Week Activities/Tasks Comments/Concerns Discussed the scope of project with Proposed project was too big Week 1 our instructor. given time and resource Submit capstone (1) proposal. constraints.
Meeting with client to discuss As our client had new Week 2 modified project proposal. recruiting team, had to explain, Agreement was made on revised and meet from the beginning. proposal. Week 3 Interview questionnaire was sent to client for initial understanding of the process. Meeting with client for initial data collection. Week 4 Survey questionnaire prepared and distributed.
Week 5 Started to draft the report. Divide the sections among the
team.
Week 6 Prymary data collected, sorted, and
analyzed.
Week 7 Interview and discussion with
recruiters of client organization. More data collected from primary sources. Week 8 Preparing the recruitment Progress of the project has process report. been discussed with our Worked individually then meet to see instructor. our progress on proposal and discuss it.
Week 9 Team examine documents, including Working on our secondary
progress reports to find out what was research for software features done right, what went wrong, and what to help the client. can be improved. Week 10 All team working in editing Final report and management tool and finalizing the report. submission
Week 11 Presenting on the class All team practicing and
preparing their script for the presentation. Week 12 Getting feedback before presenting for the Get feedback from our clients instructor and set a date to present to our client and send them the report. Week 13 Presenting for the client