10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24
1
CAI-299 53 days Mon 10/22/18 Sat 12/22/18
Page 1
ID Task Name Duration Start Finish November 2018 December 2018
10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24
42 Sill and Jamb 1 day Tue 11/27/18 Wed 11/28/18
43 Guide Rail 1 day Wed 11/28/18 Thu 11/29/18
44 Civil work arround jambs By Owner 3 days Thu 11/29/18 Mon 12/3/18
45 M/R Works 1.5 days Mon 12/3/18 Tue 12/4/18
46 Control in M/R 1 day Wed 12/5/18 Wed 12/5/18
47 Mechanical Completed 0 days Wed 12/5/18 Wed 12/5/18 12/5
48 Electrical Work 5 days Wed 12/5/18 Tue 12/11/18
49 Electrical Start 0 days Wed 12/5/18 Wed 12/5/18 12/5
50 Car, CWT Frame, Roping and Speed Governor 1.5 days Thu 12/6/18 Sat 12/8/18
51 Car and Car Door Device Assembly 1 day Sat 12/8/18 Sun 12/9/18
52 Shaft Wiring& Traveling Cable 1 day Sun 12/9/18 Mon 12/10/18
53 Hatch Door Installation 1 day Mon 12/10/18 Tue 12/11/18
54 Shaft Devices 0.5 days Tue 12/11/18 Tue 12/11/18
55 (Owner) power source + circuit breakers 0 days Tue 12/11/18 Tue 12/11/18 12/11
56 Electrical Completed 0 days Tue 12/11/18 Tue 12/11/18 12/11
57 Commissioning 4 days Tue 12/11/18 Sun 12/16/18
58 Commissioning Start 0 days Tue 12/11/18 Tue 12/11/18 12/11
59 Low Speed Operation 1 day Wed 12/12/18 Wed 12/12/18
60 Landing Plates 0.5 days Thu 12/13/18 Thu 12/13/18
61 Adjusting the Wiring, Car Door and SDE 1 day Thu 12/13/18 Sat 12/15/18
62 High Speed Operation 1.5 days Sat 12/15/18 Sun 12/16/18
63 Commissioning Complete 0 days Sun 12/16/18 Sun 12/16/18 12/16
64 Handing Over 5 days Sun 12/16/18 Sat 12/22/18
65 H.O. Start 0 days Sun 12/16/18 Sun 12/16/18 12/16
66 Adjusting Hatch Door 1 day Mon 12/17/18 Mon 12/17/18
67 Final Adjustment 2 days Tue 12/18/18 Wed 12/19/18
68 Extra Stops 0 days Wed 12/19/18 Wed 12/19/18 12/19
69 QC/Client 2 days Thu 12/20/18 Sat 12/22/18
70 H.O. completed 0 days Sat 12/22/18 Sat 12/22/18 12/22
Page 2