You are on page 1of 169

IEM TRAINING CENTRE SDN. BHD.

TWO DAY INTENSIVE COURSE ON

CONTRACT ADMINISTRATION FOR


CONSTRUCTION & ENGINEERING
CONTRACTS

Presented by: IR. HARBANS SINGH K.S.


B.E. (Mech) S’PORE, LLB (Hons) London
CLP, DipICArb, C. Eng, PE.
ABOUT THE COURSE PRESENTER

Ir. Harbans Singh K.S.


B.E. (Mech) S’pore, LLB (Hons) London,
CLP, DipICArb, P.E.,
C. Eng., MIEM, MIMechE,
MIHEEM, MASHRAE, MCIArb, MMIArb.

Ir. Harbans Singh K.S. is a Professional and Chartered Engineer, Arbitrator,


Adjudicator, Mediator, Advocate & Solicitor (non-practising). He commenced his
career in Malaysia before working in Germany and then locally in various professional
capacities. He is presently domiciled in Malaysia where he is active in construction
law and dispute resolution. Ir. Harbans is the recipient of IEM’s Tan Sri Hj. Yusoff
Prize (2001), the Cedric Barclay and the Chartered Institute of Arbitrator’s Awards for
the Diploma in International Commercial Arbitration Examination (Oxford 2003). He
is also the author of a series of four books entitled ‘Engineering & Construction
Contracts Management’, coauthor of the book ‘The PAM 2006 Standard Form of
Building Contract’, contributor to the ‘Malaysian Standard Forms & Precedents:
Construction & Engineering Contracts’, ‘The Ingenieur’ and the ‘Malayan Law
Journal’.

© HSKS
CONTRACT ADMINISTRATION FOR
CONSTRUCTION/ ENGINEERING CONTRACTS

DAY 1 - PROGRAMME

8.30 a.m. - 9.00 a.m. : Registration

9.00 a.m. - 10.30 a.m. : Session 1

10.30a.m. - 10.45a.m. : Tea/Coffee Break

10.45 a.m. - 12.30 noon : Session 2

12.30 noon - 1.00 p.m. : Q & A Session

1.00 p.m. - 2.00 p.m. : Lunch Break

2.00 p.m. - 3.15 p.m. : Session 3

3.15 p.m. - 3.30 p.m. : Tea/Coffee Break

3.30 p.m. - 4.45 p.m. : Session 4

4.45 p.m. - 5.00 p.m. : Q & A Session

5.00 p.m. : End of Day 1


© HSKS
CONTRACT ADMINISTRATION FOR
CONSTRUCTION/ ENGINEERING CONTRACTS

DAY 2 - PROGRAMME

9.00 a.m. - 10.30 a.m. : Session 1

10.30a.m. - 10.45a.m. : Tea/Coffee Break

10.45 a.m. - 12.30 noon : Session 2

12.30 noon - 1.00 p.m. : Q & A Session

1.00 p.m. - 2.00 p.m. : Lunch Break

2.00 p.m. - 3.15 p.m. : Session 3

3.15 p.m. - 3.30 p.m. : Tea/Coffee Break

3.30 p.m. - 4.45 p.m. : Session 4

4.45 p.m. - 5.00 p.m. : Q & A Session

5.00 p.m. : End of Course

© HSKS
CONTENTS

1.0 CONSTRUCTION/ENGINEERING CONTRACTS: INTRODUCTION

2.0 COMMENCEMENT OF CONTRACT AT SITE

3.0 MONITORING OF WORK PROGRESS

4.0 SUPERVISION OF WORKS/CONTRACT ADMINISTRATION

5.0 PAYMENTS/COMMERCIAL MATTERS

6.0 VARIATIONS/CHANGES

7.0 DELAY AND EXTENSION OF TIME

8.0 NON-COMPLETION AND DAMAGES

9.0 COMPLETION AND HANDING OVER

10.0 DEFECTS

11.0 POST COMPLETION AND FINAL ACCOUNT

© HSKS
CONSTRUCTION/
ENGINEERING CONTRACTS:
INTRODUCTION

© HSKS
1.0 CONSTRUCTION/ENGINEERING CONTRACTS: INTRODUCTION

• TYPES OF CONTRACTS

1. GENERAL CONTRACTS

2. ENGINEERING/CONSTRUCTION CONTRACTS

• TYPES OF BUILDING CONTRACTS

• COMMON CONTRACT PROCUREMENT METHODS

1. TRADITIONAL GENERAL CONTRACTS

2. MANAGEMENT TYPES

3. ‘PACKAGE DEAL’ TYPES

4. MISCELLANEOUS METHODS

© HSKS
• BASIC CONTRACT PRINCIPLES

1. CONTRACT DEFINITIONS

2. ELEMENTS OF CONTRACT

3. STANDARD FORMS OF CONTRACT

4. BREACH OF CONTRACT: REMEDIES

• MISCELLANEOUS ISSUES

© HSKS
SIMPLE
CONTRACTS
COLLATERAL SPECIALITY
CONTRACTS CONTRACTS
(DEED)
MATERIAL
& LABOUR
CONTRACTS ORAL
CONTRACTS

LABOUR
CONTRACT GENERAL EXPRESS
CONTRACTS
CONTRACTS:
TYPES
MATERIAL SUPPLY
MAIN CONTRACTS
CONTRACT

INDEPENDENT
CONTRACTS SUB-CONTRACTS

EMPLOYMENT SUB-SUB
CONTRACTS CONTRACTS

FIG. 1-1: GENERAL CONTRACTS - TYPES


© HSKS
ENGINEERING/
CONSTRUCTION
CONTRACTS:
TYPES’

FIG. 1-2 : ENGINEERING/CONSTRUCTION CONTRACTS - TYPES


© HSKS
TYPE OF CONTRACT

LUMP SUM MESUREMENT COST


CONTRACTS CONTRACTS REIMBURSEMENT
CONTRACTS

LUMP SUM WITH LUMP SUM WITH


PLAN AND BILLS
SPECIFICATION OF QUANTITIES

BASED ON
BASED ON A
APPROXIMATE SCHEDULE
QUANTITIES

COST PLUS COST PLUS COST PLUS TARGET COST


FLUCTUATING FEE VALUE COST
FIXED FEE PERCENTAGE

FIG. 1-3 : TYPES OF CONTRACTS BASED ON PRICING MECHANISM

© HSKS
COMMON CONTRACT PROCUREMENT METHODS

TRADITIONAL
MANAGEMENT PACKAGE MISCELLANEOUS
GENERAL
TYPE DEAL TYPE METHODS
CONTRACTTING

MANAGEMENT CONSTRUCTION
CONTRACTING MANAGEMENT BUILD, OPERATE FAST
& TRANSFER TRACKING PARTNERING

DESIGN & BUILD/ ENGINEERING, PROCUREMENT, ‘TURNKEY’


TURNKEY’
DESIGN & CONSTRUCT CONSTRUCTION & COMMISSIONING

FIG. 1-4 : COMMON CONTRACT PROCUREMENT METHODS IN USE


© HSKS
FIG. 1-5 : COMPARISON OF COMMON CONTRACT PROCUREMENT METHODS

1985 1990 1995 2000

1.0 TRADITIONAL GENERAL 95% 76% 31% 20%


CONTRACTING

2.0 MANAGEMENT 2% 3% 2% 1%
CONTRACTING

3.0 CONSTRUCTION 1% 3% 9% 10%


MANAGEMENT

4.0 PACKAGE DEAL TYPE’ 2% 15% 52% 60%

5.0 BUILD, OPERATE AND - 2% 5% 8%


TRANSFER

6.0 OTHER - 1% 1% 1%
MISCELLANEOUS

© HSKS
FIG. 1-6: TRADITIONAL GENERAL CONTRACTING (TGC) – CONTRACTUAL RELATIONSHIPS

EMPLOYER

PROFESSIONAL
TEAM - DESIGN AND
CONTRACT ADMINISTRATION

1. Architect MAIN CONTRACTOR


2. Engineers - C&S, M&E (MC)
3. Quantity Surveyor
4. Other Specialist

DOMESTIC SUPPLIER NOMINATED SUPLLIER


(DS) (NS)

SUB-
SUB-SUB SUB-
SUB-SUB
CONTRACTORS SUB--SUB SUPPLIERS
SUB CONTRACTORS SUB-
SUB-SUB SUPPLIERS

Key
_______ : Contractual Link
_____ : Responsibility

© HSKS
FIG. 1-7: ‘TURNKEY’ CONTRACTS/DESIGN & CONSTRUCT (D&C) - CONTRACTUAL
RELATIONSHIPS

PROFESSIONAL 1. Architect
EMPLOYER 2. Engineers - C&S, M&E
ADVISORS 3. Quantity Surveyor
4. Other Specialist
1. Setting up Employers
Requirements
2. Auditing role during
construction

D & C CONTRACTOR

1. Architect PROFESSIONAL SUB-


SUB- SUB-
SUB-
2. Engineers - C&S, M&E
3. Quantity Surveyor TEAM CONTRACTOR SUPPLIER
4. Other Specialist
1. Detailed Design
2. Construction supervision

SUB-
SUB-SUB SUB-
SUB-SUB
CONTRACTORS SUB-
SUB-SUB SUPPLIERS CONTRACTORS SUB--SUB SUPPLIERS
SUB

Key
_______ : Contractual Link
_____ : Responsibility

© HSKS
FIG. 1-8: MANAGEMENT CONTRACTING (MC) - CONTRACTUAL RELATIONSHIPS

EMPLOYER

MANAGEMENT
PROFESSIONAL TEAM CONTRACTOR
(MC)
1. Architect
2. Engineers - C&S, M&E
3. Quantity Surveyor
4. Other Specialist

TRADE TRADE TRADE


CONTRACTOR CONTRACTOR CONTRACTOR

Key
_______ : Contractual Link
_____ : Responsibility

© HSKS
FIG. 1-9: CONSTRUCTION MANAGEMENT (CM) - CONTRACTUAL RELATIONSHIPS

EMPLOYER

PROFESSIONAL CONSTRUCTION
TEAM MANAGER (CM)

1. Architect
2. Engineers - C&S, M&E
3. Quantity Surveyor
4. Other Specialist

Key TRADE TRADE


CONTRACTORS CONTRACTORS
_______ : Contractual Link
_____ : Responsibility

© HSKS
* CONTRACT - DEFINATIONS

1.0 PER ANSON

* Legally binding agreement


* Between two or more parties
* By which rights are acquired by one or more
* To acts or forbearances on the part of the other or others

2.0 PER SECTION 2(h) MALAYSIAN CONTRACTS ACT 1950 (REV. 1974)

* An agreement
* Enforceable by Law

** CONTRACT - BASIC ELEMENTS

CLEAR + UNQUALIFIED + CONSIDERATION = CONTRACT


CONTRACT
OFFER ACCEPTANCE (LEGAL
AGREEMENT)

FIG. 1-10: CONTRACT DEFINITIONS

© HSKS
FIRM OFFER/
PROPOSAL

+
UNQUALIFIED
ACCEPTANCE

+
CONSIDERATION

INTENTION TO CREATE FREE CONSENT


LEGAL RELATIONS

CERTAINTY OF TERMS LAWFUL OBJECT AND


CONSIDERATION

LEGAL CAPACITY TO PHYSICAL/LEGAL


CONTRACT POSSIBILITY

FIG. 1-11: ELEMENTS OF A VALID/ENFORCEABLE AGREEMENT

© HSKS
DEFINITION/
MEANING

CHARACTERISTICS
MAIN TYPES

STANDARD
DISADVANTAGES FORMS OF TYPES
CONTRACT

ADVANTAGES
PURPOSE

FIG. 1-12 : STANDARD FORMS OF CONTRACT (PART I)

© HSKS
STANDARD FORMS OF CONTRACT

GOVERNMENT/ INTERNATIONAL
PRIVATE SECTOR
PUBLIC SECTOR CONTRACTS

1. FIDIC Conditions

2. ICE Conditions
JKR / PWD MISCELLANEOUS 3. IEEE Conditions

• 203 (Rev. 1/2010) - without • CIDB Form for: 4. IMechE Conditions


quantities
- Building Contracts 2000 Edn. 5. JCT Conditions
• 203A (Rev. 1/2010) - with - Form CIDB.B (NSC/2002)
quantities
• Modified JKR/PWD Forms e.g.
• 203N (Rev. 1/2010) - For NSC LPK, MHA, etc.

• 203P (Rev. 1/2010) - For


Nominated Suppliers

• PWD Form DB (2007 Edn.)


BUILDING WORKS CIVIL ENGINEERING M & E WORKS
For Design & Build Contracts WORKS

• PAM Contract 2006 • IEM Conditions • IEM Conditions


(with quantities)
- IEM.CE 2011 - IEM.ME 1/94
• PAM Contract 2006 - IEM.CES 1/90
(without quantities) • TNB Conditions, etc.

• PAM Sub-Contract 2006

FIG. 1-13: STANDARD FORMS OF CONTRACT (PART II)


© HSKS
COMMENCEMENT OF
CONTRACT AT SITE

© HSKS
2.0 COMMENCEMENT OF CONTRACT AT SITE

• APPROACHES IN:
1. TRADITIONAL GENERAL CONTRACTS
2. DESIGN & BUILD / TURNKEY CONTRACTS
• FORMALITIES:
1. CONDITIONS PRECEDENT
2. INSURANCES, PERFORMANCE BONDS, ETC.
• SITE POSSESSION : MEANING AND EFFECT
• SUBMITTALS :
1. CONSTRUCTION DRAWINGS
2. SHOP DRAWINGS
3. SAMPLES
4. QA AND QC DOCUMENTS
5. HEALTH AND SAFETY DOCUMENTS
6. METHOD STATEMENTS
• TEMPORARY WORKS
• ISSUES FOR ATTENDANCE OF NOMINATED SUB-
SUB-CONTRACTORS
• MISCELLANEOUS ISSUES

© HSKS
• RELEVANT CASES

1. THE RADIO & GENERAL TRADING CO. SDN. BHD. V WYASS & FREYTAG (M)
SDN. BHD. [1998] 1 MLJ 346

2. LEC CONTRACTORS (M) SDN. BHD. V CASTLE INN SDN. BHD. & ANOR [2000]
3 MLJ 339

3. KLEINWORT BENSON LTD. V MALAYSIA MINING CORP. BHD [1989] 1 WLR 379

4. NANYANG INSURANCE CO. LTD. V SALBIAH & ANOR [1967] 1 MLJ 94

5. SURREY HEALTH BOROUGH COUNCIL V LOVELL CONSTRUCTION


[1988] 42 BLR 25

6. FREEMAN V HENSLER [1981] 20 BLR 78

7. TAN HOCK CHAN V KHO TECK SENG [1980] 1 MLJ 308

8. PUTRA PERDANA CONSTRUCTION SDN. BHD. V AMI INSURANCE BHD


& ORS [2005] 2 MLJ 123 HC

9. YIP SHOU SHAN V SIN HEAP LEE – MARUBENI SDN. BHD. [2002] 5 MLJ
43, HC`

© HSKS
TAKING OVER OF COMMENCEMENT
THE SITE OF CONTRACT

COMMENCEMENT: COMMENCEMENT
SITE POSSESSION
OF CONTRACT
COMMON LABELS PERIOD

COMMENCEMENT
COMMENCEMENT
OF OPERATIONS OF WORKS
ON SITE

FIG. 2-1 : COMMENCEMENT - COMMON LABELS

© HSKS
PARENT COMPANY
GUARANTEE

INSURANCE PERFORMANCE BOND

PROTECTION AGAINST
CONTRACTOR’S FAILURES:
COMMON MECHANISMS

STANDBY LETTER LETTER OF COMFORT


OF CREDIT

LETTER OF AWARENESS

FIG. 2-2: PROTECTION AGAINST CONTRACTOR’S FAILURES – COMMON MECHANISMS

© HSKS
PROTECTION AGAINST CONTRACTOR’S FAILURES: AN OVERVIEW (PART I)

COMMON MECHANISMS/ PARENT COMPANY


PURPOSE
INSTRUMENTS: TYPES GUARANTEES

• Risk transferring contracts • Parent Company Guarantees

• Enable recovery of compensation • Performance Bonds


upon contractor’s default/failure
under the contract • Miscellaneous Types:

1. Letters of Comfort
2. Standby Letters of Credit
3. Insurances

PROCEDURAL
NATURE USE REQUIREMENTS

• Contractual performance of • For commercial and • Preliminary review


‘Company within a corporate administrative convenience
group is underwritten by other • Check for legal compliance
members of group • Owing to requirements of
applicable law e.g. company • Check for compliance with
• E.g. Subsidiary and Holding law, etc. formalities
Company

Cont’d….

FIG. 2-3 : PROTECTION AGAINST CONTRACTOR’S FAILURES – AN OVERVIEW (PART I)

© HSKS
Cont’n.

PROTECTION AGAINST CONTRACTOR’S FAILURES: AN OVERVIEW (PART II)

MISCELLANEOUS MECHANISMS/
PERFORMANCE BONDS
INSTRUMENTS

STANDBY LETTER INSURANCE


LETTER OF COMFORT LETTER OF AWARENESS
OF CREDIT
• Reasons for • Reasons for • Reasons for • Reasons for:
• Typical contents • Comparison with letters of • Comparison with • Legal effect of Insurance
• Legal effect of letter comfort ‘Unconditional/On-Demand’ Bond • Comparison with the other
• Typical contents • Obligations under mechanisms/instruments
• Legal effect of letter • Legal effect of letter

DURATION
DURATION OF
OF FINANCIAL LIMITS PROCEDURAL
PROCEDURAL NON-
NON--PROVISION
PROVISION OF
OF RELEASE OF BOND
DEFINITION
DEFINITION TYPES
TYPES LIABILITY
LIABILITY OF LIABILITY REQUIREMENTS BOND/GUARANTEE /GUARANTEE

• See Robinson and • Two main types: • Normally stipulated in • Normally • Preliminary • Timing for • Seven main
Laver’s definition bond. Types include: stipulated in review submission circumstances
1. ‘Conditional/
Bond itself.
• Means of Default’ Bond 1. Entire duration of • Checks for • Consequences of • Effect of
guaranteeing to contract • Normally 5-10% authenticity failure to submit: breaches of
the employer: 2. ‘Unconditional/
terms and
On-Demand’ 2 Up to CPC - • Sometimes • Check for 1. Contract
conditions
1. The Bond ‘Construction’ higher compliance with provisions
contractor’s Bond formalities 2. Common law
financial • Features of • See use of
rules
local practice 3 CPC to Final ‘Indexed
viability and
Certificate – Performance
2. Contractor’s • Rules of
‘Maintenance’ Bonds’
construction
ability to Bond
and
perform
obligations enforcement 4 Up to date of
release stipulated
under the
contract by guarantor

FIG. 2-4 : PROTECTION AGAINST CONTRACTOR’S FAILURES – AN OVERVIEW (PART II)


© HSKS
FIG. 2-5 : CONTRACTOR’S INSURANCE POLICIES – COMMON TYPES

© HSKS
INSURANCES: AN OVERVIEW (PART I)

PURPOSES DEFINITION TYPES

• Risk allocation mechanisms • Per Robinson and Lavers

• Means of seeking compensation • Voluntary assumption of


following default/failure specified risk in return for an
agreed payment

CATEGORISATION CATEGORY I CATEGORY II PRINICPAL TYPES

• Two Main Categorization: • Liability based • Loss based • Contractor: Common Types

1. Liability based • Indemnification of insured • Compensate insured for • Employer: Common Types
2. Loss based against damages payable to loss/damage directly
3rd party incurred by insured • Occupier: Common Types
• Difference: basis of
compensation • Examples: • Examples: • Management Corporation:
Common Types
1. 3rd Party Liability 1. Contractor’s All Risk
Insurance Policy
2. Workmen’s 2. Erection All Risk
Compensation Policy
3. Professional Indemnity
Insurance

FIG. 2-6 : INSURANCES – AN OVERVIEW (PART I)


© HSKS
Cont’d…….

