Drilling Schedule (Days post FID)

Wellpad to Drilling
Wellpad Producers Injectors Drilling Start
(From EPC)
NG-08 16 5 380 410
AM-01 9 6 442 472
NG-03 9 5 501 531
AM-03 13 6 648 678
NG-01 10 6 668 698
NG-11 11 6 686 716
NG-07 12 8 871 901
AM-08 7 4 888 918
NG-12 10 3 901 931
AM-04 6 4 1028 1058
NG-13 7 4 1066 1096
NG-09 12 5 1123 1153
AM-09 8 3 1156 1186
NG-14 7 2 1206 1236
AM-07 3 1 1296 1326
NG-16 3 3 1321 1351
NG-15 7 4 1338 1368
AM-10 4 1 1348 1378
NG-17 4 3 1399 1429
AM-11 3 1 1413 1443
TW-04 4 3 1466 1496
NG-18 5 1 1478 1508
NG-02 4 2 1489 1519
NG-19 5 5 1556 1586
NG-04 4 2 1566 1596
NG-20 6 3 1581 1611
NG-22 4 1 1644 1674
NG-23 4 2 1683 1713
NG-21 6 2 1696 1726
NG-10 4 2 1709 1739
NG-24 4 2 1761 1791
TW-05 2 1 1786 1816
AM-19 1 1 1876 1906
chedule (Days post FID)
Hook-up Start
Drilling End Completion Start Completion End
(To EPC)
698 979 1000 1003
678 935 958 961
716 958 979 982
918 1000 1025 1028
901 1025 1050 1053
931 1050 1075 1078
1153 1200 1233 1236
1058 1081 1098 1101
1096 1134 1147 1150
1186 1233 1250 1253
1236 1250 1267 1270
1368 1463 1484 1487
1326 1353 1366 1369
1351 1388 1397 1400
1378 1388 1404 1407
1429 1463 1478 1481
1508 1549 1566 1569
1443 1478 1498 1501
1519 1566 1587 1590
1496 1498 1514 1517
1611 1644 1661 1664
1586 1599 1608 1611
1596 1619 1628 1631
1713 1726 1747 1750
1674 1682 1691 1694
1726 1756 1769 1772
1739 1777 1782 1785
1791 1799 1808 1811
1828 1855 1864 1867
1816 1825 1834 1837
1868 1877 1886 1889
1894 1902 1911 1914
1983 1991 2000 2003
Drilling Schedule (Years post FID)
Wellpad to Drilling
Wellpad Producers Injectors Drilling Start
(From EPC)
NG-08 16 5 1.04 1.12
AM-01 9 6 1.21 1.29
NG-03 9 5 1.37 1.45
AM-03 13 6 1.78 1.86
NG-01 10 6 1.83 1.91
NG-11 11 6 1.88 1.96
NG-07 12 8 2.39 2.47
AM-08 7 4 2.43 2.52
NG-12 10 3 2.47 2.55
AM-04 6 4 2.82 2.90
NG-13 7 4 2.92 3.00
NG-09 12 5 3.08 3.16
AM-09 8 3 3.17 3.25
NG-14 7 2 3.30 3.39
AM-07 3 1 3.55 3.63
NG-16 3 3 3.62 3.70
NG-15 7 4 3.67 3.75
AM-10 4 1 3.69 3.78
NG-17 4 3 3.83 3.92
AM-11 3 1 3.87 3.95
TW-04 4 3 4.02 4.10
NG-18 5 1 4.05 4.13
NG-02 4 2 4.08 4.16
NG-19 5 5 4.26 4.35
NG-04 4 2 4.29 4.37
NG-20 6 3 4.33 4.41
NG-22 4 1 4.50 4.59
NG-23 4 2 4.61 4.69
NG-21 6 2 4.65 4.73
NG-10 4 2 4.68 4.76
NG-24 4 2 4.82 4.91
TW-05 2 1 4.89 4.98
AM-19 1 1 5.14 5.22
hedule (Years post FID)
Hook-up Start
Drilling End Completion Start Completion End
(To EPC)
1.91 2.68 2.74 2.75
1.86 2.56 2.62 2.63
1.96 2.62 2.68 2.69
2.52 2.74 2.81 2.82
2.47 2.81 2.88 2.88
2.55 2.88 2.95 2.95
3.16 3.29 3.38 3.39
2.90 2.96 3.01 3.02
3.00 3.11 3.14 3.15
3.25 3.38 3.42 3.43
3.39 3.42 3.47 3.48
3.75 4.01 4.07 4.07
3.63 3.71 3.74 3.75
3.70 3.80 3.83 3.84
3.78 3.80 3.85 3.85
3.92 4.01 4.05 4.06
4.13 4.24 4.29 4.30
3.95 4.05 4.10 4.11
4.16 4.29 4.35 4.36
4.10 4.10 4.15 4.16
4.41 4.50 4.55 4.56
4.35 4.38 4.41 4.41
4.37 4.44 4.46 4.47
4.69 4.73 4.79 4.79
4.59 4.61 4.63 4.64
4.73 4.81 4.85 4.85
4.76 4.87 4.88 4.89
4.91 4.93 4.95 4.96
5.01 5.08 5.11 5.12
4.98 5.00 5.02 5.03
5.12 5.14 5.17 5.18
5.19 5.21 5.24 5.24
5.43 5.45 5.48 5.49