You are on page 1of 34

®

NECA 200-2016
Standard for Installing and Maintaining

Temporary Electric Power


at Construction Sites

AN AM ERIC AN N ATI O NA L S TA NDA RD

Published by
National Electrical Contractors Association
NECA 200-2016
Standard for
Installing and Maintaining

Temporary
Electric Power at
Construction Sites
An American
National Standard

Published by
National Electrical
Contractors Association
Revision History
NECA 200-2010 originally published 08/2010
NECA 200-2016 revised 04/2016

NOTICE OF COPYRIGHT
This document is copyrighted by NECA

ISBN: 978-1-944148-10-2

©2016. Reproduction of these documents either in hard copy or soft (including posting on the web) is
prohibited without copyright permission. For copyright permission to reproduce portions of this document,
please contact NECA Standards & Safety at (301) 215-4549, or send a fax to (301) 215-4500.

OR

National Electrical Contractors Association


3 Bethesda Metro Center, Suite 1100
Bethesda, Maryland 20814
(301) 657-3110
1. Scope
Table of Contents

Foreword...............................................................................................................................................v

1. Scope............................................................................................................................................... 1
1.1 Products and Applications Included................................................................................................................1
1.2 Products and Applications Excluded...............................................................................................................1
1.3 Regulatory and Other Requirements...............................................................................................................1

2. Responsibilities................................................................................................................................ 2
2.1 Design, Permits, and Approvals........................................................................................................................2
2.2 Install and Maintain..........................................................................................................................................2

3. Planning the Installation.................................................................................................................. 3


3.1 Project Plan and Schedule................................................................................................................................3
3.2 Construction Phasing Requirements...............................................................................................................3
3.3 Site Plan.............................................................................................................................................................3
3.4 Coordination With Other Trades.....................................................................................................................4
3.5 Utility Coordination.........................................................................................................................................4
3.6 System Documentation.....................................................................................................................................4

4. Load Estimate................................................................................................................................... 6
4.1 Load Survey.......................................................................................................................................................6
4.2 Load Estimate....................................................................................................................................................6
4.3 Spare Capacity...................................................................................................................................................6

5. Power Source Selection................................................................................................................... 7


5.1 Utility Supply.....................................................................................................................................................7
5.2 Existing Building Distribution System.............................................................................................................7
5.3 Supply From Another Building........................................................................................................................8
5.4 On-Site Generation...........................................................................................................................................8
5.5 Multiple Power Sources....................................................................................................................................8

6. Temporary Construction Power System............................................................................................ 9


6.1 System Layout....................................................................................................................................................9
6.2 Temporary Service Equipment.........................................................................................................................9
6.3 Temporary Downstream Distribution Equipment.........................................................................................9
6.4 Coordinate With Construction Plan................................................................................................................9
6.5 Voltage Drop Considerations...........................................................................................................................9
6.6 Sufficient Number of Outlets...........................................................................................................................9
6.7 Accessibility and Protection of Outlets..........................................................................................................10

iii n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites

7. Grounding and Bonding................................................................................................................ 11


7.1 System Grounding...........................................................................................................................................11
7.2 Grounding Electrodes and Grounding Electrode Conductors.....................................................................11
7.3 Equipment Grounding Conductors...............................................................................................................11
7.4 Bonding Jumpers.............................................................................................................................................11
7.5 Assured Equipment Grounding Conductor Program..................................................................................11

8. Equipment Installation and Protection........................................................................................... 12


8.1 Equipment Physical Protection......................................................................................................................12
8.2 Hazardous (Classified) Locations...................................................................................................................12
8.3 Equipment Support.........................................................................................................................................12
8.4 Equipment Accessibility and Working Space.................................................................................................13
8.5 Equipment Illumination.................................................................................................................................13
8.6 Equipment Marking and Labeling.................................................................................................................13

9. Wiring Methods............................................................................................................................. 14
9.1 Identification of Branch Circuit and Feeder Conductors.............................................................................14
9.2 Branch Circuits................................................................................................................................................14
9.3 Raceway Systems.............................................................................................................................................14
9.4 Flexible Cords and Cables...............................................................................................................................14
9.5 Underground Conductors..............................................................................................................................14
9.6 Overhead Conductors.....................................................................................................................................14

10. Receptacle Outlets....................................................................................................................... 15


10.1 Receptacle Configurations..............................................................................................................................15
10.2 Receptacle Outlets...........................................................................................................................................15
10.3 Enclosures and Covers....................................................................................................................................15
10.4 Ground-Fault Circuit-Interrupter (GFCI) Protection for Personnel..........................................................15
10.5 Receptacle Grounding.....................................................................................................................................16

11. Temporary Lighting...................................................................................................................... 17


