ID Task Name Duration Start Finish Oct 27, '18 Nov 3, '18 Nov 10, '18 Nov 17,

Finish Oct 27, '18 Nov 3, '18 Nov 10, '18 Nov 17, '18 Nov 24, '18 Dec 1, '18
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1
CAI-702 Annex2 (Palm Hills Casa) 30 days Sat 10/27/18 Sun 12/2/18
2 Construction Work 30 days Sat 10/27/18 Sun 12/2/18
3 Block 33 10 days Mon 11/19/18 Sun 12/2/18
4 Elevator B 10 days Mon 11/19/18 Sun 12/2/18
5 Commissioning 5.5 days Mon 11/19/18 Tue 11/27/18
6 Commissioning Start 0 days Mon 11/19/18 Mon 11/19/18 11/19
7 Low Speed Operation 1 day Tue 11/20/18 Tue 11/20/18
8 Maintenance 2 days Thu 11/22/18 Sat 11/24/18
9 Landing Plates 1 day Sun 11/25/18 Sun 11/25/18
10 Adjusting the Wiring, Car Door and SDE 0.5 days Mon 11/26/18 Mon 11/26/18
11 High Speed Operation 1 day Mon 11/26/18 Tue 11/27/18
12 Commissioning Complete 0 days Tue 11/27/18 Tue 11/27/18 11/27
13 Handing Over 4.5 days Tue 11/27/18 Sun 12/2/18
14 H.O. Start 0 days Tue 11/27/18 Tue 11/27/18 11/27
15 Adjusting Hatch Door 0.5 days Tue 11/27/18 Tue 11/27/18
16 Final Adjustment 2 days Wed 11/28/18 Thu 11/29/18
17 Extra Stops 0 days Thu 11/29/18 Thu 11/29/18 11/29
18 QC/Client 2 days Sat 12/1/18 Sun 12/2/18
19 H.O. completed 0 days Sun 12/2/18 Sun 12/2/18 12/2
20 Elevator C 10 days Mon 11/19/18 Sun 12/2/18
21 Commissioning 5.5 days Mon 11/19/18 Tue 11/27/18
22 Commissioning Start 0 days Mon 11/19/18 Mon 11/19/18 11/19
23 Low Speed Operation 1 day Tue 11/20/18 Tue 11/20/18
24 Maintenance 2 days Thu 11/22/18 Sat 11/24/18
25 Landing Plates 1 day Sun 11/25/18 Sun 11/25/18
26 Adjusting the Wiring, Car Door and SDE 0.5 days Mon 11/26/18 Mon 11/26/18
27 High Speed Operation 1 day Mon 11/26/18 Tue 11/27/18
28 Commissioning Complete 0 days Tue 11/27/18 Tue 11/27/18 11/27
29 Handing Over 4.5 days Tue 11/27/18 Sun 12/2/18
30 H.O. Start 0 days Tue 11/27/18 Tue 11/27/18 11/27
31 Adjusting Hatch Door 0.5 days Tue 11/27/18 Tue 11/27/18
32 Final Adjustment 2 days Wed 11/28/18 Thu 11/29/18
33 Extra Stops 0 days Thu 11/29/18 Thu 11/29/18 11/29
34 QC/Client 2 days Sat 12/1/18 Sun 12/2/18
35 H.O. completed 0 days Sun 12/2/18 Sun 12/2/18 12/2
36 Block 32 10 days Sat 10/27/18 Wed 11/7/18
37 Elevator B 10 days Sat 10/27/18 Wed 11/7/18
38 Commissioning 5.5 days Sat 10/27/18 Sat 11/3/18
39 Commissioning Start 0 days Sat 10/27/18 Sat 10/27/18 10/27
40 Low Speed Operation 1 day Sun 10/28/18 Sun 10/28/18
41 Maintenance 2 days Mon 10/29/18 Tue 10/30/18

Task Project Summary Manual Task Start-only Deadline

Project: Project1 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 10/21/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone