and what may be expected is given in The Good Practice Guide:
designs, it would be prudent to enquire of the contractor that he site inspections. In order to avoid, or be able to refute, such
has been provided with all of the design documentation that he claims, an architect must:
is expected to review and comment upon. It should not simply be
assumed that where design documents have not been provided, (i) Have a clear and informed idea about what is the appropri-
the undertaking to comment has fallen away. ate regime of site visits for each project;
(ii) Ensure that this is clearly communicated to the client;
(iii) Ensure that it is clearly set out in the appointment;
Specialist suppliers (iv) Be prepared to vary the regime should changing circum-
3.22 Suppliers of specialist products often make specific claims stances require it;
or assertions about the capabilities and performance of those (v) Ensure that the appropriate regime is effectively carried out.
products. Frequently, these assertions relate to technical param-
eters that would be beyond the ordinary competence of an 3.28 The role of the architect in respect of visits to the construc-
architect to assess. tion site and any inspection of the works must be set out clearly
in the architect’s appointment agreement, including in respect
3.23 Whilst, in matters that fall outside their technical com- of limitations or exclusions. This applies to contracts with the
petence, it may be reasonable for an architect to rely on the client, and to contracts where a contractor engages an architect
specialist design skills of other professional disciplines or of on a D&B procured project. Team members from the architect’s
specialist sub-contractors, the commercial imperative underly- office who are visiting the site need to be familiar with the duties
ing the manufacture and marketing of products may require the to be undertaken as well as those duties excluded.
adoption of a more cautious approach to specialist construction
products. For example, BS 5534: 2003 Code of practice for slat-
ing and tiling (including shingles) provides recommendations for 4 Minimising the risks
minimum pitches and laps for slate and tile products. However,
at paragraph 5.3.1 it states: 4.01 In principle, the risk of misunderstandings and resulting
disputes will be minimised by: having the scope of services
Where proprietary tile and artificial slate products are to be and obligations of all parties clearly set out and formally
specified, the manufacturer’s recommendations should be documented; clearly identifying limits and exclusions to the
followed. Additionally, the specifier should obtain evidence services to be provided; careful consideration of and coordina-
that the performance of these products and recommenda- tion between the various different, but related, areas of docu-
tions have been proven to be satisfactory, by relevant expe- mentation; reviewing and updating documentation to reflect any
rience in use or relevant test data based on the conditions changes in project requirements as work progresses; and careful
and methods of use in equivalent and appropriate climatic operation of the contractual mechanisms.
conditions. The application of these principles to the relationships
(Emphasis added) described in the previous sections is considered below.

In this example, without having undertaken at least such a basic


level of checking of the manufacturer’s claims, it may be dif-
Architect’s appointment
ficult for an architect to avoid responsibility for any damaging 4.02 The architect’s appointment is a contract between the
results that may arise from the incorporation of the product into architect and his employer, whether this is the procurer of the
the design. project or a D&B contractor. The appointment should set out
clearly the scope of the services to be provided by the architect
and the terms on which they are offered. This is a requirement
The Contractor – workmanship details of both the ARB and RIBA Codes of Conduct. The appointment
3.24 Many claims against architects involve misunderstandings should also identify clearly any services which are specifically
about site visits and inspections. These claims appear to have excluded, for example,, interior design, and identify any limita-
two main underlying causes. tions that may apply to certain services, for example the review
of specialist sub-contractor drawings and the extent and purpose
3.25 Firstly, clients, particularly those who have little or no of any site inspections.
experience of procuring building works, often expect the archi-
tect to supervise the work of the builder. That is, to monitor 4.03 The standard forms of appointment produced by the RIBA
closely his activities and to direct and guide his work to ensure should be used wherever possible, completed as appropriate for
that the final product meets the expectations of the client. This is the circumstances of the project. Where the scale and complex-
not a service normally provided by an architect. Disagreements ity of the project requires either extensive amendment to these
Minimising the risks 325

standard forms or a bespoke appointment document, specialist for products of that type, the architect should seek evidence that
legal advice should be sought. the claimed performance has been achieved reliably and consist-
ently in practice, rather than place unquestioning reliance upon
the manufacturer’s assertions and claims.
Other design consultants
4.04 Where other design consultants are to be appointed, then
the scope of services and the terms incorporated in the archi-
Contractor workmanship details
tect’s appointment should be carefully considered in the light 4.11 The architect should consider carefully, in conjunction with
of the scope and terms of the appointment documents of the the employer, the services that are reasonably and realistically
other consultants. This is to ensure that the combined scope of required in respect of visits to the construction site and any
services will provide all that is necessary for the proper design inspection of the works. The agreed scope of these services must
of the project and that the terms of the various appointments are be set out clearly in the appointment, including any limitations
compatible with one another in terms of standard of care and or exclusions that have been identified. This applies whether
extent of any limitations on liability. the appointment is with the procurer of the project or with a
D&B contractor. The architect must ensure that team members
from the architect’s office who are visiting the site are familiar
Sub-consultant appointments with the duties to be undertaken as well as those duties that are
4.05 Where the architect has agreed to appoint sub-consultants, excluded.
it should ensure that the combined scope of services provides
all that is necessary for the proper design of the project and that
the terms of the various appointments are compatible with one
Contractual safeguards
another in terms of standard of care, extent of any limitations 4.12 In addition to minimising the risks by clear drafting of
on liability, and dispute resolution procedures. Each appoint- appointments and coordination of the terms of appointment of all
ment document should identify clearly any services which are parties undertaking design responsibilities, a specific limitation
specifically excluded and any limitations that may apply to of liability may be achieved by the incorporation of a net con-
certain services. tribution clause into the appointment. A net contribution clause
is a term in an agreement that limits the liability of a contracting
4.06 In addition, the architect should ensure that all the proposed party where the responsibility for loss or damage is shared with
sub-consultants have the necessary skills and resources to carry another party, for example where design of a specialist item is
out the work required and are likely to retain these over the time shared between the architect and a specialist sub-contractor.
period needed to carry out the work. Liability is limited to a share that is proportionate to the party’s
contribution to the loss or damage. This is advantageous to an
architect and its PI insurer, because it protects them from hav-
Specialist sub-contractors ing to pay out in full and then seek to recover monies from
4.07 Where it is intended that parts of the design will be carried other parties who may have contributed to the loss. However, it
out by specialist sub-contractors, either as part of a D&B con- removes the right, that the Employer would otherwise have, to
tract, or in relation to Contractor Designed Portions of work, the recover all of the loss from a single party under the principle of
architect should ensure that it, or the Contract Administrator, if joint and several liability.
this role is being carried out by another, puts in place the proper
sub-contract documentation to allocate design responsibility to 4.13 The RIBA Standard Agreement 2010 (2012 revision) incor-
the party intended to bear it. The architect should also ensure porates a net contribution term at clause 7.3, but it should be
that it, or the Contract Administrator, properly operates any noted that such standard clauses may be subject to the principles
contractual mechanisms required in order to give effect to the of the Unfair Contract Terms Act 1977 (UCTA), the Unfair
sub-contractor’s responsibilities. Terms in Consumer Contracts Regulations 1999 (UTCC), or the
Consumer Rights Act 2015 (see, further, Chapter 33). An archi-
4.08 In addition, the architect should ensure that any limita- tect wishing to rely on clause 7.3 or any similar net contribution
tions to any undertaking to review any drawings or other work clause should take care, at the very least, to bring its existence to
produced by specialist sub-contractors are set out clearly, both the Employer’s attention and ensure that its effects are explained
in its appointment and in the specialist sub-contract documents. and understood.

4.09 Where there is no formal provision within the chosen build- 4.14 The operation of a net contribution clause in an architect’s
ing contract for design by a specialist sub-contractor, then it is appointment was considered in the case of West v Ian Finlay
especially important for the allocation of design responsibility Associates [2014] EWCA 316. In that case, the judge decided
between the architect and any other party responsible for design that the Employer was aware of the clause and understood its
to be clearly set out and incorporated into the contract documen- effect, and that the clause was, therefore, applicable.
tation. This is likely to require specialist legal advice.
4.15 A prudent safeguard in relation to the possibility of tor-
tious third party claims is the inclusion of a disclaimer stating
Specialist suppliers in terms that liability under the agreement is limited to the
4.10 Where proprietary products are selected on the basis of parties to the agreement and that no liability will be owed to
claims that they exceed the typical standards and performance any third party.
33
Architects’ liability
JAMES CROSS QC

1 Introduction (b) Fitness for purpose, etc.


2.02 An architect’s professional obligations are rooted in the
1.01 This chapter is principally about the liability of an architect obligation to exercise reasonable care and skill. Like all pro-
to pay damages for professional negligence. fessionals, an architect does not ordinarily owe any stricter
(or higher) obligation to achieve a particular result; to ensure,
1.02 ‘Professional negligence’ is a convenient shorthand for for example, that its design is fit for the purpose for which the
describing the liability of a professional – whether in contract architect knows it is intended to be used. In short, an archi-
or in tort – for breach of the obligation (or duty) to provide pro- tect’s liability is usually dependent upon a finding of ‘fault’, in
fessional services with reasonable care and skill and diligence. the sense of professional negligence. As Denning LJ stated in
Greaves & Co (Contractors) Ltd v Baynham Meikle & Partners
1.03 Professional negligence is a big topic, even when confined [1975] 1 WLR 1095:
to architects. Nevertheless, it is narrower in scope than the
topic of the ‘professional liability’ of an architect, because an ‘The law does not usually imply a warranty that [the profes-
architect may be liable for the breach of obligations which are sional] will achieve the desired result, but only a term that
either different in character, and content, to the obligation of he will use reasonable care and skill. The surgeon does not
reasonable care and skill and diligence, or which are additional warrant that he will cure the patient. Nor does the solicitor
(sometimes more onerous) obligations which an architect must warrant that he will win the case.’
discharge. These other sources or forms of professional liability
are discussed in this chapter in Section 2 below. And, as HHJ Humphrey LLoyd QC stated in Payne v John
Setchell Ltd [2002] PNLR 7:
1.04 The balance of this chapter, Sections 3–9 below, is
concerned with the liability of an architect for professional
‘A professional person … does not normally undertake obli-
negligence. The final section (Section 10) gives the Scots law
gations of an absolute nature but only undertakes to exercise
perspective on the subject.
reasonable professional skill and care in performance of the
relevant service or in the production of the product.’
2 Other professional liability
2.03 In this important respect, an architect is ordinarily in a dif-
ferent (and more favourable) position to a building contractor,
(a) Introduction whose obligations to its employer, as one who supplies work
2.01 The primary source of an architect’s obligations, vis-à-vis and materials as well as services, will often involve express or
its employer client, is the contract (or agreement of appoint- implied obligations relating to the quality and/or fitness for pur-
ment) between the architect and the employer client (see pose of the contractor’s workmanship and materials. Moreover,
Chapter 30). An architect may also owe contractual obligations this general position, so far as an architect is concerned, tends
to third parties as a result of the provision of collateral war- to be reinforced (i) by the standard forms of appointment of
ranties (see Chapter 31). There is no substitute for examining an architect (see, for example, Clause 3.1 of the ‘Standard
the terms of each contract with care in order to identify and Professional Services Contract 2018’, which states that ‘nothing
understand the obligations upon an architect in any particular contained in this Agreement or elsewhere shall be construed as
case and, hence, what it is that an architect may be liable for. imposing on the Architect/Consultant any greater duty than the
In theory, there are no restrictions upon the nature and content exercise of … reasonable skill, care and diligence’); and (ii) by
of the obligations which an architect can, or may, agree to section 4 of the Supply of Goods and Services Act 1982, which
or assume, and hence, of the liabilities to which an architect provides for the implication, in certain circumstances, of fitness
may be subject. In practice, however, compliance with the for purpose obligations into contracts for the sale of goods, but
ARB and RIBA Codes of Conduct leads to contracts being not – by contrast – into contracts for the supply of services (of
made substantially upon written standard forms of contract which architects’ appointments are examples).
– something which has done much to identify and define an
architect’s general and specific obligations both with clarity 2.04 Even so, there may be circumstances in which an architect
and consistency. does owe stricter obligations, either expressly or by implication.

327
328 Architects’ liability

2.05 For an example of express fitness for purpose obligations, and would be dependent upon the architects’ expertise and
see Associated British Ports v Hydro Soil Services NV [2006] experience.
EWHC 1187, in which architects to whom the design and build
contractor sub-contracted the design of strengthening works to a 2.08 The cases discussed in paragraphs 2.04–2.07 above were all
quay wall were found – on a proper understanding of the design cases in which the designer provided professional services only.
sub-contract – to owe the same obligation to the contractor in In that context, the cases highlight the need either for express
relation to fitness for purpose as that owed by the contractor to agreement as to a fitness for purpose obligation or for facts
the employer under the main design and build contract (i.e. that which justify the implication of such an (absolute) obligation.
there was an express obligation upon the architects to provide a They are the exception rather than the rule. For cases highlight-
design for the strengthening works which was fit for purpose). ing the rule, see George Hawkins v Chrysler (UK) and Burne
And, moreover, an express fitness for purpose obligation may Associates (1986) 38 BLR 36 (no basis for holding that engi-
be strictly enforced. In MT Hojgaard v E.ON Climate and neers who designed showers for installation at a foundry owed
Renewables UK Robin Rigg East Ltd [2017] UKSC 59, although any stricter obligation in respect of the flooring on which the
the design of foundations to wind turbines in compliance with claimant slipped than the normal obligation of reasonable care
an international standard was consistent with the exercise of and skill) and Payne v John Setchell Ltd [2002] PNLR 7 (issue
reasonable care and skill by the designers, it was no answer to of a certificate by an engineer that he was satisfied that the foun-
a claim against them for breach of an express 20-year service dations of dwellings had been constructed in accordance with his
life obligation that the international standard contained a fun- design and were suitable for support of the dwellings was not a
damental error. fitness for purpose warranty in respect of the foundations, only
the expression of the defendant’s professional opinion).
2.06 For an example of implied fitness for purpose obligations,
see the case of Greaves itself (albeit involving structural engi- 2.09 However, where, by contrast, the architect designs and
neers), in which contractors who undertook to build a factory supplies a product (or similar) pursuant to his professional
complex and warehouse, supplying all necessary labour, mate- appointment, different considerations arise, and it is likely that
rials, and expertise to produce the finished product, engaged the architect will owe a fitness for purpose obligation in respect
consultant structural engineers to design the warehouse. The of the product or article supplied. The fact of supply of the
building was to be constructed according to a newly introduced product or article is thought to be vital in this context: see IBA
method of composite construction and was to be used for storing v EMI and BICC Construction (1980) 14 BLR 1.
and moving oil drums loaded onto stacker trucks. However, the
floors were not designed with sufficient strength to withstand
the vibration which was produced by the stacker trucks, and
(c) Honesty
the contractors claimed an indemnity from the engineers on 2.10 It is no surprise that an architect owes fundamental obli-
the grounds that the engineers had warranted that their design gations of honesty and integrity in its dealings with others in
would produce a building fit for its purpose. The Court of Appeal addition to obligations of competence. Honesty and integrity
explained that the professional is not usually under a duty to are, rightly, at the forefront of the conduct required of architects
achieve a specified result, but they went on to compare the situ- by RIBA.
ation with that of a dentist who agrees to make a set of false
teeth for a patient, in which case there is an implied warranty 2.11 There may, therefore, be circumstances in which an archi-
that they will fit the patient’s gums (Samuels v Davies [1943] tect is liable for breach of obligations of honesty and integrity.
KB 526). Denning LJ said: Vis-à-vis the employer client, any liability on the part of the
architect for breach of such obligations is likely to be deter-
What then is the position when an architect or an engineer mined by reference to the principles of the law of agency (see,
is employed to design a house or a bridge? Is he under an for example, in respect of an architect’s liability in respect of
implied warranty that, if the work is carried out to his design, bribes and secret commissions, the old case of Tahrland v Rodier
it will be reasonably fit for the purpose? Or is he only under [1866] 16 L.C. Rep. 473). Vis-à-vis third parties, any liability on
a duty to use reasonable care and skill? In the present case … the part of the architect (or vicarious liability of its principal) for
the evidence shows that both parties were of one mind on the breach of such obligations is likely to be in the tort of deceit:
matter. Their common intention was that the engineer should the making of a false statement of fact knowingly, or without
design a warehouse which would be fit for the purpose for an honest belief in its truth, or recklessly, careless whether it be
which it was required. That common intention gives rise to a true or false (Derry v Peek [1889] 14 App Cas 337). For a rare
term implied in fact. example of a case involving liability for fraudulent misrepresen-
tation by an architect in inviting tenders: see Pearson v Dublin
He concluded: Corporation [1907] 1 AC 351.

In the light of that evidence it seems to me that there was 2.12 There are many reasons why an architect’s liability for
implied in fact a term that if the work was completed in breach of its obligations of honesty and integrity are likely to
accordance with the design it would be reasonably fit for the be rare. The ineffectiveness of professional indemnity insur-
use of loaded stacker trucks. The engineers failed to make ance cover in respect of such liability also acts as a significant
such a design and are therefore liable. disincentive to the making of any allegation of fraud against an
architect. Furthermore, there are significant evidential and other
2.07 Another example is provided by the decision in Consultants hurdles that properly need to be surmounted if such serious
Group International v John Worman Ltd (1985) 9 ConLR 46, in allegations are to be established. It should be noted, however,
which providers of specialist architectural and consultancy ser- that there may be advantages to a claimant in alleging fraud. It
vices for the refurbishment of an abattoir were found to be under may afford a remedy where there would otherwise be none (for
an express or implied contractual obligation to the contractors example, vis-à-vis a contractor to whom – in the absence of
(the architects’ employers) to ensure that the works which they any contractual relationship – an architect owes no duty of care
designed would be fit for purpose, namely in accordance with in tort to safeguard the contractor from economic loss); it may
the relevant UK and EC standards and requirements for grant enable damages to be recovered which could not otherwise be
aid. Factors relevant to the decision were the Court’s findings recovered (for example, contractual limitations on the amount
that the architects were the ‘prime movers in the project from of damages recoverable are likely to be of no effect in a case
start to finish’ and the fact that the contractors had made it clear of fraud); it is likely to render any contributory negligence on
to the architects that they had no experience of abattoir work the part of the claimant irrelevant; and it may enable a claimant
Other professional liability 329

to surmount a limitation defence which would otherwise bar a 2 A ‘dwelling’ is any place where a person or household
claim in contract or in tort or pursuant to statute. lives to the exclusion of members of another household.
So, every apartment in a block of flats is a dwelling and,
for example, design work relevant to the construction of the
(d) Agency structural elements and/or common parts of a block of flats
2.13 As the agent of the employer client, an architect will owe to is likely to be ‘work … in connection with the provision
its employer client (its principal) all the usual duties of an agent of a dwelling’: see Rendlesham Estates Plc v Barr [2014]
(see Chapter 2), and there may be circumstances in which, as a EWHC 3968.
result, an architect owes fiduciary duties to the employer client. 3 The DPA 1972 imposes a statutory obligation upon an
However, such fiduciary duties do not enlarge the scope of an architect, in relation to work which an architect takes on
architect’s contractual (or tortious) duties (Chesham Properties for, or in connection with, the provision of a dwelling, to
Ltd v Bucknall Austin Project Management Services Ltd [1996] do that work in a ‘professional manner’ (i.e. with reasonable
82 BLR 92) and, in practice, the obligations of an architect as care and skill). However, a failure to exercise reasonable
agent are most likely to be relevant in the context of the archi- care and skill will not – of itself – give rise to a liability
tect’s authority (or not) to do things on the employer client’s for breach of the statutory duty because the key obligation
behalf and/or to bind the employer client vis-à-vis the contractor is that the architect should carry out its work in a manner
and others. Of course, most standard forms of building contract which will result in the dwelling being fit for habitation
now seek to define the scope of an architect’s authority in consid- when completed. A failure to carry out work in a profes-
erable detail with the result that cases involving breach of war- sional manner may result in the dwelling being defective
ranty of authority on the part of an architect (Yonge v Toynbee when completed, but unless those defects render the dwell-
[1910] 1 KB 215) or personal liability as a result of entering ing unfit for habitation when completed, there is no liability
into contracts with contractors without making it clear that the for breach of the statutory duty: see Harrison v Shepherd
architect is acting only as agent for his principal (Beigtheil and Homes Ltd [2011] EWHC 1811, Catlin Estates Ltd v
Young v Stewart [1900] TLR 177 and Sika Contracts v Gill and Carter Jonas (A Firm) [2006] PNLR 15, Thompson v Clive
Closeglen Properties [1978] 9 BLR 11) are now rare. Alexander & Partners (1993) 59 BLR 77 and Alexander v
Mercouris [1979] 1 WLR 1279.
4 A defect rendering a dwelling unfit for habitation may
(e) Defective Premises Act be latent rather than patent (Andrews v Schooling [1991]
1972 (‘DPA 1972’) 1 WLR 783) and may be a defect in only part of the dwell-
2.14 Section 1(1) of the DPA 1972 provides: ing (Bole v Huntsbuild Ltd [2009] EWHC 483). However,
in all cases, fitness for habitation (or not) is a question of
‘A person taking on work for the provision of a dwelling fact to be determined by the standards prevailing at the time
(whether the dwelling is provided by the erection or by the when the dwelling was completed.
conversion or enlargement of a building) owes a duty – 5 The statutory duty is owed in respect of both new construc-
tion and improvements.
(a) if the dwelling is provided to the order of any person, to 6 The statutory duty applies as much to the failure to carry
that person; and out work as the actual carrying out of work.
(b) without prejudice to paragraph (a) above, to every person 7 An architect who arranges for another to take on work
who acquires an interest (whether legal or equitable) in for or in connection with the provision of a dwelling will
the dwelling; be treated as having taken on the work itself if it does so
in the course of a business which consists of, or includes
to see that the work which he takes on is done in a workman- providing or arranging for, the provision of dwellings or
like or, as the case may be, professional manner, with proper installations in dwellings: DPA 1972, section 1(4).
materials and so that as regards that work the dwelling will 8 Any term of an agreement which purports to exclude or
be fit for habitation when completed.’ restrict, or has the effect of excluding or restricting, the
operation of any of the provisions of the DPA 1972, or any
2.15 It is important to understand that the DPA 1972 gives rise liability arising by virtue of any its provisions, is void: DPA
to a separate right of action for breach of the statutory duty 1972, section 6(3). An architect cannot therefore contract
set out in Section 1(1). The DPA 1972 is an important piece out of the statutory duty or seek to restrict it.
of legislation. For reasons which have already been explained 9 The statutory duty is owed both to those who commission
in Chapter 3, it is the more so (i) because since the decision the work and to every other person who acquires an interest
in Murphy v Brentwood District Council [1991] AC 398 there in the dwelling ‘whether legal or equitable’. In practice, this
have been substantial restrictions on the ability of a claimant means subsequent purchasers of the dwelling, mortgagees
to recover damages for pure economic loss in tort (see further and tenants.
in Section 4 below) which do not affect a claim for damages 10 There are special rules affecting the time (the limitation
for breach of the statutory duty set out in section 1(1); and (ii) period) within which claims for breach of the statutory duty
because it has now been a very long time indeed since there was set out in section 1(1) of the DPA 1972 must be made if
an ‘approved scheme’ for the purposes of section 2 of the DPA they are not to be statute barred by the Limitation Act 1980.
1972, which significantly restricted the right of action for breach The effect of section 1(5) of the DPA 1972 is that the date
of the statutory duty set out in Section 1(1). (Until 31 March on which the cause of action for breach of statutory duty
1979, the main approved scheme was the 10-year NHBC accrues is ‘when the dwelling was completed’ and that any
scheme, but there has been no ‘approved scheme’ since then.) claim must be made within six years of that date. This is
subject to the proviso that if, after completion of the dwell-
2.16 The following points should be noted: ing, further work is done to rectify defects in the original
work, any cause of action in respect of that further work
1 The statutory duty only applies in relation to an architect does not accrue until such time as that ‘further work was
taking on work ‘for or in connection with the provision of finished’: see Alderson v Beetham Organisation Ltd [2003]
a dwelling’, i.e. a building which is to be used as a home (a 1 WLR 1686.
dwelling-house). The duty is not owed by an architect taking 11 A claim for breach of the statutory duty set out in section 1(1)
on work in relation to the provision of commercial premises of the DPA 1972 is not ‘an action for damages for negli-
or premises used predominantly for commercial purposes: see gence’ within the meaning of section 14A of the Limitation
Catlin Estates Ltd v Carter Jonas (A Firm) [2006] PNLR 15. Act 1980: Payne v John Setchell Ltd [2002] PNLR 7.
330 Architects’ liability

3 Liability for professional there is an implied term to that effect in every contract (oral
or written) whereby an architect is engaged to provide profes-
negligence sional services.

Sources of the obligation of 3.05 Section 14 of the Supply of Goods and Services Act
reasonable care and skill 1982 provides that, where the time for the service to be carried
out is not fixed by the contract or is left to be fixed in a manner
(a) Contract agreed by the contract or determined by the course of dealing
between the parties, ‘there is an implied term that the supplier
Express terms will carry out the service within a reasonable time’.

3.01 The primary source of an architect’s obligation to exercise 3.06 It is the implied term of reasonable care and skill (section 13)
reasonable care and skill is usually the express term to that which is probably the more important of these two statutory
effect either in the architect’s contract of appointment with the provisions, so far as architects are concerned, but for a case in
employer/client or in the collateral warranty provided by an which it was held that it was an implied term of the architect’s
architect to the beneficiary of a collateral warranty. appointment by the contractor under a design and build contract,
that the architect would provide his design drawings by particu-
3.02 So far as contracts of appointment between the architect lar dates (and not simply exercise reasonable care and skill to do
and the employer/client are concerned, any appointment upon a so) so as to enable the contractor to comply with its contractual
RIBA Standard Form (for example, RIBA ‘Standard Conditions obligations – apparently without reference to section 14 of the
of Appointment for an Architect 2010 (2012 Revision)’ or RIBA 1982 Act, but in reliance on the parties’ common intentions (as
‘Standard Professional Services Contract 2018’) will oblige the in the case of Greaves): see CFW Architects (a firm) v Cowlin
architect, expressly, to exercise reasonable care and skill in con- Construction Ltd (2006) ConLR 116.
formity with the normal standards of the architect’s profession or
similar. Clause 2.1 (‘Duty of care’) of the ‘Standard Conditions
of Appointment for an Architect 2010 (2012 Revision)’, states (b) Tort
that the ‘Architect shall exercise reasonable skill, care and dili-
gence in accordance with the normal standards of the Architect’s Concurrent duty of care
profession in performing the Services and discharging all the
obligations under this clause 2’. Clause 3.1 of the ‘Standard 3.07 Where there is a contract between the architect and its
Professional Services Contract 2018’ states: employer client, it is very often unnecessary to seek to rely
on any duty of care owed concurrently by the architect to the
In the performance of the Services and discharging all the employer client in tort because of the express and/or implied
obligations under the Contract, the Architect/Consultant contractual duty of care which is already part and parcel of the
will exercise the reasonable skill, care and diligence to be contractual relationship between them. The same is true of con-
expected of an Architect/ Consultant experienced in the provi- tracts between the architect and the beneficiary of a collateral
sion of such services for projects of a similar size, nature and warranty.
complexity to the Project.
3.08 Nevertheless, suggestions that the existence of contractual
3.03 So far as collateral warranties are concerned, the architect duties of care should exclude the existence of any concur-
will ordinarily warrant expressly to the beneficiary that it has rent (or parallel) duty of care in tort were decisively rejected
exercised, and will continue to exercise, ‘reasonable skill, care in Henderson v Merrett Syndicates Ltd [1995] 2 AC 145.
and diligence’ in the performance of its services to the employer Essentially, a contractual relationship between the professional
client under the contract of appointment. and its employer client was regarded as being a pre-eminent
example of a proximate relationship involving an assumption
of responsibility sufficient to make it fair, just, and reasonable
Implied terms that a duty of care in tort should be owed by the professional to
the employer client. It is now well established, therefore, that
3.04 Section 13 of the Supply of Goods and Services Act an architect owes a concurrent duty of care in tort to those to
1982 provides that ‘in a contract for the supply of a service whom it also owes contractual duties of care.
where the supplier is acting in the course of a business, there
is an implied term that the supplier will carry out the service 3.09 The significance of this conclusion is principally in the
with reasonable care and skill’. It follows that, in the absence context of limitation of actions (the time which the law allows
of any standard form appointment or any express term requir- an employer client to bring a claim for professional negligence
ing the exercise of reasonable care and skill, nevertheless, against its architect) because it allows a claimant to bring its
claim in tort (in reliance on breach of the concurrent duty of
care owed in tort within six years of the date of damage) in
circumstances where its claim for breach of contract (in reli-
ance on breach of the contractual duty of care within six years
of the date of breach) is already statute barred, and indeed may
have become so without its knowledge. As Lord Goff said in
Henderson:

If concurrent liability in tort is not recognised, a claimant


may find his claim barred at a time when he is unaware of
its existence. This must moreover be a real possibility in the
case of claims against professional men, such as solicitors
or architects, since the consequences of their negligence
may well not come to light until long after the lapse of six
years from the date when the relevant breach of contract
occurred. Moreover the benefits of the Latent Damage Act
1986, under which the time of the accrual of the cause
Scope of the obligation of reasonable care and skill 331

of action may be postponed until after the [claimant] has 4 Scope of the obligation of
the relevant knowledge, are limited to actions in tortious
negligence. reasonable care and skill
3.10 The scope of the concurrent duty of care in tort, in particu- (a) Contract and concurrent
lar as to whether an employer client or similar – suing its archi- duty of care in tort
tect only in tort because of, for example, limitation difficulties
in respect of any claim in contract – may recover damages for Contract
pure economic loss in tort (damages which in many cases could
4.01 The scope of the contractual obligation of reasonable care
probably have been recovered, had the contractual claim still
and skill in terms of the parties to whom that obligation is owed
been ‘alive’) is discussed further in Section 4 below.
and the types of loss which may be recoverable for breach of
that obligation is a matter which is, first and foremost, regulated
3.11 For present purposes, the most important thing to emphasise
and defined by the terms of the relevant contract.
is that the contract out of which the concurrent duty of care in
tort arises remains vitally important to the scope of any concur-
4.02 Ordinarily, the obligation will obviously be owed to the
rent duty of care in tort. It is often said that the concurrent duty
party with whom the architect has entered into a contract.
of care in tort is ‘co-terminous’ or ‘co-extensive’ with the con-
Ordinarily, too, and subject to the application of general princi-
tractual obligation of reasonable care and skill. Such language
ples of causation and remoteness and mitigation of damage, the
recognises that the terms of the relevant contract limit or define
types of damage or loss for which the architect may be liable
the scope of the concurrent duty of care in tort and emphasises
in damages for breach of the contractual obligation of reason-
that the duty of care in tort is ordinarily no wider in scope than
able care and skill vis-à-vis its employer client will embrace
the relevant contractual obligation. So, for example, if there is
the following:
no contractual obligation as a result of any breach of the contrac-
tual duty of care to pay damages in respect of particular losses
(damages representing pure economic loss in tort, for example), 1 Damages in respect of personal injury sustained by the
there is no concurrent tortious obligation to do so: see Greater employer client, or in respect of the death of the employer
Nottingham Co-operative Society Ltd v Cementation Piling & client.
Foundations Ltd [1989] QB 71. 2 Damages in respect of (physical) damage to the employer
client’s property and in respect of financial losses sustained
by the employer client in consequence of that damage,
Duty of care to third parties for example, the cost of repairing or replacing damaged
property.
3.12 ‘Third parties’, in this context, essentially means anyone 3 Damages in respect of any financial losses sustained by the
with whom the architect does not have a contractual relationship. employer client by reason of the architect’s professional
As the source of a duty of care in tort, the absence of a contrac- negligence, for example, the costs involved in remedying
tual relationship is of the very essence of the law of tort, and the or rectifying design or other defects in a building.
position is already explained in Chapter 3. The principal debates
in the context of the duty of care in tort owed to third parties are 4.03 As a matter of terminology, financial loss in category
in relation to (i) identifying the third parties to whom a duty of 3 above is referred to in the language of the law of tort as ‘pure
care in tort is owed; and (ii) more importantly, understanding the economic loss’, because it has no association – in the eyes of the
scope of the duty of care in tort which is owed. Each of those law – with any damage to property. This concept is considered in
matters is discussed in more detail in Section 4 below. more detail below, because its primary relevance is in the law of
tort. In the law of contract, however, there are no objections of
(c) Statute principle to the recovery of pure economic loss. Pure economic
loss is routinely recovered in claims relying on breach of a
Supply of Goods and Services Act 1982 contractual duty of care.

3.13 The relevant provisions of the Supply of Goods and 4.04 The following matters should be noted as potentially
Services Act 1982 have already been discussed above. The affecting the scope of the contractual obligation of reasonable
1982 Act is a source of an architect’s obligation of reasonable care and skill in terms of the parties to whom that obligation is
care and skill (and the obligation to provide the professional ser- owed and the losses which may be recoverable for breach of
vices within a reasonable time) only in the sense that it implies that obligation.
terms into an architect’s contracts to that effect. The 1982 Act
gives rise to no free-standing obligation of reasonable care and 1 The effects of an assignment of an architect’s appointment
skill and no action for breach of statutory duty. to another party; alternatively of a novation of an architect’s
appointment from, say, the building owner to the contrac-
tor on a design and build project. Assignment, alternatively
novation, will always call for very careful consideration
Construction (Design and if the architect is not to find itself owing a contractual
Management) Regulations 2015 obligation of reasonable care and skill not only to a dif-
ferent party to its original employer client, but also with,
3.14 The Construction (Design and Management) (‘CDM’) potentially, unintended consequences so far as an architect’s
Regulations 2015 are the source of a number of important liability for loss is concerned: see, for example, Blyth &
obligations and duties upon architects, whether an architect is Blyth Ltd v Carillion Construction Ltd (2001) 79 ConLR
a ‘designer’, the ‘principal designer’, or the client’s appointed 142 in which, in reliance upon a novation agreement, the
‘CDM co-ordinator’: see Chapter 15. For present purposes, defendant contractors (the new client) – unsuccessfully, on
it can be noted that the CDM Regulations are not so much a the facts – sought to recover damages for their own losses
source of an architect’s obligation of reasonable care and skill sustained as a result of alleged professional negligence on
as a ‘spelling out’ of the substantive content of that obligation so the part of the claimant engineers in providing professional
far as an architect’s involvement in the design and management services for the original employer client (the provision of
of construction projects is concerned. In short, it is likely that tender information) before the date of novation.
any breach of the duties and obligations imposed by the CDM 2 The potentially retrospective effect of an architect’s appoint-
Regulations will amount to professional negligence. ment so as to impose obligations upon the architect in
332 Architects’ liability

respect of professional services provided – as often hap- (b) Duty of care in tort to third parties
pens – before the contract was made or formally concluded.
Whether an architect’s appointment expressly or impliedly Personal injury
has retrospective effect may be important: see Consarc 4.07 An architect owes a duty of care in tort not to cause per-
Design Ltd v Hutch Investments Ltd [2002] PNLR 712. sonal injury (or death) to those who might be foreseeably injured
3 The content of any contractual term of an architect’s (or killed) as a result of its professional negligence: Clay v A.J.
appointment seeking to limit the architect’s professional Crump & Sons Ltd [1964] 1 QB 533. In that case, an architect
negligence liability for loss and damage to a specified sum supervising demolition and rebuilding instructed the demolition
and/or to exclude the architect’s liability for certain types of contractor to leave a wall standing as a temporary measure. He
loss or damage. The effectiveness (enforceability) of such accepted the demolition contractor’s word that the wall was safe,
terms requires consideration of the Unfair Contract Terms and, although he visited the site, he did not check for himself.
Act 1977 (‘UCTA’) as amended by the Consumer Rights Had he looked, he would have seen that the wall was tottering
Act 2015 (NB. since its amendment, UCTA applies only to above a six-foot trench cut under its foundations. The architect,
persons other than a ‘consumer’ within the meaning of the together with the demolition contractor and the builder, was
Consumer Rights Act 2015) or, in relation to consumer con- found liable when the wall collapsed and injured one of the
tracts concluded since 1 October 2015, under the Consumer builder’s men.
Rights Act 2015 itself. At the risk of over-generalisation in
a complex area of legislative control, such terms are open 4.08 Nevertheless, ordinarily, the safety of the contractor’s
to challenge, and must satisfy the statutory requirement employees is principally a matter for the contractor, and it is
of reasonableness or fairness, where the party with whom not ordinarily (subject, of course, to the CDM Regulations) the
the architect contracts is a ‘consumer’ (a householder is a architect’s job to tell the contractor how to do its work or what
‘consumer’, for example) or where the contract is made safety precautions the contractor should take (especially with
upon the architect’s written standard terms of business. For respect to temporary works). So, an architect was not negligent
an example of a case involving an architect in which the when he instructed a chase to be cut in a wall and, as a result of
statutory requirement of reasonableness was satisfied: see the builder choosing to do it without shoring the wall up, it fell
Moores v Yakeley Associates Ltd (1998) 62 ConLR 76 (a and injured a workman: Clayton v Woodman & Sons (Builders)
£250,000 limitation of liability in an architect’s contract Ltd [1962] 1 WLR 585.
with his employer client was held to be reasonable on the
facts – despite the architect having PI cover of £500,000 4.09 Where personal injury is suffered as a result of a design
– having regard to such matters as the likely cost of the defect, again, it is uncontroversial that an architect owes a duty
works [£250,000]; the limitation being more than ten times of care in tort to all those who may foreseeably be injured (or
the amount of the architect’s fees of £20,000; the involve- killed) as result of its professional negligence to take reason-
ment of solicitors on behalf of the employer client, and their able steps to avoid causing personal injury (or death): see, for
awareness of the relevant clause, and their lack of objec- example, Eckersley v Binnie & Partners (1988) 18 ConLR 1
tion to it; the employer client’s means as compared to the (liability of engineer designers to claimants injured or killed in
architect’s means; and the strength of the employer client’s the Abbeystead explosion for failure properly to design for the
bargaining position as compared to the architect’s). Net risk of methane gas) and Targett v Torfaen Borough Council
contribution clauses are also relevant in this context (albeit [1992] 3 AER 27 (liability of local authority designers to a
that they seek to limit the architect’s liability in a different council house tenant injured as a result of the failure to provide
way), and they are discussed in Section 8 below. adequate lighting and a handrail).

Concurrent duty of care in tort


Damage to ‘other property’ and
4.05 Many of the matters discussed in paragraphs 4.01–4.04 are consequential economic loss
equally relevant to a consideration of the scope of any concur-
rent duty of care in tort. The principal unique debate, so far as 4.10 An architect also owes a duty of care in tort not to cause
the scope of the concurrent duty of care in tort is concerned, has physical damage to the property of anyone whose property might
been whether the duty extended to safeguarding the employer foreseeably be damaged as a result of its professional negli-
client from pure economic loss, or was limited – in the same gence. However, this principle is subject to two very significant
way as the conventional duty of care in tort which is owed to qualifications:
third parties – to safeguarding the employer client from personal
injury and damage to property only. 1 The property involved must be what is referred to as ‘other
property’, namely property which is different to the property
4.06 After a number of conflicting first-instance decisions in respect of which the architect is (or was) contractually
(albeit most were in favour of the recovery of economic loss engaged. This differentiation is vital, because financial loss
in tort by the designer’s client, see Storey v Charles Church sustained as a result of physical damage to ‘other property’
Developments Ltd [1995] 73 ConLR 1; Tesco Stores v Costain is regarded as consequential economic loss, which is gener-
Construction Ltd [2003] EWHC 1487; and Mirant-Asia Pacific ally recoverable in tort; whereas financial loss sustained as
Ltd v Ove Arup & Partners International Ltd [2005] PNLR a result of defects in (or damage to) the property in respect
10), it now seems settled that – subject always to the terms of which the architect is (or was) engaged is – following
of the contract of appointment (see paragraph 3.11 above) Murphy v Brentwood – regarded as pure economic loss,
– a construction professional such as an architect ordinar- which is not generally recoverable in tort by third parties.
ily assumes responsibility for safeguarding its client against In terms of its practical application, the differentiation is rel-
economic loss as a result of reliance by the client upon the evant particularly in the context of claims against architects
architect’s professional work and services: see Robinson v PE in tort by subsequent owners and purchasers of property
Jones (Contractors) Ltd [2011] EWCA Civ 9, [2012] QB 44 (in designed by an architect and/or whose construction has been
which the Court of Appeal drew a distinction, in this context, inspected by an architect.
between the position of a construction professional and a build- 2 The existence (and scope) of any duty of care in respect of
ing contractor) and Lejonvarn v Burgess [2017] EWCA Civ physical damage to ‘other property’ is very much affected
254 (in which the Court of Appeal reiterated the correctness of by the question of whether the third party whose ‘other
that distinction, even where an architect provided professional property’ has been damaged (usually a subsequent owner
services in the absence of any contract between the architect or purchaser) had a reasonable opportunity to discover the
and her ‘professional clients’). relevant defect before it caused the damage.
Scope of the obligation of reasonable care and skill 333

‘Other property’ Reasonable opportunity for


4.11 Identifying what is, or what is not, damage to ‘other prop- discovery of defect
erty’ will sometimes be straightforward: for example, properties 4.13 A potential limitation upon the existence (and scope) of
adjoining, or in the vicinity of, a construction site which are an architect’s duty of care in tort to avoid causing damage to
damaged as a result of design defects in the permanent works ‘other property’, particularly vis-à-vis subsequent owners and
or as a result of negligently ‘supervised’ construction operations occupiers of property designed by an architect whose contents
on site will clearly be ‘other property’ in respect of which a duty etc. (‘other property’) are damaged by reason of a design defect
of care in tort is owed. So, for example, in Nitrigin Eireann in the building, is the principle that an architect’s liability is
Teoranta v Inco Alloys Ltd [1992] 1 WLR 498, when a pipe essentially confined to a liability in respect of damage to ‘other
supplied by specialist pipe-makers to a building owner cracked, property’ caused by latent defects only – latent defects for these
the cost of repairs was irrecoverable economic loss, because the purposes being defects which could not reasonably have been
defective pipe had not caused damage to anything other than discovered on reasonable inspection of the building by or on
itself. However, when the pipe cracked again a year later and behalf of the subsequent owner or occupier. For cases illustrat-
caused an explosion which damaged surrounding plant, the cost ing this principle, see:
of repairing the damaged plant was recoverable because the
defective pipe had caused damage to ‘other property’. 1 Baxhall Securities Ltd v Sheard Walshaw Partnership
[2002] PNLR 564 (architect designers of an industrial ware-
4.12 In other circumstances, the task of identifying what is, or house were not liable to subsequent owners/occupiers of the
what is not, damage to ‘other property’ may be difficult and warehouse whose electrical goods stored in the warehouse
contentious. It can be further complicated by reference (argu- were damaged by flooding by reason of the negligent design
ably unnecessary reference) to the pre-Murphy v Brentwood of the rainwater drainage system because the relevant defect
– and much-criticised – ‘complex structure theory’ (see further – the absence of adequate overflows – was one which ought
in Chapter 3 above). This will be particularly so, perhaps, in reasonably to have been discovered by the claimants with
circumstances where an architect’s design or ‘supervision’ role the benefit of the skilled advice from a building surveyor,
is limited to particular elements of a building only. The follow- which it was to be expected they would obtain).
ing are illustrations: 2 Sahib Foods Ltd v Paskin Kyriades Sands (A Firm) (2003)
Con LR 1 (architect designers of a food production factory
1 Warner v Basildon Development Corporation (1991) Const were liable to their employer client [the occupiers, Sahib]
LJ 146 (negligent construction of foundations of a house by for the spread of fire because of the negligent design deci-
a builder which caused damage to parts of the superstructure sion to use combustible panels, but were not liable in tort to
of the house constructed by the same builder did not involve subsequent purchasers of the factory [the second claimants]
causing damage to ‘other property’; therefore no recovery because, on the facts, there was no evidence that the use of
by subsequent purchasers of the house for diminution in combustible panels was a defect that would not have been
value). revealed by a pre-purchase survey/inspection).
2 Jacobs v Morton and Partners [1995] 72 BLR 92 (engineer
designers of piled raft foundations as part of a separate 4.14 However, the principle has been doubted: Pearson
remedial scheme to repair cracking in an existing house Education Ltd v The Charter Partnership Ltd (2007) BLR 324.
were liable, when the remedial scheme failed, for the cost In that case, architect designers of a warehouse used for book
of demolition and rebuilding of the house on the basis that storage were liable to subsequent occupiers of the warehouse for
this involved damage to ‘other property’). damage caused to their stock of books by flooding as a result of
3 Tesco Stores Ltd v Norman Hitchcox Partnership Ltd the negligent design of the rainwater drainage system because
(1997) 56 ConLR 42 (architect designers of shell works – despite there having been an earlier flood damaging the stock
for a supermarket were not liable when fire spread in the of a different occupier – the claimants ‘neither knew nor should
supermarket as a result of inadequate compartmentation, for have known of the flood so that there was no reason why they
physical damage to the structure of the supermarket because should carry out any investigation of the adequacy of the rain-
in contrast to the damage caused to stock and equipment, water systems’. In other words, on the facts, there was no ques-
this was not damage to ‘other property’). tion that the relevant defect should have been discovered. It was
4 Tunnel Refineries Ltd v Bryan Donkin Co. Ltd (1998) CILL latent, so the subsequent occupiers were entitled to damages.
1392, (suppliers and manufacturers of a fan in a compressor Nevertheless, the principle absolving an architect in respect of
were not liable in tort to the compressor owner/purchaser damage caused by defects which should reasonably have been
for the cost of replacing the compressors when the fan shat- discovered was doubted by the Court of Appeal:
tered so as to wreck the compressor on the basis that there
was no damage to ‘other property’ as a matter of fact and If an architect who has the primary responsibility for pro-
degree). ducing a safe design produces a defective design, it is not
5 Bellefield Computer Services Ltd v E Turner & Sons Ltd obviously fair, just and reasonable that he should be absolved
(2000) BLR 97 (negligent construction of an internal fire from any liability in tort in respect of its consequences on
[compartment] wall in a dairy by a builder which meant the ground that another professional could reasonably be
that fire spread from a storage area so as to damage the rest expected to discover his shortcoming … [I]t is not obvious
of the dairy when it should not have done, did not involve why a failure of a person put at risk by a defective design,
damage to ‘other property’ in circumstances where the to take due care for his own safety or that of his property
whole dairy had been built by the same builder; therefore should break the chain of causation, rather than amount to
no recovery by subsequent purchasers of the cost of repairs contributory negligence.
to the fabric of the building itself beyond the storage area.
However, there was recovery in respect of damage to the
subsequent purchasers’ plant, equipment, stock and other
Pure economic loss
chattels in areas of the building beyond the storage area, 4.15 A general principle of professional negligence liability in
because such items were distinct items of ‘other property’). tort, and it applies to architects as much as to any other profes-
6 Payne v John Setchell Ltd [2002] PNLR 7 (engineer design- sion, is that an architect is not usually liable to third parties in
ers of raft foundations to a pair of cottages built by the same tort for pure economic loss. Putting matters another way, it is not
builder were not liable to subsequent owners of the cottages within the scope of an architect’s duty of care in tort to safeguard
for defects in the foundations on the basis that there was no all those whom it may reasonably foresee will suffer loss if it is
damage to ‘other property’). negligent from pure economic loss. An architect is liable to third
334 Architects’ liability

parties in tort for causing personal injuries and damage to ‘other contractual relationship in that way. Nevertheless, there may be
property’, but – ordinarily – the buck stops there. circumstances, in which an architect will owe a Hedley Byrne-
type duty of care in its communications and/or dealings with
4.16 In terms of its practical application, the general principle third parties to avoid causing them economic loss, for example
means that an architect is not ordinarily liable in tort (i) to (i) subsequent purchasers; and (ii) contractors.
subsequent owners and occupiers or similar in respect of the
cost of repairing design (or other) defects in a building which it 4.20 As to subsequent purchasers:
designed; or (ii) to contractors with whom it has no contractual
relationship in respect of, for example, negligent certification 1 Machin v Adams (1997) 84 BLR 79 (architect owed no duty
which causes contractors economic loss. of care to prospective purchasers of a property in respect of
a letter which he provided to his employer client in which
4.17 To any general principle, there are exceptions. They have he made various statements relating to works of alteration
been discussed in Chapter 3. Much the most important to and refurbishment being carried out at the property and the
architects is the application of the Hedley Byrne principle – the time which would be needed to complete them, including
essence of which requires a special relationship of proximity the statement that ‘all works to date are to a satisfactory
between the architect and any third party, a positive assumption standard’. Even though the architect knew that this letter
of responsibility by the architect towards the third party to avoid would probably be shown to the prospective purchaser, the
causing economic loss and reasonable reliance by the third party works were ongoing and, on the facts, it was not reasonable
upon the architect, before a liability in tort for pure economic that the purchaser should have proceeded without further
loss will be imposed. Indeed, for a recent example of a duty enquiry).
of care in tort in respect of pure economic loss arising in the 2 Lidl Properties v Clarke Bond Partnership [1998] Env
absence of a contract between an architect and its ‘professional LR 622 (engineer owed a duty of care to a prospective
client’: see Lejonvarn v Burgess [2017] EWCA Civ 254, in purchaser of a supermarket in respect of statements made/
which the Court of Appeal concluded that – despite the absence advice given in an informal meeting about ground con-
of a contract – it was nevertheless fair, just, and reasonable, by tamination and the likely costs of decontamination, but there
reference to the assumption of responsibility test, to find that a was no liability on the facts, because the engineer was not
duty of care in respect of economic loss was owed by the archi- in breach of his duty and the claimant had not relied on the
tect to her clients on the facts. As Hamblen LJ stated: engineer’s advice).
3 Payne v John Setchell Ltd [2002] PNLR 7 (engineer owed a
the context was a professional one. It was not informal duty of care to subsequent purchasers of cottages in respect
or social. There was an obvious relationship of proximity. of his certificates/statements that the foundations were
Although she [Mrs Lejonvarn] was not going to be paid satisfactorily constructed, because he intended that his cer-
initially the expectation was that she would be paid for later tificates would be seen and relied upon, and was therefore
work. She held herself out as having professional skills. She liable to the subsequent purchasers for pure economic loss
said she would perform professional services and did so. She [diminution in value measured by cost of remedial works]
was aware that the Burgesses would be relying upon her to in circumstances where the foundations were defective and
properly perform those services and it was foreseeable that his statement had not been made with reasonable care and
economic loss would be caused to them if she did not. skill).
4 Offer-Hoar v Larkstore Ltd [2006] PNLR 17 (geotechnical
4.18 Nevertheless, on a ‘normal’ construction project, it will engineer owed no duty of care in tort to a subsequent owner
usually be inimical to any Hedley Byrne liability of the architect in respect of a site investigation report because the use of
in tort that the parties have chosen to formulate their contractual the report by the subsequent owner was not reasonably
relationships in the way that they have because it will usually be foreseeable).
inconsistent with the alleged tortious duty to the third party. An 5 BDW Trading Ltd v Integral Geotechnique (Wales) Ltd
architect who is not in a contractual relationship with someone [2018] EWHC 1915 (engineers who prepared an asbestos
involved with the project, who claims to have suffered economic report for the local authority in relation to a develop-
loss as a result of the architect’s negligence, will not usually be ment site owed no duty of care to the purchaser of the
liable to that party for such loss: see Architype Projects Ltd v site because, although the report could have been validly
Dewhurst MacFarlane & Partners (2003) 96 ConLR 35 (archi- assigned to the eventual purchaser of the site (and indeed
tect’s claim against sub-consultant engineers on basis that the contemplated such an assignment), the purchaser’s failure
sub-consultants owed a duty of care in tort to the architect’s to obtain any assignment of the benefit of the report was
employer client was struck out as having no reasonable pros- inimical to successful legal reliance on the report by the
pect of success) and Sainsbury’s Supermarkets Ltd v Condek purchaser and was inconsistent with any assumption of
Holdings Ltd [2014] EWHC 2016 (a claim that structural engi- responsibility by the engineers to the purchaser in respect
neers engaged by a building contractor owed a Hedley Byrne of the report in the absence of an assignment).
duty of care to the employer under the building contract was
struck out as having no reasonable prospect of success). It is 4.21 As to contractors:
similar considerations which, ordinarily, mean that an architect
owes no duty of care in tort to a contractor to detect faults in 1 Townsend (Builders) Ltd v Cinema News and Property
the work carried out by the contractor so as to safeguard the Management (1958) 20 BLR 118 (architect’s written state-
contractor from economic loss, even though the architect clearly ment to the contractor that he would serve all necessary
owes such a duty to its employer client: Oldschool v Gleeson notices required by building byelaws gave rise to liability
(Construction) Ltd (1976) 4 BLR 103. to the contractor for damages when the notices were served
late. This was pre-Hedley Byrne, but was a Hedley Byrne-
4.19 Hedley Byrne involved negligent statements and the provi- type liability).
sion of information and advice. Henderson v Merrett confirmed 2 Pacific Associates Inc v Baxter [1990] 1 QB 993 (engineers
that the principle also applies to negligent conduct and the pro- not liable to contractors for economic loss caused by alleged
vision of negligent services, but – generally speaking – in the negligent certification because there was a contractual
context of an architect’s liability, English law has been resistant structure in place whereby the contractor was entitled to
to imposing a liability for pure economic loss in the absence challenge the engineer’s decision in proceedings against the
of some specific representation or intervention by the architect employer, which made it inappropriate to impose a duty of
and/or in the absence of sound policy reasons why an architect care on the engineers. There was also a relevant disclaimer
should protect the position of parties with whom it has no of personal liability on the part of the engineers for their
Breach of the obligation of reasonable care and skill: pre-construction work stages 335

acts and omissions in carrying out their duties under the 3 Visiting the site itself for the purposes of obtaining accurate
building contract). Ordinarily, an architect owes no Hedley (above ground) site information by taking measurements
Byrne duty of care in tort to a contractor in and about its and so forth, or checking measurements and dimensional
administration of the building contract as the agent of its information provided by others: see Columbus Co Ltd v
employer client to avoid causing the contractor economic Clowes [1903] 1 KB 244 (site was bigger than assumed
loss. Obviously, deliberate misapplication by an architect for design purposes by the architect in reliance on infor-
of the provisions of the building contract when issuing cer- mation provided by someone with no authority to provide
tificates is a very different matter: see Lubenham Fidelities it) and Cardy v Taylor (1994) 38 ConLR (site was smaller
Investment Co. Ltd v South Pembrokeshire DC (1986) than assumed for design purposes by the architect, and the
6 ConLR 85. building had to be redesigned). Advice to clients based on
3 Before any building contract is entered into, however, the measurements should be appropriately qualified where nec-
position may be different: J Jarvis & Sons Ltd v Castle essary: see Gable House Estates v The Halpern Partnership
Wharf Developments Ltd [2001] EWCA Civ 19 (no reason (1995) ConLR 1 (substantially inaccurate advice given
in principle why the professional agent of the employer by the architect about the useable office space that would
under a building contract could not be liable to a contrac- result from a development was not excused by stating that
tor for negligent misstatements made by the agent to the all areas were ‘approximate’ in circumstances where a clear
contractor to induce the contractor to tender, but there was warning should have been given to the client both of errors
no reliance and no liability on the facts). But see Galliford of up to 500 sq. ft and the risk of the advised square footage
Try Infrastructure Ltd v Mott MacDonald Ltd [2008] EWHC not being achieved).
1570 (no duty of care owed by engineers to contractors 4 Visiting the site itself for the purposes of making other rel-
in respect of concept design produced for client at tender evant observations and generally considering the effect of
stage, given engineers’ disclaimer of responsibility to any observable site features in terms of their consequences and
party other than their client and the contractors’ engagement implications for the contemplated project: see Dalgleish v
of their own design consultants). Bromley Corporation (1953) 161 EG 738 (site on a steep
slope making the expense of the contemplated project une-
conomic); Armitage v Palmer (1959) 173 EG 91 (proposed
position of building on the site potentially interfering with
5 Breach of the obligation of easement enjoyed by neighbouring owners); Acrecrest Ltd
reasonable care and skill: v WS Hattrell & Partners (1979) 252 EG 1107 (insufficient
pre-construction work stages regard paid by architects to the effect of removing trees on
the site).
Appraisal and feasibility
Cost estimates
Site investigation and surveys 5.02 The preparation and provision of cost estimates by an
5.01 Appraising the site and the construction project which is architect, and the ongoing need to consider revisions to cost
proposed requires the architect to take reasonable steps to inves- estimates and to provide up-to-date cost information as a project
tigate the site with a view to satisfying itself, and so advising progresses, are among an architect’s key services. Cost estimates
the employer client, as to the feasibility and buildability of the must be produced with reasonable care and skill. Ordinarily that
contemplated scheme on the particular site involved. Commonly, means:
such steps will involve:
1 Liability to an employer client for a negligent cost estimate
1 Considering the need for ground investigation of the site cannot be avoided by delegating the task to a quantity sur-
and advising the employer client on the appointment of veyor: Nye Saunders & Partners v Bristow (1987) 37 BLR
specialist consultants/contractors to carry out any neces- 92 (estimate of £238,000, which was within the client’s
sary investigation. Not to carry out any investigation at all budget of £250,000, was based on current costs, rather than
of made ground, for example, or to advise as to the need on an estimate of what the likely outturn cost [£440,000]
for specialist investigation in such circumstances, is likely was going to be over the life of the project).
to be negligent: see Eames London Estates Ltd v North 2 A cost estimate ordinarily needs to be a forecast of the
Hertfordshire DC (1980) 259 EG 491 (industrial build- likely out-turn cost of the project: Nye Saunders. An archi-
ing constructed on made ground, architect designer of the tect therefore needs to be careful to identify factors which
foundations made no examination of the ground and so took are foreseeably likely to affect that anticipated final cost of
no steps to satisfy itself as to the bearing capacity of the construction.
ground). However, where an architect recognises the risk 3 A cost estimate needs to be reasonably accurate when objec-
and recommends the appointment of an appropriate special- tively assessed by reference to the information which ought
ist to deal with the matter, the architect will ordinarily be to have been taken into account at the time the estimate was
entitled to rely on that specialist to carry out – or to organise produced. However, the fact that the final out-turn cost is in
the carrying-out by others of – whatever ground investiga- excess of a cost estimate, perhaps massively so, is not evi-
tion is needed (and to rely on such ground information as dence of negligence in itself: Copthorne Hotel (Newcastle)
is produced): see Industry Commercial Properties v South Ltd v Arup Associates (1996) 58 ConLR 105.
Bedfordshire DC [1985] 1 All ER 787 (structural engineers
engaged, on architect’s recommendation, to design foun-
dations to warehouse failed to ensure that a proper site
Planning and building control
investigation was carried out; architect entitled to rely on 5.03 An architect must ordinarily obtain both planning permis-
engineers). sion and building regulation consent. An architect is expected
2 Ensuring that significant assumptions made about ground to have a good working knowledge of planning and building
conditions for the purposes of design are verified by control requirements accordingly, and this may extend to hav-
appropriate ground investigation: Ove Arup & Partners ing some knowledge of relevant planning law in circumstances
International Ltd v Mirant Asia Pacific Construction (Hong where an architect holds itself out as being able to advise on the
Kong) Ltd (No. 2) (2006) BLR 187 (engineer designers planning aspects of a project and does not advise its employer
of foundations were negligent in making assumptions client to seek legal advice on the matter: see B L Holdings Ltd
about bearing capacity which needed to be verified by site v Robert J. Wood & Partners (1979) 10 BLR 48 (reversed, on
investigation). the facts, on appeal).
336 Architects’ liability

