Professional Documents
Culture Documents
NECA 200-2016
Standard for Installing and Maintaining
Published by
National Electrical Contractors Association
NECA 200-2016
Standard for
Installing and Maintaining
Temporary
Electric Power at
Construction Sites
An American
National Standard
Published by
National Electrical
Contractors Association
Revision History
NECA 200-2010 originally published 08/2010
NECA 200-2016 revised 04/2016
NOTICE OF COPYRIGHT
This document is copyrighted by NECA
ISBN: 978-1-944148-10-2
©2016. Reproduction of these documents either in hard copy or soft (including posting on the web) is
prohibited without copyright permission. For copyright permission to reproduce portions of this document,
please contact NECA Standards & Safety at (301) 215-4549, or send a fax to (301) 215-4500.
OR
Foreword...............................................................................................................................................v
1. Scope............................................................................................................................................... 1
1.1 Products and Applications Included................................................................................................................1
1.2 Products and Applications Excluded...............................................................................................................1
1.3 Regulatory and Other Requirements...............................................................................................................1
2. Responsibilities................................................................................................................................ 2
2.1 Design, Permits, and Approvals........................................................................................................................2
2.2 Install and Maintain..........................................................................................................................................2
4. Load Estimate................................................................................................................................... 6
4.1 Load Survey.......................................................................................................................................................6
4.2 Load Estimate....................................................................................................................................................6
4.3 Spare Capacity...................................................................................................................................................6
iii n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
9. Wiring Methods............................................................................................................................. 14
9.1 Identification of Branch Circuit and Feeder Conductors.............................................................................14
9.2 Branch Circuits................................................................................................................................................14
9.3 Raceway Systems.............................................................................................................................................14
9.4 Flexible Cords and Cables...............................................................................................................................14
9.5 Underground Conductors..............................................................................................................................14
9.6 Overhead Conductors.....................................................................................................................................14
Annex A: OSHA 29 CFR 1926.56 Minimum Light Levels for Construction Work.............................. 20
n iv
(This foreword is not a part of the standard)
1. Scope
Foreword
National Electrical Installation Standards® are Standard for Electrical Safety in the Workplace for
designed to improve communication among complete requirements related to working safely with
specifiers, purchasers, and suppliers of electrical electricity.
construction services. They define a minimum
baseline of quality and workmanship for installing Suggestions for revisions and improvements to this
electrical products and systems. NEIS® are intended standard are welcome.They should be addressed to:
to be referenced in contract documents for electrical
NECA Standards & Safety
construction projects. The following language is
3 Bethesda Metro Center, Suite 1100
recommended:
Bethesda, MD 20814
Temporary electric power installations at (301) 215-4521
construction sites shall be installed and (301) 215-4500 Fax
maintained in accordance with NECA 200- neis@necanet.org
2016, Standard for Installing and Maintaining www.neca-neis.org
Temporary Electric Power at Construction Sites
To purchase National Electrical Installation
(ANSI).
Standards, contact the NECA Order Desk at (301)
Use of NEIS is voluntary, and the National Electrical 215-4504 tel, (301) 215-4500 fax or orderdesk@
Contractors Association assumes no obligation necanet.org. NEIS can also be purchased in pdf
or liability to users of this publication. Existence download format from www.neca-neis.org/store.
of a standard shall not preclude any member or
Copyright©2016, National Electrical Contractors
nonmember of NECA from specifying or using
Association. All rights reserved. Unauthorized
alternate construction methods permitted by
reproduction prohibited.
applicable regulations.
The installation and maintenance practices
National Electrical Installation Standards, NEIS, and
recommended by this publication are intended to the NEIS logo are registered trademarks of the National
comply with the edition of the National Electrical Electrical Contractors Association. National Electrical
Code (NEC) in effect at the time of publication. It is Code and NEC are registered trademarks of the National
the responsibility of users of this standard to comply Fire Protection Association, Quincy, Massachusetts.
with state and local electrical codes when installing
electrical products and systems. All photos are courtesy James T. Dollard unless otherwise
noted.
