Professional Documents
Culture Documents
2. Scheduling
3. Critical Path
4. Example
1. Scope
What is scope?
Quality
Scope Cost
What is project success?
In many engineering projects safety can be considered as a key indicator of a
projects success…
Safety
Measuring a projects success
Time bound project Projects must be delivered on time, i.e. the opening of the
millennium dome, even if this is at the expense of cost,
scope, and safety
Cost bound project Projects must be delivered within cost, i.e local authority
funding for new housing provision may result in a
reduction of units (scope)
Scope bound project Project must be delivered to meet the initial scope i.e the
launch of a new project may be delayed to allow for
further testing to meet scope and quality requirements
Safety bound project Safe practices must be built into every project to meet the
needs of the Health and Safety at Work Act.
Under New Labour Government Tony Blair stated five benefits for the
Millennium Dome:
Blair, T (1998) ‘Why the Dome is good for Britain’, People’s Palace
Speech, Royal Festival Hall, 24 February pp1-5
The Millennium Dome
• The content should inspire people:
• The project was littered with disagreements between designers, and
sponsors
• It should have national reach
• What does this mean?
• The management of the project should be first rate
• There was no clear communication protocols between NMEC,
designers, sponsors, contractors.
• It should not call upon the public purse
• Most of the budget came from the National Lottery, costs spiralled
from £399million to £789million
• There should be a lasting legacy
• No one asked the question… what are we going to do with this
building after 31st December 1999?
What is Scope?
Scope comprises of the totality of the outputs, outcomes and benefits and the work
required to produce them. It involves determining the goals, deliverables, tasks,
functions and deadlines
Outcome: the changed circumstance or behaviour that results from the output
The SCOPE of a project is defined in the Design Specification and the Business Case
How do we define scope?
Once we have selected a concept to move forward with we can start to develop
a product breakdown structure and a work breakdown structure
The work breakdown structure details the work packages required to deliver
each of the components - TIME
Producing a PBS
• Breakdown a product into components to clarify work needed
• Objectives
• Identify customers' requirements products
• Identify additional products which will facilitate building and supporting
these products
• Gain consensus on scope
• Topmost product is “final” product or project output
• Includes “external” products from outside the project
• Needs several levels, higher level products completely defined by lower level
• May include “intermediate” or “enabling” products or “sub-assemblies”
Example PBS
Landscape
garden
Prepared Construction
site elements
Example WBS
Pinpoint activities
http://web.eng.fiu.edu/chen/Fall%202015/ESI%206455/Team%204
%20Project%20Proposal%20-
%20Design%20and%20Fabrication%20of%204%20wheel%20off
%20road%20vehicle.pdf
The critical path
Once we know what we are going to deliver and how it will be delivered we can
start to plan for time
Critical path analysis is a common technique identifying the key activities within a
work package
It outlines a sequence of activities through a project network from start to finish, the
sum of whose durations determines the overall project duration
The path through a series of activities, taking into account interdependencies, in
which the late completion of activities will have an impact on the project or delay a
key milestone
Name of activity
Name of activity
Start to Start
Name of activity
Summary of formulae
Forward Pass
-Start on time 0
-Earliest start = earliest finish of previous task
-Earliest Finish = Earliest start + duration
Backwards Pass
-Latest Finish (last task) = earliest finish of last task
-Latest Finish = Latest Start of successor task
-Latest Start = Latest finish – Duration
Floats
-Total Float = Latest Float – Duration – Earliest Start
(Also Total Float = Latest Start – Earliest Start)
- Free Float = Earliest Start (successor) – Earliest Finish
Activity C Step one – determine activity
duration
Activity E
0 1 1
Activity A
0 0 1 Activity B
Activity G
Activity D
Activity F
1 2
Step one – determine activity
Activity C
duration
7
Activity E
0 1 1
Activity A 1 4
0 0 1 Activity B 4
Activity G
1 8
5
Activity D
Activity F
1 2 3
2
Activity C
5 7 12
Activity E
0 1 1 1 4 5 1
Activity B 14 4 18
Activity A
Activity G
0 0 1
2
1
3
1 8 9 9 5 14
Forward pass Activity D
Earliest start = earliest finish
Activity F
of previous task
Activity C
5 7 5 7 12
Activity E
7 14
1
14 4 18
0 1 1 1 4 5
Activity G
Activity A Activity B
14 18
0 0 1 3 7
18-4
2
1 8 9 9 5 14
Activity D Activity F
1 9 9 14 3
Float
Total float = latest finish – duration – earliest start
1 2 3 Free float = earliest start (successor) – earliest finish
Activity C
FF = 0 5 4 7 FF = 2
2 1 7-2-1 5 7 12
Activity E
0 1 1 1 4 5 FF = 2
7 2 14
Activity A Activity B
0 0 1 3 5 7 FF = 0 14 4 18
FF = 0 Activity G
14 0 18
1 8 9 FF = 0 9 5 14 FF = 0
Activity D Activity F
1 0 9 9 0 14
FF = 0
1 2 3
Activity C
FF = 0 5 4 7 FF = 2
2 1 7-2-1 5 7 12
Activity E
0 1 1 1 4 5 FF = 2
7 2 14
Activity A Activity B
0 0 1 3 5 7 FF = 0 14 4 18
FF = 0 Activity G
14 0 18
1 8 9 FF = 0 9 5 14 FF = 0
Activity D Activity F
1 0 9 9 0 14
FF = 0
Gantt Chart
Activity Number Description Duration (secs) Predecessor
The critical
2 Get path - example
clean mug from cupboard 5 1
This is a weighted average (M is weighted four times more likely than the other
two values)
9 Get milk from fridge and take to kettle area 10 15 12 2.8 5(2)