This document explains the process and requirements to complete and submit a
Quality Assurance and Mechanical Report for Symbia E / S / T, Symbia Intevo
and e.cam.
The Siemens installer is required to fill out the electronic Quality Assurance
Report and his portion, if any, of the Mechanical Report. The installer is required
to submit both electronic documents, and follow their country specific process.
All Reports must be completed fully. There are drop down and check boxes for
various tasks. If a task or option is not part of system startup, “N/A” option must
be selected. Some task boxes require manual entry of “N/A”.
The Reports can be downloaded from the CB-DOC’s link located on the Siemens
Service Intranet, under Installation.
10908999, Rev.01
3.) Measurement Tools section: Enter all calibrated tools used during
installation; “N/A” any unused section.
5.) Installation Corrective Action section: Following Steps 1 through 16, for
Mechanical Phase, if any corrections are performed, “Yes” must be
selected, and you must indicate which step it corresponds to, and describe
the corrective action that was taken.
6.) Parts Replaced section: Following Steps 1 through 16, for Mechanical
Phase, if any parts are replaced, “Yes” must be selected, and you must
indicate which step it corresponds to, and describe what part number was
replaced.
Expected
Alignment operation Orientation Value Level value Range
Baseframe in
Gantry level left/right ▲
center (backside) 0.01▼ 0 0.02
(roll) of gantry ▼
2.) System type section: A drop down menu is indicated by the ◄ symbol;
select the system type. Enter serial number and network information. See
example below.
4.) SPECT Camera Verifications section: Check “Pass” box when test for
Pedestal and Tuning is successful.
7.) Center the Source section: For Symbia E and e.cam only. Enter system
values manually.
8.) COR Calibration section: For Symbia E and e.cam only. Enter results for
single head system only. If you have a dual head system, check the “N/A”
box.
9.) MHR Calibration sections: There are 3 MHR TOMO angles: 180, 90 and
76. Four collimator sets can be entered for each angle. The ◄ symbol
indicates a pull down menu. Select the collimator type that applies to the
TOMO angle, and enter corresponding data. In the example below, only
LEHR and MEDLP collimators are part of the customer’s system. Note
that the other 2 collimator selections are “N/A”.
Center of Rotation
-0.73 4.72 -2.07 3.11
(mm) < ± 10.0
11.) NCO Calibration section: For Symbia E and e.cam only. Complete if
applicable or check the “N/A” box.
14.) AQC Verification section: For Symbia S, Symbia T and Symbia Intevo
only. Complete if option is present.
17.) System Backup section: Check box to indicate a backup was performed.
19.) Parts Replaced section: For Commissioning Phase, if any parts are
replaced, “Yes” must be selected and you must enter part number and
description of part replaced.
20.) Installation Instructions section: In this section, select the drop down
menu to “N/A” or choose the Quality procedures used for the
commissioning phase. Below example indicates the procedure for Symbia
S / T with IQ.SPECT.
PROCEDURES
Startup and QC Procedure for Symbia S And T Series 10052638 ◄
IQ SPECT Option for Symbia S and T Series 10182753 ◄
N/A ◄