Project Phase From To Form Code Discipline Code Number Rev.

Technical_Submittal 4 Alphabet
- 2 Digit & 1 Alphabet
- Alphabet
- Alphabet
- Alphabet
- 1 Alphabet & 2 Digit
- 5 Digit 1 Digit

Drawing Shop Drawing Mechanical


ZEDW - GE - SOL - ECG - S-SD - ME - 00015 1
ZEDW-GE-SOL-ECG-S-SD-ME-00015
Project Phase From To Form Code Discipline Code Number Rev.
Information_Requested 4 Alphabet
- 2 Digit & 1 Alphabet
- Alphabet
- Alphabet
- Alphabet
- 1 Alphabet & 2 Digit
- 5 Digit 1 Digit

Request For Inofrmation General


ZEDW - GE - SIT - ECG - RFI - GE - 00011 1
ZEDW-GE-SIT-ECG-RFI-GE-00011
Project Phase From To Form Code Discipline Code Number Rev.
Site_Requests 4 Alphabet
- 2 Digit & 1 Alphabet
- Alphabet
- Alphabet
- Alphabet
- 1 Alphabet & 2 Digit
- 5 Digit 1 Digit

Work Inspection Request Civil


ZEDW - 01B - RME - ECG - WIR - CI - 00011 1
ZEDW-01B-RME-ECG-WIR-CI-00011
Project Phase From To Form Code Discipline Code Number Rev.
Site_Instruction 4 Alphabet
- 2 Digit & 1 Alphabet
- Alphabet
- Alphabet
- Alphabet
- 1 Alphabet & 2 Digit
- 5 Digit 1 Digit

Job Site Instruction Mechanical


ZEDW - 01A - ECG - OC - JSI - ME - 00001 1
ZEDW-01A-ECG-OC-JSI-ME-00001
Project Phase From To Form Code Discipline Code Number Rev.
Design_Change 4 Alphabet
- 2 Digit & 1 Alphabet
- Alphabet
- Alphabet
- Alphabet
- 1 Alphabet & 2 Digit
- 5 Digit 1 Digit

Agreed Variation Order Civil


ZEDW - 01B - SOL - ECG - AVO - CI - 00011 1
ZEDW-01B-SOL-ECG-AVO-CI-00011
Project Phase From To Form Code Number Rev.
Transmittal 4 Alphabet
- 2 Digit & 1 Alphabet
- Alphabet
- Alphabet
- Alphabet
- 5 Digit 1 Digit

Transmittal for Progress Photos


ZEDW - 01A - ALI - ECG - T-PP - 00001 1
ZEDW-01A-ALI-ECG-T-PP-00001
Project Phase From To Form Code Number
Formal_Letter 4 Alphabet
- 2 Digit & 1 Alphabet
- Alphabet
- Alphabet
- Alphabet
- 5 Digit

Formal Letter
ZEDW - 01A - ALI - ECG - LRS - 00001
ZEDW-01A-ALI-ECG-LRS-00001
Company Name Code