Design Buildability
Generally 5.08 An architect must ordinarily consider the buildability of
the design. An architect is entitled to expect certain standards
5.04 In the absence of any fitness for purpose obligation (see of skills and experience on the part of those who will build the
Section 2 above), the design obligation is one of reasonable design and, on certain projects, may be entitled to expect very
care and skill. Whether or not that obligation has been com- high standards of skill and experience, as in the British Library
plied with in any particular case will inevitably depend on case (Department of National Heritage v Steensen Varming
the facts of the case and the view of those facts taken by the Mulcahy [1998] ConLR 33). Nevertheless, an architect’s design
court, assisted (almost always) by the evidence of independ- must give rise to realistic expectations of buildability: George
ent experts (usually architects themselves) as to the objective Fischer Holding Ltd v Multi Design Consultants Ltd (1998)
standard(s) which the particular architect in question ought to 61 ConLR 85 (design of roof requiring perfect construction of
have attained. This is true of any complaint of professional the end lap joints if it was not to let in water was unrealistic in
negligence on the part of an architect (i.e. it is applicable in its expectations of workmanship).
all situations covered by Sections 5 and 6), but is perhaps
most commonly encountered in the context of an architect’s
paradigm responsibility for design. Tender action
5.05 The standard demanded by an architect’s obligation of Tender documentation
reasonable care and skill is the reasonable care and skill of the
5.09 RIBA Standard Forms of Agreement commonly require an
ordinarily competent architect. An architect is not required to
architect to prepare and collate tender documents in sufficient
have an extraordinary degree of skill or the highest professional
detail to enable a tender or tenders to be obtained. They also
attainments. However, ‘he must bring to the task he under-
commonly require an architect to consider with the employer
takes the competence and skill that is usual among architects
client the responsibilities of the parties and the authority and
practising their profession. And he must use due care’: see the
duties of the architect under the building contract. This process
Australian decision of Voli v Inglewood Shire Council [1963]
will often involve the architect in preparing contract docu-
ALR 657. In Eckersley v Binnie & Partners (1988) 18 ConLR 1,
ments (including relevant specifications and contract drawings)
Bingham LJ’s observations regarding the standard to be attained
and will often involve advising the employer client as to the
by engineers are equally applicable to architects:
choice of building contract and the way in which it should be
completed.
a professional man should command the corpus of knowl-
edge which forms part of the professional equipment of the
5.10 So far as preparation of contract documents is concerned,
ordinary member of his profession. He should not lag behind
the principal objectives are that they should contain a compre-
other ordinarily assiduous and intelligent members of his
hensive description of all the work which is necessary for the
profession in knowledge of new advances, discoveries and
satisfactory completion of the project and that, so far as pos-
developments in his field. He should be alert to the hazards
sible, there is internal consistency between the various contract
and risks inherent in any professional task he undertakes to
documents (for example, between architectural drawings and
the extent that other ordinarily competent members of the
specifications and any Bills of Quantities). Where the architect
profession would be alert. He must bring to any professional
is the lead consultant, these responsibilities call for wider co-
task he undertakes no less expertise, skill and care than other
ordination and liaison.
ordinarily competent members would bring but need bring no
more. The standard is that of the reasonable average. The law
5.11 So far as choice of building contract is concerned, there are
does not require of a professional man that he be a paragon
numerous standard forms of building contract available (many
combining the qualities of polymath and prophet.
of them very complex), and an architect is required to exercise
reasonable care and skill when advising its employer client as to
British Standards and Codes of Practice which form to use. The architect also needs to be careful when
advising as to the choices to be made regarding the incorpora-
5.06 Bearing in mind the function of codes of practice and
tion (or not) of particular terms and conditions into the building
British Standards, a design which does not comply with rel-
contract, for example, in respect of the insurance of the works.
evant guidance is likely to require justification and explanation
The exercise of reasonable care and skill in such circumstances
if it is not be found to be a negligent design: see the New
may well involve the architect in recommending to the employer
Zealand decision of Bevan Investments Ltd v Blackhall and
client that it should take legal or other appropriate professional
Struthers (No. 2) [1973] 2 NZLR 45. However, in the same
advice.
way that non-compliance with relevant guidance will not auto-
matically lead to a finding of negligence, so rigid adherence
5.12 More generally, an architect may be called upon to make
to relevant guidance will not automatically save an architect
strategic choices and/or to give advice (and probably at a much
from a finding of negligence either, particularly – perhaps –
earlier stage in many cases) as to the procurement route which
where the design is a novel one: Holland Hannen and Cubitts
its employer client should take on a particular project. It will
(Northern) Ltd v Welsh Health Technical Services Organisation
need to exercise reasonable care and skill when doing so (which
(1985) 35 BLR 1.
will include ensuring that the employer client is involved with
the choices to be made and the various alternatives available, so
that any decisions are taken on a properly informed basis). For
Choice of materials example, it will usually be important to ensure that the build-
5.07 Design includes the choice and specification of materials. ing contract is properly executed (and that the standard form
The decision to use new materials or to use a proprietary prod- protections against contractor claims are therefore in place)
uct or system will require the making of appropriate enquiries instead of allowing the project works to be carried out on the
by an architect to ensure its suitability for the job in question: basis of letters of intent only: see Ampleforth Abbey Trust v
see Richard Roberts & Holdings Ltd v Douglas Smith Stimson Turner & Townsend Project Management Ltd [2012] EWHC
Partnership (1988) 46 BLR 50 (negligent investigation by archi- 2137. Moreover, the architect will need to keep its recommen-
tects of specialist linings for effluent tanks) and Michael Hyde dations under review as circumstances change: see Plymouth &
& Associated Ltd v JD Williams & Co Ltd [2001] PNLR 233 South West Co-operative Society Ltd v Architecture, Structure
(negligent acceptance by architects of assurances regarding risk & Management Ltd (2006) 108 ConLR 77 (architects were neg-
of discoloration of stored textiles with selected heating system). ligent in proceeding with their original recommended approach
Breach of the obligation of reasonable care and skill: construction work stages 337

to construction works when they should have realised that that in advance, without any reference to the particular elements
approach would result in a costs overrun). of work being progressed on site at the time. Moreover, if
inspections are confined to the fortnightly or monthly site
meetings, the contractor will know that, at all other times,
Appointment of contractor its work will effectively remain safe from inspection.
5.13 RIBA Standard Forms of Agreement anticipate that no 2 Depending on the importance of the particular element or
building contract should generally be awarded unless competi- stage of the works, the inspecting professional can instruct
tive tenders have first been invited and refer to the following the contractor not to cover up the relevant elements of the
as services commonly provided by an architect: consideration work until they have been inspected: see Florida Hotels
with the employer client of a list of tenderers, the invitation of Pty Ltd v Mayo [1965] 113 CLR. 588. In most cases, how-
tenders and the appraisal of tenders when they are received, and ever, the need for such an instruction is unlikely to arise
consideration with the employer client of the appointment of a because, if the architect is carrying out inspections which
contractor. This process commonly requires choices to be made are tailored to the nature of the works proceeding on site at
between competing tenders and tenderers and, ultimately, may any particular time, the inspections will have been timed in
require the architect to make a recommendation to its employer such a manner as to avoid affecting the progress of those
client as to which contractor should be appointed/selected to works.
carry out the work. All of this calls for the exercise of reason- 3 The mere fact that defective work is carried out and covered
able care and skill by the architect, the demands of which may up between inspections will not, therefore, automatically
embrace the following: amount to a defence to an alleged failure on the part of the
architect to carry out proper inspections; that will depend
1 Being careful not to make positive recommendations about on a variety of matters, including the architect’s reasonable
a contractor which are not justified: Pratt v George Hill & contemplation of what was being carried out on site at the
Associates (1987) 38 BLR 25 (negligent written statement time, the importance of the element of work in question,
by architect that contractor was ‘very reliable’ when, in fact, and the confidence which the architect may have in the
the contractor was anything but reliable). contractor’s overall competence: see Sutcliffe v Chippendale
2 Taking reasonable steps to check as to the skill and relevant & Edmondson (A Firm) (1971) 18 BLR 149.
experience of the contractor and, in an appropriate case, as 4 If the element of the work is important because it is going
to the experience and relevant capabilities of a nominated to be repeated throughout one significant part of the build-
sub-contractor: Equitable Debenture Assets Corp Ltd v ing, such as the construction of a proprietary product or the
William Moss Group Ltd (1984) 2 ConLR 26. achievement of a particular standard of finish to one ele-
3 Taking reasonable steps to check on the financial standing ment of the work common to every room, then the architect
of the contractor: Partridge v Morris [1995] CILL 1095 should ensure that he or she has seen that element of the
(architect negligent because he failed to obtain or consider work in the early course of construction/assembly so as to
a bank reference or a trade credit reference, or failed to form a view as to the contractor’s ability to carry out that
make appropriate enquiries of other architects, to carry out particular task: see George Fischer Holdings Ltd v Multi
a company search, or to obtain a copy of the contractor’s Design Consultants Ltd (1998) 61 Con LR 85.
accounts). Such steps may also include ensuring that suit- 5 However, even then, reasonable examination of the works
able insurance arrangements are put in place by the contrac- does not require the architect to go into every matter in
tor: Pozzolanic Lytag Ltd v Brian Hobson Associates (1999) detail; indeed, it is almost inevitable that some defects will
BLR 267. escape the architect’s notice: see East Ham Corporation v
4 Taking reasonable steps to check the tender for errors and Bernard Sunley & Sons Ltd [1966] AC 406. Nevertheless,
the reasonableness of rates: Tyrer v District Auditor of where he or she does notice defective workmanship and
Monmouthshire (1973) 230 EG 973. draws it to the contractor’s attention, the architect is obliged
to monitor progress to ensure that either the defect is recti-
fied or the value of the defective work is deducted from
6 Breach of the obligation of the contractor’s account: Ian McGlinn v Waltham Forest
Contractors Ltd.
reasonable care and skill: 6 It can sometimes be the case that an employer with a claim
construction work stages for bad workmanship against a contractor makes the same
claim automatically against the architect, on the assumption
that, if there is a defect, then the architect must have been
Periodic inspection (and supervision) negligent or in breach of contract for missing the defect dur-
6.01 An architect’s usual obligation is to make such appropri- ing construction. However, that is a misconceived approach.
ate visits to the site during construction as are necessary for The architect does not guarantee that inspection will reveal
the purposes of inspecting, generally, the progress of the works or prevent all defective work: see Consarc Design Ltd v
and their quality. The obligation is commonly characterised as Hutch Investments Ltd [2002] PNLR 712. It is not appro-
requiring ‘periodic inspection’, not ‘supervision’ – supervision priate to judge an architect’s performance by the result
calling for detailed and continuous oversight. Periodic inspec- achieved.
tion is therefore generally regarded as being less onerous than
supervision, but ‘supervision’ is a term which is nevertheless 6.02 To this summary, it can be added that the engagement of
often referred to as being synonymous with an architect’s duty to a Clerk of Works will not ordinarily diminish the architect’s
monitor the quality of the works under construction. The follow- obligation of periodic inspection, although the traditional demar-
ing summary of the relevant principles is drawn largely from the cation is that a Clerk of Works will be attentive to matters of
judgment of HHJ Peter Coulson QC in Ian McGlinn v Waltham detail, whilst an architect’s concern will be upon more impor-
Forest Contractors Ltd (2007) 111 ConLR 1. tant matters: see Kensington, Chelsea and Westminster AHA v
Wettern Composites Ltd [1985] 1 AER 346. Nevertheless, the
1 The frequency and duration of inspections should be tai- involvement of a Clerk of Works by the architect’s employer
lored to the nature of the works going on at site from time client (and the architect’s own confidence [or not] in the Clerk of
to time: see Corfield v Grant (1992) 29 ConLR 58. It is Works) will be relevant matters wherever the essential complaint
not enough for the architect religiously to carry out an is one of bad workmanship by the contractor; not least in the
inspection of the work either before or after the fortnightly context of the issues discussed in Section 8 below, because an
or monthly site meetings, and not otherwise. The dates of architect will not usually be liable for negligence and/or breach
such site meetings may well have been arranged some time of contract on the part of the Clerk of Works.
338 Architects’ liability

Duty to review own design [1974] AC 727. Moreover, the consequences of such negligence
may be particularly serious if the final certificate is of the ‘con-
6.03 An architect with obligations of periodic inspection (or clusive evidence’ variety so far as the contractor’s materials and
supervision) is required to review its own design as necessary workmanship are concerned, because then the final certificate
until the completion of construction. ‘The architect is under may (dependent upon the wording of the building contract)
a continuing duty to check that his design will work in prac- have the effect of preventing the employer from establishing
tice and to correct any errors which may emerge’: Brickfield liability on the part of the contractor (as in the much-criticised
Properties Ltd v Newton [1971] 1 WLR 862. However, the decision in Crown Estates Commissioners v John Mowlem & Co
obligation to review is generally regarded as being reactive (i.e. Ltd [1994] 70 BLR 1) and of absolving the contractor from his
as requiring a trigger such as the discovery of a defect that calls liability to contribute to the architect pursuant to the 1978 Act
the design into question) rather than proactive (i.e. as something (see Section 8 below).
which an architect, having completed its design work, must do
as a matter of course): see New Islington and Hackney Housing
Association Ltd v Pollard Thomas & Edwards Ltd [2001] PNLR Other certifcates and notices
515 (the duty to review only arises ‘where something occurs
to put the architect on notice that, as a reasonably competent 6.08 All certification obligations upon an architect call for the
architect, he ought to review the design’). Moreover, it will be exercise of reasonable care and skill in addition to the obligation
rare for the duty to review to extend beyond practical comple- to act fairly as between employer and contractor: see, for exam-
tion, but not impossible: see London Borough of Merton v Lowe ple, George Fischer Holdings Ltd v Multi Design Consultants
(1981) 18 BLR 130 (discovery of cracks in ceiling after practi- Ltd (1998) 61 Con LR 85 (negligent issue of certificate of practi-
cal completion triggered duty to review design before issue of cal completion). Similarly, an architect needs to be careful when
final certificate) and University of Glasgow v Whitfield (1988) deciding whether or not to issue, for example, a notice stating
42 BLR 66 (continuing problems with water ingress at practical that the contractor has failed to proceed regularly and diligently
completion triggered an obligation to review in circumstances with the works; and needs to be careful to ensure that his or her
where no final certificate had ever been issued, and the architect own approach as to the way in which such notice provisions
was called back to look at the problem of water ingress three should operate is one which a reasonably competent architect
years after practical completion). would take: West Faulkner Associates v London Borough of
Newham (1992) 71 BLR 1 (architect failed to issue a notice
6.04 The line between reviewing a design and reporting on one’s when he should have done because he took a negligent approach
own mistakes can sometimes be a thin one, but an architect is to the meaning of the relevant clause).
ordinarily under no duty of self-accusation: Chesham Properties
Ltd v Bucknall Austin Project Management Services Ltd (1996)
82 BLR 92 (no duty upon an architect to advise, warn, or inform
Extensions of time
of own actual or potential deficiencies in performance). 6.09 In John Barker Construction Ltd v London Portman Hotel
Ltd (1996) 83 BLR 35, the judge was critical of the architect for
6.05 The duty to review discussed here is, of course, distinct ‘making an impressionistic, rather than a calculated, assessment
from the architect’s quite separate obligation in the construction of the time which he thought was reasonable for the various
work stages of a project to review design information provided items individually and overall’. However, an impressionistic
to him by contractors or specialists. assessment only is not necessarily negligent, and there is little
support for the view that anything approaching a full retrospec-
tive delay analysis to demonstrate the effects of delay must be
Contract administration carried out before an architect can properly certify an extension
of time. An architect is required to act fairly, lawfully, rationally,
Interim certifcates and valuations and logically when considering an extension of time; but what
6.06 There is obviously a link between an architect’s inspection logical analysis is actually required in any particular case will
obligations and his obligations when issuing interim certificates. depend on many different factors and is very much dependent on
As HHJ Stabb QC explained in Sutcliffe v Chippendale & the quality of the information available to enable the assessment
Edmondson (A Firm) (1971) 18 BLR 149: to be made. The proper approach to be taken by an architect to
the assessment of extensions of time was considered at length
the issuing of certificates is a continuing process, leaving by HHJ Seymour QC in Royal Brompton Hospital NHS Trust v
each time a limited amount of work to be inspected and I Hammond & Others (No. 7) (2000) 76 ConLR 148. In that case,
should have though that more than a glance around was to be having referred to the number of established ways in which the
expected. Furthermore, since everyone agreed that the qual- effects of delay might be assessed and some of the difficulties
ity of work was always the responsibility of the architect and involved in making that assessment, it was emphasised:
never that of the quantity surveyor and since work properly
executed is the work for which a progress payment is being that the duty of a professional man, generally stated, is not to
recommended, I think that the architect is duty bound to be right, but to be careful … [T]he fact that he is in the event
notify the quantity surveyor in advance of any work which proved to be wrong is not, in itself, any evidence that he has
he, the architect, classifies as not properly executed, so as to been negligent. His conduct has to be judged having regard
give the quantity surveyor the opportunity of excluding it. to the information available to him, or which ought to have
been available to him, at the time he gave his advice or made
In short, not only must an architect act fairly when discharg- his decision or did whatever else it is that he did.
ing certification obligations, it must also take reasonable care
to ensure that interim valuations of the work, on the basis of So, an approach to assessment which ‘did not depend upon any
which payment will be made to the contractor, are reasonable sort of scientific evaluation of any particular type of material,
and justified by the work done at the time, both in terms of but simply upon impression formed on the basis of previous
quality and amount. experience’ was not negligent on the facts. Indeed,

in practical terms the burden shouldered by a claimant who


Final certifcates contends that an architect or a project manager has been
6.07 As with interim certificates, an architect may also be liable negligent in granting, or being involved in the grant of, an
for negligence in issuing a final certificate: Sutcliffe v Thackrah extension of time for completion of works governed by a
Damages 339

contract in the Standard form is a heavy one: unless the case 3 Where cost of repairs have not already been incurred, a
is very obvious it is most unlikely to succeed. claimant’s intentions as to whether or not he may (or will)
actually carry out the work of repair and/or the use to which
he may (or will) put any award of damages in respect of
Instructions and information cost of repairs may be relevant to the question of whether an
6.10 Cooperation between employer and contractor is vital to award of cost of repairs is fair and reasonable: see McGlinn
satisfactory progress in the construction stages of a project v Waltham Forest Contractors Ltd (2007) 111 ConLR.
and, as the employer’s agent, the architect is often at the sharp 4 Where the only way of rectifying defects or repairing dam-
end of ensuring the smooth running of the project. Issuing ages is by building to a higher standard than that originally
instructions as and when required, and within a reasonable designed for, a claimant may recover for the full cost of
time of the need to issue an instruction arising, is part and par- building to that higher standard without giving credit for
cel of this aspect of an architect’s job; so, too, is the provision any betterment. However, if building to a competent design
of accurate drawings and other information to the contractor in the first place would have cost the claimant more than
in the course of the work in a regular and orderly manner. It the cost of building the defective design which was actu-
is no surprise that an architect needs to do all these things ally built, then credit should normally be given for this: see
on behalf of its employer with reasonable care and skill: see Cooperative Group Ltd v John Allen Associates Ltd [2010]
London Borough of Merton v Leach (Stanley Hugh) Ltd (1985) EWHC 2300.
32 BLR 51. 5 Where, by contrast, the claimant chooses to build to a higher
standard, the claimant cannot properly recover for the
increased costs involved in building to that higher standard:
7 Damages see Ministry of Defence v Scott Wilson Kirkpatrick (2000)
BLR 20.
Measure of damages 6 A claimant who carries out remedial work in reliance on
professional expert advice will probably be regarded as
7.01 The fundamental principle is that a claimant is entitled to be having acted reasonably, but that will not automatically
put into the position, so far as an award of money can do so, in mean that the cost of those works are recoverable: see
which it would have been had the architect not been negligent. Board of Governors of the Hospitals for Sick Children v
For the general principles upon which damages for breach of McLaughlin and Harvey plc (1987) 19 ConLR 25. However,
contract and/or negligence in tort are ordinarily assessed, see where remedial work recommended (non-negligently) by an
Chapters 2 and 3 above. expert has not been yet been carried out by a claimant, the
courts have shown themselves to be more prepared to weigh
Types of loss alternatives and to decide in favour of alternative (reason-
able) approaches where necessary: see McGlinn v Waltham
7.02 Applying the fundamental principle in any particular case Contractors Ltd [2007] EWHC 149, AXA Insurance UK Plc
can lead to an architect being liable for a variety of losses. v Cunningham Lindsey UK [2007] EWHC 3023. (But see
Commonly, however, the losses will fall into one or more of the Cooperative Group Ltd v John Allen Associates Ltd [2010]
three categories discussed below. EWHC 2300 in which – had the claimant succeeded on
liability – the court would nevertheless have allowed the
Cost of repairs claimant to have recovered the costs of its preferred, more
expensive, remedial scheme.)
7.03 The costs of correcting the consequences of an architect’s 7 A claimant who delays in carrying out repairs because it is
negligent errors are at the forefront of the majority of profes- financially (or otherwise) unable to do so will not usually
sional negligence claims against architects. This is true of claims be successfully criticised for failing to mitigate loss; and
in respect of building defects that are alleged to be the product will have its cost of repairs assessed at the later date of trial
of an architect’s negligence (the cost of putting the defects right, rather than the earlier (and conventional) date of breach:
or ‘rectification costs’); it is also true of claims in respect of see Dodd Properties (Kent) Ltd v Canterbury City Council
damage to ‘other property’ alleged to have been caused by an [1980] 1 WLR 433 and Alcoa Minerals of Jamaica Inc v
architect’s negligence (the cost of repairing or replacing dam- Herbert Broderick [2002] 1 AC 371.
aged property, or ‘reinstatement costs’). 8 Losses which are consequential upon the cost of repairs are,
in principle, recoverable by a claimant. Professional fees are
7.04 The following are the key points: an obvious example, as are the costs of alternative accom-
modation or alternative premises where repairs reasonably
1 It must always be fair and reasonable to incur (or to have require the subject premises to be vacated for the duration
incurred) the cost of repairs before an architect will be liable of the repairs.
for the cost of repairs. It very often will be fair and reason-
able to insist on rectification/reinstatement. However, cost
of repairs must always be a reasonable and proportionate
way of remedying the relevant defect or damage: see Ruxley
Wasted expenditure
Electronics and Construction Ltd v Forsyth [1996] 1 AC 7.05 Where an architect’s negligence causes a building project
344 (claimant not entitled to cost of completely rebuilding to be abandoned (for example, as a result of a negligent under-
a six ft deep swimming pool that should have been con- estimate of out-turn costs as in Nye Saunders v Bristow), the
structed 18 inches deeper because, on the facts, demolition wasted costs incurred in progressing the project to that stage
and reconstruction of the swimming pool was out of all will be the principal claim, subject to the duty of mitigation
proportion to the benefit to be gained). and giving credit for the value of any development carried out.
2 Where it is not fair and reasonable to rebuild, a sum in
respect of diminution in value will usually be the appro-
priate alternative or, rarely, a sum in respect of loss of
Overpayments/additional expenditure
amenity. In some cases involving residual blight, it may be 7.06 Where an architect’s negligence causes overpayments to
appropriate for a claimant to recover damages in respect have been made to the contractor, such overpayments are recov-
of diminution in value in addition to cost of repairs: see erable in principle, particularly – for example – if the contractor
George Fischer Holdings Ltd v Multi Design Consultants has become insolvent. Similarly, where an architect’s failure to
Ltd (1998) 61 Con LR 85. design properly leads to the need to expend additional sums, this
340 Architects’ liability

additional expenditure, too, may be recoverable in an appropriate 8.03 Whether the defence of contributory negligence is suc-
case: see Turner Page Music Ltd v Torres Design Associates Ltd cessful will always depend on the facts and upon consideration
[1997] CILL 1263. as to whether the claimant contributed to its own loss by fail-
ing to take reasonable care of its own person or property. The
concept of ‘responsibility’, for the purposes of section 1(1) of
Causation, foreseeability, and mitigation the 1945 Act, includes the concepts both of causative potency
Causation and blameworthiness (or culpability); and the overriding cri-
terion is that any reduction of the claimant’s damages must be
7.07 For any loss to be recoverable from an architect, it must ‘just and equitable’. In that regard, it will always be relevant to
have been caused by the architect’s professional negligence. This consider the extent to which the damage caused by the archi-
is often straightforward, but in a case where the complaint is one tect’s negligence was within the very scope of the risk which
of negligent advice to its employer client or to a third party, it it was his or her obligation to guard against; but even where
will usually be necessary for the employer client or the third wholly within the risk (fire spread because of inadequate fire
party to prove what they would have done (and, in particular, spread design, for example), the extent to which the claim-
that they would have acted differently) had the correct advice ant itself was responsible for the damage remains a relevant
been given: see Hill Samuel Bank v Frederick Brand Partnership consideration (for example, where its contributory negligence
(1993) 45 ConLR 141 (defective panels recommended by an caused the fire in the first place): see Pride Valley Foods Ltd
architect would still have been chosen by the claimant even v Hall & Partners (Contract Management) Ltd (2001) 76 Con
if the architect had properly investigated the suitability of the LR 1 (claimant’s damages reduced by 50% for its contribu-
panels). tory negligence in failing to take reasonable steps to prevent
a fire starting in the factory which then spread out of control
Foreseeability because of the use of panels which the defendants failed to
warn the claimant were highly combustible) and Sahib Foods
7.08 For any loss to be recoverable from an architect it, or – Ltd v Paskin Kyriades Sands (2003) 93 ConLR 1 (claimant’s
more pertinently – its type, must be reasonably foreseeable: see damages reduced by 50% for its contributory negligence, both
Balfour Beatty Construction (Scotland) Ltd v Scottish Power in relation to the outbreak of the fire [which was nothing to
plc (1994) 71 BLR 20 (wastage of concrete and site resources do with the defendant] and the spread of fire [for which the
was a foreseeable consequence of the interruption of electricity defendant was largely to blame]).
supply; the demolition and reconstruction of an aqueduct was
not). However, once the type of loss is reasonably foreseeable,
the architect will ordinarily be liable for the full consequences Civil Liability (Contribution)
of damage of that type: Acrecrest Ltd v W.S. Hattrell & Partners Act 1978 (‘the 1978 Act’)
(1979) 252 EG 1107 (slight damage by heave as a result of tree
8.04 The 1978 Act is a very important piece of legislation.
removal reasonably foreseeable: architects liable for inadequate
The need for rights of contribution has its origins in the
foundations to prevent damage by heave which was far greater
long-standing rule that where a claimant suffers the same
than could have been anticipated).
damage as a result of breaches of contract and/or negligence
on the part of a number of different parties (the single loss
Mitigation [cost of repair] suffered as a result of poor workmanship by
a contractor which should have been picked up on inspection
7.09 A claimant must always take reasonable steps to mitigate
by an architect being a paradigm example), the claimant is at
its loss. It cannot recover for loss which it either ought to have
liberty to recover compensation in full against only one of the
avoided as a result of taking mitigating action or which it has in
‘guilty’ parties if that is what it chooses to do, because each
fact avoided as a result of taking mitigating action.
party with a common liability to the claimant for the same
damage is separately liable to the claimant for the whole of
8 Sharing liability for professional the damage or harm suffered by the claimant. It was the law’s
long-standing failure to permit or provide for contribution
negligence with others between concurrent wrongdoers in that situation which is
the fundamental injustice (the unjust enrichment of the non-
8.01 Leaving aside the claims which an architect may be able to contributing wrongdoer at the expense of the other) that the
make in contract (or in tort) against a sub-consultant (or similar) 1978 Act was intended to address.
for damages amounting to an indemnity in respect of such liabil-
ity as the architect may have to its employer client as a result 8.05 Most discussions of the 1978 Act require a working termi-
of breaches of obligations owed by the sub-consultant directly nology to identify the various parties involved. Unfortunately,
to the architect, there are two main routes by which an architect there is no unanimity in either cases or textbooks as to the
may be able to share its liability for professional negligence terminology which should be used. The terminology used in
with others, namely: this Section therefore adopts the terminology used in Royal
Brompton Hospital NHS Trust v Hammond [2002] 1 WLR 1397,
1 By establishing contributory negligence on the part of the whereby:
claimant; and/or
2 By recovering a contribution (or indemnity) towards its A means the person who has suffered damage and who is the
liability to the claimant from others who are also liable to person with a claim. A is usually the claimant.
the claimant in respect of the same damage for which the B means the person against whom A makes the claim: the
architect is liable. person who is alleged to be liable to A in respect of the
damage suffered by A. B is usually the Defendant and, for
Law Reform (Contributory Negligence) the purposes of this discussion, is the architect.
C means the person from whom B seeks contribution (or
Act 1945 (‘the 1945 Act’) indemnity) in respect of its (B’s) liability to A. C is usu-
8.02 Contributory negligence is a defence to negligence claims ally either a co-defendant with B or a Third Party joined
in tort. It is also a defence to claims in contract where the by B into the proceedings for the purposes of claiming a
architect’s liability in contract is the same as his liability in contribution (or indemnity). For the purposes of this dis-
tort: Forskirings-aktieselskapet Vesta v Butcher [1989] AC 852. cussion, C (and, of course, there may be more than one C)
Sharing liability for professional negligence with others 341

is likely to be the contractor and/or another construction A’s claim against him was good in law: Dubai Aluminium
professional. Co Ltd v Salaam [2003] 2 AC 366. He must also show that
the settlement was reasonable, for example that heads of
loss claimed against him were recoverable from him in law:
The right to contribution J Sainsbury plc v Broadway Malyan (a firm) [1999] PNLR
8.06 The key provisions are section 1(1) of the 1978 Act as 286 (architects’ settlement with building owner was unrea-
‘supplemented’ by section 1(6) and section 6(1). sonable because it had made no allowance for the building
owner’s contributory negligence and it had assumed that the
1 Entitlement to contribution fire brigade would have been able to control the fire when
(1) Subject to the following provisions of this section, any there was only a chance (no more than 35%) that they would
person liable in respect of any damage suffered by another have done so).
person may recover contribution from any other person liable
in respect of the same damage (whether jointly with him or 8.10 ‘may recover contribution from any other person liable
otherwise)… …’ [i.e. C]: It does not matter that C has ceased to be liable
(6) References in this section to a person’s liability in in respect of the damage suffered by A since the time when
respect of any damage are references to any such liability the damage occurred, ‘unless he ceased to be liable by virtue
which has been or could be established in an action brought of the expiry of a period of limitation or prescription which
against him in England and Wales by or on behalf of the per- extinguished the right on which the claim against him in respect
son who suffered the damage; but it is immaterial whether any of the damage was based’: 1978 Act, section 1(3). So B is not
issue arising in any such action was or would be determined prevented from claiming contribution from C if, by the time the
(in accordance with the rules of private international law) by contribution claim is made (which is very often the position),
reference to the law of a country outside England and Wales. the relevant limitation period applicable to A’s claim against C
… 6 Interpretation (or C’s liability to A) has expired, because the ordinary effect
(1) A person is liable in respect of any damage for the of a limitation defence is that it only bars the remedy, and does
purposes of this Act if the person who suffered it (or anyone not extinguish the right on which the claim is based. It follows
representing his estate or dependents) is entitled to recover that the proviso is of narrow scope. Moreover, the expiry of the
compensation from him in respect of that damage (whatever 15-year long-stop provided for by section 14B of the Limitation
the legal basis of his liability, whether tort, breach of contract, Act 1980 does not extinguish the right to bring a claim in negli-
breach of trust or otherwise). gence; it only bars the remedy: Financial Services Compensation
Scheme Ltd v Larnell (Insurances) Ltd [2006] PNLR 13.
8.07 ‘liable’: ‘The 1978 Act is drafted on the basis that the word
‘liability’ is used potentially in the widest possible sense’: R A 8.11 ‘… in respect of the same damage’
Lister & Co Ltd v E G Thomson (Shipping) Ltd (No. 2) [1987]
3 All ER 1032. It embraces a liability of B to A, and C to A, 1 These are the most important words in the 1978 Act and
whatever the legal basis of the liability (whether in tort, breach were the focus of the decision in the architect’s case of
of contract, breach of trust or otherwise), and it embraces any Royal Brompton Hospital NHS Trust v Hammond [2002]
liability which could be established by A in an action brought 1 WLR 1397.
against either B or C in England and Wales. It includes a liability 2 Lord Bingham stated:
under the DPA 1972: McKenzie v Potts (1997) 50 ConLR 40.
‘It is … a constant theme of the law of contribution
8.08 ‘damage’: does not mean ‘damages’. The fact that the from the beginning that B’s claim to share with others
damages recoverable by A from B or C may be different does his liability to A rests upon the fact that they (whether
not mean that B and C’s liability is not a common liability in equally with B or not) are subject to a common liabil-
respect of the same damage: see Eastgate Group Ltd v Lindsay ity to A … the words “in respect of the same damage”
Morgan Group Inc [2002] 1 WLR 642. ‘Damage’ means ‘the emphasise the need for one loss to be apportioned
harm suffered by the ‘another person’ [i.e. A], to use the phrase among those liable.’
in section 1(1), for which that person is entitled to recover com-
pensation’: Birse Construction Ltd v Haiste Ltd [1996] 1 WLR 3 The need for a shared or common liability of B and C to A
675 (a passage approved in Royal Brompton Hospital NHS Trust emphasises that the sufferer of the damage ‘inflicted’ by B
v Hammond [2002] 1 WLR 1397). and C must be the same person as the person who is entitled
to recover the compensation for that damage.
8.09 ‘any person liable [i.e. B] in respect of any damage suffered 4 The right to contribution arises not only in respect of a
by another person [i.e. A]’: common liability of B and C for the same damage, but also
in respect of a common liability of B and C for part of the
1 It does not matter that B has ceased to be liable in respect same damage. Lord Bingham framed the relevant questions
of the damage suffered by A since the time when the dam- to be asked as follows:
age occurred – for example, as a result of compromising the
claim or as a result of the fact that the limitation period has ‘When any claim for contribution falls to be decided the
since expired against him – provided that ‘he was so liable following questions in my opinion arise. (1) What dam-
immediately before he made or was ordered or agreed to age has A suffered? (2) Is B liable to A in respect of that
make the payment in respect of which the contribution is damage? (3) Is C also liable to A in respect of that dam-
sought’: 1978 Act, section 1(2). In short, B’s liability to A age or some of it? … I do not think it matters greatly
does not need to be a continuing or present liability at the whether, in phrasing these questions, one speaks (as the
time the contribution claim is made. 1978 Act does) of “damage” or of “loss” or “harm”,
2 Where B has reached a bona fide settlement with A, there provided it is borne in mind that “damage” does not
is no need for B to prove his own liability to A in order mean “damages” … and that B’s right to contribution
to be able to claim contribution from C, provided that ‘he by C depends on the damage, loss or harm for which B
would have been liable assuming that the factual basis of is liable to A corresponding (even if in part only) with
the claim against him could be established’: 1978 Act, the damage, loss or harm for which C is liable to A.
section 1(4). So, B does not need to prove the facts which This seems to me to accord with the underlying equity
A alleged against him. However, he does have to show that of the situation: it is obviously fair that C contributes
342 Architects’ liability

to B a fair share of what both B and C owe in law to A, claimant simply could not be established because the claim-
but obviously unfair that C should contribute to B any ant employer’s claim against the contractor was barred by
share of what B may owe in law to A but C does not.’ the issue of that certificate.

5 So, in Royal Brompton Hospital itself, the nature of the 8.13 The requirement to pay ‘compensation’. Not only must
damage suffered by a hospital by reason of an architect’s C be liable to A, but C’s liability to A must be to pay ‘compen-
breaches, namely the weakening or impairment of its pros- sation’ to A. This, too, was very important in the CRS case and
pects of success as against the main contractor was quite arguably provided a distinct reason why the professional team’s
different to the damage suffered by the hospital by reason contribution claim against the contractor failed. In the CRS case,
of the main contractor’s breaches, namely wrongful delay because of the contract agreed between Wimpey and the Co-op,
in practical completion. Indeed, a claim against an architect Wimpey’s only liability to the Co-op in respect of the fire was
for wrongful certification is in respect of damage done to to reinstate the property (the Works) damaged by the fire using
a building owner’s relations with the contractor and is not the insurance proceeds to do so. This was not a liability to pay
the same damage as the damage suffered by the building compensation and, for that reason, could not give rise to rights
owner as a result of negligence by the architect in failing of contribution. Lord Rodger dealt with the matter succinctly:
to prevent defective work. As Lord Bingham stated:
Under section 1(1) of the [Act] a person who is liable in
‘It would seem to me clear that any liability the respect of damage can recover contribution from any other
Employer [Hospital] might prove against the Contractor person who is liable in respect of the same damage. It follows
would be based on the Contractor’s delay in perform- that the appellants can recover contribution from Wimpey in
ing the contract and the disruption caused by the delay, respect of the fire damage to the works only if Wimpey were
and the Employer’s damage would be the increased “liable in respect of” the fire damage. Section 6(1) provides
cost it incurred, the sums it overpaid and the liquidated that a person is liable in respect of any damage if the person
damages to which it was entitled. Its claim against the who suffered it “is entitled to compensation from him in
Architect, based on negligent advice and certification, respect of that damage”. So the appellants can recover a con-
would not lead to the same damage because it could not tribution from Wimpey only if CRS were “entitled to recover
be suggested that the Architect’s negligence had led to compensation from [them] in respect of” the fire damage to
any delay in performing the contract’. the works.
On no conceivable construction of section 6(1) can it be
6 A claim by an employer against a contractor for negligent said that a person who is liable to restore damaged work is a
site investigation services and a claim by the employer person from whom the employer is “entitled to recover com-
against insurance brokers for failure to insure against the pensation” in respect of the fire damage to the works.
contingency were not claims for ‘the same damage’ entitling
the insurance brokers to claim a contribution against the Lord Hope’s views were similar:
contractor: see the Royal Brompton Hospital case in holding
that Hurstwood Developments Ltd v Motor and General & The employer has no claim for compensation against the con-
Andersley & Co Insurance Services Ltd [2001] EWCA Civ tractor. All he can do is insist that the contractor must proceed
1785 was ‘wrongly decided’. with due diligence to carry out the reinstatement work and
must authorise the release to him of the insurance monies.
The contractor has no claim for compensation against the
Restrictions on the right to contribution employer. All he can do is insist that the employer must use
8.12 C must have a substantive liability to A: Co-operative the insurance monies for payment of the cost of carrying out
Retail Services v Taylor Young Partnership Ltd [2002] 1 WLR the reinstatement work … The ordinary rules for the payment
1419. of compensation for negligence and for breach of contract
have been eliminated.
1 In the CRS case, C (Wimpey) was employed by A (the
Co-op) to build a new HQ, which burned down shortly 8.14 Contractual limitation or exclusion clauses. One of the
before practical completion. Under the joint insurance reasons why the CRS case is important is because it serves as
arrangements under the relevant JCT Contract, Wimpey an important reminder that the 1978 Act essentially respects
and the Co-op were coinsureds in respect of the risk of fire. contractual arrangements between the parties which are in place
The Co-op alleged that the fire was the result of negligence at the time damage is sustained by A. Subject to satisfying the
on the part of the professional team: the architect (Taylor requirements of reasonableness or fairness under UCTA and/or
Young) and the M&E engineer (Hall) – collectively ‘B’ in the Consumer Rights Act 2015, where appropriate, such limita-
the terminology of this section. The professional team (B) tions or exclusions are effective in terms of placing an upper
sought a contribution from Wimpey, alleging that Wimpey’s limit on C’s liability to contribute to B. In a professional neg-
negligence or breach of contract had also caused or contrib- ligence context, this is of very considerable importance where
uted to the fire. The professional team’s claim for contribu- a professional seeks – by contract – to limit his or her liability
tion failed. It failed on a number of interrelated grounds, to A to a specific sum, as in Moores v Yakeley Associates Ltd
but the essence of the argument which was at the forefront (1998) 62 ConLR 76 (discussed in Section 4 above) or, perhaps
of the reasoning in the House of Lords was that Wimpey more usually, to the amount of his or her professional indem-
was simply never liable to the Co-op, either in negligence nity insurance cover – as in, for example, both Clause 7.2.1 of
or in contract, for the fire damage sustained by the Co-op, the ‘Standard Conditions of Appointment for an Architect 2010
because the effect of the contractual arrangements for joint (2012 Revision)’ and Clause 7.2.1 of the ‘Standard Professional
insurance was to eliminate (by agreement between A and Services Contract 2018’. (And see section 2(3) of the 1978 Act
C) ‘the ordinary rules for the payment of compensation for in this context.)
negligence and for breach of contract’ as between Wimpey
and the Co-op. 8.15 Net contribution clauses. Another limitation (or control)
2 In Oxford University Fixed Assets Ltd v Architects Design mechanism is a net contribution clause (‘NCC’), sometimes
Partnership (1999) 64 ConLR 12, the architect’s claim called a ‘proportional liability clause’ or an ‘equitable contribu-
for contribution against the contractor also failed – this tion clause’. An NCC essentially seeks to do ‘what it says on the
time because the effect of the issue of a final certificate tin’ which – so far as the liability of B and/or C to A is concerned
by the architect was that the contractor’s liability to the – is to limit the professional’s liability to A to a proportional or
Sharing liability for professional negligence with others 343

proportionate liability only; in other words, to a liability which of further elaboration’ and decided, accordingly, that UCTA
effectively seeks to render any claim by B against C for contri- did not apply so as to impose a ‘fair and reasonable’ test in
bution otiose because – if the clause does its job properly – B’s the case before him. In relation to the second issue, Lord
maximum liability to A reflects B’s fair and reasonable contribu- Glennie was clear that – even if he was wrong in relation to
tion to the damage, no more and no less. In other words, such the first issue – nevertheless, the NCC was fair and reason-
a clause seeks to be an express contractual modification of the able on the particular facts of the case.
usual consequences of joint and several liability.
It is a relevant matter that the clause is part of a body
8.16 Are NCCs effective? The short answer is ‘Yes’; but where of conditions drafted by a professional body and is
NCCs must satisfy the statutory requirement of reasonableness widely used within the profession and in the industry.
or of fairness, it is likely to be important that NCCs are fully Albeit that they have attracted controversy, this has not
explained to the client and to ensure that they are fully under- stopped them being used. The [claimants] themselves
stood by the client if they are to be an effective contractual have shown a willingness to contract on the basis of
regulation of rights of contribution in place of the 1978 Act, the ACE Conditions. Further, and perhaps of greatest
either in a business liability context or vis-à-vis consumers. The importance, it is open to the [claimants], who choose
following can be highlighted: their contractors and consultants, to ensure that proper
insurance is in place in the event that one or more of
1 Contractual regulation (or indeed exclusion) of rights of them is in breach of contract or duty. If proper insurance
contribution is expressly contemplated by Section 7 of the is in place, then it should be possible in the event of
1978 Act. insolvency of the contractor or consultant to go against
2 NCCs are commonplace in many standard form contracts the insurer. I see nothing unfair or unreasonable in the
used in the construction and engineering industry. The client taking the risk that he has adequately covered
standard forms of appointment (or of collateral warranty) himself against the possible insolvency of those whom
of an architect or an engineer published by RIBA or ACE he himself has appointed.
all contain NCCs. Clause 7.3 of the ‘Standard Conditions
of Appointment for an Architect 2010 (2012 Revision)’ and 6 In West & West v Ian Finlay & Associates [2014] EWCA
Clause 7.3 of the ‘Standard Professional Services Contract Civ 316, in which architects relied on an NCC vis-à-vis
2018’ are typical examples. Such clauses are relied on their ‘consumer’ clients in relation to works on residential
by consultants, and more especially by their professional property, the Court of Appeal in England was satisfied
indemnity insurers, to seek to shift the risk of the effects of (reversing the decision of the trial judge) that the NCC
insolvency of other liable parties away from the consultant was neither unfair for the purposes of the Unfair Terms in
and on to the employer. Consumer Contract Regulations 1999, nor unreasonable for
3 In its Guide to the 2018 set of RIBA Professional Services the purpose of UCTA, and was therefore an effective limita-
Contracts, the NCC is described as being ‘a key limitation tion on the architects’ liability.
of liability for Architects and Consultants’, and the Guide
cautions against agreeing to the removal or modification of
the NCC. As the Guide explains, if a court finds an architect
Assessment of the amount of contribution
60% liable for damages and a contractor 40% liable for 8.17 Apportionment is pre-eminently a question of fact in each
damages, the inclusion of an NCC means that ‘the Client case, and reported cases on apportionment are only examples of
is restricted to claiming 60% from the Architect/Consultant how responsibility or liability may be split in any particular case.
and would have to bring a separate claim for the 40% Extracting any general principles from cases on apportionment
against the Contractor’. is difficult. Nevertheless:
4 In the Scottish case of Glasgow Airport Limited v Messrs
Kirkman & Bradford [2007] CSOH 52, there was no argu- 1 The question of apportionment between B and C under the
ment that the NCC was effective; it being accepted by both 1978 Act should be considered separately from the assess-
parties that it was. (The argument was as to the proper ment of contributory negligence as between A on the one
construction of the clause.) In the more recent Northern hand, and B and C on the other: Fitzgerald v Lane [1989]
Irish decision of Radius Housing Association Limited v AC 328.
JNP Architects (& Others) [2018] NIQB 57, all parties 2 The concept of ‘responsibility’, for the purposes of
similarly proceeded on the premise that the NCC was section 2(1), includes the concepts both of causative
enforceable. potency and blameworthiness (or culpability): Madden v
5 In Langstane Housing Association Limited v Riverside Quirk [1989] 1 WLR 702. However, the overriding criterion
Construction Limited (& Others) [2009] CSOH 52; (2009) is that apportionment must be ‘just and equitable’, and this
124 ConLR 211, the Scottish Court of Session considered allows the court to have regard to other matters, includ-
Clause B8.2 of the ACE Conditions of Engagement, B(1). ing breaches of duty or conduct, which are non-causative:
The court considered two issues of particular relevance: (i) see Re-Source America International Ltd v Platt Site
whether the NCC was a term of the contract which ‘pur- Services and Barkin Construction Ltd [2004] EWCA (Civ)
ports to exclude or restrict liability for breach of duty aris- 665, followed in Brian Walker Partnership PLC v HOK
ing in the course of any business’ within the meaning and/ International Ltd [2006] PNLR 5. So, as Lord Nicholls
or for the purposes of Section 16(1) of the Unfair Contract remarked in the Dubai Aluminium case:
Terms Act 1977 (NB. Section 16 is in Part II of UCTA
which applied to Scotland only); and (ii) whether, if it was, ‘if one of three defendants equally responsible is
it was fair and reasonable to incorporate the term in the insolvent, the court will have regard to this fact when
contract. In relation to the first issue, Lord Glennie agreed directing contribution between the two solvent defend-
with the engineers’ argument that the NCC did not seek to ants. The court will do so, even though insolvency has
exclude or restrict liability for the engineers’ breach of duty: nothing to do with responsibility’.
‘it simply sought to ensure that the [engineers] were only
held liable for the consequence of their own breach of duty 3 Rules of thumb are dangerous, but in Carillion JM Ltd v
and were not held liable, by the doctrine of joint and several PHI Group Ltd [2011] EWHC 1379, the court suggested
liability, for the breaches of duty by other contractors and that the conventional approach in construction defects (bad
consultants’. Lord Glennie felt that there was considerable workmanship) cases was to apportion liability on the basis
force in this argument and stated that ‘the point is incapable of between 66% (two-thirds) and 80% to the contractor, and
344 Architects’ liability

of between 20% and 33% (one-third) to the construction building projects) the relevant limitation period is 12 years from
professional. date of breach.

8.18 For specific apportionment examples, see Equitable


Debenture Assets Corp Ltd v William Moss Group Ltd (1984)
(b) Tort
2 ConLR 1 (liability for defective design of curtain wall was 9.05 For professional negligence claims in tort in respect of
apportioned 75% to the specialist design sub-contractors and personal injury, the primary limitation period claims is ordinar-
25% to the architects; liability for bad workmanship to the ily three years either from the date when personal injury was
parapet walling was apportioned 80% to the specialist sub-con- caused or three years after the ‘date of knowledge’ (Limitation
tractors, 15% to the main contractors, and 5% to the architects), Act 1980, section 14), if later. This time limit may also be disap-
Oxford University Press v John Stedman Design Group (1990) plied by the courts in certain circumstances.
34 ConLR 1 (liability for three different defects in a warehouse
floor – cracking, surface crazing, and edge breakdown – were 9.06 For professional negligence claims in tort in respect of
apportioned as between the architect and the contractors respec- physical damage to property, or where the harm suffered is in
tively, on the basis of 60:40 (cracking); 50:50 (surface crazing), the form of pure economic loss, the primary limitation period is
and 0:100 (edge breakdown), and Board of Trustees of National ordinarily six years from the date of damage/harm or, if later,
Museums and Galleries on Merseyside v AEW Architects & three years from the date when the claimant first knows about
Designers Ltd [2013] EWHC 2403 (liability apportioned 75% the damage and certain material facts about it: Limitation Act
to the architect and 25% to the contractor). 1980, section 14A (as inserted by the Latent Damage Act 1986).
However, this is all subject to a long-stop provision which
prevents an action for damages for professional negligence in
Special time limit for tort being brought after the expiry of 15 years after the act or
claiming contribution omission, which is alleged to be negligent and to which the
8.19 There is a special limitation period for contribution claims: damage suffered is alleged to be attributable: Limitation Act
two years from the date on which the right (B’s right) to contri- 1980, section 14B.
bution accrued: section 10(1).

8.20 In circumstances where B is held liable in respect of


10 Liability in Scots law1
damage to A, either by a judgment given in any civil proceed-
10.01 The liability of an architect to pay damages, and the
ings, or an award in any arbitration the right to contribution
measure of damages, for professional negligence in Scots law
accrues on the date of the judgment, or award, as the case may
is nearly identical to that in England and Wales. Liability may
be: 1978 Act, section 10(3). This means a judgment or award
arise from breach of contract at common law, from delict (fault
which ascertains the quantum, and not merely the existence, of
and negligence) at common law, and from breach of statutory
the relevant liability: Aer Lingus PLC v Gildacroft Ltd [2006]
duty. Since liability will be fact-specific, previous decisions are
1 WLR 1173.
of little assistance beyond general statements of principle.
8.21 In circumstances where B ‘makes or agrees to make any
10.02 The test in Scots law for professional negligence is
payment to one or more persons in compensation’ for the dam-
whether the architect has exhibited the standard of skill and
age, the right to contribution accrues on ‘the earliest date on
care to be expected of an architect of ordinary competence. In
which the amount to be paid by him is agreed between him (or
practice, the architect must display the reasonable skill and care
his representative) and the person (or each of the persons, as the
to be expected of a properly qualified and competent architect
case may be) to whom the payment is to be made’: 1978 Act,
experienced in carrying out services for projects of a similar
section 10(4). Time runs from the date of the agreement, not
size, scope, and complexity to the project in question. Expert
from the date of the formal consent order: Knight v Rochdale
evidence is critical. The court may be faced with two bodies
Healthcare NHS Trust [2004] 1 WLR 371.
of reliable and credible testimony supporting differing opinions
as to whether the course adopted was a practice which would
9 When liability for professional have been followed by a responsible body of architects; in
those circumstances, it will not prefer one body of responsible
negligence is barred by lapse professional opinion to another. As a result, the claim will fail,
of time unless in an exceptional case where a practice followed by
responsible architects could be said not to stand up to rational
9.01 The Limitation Act 1980 imposes time limits within which analysis because it was not reasonable or responsible or could
litigation or arbitration must be commenced if the relevant claim not be logically supported (Stewart Milne Westhill Ltd v Halliday
is not to be statute barred. Fraser Munro [2016] CSOH 76).

9.02 Time limits for claims under the DPA 1972 and for claims 10.03 The scope of an architect’s duty is always a matter of the
for contribution under the 1978 Act have already been discussed contractual interpretation of the appointment, including whether
above. an architect appointed as lead consultant assumes responsibility
for work carried out by other parties. For example, the appoint-
9.03 So far as claims for professional negligence are concerned, ment of an architect as lead consultant with responsibility for
the relevant time limits vary according to whether the claim progress and design will embody the architect’s usual responsi-
is made in reliance upon a contractual duty of care or a tortu- bilities for overall co-ordination of the design works and to use
ous duty of care. The following is a brief summary only, and reasonable endeavours rather than an acceptance of liability for
reference also be made to Chapters 2 and 3 above in respect of anything that might ultimately go wrong with the design, no
contract and tort. matter what its cause (Midlothian Council v Bracewell Stirling
Architects [2018] CSIH 21).
(a) Contract
9.04 For professional negligence claims in contract, the relevant
limitation period is ordinarily six years from date of breach.
Where the contract has been entered into as a deed or under
seal (which is now common for architect appointments on large 1 This section was written by Andrew Bowen QC.
Liability in Scots law 345

10.04 The Scottish equivalent of proceedings for contribution, must be brought within five years of the damage. In the case
contribution among joint wrongdoers under the Law Reform of concealed damage, time starts to run only when the damage
(Miscellaneous Provisions) (Scotland) Act 1940, applies only is discovered or becomes discoverable, but the Scottish courts
where, in an action of damages for loss or damage arising from have interpreted the relevant damage in some circumstances
a wrongful or negligent act or omission, two or more persons as the date that wasted expenditure was incurred, even where
are found jointly and severally liable in damages by a court. As the claimant did not know that there had been a breach of duty
a result, a statutory claim for contribution cannot be made in (Midlothian Council v Raeburn Drilling and Geotechnical
the absence of a court decree establishing the primary liability. Limited [2019] CSOH 29). When in force, section 5 of the
Prescription (Scotland) Act 2018 will amend this situation.
10.05 Scotland’s scheme of time limits for suing (limitation) However, the issue of interim certificates by the architect may
and extinction of claims by lapse of time (prescription) is amount to relevant error, which suspends the prescriptive period
contained in the Prescription and Limitation (Scotland) Act (Loretto Housing Association Ltd v Cruden Building & Renewals
1973 (as amended), and claims for breach of contract or duty Ltd [2019] CSOH 78).
34
Professional disciplinary proceedings
JAMES HATT

1 Introduction 1.06 If a complainant is listened to with respect, and their com-


plaint is acknowledged and handled swiftly, it may be possible to
1.01 This chapter is intended to act as a guide to what happens prevent the cost (in terms of time, money, and stress) that more
when an architect is faced with disciplinary proceedings brought formal legal proceedings almost inevitably entail.
under one of the codes of professional conduct that govern the
practice of an architect and to provide some general guidance on Professional indemnity insurance
how to deal with such proceedings. Further information on the
codes of professional conduct is set out in Chapter 39. 1.07 An architect should also be aware of the terms of their
professional indemnity insurance (see also Chapter 35). This
is relevant to complaints and disciplinary proceedings in four
Complaints key respects.
1.02 Disciplinary proceedings normally start because someone
1.08 First, professional indemnity insurance generally works on
has made a complaint about an architect. In the first instance,
a ‘claims made’ basis, i.e. cover is provided in respect of the
such complaints will often be made directly to the architect in
period in which the claim is made, not the period in which the
question.
act or omission of the architect complained about took place. An
architect will likely be required, under the terms of their policy,
1.03 Both the Code of Conduct of the Architects Registration
to inform their insurers of any claims made, or of any circum-
Board (the ARB Code) and the Code of Professional Conduct of
stances likely to give rise to a claim, as soon as possible after
the Royal Institute of British Architects (the RIBA Code) require
becoming aware of them. Complaints from clients will likely
architects to have written complaints procedures: see ARB Code
constitute matters likely to give rise to a claim.
Standard 10 and RIBA Code 8.1.
1.09 Second, the terms of the professional indemnity insurance
1.04 Quite apart from these professional obligations, there is
might require the architect not to make any admission or offer
good reason for architects to have complaints procedures in
to settle a complaint without insurers’ approval. There can be
place – and to follow them – not least to reduce the risk of a
a difficult line to tread in trying to deal with a complaint con-
complaint being escalated either by way of professional negli-
structively without admitting any fault: this will be made easier
gence proceedings or disciplinary proceedings.
by prompt notification of the matter to insurers and making sure
they are kept fully informed.
1.05 The Guidance Note to RIBA Code 8.1 suggests that such
procedures should be appropriate to the scale and nature of the
1.10 Third, in addition to covering claims for damages, some
architect’s practice, and that architects should handle disputes
insurers are also prepared to cover some of the costs of attend-
and complaints promptly. The ARB also has helpful guidance
ing a disciplinary hearing, should this later become necessary.
on handling complaints from clients:
1.11 Fourth, the architect should consider referring a serious
● If the complaint is in writing, you should try to acknowledge
complaint or any disciplinary proceedings to a solicitor or barris-
it immediately.
ter who has experience in such matters. Professional indemnity
● Tell your client who will be dealing with the complaint, and
insurers have good relationships with lawyers who specialise
let them know how long it is likely to take.
in professional negligence proceedings and may also be able
● Find out what the client expects from the complaints pro-
to recommend lawyers who work in the field of professional
cess, and whether their expectations are reasonable.
discipline.
● If your client asks for a meeting, try to arrange one as
quickly as possible.
● Open a complaint file, and keep a record of the steps you 2 Disciplinary proceedings
take to settle the matter.
● Make sure you keep your client informed of the progress of under the ARB and RIBA
their complaint. rules – introduction
● Finally, remember that dealing with complaints quickly
helps to keep your client’s good will and is often the most 2.01 Both the ARB and RIBA follow a two-stage process in
cost-effective solution for you. response to complaints they receive.

347
348 Professional disciplinary proceedings

2.02 First, there is an investigation carried out by a panel which there is evidence to support allegations that would, if proved to
decides whether the complaint should proceed further. This be true, support a finding of unacceptable professional conduct
part of the process is conducted in writing. or serious professional incompetence. The IP will consider evi-
dence that is provided to it, including the evidence provided by
2.03 Second, if the complaint is not dismissed at the investiga- the architect, but it will not decide whether the allegations are
tion stage and is instead deemed worthy to continue further, then proved or not, simply whether there is a realistic prospect that a
there will be a formal hearing, not unlike a hearing in Court, finding of unacceptable professional conduct or serious profes-
at which there can be oral evidence, oral argument, and a final sional incompetence would be made if the matter went to a final
decision. hearing. The upshot of this is that allegations against architects
that are not very strong may nonetheless be permitted by the IP
2.04 The overall structure of the processes is similar for the to proceed to a final hearing.
ARB and RIBA, but there are subtle differences between the
two procedures as set out below. 3.07 After carrying out its investigations, the IP will make one
of three final decisions:
2.05 Although the investigation stage is designed to filter out
unmeritorious complaints, this does not always happen. The 1 Require no further action;
writer has had experience of successfully arguing at an ARB 2 Require cautionary advice to be given to the architect con-
hearing that the architect had no case to answer on a number cerning their future conduct and/or competence; or
of counts that the ARB had considered, after argument at the 3 Refer the complaint to the PCC.
preliminary stage, did raise a case to answer. The writer has
also had experience (although not recently) of appearing at a 3.08 If the IP decides not to refer a complaint to the PCC, the
RIBA hearing which started with the hearing board dismissing architect or the complainant can request an independent third-
the charge and apologising to the architect that the proceedings party review. The grounds for such a review are that the IP’s
had got so far. As with all human endeavours, neither the RIBA procedure was unlawful, unfair, and/or contrary to the ARB’s
nor the ARB procedure is fool-proof. rules or published guidance. Such a review should be requested
within 30 days of notification of the IP’s decision. There is no
fee for a third party review.
3 ARB disciplinary proceedings
3.09 The IP will consider the outcome of the third party review
Investigation stage and may then either take no further action (if so, giving reasons)
or review its decision.
3.01 When the ARB receives a complaint, it will first determine
whether the complaint is one that meets the ARB’s standard of
acceptance for allegations. This just means that the ARB will Hearing stage
weed out the most fanciful or irrelevant complaints. Any com- 3.10 If the IP decides to refer an allegation to the PCC, then it
plaint that passes this hurdle becomes an allegation. It will be will issue a formal report setting out the facts and the ‘Charge’,
formally formulated by the ARB and is then sent to the architect i.e. the charge that the architect is guilty of unacceptable profes-
for comment. This is the architect’s first chance to put their side sional conduct, and/or serious professional incompetence (and/or
of the story to the ARB. has been convicted of a criminal offence other than an offence
which has no material relevance to fitness to practise as an archi-
3.02 At this stage, the matter will be handled by the ARB’s tect). The report will include documents and the name of any
Investigations Panel (IP). This is a panel of three or five individ- witness to be called together with a summary of their evidence.
uals which always has at least one architect and a lay majority:
a typical panel consists of one architect and two lay members. 3.11 Not less than 49 days before the date of the hearing, the
PCC will give notice of the date, time, and place of the hear-
3.03 The IP meets in private and will not hear oral evidence ing of the Charge together with a copy of the IP’s report. The
except in exceptional circumstances. The ARB’s Registrar may, hearing is likely take place in London. During the COVID-19
in consultation with the IP, appoint an ‘Inquirer’. The Inquirer’s lockdown, the ARB arranged for hearings to take place by video
role is to provide advice and guidance to the ARB on the archi- conferencing technology.
tectural elements of the case.
3.12 The PCC might make further directions in preparation for
3.04 The task for the IP is to consider whether the architect the hearing, but the standard directions are as follows.
has a case to answer and whether it is in the public interest
for the case to go to a hearing before the Professional Conduct 3.13 First, the ‘Presenter’, i.e. the ARB’s prosecuting lawyer,
Committee (PCC). must serve their documents (including witness evidence) not less
than 35 days before the hearing.
3.05 The IP will not make this decision without first considering
the material submitted by the architect in their defence. The IP 3.14 Then, if the architect intends to plead not guilty to the
might issue a preliminary decision and invite the complainant charge, they must serve their documents not less than 21 days
and the architect to comment on that decision before making before the hearing date. These documents are: (a) particulars
its final decision. Under the previous ARB rules, the IP would of the defence; (b) written statement(s) or other documents or
always issue a preliminary decision which, in the writer’s expe- plans; and (c) the name and address of any witnesses, and sum-
rience, was usually very similar to the final decision. Under the maries of their evidence (in practice, witness statements similar
current rules, however, the ARB’s guidance suggests that pre- to the kind used in civil court proceedings can be used).
liminary decisions will tend to be issued only in more complex
cases, for example, where an Inquirer has been appointed, where 3.15 Neither the Presenter nor the architect can call a witness
the parties’ submissions have not fully addressed the issues, or or rely on evidence if it was not notified or served at the right
where the architect has been involved in previous disciplinary time, unless the other side agrees or the Hearing Panel permits
proceedings. them to.