INSURANCES: AN OVERVIEW (PART II)

FEATURES AND PROCEDURAL


FAILURE TO INSURE
CONDITIONS REQUIREMENTS

• Necessity for checking authenticity


of: 1. Cover notes 2. Policy
• Necessity to check for compliance
with: 1. Contract requirements TIMING FOR SUBMISSION FAILURE TO INSURE
2. Formalities
• Normally stipulated in contract • Effects dictated by:

• 2 Common alternatives: 1. Governing contractual


provisions
1. Before commencement of 2. Common law rules
work/contract; or
• Possible options: Employer insures
2. Within stipulated period of and charges premiums to contractor
award of contract • Apparently not a serious ground to
effect determination

IMPORTANT
IMPORTANT
BASIS
BASIS OF
OF STANDARD PARTIES
PARTIES COMMENCEMENT
COMMENCEMENT DURATION
DURATION FINANCIAL
FINANCIAL LIMITS
LIMITS TERMINATION
TERMINATION
CONTRACTING STANDARD OF
CONTRACTING CONDITIONS
CONDITIONS
EFFECTING POLICY
POLICY OF
OF POLICY
POLICY OF POLICY
POLICY OF
OF LIABILITY
LIABILITY OF
OF POLICY
POLICY

• Submission of • Six main ones i.e. • General rule: • Various possibilities: • Different formulae: • Normally stipulated • Three main methods:
proposal by employer in
1. Condition precedent 1. Named party 1. Date of 1. Up to issue of CPC tender/contract 1. Satisfaction of
• Issue of policy to liability 2. With insurable commencement of conditions
interest contract; or 2. Up to issue of CMGD • Guidelines for precedent in
• Effect of : 2. During estimating limits. contract e.g. issue
work/construction • Typical parties: 2. Date of 3. Up to issue of Final
1. Contracts of Certificate of CPC, etc.
commencement of • General rule on
‘uberrimae 3. As to risk 1. Employer work on site; or deductibles/excess 2. Termination of
fidei’ 2. Contractor 4. Up to Final Certificate
4. Following a loss plus fixed period clauses policy by
3. Sub-contractors 3. Date of delivery of breach/mutual
2. Cover notes, event 4. Selected 3rd parties material, etc.
etc. • Requirements agreement
5. As to subrogation • Effect of ‘cross • Function of the nature pertaining to extension
of period 3. Lapse of insurance
6. On contribution liability’ provisions of contract works period and/or
extension
FIG. 2-7 : INSURANCES – AN OVERVIEW (PART II)
© HSKS
SITE POSSESSION: AN OVERVIEW

PROVISIONS FAILURE TO GIVE


MEANING DEGREE POSTPONEMENT
FOR POSSESSION

• Licence revocable by
Employer at any time
• Licence to be free from
any encumbrances

GENERAL
EXCEPTIONS
EXPRESS IMPLIED LEGAL POSITION

• In Letter of • If not expressed, by • No • Express contract


Acceptance Law stipulations permitting
postponement
• Or in Contract • Freeman & Son v
Hensler

EXCEPTIONS POSSESSION
GENERAL LATEST LEGAL GENERAL
TO GENERAL ON PIECEMEAL EFFECT
PRINCIPLE POSITION LEGAL POSITION
PRINCIPLE BASIS?

• Contractor entitled to • Express Stipulations • Sufficient degree • General Position: No • Breach of Contract • Contractor entitled to
Sole/exclusive of possession/ loss occasioned
possession • Case Law • Exceptions: • Entitles Contractor to
access rescind Contract. • Contractor entitled to
a) Express EOT if expressly
• To execute work
stipulations to permitted
unimpeded
contrary contractually
• To be able to
b) Where Common • Otherwise, LAD
perform work
Law applies cannot be imposed

FIG. 2-8 : SITE POSSESSION – AN OVERVIEW

© HSKS
SITE POSSESSION MEETINGS

MATTERS PARTICIPANTS
TIMING PURPOS E MINUTES
DEALT

· On Date of Commencement · 1. All Project Team


To officially handover
of Contract / Possession of Site to Member
· Date of Site Possession the Contractor
WHO DISTRIBUTION/
PREPARES ? CIRCULATION

· Contract Administrator · To all parties

EXPLANATION INTRODUCTION HANDOVER SET OUT


OF CONTRACT OF PROJECT OF VARIOUS PROCEDURES
REQUIREMENTS MEMBERS DOCUMENTS COVERING

· Document Submittals and


Approvals
· Sample Submittals and
Approvals
·
· Inspection of Work
LETTER OF COPY OF SET OF
DELEGATION CONTRACT PRICED COPY CONSTRUCTION Interim Valuations
OF POWERS DOCUMENTS OF B.Q. DRAWINGS · Claim Procedures

FIG. 2-9 : SITE POSSESSION MEETINGS

© HSKS
WORK PROGRAMME

MISCELLANOUES
REPORTS
AND DOCUMENTS METHOD STATEMENTS

DESIGN AND CALCULATIONS


FOR WORKS UNDER P.C. DRAWINGS I.E. SHOP,
SUM, ‘PACKAGE DEAL’ TYPE FABRICATION, SETTING
CONTRACTS, ETC. WORKS UNDER CONTRACT: OUT, ETC.
TYPICAL SUBMITTALS BY
CONTRACTOR

DESIGN AND QA/QC DOCUMENTS


CALCULATIONS FOR
TEMPORARY WORKS
HEALTH AND SAFETY
DOCUMENTS

FIG. 2-10: WORKS UNDER CONTRACT – TYPICAL SUBMITTALS BY CONTRACTOR

© HSKS
MONITORING OF
WORK PROGRESS

© HSKS
3.0 MONITORING OF WORK PROGRESS

• PROGRAMMING OF WORKS

• PARTIES RESPONSIBLE:

1. EMPLOYER
2. MAIN CONTRACTOR
3. CONTRACT ADMINISTRATOR

• PROGRESS REPORTS

• SITE RECORDS

• MEETINGS:

1. SITE POSSESSION
2. PROGRESS/SITE
3. NSC COORDINATION
4. AD-HOC

• MISCELLANEOUS ISSUES

© HSKS
• RELEVANT CASES

1. GLENLION CONSTRUCTION LTD. V THE GUINESS TRUST [1987] 39 BLR 89

2. YORKSHIRE WATER AUTHORITY V SIR ALFRED MCALPINE & SON


(NORTHERN) LTD. [1986] 32 BLR 114

3. GREATER LONDON COUNCIL V CLEVELAND BRIDGE & ENGINEERING CO.


LTD. [1986] 8 Con LR 30

4. KITSONS SHEET METAL LTD. V MATTHEW HALL MECHANICAL &


ELECTRICAL ENGINEERS LTD. [1989] 47 BLR 82

5. WEST FAULKNER ASSOCIATES V LONDON BOROUGH OF NEWHAM [1994]


71 BLR 1

6. EQUITABLE DEBENTURES ASSETS CORP. LTD. V MORGAN BRANCH


ROBERTS & ORS [1984] 2-CLD-10-01

© HSKS
FIG. 3-1 : WORK PROGRAMME - TYPICAL FORMS

© HSKS
PRINCIPAL ACTIVITIES

IMPORTANT
MILESTONES FOR
EMPLOYER TO MEET SEQUENCE OF
ACTIVITIES

WORK PROGRAMME:
PRINCIPAL CONTENTS

IMPORTANT
TIMING OF ACTIVITIES
MILESTONES FOR
CONTRACTOR TO MEET
IDENTIFICATION OF
CRITICAL ACTIVITIES
AND CRITICAL PATH

FIG. 3-2 : WORK PROGRAMME – PRINCIPAL CONTENTS

© HSKS
WORK PROGRAMME: AN OVERVIEW

RESPONSIBILITY MEANING FORM CONTENTS PURPOSE OPTIONS ON PART OF ALTERATION/


SUBMISSION CONTRACT? REVISION

• Express Provisions • Sequence and • Approval • General


Timing of Activities • Rejection Policies
• By Implication • Withholding of
• Mode of
• Critical Milestones Approval
Alternatives /
Revision

• Effect of
Alternatives/
Revision
METHOD OF SEQUENCE OF FOR CONTRACT FOR
WORKING WORKING ADMINISTRATOR CONTRACTOR

PRIMIVERA/ PART OF TENDER SUBMITTED AFTER


BAR CRITICAL PATH
PERT MICROSOFT MISCELLANEOUS SUBMISSION? TENDER AWARD
CHARTS ANALYSIS
‘PROJECT’
PROJECT’

FIG. 3-3 : WORK PROGRAMME – AN OVERVIEW

© HSKS
TO LEVY CONTROL OVER
PROGRESS OF THE WORKS
TO ENSURE CONTRACT
MISCELLANEOUS IS COMPLETED
PURPOSES ACCORDING TO
SCHEDULE

PROGRESS MONITORING:
EMPLOYER’S PURPOSES

TO PLAN AND TO WARN CONTRACTOR


STREAMLINE FINANCIAL TO TAKE REMEDIAL
ARRANGEMENTS MEASURES IN CASE
TO OBVIATE DEFAULT TO TAKE NECESSARY DELAY OCCURS
REMEDIAL MEASURES IF
DELAY OCCURS OR IF
EMPLOYER IS AT FAULT

FIG. 3-4 : PROGRESS MONITORING – EMPLOYER’S PURPOSES

© HSKS
PROGRESS MONITORING: AN OVERVIEW

FREQUENCY/
DURATION PURPOSE METHODS BASIS PARTIES NATURE OF
RESPONSIBLE CHECKS

• From Site • Primary Purposes • Use of Contractor’s • Employer/ contract • On regular basis
Possession Work Programme administrator
• Secondary Purposes • Normally ‘monthly’
• To Issue of Final • Contractor
Certificate • Maybe

• Normally up to i. Weekly
Practical Completion ii. Fortnightly
only PROGRESS SITE iii. Quarterly, etc.
MEETINGS RECORDS

COORDINATION/
SITE SUB-
SUB-
SITE PROGRESS PROJECT ‘AD-
AD-HOC’
HOC’
POSSESSION CONTRACTORS
MEETINGS MANAGEMENT MEETINGS
MEETINGS MEETING
MEETINGS

DURATION PURPOSE METHODS EVIDENTIAL VALUE

OFFICIAL SITE
OFFICIAL WORK
PROGRESS DIARY
RECORDS
REPORTS

FIG. 3-5 : PROGRESS MONITORING – AN OVERVIEW


© HSKS
MISCELLANEOUS SITE POSSESSION
MEETINGS MEETINGS

POST CONTRACT
AD-HOC AWARD STAGE: SITE PROGRESS
MEETINGS PRINCIPAL TYPES MEETINGS
OF MEETINGS

COORDINATION/
SUB-CONTRACTOR’S PROJECT
MEETINGS MANAGEMENT
MEETINGS

FIG. 3-6 : POST CONTRACT AWARD STAGE – PRINCIPAL TYPES OF MEETINGS


© HSKS
SITE PROGRESS MEETINGS: AN OVERVIEW

TIMING PURPOSE ISSUES/ PARTICIPANTS


MINUTES
MATTERS DEALT

WHO DISTRIBUTION/
ENABLE PERMIT WORK MISCELLANEOUS PREPARES? CIRCULATION
CONTRACTOR TO PROGRESS TO

• Officially present • Be reviewed on • Enable Employer/ C.A. to • S.O./ Contract • To all parties/
progress report regular basis redress delay caused by Administrator attendees
him/them
• Present problems • Identify areas and
encountered causes of delay • Keep track of financial
progress/allocation

3RD PARTY
ONLY SITE ISSUES FINANCIAL ISSUES ISSUES AFFECTING MISCELLANEOUS
CONTRACT ISSUES

CONTRACT MAIN CONSULTANTS NSCs EMPLOYER


ADMINISTRATOR CONTRACTOR

• Chairs Meeting • Main participant • Observers Only • By invitation only • Observer only
• Main participant • Participants if contract
administrator's assistants/
representatives

FIG. 3-7 : SITE PROGRESS MEETINGS – AN OVERVIEW


© HSKS
SUB-CONTRACTORS MEETINGS: AN OVERVIEW

TIMING PURPOSE ISSUES/ MINUTES PARTICIPANTS


MATTERS DEALT

• Usually monthly prior


to site meetings
• If necessary more
frequently
WHO DISTRIBUTION/
TO ENABLE SUB-
SUB- TO PERMIT PREPARES? CIRCULATION
CONTRACTOR TO CONTRACTOR TO
• Main • To all parties/
• Officially present • Review NSC’s progress,
Contractor attendees
progress report to areas of delay, etc.
Contractor
• Identify and sort
• Present problems coordination problems
encountered

CONTRACTOR NOMINATED DOMESTIC OTHERS


(MAIN) SUB-
SUB- SUB-
SUB- (BY
CONTRACTORS CONTRACTORS INVITATION)

• Chairs Meeting • Employer


• Third Parties
• Contract
COORDINATION 3RD PARTY ISSUES MISCELLANEOUS Administrator
SITE PROBLEMS FINANCIAL ISSUES
MATTERS ISSUES

• Design • Possession • Payments • Authorities


• Site Work • Access • V.O.s • Utilities Providers
• Security • Claims • Others

FIG. 3-8 : SUB-CONTRACTORS MEETINGS – AN OVERVIEW

© HSKS
‘AD-HOC’ MEETINGS: AN OVERVIEW

CONVENORS
TIMING PURPOSE
(AS APPLICABLE)

• The Employer

• The Contract Administrator

• The Contractor

• The Sub-Contractors
AS AND WHEN USUALLY TO DISCUSS
NECESSARY FROM DICTATED BY SPECIFIC ISSUES /
TIME TO TIME CIRCUMSTANCES MATTERS

EMERGENCY FINANCIAL TECHNICAL ADMINISTRATIVE MISCELLANEOUS


ISSUES ISSUES ISSUES MATTERS ISSUES

• Site Issues • Payments • Design • Training


• Design/ Work Issues • V.O.s • Construction/Installation • Maintenance
• 3rd Party Issues • Claims • Testing and • ‘As-Built’ Records
Commissioning
• Defects

FIG. 3-9 : ‘AD-HOC’ MEETINGS – AN OVERVIEW


© HSKS
SITE RECORDS: AN OVERVIEW

DURATION PURPOSE METHODS EVIDENTIAL VALUE

• From Date of Commencement /


Site Possession to

• Completion of works

• Normally up to Practical
Completion only
PROVIDE NECESSARY OFFICIAL
INFORMATION/ EVIDENCE OFFICIAL WORK PROGRESS SITE DIARY
TO RECORDS REPORT

REVIEW WORK EVALUATE PERMIT


CONTRACTOR’’S
CONTRACTOR DULY SIGNED/ ACKNOWLEDGEMENT
PROGRESS DECISION MAKING
CLAIMS TO ENDORSED RECORDS OF RECEIPT RECORDS

• Contractor’s Scope • Extension of Time • Best evidential value • Some evidential value
• NSC’s/DSC’s Scope • Additional Work

• Direct loss and/or


expense

• Miscellaneous matters

FIG. 3-10 : SITE RECORDS – AN OVERVIEW

© HSKS
OFFICIAL WORK RECORDS: AN OVERVIEW

TIMING OF PURPOSE CONTENTS PROCEDURAL


SUBMISSION MATTERS

USE OF
DAILY WEEKLY FORTNIGHTLY DESIGNATED SIGNING OR
STAFF FOR ENDORSEMENT

• Preparing • By authorized
TIME OF SAFE
• Maintaining ENTRY Person(s) KEEPING
• Submitting • S.O/ Contract
• Daily Administrator • By S.O./Contract
FOR BASIS administrator
RECORD OF FOR CONTRACT OF OFFICIAL
SITE INFORMATION ADMINISTRATION PROGRESS REPORT • Up to lapse of
period of
limitation

SITE WORK/ RECORD RECORD OF WEATHER PROBLEMS INSTRUCTIONS MISCELLANEOUS


ACTIVITIES OF WORKERS PLANT/MACHINER CONDITIONS ENCOUNTERED
Y

• Planned • Skilled • On site • Affecting work • Design • Received • Site/ Factory


Visits
• Undertaken • Unskilled • Delaying site • Site • Carried Out
operations • Inspections
• Coordination • Outstanding
• Due to 3rd Parties

FIG. 3-11 : OFFICIAL WORK RECORDS – AN OVERVIEW


© HSKS
SITE DIARY: AN OVERVIEW

NATURE DURATION CONTENTS PROCEDURAL


MATTERS

• Preferably kept by • From commencement of


each and every site work on site until
personnel completion

• Personal record of site • If necessary until the end


activities of the contract CHECKING / PRESENTATION
ENTRIES ON ON REQUEST/ SAFE KEEPING/
DAILY BASIS ENDORSEMENT CUSTODY
• Otherwise by DEMAND
designated site
supervision team
member • By designated • By Employer’s • By Employer/ • By S.O./ contract
person Representative/ S.O./ any administrator
Designated interested party
person • Up to lapse of
period of
• Accuracy of limitation
entries

SITE WORK/ PROBLEMS


ACTIVITIES ENCOUNTERED INSTRUCTIONS RECORD OF MISCELLANEOUS ATTACHMENTS

• Undertaken • As to Site Work • Issued to Contractors • Contractor’s • Site/ factory visits • ‘As-Built’ sketches,
defaults drawings, diagrams,
• Coordination • Carried out by /omissions • Weather conditions etc.
Contractor
• Disruption to site • ‘As-erected’/ ‘As-
activities Installed’ Work/ plant,
etc.
FIG. 3-12 : SITE DIARY – AN OVERVIEW

© HSKS
SUPERVISION OF WORKS/
CONTRACT ADMINISTRATION

© HSKS
4.0 SUPERVISION OF WORKS/CONTRACT ADMINISTRATION

1.0 CONTRACT ADMINISTRATION

 PURPOSE
 DESIGNATION
 ROLES
 SOURCES OF DUTIES AND POWERS
 REPRESENTATIVE/ASSISTANTS
 PRINCIPAL DUTIES
 LIABILITY

2.0 SUPERVISION

 FORMS
 DURATION
 LEVEL
 LIABILITIES

3.0 DISCUSSION OF CASE LAW

© HSKS
ENSURE THAT CONTRACTOR
FULFILLS HIS OBLIGATIONS
ENSURE WORKS UNDER THE CONTRACT
SATISFACTORILY
COMPLETED WITHIN ENSURE THAT EMPLOYER
ORIGINAL CONTRACT PERIOD FULFILLS HIS OBLIGATIONS
AND PRICE UNDER THE CONTRACT

CONTRACT
ADMINISTRATION:
PRIMARY PURPOSES

ENSURE THAT NEEDS/ ENSURE THAT EMPLOYER


OBLIGATIONS OF CONTRACT FULFILS HIS
ADMINISTRATOR UNDER STATUTORY/LOCAL
CONTRACT/STATUTE AUTHORITY REQUIREMENTS
ADEQUATELY FULFILLED ENSURE THAT EMPLOYER’S
POSITION ADEQUATELY
PROTECTED AGAINST VARIOUS
CLAIMS

FIG. 4-1 : CONTRACT ADMINISTRATION – PRIMARY PURPOSES

© HSKS
CONSTRUCTION SUPERINTENDING
MANAGER OFFICER/ S.O.