Electrical safety-related work practices are beyond
the scope of this document. Electrical safety in
the workplace requirements found in NFPA 70E
also apply to temporary electrical installations
addressed in this standard. NECA supports safe
work practices in the electrical industry and safety
training for the electrical workforce. See NFPA 70E
v n
<This page intentionally left blank>
1. Scope
1.1 Products and Applications Included • Use of portable generators for temporary
construction power
This standard describes temporary electrical
power and lighting systems at construction sites,
operating at 600 volts or less. It covers the planning, 1.3 Regulatory and Other Requirements
installation, expansion, maintenance, cutover, and a) All information in this publication is intended
removal of the temporary power system. This to conform to the National Electrical Code (ANSI/
standard is intended to ensure a safe, adequate, NFPA standard 70). Installers should always
functional, and reliable temporary electrical power follow the NEC, applicable state and local codes,
system for all trades at construction sites. manufacturers’ instructions, and contract documents
when installing and maintaining temporary power
1.2 Products and Applications Excluded systems at construction sites.
This standard does not cover the following: b) Only qualified persons familiar with the
construction and operation of temporary electrical
• Temporary electrical power installations power systems should perform the work described in
operating at more than 600 volts. this publication.
• Temporary electrical power installations for
c) General requirements for installing electrical
purposes other than construction.
products and systems are described in NECA 1,
Standard Practices for Good Workmanship in Electrical
Construction (ANSI). Other National Electrical
Installation Standards provide additional guidance
for installing particular types of electrical products
and systems. A complete list of NEIS is provided in
Annex B.
1 n
1.
2. Scope
Responsibilities
2.1 Design, Permits, and Approvals 2.2.1 Moves, adds, changes, and repairs
When the temporary construction power system is The electrical contractor will be reimbursed in
not designed by the engineer of record, the electrical accordance with the contract documents for moves,
contactor shall design the system, submit necessary additions, changes (MAC), and repairs required
documentation, and obtain necessary permits from during construction that were not part of the original
the local authority having jurisdiction (AHJ) and the contract documents, or the approved temporary
serving electric utility. construction power distribution system and could
not have been reasonably anticipated.
The electrical contractor is not responsible
for obtaining property surveys, right-of-ways, 2.2.2 Outages
easements, environmental permits, or other similar
requirements. The electrical contractor is not responsible for the
effects of power outages caused by others, or by
external factors beyond its control that could not be
2.2 Install and Maintain
reasonably anticipated.
Install and maintain the temporary construction
power distribution system throughout the period of 2.2.3 Equipment owned and operated by others
construction and remove it at the end of the project.
The electrical contractor is not responsible for the
The exact scope and responsibilities are governed by
installation, maintenance, repair, or removal of
the contract documents, but generally include the
equipment owned and operated by others. This
following:
includes, but is not limited to, portable power tools,
• Moves, adds, changes, and repairs. extension cords, power distribution boxes, and task
lighting. Unless otherwise required by the contract
• Outages. documents, equipment owned and used by others
at the construction site is the responsibility of those
• Equipment owned and operated by others. who own and use it.
n 2
1. Planning
3. Scope the Installation
3.1 Project Plan and Schedule plan showing property boundaries and planned
construction areas, as well as the planned location
Install temporary construction power in accordance
and/or routing of the following that may affect
with the overall project plan and schedule. Work
the installation of the temporary electric power
with the party responsible for overall project
distribution system:
coordination to ensure that temporary power is
available when needed to support construction (a) Access roads and temporary parking.
operations. Identify the following project milestones:
(b) Other temporary and permanent utility
(a) When temporary power must be available at services.
the construction site. (c) Existing and planned underground tanks and
(b) When the temporary power supply needs to structures.
be increased, modified, or extended to meet (d) Fixed and movable construction equipment
the needs of specific construction operations. and structures.