3.06 It is important to realise that the ‘case to answer’ test that 3.16 If the architect cannot attend the hearing, then they should
the IP has to apply is not a difficult test for a complaint to pass. let the ARB know as soon as possible and request an adjourn-
A decision that an architect has a case to answer only means that ment to another date. Not attending the hearing will not mean
ARB disciplinary proceedings 349

that it does not go ahead: the hearing may take place in the that may be imposed by the PCC are, in increasing order of
absence of the architect if the Hearing Panel considers that the seriousness, as follows:
architect has been given an adequate opportunity to appear and
has not provided sufficient reason for their absence. (If a hearing 1 A reprimand. This is suitable for the least serious cases
goes ahead in the architect’s absence, and, in fact, the architect where the PCC simply considers it appropriate to mark an
did have a good reason for non-attendance, then they can apply architect’s conduct or competence as being unacceptable.
to the PCC for a re-hearing by submitting a sworn statement This may be appropriate in cases where there is no serious
and medical or other relevant evidence explaining the situation effect on clients or the public, the architect has a previ-
within 28 days of notice of the decision.) ously good disciplinary record, and the architect has taken
corrective steps. A reprimand remains permanently on an
3.17 The hearing will be in front of a Hearing Panel of at least architect’s record, but will only be on the ARB’s website
three. This is likely to be a legally-qualified chair and two lay for one year.
members. No one who sat on the IP can sit on the Hearing Panel. 2 A fine, up to a maximum of £2,500 per charge (i.e. per
charge of unacceptable professional conduct or seri-
3.18 The final hearing is conducted in a formal manner. For ous professional incompetence) and a maximum of two
example, the proceedings start with the architect being asked charges. This is for more serious offences, for example,
whether they plead guilty or not guilty to the charge. Witnesses where there is limited remorse or where the architect has
who attend the hearing will give evidence on oath, just as they benefitted financially. A fine remains permanently on an
would in Court. The proceedings are in public unless the Hearing architect’s record, but will only be publicised for two
Board orders otherwise. years.
3 Suspension from the Register of Architects for up to
3.19 The burden of proof lies on the Presenter, just as the bur- two years. This is for even more serious offences where a
den of proof lies on the prosecution in criminal proceedings. reprimand or penalty order would be insufficient to protect
However, unlike in criminal proceedings, where the charge either the public or the reputation of the profession. An
needs to be proved beyond reasonable doubt, a charge before architect who is suspended from the Register cannot use
the PCC only needs to be proved on the civil standard of proof, the title ‘architect’ in business or practice for the duration
i.e. on the balance of probabilities. of the suspension. Suspension remains permanently on an
architect’s record, and will be publicised during the period
3.20 After the plea, and after any preliminary or ‘housekeep- of suspension and for two years after that period ends.
ing’ matters, the case will start with the Presenter outlining the 4 Permanent erasure from the Register. This is the most
case, calling witnesses and adducing evidence in support of the serious sanction, suitable for serious matters fundamentally
charge. The architect or their legal representative will be entitled incompatible with continuing to be an architect, such as
to cross-examine those witnesses. dishonesty or a severe lack of integrity. The architect cannot
use the title ‘architect’ when erased from the Register. This
3.21 After the evidence against the architect has been brought, sanction is publicised for five years. An architect can apply
the architect can make a submission of no case to answer, i.e. to re-enter the Register after a minimum of two years from
to argue that even on the evidence submitted by the Presenter, the date of the erasure order.
and without needing to hear the architect’s evidence in response,
it is possible to see that a finding of guilty will not be made. 3.28 Appeals from decisions of the PCC may be brought before
the High Court or, in Scotland, the Court of Session.
3.22 If a submission of no case to answer is not made, or is not
successful, then the architect will be entitled to call witnesses 3.29 As an alternative to the Charge being contested at a hearing,
and adduce evidence. Those witnesses can be cross-examined proceedings before the PCC may be settled by a compromise:
by the Presenter. the PCC’s rules make specific provision for the Presenter to
propose a consent order under which the architect and the ARB
3.23 The Presenter then has the opportunity to adduce further agree to a disciplinary order without the need for a hearing.
witness or other evidence in rebuttal. Any such agreed consent order is subject to the approval of a
specially-convened Consent Order Panel, similar to but distinct
3.24 The Presenter then makes their closing submissions and, from a Hearing Panel.
finally, the architect or their legal representative has the last
word with their closing submissions.
Confdentiality
3.25 The Hearing Panel will then announce, as soon as practica- 3.30 Complaints to the ARB are confidential only for so long
ble, whether it finds the architect guilty or not guilty. as the matter remains before the IP. If the IP decides that the
architect has a case to answer and decides that the matter
3.26 An architect who pleads guilty or has been found guilty should be referred to the PCC, then the complaint will become
will be allowed to make a plea in mitigation, i.e. to present public: for example, details of forthcoming PCC hearings are
arguments to show that their offence deserves leniency because available on the ARB’s website and, as noted above, hearings
it is towards the less serious end of the scale. Mitigating fac- take place in public unless the Hearing Panel orders otherwise.
tors include: voluntarily notifying the ARB of the issue; a The proceedings at a hearing are recorded, and a transcript can
good previous disciplinary record; the offence was an isolated be made.
incident; there was little or no damage to others; contrition;
corrective steps have been taken; low chance of re-offending. 3.31 If an architect is found not guilty at the hearing, then they
On the other hand, there are aggravating factors that tend to have traditionally been offered the choice of either allowing the
increase the seriousness of the offence and the severity of the fact of (and reasons for) the not guilty finding to be published
penalty. These include: dishonesty; concealment of wrongdo- by the ARB, or leaving the decision unreported, but architects
ing; committing a criminal offence; a pattern of poor conduct in such circumstances have generally chosen to have the deci-
or incompetence; refusal to acknowledge failings and lack of sion unreported.
remorse; causing substantial loss to clients; the architect ben-
efitting from the offence. 3.32 A finding of guilty, on the other hand, is always made
public. The ARB will issue a press release about the decision,
3.27 In the event of a finding of guilt, the PCC can decide to and recent PCC decisions involving guilty architects are also
impose no sanction or it can impose a penalty. The penalties published on the ARB’s website.
350 Professional disciplinary proceedings

4 RIBA disciplinary proceedings mitigation to RIBA within 28 days to say why they should not
be referred to a RIBA hearing panel.
Investigation stage
4.01 A RIBA Member or Chartered Practice is considered to be
Hearing stage
the subject of an investigation when RIBA has received a signed 4.10 If a case is referred to a RIBA hearing panel, then the
and dated complaint form, details of the conduct complained architect will be informed of the ‘charge’ and required to respond
of, supporting documentation, and a chronology. The complaint to it within 28 days (again subject to a possible extension to be
must be limited to 20 single sides of A4 (although longer sub- granted at the discretion of the Head of Professional Standards).
missions can be admitted at the discretion of RIBA’s Head of If the architect wants to defend the ‘charge’, then their answer
Professional Standards). should set out the details of their defence and should refer to
evidence which they intend to rely on. The architect can submit
4.02 RIBA will then send a letter of enquiry to the architect, further evidence at this stage which has not been presented to
requiring a response within 28 days. The period of 28 days the appraisal team.
can be extended at the discretion of the Head of Professional
Standards. 4.11 If the architect intends to call any witnesses or to be rep-
resented by counsel or a solicitor then they should say so at the
4.03 As with the original complaint, the architect’s response to same time as submitting the answer and they should also give the
the complaint, including supporting evidence, must be limited to names of any witnesses. The architect does not have the right to
20 pages (although, again, the Head of Professional Standards call witnesses who are not notified to RIBA at this stage without
has the discretion to accept longer submissions). the permission of the hearing panel.

4.04 The complaint and the response will then be considered by 4.12 The architect’s answer will be sent to the complainant, but
a three-person ‘appraisal team’, made up of two RIBA members the complainant has no right to respond further.
and one non-member.
4.13 The date for the hearing will be at least one month after the
4.05 The RIBA appraisal team will then make one of the follow- date of the charge. RIBA aims for hearings to take place within
ing decisions (within 28 days, unless the Head of Professional two months of the charge.
Standards allows longer):
4.14 The hearing panel consists of one RIBA member and two
1 Dismiss the complaint; non-members. No one from the appraisal team may sit on the
2 Issue a private caution by consent order; or hearing panel. The hearing panel has the power to amend the
3 Formulate charges for determination by a hearing panel. charge or even to formulate a new charge. If it does so before
the hearing, then the architect will be given 28 days to respond.
4.06 Option 1 is clearly the desired outcome for the architect. But it should be noted that the hearing panel can amend or add
However, it should be noted that if the appraisal team dismisses charges during the hearing, in which case the architect can ask
a complaint, it is open to the complainant to refer the matter to for an adjournment to consider the new charge, but it is up to
an independent review, which in the case of RIBA, is carried the hearing panel to decide whether to grant the adjournment.
out by the Centre for Effective Dispute Resolution (CEDR).
The application for review must be based on evidence that 4.15 At the hearing, the architect can speak in person or use
the process was not conducted correctly or fairly – it is not an a lawyer or a friend to do so. They can call witnesses. The
appeal simply because the complainant considers the result to complainant has the right to attend the hearing as well, and the
be wrong. A complainant has 28 days from notification of the complainant can, if notice is given, be represented and call wit-
appraisal team’s decision to seek an independent review, which nesses as well. The hearing panel can also call witnesses.
they can do by making a request to CEDR copied to the Head
of Professional Standards at RIBA. 4.16 The procedure at hearings is relatively formal. The normal
course is to begin with introductions of the parties and the panel,
4.07 Option 2 – the private caution – needs further explana- following which the charge is read out, and the architect is asked
tion. This can happen if the appraisal team decides that there whether they confirm their written answer or wish to amend it.
is a prima facie case of misconduct but the matter is not suf- The architect (or their representative) addresses the panel first,
ficiently serious to warrant a hearing. The architect will then followed by the complainant (or their representative). The next
be sent a letter setting out details of what the caution entails: stage is witnesses, who will be questioned by the panel. The
the architect has to sign and accept the letter or else the mat- complainant then speaks again, followed by the last being given
ter will be referred to a hearing. The caution will remain on to the architect.
record for two years and may be taken into account if the
architect is referred to RIBA for another matter during that 4.17 Similarly to the ARB, the hearing panel applies the normal
period. The complainant will be informed of the issue of the civil standard of proof, i.e. the balance of probabilities, and not
caution. the more exacting criminal standard of beyond reasonable doubt.
The panel’s decision will be given in writing within seven days
4.08 Option 3 – referral to a hearing – will happen when the of the hearing, and written reasons will be provided.
appraisal team considers that there is a prima facie case of mis-
conduct and the matter is sufficiently serious to warrant further 4.18 If a charge is proved, the hearing panel has a range of
investigation. options open to it:

4.09 A somewhat different approach to the investigation stage is 1 A private caution;


taken in cases where the ARB is also involved. Where the same 2 A public reprimand;
or a related complaint has also been made to the ARB and RIBA, 3 Suspension; or
then the RIBA investigation is suspended pending the outcome 4 Expulsion.
of the ARB’s process. If the ARB takes no action, then the RIBA
appraisal team considers the complaint and response as set out 4.19 The panel can, in addition to these options:
above. However, if the ARB’s PCC makes a guilty finding and
issues a disciplinary order, then the matters is effectively ‘fast- 1 Require the architect to carry out up to 35 additional hours
tracked’: the architect will be required to make a written plea in of CPD within a year; and
What you can do 351

2 Provide up to five references of good character. (i.e. the facts as shown by the evidence) did not amount to
unprofessional conduct or serious professional incompetence
4.20 There is the possibility of an independent review of the on your part.
decision of the hearing panel. The architect can apply for review
in the case of any sanction being imposed, while complainants 5.05 You should think carefully about how your evidence and
can apply in cases of dismissal of the charge, cautions, repri- arguments are going to be used.
mands, and suspensions. As with the case of independent review
at the appraisal stage, the review must be based on evidence 5.06 First, think carefully about tone and content. Your written
that the process was not conducted correctly or fairly and is not submissions are your opportunity to persuade the professional
simply an appeal. Applications must be made within 28 days to body in question that you are a reasonable and competent
CEDR, copied to the Head of Professional Standards. professional: so make sure that you present yourself as a
reasonable and competent professional in all your dealings
4.21 Appeals are also possible: the architect or complainant must with them! That means avoiding making irrelevant personal
appeal in writing within 28 days of the decision with clear and attacks on the complainant (or anyone else), and avoiding
detailed reasons why the decision was unreasonable, or because making unsubstantiated allegations. Make your points in short,
new evidence has emerged since the hearing. Appeals are con- clear sentences. If you are making technical points, then bear
ducted in writing. Any sanction imposed by a hearing panel will in mind that what you write will be read by non-architects,
not take effect until after the appeal has been concluded. and you may need to explain points of architectural practice
with which they are not familiar: there is no guarantee, for
example, that an ARB panel will use an Inquirer to assist it
Confdentiality with details of architectural practice even if you consider that
4.22 RIBA disciplinary proceedings are confidential. Hearings to be sensible.
are in private and the public is not entitled to attend.
5.07 Second, think carefully about the practicalities of your sub-
4.23 So far as sanctions are concerned, a caution is private, missions. It is normally a good idea to use numbered paragraphs
but reprimands, suspensions, and expulsions are reported to the in any documents you write, and to label your attachments
RIBA Council and, unless the hearing panel decides otherwise, clearly. You should consider the volume of documentation that
published on the RIBA website and in the RIBA Journal. you wish to rely on: you will not help yourself by asking the
reader to wade through vast volumes of irrelevant documents;
but, on the other hand, if you have contemporaneous letters,
5 What you can do meeting minutes, site notes, or other documents that support
your case, then make legible copies of them and append them
5.01 Professional disciplinary proceedings can be very stress- to your submissions to prove your points. Note the page limits
ful. Dealing with them involves diverting time and effort that imposed by RIBA. If you are going to be relying on plans or
the architect would like to devote to their professional practice other documents that are hard to copy, then think carefully about
or personal life and spending it instead on correspondence or how you are going to present them.
meetings of a difficult and unfamiliar kind, while throughout
the process, the threat of serious sanctions, potentially including 5.08 Finally, you should seriously consider taking legal advice
expulsion from the profession, hangs over them. Each situation from a solicitor or barrister who has experience of professional
will be different, but it is hoped that the following points will be disciplinary proceedings. You should be aware that neither the
helpful to an architect facing disciplinary proceedings. ARB nor RIBA’s rules make any provision for the recovery of
legal costs. That means that any money you pay for a lawyer to
5.02 You should consider taking advice on how to handle such assist you in disciplinary proceedings will not be recovered even
proceedings from someone who is familiar with them. A col- if you successfully show that you are not guilty – or even that
league who has faced a similar situation may be a useful source there was no case to answer in the first place. On the other hand,
of guidance. a good lawyer should be able to save you time in the preparation
of evidence and correspondence, and should be able to ensure
5.03 You should not start from the assumption that either the that your case is presented strongly and persuasively.
ARB or RIBA is ‘on your side’ in professional conduct proceed-
ings. They are not. They are trying to be fair. If you start from 5.09 A lawyer may be particularly helpful if your case reaches
the expectation that they will be giving you the benefit of the the hearing stage, since professional disciplinary hearings are
doubt then you may perceive the reality as them being biased modelled on court hearings. ARB hearings in particular are
against you when, again, that is not the case. strongly reminiscent of court proceedings, with architects being
asked whether they are pleading guilty or not guilty, and wit-
5.04 At the investigation stage, you will have the opportunity to nesses giving evidence on oath. Experience of architects’ disci-
put forward your case in writing. It may be helpful to think of plinary proceedings shows that lawyers can help the defence by
your case as having two elements: (a) evidence, i.e. documents, making arguments that may appear technical or legalistic to the
statements (from you or others) and other materials which prove layperson, but which are really criticisms of the clarity or fair-
facts; and (b) argument, i.e. reasons why what in fact happened ness of the charges brought against the architect.
35
Architects’ professional indemnity insurance
JAMES LEABEATER QC

1 Why be insured? respects by reason of the Insurance Act 2015, which applies to
all policies written after 12 August 2016.
In case of claims
1.01 If architects make mistakes, they can cause losses which
The broker
are many times larger than the fees received for the particular 2.02 The insured will usually arrange insurance through a bro-
project. On larger projects, architects can be liable for millions ker. The broker is traditionally the agent of the insured, not the
of pounds in damages. If an architect practises in a limited insurer, although the broker will have connections with different
company, a large claim can cause the company to become insurers. It is a good idea to use a broker: they may be able to
insolvent, thereby leaving the client without full compensation. secure better rates; they will advise in relation to the appropri-
If architects are practising as a partnership, the partners will ate ambit of cover; they may help when making a claim; and, if
each be personally liable for the full amount of the claim, which something goes wrong with the insurance cover, the insured may
could potentially lead to partners being made bankrupt. Suitable be able to seek recourse from the broker instead.
professional indemnity insurance will, subject to the limits of
cover, protect the company or partnership against the financial
impact of the claim.
The proposal
2.03 The insured will have to complete a proposal form supplied
by the insurer or the broker. On the basis of that proposal form
Professional rules (and what the broker tells the insurer) the insurer will offer to write
1.02 It is obligatory for practicing architects to be properly the risk for a certain premium, subject to the terms of the proposed
insured. Standard 8 of the Architects’ Code of Professional policy. There may be a process of negotiation about the terms of
Conduct (see Chapter 39) provides that architects must hold cover. If the architect chooses to accept the insurer’s offer, there
suitable insurance to cover any potential liabilities arising from will come into existence a binding contract of insurance.
negligence or breach of contract associated with their profes-
sional activities.
Duty to make a fair presentation
2.04 As a matter of law, the parties to an insurance contract
Required by clients owe each other a duty of utmost good faith. This is specific to
1.03 Since architects can cause substantial losses, clients will insurance contracts, and arises principally because the insurer
often require architects to provide proof of adequate insurance has to rely upon the insured for information about the risk. As
cover. Standard form agreements often require cover for the part of the duty of good faith, and as set out in section 3 of the
same reason: for example, Clause 7.4 of the Standard Conditions Insurance Act 2015, the insured must make a ‘fair presentation’
of Appointment (see Chapter 30) requires the architect to of the risk to the insurer.
maintain insurance in the amount stated in the appendix to the A fair presentation requires the insured to disclose every
agreement, which will be the subject of negotiation between the material circumstance which the insured knows or ought to
architect and client. know; or, failing that, disclosure which gives the insurer suf-
For these and other reasons, architects need professional ficient information to put the insurer on notice that it should
indemnity insurance, and they need to know the basic principles make further enquiries. A fact is material if it would influence
of how it works. the judgment of a prudent insurer in fixing the premium or other
terms, or determining whether to take the risk. It includes special
or unusual facts relating to the risk.
2 Some basic insurance principles If the insured fails to disclose a material fact, the insurer will
be entitled to reject the claim if the insurer would have refused
2.01 The subject-matter of an insurance policy may be the prop- to cover the risk had the fact been disclosed. If disclosure of the
erty owned by the insured, which it wishes to insure (e.g. the fact would have led to a higher premium, then the insurer will be
contract works), or it may be liability on the part of a person entitled to claim the higher premium. If the non-disclosure was
or company to third parties (e.g. the liability of the architect fraudulent, then the insurer will be entitled to treat the insurance
to the client). In this chapter, we are concerned with the latter. contract as avoided; it will not be obliged to pay claims; and it
Insurance law has recently changed in some quite significant will be entitled to keep the premium.

353
354 Architects’ professional indemnity insurance

Only if there has been a significant loss do insurers usually 3.02 The purpose of a professional indemnity policy is to indem-
carry out investigations into the insured, whereby they discover nify the insured in respect of claims made against or notified to
failures to disclose material facts. In such cases, if the insurer is it within the period of the policy for breach of professional duty.
released from any obligation to pay the claim, that can be ruin- The policy will generally indemnify the insured against sums
ous for the insured. It is therefore very important for the insured which it becomes legally liable to pay by way of compensation
to make sure that all material facts have been disclosed honestly for breach of professional duty (in tort or contract) as a result of
and accurately. If necessary, the insured should take advice from a court order, arbitration award, or settlement. Architects would
the broker on what to disclose. be well advised to ensure that the particular policy responds to
sums which are awarded by adjudicators (see Chapter 23).
2.05 The proposal form will set out a number of questions which
must be answered honestly, accurately, and fully. However, the
insured must disclose all material facts, even if they are not
Limits of indemnity
covered by any matters in the proposal form. In particular, any 3.03 The insured will be liable for a certain sum by way of
claims made against the insured must be disclosed, and any excess or deductible in respect of each and every claim, although
negligent work carried out. More generally, the insured must there may be a clause which allows related claims to be treated
disclose: as one claim for the purposes of the deductible.

1 Facts indicating that the subject matter of the insurance is 3.04 The insured must be careful to select an appropriate level
exposed to more than the ordinary degree of risk or that the of cover, depending on the value of the projects on which it
liability of the insurer is greater than expected. works. This may, for example, be a limit of £5m for each and
2 Facts indicating that the insured has some special motive: every claim, including the claimant’s legal costs. Other ways of
for example, that it has greatly over insured. limiting cover are to provide that there is an aggregate limit of
3 Facts showing that there is a moral hazard, suggesting that (say) £5m in respect of all claims made in the year, or in respect
the insured is not a fit person to be insured: for example, of a series of claims which are linked in a defined way (e.g. they
that he or she has been convicted or suspected of fraud. arise out of the same originating cause).
4 Facts which are, to the insured’s knowledge, material or
regarded by insurers as material. 3.05 The policy is likely to cover the insured’s own legal costs
in addition to sums payable to the third party. Whether such
2.06 The insured in general need not disclose: costs are included within the limit of indemnity or not depends
upon the wording of the particular policy. If payment to the third
1 Facts which are already known to the insurer or which it party is greater than insurers’ limit of indemnity, then insurers’
might reasonably be presumed to know. liability to pay costs may be scaled down by the proportion
2 Facts which the insurer could have discovered by making which the level of indemnity bears to the total amount payable
some enquiries. to the third party.
3 Facts where the insurer has waived further information.
4 Facts tending to lessen the risk.
Claims made
3.06 Professional indemnity policies are almost always ‘claims
Terms of insurance policies made’ policies: they respond to claims made against or notified
2.07 A further idiosyncrasy of insurance contracts is that the to the insured within the period of the policy, not claims arising
terms are classified differently. In other contracts, breach of a out of a breach of duty within the policy period. Partners should
condition will give the innocent party the right to treat the con- ensure that the firm’s policies continue to cover them against
tract as being at an end, while breach of a warranty will only claims in retirement, and sole practitioners should obtain ‘run-
give rise to a claim for damages. Under insurance contracts, the off’ cover to protect them through retirement.
position is different.
3.07 The policy will require the insured to inform insurers of
1 A warranty must be exactly complied with, and if it is not claims made as soon as possible. It will probably require the
so complied with, the insurer may not have to pay a claim insured to inform insurers of any circumstance or event which is
under s.10(2) of the Insurance Act 2015. likely to result in a claim. Failure to do so may mean that insur-
2 Other terms may be ‘conditions precedent’. Unless the ers do not have to pay. The importance of timely notification of
insured complies with the condition precedent, insurers claims to insurers cannot be overstated. Disputes about whether
will (depending upon the particular clause) have no liability or not the insured has notified insurers of a claim or a circum-
under the policy, or have no liability for a particular claim. stance likely to give rise to claim are common. Confrontational
3 Otherwise, breach of a condition may give rise to a right on correspondence may be sent or difficult meetings held; the
the part of insurer to reject a claim and/or a right to damages employer may blame the contractor for delays and the contrac-
caused by the breach. tor may in turn blame the architect for late provision of design.
The architect will have to consider whether the correspondence
Whatever the correct description of the term of the contract, the amounts to a notification of a claim or a circumstance likely to
insured must comply strictly with it, or the effectiveness of cover give rise to a claim; and, if he or she has already notified insurers
under the policy may be jeopardised. of a claim or circumstance in relation to the project, whether he
or she should notify insurers of a further claim or circumstance.
It is prudent to notify insurers of each relevant document or con-
3 Professional indemnity versation until insurers say otherwise; if in doubt, seek advice
insurance policies from a broker or solicitor.

3.01 There is no one standard architects’ professional indemnity 3.08 An insurer will not generally be liable for claims which the
policy. Careful reference must be made to the actual terms of insured knew about before the policy was agreed. They should
the particular policy to see what it covers and what it does not be covered by the previous year’s policy. The insured should
cover. Insurance contracts are interpreted by giving effect to the therefore ensure that all claims or circumstances likely to give
usual meaning of the language used. In the case of ambiguity, the rise to a claim have been notified to insurers before the end of
court may favour the interpretation which is against the person each policy year. This is always important, but particularly so
who drafted it: almost always the insurer. when the architect is changing insurers.
Risk management 355

3.09 If the insured makes a fraudulent claim on the policy, then impose guarantees in respect of work done, whereas usu-
the insured is not permitted to recover at all in respect of that ally, the architect is only liable in the event he has failed to
claim, even if the claim or part of it could have been made hon- exercise reasonable care and skill.
estly. This rule arises from the duty of good faith and s.12 of the 6 Claims arising out of a survey or valuation report carried
Insurance Act 2015. It may be reinforced by a term in the policy. out by the insured, unless it was carried out by a quali-
fied architect or surveyor and a disclaimer as specified by
the insurer was included in the terms of appointment. The
Control of the claim and subrogation disclaimer normally tries to exclude liability for woodwork
3.10 The insurer will be entitled to take control of the claim once and parts of the structure which are covered up, and high
it has been notified to it. The insured may not admit liability alumina cement.
for any breach of duty or compensation without the insurer’s 7 The policy may only cover work done in the United
consent. The insured will have to give all such assistance to the Kingdom.
insurer as is necessary for it to handle any claim. However, in
the event of a dispute between the insured and insurer, the policy
will probably provide that the insured need not contest any legal
Fees recovery extension
proceedings unless an independent lawyer (often a Queen’s 3.13 It may be possible for the insured to extend the policy to
Counsel) has advised that such proceedings may be contested protect the insured against costs which are necessarily incurred
with the probability of success. in recovering or attempting to recover professional fees.

3.11 If the claim against the insured is successful, and the insurer
indemnifies the insured for the loss, the insurer will be subro- 4 Risk management
gated to the insured’s position in respect of any possible claims
against third parties (e.g. the building contractor) in respect of 4.01 Architects can take steps to minimise the likelihood of
the loss. The insured may be required to allow the insurer to use claims being made against them. This is largely a matter of com-
his name to bring proceedings against such third parties. The mon sense, but the following list may be helpful.
policy will, however, generally provide that the insurer will not
exercise rights of subrogation against employees of the insured, 1 Consider the terms of your appointment carefully. Make
unless there was dishonest, criminal or malicious conduct on the sure its terms are clearly agreed and that fee provisions and
part of the particular employee. the scope of services are expressly stated.
2 Do not take on work which is beyond the capability of the
person or the capacity of the team doing it.
Exclusions 3 Have a system set up to check drawings and other work
3.12 The insured should read the exclusions to cover with care. before it is sent out.
The following are common exclusions: 4 Make sure that everyone knows when deadlines fall. Do not
agree to take on projects with unrealistic deadlines.
1 An excess or deductible (see paragraph 3.03 above). 5 Have a proper document management system.
2 Claims arising out of participation in a consortium or joint 6 Make sure you know and comply with contractual formali-
venture. ties. Many disputes arise when there are no proper records
3 Claims arising out of any circumstance or event which has of variations to the works, or additional instructions. The
or should have been disclosed by the insured on the pro- fact that the project is proceeding amicably at the beginning
posal form or renewal form (see paragraph 2.05 above). does not mean it will stay that way until the end. Everyone
4 Claims caused by a dishonest, fraudulent, criminal, or mali- will benefit from a clear record of the scope, cost, and time
cious act or omission on the part of any partner, director, implications of work done.
or principal of the insured. Such conduct on the part of 7 Consider any third party guarantee, collateral warranty, or
employees, on the other hand, if it leads to liability to third duty of care deed very carefully, and check that it will be
parties, will generally be covered by the policy. covered by the policy. If necessary, take legal advice.
5 Claims made out of performance warranties, collateral 8 Make sure any consultants or contractors have written terms
warranties, penalty clauses or liquidated damages clauses, of appointment and insurance.
unless the liability would have existed in the absence of 9 Make sure that all projects are properly supervised.
such clauses. This is because such warranties or clauses 10 If project is going wrong, ensure that you keep good records
generally extend the usual liability of the architect. They (including dated photographs) of what is happening.
36
Copyright and design protection
CLIVE D. THORNE

The most relevant intellectual property rights for architects are (d) Broadcasts and cable programs: 50 years from the end of
copyright and designs. They both protect the expression of ideas. the calendar year in which the broadcast was made, or the
cable programme included in a cable programme service;
(e) Typographical arrangements: 25 years from the end of the
1 Copyright calendar year in which the edition was first published.

1.01 UK copyright law is contained in the Copyright, Designs 1.03 If a work is entitled to copyright protection, the right vested
and Patents Act 1988 (‘the Act’) and Statutory Instruments in the copyright owner is that of preventing others from doing
made under that Act, including the implementation of EU law. certain specified acts, called ‘the restricted acts’ (paragraph
Copyright exists only in works which come within one of the 2.02). The restricted acts are specified by the Act in relation to
categories prescribed as being capable of having copyright pro- each category of work and differ for each category. Acts done in
tection. These are as follows: relation to a copyright work which are not one of the restricted
acts specified for that type of work do not infringe.
1 Literary works;
2 Dramatic works; 1.04 Performing restricted acts without the consent of the copy-
3 Musical works; right owner may not constitute infringement of copyright if a
4 Artistic works (including works of architecture being a substantial part of the copyright work is not reproduced or a
building or a model for a building); fair dealing defence (see section 6) is available. There are other
5 Sound recordings; exceptions, differing according to the types of works or subject
6 Films; matter (for example, see paragraphs 6.01 and 6.02).
7 Broadcasts (including electronic transmissions);
8 Typographical arrangements of published editions. 1.05 In most cases, the author of a work is its first owner. But
there are special rules which can override this general provision
The Act describes all these copyright categories as ‘works’. (see section 5 below).
Material which does not fall within one of the categories
will have no copyright protection; it will not be copyright 1.06 There is generally no copyright in ideas per se but only in
material. the manner of their expression.

1.02 Copyright subsists for defined terms which differ according 1.07 To acquire copyright protection, works must be recorded
to the category of work. The Duration of Copyright and Rights in a material form.
in Performance Regulations 1995 (SI 1995 No. 3297), which
came into force on 1 January 1996, determines the duration of 1.08 Literary, dramatic, musical and artistic works must be
copyright in each category of work. The position can be sum- ‘original’ (i.e. have involved the use of independent skill and
marised as follows: labour by the author).

(a) Literary, dramatic, musical, and artistic works (which 1.09 The work does not have to be published, nor does it have
include architectural works): 70 years from the end of the to be registered, for it to have copyright protection.
calendar year in which the author died;
(b) Sound recordings: 50 years from the end of the year in which 1.10 The author of the work must be a ‘qualified person’: a
they were made or, if released before the end of that period, citizen or resident of the UK or of one of the countries which
50 years from the end of the calendar year in which released; is a signatory to the Berne Copyright Convention (‘BCC’) or
(c) Films: 70 years from the end of the calendar year in which the Universal Copyright Convention (‘UCC’). Alternatively,
the last of the principal director, the author of the screen- the work must have been made or published in a qualifying
play, the author of the dialogue, or the composer of the country, which, for most purposes (although there are important
specially created music dies, or if there is no one within this exceptions for sound recordings, films, broadcasts, and cable
designated list, 50 years from the end of the year in which programs), are the same countries. There are no significant
they were made; countries which are not party to these conventions.

357
358 Copyright and design protection

The nature of copyright work. Plans and sketches were protected as ‘literary works’
and drawings as ‘artistic works’. The Copyright Act 1911 was
1.11 This can be summarized by the following extract from the repealed by the Copyright Act 1956. Protection for works of
Whitford report, which was the precursor to the Act. architecture under the 1956 Act was similar to that accorded by
the 1911 Act. The 1988 Act repealed the 1956 Act and came into
A writer writes an article about the making of bread. He force on 1 August 1989 (Figure 36.1).
puts words on paper. He is not entitled to a monopoly in the
writing of articles about the making of bread, but the law
has long recognized that he has an interest not merely in the Database right
manuscript, the words on paper which he produces, but in the 1.14 Following the implementation of an EC Council Directive
skill and labour involved in the choice of words and the exact on the legal protection of databases, the Copyright Rights in
way in which he expresses his ideas by the words he chooses. Databases Regulations 1997 (SI 1997. No. 3032) came into
If the author sells copies of his article then again a purchaser force on 1 January 1998 and created a sui generis ‘database
of a copy can make such use of that copy as he pleases. He right’. The right provides protection where there has been a
can read it or sell it second-hand, if he can find anyone who ‘substantial investment in obtaining, verifying or presenting the
will buy it. If a reader of the original article is stimulated into contents of the database’. A database is defined as a ‘collec-
writing another article about bread the original author has no tion of independent works, data or other materials arranged in
reason to complain. It has long been recognized that only a systematic or methodical way and individually accessible by
the original author ought to have the right to reproduce the electronic or other means’. A new class of literary work, qualify-
original article and sell the copies thus reproduced. If other ing for copyright protection, has been created for databases, but
people were free to do this they would be making a profit the originality test is stricter than for other works.
out of the skill and labour of the original author. It is for this
reason that the law has long given to authors, for a specified 1.15 The database right can subsist whether or not the database
term, certain exclusive rights in relation to so-called literary or its contents is a copyright work. The general rule is that the
works. Such rights were recognized at common law at least right subsists for 15 years from the end of the calendar year in
as early as the fifteenth century. which the database was completed, and the maker of the data-
(Whitford Committee on Copyright and Design Law (1977)) base will be the first owner of the database right.
As the word itself implies, ‘copyright’ is literally a right to 1.16 If a database qualifies for protection, the owner can pre-
prevent other people copying an original work. It must be an vent third parties extracting or re-utilising all or a substantial
original work, not an original idea. part of the contents of the database without consent. In British
Horseracing Board v William Hill Organisation Ltd (Case
The sources of copyright law C-2003/002), the European Court held that to qualify for pro-
tection there must be a substantial investment in creating the
1.12 UK copyright law is now contained in the Act as amended.
There are a significant number of Statutory Instruments made
under the Act or under powers contained in the European
Communities Act 1972 to incorporate the UK’s obligations
under European Union law and decisions of the European Court.
Orders in Council extend the provisions of the Act to works cre-
ated outside the UK.
The UK is party to international conventions covering recip-
rocal international copyright recognition. The most important are
the BCC and the UCC. The WTO TRIPS Agreement consoli-
dates many of the provisions of both conventions.
There is also case law consisting of judgments in copyright
cases. Decisions on earlier legislation, the Copyright Acts of
1911 and 1956, can be still relevant.

The history of copyright


1.13 Copyright came into existence with the invention of
printing. The foundations of copyright were in the granting
of licenses by the Crown to printers giving them the right to
print (i.e. copy) against the payment of fees to the Crown. The
Licensing Act 1662 prohibited the printing of any book which
was not licensed and registered at the Stationers Company.
The first Copyright Act was passed in 1709. This Act gave
protection for printed works for only 21 years from the date of
printing and unprinted works for 14 years. Again, books had to
be registered at the Stationers’ Company.
The Copyright Act 1842 accorded copyright protection only
to literary works. It set out the term of copyright as the life of
the author plus 7 years or 42 years from the date of publication,
whichever was longer.
Architects’ plans, provided they had artistic quality, first
became entitled to copyright protection as artistic works under
the Fine Arts Copyright Act 1862.
The so-called ‘Imperial’ Copyright Act 1911 repealed all
previous copyright legislation. The Act extended copyright pro-
tection to ‘architectural works’. In Meikle v Maufe [1941] 3 All
ER 144, plans for an elaborate garden design were found to be a
‘structure’ and entitled to copyright protection as an architectural
Qualifcation for protection 359

database which was restricted to ‘the obtaining ,verification or in which the work is reduced to a material form rather than
presentation of the contents’. the originality of the content or idea upon which the work is
based.
The test for ‘originality’ is low, as was demonstrated in
2 Protection for architectural Walter v Lane [1900] AC 539, a case which it was held that
works under the Act a reporter was entitled to copyright in his verbatim report of
a public speech. The work must originate from the author
2.01 ‘Works of architecture’ are included in the definition of instead of merely being copied from another work. In the
‘artistic works’ purposes. Section 4 defines an ‘artistic work’: leading case of Interlego AG v Tyco Industries Inc [1989] AC
217 the Privy Council held that skill, labour and judgment
‘s.4 (1) In this Part “artistic work” means – exercised in copying by making minor emendations to design
(a) a graphic work, photograph, sculpture or collage, drawings is insufficient to confer ‘originality’. This is despite
irrespective of artistic quality, the fact that mere copying of an artistic work may in fact
(b) a work of architecture being a building or a model require considerable technical skill. The case involved copy-
for a building, or right in design drawings for toy bricks. The drawings were
(c) a work of artistic craftmanship. amended with small emendations and measurements. There
was insufficient skill and labour in making the emendations
(2) In this Part; to establish ‘originality’.
“building” includes any fixed structure, and a part of a In University of London Press Ltd v University Tutorial Press
building or fixed structure; “graphic work” includes Ltd (1916 2 Ch 601), which concerned the copying of examina-
(a) any painting, drawing, diagram, map, chart or plan, and tion papers, the court held that ‘original’ does not mean that the
(b) any engraving, etching, lithograph, woodcut or similar work must be the expression of ‘original or inventive thought
work; … but that it should originate from the author’.
The EU Information Society Directive (2001/29/EC) has
“photograph” means a recording of light or other radiation raised the test for ‘originality’ This was interpreted by the CJEU
on any medium on which an image is produced or from in Infopaq International A/S v Danske (2012) EUECJ C-302/10
which an image may by any means be produced, and which as a test, ‘whether the work comprises the expression of the
is not part of a film; “sculpture” includes a cast or model author’s own intellectual creation’.
made for purposes of sculpture.’ It has yet to be decided whether the Directive and CJEU case
law effects a substantial change to the long-established UK test.
Works of architecture include buildings and models for build- In The Newspaper Licensing Agency v Meltwater Holding BV
ings. Plans, sketches, and drawings upon which works of archi- (2013) EWCA Civ 890, both the Court of Appeal and Supreme
tecture are based are also artistic works, which have their own Court held, in applying Infopaq, that the existing test had not
separate copyright. So also do notes prepared by the architect, been qualified by Infopaq.
but as ‘literary works’.
There is no definition of ‘fixed structure’. In Meikle v Maufe 2.04 For architectural works, the reproduction of some distinc-
(see 1.13 above) the court held, under the 1911 Act, that an tive design detail will make the architect’s task of showing
elaborately laid-out garden was a ‘structure’ and therefore a infringement easier. In Stovin-Bradford v Volpoint Properties
‘work of architecture’. Ltd [1971] Ch 1007 the court was influenced by the fact that
‘Drawing’ is not defined by the Act. The definitions of ‘artistic although many details of the architect’s drawings were not
work’ and ‘literary work’ are wide so that they cover the typical reproduced in the constructed buildings, ‘a distinctive diamond-
output of an architect’s practice, for example, design drawings shaped feature which gave a pleasing appearance to the whole’,
and sketches, blueprints, descriptive diagrams, working draw- was reproduced.
ings, final drawings, artistic presentations, notes both alphabeti-
cal and numerical, and reports.
Duration of copyright
Restricted acts
2.05 Copyright in an artistic work extends for the lifetime of
2.02 There are separate restricted acts specified in the Act in the artist/author plus a further term of 70 years from the end of
relation to each category of work. The restricted acts applicable the calendar year in which he died. In the case of architectural
to works of architecture are the same as those applicable to artis- works, this period is not affected by the fact that the work was
tic works, although there are exceptions (see section 6) expressly not published during the architect’s lifetime.
in relation to works of architecture. In the case of jointly authored works, the 70 years runs
from the end of the calendar year in which the last of the
The acts restricted by the copyright in an artistic work include joint authors dies. A joint work is one in which the work
either directly or indirectly: is produced by the collaboration of two or more authors in
which the contribution of each author is not distinct from that
i. Copying the whole or a substantial part of the work; of the other author or authors. Thus, if a building is designed
ii. Issuing copies of the work to the public; by two architects, but one is exclusively responsible only for
iii. Renting or hiring the work. the design of the doors and windows, so that it is possible to
distinguish between the contributions of the two architects, it
Secondary infringement arises in relation to the possession or will not be a joint work.
dealing with, or providing the means for making the infringing
work, provided the alleged infringer knows, or has reason to
believe the work is an infringing copy. This is more fully dealt 3 Qualifcation for protection
with in section 7.
3.01 In order to qualify for copyright protection in the UK,
the qualification requirements of the Act must be satisfied
Originality either by the author or the country in which the work was
2.03 Copyright in an artistic work (for example, a building, first published.
model, architectural drawing, or plan) is not dependent on any
aesthetic appeal nor requires any artistic character but requires 3.02 In the case of authorship, in respect of unpublished works,
the existence of ‘originality’. ‘Originality’ refers to the way copyright will subsist only if the author was a ‘qualifying
360 Copyright and design protection

person’ at the date when the work was created, or, if it was In Cala Homes (South) Ltd v Alfred McAlpine Homes East
created over a period, for a substantial part of that period. In Ltd (1995) FSR 818, a Cala employee supervised in detail the
the case of a published work, the author must be a ‘qualifying drawings for the designs and plans for houses. The drawings had
person’ qualified at the time when the work was published, or been drawn by employees of a firm of technical draughtsman.
immediately before his or her death (if earlier). The court held that, even though the employee had not actually
drawn anything, he was a joint author. As an employee, his
3.03 For copyright purposes, the expression ‘qualifying person’ copyright vested in Cala as his employer.
refers to any British citizen, British Dependent Territories citi-
zen, a British National (overseas), a British Overseas citizen, a
British subject, or a British protected person within the mean-
Employees
ing of the British Nationality Act 1981, or a person domiciled 5.02 Copyright in architects’ drawings, buildings, or models
or resident in the UK or in another country to which the Act produced by employees in the course of their employment auto-
extends or is applied, or a body incorporated under the laws of matically vests in the employer, whether the latter is an architect
the UK or such another country. The countries to which the Act in partnership, a limited company, or a public authority. The
extends or has been applied are the signatories to the BCC and copyright in work created by employees in their personal time
the UCC, which includes all the major and most of the develop- and not in the course of employment vests in them (Thomas
ing countries in the world. Scott v Universal Components Ltd [2002]).
A corporation cannot be the author of an artistic work, though An employer architect can discourage employees from
can be the assignee of artistic copyright. accepting private commissions by providing in the contract of
employment that the copyright in the employee’s work, whether
3.04 In respect of the country of publication, the work must have produced in the course of employment or not, will vest in the
been published first in either the UK or another country to which employer.
the Act extends or has been applied, i.e. BCC or UCC countries.
Publication in one country shall not be regarded as other 5.03 Section 178 of the Act provides that the words ‘employed’,
than first publication by reason of the simultaneous publication ‘employee’, ‘employer’, and ‘employment’ refer to employment
elsewhere. Publication elsewhere, within 30 days, is regarded under a ‘contract of service or apprenticeship’. Frequently,
as simultaneous. architects employ independent architects and artists to carry
out parts of the drawing. Increasingly, persons who would
3.05 The Act provides that the territorial waters of the UK shall appear to be employees are, for a variety of reasons (includ-
be treated as part of the UK for copyright purposes. In addition, ing tax avoidance), engaged as self-employed sub-contractors.
oil rigs and other structures that are present on the UK continen- Such persons are rarely employed under ‘a contract of service’
tal shelf for purposes directly connected with the exploration of as distinct from ‘a contract for services’. Employer architects
the sea bed or the exploration of their natural resources and UK would be advised to make it an express term of a sub-contrac-
aircraft and ships are subject to UK copyright law. tor’s appointment that copyright should vest in the employing
architect.

4 Publication 5.04 Where a work is made by an officer or Crown servant of


the Crown in the course of his duties, the Crown is deemed to
4.01 ‘Publication’ is defined in s.175(1)(a) of the Act as mean- be the first owner of the copyright in the work.
ing the issue of copies to the public. Qualification for copyright
protection by reference to the country of first publication applies
to literary, dramatic, musical, and artistic works and includes Partners
making the work available to the public by means of an elec- 5.05 A partner of a firm is not an ‘employee’ of the partner-
tronic retrieval system. ship and the partner or partnership (subject to the partnership
There is an express provision in s 175(3) of the Act relating deed) will own the legal title to a work created by the partner.
to architectural works. In the case of works of architecture in the However, if the work is created in the ordinary course of the
form of a building or an artistic work incorporated in a build- partnership business and for the purposes of the partnership, the
ing, construction of the building shall be treated as equivalent copyright in the work will be considered as a partnership asset.
to publication of the work. Legal title remains with the partner who created the work until
a written assignment is executed, but the other partners have a
4.02 The issue to the public of copies of a graphic work rep- right to apply the copyright to benefit the partnership. For the
resenting, or of photographs of, a work of architecture in the avoidance of doubt, the partnership deed should set out deemed
form of a building, or a model for a building, does not constitute ownership of copyright.
‘publication’ for the purposes of the Act, nor does the exhibition,
issuing to the public of copies of a film including the work, or
the broadcasting of an artistic work constitute publication. Thus,
Ownership of drawings
the inclusion of a model of a building in a public exhibition such 5.06 Ownership of copyright in drawings should be distin-
as the Royal Academy Summer Exhibition, would not amount guished from ownership of the physical paper upon which they
to ‘publication’, nor would the inclusion of photographs of the are drawn. Generally, upon payment of the architect’s fees, the
model in a book. client is entitled to possession of all the drawings prepared at
its expense. In the absence of agreement to the contrary, copy-
right remains with the architect who also has a lien on (right to
5 Ownership withhold) the drawings until the fees are paid. If copyright is
assigned to the client, it may make such use of the copyright as
5.01 Subject to the exception for employees set out in the follow- it wishes. Architects should note that, even if they have assigned
ing paragraph, ownership of artistic copyright in drawings usually the copyright, by virtue of the provisions of section 64 of the
resides with the architect who actually drew the plan, drawing, Act, they may reproduce in a subsequent work their own origi-
sketch, or diagram. As a chose in action, it passes to its owner’s nal design provided that they do not ‘repeat or imitate the main
personal representatives after his or her death. If a building con- design’. This provision enables architects to repeat standard
tractor constructs the building without reference to any plans, it details which would otherwise pass to the client upon prior
will be the author and owner of the work of architecture. assignment of copyright.
Infringement 361

Joint ownership 6.05 Express exceptions are contained in the Act for copying for
educational purposes and copying by libraries and archives and
5.07 A work of joint authorship is one which results from the by public administration.
collaboration of two or more authors where it is not possible to
distinguish the contribution of those authors. There is no require-
ment for the authors to have a joint intention to create the work
(Robert James Beckingham v Robert Hodgens & Others [2003] 7 Infringement
EWCA Civ 143).
7.01 To show infringement, claimants must demonstrate that:
5.08 The general rule, in circumstances of joint authorship, is
that the joint authors will be the joint owners of the copyright 1 Copyright subsists in their work;
in the work. In Robin Ray v Classic FM plc [1998] FSR 622, it 2 The copyright is vested in them;
is suggested that joint authors will hold copyright as tenants in 3 The alleged infringement reproduces a substantial part of
common in equal shares (i.e. hold distinct, severable shares that their work in material particulars;
can be assigned or passed by will). However, this decision has 4 The alleged infringement was copied from their work.
been criticised, and there may be situations where joint authors
will hold title as joint tenants (i.e. where one owner’s share will 7.02 A claim for infringement cannot succeed if the defend-
pass automatically to the joint owner on death). ant who is claimed to have infringed had no knowledge of the
existence of the work of the owner. Copyright restricts the right
to copy, which presupposes some knowledge of the original by
6 Exceptions to infringement the copier. Ignorance of the fact that the work copied was the
of architects' copyright copyright owner’s is not, however, a defence. It is in the nature
of architects’ copyright that the person allegedly infringing
must have had access directly or indirectly to the drawings.
Photographs, graphic works Infringement can therefore take three forms, as detailed below.
6.01 Frequently, photographs of buildings designed by
architects appear as publicity material by contractors who 7.03 Whether a ‘substantial part’ is reproduced, so as to establish
constructed the buildings. The contractor may make some infringement, is a ‘qualitative’, rather than a ‘quantitative’ test.
acknowledgment of the design. Under section 62 of the Act,
the copyright in a work of architecture is not infringed by Copying in the form of drawings
making a graphic work representing it, making a photograph
or film of it, or broadcasting or including a visual represen- 7.04 Other than by photo-copying, it is exceptional for drawings
tation of it in a cable programme service. Copies of such to be copied in every detail. Potential infringers of an architect’s
graphic works, photographs, and films can be issued to the copyright may consider that if detail is altered, infringement is
public without infringing the copyright in the building and avoided. This is not so. Section 16 of the Act (see section 2.02)
models of it. Making a graphic work in this context refers to makes it clear that references to reproduction include reproduc-
a perspective or even detailed survey of the building as built: tion of a ‘substantial part’. The word ‘substantial’ refers to qual-
it would remain an infringement to copy the drawing or plan ity rather than to quantity. Reference has already been made to
from which the building was constructed. the Stovin-Bradford case (see section 2.04), to the distinctive
diamond-shaped detail of the design that was taken even though
many details of the design drawings were not reproduced in the
Reconstruction constructed and infringing buildings. It is immaterial that the
6.02 Section 65 provides that, where copyright exists in a build- size of the copy may have been increased or reduced or that only
ing, anything done for the purposes of reconstructing the build- a small detail of an original drawing has been copied.
ing does not infringe copyright. There will be no infringement
of the drawings or plans in accordance with which the building 7.05 In Signature Realty Ltd v Fortis Developments [2016]
was constructed, by or with the licence of the copyright owner, if EWHC 3583, the parties competed to purchase the same site.
subsequent reconstruction of the building or part of it is carried Prior to completion, the claimant was granted planning consent
out by reference to original drawings or plans. based upon architectural drawings it had commissioned. The site
was then purchased by the defendant who used the drawings
obtained by the claimant. The claimant obtained an assignment
Fair dealing of copyright from the architects who had created the draw-
6.03 A general defence to any alleged infringement of copyright ings and who were copyright owners and successfully sued for
in an artistic work may exist under the ‘fair dealing’ defence of infringement.
criticism or review, provided that there is sufficient acknowledg-
ment. As reproduction of the work by photograph is the most 7.06 Reproduction of a drawing in the form of a building
likely method of illustrating a review, and as a photograph of a infringes the copyright in the drawing, even if no copy of the
building is specifically exempt from infringement, this defence drawing itself is made by the infringer.
of ‘fair dealing’ would generally exist only in the case of draw-
ings of buildings. A sufficient acknowledgment is an acknowl- Copying the drawing in the
edgment identifying the building by its name and location, which
also identifies the name of the architect who designed it. The
form of a building
name of the copyright owner need not be given if he or she has 7.07 Two-dimensional plans can be ‘copied’ three-dimensionally
previously required that no acknowledgment of his or her name in the form of a building which reproduces the plans. The
should be made. leading case on this form of infringement is Chabot v Davies
[1936] 3 All ER 221. Mr Chabot, who was not an architect but
6.04 Fair dealing with an artistic work for the purposes of ‘a designer and fixer of shop fronts and the like’, prepared a
research for a non-commercial purpose, with a sufficient drawing for the defendant, who ‘was just about to open what is
acknowledgment, is also a defence to an alleged copyright known as a fish and chip shop’. Mr Chabot was able to show
infringement. However, there are limits on how, and how many that the contractor had actually been handed his drawing by
copies may be made. the defendant and had made a tracing from it. The defendant
362 Copyright and design protection

argued that a plan cannot be reproduced by a shop front but 8.02 Paragraph 6.2 of the Conditions of Engagement modifies
only by something in the nature of another plan. The judge held, paragraph 6.1 to give the client a licence to use the architect’s
however, that ‘reproduce … in any material form whatsoever’ design in certain circumstances, including the performance of
must include reproduction of a drawing by the construction of the architectural project. Paragraph 6.2 entitles the client to
an actual building based on that drawing. copy and use the architect’s design (including drawings, docu-
ments, and bespoke software) for purposes related to the project
7.08 In the more modern case of Cala Homes (South) Ltd v provided that:
Alfred McAlpine East Ltd [1995] FSR 818, the defendant had
allegedly copied floor plans. Hence, it was difficult to see (a) The entitlement applies only to the site or part of the site to
whether there had, in fact, been infringement. However, it was which the design relates; and
held that if it is possible to show copying, whether by recreating (b) Any fees due to the architect have been paid (note: if the
the floor plan by measurement of the building, or by reference client is in default of payment, the architect can suspend
to the plans which the defendant used to construct the building, further use of the license on giving 7 days’ notice to the
then infringement may be established, as the plans have been client).
reproduced in a ‘material form’.
This entitlement applies to the operation, maintenance, repair,
reinstatement, alteration, extension, promotion, leasing, and sale
Infringement by copying a building in of the works, but excludes the reproduction of the architect’s
the construction of another building design for any part of any extension of the project or for any
7.06 The leading case remains Meikle v Maufe [1941] 3 All ER other project.
144. In 1912, Heal & Son Ltd employed Smith & Brewer as
architects for the building of premises on the northern part of Sub-paragraph 6.2.2 provides that, if permitted use occurs after
the present site of Heal’s store in Tottenham Court Road. At that the date of the last service performed under the agreement and
time, there were vague discussions about a future extension on prior to practical completion of the construction of the project,
the southern part of the site, but because of difficulties over land the client shall:
acquisition, nothing could be done. In 1935, Heal’s employed
Maufe as their architect for the extension of the building. Meikle (a) Obtain the architect’s consent if the architect has not com-
was, by this time, the successor in title to Smith & Brewer’s pleted detailed proposals. The architect’s consent must not
copyright, and claimed that both the extension as erected and be unreasonably withheld; and/or
the plans for its erection infringed the original copyright. Maufe (b) Pay a reasonable license fee if none is agreed.
admitted that he thought it necessary to reproduce in the south-
ern section of the facade the features which appeared in the Finally, sub-paragraph 6.2.1 provides that the architect shall not
original northern section. His object was ‘to make the new look be liable for the consequences of any use of any information
like the old throughout nearly the whole of the Tottenham Court or designs prepared by the architect except for the purposes for
Road frontage’. The layout of the interiors was also substantially which they were provided.
reproduced. The defendants contended that there could not be
a separate copyright in a building as distinct from copyright in 8.03 Copyright may also be expressly assigned to the client at
the plans or drawings on which it was based. This argument some later stage, but it is usual to grant a license authorising
was rejected and the court recognised copyright could subsist use of copyright subject to conditions rather than an outright
in a building as distinct from the plans on which the building assignment of all the architect’s rights. An increasing number
was based. This has been expressly recognised by s.4(1)(b) of of public and commercial clients make it a condition of the
the Act. architect’s appointment that all copyright shall vest in the
client.
7.07 Infringement is largely confined to making a three-dimen- The architect should not consent to this without careful
sional copy whether in the form of another building or a model. thought. Following Meikle v Maufe, it would seem reasonable
that a client should not be prevented from extending a build-
ing and incorporating distinctive design features of the original
Copying a building in the building so that the two together should form one architectural
unit. If the time between the original building and the extension
form of drawings were 23 years, as in that case, it would be restrictive to make
7.08 Copyright in a work of architecture is not infringed by use of copyright to force the client into employing the original
making a graphic work representing it, making a photograph or architect or his successor in title. Less scrupulous clients could,
file of it, or broadcasting or including a visual representation however, make use of an architect’s design for a small and
of it in a cable program service. In addition, once a building is inexpensive original building with the undisclosed intention of
erected, it is not an infringement of copyright to create and use greatly extending the building using the same design, but at no
drawings of the building to repair or reconstruct the building extra cost in terms of architects’ fees.
(see section 6.02).
8.04 So far as drawings are concerned, it must be remembered
that they are the subject of copyright ‘irrespective of artistic
8 Licenses quality’, so that a prior express assignment of copyright to the
client could theoretically grant him copyright in respect of even
Express licenses the most simple standard detail contained in the drawings (but
see paragraph 5.06).
8.01 Paragraph 6.1 of the Conditions of Engagement which
appear in the RIBA Standard Agreement for the Appointment
of an Architect 2010 (2012 Revision) states that copyright in Implied licenses
all documents and drawings prepared by the architect remains 8.05 While the RIBA Architect’s Appointment contains an
the property of the architect. Section 91 of the Act permits prior express licence of the architect’s copyright, situations may arise
assignment of future copyright so that client and architect can where the RIBA Architect’s Appointment does not form part of
agree at the beginning of an engagement to vary the Conditions the contract between the architect and the client, or where the
of Engagement so that the copyright which will come into exist- terms of the RIBA Architect’s Appointment do not cover particu-
ence during the commission will vest in the client. lar circumstances. Problems may then arise as to what rights the
Licenses 363

client has to use the architect’s drawings. As long ago as 1938, detail necessary to obtain Building Regulations consent, this
the RIBA took Counsel’s opinion on the theory that an architect consent having been obtained the contractor erected the houses.
impliedly licenses his client to make use of the architect’s draw- When the architect discovered that his plans were being used
ings for the purposes of construction, even when the client does he claimed that this was an infringement of his copyright. The
not employ the architect to supervise the building contract. Such Court of Appeal held that although the RIBA Conditions of
an implied consent can be understood when, from the beginning Engagement provided that copyright remained with the architect,
of the engagement, the client made it clear that all he required of it was open to him to give a license for the drawings to be used
the architect was drawings; for if the client received the draw- for a particular site. The court was influenced by the provision
ings and paid for them, they would be valueless unless he could in the RIBA Conditions which entitled both architect and client
use them for the purpose of construction. The courts would not to terminate the engagement ‘upon reasonable notice’. It seemed
allow an architect to use his copyright to prevent construction in inconceivable that upon the architect withdrawing consent he
such circumstances. Counsel advised further that even if it had could stop any use of the plans on the ground of infringement of
originally been assumed that the architect would perform the full copyright. It seemed equally inconceivable that he could prevent
service and supervise construction, but the client subsequently their use at an earlier stage when he had done his work up to a
decided that he did not require supervision, an implied licence particular point and had been paid according to the RIBA scale.
to use the copyright in the drawings would arise in the client’s The court approved the defendant’s submission that the implied
favour when working drawings had been completed. Counsel license was ‘to use whatever plans had been prepared at the
did not then believe that an implied license could arise at an appropriate stage for all purposes for which they would normally
earlier stage, but since 1938 the extent of architects’ work and be used, namely, all purposes connected with the erection of
its stages have increased greatly. Cumulatively, detailed draw- the building to which they related’. If this was not correct, ‘the
ings required for outline planning consent, detailed planning architect’ could hold a client to ransom, and that would be quite
consent, and Building Regulations consent all create different inconsistent with the term that the engagement could be ‘put an
stages, and an implied license can now arise earlier than was end to at any time’.
contemplated in 1938.