CONTRACT
PROJECT DIRECTOR ADMINISTRATORS:
ARCHITECT
COMMON
DESIGNATIONS

EMPLOYER’S
ENGINEER
REPRESENTATIVE

FIG. 4-2 : CONTRACT ADMINISTRATORS – COMMON DESIGNATIONS

© HSKS
AS TO
RIGHTS/ DUTIES UNDER
THE CONTRACT
WITH IMPLIED/
WITH EXPRESS OSTENSIBLE AS TO MATTERS AS TO OTHER
AUTHORITY AUTHORITY OF COST MATTERS

AS AN AGENT AS AN ADVISOR
OF THE EMPLOYER TO THE EMPLOYER

CONTRACT
ADMINISTRATOR:
RANGE OF ROLES
PERFORMED

AS AN INDEPENDENT AS AN INDEPENDENT/
CONTRACTOR IMPARTIAL
ADJUDICATOR

WHERE SUCH FOR MAINLY AS TO DISPUTE AS TO


WORK DESIGN/ RESOLUTION CERTIFICATION
IS REQUIRED DETAILING
POST- WORK
CONTRACT

FIG. 4-3 : CONTRACT ADMINISTRATOR – RANGE OF ROLES PERFORMED

© HSKS
CONDITIONS
CONDITIONS OF CONDITIONS OF
TERMS OF OF CONTRACT ENGAGEMENT/ CONTRACT
REFERENCE OF BEING SERVICES BEING
APPOINTMENT ADMINISTERED AGREEMENT ADMINISTERED

‘IN-HOUSE’ EMPLOYEE EXTERNAL BODY/PERSON

CONTRACT ADMINISTRATOR: SOURCES OF DUTIES AND POWERS

FIG. 4-4 : CONTRACT ADMINISTRATOR – SOURCES OF DUTIES AND POWERS

© HSKS
ARCHITECT

SPECIALIST
CONSULTANT CIVIL ENGINEER

PROJECT MANAGER CONTRACT ADMINISTRATOR’S STRUCTURAL ENGINEER


REPRESENTATIVES/ ASSISTANTS:
TYPICAL EXAMPLES

QUANTITY SURVEYOR MECHANICAL ENGINEER

ELECTRICAL ENGINEER

FIG. 4-5 : CONTRACT ADMINISTRATOR’S REPRESENTATIVES/ASSISTANTS - TYPICAL


EXAMPLES

© HSKS
OVERALL SUPERVISION PROGRESS MONITORING

ADMINISTRATION OF PAYMENTS ORDERING VARIATIONS

ISSUING INFORMATION,
DRAWINGS, DETAILS, ETC. ISSUING RELEVANT INSTRUCTIONS

GRANTING APPROVALS, CONSENTS, ETC. INSPECTIONS OF WORKS

NOMINATING SUB-CONTRACTORS, ETC. ADVISING EMPLOYER

CONTRACT ADMINISTRATOR’S PRINCIPAL DUTIES FOR


TRADITIONAL GENERAL CONTRACTS

ISSUING NECESSARY REPORTS PARTICIPATING IN TESTING AND COMMISSIONING

OVERSEEING TRAINING OF EMPLOYER’S


O & M PERSONNEL MONITORING SERVICING AND MAINTENANCE

OVERSEEING COMPLETION & CHECKING AND APPROVING O & M MANUALS &


HANDING OVER OF WORKS ‘AS-BUILT’ DRAWINGS

MONITORING
PREPARING ‘FINAL ACCOUNT’
RECTIFICATION OF DEFECTS

PARTICIPATING IN PREPARATION OF MIGRATION/


FACILITIES MANAGEMENT PLANS ‘CLOSING-OFF’ CONTRACT

FIG. 4-6: CONTRACT ADMINISTRATOR’S PRINCIPAL DUTIES FOR TRADITIONAL GENERAL


CONTRACTS
© HSKS
FULL-TIME SUPERVISION

NOMINAL SUPERVISION STANDING


SUPERVISION

FORMS OF SUPERVISION:
COMMON LABELS

PERIODIC SUPERVISION CONSTANT SUPERVISION

PART-TIME SUPERVISION

FIG. 4-7 : FORMS OF SUPERVISION – COMMON LABELS

© HSKS
SUPERVISION/INSPECTIONS: OVERVIEW (PART I)

TYPICAL TYPICAL
CLAUSES IN NATURE PURPOSES
PROVISIONS IN
AGREEMENTS AND MEANING
BY-
BY-LAWS

• Engineer’s Agreement: • Building (Federal Territory of • Terms used synonymously • See Keating’s definition in
Kuala Lumpur) By-Laws 1985: ‘Building Contracts’
1. Clause 8.1 and 8.7 BEM • See Newey J’s definition
Form (1999) 1. By-Law 6: Supervision of • Three fold purpose:
Works • Distinction: Inspection imposes a
• Architect’s Agreement lesser duty: William Tompkinson 1. To ensure contractor
2. By-Law 23(1): Certificate For v St. Michael in the Hamlet. carries out work in
1. Clause 5(4)(iv) Part II: Occupation accordance with contract.
Architects (Scale of • In absence of express provisions
Minimum Fees) • By-Law 5(1) City of Kuala to contrary courts imply a duty of 2. To enable contract
(Amendment) Rules 1992 Lumpur (Earthworks) By-Laws supervision: Alexander Corfield v administrator to discharge
1975 David Grant. his obligations to employer.
2. Clause 9 Conditions of
Engagement of Architect • Malaysia: Statutory provisions 3. To enable contract
necessitate ‘supervision’ administrator to meet his
statutory obligations

FIG. 4-8 : SUPERVISION/INSPECTIONS – OVERVIEW (PART I)

© HSKS
SUPERVISION/INSPECTIONS: OVERVIEW (PART II)

LEVEL OF RESIDENT
DURATION SUPERVISION LIABILITIES
SITE STAFF
REQUIRED

• Determining factors: • Determined by: • Necessity for Resident Site • Primary responsibility for
Staff (RSS) supervision: contractor’s.
1. Nature of works under 1. Conditions of engagement See East Ham Corp. v
contract • Typical examples: Bernard Sunley.
2. Applicable statutory
2. Conditions of engagement provisions e.g. By-Laws 1. Resident architect/engineer • Heads of liabilities of contract
2. Clerk-of-works. administrator for defaults/
• Normal periods: • Prevailing Forms: 3. Other relevant staff breaches:
1. Up to issue of Practical 1. Category I: Full- • Engagement:
Completion; or time/Standing/ Constant 1. Contractual
supervision 1. By employer; or 2. In tort
2. Up to application of certificate 2. By contract administrator 3. Statutory
for occupation; or 2. Category II: Part-
Time/Periodic Supervision • Powers and duties determined • Position of contract
3. Up to issue of Certificate of by engineering/construction administrators who are
Making Good Defects 3. Category III: ‘Nominal’ contract being administered professional engineers,
Supervision and/or letter of delegation of architects, etc.
• Common practice is up to issue of
Certificate of Making Good • Legal Position: power.
Defects • Responsibilities of:
1. Must be reasonable for
works involved 1. RSS
2. Must be sufficient to check 2. Contract Administrator
the important elements
3. Adequate to meet statutory
requirements
4. Sufficient to meet
obligations of engagement

FIG. 4-9 : SUPERVISION/INSPECTIONS – OVERVIEW (PART II)

© HSKS
CONTRACT ADMINISTRATOR’S LIABILITIES: AN OVERVIEW (PART I)

LEGAL KNOWLEDGE CONTRACTUAL


HEADS OF LIABILITIES LIABILITY
AND PERSONAL DUTY

• Three main categories: • General position: Required to have


knowledge of all legal matters
1. Contractual relating to work being undertaken
2. Tortious
3. Statutory • Nature of matters.
DEFENCES
• Characteristics: • Consequences of failure
1. Not distinct/mutually exclusive • Duty is personal and non-delegable
2. Concurrent/complementary • Prove no valid
express/implied contract
3. Choice of option on aggrieved part of engagement
• If there is such valid
contract prove:

1. Contract didn’t impose


particular duty breach
of which claimed, or
GENERAL POSITION STANDARD OF CARE EFFECT OF BREACH
2. Service actually
rendered was of the
• Action by employer under terms • Duty of care owed to employer • Two options available to standard reasonably
of contract of engagement employer: expected under the
• Usually to use ‘reasonable skill circumstances
• If no express terms, implied by and care’ 1. Rescind contract and sue for
law damages; or
• Duty and standard of care either:
• Contract of engagement: 2. Affirm contract and sue for
1. Expressed in contract of damages
1. Standard forms, or engagement, or
2. ‘Bespoke’ Forms • Right of election of option
2. Implied by law belongs to employer

FIG. 4-10 : CONTRACT ADMINISTRATOR’S LIABILITIES – AN OVERVIEW (PART I)

© HSKS
CONTRACT ADMINISTRATOR’S LIABILITIES: AN OVERVIEW (PART II)

TORTIOUS LIABILITY

GENERAL POSITION NEGLIGENCE

• Duty of care in tort of negligence concurrent


with contractual duty: Brown v Boorman
• Common Forms:
1. Acts/omissions
2. Mis-statements

BASIC STANDARD REASONABLE ESTABLISHING LIABILITY TO


DEFINITION ELEMENTS SKILL & CARE LIABILITY DEFENCES
OF CARE 3RD PARTIES

• Laid down in • D owed P duty of • Application of the • Criterion: Objective • Per Hunter v • Only 3 types: • No liability to
Donoghue v care ‘Bolam Test’ Henley contractor
Stevenson • Less onerous 1. Deny existence of
• D breached this duty • Use of ‘Reasonable 1. There is a usual duty of care • Possible
• ‘Neighbourhood’ Man’ test • Use of standards and normal exceptions:
principle • Consequence: P prevailing at time of practice 2. Prove claim made See Para 5.9B5.
suffered • Use by Malaysian default not of type
• Important elements: loss/damage Courts 2. D did not adopt currently
• Proscribe use of the practice recognized
1. Causation • Loss/damage • 2 Categories: hindsight
2. Forseeability suffered not remote 3. Practice 3. Show service
1. Reasonable • See Eckersly v adopted by D rendered meets
skill & care Binnie & Partners would not be ‘Bolam Test’
2. Fitness for adopted by
another • No immunity to suit:
purpose Sutcliffe v Thackrah
reasonable D
• Need to satisfy all 3 • Situation per ‘Pure
element on balance Economic Loss’
of probabilities

FIG. 4-11 : CONTRACT ADMINISTRATOR’S LIABILITIES – AN OVERVIEW (PART II)


© HSKS
CONTRACT ADMINISTRATOR’S LIABILITIES: AN OVERVIEW (PART III)

STATUTORY LIABILITY

LIABILITIES UNDER PROFESSIONAL


GENERAL POSITION DIRECT
DELEGATED LIABILITY
STATUTORY LIABILITY
LEGISLATION

• In addition to Contractual and • Various Acts of Parliament • Liability under various By- • For professional contract
Tortious Liability applicable Laws e.g. UBBL, etc. administrator
• Various sub-heads: • Principal example: S71 Street, • Penalties/sanctions stipulated • Under specific Acts of
Drainage & Building Act 1974 in the By-Laws Parliament
1. Direct statutory liability
2. Under delegated legislation • Penalty for mis-supervision, etc. • Possible sanctions:
3. Professional liability 1. Fine
2. Suspension
3. Cancellation of
registration

FIG. 4-12 : CONTRACT ADMINISTRATOR’S LIABILITIES – AN OVERVIEW (PART III)

© HSKS
PAYMENTS/
COMMERCIAL MATTERS

© HSKS
5.0 PAYMENTS/COMMERCIAL MATTERS

• LEGAL OBLIGATION OF EMPLOYER

• PAYMENT TO MAIN CONTRACTOR/TURNKEY CONTRACTOR

• PAYMENT TO SUB-
SUB-CONTRACTORS

• ‘BACK TO BACK’
BACK’ PAYMENTS

• BREACHES IN PAYMENT OBLIGATIONS

• RELEVANT CASES

• SUTCLIFFE V THACKRAH [1974] 1 ALL ER 319

* CROUDACE LTD. V THE LONDON BOROUGH OF LAMBETH [1986] 33 BLR 20

* GUNUNG BAYU SDN. BHD. V SYARIKAT PEMBINAAN PERLIS SDN. BHD. [1987] 2 MLJ 332

* HAJI ABU KASSIM V TEGAP CONSTRUCTION SDN. BHD. [1981] 2 MLJ 149

* KAH SENG CONSTRUCTION SDN. BHD. V SELSIN DEVELOPMENT SDN. BHD. [1997] 1 CLJ
SUPP 448

* YONG MOK HIN V UNITED MALAY STATES SUGAR INDUSTRIES LTD. [1966] 2 MLJ 286

* JALLCON (M) SDN. BHD. V NIKKON METAL (M) SDN. BHD. (No. 2) [2001] 5 MLJ 716, HC.

© HSKS
PROCEDURES AND CONDITIONS
PRECEDENT

QUANTUM/AMOUNT SET-OFF/DEDUCTIONS

TIMING ENFORCEMENT/HONOURI
NG

PAYMENT: ASPECTS OF CONTRACTOR’S


ENTITLEMENTS/EMPLOYER’S OBLIGATIONS

FIG. 5-1: PAYMENTS – ASPECTS OF CONTRACTOR’S ENTITLEMENT/EMPLOYER’S OLIGATIONS

© HSKS
TIMING OF PAYMENT TO CONTRACTOR: PRINCIPAL SCHEMES/SCHEDULES

PERIODIC SCHEDULE PERIODIC SCHEDULE


DURING CURRENCY ADVANCE PAYMENT AFTER COMPLETION/
OF THE CONTRACT END OF CONTRACT

OF WHOLE OF PART OF AFTER ISSUE AFTER ISSUE OF


CONTRACT SUM CONTRACT SUM OF CPC FINAL CERTIFICATE

STAGES/MILESTONE AFTER COMPLETION/ MISCELLANEOUS/


PAYMENT END OF CONTRACT METHODS

AFTER AFTER ISSUE OF


PHYSICAL WORKS FINANCIAL
ISSUE OF CPC FINAL CERTIFICATE

FIG. 5-2 : TIMING OF PAYMENT TO CONTRACTOR – PRINCIPAL SCHEMES/SCHEDULES

© HSKS
START

Contract administrator to
resolve all preliminary issues

Yes Are the preliminary


matters expressly stipulated
in the contract?

No

Yes Are they included


in the Project Procedures
Manual?

No

Have these been No


sorted- out following award of
contract?

Yes

Have these No Contract administrator


been formalized by all the to take necessary
parties? action forthwith

Yes
Contract administrator to issue
formal record of issues agreed
upon by all relevant parties

All relevant parties


to take necessary steps to
implement issues

FIG. 5-3: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART I)


© HSKS
A

Establish if the contractor


has fulfilled his first
pre -condition to payment

Has the contractor No


commenced with the work
under the contract?

Yes

Has he No
executed any physical
work?

Yes

Has he No Contractor not


delivered materials to entitled to any
site? payment

Yes

Prima facie, contractor Contract administrator


may be entitled to payment not obliged to initiate
the progress payment

Establish if it is necessary
for the contractor to apply for
the required payment

No Does the contract


contain an express term
thereto?

Yes

B C D

FIG. 5-4: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART II)
© HSKS
B C D

Contractor not No
Is it mandatory?
obliged to apply

Yes

Contract administrator Has No Contractor may


obliged to initiate contractor complied with not be entitled to
process on his own requirements? payment until
volition he satisfies
pre -conditions
Yes

Contract administrator to proceed


with the next stage i.e. valuation

Has the No
date of valuation been
reached?

Yes

No Prima facie, valuation


Have the may not be initiated
relevant pre-conditions been until achievement
fulfilled? of necessary
requirements
Yes

No Have the
parties involved been
identified?

Yes

Deficiencies/omissions No Has the


to be addressed method for valuation been
forthwith to enable confirmed?
process to continue
Yes

E F G

FIG. 5-5: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART III)
© HSKS
E F G

Valuation of works to be carried


out jointly by the relevant parties

Valuers to prepare a valuation report

Yes Does the


contractor agree with the valuation?