11.1 System Layout..................................................................................................................................................17
11.2 Installation.......................................................................................................................................................17
11.3 Cutover To Permanent Lighting.....................................................................................................................17

12. System Maintenance.................................................................................................................... 18

13. System Removal........................................................................................................................... 19


13.1 System Cutover................................................................................................................................................19
13.2 Removing Temporary System.........................................................................................................................19
13.3 Penetrations.....................................................................................................................................................19

Annex A: OSHA 29 CFR 1926.56 Minimum Light Levels for Construction Work.............................. 20

Annex B: Reference Standards........................................................................................................... 21

n iv
(This foreword is not a part of the standard)

1. Scope
Foreword

National Electrical Installation Standards® are Standard for Electrical Safety in the Workplace for
designed to improve communication among complete requirements related to working safely with
specifiers, purchasers, and suppliers of electrical electricity.
construction services. They define a minimum
baseline of quality and workmanship for installing Suggestions for revisions and improvements to this
electrical products and systems. NEIS® are intended standard are welcome.They should be addressed to:
to be referenced in contract documents for electrical
NECA Standards & Safety
construction projects. The following language is
3 Bethesda Metro Center, Suite 1100
recommended:
Bethesda, MD 20814
Temporary electric power installations at (301) 215-4521
construction sites shall be installed and (301) 215-4500 Fax
maintained in accordance with NECA 200- neis@necanet.org
2016, Standard for Installing and Maintaining www.neca-neis.org
Temporary Electric Power at Construction Sites
To purchase National Electrical Installation
(ANSI).
Standards, contact the NECA Order Desk at (301)
Use of NEIS is voluntary, and the National Electrical 215-4504 tel, (301) 215-4500 fax or orderdesk@
Contractors Association assumes no obligation necanet.org. NEIS can also be purchased in pdf
or liability to users of this publication. Existence download format from www.neca-neis.org/store.
of a standard shall not preclude any member or
Copyright©2016, National Electrical Contractors
nonmember of NECA from specifying or using
Association. All rights reserved. Unauthorized
alternate construction methods permitted by
reproduction prohibited.
applicable regulations.

The installation and maintenance practices
National Electrical Installation Standards, NEIS, and
recommended by this publication are intended to the NEIS logo are registered trademarks of the National
comply with the edition of the National Electrical Electrical Contractors Association. National Electrical
Code (NEC) in effect at the time of publication. It is Code and NEC are registered trademarks of the National
the responsibility of users of this standard to comply Fire Protection Association, Quincy, Massachusetts.
with state and local electrical codes when installing
electrical products and systems. All photos are courtesy James T. Dollard unless otherwise
noted.
Electrical safety-related work practices are beyond
the scope of this document. Electrical safety in
the workplace requirements found in NFPA 70E
also apply to temporary electrical installations
addressed in this standard. NECA supports safe
work practices in the electrical industry and safety
training for the electrical workforce. See NFPA 70E

v n
<This page intentionally left blank>
1. Scope

1.1 Products and Applications Included • Use of portable generators for temporary
construction power
This standard describes temporary electrical
power and lighting systems at construction sites,
operating at 600 volts or less. It covers the planning, 1.3 Regulatory and Other Requirements
installation, expansion, maintenance, cutover, and a) All information in this publication is intended
removal of the temporary power system. This to conform to the National Electrical Code (ANSI/
standard is intended to ensure a safe, adequate, NFPA standard 70). Installers should always
functional, and reliable temporary electrical power follow the NEC, applicable state and local codes,
system for all trades at construction sites. manufacturers’ instructions, and contract documents
when installing and maintaining temporary power
1.2 Products and Applications Excluded systems at construction sites.
This standard does not cover the following: b) Only qualified persons familiar with the
construction and operation of temporary electrical
• Temporary electrical power installations power systems should perform the work described in
operating at more than 600 volts. this publication.
• Temporary electrical power installations for
c) General requirements for installing electrical
purposes other than construction.
products and systems are described in NECA 1,
Standard Practices for Good Workmanship in Electrical
Construction (ANSI). Other National Electrical
Installation Standards provide additional guidance
for installing particular types of electrical products
and systems. A complete list of NEIS is provided in
Annex B.

Figure 1. High-rise construction and other


construction sites site utilize temporary constriction
power and lighting.