8.06 Before any term can be implied into a contract, the courts
Stovin-Bradford v Volpoint
must consider what the parties would have decided if they Properties Ltd (1971)` Ch 1007
had considered the question at the time they negotiated other 8.09 The defendant companies, which had their own draw-
terms of the engagement. The courts are reluctant to imply a ing office, acquired an old factory which they considered had
term unless it is necessary to give efficacy to the intention of considerable development potential, and applied for planning
the parties. Application of these rules to an architect’s engage- consent for the erection of seven large warehouses. Permission
ment would suggest that it is reasonable to infer that architects was refused, and the defendants approached Stovin-Bradford,
impliedly consent to the client making use of their drawings whose work they had previously admired, explaining that they
for the purpose for which they were intended. If, therefore, needed a plan and drawing that ‘showed something which
the nature of the engagement is not full RIBA service but, for was more attractive-looking than the existing building’. What
example, obtaining outline planning permission and no more, they wanted was ‘a pretty picture’, but because they had their
the architect impliedly consents to the client making use of his own drawing office, they did not need the full services of an
copyright to apply for such permission. Again, if an architect is architect.
instructed to prepare drawings of a proposed alteration for sub- It was accepted by the court that, although the then Conditions
mission to the client’s landlord, the client may use the drawings of Engagement were not incorporated into their contract, both
to obtain a consent under the terms of the lease but not for any architect and defendants were fully aware that they existed. It
other purpose, and certainly not for the purpose of instructing a was also accepted that both parties were concerned only with
contractor to carry out the alteration work. obtaining planning permission. At first instance, it was held that
the agreement reached between the parties was very simple and
8.07 The whole question of implied licence has been considered amounted to this:
by the Court of Appeal in Stovin-Bradford. Reference should
also be made to Robin Ray v Classic FM pic, (see section 5.08), that Stovin-Bradford would suggest architectural improve-
which reviewed the authorities relating to implied copyright ments to the defendant’s existing plan for the modification
licenses in consultancy agreements, in that case the copyright and extension of the existing building for the purpose of try-
in a database of classical music. ing to obtain planning permission and that he would receive
for this plan the sum of 100 guineas and his out-of-pocket
expenses.
Blair v Osborne & Tompkins
(1971 2 QB 78) The drawing was produced showing an effect quite striking to
the eye: a unification of two original structures into one with,
8.08 Blair, an architect, was asked by his clients whether it in particular, a diamond feature in the left hand building caused
would be possible to obtain planning consent for a development by the arrangement of the roof line and the windows placed in
at the end of his clients’ garden. Having made enquiries, Blair the top part of the old portal frame building.
advised that it should be possible to obtain consent for erection The plan was passed to the defendants, who made certain
of two semi-detached houses. The clients instructed Blair to amendments and obtained planning permission. Stovin-Bradford
proceed to detailed planning consent stage and agreed to pay had presented his account for the agreed ‘nominal’ 100 guineas,
on the RIBA scale. The application was successful, and Blair headed it ‘Statement no. 1’, and confirmed that the payment was
sent the planning consent to his clients, with his account for ‘for preparing sketch plans and design drawings in sufficient
£70 for ‘taking instructions, making survey, preparing scheme detail to obtain or apply for planning permission’. At the foot
and obtaining full planning consent’. As was well known to the of the invoice was typed a note saying: ‘The copyright of the
architect, the clients did not, at that stage, know whether they design remains with the architect and may not be reproduced
were going to develop the land or sell it. in any form without his prior written consent’. The defendants
They paid Blair’s account, which he acknowledged, adding proceeded to erect the buildings, and although many details
‘wishing you all the best on this project’, but did not employ were changed, the result incorporated the particular features
him to do any further work, because they sold the plot to a of the Stovin-Bradford design to which the trial judge drew
contractor/ developer. They also handed over Blair’s draw- notice. The trial judge held that there was an infringement and
ings to the contractor, who used his own surveyors to add the awarded £500 damages as the amount which would have been
364 Copyright and design protection

‘ reasonably chargeable’ for a license to make use of the copy- made if he had been employed to carry out the work which
right. This was upheld by the Court of Appeal which found there infringed his copyright: ‘Such profits do not provide either a
was infringement, no implied licence, and that the £500 damages mathematical measure for damages or a basis upon which to
was reasonable. estimate damages. Copyright is not the sickle which reaps an
architect’s profit’.
8.10 From these two decisions, it would appear that charging Graham J, in the Stovin-Bradford case, confirmed the licence
by the RIBA scales for partial services (whether originally fee basis of the two earlier cases and awarded £500 against the
contemplated or brought about by a termination) will give rise claimant’s request for £1000 and the defendant’s suggestion of
to an implied license, while charging a nominal fee will not. between £10 and £20. Although this point has not been decided
If the agreement between the parties is silent, it is usually the with reference to architect’s copyright, it would appear that on
case that some form of license will be implied, but the extent general principles, exemplary damages could be awarded in
of that license will depend on the facts. The RIBA Architect’s addition to the licence fee where the breach was particularly
Appointment provides that the client will have an express license flagrant.
to use the drawings only for the specific purpose for which they In Potton Ltd v Yorkelose Ltd [1990] 17 FSR, the defend-
were prepared, and in particular, that the preparation of draw- ants admitted that they had constructed 14 houses, in
ings for obtaining planning permission does not carry with it the infringement of the claimants’ copyright, on a style of house
right to use them for construction of the building without the named ‘Grandsen’. The defendants’ houses were substantial
architect’s express consent (which ought not to be unreasonably reproductions of the claimants’ Grandsen drawings, and they
withheld). had copied the drawings for obtaining outline planning per-
mission and detailed planning permission. It was held that
8.11 The implied license probably includes a right to mod- the claimants were entitled to the profits realised on the sale
ify the plans, although the law is not settled on this point of the houses, apportioned to include profits attributable to
(Hunter v Fitzroy Robinson [1978] FSR 167). If the Architect’s (a) the purchase, landscaping, and sale of the land on which
Appointment does not apply, the probability is that the implied the houses were built; (b) any increase in value of the houses
license will not be revocable by the architect, even if the fees during the interval between the completion of the houses and
have not been paid. their sale; and (c) the advertising, marketing, and selling of
the houses.
In Charles Church Development plc v Cronin [1990] 17 FSR
Alterations to architect’s drawings the defendants admitted that they had had a house built based
and works of architecture on plans which were the copyright of the claimant. The dis-
tinction between this case and Potton Ltd v Yorkelose Ltd is
8.12 If the client alters the plans or the completed building, that in the former case, the houses were built for sale and
the probability is that he will not thereby be in breach of the had been sold, whereas in this case, the house had not been
architect’s copyright (Hunter v Fitzroy Robinson). However, sold, and the claimants had obtained an injunction to prevent
the client may not ‘sell or hire’ buildings or plans as the unal- its sale. In the former case, the claimant sued for an account
tered work of the architect (see Section 11 below dealing with of profits. In the latter case, the claim was for compensatory
moral rights). damages for the loss caused by the infringement. The judge
held that the measure of damages was a fair fee for a licence
to use the drawings, based on what an architect would have
9 Remedies for infringement charged for the preparation of drawings. The architect’s fee
should be calculated on the basis that the architect would have
Injunction provided the whole of the basic services – in that case, 8.5%
of the building costs.
9.01 An injunction can be obtained to prevent the construction of
a building that would infringe the copyright in another building, 9.04 Secondary losses caused by an infringement, such as
even if that building is part-built. Section 17 of the 1956 Act payment discounts and overdraft requirements relating to cash
provided that no injunction could be granted after the construc- flow problems, are too remote to merit compensation (Claydon
tion of a building had started, nor could an injunction be granted Architectural Metalwork Ltd v DJ Higgins & Sons Ltd [1997]
to require the building (so far as it has been constructed) to be Ch D 16/1/97).
demolished. This provision was repealed by the 1988 Act and is
not re-enacted in any form. 9.05 The court can award additional damages under section 97(2)
However, there is a general principle of law that an injunction of the Act in cases of flagrant infringement of copyright. In
will not be granted if damages are an adequate relief. It is prob- Cala Homes v McAlpine, Laddie J held that when considering
able that a court would, in most cases, apply this rule in the case whether to award additional damages, the court must look at all
of an injunction to prevent the construction of a building when the circumstances of the case:
the construction has substantially commenced. The decision of
the court will depend upon all the facts and circumstances of Although the court must have regard to the flagrancy of the
the case. infringement and the benefit accruing to the defendant, there
is no requirement that both or indeed either of these features
Damages and account of profts be present. It is possible to envisage cases where the infringer
has gained no benefit from his infringement save for the
9.02 Damages are available to compensate the claimant for satisfaction of spite fulfilled. In such a case, if infringement
the loss in value of the copyright resulting from the infringing was flagrant it appears that the court might award additional
action. An alternative claim to damages is an account of profits. damages’. Laddie J acknowledged that these damages could
The claimant elects for the profits that the defendant has made be ‘of a punitive nature.
by the unauthorised exploitation of the copyright.
More recently, the High Court in Nottinghamshire Healthcare
9.03 In Chabot v Davies the court held that the measure of dam- National Health Service Trust v News Group Newspapers Ltd
ages for infringement of the designer’s copyright was the amount [2002] EWHC 109 held that additional damages can be awarded
which he might reasonably have charged for granting a licence under section 97 of the Act in a case of deliberate or reckless
to make use of his copyright. infringement. However, additional damages will not be awarded
In Meikle v Maufe, the court rejected an argument that the if a successful claimant seeks an account of profits (Redrow
architect might reasonably claim the profit which he would have Homes Ltd v Bett Brothers Plc [1999] 1 AC 197).
UK Design Law 365

10 UK Design Law should reasonably have become known in the normal course of
business to persons working in the European Economic Area and
10.01 The law on this subject is complicated, involving UK and specialising in the sector concerned.
EU rights. In summary, there are five relevant design rights:
10.06 Registration initially lasts for five years, on payment of
1 UK registered design right (Registered Designs Act 1949 as fees, and is renewable for further five-year terms, up to 25 years.
amended by the Act); The owner of the registered design would normally be the
2 UK design right (created by the Act); original author, but frequently, manufacturers who commission
3 EU unregistered design right (EU Regulation No 6/2002); a component insist upon the design being registered in its name.
4 EU registered design right (EU Regulation No 6/2002);
5 Copyright in the industrial application of ‘artistic works’ 10.07 A design is taken to have been used industrially for the
applied industrially. purpose of the Registered Designs Act if it is applied to more
than 50 articles.
Architects who may be commissioned to design articles or
components capable of mass reproduction are advised to seek
professional advice before entering into any agreement commis-
sioning the design of such articles or components or assigning UK Unregistered Design Right
or licensing the rights therein.
Similarly, architects who design such articles or components 10.08 The Act largely abolished copyright protection for most
should seek professional advice as to what steps should be industrial designs, although copyright will subsist in the design
taken to protect them. Design falls mid-way between copyright document per se. It introduced a new, unregistered ‘design
(not registrable in the UK), which is concerned with ‘artistic right’. For this right, ‘design’ means the design of any aspect of
quality’, and patents, which must be registered and are not the shape or configuration (whether internal or external) of the
concerned with artistic quality, but with function and method whole or part of an article.
of manufacture.
The law on industrial designs was considerably changed by 10.09 The design must be original in that it is ‘not common-
the Act and subsequent EU law. The present law is contained in place in the relevant design field’. Ocular Sciences Ltd v Aspect
the Registered Designs Act 1949 (as amended by the Act) and Vision Care Ltd [1997] RPC 289 decided that ‘commonplace’
the Registered Designs Regulations 2001SI 2001/3949 (which requires an objective assessment and is likely to cover ‘any
implements the EU Directive on the Legal Protection of Designs design which is trite, trivial, common-or-garden, hackneyed or
Directive 98/71/EC) and the Act. of the type which would excite no peculiar attention in those in
The EU system of unregistered and registered designs is the relevant art’.
directly enforceable in the UK as a result of Regulation (EC)
No. 6/2002. 10.10 The general rule (Farmers Build Ltd v Carier Bulk
Materials Handling Ltd [1999] RPC 461 (CA)) in determining if
a particular design is commonplace is whether, from the perspec-
UK Registered designs tive of the ultimate consumer, at the time of creation, the features
of design are reproduced in the design of similar articles. The
10.02 The design of any industrial (or handicraft, which closer the similarity in features, the more likely the design in
includes sculpture) item, part of an item, or its ornamenta- question is ‘commonplace’.
tion resulting from features of lines, contours, colours, shape,
textures, and materials, provided it is new and has individual 10.11 Design right does not subsist in a method or principle of
character, may be registered at the UK Intellectual Property construction, nor does it subsist in surface decoration. It does
Office under the provisions of the Registered Designs Act not subsist in features of shape or configuration of an article
1949, as amended. that enables the article to be connected to, or placed in, around,
or against, another article so that either article may perform
The definition of a design under section 1 is: its function; nor must it be dependent upon the appearance of
another article of which the article is intended by the designer
the appearance of the whole or a part of a product result- to be an integral part. This means that designs of spare parts are
ing from the features of, in particular, the lines, contours normally excluded from design right protection. Because design
, colours ,shape, texture or materials of the product or its right subsists additionally to and does not replace artistic
ornamentation. copyright, the exclusions from design right protection do not
exclude artistic copyright protection from, for example, surface
10.03 Protection is granted to designs irrespective of artistic decoration.
merit. Protection is not granted for features of a design that are
(inter alia) not novel or of individual character, are dictated by 10.12 Design right does not subsist unless and until the design
their technical function, consist of features which must be repro- has been recorded in a design document or an article has been
duced so as to permit the product to fit or connect to another made to the design.
(‘must-fit’), or conflict with an earlier design application or
registration. 10.13 Design right expires 15 years from the end of the calendar
year in which the design was first recorded in a design document
10.04 It is the design, not the article bearing the design, that is or an article was made to the design. Alternatively, if articles
protected. Therefore, although a design owner must specify the made to the design are made available for sale or hire within
products to which the design will be applied or incorporated this five years from the end of that calendar year, the design right
does not limit the scope of protection. will expire 10 years from the end of the calendar year in which
that first occurred. In the last five years of design right, protec-
10.05 Registration of a design grants to the registered owner the tion licences for the exploitation of the design must be granted
exclusive or monopoly right to use the design, thereby entitling (licenses of right) if requested.
the owner to restrain reproduction of the design in the UK,
regardless of independent creation. For this reason, a registration 10.14 To qualify for design right protection, the requirements
is valid only if the design (or a variation that is wholly insig- set out in sections 217 to 221 of the Act must be met, which
nificant) has not previously been used, published, or exhibited have similarity to the qualification requirements described in
anywhere in the world. The proviso is that the earlier design section 3 above.
366 Copyright and design protection

10.15 As for copyright protection, design right enables the owner on the building as constructed, or, where more than one building
to prevent unauthorised copying and other infringements. The is constructed to the design, on the first to be constructed.
test for infringement of design right was differentiated from the
copyright test in Woolley Jewellers Ltd v A& A Jewellery Ltd 12.04 The right must be asserted by the author on any assign-
[2002] EWCA Civ 1119: ment of copyright in the work or by instrument in writing signed
by the author. In the case of the public exhibition as an artistic
There is a difference between an enquiry into whether the work (for example, the inclusion of a model of a building in an
item copied forms a substantial part of the copyright work exhibition), the right can be asserted by identifying the author
and an inquiry into whether the whole design containing the on the original or copy of the work, or on a frame, mount, or
element copied is substantially the same design as that which other thing to which the work is attached. If the author grants a
enjoys design right protection. license to make copies of the work, then the right can be asserted
for exhibitions by providing in the license that the author must
Arden LJ went on to conclude that: ‘It may not be enough to be identified on copies which are publicly exhibited.
copy a part or even a substantial part. Regard has to be had to
the overall design which enjoys design right’. 12.05 There are certain exceptions to the right, of which the most
The provisions of the Act ensure that a claimant cannot suc- important is that it does not apply to works originally vested in
ceed in both copyright and design right infringement claims in the author’s employer (see section 5.02).
respect of the same acts of infringement.
12.06 The author of a literary, dramatic, musical, or artistic
work has the right to object to his or her work being subjected
11 EU Design Law to derogatory treatment. ‘Treatment’ means any addition to,
deletion from or alteration to or adaptation of the work. The
11.01 The EU Design Regulation came into force on 6 March treatment is derogatory if it amounts to distortion or mutilation
2002. It created two methods of EU-wide protection for designs: of the work or is otherwise prejudicial to the honour or reputa-
tion of the author.
(a) EU Registered Designs: registration of qualifying designs The right in an artistic work is infringed by the commercial
entitles the owner to a monopoly against use of that design publication or exhibition in public of a derogatory treatment
throughout the EU for a maximum of 25 years from filing. of the work, or a broadcast or the inclusion in a cable pro-
The registration process is equivalent to the UK system and gram service of a visual image of a derogatory treatment of
can be organised via the UK Patent Office or direct with the the work.
EU Intellectual Property Office. In the case of a work of architecture in the form of a model of
(b) EU Unregistered Designs: qualifying designs automati- a building, the right is infringed by issuing copies of a graphic
cally receive EU-wide protection against copying, lasting work representing, or of a photograph of, a derogatory treatment
three years from the first public disclosure of the design of the work.
in the EU. However, and most importantly, the right is not infringed in
the case of a work of architecture in the form of a building. But
The rules relating to the qualification for both unregistered and if a building is the subject of derogatory treatment, the architect
registered EU designs are equivalent to the rules for UK regis- is entitled to have his or her identification on the building as its
tered designs, as outlined in paragraphs 10.02–10.07 above. This architect removed.
differentiates the protection granted by virtue of the UK unreg- In the case of works which vested originally in the author’s
istered design right with the rights granted by the Community employer, the right does not apply.
unregistered design right (see paragraph 10.06 above).
Both rights are justiciable in the UK courts. 12.07 In the case of a literary, dramatic, musical, or artistic
work, a person has the right not to have its authorship falsely
11.02 Following the UK’s departure from the EU, it is probable attributed to him or her. Thus, architects can prevent a building
that EU registered designs owned by UK entities will be converted which they have not designed being attributed to them as its
into UK registered designs. It has been indicated by the UK gov- architects.
ernment that a new unregistered design right equivalent to the cur-
rent EU unregistered design right will be introduced into UK law. 12.08 The right to privacy of certain films and photographs
Existing EU design rights will remain enforceable within the EU. applies only to films and photographs commissioned for pri-
vate and domestic purposes, and accordingly, is hardly relevant
here.
12 Moral Rights
12.09 The rights to be identified as an author of a work and to
12.01 Moral rights of authors have existed in continental object to derogatory treatment of a work subsist as long as copy-
European legal systems for many years, but the 1988 Act intro- right subsists in the work. The right to prevent false attribution
duced them to UK law for the first time. continues to subsist until 20 years after a person’s death.

12.02 There are four basic categories of moral rights contained 12.10 Moral rights can be waived by an instrument in writ-
in the Act: ing signed by the person entitled to the right. However, moral
rights may not be assigned to a third party, although they pass
1 The right to be identified as author; on death as part of the author’s estate and can be disposed of
2 The right to object to derogatory treatment of work; by the author’s will.
3 False attribution of work;
4 The right of privacy of certain photographs and films.
13 Law of copyright in Scotland
12.03 Under section 77(4)(c) of the Act, the author of a work of and Northern Ireland
architecture in the form of a building or a model for a building,
has the right to be identified whenever copies of a graphic work 13.01 There is no difference between the substantive law of
representing it, or of a photograph of it, are issued to the public. copyright in Scotland and England, and the Act applies to all
parts of the UK. The power to legislate on intellectual property
Section 77(5) also provides that the author of a work of architec- in Scotland is reserved to the UK Parliament under the provi-
ture in the form of a building also has the right to be identified sions of the Scotland Act 1998.
37
Data protection
HAZEL GRANT

1 Introduction Regulations 2019) will make some small amendments to the


DPA to ensure that it continues to apply even after the UK
1.01 This chapter addresses the application of data protection leaves the EU.
law to an architect's business. Data protection law applies, in
almost all cases, to protect information relating to living indi- 1.06 Guidance and assistance in understanding and applying data
viduals. As a result, its scope, when applied to an architect's protection law is provided by the UK’s data protection regula-
business, will likely relate to employees, individual clients, and tor, the ICO, or Information Commissioners Office. Helpfully,
business contacts. This chapter will look at examples of the the ICO has a comprehensive website at www.ico.org.uk (and
impact of data protection law on those individuals. helpline) where businesses can find out more about the GDPR
and DPA.

The Key Legislation


2 Overview of Data Protection Law
1.02 The relevant data protection legislation in the UK is as
follows:
Defned Terms
● the General Data Protection Regulation (‘GDPR’). The 2.01 Data protection uses its own language of certain defined
GDPR is a regulation of the European Union (EU) and, as a terms which are worthy of review before delving into the law.
result, directly applies to all EU member states in full force First, organisations such as architect’s businesses are likely
from 25 May 2018. to be ‘data controllers’. A data controller is ‘the natural or
● the Data Protection Act 2018 (‘DPA’). This expanded upon legal person … which, alone or jointly with others, determines
and explained the GDPR in the UK. Essentially, the DPA the purposes and means of processing of personal data’. In
explained that the GDPR applied to all private sector busi- essence, this means it is the organisation or the person who
nesses operating in the UK, and therefore in many cases it is decides if personal data will be collected and why it will be
necessary to go back to the GDPR to find the wording of the processed. In any situation, it is key to decide who is/are the
relevant law. Additionally, the DPA added some specific UK data controller/s. This is because the vast majority of obliga-
provisions, such as detailed exemptions, so for those aspects tions under data protection law will fall on the shoulders of
of the law it is necessary to refer to the DPA. the data controller/s. It is important to note (and can cause
confusion) that if an architect's business is a legal entity (e.g.
1.03 This chapter will therefore refer to both the DPA and the a company), then the company will be the data controller (and
GDPR. Although the GDPR is a regulation, and therefore takes not any individual who might be tasked with dealing with data
direct effect in EU member states, it allowed member states protection compliance).
some flexibility in applying the law (for example, in relation to A data processor is ‘a natural or legal person … which pro-
freedom of information – i.e. access to publicly held informa- cesses personal data on behalf of the controller’. Essentially,
tion). This chapter therefore looks at how the UK has applied the therefore, a processor is a service provider acting on behalf of
GDPR, and readers should note that in some EU jurisdictions, a controller. Examples of a processor might be an organisation
there can be some local variations. that carries out payroll processing for an architect's business or
an IT service provider that hosts an architect's email infrastruc-
1.04 Additionally, there are some situations, described below, ture or website.
where another piece of legislation, the e-privacy regulations Both of these definitions have referred to personal data. The
(the Privacy and Electronic Communications (EC Directive) definition of personal data is exceptionally broad and refers to
Regulations 2003 or ‘PECR’), can apply to marketing carried
out by an architect's business. any information relating to an identified or identifiable
natural person (“data subject”); an identifiable natural per-
1.05 At this point, it is worth highlighting that Brexit (the son is one who can be identified, directly or indirectly in
proposed departure of the UK from the EU) should not fun- particular by reference to an identifier such as a name, an
damentally affect the description of the law as set out in this identification number, location data, an online identifier or
chapter. The DPA has already applied the GDPR to the UK. to one or more factors specific to the physical, physiologi-
Upon Brexit a statutory instrument (the Data Protection, Privacy cal, genetic, mental, economic, cultural or social identity of
and Electronic Communications [Amendments etc] [EU Exit] that natural person.

367
368 Data protection

As will be self-evident, employee records will clearly be per- ● a requirement for a legal justification for processing of
sonal data, as the employee will be identified by the records. personal data.
Equally, a CRM system (customer relationship management) or
marketing system will contain personal data, as the individual 2.07 There is also a broader requirement that the processing be
customers (or contacts) will be identified natural persons. ‘lawful’. This has been interpreted as saying that the processing
must comply with other relevant laws as well as data protection
Lastly, it is worth looking at the definition of processing. Again, in order to be lawful under data protection law. For example, if
this is exceptionally broad and covers an architect is processing confidential information about a client
(e.g. a potential development that for commercial reasons needs
any operation or set of operations which is performed to be kept secret), then the architect could be in breach of both
on personal data or on sets of personal data … such as confidentiality and data protection law if it discloses the poten-
collection, recording, organisation, structuring, storage, tial development to the public.
adaptation or alteration, retrieval, consultation, use, disclo-
sure by transmission dissemination, or otherwise making
available, alignment or combination, restriction, erasure Notices
or destruction.
2.08 Under the GDPR, there is a specified list of information that
As can be seen, this covers anything to do with the handling of must be made available in a privacy notice (sometimes called a
personal data – from collection to destruction. If a business has privacy policy). This includes details of the data controller, the
personal data (even just in storage), then data protection law name of any data protection officer (DPO), details of the per-
will be relevant. sonal data handled, the reasons why, any international data trans-
fers, and the availability of individual rights. This is an expanded
list from previous legislation, so any privacy notices (to either
Data Protection Principles employees or clients) will need to be reviewed and expanded.
2.02 In data protection law, it has long been the practice to have
a set of core principles around which the law is structured. This
applies also to the GDPR, where there are the following core Legal justifcation for processing
principles, stating that personal data shall be:
2.09 All data controllers must have a legal justification for
● processed lawfully, fairly, and in a transparent manner (‘law- processing of personal data. This can (but need not) be consent,
fulness, fairness and transparency’); discussed further below. Common justifications are:
● collected for specified, explicit, and legitimate purposes and
not further processed in a manner that is incompatible with ● consent from the individual;
those purposes (‘purpose limitation’); ● the processing is necessary to comply with a contract or
● Adequate, relevant, and limited to what is necessary in other legal obligation;
relation to the purposes for which they are processed (‘data ● the processing is necessary for the purpose of the legitimate
minimisation’); interests of the controller or a third party, except where
● accurate and, where necessary, kept up to date (‘accuracy’); such interests are overridden by the interests or fundamental
● kept in a form that permits identification of data subjects rights or freedoms of the individual (called ‘legitimate inter-
for no longer than is necessary for the purposes for which ests’ and requiring a controller to document the decision to
the personal data are processed (‘storage limitation’); and process on this basis).
● processed in a manner that ensures appropriate security of
the personal data including protection against unauthorised 2.10 Where a data controller is handling ‘special categories of
or unlawful processing and against accidental loss, destruc- personal data’, then additional, stricter justifications must be
tion, or damage using appropriate technical organisational met. These include:
measures (‘integrity and confidentiality’).
● explicit consent of the individual;
● the processing is necessary to comply with a legal obligation
Accountability principle in relation to employment law.
2.03 New in the GDPR is the ‘accountability principle’. This
requires the data controller to be responsible for and demonstrate These special categories of personal data include information
compliance with the principles above. revealing racial or ethnic origins, religious or philosophical
beliefs, genetic or biometric data, and data concerning health.
2.04 This is generally understood to require data controllers to Information relating to criminal convictions is not classified as
maintain detailed records of their data protection compliance being in the special categories of personal data, but is similarly
programme (see, for example, the ICO’s website on account- protected.
ability). As mentioned below, this principle is likely to require a
controller to maintain records of processing (Article 30 records), This will be relevant where an architect collects information on
documentation on use of consent (to prove that it has been pro- health or religious beliefs, or criminal convictions. So, possible
vided), and documentation on use of legitimate business interests scenarios may be where an architect collects information on the
and to ensure staff handling personal data are trained. ill health of its employees, or where an architect runs an event
and is told that attendees require certain meals due to their
2.05 Turning to some of the principles in a little more detail, religious beliefs.
we can explain below the application of these principles to an
architect’s business: Note that under the DPA, if special categories of personal data
are being processed, then the architect should draw up and retain
an appropriate policy document.
Lawfulness, fairness, and transparency
2.06 Under this principle, there are two central requirements on
an architect's business; Consent
● a requirement for a privacy notice or policy to be made 2.11 Under the GDPR, consent is defined as ‘any freely
available to individuals; and given, specific, informed and unambiguous indication of the
Overview of Data Protection Law 369

[individual’s] wishes by which he or she, by a statement or by ● where the information is no longer necessary for the purpose
a clear affirmative action, signifies agreement to the processing for which it was collected; or
of personal data relating to him or her’. ● where the individual withdraws his or her consent, and there
is no other legal justification for processing the information.
2.12 The definition of consent has not fundamentally changed
with the GDPR, however, there is a clear emphasis now on the 2.20 It is clear that, post-implementation of the GDPR, individu-
right to withdraw consent at any time. als are increasingly using this right. That said, it is unlikely to
be relevant for an architect’s business, except in a dispute with
2.13 Data protection regulators have taken the view that in an an individual where he/she wishes to ensure his or her informa-
employment relationship, it is often detrimental to the employee tion is no longer kept. Again, there will be exemptions to this
if he or she does not consent to processing and, as a result, it right, for example, where a legal obligation on the controller
cannot be said that the consent is ‘freely given’. Additionally, requires information to be retained, or the controller may need
the employee must be able to withdraw consent at any time, to defend/pursue legal claims. (An architect may need to keep
which could result in difficult practical situations (e.g. if an some information in order to justify invoices sent to individual
architect relies on consent to allow processing of payroll data by clients or payments made to employees, even in the event that a
a processor based outside the EU, and the employee withdraws client or an employee asks for a right of erasure.)
consent, the architect will then need to find another basis or an
alternative payroll solution for that employee). Therefore, it is
advisable, when collecting information from employees, to avoid
Right to restriction of processing
using consent or consent language and instead to rely on other 2.21 In some circumstances, an individual can require the
justifications. controller to restrict processing. Often, this is an interim step
before another right is being exercised. For example, where the
accuracy of the information is contested by the individual, there
Individual rights could be a period of restriction of processing before the inac-
2.14 Under the GDPR, there are a number of rights given to curate data is corrected.
individuals. In general, where an individual makes a request to
exercise one of these rights, it should be complied with within
one month. There is the possibility to extend this by a further
Right to data portability
two months (making three months in total) where the request 2.22 Individuals have a right to receive personal data concerning
is complex. them that they have provided to a controller. This information
is to be provided in a structured, commonly used, and machine-
readable format, and there is a right to transfer this information
Right of access to another controller.
2.15 This is the right that is most often used and has been
available for decades. Individuals have a right to request a 2.23 This right is likely to be used in situations where people
copy of the information that is held about them. In addition wish to transfer lists of their preferences, shopping, and listen-
to receiving a copy of the information that is held about them, ing habits between service providers. As can be seen, it relates
the individual is entitled to further pieces of information about to information that has been provided by a data subject to a
the processing, such as the purposes of processing, categories controller. It also relates to information that has been generated
of information held, the categories of recipient, the retention by a controller from observation of the individual.
period information, and the sources of the information (where
available). 2.24 Some elements of this could apply to information relating
to a client of an architect, although in all likelihood, the crea-
2.16 Often, this right of access (called a subject access right tion of plans and detailed information or a building would not
[SAR] or data subject access right [DSAR]) can be used as a be considered to be information that has been ‘provided’ by an
precursor to litigation. For example, in employment disputes, individual client; rather, it has been generated by an architect.
disgruntled employees or rejected candidates for positions can In any event, the right to data portability is subject to a limita-
request access to the information held about them in order to tion that it shall not adversely affect the rights and freedoms of
gain evidence or information which is then used for a claim others. This is generally understood to include impacting on the
against the employer or potential employer. There have been intellectual property rights. Therefore, were a client to request
cases concerning this and there is some dispute as to whether the right to data portability in order to obtain plans, it is likely
this right should be used to circumvent the normal rules of that an architect would argue that its intellectual property rights
disclosure and litigation. Nevertheless, the view of the ICO is would be adversely affected by implementing that right to data
that this is a fundamental right of individuals, and therefore, if portability.
a request is made, it must be satisfied regardless of any potential
litigation.
Right to object
2.17 It is important to know that there are some limited exemp- 2.25 An individual has the right to object to any processing of
tions that can apply to the disclosure of this information, which personal data relating to them when the processing is based on
will be discussed below. legitimate interests and the balancing of interests is no longer
in favour of the controller. Additionally, there is specific right
to object to direct marketing, which is the scenario where an
Right to rectifcation architect's business is most likely to come across the exercise
2.18 An individual has the right to obtain rectification of inac- of this right. If a client objects to direct marketing, the architect
curate information held about them. In truth, it is difficult to see will be required to stop direct marketing.
how this might apply in an architect's business.
Automated decision making
Right to erasure or right to be forgotten 2.26 Lastly, an individual has the right not to be subjected to
2.19 The GDPR introduced this as a formal right, although it did automated decision making where this produces legal effects
exist in a different format in previous legislation. In this case, concerning him or her. In relation to an architect’s business, this
the individual has the right to obtain erasure of information held is unlikely to exist, but could come up potentially if, for exam-
about him or her in various situations, including: ple, an architect used an automated system in order to assess or
370 Data protection

prequalify candidates for a job. In this situation, an individual ● the data processor will assist in complying with data subject
must be informed of the use of automated decision taking and rights and audits and inspections from the controller.
consent to the use of automated decision taking in the process.
Additionally, the individual must be given an opportunity to
have human intervention in the decision and to allow the indi-
Records of processing
vidual to contest the decision. 2.33 Both data controllers and data processors are required
to keep detailed records of the processing that they carry out.
These Article 30 records (named after the relevant article of the
Exemptions to individual rights GDPR) need to be compiled, completed, documented, and kept
2.27 The law sets out a number of exemptions to the rights up-to-date, and can be requested by the ICO when they carry
referred to above, and these vary by EU member state. The rel- out investigations.
evant exemptions for the UK are set out in the DPA.
2.34 The records should detail a number of specific items (the
2.28 Generally, the exemptions are most relevant when applied ICO have produced a sample Article 30 spreadsheet to assist
to the right of access, where the most commonly used exemp- with this process). In brief, the details include the data pro-
tions include: cessed, legal justification, retention period, use of third parties,
transfer outside the EU, and justification for transfer.
● legal privilege – information that is protected by legal
privilege;
● negotiations – information about negotiations with the indi-
Security and security breaches
vidual requesting the right; 2.35 Under the GDPR, there is an obligation to ‘implement
● management forecasts – information about management appropriate technical and organisational measures to ensure a
planning; level of security appropriate to the risk’.
● confidential references – given or to be given;
● information relating to third parties – where the individuals 2.36 It is worth noting this is an obligation that is placed both
have not agreed to its disclosure; on the controller (i.e. the architect) and the processor (i.e. the
● prevention or detection of crime – information necessary for service provider). Although this is a very general statement,
the prevention or detection of crime. it does allow for the obligation to change over time, as the
expectations for security, and technical solutions to ensure
2.29 When applying these exemptions, it is necessary for a con- security change.
troller to look carefully at the wording, as often, the exemptions
only apply to the extent ‘necessary’, or where to disclose the 2.37 The GDPR and DPA do not, unfortunately, provide a
requested information would prejudice the aims of the exemp- checklist of what is good security. There are, however, standards
tion. Therefore, it is likely that an exemption will not apply in a that can be followed that are likely to address the mostly com-
‘blanket’ manner to all information requested, but rather, it will monly required security measures (e.g. BSI or ISO certifications/
need to be applied to specific pieces of information requested. standards). The GDPR also specifically mentions actions such
For example, if an employee makes a SAR, information may be as pseudonymisation of data (e.g. storing identifiers separately
withheld if there are salary negotiations with the employee, but to the remainder of the personal data) and encryption of data
he/she would be entitled to other information such as his/her as being beneficial. It also refers to backups and the ability to
personnel record and potentially emails about him/her. restore availability. It is sensible for architects to pay particular
attention to security as, historically, the ICO has carried out the
majority of its enforcements in this area.
Responsibilities of the architect
2.30 The data controller is considered the primary organisation 2.38 A new obligation within the GDPR was a clear requirement
responsible for compliance with data protection law. For our to notify personal data breaches to the ICO and, in certain situ-
purposes, most responsibilities will fall on the shoulders of the ations, to the affected individuals. It is important to note that
architect as data controller. Nevertheless, in some situations, data this new obligation to notify the ICO does not cover any breach
processers (i.e. service providers or agents) also have their own of the GDPR or DPA: it is limited to personal data breaches,
set of responsibilities. which is a breach of security leading to accidental or unlawful
destruction, loss, alteration, unauthorised disclosure of, or access
2.31 Where an architect’s business decides to engage a service to, personal data. So, for example, a failure to complete records
provider (called a data processor) to process personal data, of processing (or Article 30 records), as described above, does
then specific obligations fall upon the architect to carry out due not need to be confessed to the ICO; whereas the loss of a lap-
diligence, i.e. raise questions of the processor to ensure that it top containing employee data, or a hack of a website including
is carrying out its processing in accordance with data protection client contact details may well be notifiable to the ICO (and the
law and has adequately trained its staff. affected individuals).

2.32 It is also necessary to put in place a contract between the 2.39 Where a breach occurs, the first step might be that the agent
architect data controller and the service provider whereby the or processor notices a breach. In this case the processor must
service provider confirms that: notify its controller without undue delay upon becoming aware
of the breach. At that point or, at the point at which the architect
● it will only process personal data on the documented instruc- controller recognises that a breach has occurred, it has 72 hours
tions from the controller (which can be as set out in the after becoming aware of the breach to notify the ICO. That
contract between the two parties); said, notifications are not required in all situations: where the
● individuals processing the data have confirmed that they will personal data breach is ‘unlikely to result in a risk’ to the rights
keep it confidential; and freedoms of natural persons, no notification is required.
● there are appropriate security measures in place; For example, where the personal data lost was encrypted to an
● if there is a sub-processor, similar conditions will be adequate level, then there is unlikely to be risk to individuals,
imposed up in that sub-processor; and so notification is not required.
● if there is a data breach, the processor will promptly notify
the controller and assist in the remediation steps; 2.40 Where the personal data breach is likely to result in a high
● the processor will delete all personal data belonging to a data risk to an individual, then the controller also needs to notify the
controller at the end of a contract; and individuals affected. An example of where this might occur is
Application of the law: common scenarios 371

if the data that has been lost relates to living individuals and 2.49 There are various ways of justifying or permitting the
potentially includes, for example, their financial details. transfer of personal data outside the EEA. Almost inevitably,
for the vast majority of businesses, the method of choice is
using the Standard Contractual Clauses (or SCCs). These are
Data protection impact assessments contracts that have been approved by the European Commission
2.41 The GDPR requires data protection impact assessments (EC) and address transfers to either a controller or a processor
(‘DPIAs’) in limited circumstances where there is profiling outside the EEA.
or other systematic and extensive evaluation of individuals or
where there is processing on a large scale of the special catego- 2.50 There are exemptions for certain transfers, for example,
ries of personal data. It is unlikely that an architect's business to permit transfers to pursue legal claims or where the affected
will be involved in this type and scale of processing. individuals have consented to the transfer.

2.42 That said, some form of impact assessment is good for any
business in order to show accountability and to document how
Registration/notifcation
data protection risks have been addressed. Therefore, although 2.51 Data controllers are required to notify the ICO and pay a
a formal DPIA may not be necessary, it would be good practice notification fee. Whilst, under the GDPR, it was proposed that
for an architect’s business to carry out a more informal impact this practice would be stopped, it has in fact continued in the
assessment when any new system or process for handling UK (albeit with a much briefer notification form).
personal data is contemplated (e.g. before buying a new CRM
system or new HR system). 2.52 Data controllers are required to pay a fixed fee depending
on the number of employees in their business and its turnover.
Full details are set out on the ICO’s website. Failure to pay the
Data Protection Offcer fee (or the correct fee) can result in a fine of £4350.
2.43 Under the GDPR, both a controller and a processor are
required to appoint a Data Protection Office (‘DPO’) in certain
circumstances, including where the core activities of the organi- 3 Enforcement
sation consist of processing operations which require regular and
systematic monitoring of individuals on a large scale. 3.01 Supervisory authorities (i.e. regulators under GDPR, such
as the ICO) have a range of tools available to them in order to
2.44 Under the GDPR, a DPO needs to have some independ- carry out enforcements.
ence from the controller to ensure that he or she can provide
independent advice to the controller on its compliance, and if 3.02 By way of example, the ICO can issue information notices
necessary, warn of non-compliance issues. As a result, under requiring information to be provided to it from a controller. It
GDPR, the DPO has a protected status and cannot be told how can also issue orders suspending or stopping the processing or
to carry out his or her role, or be penalised due to the manner transfer of personal data. However, in most serious cases, the
in which the role has been fulfilled. ICO is likely to rely on its ability to issue administrative fines.
This element of the GDPR was the most highly publicised
2.45 Due to the threshold for the requirement of a DPO, which change implemented by this piece of law. It allows a regulator
provides for the monitoring of a significant number of individu- such as the ICO to impose two levels of fine: the first level is set
als, it is unlikely that an architect’s business will be affected at up to 2% of the total worldwide annual turnover, or 10 million
and required to appoint a DPO. Additionally, guidance from euros, whichever is the higher, and the second level is set at
data protection regulators has confirmed that if the majority of up to 4% of the total worldwide annual turnover or 20 million
processing of personal data relates to employees, a DPO will not euros, whichever is the higher. The two levels apply to different
be required simply to address that type of processing. types of breaches under the GDPR. In general, the first level
applies to administrative failings by a controller or processor.
2.46 Again, though, for the purpose of accountability and The second, higher, level applies to failings which are likely to
ensuring compliance with GDPR, it would be good practice to affect individuals more directly, for example, failure to comply
appoint employees to manage data protection compliance for with individuals rights.
the business. These individuals should not be called ‘DPOs’,
which could be confusing and could lead to the individuals 3.03 As at the date of writing, the vast majority of the fines
having the protected status of the DPO. Instead, some alter- issued by the ICO fell under the previous legislation (with a
native position should be created, such as data protection maximum of £500,000). The ICO has had to wait for breaches
coordinator/manager. which occurred/were occurring post 25 May 2018 to turn to the
new fining powers. That said, the ICO has issued intention to
fine notices to BA of £183 million (approx. 1.5% of turnover)
Transfers of personal data and to Marriott Hotels of £99 million (approx. 3% of turnover).
Both relate to alleged security failings and are (at the time
outside the EEA of writing) not finalised. (Prior to issuing a monetary penalty
2.47 It has long been a concept under European Data Protection notice, the ICO issues an intention to fine notice to the relevant
law that personal data is protected whilst it is kept within the entity.) To date, the ICO has fined businesses based on security
EEA. The EEA comprises the EU plus Norway, Iceland, and breaches (since these are notified to the ICO and are generally
Liechtenstein. These jurisdictions apply, and are therefore con- straightforward for the ICO to justify a fine), but it will no
sidered to be compliant with the GDPR. doubt turn to other breaches of the DPA as information on other
breaches comes to light.
2.48 Therefore, when data is sent outside the EEA (or is available
to users from outside the EEA) further compliance steps needs to
be put in place. This issue becomes relevant if, for example, an 4 Application of the law:
architect is running a multi-jurisdictional project or has decided common scenarios
to outsource its HR or IT functions to a service provider that is
based outside the EEA. Where an architect has offices outside Employees
the EEA and centralises its CRM or employee databases outside
the EEA, employment records of UK employees might also be 4.01 As indicated earlier, the most likely scenario in which an
sent to the central hub that exists outside the EEA. architect’s business will be involved with the processing of
372 Data protection

personal data is information relating to its employees (includ- ● all employees handling personal data are trained in how to
ing contract staff, in respect of whom similar records are likely do so;
to be kept). ● all employees have a data protection provision in their con-
tract of employment which addresses both the personal data
4.02 The areas where data protection is likely to affect employ- about the employee (that the architect will hold) and the
ees include the following: requirement for an employee to comply with data protec-
tion law in carrying out his or her duties. Often, the detail
(1) Hiring process and notices: it will be necessary during in how personal data of employees is handled is set out in
the hiring process to provide a notice to the individual to an employee handbook (so that there is not too much detail
explain how information will be processed by the architect in the employment contract);
during the process. Once hired, the new employee will ● the architect’s business provides guidance to employees on
need to be given an employee privacy notice covering the how to comply with data protection law. Beyond training,
processing of information relating to him or her during the this is likely to require a process/procedure on how to han-
employment relationship. It may be possible or sensible to dle personal data, how to keep it confidential when working
combine these two notices (to cover both the hiring process away from the office, and what to do if personal data is lost,
and the employment relationship). Existing employees of for example, on a laptop or device.
the business also need to see a privacy notice, and therefore,
any existing notices should be updated to comply with the
GDPR.
Clients
(2) Disciplinary action and individual rights: information 4.04 An architect is likely to have individual clients as well as
will be collected on employees during the course of their corporate clients. In this section, we are looking into the appli-
employment. It will be important to ensure that this infor- cation of data protection to individual clients. The main issues
mation is accurate and is held securely. For example, if affecting client information will be as follows:
there are complaints against employees, that information
will need to be kept in a restricted manner so that only (1) Notices: it will be necessary for architects to have shown
those individuals who need to know it have access to it. they have produced a privacy notice for clients to explain
This is part of the obligation of data minimisation. It should how their information is kept. This could be included as
also be remembered that individuals have a right to access part of the terms and conditions in the engagement letter
information about them. Therefore, it would be possible for with clients and/or set out on to the architect’s website.
an employee to make a subject access request asking for (2) Individual Rights: as with employees, clients could poten-
information held on their records. At this point, an architect tially make requests to use their rights under data protection
would need to review the records and see whether all of the law. This might, for example, include a request for access to
information is disclosable. There could be some situations their information or a request for portability, as mentioned
where exemptions apply (see above). above.
(3) Monitoring: it is likely that any business will have some (3) Breaches: if an architect suffers a security breach and loses
form of monitoring of staff and/or visitors. For example, information about its clients, it may be required to notify
CCTV may be used to protect the physical office and the the ICO and/or notify the affected clients.
business would need to follow the ICO’s guidance (avail-
able on its website) on compliance with data protection 4.05 Where an architect decides to carry out marketing to its
laws when using CCTV. There should be a physical notice clients, it will also need to consider the PECR. Marketing
available in the building to ensure that individuals are aware that is carried out by email to individual clients requires their
that CCTV is in place. There is also likely to be a form specific consent to receive the marketing material. This could
of monitoring on the architect’s email and communication be obtained as part of the client’s sign up process, e.g. in the
system. This will require an IT monitoring policy to explain engagement letter/terms of business.
to employees that there will be either human or automated
monitoring of the use of IT systems. 4.06 Marketing emails must be clear as to the sender and include
(4) Outsourcing: a business is likely to outsource the hosting an ‘opt out’ link. It is also possible in some situations to use the
of its data with a service provider. This is the appointment so called ‘soft opt in’. This covers a situation where a business
of a processor, and therefore, due diligence will need to be has existing client relationships and wishes to continue to market
carried out on the processor and an appropriate contract similar products or services to existing clients (who have bought
will need to be put in place. Similarly, it is quite possible services from that business before). In this case, the business can
that an architect's business may outsource management of market, provided it makes available an opt out when it collects
its HR data or HR functions. Again, there would need to the data and in marketing emails.
be due diligence on the service provider and an appropriate
contract put in place. 4.07 It will be necessary for the architect to keep a list of those
(5) Disclosure to third parties: in some situations, businesses clients who have consented to receiving marketing and to also
are asked to disclose information on their employees to keep a list of those clients who have decided to opt out of receiv-
third parties, such as the police or insurers. There should ing further marketing.
be a process in place to ensure that this information is not
routinely disclosed. It is quite possible that the request for
employee data from, say, the police or courts will be legally
Business contacts
justified, but there should be some investigation to ensure 4.08 The final category of individuals concerns business con-
that the requester is genuinely employed by the police or tacts. By this we mean individuals who work at a corporate
courts and also that the information being requested is the business. These could be individuals who are directors, relevant
minimum amount required. contacts at builders’ firms, or other professionals with whom the
architect interacts. It could also include individuals who are the
4.03 Also relevant with respect to employees is the way in which contact points at corporate clients of the architect.
the architect’s business needs to train and manage the handling
of personal data by employees. This is relevant as the employees 4.09 Here, the most likely implication is the need to ensure that
will be handling data about other employees, clients, and busi- the collection of this information is addressed in notices and in
ness contacts, and they need to do so in a compliant fashion. any engagement letters. Additionally, if there are any breaches,
Therefore it is important that: they could also affect these contacts. Lastly, if there are disputes
Application of the law: common scenarios 373

with such contacts, they could also make access requests or notice will be required if the website itself is capable of
attempt to use their rights under the GDPR. collecting personal data, e.g., if there is functionality for
clients to request marketing materials or book into events,
4.10 Marketing to business contacts is slightly less onerous or for candidates to apply for new positions.
than to individual clients. It is therefore possible to market (2) Cookie notice/policy: most websites will use cookies, small
to individuals at corporate businesses, provided some notice files that are placed on user devices to allow the website
has been given (e.g. in the engagement letter), an opt out is to work seamlessly, or perhaps to collect analytics on the
provided in the email, and that the individual has not spe- visitors to the website, or to provide marketing from third
cifically stated that he/she does not wish to receive marketing parties. If the website uses cookies, then a cookie notice
materials. will be required, and depending on the type of cookies being
used, it may be necessary to have positive consent from
visitors (e.g. through a banner or pop-up).
Website (3) Contract with website host/developer: as mentioned above,
4.11 Most businesses will have a website, and this is very likely if a service provider is holding personal information on
to need to comply with data protection laws. In general, the behalf of an architect’s business, then a specific contract
actions required will be: must be put in place with the processor (the website host/
developer). This will depend on what the website holds in
(1) Website privacy notice/policy: it will usually be convenient terms of personal data, but is very likely to be relevant, as
for the architect’s business to display a copy of its privacy the site will include details of the individual architects in
notice on the website. In addition, the display of such a the business.
38
Architects’ registration
SARAH LUPTON

1 The nature of professionalism a register of architects, but in merely protecting the use of title
‘architect’, it did not prevent others from carrying on the practice
in architecture of architecture in the way that the sponsors hoped. This remains
the position in the United Kingdom; it is an offence for anyone
1.01 The concept of a professional person and an institutional other than those on the register to use the title ‘architect’, but
profession has been continually evolving since the eighteenth anyone may design buildings, carry out project administration,
century. Numerous studies of the subject have been made; and undertake all the tasks usually done by architects. The
one of the most concise appeared in 1970 as the report of the Architects (Registration) Act 1931 and the amending Acts of
Monopolies Commission (Part 1: The Report, A report on the 1938 and 1969 provided for the setting up, maintenance, and
general effect on the public interest of certain restrictive prac- annual publication of a Register of Architects; the maintenance
tices so far as they prevail in relation to the supply of profes- of proper standards of professional conduct; and the provision
sional services [Cmnd 4463]. Part 2: The Appendices [Cmnd of limited financial assistance for some students. The registra-
4463–1]). Appendix 5 of the Report provides a range of defini- tion body was funded by the annual registration fee of those on
tions and descriptions which vary considerably, but there is a the register.
general acceptance that a professional person is one who offers
competence and integrity of service based upon a skilled intel- 2.02 In the 1980s, many of the professions found themselves
lectual technique and an agreed code of conduct. under criticism; there was an increasing concern for consumer
rights; and the role of the professional bodies as the protec-
1.02 The early history and development of the architectural tors of the public interest was questioned. In the case of the
profession in Britain are analysed in Barrington Kaye, The architectural profession, the whole basis of its statutory posi-
Development of the Architectural Profession in Britain. In a tion under the Architects (Registration) Acts 1931 onwards was
parallel study, Architect and Patron, Frank Jenkins, analysed questioned; other professions in the construction industry asked
the development of professional relations between architects and why architects alone enjoyed protection of title, and architects
their clients prior to the beginning of the 1960s. themselves questioned the value of protection of title when
the function and activity were open to anyone wishing to offer
1.03 The place of professionalism and the role of the profes- their services. The Royal Institute of British Architects and
sional person in a rapidly changing society has been questioned other bodies also questioned the role and need for a statutory
frequently, not only by society in general, but also by the mem- registration body. The RIBA Council, originally in favour of
bers of the professions. The concerns of society are reflected the dissolution of the Registration Council and the transfer of
in the Government’s questioning of the role of the Architects its powers to the RIBA, reversed its policy and campaigned for
Registration Council of the United Kingdom in the late 1980s its retention. The Government undertook an extensive consulta-
and subsequent legislation, leading to the establishment of the tive exercise.
Architect’s Registration Board with its lay majority. There
is a trend towards increased regulation of many professions, 2.03 In parallel with these discussions, Sir Michael Latham was
but architects are the only profession within the construction conducting a Government-sponsored review of procurement
industry that have a protected title and are subject to statu- and contractual arrangements in the construction industry, and
tory regulation. The concerns of the architectural profession in July 1994, his final report, Constructing the Team, appeared.
are reflected in the radical changes in its codes, the periodic Its executive summary covered a wide range of radical recom-
reviews that it undertakes, and the ongoing debate on the status mendations, some of which were to receive official support,
and role of the profession, as can be seen in the architectural although not as many as Latham had hoped. As there was
press. little opportunity in the crowded parliamentary programme to
introduce a Construction Bill, the Government took advantage
of a largely non-contentious Bill on housing grants to adopt its
2 Architects' registration preferred recommendations from the Latham Report, as Part II
of the Housing Grants, Construction and Regeneration Act 1996.
2.01 In 1899, the first Architects’ Registration Bill attempted to Also, having made its decision on registration following the
restrict the practice of architecture to those who were formally receipt of the Warne Report on the future of registration it added
qualified; it was rejected, as were several others that followed. a Part III to the same Act. Subsequently, Part III of the Housing
In 1931, the Architects (Registration) Act did not achieve the Grants, Construction and Regeneration Act 1996 was repealed
full intentions of its sponsors. It provided for the setting up of in the Architects Act 1997.

375
376 Architects’ registration

2.04 The Architects Act 1997 also repealed the Architects 12 months working in the EEA, Channel Islands or the Isle
(Registration) Act 1931, the Architects Registration Act 1938, of Man, under the direct supervision of an architect.
the Architects’ Qualifications (EEC Recognition) Order 1987,
and the Architects’ Qualifications (EC Recognition) Order 1988. These requirements have been agreed with the RIBA, which
The provisions of the Act are significantly different in principle has similar requirements for membership. They can be varied
and detail from those of the 1931 and 1938 legislation. The large, by the Board, acting within guidelines published by the Board
former Architects Registration Council, which consisted almost from time to time.
exclusively of architects, was replaced by a small Architects
Registration Board (ARB). The current format was introduced 3.02 Under the Architects Act 1997, the ARB has the statutory
in 2018 through the Architects Act 1997 (Amendments etc.) responsibility for prescribing those qualifications which lead to
Order 2018, when the board was reconstituted following a entry onto the UK Register of Architects.
periodic review by the DCLG. It replaced the earlier version The current Prescription Procedures are those approved in
of seven members elected by persons on the register and eight 2010, and which came into effect in 2012. Schools of architec-
persons appointed by the Privy Council in consultation with ture, and other institutions that award architectural qualifications,
the Secretary of State. It should be noted the 1997 Act may be must apply for and obtain the decision of the ARB as to whether
revised in the near future, as the Government has recently pro- any qualification it proposes to offers will be recognised as a
posed amendments under the Building Safety Bill. prescribed qualification, and once prescribed, they are subject
to periodic review. The ARB may also revoke prescription of
2.05 The ARB now consists of 11 Board members, all appointed a qualification. At the time of writing, the ARB is undertaking
by the Privy Council, and comprises one independent, non-exec- a consultation on proposals to review its governance structure
utive Chair and ten non-executive Board members made up of in relation to the prescription of qualifications. The Board has
five members of the public and five architects, serving a term of also agreed to undertake a significant review of its approach to
up to four years. As the Act specifically makes registered persons prescribing qualifications and practical experience in 2020.
ineligible from being appointed as Chair, there must always be
a lay majority on the Board. 3.03 In addition to the ARB prescription of qualifications, the
RIBA operates a validation procedure. This is a peer review
The ARB’s duties are contained in the Architects Act 1997, and process that ‘monitors schools of architecture’s compliance with
cover six main areas: internationally recognised minimum standards in architectural
education and encourages excellence and diversity in student
● Maintaining the UK Register of Architects (s. 3); achievement’. Visiting Boards, composed of experienced prac-
● Prescribing the qualifications needed to become an architect tising architects, academics, and lay persons, visit schools of
(s. 4); architecture to assess the standard of courses for exemption
● Ensuring that architects meet the ARB standards for conduct from the RIBA’s Examinations in Architecture. Although these
and practice, including issuing a Code (s. 13); visits had, in the past, been run jointly with the ARB, under
● Investigating complaints about an architect’s conduct or the current Prescription Procedures, the ARB need no longer
competence (s.14); participate in visits to Schools of Architecture. Nevertheless the
● Making sure that only people on the ARB Register offer two institutions continue to work closely in the development
their services as an architect (s. 20); and and monitoring of criteria for assessment and validation of
● Acting as the UK’s Competent Authority for architects (s. courses. For example, the criteria used by the ARB to prescribe
1A). qualifications and the RIBA to validate qualifications are jointly
held. The ARB is currently reviewing the current Criteria. The
2.06 In addition to the Board, the Architects Act 1997 makes RIBA has recently published a new Education and Professional
provision for a Statutory Professional Conduct Committee that Development Framework but confirmed that it will continue to
is responsible for disciplinary matters. It is constituted in its own share the ARB education criteria for prescription of architecture
right under Schedule 1, Part II of the Architects Act to consider courses.
allegations of unacceptable professional conduct and serious
professional incompetence against architects. The make-up of 3.04 The Recognition of Professional Qualifications Directive
the Professional Conduct Committee comprises: (2005/36/EC), which covers the architectural profession,
requires that
● At least three persons who are legally qualified;
● At least three persons registered in Part 1 of the Register (i.e. a Member State which makes access to or pursuit of a regu-
architects), of whom at least one must be a person whose lated profession in its territory contingent upon possession
address in the Register is in Scotland; and of specific professional qualifications (referred to hereinaf-
● At least three persons who are not legally qualified and are ter as the host Member State) shall recognise professional
not registered in Part 1 of the Register.

3 Eligibility for registration


3.01 Persons are eligible for registration if they hold such
qualifications and have gained such experience as the ARB
may prescribe, or if they have an equivalent standard of
competence (Architects Act 1997 s4(1)). For UK registra-
tion, this normally means that they must pass prescribed
Parts 1, 2, and 3 qualifications (a list of all the Part 1, Part 2,
and Part 3 qualifications is available on the ARB website).
The prescribed experience is set out under rule 13(b) of
ARB’s General Rules, which state that the applicant must
have

recently completed a minimum of 24 months’ practical experi-


ence under the direct supervision of a professional working
in the construction industry which should include at least
Eligibility for registration 377

qualifications obtained in one or more other Member States professional work in the UK would be prudent to check their
… and which allow the holder of the said qualifications to position with regard to registration before embarking on a
pursue the same profession there, for access to and pursuit course. ARB has set out on its website guidance on what it
of that professional. anticipates will be the likely position following Brexit, in a range
(Article 1) of different scenarios.