No
Yes Does he
sign off the No Does he officially
valuation report? register his protest with
valuers?
No Yes
Do the valuers No
Valuation deemed to have consider the objections
been accepted by the protest?
contractor
Yes
Do they No
agree with the Contractor may protest to
objections? the certifier if necessary
Yes
Valuers may revise/amend Does the
the valuation as necessary Contractor No
protest to the
certifier?
Valuers to endorse/sign off
the valuation report prepared Yes

H I J K

FIG. 5-6: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART IV)

© HSKS
H I J K

Valuation report together with


all other necessary documents to
be submitted to the certifier
Certifier to clarify/
discuss deficiencies/
Certifier to carry out preliminary reviews omissions with the
valuers

Is the valuation Deficiencies/


No omissions may
report complete, sufficient and
accurate? compromise the
certification
Yes
Certifier to take Has the
objections into Yes
contractor any valid grounds
consideration before for objecting?
undertaking certification
No
Certifier not to consider
L objections any further

Certifier may exercise Is the date


his discretion in No
for certification
undertaking certification imminent?
Yes

Should in Has the stipulated No Certifier has no discretion to


No his discretion a minimum value of work been exceeded?
carry out certification
certificate be
issued? Yes
Yes Certifier to proceed with the
necessary certification procedures

M N O

FIG. 5-7: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS


(PART V)
© HSKS
M L N O

Is the 1st Interim Certificate due? No

Yes
Have all No
the stipulated pre-conditions been met?

Yes
Is the
subsequent Interim Certificate No
due?
Yes
Have all Prima facie,
No certificate cannot
the relevant pre-conditions
- been met?
be issued

Yes
Certifier to proceed with
preparation of Interim Certificate

Is there a Yes Use the


standard form of certificate prescribed? standard form
as prescribed
No
Utilize the form Yes
unless found Has a ‘bespoke’ form been generated?
not suitable
No
Certifier to develop an ‘ad hoc’ form
meeting the necessary criteria/contents
requirements

P Q R S T

FIG. 5-8: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VI)
© HSKS
P Q R S T

Certifier to fill in all details


completely, sufficiently and
correctly in certificate

Are there Yes


any NSCs/Nominated
Suppliers?

No
Amount certified
Are for such parties
Yes to be indicated
there any official
assignees? separately in certificate

No

No Are
all procedural requirements met?

Yes

No Are
all formal requirements
met?

Yes
Certificate may be
challenged as invalid and No Is the signatory an
unenforceable, if and authorized person under the
when issued contract?

Yes

Have all the Deficiencies/ errors may


relevant checks for errors, No
compromise validity of
etc. been undertaken? certificate

Yes

U V W X

FIG. 5-9: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VII)

© HSKS
U V W X

Contract administrator to CA to rectify


issue relevant certificate deficiencies/errors
as soon as possible

Is there a Certificate to be issued


certification period stipulated No within a reasonable time
in the contract? of application/ valuation

Yes
Prima facie, employer may
be in breach of contract. Is certificate
Contractor may take No
issued within the said
appropriate action for period?
employer’s breach
Yes
Contractor to Is the recipient
be furnished with No
of the original copy
original copy stipulated?

Yes
Default in service may
constitute a breach of
Is the certificate No contract on employer’s part.
issued to the stipulated To be corrected/ rectified
person? forthwith
Yes

Are copies Relevant parties have a


No
issued to the relevant right to demand the
parties? necessary copies from
contract administrator
Yes

No Is the service
of certificate formally
evidenced?

Yes

Y Z AA AB

FIG. 5-10: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART VIII)
© HSKS
Y Z AA AB

Establish the specific post--


certification requirements

Do the Omission to
recipients formally No acknowledge may
acknowledge receipt of lead to future evidential
document? problems
Yes
Contract administrator
No Is presentation to procure said
of certificate stipulated in the acknowledgements as
contract? soon as possible
Yes
Contractor
may present Is there a
certificate within No period stipulated for the
a reasonable presentation?
period of receipt
Yes

Is presentation No Delay may postpone


formally effected within this employer’s obligation to
period? honour certificate

Yes
Does employer Omission to acknowledge may
formally acknowledges receipt No lead to future evidential
of the certificate from problems and may affect the
contractor? honouring of certificate

Yes
Employer to review Contractor to procure
certificate for validity said acknowledgement
as soon as possible

AC AD AE AF

FIG. 5-11: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART IX)
© HSKS
AC AD AE AF

Are Employer may challenge


there grounds for Yes certificate and refuse to
challenging validity of honour it citing the
certificate? relevant grounds
No
Employer to proceed with honouring
certificate issued/ presented (as
applicable)

No Are there any


set-offs/deductions
- to be
made?

Yes
Employer must
No Are these
pay amount
expressly permitted by the
as certified
contract?
to the contractor
Yes
Has the Employer to determine amount
amount certified less the set- No due before the stipulated
-
offs/ deduction been honouring period lapses
established?
Yes

Has the final No


sum due been paid to the
contractor?

Yes

Has this been done in the No Employer culpable


stipulated honouring of breach of contract.
period? Contractor to take
appropriate action.
Yes

STOP

FIG. 5-12: FLOWCHART ON GENERAL PROCEDURE FOR PROCESSING OF PAYMENTS (PART X)


© HSKS
RECOVERY OF THE UNPAID
AMOUNT

MISCELLANEOUS INTEREST ON THE


REMEDIES UNPAID AMOUNT

DEFAULT IN PAYMENT:
TYPICAL CONTRACTUAL
REMEDIES

RIGHT TO DETERMINE RIGHT TO REDUCE RATE


EMPLOYMENT UNDER OF EXECUTING WORK
CONTRACT
RIGHT TO SUSPEND WORK

FIG. 5-13 : DEFAULT IN PAYMENT - TYPICAL CONTRACTUAL REMEDIES

© HSKS
CERTIFICATE WRONG ON ITS’ FACE

CERTIFICATE FUNDAMENTALLY INACCURATE

CERTIFICATE NOT IN CORRECT FORM

CERTIFICATE ISSUED BY UNAUTHORISED PERSON

CERTIFICATE ISSUED IN UNAUTHORISED MANNER

INTERIM CERTIFICATES:
TYPICAL CHALLENGES

CERTIFICATE ISSUED OUT OF TIME

CERTIFIER ACTING ‘ULTRA VIRES’

CERTIFIER IMPROPERLY PRESSURIZED/INFLUENCED

CERTIFICATE SUBJECT TO FRAUD/COLLUSION

FRAUD, DISHONESTY/FRAUDULENT CONCEALMENT BY CONTRACTOR

MISCELLANEOUS CHALLENGES

FIG. 5-14: INTERIM CERTIFICATES – TYPICAL CHALLENGES

© HSKS
DIRECT PAYMENT BY THE
EMPLOYER

PAYMENT UPON CERTIFICATION CONTINGENT PAYMENT

PAYMENT TO SUB-CONTRACTORS:
PRINCIPAL METHODS

FIG. 5-15 : PAYMENT TO SUB-CONTRACTORS – PRINICPAL METHODS

© HSKS
START

- SC to make fresh submission in the


Sub-Contractor (SC) forwards details of amount
claimed to Main Contractor (MC) officially next application
No

Is it within No Does the


the prescribed time MC accept the
limits? submission?

Yes
Yes
MC to include
SC’s details in his claim

MC to submit consolidated claim


to the Contract Administrator (CA)

CA to carry out the necessary valuation

CA to issue interim
payment certificate to MC

Employer to pay certified amount to


MC within the Honouring Period

Establish if there is a
Contingent Payment Type II
-
clause in the sub-contract

FIG. 5-16: FLOWCHART ON GENERAL PROCEDURE FOR TYPE II ‘CONTINGENT PAYMENT’ (PART I)

© HSKS
A

Is there No
such a clause in the
contract?

Yes
Is the MC may pay SC within
No
period for payment a reasonable time of receipt of
stated? monies from the Employer

Yes

Yes Does the MC


pay the SC within the
said period?

No
SC to pursue the remedies
available under the contract

Are there
Yes SC to initiate the contractual
any contractual remedies
remedies as applicable
available?

No

Is there Yes SC to initiate the Arbitration


an arbitration process if necessary
agreement?

No

SC to pursue his common


law remedies if necessary

STOP
FIG. 5-17: FLOWCHART ON GENERAL PROCEDURE FOR TYPE II ‘CONTINGENT PAYMENTS’
(PART II)
© HSKS
PAYMENT IN ‘PACKAGE DEAL’ TYPES OF CONTRACTS: AN OVERVIEW

CONTRACT SUM QUANTITIES MEASUREMENT


ANALYSIS

PURPOSE DRAFTING STRUCTURE GENERAL SITUATIONS


ACCURACY
POSITION WHERE USED
• For Tender Analysis • Normally by • Given in some Forms • As based on • Changes/V.O.s • Effect of
• For Interim Payment Contractor e.g. JCT 98, PWD Lump Sum and measurement
Form DB/T, etc. • Unforeseen
• Samples may be due to nature of expressly
• Valuation of Conditions
given by Employer • Required for: contract stipulated in
Changes/
in Employer’s some forms
Provisional Sums • No requirement
Requirements 1. Overall Works for measurement • Mostly deals with
• For any Price 2. Sections or patent errors
Adjustment Phases

GENERAL EXPRESS ERRORS/


POSITION PROVISIONS OMISSIONS PREPARATION

• Whenever used, effect • Included in most • Risk on Contractor • Contractor responsible


not similar to TGC Standard Forms
• E.g. Clause 55(2) ICE • If Employer prepares,
• Are deemed to be only • E.g. Clause 55(1) ICE, Form risk for errors/omissions
estimates Clause 13.1(d) FIDIC, etc. normally passed on to
Contractor

FIG. 5-18 : PAYMENT IN ‘PACKAGE DEAL’ TYPES OF CONTRACTS: AN OVERVIEW

© HSKS
FINAL AMOUNT TO WHICH
CONTRACTOR ENTITLED TO UNDER
THE CONTRACT

FINAL AMOUNT (SET OFFS/


DEDUCTIONS) TO WHICH
FINAL ADJUSTMENTS TO EMPLOYER ENTITLED TO UNDER
THE CONTRACT SUM THE CONTRACT

FINAL ACCOUNT: PRINCIPAL CONTENTS

FIG. 5-19 : FINAL ACCOUNT – PRINCIPAL CONTENTS

© HSKS
APPROVED VARIATIONS
TO THE CONTRACT

MISCELLANEOUS
APPROVED
ADJUSTMENTS
CONTRACTOR’S CLAIMS

PERMITTED COSTS FOR


ADJUSTMENT FOR PRICE TESTING, OPENING UP OF
FLUCTUATION, ETC. ADJUSTMENT TO THE WORK, ETC.
CONTRACT SUM: TYPICAL
HEADS/ITEMS

ADJUSTMENT FOR P.C. FEES AND CHARGES FOR


SUMS/ PROVISIONAL PERMANENT
SUMS CONNECTIONS
REMEASUREMENT OF
‘PROVISIONAL’
ITEMS/WORK

FIG. 5-20 : ADJUSTMENT TO THE CONTRACT SUM – TYPICAL HEADS/ITEMS

© HSKS
VARIATIONS/CHANGES

© HSKS
6.0 VARIATIONS/CHANGES

• WHAT CONSTITUTES ‘VARIATIONS/CHANGES’


VARIATIONS/CHANGES’

• ISSUES AS TO VALIDITY

• PROBLEMS WITH VARIATIONS

• INVALID VARIATION ORDERS AND EFFECTS

• LIMITATIONS OF VARIATIONS

• RELEVANT CASES

* SHARPE V SAN PAULO RAILWAY [1873] L.R. 8 CH. APP. 597

* RE CHITTICK & TAYLOR [1954] 12 WWR 653

* MITSUI CONSTRUCTION CO. LTD. V A.G. OF HONG KONG [1986] 33 BLR 1

* CARR V JA BERRIMAN PTY LTD. [1953] 27 A.L.J.R. 273

* COMMISSIONER FOR MAIN ROADS V REED & STUART PTY LTD. & ANOR [1974] A.L.J.R.
461

* SIR LINDSAY PARKINSON & CO. LTD. V COMMISSIONERS OF HIS MAJESTY’S WORKS
AND PUBLIC BUILDINGS [1950] 1 ALL ER 2008

* ANTARA ELEKTRIK SDN. BHD. V BELL & ORDER BHD [2002] 3 MLJ 321, HC.
© HSKS
VARIATIONS

FACTORS DETERMINING
TYPES A VALID V.O.

ADDITION OMISSION HYBRID

LEGAL NATURE OF
FORMALITIES
PROPOSED CHANGE

ISSUE BY PROCEDURAL EXPRESS CONTRACT APPLICABLE


DESIGNATED CONDITIONS COMMON
REQUIREMENTS
OFFICER APPLICABLE LAW RULES

FIG. 6-1: VARIATIONS: OVERVIEW

© HSKS
CHANGE TO BE IN RELATION
TO SCOPE OF THE WORK

SCOPE OF WORK BEING


CHANGED MUST BE AS
EXPRESSLY OR IMPLIEDLY
CONTAINED IN CONTRACT
A CHANGE BEING EFFECTED DOCUMENTS

CHANGES/VARIATIONS: BASIC ELEMENTS

FIG. 6-2 : CHANGES/VARIATIONS – BASIC ELEMENTS

© HSKS
INCREASE/
DECREASE OMIT
QUANTITY OF
WORK
WORK

EXECUTE
CHANGE
ADDITIONAL WORK
CHARACTER OF
OF ANY KIND
WORK

CHANGE VARIATIONS: CHANGE QUALITY


SEQUENCE OF TYPICAL OF WORK
WORK
EXAMPLES

CHANGE TIMING
OF WORK CHANGE
ACTIVITIES KIND OF WORK

CHANGE
DIMENSIONS OF CHANGE LEVELS
WORK OF WORK
CHANGE POSITION
OF WORK

FIG. 6-3: VARIATIONS - TYPICAL EXAMPLES

© HSKS
OMISSIONS

ADDITIONS HYBRID

ACCORDING TO NATURE
OF THE CHANGE

CONTRACTOR NSC
TIME IMPLICATIONS

CONTRACT FINANCIAL COMBINATION


EMPLOYER ADMINISTRATOR CONSIDERATIONS OF BOTH

ACCORDING TO
ACCORDING TO IDENTIT Y
CONSEQUENCES/EFFECT
OF INITIATOR OF CHANGE
OF THE CHANGE

TYPES OF VARIATIONS:
MAIN METHODS OF CLASSIFICATION

FIG. 6-4: TYPES OF VARIATIONS – MAIN METHODS OF CLASSIFICATION

© HSKS
CHANGES IN
EMPLOYER’S DEFECTIVE
REQUIREMENTS DRAWINGS

INTEFERENCE DEFECTIVE
BY EMPLOYER SPECIFICATIONS

MAL- ITEMS DEFECTIVE


ADMINISTRATION CONSTITUTING CONTRACT
OF CONTRACT DOCUMENTS
VARIATIONS

WRONG/
NEGLIGENT ADVICE DIFFERENCES
FROM CONTRACT BETWEEN BILLED
ADMINISTRATOR AND ACTUAL
QUANTITIES

CHANGES DUE
TO STATUTORY/
LEGISLATIVE
CHANGES

FIG. 6-5: ITEMS CONSTITUTING VARIATIONS

© HSKS
WHAT CONSTITUTES VARIATION WORKS

CONTRACTS CONTRACTS BASED ON VARIATION TEST


LEGAL POSITION BASED ON DRAWINGS PER RE:
BILL OF QUANTITIES AND SPECIFICATIONS CHITTICK & TAYLOR

1. Test: What is the intention of 1. Rule: All items intended to be 1. Rule: Contract requires: 1. Item specifically provided for
the parties at time of executed by Contractor must in Contract: ‘Not Extra’
contracting be provided for in the a) Not only work set out in
Contract. drawings and/or 2. If Contractor varies, contract
2. Extras: Work not specifications without an instruction:
contemplated by parties when 2. All items not provided for in Cannot Claim for ‘Extra’
contracting and not provided Contract are extras. b) But also all work incidental or
in Contract. necessarily required whether 3. If Contractor instructed by
3. Literal interpretation/ strict set out in the drawings and/or C.A. to change contract: has
3. Works which are construction. described in specifications or basis for claim for ‘Extra’
indispensably necessary to not
give effect to parties
intentions: Not extra 2. Effect: Difficult to claim extra
work [Re: Sharpe v Sao Paulo
Railway]

FIG. 6-6 : WHAT CONSTITUTES VARIATION WORKS


© HSKS
WORKS CHANGED MUST BE
DEFINED IN CONTRACT THERE MUST BE AN
DOCUMENTS ‘INSTRUCTION’

VALID VARIATION ORDER: PRINCIPAL ELEMENTS

INSTRUCTION MUST EFFECT A ‘INSTRUCTION’ TO BE ISSUED BY


CHANGE TO THE WORKS CONTRACT ADMINISTRATOR OR
BY AUTHORISED PERSON

FIG. 6-7 : VALID VARIATION ORDER – PRINCIPAL ELEMENTS

© HSKS
EXISTENCE OF EXPRESS
COMPLIANCE WITH THE CONTRACTUAL PROVISION
RELEVANT EXPRESS CONTRACT PERMITING VARIATION OF WORK
PROCEDURES UNDER THE CONTRACT

VALIDITY OF VARIATION ORDERS:


PRINCIPAL FACTORS DETERMINING

ISSUE OF VARIATION ORDER BY COMPLIANCE WITH THE


DESIGNATED PERSON APPLICABLE COMMON LAW
RULES IN RELATION TO
VARIATIONS WORKS

FIG. 6-8 : VALIDITY OF VARIATION ORDERS – PRINCIPAL FACTORS DETERMINING

© HSKS
LIMITATIONS TO VARIATIONS

LEGAL POSITION CARDINAL CHANGES

EXERCISE OF POWER
BY CONTRACT SCOPE OF WORK NATURE TESTS EFFECTS
ADMINISTRATOR
1. Power to vary work 1. Power to vary confined 1. Was it in the reasonable 1. General Rule:
confined to genuine to scope of works contemplation of the Invalid
omissions contemplated by parties parties when
at time of contracting. contracting? 2. Contractor cannot
2. If effect of omission is be compelled to
to give omitted work to 2. If effect of variation is to 2. Although not included, carry it out
3rd Parties: Invalid substantially change can it be considered an
Omission scope of work (‘Cardinal indispensable part of 3. If compelled,
Change’): Invalid the Contract? breach of contract
Variation 4. If Contractor
3. Functionally is it similar
to the intended work or carries out work,
some other work Contract rates not
required by the applicable
Contract?