1 n
1.
2. Scope
Responsibilities

2.1 Design, Permits, and Approvals 2.2.1 Moves, adds, changes, and repairs
When the temporary construction power system is The electrical contractor will be reimbursed in
not designed by the engineer of record, the electrical accordance with the contract documents for moves,
contactor shall design the system, submit necessary additions, changes (MAC), and repairs required
documentation, and obtain necessary permits from during construction that were not part of the original
the local authority having jurisdiction (AHJ) and the contract documents, or the approved temporary
serving electric utility. construction power distribution system and could
not have been reasonably anticipated.
The electrical contractor is not responsible
for obtaining property surveys, right-of-ways, 2.2.2 Outages
easements, environmental permits, or other similar
requirements. The electrical contractor is not responsible for the
effects of power outages caused by others, or by
external factors beyond its control that could not be
2.2 Install and Maintain
reasonably anticipated.
Install and maintain the temporary construction
power distribution system throughout the period of 2.2.3 Equipment owned and operated by others
construction and remove it at the end of the project.
The electrical contractor is not responsible for the
The exact scope and responsibilities are governed by
installation, maintenance, repair, or removal of
the contract documents, but generally include the
equipment owned and operated by others. This
following:
includes, but is not limited to, portable power tools,
• Moves, adds, changes, and repairs. extension cords, power distribution boxes, and task
lighting. Unless otherwise required by the contract
• Outages. documents, equipment owned and used by others
at the construction site is the responsibility of those
• Equipment owned and operated by others. who own and use it.

n 2
1. Planning
3. Scope the Installation

3.1 Project Plan and Schedule plan showing property boundaries and planned
construction areas, as well as the planned location
Install temporary construction power in accordance
and/or routing of the following that may affect
with the overall project plan and schedule. Work
the installation of the temporary electric power
with the party responsible for overall project
distribution system:
coordination to ensure that temporary power is
available when needed to support construction (a) Access roads and temporary parking.
operations. Identify the following project milestones:
(b) Other temporary and permanent utility
(a) When temporary power must be available at services.
the construction site. (c) Existing and planned underground tanks and
(b) When the temporary power supply needs to structures.
be increased, modified, or extended to meet (d) Fixed and movable construction equipment
the needs of specific construction operations. and structures.
(c) When the temporary power must be (e) Material delivery and storage areas.
transferred (cutover) to the permanent
building distribution system. (f) Construction offices and facilities.
(d) When all or part of the temporary (g) Other structures or areas that will conflict
construction power distribution system is to with or impact the layout, installation, or
be removed. maintenance of the temporary construction
power distribution system.
(e) Other milestones during construction that
require a change, expansion, or removal (h) Floor-to-ceiling walls and other construction
of the temporary construction power features that may hinder construction or the
distribution system. removal of temporary wiring.
(i) The extent and classification of all areas
3.2 Construction Phasing Requirements on the construction site that are or will be
When planning the temporary power installation, hazardous (classified) locations due to the
consider construction phasing requirements to ensure properties of the flammable vapors, liquids,
adequate, convenient, and serviceable power supply or gases, or the combustible dusts or fibers
throughout construction. The temporary power that may be present, and the likelihood that
distribution system should be laid out to minimize a flammable or combustible concentration or
disruption and rework of the temporary power quantity will be present during construction.
distribution system during the period of construction. (j) Location of permanent electrical service.
When different areas of the construction site will
3.3 Site Plan change their uses over the course of construction,
Work with the party responsible for the overall develop a series of site plans so that temporary
project coordination to develop a construction site construction power can be coordinated with the

3 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites

planned site development. Site plans should be (b) Schedule for providing the needed temporary
keyed to milestones in the project schedule. electrical power.
(c) Preparatory work required at the
3.4 Coordination With Other Trades construction site prior to utility construction
Notify other trades of the planned temporary electrical or energizing the temporary electrical
service as soon as possible after receiving notice to service.
proceed (NTP) with construction. Request information (d) Cost to provide temporary electrical power
on any special electrical requirements or coordination including aid to construction and any
needs. Special electrical requirements include the other charges related to the installation,
testing of installed equipment, such as pumps, maintenance, cutover to permanent service,
compressors, chillers, elevators, and other equipment and removal of temporary service.
using the temporary electrical power distribution
system. Special requirements may also include large (e) Rate schedule for temporary service.
loads such as electric cranes, electric heat and branch (f) Required service contracts, easements, and
circuits at other than 125-volts, 15 and 20-amps. other documents that need to be drafted,
reviewed, and/or executed prior to start
3.5 Utility Coordination of utility construction or energizing the
temporary electrical service.
3.5.1 Utility contact
(g) Available symmetrical short-circuit current
Where temporary construction power will be with X/R ratio or equivalent information
supplied totally or partially from the serving electric at the point of connection to temporary
utility, contact the utility to determine the following: electrical service.

(a) The utility’s ability to provide temporary 3.5.2 Service Point


electrical power.
Identify the location on site where temporary
electrical service will be provided, and the routing
of overhead or underground utility conductors from
the property line to the service point. Coordinate
the temporary electrical service with the permanent
electrical service where possible. Discuss any other
special requirements that the serving utility has that
could affect the project. This may include but not
be limited to local requirements that could impact;
burial depths, installation of conductors and cables
to and from the utility transformer or supply to the
service point by the contractor, and so forth. Many
utility companies have published requirements for
electric service (temporary and permanent) that can
be a valuable reference.

3.6 System Documentation


3.6.1 Preparation
Figure 2. Temporary construction power planning
and management is essential during all phases of Prepare a set of record drawings for the temporary
construction projects. power system. Maintain and update these drawings

n 4
Standard for Installing and Maintaining Temporary Electric Power at Construction Sites NECA 200

throughout construction. Include the following the latest revision available at the project site.
information on these drawings: Maintain all previous revisions on file with other
project documentation for reference.
(a) One-line diagram of temporary power
distribution system. 3.6.5 Document distribution
(b) Location and configuration of service Distribute the latest revision of temporary
grounding electrode system. construction power system drawings as follows:
(c) Available short-circuit current obtained from
(a) Provide one set to the party responsible for
the serving utility in 3.5.1.
overall project coordination.
(d) Rating, type, size, configuration, and
(b) Provide one set to each trade contractor that
insulation of all conductors and/or cables.
requests them.
(e) Protective device types, with continuous
(c) Post one set in the electrical contractor’s field
(overcurrent) ratings and interrupting rating.
office.
(f) Location, type, arrangement, and ratings
(d) Where the arrangement of the temporary
of switchboards, panelboards, disconnect
distribution system is not obvious, post one
switches, motor starters, and other electrical
set of record drawings in a weatherproof
equipment.
display at the temporary service location.
(g) Locations, configurations, and ratings of
receptacle outlets serving cord- and plug-
connected equipment.
(h) Temporary lighting system luminaires and/
or lampholders, lamp types, locations,
supports, and controls.
(i) Electrical equipment installation and
physical protection details.
(j) Notes and legend as required.

3.6.2 Submission

Submit these record drawings to the party


responsible for overall project coordination, the
serving utility, and/or the local authority having
jurisdiction (AHJ) for review and/or approval if
required.

3.6.3 Record documents

Maintain a permanent updated set of record


drawings showing the temporary power system
throughout the period of construction.

3.6.4 Document control

Mark all temporary construction power system


drawings with the date and revision number. Keep

5 n
1. Load
4. ScopeEstimate

4.1 Load Survey (d) Receptacle configuration required by cord-


and plug-connected equipment.
Perform a load survey to identify and estimate
anticipated loads on the temporary power (e) Special power supply requirements (e.g.,
distribution system including temporary lighting power quality and reliability).
based on available information. Gather the following (f) Required system specifications in contract
information for significant loads: drawings.
(a) Nameplate amperage and/or power
consumption in volt-amperes (VA), watts 4.2 Load Estimate
(W) and power factor (PF), or horsepower Estimate the total load to be served by the temporary
(hp). power distribution system based on the load survey
(b) Operating voltage. and experience with similar installations.

(c) Number of phases.


4.3 Spare Capacity
Consideration should be given for spare capacity
based on anticipated changes during construction,
uncertainty about planned construction means and
methods, and experience with similar installations.

Figure 3. Typical pole-mounted outdoor


transformer(s) are often used for supplying temporary
construction power and lighting.

n 6
1. Power
5. Scope Source Selection

5.1 Utility Supply (2) If not included in this measurement, estimate


the larger of either the heating or cooling
equipment load and other loads that may be
Obtain information from the serving utility as periodic in nature due to seasonal or similar
described in 3.5.1. conditions. Add this load to the measured load.

(3) Add any other existing or anticipated loads


5.2 Existing Building Distribution System that may not have been included in the
When performing work such as moves, additions, measurement.
changes, repairs, and maintenance in existing
buildings and structures, it is often practical to use the (c) The sum of the maximum demand of the
building’s distribution system to provide temporary building service or feeder load plus 125 percent
construction power. If the owner grants permission of the estimated construction load should not
to use the permanent power distribution system, the exceed the capacity of the service or feeder.
following should be verified:
5.2.2 Supply methods
5.2.1 Capacity verification
(a) Spare Space In Existing Equipment
Verify that the building distribution system has
sufficient spare electrical capacity to provide If a spare circuit breaker or fused switch of correct rating
temporary construction power based on the load is not available in the existing equipment , and there is
estimate. Verify the capacity of the existing building spare space available, obtain a circuit breaker or fused
distribution system as follows: switch manufactured and listed for use in the equipment.
Install this in accordance with the manufacturer’s
(a) Use actual demand data for a one-year instructions. Select the fuse rating, or set adjustable-trip
period to determine the maximum load on circuit breaker trip setting, as required.
the existing service.