The requirements of this Directive (which supersedes the 3.06 An application fee and an annual retention fee are payable
Architects Directive (85/384/EEC) were implemented through for registration, these being set annually by the Board.
the European Communities (Recognition of Professional
Qualifications) Regulations 2007, and the Architects (Recognition 3.07 It is an offence to become registered or attempt to become
of European Qualifications) Regulations 2008. registered by making false or fraudulent representations or
Under the current system, an EU applicant who is eligible declarations, the penalty for which is a fine not exceeding level
to practise, or is lawfully established, as an architect in their 3 on the standard scale (Act s7(2)). It is also an offence for an
home state, and who holds a qualification which is specifically unregistered person to practise or carry on a business under a
listed in the Directive, and is a national of an EEA country, (or title containing the word ‘architect’, the penalty for which is a
a ‘Directive Rights National’, i.e. someone with an enforce- fine not exceeding level 4 on the standard scale s21(1).
able Community right), would usually be eligible to register
on ‘Part 1’ of the Register. ‘Part 2’ of the Register is reserved 3.08 A person’s name may be removed from the register if the
for visiting EEA architects who may provide temporary or Professional Conduct Committee makes an erasure or suspen-
occasional services only in the UK. EU applicants who do not sion order, or if that person fails to pay the annual retention fee.
meet all the requirements for automatic recognition should con-
tact the ARB regarding their eligibility. 3.09 Disciplinary Orders may be made by the Professional Conduct
Committee in the event of a registered person being found guilty of
3.05 In the case of overseas applicants for registration other than unacceptable professional conduct, or serious professional incom-
EEA nationals, the Board requires them to sit the ARB’s pre- petence, or a criminal offence relevant to the fitness of the person
scribed examination, which provides recognition that candidates to practise as an architect. Unacceptable professional conduct and
have achieved a standard of attainment that the Board views as serious professional incompetence are assessed taking into account
comparable to prescribed qualifications at Parts 1 and 2 levels. the Architects Code: Standards of Professional Conduct and
Overseas persons wishing to undertake further academic and Practice and the context of the particular circumstances of the case.
39
Professional conduct of architects
SARAH LUPTON AND PETER ANDERSON

1 Codes of professional conduct public and relations between architects and their clients. The
codes of the institutions are not incompatible with the Architects
1.01 An agreed and enforceable code of professional conduct is Code and reflect many of the same concerns.
an essential part of any recognised profession. It is the profes-
sion’s demonstration of its commitment to the service it offers 1.05 Failure to comply with the ARB code could result in the
and the standards that it upholds. Codes are devised in the removal of the person’s name from the register, terminating the
interests of the clients of the profession, and less directly in the person’s right to practise under the title ‘architect’ and possibly
interests of its members, through the maintenance of the status leading to the loss of livelihood. Failure to comply with the
of the profession in the eyes of society. The integrity of purpose requirements of the code of a particular institution may lead
of the codes and the impartiality of their enforcement is crucial to the suspension or loss of membership, but provided that
to the public’s perception of the profession. The requirements of the person is not in breach of the Architects Code, the right
codes change and evolve in response to changing circumstances to practise under the title ‘architect’ remains, and the business
and attitudes and emerging economic, political, and social pres- may continue. There are ‘unattached’ architects who are eligible
sures. They have to reflect the attitudes of the membership of the for institutional membership, but do not take up membership,
profession and the consequences of legislation and litigation but, and there are a few properly qualified individuals who do not
above all, the explicit and implicit expectations of an increas- apply for registration. The extent to which a person feels that
ingly sophisticated clientele. it is necessary to take up and retain the right to the title or to
continue institutional membership has to be a matter for the
1.02 Architects in the United Kingdom are subject to ‘The commercial and professional judgement of the individual. There
Architects Code: Standards of Professional Conduct and are no statutory requirements for the employment of architects in
Practice’ issued by the Architects Registration Board (ARB). the marketplace, and clients may use whomsoever they wish to
In addition, those architects who choose to join other profes- prepare designs, or inspect building works. Should clients pursue
sional bodies, such as the Royal Institute of British Architects such action, neither the ARB nor the professional institutions
(RIBA) or the Royal Incorporation of Architects in Scotland have any power to address matters of complaint.
(RIAS), become subject to their codes. Until 1998 and the
advent of the ARB, the codes of the Architects Registration 1.06 Where allegations of improper conduct also concern matters
Council (ARC) and the codes of the institutions covered simi- covered by the ARB Code, the institutions usually delay disci-
lar ground, and while in general terms this is still the case, plinary proceedings until the ARB’s findings are known in order
there are some differences between the ARB and RIBA Codes. to avoid unnecessary expense and inconvenience for the parties.
From 2003, the RIAS Code has been in full alignment with Where an allegation of a breach of one of the codes relates to
that of the ARB. court proceedings, it is usual for all disciplinary proceedings
to be delayed until after the court’s decision, but it should be
1.03 The codes have both positive and negative aspects; there noted that disciplinary proceedings are not conditional on the
are essential actions that are specifically required and there court’s decision.
are also actions which are specifically prohibited. The codes
must not be regarded as a mere technical formality; they have
a direct effect on practice and the ways in which an architect 2 ARB code of conduct
works. A lack of knowledge of the detailed requirements of the
codes is not acceptable as a defence in the case of an alleged 2.01 Section 13 of the Architects Act 1997 requires the ARB
misdemeanour or breach of the codes; in some circumstances, to issue a code laying down the standards of professional con-
it could even be held to compound the offence. Lay clients are duct and practice expected of persons registered as architects
not expected to be familiar with the requirements of the codes, under the Act. The full title of the ARB code of conduct is The
but architects are required to inform their clients that they are Architects Code: Standards of Professional Conduct and Practice
registered with the Architects Registration Board and that they (the Architects Code). It can be viewed and downloaded from the
are subject to its Code (Code 4.4). It is essential that architects ARB web site at www.arb.org.uk and is published in hard copy.
have available copies of all the current relevant codes of conduct The most recent version was published in 2017.
for immediate reference. The Architects Code comprises twelve Standards with which
architects are expected to comply, each with between one and
1.04 The code published by ARB (the Architects Code) is six sub-sections, an introduction, and three pages of general
primarily concerned with the protection of the interests of the guidance. All parts of the Code are inter-related and have to

379
380 Professional conduct of architects

be read together. In addition to the Architects Code, the Board consideration of an architect’s conduct under any of the other
also publishes General Rules, and the Professional Conduct standards (1.1).
Committees publishes Investigations Rules and Professional Architects are prohibited from making a statement which is
Conduct Committee Rules. contrary to their professional opinion or which they know to be
A breach of the Architects Code can result in the ARB misleading, or unfair to others, or otherwise discreditable to the
Professional Conduct Committee issuing a disciplinary order profession (1.2).
reprimanding the architect; or fining the architect; or suspend- Architects are required to disclose, in writing, to a prospective
ing the architect’s registration for a period of up to two years; client or employer any financial or personal business interest
or erasing the architect’s name from the register (Architects Act which would or could raise a conflict of interest and doubts
1997 s15). about their integrity, if not so declared. Where the situation
cannot be satisfactorily resolved and the parties concerned have
The Code begins by setting out the standards as follows: not given their informed consent, architects are required to with-
draw from the situation (1.3). Developing complexity in funding
‘As an architect you are expected to: arrangements, joint venture initiatives, partnering, and non-
1. Be honest and act with integrity traditional procurement procedures increases the possibilities
2. Be competent of conflicts of interest arising, especially where circumstances
3. Promote your services honestly and responsibly change during the project.
4. Manage your business competently Where an architect has received any inducement for the intro-
5. Consider the wider impact of your work duction or referral of work, this should be disclosed to the client
6. Carry out your work faithfully and conscientiously or prospective client at the outset (1.4).
7. Be trustworthy and to look after your clients’ money
properly
8. Have appropriate insurance arrangements Standard 2: competence
9. Maintain the reputation of architects 2.05 Architects are expected to be competent to carry out any
10. Deal with disputes or complaints appropriately professional work that they undertake (2.1). It is fundamentally
11. C o - o p e r a t e w i t h r e g u l a t o r y r e q u i r e m e n t s a n d important that architects have regard to this standard, and do
investigations not take on commissions, however attractive, that they do not
12. Have respect for others’ have the expertise to deliver. Where work is done by others
working under the direction of the architect, the architect is
responsible for ensuring that they have the necessary compe-
The Introduction tence to carry out the work and are properly supervised (2.1).
Architects should have arrangements in place for the conduct
2.02 The overriding obligation of the Architects Code is that the of their business in the event of their death, incapacity, absence
architect is expected to act competently and with integrity in from, or inability to work (2.2). This is clearly of particular
carrying out professional work. The Introduction comments that relevance for sole practitioners, but even in larger practices,
the fact that a course of conduct is not specifically referred to architects must arrange for the smooth handover of projects
in the Code does not mean that it cannot form the basis of dis- in their absence.
ciplinary proceedings: architects are expected to have regard to Architects are expected to ensure that the necessary commu-
the spirit of the Code as much as its express terms. Conversely, nication skills and local knowledge are available to them (2.3).
it comments that not every shortcoming on the part of an archi- This would be particularly relevant to UK registered architects
tect will necessarily give rise to disciplinary proceedings (minor who are undertaking work outside the UK (as the Code still
transgressions of the Code are not likely to prompt action unless applies to them) and to those registered architects who qualified
they form part of a pattern of unacceptable professional conduct outside the UK.
or serious professional incompetence). Architects are required to keep their knowledge and skills
Disciplinary orders may be made if an architect is convicted in areas relevant to their professional work up-to-date. This
of a criminal offence that is relevant to the person’s fitness to Standard reflects the policy of most professions which now
practise as an architect. In addition, a disciplinary order may require their members to undertake continuing professional
be made against an architect if, after considering the case, the development work. Failure to maintain professional competence
Professional Conduct Committee is satisfied the architect is could count against an architect in the event of that competence
guilty of unacceptable professional conduct and/or serious pro- having to be investigated (2.4).
fessional incompetence.

The Standards Standard 3: honest promotion


2.03 The twelve Standards have to be read in conjunction
of your services
with the Introduction and the General Guidance. Most of the 2.06 Architects are expected to promote their professional ser-
Standards concern self-evident aspects of sound business and vices in a truthful and responsible manner (3.1). This allows
good practice, but some are less obvious, but equally important; architects to advertise their services, provided that it is not
practising architects must be aware of all twelve Standards and done in a manner that is untruthful or misleading and complies
must understand their full implications. with the codes applying to advertising, including those of the
The importance of the Standards must not be under-estimated; Advertising Standards Authority (3.2).
the consequences of an architect’s failure to understand or apply The business style of the practice must not be misleading
the principles of the Standards can be serious. In the following (3.3). Difficulties can arise when partnerships are dissolved,
commentary, the numbers in parentheses refer to the sub-clauses businesses are restructured, and where former partners or staff
of the Standards. setting up new practices wish to take credit for their previous
work. Ideally, these matters should be covered in termination
agreements, but where this has not happened, care must be taken
Standard 1: honesty and integrity to ensure that any statements made are factually correct and
2.04 In its stringent requirements, Standard 1 of the Code capable of objective justification (3.1).
embodies many of the traditional principles of professional Principals in a practice are expected to ensure that all
codes of conduct, especially in context of relationships between architectural work is under the control and management of
architects and their clients and other affected parties. It is stated one or more architects, and that their names are made known
to underpin the Code, and will be taken to be required in any to clients and any relevant third party (3.4). Clients must be
ARB code of conduct 381

notified promptly of any change in the architect responsible clause 5.1 now states ‘Where appropriate, you should advise
for the work (3.5). your client how best to conserve and enhance the quality of
the environment and its natural resources’. This places a posi-
tive duty on the architect to guide the client with respect to the
Standard 4: competent project, as well as to consider the impact of the activities of its
management of your business practice generally.
2.07 Architects are expected to have effective systems in place to
ensure that their practices are run professionally and that projects Standard 6: you should carry out
are regularly monitored and reviewed (4.1). This would include your professional work faithfully
ensuring that appropriate and effective internal procedures are
in place. Architects should also ensure that they are able to
and conscientiously and with
provide adequate professional, financial, and technical resources due regard to relevant technical
when entering into a contract and throughout its duration, and and professional standards
that there are sufficient suitably qualified and supervised staff
to enable the delivery of an effective and efficient client service 2.09 The overriding concern of practising architects must be
(4.2). Although no prudent architect would knowingly take on to ensure that work is carried out with due skill, care, and dili-
work without the necessary competence and resources being gence, and without undue delay, and so far as it is practicable,
available, difficulties can arise in at least three ways. First, the within the time scale and cost limits agreed with the client (6.1
nature of the work may not be fully apparent at the start of the and 6.2). The requirement reflects the standard applied by the
project; second, the needs of the project and the nature of the courts in their consideration of allegations of professional neg-
work may vary during the project; and third, the circumstances ligence. Architects are expected to keep the client informed of
of the architect’s practice may change drastically during the the progress of work undertaken on their behalf and of any issue
work. It is important that the situation is continually monitored which may significantly affect its quality or cost (6.3). Another
and essential that the client is immediately advised of anything key source of disputes and complaints to the ARB is the fact that
that might prevent the architect from fulfilling the obligations the client felt that they were not fully updated on progress, and
under the Standard. architects should always ensure that adequate reporting systems
Architects are required to ensure that adequate security is in are in place.
place to safeguard records for their clients (including electronic Architects, when acting between parties or giving advice,
records), taking full account of data protection legislation, and are required to exercise impartial and independent professional
that clients’ confidential information is safeguarded (4.3). The judgment to the best of their ability and understanding (6.4).
safeguarding of confidential electronic information may, in some
cases, require secure back-up storage. Standard 7: trustworthiness and
Architects are prohibited from undertaking professional work safeguarding clients’ money
unless the terms of the contract have been recorded in writing.
The standard requires that terms should specify: the identity 2.10 Generally, architects should avoid situations in which they
of the parties, the scope of the work, the fee or method of are required to hold monies belonging to the client, but where it
calculating it, the allocation, and any limitation of responsibili- is necessary to do so, the requirements of the Standard should
ties. In addition, it requires that they set out the provisions for be followed in every detail, and before doing so, an architect
suspension or termination of the appointment, including any invited to manage the client’s monies would be wise to take
legal rights of cancellation (consumer clients will have rights impartial advice.
under consumer protection legislation), a statement that they A careful record of all transactions must be kept with the mon-
have adequate and appropriate insurance cover as specified by ies being held in an interest-bearing account separate from any
ARB, the existence of any special alternative dispute resolution account held by the practice or the architect concerned (7.1, 7.2).
schemes that the contract is subject to and how they might be The designated ‘client account’ must be protected with the
accessed, that they have a complaints handling procedure avail- bank being instructed in writing that the account may not be
able on request, and that they are registered with the ARB and combined with other accounts or set-off against other claims
are subject to its Code (4.4). (7.3).
Apart from being requirements of the Code, these procedures Withdrawals may only be made from a client account on the
represent good practice and are obviously in the best interests of client’s instructions or on behalf of the client (7.4).
both the client and the architect. A large proportion of disputes Unless otherwise agreed, any interest earned has to be paid
and complaints to the ARB arise from inadequate, informal, or to the client (7.5).
non-existent terms of appointment, leaving the client uncertain
as to the service they can expect from their architect. Any agreed
variations to the written agreement should be recorded in writ- Standard 8: insurance arrangements
ing (4.5). 2.11 An architect is expected to have ‘adequate and appropri-
At the end of the contract, the architect is required to return to ate’ insurance cover. The insurance policy must cover work
the client on request all the papers, plans, and other property to undertaken by employees (8.1). The cover should be adequate
which the client is legally entitled (4.6). Normally, this material to meet a claim, and architects are required to maintain a
includes all the drawings and other documents used in the works, minimum level, including run-off cover, in accordance with
but not the material used by the architect in the development of ARB’s guidance.
the design. It may be pertinent to note that although the client is The Standard draws attention to the need for insurance to
entitled to the drawings and other documents, on the final pay- cover work outside the architect’s main professional practice
ment of fees and charges, the copyright in the design remains (8.2). It is important that practitioners obtain confirmation from
with the architect, unless otherwise specifically agreed. their insurers that any extensions in the services provided are
covered by their insurance policies.
Standard 5: considering the The requirement that employed architects should ensure that
professional indemnity insurance cover or other appropriate
wider impact of your work cover is provided by their employer could pose problems in
2.08 The possible implications of this Standard are extremely practice, but the Code takes a practical view, and the requirement
wide-ranging. The 2009 Code only referred to the need to take is qualified by the phrase ‘so far as possible’ (8.3). There is no
into account the environmental impact of professional activities mention of the possible consequences of an employer’s default
(5.1). However, under the 2017 Code this had been revised, and on insurance cover.
382 Professional conduct of architects

If required, architects must provide evidence to demonstrate the Board of a change of address may be removed from the
compliance with this Standard (8.4). Register (11.2).

Standard 9: maintaining the Standard 12: respect for others


reputation of architects 2.15 This standard (which was introduced with the 2010 code)
requires architects to treat everyone fairly and in line with the
2.12 Architects should ensure that their professional finances are
law, and not to discriminate because of disability, age, gen-
managed responsibly (9.1), and are expected to conduct them-
der, sexual orientation, ethnicity, or any other inappropriate
selves in a way which does not bring either themselves or the
consideration.
profession into disrepute (9.2). An architect is required to report
to the Registrar within 28 days if they are convicted of a crimi-
nal offence; are made the subject of an order of disqualification
from acting as a company director; are made the subject of a 3 RIBA Code of Professional
bankruptcy order; are director of a company which is wound up, Conduct.
make an accommodation with creditors, or fail to pay a judge-
ment debt (9.2). It should be noted that not all such instances 3.01 The latest version of the RIBA Code of Professional
would result in any action being taken by the ARB or the PCC, Conduct (the RIBA Code) came into effect on 1 May 2019.
as in times of recession, even with prudent management, a firm This replaced the previous version that had been published
may nevertheless get into financial difficulties. The standard is in April 2005, which in turn had replaced the 1997 version.
aimed primarily at irresponsible and wilful conduct. It applies to all RIBA members ‘whether they are working in
Architects are also required to inform the Board of any seri- traditional architectural practice or have followed a different
ous breach of the Code by another architect which may come to career path, such as in a multidisciplinary organisation, aca-
their notice (9.3). The Standard’s requirement that an architect demia or a construction company’. It was published along with
must draw attention to the apparent misconduct of fellow practi- the RIBA Code of Practice, which applies to all practices reg-
tioners provoked some critical comments when it first appeared, istered with the RIBA Chartered Practice Scheme (Chartered
but is a common feature of the codes of professionals generally, Practices), and to all staff in such practices (whether or not
and has been retained in this version. The standard is qualified RIBA members). The provisions of both Codes are essentially
by the phrase ‘in appropriate circumstances’, and architects are the same.
required to consult with the Board if in any doubt.
The Standard accepts that an architect appointed as an arbi- 3.02 Tracking the development of the RIBA Code over the
trator, adjudicator, mediator, conciliator, or expert witness and years reveals shifting approaches to the role of the profes-
in receipt of privileged information may have duties which take sional and the RIBA’s position with regard to the conduct of its
precedence over any requirements to report breaches of the Code members. The 1981 Code was of particular significance, in that
to the Board (9.4). the changes reversed much of the Institute’s long-established
Apart from such situations or those concerned with the set- stance on professionalism. They removed the restrictions on
tlement of a dispute, an architect may not enter into an agree- carrying on the business of trading in land or buildings, or as
ment which would prevent any party from reporting an apparent property developers, auctioneers, estate agents or contractors,
breach of the Code to the Board (9.5). subcontractors, manufacturers, or suppliers in or to the con-
struction industry; permitted members to negotiate fees with
Standard 10: deal with disputes potential clients and abandoned the mandatory minimum fee
system; and removed the ban on practising in the form of a
or complaints appropriately limited liability company and extended the permitted means
2.13 The requirements of the Standard are rigorous; they lay by which an architect might bring himself to the notice of
down strict time limits for dealing with complaints. The provi- potential clients.
sions of the Standard represent good practice and reflect those The 1997 version introduced the Standard of Professional
already included in a number of Quality Assurance Schemes. Performance as part of its Code of Professional Conduct,
Architects are expected to have a written procedure for whereby the RIBA predated the use of standards in the Code
prompt and courteous handling of complaints and provide this of Conduct published by the Architects Registration Board in
to clients. This should include the name of the architect who August 1997. Both Codes took into account the requirements of
will respond to complaints (10.1). As far as practicable, the the Architects Act 1997.
client should be sent an acknowledgement of the complaint In July 2003, RIBA Council agreed to a complete redrafting
within ten days, and the complaint should be dealt with within of its Code of Professional Conduct. The Code review coin-
thirty days of the receipt of the complaint (10.2). At every cided with a notification from the Office of Fair Trading that
stage, complaints have to be handled promptly, courteously, it considered undertakings 3.1 and 3.3 of the RIBA Code of
and sympathetically. Professional Conduct to be contrary to the Competitions Act
Wherever it is thought to be appropriate, the Standard encour- 1998, following which, the RIBA Council agreed that the two
ages the use of alternative dispute resolution procedures such as undertakings should be suspended, and a new version was pub-
mediation or conciliation (10.3). lished in January 2005.
The 2005 Code was much shorter than the previous Code,
used of the separate Guidance Notes means that were updated in
Standard 11: co-operation with regulatory the light of changing circumstances. On publication, the website
explained:
requirements and investigations
2.14 Architects are expected to co-operate fully and promptly the focus of the 2005 code is the consumer, and society at
with the Board, within any specified timescale, if asked to pro- large. It is more outward-looking than its predecessor and
vide information that it needs to carry out its statutory duties, states the standards of professional ethics and behaviour
including evidence of compliance with the Standards. This expected of chartered architects in the early twenty-first cen-
requirement is broadly expressed and would cover such matters tury more clearly and concisely.
as evidence of compliance with insurance or CPD requirements
set by the Board (11.1). Architects are required to notify the 3.03 The 2019 RIBA Code of Professional Conduct is a sub-
Board promptly and in writing of any changes in their details stantial development from the previous version. The three
held on the Register. Under the Act, architects who do not tell underlying principles remain the same, but the ‘values’ that
RIBA Code of Professional Conduct. 383

underpinned the principles have been omitted. The rules statements which they know to be ‘untrue, misleading, unfair
have increased in number, and instead of guidance notes to others, or contrary to their own professional knowledge’ and
being published separately, these are now embedded within clarified the obligation by explaining that ‘be party to’ means
the Code itself. The RIBA Code has much in common with not only making such a statement, but also ‘acquiescing to its
the ARB Code of Conduct, although there are some differ- being made by others’. This guidance would still apply to the
ences. In particular, the RIBA Code’s provisions covering the 2019 Code.
behaviour of members to each other has no equivalent in the
ARB Code. The new, detailed provisions regarding health and
safety, inspection services, building performance, heritage and
3. Conficts of interest
conservation, town and country planning, law and regulations, The 2019 Code does not (as did the 2005 only) state that
certification, and the environment, have no equivalent in the ‘Members should avoid conflicts of interest’. Instead, it
ARB Code (save for general requirements that would cover requires a more proactive role, i.e. that Members must have
such aspects). effective systems in place to identify and assess potential
conflicts of interests. As before, it requires members to
3.04 The 2019 RIBA Code of Professional Conduct begins with declare any conflict to all parties affected and either remove
an introduction, which includes a note on discipline, and an its cause or withdraw from that situation. GN 3.2 gives the
example showing the structure of a principle. The main body example of an architect that also runs a separate contractor
of the Code comprises the three principles, each of which has a business. There is no specific guidance on the situation where
heading, a list of ‘mandatory’ duties, and ‘non-binding guidance an architect novated to a contractor in a design build procure-
notes/commentary’ with examples to aid understanding. A list of ment context, but retains formal or informal links with its
definitions is set out at the end of the Code. former Employer client. It is suggested that this frequently
gives rise to a conflict of interest, and should be handled as
required under the Code.
Principles Under the 1981 Code, there had been a prohibition on simul-
3.05 The RIBA Code has three principles: integrity, competence, taneous practice as an independent consultant and involvement
and relationships. Each of these has a ‘strapline’, which is stated as a principal of business trading in land or buildings, property
to be ‘a non-binding section aimed at setting aspirations for best development, auctioneering, estate agency, contracting, manu-
practice and informing interpretation of the specific duties’. This facturing, or materials supply, unless the firm is clearly distinct
is followed by ‘the components of the principle’, which each from the architectural practice. This was later dropped from the
comprise a heading setting out the duty, followed by ‘specific, code; instead, the emphasis is now on awareness, transparency,
mandatory provisions of the duty,’ some of which are supported and taking appropriate measures.
by Guidance Notes (GNs). The GNs are inserted in boxes, just
below the relevant provision. Each of the three principles is
numbered separately, so that the Code, rather confusingly, has
4. Confdentiality and privacy
three provisions numbered 1.1, 1.2, etc. This section has been considerably expanded and refers to
safeguarding the privacy of the member’s clients and others,
and to treating confidential information acquired during the
Principle 1: integrity course of their work as such, as well as adhering to all legal
The strapline states: rights of privacy and any contractual provisions regarding
confidentiality. A list of the only situations where members
Members shall behave with integrity and shall strive to may use and/or disclose confidential information is set out.
safeguard and improve the standing, reputation and dignity GN 4.7 refers members to government guidance on data
of the Institute and its Members in all their professional protection and the Data Protection Act 2018 (www.gov.uk/
activities. Members shall consistently promote and protect data-protection).
the public interest and social purpose, taking into account
future generations.
5. Handling clients’ money
The duties are listed under the following headings: 1. Impartiality Members requested by a client to hold money on the client’s
and undue influence; 2. Statements; 3. Conflicts of interest; 4. behalf are required to keep it in a designated interest-bearing
Confidentiality and privacy; 5. Handling client money; 6. bank account (a ‘client account’), which is separate from the
Bribery and corruption; and 7. Criminal conviction/disqualifica- Member’s personal or business accounts. They must return it as
tion as a director/sanction. These are summarised below, but of soon reasonably practicable following a written request to do
course, the Code itself should always be consulted. so, ensure it is not withdrawn or used otherwise than in accord-
ance with the client’s written instructions, and arrange for any
interest to be paid to the client, unless otherwise agreed by the
1. Impartiality and undue infuence client in writing.
This refers to members acting with objectivity at all times in
their professional and business activities, being honest and truth-
ful, and not allowing themselves to be improperly influenced by
6. Bribery and corruption
others or by their own self-interest. The requirement not to offer or take bribes in connection with
professional work is of long-standing duration. GN 6.1 and 6.2
explains that bribes may not always direct offers of money, but
2. Statements instead may be more indirect gifts and incentives. However, it
Forbids members making or being a party to any statement states that the exchange of small gifts and advantages in the
which is: (a) untrue; (b) misleading; (c) unfair; and/or (d) con- normal course of business (such as promotional gifts or corpo-
trary to their professional knowledge. If they find themselves rate hospitality) is not prohibited, so long as the value to the
party to any such statement, they must take all reasonable steps recipient is not such that it exerts an improper influence over
to correct the statement immediately, and GN 2.2 outlines how them. The mandatory provisions also require that members take
this may be done. reasonable steps to report any suspicion of corruption or bribery
The requirement not to make a statement which the mem- of which they become aware in their professional activities, and
ber knows to be misleading or contrary to their professional to conduct due diligence checks on potential clients to establish
knowledge was first covered in the 1997 version of the code. and verify their identity, with GN 6.5 giving guidance on due
The 2005 code also advised members not to be party to diligence checks.
384 Professional conduct of architects

7. Criminal conviction/disqualifcation community’s and the project’s capital costs with its overall
as a director/sanction performance).

Under this duty, Members who receive a criminal conviction


of any kind, or are disqualified from acting as a director, are 2. Terms of appointment
sanctioned by the ARB, or by any other professional regulator Duty 2.1 requires that all terms of appointment between a
or professional membership body, must report this to the RIBA Member and their client must be clear, agreed, and recorded
Professional Standards team within 30 days. Members convicted in writing before the commencement of any professional ser-
of a criminal offence which could carry a sentence of imprison- vices. This is an unqualified obligation, and applies to all or
ment for 12 months or more will be expelled from membership any services, no matter of what type or how early in the project
of the RIBA. development it occurs. In practice, this is often ignored, but the
RIBA has good evidence that it is frequently a major cause of
complaints and dispute, and therefore underlies the need for
clear appointment in its Code and in all its published guidance.
Principle 2: competence The specific requirements are more detailed than in the
2005 Code, and reflect the ARB Code requirements regarding the
The strapline states: need for a written appointment and what should be covered. This
includes a clear statement of the client’s requirements, the role of
Members should continuously strive to improve their profes- others who are to undertake services, the method of calculation
sional knowledge and skill. Members should persistently seek of remuneration, and the provision for termination and dispute
to raise the standards of architectural education, life-long resolution. Unlike the ARB Code, the RIBA guidance refers
learning, research, training, and practice for the benefit of to the Professional Services Contracts published by the RIBA.
the public interest, those commissioning services, the profes- Although there is no absolute requirement to use these forms,
sion and themselves. Members should strive to protect and they should be used ‘where appropriate and possible.
enhance heritage and the natural environment. The Code sets out further requirements relating to explaining
the terms to the client, and to amendment of the appointment.
The duties are listed under the following headings: 1. Skill, Members should explain to their clients the implications of the
knowledge, care, ability; 2. Terms of appointment; 3. Time, cost, terms, including how their fees are to be calculated and charged.
quality; 4. Keeping the client informed; 5. Record keeping; 6. It also requires Members to give details of their written com-
Health and safety; 7. Inspection services; 8. Building perfor- plaints procedure (see Principle 3, 8.2) with the terms of appoint-
mance; 9. Heritage and conservation; 10. Town and country ment, or to make it clear that the written complaints procedure
planning; 11. Law and regulations; 12. Certification; 13. The will be provided on request
environment; and 14. Community and society. This section
of the Code is undoubtedly more fully developed, with more
detailed and specific duties than in the 2005 duties. Some key
points are summarised below. 3. Time, cost, quality
This includes a range of duties both with respect to the provi-
1. Skill, knowledge, care, ability sions of services (without undue delay and within an agreed
reasonable time limit, and in accordance with any cost limits
Members are required to act ‘competently, conscientiously and agreed with their clients, and also with respect to their projects
responsibly’ and are expected to apply ‘reasonable standards of that they are safe; cost-effective to use, maintain, and service;
skill, knowledge and care in the performance of all their work’. and minimise negative impacts on the environment during their
It should be noted that this is the Code standard; if a member anticipated life-cycle).
has promised a higher one to its client, it would be contractu-
ally obliged to provide it. They must provide the knowledge,
the ability, and the financial and technical resources appropriate 4. Keeping the client informed
for the work they undertake. They should realistically appraise Failure to keep the client informed is another key cause of
their ability to undertake and achieve any proposed work, and disputes, and the Code requires members to keep them updated
undertake services only when they are sufficiently qualified. GN on a range of matters, including the progress of a project, deci-
1.2 and 2.2 underlines this by advising that members should sions made on the client’s behalf, risks, and circumstances which
not accept work that they do not have sufficient resources to may adversely impact on the overall time, cost, or quality of the
satisfactorily complete, and that they must ensure that the project, or on their own work.
individuals actually carrying out the work are competent to
do so. They shall not make or be party to misleading, decep-
tive, or false statements or claims regarding their professional 5. Record keeping
qualifications, resources, or the services provided. Practising Members are required to maintain appropriate records through-
Chartered Members are furthermore required to comply with out their engagement, and GN 5.1 gives detailed advice on
any current RIBA scheme or guidance for continuing profes- exactly what should be covered. The Code also explains how the
sional development. records should be stored and the circumstances in which they
Members are required to make appropriate arrangements for should be made available.
their professional work to continue in the event of incapacity,
death, absence from, or inability to, work – this can be particu-
larly important for small practices, or for sole practitioners. 6. Health and safety
Members should advise their clients at the outset of the likeli- Members are required to have reasonable knowledge of, and
hood of achieving the client’s requirements and aspirations and abide by, all laws and regulations relating to health and safety
update them if their assessment of this changes. If members feel as they apply to building projects. They must take reasonable
they are unable to comply with this, they should not quote for, steps to ensure their clients and others they have contact with
or accept, the work. understand their duties, and to protect the health and safety of
They must also apply their informed and impartial judgment those under their control, and those carrying out, or likely to be
in reaching any decisions, which GN 1.10 explains may require directly affected by, construction work for which they are pro-
members having to balance differing and sometimes oppos- viding professional services, including members of the public. If
ing demands (for example, the stakeholders’ interests with the a Member becomes aware of a decision taken by their employer
RIBA Code of Professional Conduct. 385

or client which violates any law or regulation, they must advise


the client, and/or refuse to consent to the decision, and/or ‘report
the decision to the local building inspector or other public offi-
cial’. It should be noted that the ‘whistle blow’ requirement is an
option, and it is suggested that this action should only be taken
if all other have been explored.

7. Inspection services
The Code requires members to advise their client on the need
for, nature, and frequency of inspections, ‘based on the require-
ments of the specific project and the terms of the appointment’.
Further advice is given on this under GN 7.1, which reflects that
given in the case of McGlinn v Waltham Contractors Ltd [2007]
111 Con LR 1.

8. Building performance
Members are required to ‘facilitate and support an effective
handover and building commissioning process, when engaged
at the relevant project stage’. In reality, the obligation to do
this would depend on the services agreed for that stage. The
Code states that Members should promote and support the
value and benefits of monitoring building performance after
occupation, and unusually, GN 8.2 states that members, ‘where
competent to do so, should offer post occupancy evaluation as
an additional added value service’. This is the only point where
the guidance states that members should offer a particular ser-
vice. This is somewhat out of step with guidance in the PSCs,
which recommends that members should only undertake a
POE under a separate appointment (it is not listed as a service
under the Standard PSC) and should inform their PI insurers
before doing so.
completed projects may have on users, the local community, and
society (Figure 39.1).
9. Heritage and conservation; 10.
Town and country planning; and
Principle 3: relationships
11. Law and regulations
The strapline states:
Under these, the member is required to respect the importance
and significance of Heritage Assets., advise their client on and Members shall respect and seek to uphold the relevant rights
comply with relevant planning legislation and regulations, and interests of others. Members shall treat people with respect
and only undertake services related to these if competent to and shall strive to be inclusive, ethical, and collaborative in all
do so. Members also ‘shall not knowingly violate the law’ or they do. Members shall seek and promote social justice.
advise clients in relation to anything illegal, and shall take
appropriate steps to ensure that clients are properly advised of Principle 3 differs in scope from the other requirements in that
their own relevant legal responsibilities. This is a very broad it covers not only relationships with clients, employees, and
requirement, but GN 11.2 refers only to CDM and Planning. society at large, but also relations with other members of the
Unless the area is one in which the architect has expertise, the RIBA. The duties are listed under the following headings: 1.
only appropriate step would be to advise the client to consult Copyright; 2. Previous appointments; 3. Peers; 4. Equality,
a lawyer. diversity and inclusion; 5. Modern slavery; 6. Employment and
responsibilities as an employer; 7. Competitions; 8. Complaints
12. Certifcation and dispute resolution; 9. Advertising/business names/use of
RIBA crest and logo; 10. Insurance; 11. Non-disclosure agree-
This states that the member must exercise reasonable skill ments; 12. Whistleblowing.
and care when issuing or recommending the issue of any
certificate. This is followed by a sensible guidance note on
practical completion and valuation – however, it should be 1. Copyright
noted that the role of a certifier will always depend on exactly Members are required to respect applicable laws on copyright
what has been agreed with respect to certification under the and other rights of intellectual property. There is no copyright
building contract. protection in ideas, but the Code goes further than the applicable
laws, in that it prohibits taking advantage of the ideas of another
13. The environment; and 14. architect or designer without express authority from the originat-
ing architect or designer.
Community and society.
Members are required to consider the environmental impact of
their professional activities, including the impact of each project
2. Previous appointments
on the natural environment. They must also promote sustainable Members are required to inform the previous appointee before
design and development principles in their professional activi- accepting an appointment to continue a project started by
ties. Similarly, they are required to have proper concern and someone else, and to check a range of matters with the client,
due regard for the effect that their professional activities and including whether the appointment was properly terminated
386 Professional conduct of architects

and whether the client has any necessary copyright or license If the complaint cannot be resolved internally, members are
to sue material prepared by that firm. When approached to required to encourage alternative methods of dispute resolution
undertake work, they must also make reasonable enquiries as to (ADR), such as mediation or conciliation. GN 8.4 draws atten-
whether or not any other architect is already involved. GN 2.1 tion to the RIBA’s various ADR services, which include media-
makes it clear that the existence of a dispute or contractual issue tion, adjudication, and arbitration.
does not necessarily prevent them from taking over the project.

The code does not prevent an architect from undertaking work 9. Advertising/business names/
in situations where another architect has or had an engagement use of RIBA crest and logo
with the same client, but the architect is advised to notify the
The Code states that all marketing and promotional material
other architect. The undertaking is devised in the interests of
should be legal, decent, honest and truthful, fair to others, and
both architects, but it is often misunderstood.
accurate. Amongst other things, it should not unfairly discredit
competitors, either directly or by implication, or encourage or
3. Peers condone unacceptable behaviour. The duties cover the use of the
term Chartered Architect, including that Members using it must
This duty also concerns conduct towards other professionals,
also be registered wherever registration is a requirement under
for example, it states that ‘members must not seek to damage
the law. It also sets out the circumstances when a member may
anyone’s reputation or practice’, nor should they ‘deliberately
use the RIBA crest and affix.
approach another architect’s client in a conscious attempt to take
over an active project’. A member engaged to give an opinion on
the work of another architect must do so fairly and objectively, 10. Insurance
based on their own knowledge and experience.
Members are required to hold suitable insurance to cover any
potential liabilities arising from negligence or breach of contract
4. Equality, diversity and inclusion; 5. associated with their professional activities. GN 10.2 and 10.3
expand on the requirements for insurance. The duties cover when
Modern slavery; and 6. Employment the details of insurance should be made available, and refer to
and responsibilities as an employer The Provision of Services Regulations 2009.
Members are required to provide their professional services and
conduct their professional activities in a manner that encour- 11. Non-disclosure agreements
ages and promotes equality of opportunity and diversity, and
The use of non-disclosure agreements (NDAs) to prevent the
a range of behaviour relating to discrimination and harassment
reporting of wrongdoing or professional misconduct to the rel-
are prohibited.
evant authorities (for example by making improper threats of
Members are also required to comply with all applicable leg-
litigation) is prohibited.
islation concerning Modern Slavery and to seek to raise aware-
ness of this in construction, including using supply chains which
are free from Modern Slavery and reporting abusive labour
practices to the appropriate authority.
12. Whistleblowing
There are detailed duties in relationship to employment, includ- This covers both a requirement to have internal procedures
ing providing employees with a fair, safe, and equitable working that allow for and support whistleblowing, by employees, and
environment and a full written contract of employment, to pay all a positive duty to ‘report dangerous situations and suspected
staff fairly, and to regard for the maximum weekly working hours wrongdoing to an appropriate person or organisation as soon as
and the 48-hour working week under the working time directive. possible’. GN 12.2 and 12.3 set out further details of what is
Employers are also required to facilitate and encourage employees’ expected in relation to these duties, including referring to the
professional development, and there are particular requirements for relevant government website (https://www.gov.uk/whistleblow
architecture students, for example, having regard for the student’s ing/who-to-tell-what-to-expect).
training and education in accordance with the objectives of the
RIBA professional experience scheme. GN 6.8 refers to the model
employment contracts provided by the RIBA for members employ- 4 Statement of professional conduct
ing students, together with a requirement to meet regularly with the of the Royal Incorporation of
students and allow them time to attend courses and to study.
Architects in Scotland (RIAS)*
7. Competitions 4.01 The Architects Act 1997 applies throughout the United
Members involved in any form of competition to win work or Kingdom and elsewhere, as an architect practising in Scotland
awards are required to act fairly and honestly with potential cli- is subject to its Code. In addition, the architect members of the
ents and competitors. If members find that a competition process Royal Incorporation of Architects and architect members of the
is not known to be reasonable, transparent, and impartial, they Royal Institute of British Architects are subject to their respec-
are required to endeavour to rectify the competition process or tive codes. Many architects belong to both bodies and as such,
withdraw. are subject to requirements of all three codes.

4.02 The existence of a separate RIAS Code stems from the


8. Complaints and dispute resolution Incorporation’s Charter of 1922 and consequent By-laws, which
Detailed provisions are included regarding complaints and dis- call for a Declaration to be made by all who join. This statement
pute resolution. Those for complaints embody the requirement of principle is the basis against which any alleged complaint is
of the Provision of Services Regulations 2009. Members are judged. The RIAS Council has authority to publish intimations
expected to have in place (or have access to) written procedures illustrating good practice behaviour, which, in the breach of,
for dealing promptly and appropriately with disputes or com- require investigation and possible disciplinary sanctions. These
plaints. They should provide details of the written complaints comprise, as with RIBA: reprimand, suspension, and expulsion.
procedure with the terms of appointment, or make it clear that The Charter authorises the by-laws. The most recent version
it will be provided on request. Complaints must be handled
courteously and speedily, and the Code sets out suggested time
limits and procedures. * This section was written by Peter Anderson.
Statement of professional conduct of the Royal Incorporation of Architects in Scotland (RIAS) 387

of the by-laws is dated 22 January 2004. Any member joining 4.09 RIAS Council, in agreeing this step, approved plans for
RIAS signs a Declaration that they will not conduct themselves continuing to issue wise counsel to members on matters of
in a manner which in the opinion of the Special Committee of behaviour, via its other organs of communication, and deal-
the Disciplinary Panel is derogatory to his or her professional ing with matters of dispute or complaint (particularly between
character or engaging in any occupation which in the opinion of members) through conciliation, via a panel of members with
the Special Committee of the Disciplinary Panel is inconsistent appropriate experience.
with the profession of an architect.
4.10 The sanction of RIAS disciplinary procedures remain in
4.03 It is a prerequisite of membership of RIAS that applicants place, however, to deal with behaviour about which the ARB
demonstrate their registration with ARB. For this reason, the first would have no interest, as it has no consumer-related aspects,
intimation of every Statement of Professional Conduct published but which could be seen to be damaging the Incorporation and
since 1982 has been to bind active architect members explicitly thus in breach of the Declaration.
to the code requirements of the registration body.
Prior to the 1997 Act, the 1931 Act, which governed the activ- 4.11 At the same time, RIAS staff continue to handle a wide
ity of the Architects Registration Council of the United Kingdom range of complaints from third parties – most often clients –
(ARCUK), made it difficult and cumbersome for ARCUK to deal giving advice and assistance where possible to indicate ways in
with complaints. For this reason, the RIAS published additional which difficulties can be overcome. For any serious complaints,
intimations, which enabled it to address complaints effectively complainants are referred to ARB.
and efficiently in Scotland, the numbers increasing during the
later 1980s and into the 1990s as consumerism advanced. 4.12 The RIAS Charter and by-laws have been subject also
to substantial revision during 2001–2003, as a result of the
4.04 However, the possibilities of one complaint being subject realignment of roles vis-à-vis RIBA, post the devolution set-
to three separate sets of investigations under three distinct codes tlement of 1999. The greater clarity between the respective
(RIAS, RIBA, and ARB) was considered to be extremely unde- roles of ARB, RIBA, and RIAS is welcome, and is reflected
sirable. As soon as a clear and robust code emerged from ARB in the current simplicity of the RIAS Statement of Professional
with its second edition in September 1999, it became possible Conduct.
to start to address revisions to the RIAS Code, and in particular,
the intimations. 4.13 The Statement of Professional Conduct:
At the same time, arrangements were put in place to refer all
serious complaints directly to ARB in recognition of its statutory A member shall be bound by the Declaration signed upon elec-
role and powers. tion and in particular of the responsibility for upholding the
repute of the Royal Incorporation as a professional body and
4.05 The 1993 RIAS Statement included 16 intimations, one of fellow members as individuals. Actions inconsistent with the
of which incorporated a six-point set of Client Account Rules. Declaration shall be held to constitute unprofessional conduct
The intimations dealt with a range of issues including carrying and, as such, will be dealt with by Council in accordance with
Professional Indemnity Insurance and undertaking Continuing by-law 16.1.
Professional Development, and having proper forms of agreement
in place for appointments with an architect in control. The code had The Declaration:
attempted to deal with competitive fee-tendering by referral to set
procedures, and included reference to advertising, and promotion. I declare that I have read the Charter and by-laws of the said
Reviewing the ARB Code made clear that the majority of the Incorporation and the by-laws of my chapter, and will be
intimations could be swept away, as they could now be dealt governed and bound thereby, and will submit myself to every
with by ARB, and slight differences between Codes would cause part thereof and to any alterations thereof which may hereafter
confusion. be made until I have ceased to be a member: and that by every
lawful means in my power I will advance the interests and
4.06 The January 2000 RIAS Statement therefore only included objects of the said Incorporation.
two intimations, the second of which regulated behaviour
between RIAS members and ‘employees, employers, profes- 4.14 By-law 18 clearly sets out the current position – by-law 18,
sional colleagues and business associates’. This required clarifying the role of RIAS vis-à-vis ARB:
members to notify another member if they had been invited or
instructed to proceed with work on a project that another mem- 18 Discipline
ber had been engaged with. Secondly, it required members not
to attempt to supplant another member. And thirdly, it required – 18.1 The Council shall put in place formal procedures for
subject to a member’s right and obligations under the ARB Code handling of complaints.
– that members having any matter of complaint or protest against 18.2 Any Member contravening the Declaration signed by
another member notify the Secretary of the Incorporation, and the Member or conducting himself or herself in a man-
make no other protest. ner which in the opinion of the Special Committee of
the Disciplinary Panel is derogatory to his or her profes-
4.07 After a further year, it became clear that ARB was not sional character or engaging in any occupation which in
specifically concerned under its code with the specifics of the the opinion of the Special Committee of the Disciplinary
obligations related to continuing professional development. Panel is inconsistent with the profession of an architect
The Incorporation therefore approved a further adjustment to shall following investigation and disciplinary procedures
its Statement in February 2001 clarifying members’ obligations as approved by the Council from time to time be liable
as individuals and as employers, and emphasising the need to to reprimand, suspension or expulsion.
record their activity. 18.3 Where a complaint against a member is considered
and determined by the Architects Registration Board
4.08 By the summer of 2003, however, it became clear that with or any successor to it, the Council shall be entitled to
new forms of procurement (including online fee bidding) and accept, adopt and apply the findings of the Architects
further interest by the Office of Fair Trading in any code aspects Registration Board both in relation to the merits of the
that could inhibit competition (i.e. the curb on attempting to complaint and any penalty imposed as being the appropri-
supplant), the supplementary intimations were no longer appro- ate disposal of a complaint involving a breach of by-law
priate. From June 2003, therefore, the RIAS Code incorporated 18.2 without holding any further enquiry or proceedings
merely the ARB Code under Intimation 1. provided always that the Council shall have before it a
388 Professional conduct of architects

copy certified by the Clerk or other authorised official of the Council of RIAS), then the RIAS Legal Adviser is instructed
the Architects Registration Board of their findings. The to prosecute before that Committee the case made against the
Council shall not however be obliged if it so resolves member. A formal written complaint is formulated and then
to adopt and apply the determination of the Architects served on the respondent member, who has the opportunity to
Registration Board. submit written answers. Thereafter, a formal hearing is con-
vened. The RIAS Legal Adviser has the responsibility to present
4.15 As can be seen from the wording of by-law 18.2, where a the evidence, which can be cross-examined by the respondent or
complaint is submitted to RIAS, it is, in practice, considered in any representative of the respondent. The respondent can then
the first place by the Secretary (or Chief Executive, if such is present any evidence that is considered relevant and necessary.
appointed) who, on a direction from the President, remits the The Special Committee of the Disciplinary Panel appoints an
complaint to an Investigation Committee. The Investigation independent lawyer, typically a QC of the Scots Bar, to act as
Committee carries out preliminary work to identify whether its adviser for the conduct of the proceedings.
there is a case to answer. It submits a report to the Council of At the conclusion of the proceedings, the Special Committee
RIAS who then determine whether or not to act on any recom- advises RIAS and the respondent of its opinion and submits a
mendation to establish the Special Committee of the Disciplinary report to RIAS Council. RIAS Council then consider the opinion
Panel referred to in by-law 18.2. of the Special Committee and any recommendation it may have
made in relation to penalty. Again, the independent legal adviser
4.16 If such a Special Committee of the Disciplinary Panel is would be present at the meeting of RIAS Council for this limited
set up (members of the Disciplinary Panel are appointed for purpose, and RIAS Council would then decide on any penalty
periods from time to time and do not require to be members of to be imposed.
Table of Statutes and Statutory Instruments

Animal Welfare (Licensing of Activities Involving Animals) (England) Building Regulations (Scotland) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105
Regulations 2018 SI 2018/486 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71 applications for warrants . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112–113
Architects (Recognition of European Qualifications) Regulations 2008 . . . . 377 Building (Scotland) Act 2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105–112
Architects Directive (85/384/EEC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 377 Building Standards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106
Architects’ Qualifications (EC Recognition) Order 1988 . . . . . . . . . . . . . . . . 376 energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119–120
Architects’ Qualifications (EEC Recognition) Order 1987 . . . . . . . . . . . . . . 376 environment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116–118
Asbestos (Licensing) Regulations 1983 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 166 fees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113
Asbestos (Prohibitions) Regulations 1992 . . . . . . . . . . . . . . . . . . . . . . . . . . . 166 fires . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114–116
BR(A)R 2012 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79 forms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113
BR(A)R 2016 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79 noise . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118–119
BR(A)R 2018 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79 safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
Building (Amendment) Regulations 2018 . . . . . . . . . . . . . . . . . . . . . . . . . 90–91 structures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114
Building (Amendment) (Wales) Regulations 2017 . . . . . . . . . . . . . . . . . . . . . . 91 Building Regulations 2010 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79–83, 98
Building (Amendment) (Wales) Regulations 2019 . . . . . . . . . . . . . . . . . . . 91–92 applications for determination . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building (Approved Inspectors etc.) Regulations 2010 . . . . . . . . . . . .79, 84, 99 Approved Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80–81
Building (Energy Performance of Buildings) (Scotland) Amendment breach of building regulations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81–82
Regulations 2016 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120 building notice procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82–83
Building (Fees) (Scotland) Regulations 2004 . . . . . . . . . . . . . . . . . . . . . . . . 113 completion certificates . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building (Forms) (Scotland) Regulations 2005 . . . . . . . . . . . . . . . . . . . . . . . 113 control of building work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building (Inner London) Regulations 1985, 85 . . . . . . . . . . . . . . . . . . . . . . . . 79 discretion of local authority . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
Building (Inner London) Regulations 1987 . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 dispensations and relaxations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building (Miscellaneous Amendment) (Scotland) Regulations 2013 . . . . . . . 120 enforcement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building (Miscellaneous Amendments) (Scotland) exemptions from control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
Amendment Regulations 2017 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120 fire safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90
Building (Miscellaneous Amendments) (Scotland) Regulations 2017 . . . . . . 120 full plans procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building (Procedure) (Scotland) Regulations . . . . . . . . . . . . . . . . . . . . . 112–113 material alteration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
Part III . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112 material change of use . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
Part IV . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112 Part 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Part IX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113 Part 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Part V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112 Part 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Part VII . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112 procedural rules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
Part VIII . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112 provision of exits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
Part X . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113 Regulation 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
Regulation 19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112 Regulation 3(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .79, 82
Regulation 57 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113 Regulation 4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
Regulation 58 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113 Regulation 4(1)(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
Building (Repeal of Provisions of Local Acts) Regulations 2012 . . . . .98, 99, 161 Regulation 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .79, 81, 82
Building (Safety, Health and Welfare) Regulations 1948 . . . . . . . . . . . . . . . 163 Regulation 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .79, 81, 82
Building (Scotland) Amendment Regulations 2006 . . . . . . . . . . . . . . . . . . . . 120 Regulation 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
Building (Scotland) Amendment Regulations 2007, 113 . . . . . . . . . . . . . . . . 120 Regulation 11 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building (Scotland) Amendment Regulations 2008 . . . . . . . . . . . . . . . . . . . . 120 Regulation 12 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .82, 83
Building (Scotland) Amendment Regulations 2009 . . . . . . . . . . . . . . . . 113, 120 Regulation 13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .82, 83
Building (Scotland) Amendment Regulations 2010 . . . . . . . . . . . . . . . . . . . . 120 Regulation 13[5] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building (Scotland) Amendment Regulations 2011 . . . . . . . . . . . . . . . .106, 120 Regulation 14, 81 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building (Scotland) Amendment Regulations 2012 (SSI 2012/209) . . . . . . . 120 Regulation 16 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building (Scotland) Amendment Regulations 2014 . . . . . . . . . . . . . . . . . . . . 120 Regulation 16[1][a] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building (Scotland) Amendment Regulations 2015 . . . . . . . . . . . . . . . . . . . . 120 Regulation 16[1][b] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building (Scotland) Amendment Regulations 2016 . . . . . . . . . . . . . . . . . . . . 120 Regulation 17, 82 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building Regulation 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 Regulation 18, 82 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building Regulation 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 Regulation 18(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building Regulation 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 Regulation 22 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building Regulation 7, 80 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 Regulation 23 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building Regulation 7(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 Regulation 28 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Building Regulation 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80 Schedule 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .84
Building Regulation 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 technical requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80
Building Regulation 12(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 unauthorised building work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
Building Regulation 13[3] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81 Building Regulations Part B (Fire Safety) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
Building Regulation 14(3)(b) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 Building Regulations Schedule 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
Building Regulation 15 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 Part C . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Building Regulation 38 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 Building Regulations Schedule 1 Part L (Conservation of fuel
Building Regulations (Northern Ireland) 2012 . . . . . . . . . . . . . . . . . . . . . . . . . 79 and power) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
Building Regulations &c. (Amendment) (Excepted Energy Buildings) Building Regulations Schedule 1 Part M (Access to and use
(Wales) Regulations 2018 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91 of buildings) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
Building Regulations &c. (Amendment No. 3) . . . . . . . . . . . . . . . . . . . . . . . . 91 Building Regulations Schedule 1 Part P (Electrical Safety) . . . . . . . . . . . . . . 84
Building Regulations &c. (Amendment) Regulations 2012 . . . . . . . . . . . . . . . 90 Building Regulations (Scotland)
Building Regulations &c. (Amendment) Regulations (‘BR(A)R’) . . . . . . . . . 79 Regulation 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107

389
390 Table of Statutes and Statutory Instruments

schedule 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106 Regulation 38 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67


Schedule 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106 Environmental Permitting Regulations 2017 . . . . . . . . . . . . . . . . . . . . . . . . . . 71
section 17(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109–110 EU (European Union) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14–15, 365
Building (Scotland) Regulations 2004 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75 2014 Procurement Directives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143
Regulation 8(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114 Concessions Directive (2014/23/EU) . . . . . . . . . . . . . . . . . . . . . . . . . . .143, 152
Regulation 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113 Construction Products Directive (1989) . . . . . . . . . . . . . . . . . . . . . . . . . . . 87–88
Regulation 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113 Construction Products Regulation (EU) 305/2011 . . . . . . . . . . . . . . . . . . . 87–88
Regulation 8(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113 Construction Sites Directive, EU Directive 92/57/EEC
Regulation 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114 (OJ L245, 26.8.92) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 164
Regulation 10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114 Copyright Rights in Databases Regulations 1997 (SI 1997. No. 3032) . . . . 358
Regulation 13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114 Defence Directive (2009/81/EC) . . . . . . . . . . . . . . . . . . . . . . . . . . 143, 152–153
Regulation 14 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114 Design Regulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 366
Regulation 15 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114 Directive 89/665/EEC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
Schedule 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106 Directive 92/13/EEC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
Schedule 5, Section 1: Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114 Directive 2003/18/EC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 166
Schedule 5, Section 2: Fire . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 114–116 Directive 2005/36/EC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161
Schedule 5, section 3: environment . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116–118 Directive 2007/66/EC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
Schedule 5, section 4: safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118 Directive on the Legal Protection of Designs Directive 98/71/EC . . . . . . . . 365
Schedule 5, section 5: noise . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118–119 EU Regulation No 6/2002 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 365
Schedule 5, section 6: energy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 119–120 Framework Directive . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 170
Building Standards Advisory Committee (Scotland) Regulations 2004 . . . . . 120 Energy Performance of Buildings Directive, Article 9 . . . . . . . . . . . . . . . . . 114
CDM (Construction Design and Management) Regulations . . . . . . . . .164, 166 General Data Protection Regulation 2016/679 (GDPR) . . . . . . . . . . . . . . . . . 304
Regulation 11 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165 Health and Safety [Amendment] [EU Exit] Regulations 2018 . . . . . . . . . . . 167
Regulation 13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165 Information Society Directive (2001/29/EC) . . . . . . . . . . . . . . . . . . . . . . . . . 359
CDM 1994 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165 Mediation Directive (2008/52/EC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 283
CDM (Construction Design and Management) regulations . . . . . . . . . . .86, 102 Privacy and Electronic Communications (EC Directive)
CDM Regulations 2015 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 312 Regulations 2003 (PECR) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 367
Cinematography (Safety) (Scotland) Regulations 1955 . . . . . . . . . . . . . . . . . . 76 Public Sector Directive (2014/24/EU) . . . . . . . . . . . . . . . . . . . . . . 143, 144–151
Clean Air (Emissions of Grit and Dust from Furnaces) Regulations 1971 . . . 71 Public Works Directive, Article 72 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 150
Construction (Design and Management) Regulation 1370/2007/EC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143
Regulations (2015) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .86, 102, 311, 314, 331 Remedies Directives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 153
Regulation 14 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 159 Temporary or Mobile Construction Sites Directive
Regulation 15 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 159 (Directive 92/57/ECC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 164
Construction Contracts (England and Wales) Exclusion Order 1998 Treaty on the Functioning of the EU (TFEU), 143 . . . . . . . . . . . . . . . . . . . . 150
(SI 1998 No. 648), 242 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 250 Utilities Directive (2014/25/EU) . . . . . . . . . . . . . . . . . . . . . . . . . . 143, 151–152
Construction Products Regulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80 EU Design Regulation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 366
Construction Products Regulation (EU) 305/2011 . . . . . . . . . . . . . . . . . . . 87–88 EU Directives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14–15
Construction Products Regulations 2013 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87 Fees Regulations 2012 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
Control of Asbestos at Work Regulations 2006 . . . . . . . . . . . . . . . . . . . . . . . 166 Regulation 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
Control of Asbestos Regulations 2012 (CAR12) . . . . . . . . . . . 86, 165, 166–167 Fire Certificate (Special Premises) Regulations 1976 . . . . . . . . . . . . . . . . . . .99
Control of Industrial Major Accident Hazard Regulations 1984 . . . . . . . . . . 165 Fire Precautions (Workplace) Regulations 1997 . . . . . . . . . . . . . . . . . . . . . . 161
Control of Lead at Work Regulations 1980 . . . . . . . . . . . . . . . . . . . . . . . . . . 165 Fire Precautions (Workplace) Regulations 1999 . . . . . . . . . . . . . . . . . . . . . . . 99
Control of Lead at Work Regulations 2002 . . . . . . . . . . . . . . . . . . . . . . . . . . 165 Food Safety and Hygiene (England) Regulations 2013 (SI 2013/2996) . . . . . 71
Control of Major Accident Hazards Regulations 2015 . . . . . . . . . . . . . . . . . 165 General Data Protection Regulation (GDPR) . . . . . . . . . . . . . . . . . . . . . 367–371
Control of Noise at Work Regulations 2005 . . . . . . . . . . . . . . . . . . . . . . . . . 165 GPO 2015 (Town and Country Planning (General Permitted Development)
Control of Substances Hazardous to Health Regulations 1988 . . . . . . . . . . . 165 (England) Order 2015 (SI 2015/596)) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125
Control of Substances Hazardous to Health Regulations 2002, 165 . . . . . . . 302 Article 2(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
Conversation of Habitats and Species Regulations 2017 Habitats Regulations 2017 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125
(SI 2017 No. 1012) (‘Habitats Regulations 2017’) . . . . . . . . . . . . . . . . . . . . 125 Health and Safety (Display Screen Equipment) Regulations 1992 . . . . . . . . 169
DMP Order 2015 (Town and Country Planning (Development Management Health and Safety (Display Screen Equipment) Regulations 2002 . . . . . . . . 169
Procedure) (England) Order 2015 (SI 2015 No. 585)) . . . . . . . . . . . . . . . . . 125 Health and Safety (First Aid) Regulations 1981 . . . . . . . . . . . . . . . . . . . . . . 302
Article 13, 127 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128 Health and Safety (Miscellaneous Amendments) Regulations 2002
Article 14 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 (SI 2002 No 2174) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 168–169
Article 34 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128 Home Energy Assistance Scheme (Scotland) Regulations 2013 . . . . . . . . . . . 76
Article 35 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128 HSG 168 Fire safety in construction (2010) . . . . . . . . . . . . . . . . . . . . . . . . . 102
Article 37 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128 Licensing of Houses in Multiple Occupation (Mandatory Conditions
Regulation 18 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137 of Licenses (England) Regulations 2018 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
DMPR (Town and Country Planning (Development Management Procedure) Lifting Operations and Lifting Equipment Regulations 1998 (LOLER) . . . . 170
(Scotland), Regulation 13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137 Listed Building Consent
Domestic Fire Safety (Wales) Regulations 2013 . . . . . . . . . . . . . . . . . . . . . . . 91 section 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139
Duration of Copyright and Rights in Performance Regulations 1995 section 7(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139
(SI 1995 No. 3297) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 357 Management of Health and Safety at Work Regulations 1999, 99, 170 . . . . 302
Electricity at Work Regulations 1989 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 303 Manual Handling Operations Regulations 1992 (MHOR) . . . . . . . 168–169, 302
Employers’ Liability (Compulsory Insurance) Regulations 1998 . . . . . . . . . 304 Noise at Work Regulations 1989 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165
Energy Performance of Buildings Directive . . . . . . . . . . . . . . . . . . . . . . . . . 110 Partnerships (Unrestricted Size) (No. 4) Regulations 1992
Energy Performance of Buildings (England and Wales) (amended 2002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 296
Regulations 2012 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87 Personal Protective Equipment at Work Regulations 1992 . . . . . . . . . .165, 302
Energy Performance of Buildings (Scotland) Amendment (No. 2) Personal Protective Equipment Regulations 2002 . . . . . . . . . . . . . . . . . . . . . 168
Regulations 2012 (SSI 2012/208) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120 Petroleum (Consolidation) Regulations 2014 SI 2014/1637 . . . . . . . . . . . . . . 71
Energy Performance of Buildings (Scotland) Amendment (No. 3) Planning (Listed Building Consent and Conservation Area Consent
Regulations 2012 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120 Procedure) (Scotland) Regulations 2015 (S.S.I. 2015/243) . . . . . . . . . . 139–140
Energy Performance of Buildings (Scotland) Amendment (No 386) Planning (Listed Buildings and Conservation Areas)
Regulation 2015 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120 Regulations 1990 (SI 1990 No. 1519) . . . . . . . . . . . . . . . . . . . . . . 128, 130–131
Energy Performance of Buildings (Scotland) Amendment Regulations 2008 120 Procedure Regulations
Energy Performance of Buildings (Scotland) Amendment Regulation 7(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
Regulations 2012 (SSI 2012/190) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120 Regulation 19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 112
Energy Performance of Buildings (Scotland) Amendment Regulations 2013 120 Regulation 61 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Energy Performance of Buildings (Scotland) Regulations 2008 . . . . . . . . . . 120 Professional Services Regulations 2009 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 311
Environmental Impact Assessment Regulations . . . . . . . . . . . . . . . . . . . . . . . 137 Protection of Eyes Regulations 1974 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165
Environmental Information Regulations 2004 (SI 2004/3391) (EIR) . . . . . . . 61 Provision and Use of Work Equipment Regulations 1998 (PUWER) . . . . . . 169
Environmental Permitting (England and Wales) Regulations 2016 . . . . . . . . . 67 Recognition of Professional Qualifications Directive (2005/36/EC) . . . . . . . 376
Table of Statutes and Statutory Instruments 391

