EXE
=========================================================
Default Project..................................................600098BL00-5
Projects:
600098BL00-
5.....................................................UPGRADE WATER DISPOSAL
FACILITY - QATIF
Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar
Advanced
--------
Calculate multiple float paths...................................No
Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................1434
# Not Started....................................................1434
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................1964
# Activities with Constraint.....................................0
Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................1434
# Relationships with other projects..............................0
Data Date........................................................29-Sep-19
12:00 AM
Earliest Early Start Date........................................29-Sep-19
07:00 AM
Latest Early Finish Date.........................................19-Aug-21
05:00 PM
Exceptions:
-----------
Critical Activities..............................................69
Project: 600098BL00-5 Activity: CNTA30000 LAYING OF PIPES
Project: 600098BL00-5 Activity: CNTA30010
LAMINATION/JOINTING OF RTRP PIPES
Project: 600098BL00-5 Activity: CNTA30020 HYDROTESTING
Project: 600098BL00-5 Activity: CNTA30025 TIE IN
Project: 600098BL00-5 Activity: CNTA30030 BACKFILLING
Project: 600098BL00-5 Activity: CNTA30040 PIPING
REINSTATEMENT
Project: 600098BL00-5 Activity: CNTA30050 BERMING
Project: 600098BL00-5 Activity: CNTA30060 LEAK TEST
Project: 600098BL00-5 Activity: CNTA30080 PUNCHLIST
CLEARANCE
Project: 600098BL00-5 Activity: CNTA30081 FINAL WALKTHROUGH
BY SA
Project: 600098BL00-5 Activity: DMBA23180 SUBMIT ALL SPARE
PARTS AND DATA PACKAGES
Project: 600098BL00-5 Activity: DMBA23190 SUBMIT RED LINE AS
BUILTS DRAWINGS FOR REVIEW
Project: 600098BL00-5 Activity: DMBA23210 PROJECT RECORD
BOOKS
Project: 600098BL00-5 Activity: DMBA23220 DEMOBILIZATION /
PROJECT COMPLETION
Project: 600098BL00-5 Activity: ENGA1150 CIVIL - 60%
COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA1270 CMP - 60% COMMENTS
INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA1470 ELECTRICAL
SCHEMATIC DIAGRAM
Project: 600098BL00-5 Activity: ENGA1480 ETAP STUDY &
REPORT
Project: 600098BL00-5 Activity: ENGA1510 FDAS BATTERY
CALCULATION
Project: 600098BL00-5 Activity: ENGA1680 FIRE PROTECTION -
60% COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA1720 FOUNDATION
FIELDBUS SEGMENT CALCULATION
Project: 600098BL00-5 Activity: ENGA1740 INPUT / OUTPUT
LIST
Project: 600098BL00-5 Activity: ENGA1750 INSTRUMENT BLOCK
DIAGRAM
Project: 600098BL00-5 Activity: ENGA1910 ELECTRICAL - 60%
COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA1920 FDAS - 60%
COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA1930 INSTRUMENTATION -
60% COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA1940 DATASHEET FOR
PUMPS
Project: 600098BL00-5 Activity: ENGA1950 DATASHEET FOR
WATER OIL SEPARATOR
Project: 600098BL00-5 Activity: ENGA1980 TECHNICAL
SPECIFICATION - MECHANICAL
Project: 600098BL00-5 Activity: ENGA2040 OVERALL PIPELINE
ROUTING PLAN
Project: 600098BL00-5 Activity: ENGA2090 PIPELINE - 60%
COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA2220 TIE-IN SCHEDULE -
TIE IN DETAILS
Project: 600098BL00-5 Activity: ENGA2270 ISOMETRIC
DRAWINGS/MTO
Project: 600098BL00-5 Activity: ENGA2310 PIPING - 60%
COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA2330 PIPELINE WALL
THICKNESS CALCULATION
Project: 600098BL00-5 Activity: ENGA2340 3D MODELLING -
PIPING (90%)
Project: 600098BL00-5 Activity: ENGA2360 INPUT TO OTHER
DISCIPLINE (PID, LDT)
Project: 600098BL00-5 Activity: ENGA2380 PROCESS DESIGN
BASIS
Project: 600098BL00-5 Activity: ENGA2420 BASIS OF DESIGN
FOR OILY WATER PIPELINE
Project: 600098BL00-5 Activity: ENGA2430 BASIS OF DESIGN
FOR SALT WATER DISPOSAL NETWORK
Project: 600098BL00-5 Activity: ENGA2440 BASIS OF DESIGN
FOR WATER INJECTION NETWORK
Project: 600098BL00-5 Activity: ENGA2650 PROCESS - 60%
COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA2660 STRUCTURAL - 60%
COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA2930 MECHANICAL
EQUIPMENT - 60% COMMENTS INCORPORATION & PREPARE FOR 90% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA2980 PREPARATION OF
100% DD PACKAGE
Project: 600098BL00-5 Activity: ENGA3240 Finalize DD
agreement with GES+ Contractor
Project: 600098BL00-5 Activity: ENGA3250 ENGINEERING KICK-
OFF MEETING
Project: 600098BL00-5 Activity: ENGA3260 ISSUE MRS SALT
WATER DISPOSAL PUMPS INJECTION PUMP, WOSEP VESSEL
Project: 600098BL00-5 Activity: ENGA3270 ISSUE 50% DETAILED
DESIGN PACKAGE + 3D PACKAGE
Project: 600098BL00-5 Activity: ENGA3310 ISSUE 90%
TECHNICAL REVIEW PACKAGE
Project: 600098BL00-5 Activity: ENGA3470 PIPELINE ROW
LAYOUT LAYOUT
Project: 600098BL00-5 Activity: ENGA3480 PIPELINE ROW
SECTION AND DETAIL
Project: 600098BL00-5 Activity: ENGA3500 TOPO SURVEY SOW
Project: 600098BL00-5 Activity: ENGA3590 ISSUE EARLY IFC
Project: 600098BL00-5 Activity: ENGA5330 CIVIL EARLY IFC -
90% COMMENTS IMPLEMENTATION & PREPARE IFC PACKAGE
Project: 600098BL00-5 Activity: ENGA5370 50% REVIEW &
REVIEW MEETING
Project: 600098BL00-5 Activity: ENGA5410 PREPERATION OF
ISSUE MR'S -P1
Project: 600098BL00-5 Activity: ENGA5540 90% REVIEW &
REVIEW MEETING (EARLY IFC)
Project: 600098BL00-5 Activity: ENGA5550 PIPING EARLY IFC -
90% COMMENTS IMPLEMENTATION & PREPARE IFC PACKAGE
Project: 600098BL00-5 Activity: MILGEN0022 Project Finish -
Project Completion & Demobilization
Project: 600098BL00-5 Activity: PRCA24070 MANUFACTURING &
DELIVERY OF MATERIAL
Project: 600098BL00-5 Activity: PRCA24080 RECEIPT OF
MATERIAL AT SITE
Project: 600098BL00-5 Activity: PRCA3740 ISSUE MR
Project: 600098BL00-5 Activity: PRCA3950 ISSUE MR
Project: 600098BL00-5 Activity: PRCA4790 ISSUE MR
Project: 600098BL00-5 Activity: PRCA4800 RECEIVE VENDOR
QUOTATIONS
Project: 600098BL00-5 Activity: PRCA4810 TBC & TBE
Project: 600098BL00-5 Activity: PRCA4820 PO PLACEMENT
Project: 600098BL00-5 Activity: PRCA4830 RECEIVE, REVIEW
AND APPROVAL OF NMR 601