STEELIN LIGHT GAUGED STEEL BUILDING QUOTATION FOR FOREIGN BID

Date 17.09.2020 Buyer


Seller's Representative Yıldız DEMİR Moaaz Tabbaa
Buyer's Representative
Sales & Marketing Coordinator
E- Mail yildiz.demir@prefabrikyapi.comE- Mail moaaztabbaa@gmail.com
Seller's Tel. No +90 216 392 12 89 Buyer' s Tel. No

P2PR2007/1911-0 Rooneby , SWEDEN


Ref.No Destination
P2007044

1 PRICE

UNIT PRICE TOTAL PRICE


NO NAME OF PROJECT AREA ( m2 ) QTY
($) ($)

3 Floors Villa Project H=3,00m


1 734,79 10 95.350,00 $ 953.500,00 $
( steel profile )

TOTAL AMOUNT
953.500,00 $
EXW, GUZELYALI, PENDIK, ISTANBUL, TURKEY, Incoterms® 2020

* Assembly And Shipping is not included in the price.


* Price Prepared As Exported Directly.
* Snow Load is 200 kg / m2

2 EXPLANATIONS

Structural system is produced with unwelded structure technology and based on high quality galvanized steel
* Manifacturing System
profiles which are and connected by bolts and nuts.
Trusses, panel carcasses, purlins, chassis and columns are manifactured by HIGH QUALITY GALVANIZED STEEL
* Load Bearing System
and HIGH TECHNOLOGY STRUCTUREROBOTS

* Product Warranyt The firm is guaranteed 1 (one) year against the manufacturing and labour mistakes.

Maintence is sevrving by quality assurance department within ISO 9001.Our firm has got the service adequacy
* Service & Maintenance
certificate.
The project and statics are calculated by technical specialist team using SAP2000-Autocad-Strucad-Revit
* Project / Statical Calculations
programme. (Every project is analyzed by technical team)

* Quotation Period We provide your information to keep this quotation for a period of 5 (five) days.
3 SCOPE OF QUATATION

SELLER BUYER

3.1 LOAD BEARING SYSTEM

Light Steel Construction Included P


Light Steel Staircase Outside staircase is included P
3.2 EXTERIOR WALL
12 mm Flat Fluted Fibercement - Brand Of HEKİMBOARD EN 13501-1
Exterior Wall Coating
A1class (CE Certificated) P
Steam Equalizer Bizofol ABA P
Under Coating 11 mm OSB 2 P
Under Coating Z Profile 50mm P
Insulation Between Construction 50 mm Rockwool 50 kg/m3 P
Insulation Between Construction 100+50 mm Rockwool 50 kg/m3 P
Paint Works Excluded P
3.3 INTERIOR WALL

Interior Wall Coating - Dry Areas Excluded P


Interior Wall Coating - Wet Areas Excluded P
Insulation Between Construction Excluded P
Paint Works Excluded P
3.4 CEILING

Dry Areas Excluded P


Wet Areas Excluded P
Surface Coating 8 mm Fibercement P
Paint Works Excluded P
3.5 ROOF
100 mm Sandwich Panel With Filling Polyurethane ,
Roof Coating
5 ribbed , RAL 9002 painted P
Insulation Between Construction Excluded P
RAL 9002 painted galvinised RAL 9002 painted galvinised
Rain Gutter / Downspout
sheet rain water gutter sheet rain water downspouts
P
8 mm Flat Fibercement - Brand Of HEKİMBOARD EN 13501-1 A1 class
Eaves Fascia
(CE Certificated) P
Parapet Excluded P
SELLER BUYER

3.6 JOINERY - DOOR

Exterior Door Excluded P


Exterior Door Joinery / Pane Excluded Excluded P
Interior Door Excluded P
Window Joinery / Pane Excluded Excluded P
Jamb / Window Sill Excluded Excluded P
3.7 MEZZANINE CHASSIS ( TWO - STOREY AND MORE )

Surface Coating Flooring Trapezoid Sheet 0,50 mm P


Insulation Between Construction Knauf Mineral Plus IPB 037 80mm ( plate ) P
3.8 STAIRS ( TWO - COAT AND MORE )