(b) When demand data is not available (b) Existing Busway


for a one-year period, service, or when If an existing plug-in busway is available, install a
construction power will be added to the load fused disconnect switch manufactured and listed
on an existing feeder, estimate the load on for use with the busway. For feeder busway, install
the existing service or feeder as follows: fittings manufactured and listed for use with existing
feeder busway to permit the installation of a fused
(1) Place a recording ammeter or power meter disconnect switch or bus tap fitting. Fuse as required.
on the highest loaded phase of the service or
feeder and measure the load for thirty days.
This is the phase that has the highest load (c) Bus Tap
when the recording ammeter or power meter Where space is not available in existing switchgear
is installed. for an additional circuit breaker or fused switch, tap a

7 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites

temporary feed from the existing switchgear bus using 5.2.4 Selective Coordination
a listed bus tap kit. Verify acceptability of this use with
the applicable authority having jurisdiction prior to When temporary power is supplied from an essential
installation. A temporary fused safety switch can then system in a health care facility or another system
be installed on or adjacent to the switchgear. Install that is selectively coordinated, the overcurrent
the safety switch and bus tap as follows: devices for the temporary system must be selectively
coordinated with all upstream overcurrent devices.
(1) Install a heavy-duty fused safety switch
with equipment grounding terminal. The 5.3 Supply From Another Building
safety switch should have the appropriate
voltage class, current and horsepower rating, When planning to supply temporary construction
number of poles, and enclosure suitable power from another building that is either not
for the installation. Insert overcurrent owned by the owner of the construction project, or
protection in ungrounded circuit conductors that requires the temporary service to cross a public
as required. Provide a solid neutral for thoroughfare, do the following:
systems requiring a neutral.
(a) Obtain permission from the serving utility,
(2) Locate the safety switch as near as practical to where necessary.
the switchgear and install tap conductors in a
(b) Obtain permission from the local authority
raceway suitable for the application. Ensure
having jurisdiction (AHJ), if required.
that the safety switch is readily accessible and
working space is maintained around it. (c) Verify that the other building’s distribution
system has sufficient spare electrical capacity,
(3) Tap the bus using a listed tap kit. Maintain
as described in 5.2.2.
phase-to-phase and phase-to-ground
clearances as required at the tap point inside (d) Provide coordinated GFPE in accordance
the switchgear. with 5.2.4, where applicable.
(4) Tap conductor circuits must meet the
5.4 On-Site Generation
applicable requirements in NEC Section
240.21 and include an equipment grounding Size and install any fixed or vehicle-mounted motor-
conductor(s) sized in accordance with 250.122. generator sets in accordance with NECA/EGSA
404 and supplier/manufacturer recommendations.
5.2.3 Ground-fault protection of equipment Portable generator use is beyond the scope of this
installation standard.
Provide ground-fault protection of equipment (GFPE)
when a temporary construction power feeder is supplied
from a bus where all feeders have GFPE. This provides 5.5 Multiple Power Sources
selectivity in the event of an arcing ground fault on the Where multiple power sources are used to provide
construction feeder. Coordinate the ground-fault relay temporary construction power, never interconnect
(GFR) with the main GFPE protecting the bus. these sources unless the temporary power system is
designed to be supplied by multiple interconnected
When a temporary construction power feeder is power sources. If multiple power sources are
supplied from a bus in a health care facility equipped intended to be interconnected and operated in
with GFPE, the temporary construction power feeder parallel, ensure that all sources are synchronized
must have GFPE set to coordinate with the main and all safety precautions are followed before
GFPE protecting the bus in accordance with NEC interconnecting sources. Article 705 of the NEC
Sections 517.17(B) and 517.17(C). Performance test provides the requirements for interconnected electric
the construction feeder GFPE device as required by power production sources.
NEC Section 517.17(D).

n 8
6. Temporary
1. Scope Construction Power
System

6.1 System Layout 6.3.2 Local disconnecting means


The temporary construction power distribution Provide a readily accessible disconnecting means for
system should be of radial (star) design unless temporary downstream distribution equipment that
reliability concerns dictate that it be primary simultaneously disconnects all ungrounded feeder
selective, secondary selective, spot network, loop, or conductors. This local disconnecting means should
some other arrangement. be either integral to the temporary distribution
equipment or adjacent to the equipment.
6.2 Temporary Service Equipment
6.2.1 Location 6.4 Coordinate With Construction Plan
Coordinate the installation of temporary
Locate and install temporary service equipment in
downstream distribution equipment with the
accordance with the NEC and any requirements of
construction plan.
the serving utility.