DEFINITION TYPES FORM

1. Changes which render the 1. Physical work changes 1. A Single change


works substantially different
from that contracted for by 2. Financial Changes 2. A large number of
the parties otherwise small permissible
changes.
2. Constitutes a fundamental
change in the scope of the
Contract

FIG. 6-9 : LIMITATIONS TO VARIATIONS


© HSKS
PAYMENT FOR VARIED WORK:
GENERAL PRINCIPLES/METHODS

VARIED WORK WITHIN CONTRACT VARIED WORK OUTSIDE CONTRACT

ABSENCE OF EXPRESS A ‘CARDINAL’


CARDINAL’ CHANGE NOT A ‘CARDINAL’
CARDINAL’ CHANGE i.e.
EXISTENCE OF EXPRESS i.e. FUNDAMENTALLY
FORMULA IN CONTRACT DOES NOT FUNDAMENTALLY
FORMULA IN CONTRACT ALTERS CONTRACT ALTER CONTRACT

• Mutually agree upon a formula/rate; • Any contractual formula rendered • Portion of works within scope of
or invalid /inapplicable contract to be paid according to
the contract formula (if
• Be paid a reasonable sum i.e. on a • Whole works to be paid on applicable)
‘quantum meruit’ basis, etc. ‘measure and value’ basis and on
‘altered’ or ‘adjusted’ rates • Remaining works falling outside
scope of contract to be paid at a
reasonable rate

FORMULA VALID FORMULA INVALID AND/OR


AND APPLICABLE INAPPLICABLE

• Use the formula for valuation • Mutually agree upon a formula/rate;


and payment or
• No right of election • Be paid a reasonable sum i.e. on
‘quantum meruit’ basis, etc.

FIG. 6-10 : PAYMENT FOR VARIED WORK – GENERAL PRINCIPLES/METHODS


© HSKS
COST OF DELAY AND
DISRUPTION
COST OF VARIED WORK DELAY AND DISRUPTION
e.g. • Direct loss and/or
expense TO CONTRACT
• Additions
• Extended • Extension of time to
• Omissions Preliminaries Contract Period, etc.

FINANCIAL EFFECTS TIME EFFECTS

PRINCIPAL CONTRACTUAL CONSEQUENCES


OF VARIATION OF WORK UNDER CONTRACT

FIG. 6-11 : PRINCIPAL CONTRACTUAL CONSEQUENCES OF VARIATION OF WORK


UNDER THE CONTRACT
© HSKS
VALUATION OF VARIATIONS:
COMMON COMPUTATIONAL METHODS

WHERE THERE ARE


RATES/ PRICES IN THE WHERE WORK CANNOT
CONTRACT BE MEASURED

• Use of B.Q. rates • Use of Daywork Rates in Contract

• Use of Schedule of Unit Rates • On a cost-reimbursible basis


• Use of Adjusted Contract Rates

• Use of Contract Prices in: MISCELLANEOUS


WHERE NO RATES/
METHODS
a) Contract Bills; or PRICES IN CONTRACT
b) Summary of Prices; or
c) Contract Sum Analysis
• Use of ‘Fair Valuation’ principles • Use of ‘Quotation’ Method

• Use of ‘Negotiated’/’Agreed’ • Use of ‘Negotiated’/’Agreed’


Rates Rates

• Use of ‘Quotation’ Method • Payment on ‘quantum meruit’


basis or a reasonable sum
• Payment of a reasonable sum

FIG. 6-12 : VALUATION OF VARIATIONS – COMMON COMPUTATIONAL METHODS

© HSKS
START

Establish if the conditions


precedent have been satisfied

Has measurement No
stage been satisfactorily
completed?

Yes

Has the valuation No Prima facie, premature


stage been satisfactorily to prepare and issue
completed? certificate concerned

Yes

Contract administrator to prepare


certificate of variation of works

No Is there a
contract provision prescribing
the same?

Yes

Yes Are its


A requirements clear and
complete?

No

Have the No
requirements been agreed to by
the parties?

Yes

B C D

FIG. 6-13: FLOWCHART ON THE GENERAL PROCEDURE FOR THE CERTIFICATION OF


VALUATION (PART I)
© HSKS
A B C D

Have the No
requirements been complied
with?

Yes

Have the No
particulars been completely and
properly filled in?

Yes

Is the No
V.O./instruction
attached?

Yes

Are the No Omissions/deficiencies


measurement and valuation may render certificate
details endorsed? invalid

Yes

Has the certificate Contract administrator


No to address omissions
been checked for sufficiency and
accuracy? /deficiencies forthwith

Yes

No Has it been
signed by the authorized
person?

Yes

E F G

FIG. 6-14: FLOWCHART ON THE GENERAL PROCEDURE FOR THE CERTIFICATION OF


VALUATION (PART II)
© HSKS
E F G

Has it been
No prepared within a
reasonable/ prescribed period of
completion of measurement
and valuation?

Yes

Contract administrator to
issue certificate to the contractor

Contractor to check and


undertake necessary action

No Is the
certificate sufficient and
accurate?

Yes

No Has it been
signed by the authorized
person?

Yes

No Does it
Prima facie, comply with any prescribed
certificate is invalid requirements?

Yes

H I J

FIG. 6-15: FLOWCHART ON THE GENERAL PROCEDURE FOR THE CERTIFICATION OF


VALUATION (PART III)
© HSKS
H I J

Does the Yes Contractor


contractor agree with the to formally signify
content? acceptance

No

Does he notify No
the contract administrator officially
of his dissent?

Yes

Are the No
full particulars/details
given?

Yes

Contractor obliged No Is there a


to give notice period stipulated for the giving of
within reasonable the notice?
period only

Yes
Contractor deemed
Has the No to have accepted
contractor met the time the measurement
requirements? and valuation

Yes
Contract administrator
to review contractor’s notice
and make decision

K L M

FIG. 6-16: FLOWCHART ON THE GENERAL PROCEDURE FOR THE CERTIFICATION OF


VALUATION (PART IV)
© HSKS
K L M

Is the
Yes notice sufficient and
accurate?

No

No Has the contractor


been asked to furnish further
details?

Yes

No
Has he complied with the request?

Yes

Is the contractor’s stand Yes


reasonable?

No Contract
administrator to
Is there any Yes undertake necessary
reason not to reject the contractor’s amendments/
application? revisions

No
N
Reject the contractor’s application/notice

Communicate decision to the contractor N

Does the Contractor to give


Yes necessary notice. Contract
contractor wish to proceed with
dispute resolution? administrator to use valuation
set out in the interim period
No

STOP
FIG. 6-17: FLOWCHART ON THE GENERAL PROCEDURE FOR CERTIFICATION OF VALUATION (PART V)
© HSKS
VARIATIONS: PRINCIPAL REQUIREMENTS FOR ‘PACKAGE DEAL’
TYPE OF CONTRACTS

EXPRESS EMPLOYER’
EMPLOYER’S CONTRACTOR’
CONTRACTOR’S VARIATIONS VARIATIONS EFFECT OF
STIPULATIONS RIGHT TO VARY RIGHT TO VARY IN DLP/DCP IN WRITING PROCEDURE

• In most Standard • Permitted expressly • Permissible if only • Formal V.O.


Forms in most Standard expressly allowed Instruction from
Forms by contract E.R./P.D. condition
• Stipulate – Extent, precedent to recovery
Procedure, etc. • Due to: • Some Standard of payment
1. Value Forms do allow e.g.
engineering ICE, FIDIC, etc. • Failure of Contractor
2. Buidability • Others are silent to observe procedure/
3. Safety e.g. JKR, etc. formalities – may
4. Legal/Physical compromise recovery
NEED impossibility
EXPRESS
EXPRESS NEED FOR
FOR CONTRACTOR’
CONTRACTOR’’SS
PROVISIONS
PROVISIONS CONSULTATION RESPONSIBILITY

• Enshrined in • Prior to ordering • Be pro-active


all Standard V.O.
Forms • Not to unreasonably
• Get Contractor’s withhold consent, etc.
view on effect of
V.O. on
programme

NECESSITY
NECESSITY FOR
FOR
CONTRACT
CONTRACT ‘‘WRITTEN’
WRITTEN’’ RECOVERY
RECOVERY WITHOUT
WITHOUT
PROVISIONS ORAL INSTRUCTIONS INSTRUCTIONS
PROVISIONS INSTRUCTIONS
INSTRUCTIONS INSTRUCTIONS

• Most Standard Forms have • Requirement for ‘Writing’ • Only if contract expressly • Generally no
express clauses allows
• Includes: • Situations where permitted:
• Issued by E.R./ P.D. • Need for written confirmation
1. Letters 1. If contract expressly allows
2. Minutes of Meetings • Duty of confirmation either on: 2. Under Waiver/Estoppel
3. Drawings 3. Under concept of
1. Contractor or ‘Constructive Change’
2. Employer

FIG. 6-18: VARIATIONS – PRINCIPAL REQUIREMENTS FOR ‘PACKAGE DEAL’ TYPE OF CONTRACT

© HSKS
DELAY AND
EXTENSION OF TIME

© HSKS
7.0 DELAY AND EXTENSION OF TIME

• OPTIONS AVAILABLE TO EMPLOYER

• EXTENSION OF TIME ISSUES

• ACCELERATION OF WORKS

• DRAFTING OF DELAY AND DISRUPTION CLAIMS

• MISCELLANEOUS ISSUES

• RELEVANT CASES

* PEAK CONSTRUCTION (LIVERPOOL) LTD. V MCKINNEY FOUNDATION LTD. [1970] 1 BLR 114

* MILLER V L.C.C. [1934] 50 T.L.R. 479, 482

* MERTON LONDON BOROUGH V STANLEY HUGH LEACH [1985] 32 BLR 55

* WESTMINSTER CITY COUNCIL V JARVIS & SONS LTD. [1970] 7 BLR 64

• SYARIKAT TAN KIM BENG DAN RAKAN-RAKAN V PULAI JAYA SDN. BHD. [1992] 1 MLJ 42

© HSKS
CONSEQUENCES OF DELAY: AN OVERVIEW

BY EMPLOYER
(ACTS OF PREVENTION) BY CONTRACTOR

GRANT OF INSTRUCT CONTRACTOR


EXTENSION OF TIME TO ACCELERATE WORKS

• Only if contract expressly permits • Only if contract expressly permits


• Contractor may be entitled to: • To meet original contract deadline
1. Extended Preliminaries • Contractor to be compensated for
reasonable expenses incurred
2. Direct Loss and/or Expense

DUE TO CONTRACTOR’
CONTRACTOR’S DUE TO CONTRACTOR’
CONTRACTOR’S
DUE TO
OWN ACTS AND/OR OR SUB-
SUB-CONTRACTORS/
NEUTRAL EVENTS
OMISSIONS SUPPLIERS

• Contractor entitled to E.O.T. but • Contractor culpable • Contractor vicariously liable to


not to extended preliminaries or Employer
other claims • May be liable for:
• May seek indemnity from the
• If asked to accelerate works, 1. Liquidated Damages, or culpable party e.g. Sub-
entitled to reasonable expenses 2. Unliquidated Damages contractor, Supplier, etc.
incurred therefrom caused to Employer

FIG. 7-1 : CONSEQUENCES OF DELAY – AN OVERVIEW

© HSKS
‘FORCE MAJEURE’

EXCEPTIONALLY INCLEMENT WEATHER

CIVIL COMMOTION, STRIKES, LOCK-OUT, ETC.

LOSS OR DAMAGE TO THE WORKS OCCASIONED BY SPECIFIED PERILS

CONTRACTOR’S INABILITY TO SECURE LABOUR, GOODS, MATERIALS, ETC.

CARRYING OUT OF WORK BY STATUTORY UNDERTAKERS

EXERCISE BY GOVERNMENT OF ANY POWER WHICH DIRECTLY AFFECTS THE WORKS

EXTENSION OF TIME: COMMON


‘RELEVANT EVENTS’

FAILURE OF EMPLOYER TO GIVE POSSESSION/ACCESS IN TIME

DELAY IN THE SUPPLY OF INFORMATION/INSTRUCTIONS

VARIATIONS AND EXTRA WORKS

COMPLIANCE WITH CONTRACT ADMINISTRATOR’S INSTRUCTIONS

DELAY ON PART OF NOMINATED SUB-CONTRACTORS/SUPPLIERS

EXECUTION OF WORK NOT FORMING PART OF THE CONTRACT

LATE SUPPLY OF MATERIALS BY THE EMPLOYER


OTHER SPECIAL CIRCUMSTANCES

FIG. 7-2 : EXTENSION OF TIME – COMMON ‘RELEVANT EVENTS’


© HSKS
DEFERMENT/POSTPONEMENT
IN GIVING SITE POSSESSION
OTHER ACTS OF PREVENTION
EXPRESSLY PERMITTED BY LATE SUPPLY OF
THE CONDITIONS OF INFORMATION, DRAWINGS,
CONTRACT INSTRUCTIONS, ETC.

‘ACTS OF PREVENTION’:
TYPICAL EXAMPLES

LATE SUPPLY OF MATERIALS COMPLIANCE WITH


BY THE EMPLOYER CONTRACT
ADMINISTRATOR’S
INSTRUCTIONS, DIRECTIONS,
EXECUTION OF WORK NOT ETC.
FORMING PART OF THE
CONTRACT

FIG. 7-3 : ‘ACTS OF PREVENTION’ – TYPICAL EXAMPLES

© HSKS
‘FORCE MAJEURE’
DELAYS BY NOMINATED SUB-
CONTRACTORS/SUPPLIERS
FOR THE SAID ‘NEUTRAL
EXCEPTIONALLY INCLEMENT/
EVENTS’
ADVERSE WEATHER

‘NEUTRAL EVENTS’:
TYPICAL EXAMPLES

CONTRACTOR’S IN ABILITY CIVIL COMMOTION, STRIKES,


TO SECURE LABOUR, GOOD, LOCK OUTS INDUSTRIAL
MATERIALS AND/OR OTHER ACTION, EMBARGOES, ETC.
RESOURCES
LOSS/DAMAGE TO THE WORKS
OCCASIONED BY SPECIFIED
PERILS
OR CONTINGENCIES

FIG. 7-4 : ‘NEUTRAL EVENTS’ – TYPICAL EXAMPLES

© HSKS
CAUSE OF THE DELAY
APPROPRIATE
CONTRACT
ALL OTHER SUPPORTING REFERENCES TO SUCH
RECORDS, DETAILS, ETC. EVENT OF DELAY

DETAILS OF EFFECT OF
SCHEDULING DELAY ON WORK
DOCUMENTATION APPLICATION FOR PROGRAMME
EXTENSION OF TIME:
TYPICAL CONTENTS

ESTIMATE OF THE ESTIMATED LENGTH


EXTENSION OF TIME OF THE DELAY
REQUIRED
STEPS TAKEN/PROPOSED
TO MINIMIZE/AVOID DELAY

FIG. 7-5 : APPLICATION FOR EXTENSION OF TIME – TYPICAL CONTENTS

© HSKS
OFFICIAL WORK RECORDS

OFFICIAL PROGRESS REPORTS

SITE DIARIES

LETTERS, INSTRUCTIONS, ETC.

MEMORANDA

FACSIMILE TRANSMISSIONS, ETC.

DRAWINGS, ETC.

EXTENSION OF TIME
APPLICATION: TYPICAL
SOURCES OF INFORMATION

OFFICIAL MINUTES OF MEETING

WORK PROGRAMMES, ETC.

RECORDS/REPORTS FROM AUTHORITIES/INDEPENDENT BODIES, ETC.

SHIPPING/AIRFREIGHT RECORDS, ETC.

PROCUREMENT RECORDS, INVOICES, ETC.


DELIVERY ORDERS

OTHER MISCELLANEOUS RECORDS, DOCUMENTS, ETC.

FIG. 7-6 : EXTENSION OF TIME APPLICATION – TYPICAL SOURCES OF INFORMATION


© HSKS
START

Is progress No
delayed or is likely to be
delayed?

Yes
Does the
delaying event constitute No
one of the ‘relevant events’ /grounds
under the provisions of the
contract?

Yes

Initiate notification
of the delay procedure

Is the No
notice given in writing?

Yes

Is the notice No Is the Yes


given within the period expressly notice a condition
stipulated? precedent?

Yes No
Has an
Proceed with the Yes extension been No
application of the extension granted by the contract
of time process administrator?

A B

FIG. 7-7: FLOWCHART ON THE GENERAL PROCEDURE FOR CLAIMING EXTENSION OF TIME (PART I)
© HSKS
A B

Is the No
application given in
writing?

Yes
Is the
application made within No Is the Yes
the period expressly application a condition
stipulated? precedent?

Yes No
Has an
Contract Administrator to Yes extension been No
check application made granted by the contract
administrator?

Is the
Is the application No requirement as to Yes
complete/sufficient and sufficiency, etc. a condition
accurate? precedent?

Yes No
Establish whether contractor Has the
has done all that is reasonably No contract administrator Yes
required of him requested for information,
details, etc.?