Registered Designs Regulations 2001SI 2001/3949 . . . . . . . . . . . . . . . . . . . . 365 Town and Country Planning (Environmental Impact Assessment)
Regulation (EC) No. 6/2002 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 365 Regulations 2017 (SI 2017 No. 571) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125
Regulatory Reform (Fire Safety) Order 2005 Town and Country Planning (Fees for Applications and Deemed
(RRFSO) . . . . . . . . . . . . . . . . . . . . . . . . . . 81, 82, 83, 85, 89, 99, 161–162, 303 Applications) (Scotland) Regulations 2004 (S.I. No. 219) . . . . . . . . . . . . . . 137
Article 37 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161 Town and Country Planning (Fees for Applications, Deemed Applications,
Regulatory Reform (Fire Safety) Order 2005 (SI 2005/1541) . . . . . . . . . . . . . 71 Requests and Site Visits) (England) Regulations 2012 (SI 2012 No. 2920)
Regulatory Reform (Housing Assistance) (England and Wales) (‘Fees Regulations 2012) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
Order 2002 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69 Town and Country Planning (General Permitted Development) (England)
Scheme for Construction Contracts (England and Wales) Order 2015 (SI 2015/596) (‘GPO 2015’) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
Regulations 1998/649 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 249 Town and Country Planning (General Permitted Development) (Scotland)
Scottish Arbitration Rule 26 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 289 Order 1992 (S.I. No. 223) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137
Town and Country Planning Appeals (Determination by Inspectors) Town and Country Planning (Hearings Procedure) (England) Rules 2000
(Inquiries Procedure) Rules 2000 (SI 2000 No 1625) . . . . . . . . . . . . . . . . . . 126 (SI 2000 No. 1626) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
Town and Country Planning (Appeals) (Scotland) Regulations 2013 Town and Country Planning (Hierarchy Development) (Scotland)
(S.S.I. 2013/156) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138 Regulations 2009 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137
Town and Country Planning (Appeals) (Written Representations Procedure) Town and Country Planning (Inquiries Procedure) Rules 2000
Regulations 2000 (SI 2000 No. 1628) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126 (SI 2000 No. 1624) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126
Town and Country Planning (Control of Advertisements) (England) Town and Country Planning (Schemes of Delegation and Local Review
Regulations 2007 (SI 2007 No. 783) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129 Procedure) (Scotland) Regulations 2013 (S.S.I. 2013/157) . . . . . . . . . . . . . . 138
Town and Country Planning (Determination of Appeals by Appointed Town and Country Planning (Use Classes) Order 1987 (SI 1987 No. 764)
Persons) (Prescribed Classes) Regulations 1997 (SI 1997 No. 420) . . . . . . . 126 (‘the 1987 Order) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
Town and Country Planning (Development Management Procedure) Town and Country Planning (Use Classes) (Scotland) Order 1997
(England) Order 2015 (SI 2015 No. 585) (‘DMP Order 2015’) . . . . . . . . . . 125 (S.I. No. 3061) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 136
Town and Country Planning (Development Management Procedure) Unfair Terms in Consumer Contracts Regulations 1999
(England) Order 2015 (SI 2015/595) (UTCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14–15, 325, 343
Article 18 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65 Water Environment (Water Framework Directive) (England and Wales)
Schedule 4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .65 Regulations 2017 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
Town and Country Planning (Development Management Procedure) Water Resources Act 1991, section 221 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
(Scotland) Regulations 2013 (S.S.I. 2013/155) (‘the DMPR’) . . . . . . . . . . . 137 Work at Height Regulations 2005 (WAHR), . . . . . . . . . . . . . . . . . . . . . .86, 166
Town and Country Planning (Development Management Procedure) Workplace (Health, Safety and Welfare) Regulations 1992
(Wales) Order 2012 (SI 2012/801) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65 (SI 1992/3004) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .71, 86, 167–168, 302
Town and Country Planning (Enforcement Notices and Appeals)
Regulations 2002 (SI 2002 No. 2682) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131
Table of Cases

A v B 2003 SLT 242 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .290 Balfour Beatty v Shepherd Construction [2009]


Abbott v Will Gannon & Smith Ltd [2005] BLR 195 . . . . . . . . . . . . . . . . . . .30 EWHC 2218 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .253, 254
Aberdeen City and Shire Strategic Development Planning Authority v Elsick Balfour Beatty-Ltd v Britannia Life Ltd 1997 SLT 10 . . . . . . . . . . . . . . . . . .231
Development Company Ltd [2017] P.T.S.R. 1413 . . . . . . . . . . . . . . . . .128 Balfour Beaty Construction v Serco [2004]
Acrecrest Ltd v WS Hattrell & Partners (1979) 252 EG 1107, 335 EWHC 3336 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .254
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .340 Baron Bernstein v Skyviews & General Ltd [1978] QB 479
Adam Architecture Ltd v Halsbury Homes Ltd [2017] EWCA Civ 1735 . . .244 at 488 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .36
Aedifice v Shar [2010] EWHC 2106 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .255 Barry D. Trentham Ltd v McNeil 1996 SLT 202 . . . . . . . . . . . . . . . . . . . . . .231
Aer Lingus PLC v Gildacroft Ltd [2006] 1 WLR 1173 . . . . . . . . . . . . . . . . .344 Bath and North East Somerset District Council v Mowlemplc [2004]
African Export-Import Bank v Shebah Exploration [2016] EWHC 311 BLR 153 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .199
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14 Baxall Securities Ltd v Sheard Walshaw Partnership [2002]
Alan Wibberley Building Ltd v Insley (April 1999), 37 BLR 100, . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .26
Alcoa Minerals of Jamaica Inc v Herbert Broderick [2002] Baxhall Securities Ltd v Sheard Walshaw Partnership [2002]
1 AC 371 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .339 PNLR 564 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .333
Alderson v Beetham Organisation Ltd [2003] 1 WLR 1686 . . . . . . . . . . . . .329 BDW Trading Ltd v Integral Geotechnique (Wales) Ltd [2018]
The Alexander Devine Children’s Cancer Trust v Millgate Developments Ltd. and EWHC 1915 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .334
Housing Solutions Ltd. [2018] EWCA Civ 2679 . . . . . . . . . . . . . . . .36, 40 Beauford Developments Ltd v Gilbert-Ash (Northern Ireland) Ltd (1998)
Alexander v Mecouris [1979] 1 WLR 1270 . . . . . . . . . . . . . . . . . . . . . . . . . . .26 88 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .213
Alexander v Mercouris [1979] 1 WLR 1279 . . . . . . . . . . . . . . . . . . . . . . . . .329 Beigtheil and Young v Stewart [1900] TLR 177 . . . . . . . . . . . . . . . . . . . . . .329
Alfred McAlpine Ltd v Panatown Ltd [1998] 88 BLR 67 . . . . . . . . . . . . . . .234 Bell S Trustee v Coatbridge Tinplate Co (1886) 14 R (HL) 246 . . . . . . . . . .307
Alstom Signalling Ltd v Jarvis Facilities Ltd . . . . . . . . . . . . . . . . . . . . . . . . .243 Bellefield Computer Services Ltd v E Turner & Sons Ltd [2000]
Amalgamated Investment and Property Co. Ltd v John Walker and Sons Ltd BLR 96 per Schieman LJ at 102 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .25
[1976] 3 all ER 509 SA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .130 Bellefield Computer Services Ltd v E Turner & Sons Ltd [2000]
Ambler v Gordon [1905] 1 KB 417, 40 BLR 97 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24, 333
Amec Building Ltd v Cadmus Investments Co Ltd [1996] 51 Con LR 105 at 125- Beumer v Vinci [2016] EWHC 2283 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .255
128 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .207 Bevan Investments Ltd v Blackball and Struthers (No. 2) [1973] 2
Amec Civil Engineering Ltd v Secretary of State for Transport [2005] CILL 2288 NZLR 45 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .336
224 Birse Construction Ltd v Haiste Ltd [1996] 1 WLR 675 . . . . . . . . . . . . . . . . 341
Amec Civil Engineering v Secretary of State for Transport [2004] Blair v Osborne & Tompkins (1971 2 QB 78) . . . . . . . . . . . . . . . . . . . . . . . . 363
EWHC 2339 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .251 Blue Circle Industries PLC v Holland Dredging Co (UK) Ltd [1987] 37
Amec Mining Ltd v The Scottish Coal Company Ltd, 6 August 2003, BLR 40 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207
unreported . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .231 Blyth & Blyth Ltd v Carillion Construction Ltd (2001) 79 ConLR 142
Amec v Whitefriars [2004] EWCA Civ 1418 . . . . . . . . . . . . . . . . . . . . . . . . .255 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 331
Ampleforth Abbey Trust v Turner & Townsend Project Management Ltd [2012] Blyth v Birmingham Waterworks Company [1856] 11 Ex 781 . . . . . . . . . . . . 22
EWHC 2137 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .336 BN Rendering Ltd v Everwarm Ltd [2018] CSOH 45 . . . . . . . . . . . . . . . . . . 291
Anchor Brewhouse Developments Ltd v Berkley House (Dockland Developments) Board of Governors of the Hospitals for Sick Children v
Ltd [1987] 2 EGLR 173 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .36 McLaughlin and Harvey plc (1987) 19 ConLR 25 . . . . . . . . . . . . . . . . 339
Andrews v Schooling [1991] 1 WLR 783 . . . . . . . . . . . . . . . . . . . . . . . . . . . .329 Board of Trustees of National Museums and Galleries on Merseyside v
Anglian Water Services v Crawshaw Robins & Co [2001] BLR 173 . . . .27, 29 AEW Architects & Designers Ltd [2013] EWHC 2403 . . . . . . . . . . . . . 344
Anns v Merton . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24 The Board of Trustees of the Tate Gallery v Duffy Construction Ltd
Anns v Merton (1978) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .81 [2007] BLR 216 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210
Anns v Merton London Borough Council [1978] AC 728 . . . . . . . . . . . .22, 234 Bole v Huntsbuild Ltd [2009] EWHC 483 . . . . . . . . . . . . . . . . . . . . . . . . . . . 329
Arcadis v AMEC [2019] BLR 27 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12 Bolitho v City & Hackney HA [1998] AC 232, HL . . . . . . . . . . . . . . . . . . . . . 22
Architype Project Ltd v Dewhurst MacFarlane & Partners (2003) Bolton v Mahadeva [1972] 1 WLR 1009 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
96 ConLR 35 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .333 Bouygues (UK) Ltd v Dahl-Jensen (UK) Ltd [2000] BLR 522 . . . . . . . . . . . 249
Armitage v Palmer (1959) 173 EG 91 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .335 Bouygues Offshore (UK) Ltd v Dahl-Jensen (UK) Ltd [2002] BLR 522 . . . . 291
Arnold v Britton [2015] UKSC 36 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12 Braganza v BP Shipping [2015] UKSC 17 . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Arscott v Coal Authority [2005] Env LR 6, CA . . . . . . . . . . . . . . . . . . . . . . . .27 Bramali & Ogden Ltd V Sheffield City Council (1985) 29 BLR 73, 194 . . . 195
Associated British Ports v Hydro Soil Services NV [2006] EWHC 1187 . . .328 Bremer Handelgesellschaft mbH v Vanden AVenne Izegem NV [1978]
Attorney General v Chambers [1854] 4 De GM & G 206 at 218 . . . . . . . . . .38 2 Lloyd’s Rep, 113 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 223
Attorney General v Laird [1925] 1 Ch 318 at p. 329 . . . . . . . . . . . . . . . . . . .69 Brian Walker Partnership PLC v HOK International Ltd [2006]
Aveat Heating Ltd v Jerram Falkus Construction Ltd [2007] PNLR 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 343
EWHC 131 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .250 Brickfield Properties Ltd v Newton [1971] 1 WLR 862 . . . . . . . . . . . . . . . . 338
Aveat v Jerram Falkus [2007] EWHC 131, 252 Britain’s Heritage v Secretary of State and Others [the Peter
AXA Insurance UK Plc v Cunningham Lindsey UK [2007] Paulumbo case] [1991] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130
EWHC 3023 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .339 British Fermentation Products Ltd v Compair Reavell Ltd . . . . . . . . . . . . . . . 14
B L Holdings Ltd v Robert J. Wood & Partners (1979) 10 BLR 48 British Horseracing Board v William Hill Organisation Ltd
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .335 (Case C-2003/002) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358
BAA v Secretary of State for Scotland 1979 SC 200 . . . . . . . . . . . . . . . . . . .139 Broster v Galliard [2011] EWHC 1722 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . 24
Babcock Marine (Clyde) Ltd v HS Barrier Coatings Ltd [2019] Bryant & Son Ltd v Birmingham Hospital Saturday Fund [1938] 1
EWHC 1,659 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .231 All ER 503 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185
Balfour Beatty Building Ltd v Chestermount Properties Ltd (1993) Burchell v Bullard [2005] EWCA Civ 358 . . . . . . . . . . . . . . . . . . . . . . . . . . 284
62 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .191 Burgess v Levonjarn [2017] EWCA 254 . . . . . . . . . . . . . . . . . . . . . . . . . . . . .26
Balfour Beatty Construction (Scotland) Ltd v Scottish Power plc (1994) Burgess v Purchase & Sons (Farms) Ltd [1983] Ch 216 . . . . . . . . . . . . . . . . 42
71 BLR 20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .340 Butler Machine Tool Co Ltd v Ex-Cell-O Corporation (England) Ltd [1979]
Balfour Beatty v Lamberth BC [2002] BLR 288 . . . . . . . . . . . . . . . . . . . . . .253 1 WLR 401 at 405 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

392
Table of Cases 393

Byrne v Van Tienhoven [1850] 5 CPD 344 . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 Darlington Borough Council v Wiltshier Northern Ltd [1995] 1
C & B Scene Concept Design Ltd v Isobars Ltd [2002] 82 Con LR 154 . . . 291 WLR 68 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234
C&B Scene Concept v Isobars [2002] EWCA Civ 46 . . . . . . . . . . . . . . . . . . 254 David McLean Housing Ltd v Swansea Housing Association Ltd
Cable & Wireless plc v Ibm Uk Ltd [2002] EWHC 2059 . . . . . . . . . . . . . . . 284 [2002] BLR 125 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 251
Cala Homes (South) Ltd v Alfred McAlpine Homes East Ltd (1995) Department of National Heritage v Steensen Varming Mulcahy
FSR 818, 360 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362 [1998] ConLR 33 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 336
Cala Homes v McAlpine . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 364 Department of the Environment v Thomas Bates & Sons Ltd [1991]
Caledonian Modular Ltd v Mar City Developments [2015] 1 AC 499 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
EWHC 1855 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202 Derry v Peek [1889] 14 App Cas 337 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 328
Cambridge Water v Eastern Counties Leather plc [1994] 2 AC 264 . . . . . . . 28 Dodd Properties (Kent) Ltd v Canterbury City Council [1980]
Campbell v Edwards [1976] 1 WLR 403 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 1 WLR 433 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 339
Cantillon Ltd v Urvasco Ltd [2008] EWHC 282 (TCC) . . . . . . . . . . . . . . . . 255 Donoghue v Stevenson, 24 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Caparo v Dickman [1990] 2 AC 605 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 Donoghue v Stevenson [1932] AC 562 at 580, 21 . . . . . . . . . . . . . . . . . . . . . 234
Cardy v Taylor (1994) 38 ConLR . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 335 Dorset Yacht Co Ltd v Home Office [1970] AC 1004 . . . . . . . . . . . . . . . . . . . 22
Carillion Construction Ltd v Devonport [2006] BLR 15, 249 Dubai Aluminium Co Ltd v Salaam [2003] 2 AC 366 . . . . . . . . . . . . . . . . . . 341
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .254, 255 Dunlop v Selfridge [1951] AC 847 855 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Carillion JM Ltd v PHI Group Ltd [2011] EWHC 1379 . . . . . . . . . . . . . . . . 343 Dwyer v Westminster City Council ([2014] EWCA Civ 153) . . . . . . . . . . . . . 40
Carillion v Devonport [2005] EWHC 778 . . . . . . . . . . . . . . . . . . . . . . . . . . . 254 Eames London Estates Ltd v North Hertfordshire DC (1980)
Carleton (Earl of Malmesbury) v Strutt & Parker (a partnership) 259 EG 491 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 335
[2008] EWHC 424 (QB) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 285 East Dorset District Council v Eaglebeam [2007] Env LR D9 . . . . . . . . . . . . 27
Carlill v Varbolic Smoke Ball Company [1892] 2 QB 484, [1893] East Ham Corporation v Bernard Sunley & Sons Ltd [1966]
1 QB 256 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 AC 406 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 337
Carroll v Scottish Borders Council [2015] CSIH 73 . . . . . . . . . . . . . . . . . . . 138 Eastgate Group Ltd v Lindsay Morgan Group Inc [2002] 1
Castle Inns (Stirling) Ltd, Petitioner v Clark Contracts Ltd WLR 642 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 341
2006 SCLR 663 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 291 Eckersley v Binnie & Partners (1988) 18 ConLR 1, 332 . . . . . . . . . . . . . . . 336
Castle Inns (Stirling) Ltd v Clark Contracts Ltd 2006 S.C.L.R. 663 . . . . . . 231 Edgington v Fitzmaurice [1885] 29 ChD 459 at 483 . . . . . . . . . . . . . . . . . . . . 15
Castle Inns (Stirling) Ltd v Clark Contracts Ltd, infra . . . . . . . . . . . . . . . . . 289 Edwards v National Coal Board (1949) 1 All ER 743 (CA) . . . . . . . . . . . . . 160
Catlin Estates Ltd v Carter Jonas (A Firm) [2006] PNLR 15 . . . . . . . . . . . . 329 Elitestone Ltd v Morris [1997] 1 W.L.R. 687 . . . . . . . . . . . . . . . . . . . . . . . . . 41
Cavendish Square Holding VB v Tala El Makdessi [2015] UKSC 67 . . . . . . 194 Elsick Development Company Limited v Aberdeen City and
Cawoods v Croudace [1978] 2 Lloyd’s Reports 55 . . . . . . . . . . . . . . . . . . . . 205 Shire Strategic Development Planning Authority [2017]
CFW Architects (a firm) v Cowlin Construction Ltd (2006) UKSC 66 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139
ConLR 116 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 330 Enviroflow v Redhill [2017] EWHC 2159 . . . . . . . . . . . . . . . . . . . . . . . . . . . 254
Chabot and Davies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 364 Equitable Debenture Assets Corp Ltd v William Moss Group Ltd (1984)
Chabot v Davies [1936] 3 All ER 221 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 361 2 ConLR 26 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 337
Charles Church Development plc v Cronin [1990] 17 FSR . . . . . . . . . . . . . 364 Equitable Debenture Assets Corp Ltd v William Moss Group Ltd (1984)
Chesham Properties Ltd v Bucknall Austin Project Management 2 ConLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 344
Services Ltd [1996] 82 BLR 92 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 329 F. G. Minter v Welsh HTSO (1980) 13 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . 205
Chesham Properties Ltd v Bucknall Austin Project Management Fairclough Scotland Ltd v Jamaica Street Ltd, 30 April 1992 . . . . . . . . . . . 231
Services Ltd (1996) 82 BLR 92 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 338 Fairclough v Vale of Belvoir Superstore [1991] 56 BLR 74 . . . . . . . . . . . . . 205
Chesterton RDC v Ralph Thompson Ltd [1947] KB 300 . . . . . . . . . . . . . . . . . 84 Fairweather v Asden Securities [1980] 12 BLR 40 . . . . . . . . . . . . . . . . . . . . 194
City Inn Ltd v Shepherd Construction Ltd . . . . . . . . . . . . . . . . . . . . . . . . . . . 290 Farm Assist Limited (in liquidation) v The Secretary of State for the
City Inn Ltd v Shepherd Construction Ltd 2002 SLT 781 . . . . . . . . . . . . . . . 290 Environment, Food and Rural Affairs (No. 2) [2009]
City of Glasgow DC v Secretary of State for Scotland 1993 SLT 268 . . . . . 139 EWHC 1102 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 284
City of London Corporation v Secretary of State for the Environment and Farmers Build Ltd v Carier Bulk Materials Handling Ltd [1999]
Watting Street Properties Ltd (1971) 23 P and CR 169 . . . . . . . . . . . . . 124 RPC 461 (CA) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 365
Clay v A.J. Crump & Sons Ltd [1964] 1 QB 533 . . . . . . . . . . . . . . . . . . . . . 332 Financial Services Compensation Scheme Ltd v Larnell (Insurances)
Claydon Architectural Metalwork Ltd v DJ Higgins & Sons Ltd [1997] Ch D Ltd [2006] PNLR 13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 341
16/1/97 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 364 Fiona Trust v Privalov [2007] 4 All ER 951 . . . . . . . . . . . . . . . . . . . . . . . . . 213
Clayton v Woodman & Sons (Builders) Ltd [1962] 1 WLR 585 . . . . . . . . . . 332 Fiona Trust v Privalov [2007] UKHL 40 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 251
Clydesdale Bank pic v Messrs MacLay Collier & Partners Fisher v Winch [1939] 1 KB 666 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
1998 SLT 1102 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 290 Fitzgerald v Lane [1989] AC 328 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 343
Columbus Co Ltd v Clowes [1903] 1 KB 244 . . . . . . . . . . . . . . . . . . . . . . . . 335 Flitcroft’s Case (1882) 21 Ch D 519 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 307
Commissioner for Main Roads v Reed & Stuart Pty [1974] 12 Florida Hotels Pty Ltd v Mayo [1965] 113 CLR 588 . . . . . . . . . . . . . . . . . . 337
BLR 55 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 199 Forskirings-aktieselskapet Vesta v Butcher [1989] AC 852 . . . . . . . . . . . . . . 340
Commissioner for Main Roads v Reed & Smart Pty [1980] 12 Foster v Warblington UDC [1906] 1 KB 648 . . . . . . . . . . . . . . . . . . . . . . . . . 67
BLR 55 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 207 Freeborn v De Almeida Marcal [2019] EWHC 454 (TCC) . . . . . . . . . . . . . . . 23
Consarc Design Ltd v Hutch Investments Ltd [2002] PNLR 712 . . . . .332, 337 FSHC Group Holdings Limited v GLAS Trust Corporation Limited
Construction Centre Group Ltd v Highland Council 2002 SLT 1274, . . . . . 290 [2019] EWCA Civ 1361 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 199
Construction Centre Group Ltd v Highland Council 2003 SLT 623, . . . . . . 291 Fytche v Wincanton Logistics plc [2004] UKHL 31 . . . . . . . . . . . . . . . . . . . 168
Consultants Group International v John Worman Ltd (1985) 9 Gable House Estates v The Halpern Partnership (1995) ConLR . . . . . . . . . 335
ConLR 46 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 328 Galliford Try Building v Estura [2015] EWHC 412 (TCC) . . . . . . . . . . . . . . 245
Cooperative Group Ltd v John Allen Associates Ltd [2010] Galliford Try Infrastructure Ltd v Mott McDonald Ltd [2008]
EWHC 2300 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 339 EWHC 1570 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .26, 335
Co-operative Retail Services Ltd v Taylor Young Partnership Galoo v Bright Grahame Murray [1994] 1 WLR 1360 . . . . . . . . . . . . . . . . . . 23
& Others [2002] BLR 272 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210 George Fischer Holding Ltd v Multi Design Consultants Ltd (1998)
Co-operative Retail Services v Taylor Young Partnership Ltd [2002] 1 61 Con LR 85 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .25, 336, 337, 338, 339
WLR 1419 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342 George Hawkins v Chrysler (UK) and Burne Associates (1986) 38 BLR 36 328
Corfield v Grant (1992) 29 ConLR 58 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 337 Glasgow Airport Limited v Messrs Kirkman & Bradford [2007]
Costain Ltd v Strathclyde Builders Ltd 2004 SLT 102 . . . . . . . . . . . . . . . . . 290 CSOH 52 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 343
Costain v Charles Haswell & Partners [2009] . . . . . . . . . . . . . . . . . . . . . . . 313 Glencot v Barrett [2001] BLR 207 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 255
Cotton v Wallis [1955] 1 WLR 1168 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185 Gloucestershire Health Authority v Torpy [1997] CILL 1281 . . . . . . . . . . . . . 22
Crown Estates Commissioners v John Mowlem & Co Ltd [1994] 70 Greater Nottingham Co-operative Society Ltd v Cementation Piping &
BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 338 Foundations Ltd [1989] QB 71 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 331
Crown Estates v John Mowlem & Co. Ltd (1994) 70 B.L.R. 1 (CA) . . . . . . 185 Greaves & Co (Contractors) Ltd v Baynham Meikle & Partners
CRS case . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342 [1975] 1 WLR 1095 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 327
Cubitt Building Interiors Ltd v Fleetglade Ltd [2006] EWHC 3413, Grove Developments v S&T [2017] EWHC 123 (TCC) [2018]
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .253, 254 EWCA Civ 2448 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 244
D & F Estates Ltd and Others v The Church Commissioners of Hadley v Baxendale (1859) 9 Ex. 3421 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 205
England and Others [1988] 49 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . 234 Hale v Jennings Brothers [1938] 1 All ER 579 . . . . . . . . . . . . . . . . . . . . . . . . 28
Dalgleish v Bromley Corporation (1953) 161 EG 738 . . . . . . . . . . . . . . . . . 335 Halsbury Homes Ltd v Adam Architecture Ltd [2016] B.L.R. 419 . . . . . . . . 289
Halsbury’s Laws of England [4th ed], vol. 4, paragraph 831 . . . . . . . . . . . . . 37
394 Table of Cases

Halsey v Milton Keynes NHS Trust and Steel v Joy and Halliday Khorasandjian v Bush [1993] QB 727 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
[2004] EWCA (Civ) 576 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 284 Kirkintilloch Equitable Co-operative Society Ltd v Livingston and others
Harding v Paice [2015] EWCA Civ 1231 . . . . . . . . . . . . . . . . . . . . . . . . . . . 245 1972 SLT 154 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 305
Harrison v Shepherd Homes Ltd [2011] EWHC 1811 26 . . . . . . . . . . . . . . . 329 Knight v Rochdale Healthcare NHS Trust [2004] 1 WLR 371 . . . . . . . . . . . 344
Hart Investments Ltd v Fidler [2007] EWHC 1058 (TCC) . . . . . . . . . . . . . . . 22 Koonjul v Thameslink Healthcare Services NHS Trust (CA)
Hedley Byrne & Co. Ltd v Heller & Partners [1963] AC 465 . . . . . . . . 23–24 [2000] PIQR P123 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 169
Hedley Byrne & Co v Heller and Partners [1964] AC 465 . . . . . . . . . . . . . . 234 Lam v Brennan [1997] 3 PLR 22 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
Henderson v Merrett . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 Lanes v Galliford Try [2011] EWCA Civ 1617 . . . . . . . . . . . . . . . . . . . . . . . 255
Henderson v Merrett Syndicates Ltd [1994] 3WLR 761 . . . . . . . . . . . . . . . . . 25 Langstane Housing Association Limited v Riverside
Henderson v Merrett Syndicates Ltd [1995] 2 AC 145 . . . . . . . . . .22, 234, 330 Construction Limited (& Others) [2009] CSOH 52 . . . . . . . . . . . . . . . . 343
Henry Boot Construction Ltd v Central Lancashire New Town Development Leaky v National Trust [1980] QB 485 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Corporation (1981) 15 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . .185, 192 Lee v Chartered Properties [2010] EWHC 1540 . . . . . . . . . . . . . . . . . . . . . . 253
Henry Boot Ltd v Alstom Combined Cycles Ltd [2005] 1 WLR 3850 . . . . . . 202 Lejonvarn v Burgess [2017] EWCA Civ 254 . . . . . . . . . . . . . . . . . . . . . . . . . 332
Henry Boot Ltd v The Croydon Hotel and Leisure Co Ltd [1985] Lidl Properties v Clarke Bond Partnership [1998] Env LR 622 . . . . . . . . . . 334
36 BLR 41 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 205 Lidl v RG Carter [2012] EWHC 3138 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 255
Hiap Hong & Co Pte Ltd v Hong Huat Development Co (Pte) Ltd [2001] Linden Garden Trust Ltd v Lenesta Sludge Disposals Ltd
17 Const LJ 530 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 184 [1993] 3 All ER 417 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210
Hill Samuel Bank v Frederick Brand Partnership (1993) Linklaters v McAlpine [2010] EWHC 1145 (TCC) . . . . . . . . . . . . . . . . . . . . . 24
45 ConLR 141 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 340 Linnett v Halliswells LLP [2009] EWHC 319 . . . . . . . . . . . . . . . . . . . . . . . . 254
Hillcrest Homes v Beresford [2014] EWHC 280 . . . . . . . . . . . . . . . . . . . . . . 251 LMS International Ltd v Styrene Packaging & Insulation Ltd [2005]
Hoenig v Isaacs [1952] 2 All ER 176 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18 EWHC 2065 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Holland Hannen and Cubitts (Northern) Ltd v Welsh Health London Borough of Merton v Leach [1985] 32 BLR 51 . . . . . . . . . . . .185, 205
Technical Services Organisation (1985) 35 BLR 1 . . . . . . . . . . . . . . . . 336 London Borough of Merton v Leach (Stanley Hugh) Ltd (1985)
Hollywood Silver Fox Farm Ltd v Emmett [1936] 2 KB 468 . . . . . . . . . . . . . 27 32 BLR 51 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 339
Holt v Payne Skillington [1995] 77 BLR 51 . . . . . . . . . . . . . . . . . . . . . . . . . . 22 London Borough of Merton v Lowe (1981) 18 BLR 130 . . . . . . . . . . . . . . . . 338
Homer Burgess Ltd v Chirex (Annan) Ltd . . . . . . . . . . . . . . . . . . . . . . . . . . . 291 Loretto Housing Association Ltd v Cruden Building & Renewals Ltd [2019]
How Engineering Services Ltd v Lindner Ceilings Ltd [1999] CSOH 78 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 345
64 Con LR 67 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 205 Lubenham Fidelities & Investment Co Ltd v South Pembrokeshire District
Hughes v Lord Advocate [1963] AC 837 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23 Council [1986] 6 Con LR 85 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .29
Hunter v Canary Wharf Ltd [1997] AC 655, 27 . . . . . . . . . . . . . . . . . . . . . . .36 Lubenham Fidelities Investment Co. Ltd v South Pembrokeshire DC (1986)
Hunter v Fitzroy Robinson [1978] FSR 167 . . . . . . . . . . . . . . . . . . . . . . . . . 364 6 ConLR 85 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 335
Hurstwood Developments Ltd v Motor and General & Lynn Shellfish Ltd v Loose [2016] UKSC 14 . . . . . . . . . . . . . . . . . . . . . . . . . . 38
Andersley & Co Insurance Services Ltd [2001] . . . . . . . . . . . . . . . . . . . 342 Machin v Adams (1997) 84 BLR 79 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 334
HWNevill [Sunblest] Limited v Wm Press & Son Limited [1982] MacJordan Construction Ltd v Brookmount Erostin Ltd [1991]
20 BLR 78 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 194 53 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 204
Hyde v Wrench [1840] 3 Beav 334 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 Madden v Quirk [1989] 1 WLR 702 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 343
Ian McGlinn v Waltham Forest Contractors Ltd (2007) 111 Marcic v Thames Water Utilities Ltd [2002] 2 All ER 55 . . . . . . . . . . . . . . . . 27
ConLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 337 Marks & Spencer plc v BNP Parisbas Securities [2016] AC 742 . . . . . . . . . . 13
IBA v EMI and BICC (1980) 14 BLR 1 at 37 . . . . . . . . . . . . . . . . . . . . . . . . . 23 McAlpine v Property and Land Contractors Ltd [1995]
IBA v EMI and BICC Construction (1980) 14 BLR 1 . . . . . . . . . . . . . . . . . . 328 76 BLR 59 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 205
Imperial Castelli: SpA v Cola Holdings [2002] C.I.L.L. 1904 . . . . . . . . . . . 185 McGlinn v Waltham Contractors Ltd [2007] 111 Con LR 1 . . . . . . . . . . . . . 385
Industry Commercial Properties v South Bedfordshire DC McGlinn v Waltham Contractors Ltd [2007] EWHC 149 . . . . . . . . . . . . . . . 339
[1985] 1 All ER 787 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 335 McGlinn v Waltham Forest Contractors Ltd (2007) 111 ConLR . . . . . . . . . . 339
Infopaq International A/S v Danske (2012) EUECJ C-302/10 . . . . . . . . . . . 359 McKenna v British Aluminum Ltd, The Times,
Interlego AG v Tyco Industries Inc [1989] AC 217 . . . . . . . . . . . . . . . . . . . . 359 25 April 2002, 27 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
International Tea Stores Co. v Hobbs [1903] 2 Ch 165) . . . . . . . . . . . . . . . . . 39 McKenzie v Potts (1997) 50 ConLR 40 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 341
Interserve Industrial v Cleveland Bridge [2006] EWGC 741 . . . . . . . . . . . . 254 Mears Limited v Costplan [2019] EWCA Civ 502 . . . . . . . . . . . . . . . . . . . . 194
Inverclyde District Council v Inverkip Building Co. Ltd Meikle v Maufe, 359 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 364
1983 SLT 563 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137 Meikle v Maufe [1941] 3 All ER 144, 358 . . . . . . . . . . . . . . . . . . . . . . . . . . . 362
ISG Construction v Seevic College [2014] EWHC 4007 (TCC) . . . . . . . . . . 245 Merrett v Babb [2001] 3 WLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
ISG v Castletech [2015] EWHC 1443 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 251 Michael Hyde & Associated Ltd v JD Williams & Co Ltd [2001]
J Jarvis & Sons Ltd v Castle Wharf Developments Ltd [2001] PNLR 233 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 336
EWCA Civ 19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 335 Michael John Construction Ltd v Golledge [2006] EWHC 71 . . . . . . . . . . . 251
J Jarvis & Sons Ltd v Castle Wharf Developments Ltd [2001] Michael v Chief Constable of South Wales [2015] AC 1732 . . . . . . . . . . . . . . 22
Loyd’s Rep PN 308 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 Midland Bank Trust Co. Ltd v Green [1981] AC 513 . . . . . . . . . . . . . . . . . . . 35
J M Hill & Sons Ltd v London Borough of Camden (1982) Midland Bank Trust Company v Green [1980] Ch 590 . . . . . . . . . . . . . . . . . . 10
18 BLR 31, CA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211 Midland Expressway Ltd v Carillion Construction Ltd [2006]
J Sainsbury plc v Broadway Malyan (a firm) [1999] BLR 325 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 253
PNLR 286 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 341 Midlothian Council v Bracewell Stirling . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232
Jacobs v Morton and Partners [1995] 72 BLR 92 . . . . . . . . . . . . . . . . . . . . 333 Midlothian Council v Bracewell Stirling Architects [2018]
Jacobs v Skanska [2017] EWHC 2395 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 253 CSIH 21 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 344
Jarndyce v Jarndyce (Bleak House) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6 Midlothian Council v Raeburn Drilling and Geotechniccal Limited [2019] CSOH
John Barker Construction Ltd v London Portman Hotel Ltd 29 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 345
(1996) 83 BLR 35 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 338 Ministry of Defence v Scott Wilson Kirkpatrick (2000) BLR 20 . . . . . . . . . . 339
John Jarvis Limited v Rockdale Housing Association Ltd (1986) Mirant-Asia Pacific Ltd v Ove Arup & Partners International Ltd [2005] PNLR
36 BLR 48, CA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211 10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 332
John Jarvis Ltd v Rockdale Housing Association Ltd (1986) Moores v Yakeley Associates Ltd [2000] 3WLUK 644 . . . . . . . . . . . . . . . . . . 14
36 BLR 48 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212 Moores v Yakeley Associates Ltd (1998) 62 ConLR 76, 332 . . . . . . . . . . . . . 342
John Laing Construction Ltd v County and District Properties Morse v Barrett (Leeds) Ltd (1993) 9 Const LJ . . . . . . . . . . . . . . . . . . . . . . . 25
[1982] 23 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208 Mowlem (Scotland) Ltd v Inverclyde Council, 1 October 2003, unreported) 289
John Sisk v Duro Felguera [2016] EWHC 81 . . . . . . . . . . . . . . . . . . . . . . . . 255 MT Hojgaard v E.ON Climate and Renewables UK Robin Rigg East Ltd [2017]
Junior Books v Weitchi & Co. [1983] 1 AC 520 . . . . . . . . . . . . . . . . . . . . . . . 25 UKSC 59 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 328
Kane v New Forest District Council [2001] EWCA Civ 878 . . . . . . . . . . . . . 62 Multiplex Construction v Honeywell Control Systems [2007] EWHC 447 (TCC)
Kensington, Chelsea and Westminster AHA v Wettern Composites Ltd [1985] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 223
1 AER 346 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 337 Murphy v Brentwood . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25, 26, 27, 29
Kensington and Chelsea and Westminster AHA v Wettern Murphy v Brentwood District Council [1990] 2 All ER 908 . . . . . . . . . . . . . . 62
Composites Ltd (1984) 1 Con LR 114 . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 Murphy v Brentwood District Council [1991] 1 AC 398, . . . . . . . . . . . .24, 234
Kensington and Chelsea and Westminster Area Authority v Murphy v Brentwood District Council [1991] AC 398 . . . . . . . . . . . . . . . . . 329
Wettern Composites (1986) 31 BLR 57 . . . . . . . . . . . . . . . . . . . . . . . . . 196 Murphy v Brentwood District Council (1991) . . . . . . . . . . . . . . . . . . . . . . . . . 81
Kent County Council v Kingsway Investments (Kent) Ltd National Justice Compania Naviera SA v The Prudential Assurance Company
[1971] AC 72 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128 Ltd (the Ikarian Reefer) [1993] 2 Lloyd’s Reports 68 (QBD) . . . . . . . . 273
Table of Cases 395

New Islington and Hackney Housing Association Ltd v Pollard Thomas & Prudential Assurance v Waterloo Real Estate [1999] . . . . . . . . . . . . . . . . . . . 37
Edwards Ltd [2001] PNLR 515 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 338 Punjab National Bank v de Boinville [1992] 1 WLR 1138 . . . . . . . . . . . . . . . 25
Newbury DC v Secretary of State for the Environment [1978] 1 W.L.R. 1241, Pye v Secretary of State for the Environment [1999] PLCR 28 . . . . . . . . . . 139
1248 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128 Pyx Granite Co. Ltd v Ministry of Housing and Local Government
The Newspaper Licensing Agency v Meltwater Holding BV (2013) EWCA Civ [1958] 1 QB 554, CA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128
890 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 359 R (Gresty) v Knowsley MBC (2012) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
NH International (Caribbean) Ltd v National Insurance Property Development R A Lister & Co Ltd v E G Thomson (Shipping) Ltd (No. 2)
Company Ltd (Trinidad and Tobago), [2015] [1987] 3 All ER 1032 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 341
UKPC 37 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 223 R B Burden Ltd v Swansea Corporation compliance; [1957]
Nitrigin Eireann Teoranta v Inco Alloys [1992] 1 All 854 . . . . . . . . . . . . . . . 24 3 All ER 243 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208
Nitrigin Eireann Teoranta v Inco Alloys Ltd [1992] 1 R v Dilwyn Roberts Penseiri/Architects Ltd (2012) . . . . . . . . . . . . . . . . . . . . 166
WLR 498 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 333 R v East Sussex County Council, ex p. Reprotech (Pebsham) Ltd
North Lanarkshire Council v Stewart & Shields Ltd . . . . . . . . . . . . . . . . . . . 289 [2002] UKHL 8; [2003] 1 WLR 348 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
Northern Developments v J&J Nichol [2000] BLR 3 . . . . . . . . . . . . . . . . . . 254 R v East Sussex County Council ex p. Reprotech (Pebsham) Ltd
Northern Regional Health Authority v Derek Crouch construction [2002] UKLR 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125
Co Ltd [1984] QB 644 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213 R v Goldstein [2006] 1 AC 459 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
Northumbrian Water Limited v Sir Robert MacAlpine Limited R v Local Commissioner for Administration in the North and North East
[2014] EWCA Civ 685 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28 England, exp. Liverpool City Council (2000) 2 LGLR 603 . . . . . . . . . . . 62
Nottinghamshire Healthcare National Health Service Trust v News Group R v Rochdale MBC ex p. Tew [1999] 3 PLR 74 . . . . . . . . . . . . . . . . . . . . . . 127
Newspapers Ltd [2002] EWHC 109 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 364 R v Secretary of State for the Environment, exp. London Borough of Hillingdon
NRAM Ltd v Steel [2018] 1 WLR 1190 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 [1986] 2 All ER 273 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
Nye Saunders v Bristow [1987] 37 BLR 92 . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 R v Waltham Forest London Borough Council, ex p. Baxter [1988]
Nye Saunders v Bristow [1987] 37 BLR 92 per Stephen Brown 1 QB 419 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
LJ at 103 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 Radius Housing Association Limited v JNP Architects (& Others)
Ocular Sciences Ltd v Aspect Vision Care Ltd [1997] RPC 289 . . . . . . . . . . 365 [2018] NIQB 57 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 343
Offer-Hoar v Larkstore Ltd [2006] PNLR 17 . . . . . . . . . . . . . . . . . . . . . . . . 334 Ramac Construction v Lesser [1975] 2 Lloyd’s Reports 430 . . . . . . . . . . . . 193
Oldschool v Gleeson (Construction) Ltd (1976) 4 BLR 103 . . . . . . . . . . . . . 334 Raymoyle Developments Limited v Scottish Borders Council [2020]
O’Reilly v Mackman [1983] 2 AC 287 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 291 CSIH 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 137
Ossory Road (Skelmersdale) Limited v Balrou Beatty Building Limited Redrow Homes Ltd v Bett Brothers Plc [1999] 1 AC 197 . . . . . . . . . . . . . . . 364
[1993] CILL 882 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 209 Regency Villas Title Ltd v Diamond Resorts (Europe) Ltd
Ove Arup & Partners International Ltd v Mirah Asia-Pacific Construction (Hong [2018] UKSC 57 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
Kong) (No. 2) [2004] Rendlesham Estates Plc v Barr [2014] EWHC 3968 . . . . . . . . . . . . . . . . . . . 329
EWHC 1750 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 Re-Source America International Ltd v Platt Site Services and Barkin
Ove Arup & Patners International Ltd v Mirant Asia Pacific Construction (Hong Construction Ltd [2004] EWCA (Civ) 665 . . . . . . . . . . . . . . . . . . . . . . 343
Kong) Ltd (No. 2) (2006) BLR 187 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 335 R(Harvey) v Ledbury Town Council [2018] EWHC 1151 (Admin) . . . . . . . . . 62
Oxford Architects v Cheltenham Ladies’ College [2006] Richard Roberts & Holdings Ltd v Douglas Smith Stimson Partnership
EWHC 3156 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 (1988) 46 BLR 50 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 336
Oxford University Fixed Assets Ltd v Architects Design Partnership (1999) Rickarby v New Forest RDC [1910] 26 TLR 586 . . . . . . . . . . . . . . . . . . . . . . 67
64 ConLR 12 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342 Rickards v Kerrier District Council [1987] CILL 345 . . . . . . . . . . . . . . . . . . . 81
Oxford University Press v John Stedman Design Group (1990) 34 ConLR 1 Ritchie Brothers (PWC) Ltd v David Philip (Commercials Ltd)
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 344 2005 1 SC 384 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 290
Pacific Associates Inc v Baxter [1990] 1 QB 993 . . . . . . . . . . . . . . . . . . . . . 334 Robert James Beckingham v Robert Hodgens & Others [2003]
Pacific Associates v Baxter [1990] QB 993 . . . . . . . . . . . . . . . . . . . . . . . . . . 184 EWCA Civ 143 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 361
Parker, the 9th Earl of Macclesfield v Hon Jocelyn Parker, 2003 . . . . . . . . . 37 Robin Ray v Classic FM plc [1998] FSR 622 . . . . . . . . . . . . . . . . . . . . . . . . 361
Partridge v Morris [1995] CILL 1095 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 337 Robinson v Chief Constable of West Yorkshire [2018] AC 736 . . . . . . . . .21, 22
Paul Thomas Construction Ltd v Hyland [2002] 18 Robinson v PE Jones (Contractors) Limited [2012] QB 44, 21 . . . . . . . . . . . 25
Constr LJ 345 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213 Robinson v PE Jones (Contractors) Ltd [2011] EWCA Civ 9, [2012] QB . . 332
Payne v John Setchell Ltd [2002] BLR 48 . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 Rock Advertising v MWB Business Exchange [2018] UKSC 24 . . . . . . . . . . . 16
Payne v John Setchell Ltd [2002] PLNR 7 . . . . . . . . . .327, 328, 329, 333, 334 Royal Brompton Hospital NHS Trust v Hammon & Others (No. 7)
Payne v Setchell [2002] PNLR 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24 (2000) 76 ConLR 148 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 338
Pearson Education Ltd v The Charter Partnership Ltd Royal Brompton Hospital NHS Trust v Hammond [2002] 1
[2007] EWCA Civ 130 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 WLR 1397 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 340, 341–342
Pearson Education Ltd v The Charter Partnership Ltd Royal Brompton Hospital NHS Trust v Hammond (No. 7)
(2007) BLR 324 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 333 (2001) 76 Con LR 148 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Pearson v Dublin Corporation [1907] 1 AC 351 . . . . . . . . . . . . . . . . . . . . . 328 Royal Brompton Hospital NHS Trust v Hammond (No. 9)
Pegler v Wang [2000] BLR 218 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 [2002] EWHC 2037 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185
Percy Bilton Ltd v Greater London Council [1982] 2 All ER 63 (HL) . . . . . 194 R(Taylor) v Honiton Town Council [2016] EWHC 3307(Admin) . . . . . . . . . . 62
Perry v Sidney Phillips & Son [1982] 1 WLR 1297 . . . . . . . . . . . . . . . . . . . . 43 Ruxley Electronics and Construction Ltd v Forsyth [1996] 1
Petroships Pte Ltd v Petec Trading and Investment Corporation AC 344 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 339
[2001] Lloyd’s Rep 348 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 Rylands v Fletcher [1866] LR 1 Ex 265 at 279, 28– . . . . . . . . . . . . . . . . . . . . 29
PGF II SA v OMFS Co 1 Ltd [2013] EWCA Civ 1288 . . . . . . . . . . . . . . . . . 284 S&T (UK) v Grove Developments [2018] EWHC 123 (TCC) [2018]
Philips Electronic v B Sky B [1995] EMLR 472 . . . . . . . . . . . . . . . . . . . . . . . 13 EWCA Civ 2448 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245
Phillips v Ward [1956] 1 WLR 471 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43 S&T [UK] Limited v Grove Developments Limited [2019] BLR 1 . . . . . . . . 203
Pilon v Breyer [2010] EWHC 837 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 252 Sahib Foods Ltd v Paskin Kyriades Sands (A Firm) (2003)
Pioneer Aggregates (UK) Ltd v Secretary of State for the Environment Con LR 1, 333 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 340
[1985] AC 132 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129 Sainsbury’s Supermarkets Ltd v Condek Holdings Ltd [2014]
Pirelli General Cable Works v Oscar Faber [1983] 2 AC 1 . . . . . . . . . . . . . . 30 EWHC 2016 (TCC), 26 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 334
Platt v Crouch ([2003 EWCA Civ 1110) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 Saint Line Ltd v Richardson [1940] p4060 2 KB 99 . . . . . . . . . . . . . . . . . . . 205
Playboy Club London Ltd v Banca Nationale di Lavoro [2018] 1 Samuels v Davies [1943] KB 526 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 328
W.L.R. 4041 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 Scheldebouw BV v St James Homes Ltd [2006] BLR 113 . . . . . . . . . . . . . . . 184
Plymouth & South West Co-operative Society Ltd v Architecture, Scott v Hanson [1829] 1 Russ & M 128 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
Structure & Management Ltd (2006) 108 ConLR 77 . . . . . . . . . . . . . . . 336 Scottish & Newcastle Plc v GD Construction (St Albans) Ltd [2003] BLR 131
Potton Ltd v Yorkelose Ltd [1990] 17 FSR . . . . . . . . . . . . . . . . . . . . . . . . . . 364 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210
Pozzolanic Lytag Ltd v Brian Hobson Associates (1999) Signature Realty Ltd v Fortis Developments [2016] EWHC 3583 . . . . . . . . 361
BLR 267 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 337 Sika Contracts v Gill and Closeglen Properties [1978] 9 BLR 11 . . . . . . . . 329
Pratt v George Hill & Associates (1987) 38 BLR 25 . . . . . . . . . . . . . . . . . . 337 Simplex Concrete Piles v Borough of St Pancras [1980] 14 BLR 80 . . . . . . 199
Pride Valley Foods Ltd v Hall & Partners (Contract Management) Ltd Sloan v The Governors of Rastrick High School [2014] EWCA Civ 1063 . . . 169
(2001) 76 Con LR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 340 Smith v Eric S Bush [1990] AC 831 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Priestly v Fowler [1837] 150 All ER 1030 . . . . . . . . . . . . . . . . . . . . . . . . . . 160 South Australia Asset Management Corp v York Montague Ltd
Pring v Hafner [2002] EWHC 1755 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 255 [1997] AC 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22
Proudfoot v Hart [1890] 25 QBD 42 at 55 . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
396 Table of Cases

Southend-on- Sea Corporation v Hodgson (Wickford) Ltd Treasure & Sons Ltd v Dawes [2008] BLR 24 . . . . . . . . . . . . . . . . . . . . . . . 250
[1961] 2 All ER 46 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62 TSG v South Anglia Housing [2013] EWHC 1151 . . . . . . . . . . . . . . . . . . . . 251
Spartan Steel and Alloys Ltd v Martin & Co. (Contractors Ltd) Tunnel Refineries Ltd v Bryan Donkin Co. Ltd (1998) CILL 1392 . . . . . . . . 333
[1973] 1 QB 27 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23 Turner Page Music Ltd v Torres Design Associates Ltd [1997]
Squibb Group v Vertase [2012] EWHC 1958 . . . . . . . . . . . . . . . . . . . . . . . . 254 CILL 1263 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 340
St Andrews Bay Development Ltd v HBG Management Ltd Tyrer v District Auditor of Monmouthshire (1973) 230 EG 973 . . . . . . . . . . 337
2003 SLT 740 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 290 Universal Cargo Carriers v Citati [1957] 2 QB 401 . . . . . . . . . . . . . . . . . . . 211
St Martins Property Corporation Ltd v Sir Robert McAlpine Ltd University of Glasgow v Whitfield (1988) 42 BLR 66 . . . . . . . . . . . . . . . . . . 338
[1994] AC 85 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234 University of London Press Ltd v University Tutorial Press Ltd
Stafford v Lee . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 (1916 2 Ch 601) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 359
Stewart Milne Westhill Ltd v Halliday Fraser Munro [2016] CSOH 76 . . . . 344 Urang v Century Investments [2011] EWHC 1561 . . . . . . . . . . . . . . . . . . . . 254
Storey v Charles Church Developments Ltd [1995] 73 ConLR 1 . . . . . . . . . 332 Verrall v Great Yarmouth Borough Council [1981] QB 202 . . . . . . . . . . . . . . 37
Storey v Charles Church Developments Ltd [1996] 12 Const LJ 206 . . . . . . . 22 Voli v Inglewood Shire Council [1963] ALR 657 . . . . . . . . . . . . . . . . . . . . . 336
Stoven-Bradford v Volpoint Properties Ltd (1971) Ch 1007, . . . . . . . . 363–364 The Wagon Mound (No. 2) [1967] AC 617, 23 . . . . . . . . . . . . . . . . . . . . . . . . 27
Stovin-Bradford v Volpoint Properties Ltd [1971] Ch 1007, . . . . . . . .359, 361 Wales Construction Ltd v Franthom Property Ltd (1991) 53 BLR 23 . . . . . 204
Strable v Dartford Borough Council [1984] JPL 329 . . . . . . . . . . . . . . . . . . . 62 Walter Lawrence v Commercial Union Properties (1984)
Strathmore Building Services Ltd v Greig (t/a Hestia Fireside Design) 4 Con. L.R. 37 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192
([2001] 17 Const LJ 72) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245 Walter Lilly & Co Limited v Clin [2018] BLR 321 . . . . . . . . . . . . . . . . . . . . 192
Sturges v Bridgman [1879] 11 ChD 852 at 856 . . . . . . . . . . . . . . . . . . . . . . . . 27 Walter Lilly & Co Limited v Mackay [2012] BLR 503, . . . .188, 191, 194, 205
SulamErica Cia Nacional De Seguros S.A. and others v Enesa Walter Lilly v McKay [2012] EWHC 1773 (TCC) . . . . . . . . . . . . . . . . . . . . . 323
Engenharia S.A. and others [2012] EWCA Civ 638 . . . . . . . . . . . . . . . 284 Walter v Lane [1900] AC 539 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 359
Sutcliffe v Chippendale & Edmondson (A Firm) (1971) Warner v Basildon Development Corporation (1991) Const LJ 146 . . . . . . . 333
18 BLR 149, 337 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 338 West & West v Ian Finlay & Associates [2014] EWCA Civ 316 . . . . . . . . . . 343
Sutcliffe v Thackrah [1974] AC 727, 183, 199 . . . . . . . . . . . . . . . . . . . . . . . 338 West Faulkner Associates v London Borough of Newham
Swain v Denso Marston (2000) ICR 1079 . . . . . . . . . . . . . . . . . . . . . . . . . . . 169 (1992) 71 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 338
Systems Pipework Ltd v Rotary Building Services Ltd West Faulkner Associates v London Borough of Newham
[2017] EWHC 3235 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 243 (1995) 74 BLR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 211
Tahrland v Rodier [1866] 16 L.C. Rep. 473 . . . . . . . . . . . . . . . . . . . . . . . . . 328 West Register Street (Property) Ltd v Central Demolition Ltd
Tameside Metropolitan Borough Council v Barlow Securities [2018] CSOH 98 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 291
Group Services Ltd [2001] BLR 113 . . . . . . . . . . . . . . . . . . . . . . . . . . . 199 West v Ian Finlay Associates [2014] EWCA 316 . . . . . . . . . . . . . . . . . . . . . . 325
Targett v Torfaen Borough Council [1992] 3 AER 27 . . . . . . . . . . . . . . . . . . 332 Western Fish Products Ltd v Penwith DC [1979] 77 LGR 185 . . . . . . . . . . . . 62
Taylor Woodrow Civil Engineering Ltd v Hutchison IDH Westminster City Council v Jarvis Limited [1970] 1 All ER 943 at 948 . . . . 193
Development Ltd [1998] Con LR 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272 Wheeldon v Burrons [1879] 12 ChD 31 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
Tesco Stores Ltd v Norman Hitchcox Partnership Ltd (1997) Whittal Builders v Chester Le Street DC (1988) 40 BLR 82 . . . . . . . . . . . . 185
56 ConLR 42 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 333 Williams & Glyn’s Bank Ltd v Boland [1981] AC 487 . . . . . . . . . . . . . . . . . . 35
Tesco Stores v Costain Construction Ltd [2003] EWHC 1487 . . . . . . . . . . . 332 Williams & Roffey Bros. & Nicholls (Contractors) LTD
Thomas Scott v Universal Components Ltd [2002] . . . . . . . . . . . . . . . . . . . . 360 [1990] 1 All ER 512 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Thomas v Taylor Wimpey Developments Ltd [2019] Wood v Waddington ([2015] EWCA Civ 538) . . . . . . . . . . . . . . . . . . . . . . . . . 39
EWHC 1134 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 Woolley Jewellers Ltd v A&A Jewellery Ltd [2002] EWCA Civ 1119 . . . . . 366
Thompson v Clive Alexander & Partners [1993] 59 BLR 77 . . . . . . . . .26, 329 Wordie Property Ltd v Secretary of State for Scotland 1984 SLT 345 . . . . . 291
Thomson v Thomson 1962 SC (HL) 28 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 306 Workspace Management v YJL [2009] EWHC 2017 . . . . . . . . . . . . . . . . . . . 253
Three Rivers District Council and others (Respondents) v Governor and Wraight Ltd v PH & T (Holdings) Ltd (1980) 13 BLR 26 . . . . . . . . . . . . . . 205
Company of the Bank of England (Appellants) [2004] UKHL 48 . . . . . 267 Yonge v Toynbee [1910] 1 KB 215 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 329
Townsend (Builders) Ltd v Cinema News and Property Management Yuanda (UK) Co Ltd v WW Gear Construction Ltd [2010]
(1958) 20 BLR 118 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 334 EWHC 720 (TCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 250
Trafalgar House v Railtrack [1995] 75 BLR 55 . . . . . . . . . . . . . . . . . . . . . . 263 Zealander v Laing Homes Ltd. (2000) 2 TCLR 724 . . . . . . . . . . . . . . . . . . . . 15
Transco Plc v Stockport MBC [2003] 2 A.C. 1, 28 . . . . . . . . . . . . . . . . . . . . . 29
Table of Legislation

