You are on page 1of 2

BASIS FOR ESTIMATION

Sl. Description of work Estimated Basis for Estimated Rate


No Unit rate/m2
1.0 SCAFFOLDING WORKS
1.1 PACKAGE BOILER CHIMNEY
A) Double tubular Scaffolding around Package 248.0 IGCAR Civil Estimate rate @
Boiler Chimney Rs 221/m2

B) Double tubular Scaffolding around Package 280.0 IGCAR Civil Estimate rate @
Boiler Chimney Rs 221/m2 and height allowance
@ Rs 3 / meter for height above
20 m
2.0 PAINTING WORKS

Inflation Unit rate


Painting cost including supply of paints Year
Rate % /m2
Cost of painting including supply in 2011
IGC/FRTG/STG/SGTF/Chimney/2010/05/WO/MSC
/5348 Dated: 04/04/2011 220.0
Considering inflation in 2011 2011 6.49 234.278
Considering inflation in 2012 2012 11.17 260.4469
 Considering inflation in 2013 2013 9.13 284.2257
 Considering inflation in 2014 2014 5.86 300.8813
 Considering inflation in 2015 2015 6.32 319.897
 Considering inflation in 2016 2016 2.23 327.0307
 Considering inflation in 2017 2017 4 340.1119
 Considering inflation in 2018 2018 5.24 357.9338
Considering inflation in 2019 2019 9.63 392.4028
Cost of painting including supply of Paints & thinner
in 2019, accounting for inflation 2019 9.63 392.4028 (A)

COST OF PAINTS (Ref: P/O DPS/MRPU/IGCAR/POL/1545/PO/118693 Dated: 18/07/2017)

Sl Quantity Unit Total


Description
No (liter) rate/liter Cost
1 Supply of Light green epoxy brand, Vista 220 170 37400
2 Epoxy primer Brand Vista 180 145 26100
3 Epoxy thinner suitable for Brand Vista 80 100 8000
4 High temperature aluminium brand vista 400 150 60000
5 Red oxide metal primer brand Vista 60 110 6600
6 Coal tar high build epoxy paint as per IS 14948 30 170 5100
7 Chlorinated rubber paint Blue ISC 176 Brand Vista 80 190 15200
8 Synthetic enamel Oxford blue paint to IS 2932-Brand Vista 40 190 7600
    1090 1225 166000
Since different quantity of paints is purchased at different rates, weighted mean is considered as
shown below for calculation.
Weighted mean rate of Paint =
∑ QR
Q
166000
=
1090
= 152.29 Rs /liter in the year 2017.
Hence the rate of paint has to be subtracted from this to arrive at labour charge alone.

cost of paint (weighted mean) @ 2017 152.2936


cost of paint @ inflation 2018 5.24 160.2738
cost of paint @ inflation 2019 9.63 175.7081 (B)
labour charge = Cost of painting including supply in
2019, accounting for inflation - cost of paint @ inflation 392.4028-
2019 A-B 175.7081 = 216.6947

This estimated rate @ Rs 242/m2 is calculated for estimation of painting cost.

3.0 FABRICATION AND ERECTION OF CARBON STEEL MATERIAL:

3.1 Carbon steel structural support fabrication and replacement

Carbon steel cone hood above package boiler chimney has severely corroded and needs
replacement. Fabrication is required as per attached drawing by cutting / rolling/bending from the
given MS sheet. This includes cutting / dismantling of existing cone hood from top of stack to dump
yard, fit up, welding and erection of newly fabricated and painted cone hood to the top of chimney,
replacement of any channel, angle, supports, monkey ladder, handrails etc by new one. For the
structural support fabrication for the carbon steel materials budgetary offers were received by two
local contractors namely M/s. J K Engineers, Kalpakkam and M/s. Rambhal. Sadras,Kalpakkam.

Unit rate quoted by M/s. Rambhal. Sadras, Kalpakkam = Rs. 53/ kg


Unit rate quoted by M/s., M/s. J K Engineers, Kalpakkam = Rs. 52/ kg

Hence estimated unit rate for the carbon steel structural support fabrication is Rs.56 /kg
considering the previous work order.

(Radhakrishnan Unni, TO/D)


SGTF OS