You are on page 1of 1

OFFICE OF THE

EXECUTIVE ENGINEER
QADIRABAD-BALLOKI LINK CANAL DIVISION
FAROOQABAD
xen-qblink@irrigation.punjab.gov.pk
056-3863045

To
Muhammad Arif Associates,
Government Contractor,
R/O Sheikhupura.
No_____________/9-A, Dated _____________2021
Subject: - ACCEPTANCE FOR THE WORK “APPLYING KHANKI MIXTURE TO HYDRAULIC GATES AND PAINTNG SUPER
STRUCTURE OF FALL OF JHANG AND RAKH BRANCH AT TAIL OF LCC FEEDER CANAL AT RD. 103+492".

Reference:- Your tender dated 29.12.2021.

It is notified that your tender for the subject cited work @ 0.01% below as per prevailing MRS is hereby accepted being
the lowest with a cost of Rs. 1,51,444/- (Rupees One Lac Fifty One Thousand Four hundred & Forty Four only) based on your quoted
rates as detailed below:
As per T.S Estimate Quoted / Approved Rate
Sr.# Rate 0.01% below as per
Description of items Quantity Rate Unit Amount Amount
prevailing MRS rates
Scrapping, brushing and removing
1 old paint from metal surface 80% of 3110 1531.20 % Sft 47620 1531.05 47616
total quantity.
Painting iron guard bars, gates of iron
bars, grating, railing (including
2 3887.52 730.80 % Sft 28410 730.73 28407
standards, braces etc.) and similar
open work two coats.
Scrapping from hydraulic gates
3 1506 1531.20 % Sft 23060 1531.05 23058
Khanki Paint
Applying Khanki Mixture hot to
4 1882.41 1148.05 % Sft 21611 1147.94 21609
barrage gates two coats
Painting two feet vide gauges reading
5 60 164.45 Per Rft 9867 164.43 9866
to 10th of a foot (Metre)
Total 130568 130555
PST 16% 20891 20891 20889 20889
G.Total 151459 151444
The work is to be completed within Closure Period under the supervision of the Sub Divisional Officer Hafizabad Link Sub Division
Hafizabad under the contractual obligations and conditions to the following requirement:
1. All the codal formalities shall be strictly observed before and during execution of work.
2. The work is to be completed within specified time period however if you fail to execute/complete the work within scheduled time period
then compensation of delay will be recovered as per contract agreement.
3. The department is at full liberty to revise quantities (increase or decrease) depending upon the site conditions and you will have no claim
in any court of law against such revision.
4. The department shall not accept any responsibility for the loss suffered by you due to interruption of work on any account except as
provided in the agreement.
5. Any item of work not mentioned in bid schedule if got executed from contractor at site shall be paid as per rates approved by the
competent authority and the market rate prevailing at the time of technically sanctioned estimate shall form the basis for such approval.
6. All quality control and quantity assurance tests of works and materials will be carried out through the department at the cost of contractor
as and when required.
7. You would have to execute the work strictly according to the design, drawing and specifications under the supervision of the Sub
Divisional Officer Hafizabad Link Sub Division.
8. The payment will be made subject to the availability of funds as well as clearance of executed work by the 3 rd Party Monitoring
Consultants or any other committee constituted by the Government.
You are requested to attend the office of SDO Hafizabad Link Sub Division, Hafizabad for getting necessary instructions and guidance
to start the work. Moreover, you are also requested to attend the office of undersigned within 03 days from the date of issuance of this
acceptance letter along with following documents for making part of your contract agreement. In case of failure, your contract will stand
automatically cancelled/withdrawn and earnest money will be forfeited.
I. A detailed working schedule alongwith organizational chart.
II. Attested copy of Partnership Deed/Power of Attorney/CNIC
III. Copy of valid License from Pakistan Engineering Council.
IV. Copy of Enlistment / Renewal Letter alongwith Government Receipt for the year 2021-22.
V. Income Tax certificate from Income Tax Department / NTN

Executive Engineer,
Qadirabad Balloki Link Canal Division,
Farooqabad.

C.C.
1. Sub Divisional Officer, Hafizabad Link Sub Division Hafizabad. He is directed to intimate the date of actual commencement of the
work at site promptly and intimate the progress of the work day to day and also to complete the work as per Departmental
specifications.
2. Resident Engineer Third Party Monitoring Consultant, Faisalabad for kind information.