6.2.2 Transfer to permanent service 6.5 Voltage Drop Considerations


As soon as the building’s permanent service is Lay out the temporary construction distribution
installed, energized, tested, and accepted, transfer system to minimize voltage drop. Size feeders and
electric service from the temporary service equipment branch circuits so that the maximum calculated
to the permanent service equipment. Immediately voltage drop on either does not exceed three (3)
after cutover, de-energize and remove the temporary percent and the total voltage drop of both does not
service equipment, luminaires, power receptacles, exceed five (5) percent between the service and
conductors and cables, and other equipment that was outlet, in accordance with NEC recommendations.
part of the temporary construction power system in
accordance with Section 13.2. These recommended voltage drop percentages
are for steady-state operation and do not address
transient conditions such as motor starting. Where
6.3 Temporary Downstream Distribution large motors will be powered from the temporary
Equipment construction distribution system, perform a study
6.3.1 Location to determine the impact of motor inrush on the
distribution system voltage and the ability of motors
Locate temporary downstream distribution equipment to start properly.
at points of concentrated load where the equipment
is separated by distance (e.g., different buildings), 6.6 Sufficient Number of Outlets
physical barriers (e.g., building floors), or for
convenience. Install the temporary downstream Locate temporary construction receptacle outlets to
distribution equipment so that it is readily accessible keep the length of flexible cords required for portable
and ensure that proper working space is maintained tools and task lighting to a reasonable length. This
around it. minimizes congestion on construction sites, reduces

9 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites

tripping hazards, minimizes voltage drop, and


reduces nuisance tripping of ground-fault circuit-
interrupter protection devices.

6.7 Accessibility and Protection of


Outlets
Temporary construction receptacle outlets must be
accessible. Outlets should be reasonably protected
from damage by location, guards, height, or other
means.

Figure 4. Provide reasonable protection for receptacle


outlets. (Courtesy of NECA)

n 10
1. Grounding
7. Scope and Bonding

7.1 System Grounding 7.3 Equipment Grounding Conductors


Verify that each power source is properly grounded. For feeders and branch circuits, install a separate
Refer to the NEC, specifically, Article 250. wire-type equipment grounding conductor in all
raceways. Ensure that all cable assemblies have a
7.2 Grounding Electrodes and Grounding separate wire-type equipment grounding conductor.
Electrode Conductors
7.4 Bonding Jumpers
Where grounding electrodes are required for
temporary services and separately derived systems, Install bonding jumpers where required, to
install them so that they are protected from physical connect all metal equipment, or metal frames that
damage by location and/or physical guards. support and/or enclose electrical equipment, to the
Install the grounding electrode conductor so that equipment grounding system.
connections are accessible. Protect grounding
electrode conductors from physical damage. 7.5 Assured Equipment Grounding
Conductor Program
For receptacles other than 125-volt, single-phase,
15-, 20-, and 30-ampere that are not protected
by ground-fault circuit interrupter protection in
accordance NEC Section 590.6(B)(1), an assured
equipment grounding conductor program in
accordance with NEC Section 590.6(B)(2) shall be
implemented and enforced at the site.

Figure 5. Typical grounding electrode conductor


connectors used for temporary power services or
separately derived systems. (Courtesy of Thomas and
Betts )

11 n
8. Equipment
1. Scope Installation and
Protection

8.1 Equipment Physical Protection 8.1.2 Protection from the elements


8.1.1 Enclosures When possible, locate temporary construction
power equipment where it will be protected from the
All temporary power distribution equipment
elements. If equipment must be installed outdoors
enclosures should be deadfront and completely
in an unprotected area, install equipment that is
enclose the distribution equipment. Install only
suitable for the location and install protective covers
distribution equipment enclosures that are suitable
or canopies over distribution equipment to minimize
for the environment in accordance with NEC
solar heating, exposure to water, and snow/ice
sections 110.21(A) and 110.28. All equipment doors,
accumulation.
screws and so forth must be in place and secure. All
unused openings for cable assemblies and raceways If the operating temperature of the distribution
must be securely covered. equipment exceeds its nameplate rating, derate
or modify the equipment in accordance with the
manufacturer’s recommendations for the higher
operating temperature.

8.1.3 Physical barriers and fencing

Provide physical barriers and fencing around


electrical equipment where required for damage
protection and/or to restrict access. Where possible,
locate distribution equipment to limit access to only
qualified persons.

8.2 Hazardous (Classified) Locations


When possible, avoid installing temporary
construction power equipment in hazardous
(classified) locations. If the temporary power system
must pass through or serve equipment in hazardous
(classified) locations, install it in accordance with the
NEC and applicable Articles in Chapter 5.