(c) When the temporary power must be (e) Material delivery and storage areas.
transferred (cutover) to the permanent
building distribution system. (f) Construction offices and facilities.
(d) When all or part of the temporary (g) Other structures or areas that will conflict
construction power distribution system is to with or impact the layout, installation, or
be removed. maintenance of the temporary construction
power distribution system.
(e) Other milestones during construction that
require a change, expansion, or removal (h) Floor-to-ceiling walls and other construction
of the temporary construction power features that may hinder construction or the
distribution system. removal of temporary wiring.
(i) The extent and classification of all areas
3.2 Construction Phasing Requirements on the construction site that are or will be
When planning the temporary power installation, hazardous (classified) locations due to the
consider construction phasing requirements to ensure properties of the flammable vapors, liquids,
adequate, convenient, and serviceable power supply or gases, or the combustible dusts or fibers
throughout construction. The temporary power that may be present, and the likelihood that
distribution system should be laid out to minimize a flammable or combustible concentration or
disruption and rework of the temporary power quantity will be present during construction.
distribution system during the period of construction. (j) Location of permanent electrical service.
When different areas of the construction site will
3.3 Site Plan change their uses over the course of construction,
Work with the party responsible for the overall develop a series of site plans so that temporary
project coordination to develop a construction site construction power can be coordinated with the
3 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
planned site development. Site plans should be (b) Schedule for providing the needed temporary
keyed to milestones in the project schedule. electrical power.
(c) Preparatory work required at the
3.4 Coordination With Other Trades construction site prior to utility construction
Notify other trades of the planned temporary electrical or energizing the temporary electrical
service as soon as possible after receiving notice to service.
proceed (NTP) with construction. Request information (d) Cost to provide temporary electrical power
on any special electrical requirements or coordination including aid to construction and any
needs. Special electrical requirements include the other charges related to the installation,
testing of installed equipment, such as pumps, maintenance, cutover to permanent service,
compressors, chillers, elevators, and other equipment and removal of temporary service.
using the temporary electrical power distribution
system. Special requirements may also include large (e) Rate schedule for temporary service.
loads such as electric cranes, electric heat and branch (f) Required service contracts, easements, and
circuits at other than 125-volts, 15 and 20-amps. other documents that need to be drafted,
reviewed, and/or executed prior to start
3.5 Utility Coordination of utility construction or energizing the
temporary electrical service.
3.5.1 Utility contact
(g) Available symmetrical short-circuit current
Where temporary construction power will be with X/R ratio or equivalent information
supplied totally or partially from the serving electric at the point of connection to temporary
utility, contact the utility to determine the following: electrical service.
n 4
Standard for Installing and Maintaining Temporary Electric Power at Construction Sites NECA 200
throughout construction. Include the following the latest revision available at the project site.
information on these drawings: Maintain all previous revisions on file with other
project documentation for reference.
(a) One-line diagram of temporary power
distribution system. 3.6.5 Document distribution
(b) Location and configuration of service Distribute the latest revision of temporary
grounding electrode system. construction power system drawings as follows:
(c) Available short-circuit current obtained from
(a) Provide one set to the party responsible for
the serving utility in 3.5.1.
overall project coordination.
(d) Rating, type, size, configuration, and
(b) Provide one set to each trade contractor that
insulation of all conductors and/or cables.
requests them.
(e) Protective device types, with continuous
(c) Post one set in the electrical contractor’s field
(overcurrent) ratings and interrupting rating.
office.
(f) Location, type, arrangement, and ratings
(d) Where the arrangement of the temporary
of switchboards, panelboards, disconnect
distribution system is not obvious, post one
switches, motor starters, and other electrical
set of record drawings in a weatherproof
equipment.
display at the temporary service location.
(g) Locations, configurations, and ratings of
receptacle outlets serving cord- and plug-
connected equipment.