Has the contractor Prima facie no


used his ‘best endeavours’ to No
extension of time
minimize the delay? can be granted

Yes
Contract Administrator to Return to contractor
proceed with further assessment for resubmission
for the possible grant of or reject application
extension of time as appropriate

STOP

FIG. 7-8: FLOWCHART ON THE GENERAL PROCEDURE FOR CLAIMING EXTENSION OF TIME (PART II)
© HSKS
PROCEDURES FOR CLAIMING EXTENSION OF TIME: AN OVERVIEW (PART I)

EXPRESS CONTRACT NATURE OF TIMING OF FORM OF CONTENTS OF


PROVISIONS APPLICATION NOTIFICATION THE NOTICE THE NOTICE

• Included in most standard • Various formulae used e.g.:


forms of contract • Usually stipulated in the
1. Use of specific phrases conditions of contract.
2. Stipulation of express time • Important to comply with the
periods express requirements
• Legal effect of provisions on time: • As a minimum must inform
REQUIREMENT
REQUIREMENT CATEGORIZATION
CATEGORIZATION VARIATIONS
VARIATIONS 1. Whether notification/application
the contract administrator of
the occurrence of the delay
is a condition precedent to which is likely to affect the
• Expressly stipulated • 2 broad steps: • Either a: entitlement progress or has delayed
in conditions of progress
contract of contract; 1. Notification of 1. Single exercise, 2. If affirmative, the effect of the
or the delay; and or breach of the condition
precedent • Otherwise must include:
• Implied by law 2. Making the 2. Two separate 1. Occurrence of the delay
application processes 3. Application to acts of
prevention/neutral events 2. Cause of the delay
• Depends upon
express/ implied • Review of applicable case-law 3. Relevant events causing
requirements the delay; and
4. Contractor’s intention to
make a claim

TYPES
TYPES OF
OF WRITTEN
WRITTEN NOTICES
NOTICES
EXPRESS
EXPRESS REQUIREMENTS
REQUIREMENTS GENERAL RULE EVIDENTIAL VALUE
EVIDENTIAL
/NOTICES
/NOTICES IN
IN WRITING
WRITING

• Included in most standard forms • Correspondence • Where the form is expressly • A written notice/notice in writing is
stipulated, it must be complied with of immense evidential value
• Usually stipulated as: • Facsimile transmissions
• Where not expressly stipulated, may • Therefore, even if not expressly
1. ‘Written notice’ or • Entries in official records be implied required, must try to give written
2. ‘Notice in writing’ • Entries in site diaries notice
• Official Progress reports

FIG. 7-9 : PROCEDURES FOR CLAIMING EXTENSION OF TIME – AN OVERVIEW (PART I)


© HSKS
PROCEDURES FOR CLAIMING EXTENSION OF TIME:
AN OVERVIEW (PART II)

TIMING OF FORM OF CONTENTS OF


THE APPLICATION THE APPLICATION THE APPLICATION

• Similar to ‘Form of the Notice’ • Dictated by express stipulations in


contract
• Preferably to be in writing
• Otherwise by necessary implication.
• Compliance to any express
requirements • Typical list includes:
1. Cause of delay

EXPRESS 2. Appropriate contract


GENERAL RULE reference
REQUIREMENT
3. Details of effect of delay on
programme/progress
• Included in most standard • Where specific time periods have
forms been specified these should be 4. Estimated length of delay
adhered to
• Formulae include: 5. Steps taken to
• If not practicable, requirement for mitigate/prevent delay
1. Specific time express consent for deferment
periods 6. Scheduling documentation
• Otherwise within a reasonable
2. Within a reasonable period of notification/delay 7. Miscellaneous details,
period records, documents, etc.

FIG. 7-10 : PROCEDURES FOR CLAIMING EXTENSION OF TIME – AN OVERVIEW (PART II)
© HSKS
PROCEDURES FOR CLAIMING EXTENSION OF TIME:
AN OVERVIEW (PART III)

ADEQUACY OF INFORMATION SUPPLIED NATURE OF INFORMATION REQUIRED

DETERMINING
DETERMINING FACTORS
FACTORS PRINCIPAL
PRINCIPAL SOURCES
SOURCES

• Type of relevant event • Official work records


• Nature of relevant event • Official progress reports
• Particular requirements of applicable • Site diaries
express provisions • Correspondence
• Evidential value of information • Instructions
• Drawings, etc.
• Official minutes of meetings,
discussions, etc.
CONSEQUENCES
CONSEQUENCES WHERE
WHERE CONSEQUENCES
CONSEQUENCES WHERE
WHERE • Work programmes
BASIS
BASIS OF
OF FAILURE
FAILURE TO
TO RESPOND
RESPOND
PROVISION IS
IS A
A CONDITION
CONDITION PROVISION
PROVISION IS
IS NOT
NOT A
A • 3rd party reports/records
REQUIREMENT
REQUIREMENT AFTER
AFTER EXTENSION
EXTENSION
PRECEDENT
PRECEDENT CONDITION
CONDITION PRECEDENT
PRECEDENT • Procurement records, etc.
• Contractor must furnish • Breach of condition may be • Contract administrator can: • Should contractor fail to • Delivery orders
enough information to fatal to claim depending on respond by: • Shipping/airfreight records
enable contract its nature and seriousness 1. Request for further
administrator to undertake information 1. Deadline set, or • Miscellaneous
assessment satisfactorily records/documents
2. Set a new deadline for 2. Within reasonable period
• Information to be: contractor to respond of request

1. Sufficient/ complete Contract administrator may not


2. Accurate proceed further with
3. Relevant assessment

FIG. 7-11 : PROCEDURES FOR CLAIMING EXTENSION OF TIME – AN OVERVIEW (PART III)
© HSKS
ASSESSMENT OF THE APPLICATION: AN OVERVIEW (PART I)

EXPRESS THE CONTRACT


GENERAL CONTRACT ADMINISTRATOR’S DUTY
ADMINISTRATOR’ PRELIMINARY POST APPLICATION
OF CARE PROCEDURES PROCEDURES
PROVISIONS
• Included in most standard • Upon occurrence of delaying
forms of conditions of contract event, independently
undertake own assessment
especially for acts of
prevention
• Must take an active role
• Issue an interim extension to
DERELICTION
DERELICTION contractor if one due on facts
TO WHOM DUTY
DUTY TO
TO OF
OWED EMPLOYER OF DUTY:
DUTY:
CONSEQUENCES
CONSEQUENCES • Contractor can later apply for
reassessment based on
• To Employer • Positive duty vis-à-vis • May compromise additional information
‘acts of prevention’ employer’s position
• To Contractor
• Satisfaction of: • Contract administrator
• To Nominated Sub-
contractors/Suppliers 1. ‘Reasonableness’ liable to actions in:
Test and
2. ‘Fairness’ Test 1. Breach of contract
2. Tort of negligence INSUFFICIENT
• Help employer: INSUFFICIENT
PRELIMINARY
PRELIMINARY CHECKS
CHECKS INFORMATION: OPTIONS
1. Preserve right to LAD TO ESTABLISH AVAILABLE
AVAILABLE TO
TO CONTRACT
CONTRACT
2. Stave off claims from MATTERS
MATTERS SUCH AS
SUCH AS ADMINISTRATOR
ADMINISTRATOR
contractor

• Verification of occurrence • Request contractor to


of delay submit more details, etc. or
• Sufficiency, accuracy, • If delaying event of a
relevancy, etc. continuing nature:
• Compliance with pre- 1. Proceed with interim
WHO UNDERTAKES
WHO NATURE
NATURE OF
OF ROLE
ROLE ADDITIONAL
ADDITIONAL DUTY
DUTY conditions, procedural assessment
requirements, etc. 2. Grant an interim
extension
• Assessment of evidential
• Delegated by the employer • As an independent adjudicator • Per John Baker Construction v value
to authorized person • Decision making function London Protman Hotel Ltd.
• Assessment whether delay
• Usually it is the contract • Must act fairly, reasonably and • Must adhere to governing in principle entitles
administrator impartially express contractual contractor to extension
procedures in addition

FIG. 7-12: ASSESSMENT OF THE APPLICATION – AN OVERVIEW (PART I)

© HSKS
ASSESSMENT OF THE APPLICATION: AN OVERVIEW (PART II)

THE ASSESSMENT TIMING FOR MISCELLANEOUS


BASIS OF ASSESSMENT
PROCESS GRANTING EXTENSION ISSUES

• Basic principles • Factors to be taken into • Multiple extensions


consideration:
• Overriding requirements: • Review of prior decisions/ certificates
Satisfaction of: 1. Previous extensions granted
2. Effect of omissions • Concurrent delay: effects
1. ‘Reasonableness’ Test 3. Effect of concurrent delays
2. ‘Fairness’ Test • Extensions during culpable delay
3. Procedural requirements • Sources and types of information • Extension of time and omissions
used
• Important exceptions • Acceleration in lieu of extension
• Concluding decision:
1. Contractor not to be culpable • Extension of time and claims
2. Contractor to mitigate/prevent 1. Rejection of claim; or
delay 2. Grant of extension of time
• Definition of ‘best endeavours’

PROSPECTIVE/
PROSPECTIVE/
PRINCIPAL ISSUES
PRINCIPAL FACTORS
FACTORS DICTATING
DICTATING TIME
TIME PERIOD
PERIOD RETROSPECTIVE GRANTING
GRANTING
OF
OF EXTENSION
EXTENSION

• Factors dictating the timing • The need to preserve the LAD • Various formulae: • Where expressly permitted
of the grant provisions for the benefit of
the employer 1. Use of specific time • Where implied
• Express stipulations as to period stipulations
time period for granting • Courts approach:
• To allow contractor 2. Within reasonable time
• Prospective/Retrospective opportunity to reprogramme 1. Previous strict interpretation
granting of extension his works • Effect of failure to comply 2. Current liberal approach
• Situation of continuing delay • Circumstances where
retrospective granting permitted

FIG. 7-13: ASSESSMENT OF THE APPLICATION – AN OVERVIEW (PART II)

© HSKS
CERTIFICATE NOT GIVEN
ON TIME

OTHER MATERIAL CERTIFICATE NOT IN


BREACHES CORRECT FORM

CONTRACTUAL CERTIFICATE GIVEN


PROCEDURES NOT BY UNAUTHORIZED
FOLLOWED CHALLENGING CERTIFICATE PERSON
OF EXTENSION OF TIME:
COMMON GROUNDS

CERTIFICATE NOT NO NAMED


GIVEN FAIRLY CERTIFIER

DECISIONS IMPROPERLY
DELEGATED

FIG. 7-14: CHALLENGING CERTIFICATE OF EXTENSION OF TIME – COMMON GROUNDS


(PER EGGLESTON)

© HSKS
DELAY AND EXTENSION OF TIME FOR NOMINATED SUB-CONTRACTORS:
AN OVERVIEW

EXPRESS GENERAL GENERAL


GENERAL CONTRACTUAL CONTRACTUAL PROCEDURAL
REQUIREMENTS PROVISIONS POSITION REQUIREMENTS
• The principles and general requirements • Extension of time under contract can • Main steps involved are:
similar to that of Main Contract only be validly granted if:
1. Occurrence of delaying event
• Principal difference only in some 1. Delaying event is one of the
procedural requirements ‘relevant events’/grounds under 2. Notification of the delay
the conditions of sub-contract 3. Review by the contractor
• Applicable only to:
2. The express formalities or 4. Contractor forwards application
1. Nominated Sub-Contractors and procedures are strictly complied
2. Nominated Suppliers to contract administrator
with
• Does not encompass: 5. Contract administrator assesses
• The general contractual position application
1. Domestic Sub-Contractors and similar to Main Contract
2. Domestic Suppliers 6. Contract administrator
communicates decision to
contractor
7. Contractor informs sub-
contractor
PAM PUTRAJAYA
PUTRAJAYA
JKR 203N FORM PAM 1998
1998 CONDITIONS OF 8. Receipt and acknowledgement
JKR SUB---CONTRACT
SUB CONTRACT IEM.CES.1/90 FORM
IEM.CES.1/90 OF
(REV. 10/83) FORM NOMINATED
NOMINATED SUB-
SUB-- • The rules in the preparation and
FORM CONTRACT
CONTRACT issuance of the certificate of
extension of time similar to that of
• Clause 26: Delay and • Clause 8.0: Extension of Time • Clause 26: Delay and • Clause 24: Delay and Main Contract
Extension of Time Extension of Time Extension of Time
8.1:Notifying of events causing
(a): Notice of delay delay (a): Notice of delays
(b): Extension of time 8.2:Relevant events causing (b): Extension of time
delay for which extension of
(c): Dispute on failure of S.O. to time may be given (c): Dispute on failure of
grant extension of time Engineer to grant extension
8.3:A Fair and Reasonable of time
extension of time
8.4:Failure of architect to give
written consent for extension
of time

FIG. 7-15: DELAY AND EXTENSION OF TIME FOR NOMINATED SUB-CONTRACTORS –


AN OVERVIEW
© HSKS
NON-COMPLETION
AND DAMAGES

© HSKS
8.0 NON COMPLETION AND DAMAGES

• COMMON LAW POSITION

• CONTRACTUAL FORMULAE

• RIGHTS TO IMPOSE

• CHALLENGES

• MALAYSIAN POSITION

• RELEVANT CASES

* DUNLOP PNEUMATIC TYRE CO. LTD. V NEW GARAGE & MOTOR COMPANY LTD. [1915]
AC 79

* TEMLOC LTD. V ERRIL PROPERTIES LTD.

* GILBERT-ASH (NORTHERN) LTD. V MODERN ENGINEERING (BRISTOL) LTD. [1974] AC


689

* SIM CHIO HUAT V WENG TED FUI [1983] 1 MLJ 151

* LION ENGINEERING SDN. BHD. V PAUCHUAN DEVELOPMENT SDN. BHD. [1997] 4 AMR
3315

© HSKS
* MANIAM V STATE OF PERAK [1957] MLJ 75

* WEARNE BROTHERS (M) LTD. V JACKSON [1966] 2 MLJ 155

* SELVA KUMAR A/L MURUGIAH V THIAGARAJAH A/L RETNASAMY [1995] 1 MLJ 817

* REALVEST PROPERTIES SDN. BHD. V THE COOPERATIVE CENTRAL BANK LTD. (Under
Receivership) [1996] 2 AMR 2292, FC.

* SAKINAS SDN. BHD. V SIEW YIK HAU & ANOR [2002] 5 MLJ 497, HC.

* ARAB MALAYSIAN CORP. BUILDERS SDN. BHD. & ANOR V ASM DEVELOPMENT SDN. BHD.
[1998] 6 MLJ 136, HC.

© HSKS
RECOVERY/PAYMENT
TRIGGERED BY OCCURRENCE SUM OF MONEY AGRRED
OF SPECIFIED DEFAULT/BREACH BY THE PARTIES

LIQUIDATED DAMAGES:
PRINCIPAL CHARACTERISTICS

SUM STIPULATED IN THE GENUINE PRE-ESTIMATE OF THE


CONTRACT LOSS

FIG. 8-1 : LIQUIDATED DAMAGES – PRINCIPAL CHARACTERISTICS

© HSKS
LIQUIDATED DAMAGES: AN OVERVIEW

LIQUIDATED
BASIC DAMAGES AND
DEFINITION ADVANTAGES DISADVANTAGES
CHARACTERISTICS PENALTIES
DISTINGUISHED

• Prof. Vincent Powell- • Four basic characteristics: • Common view • Common view
Smith’s definition
1. Sum of money • Reiteration in Philips • Disadvantages to:
• Per Eggleston agreed/fixed in Hong Kong Ltd. v AG
of Hong Kong. 1. Employer
advance by parties
• Per Robinson and Lavers
Advantages to: 2. Contractor
2. Sum is a genuine •
pre-estimate of 3. Sub-contractor
1. Employer
likely loss
2. Contractor
3. Sum is stipulated in
the contract 3. Sub-contractor
4. Recovery of sum is
triggered by
contractor’s breach
e.g. non-completion

DISTINGUISHING
EXAMPLES OF LEGAL EFFECTS
GENERAL PENALTY: DEFINITION BETWEEN THE
PENALTY CLAUSES OF PENALTIES
TWO TERMS

• Use of terms • Per Prof. Vincent Powell- • Mere labeling is inclusive • Elicited from the • Penalty: Invalid and
interchangeably Smith relevant case-law unenforceable
• Depends on construction
• Distinct difference • Per Lord Dunedin in afforded to term by the • Legal effect per Watts,
Dunlop Pneumatic Tyre courts Watts & Co. Ltd. v Mitsui
• Position in Malaysia post Co. Ltd. v New Garage & & Co. Ltd.
Selvakumar v Thiagarajah Motor Co. Ltd. • Lord Dunedin’s proposed
tests. • See Keating’s view

FIG. 8-2 : LIQUIDATED DAMAGES – AN OVERVIEW


© HSKS
INCLUSION OF EXPRESS PROVISION IN
CONTRACT PERMITTING DEDUCTION
OF THE LIQUIDATED DAMAGES
EMPLOYER HAS NOT
THE EXPRESS
WAIVED HIS RIGHT TO
LIQUIDATED DAMAGES
DEDUCT LIQUIDATED
CLAUSE IS VALID AND
DAMAGES
ENFORCEABLE

IMPOSITION OF
LIQUIDATED DAMAGES:
TYPICAL PRE-CONDITIONS

SPECIFIED DETAILS ON LIQUIDATED


CONTRACTUAL DAMAGES CLEARLY AND
PROCEDURES HAVE PROPERLY FILLED IN
BEEN STRICTLY
COMPLIED WITH DEFINITE DATE FIXED
CONTRACTUALLY FROM WHICH
DAMAGES CAN RUN

FIG. 8-3 : IMPOSITION OF LIQUIDATED DAMAGES – TYPICAL PRE-CONDITIONS

© HSKS
CONTRACTOR SHALL FAIL THE CONTRACT
TO COMPLETE ON TIME ADMINISTRATOR SHALL
DETERMINE AND ISSUE
ANY EXTENSIONS OF
MISCELLANEOUS TIME DUE TO
PRE-CONDITIONS CONTRACT

DEDUCTION OF
LIQUIDATED DAMAGES:
COMMON CONDITIONS
PRECEDENTS USED

THE EMPLOYER SHALL THE CONTRACT


GIVE WRITTEN NOTICE ADMINISTRATOR SHALL
TO THE CONTRACTOR CERTIFY THAT NO
OF HIS INTENTION TO FURTHER EXTENSIONS
DEDUCT LAD THE CONTRACT ADMINISTRATOR OF TIME ARE DUE TO
SHALL ISSUE A CERTIFICATE OF CONTRACTOR
NON-COMPLETION

FIG. 8-4 : DEDUCTION OF LIQUIDATED DAMAGES – COMMON CONDITIONS PRECEDENTS


USED
© HSKS
PROCEDURAL REQUIREMENTS FOR RECOVERY OF LIQUIDATED DAMAGES:
AN OVERVIEW

GENERAL RULE FOR


DEFINITION GENERAL PROCEDURE
IMPOSITION OF LIQUIDATED DAMAGES

• Recovery of LAD must be in accordance with the • Need to satisfy general rule
contract
• Six principal pre-conditions:
• Procedural requirements/conditions precedent
must be strictly followed 1. Existence of express contractual provision on
LAD
• Effect of the application of the ‘contra proferantum’
rule 2. LAD Clause must be valid
3. LAD details must be clearly filled in
4. Contractual provisions must be strictly complied
with
5. Definite date from which LAD can run
6. Non-waiver by employer of his rights to the LAD

DETERMINE IF DETERMINE
ESTABLISH EMPLOYER
ESTABLISH EMPLOYER HAS IF RELEVANT POST LAD
BASIC STEPS EXISTENCE AND RECOVERS THE
DEFAULT OF WAIVED HIS CERTIFICATES/ DEDUCTION
VALIDITY OF LIQUIDATED
CONTRACTOR RIGHTS TO LAD NOTICES HAVE PROCEDURES
LAD CLAUSE DAMAGES
BEEN ISSUED

• Five basic steps • Triggering event: • Crucial to • 2 forms of waiver: • Certificate of Non- • Conditions precedent • Effect of further
failure of enforceability Completion (CNC) E.O.T.
• See Figures 6-11 contractor to of provision 1. Express • Decision as to recovery
to 6-13 on the complete on time and recovery of 2. Implied • Notice of Intention to • See Fig. 6-14 & 6-
flowcharts deduct LAD • Timing 15 for flowchart
LAD • Was there
consideration in
return?

