Professional Documents
Culture Documents
Abstract—To prove to a customer that a new or overhauled within the acceptance limit agreed with the customer and
gas turbine satisfies its contractual performance, mechanical and comply with international guidelines and regulations [3].
emissions target, an acceptance test is normally performed by the
manufacturer. Such acceptance tests typically involve running There are two parts to any gas turbine acceptance test; the
the turbine through its operational envelope based on a pre- first part which is always performed is the works acceptance
defined test schedule, with information regarding the test (WAT) and the second part which may or may not be
thermodynamic and mechanical performance as well as exhaust performed based on the customer request is the customer
emission levels gathered. Decisions relating to acceptance and witness test (CWT).
subsequent certification are made on the basis of agreed criteria.
At present, these tests proceed in a time-consuming, sequential The works acceptance test also referred to as factory
manner which relies heavily on manual intervention. Proposed is acceptance test involves a detailed test regime running the gas
an automated system for acceptance testing which will directly turbine over its entire operating range and checking for
address the aforementioned issues through improvements in thermodynamic, mechanical and emissions acceptability.
efficiency and throughput. The proposed system will provide a On the other hand, a customer witness test is much shorter
data archive and access system which will automate data than the works acceptance test aimed at demonstrating the gas
acquisition, facilitate real-time fault diagnostics and create and
turbine full load performance and mechanical acceptability.
manage all test documentation. In this paper, an overview of the
requirements for acceptance testing is presented and the
Also, some part load performance is demonstrated to show
principal components of an automated system for industrial gas emissions acceptability.
turbine acceptance testing are identified.
II. ACCEPTANCE TEST PROCEDURE
Keywords— test automation, automated diagnostics, test
procedure, works acceptance test
To perform a gas turbine acceptance test, first an equipment
specific test procedure is created by the test conducting party
detailing the test schedule, test instrumentation and measuring
I. INTRODUCTION methods, the test acceptance criteria and test data analysis
A gas turbine is a mechanical device that converts the approach [3]. The development of the test procedure is based
thermal energy of a fuel into shaft power or thrust [1]. The gas on guidelines from international standards for gas turbine
turbine operates basically by drawing in air from the acceptance testing e.g. ISO 2314 [3], ASME PTC 22 [4] and
atmosphere into the compressor; where the pressure of the air API 616 [5], contractual agreement with the customer and the
is increased and fed into a combustor; in the combustor, heat gas turbine manufacturer equipment experience.
energy is added by combusting a gaseous or liquid fuel in the The following themes constitute the basic building blocks
compressed air, the resulting combustion products are then of a typical test procedure.
allowed to expand through a turbine producing mechanical
power or with further expansion through a nozzle, producing
thrust. The gas turbine finds application as a mechanical drive A. Measurements and Instrumentations
for pumps and compressors, also used for power generation, Test instrumentations installed on the gas turbine and test
combined heat and power, marine and aerospace propulsion bed provide the means by which the actual operating
[2]. conditions of the gas turbine during a test are measured. The
following parameters such as temperature and pressure at
In the gas turbine industry, it is standard practice for new or various stations along the gas turbine, air mass flow, fuel flow,
overhauled gas turbines to undergo an acceptance test. The fuel properties, power output, vibration, etc. are normally
purpose of an acceptance test is to verify that the power output, measured during a test.
heat rate or thermal efficiency, exhaust gas energy, emissions
and other performance characteristics of the gas turbine are Fig. 1 illustrates a typical test instrumentation arrangement
used for the acceptance testing of a twin-shaft gas turbine with
a power turbine.
Although the turbine inlet temperature (TIT) is an
important performance operating parameter in the gas turbine,
due to the operational and technical difficulties in measuring
such high temperatures, they are not normally measured
directly during a test, but are determined indirectly applying
the energy balance method.
2) Pressure Measurement
Pressure measurements are important for the determination
of overall engine and component performance and also to
determine mass flow in venturi-flow devices.
Although there are several types of pressure transducers,
the most commonly used in gas turbine acceptance testing are
piezo-resistive pressure transducer, capacitive pressure
transducer, inductive pressure transducer and piezo-electric
Fig. 1. A typical instrumentation arrangement for testing a twin-shaft gas pressure transducer [3], [6].
turbine with power turbine
Based on the gas turbine configuration, the following
1) Temperature Measurement minimum pressure measurements are required: ambient
In the measurement of temperature during gas turbine pressure, compressor inlet and exit pressure, turbine outlet
acceptance testing, resistance temperature detectors (RTDs) pressure, exhaust pressure and fuel gas pressure.
and thermocouples are the preferred options [3].
3) Inlet Air Mass Flow Measurement
Resistance temperature detectors measure temperature Inlet air massflow measurements are vital in determining
based on the change in the resistance of the temperature the performance of the gas turbine. Massflow measurements
sensing element e.g. platinum. They are suitable for can be made with a venturi nozzle designed according to ISO
temperatures up to 1000K and give an accuracy of 0.1K [6]. 5167 [7] standard or with a flare.
Despite their high accuracy, due to their delicate nature they
are scarcely used within the engine but find application in 4) Shaft Power Output Measurement
measuring the compressor inlet temperature [6]. Shaft power output is determined from the product of the
turbine output torque and shaft rotational speed. The approach
Thermocouples on the other hand are used within the mostly commonly used to measure torque during an acceptance
engine and at the hot ends; they consist of two dissimilar test is with a dynamometer e.g. water brake or a torque meter
metals connected at a junction as the temperature sensing [3], [6].
element and the loose ends maintained at a reference
temperature. When the junctions of the dissimilar metals are On the other hand, the gas turbine speed is measured using
kept at different temperatures, a voltage is generated which is a a magnetic speed pickup or tachometer with a key phasor or a
function of the temperature difference between the junction and phonic wheel [3], [6].
the reference temperature end. Thermocouples of the Type K 5) Fuel Measurements
(Chromel-Alumel) and Type N (Nicrosil-Nisil) are mostly used Demonstrating the gas turbine operability on a single/ dual
in gas turbine acceptance testing, although Type N is the most fuel (gas and liquid) and also fuel changeover are critical parts
preferred [6]. of an acceptance test.
The following minimum temperature measurements are Natural gas and diesel are commonly used gas or liquid fuel
required: ambient temperature, compressor inlet and exit respectively for gas turbine acceptance testing.
temperatures, turbine inter-stage and exit temperatures, exhaust
stack temperature, fuel gas temperature, etc. Necessary fuel measurements for the gaseous fuel are: fuel
flow measurement either by a Coriolis meter or turbine flow
At the compressor inlet, ISO 2314 [3] recommends a meter with a pressure and temperature sensors, fuel heating
minimum of two temperature sensors to characterize the value and composition measured by online gas chromatograph
average inlet temperature. Although in literature a minimum of [3].
three is also suggested [6]. In practice, the number would
depend on the temperature non-uniformity at the compressor For the liquid fuel, the necessary fuel measurements are:
inlet. fuel flow measured by a Coriolis meter or turbine flow meter
and the fuel heating value measured using a bomb calorimeter
At the exhaust stack, the temperature and velocity profile is [3].
non-uniform, a number of temperature sensors are required to
accurately characterize the average turbine outlet or exhaust 6) Other Measurements
temperature. In literature a minimum of eight temperature Relative humidity at the inlet conditions is measured to
sensors are recommended [6], while ISO 2314 [3] suggests a refer the test data to ISO conditions. Relative humidity is
minimum of four temperature sensors. In practice, gas turbine normally measured with a hygrometer e.g. capacitance sensor
manufacturers would adopt more sensors based on either type, chilled mirrors, etc. or using a wet and dry bulb
development test data or CFD analysis. thermometer.
Exhaust emissions requirements are becoming more Before commencing the acquisition of any performance test
stringent and as such, are tested for during a gas turbine data, it is necessary to ensure that the gas turbine is warmed up
acceptance test. Multi-point mixing probes are used in sample and the operating parameters e.g. power output, temperature,
acquisition from a well-mixed location in the turbine exhaust etc. are at steady state conditions. A typical test schedule for
duct. The presence of the following emissions species such as the performance test is shown in Fig. 2.
NOx, CO, unburnt hydrocarbon (UHC) and O2 are analyzed in
a gas analyzer with chemiluminescence method, infra-red gas
filter wheel correlation method, flame ionization detection
method and paramagnetism method respectively.
Also vibration measurements provide insight into the
mechanical or rotordynamic operability of the gas turbine.
Vibration are measured during test using proximity probes on
the bearings or accelerometer on the gas turbine casing.
Other parameters that could be measured during an
acceptance test include the turbine blade metal temperature for
cooled blades using an infrared pyrometer and also the
combustion dynamics for dry low emission (DLE) combustors
using dynamic pressure sensors.
Fig. 2. A typical gas turbine performance test schedule
B. Preliminary, Commissioning & Handling Tests
The preliminary, commissioning and handling tests covers Description of a typical performance test schedule as shown
the various checks carried out with the test engine installed on in Fig. 2 is as follows:
the test bed to ensure that the test engine is properly installed,
the test engine protection system, the test bed control system • The test engine is run for 10 minutes at full speed
and any slave test equipment are functioning properly. minimum load. Multiple test data scans are taken. The
test data scan consists of both engine thermodynamic
The following check is first performed, instrument zero parameters, engine pressures (e.g. compressor inlet,
scans are taken and investigated to eliminate any faulty sensor compressor discharge, turbine interduct, turbine outlet,
reading that would compromise the quality of the test data. exhaust, etc.), engine temperatures (e.g. compressor
Also an over-speed test is performed to verify the over- inlet, compressor discharge, turbine interduct, turbine
speed protection feature of the test bed control system. For this outlet, exhaust, etc.), fuel measurements (e.g. fuel
check, with the engine running under minimum load, for flow, etc.), speed, turbine output torque, etc. and
reduced stress on the engine, the governor over-speed setting is mechanical parameters (e.g. bearing vibration, bearing
increased by a specified percentage and the engine speed is temperature).