(h) Temporary lighting system luminaires and/
or lampholders, lamp types, locations,
supports, and controls.
(i) Electrical equipment installation and
physical protection details.
(j) Notes and legend as required.
3.6.2 Submission
5 n
1. Load
4. ScopeEstimate
n 6
1. Power
5. Scope Source Selection
7 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
temporary feed from the existing switchgear bus using 5.2.4 Selective Coordination
a listed bus tap kit. Verify acceptability of this use with
the applicable authority having jurisdiction prior to When temporary power is supplied from an essential
installation. A temporary fused safety switch can then system in a health care facility or another system
be installed on or adjacent to the switchgear. Install that is selectively coordinated, the overcurrent
the safety switch and bus tap as follows: devices for the temporary system must be selectively
coordinated with all upstream overcurrent devices.
(1) Install a heavy-duty fused safety switch
with equipment grounding terminal. The 5.3 Supply From Another Building
safety switch should have the appropriate
voltage class, current and horsepower rating, When planning to supply temporary construction
number of poles, and enclosure suitable power from another building that is either not
for the installation. Insert overcurrent owned by the owner of the construction project, or
protection in ungrounded circuit conductors that requires the temporary service to cross a public
as required. Provide a solid neutral for thoroughfare, do the following:
systems requiring a neutral.
(a) Obtain permission from the serving utility,
(2) Locate the safety switch as near as practical to where necessary.
the switchgear and install tap conductors in a
(b) Obtain permission from the local authority
raceway suitable for the application. Ensure
having jurisdiction (AHJ), if required.
that the safety switch is readily accessible and
working space is maintained around it. (c) Verify that the other building’s distribution
system has sufficient spare electrical capacity,
(3) Tap the bus using a listed tap kit. Maintain
as described in 5.2.2.
phase-to-phase and phase-to-ground
clearances as required at the tap point inside (d) Provide coordinated GFPE in accordance
the switchgear. with 5.2.4, where applicable.
(4) Tap conductor circuits must meet the
5.4 On-Site Generation
applicable requirements in NEC Section
240.21 and include an equipment grounding Size and install any fixed or vehicle-mounted motor-
conductor(s) sized in accordance with 250.122. generator sets in accordance with NECA/EGSA
404 and supplier/manufacturer recommendations.
5.2.3 Ground-fault protection of equipment Portable generator use is beyond the scope of this
installation standard.
Provide ground-fault protection of equipment (GFPE)
when a temporary construction power feeder is supplied
from a bus where all feeders have GFPE. This provides 5.5 Multiple Power Sources
selectivity in the event of an arcing ground fault on the Where multiple power sources are used to provide
construction feeder. Coordinate the ground-fault relay temporary construction power, never interconnect
(GFR) with the main GFPE protecting the bus. these sources unless the temporary power system is
designed to be supplied by multiple interconnected
When a temporary construction power feeder is power sources. If multiple power sources are
supplied from a bus in a health care facility equipped intended to be interconnected and operated in
with GFPE, the temporary construction power feeder parallel, ensure that all sources are synchronized
must have GFPE set to coordinate with the main and all safety precautions are followed before
GFPE protecting the bus in accordance with NEC interconnecting sources. Article 705 of the NEC
Sections 517.17(B) and 517.17(C). Performance test provides the requirements for interconnected electric
the construction feeder GFPE device as required by power production sources.
NEC Section 517.17(D).
n 8
6. Temporary
1. Scope Construction Power
System
9 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
n 10
1. Grounding
7. Scope and Bonding
11 n
8. Equipment
1. Scope Installation and
Protection
n 12
Standard for Installing and Maintaining Temporary Electric Power at Construction Sites NECA 200
13 n
1.
9. Scope
Wiring Methods
n 14
10.
