Professional Documents
Culture Documents
This example is for a Hollowcore floor building – but the same principles apply for all precast floors
including Double Tees, Rib and Infill, and Flat Slab assessments.
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Design Drawings and Details
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Example – Ductile Frame Example Parameters
le = 3600mm
• Beam depth = 800 mm 350 Double Tee
500W x 800D
500W x 600D
75mm topping
• Column width = 800 mm 665 mesh
75mm seating
Scenarios to check:
• Initial spalling = 10 mm
Drift related spalling
• Bearing (calc = 8mm) = 10 mm (example)
= 2.6*0.0089/2*(800-65)
(U) = 8.5 mm => 9 mm ≥ 0.005hb
(R) = 4.2 mm => 4 mm (Restrained taken as ½ of reversing)
+ Additional spalling at
limiting drift of 1.39%
• Unit (27 -10) = 17 mm
10mm
• Ledge = 5 mm
• Total spalling = 32 mm 5mm
L.O.S = 1.39%
Figure C5E.26 Spalling depths to be considered for Flange hung and web supported double tees
Bearing = 10 mm
• Ledge Spalling = 5 mm
• Beam elongation = 9 mm
• Beam rotation = 4 mm
35 mm
L.O.S = 1.4%
Bearing = 10 mm
• Beam elongation = 11 mm
• Beam rotation = 5 mm L.O.S = 1.7%
45 mm
With suitable site investigation 20mm tolerance may be able to be reduced to actual site tolerance
e.g. for the above example with a site measured 10mm variance on seating (75mm +/- 10mm)
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Floor Example – Loss of Support Review
Now repeat the L.O.S for rest of the
floor
ULS design drifts are factored by 2.0 in the Yellow Book to get drift demand
Summary
[Note: this is different to NZBC = dULS x 1/SP x 1.5] Elongation and Rotation 37.8 mm
The NBS rating is based on a limiting drift to loss of support i.e. the methodology assesses the
amount of drift required before loss of precast support – this is a bi-linear function and gives a
different answer than simply comparing against the total seating that would be required for design.
Tension Shift
Note: Be careful some published values of m are lower bound or dependable values i.e. they
have a f.o.s or reduction factor for design built in and may be un-conservative for calculation
of demand.
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Example – Birdsmouth / Loop Bar
Scenario Review Qualitative Review of Detailing
a) Flexure
a) Yes - check required
b) Topping delamination
a) at loop bar – Yes likely - check
b) In unit – Yes - possible as the R6
spirals are unlikely to be sufficient
c) Shear Failure
a) Yes - check required
d) Diagonal tension failure
a) Yes - check required
e) Bond failure
a) At Leg – <600mm anchorage for
plain R12 bar in tension – to short to
develop
b) At bottom hangar bar – ? may be OK
f) Separation of Flange from Web
a) 4 sets of R6 Stirups at 50mm crs at
end of unit so failure is likely
suppressed but should check C5E 29 Example demonstrated
This check may be simple but is un-conservative and does not consider the actual failure modes of
the connection. The birds mouth is a disturbed region and you must use an appropriate method i.e.
Strut and Tie to assess the failure modes.
Further details on the assessment of the failure modes is in Hare et al. (2009)
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Example – Birdsmouth / Loop Bar
Review the Flexural Mechanism
Horizontal Reinforcing Tie 90 65
To develop Tjd of 11kNm the tension steel yeilds
C
=> for 3 R12 T* = C C = Asfy = 110 kN 30 O
75 Concrete
Compression Strut Check
Strut / Node Force = 110/Cos30 = 127 kN Tension
Node width = 200mm x 20mm (Pigtail bar width) 50 T = ASfy
Node Capacity
fFn = f*bn*f’c = 0.75*0.80*200*20*30 = 72kN < 127kN
=>Capacity Ratio = 0.56 P
Strut Capacity
fFs = f*bs*f’c = 0.75*1.0*200*20*30 = 90kN => Ratio = 0.70
Therefore node failure and concrete crushing may occur at loop bar node before you can fully
develop tension steel capacity required for flexure theory.
P
Equations for Concrete Tension – Use with Caution!
Tension capacity in slab
(NZS3101 5.2.4) gives ft = 0.38 l [f’c]1/2 = f x 2.08 MPa (for 30MPa)
Cold joint interface - for tension across slab/unit interface
(ACI) = 0.25 [f’c]1/2 = f x 1.36 MPa
By iteration you can find S&T mechanisms which may give better results than this initial review
example. A key consideration is the capacity of the tie is limited by the geometry of the joint
including the pigtail compression node width + amount of spread of strut of 1:2.5 max.
Further details on the assessment of the double tee failure modes is in Hare et al. (2009)
• Flexural Capacity derived by S&T < 40% of that provided by simple Flexure theory fMi= Tjd
=>this is quite sensitive to geometry of loop bar and joint.
• Large increase in design actions due to tension from elongation Pmt => actions almost double
– also quite sensitive to support load and friction coefficient chosen
• Tension Shift – once concrete cracks also accounts for another shift approximately additional
30% - 40% increase
• Offset of support due to elongation has less affect and accounts for about another 10% to 15%
increase in load
7.1 kNm
kNm
6.1 kNm
2.7 kNm
1.8 kNm
mm
Birdsmouth / Loop Bar – Demand / Capacity Envelope
ASSESSMENT OF EXISTING PRECAST CONCRETE FLOORS
Double Tee Example – Birdsmouth / Loop Bar
Review - Outcome
Strut and Tie Review of Mechanism (a)
• Review of the flexural mechanism with an initial S&T model gives a lower bound limiting drift
sensitive to cracking with d = <5 mm for the birdsmouth after onset of cracking.
• The S&T review indicated however that the unit it may be able to (just) carry gravity loads after
elongation has finished i.e. (Pm loads from elongation no longer action).
• Could investigate geometry further and sliding capacity – important to understand site
constraints and geometry of loop bar and joint
Other Failures – mechanism (b), (c), (d), (e), etc
• Need to now complete the review and check other modes to determine critical mode of failure
has been determined.
The floor %NBS in this example (a) Flexure will be difficult to rate as a result of the birdsmouth /
loop bar connection having insufficient capacity to accept movement that would result in a crack
forming and tension (from elongation) across the birdsmouth connection. A detailed further
investigation of the loop bar details should be undertaken to help determine the actual as built
capacity.
Topping Delaminates
tf
Section capacity is
based solely on the
double tee flange depth
tf for these areas
40
ASSESSMENT OF EXISTING PRECAST CONCRETE
40FLOORS
Precast Rib and Infill
Failure of Rib and Timber Infill Floors
42
Assessment of Rib and Timber Infill Floors