4.7 Radiation Protection

Angiography room : The walls, the ceiling, the floor, the observation window, and all entrance/exit
doors of the room require radiation protection work as specified by the local
laws or regulations.

4.8 Power Requirements

This system requires power supply facilities which supply power to the system transformer from
the power distribution board of the facility. The rooms that contain each unit should be provided
with power supply facilities that satisfy the requirements listed below. For the power requirements
of each unit, refer to subsection 7.1 "Electrical Power Supply Specifications".

Power supply Three-phase power supply Single-phase power supply


Power consumption 150 kVA or more 6 kVA or more
Recommended power transformer: Recommended power transformer:
100 kVA or more 6 kVA or more
Line voltage for power Three-phase 380/400/415/440/480 V Single-phase 200/220/230/240 V
facilities
Circuit breaker 100 A (400 V) 40 A
150 A (200 V)
Characteristics of the <1> <For 400 V> The circuit breaker must not trip at
circuit breaker 600 A for 0.01 second.
The circuit breaker must not
trip at 200 A for 10 seconds.
The circuit breaker must not
trip at 400 A for 1 second.
The circuit breaker must not
trip at 1000 A for 0.01 second.
(Estimated in-rush current
when the power is turned ON.)
<2> <For 200 V>
The circuit breaker must not
trip at 400 A for 10 seconds.
The circuit breaker must not
trip at 800 A for 1 second.
The circuit breaker must not
trip at 1600 A for 0.01 second.
(Estimated in-rush current
when the power is turned ON.)

4.9 Air Conditioning Requirements

An air conditioning facility is required to satisfy the operating environmental requirements, including
ambient temperature and relative humidity. For details of each unit's heat generation and air
conditioning work, refer to section 8 "AIR CONDITIONING WORK".