ramped up to confirm if the engine speed card would trip on an • The load on the test engine is further ramped to 100%
over-speed. Also checked are any signs of leakage in load and run at this operating point for one hour.
compressed air and lube oil. Several test scans are taken at regular intervals. Data
Further checks include demonstrating satisfactory engine from this segment of the test is vital, as it is used for
starting to specified operating conditions e.g. hot start, cold the performance rating of the engine.
start on gas and/or liquid fuel, the ability for the gas turbine to • After the full load test, the performance of the test
govern or maintain a steady output speed and its load shed and engine is evaluated at several part load conditions. Test
acceptance characteristics. engine emission performance i.e. NOx, CO & UHC are
also evaluated at the part load conditions.
C. Performance Test
• For a dual fuel engine configuration (e.g. gas and
Performance test is the heart of any gas turbine acceptance
liquid), the second fuel is being test as shown in the
test procedure; it provides the necessary data to access the
Fig. 2. The test engine is tested at 100% load, with
performance characteristics of the gas turbine. During a
several test scans taken at regular intervals. These test
performance test, the operability of the gas turbine is tested
data is used to determine the engine performance on
across its entire operating range to demonstrate acceptability in
the second fuel. Also, part load performance is
thermodynamic, mechanical (vibration) and emissions
demonstrated.
performance.
In undertaking the performance test, the following methods
Guidelines for conducting the performance test during a gas
or control modes are used to determine the power rating: fixed
turbine acceptance test has been the subject of several
power, fixed heat input and fixed turbine inlet temperature.
international standards such as ISO 2314 [3], ASME PTC 22
[4] and API 616 [5]; a typical description of the performance When fixed power is adopted as the power rating or control
test schedule is presented in this paper. mode, the test engine is run at a fixed value of the zero-loss
power (i.e. ignoring pressure loss from the inlet and exhaust
ducting and mechanical losses from gearbox) while other
parameters (e.g. .heat input, heat rate, etc.) must lie within
specified limits. 288.15
= × (3)
For fixed heat input power rating or control method, the test
engine is run at a fixed value of heat input calculated based on
the energy balance approach, while the other operating
parameters (e.g. power, heat rate, etc.) must lie within specified
limits. ISO 2314 [3] outlines how to perform the energy =
balance calculation approach for heat input. 101325
× × (4)
On the other hand, for a fixed turbine inlet temperature 288.15
power rating or control method, the test engine is run at a fixed
value of corrected turbine inlet temperature, while other
parameters (e.g. power, heat input, heat rate, exhaust gas
temperature, etc.) must lie within specified limits.
The specified limits used as acceptance criteria is based on
the gas turbine manufacturer equipment knowledge. 101325
= ×
D. Other Tests
As a follow-on from the performance test, other tests are (5)
×
performed to ensure the integrity of the engine such as a 288.15
borescope inspection of the engine to determine the internal
conditions of the gas path components (e.g. compressor blades,
combustor cans/burners, turbine blades, etc.), determination of
the temperature profile of cooled turbine blades using infra-red where & are the compressor inlet temperature and
pyrometry to verify effective turbine blade cooling and detect pressure respectively.
any blocked cooling holes and also determination of the
combustion band dynamics for dry low emission combustors. A benefit of referring the test data to ISO conditions is that
it allows the easy comparison of the performance of engines of
A proof run, which involves a trimmed down performance same rating.
test is performed on any test engine following any remedial
work due to an initial test fail. The nature of the trimmed down Before the test engine performance analysis can be
performance test is subject to the extent of the remedial work performed, the captured test instrument signals would be
effected on the test engine. converted to engineering units i.e. from mV to N/m2, K etc.,
erroneous test data points identified and multiple test scan at
particular stations averaged [6].
III. PERFORMANCE TEST DATA ANALYSIS
In most cases, the test conditions (e.g. pressure, temperature A sample performance analysis of a twin shaft gas turbine
& relative humidity) at the compressor inlet of the gas turbine with power turbine shown in Fig. 3 is presented in this paper.
would be different from ISO reference conditions i.e. ambient
temperature of 288.15K, ambient pressure of 101325 N/m2 and
relative humidity of 60%; therefore, the test data would be
corrected to the ISO reference conditions by applying (1) – (5)
to the test data [3]:
. (K)
288.15
= .× (1)
( / )
101325
= × (2)
Fig. 3. Twin shaft gas turbine configuration with power turbine
1= + ( , ) (9)