SITES Int. SIT


Phases PCode Project PRCode Company CCoode Discipline DSCode Discipline CODE Document Type DT Code DType Technical_Submittal Drawing DCode
General GE Zed West ZEDW Ora Egypt ORA Division 01 - General Requirement D01 Survey SU Basic Design S-BD Technical_Submittal Drawing Basic Design S-BD
Phase 1A 01A 3H 3H Division 02 - Existing Conditions D02 Civil CI Sketch Drawing S-KD Information_Requested Document Sketch Drawing S-KD
Phase 1B 01B Orascom Construction OC Division 03 - Concrete D03 Architecture AR Shop Drawing S-SD Site_Requests Material Shop Drawing S-SD
Phase 1 01 Orascom Foundation OF Division 04 - Masonry D04 Electrical EL As Built Drawing S-AB Site_Instruction Quantity_Survey As Built Drawing S-AB
Phase 2 02 ECG ECG Division 05 - Metals D05 Lighting LI Organization Chart S-OC Design_Change Test_Result
Phase 3A 03A MACE MACE Division 06 - Wood and Plastics D06 Power PO Qualty Plan S-QP Transmittal
Phase 3B 03B Rowad RME Division 07 - Thermal and Moisture Protection D07 Low current LC Sefty Plan S-SP Formal_Letter
Phase 3 03 Redcon RCN Division 08 - Doors and Windows D08 Mechanical ME Schedule S-SCH
Phase 4 04 SHAKER SH Division 09 - Finishes D09 HVAC HV Procedure S-PR
Phase 5A 05A ALICO Egypt ALI Division 10 - Specialties D10 Plumbing PL Prequalification S-PQ
Phase 5B 05B El-Goul GOUL Division 11 - Equipment D11 Fire Fighting FF Calculation Sheet S-CL
Phase 5 05 Zicaza ZICZ Division 12 - Furnishings D12 Medical gas MG Method Of Statement S-MOS
Phase 6 06 Mitnbishi MITS Division 13 - Special Construction D13 Telecommunications TE Inspection Test Plan S-ITP
Melco MLCO Division 14 - Conveying Systems D14 Landscape LS Other S-OT
TK Elevator Egypt TK Division 15 - Mechanical/Plumbing D15 Infrastructure IN Material Sample S-MS
Phase 1B Contractors Division 16 - Electrical D16 Elevators EV Data Sheet / Catalogs S-CT
SITES Int. SIT General GE Quantity Survey S-QS
Sphinx SPHX Test Result S-TR
GILA GILA Request For Inofrmation RFI
Alunile NIL Request For Proposal RFP
EIM EIM Work Inspection Request WIR
Miraco Carrier MCE Material Inspection Request MIR
Elsewedy Electric SWC Placing Concrete Request PCR
EMAS EMAS Release Order FRO Information_Requested Request For Inofrmation Sketch Drawing S-KD
Elandaluse Electric ANDE Commencement Notice for activit SNA Information_Requested Request For Inofrmation RFI
AFAAQ AFAQ Inspection & Check List ICL
Soler - Energy Solutions SOL Job Site Instruction JSI
Solinq Egypt SQE Non Conformace Request NCR
Doortech for Wood Industry DWI Design Chaneg Request DCR
All Contractors ALL Engineers Instruction EI
Request For Chaneg RFC
Approval Request Form ARF
Agreed Variation Order AVO
Formal Letter LRS
Minuts Of Meeting MOM
Daily Work Report DWR
HSE Daily Report SDR
Transmittal for Weekly Report T-WR
Transmittal for HSE Weekly ReportT-SWR
Transmittal for Monthly Report T-MR
Transmittal for HSE Monthly ReporT-SMR
Transmittal for Damage Report T-DR
Transmittal for Progress Photos T-PP
Transmittal for Safety Notice T-SN
Document CCode Material MCode Quantity_Survey QCode Test_Result TCode Information_Requested InfoCode Site_Requests SRCode Site_Instruction SICode Design_Change DHCode
Organization Chart S-OC Material Sample S-MS Quantity Survey S-QS Test Result S-TR Request For Inofrmation RFI Work Inspection Request WIR Job Site Instruction JSI Design Chaneg Request DCR
Qualty Plan S-QP Data Sheet / Catalogs S-CT Request For Proposal RFP Material Inspection Request MIR Non Conformace Request NCR Engineers Instruction EI
Sefty Plan S-SP Placing Concrete Request PCR Request For Chaneg RFC
Schedule S-SCH Release Order FRO Approval Request Form ARF
Procedure S-PR Inspection & Check List ICL Agreed Variation Order AVO
Prequalification S-PQ Commencement Notice for activity SNA
Calculation Sheet S-CL
Method Of Statement S-MOS
Inspection Test Plan S-ITP
Other S-OT
Transmittal TRCode Formal_Letter FLCode
Minuts Of Meeting MOM Formal Letter LRS
Daily Work Report DWR
HSE Daily Report SDR
Transmittal for Weekly Report T-WR
Transmittal for HSE Weekly Report T-SWR
Transmittal for Monthly Report T-MR
Transmittal for HSE Monthly Report T-SMR
Transmittal for Damage Report T-DR
Transmittal for Progress Photos T-PP
Transmittal for Safety Notice T-SN