Steps, Risers, Stairhead Coating Excluded P


Top Coat Coating Excluded P
Outside railing is included, balcony and inside railing is
Railing
excluded
P

3.8 FLOOR / WALL COVERINGS

Genaral Places Floor Excluded P


Bathroom / WC Floor Excluded P
Wet Space's Walls Excluded P
3.10 ELECTRICAL FITTINGS

Building Electrical Installation Materials ( Fuse box and cabling etc. ) P


Wall Plug, Switches, Lighting Armatures Belongs To The Electrical Installation Of The Building P
Main Electrical Distribution Panel ( Electricity meter,main fuse box , terminal box end etc. ),
Building Earth System P
Sortie - Lighting …………….. pcs P
Sortie - Air Conditioning …………….. pcs P
Sortie- Switch …………….. pcs P
Sortie - TV …………….. pcs P
Sortie - Data + UPS …………….. pcs P
Sortie - Data + Telephone …………….. pcs P
3.11 MECHANICAL FITTINGS

Sanitary Fittings Installation Materials ( If project includes clean water, waste water piping works ) P
Heating and Cooling Installment ( Radiator, Air Conditioning Materials and Installment ) P
Fire Alarms and Installment ( Smoke dedector, fire extinguisher, Alarm System etc. ) P
Washbasin + Battery Assembly And Materials are Excluded …… pcs P
Closet + Reservoir Assembly And Materials are Excluded …… pcs P
Shower Cabin + Showertray Assembly And Materials are Excluded …… pcs P
Chromes Accessories ( Soap dispenser,
Tissue dispenser, Toilet paper Assembly And Materials are Excluded … pcs P
dispenser )

Kitchen Sink Assembly And Materials are Excluded …… pcs P


3.12 NOTES

Exterior Wall Carcass Thickness : 200mm Coated Exterior Wall Thickness : 298mm.

Interior Wall Carcass Thickness : 200mm Coated Interior Wall Thickness : 200mm.

SELLER BUYER

3.13 TRANSPORTATION - LOADING - UNLOADING - STORAGE

3.13.1 Packaging and Loading of the goods at the factory P


3.13.2 Shipping and Shipping Insurance P
Unloading, storage, protection of equepment against all external/enviromental impacts at building site and
3.13.3
deficiency of equepments during the works. P
3.14 OTHER WORKS
Ground concrete and every kind of excavation works according to the project, lanscaping and materials, bore
3.14.1
an anchor hole on the ground and filling works P
Obtaining all necessery permission for setting up light gauged steel buildin(approval of the architectural,
3.14.2
electrical,statical project and similar works P
Crane supply according to the construction content, procurement of electricity and water which needed
3.14.3
during the assembly, cleaning to enviroment after work P
Every kind of furniture, kitchen cupboard, counter, bathroom cupboard, mirrors, soap dispenser, toilet-roll
3.14.4
holder etc. P
* Works in the SELLER'S responsibility are specified in the technical spesification above mentioned.

Items that are mentioned below is only for sample case.Items that are not mentioned in the SELLER's commitments' section are on BUYER's
*
responsibilty.
In case BUYER is responsible of the paragraph 3.14.5 that mentioned above, if BUYER does not provide that conditions. SELLER shall find a place
*
that will provide same conditions. SELLER shall invoice of price to BUYER.

4 DELIVERY OF THE WORK

* Loading will start in 15 - 20 working days from the date of order placement and advance payment recived.

5 WORK SCHEDULE

* About day calculations; Sundays and public holidays will not considered

* Off days that are originating from BUYER or eemergency state (eartquake, flood, natural disaster etc.) will be added to delivery time.

6 PAYMENT TERMS

Down Payment For ½ Of The Total Amount By Order Placement.


*
Cash Payment For The Rest (The Other ½) Of The Total Amount 5 work days before The First Loading at factory site.

7 VALIDITY

* 1 DAY

We are looking forward to hearing from your earliest convinence and waiting for your order placement.
Thank you in advance for your cooperation and remain,

Sincerely,

Civ. Eng. Yıldız DEMİR Civ. Eng. Mustafa TOLUNAY


Sales & Marketing Coordinator Deputy General Manager