8.3 Equipment Support


Securely support distribution equipment to existing
structures, temporary structures or construct a rigid
free-standing support for the equipment. Install
Figure 6. Marking and labeling methods must be distribution equipment in a workmanlike manner so
suitable for the environment. that it is level and plumb.

n 12
Standard for Installing and Maintaining Temporary Electric Power at Construction Sites NECA 200

8.4 Equipment Accessibility and Working


Space
Working space around temporary construction
power distribution equipment should be level and
clear of obstructions. To ensure that the equipment
remains readily accessible and sufficient working
space is maintained throughout the period of
construction, post appropriate signage and conduct
regular inspections. Do not use temporary structures
built to house distribution equipment for material or
tool storage.

8.5 Equipment Illumination


Provide temporary lighting around all distribution
equipment when other lighting is not available, or is
insufficient to light the area around the equipment.

8.6 Equipment Marking and Labeling


Mark or label all switchboards, switchgear and
panelboards as designated on the temporary power
distribution system one-line diagram. Mark or
label all switches, disconnects, circuit breakers, and
other control devices with the purpose, circuit, or
equipment served. A completed directory located
at the panelboard is sufficient for panelboard circuit
breakers. Mark or label each receptacle cover plate
with the panelboard designation and circuit serving
the receptacle. Use a marking or labeling method
that is durable and suitable for the environment.

13 n
1.
9. Scope
Wiring Methods

9.1 Identification of Branch Circuit and 9.3.2 Raceway installation


Feeder Conductors
Install raceways plumb and level. Support them
Identify all ungrounded feeder and branch-circuit securely at regular intervals. Run raceways parallel
conductors by system and phase. See NEC Sections or perpendicular to structural members, walls, and
210.5 and 215.12. Identify grounded conductors ceilings wherever possible. Conduit and tubing
according to NEC Section 200.6. Post the identification bends must not be kinked or flattened.
scheme at all switchboards, switchgear and panelboards.
Where factory assembled cables are used for branch 9.3.3 Boxes and conduit bodies
circuit wiring, identification of conductors is not
Install boxes plumb and level. Support them securely,
required except to comply with NEC requirements.
independently of the raceway system or cable assemblies.
Close all unused openings in boxes/equipment and install
9.2 Branch Circuits covers to provide protection substantially equivalent
9.2.1 General-purpose receptacles and hard- to the wall of the box or equipment.
wired equipment
9.4 Flexible Cords and Cables
Supply general-purpose receptacle outlets and hard-
wired equipment with branch circuits dedicated Install flexible cords and cables to minimize the risk of
to that purpose. Temporary construction lighting damage. Where they may be subject to damage due
circuits must not be supplied by a branch circuit or to their location, relocate the flexible cords and cables
a multi-wire branch circuit that supplies receptacle or provide barriers and guards for protection. Branch
outlets.. Cord- and plug-connected task lighting that circuits and feeders installed using flexible cords and
is connected only when in use may be plugged into cables must not be laid on the floor or ground.
general-purpose receptacles.
9.5 Underground Conductors
9.2.2 Temporary lighting
Mark all underground feeders, and underground
Supply temporary construction lighting luminaires branch circuits operating at more than 120 volts to
and lampholders with branch circuits dedicated to ground with a warning ribbon placed at least 12 inches
this purpose with no other loads connected. Do not above the conductors. Cables used for underground
connect general-purpose receptacle outlets or hard- feeders and branch circuits should be listed for direct
wired equipment to these same temporary lighting burial if in direct contact with the earth.
circuits.
9.6 Overhead Conductors
9.3 Raceway Systems
Install overhead conductors in accordance with the
9.3.1 Raceway types NEC. Do not support overhead conductors from
trees or other live vegetation. For overhead conductor
Select and install raceways listed and suitable for the
installations not covered by the NEC, refer to ANSI/
application and environment.
IEEE C2-2017, National Electrical Safety Code (NESC).