Abolition of Feudal Tenure (Scotland) Act 2000 . . . . . . . . . . . . . . . . . . . .51, 52 s 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82


Access to Neighbouring Land Act 1992 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36 s 10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Act of Union 1707 (Scotland) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .45, 73 s 16 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .81, 82, 83
ADB (Approved Document B) 2006 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92 s 16(10) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83
ADB (Approved Document B) 2019 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92 s 17 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
ADB Volume 1: Dwellings (2019) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92–93, 95 s 18 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
ADB Volume 2: Buildings other than dwellings (2019) . . . . . . . . . . . . . . 93–96 s 21(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
property protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95 s 22 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84–85
Agricultural Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37 s 24 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
AMSC s 25 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
s 59 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139 s 35 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
s 65 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139 s 36 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .81, 82, 83
Ancient Monuments and Archaeological Areas Act . . . . . . . . . . . . . . . . . . . . . 64 s 37 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Animal Boarding Establishments Act 1963 . . . . . . . . . . . . . . . . . . . . . . . . . . . 71 s 39 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Approved Document B (Fire Safety) (2019 . . . . . . . . . . . . . . . . . . . . . . . . . . . 92 s 40 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
Arbitration Act 1996 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213, 249, 259–260 s 40(6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82
s 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 260 s 49 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
s 5(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 263 s 66 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
s 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 264 s 89 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
s 9(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 270 s 90 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85
s 12 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 264 s 126 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
s 14 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 266 Building (Scotland) Act 2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .74, 105, 120
s 15 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 265 Part 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106–107
s 15(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 265 Part 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107–110
s 16 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .260, 265 Part 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
s 17 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .260, 265 Part 4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110–111
s 21 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 265 Part 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111–112
s 24 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 s 1 of Schedule 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108
s 24(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 273 s 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107
s 29(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272 s 4 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .106, 107
s 30 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 264 s 5 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106–107
s 33 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .260, 266 s 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .107, 109
s 34(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 266 s 7(1)(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107
s 34(2)(d) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 267 s 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .107, 108
s 35 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 263 s 14(6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108
s 37 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 268 s 17 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108, 110
s 37(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 273 s 19 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
s 40 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 266 s 20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 109
s 42 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 s 22 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106
s 44 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 s 24 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
s 45 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 s 25 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
s 64(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272 s 26 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
s 66 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 s 27 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 108, 110
s 67 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 s 28 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110
s 68 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 s 29 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
s 69(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272 s 30 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
s 73 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 271 s 36 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113
s 76 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 266 s 41 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110, 111
Arbitration (Scotland) Act 2010 . . . . . . . . . . . . . . . . . . . . . . . . . . .287, 288, 289 s 47 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Architects (Registration) Act 1931 . . . . . . . . . . . . . . . . . . . . . . . . . . . . .375, 376 s 48 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Architects (Registration) Act 1938 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 375 s 49 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Architects (Registration) Act 1969 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 375 s 50 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Architects Act 1997 . . . . . . . . . . . . . . . . . . . 161, 295, 296, 299, 305, 375, 376 s 51 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
section 13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 379 s 53 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Architects’ Registration Bill 1899 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 375 s 55 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
Automated Registration of Title to Land (Electronic Communications) Building (Scotland) Act 2003 (Charging Orders) Regulations 2014 . . . . . . . 120
(Scotland) Order 2006 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53 Building (Scotland) Act 2003 (Commencement No. 1,
Bankruptcy (Scotland) Act 1985 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .306, 307 Transitional Provisions and Savings) Order 2004 . . . . . . . . . . . . . . . . . . . . . 120
s 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 306 Building (Scotland) Act 2003 (Commencement No. 2 and Transitional
Building Act 1984 . . . . . . . . . . . . . . . . . . . . . . . . . . . 29, 66, 79, 80, 91, 98, 99 Provisions) Order 2009 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
clause 16(12) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83 Building (Scotland) Act 2003 (Exemptions for Defence a
Part II . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 nd National Security) Order 2009 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
s 4(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 Buildings (Recovery of Expenses) (Scotland) Act 2014 . . . . . . . . . . . . . . . . 120
s 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81 Business Names Act 1985 . . . . . . . . . . . . . . . . . . . . . . .296, 299, 304, 305, 306
s 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81 Caravan Sites and Control of Development Act 1960 . . . . . . . . . . . . . . . . . . 129
s 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82 Part I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71

397
398 Table of Legislation

Cinemas Act 1985 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70 European Union (Withdrawal Agreement) Act 2020 . . . . . . . . . . . . . . . . . . . . .4


Cities and Local Government Devolution Act 2016 . . . . . . . . . . . . . . . . . . . . 60 Factories Act 1961 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .71, 165
Civic Government (Scotland) Act 1982 . . . . . . . . . . . . . . . . . . . . . . . .55, 56, 76 Finance Act 1985 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 297
Civil Aviation Act 1982 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70 Fire (Scotland) Act 2006 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .76
Civil Liability (Contribution) Act 1978 . . . . . . . . . . . . . . . . . . 31, 316, 340–341 Fire Precautions Act 1971 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .70, 99, 161
Clean Air Act 1993 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71 Fire Safety and Safety of Places of Sports Act 1987 . . . . . . . . . . . . . . . . .76, 99
schedule 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70 Flood and Water Management Act 2010 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
s 14 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 FOIA (Freedom of Information Act 2000) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
s 15 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Food Safety Act 1990 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
s 16 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Freedom of Information Act 2000 (FOIA) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
s 25 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70 Freedom of Information (Scotland) Act 2002 . . . . . . . . . . . . . . . . . . . . . . . . . 46
Clean Neighbourhoods and Environment Act 2005 . . . . . . . . . . . . . . . . . . . . . 87 Gambling Act 2005 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
Part 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .87 Gas Act 1986 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
s 54 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87 schedule 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
Climate Change (Scotland) Act 2009 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110 s 10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
Communications Act 2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 Gas Act 1995 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
Community Empowerment (Scotland) Act 2015 . . . . . . . . . . . . . . . . . . . . . . . 56 Government of Wales Act 1998 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .59, 60
Companies (Floating Charges) (Scotland) Act 1961 . . . . . . . . . . . . . . . . . . . 307 Government of Wales Act 2006, 59 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
Companies Act 1989 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 183 Greater London Authority Act 1999 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
Companies Act 2006 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .298, 306 Greater London Authority Act 2007 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
s 44 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 183 Health and Morals of Apprentices Act of 1802 . . . . . . . . . . . . . . . . . . . . . . . 160
Companies Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .64, 70 Health and Safety at Work Act 1974 (HSWA) . . . . . . . . . 71, 76, 107, 159, 160,
Company Directors Disqualification Act 1986 . . . . . . . . . . . . . . . . . . . . . . . . 299 163, 165, 169, 302–303, 305
Constitutional Reform Act 2005 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6 s 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 165
Construction Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 191 Health and Safety at Work etc Act 1974 . . . . . . . . . . . . . . . . . . . . . . . . . .86, 99
Consumer Protection Act 1987 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 s 101 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
Consumer Rights Act 2015 . . . . . . . . . . . . . . . .13–15, 310, 311, 325, 332, 342 Health and Safety (Offences) Act 2008 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 163
Contract (Third Party Rights) (Scotland) Act 2017 . . . . . . . . . . . . . . . . . . . . . 49 Highway Act 1980 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Contracts (Rights of Third Parties) Act 1999 s 38 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
. . . . . . . . . . . . . . . . . . . . . . . . . . . 9, 18–19, 183, 210, 216, 233–234, 316, 322 s 73 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
conventions s 74 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Berne Copyright Convention (BCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 357 s 124 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
European Convention for the Protection of Human Rights and Fundamental s 139 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Freedoms (ECHR) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46 s 140 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
European Convention of Human Rights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61 s 168 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
New York Convention on the Recognition and Enforcement of Foreign Arbitral s 177 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Awards (1958) (New York Convention) . . . . . . . . . . . . . . . . .262, 275, 276, 280 s 184 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86
Universal Copyright Convention (UCC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 357 s 219 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
Copy Right Act 1956, section 17 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 364 Hill Farming Act 1946 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
Copyright, Designs and Patents Act 1988 . . . . . . . . . . . . . . . . . . . 357, 359–360 Historic Buildings and Ancient Monuments Act 1953 . . . . . . . . . . . . . . . . . . . 70
s 62 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 361 Homes (Fitness for Habitation) Act 2018 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
s 64 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 360 Housing (Scotland) Act 2006 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .56, 76
s 65 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 361 Part 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .76
s 91 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362 s 233 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
s 97(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 364 Housing (Scotland) Act 2010 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
s 178 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 360 Housing Act 1985 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
Copyright Act 1709 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358 Part V . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Copyright Act 1842 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358 s 11 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
Copyright Act 1911 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358 s 523 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Copyright Acts 1911 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358 Housing Act 1988
Copyright Acts 1956 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358 s 50 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Copyright and Design Law 1977 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358 s 54 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Courts Act 1971 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6 Housing Act 2004 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .87, 99, 162
Data protection Act 1998 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 304 Housing and Planning Act 1986 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 132
Data Protection Act 2018 (DPA) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 367 Housing Associations Act 1985 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Defective Premises Act 1972 . . . . . . . . . . . . . . . . . . . . . . . . .24, 26–27, 29, 329 Housing Grants, Construction and Regeneration Act 1996 (HGCRA)
Deregulation Act 2015 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61 . . . . . . . . . . . . . 18, 69, 213, 215, 228, 241–246, 245, 261, 289, 311, 314, 375
Digital Economy Act 2017 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 s 104 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 250
Disability Discrimination Act 1995 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .87 s 105(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 250
Domestic Fire Safety (Wales) Measure 2011 . . . . . . . . . . . . . . . . . . . . . . . . . . 91 s 105(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 250
DPA 1972 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 344 s 107(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242
ECHR (European Convention for the Protection of Human Rights and s 108 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .250, 251
Fundamental Freedoms) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46 s 108(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .252, 255
ECJ (European Court of Justice) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46 s 108(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .290, 291
EIR (Environmental Information Regulations 2004) . . . . . . . . . . . . . . . . . . . . 61 s 108(3a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 254
Electricity Act 1989 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .68, 75, 136 s 109-113 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 202, 242–245
Schedule 16 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .68 Human Rights Act 1998 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5, 61
s 16 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 Article 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
s 196 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 Imperial Copyright Act 1911 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358
Employers Liability Act 1880 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 160 Insolvency Act 1986 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 298
Employers’ Liability (Compulsory Insurance) Act 1969 . . . . . . . . . . . . . . . . 304 Insolvency Act 1994 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 298
Enclosure Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37 Insolvency Act 2000 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 298
English Planning Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139 Insurance Act 2015 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 353–355
Environment Act 1995 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .60, 65, 86 Interest on Damages (Scotland) Act 1958 . . . . . . . . . . . . . . . . . . . . . . . . . . . 290
Environment Act 1999 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 86 Interest on Damages (Scotland) Act 1971 . . . . . . . . . . . . . . . . . . . . . . . . . . . 290
Environmental Protection Act 1990 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74–75 International Conventions, ECHR (European Convention for
Equality Act 2010 (EqA) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .61, 87, 159 the Protection of Human Rights and Fundamental Freedoms) . . . . . . . . . . . . 46
European Communities Act 1972 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71 Judicature Acts of 1873 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
s 2(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4 Land Charges Act 1972 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34–35, 36
European Court of Justice (ECJ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46 Land Reform (Scotland) Act 2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .55, 56
European Union (Withdrawal) Act 2018 . . . . . . . . . . . . . . . . . . . . . . . . . . .4, 46 Land Reform (Scotland) Act 2016 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
Table of Legislation 399

Land Registration Act 1925 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 Occupiers’ Liability Act 1984 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .29, 303
Land Registration Act 2002 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .33, 35 Occupiers’ Liability (Scotland) Act 1960 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
Land Registration (Scotland) Act 1979 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53 Offices, Shops and Railway Premises Act 1963 . . . . . . . . . . . .71, 165, 302, 304
Landlord and Tenant Act 1927 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 Parntership Act 1980 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 295
Landlord and Tenant Act 1954 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .42, 43 Parties, Elections and Referendum Act 2000 . . . . . . . . . . . . . . . . . . . . . . . . . . 60
Landlord and Tenant (Covenants) Act 1995 . . . . . . . . . . . . . . . . . . . . . . . . . . . 43 Partnership Act 1890 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49, 296–297, 304
Latent Damage Act 1986 . . . . . . . . . . . . . . . . . . . . . . . . . 29, 30, 297, 330, 344 s 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 297
Law of Property Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1925 s 24 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 297
s 62 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 Party Wall etc. Act 1996, 86 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .155, 314
s 84 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41 s 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 155
s 146 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 s 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 155
Law of Property Act 1969 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 s 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 155
s 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34 s 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 158
s 28 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41 s 20(a) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
Law of Property (Miscellaneous Provisions) Act 1989 . . . . . . . . . . . . . . . . . 183 s 20(b) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 156
Law Reform (Contributory Negligence) Act 1945 . . . . . . . . . . . . . . . . . .31, 340 Pet Animals Act 1951 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
Law Reform (Miscellaneous Provisions) (Scotland) Act 1940 . . . . . . . . . . . 345 Pipelines Act 1962 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
Leasehold Property (Repairs) Act 1938 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 Planning Act 2008 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63
Legal Aid, Sentencing and Punishment of Offenders Act 2012 . . . . . . . . . . . 163 Planning Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121
Legal Writings (Counterparts and Delivery) (Scotland) Act 2015 . . . . . . . . . 314 Planning and Compensation Act 1991 . . . . . . . . . . . . . . . . . . . . . . . . . .121, 132
Legislative and Regulatory Reform Act 2006 . . . . . . . . . . . . . . . . . . . . . . . . . 61 Planning and Compulsory Purchase Act 2004 . . . . . . . . . . . . . . . . . . . . .63, 121
Licensing (Scotland) Act 2005 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76 Planning (Consequential Provisions) Act 1990 . . . . . . . . . . . . . . . . . . . . . . . 121
Licensing Act 1662 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358 Planning etc. (Scotland) Act 2006 . . . . . . . . . . . . . . . . . . . . . . . . .135, 137, 138
Licensing Act 2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63, 70, 71, 87 Planning etc. (Scotland) Act 2019 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 135
Limitation Act 1980 . . . . . . . . . . . . . . . . . . . . 20, 183, 264, 297, 329, 341, 344 Planning (Hazardous Substances) Act 1990 . . . . . . . . . . . . . . . . . . . . . . . . . . 121
s 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 Planning (Listed Buildings and Conservation
s 32 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 Areas) Act 1990, . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .64, 121, 130
s 33 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 s 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .64, 65, 70, 130
Limited Liability Partnerships Act 2000 . . . . . . . . . . . . . . . . .49, 295, 298, 306 s 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131
Limited Partnership Act 1907 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .304, 306 s 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130
Listed Buildings Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139 s 8 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130
Livestock Rearing Act 1951 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69 s 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130
Local Democracy, Economic Development and Construction Act 2009, s 10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .59, 60, 241 s 43 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131
Local Government (Access to Information) Act 1985 . . . . . . . . . . . . . . . . . . . 62 s 45 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
Local Government Act 1972 . . . . . . . . . . . . . . . . . . . . . . . . . . . .59, 61, 62, 123 s 49 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131
s 101 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61 s 50 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131
Local Government Act 1974 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62 s 57 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .70, 130
Local Government Act 1985 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .59, 123 s 59 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130
Local Government Act 1999 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 s 66 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
Local Government Act 2000 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .59, 60, 61 s 67 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128
Part III . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62 s 69, . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .64, 128, 131
Local Government Act 2003, Public Services (Social Value) Act 2012 . . . . . 64 s 70 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128
Local Government and Public Involvement in Health Act 2007 . . . . .59, 60, 61 s 71 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128
Local Government (Contracts) Act 1997 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 s 72 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .64, 128
Local Government (Democracy) (Wales) Act 2013 . . . . . . . . . . . . . . . . . . . . . 60 s 73 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128
Local Government etc. (Scotland) Act 1994 . . . . . . . . . . . . . . . . . . . . . . . . . . 73 s 74 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128
Local Government (Miscellaneous Provisions) Act 1982 . . . . . . . . . . . . .63, 71 s 75 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128
Local Government Planning and Land Act 1980, Schedule 32 . . . . . . . . . . . 140 Planning (Listed Buildings in Conservation Areas) Act 1990, section 69 . . . 123
Local Government (Wales) Act 1994 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997,
Local Government (Wales) Act 2016 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .138, 139
Local Government (Wales) Measure 2009 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 Planning (Scotland) Act 2019, 135, 136, 138, 140 . . . . . . . . . . . . . . . . . . . . 141
Local Government (Wales) Measures 2007 . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 PLBCA (Planning (Listed Buildings and Conservation Areas) Act 1990 . . . 130
Local Government (Wales) Measures 2011 . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 Prescription Act 1832 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .39, 40
Local Government (Wales) Measures Act 2011 . . . . . . . . . . . . . . . . . . . . . . . . 61 Prescription and Limitation (Scotland) Act 1973 . . . . . . . . . . . .49–50, 232, 305
Localism Act 2011 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .59–61, 62, 63, 64 Public Health Act 1875 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129
Chapter 7 of Part I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62 Public Health Act 1936 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
London Building Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .85, 88 Public Health (Scotland) Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
s 20 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Public Services Ombudsman (Wales) Act 2019 . . . . . . . . . . . . . . . . . . . . . . . . 62
s 21 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Public Services (Social Value) Act 2012 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
s 30(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Registered Designs Act 1949 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 365
s 30(5) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Regulation Enforcement and Sanctions Act 2008 . . . . . . . . . . . . . . . . . . . . . .61
London Building Acts (Amendment) Act 1939 . . . . . . . . . . . . . . . . . . . . .98, 99 Regulatory Reform (Business Tenancies) (England and Wales)
London Government Act 1963 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59 Order 2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
London Building (Amendment) Act 1939 . . . . . . . . . . . . . . . . . . . . . . . . . . . 155 Requirement of Writing (Scotland) Act 1995 . . . . . . . . . . . . . . . . . . . . . . . . 314
London Building Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .79, 161 Requirements of Writing (Scotland) Act 1995 . . . . . . . . . . . . . . . . . . . . .46, 231
Marine and Coastal Access Act 2009 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 RIBA Standard Professional Services Contract 2018 . . . . . . . . . . . . . . . . . . . 283
Matrimonial Homes (Family Protection) (Scotland) Act 1981 . . . . . . . . .52, 54 Riding Establishment Acts 1964 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
Misrepresentation Act 1967 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 Riding Establishment Acts 1970 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
National Heritage Act 1983 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130 Rights of Light Act 1959 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40
s 32 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 Road Traffic Act 1988 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 304
s 33 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 Roads (Scotland) Act 1984 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .76, 136
National Heritage (Scotland) Act 1991 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .74 Safety of Sports Grounds Act 1975 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .76, 99
National Parks and Access to the Countryside Act 1949 . . . . . . . . . . . . . . . . 123 Sale of Goods Act 1979 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
National Parks (Scotland) Act 2000 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74 Sale of Goods Act 1994 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Natural Environment and Rural Communities Act 2006, section 1 . . . . . . . . . 65 Sales of Goods Act . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
Nature Conservation (Scotland) Act 2004 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56 Scotland Act 1998 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .45, 46, 73, 135
New Roads and Street Works Act 1991, Part III . . . . . . . . . . . . . . . . . . . . . . . 68 s 104 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111
NHBC Buildmark Agreement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 Sewerage (Scotland) Act 1968 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74–75
Norfolk and Suffolk Broads Act 1988 . . . . . . . . . . . . . . . . . . . . . . . . . . .60, 123 Sheriff Courts (Scotland) Acts 1907 and 1913, updated in 1939,
Occupiers’ Liability Act 1957 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .29, 303 1971, and 2007 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 305
400 Table of Legislation

Smoke Detectors Act 1991 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99 s 26(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 136


Social Security Act 1990, section 15 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76 s 26(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 136
Standards 3.11 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116 s 26(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 136
Standards 3.12 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 116 s 27 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139
state, Environmental Assessment Regulations . . . . . . . . . . . . . . . . . . . . . . . . 127 s 42 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139
Statutory Instrument 2011 No. 1848 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143 s 75 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 139
Statutory Instrument 2016 No. 273 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143 s 125 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
Supply of Goods and Services Act 1982 . . . . . . . . . . . . . .13–14, 327, 330, 331 s 126 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
Sustainable and Secure Buildings Act 2004 . . . . . . . . . . . . . . . . . . . . . . . . . . . 84 s 127 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
Telecommunications Act 1984 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68 s 128 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
Tenements (Scotland) Act 2004 . . . . . . . . . . . . . . . . . . . . . . . . . . . . .51, 55, 158 s 140 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
Theatre Act 1968 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .70, 76 s 145 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141
Tithe Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37 s 146 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141
Title Conditions (Scotland) Act 2003 . . . . . . . . . . . . . . . . . . . . . . . . . . . . .51, 53 s 150 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
Town and Country Planning Act 1947 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121 s 151 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140
Town and Country Planning Act 1968 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129 Town and Country Planning (Use Classes) Order 1987
Town and Country Panning Act 1990 (TCPA) . . . . . . . . . . . . . . . . .63, 121, 242 (SI 1987 No. 764) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .123, 124
meaning of ‘development,’ . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124–125 Treaty and Acts of Union 1707 (Scotland) . . . . . . . . . . . . . . . . . . . . . . . . . . .45
Schedule 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124 Unfair Contracts Terms Act 1977 (UCTA) . . . . . . . . . . . . . . .14, 323, 332, 343
Schedule 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126 s 3 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
s 55 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .63, 123, 124 s 13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
s 55(2)(f) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124 Wales Act 2017 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
s 55(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124 Water (Scotland) Act 1980 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
s 56 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129 Water Act 1989 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .63, 64
s 58 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125 Water Environment and Water Services (Scotland) Act 2003 . . . . . . . . . . . . . 56
s 62 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 125 Water Environment (Controlled Activities (Scotland) Regulations 2005 . . . . . 56
s 65 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .127, 128 Water Industry Act 1991 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
s 65(5) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 Chapter III . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
s 70 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128 schedule 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
s 71 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 s 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
s 77 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 s 41-43A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
s 78 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128 s 42 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
s 79 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126 s 45 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67–68
s 91 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129 s 47 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
s 92 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 s 55 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
s 94 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129 s 56 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
s 96 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 129 s 60 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
s 106A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 128–129 s 98 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
s 115 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130 s 104 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
s 117 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130 s 106(2)(b) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
s 118 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130 s 106(2)(c) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .66
s 171E . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 106A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
s 171F . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 107(6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
s 171G . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 111 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
s 171H . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 118 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
s 179 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 119 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
s 183 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 121 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
s 183(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 126 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
s 186 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 129 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
s 187 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 196 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
s 187B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 s 199 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
s 191 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .124, 132 s 200 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84
s 288 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127 s 122 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
s 289 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 133 Water Industry (Scotland) Act 2002 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
s 319A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 126 Water Services etc. (Scotland) Act 2005 . . . . . . . . . . . . . . . . . . . . . . . . . .74, 75
Town and Country Planning Acts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56 Well-being of Future Generation (Wales) Act 2015 . . . . . . . . . . . . . . . . . . . . . 60
Town and Country Planning (Scotland) Act 1997, . . . . . . . . . . . . . . . . .73, 135 Welsh Ministers (Transfer of Functions) (No.2) Order 2009 . . . . . . . . . . . . . . 91
Part 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138 Wildlife and Countryside Act 1981 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 123
Part VIII . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 140 Wireless Telegraphy Act 2006 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
s 26 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 135 Workman’s Compensation Act 1897 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 160
s 26(1) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 136 WTO TRIPS Agreement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358
Index

45˚ rule, 40 ACE Professional Services Consumer agency, 19–20, 329


1993 RIAS Statement, 387 Agreement 2019, 230 Scotland, 49
1999 FIDIC form, 223 ACE Short Form 2015, 230 agents, authority, 20
2000 RIAS Statement, 387 ACE Sub-Consultancy Agreement 2017, agreed surveyors, 157
2020 Plan of Work stages, 312 230 agreement of appointment, client
ACM (Aluminium Composite Material) contracts, 310
AAA (American Arbitration cladding panels, 100–101 agreements, 11–12
Association), 276 ACMs (Asbestos Containing Materials), limited liability partnerships, 298
abandoning developments, England and 166 agriculture, grants, 69
Wales, 129 ACoP (Approved Code of Practice), 164 aids to communications, Scotland, 118
abolition of feudal burdens, Scotland, 54 acquiring easements, 38–39 air conditioning, Scotland, 119
abolition of feudal tenure, Scotland, actionable nuisance, 27 airport noise, grants, 70
51–52 Acts of Parliament, 4 All Scotland Sheriff Personal Injury
ACA (Association of Consultant ad hoc arbitration, 277 Court, 48
Architects), 225–227 ADB 1985, 89 all-in service appointments, 309
architectural appointments, 227 ADB 2000, 89 all-party parliamentary group (APPG),
contracts, 311 ADB 2006, 91 167
FAC-1 (Framework Alliance Contract), ADB 2019, 90 alterations
227 additional conditions of contract, NEC4 to drawings and works of architecture,
PPC2000, 225–227 Professional Services Contract, 216 364
TAC-1 (Term Alliance Contract), 227 adjudication, 7, 249, 261 landlord and tenant, 42
ACA Building Agreement 1982, 227 appointment of adjudicators, 252 Alterations Notice, RRFSO (Regulatory
ACA Form of Building Agreement 1982, confidentiality, 253 Reform (Fire Safety) Order 2005), 99
323 contracts, 250 alternative design guidance documents,
ACA SFA 2012 -- ACA Standard Form contractual adjudications, 250 fire safety, 96–98
of Agreement for the Appointment of decisions, 253–254 alternative dispute resolution (ADR),
an Architect, 227 disputes, 251 259
ACA Standard Form of Agreement, 311 distinctive features of, 249 arbitration. see arbitration
ACA Standard Form of Contract for enforcement, 254–255 mediation. see mediation
Project Partnering (PPC2000), 225 fees, 254 Aluminium Composite Material (ACM)
ACA98 -- The Appointment of a ineffective defences to enforcement cladding panels, 100–101
Consultant Architect for Small Works, proceedings in TCC, 254 amendments to Building Regulations,
227 JCT Standard Building Contract, 213 fire safety, 90–92
Acceleration Quotation, 209 jurisdictional defences to enforcement American Arbitration Association
acceptance, 11, 12 proceedings, 254–255 (AAA), 276
NEC4 Professional Services Contract, notices of, 251 AMSC applications, 137
217 referral notice, 252–253 any cladding material, 98
Acceptance Certificate, IChemE resignation, revocation, and AONB (area of outstanding beauty), 123
(Institution of Chemical Engineers), abandonment, 253 appeals
229 Scotland, 289–291 arbitration, 272
access, Scotland, 118 severance, 255 developments, Scotland, 138
Access and Representatives, JCT terms of HGCRA, 250 minimum compensation, 131
Standard Building Contract, 195–196 adjudicators, appointment of, 252 over developments, 125
access rights, Scots land law, 55 adjustment of completion date, JCT planning appeals, 126
accessibility, 87 Standard Building Contract, 189–190 Scotland, 111
accession, Scots land law, 51 administration of the contract, JCT Water Services Regulation Authority,
accidents, managing an architectural Standard Building Contract, 185–189 67
business, 303 ADR (alternative dispute resolution), APPG (all-party parliamentary group),
accountability principle, 368 259 167
Accountable Person, 163 ADs (Approved Documents), Building applications for determination, Building
accused, Scotland, 47 Regulations 2010 (England and Regulations 2010 (England and
ACE (Association for Consultancy and Wales), 80–81 Wales), 83
Engineering), 227, 230 advance payment code, 68 applications for warrants, Scotland, 112
ACE Professional Services Agreement advertising, RIBA (Royal Institution of appointment of adjudicators, 252
2017, 230 British Architects) code of conduct, appointments
ACE Professional Services Agreement 386 architect’s appointment, 324–325
Advisory, Investigatory and other advertisements, controlling, 129 client contracts, 309–310
Services 2019, 230 Advice Notes, 100–101 client contracts (Scotland), 314
affirmative burdens, Scotland, 53 of contractors, 337

401
402 Index

RIBA (Royal Institution of British Architect/Contract Administrator’s authorship, 359–360


Architects) code of conduct, instructions, JCT Standard Building automated decision making, data
384–386 Contract, 196–197 protection law, 369–370
apportionment of liability, law of tort, 31 Architect/Contractor Administrator, JCT automatic fire suppression systems,
appraisals, breach of obligation of Standard Building Contract, 196 94–96
reasonable care and skill, 335 architects automatic life safety fire suppression
approval of drainage, sewers, 66–67 action, JCT Standard Building systems, 116
approval of matters specified in Contract, 190–191 award criteria
conditions (AMSC applications), appointments, 342–325 Concessions Directive (EU), 152
Scotland, 137 as arbitrators, 272–273 procurement process, Public Sector
approved certification schemes, collateral warranties, 315–319 Directives (EU), 148–150
Scotland, 108 duties owed, 321–322 Utilities Directive (EU), 151
approved certifiers of construction, duty to review after practical awards
Scotland, 109 completion, JCT Standard Building arbitration, 268–270
approved certifiers of design, Contract, 191 international arbitration, 280
Scotland, 108 eligibility for registration, 376–377 party walls, 158
Approved Code of Practice (ACoP), 164 EU public procurement rules, 143
Approved Document B Fire Safety as expert witnesses, 273 balconies, fire safety, 101–102
(‘ADB’) 1992, 88 health and safety, 159–160 bankruptcy, partnerships (Scotland), 306
Approved Documents, Building JCT Standard Building Contract, bare license, land, 36
Regulations 2010 (England and 183–184 battle of the forms, contracts, 12
Wales), 80, 80–81 minimising risks, 324–325 beneficial ownership, 53
Approved Inspectors, 84 obligation of reasonable care and Berne Copyright Convention (BCC), 357
Approximate Quantities, JCT Standard skill, 331–335 Betting Premises License, 76
Building Contract, 207 offices, 43–44 BIM (building information modelling),
ARB (Architects Registration Board), professional liability, 327–329 FIDIC, 224
161, 296, 375, 376, 379 remedies, 195 boundaries (land), 37–38
code of conduct, 347, 379–382 responsibility for the work of others, boundary structures, Scotland, 158
disciplinary proceedings, 347–349 322–324 boundary walls and support, Scots
arbitral tribunals, 260 Architect’s Job Book, 324 land law, 55
arbitration, 259 Architects’ Registration Board, BRE (Building Research
advantages of, 261–262 Scotland, 49 Establishment), 89
appeals, 272 Architects Registration Board (ARB), breach of building regulations, Building
Arbitration Act 1996, 260 161, 296 Regulations 2010 (England and
awards, 268–269 architectural appointments, ACA Wales), 81–82
commencing proceedings, 266 (Association of Consultant Breach of Condition Notice,
compared to court processes, 262 Architects), 227 Scotland, 141
construction industry cases, 269–270 architectural training, 161 breach of contract, 17–18
costs, 269 architectural works, copyright, 359 law of tort, 29
deciding whether a process is or is area of outstanding natural beauty breach of duty, negligence, 22–23
not arbitration, 260–261 (AONB), 123 breach of obligation of reasonable care
definition of issues, 266–267 Articles of Agreement, JCT Standard and skill
disadvantages of, 262–263 Building Contract, 181–183 construction work stages, 337–339
disclosure of documents, 267 Articles of Association, formation of pre-construction work stages, 335–337
duty of the parties, 266 companies, 299 breach of statutory duty, law of tort, 29
enforcement, 270 artificial and display lighting, breaches, data protection law, 372
enforcement of awards, 270 Scotland, 119 Brexit, 46
evidence of fact and expert evidence, artificial intelligence (AI), 169 EU public procurement rules, 144
267–268 artistic work, 359 bribery, RIBA (Royal Institution
international arbitration. see asbestos, 86 of British Architects) code of
international arbitration health and safety, 166–167 conduct, 383
JCT Standard Building Contract, 213 Asbestos Containing Materials British Gas Corporation, 68
multi-party disputes, 265 (ACMs), 166 British Standards, design, 336
power of courts to supervise, assault, 29 Broads Authority, 60, 63, 123
271–272 assignation, partnerships (Scotland), 306 brokers, insurance, 353
power to enforce orders, 269 assignments BS 7974 Application of fire safety
process of, 265–266 CIC/ConsWa/P&T (Collateral engineering principles to the design of
role of courts, 270–271 Warranty Consultant--Purchaser/ buildings--Code of practice (2019), 98
rules for, 266 Tenant), 318 BS 8414 large-scale fire tests, 89
Scotland, 287–289 contracts, 17 BS 8414-1: 2002, 89, 91
arbitration agreements, 263, 266 JCT 2016 suite, 240 BS 8414-2: 2005, 89, 91
institutional arbitration, 276–277 JCT Standard Building Contract, BS 9991 Fire safety in the design,
submission agreements, 277 210–211 management, and use of residential
arbitration hearings, 268 associates, partnerships, 296 buildings--Code of practice (2015),
arbitration tribunals association, group practices, 301 97–98
composition of, 265 Association for Consultancy and BS 9999 Fire safety in the design,
jurisdiction, 263–265 Engineering (ACE), 227 management and use of buildings--
number of arbitrators, 265 Association of Consultant Architects Code of practice (2017), 97
arbitrators, architects as, 272–273 see ACA (Association of Consultant BSD (Building Standards Division),
Architect/Consultant’s Architects) Scotland, 105
responsibilities, RIBA assumption of responsibility, 22 BSR (Building Safety Regulator), 162
Standard Professional Service authorisation, 20 buildability, design, 336
Contract 2018, 219 authoritative writings, Scots law, 47
Index 403

Building (Procedure) (Scotland) ‘CE,’ 88 Civil Procedure Rules, 258, 262, 283
Regulations, 112–113 CECA (Civil Engineering Contractors arbitration, 267, 273
Building (Scotland) Regulations 2004, Association), 227, 230 Civilian tradition (Scotland), 45
113 Centre for Effective Dispute Resolution claimants, 9
Building Bulletin 100: Design for fire (CEDR), 283, 350 claims
safety in schools (2007), 97 Certificate of Incorporation, 299 insurance, 353, 355
building contracts. see contracts certificate of lawfulness, 124 loss and expense, JCT Standard
Building Control, 81 Scotland, 137 Building Contract, 205–206
building control, breach of obligation of Certificate of Making Good, 193, professional indemnity insurance, 354
reasonable care and skill, 335 195, 202 smash and grab claims, 245
building information model (BIM), certificate of practical completion, 194 classes of permitted development, GPO
FIDIC, 224 Certificate of Search, 35 2015, 125
building notice procedure, Building certificates classification of property, Scots land
Regulations 2010, 82–83 Acceptance Certificate, 229 law, 51
building owner’s rights, party walls, 158 breach of obligation of reasonable clean air, grants, 69–70
building performance, RIBA (Royal care and skill, 338 clerk of works, JCT Standard Building
Institution of British Architects) code final certificates. see final certificates Contract, 196
of conduct, 385 fire certificates, 162 client contracts
Building Preservation Notice, 140 interim certificates. see interim agreement of appointment, 310
special buildings, 131 certificates appointments, 309–310
Building Registration Certificate, 163 JCT Standard Building Contract, 199 appointments required by statute, 314
building regulations compliance notice, non-completion certificates, 192–193 insurance, 353
Scotland, 110 obstruction of, 212 ownership, 311
Building Regulations Advisory regularization certificate, 82 Professional Services Contracts,
Committee for Wales, 91 certificates of lawful use, enforcement of 311–313
Building Research Establishment (BRE), planning control, 132–133 Scotland, 314
89 certification speculative work and tendering,
Building Safety Manager, 163 RIBA (Royal Institution of British 313–314
Building Safety Regulator (BSR), 162 Architects) code of conduct, 385 termination of, 310–311
Building Standards assessment, Scotland, Scotland, 231 client expertise, 175
107, 109–110 Certification Handbook, Scotland, 107 Client/Consultant Model Services
Building Standards Division (BSD), certifiers, Scotland, 107 Agreement, 311
Scotland, 105 change of use, meaning of, 124 clients, data protection law, 372
Building Standards Register, Scotland, Chartered Institute of Arbitrators, 265 closing contracts, Public Sector
110 chattel, landlord and tenant, 41 Directive (EU), 151
building warrants, 106 Childrens Homes, 71 code of conduct, 379
Scotland, 107–109 chimneys, 86 ARB (Architects Registration Board),
building work Building Regulations 2010 (England 379–382
control by local authorities, 82 and Wales), 85 insurance, 353
control of, 84 China International Economic and RIAS (Royal Incorporation of
defined, 81 Trade Arbitration Commission Architects in Scotland), 347, 377,
Burgandy Book, 2nd edition, 2013, 229 (CIETAC), 276 386–388
Burgandy Book: Target Cost, 228 CIC (Construction Industry Council), RIBA (Royal Institution of British
buring debris, 103 230, 315 Architects), 295, 382–386
business contacts, data protection law, CIC Consultant Conditions -- 2nd Code of Practice, JCT Standard Building
372–373 edition, November 2011, 230 Contract, 213
business tenancies, 43–44 CIC Novation Agreement: Ab Initio codes of practice, breach of obligation
protection of, 43–44 (2018), 312, 313 of reasonable care and skill, 336
by-laws, 4 CICAIR (Construction Industry Council co-extensive, 331
Approved Inspectors Register), 84 Colindale fire, 2006, 103
C-19 (Severe Acute Respiratory CIC/ConsWa/F (Collateral Warranty collateral agreements, 309
Syndrome Coronavirus-2), 159–160, Consultant--Funder), 315, 318–319 collateral warranties, 19, 210–211, 233,
171 CIC/ConsWa/P&T (Collateral Warranty 315, 330
personal protective equipment, 168 Consultant--Purchaser/Tenant), 315, CIC/ConsWa/F (Collateral Warranty
CA07, arbitration, 263 316–318 Consultant--Funder), 318–319
CABE (Commission for Architecture CIETAC (China International CIC/ConsWa/P&T (Collateral
and the Built Environment), 87 Economic and Trade Arbitration Warranty Consultant--Purchaser/
Cadw, 65 Commission), 276 Tenant), 316–318
Cairngorm National Park, 74, 136 CIMAR (Construction Industry employers, 234–235
‘call in’ the application, Secretary of Model Arbitration Rules), funders, 235
State, 127 220, 259 importance of, 234
canon courts (Scotland), 45 arbitration, 265–266, 269–270 JCT 2016 suite, 235–240
caravan sites, 71, 129 cinemas, 70 obligation to provide, 315–316
carbon dioxide emissions, Scotland, 119 civil courts, Scotland, 48 purchasers, 235
Care Homes, 71 Civil Engineering Contractors tenants, 235
Scotland, 76 Association (CECA), 227 combustion appliances, Scotland, 117
case law, Scotland, 46–47 civil law, 9 commencement date, international
categorisation of, Scots law, 46 Scotland, 46 arbitration, 278
causation, damages, 340 civil law system, 3 commercial contracts, 14
cavities, fire safety, 114 civil liability commercial drivers, 175–176
cavity barriers, 88–89 breach of statutory duty, 29 Commission for Architecture and the
CDP Documents, discrepancies, 187–188 health and safety, 165 Built Environment, 87
CDP insurance, 210 Scotland, 111
404 Index

commissioning building services, completion notices, developments, 129 commercial drivers, 175
Scotland, 119 Concessions Directive (EU), 152 complexity, 175
committees, local government (England concurrent duty of care, 330–331 construction management, 177
and Wales), 61–62 in tort, 332 cost reimbursable/prime cost, 178
Common Council of the City of concurrent liability in tort, 330–331 design and build contracts, 177
London, 59 concurrent obligations, 321 design modification, 176
Common Law, Scotland, 45 condensation, Scotland, 117 design responsibility, 176
common law, 3–4 conditions fixed price, 176
equity, 6 contracts, 18 funding, 176
origins of, 5–6 on developments, 128 lump sum/fixed price, 178
common ownership, Scots land law, 52 on developments, Scotland, 139 management contracting, 177–178
Commonwealth Law Conference, 3 Conditions of Engagement, licenses, 362 measurement contracts, 178
communication, fire safety, 116 confidential references, 370 partnering/framework agreements, 178
community, RIBA (Royal Institution confidentiality PPP (public private partnership), 178
of British Architects) code of adjudication, 253 time, 176
conduct, 385 ARB disciplinary proceedings, 349 two-stage tendering, 177
community burdens, Scotland, 53, 54 mediation, 284 construction safety records, 163
community rights, 64 RIBA code of conduct, 383 construction sites
companies, 298 RIBA disciplinary proceedings, 350 fire safety, 102–104
consortia, 301 conflicts of interest, RIBA code of health and safety, 163
difficulties, 301–302 conduct, 383 Scotland, 77
dissolution of, 301 confrontation testimony, international construction work stages, breach of
employee trusts, 302 arbitration, 280 obligation of reasonable care and
formation of, 299 connections to sewers, Scotland, 74–75 skill, 337–339
group practices, 301 consent, data protection law, 368–369 Consultancy Agreement (Public Sector),
loose groups, 301 consents, landlord and tenant, 42 311
name of company, 299 consequential economic loss, duty of consumer contracts, 14–15
versus partnerships, 300–301 care, 332 consumers, 14
profits, 299 consequential loss, 23 Contact Details, RIBA Standard
public and private, 299 CIC/ConsWa/P&T (Collateral Professional Service Contract 2018,
rights and liabilities of directors, Warranty Consultant--Purchaser/ 313
300–301 Tenant), 316 contaminated land, 86
rights and liabilities of shareholders, JCT 2016 suite, 239 continuing requirements enforcement
299–300 conservation areas, 64, 123 notice, Scotland, 110
Scotland, 306–307 developments, 128 continuous suspension, 212
separate legal personas, 299 special buildings, 131 contract administration, breach of
service companies, 301 conservation burdens, Scotland, 54 obligation of reasonable care and
size of, 299 Conservative Government, 59 skill, 338
types of companies, 299 conservatory measures, 278 contract and concurrent duty of care in
Companies House, 298–302 consideration, contracts, 10–11 tort, 331–332
company limited by guarantee, 299 considering wider impact of your work, contract award notices, Public Sector
company limited by shares, 299 ARB (Architects Registration Board) Directive (EU), 148
compartmentation, 114 code of conduct, 381 contract awards, Public Sector Directive
compensation, 342 consortia, companies, 301 (EU), 149–150
business tenancies, 44 construction contracts, 250 Contract Bills, 204
Listed Buildings, Scotland, 140 Scotland, 290 Contract Conditions, RIBA Standard
special buildings, 131 Construction Design and Management Professional Service Contract 2018,
compensation events, NEC4 Professional Co-ordinators, 167 312
Services Contract, 217–218 Construction Excellence, 225 contract data, NEC4 Professional
competence construction industry cases, arbitration, Services Contract, 218–219
ARB (Architects Registration Board) 269–270 Contract Documents, 186
code of conduct, 380–381 Construction Industry Council Approved Contract Drawings, JCT Standard
RIBA (Royal Institution of British Inspectors Register (CICAIR), 84 Building Contract, 181
Architects) code of conduct, 384 Construction Industry Council (CIC), contract modification
competent person schemes, 84 230, 315 Concessions Directive (EU), 152
Competent Persons, 99 Construction Industry Model Arbitration Public Sector Directive (EU), 150
competition, RIBA (Royal Institution Rules (CIMAR), 220, 259 Utilities Directive (EU), 152
of British Architects) code of arbitration, 265–266 contract notices, Public Sector Directive
conduct, 386 construction information, JCT Standard (EU), 148
Competitive Dialogue Procedure, award Building Contract, 186 Contract Particulars
of public works contracts, 146–147 construction legislation JCT Standard Building Contract, 183
complaints, 62–63 Building Regulations 2010 (England SBCC (Scottish Building Contracts
ARB (Architects Registration Board) and Wales), 79–83 Committee), 231
code of conduct, 382 control of building work, 84 contract performance, Public Sector
disciplinary proceedings, 347 controls under Building Act 1984, Directive (EU), 150–151
RIBA (Royal Institution of British 84–85 Contract Sum, JCT Standard Building
Architects) code of conduct, 386 local legislation in Inner London, 85 Contract, 199
completion certificates local legislation outside Inner London, contract termination, Public Sector
Building Regulations 2010 (England 85 Directive (EU), 150
and Wales), 83 national legislation, 85–87 contracting authority, Public Sector
Scotland, 109–110 construction management, 177 Directive (EU), 144
completion dates, JCT Standard Building construction projects, 178 contractors
Contract, 189–190 client expertise, 175 appointment of, 337
Index 405

duties of, 160 contracts excluded based on remedies for infringement, 364
duties to, 321–322 subject-matter RIBA (Royal Institution of British
health and safety, 170 Public Sector Directive (EU), 145 Architects) code of conduct, 385
minimising risks, 325 Utilities Directive (EU), 151 RIBA Standard Professional Service
workmanship details, 324 contracts excluded based on value Contract 2018, 219
Contractor’s Design Portion (CDP), 323 Public Sector Directive (EU), 145 Scotland, 366
Contractor’s Design Submission Utilities Directive (EU), 151 sources of copyright law, 358
Procedure, JCT Standard Building contracts of appointment, 330. see also corporeal heritable property, Scotland,
Contract, 213 appointments 51
Contractor’s Designed Portion, 183 contractual adjudications, 250 corporeal moveable property, Scotland,
contractor’s master programme, JCT contractual duties, 321 51
Standard Building Contract, 186 contractual license, land, 36, 37 correcting defects, NEC4 Professional
contracts, 9–10, 178 contractual limitation, 342 Services Contract, 217
ACA (Association of Consultant contractual safeguards, minimising risks, corruption, RIBA code of conduct, 383
Architects), 225–227 325 cost estimates, breach of obligation of
ACE (Association for Consultancy contribution, sharing liability for reasonable care and skill, 335
and Engineering), 230 professional negligence with others, cost of repairs, damages, 339–340
adjudication, 250 340–341 cost reimbursable/prime cost, 178
agency, 19–20 contribution clauses, JCT 2016 suite, costs
agreements, 11–12 239 arbitration, 269
assignments, 17 contributions international arbitration, 280–281
battle of the forms, 12 assessment of amounts, 343–344 of mediation, 284
CECA (Civil Engineering Contractors CIC/ConsWa/P&T (Collateral RIBA code of conduct, 384
Association), 230 Warranty Consultant--Purchaser/ co-terminous, 331
CIC (Construction Industry Council), Tenant), 316–317 Council of Europe, 46
230 time limits for claiming, 344 councillors, 60
client contracts. see client contracts contributory negligence, 31, 340 counter-offers, 11
collateral warranties, 19 control of developments Countryside Agency, 65
commercial contracts, 14 planning law (England and Wales), Countryside Council for Wales, 65
consideration, 10–11 125–130 county matters, 124
consumer contracts, 14–15 Scotland, 137–139 county planning authority, 124
entire contract clause, 16 controlled land, 68 Court of Appeal, 6
exclusion clauses, 14–15 controls under Building Act 1984, 84–85 Court of Chancery, 6
express terms, 330 Convenors, 74 Court of Criminal Appeal, Scotland, 48
FIDIC, 221–224 Convention for the Protection of Human Court of Session
ICC (Infrastructure Conditions of Rights and Fundamental Freedoms, 5 judicial review, 73
Contract), 227–228 conversion, Building Regulations Scotland, 48, 258, 289
IChemE (Institution of Chemical (Scotland), 106 Court of the Lord Lyon, Scotland, 48
Engineers), 228–229 conversion of closets, grants, 69 court structure, Scotland, 47–49
IMechE (Institution of Mechanical conveyancing, 33 courts, power to supervise arbitration,
Engineers), 229–230 Scots land law, 53 271–272
implied terms, 330 cookie notices/policies, data protection covenants
intention to create legal relations, 10 law, 373 enforcement of repairing, 42
JCT 2016 suite, 235 co-operation, IChemE (Institution of landlord and tenant, 41, 42
JCT Standard Building Contract. see Chemical Engineers), 229 restrictive covenants, 40–41
JCT Standard Building Contract co-operation with regulatory Covid-19 lockdown, disciplinary
letters of intent, 12 requirements and investigations, ARB proceedings, 348
liability for professional negligence code of conduct, 382 CPR (Civil Procedure Rules), 283
barred by lapse of time, 344 coordinated groups, 301 criminal conviction, RIBA (Royal
LOGIC (Leading Oil and Gas copying Institution of British Architects) code
Industry Competitiveness), 230 a building in the form of drawings, of conduct, 384
misrepresentation, 15–16 362 criminal courts, Scotland, 47–48
NEC4 Professional Services Contract, a building in construction of another criminal law, 9
215–217 building, 362 criteria to determine winning tender,
novation, 16–17 drawings in the form of a building, procurement process, Public Sector
oral contracts, 10 361–362 Directives (EU), 148
performance and breach, 17–18 in the form of drawings, 361 crofting communities, Scotland, 56
prevention of unfair terms, 14–15 copyright, 357 Crown Court, 6
requirements for establishing, 10 CIC/ConsWa/P&T (Collateral Crown Office, Scotland, 47
RIBA (Royal Institution of British Warranty Consultant--Purchaser/ Crown rights
Architects), 228 Tenant), 317 Building (Scotland) Act 2003, 111
RIBA Standard Professional Service database right, 358–359 copyright, 360
Contract 2018, 219–220 duration of, 359 curtilage, 66
rights of those who are not exceptions to copyright infringement, CWa/F, 239–240
contracting parties, 18–19 361 CWa/P&T, 239–240
Scotland, 230–232 history of, 358
Scots land law, 53 infringement, 361–362 DAAB (Dispute Adjudication and
Scots law, 49 licenses, 362–364 Avoidance Board), 224
under seal, 10 nature of, 358 damage, 30
standard forms, 15 Northern Ireland, 366 liquidated damages, JCT Standard
terms of, 12–14 ownership of land, 360–361 Building Contract, 194
unilateral contracts, 9 publication, 360 negligence, 23
variation, 16 qualification for protection, 359–360 to other property, 332
406 Index

to property, 209–210 design, breach of obligation of disputes


reasonable opportunity for discovery reasonable care and skill, 336 adjudication, 251
of defect, 333 design and build contracts, 177, 179 ARB code of conduct, 382
damages, remedies for copyright IChemE (Institution of Chemical under contract, 251
infringement, 364 Engineers), 229 party walls, 157
danger, 28 design consultants, minimising risks, 325 disqualification as a director, RIBA code
danger from accidents, Scotland, 118 Design Council, 87 of conduct, 384
danger from heat, Scotland, 118 design liability, 323 dissolution of
dangerous buildings, Scotland, 111 design modification, construction companies, 301
data controllers, 367, 368, 371 projects, 176 partnerships, 297–298
data processors, 367 design process, PPC2000, 226 distribution of planning functions, local
data protection impact assessments, 371 design responsibility, construction government (England and Wales),
data protection law, 367 projects, 176 63–64
data protection principles, 368 design sub-consultants, 323 district councils, 60, 64
employees, 371–372 designated heritage assets, 64 licenses, 71
enforcement, 371 development plan documents, 63, 64, district planning authority, 124
responsibilities of the architect, 122, 126 ditches, boundaries (land), 37
370–371 development plans, 121, 135 divergences from statutory requirements,
Data Protection Office (DPO), 371 developments, 135 JCT Standard Building Contract, 188
data protection officers, 371 meaning of, 124–125 divided ownership, Scotland, 52
data protection regulators, 369 planning law (Scotland), 136–137 division of responsibility, managing an
data subject access right (DSAR), 369 devolution, Scotland, 45–46 architectural business, 303
database right, 358–359 Dickens, Charles, 6 documents
Date of Completion, JCT Standard dilapidations, landlord and tenant, 42 Development Plan Documents, 122
Building Contract, 211 diligence, 306 tender documentation, 336–337
dates for payment, 243 Dilwyn Roberts Penseiri/Architects Ltd, DOM/1 sub-contracts, 230
DCLG Circulars 01/2015, 79 166–167 DOM/2 sub-contracts, 230
DCLG Circulars 03/2012, 79 Directives (EU), 4 Domesday Book (1086), 5–6
DCLG Circulars 03/2018, 79 Directorate for Planning and domestic premises, water supply, 67–68
DCLG Circulars 04/2016, 79 Environmental Appeals (DPEA), 136 DPEA (Directorate for Planning and
DCP (Contractor’s Design Portion), 323 directors Environmental Appeals), 136
decisions, adjudication, 253–254 liability (Scotland), 307 DPO (Data Protection Office), 371
declaration of ineffectiveness, Remedies rights of, 300–301 drains
Directives (EU), 153 discharge Building Act 1984, 84–85
deed of partnership, 296 real burdens (Scotland), 54 Scotland, 74–75, 116
deeds, 10 of restrictive covenants, 41 drawings, 359
deemed refusal, 138 servitudes (Scotland), 55 copyright infringement, 361
deemed variation, 209 disciplinary action, data protection law, ownership of, 360
defective building cases, 30 372 drones, 164
defective buildings, Scotland, 110 Disciplinary Orders, PCC (Professional DSAR (data subject access right), 369
defects Conduct Committee), 377 dungsteads, Scotland, 118
JCT Standard Building Contract, 193, disciplinary orders, ARB (Architects duration of permission, developments,
195 Registration Board), 380 129
meaning of, 195 disciplinary proceedings duties of architects, 321
NEC4 Professional Services Contract, ARB rules, 347–349 concurrent duty of care, 330–331
217 complaints, 347 duty holders, 162
reasonable opportunity for discovery RIBA, 347–348, 350–351 duty of care
of defect, 333 disclosure of documents contract and concurrent duty of care
defects liability period, defects after arbitration, 267 in tort, 331–332
expiration, 195 international arbitration, 279 to third parties, 332
Defects Notification Period, FIDIC, 223 disclosure to third parties, data Duty of Care Agreement, 233
Defence Directive (EU), 152–153 protection law, 372 duty of care to third parties, 331
defences of liability, CIC/ConsWa/P&T discrepancies, JCT Standard Building duty to care, negligence, 21–22
(Collateral Warranty Consultant-- Contract, 187–188 duty to complete in sections, JCT
Purchaser/Tenant), 317 discretion of local authority, Building Standard Building Contract, 195
defend in place, 93 Regulations 2010 (England and duty to make a fair presentation,
defendants, 9 Wales), 81 insurance, 353–354
definition of issues, arbitration, 266–267 dispensations and relaxations, Building duty to review own design, 338
degree of annexation test, 41 Regulations 2010, 82 dwellings, 26, 329
delay caused by employer, JCT Standard display screen equipment, health and
Building Contract, 194 safety, 169 early warning process, NEC4
delay damages, NEC4 Professional disposition, Scots land law, 53 Professional Services Contract, 217
Services Contract, 215–216 disproportionate collapse, Scotland, 114 Early Warning Register, 217
delays, JCT 2016 suite, 240 Dispute Adjudication and Avoidance easements, 35
deleterious material clauses Board (DAAB), 224 acquiring, 38–39
CIC/ConsWa/P&T (Collateral dispute avoidance, FIDIC, 224 extinguishment of, 40
Warranty Consultant--Purchaser/ dispute resolution land law, 37, 38–40
Tenant), 317 ICC (Infrastructure Conditions of economic development burdens,
JCT 2016 suite, 239 Contract), 228 Scotland, 54
delict, Scotland, 49 RIBA (Royal Institution of British economic loss
Denning, Lord, 12 Architects) code of conduct, 386 CIC/ConsWa/P&T (Collateral
Department of Culture, Media and Sport, RIBA Standard Professional Service Warranty Consultant--Purchaser/
64 Contract 2018, 220 Tenant), 316
Index 407

duty of care, 332 Environment Agency, 64, 65 international arbitration, 279–280


JCT 2016 suite, 239 environment permits, 67 express grants, easements, 38–39
negligence, 23–26 Environmental Assessment, 127 express terms, 330
economic operators, Public Sector Environmental Information, 125 contracts, 12–13
Directive (EU), 144 Environmental Statement, 125 extensions of time
economic prosperity board (EPB), 60 EOT (Employee Ownership Trust), 302 breach of obligation of reasonable
Edinburgh Sheriff Court, 258 EPB (economic prosperity board), 60 care and skill, 338–339
Edward the Confessor, 5 EPCs (energy performance certificates), JCT Standard Building Contract,
EEA (European Economic Area), 144 110 188–191
Data Protection law, 371 Scotland, 119 external walls, 90–91, 96
effluent disposal, 86 equality, RIBA code of conduct, 386 extinguishment of easements, 40
effluents, Scotland, 118 equity, 6
elections, Scotland, 73 errors in bills, JCT Standard Building FAC-1 (Framework Alliance Contract),
Electoral Commission, 59 Contract, 208 227
electrical fixtures, Scotland, 118 escape, fire safety, 98, 116 facilities in dwelling, Scotland, 117
electrical safety, Scotland, 118 escape lighting, fire safety, 116 facility conditions, Scotland, 54
electricity supply, 68 escape routes, 93 factories, 71
Scotland, 75 estate, 6 factual witness evidence, international
electronic communications, 68 estate contracts, 34 arbitration, 279
eligibility for registration, 376–377 estate in land, 33 Faculty of Advocates, Scotland, 49
employee ownership, 302 estimated value, 145 fair dealing, exceptions to copyright
Employee Ownership Trust (EOT), 302 estoppel, 44 infringement, 361
employee trusts, companies, 302 Ethical Standards Officers, 62 fair presentation, insurance, 353–354
employees EU (European Union), Public Sector fairness, data protection, 368
data protection law, 371–372 Directive, 144–151 false imprisonment, 29
ownership of copyright, 360 EU design law, 366 Family Division, High Court, 6
employers EU Registered Designs, 366 farm effluent tanks, Scotland, 118
collateral warranties, 234–235 EU Unregistered Designs, 366 fatal workplace injuries, 160
duties to, 321 EU/EEA procurement regime, 144 work at heights, 167
RIBA code of conduct, 386 European Commission, asbestos, 166 feasibility site investigation, breach of
third party rights, 234–235 European Convention on Human Rights, obligation of reasonable care and
employers’ liability, personal injury, 304 5 skill, 335
Employer’s Requirements, contracts, 17 European Court of Human Rights, 5 fees
employer’s specialist consultants, European Data Protection law, 371 adjudication, 254
322–323 European directives, 46 mediation, 284
employment, RIBA code of conduct, 386 European Economic Area (EEA), 144 planning applications, 126
energy, Scotland, 119–120 European law, Scotland, 46 recovery extension, insurance, 355
Energy Performance Certificates, 87 European Union, Scotland and, 46 RIBA Standard Professional Service
energy performance certificates (EPCs), evidence Contract 2018, 219
110 arbitration, 267–268 Scotland, 113
Scotland, 119 international arbitration, 279 fences, boundaries (land), 37
enforcement Excavation Notice, party walls, 157 feu duty, 51
adjudication, 254–255 excepted energy buildings, 91 feudal burdens, Scotland, 54
of arbitration agreements, 270 exclusion clauses, 342 feudal land ownership, Scotland, 51
Building Regulations 2010 (England contracts, 14–15 feudal law, 6
and Wales), 82 exclusion grounds, procurement process, FIDIC (Fédération Internationale des
data protection law, 371 Public Sector Directives (EU), 148 Ingénieurs-Conseils), 221, 275–276
of HSW Act, 303 exclusion of persons from work, 1999 FIDIC form, 223
international arbitration, 280 Architect/Contract Administrator’s arbitration, 275–276
of planning control, Scotland, instructions, 198 BIM (building information
140–141 exclusion of tenderers, Public Sector modelling), 224
real burdens (Scotland), 54 Directive (EU), 148–149 claims, 223
of repairing covenants, 42 Exclusion Order, 250 Client/Consultant Model Services
servitudes (Scotland), 54–55 exclusions, professional indemnity Agreement, 311
Enforcement Notice insurance, 355 contracts, 221
RRFSO (Regulatory Reform (Fire executed work, Architect/Contract dispute avoidance, 224
Safety) Order 2005), 99 Administrator’s instructions, 198 engineer’s duties, 223–224
Scotland, 140–141 executive arrangements, local forms, 221–222
enforcement notices, planning law government (England and Wales), Golden Principles, 224
(England and Wales), 133 61–62 Sub-Consultancy Agreement, 311
engineer’s duties exemptions from control, Building FIDIC Rainbow Suite, 222
FIDIC, 223–224 Regulations 2010 (England and FIDIC Red Book Update Task Group,
ICC, 227–228 Wales), 84 221
English Civil Procedure rules, 279 exemptions to individual rights, data Final Certificate, SBCC (Scottish
English common law, third parties, 9 protection law, 370 Building Contracts Committee), 288
English Heritage, 64 exits, Building Regulations 2010 final certificates
English law, 3–4 (England and Wales), 85 breach of obligation of reasonable
reforms to, 6–7 expedited procedures, ICE Procedure, care and skill, 338
Enterprise Zones, 59, 123 270 JCT Standard Building Contract, 195,
Scotland, 140 expert reports, Building Regulations 202–203
entire contract clause, 10, 16 2010, 82 final payments, pay less notices,
entry, Scotland, 111 expert witnesses 244–245
environment, RIBA code of conduct, 385 architects as, 273
408 Index

