You are on page 1of 1

TANJUNG TABALONG 2 X 30 MW COAL

FIRED POWER PLANT PROJECT

SAFETY INSPECTION CHECK LIST


HSSE DEPT
ELECTRICAL PANEL Date: 28th October 2009
Rev: 0

Project/Site :
Date of Inspection :
S/N of Equipment :
Contractor :
Location of Inspection :

No Description Good Fair Poor N/A Remarks

1 General condition of the electrical panel -

2 ELCB (earth Leakage Circuit Breaker)

3 Plug and socket connection


4 ESD Push button
5 Warning Sign
6 Switch (on/off) condition
7 Supply cable proper insulated
8 Indicators (Voltage, Ampere, etc)
9 Earth/Ground System
10 Sticker inspection
Comments:

Inspected by Sub Contractor Acknowledged by PT. PLI

Name : Name :

Designation : Designation :

Signature : Signature :