ID Task Name Duration Start Finish November 2018 December 2018

10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24
1
CAI-299 53 days Mon 10/22/18 Sat 12/22/18

2 Construction Phase 53 days Mon 10/22/18 Sat 12/22/18


3 Dismantling Phase 31.5 days Mon 10/22/18 Tue 11/27/18
4 Dismantling Elevator #1 5 days Mon 10/22/18 Sat 10/27/18
5 Dismantling Elevator #2 5 days Wed 11/21/18 Tue 11/27/18
6 Installation Phase 48 days Sat 10/27/18 Sat 12/22/18
7 Elevator #1 21.5 days Sat 10/27/18 Wed 11/21/18
8 Mechanical Work 7.5 days Sat 10/27/18 Mon 11/5/18
9 Mechanical Start 0 days Sat 10/27/18 Sat 10/27/18 10/27
10 Sill and Jamb 1 day Sun 10/28/18 Sun 10/28/18
11 Guide Rail 1 day Mon 10/29/18 Mon 10/29/18
12 Civil work arround jambs By Owner 3 days Tue 10/30/18 Thu 11/1/18
13 M/R Works 1.5 days Sat 11/3/18 Sun 11/4/18
14 Control in M/R 1 day Sun 11/4/18 Mon 11/5/18
15 Mechanical Completed 0 days Mon 11/5/18 Mon 11/5/18 11/5
16 Electrical Work 5 days Mon 11/5/18 Sun 11/11/18
17 Electrical Start 0 days Mon 11/5/18 Mon 11/5/18 11/5
18 Car, CWT Frame, Roping and Speed Governor 1.5 days Mon 11/5/18 Tue 11/6/18
19 Car and Car Door Device Assembly 1 day Wed 11/7/18 Wed 11/7/18
20 Shaft Wiring& Traveling Cable 1 day Thu 11/8/18 Thu 11/8/18
21 Hatch Door Installation 1 day Sat 11/10/18 Sat 11/10/18
22 Shaft Devices 0.5 days Sun 11/11/18 Sun 11/11/18
23 (Owner) power source + circuit breakers 0 days Sun 11/11/18 Sun 11/11/18 11/11
24 Electrical Completed 0 days Sun 11/11/18 Sun 11/11/18 11/11
25 Commissioning 4 days Sun 11/11/18 Thu 11/15/18
26 Commissioning Start 0 days Sun 11/11/18 Sun 11/11/18 11/11
27 Low Speed Operation 1 day Sun 11/11/18 Mon 11/12/18
28 Landing Plates 0.5 days Mon 11/12/18 Mon 11/12/18
29 Adjusting the Wiring, Car Door and SDE 1 day Tue 11/13/18 Tue 11/13/18
30 High Speed Operation 1.5 days Wed 11/14/18 Thu 11/15/18
31 Commissioning Complete 0 days Thu 11/15/18 Thu 11/15/18 11/15
32 Handing Over 5 days Thu 11/15/18 Wed 11/21/18
33 H.O. Start 0 days Thu 11/15/18 Thu 11/15/18 11/15
34 Adjusting Hatch Door 1 day Thu 11/15/18 Sat 11/17/18
35 Final Adjustment 2 days Sat 11/17/18 Mon 11/19/18
36 Extra Stops 0 days Mon 11/19/18 Mon 11/19/18 11/19
37 QC/Client 2 days Mon 11/19/18 Wed 11/21/18
38 H.O. completed 0 days Wed 11/21/18 Wed 11/21/18 11/21
39 Elevator #2 21.5 days Tue 11/27/18 Sat 12/22/18
40 Mechanical Work 7.5 days Tue 11/27/18 Wed 12/5/18
41 Mechanical Start 0 days Tue 11/27/18 Tue 11/27/18 11/27

Task Project Summary Manual Task Start-only Deadline

Project: CAI-299 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/18/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Name Duration Start Finish November 2018 December 2018
10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24
42 Sill and Jamb 1 day Tue 11/27/18 Wed 11/28/18
43 Guide Rail 1 day Wed 11/28/18 Thu 11/29/18
44 Civil work arround jambs By Owner 3 days Thu 11/29/18 Mon 12/3/18
45 M/R Works 1.5 days Mon 12/3/18 Tue 12/4/18
46 Control in M/R 1 day Wed 12/5/18 Wed 12/5/18
47 Mechanical Completed 0 days Wed 12/5/18 Wed 12/5/18 12/5
48 Electrical Work 5 days Wed 12/5/18 Tue 12/11/18
49 Electrical Start 0 days Wed 12/5/18 Wed 12/5/18 12/5
50 Car, CWT Frame, Roping and Speed Governor 1.5 days Thu 12/6/18 Sat 12/8/18
51 Car and Car Door Device Assembly 1 day Sat 12/8/18 Sun 12/9/18
52 Shaft Wiring& Traveling Cable 1 day Sun 12/9/18 Mon 12/10/18
53 Hatch Door Installation 1 day Mon 12/10/18 Tue 12/11/18
54 Shaft Devices 0.5 days Tue 12/11/18 Tue 12/11/18
55 (Owner) power source + circuit breakers 0 days Tue 12/11/18 Tue 12/11/18 12/11
56 Electrical Completed 0 days Tue 12/11/18 Tue 12/11/18 12/11
57 Commissioning 4 days Tue 12/11/18 Sun 12/16/18
58 Commissioning Start 0 days Tue 12/11/18 Tue 12/11/18 12/11
59 Low Speed Operation 1 day Wed 12/12/18 Wed 12/12/18
60 Landing Plates 0.5 days Thu 12/13/18 Thu 12/13/18
61 Adjusting the Wiring, Car Door and SDE 1 day Thu 12/13/18 Sat 12/15/18
62 High Speed Operation 1.5 days Sat 12/15/18 Sun 12/16/18
63 Commissioning Complete 0 days Sun 12/16/18 Sun 12/16/18 12/16
64 Handing Over 5 days Sun 12/16/18 Sat 12/22/18
65 H.O. Start 0 days Sun 12/16/18 Sun 12/16/18 12/16
66 Adjusting Hatch Door 1 day Mon 12/17/18 Mon 12/17/18
67 Final Adjustment 2 days Tue 12/18/18 Wed 12/19/18
68 Extra Stops 0 days Wed 12/19/18 Wed 12/19/18 12/19
69 QC/Client 2 days Thu 12/20/18 Sat 12/22/18
70 H.O. completed 0 days Sat 12/22/18 Sat 12/22/18 12/22

Task Project Summary Manual Task Start-only Deadline

Project: CAI-299 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 11/18/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2

You might also like