1. Scope
Receptacle Outlets
15 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
n 16
1. Scope
11. Temporary Lighting
11.2.3 Types
17 n
1. Scope
12. System Maintenance
n 18
1. Scope
13. System Removal
19 n
(This annex is not part of the standard)
1. Scope
Annex A: OSHA 29 CFR 1926.56
Minimum Light Levels for
Construction Work
(a) General. Construction areas, ramps, (b) Other areas. For areas or operations not
runways, corridors, offices, shops, and storage covered above, refer to the American National
areas shall be lighted to no less that the minimum Standard A11.1-1965 (R1970), Practice for Industrial
illumination intensities listed in Table D-3 while any Lighting, for recommended values of illumination.
work is in progress:
n 20
(This annex is not part of the standard)
1. Scope
Annex B: Reference Standards
This publication, when used in conjunction with the National Electrical Code and product manufacturers’
literature, provides sufficient information to install and maintain temporary power systems at construction
sites. The following publications may also provide useful information:
21 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
Safety and Health Regulations for Construction – Electrical, 29 Code of Federal Regulations (CFR) Part 1926,
Subpart K
n 22
Standard for Installing and Maintaining Temporary Electric Power at Construction Sites NECA 200
NECA 303-2005, Standard for Installing Closed-Circuit Television (CCTV) Systems (ANSI)
NECA 305-2010, Standard for Fire Alarm System Job Practices (ANSI)
NECA 331-2009, Standard for Building and Service Entrance Grounding and Bonding
NECA 400-2007, Standard for Installing and Maintaining Switchboards (ANSI)
NECA 402-2014, Standard for Installing and Maintaining Motor Control Centers (ANSI)
NECA/EGSA 404-2014, Standard for Installing Generator Sets (ANSI)
NECA 406-2014, Standard for Installing Residential Generator Sets (ANSI)
NECA 407-2015, Standard for Installing and Maintaining Panelboards (ANSI)
NECA 408-2015, Standard for Installing and Maintaining Busways (ANSI)
NECA 409-2015, Standard for Installing and Maintaining Dry-Type Transformers (ANSI)
NECA 410-2013, Standard for Installing and Maintaining Liquid-Filled Transformers (ANSI)
NECA 411-2014, Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS) (ANSI)
NECA 412-2012, Standard for Installing and Maintaining Photovoltaic (PV) Power Systems (ANSI)
NECA 413-2012, Standard for Installing and Maintaining Electric Vehicle Supply Equipment (ANSI)
NECA 420-2014, Standard for Fuse Applications (ANSI)
NECA 430-2006, Standard for Installing Medium-Voltage Metal-Clad Switchgear (ANSI)
NECA/IESNA 500-2006, Standard for Installing Indoor Commercial Lighting Systems (ANSI)
NECA/IESNA 501-2006, Standard for Installing Exterior Lighting Systems (ANSI)
NECA/IESNA 502-2006, Standard for Installing Industrial Lighting Systems (ANSI)
NECA 503-2005, Standard for Installing Fiber Optic Lighting Systems
NECA/BICSI 568-2006, Standard for Installing Commercial Building Telecommunications Cabling (ANSI)
NECA/NCSCB 600-2014, Standard for Installing and Maintaining Medium-Voltage Cable (ANSI)
NECA/NEMA 605-2005, Recommended Practice for Installing Underground Nonmetallic Utility Duct (ANSI)
NECA/BICSI 607-2011, Standard for Telecommunications Bonding and Grounding Planning and Installation
Methods for Commercial Buildings (ANSI)
NECA 700-2010, Standard for Installing Overcurrent Protection to Achieve Selective Coordination (ANSI)
NECA 701-2013, Standard for Energy Management, Demand Response and Energy Solutions (ANSI)
23 n
<This page intentionally left blank>
<This page intentionally left blank>
<This page intentionally left blank>
National Electrical Contractors Association
3 Bethesda Metro Center, Suite 1100
Bethesda, Maryland 20785
301-657-3110 • 301-214-4500 fax
www.necanet.org
Index # NECA 200-16 | 5C-6/16