DATE SWGR NAME LEVEL FINISHED Testing activities Remaining activities

1.CT FINISHED
2.VT FINISHED
3.BREAKER FINISHED
4.RELAY FINISHED
1.INCOMER FUNCTIONAL CHECK
08.02.2020 MD-A L-6 5.POWER METER FINISHED
2.Primary injection
6.BUS WIRING FINISHED
7.OUTGOING FUNCTIONAL CHECK
FINISHED
8.BUS BAR CRM FINISHED

1.CT FINISHED
2.VT FINISHED
3.BREAKER FINISHED
4.POWER METER FINISHED 1.Relay testing ongoing
08.02.2020 MD-B L-6 5.BUS WIRING FINISHED
2.Primary Injection
6.OUTGOING FUNCTIONAL CHECK
FINISHED
7.BUS BAR CRM FINISHED

1.CT FINISHED.
2.VT FINISHED.
3.BREAKER FINISHED.
4.POWER METER FINISHED
5.BUS WIRING FINISHED.
08.02.2020 M2T2A L22 6.OUTGOING FUNCTIONAL CHECK 1.MCCB /OUTGOING
FINISHED.
7.Functional Check finished
buscoupler/incoming
8.Micrologic Relay Finished
9.BUS BAR CRM FINISHED

1.CT FINISHED.
2.VT FINISHED.
3.BREAKER FINISHED.
4.POWER METER FINISHED
5.BUS WIRING FINISHED.
08.02.2020 M2T1A L22 6.OUTGOING FUNCTIONAL CHECK 1.MCCB /OUTGOING
FINISHED.
7.Functional Check finished both
buscoupler/incoming
8.Micrologic Relay Finished
9.BUS BAR CRM FINISHED
1.CT FINISHED.
2.VT FINISHED.
3.BREAKER FINISHED.
1.Power Meter
5.BUS WIRING FINISHED.
2.Micrologic Relay
08.02.2020 S22-AE L22 6.OUTGOING FUNCTIONAL CHECK
3.Primary Injection
FINISHED. 4.outgoing MCCB Testing
7.Functional Check finished
incoming
8.BUS BAR CRM FINISHED.
Remaining activities Remarks

1.INCOMER FUNCTIONAL CHECK


1.Interlock Done by without control cables .
2.Primary injection

1.Relay testing ongoing


1.Interlock Done by without control cables .
2.Primary Injection

1.Interlock Done by without control cables .


1.MCCB /OUTGOING
2.Primery injection done and measured current and voltage.

1.Interlock Done by without control cables .


1.MCCB /OUTGOING
2.Primery injection done and measured current and voltage.
1.Power Meter
2.Micrologic Relay 1.Interlock Done by without control cables .
3.Primary Injection 2.Primery injection done and measured current and voltage.
4.outgoing MCCB Testing