financial loss, contract and concurrent form of certificate, JCT Standard Ground Investigation Version -- August
duty of care in tort, 331 Building Contract, 194 2011, ICC (Infrastructure Conditions
fire alarms, 303 form of instructions, JCT Standard of Contract), 228
fire certificates, 162 Building Contract, 199 group practices, 301
fire classification requirements, 91 forms, Building (Forms) (Scotland) guidance documents, fire safety, 92–96
fire fighting, 89 Regulations 2005, 113
fire precautions, 70–71 Forms of Bonds, JCT Standard Building Hackett, Judith 105, 162
fire protection, managing an architectural Contract, 214 harassment, 27
business, 303 Framework Alliance Contract (FAC-1), hazardous substances, 302
Fire Risk Assessment, 162 227 Heal & Son Ltd, 362
fire safety, 161–165 freedom of contract, 10 health and safety, 159–160, 170
Accountable Person, 163 freedom of information, local asbestos, 166–167
alternative design guidance government (England and Wales), 61 C-19 (Severe Acute Respiratory
documents, 96–98 freeholds, 35 Syndrome Coronavirus-2), 171
amendments to Building Regulations, FSE (fire safety engineering), 98 Construction (Design and
90–92 FSO Regulatory Reform (Fire Safety) Management) Regulations, 164
Building Regulations 2010 (England Order 2005, 303 display screen equipment, 169
and Wales), 90 fuel storage, Scotland, 117 fire safety. see fire safety
Building Safety Manager, 163 full plans procedure, Building Health and Safety at Work Act 1974,
Building Safety Regulator (BSR), 162 Regulations 2010 (England and 165–166
construction sites, 102–104 Wales), 83 history of, 160
existing buildings under new regime, funders, collateral warranties/third party lifting operations and equipment, 170
163 rights, 235 management of regulations, 170
Gateways, 162–163 funding, construction projects, 176 manual handling operations
guidance documents, 92–96 further drawings, details, and regulations, 168–169
historical background, 88 instructions, JCT Standard Building non-fire-related, 163
housing, 99–101 Contract, 187 personal protective equipment, 168
local legislation in Inner London, 98 Future Homes Standard, 81 RIBA (Royal Institution of British
local legislation outside Inner London, Architects) code of conduct,
98–99 Garnock Court fire (11 June 1999), 89 384–385
national legislation, 99–102 gas supply, 68 use of work equipment, 169–170
Scotland, 77 Scotland, 75 work at height regulations, 167
system of duty holders, 162 Gateways, fire safety, 162–163 work place regulations, 167–168
fire safety engineering (FSE), 98 GC/Works adjudication provisions, 250 Health and Safety Executive (HSE), 65,
Fire safety in purpose built blocks of GDPR (General Data Protection 86, 302
flats (2011), 100 Regulation 2016/679), 304 Scotland, 138
Fire safety (‘ADB’) 1992, 88 general publicity, planning health care burdens, Scotland, 54
fire service access, 116 applications, 127 hearing stage
fire service facilities, 116 gentlemen’s agreement, 10 ARB disciplinary proceedings,
fire service water supply, 116 GLA (Greater London Authority), 59 348–349
fire suppression systems, 116 Gold Book, FIDIC, 222 RIBA disciplinary proceedings,
Firecode, 96 Golden Principles, FIDIC, 224 350–351
fires good faith, IChemE (Institution of Heathrow Terminal 5 Inquiry, 127
balconies, 101–102 Chemical Engineers), 229 heating, Scotland, 117
Building (Scotland) Regulations 2004, goods, 184 heating systems, Scotland, 119
114–116 governing clause, RIBA Standard hedges, boundaries (land), 37
Colindale fire, 2006, 103 Professional Service Contract 2018, Hedley Byrne principle, 24, 25, 334
Garnock Court fire (11 June 1999), 89 313 Henry II, 6
Grenfell Tower fire (14 June 2017), Government building safety programme heritable property, restrictions
89–90 and advice notes, 100–101 (Scotland), 56
Knowsley Heights fire (5 April 1991), Government Procurement Agreement heritage and conservation, RIBA code of
88–89 (GPA), 144 conduct, 385
Lakanal House fire (3 July 2009), 89 Government’s online Planning Practice Heritage Funding Directory, 70
Peckham fire, 2009, 103 Guidance, 64 HGCRA (Housing Grants Construction
Sun Valley Poultry fire (6 September Grampian condition, 138 and Regeneration Act 1996), 241–246
1993), 89 grant of planning permission, 36 adjudication, 249–250
firm naming, Scotland, 305 grants, 69–70 hidden defects, surveys of property to be
fitness for purpose, 327–328 Scotland, 76 purchased, 43
fixed price, construction projects, 176 graphic works, exceptions to copyright High Court, Family Division, 6
fixed seating, Scotland, 118 infringement, 361 High Court in London, 3
fixtures gratuitous alienations, 306 High Court of Justice, 6
landlord and tenant, 41–42 gratuitous services, negligence, 26 High Court of Justiciary, Scotland, 47
Scots land law, 51 Great Fire (1666), 88 high pressure laminate (HPL), 101, 162
floating charges, Scotland, 307 Greater London, local authorities, 124 highway drains, 67
floodgates argument, 23 Greater London Authority (GLA), 59 highways, boundaries (land), 37
flooding, 86 Green Book: Cost Reimbursable, 228 hiring processes, data protection law,
Scotland, 116 GreenBook, 4th edition, 2013, 229 372
food premises, 71 Grenfell Tower fire (14 June 2017), 79, historic buildings, grants, 70
Food Standards Agency, 71 89–90 Historic Buildings and Monuments
footpaths, Scotland, 76 Gross Valuation, JCT Standard Building Commission for England, 64
force majeure, 193 Contract, 204 Historic England, 64–65, 70
foreseeability, damages, 340 Historic Environment Scotland, 74,
foreseeability of harm, 23 139–140
Index 409

history IMechE (Institution of Mechanical Scots law, 45


of common law, 5–6 Engineers), 229–230 instructions to stop or not start work,
of fire safety, 88 impartiality, RIBA (Royal Institution of NEC4 Professional Services Contract,
of health and safety, 160 British Architects) code of conduct, 217
HM Inspectorate of Pollution, 65 383 insulation, Scotland, 119
HM Land Registry, 33, 34, 36 implied fitness, 328 insulation envelope, Scotland, 119
HMO (Houses in Multiple Occupation), implied grant, easements, 39 insurance, 353–354
87, 99 implied licenses, 362–364 ARB (Architects Registration Board)
Hobbes, Thomas, 160 implied reservation, easements, 38–39 code of conduct, 381–382
Homeowner/Occupier Contract, 311 implied terms, 330 managing an architectural business,
Homes England, 70 contracts, 13–14 304
honest promotion of services, ARB improvements, landlord and tenant, 42 NEC4 Professional Services Contract,
(Architects Registration Board) code incomplete performance, contracts, 18 218
of conduct, 380–381 Incorporated Council of Law Reporting, against personal injury and property
honesty, 328–329 4 damage, 210
ARB (Architects Registration Board) incorporeal heritable property, Scotland, professional indemnity insurance,
code of conduct, 380 51 319, 347
Hong Kong, arbitration, 276 incorporeal moveable property, Scotland, RIBA code of conduct, 386
Hong Kong International Arbitration 51 risk management, 355
Centre (HKIAC), 276 incremental approach, 22 Scotland, 232
hotels, 70 independence, Scotland, 46 terms of policies, 354
House of Lords, 6 independent enquiry, CIC/ConsWa/P&T of the works, 210
houses in multiple occupation, Scotland, (Collateral Warranty Consultant-- insurance clauses, JCT 2016 suite, 240
77 Purchaser/Tenant), 317 Insurance Options, JCT Standard
Houses in Multiple Occupation and Independent Hospitals, 71 Building Contract, 213
residential property licensing reform individual rights integrity, 328–329
[/] Guidance for Local Housing data protection law, 369–370, 372 ARB code of conduct, 380
Authorities, 87 exemptions to, 370 RIBA code of conduct, 383
Houses in Multiple Occupation (HMO), infiltration systems, Scotland, 117 intellectual property law, Scotland, 49
87 informal exchanges, 310 intellectual property rights, RIBA
housing, 87 Information Commissioners, 61 Standard Professional Service
fire safety, 99–101 Information Release Schedule, JCT Contract 2018, 219
Housing and Safety Rating System, 87 Standard Building Contract, 185, 187 intention to create legal relations,
housing associations, 70 Infrastructure Conditions of Contract contracts, 10
housing corporation loans, 70 (ICC), 227–228 interest, on late payments, 246
Housing Ombudsman, 62 infringement interim certificates
Housing–Fire Safety: Guidance copyright, 361–362 breach of obligation of reasonable
on fire safety provisions for certain remedies for, 364 care and skill, 338
types of existing housing (2008), injunctions, 30–31 JCT Standard Building Contract,
99–101 planning law (England and Wales), 199–204, 204
HPL (high pressure laminate), 101, 162 133 interim payments, pay less notices,
HSE (Health and Safety Executive), 65, remedies for copyright infringement, 244–245
86, 302 364 Interim Valuation Date, 202
HTM 05 ‘Firecode’ documents, 96 injury, 234 internal linings, fire safety, 116
human rights JCT Standard Building Contract, international arbitration, 275
local government (England and 209–210 ad hoc arbitration, 277
Wales), 61 Inner House of the Court of Session, appointment of tribunal, 278
Scotland, 46 Scotland, 48 arbitration agreements, 276–277
Inner London awards, 280
IBA Rules, 279 local legislation, 85 commencement date, 278
ICC (Infrastructure Conditions of local legislation, fire safety, 98 confrontation testimony, 280
Contract), 227–228 local legislation outside Inner London, costs, 280–281
institutional arbitration, 276–277 fire safety, 98–99 enforcement, 280
ICC (International Chamber of Innovation Partnership, award of public evidence, 279
Commerce), 263 works contracts, 146–147 expert witnesses, 279–280
ICC Court of Arbitration, 276–277 insolvency, 211 factors relevant to the choice, 276
appointment of tribunal, 278 insolvency of employer, JCT Standard interim measures, 278–279
ICC Design and Construct version 2018, Building Contract, 212 pathological arbitration clauses, 277
227 inspections procedures, 277–278
ICC Partnering Addendum August 2011, Architect/Contract Administrator’s recognition, 280
228 instructions, 198 International Bar Association Rules, 279
ICC Rules of Arbitration, 281 RIBA code of conduct, 385 International Chamber of Commerce
ICC Target Cost version 2018, 228 Scotland, 111 (ICC), 263
ICE (Institution of Civil Engineers), 227 Institution of Chemical Engineers international construction arbitration,
ICE Arbitration Procedure (England and (IChemE), 228–229 275–276
Wales0, 269–270 Institution of Civil Engineers (ICE), 227 International Dispute Resolution Centre
IChemE (Institution of Chemical Institution of Engineering and (IDRC), 285
Engineers), 228–229 Technology (IET), 229–230 interpretations
IDRC (International Dispute Resolution Institution of Mechanical Engineers buildings, Scotland, 111
Centre), 285 (IMechE), 229–230 NEC4 Professional Services Contract,
IET (Institution of Engineering and institutional arbitration, 276–277 216–217
Technology), 229–230 Institutional Writers investigation stage
Scotland, 47
410 Index

ARB disciplinary proceedings, Judicial Committee of the Privy Council, Rylands v Fletcher [1866] LR 1 Ex
348–349 7 265 at 279, 28–29
RIBA disciplinary proceedings, judicial review, 73 trespass, 29
350–351 Scotland, 291 Law Society of Scotland, 49
Investigations Panel (IP), ARB jurisdiction lawfulness, data protection, 368
(Architects Registration Board), 348 arbitration tribunals, 263–265 LCIA (London Court of International
invitation to tender document, 11 Scots law, 50 Arbitration), 263, 276, 280
invitations to treat, 11 Justice of the Peace Courts, Scotland, 47 Leading Oil and Gas Industry
IP (Investigations Panel), ARB Competitiveness (LOGIC), 230
(Architects Registration Board), 348 Keeper of the Registers, Scotland, 53, 56 leasehold ownership, 52
irremediable breach, 195 King’s Court, 6 leases, 43
King’s justice, 6 business tenancies, 43–44
JCT (Joint Contracts Tribunal), 178, knowledge, RIBA (Royal Institution of Scots land law, 56
233, 276 British Architects) code of conduct, legal duty to take care, negligence,
JCT 2016 suite, 234 384 21–22
collateral warranties, 239–240 Knowsley Heights fire (5 April 1991), legal justification for processing, data
collateral warranties/third party rights, 88–89 protection law, 368
235–238 legal presumption, boundaries (land),
sub-contractor collateral warranties, LABC (Local Authority Building 37–38
240 Control), 83 legal privilege, 370
JCT Constructing Excellence Contract labels, Public Sector Directive (EU), 147 legal profession, Scotland, 49
(JCT-CE), 225 LACoRS (Local Authorities legal systems of, UK, 3–4
JCT Construction Management Contract, Coordinators of Regulatory Services), legislation, 4
235, 237 99 Scots law, 46
JCT D&B 2016, 323 Lakanal House fire (3 July 2009), 89 letters of intent, contracts, 12
JCT Design and Build Contract, land levels, JCT Standard Building Contract,
235–236 boundaries, 37–38 186
JCT ICD 2016, 323 easements, 37 liabilities, NEC4 Professional Services
JCT Intermediate Contract, 235–236 licenses, 36–37 Contract, 218
JCT Management Building Contract, meaning of, 36–38 liability
235–237 trespass, 36 of applicants, Scotland, 109
JCT MP 2016, 323 land charges, 34–35 of directors (Scotland), 307
JCT MWD 2016, 323 land law, 33 of directors, companies, 300–301
JCT Prime Cost Building Contract, business tenancies, 43–44 employers’ liability, 304
235–236 easements, 38–40 health and safety, 165
JCT SBC 2016, 323 estoppel, 44 IChemE (Institution of Chemical
JCT Standard Building Contract, land charges, 34–35 Engineers), 229
235–236, 262, 263 landlord and tenant, 41–42 limited liability partnerships, 298
arbitration, 265, 272 local land charges, 36 for negligent conduct, 24
arbitration agreements, 264 meaning of ‘land’ and intrusions upon for negligent statements, 23–24
Articles of Agreement, 181–183 it, 36–38 of partners, 296–297
Consultancy Agreement (Public mortgages, 43 partnerships, 297
Sector), 311 registered land, 35–36 partnerships (Scotland), 305
Homeowner/Occupier Contract, 311 restrictive covenants, 40–41 professional negligence, 330–331
Schedules, 213–214 Scotland. see Scots land law public liability insurance, 304
Scotland, 230, 231 surveys of property to be purchased, RIBA Standard Professional Service
section 1: definitions and 43 Contract 2018, 219–220
interpretation, 183 title to land, 33–34 Scotland, 111
section 2: carrying out the works, unregistered title, 33 Scots law, 344–345
183–195 land ownership, 6 of shareholders, companies, 299–300
section 3: control of the works, Scots law, 51–52 sharing professional negligence with
195–199 Land Register, Scotland, 53, 54 others, 340–344
section 4: payment, 199–207 land registration, Scots land law, 53–55 of unauthorised agents, 20
section 5: variations, 207–209 Land Registry, 33 liability for design, JCT Standard
section 6: injury, damage, and land registry, 33 Building Contract, 184–185
insurance, 209–210 Lands Tribunal for Scotland, 54, 55 licensed work, asbestos, 166
section 7: assignment, performance LANTAC (Local Authority National licenses, 87, 362–363
bonds and guarantees, Third Party Type Approval Confederation) district councils, 71
Rights, and collateral warranties, scheme, 83 land, 36–37
210–211 lateness, JCT Standard Building RIBA Standard Professional Service
section 8: termination, 211–212 Contract, 192–193 Contract 2018, 219
settlement of disputes, 212–213 Latham, Michael, 241, 249, 375 Scotland, 76
Joining Agreement, PPC2000, 225 law of contracts, 9 Licensing Authority, 70, 87
Joint Contracts Tribunal (JCT), 178, law of tort, 9, 21 liens, 307
233, 276 apportionment of liability, 31 lifting operations and equipment, 170
Joint Fire Code, 102–103, 210 breach of statutory duty, 29 limitation of liability, NEC4 Professional
joint liability, JCT 2016 suite, 239 Defective Premises Act 1972, 26–27 Services Contract, 216
joint ownership, copyright, 361 inducing breach of contract/wrongful limitation periods, law of tort, 29–30
judge-made law, Scotland, 46 interference with contract, 29 limitations
judgments, 4 limitation periods, 29–30 assignments, 17
Judicial Committee of the House of negligence, 21–26 CIC/ConsWa/P&T (Collateral
Lords, 4, 45 nuisance, 27–28 Warranty Consultant--Purchaser/
remedies, 30–31 Tenant), 318
Index 411

JCT 2016 suite, 240 Lord Justice-General, Scotland, 47 minimum compensation, 131
Limitation Act 1980, 20 loss, economic loss, 23–26 Minister of Agriculture, Fisheries and
Scots law, 49–50 loss and expense, JCT Standard Building Food, 69
limited combustibility, 91, 94 Contract, 205–206 Minor Works Version -- August 2011,
limited liability partnerships, 295, 298 losses, contracts, 14 ICC (Infrastructure Conditions of
Scotland, 306 lump sum/fixed price, 178 Contract), 228
limited partnerships, Scotland, 306 misrepresentation
limited-life buildings, Scotland, 108 mains, construction of, 68 contracts, 15–16
limits on Architect’s powers, JCT maintenance, tenements (Scotland), 55 remedies for, 15–16
Standard Building Contract, 207 major developments, 128 missives, Scots land law, 53
limits of indemnity, 354 Scotland, 137 mitigation, damages, 340
Line of Junction Notice, party walls, 157 management contracting, 177–178 mixed contracts, Public Sector Directive
liquidated damages, JCT Standard management forecasts, 370 (EU), 145
Building Contract, 192–193, 194 manager burdens, Scotland, 53 Model Mediation Agreement, 284
liquified petroleum gas storage, managing an architectural business, 295 modern reforms to English law, 6–7
Scotland, 118 companies, 298–302 modern slavery, RIBA code of conduct,
listed building consent, 130–131 insurance, 304 386
listed building enforcement notices, 131, limited liability partnerships, 298 modifying, planning permissions,
140 partnerships, 295–298 129–130
listed buildings, Scotland, 139–140 premises and persons, 302–304 money, handling for clients, RIBA code
Listed Items, JCT Standard Building Scotland, 304–307 of conduct, 383
Contract, 204 mandatory exclusion grounds, Public monitoring, data protection law, 372
listing, special buildings, 130–131 Sector Directive (EU), 148–149 Moore-Bick, Martin James, 162
literary work, 359 mandatory injunctions, 31 moral rights, 366
litigation, 257–258 manifestation of physical damage test, mortgages, land law, 43
JCT Standard Building Contract, 213 30 motor vehicles, insurance, 304
LLPs (limited liability partnerships), 298 manual handling operations regulations, MPs (Scotland), 46
Local Authorities Coordinators of health and safety, 168–169 MSPs (Scotland), 46
Regulatory Services (LACoRS), 99 marketing emails, data protection law, multi-occupation, managing an
local authorities (England and Wales) 372 architectural business, 303
characteristics of, 60–64 Masterplan, 127 multi-party disputes, arbitration, 265
officers, 61 Masterplan Consent Areas, 140
local authorities (Scotland), 73–74 material alteration, 79 national development, Scotland, 137
local authority, defined, 81 material change of use, 79, 81, 90 National Grid, Scotland, 119
Local Authority Building Control material considerations, 121 National House Builders’ Council
(LABC), 83 development plan documents, 126 (NHBC), Scotland, 53
Local Authority National Type Approval Scotland, 138 National Housing Federation, 70
Confederation (LANTAC), 83 materials, 184 national legislation, 85–87
local authority procedures, planning law design, breach of obligation of national legislation, fire safety, 99–102
(England and Wales), 128 reasonable care, 336 National Park Authorities, 60
local development, Scotland, 137 mayors, 60 national parks, 123
local development documents, 64 means of escape, fire safety, 98 Scotland, 74, 136
Local Development Schemes, 63 measure and value contract, 222 National Parks Authority, Wales, 63
Local Government and Social Care measurement contracts, 178 National Planning Framework (NPF4),
Ombudsman, 62 Measurement Version -- August 2011, 135, 138
Local Government Commission, 59 ICC (Infrastructure Conditions of National Planning Policy Framework,
local government (England and Wales), Contract), 228 64, 121
59–60, 64 mechanical ventilation, Scotland, 119 National Planning Policy Guidelines
characteristics of local authorities, mediation, 213, 283, 285 (NPPGs), 135
60–64 advantages of, 285–286 National Rivers Authority, 65
distribution of planning functions, confidentiality, 284 Natural England, 65
63–64 costs, 284 natural lighting, Scotland, 117
local land charges, 36 disadvantages of, 286 Natural Resources Wales, 64, 65
local legislation online mediation, 286 Nature Conservancy Council, 65
Inner London, 85 preparation for, 285 NCC (net contribution clauses), 342–343
Inner London, fire safety, 98 privilege, 284 NEC (New Engineering Contract), 178
outside Inner London, 85 selecting mediators, 284 NEC4 (Short Contract), 215, 323
outside Inner London, fire safety, settlement of disputes, 285 NEC4 Professional Services Contract,
98–99 time for, 284 215–217, 323
local place plans, 138 mediators, selecting, 284 compensation events, 217–218
Local Plan, 64 membership, limited liability contract data, 218–219
local planning authorities, England and partnerships, 298 liabilities and insurance, 218
Wales, 123–124 Memorandum and Articles of parties’ main responsibilities, 217
Loch Lomond & the Trossachs National Association, 301 payment, 217
Park, 74, 136 Memorandum of Association, formation quality management, 217
LOGIC (Leading Oil and Gas Industry of companies, 299 rights of material, 218
Competitiveness), 230 metering, Scotland, 119 termination, 218
London Borough Councils, 59 MF/1, 230 NEC4ALC, 225
London Court of International MF/2, 230 negative burdens, Scotland, 53
Arbitration (LCIA), 263, 276 MF/3, 230 negative easements, 38
loose groups, companies, 301 MF/4, 230 negligence, 21, 234, 333
Lord Advocate, Scotland, 47 MHCLG, 82, 84 breach of duty, 22–23
Lord Justice-Clerk, Scotland, 47 minimising risks, 324–325 contributory negligence, 31, 340
412 Index

economic loss, 23–26 novation, contracts, 16–17 PANs (planning advice notes), 135
gratuitous services, 26 NPPF, 126, 128 parameter plans, 127
legal duty to take care, 21–22 NPPGs (National Planning Policy parish councils, 124
versus nuisance, 28 Guidelines), 126, 135 Part 20 proceedings, 31
professional negligence. see enforcement, 133 partial non-disclosure, 15
professional negligence nuisance, 21, 27–28 partial possession by employer, JCT
relationship to any duties existing in versus negligence, 28 Standard Building Contract, 194–195
law of contract, 22 Scots land law, 55–56 Partner Authority Scheme (PAS), 83
negligent conduct, liability for, 24 Partnering Agreements, ACA
negligent statements, liability for, 23–24 obiter dicta, 4 (Association of Consultant
Negotiated Procedure, award of public obligation of reasonable care and skill, Architects), 226
works contracts, 146–147 331–335 Partnering Terms, PPC2000, 226
negotiation, Concessions Directive (EU), breach of, 335–337 partnering/framework agreements, 178
152 obstruction of certificates, JCT Standard partnership, Scotland, 49
negotiations, 370 Building Contract, 212 partnership property, Scotland, 305
neighbour’ principle, 22, 29 offenses, Scotland, 111 partnerships, 300
neighbourhood plans, 63–64 offers, 11 associates, 296
net contribution clauses, 331 revocation of, 12 versus companies, 300–301
net contribution clauses (NCC), 342–343 Office of National Statistics (ONS), 160 deed of partnership, 296
New Engineering Contract (NEC), 178 Office of Public Sector Information, dissolution of, 297–298
New Engineering suite, 311 Scotland, 46 formation of, 295
new partners, Scotland, 306 officers liability, 297
new tenancy, business tenancies, 44 finding, 63 limited liability partnerships, 298
New York Convention, 262, 275, 276, local authorities (England and Wales), name of practice, 296
280 61 PPC2000, 226
NHBC (National House Builders’ powers of, 62–63 relationship of partners, 297
Council), Scotland, 53 responsibilities of, 63 rights and liabilities of partners,
No Oral Modification clauses, contracts, offices, 71 296–297
16 Official Journal of the European Union Scotland, 305–306
noise, Scotland, 118–119 (OJEU), 145, 148, 151 sharing facilities and profits, 295–296
non-combustible, 91 Official Referees, TCC (Technology and single-project partnerships, 301
non-completion certificates, JCT Construction Court), 257 size of practice, 296
Standard Building Contract, 192–193 Ofgem (Gas and Electricity Markets types of partners, 296
non-compliance with instructions, JCT Authority), 68 party autonomy, arbitration, 265
Standard Building Contract, 197 Ofwat, 66, 68 party fence walls, 157
non-disclosure, 15 OJEU (Official Journal of the European Party Structure Notice, party walls, 157
RIBA (Royal Institution of British Union), 145, 148, 151 party walls, 86, 155–156
Architects) code of conduct, 386 one-off disputes, 272 awards, 158
non-domestic premises, water supply, 68 online mediation, 286 building owner’s rights, 158
nondomestic premises, asbestos, 166 ONS (Office of National Statistics), 160 notices, 157
non-friable, asbestos, 166 Open Procedure, award of public works surveyors, 157
non-licensed work, asbestos, 166 contracts, 146 PAS (Partner Authority Scheme), 83
non-natural user of land, 28 operations, meaning of, 124 passive easements, 38
non-payment, right to suspend optional exclusion grounds, Public pathological arbitration clauses, 277
performance for, 245 Sector Directive (EU), 149 pay less notices, 202, 243–244
non-payment of certificates, JCT oral agreements, 310 determining true value, 245
Standard Building Contract, 212 oral contracts, 10, 12 pay when paid clauses, 246
Normans, 5–6 Scots land law, 53 payment
Northern Ireland, 3–4 oral hearings, international arbitration, CIC/ConsWa/P&T (Collateral
copyright, 366 278 Warranty Consultant--Purchaser/
notice, loss and expense, JCT Standard orders of competent authorities, Tenant), 318
Building Contract, 205–206 boundaries (land), 37 JCT Standard Building Contract,
Notice of discrepancies etc., JCT Ordinance Survey maps, 37 199–207
Standard Building Contract, 187–188 originality, copyright, 359 NEC4 Professional Services Contract,
notices ostensible authority, 20 217
of adjudication, 251 other property, 332–333 payment notices, 243–244
breach of obligation of reasonable Outer House, Scotland, 48 payment provisions, 242–243
care and skill, 338 outline applications, 127 contracts excluded from, 242
data protection, 368 outline permission HGCRA, 242
data protection law, 372 planning law (England and Wales), Payment Rules, HGCRA, 241
enforcement notices, 133 127 payments
Excavation Notice, party walls, 157 Scotland, 137 determining after failing to serve, 245
party walls, 157 outsourcing, data protection law, 372 interest on late payments, 246
pay less notices, 202, 243–244 overpayments, 339–340 PCC (Professional Conduct Committee),
payment notices, 243–244 ownership 348, 376, 377
planning applications, 127 client contracts, 311 Peckham fire, 2009, 103
Planning Contravention Notice, 140 copyright, 360–361 pedestrian protective barriers, Scotland,
preservation notices, Scotland, 54 ownership of land, 6 118
Prohibition Notice, 99 Scotland, 49 peers, RIBA code of conduct, 386
Temporary Stop Notices, 133 Scots law, 51–52 penalties, JCT Standard Building
notifiable non-licensed work, asbestos, Contract, 194
166 PAN (proposal of application notice), performance
notour bankruptcy, 306 137 Public Sector Directive (EU), 150
Index 413

Utilities Directive (EU), 151 listed building consent, 130 Scotland, 76


performance bonds, 210–211 modifying, 129–130 private wastewater treatment systems,
performance of contract, 17–18 revoking, 129–130 Scotland, 117
periodic inspection, breach of obligation Scotland, 136–137, 137–138, 138–139 privilege, mediation, 284
of reasonable care and skill, 337 Police Scotland, 73 privity of contract, 9, 18
permissive waste, 41 policy, 61 privity rule, 233
permitted development, 123, 125 positive easements, 38 Privy Council, 359
Scotland, 135, 137 possession, 6 pro indivisio ownership, Scotland, 52
personal injury, 30, 209–210 possession of the site, JCT Standard procedures
duty of care in tort to third parties, Building Contract, 185 Building Regulations 2010 (England
332 postal rules, 12 and Wales), 81
employers’ liability, 304 post-contractual remedies, Remedies for connecting sewers, 66
personal protective equipment, health Directives (EU), 153 international arbitration, 277–278
and safety, 168 postponement of work, Architect/ JCT Standard Building Contract, 194
personal rights, Scotland, 51 Contract Administrator’s instructions, procedures for award of public works
persons, managing an architectural 198 contracts, Public Sector Directive
business, 302–304 power to issue instructions, JCT (EU), 146–147
petroleum, 71 Standard Building Contract, 199 Procurator Fiscal Service, Scotland, 47
PFI (Private Finance Initiative), 178 powers of, officers, 62–63 procurement documents, Public Sector
PHE (progressive horizontal evacuation), PPC2000 (Amended 2013), 225–226 Directive (EU), 145
96 PPP (public private partnership), 178 procurement methods for construction
photographs, exceptions to copyright PPQs (pre-qualification questionnaires), projects
infringement, 361 146 client expertise, 175
PI (Personal Injury), Scotland, 48 Practical Completion, 30 commercial drivers, 175–176
plaintiff. see claimants practical completion, JCT Standard complexity, 175
plan lines, 37 Building Contract, 192–194 construction management, 177
Plan of Work Multi-Disciplinary Practical Completion Certificate, 209 design and build contracts, 177
Services, 312 practical insolvency, 306 design modification, 176
plan-led system, 121, 135 Pre-Action Protocol for Construction and design responsibility, 176
planning, RIBA code of conduct, 385 Engineering Disputes, 258, 284 fixed price, 176
planning advice notes (PANs), 135 precipitation, Scotland, 117 funding, 176
planning appeals, 126 pre-construction work stages, breach management contracting, 177–178
planning applications of obligation of reasonable care and partnering/framework agreements, 178
deciding, 126–127 skill, 335–337 PPP (public private partnership), 178
general publicity, 127 pre-contractual remedies, Remedies pricing mechanisms, 178
notices, 127 Directives (EU), 153 time, 176
other than permitted development, premises, managing an architectural traditional procurement, 176–177
125–126 business, 302–304 two-stage tendering, 177
permitted development, 125 premises for sale and supply of alcohol, procurement models
Scotland, 137 70 Concessions Directive (EU), 152
planning authorities, Scotland, 136 Scotland, 76 Utilities Directive (EU), 151
Planning Contravention Notice, 140 prescription procurement process
planning control process, 122–123 Scots law, 49–50 Concessions Directive (EU), 152
breach of obligation of reasonable servitudes (Scotland), 55 Public Sector Directive (EU),
care and skill, 335 Prescription Procedures, 376 147–148
Scotland, 140–141 preservation notices, Scotland, 54 Professional Conduct Committee (PCC),
Planning Inspectorate’s ‘Procedural prevention of unfair terms, contracts, 348, 376, 377
Guide,’ 126 14–15 professional disciplinary proceedings,
planning law (England and Wales), 121 price, PPC2000, 226 351
control of development, 125–130 pricing mechanisms professional indemnity insurance, 304,
enforcement of planning control, lump sum/fixed price, 178 319, 347, 354–355
132–133 measurement contracts, 178 CIC/ConsWa/P&T (Collateral
local planning authorities, 123–124 primary legislation, 4 Warranty Consultant--Purchaser/
Planning Acts, 121 prime costs, JCT Standard Building Tenant), 317–318
planning control process, 122–123 Contract, 207 professional liability, 327
special buildings, 130–131 Principal Contractors, 86 agency, 329
TCPA 1990, 121 duties of, 159 fitness for purpose, 327–328
Urban Development Corporations, health and safety, 170 honesty, 328–329
131–132 Principal Designers, 86 professional negligence, 327
planning law (Scotland), 135 principles, RIBA (Royal Institution of damages, 339–340
2019 Act, 141 British Architects) code of conduct, liability, 330–331
control of developments, 137–139 383–386 sharing liability with others, 340–344
enforcement of planning control, prior information notices, Public Sector professional negligence liability
140–141 Directive (EU), 148 lapse of time, 344
Enterprise Zones, 140 privacy, RIBA (Royal Institution of pure economic loss, 333–334
listed buildings, 139–140 British Architects) code of conduct, professional standards, ARB (Architects
meaning of development, 136–137 383 Registration Board) code of conduct,
planning permission, 124 private access, Scots land law, 55 381
Planning Permission in Principle, private companies, 299 professionalism, code of conduct. see
Scotland, 137 Private Finance Initiative (PFI), 178 code of conduct
planning permissions private law, Scotland, 46 profits
developments, 125–130 private nuisance, 27 companies, 299
duration of, 129 private streets, 68–69
414 Index

remedies for copyright infringement, Public Works Directive, 151 relevant claims, Scotland, 232
364 publication Relevant Events, JCT Standard Building
progressive horizontal evacuation (PHE), copyright, 360 Contract, 188, 190–191, 191–193
96 procurement process, Public Sector Relevant Matters, JCT Standard Building
Prohibition Notice, RRFSO (Regulatory Directives (EU), 148 Contract, 206
Reform (Fire Safety) Order 2005), 99 purchasers, collateral warranties/third relevant person, Scotland, 109
prohibitive injunctions, 30 party rights, 235 reliance, 15
Project Brief, RIBA Standard purchaser’s solicitors, 34 remedies
Professional Service Contract 2018, pure economic loss, professional against incomplete performers,
312 negligence liability, 333–334 contracts, 18
promisors, 19 purpose of annexation test, 41 Architects, 195
property for copyright infringement, 364
partnerships (Scotland), 305 qualifications, of arbitrators, 265 law of tort, 30–31
Scots land law, 51 qualifying person, 359–360 Remedies Directives (EU), 153
Property Chamber of the First Tier quality, RIBA code of conduct, 384 remedies for misrepresentation, 15–16
Tribunal, 41 quality management, NEC4 Professional removal of Crown immunity, Scotland,
property damage, 209–210 Services Contract, 217 111
property law, Scotland, 49, 51 quid pro quo, 10 renunciation, 18
property protection, fire safety, 94 servitudes (Scotland), 55
proposal of application notice (PAN), Ratification Period, 195 repairing covenants, landlord and tenant,
137 ratio decidendi, 4 42
proposals, insurance, 353 real burdens, Scots land law, 53–54 repairs, tenements (Scotland), 55
proprietary interests, 33 real rights, Scotland, 51 replacement local development plans,
prosecutions, under CDM 2015, 165 reasonable care, 22 Scotland, 138
protection, of business tenants, 43–44 Reasonable Cost, 75 representations, contracts, 15
proved acts of the parties, boundaries reasonable opportunity for discovery of reprimands, ARB disciplinary
(land), 37 defect, 333 proceedings, 349
provisional relief, 278 reasonable practicability, 160 repudiatory breach, contracts, 18
provisional sums Recitals, JCT Standard Building reputation of architects, ARB code of
Architect/Contract Administrator’s Contract, 181 conduct, 382
instructions, 198 recognition, international arbitration, 280 rescission, 16
JCT Standard Building Contract, 207 reconstruction, exceptions to copyright reservations, easements, 38–39
provisions, 85 infringement, 361 reserved matters applications, 137
public administration, Scotland, 73–74 record keeping, RIBA (Royal Institution residential occupiers, 242
public companies, 299 of British Architects) code of conduct, resignation, adjudication, 253
public contracts, Public Sector Directive 384 respect, ARB code of conduct, 382
(EU), 144 records of processing, 370 responsibilities of the architect, data
public law, Scotland, 46 rectification, 35 protection law, 370–371
public liability insurance, 304 IChemE (Institution of Chemical responsibility, 343
public nuisance, 27 Engineers), 229 responsibility for the work of others,
public private partnership (PPP), 178 rectification costs, 339 322–324
public procurement, EU law, 143–144 Red Book, FIDIC, 222 Responsible Person, 99, 161–162
public right to roam, Scots land law, 55 Red Book, 5th edition, 2013, 229 restricted acts, copyright, 359
public rights of way, Scots land law, 55 Red Book: Lump Sum, 228 Restricted Procedure, award of public
public roads, Scotland, 76 Reed, Lord, 48 works contracts, 146
Public Sector Directive (EU), 144 referral notice, adjudication, 252–253 restrictions, on right to contribution,
Article 18(2), 150 reforms to English law, 6–7 342–343
contract awards, 149–150 Register of Architects, 296 restrictions (Scotland), heritable
contract performance, 150–151 Register of Title, 35 property, 56
contracting authority, 144 registered designs restrictive covenants, 34
contracts excluded based on subject- EU (European Union), 366 discharge of, 41
matter, 145 UK, 365 land law, 40–41
contracts excluded based on value, registered land, 35–36 retention, JCT Standard Building
145 registered offices, Scotland, 306–307 Contract, 204–205
economic operators, 144 registered proprietors, 35 Retention Bond, 205
mixed contracts, 145 registered social landlords (RSLs), retiring, partners (Scotland), 305
procedures for award of public works Scotland, 76 Review Panel on Building Standards
contracts, 146–147 registration, land charges, 35 (Fire Safety) (29 June 2018), 105
procurement documents, 145 registration/notification, data protection revocation
procurement process, 147–148 law, 371 adjudication, 253
public contracts, 144 regularisation certificate, 82 of offers, 12
public services contracts, 145 Regulations, 4 revoking, planning permissions, 129–130
public supply contracts, 145 regulations, European law, 46 RIAS (Royal Incorporation of Architects
public works contracts, 144–145 Reid, Lord, 27 in Scotland), 379
scope of applications, 145 reinstatement costs, 339 code of conduct, 386–388
public services contracts, Public Sector relationships, RIBA (Royal Institution of RIBA (Royal Institution of British
Directive (EU), 145 British Architects) code of conduct, Architects), 161, 296, 376, 379
Public Services Ombudsman for Wales, 385–386 arbitration, 277
62, 63 relative moral blameworthiness, 31 code of conduct, 382–386
public supply contracts, Public Sector relative responsibility, 31 contracts, 215, 228
Directive (EU), 145 relaxations, Building (Scotland) Act disciplinary proceedings, 347–348,
public works contracts, Public Sector 2003, 107 350–351
Directive (EU), 144–145 relevant buildings, 90, 91, 94, 96 RIBA 2018, arbitration, 266
Index 415

RIBA Architect’s Appointment, 362–364 risk Building Regulations. see Building


RIBA Code of Professional Conduct, ICC (Infrastructure Conditions of Regulations (Scotland)
184, 295, 311, 347 Contract), 227 building regulations compliance
companies, 299 PPC2000, 226–227 notice, 110
RIBA Concise Professional Services risk assessment, fire safety, 99 Building Standards assessment,
Contract 2018, 220, 228 risk management, insurance, 355 109–110
RIBA Concise PSC 2018, 312 rivers/streams, boundaries (land), 38 Building Standards Register, 110
RIBA Domestic Building Contract 2018, Robens, Alfred, 160 building warrants, 107–109
228, 312, 313 Roman law, 47 canon courts, 45
RIBA Domestic Professional Services root of title, 34 Care Homes, 76
Contract 2018, 220 Royal Incorporation of Architects in civil courts, 48
RIBA Plan of Work, 312 Scotland (RISA), 314, 379 companies, 306–307
RIBA Principal Designer Professional code of conduct, 386–388 completion certificates, 109, 109–110
Services Contract 2018, 220 Royal Institute of Chartered Surveyors, connections to sewers, 74–75
RIBA Professional Services Contracts, Scotland, 49 construction sites, 77
311–312, 343 Royal Institution of British Architects. continuing requirements enforcement
RIBA Standard Agreement 2010 (2012 see RIBA, 375 notice, 110
revision), 325 Royal Town Planning Institute, Scotland, copyright, 366
RIBA Standard Agreement for, 49 court structure, 47–49
Conditions of Engagement, 362 RSLs (registered social landlords), 76 devolution, 45–46
RIBA Standard Forms of Agreement, Rule of Law, 3 drains, 75
336 rural housing burdens, Scotland, 54 entry, inspection, and tests, 111
RIBA Standard Professional Service rural parishes, 60 environment, 116–118
Contract 2018, 219, 228, 311–313, European law, 46
323, 330, 375 safeguarding clients’ money, ARB code fees, 113
RIBA Sub-Consultant Professional of conduct, 381 fire safety, 114–116
Services Contract 2018, 220 safety, Building Regulations (Scotland), footpaths, 76
RIBA Sub-consultant PSC 2018, 312, 118 forms, 113
323 safety records, construction, 163 grants, 76
RIDDOR, 167 salaried partners, 296 historical context, 45
right to access, data protection law, 369 sale of land and buildings, Scots land human rights, 46
right to be forgotten, data protection law, law, 52–53 independence, 46
369 sales-speak, 15 legal profession, 49
right to buy, Scots land law, 56 sanctions, RIBA code of conduct, 384 liability, 111
right to contribution, 341–342 sanitary facilities, Scotland, 117 liability of applicants, 109
restrictions on, 342–343 SAR (subject access right), 369 licenses, 76
right to data portability, data protection Saudi Arabia, arbitration, 276 limited-life buildings, 108
law, 369 SBCC (Scottish Building Contracts litigation, 258
right to erasure, data protection law, 369 Committee), 230 local authorities, 73–74
right to information, employees, 303 SBCC Agreement, 287 managing an architectural business,
right to object, data protection law, 369 SBCC Arbitration Clause, 288 304–307
right to rectification, data protection law, SCCs (Standard Contractual Clauses), national legislation affecting building,
369 371 120
right to restriction of processing, data schedule of dilapidations, 42 national parks, 74
protection law, 369 Schedule of Services, RIBA Standard permitted development, 135
right to sue on partial performance of a Professional Service Contract 2018, planning authorities, 136
complete contract, 17–18 313 planning law, 135
right to suspend performance for, non- Schedules, JCT Standard Building premises for sale and supply of
payment, 245 Contract, 213–214 alcohol, 76
rights Scheme, adjudication, 249–252, 253 private streets, 76
moral rights, 366 Scheme of Delegation, 138 public administration, 73–74
Scots land law, 51 S-Con-07-A, 246 registered social landlords (RSLs), 76
rights of directors, companies, 300–301 scope of applications relevant person, 109
rights of light, easements, 40 Concessions Directive (EU), 152 removal of Crown immunity, 111
rights of material, NEC4 Professional Public Sector Directive (EU), 145 rights, 51
Services Contract, 218 Scotland, 4, 45. see also Scots law sheriffdoms, 47
rights of parties after determination, JCT adjudication, 289–291 Simplified Planning Zones (SPZs),
Standard Building Contract, 212 appeals, 111 140
rights of parties after termination by applications for warrants, 112 sports grounds, 76
employer, JCT Standard Building appointments, 314 trade effluent, 75
Contract, 211–212 approved certification schemes, 108 unauthorised occupation or use, 109
rights of partners, 296–297 approved certifiers of construction, Water Industry Commission, 74
rights of shareholders, companies, 109 water supply, 75
299–300 approved certifiers of design, 108 workplaces, 76
rights of support, easements, 40 arbitration, 287–289 Scots land law, 51
rights of those who are not contracting boundary structures, 158 access rights, 55
parties, 18–19 Building (Forms) (Scotland) boundary walls and support, 55
rights of way, easements, 40 Regulations 2005, 113 classification of property, 51
rights to connection Building (Procedure) (Scotland) land registration, 53–55
sewers, 66 Regulations, 112–113 leases, 56
water supply, 67–68 Building (Scotland) Regulations 2004, nuisance, 55–56
RISA (Royal Incorporation of Architects 113 restrictions on heritable property, 56
in Scotland), 314 building contracts, 230–232 rights, 51
416 Index

sale of land and buildings, 52–53 service conditions, Scotland, 54 specialist sub-contractors, 323
tenements, 55 servitudes minimising risks, 325
title conditions, 53 Scotland, 54–55 specialist suppliers, 324
Scots law, 45 Scots land law, 53 minimising risks, 325
authoritative writings, 47 Session Cases, Scotland, 47 speculative work, client contracts,
branches of, 49 settlement of disputes 313–314
case law, 46–47 JCT Standard Building Contract, Sport England, 65
categorisation of, 46 212–213 Sport Wales, 65
court structure, 47–49 mediation, 285 Sports Council for England, 65
jurisdiction, 50 severance, adjudication, 255 Sports Council for Wales, 65
land ownership, 51–52 Severe Acute Respiratory Syndrome sports grounds, Scotland, 76
legislation, 46 Coronavirus-2 (SARS-CoV-2) (‘C- SPPs Scottish Planning Policies (SPPs),
liability, 344–345 19’), 159–160 135
limitation of actions/prescription, sewers, 64, 66–68 spread of fires, fire safety, 116
49–50 Building Act 1984, 84 SPZs (Simplified Planning Zones), 123,
Scots Law Times, 47 Scotland, 74–75 132
Scottish Building Contracts Committee SFA/92, 227 Scotland, 140
(SBCC), 230 SFA/99, 227 SSSIs, 65
Scottish Building Standards Agency, 105 shared ownership, Scotland, 52 stairs, Scotland, 118
Scottish Councillors, 73 shareholders, rights and liabilities, Standard Building Contract, 181
Scottish Courts Service, 47 299–300 changes to 2011 edition, 181
Scottish Environment Protection Agency, shares, 307 changes to 2016 edition, 181
74, 138 sharing liability for professional Standard Conditions of Appointment for
Scottish Government, 46 negligence with others, 340–344 an Architect 2010 (2012 Revision),
Scottish Housing Regulator, 76 Sheriff Appeal court, Scotland, 47, 48 330, 343
Scottish Land Court, 48 Sheriff Courts, Scotland, 47, 48 Standard Contractual Clauses (SCCs),
Scottish Law Commission, 51 Sheriff Personal Injury Court, 258 371
Scottish Ministers, 46, 106, 135 sheriffdoms, Scotland, 47 standard form contracts, 15
planning authorities, 136 shops, 71 Standard Method of Measurement
verifiers, 107 short procedures, ICE Procedure, 270 (SMM), 185
Scottish National Heritage, 138 SIAC (Singapore International standards
Scottish National Party, 46 Arbitration Centre), 276 ARB code of conduct, 380–382
Scottish Natural Heritage, 74 Silver Book, FIDIC, 222 technical harmonisation and standards,
Scottish Parliament, 46 Silver Book, 1st edition, 2017, Orange 87–88
Scottish Planning Policies (SPPs), 135 Book, 3rd edition, 2018, 228 Standards Boards for England and
Scottish solicitors, 49 Simplified Planning Zones (SPZs), 123, Wales, 62
Scottish Standard Form Building 132 stare decisis, 4
Contract, 287 Scotland, 140 starting developments, England and
Scottish Water, 73, 74–75 Singapore International Arbitration Wales, 129
SCWa/F, 240 Centre (SIAC), 276 statement of case, arbitration, 266–267
SCWa/P&T, 240 single occupation, managing an statement of existing fact, 15
SDPAs (strategic development plan architectural business, 303 statements, RIBA (Royal Institution of
authorities), 138 single-project partnerships, 301 British Architects) code of conduct,
SDS (spatial development strategy), 63 site investigation, breach of obligation of 383
seashores, boundaries (land), 38 reasonable care and skill, 335 statutory adjudication, 261
secondary losses, infringement, 364 site meeting minutes, JCT Standard statutory immunity, officers, 62
Secretary of State, 60 Building Contract, 199 statutory undertakers, 66–68
‘call in’ the application, 127 site notices, developments, 128 stay-put, 93
Secretary of State for Culture, 64 site preparation, Scotland, 116 step-in rights, JCT 2016 suite, 239–240
Secretary of State for the Environment, site visits, 324 Stollard, Paul, 105
Food and Rural Affairs, 64 six-pack, 167 Stop Notices
Secretary of State for Transport, 70 smash and grab claims, 245 planning law (England and Wales),
Secretary of States for Housing, SMM (Standard Method of 133
Communities and Local Government, Measurement), 185 Scotland, 140–141
122 SNH (Scottish Natural Heritage), 74 STPC2005 (Issued 2010) –ACA
section 106 agreements, TCPA 1990, social-distancing, 171 Standard form of Specialist Contract
128–129 sole traders for Term Partnering, 225
security, data protection law, 370 contract of engagement, 310 strategic development plan authorities
security breaches, 370 Scotland, 305 (SDPAs), 138
selection criteria, procurement process, solid waste storage, Scotland, 118 streets, private streets, 68–69
Public Sector Directives (EU), 148 spatial development strategy (SDS), 63 structural protection, fire safety, 114
selection of tenderers SPC2000 (Amended 2008) – ACA Sub-Consultancy Agreement, 311
Concessions Directive (EU), 152 Standard Form of Specialist Contract sub-consultants, 309–310, 323
Public Sector Directive (EU), 149 for Project Partnering, 225 minimising risks, 325
Utilities Directive (EU), 151 SPC2000 Short Form (Issued 2010) sub-contracting, JCT Standard Building
SEPA (Scottish Environment Protection –ACA Standard Form of Specialist Contract, 196
Agency), 74 Contract for Project Partnering, 225 sub-contractor collateral warranties, JCT
separate legal entity, Scotland, 305 special buildings, planning law (England 2016 suite, 240
separate legal personas, companies, 299 and Wales), 130–131 sub-contractors
separate tenements, Scotland, 52 special classes of building, 87 health and safety, 170
separation, fire safety, 114 special premises, 70–71 specialist sub-contractors, 323
separation distances, 103 special procedure for experts, ICE subject access right (SAR), 369
service companies, 301 Procedure, 270 submission agreements, 277
Index 417

subrogation, 322 NEC4 Professional Services Contract, traders, 14


insurance, 355 216, 218 traditional procurement, 176–177
SUD (Sustainable Urban Drain), 74 of partnerships (Scotland), 306 transfer of rights, NEC4 Professional
Sun Valley Poultry fire (6 September RIBA Standard Professional Service Services Contract, 216
1993), 89 Contract 2018, 220 transfers of personal data outside EEA,
sunset clause, 2019 Act, 141 terms implied by custom, contracts, 13 371
Supplementary Agreements, RIBA terms implied by statute, contracts, transparency
Standard Professional Service 13–14 Concessions Directive (EU), 152
Contract 2018, 312 terms implied by the court, contracts, 13 data protection, 368
Supreme Court of Judicature, 6 terms of contracts, 12–14 procurement process, Public Sector
Supreme Court (UK), 4, 6 terms of insurance policies, 354 Directives (EU), 148
surface water drainages, Scotland, 116 test of reasonableness, 14 Utilities Directive (EU), 151
surveyors, party walls, 157 testing, IChemE (Institution of Chemical treaties, Treaty on the Functioning of the
surveys Engineers), 229 EU (TFEU), 143
breach of obligation of reasonable tests, Scotland, 111 treatment plants, Scotland, 117
care and skill, 335 TFEU (Treaty on the Functioning of the Treaty on the Functioning of the EU
of property to be purchased, 43 EU), 143 (TFEU), 143
suspension, RIBA Standard Professional thalweg, boundaries (land), 38 trespass, 21, 29
Service Contract 2018, 220 theatres, 70 land, 36
sustainability, Scotland, 106 third parties, 9 true value, determining after failing to
Sustainable Urban Drain (SUD), 74 collateral warranties, 233, 235 serve payment or pay less notices,
system of duty holders, 162 duties to, 322 245
duty of care, 331 trustworthiness, ARB (Architects
TAC-1 (Term Alliance Contract), 227 rights of those who are not Registration Board) code of conduct,
TCC (Technology and Construction contracting parties, 18–19 381
Court), 257–258, 262, 283 Third Party Rights, 210–211, 322 two-stage tendering, construction
technical guidance, Building Regulations JCT Standard Building Contract, 214 projects, 177
(Scotland), 106–107 third party rights types of loss, damages, 339–340
technical handbooks employers, 234–235
Building Regulations (Scotland), 107 funders, 235 UCC (Universal Copyright Convention),
Scotland, 120 importance of, 234 357
technical harmonisation and standards, JCT 2016 suite, 235–238 UK, legal systems of, 3–4
87–88 obligation to provide, 315–316 UK design law, 365–366
technical requirements, Building purchasers, 235 UK Intellectual Property Office, 365
Regulations 2010 (England and tenants, 235 UK Parliament, 46
Wales), 80 three-stage test, 22 UK Register of Architects, 161
technical specifications, Public Sector tilted planning balance, 126 UK registered designs, 365
Directive (EU), 147 time UK Supreme Court, Scotland, 48–49
Technology and Construction Court, 13 construction projects, 176 UK unregistered design right, 365–366
Technology and Construction Court JCT Standard Building Contract, ultra vires (outside the body’s power),
(TCC), 257–258, 262, 283 188–191 4, 60
telephones, Scotland, 75–76 liability for professional negligence unauthorised building work, Building
temporary buildings, 98 barred by lapse of time, 344 Regulations 2010 (England and
temporary finality, adjudication, 249 NEC4 Professional Services Contract, Wales), 83
Temporary Stop Notices, planning law 217 unauthorised occupation or use,
(England and Wales), 133 RIBA code of conduct, 384 Scotland, 109
tenants time limits UNCITRAL Arbitration Rules, 277,
collateral warranties/third party rights, for claiming contribution, 344 278–279
235 enforcement of planning control, 132 UNCITRAL Model Law for arbitration,
exceptions to repairing obligations, 42 time-bar 260, 275, 288
tenant’s fixtures, 42 arbitration, 264 under seal, contracts, 10
tender, criteria to determine winning arbitration (Scotland), 288 undertaking to others, NEC4
tender, Public Sector Directives (EU), Scotland, 232 Professional Services Contract, 216
148 title conditions, Scots land law, 53 undesignated heritage assets, 64
tender action, breach of obligation of title register, 33 unilateral contracts, 9
reasonable care and skill, 336–337 title to land, 33–34 unitary authorities, 123–124
tender documentation, 336 tortious duties, 21 Scotland, 136
tenderers, selection of, Public Sector torts, 9. see also law of tort United Nations Commission on
Directives (EU), 149 concurrent duty of care, 330–331 International Trade Law, 275
tendering for services, client contracts, contract and concurrent duty of care, Universal Copyright Convention
313–314 331–332 (UCC), 357
tenement, 38 duties arising in, 322 unlimited companies, 299
Scots land law, 55 liability for professional negligence unregistered design right, UK, 365–366
tenure, 6 barred by lapse of time, 344 unregistered designs, EU (European
Term Alliance Contract (TAC-1), 227 trespass, 36 Union), 366
Term Version -- August 2011, ICC TPC2005 (Amended 2008) -- ACA unregistered title, 33
(Infrastructure Conditions of Standard Form of Contract for Term up-and-down theory of contractual
Contract), 228 Partnering, 225 liability, 18
termination trade effluent, 67 Urban Development Area, 123
of business tenants, 43 Scotland, 75 urban development areas, 131
of client contracts, 310–311 trade effluent discharges, into public Urban Development Corporations,
JCT Standard Building Contract, sewers, 67 131–132
211–212 trade effluent notices, 67 Use of Planning Conditions, 138
418 Index

Utilities Directive (EU), 151–152 fire safety and amendments to Welsh Ministers, 60, 62
utilities procurement, Utilities Directive Building Regulations, 91–92 White Book, FIDIC, 223
(EU), 151 local planning authority, 63 without prejudice, arbitration, 267
well-being power, 60 witnesses, planning appeals, 126
valuation of off-site materials, JCT walls, boundaries (land), 38 work at height regulations, 167
Standard Building Contract, 204 warranties, 18 work equipment, health and safety,
valuation rules, JCT Standard Building collateral warranties, 19 169–170
Contract, 207 Warranty Agreement, 233 work not in accordance with contract,
valuations, breach of obligation of waste, 41 Architect/Contract Administrator’s
reasonable care and skill, 338 Waste Regulation Authorities, 65 instructions, 198
variation wasted expenditures, 339 workmanship, 184
contracts, 16 wastewater drainage, Scotland, 116 architect’s responsibilities, 324
JCT Standard Building Contract, water, 64 contracts, 325
207–209 water discharges, into rivers or not in accordance with contract, 198
servitudes (Scotland), 55 seas, 67 workplace injuries, 160
Variation and Acceleration Quotation Water Industry Commission, workplace regulations, 167–168
Procedures, JCT Standard Building Scotland, 74 workplaces
Contract, 213 Water Services Regulation Authority, health and safety, 167–168
variation instruction, JCT Standard 66, 67 Scotland, 76
Building Contract, 209 water supply, 67–68 World Heritage Site, 123
Variation Quotation, 204, 209 Building Regulations 2010 (England World Trade Organization
vehicle protective barriers, Scotland, 118 and Wales), 85 (WTO), 144
ventilation, Scotland, 117, 119 grants, 70 written contracts, 10
verifiers, Scotland, 107 Scotland, 75 written information, Scotland, 119
Victorian reforms to English law, 6 waterwater treatment, Scotland, 117 wrongful interference, law of
video-conferencing software, mediation, wayleaves, 68 tort, 29
286 weather delays, 192 WTO (World Trade Organization), 144
voluntary waste, 41 websites, data protection law, 373
well-being power, 60 Yellow Book, 228
Wales, 4 Welsh Assembly, 59, 60, 62 Yellow Book, 4th edition, 2013, 229
ADB Volume 1 Dwellinghouses, 95 Welsh Government, housing corporation
ADB Volume 2 Buildings other than loans, 70
dwellinghouses, 95–96 Welsh law, 4

You might also like