FIG. 8-5 : PROCEDURAL REQUIREMENTS FOR RECOVERY OF LIQUIDATED DAMAGES – AN


OVERVIEW
© HSKS
NON-COMPLETION AND DAMAGES IN NOMINATED
SUB-CONTRACTS: AN OVERVIEW

GENERAL POSITION EXPRESS CONTRACTUAL


NSC’S LIABILITY FOR DAMAGES
PROVISIONS

• Legal principles similar to Main Contractor • Clause 7.0: PAM ‘98 Sub-Contract Form
• Liability for 2 types of damages: • Clause 27: JKR 203N (Rev. 10/83)
1. Liquidated damages, or • Clause 27: IEM.CES 1/90 Form
2. Unliquidated/general damages
• Clause 25: ‘Putrajaya’ Conditions of Nominated Sub-Contract

EFFECT OF DAMAGES FOR EXPRESS GENERAL


NSC’S DEFAULT BREACH OF CONTRACT CONTRACTUAL FORMULA OBSERVATIONS

• Effect of default in completing • Governing Provision: S 74 • Called the ‘Financial Contractual • Necessity for parties to agree
works in time: breach of contract Contracts Act 1950 (Rev. 1974) - Remedy’ upon and arrive at a genuine pre-
‘Compensation for loss or damage estimate
• Consequences of the said breach • Usually an LAD clause
caused by breach of contract’
- Employer entitled to damages • Need to clearly stipulate
• Express stipulations as to:
i.e., either: • Three main heads of damage per conditions precedent to recovery
.
Eggleston: 1. Rate
1. LAD as stipulated in the sub- • Prudent to cap maximum limit
2. Scope of coverage
contract, or 1. Main Contractor’s liability to
3. Maximum limit • If LAD clause ‘stepped down’ into
pay LAD to employer of NSC’s
2. General damages 4. Pre-conditions, etc. sub-contract, sub-contractor
default
enforceable through bound irrespective of value of the
• Issues pertaining to the
arbitration/court action 2. Main Contractor’s own loss sub-contract
‘stepping down’ of the Main
consequent to NSC’s default
Contractor’s LAD clauses
3. Third party claims due to NSC’s
default

FIG. 8-6: NON-COMPLETION AND DAMAGES IN NOMINATED SUB-CONTRACTS – AN OVERVIEW

© HSKS
CONTRACTUAL PROVISION IS A PENALTY CLAUSE

CONTRACTUAL PROVISION IS UNCERTAIN/INCONSISTENT

NO CONTRACTUAL PROVISION TO EXTEND TIME FOR ACT OF PROVISION IN QUESTION

NO DATE STIPULATED FOR THE COMMENCEMENT OF THE CONTRACT

CONTRACT IS AT LARGE

CONDITIONS PRECEDENT NOT OBSERVED

LIQUIDATED DAMAGES:
TYPICAL GROUNDS FOR
CHALLENGING

EMPLOYER HAS WAIVED LIQUIDATED DAMAGES

CERTIFICATES OF EXTENSION OF TIME


AND/OR PRACTICAL COMPLETION NOT VALID

EXTENSIONS OF TIME GRANTED INSUFFICIENT

PRACTICAL COMPLETION ACHIEVED EARLIER THAN CERTIFIED

MISCELLANEOUS CHALLENGES/DEFENCES

FIG. 8-7: LIQUIDATED DAMAGES – TYPICAL GROUNDS FOR CHALLENGING


© HSKS
LAD: MALAYSIAN LEGAL POSITION – AN OVERVIEW

EFFECT OF S75 CONTRACTS EFFECT OF SELVAKUMAR V CIRCUMVENTING SELVAKUMAR


ACT 1950 (REV. 1974) THIAGARAJAH [1995] V THIAGARAJAH

1. No difference between penalty and liquidated 1. Employer cannot recover simpliciter sum fixed
damages clauses. in contract, whether as a penalty or liquidated
damages.
2. All liquidated damages clauses to be treated
as penalty clauses under English law. 2. Must prove actual damages/reasonable
compensation per Hadley v Baxendale.

3. Figure stipulated in Contract is the ceiling


amount recoverable.

UNDER DOCTRINE MUTUAL CLAUSE 22.2:


OF FREEDOM TO AGREEMENT PAM CONTRACT 2006
CONTRACT

1. Parties of equal bargaining strength. 1. By parties on circumventing decision 1. Contractor confirms that by
in Selvakumar v Thiagarajah. entering into the Contract
2. Free to agree on any terms between
themselves. 2. Can draft appropriate clause 2. He agrees to pay such sums

3. Philips HK Ltd. v AG of Hong Kong. 3. Which become due

4. Without Employer having to


prove his actual loss/damage

FIG. 8-8 : LAD – MALAYSIAN LEGAL POSITION – AN OVERVIEW


© HSKS
START

Is the No
contractor liable to pay
LAD?

Yes

Have all Prima facie, employer


the conditions precedents No
cannot recover liquidated
been fulfilled? damages (LAD)

Yes

Employer can proceed to


recover simpliciter the sum
fixed in the contract as LAD

Does the
contractor challenge the No
employer’s deduction of the
LAD?

Yes

Is there an Prima facie, employer


express clause circumventing Yes
can deduct the stipulated
rule in Selvakumar LAD amount
Thiagarajah?

No

Matter to be resolved
through arbitration/litigation

A B

FIG. 8-9: FLOWCHART ON THE RECOVERY OF LIQUIDATED DAMAGES - THE MALAYSIAN


POSITION POST SELVAKUMAR V THIAGARAJAH (PART I)
© HSKS
A B

Employer must prove the actual damages or


reasonable compensation per rule in Hadley v
Baxendale / S74 Contracts Act

Is
employer able to No Employer may not be
prove damages as able to recover any damages at all
required?

Yes

Are the Prima facie, employer


damages more than the sum stipulated in the Yes
can deduct the stipulated
contract LAD amount
as LAD?

No

Employer can recover only his actual damages or


reasonable compensation as decided by the arbitral
forum or the court

STOP

FIG. 8-10: FLOWCHART ON THE RECOVERY OF LIQUIDATED DAMAGES - THE MALAYSIAN


POSITION POST SELVAKUMAR V THIAGARAJAH (PART II)
© HSKS
COMPLETION AND
HANDING-OVER

© HSKS
9.0 COMPLETION AND HANDING-OVER

• PROBLEMS WITH DEFINITIONS AND TERMINOLOGY

• CONDITIONS PRECEDENT

• NON-
NON-ISSUE BY CONTRACT ADMINISTRATOR

• CHALLENGES TO CPC

• PROBLEMS ARISING FROM CPC ISSUES

• SECTIONAL COMPLETION, PARTIAL POSSESSION AND CONDITIONAL CPC

• RELEVANT CASES

* WESTMINSTER CITY COUNCIL V JARVIS & SONS LTD. [1970] 7 BLR 64

* H.W. NEVILL (SUNBLEST) LTD. V WILLIAM PRESS & SONS LTD. [1981] 20 BLR 78

* P & M KAYE LTD. V HOSIER DICKINSON LTD. [1972] 1 WLR 64

* EMSON EASTERN (IN RECEIVERSHIP) V EME DEVELOPMENTS LTD. [1991] 55 BLR 114

* BRUNO ZORNOW (BUILDERS LTD.) V BEECHCROFT DEVELOPMENTS LTD. [1990] 51 BLR 16

© HSKS
CONTRACT ADMINISTRATOR
HAS DISCRETION TO ISSUE
C.P.C. WHERE MINOR WORKS C.P.C. CAN BE ISSUED
ARE LEFT TO BE DONE ON A ‘DE NOTWITHSTANDING PRESENCE
MINIMIS’ BASIS OF LATENT DEFECTS

GUIDELINES TO DETERMINE PRACTICAL


COMPLETION PER KEATING

PRACTICAL COMPLETION MEANS C.P.C. CANNOT BE ISSUED IF


COMPLETION OF ALL WORK THAT THERE ARE PRESENT PATENT
HAS TO BE DONE DEFECTS

FIG. 9-1 : GUIDELINES TO DETERMINE PRACTICAL COMPLETION PER KEATING

© HSKS
FUNCTIONAL TEST

MISCELLANEOUS TESTS
COMPLETENESS TEST

ESTABLISHING PRACTICAL
COMPLETION:
PRINICPAL TESTS

AUTHORITIES TEST SAFETY TEST

INCONVENIENCE TEST

FIG. 9-2 : ESTABLISHING PRACTICAL COMPLETION – PRINICPAL TESTS

© HSKS
MARKS END OF CONSTRUCTION PERIOD

CONTRACTOR’S RIGHT TO POSSESSION OF SITE CEASES

CONTRACTOR’S LIABILITY FOR CARE, SECURITY, ETC., ENDS

CERTIFICATION OF INTERIM PAYMENT ENDS

EMPLOYER TO RELEASE ONE MOIETY OF RETENTION SUM

DEFECT LIABILITY PERIOD COMMENCES

ISSUE OF THE CERTIFICATE


OF PRACTICAL COMPLETION:
PRINCIPAL EFFECTS

FREE SERVICE AND MAINTENANCE PERIOD STARTS


TRIGGERS COMMENCEMENT OF PERIOD OF FINAL MEASUREMENT
AND VALUATION OF THE WORKS

CONTRACTOR’S LIABILITY TO INSURE WORKS ENDS

CONTRACTOR’S LIABILITY FOR FURTHER LAD ENDS

CONTRACT ADMINISTRATOR’S POWER TO ORDER VARIATIONS CEASES

ENDS RESTRICTION ON OPENING OF ARBITRATION

FIG. 9-3 : ISSUE OF THE CERTIFICATE OF PRACTICAL COMPLETION – PRINCIPAL EFFECTS


© HSKS
CERTIFICATE OF PRACTICAL
OBLIGATION TO INSURE COMPLETION FOR EACH SECTION
FOR EACH SECTION
ENDS WITH CPC SEPARATE EXTENSION
(DEPENDING ON OF TIME CERTIFICATION
CONTRACT PROVISION) FOR EACH SECTION

SECTIONAL COMPLETION:
PRINICPAL ISSUES/EFFECTS

RELEASE OF ONE SEPARATE LIQUIDATED


MOIETY OF RETENTION AND ASCERTAINED
SUM FOR EACH SECTION DAMAGES FOR EACH
SECTION
SEPARATE DEFECT LIABILITY
PERIOD FOR EACH SECTION

FIG. 9-4 : SECTIONAL COMPLETION – PRINCIPAL ISSUES/EFFECTS

© HSKS
ISSUE OF CERTIFICATE OF
PARTIAL OCCUPATION OF COMMENCEMENT OF
RELEVANT PART WITHIN DEFECT LIABILITY
RELEASE OF STIPULATED PERIOD PERIOD FOR RELEVANT
PERFORMANCE BOND PART ON DATE OF
AND FINAL PAYMENT POSSESSION/
UNAFFECTED OCCUPATION

PARTIAL POSSESION/
OCCUPATION:
PRINICPAL ISSUES/EFFECTS

CESSATION/REDUCTION PROPORTIONING DOWN


OF INSURANCES OF LIQUIDATED AND
CORRESPONDINGLY (IF ASCERTAINED DAMAGES
EXPRESSLY PERMITTED)
RELEASE OF A PROPORTION OF
FIRST HALF OF RETENTION SUM IN
RESPECT OF RELEVANT PART
WITHIN STIPULATED PERIOD

FIG. 9-5 : PARTIAL POSSESSION/OCCUPATION – PRINCIPAL ISSUES/EFFECTS


© HSKS
COMPLETION OF WORKS UNDER THE CONTRACT

LITERAL MEANING/ PRACTICAL SECTIONAL PARTIAL


INTERPRETATION COMPLETION COMPLETION POSSESSION

• Strict View • Also termed ‘Substantial • Envisages completion in • Situation where Employer takes
Completion’ in some cases sections/ stages/phases over/resumes possession of:
• Absence of any patent
defects; and • Adopts an expedient view • Intention must be a)Whole works, or
agreed/expressed at time of b) Part of works
• Absence of any outstanding • Connotates a state of contracting. before Contract Completion Date
works however trifling readiness for use or
occupation by Employer • Contract Documents must • Pre-Conditions:
• Rarely used in practice identify/ define: a)With consent of Contractor
• Formalized by issue of b) Consent not to be
• Has been abandoned in Certificate of Practical a) Each Section unreasonably withheld
favour of a more expedient Completion (CPC) or Taking b) The Completion dates
approach Over Certificate (TOC) c) The Corresponding LAD • Procedural aspects:
a)Issue of Certificate of Partial
• More common in practice • Each section has separate: Occupation (CPO) within 7
days of possession.
• Provided for expressly in a) Certificate of Practical
many Standard Forms Completion (CPC)/TOC b) Certificate to identify:
or Defect Notification
i) Relevant part possessed
Period (DNP)
ii) Its estimated value
b) Defects Liability Period c)DLP/DNP starts on date of
(DLP) possession
c) Liquidated and d) LAD rate reduced pro-
Ascertained Damages rata for unoccupied
(LAD) part/portion

FIG. 9-6 : COMPLETION OF WORKS UNDER THE CONTRACT – AN OVERVIEW


© HSKS
TEST ON COMPLETION: AN OVERVIEW

TYPES PURPOSE RESPONSIBILITY FAILURES

• To show compliance with the


Performance Specification/
Contract Requirements
• To meet applicable statutory
requirements.
PRELIMINARY • As a pre-condition to issue of
FINAL CPC
• As a pre-condition to
• Normally undertaken • Normally undertaken by certification by Independent 3rd
by Contractor on his either: Party Specialist.
own.
a) Contractor in the
• Prior to Final Tests on presence of
Completion. Contract
Administrator (or)
• Is a necessary prelude
to the Final Tests b) Independent 3rd
Party Specialists
• Is usually a pre-
condition to issue of
CPC.
CONTRACTOR CONTRACT INDEPENDANT TESTER
ADMINISTRATOR

• Contractually, responsible for: • Active participant and • Scope as expressly stipulated


certifier of Final Testing and in Contract.
a) Preliminary and Final Commissioning.
Testing and • Eg. SIRIM, DNV, Lloyds, TÜV,
Commissioning. • Default/negligence in Statutory authorities, etc.
certification does not relieve
b) Satisfactory Completion Contractor’s obligations.\ • May also be required under
statute.

FIG. 9-7 : TEST ON COMPLETION – AN OVERVIEW


© HSKS
OPERATION AND MAINTENANCE MANUALS: AN OVERVIEW

GENERAL
GENERAL TIMING
TIMING FOR
FOR TYPES/
TYPES/ NATURE
NATURE UPDATING ACCURACY
ACCURACY
POSITION SUBMISSION

• Must follow express • Must comply with express • Contractor’s


Contract stipulations as Contract stipulations. responsibility at least
to: during Limitation Period
• Normal practice is: for:
a) Type/Nature
b) Contents a) Before TOC a) O & M manuals due
c) Quantity b) After TOC CONTRACTOR
CONTRACTOR ‘‘S
S PROFESSIONAL’
PROFESSIONAL’’S
S
to product
d) Timing for c) Before Performance RESPONSBILITY RESPONSBILITY
RESPONSBILITY
Certificate
improvement. RESPONSBILITY
Submission
b)Errors/
• Most Contracts have • Usual requirements include inaccuracies
incorporated such draft copies for approval • In Contract and Tort • In Tort, on joint and
prior to finalization. • Professionals to update several basis
stipulations
on safety issues and • Primary responsibility
errors detected. for errors, omissions, • Especially so for
etc. signing-off/
endorsing ‘Qualified
Person’.

AS-
AS--BUILT/
BUILT/ OPERATION & RECORDS
RECORDS OF
OF FINAL
FINAL MISCELLANEOUS
AS-
AS--CONSTRUCTED/
CONSTRUCTED/ MAINTENANCE MANUALS/
MAINTENANCE MANUALS/
MEASUREMENT
MEASUREMENT RECORDS/ DOCUMENTS
RECORDS/
AS-
AS-INSTALLED DRAWINGS HANDBOOKS

• Permanent record of works • To enable Works to be operated and • Undertaken by Contract • Final testing and commissioning
maintained efficiently and safely. Administrator jointly with records
• Suitably detailed for future Contractor.
reference. • Contents, etc. to express contract • Servicing and Maintenance
stipulations/industry practice. • To facilitate preparation of Final records
• Contents, etc. to express Account.
contract stipulations/industry • O & M Training records, etc.
practice.

FIG. 9-8 : OPERATION AND MAINTENANCE MANUALS – AN OVERVIEW

© HSKS
IDENTIFICATION OF PATENT
ISSUE OF RELEVANT
DEFECTS
COMPLETION CERTIFICATE
& OUTSTANDING WORKS

HANDOVER OF APPROVALS/ COMPLETION


CLEARANCES FROM OF TESTING &
STATUTORY AUTHORITIES COMMISSIONING

TAKING OVER: TRAINING OF


HANDOVER OF ALL TYPICAL PRE- EMPLOYER’S OPERATION
NECESSARY SPARES & MAINTENANCE PERSONNEL
CONDITIONS

HANDOVER OF HANDOVER OF
ALL NECESSARY TOOLS ALL ‘AS-BUILT’ DOCUMENTS/
RECORDS

HANDOVER OF ALL
KEYS

FIG. 9-9: ‘TAKING OVER’ OF COMPLETED WORKS BY EMPLOYER – TYPICAL PRE-CONDITIONS

© HSKS
IDENTIFICATION OF THE TYPES AND
DETAILS OF NECESSARY INSPECTIONS

IDENTIFICATION OF THE IDENTIFICATION OF


MODE OF FORMALIZING THE SEQUENCE OF
THE TAKING OVER TAKING-OVER

TAKING OVER OF
COMPLETED WORKS:
PROCEDURAL ISSUES

SETTING UP OF THE ESTABLISHMENT OF


PROCEDURES FOR TAKING-OVER
RECORDING PROGRAMME

ESTABLISHMENT OF THE
RELEVANT DELIVERABLES

FIG. 9-10 : TAKING OVER OF COMPLETED WORKS – PROCEDURAL ISSUES

© HSKS
DEFECTS

© HSKS
10.0 DEFECTS

• PROBLEMS WITH DEFINITIONS AND TERMINOLOGY

• DEFECTS FOR WHICH CONTRACTOR RESPONSIBLE

• PROBLEMS WITH DEFECT RECTIFICATION

• CERTIFICATION – DELAY, NON-ISSUE, ETC.

