CAI-702 Annex2 (Palm Hills Casa) 30 days Sat 10/27/18 Sun 12/2/18
2 Construction Work 30 days Sat 10/27/18 Sun 12/2/18
3 Block 33 10 days Mon 11/19/18 Sun 12/2/18
4 Elevator B 10 days Mon 11/19/18 Sun 12/2/18
5 Commissioning 5.5 days Mon 11/19/18 Tue 11/27/18
6 Commissioning Start 0 days Mon 11/19/18 Mon 11/19/18 11/19
7 Low Speed Operation 1 day Tue 11/20/18 Tue 11/20/18
8 Maintenance 2 days Thu 11/22/18 Sat 11/24/18
9 Landing Plates 1 day Sun 11/25/18 Sun 11/25/18
10 Adjusting the Wiring, Car Door and SDE 0.5 days Mon 11/26/18 Mon 11/26/18
11 High Speed Operation 1 day Mon 11/26/18 Tue 11/27/18
12 Commissioning Complete 0 days Tue 11/27/18 Tue 11/27/18 11/27
13 Handing Over 4.5 days Tue 11/27/18 Sun 12/2/18
14 H.O. Start 0 days Tue 11/27/18 Tue 11/27/18 11/27
15 Adjusting Hatch Door 0.5 days Tue 11/27/18 Tue 11/27/18
16 Final Adjustment 2 days Wed 11/28/18 Thu 11/29/18
17 Extra Stops 0 days Thu 11/29/18 Thu 11/29/18 11/29
18 QC/Client 2 days Sat 12/1/18 Sun 12/2/18
19 H.O. completed 0 days Sun 12/2/18 Sun 12/2/18 12/2
20 Elevator C 10 days Mon 11/19/18 Sun 12/2/18
21 Commissioning 5.5 days Mon 11/19/18 Tue 11/27/18
22 Commissioning Start 0 days Mon 11/19/18 Mon 11/19/18 11/19
23 Low Speed Operation 1 day Tue 11/20/18 Tue 11/20/18
24 Maintenance 2 days Thu 11/22/18 Sat 11/24/18
25 Landing Plates 1 day Sun 11/25/18 Sun 11/25/18
26 Adjusting the Wiring, Car Door and SDE 0.5 days Mon 11/26/18 Mon 11/26/18
27 High Speed Operation 1 day Mon 11/26/18 Tue 11/27/18
28 Commissioning Complete 0 days Tue 11/27/18 Tue 11/27/18 11/27
29 Handing Over 4.5 days Tue 11/27/18 Sun 12/2/18
30 H.O. Start 0 days Tue 11/27/18 Tue 11/27/18 11/27
31 Adjusting Hatch Door 0.5 days Tue 11/27/18 Tue 11/27/18
32 Final Adjustment 2 days Wed 11/28/18 Thu 11/29/18
33 Extra Stops 0 days Thu 11/29/18 Thu 11/29/18 11/29
34 QC/Client 2 days Sat 12/1/18 Sun 12/2/18
35 H.O. completed 0 days Sun 12/2/18 Sun 12/2/18 12/2
36 Block 32 10 days Sat 10/27/18 Wed 11/7/18
37 Elevator B 10 days Sat 10/27/18 Wed 11/7/18
38 Commissioning 5.5 days Sat 10/27/18 Sat 11/3/18
39 Commissioning Start 0 days Sat 10/27/18 Sat 10/27/18 10/27
40 Low Speed Operation 1 day Sun 10/28/18 Sun 10/28/18
41 Maintenance 2 days Mon 10/29/18 Tue 10/30/18