• LIABILITY UNDER LIMITATION ACT

• RECENT DEVELOPMENTS

• RELEVANT CASES

* HII SOO CHIONG V BOARD OF MANAGEMENT YEE TING PRIMARY SCHOOL [1973] 2 MLJ 204

* LEO TENG CHOY V BEETILE CONSTRUCTION [1982] 2 MLJ 304

© HSKS
* DANCOM ENGINEERING PTE LTD. V TAKASAGO THERMAL ENGINEERING CO. LTD. [1989] BLD
[MAY] 606

* PIRELLI GENERAL CABLE WORKS LTD. V OSCAR FABER & PARTNERS [1983] 2 AC 1

* PEARCE & HIGH LTD. V JOHN BAXTER & MRS. A.S. BAXTER [1999] BLR 101

* BAGOT V STEVEN SCANLON & CO. [1996] 1 QB 197

* DUTTON V BOGNOR REGIS UNITED BUILDING CO. LTD. & ANOR [1972] 1 QB 373

* STEVEN PHOA CHENG LOON & 72 ORS V HIGHLAND PROPERTIES SDN. BHD. & 9 ORS [2000]
3 AMR 3567

© HSKS
STANDARD OF
WORKMANSHIP

QUALITY OF STANDARD
PATENT DEFECT LATENT DEFECT MATERIAL OF DESIGN

TYPES NATURE

DEFECTS: PRINCIPAL TYPES AND NATURE

FIG. 10-1 : DEFECTS – PRINCIPAL TYPES AND NATURE

© HSKS
DEFECTS FOR WHICH CONTRACTOR IS GENERALLY RESPONSIBLE

TRADITIONAL GENERAL MANAGEMENT FEE ‘PACKAGE DEAL’


DEAL’ TYPES
CONTRACTING CONTRACTING OF CONTRACTS

• Quality of Materials
• Standard of Workmanship

WHOLLY EMPLOYER PARTLY EMPLOYER • Standard of Design


DESIGNED CONTRACT DESIGNED CONTRACT

• Quality of Materials • Quality of Materials


• Standard of Workmanship • Standard of Workmanship
• Standard of Design (For
elements of design in
contractor’s scope of work)

WHOLLY EMPLOYER PARTLY EMPLOYER


DESIGNED CONTRACT DESIGNED CONTRACT

• Quality of Materials • Quality of Materials


• Standard of Workmanship • Standard of Workmanship
• Standard of Design (For elements of
design in contractor’s scope of work)

FIG. 10-2 : DEFECTS FOR WHICH CONTRACTOR IS GENERALLY RESPONSIBLE

© HSKS
ARISING FROM
‘FAIR WEAR AND TEAR’

HAVING NUMBER OF
CAUSES, CONTRACTOR’S ARISING FROM MISUSE/
PORTION BEING MINOR ABUSE BY USERS /
EMPLOYER

DEFECTS FOR WHICH


CONTRACTOR IS GENERALLY
NOT RESPONSIBLE

WAIVED BY EMPLOYER ARISING FROM WORK


WHICH IS NOT
CONTRACTOR’S
RESPONSIBILITY
OUT OF TIME OR STATUTE
BARRED

FIG. 10-3 : DEFECTS FOR WHICH CONTRACTOR IS GENERALLY NOT RESPONSIBLE

© HSKS
POST-COMPLETION STAGE
• Or Post-Handing Over Stage
• Or During ‘Defects Liability Period’, etc.

PRE-COMPLETION STAGE POST-CMGD STAGE


• Or Pre-Handing Over Stage • Or Post-Certification of
• Or During Currency of Completion of Making Good
Construction, Installation, Defects
etc. • Or During Limitation Period

CONTRACTOR’S LIABILITY FOR DEFECTS:


PRINCIPAL STAGES OF CONTRACT

FIG. 10-4 : CONTRACTOR’S LIABILITY FOR DEFECTS – PRINCIPAL STAGES OF CONTRACT

© HSKS
DETERMINATION OF
CONTRACTOR’S EMPLOYMENT THIRD PARTY ACTION TO MAKE
UNDER THE CONTRACT GOOD DEFECTS

EMPLOYER’S PRINCIPAL REMEDIES FOR CONTRACTOR’S


DEFAULT IN RECTIFYING REPORTED DEFECTS AT PRE-
CONTRACT COMPLETION STAGE

POSTPONEMENT/NON- EMPLOYER MAY UNDERTAKE


CERTIFICATION OF COMPLETION RECTIFICATION WORKS HIMSELF
OF WORKS

FIG. 10-5: EMPLOYER’S PRINCIPAL REMEDIES FOR CONTRACTOR’S DEFAULT IN


RECTIFYING REPORTED DEFECTS AT PRE-CONTRACT COMPLETION STAGE

© HSKS
LIMITATION ACT 1953 (REV.
MISCELLANEOUS ACTS 1981) - WEST MALAYSIA
E.G. RAILWAYS ACT
1991 (SECTION 97) CIVIL LIMITATION ORDINANCE
LAW ACT 1965 (SECTION 1959 (REPRINT 1965) -
7(5), ETC. SARAWAK

LIMITATION: RELEVANT
STATUTORY ENACTMENTS

PUBLIC AUTHORITIES LIMITATION ORDINANCE


PROTECTION ACT 1948 1952 (REPRINT 1966) -
(REV. 1978) SABAH

LIMITATION ACT (CAP 14)


REVISED EDN. 2000 -
BRUNEI

FIG. 10-6 : LIMITATION – RELEVANT STATUTORY ENACTMENTS

© HSKS
EXPIRY OF PERIOD FOR RECTIFYING DEFECTS:
OPTIONS AVAILABLE TO CONTRACT ADMINISTRATOR

ALL DEFECTS SATISFACTORILY DEFECTS REMAINING OUTSTANDING


MADE GOOD/RECTIFIED AND/OR UNRECTIFIED

• Contract administrator to:


a) Prepare and
b) Issue
the Performance Certificate forthwith. DEFECTS ARE EITHER:
DEFECTS ARE EITHER:
• See express clauses under ICTAD/SBD/02
• minor or not material
• Serious and/or
• Impracticable or inconvenient
• Material
for contractor to make good

Contract administrator to:


• Carry out diminution in value; and
• Prepare and Issue Certificate of Making Good Defects

EMPLOYER TO UNDERTAKE
TAKE 3RD
RD PARTY ACTION WORKS HIMSELF I.E.
DEPARTMENTALLY
• Deduct costs involved from: • Deduct costs involved from:
a) money due to contractor and/or a) money due to contractor and/or
b) Performance bond and/or b) Performance bond and/or
c) as a liquidated demand c) as a liquidated demand

FIG. 10-7 : EXPIRY OF PERIOD FOR RECTIFYING DEFECTS – OPTIONS AVAILABLE TO


CONTRACT ADMINISTRATOR
© HSKS
OFFICIALLY ENDS THE
DEFECT LIABILITY PERIOD DISCHARGES
PARTIES’ OUTSTANDING (DLP) CONTRACTOR’S RIGHTS
OBLIGATIONS UNDER THE UNDER CONTRACT TO
CONTRACT ARE NOT PHYSICALLY ATTEND TO
RELIEVED DEFECTS

CONTRACTOR’S LIABILITY
FOR LATENT AND PATENT MARKS THE BEGINING OF
DEFECTS CONTINUES FOR THE CONTRACTUAL PERIOD
THE STATUTORY PERIOD OF ISSUE OF CERTIFICATE FOR PREPARATION OF FINAL
LIMITATION ACCOUNT
MAKING GOOD OF
DEFECTS: PRINCIPAL
EFFECTS ON PARTIES

DISCHARGES LIABILITY OF MARKS THE


GUARANTORS, INSURERS, COMMENCEMENT OF THE
ETC. UNDER THE CONTRACTUAL PERIOD
EMPLOYER HAS TO
CONTRACT FOR CONTRACT
RELEASE SECOND MOIETY
OF RETENTION SUM THAT ADMINISTRATOR TO ISSUE
IS WITHHELD FINAL CERTIFICATE

FIG. 10-8: ISSUE OF CERTIFICATE OF MAKING GOOD OF DEFECTS – PRINCIPAL EFFECTS


ON PARTIES

© HSKS
POST-COMPLETION
AND
FINAL ACCOUNT

© HSKS
11.0 POST COMPLETION AND FINAL ACCOUNT

• LIABILITIES ARISING FROM DEFAULTS/OMISSIONS IN:

* TRAINING

* O & M MANUALS

* AS-BUILT DRAWINGS

• FINALISATION OF ACCOUNT ISSUES

• FINAL CERTIFICATE ISSUES

• POST-
POST-FINAL CERTIFICATE PROBLEMS

• RELEVANT CASES

* FAIRWEATHER LTD. V ASDEN SECURITIES LTD. [1979] 12 BLR 40

* CHEW SIN LONG CONSTRUCTION CO. LTD. V COSY HOUSING DEVELOPMENT PTE LTD.
[1988] 1 MLJ 331

* THAMESA DESIGNS SDN. BHD. & ORS V KUCHING HOTELS SDN. BHD. [1993] 3 MLJ 28

* TOKEN CONSTRUCTION CO. LTD. V CHARLTON ESTATES LTD. [1973] 1 BLR 48

* SHEN YUAN PAI V DATO’ WEE HOOD TECK & ORS [1976] 1 MLJ 16

© HSKS
SERVICING & MAINTENANCE: AN OVERVIEW

PROCEDURE
GENERAL PURPOSE FREQUENCY EXTENT EFFECT OF
FOR
POSITION FAILURE
MONITORING
• Must follow express • To ensure Contractor • Per stipulations in: • To carry out and/or
Contract stipulations meets contractual erroneous/negligent
obligations a) Contract and/or servicing.
• Most Contracts e.g. b) O & M Manuals
M&E have such • Not to nullify equipment • P.C. may not be issued
provisions in the warranties. • Implied from:
specifications. • Period may be extended
• To minimize defects and a) Statutory
downtime and prolong requirements • Use of 3rd Parties at
lifetime and efficiency. Contractor’s Cost
b) Trade usage
• Warranties may be
c) Local practice compromised.
• Possible action in contract,
tort, statute, etc.

PREVALENT
PREVALENT EXPRESS
EXPRESS IMPLIED
PRACTICE
PRACTICE REQUIREMENTS REQUIREMENTS
REQUIREMENTS

• Daily • As stipulated: • In absence of express


• Weekly
a) In Contract
stipulations implied CONTRACT
• Monthly from: CONTRACTOR’
CONTRACTOR’’S
S ADMINISTRATOR’
ADMINISTRATOR’S EMPLOYERS
EMPLOYERS
• Quarterly b) In Manufacturer’s
Warranties/ a) Trade usage DUTY
DUTY RESPONSIBILITY OBLIGATIONS
• Yearly
recommendations b) Local practice
c) In O & M Manuals c) Statute
• Proper and effective • Monitoring of • Undertaking of routine
• Generally, most contracts • General implication is record keeping of: Contractor’s work servicing and
require contractor to do that Employer will maintenance e.g. daily,
monthly/ quarterly undertake daily and a) Compliances • Signing-off the weekly, etc.
servicing. weekly servicing and b) Deviations records
maintenance. c) Unusual • Affording Contractor
observations • Reporting to proper access to work
Employer of unusual being serviced.
• Timely recording and observations
signing-off. • Attending to unusual
observations reported.

FIG. 11-1 : SERVICING AND MAINTENANCE – AN OVERVIEW


© HSKS
PLANS OF COMPLETED WORKS ‘AS-BUILT’ DRAWINGS

COMMON LABELS FOR RECORDS/


DRAWINGS OF COMPLETED WORKS

‘AS-INSTALLED’ DRAWINGS ‘AS-CONSTRUCTED’ DRAWINGS

FIG. 11-2 : COMMON LABELS FOR RECORDS/DRAWINGS OF COMPLETED WORKS

© HSKS
‘AS-BUILT’ DRAWINGS: AN OVERVIEW

GENERAL TIMING FOR ACCURACY


TYPES/ NATURE UPDATING
POSITION SUBMISSION

• Must follow express • Must comply with express • Contractor’s


Contract stipulations contract stipulations. responsibility at least
as to: during Limitation Period
• Normal practice is:
for:
a) Type/Nature CONTRACTOR’S PROFESSIONAL’S
a) Before CPC
b) Contents RESPONSBILITY RESPONSBILITY
b) After CPC a) Revisions due to
c) Quantity
c) Before CMGD product
d) Timing for
improvement. • In Contract and • In Tort, on joint
Submission • Usual requirements include
Tort and several basis
draft copies for approval b) Errors/ inaccuracies
• Most Contracts have
prior to finalization.
express provisions • Primary • Especially so for
incorporated. • Professionals to update responsibility for signing-off/
on safety issues and errors, endorsing
errors detected. omissions, etc. ‘Qualified
Person’.

AS-BUILT/ OPERATION &


RECORDS OF FINAL
AS-CONSTRUCTED/ MAINTENANCE SCHEMATICS
MEASUREMENT
AS-INSTALLED DRAWINGS /DIAGRAMMES

• Permanent record of works • To supplement O&M Manuals • Undertaken by Contract Administrator


jointly with Contractor.
• Suitably detailed for future • Contents, etc. to express
reference. contract stipulations/industry • To facilitate preparation of Final
practice. Account.
• Contents, etc. to express
contract stipulations/industry
practice.

FIG. 11-3: ‘AS-BUILT’ DRAWINGS – AN OVERVIEW

© HSKS
FINAL CERTIFICATE

MISCELLANEOUS FINAL ACCOUNT


LABELS CERTIFICATE

CERTIFICATION UPON EXPIRY


OF CONTRACT PERIOD:
COMMON LABELS

PERFORMANCE ULTIMATE CERTIFICATE


CERTIFICATE

FINAL PAYMENT
CERTIFICATE

FIG. 11-4 : CERTIFICATION UPON EXPIRY OF CONTRACT PERIOD – COMMON LABELS

© HSKS
ISSUED UPON EXPIRY OF THE
CONTRACT PERIOD

ACTUAL EFFECT DICTATED


BY THE PRECISE TERMS OF
THE APPLICABLE
ISSUED BY THE CONTRACT
CONDITIONS OF CONTRACT
ADMINISTRATOR

FINALCERTIFICATE:
PRINCIPAL
CHARACTERISTICS

RENDERS THE CONTRACT LAST OF THE VARIOUS


ADMINISTRATOR ‘FUNCTUS CERTIFICATES ISSUED
OFFICO’ DURING CONTRACT PERIOD

PRIMA FACIE, SIGNIFIES


DISCHARGE OF THE CONTRACT
BY PERFORMANCE

FIG. 11-5 : FINAL CERTIFICATE – PRINCIPAL CHARACTERISTICS

© HSKS
ISSUE OF PERFORMANCE
CERTIFICATE (P.C.)

SATISFACTION OF ALL
OTHER OBLIGATIONS/DUTIES EXPIRY OF DEFECT
UNDER CONTRACT NOTIFICATION PERIOD (DNP)

TYPICAL PRE-CONDITIONS TO
THE ISSUE OF THE
FINAL CERTIFICATE

FORMAL APPLICATION FOR CERTIFICATION OF


THE FINAL PAYMENT COMPLETION OF SERVICING
CERTIFICATE AND MAINTENANCE

PREPARATION AND
FINALIZATION OF THE FINAL
ACCOUNT

FIG. 11-6 : TYPICAL PRE-CONDITIONS TO THE ISSUE OF THE FINAL PAYMENT CERTIFICATE

© HSKS
SATISFACTION OF THE COMPLETION
CRITERIA AS SPELT OUT IN THE
CONTRACT AND WHERE IT IS
THAT ALL THE CONTRACTOR’S STIPULATED TO BE TO THE
FINANCIAL CLAIMS HAVE BEEN REASONABLE SATISFACTION OF THE
PROPERLY ACCOUNTED FOR CONTRACT ADMINISTRATOR

EFFECT OF ISSUE OF FINAL PAYMENT CERTIFICATE –


PRINCIPAL MATTERS FOR WHICH CERTIFICATE PROVIDES
‘CONCLUSIVE EVIDENCE’

THAT ALL EXTENSIONS OF TIME THAT EXCEPT FOR ANY COMPUTING


OFFICIALLY GRANTED ARE CORRECT ERRORS, ETC. ALL RELEVANT
ADJUSTMENTS (ADDITIONS/
DEDUCTIONS) HAVE BEEN MADE TO
THE CONTRACT SUM

FIG. 11-7 : EFFECT OF ISSUE OF FINAL PAYMENT CERTIFICATE – PRINCIPAL MATTERS FOR
WHICH CERTIFICATE PROVIDES ‘CONCLUSIVE EVIDENCE’
© HSKS
FRAUD/DISHONESTY/FRAUDULENT CONCEALMENT BY CONTRACTOR

UNDISCOVERED DEFECTS E.G. LATENT DEFECTS, ETC.

COMPUTATIONAL ERRORS, ACCIDENTAL INCLUSIONS/EXCLUSIONS, ETC.

CERTIFICATE NOT GIVEN IN CORRECT FORM

CERTIFICATE NOT GIVEN ON TIME

CERTIFICATE NOT GIVEN BY AUTHORIZED PERSON

FINAL CERTIFICATE:
TYPICAL CHALLENGES TO
‘CONCLUSIVENESS’/’FINALITY’

CERTIFIER ACTING ‘ULTRA VIRES’

CERTIFIER IMPROPERLY PRESSURIZED/INFLUENCED

FRAUD/COLLUSION BETWEEN CERTIFIER AND OTHER PARTY

CERTIFICATE EMBODIES WRONG DECISION ON A POINT OF LAW

THE EFFECT OF THE PRESENCE OF AN ARBITRATION CLAUSE

MISCELLANEOUS CHALLENGES/GROUNDS FOR CHALLENGING

FIG. 11-8: FINAL PAYMENT CERTIFICATE – TYPICAL CHALLENGES TO ‘CONCLUSIVENESS’/


’FINALITY’
© HSKS
THANK YOU

© HSKS

You might also like