n 14
10.
1. Scope
Receptacle Outlets

10.1 Receptacle Configurations for minimum requirements that apply to receptacles


installed in damp and wet locations.
Provide receptacle configuration compatible with the
cord- and plug-connected equipment anticipated to
be used at that location. 10.4 Ground-Fault Circuit-Interrupter
(GFCI) Protection for Personnel
10.2 Receptacle Outlets Provide GFCI protection for personnel on temporary
construction receptacle outlets including receptacles
Locate receptacles so that they are accessible and
supplied by any on-site-generated power source such
reasonably protected from physical damage. Where
as portable generators. GFCI circuit breakers, GFCI
receptacle outlets are located on structural elements,
receptacles, and other GFCI devices should have
loctate them to eliminate rework or back-charges
enclosures that minimize moisture build-up around
due to removal by other trades or the application
the device. Install GFCI protected branch-circuit
of building finishes.. Receptacle outlets should be
conductors and wiring devices in a manner that
installed to limit the need to lay extension cords
minimizes moisture build-up around the conductors
across corridors or main access routes that are used
or device. Use sealing locknuts on connectors or use
for vehicles, transfer of heavy loads or access to
weatherproof connectors wherever possible.
stairs and so forth. Where receptacles are likely to
be subject to damage due to their location, provide 10.4.1 Permanent receptacles
barriers and guards for protection. Securely attach
the enclosure to a temporary, movable support, When receptacles that are part of a permanent-
permanent surface or other structure that provides premises wiring system and not GFCI-protected
secure support. are used for temporary construction power, provide
GFCI protection in one of the following ways:
10.3 Enclosures and Covers
(a) Use listed cord sets or devices incorporating
Provide enclosures suitable for the environment listed GFCI protection for personnel that are
in which the receptacles are located. All 15- identified for portable use.
and 20-ampere, 125- and 250-volt, non-locking
(b) Use portable GFCI devices and assemblies.
receptacles located in damp or wet locations must
have covers that are weatherproof when a plug (c) Temporarily replace the permanent non-
is plugged into the receptacle. These receptacles GFCI receptacles with GFCI-protected
must also be listed as weather-resistant types (WR). receptacles.
Provide enclosures suitable for the environment (d) Temporarily replace the permanent non-
in which the receptacles are located. All 15- and GFCI circuit breakers protecting the branch
20-ampere, 125- and 250-volt, non-locking circuits used for construction power with
receptacles located in damp or wet locations GFCI circuit breakers.
must be provided with extra duty covers that are
weatherproof when in use. See NEC 406.9(A) and (B)

15 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites

10.4.2 GFCI testing

Test GFCI circuit breakers, GFCI receptacles, and


other GFCI devices when they are first installed, and
on a regular basis in accordance with manufacturer
recommendations. Document the results of all GFCI
testing. Immediately de-energize and tag any branch
circuit or device whose GFCI protection fails the
test or exhibits physical damage. Do not re-energize
the branch circuit or device until the defective GFCI
device is replaced and/or the physical damage has
been repaired. Keep permanent written records of
all testing and repair work performed.

10.5 Receptacle Grounding


Receptacles shall be electrically connected to the
equipment-grounding conductor of the branch
circuit supplying the receptacle.

Figure 7. Grounding receptacles must be connected


to the equipment-grounding conductor of temporary
branch circuit wiring.

n 16
1. Scope
11. Temporary Lighting

11.1 System Layout Task lighting is frequently used to supplement


temporary lighting for general tasks such as layout.
Install temporary lighting in accordance with the
contract documents and/or the approved temporary
construction power distribution system record 11.2 Installation
drawings (see 3.6). 11.2.1 Support
Select luminaires and lampholders suitable for Support luminaires and lampholders securely from
the application and environment. Luminaires and boxes, structural members, building surfaces, ceiling
lampholders must have lenses, guards, or other grid, cables, chains, poles, or other support means.
means to protect lamps from physical damage. Do not support luminaires and lampholders by
power supply conductors or cords unless they are
Unless specifically required by the contract approved to be supported in this manner, such as
documents, it is not the electrical contractor’s listed pigtail-type lampholders. Do not support
responsibility to ensure that temporary lighting luminaires for temporary construction lighting from
meets the illumination requirements of OSHA 29 trees or other live vegetation.
CFR Part 1926, Subpart D, Section 1926.56 (See
Annex A). It is the responsibility of each employer 11.2.2 Location
at the construction site to ensure that their workers
have adequate illumination to perform their work. Locate luminaires and lampholders where they are
reasonably protected from physical damage. Where
this is not possible due to lighting needs, provide
barriers and guards for protection.

11.2.3 Types

All temporary lighting luminaires shall be listed and be


of a type identified for the environment in which they
are located or otherwise be protected from the elements
of the environment in which they are installed.

11.3 Cutover To Permanent Lighting


As soon as the permanent lighting has been installed
in an area, energized, and fully tested, remove the
temporary lighting and conductors. When the
permanent lighting of a building or structure is
used during the period of construction, protect
the permanent lighting equipment from dust and
Figure 8. Listed temporary lighting assembly with damage as described in NECA/IESNA 500, NECA/
lampholder and protective basket. IESNA 501, and NECA/IESNA 502.

17 n
1. Scope
12. System Maintenance

Perform regular inspections and routine


maintenance on the temporary construction power
distribution system throughout construction.

(a) Immediately de-energize and tag any


equipment that is found to be defective or
physically damaged.
(b) Do not reenergize the feeder or branch
circuit until the defective or damaged
equipment has been removed, repaired, or
replaced.
(c) Keep written records of all inspections and
maintenance performed.

Figure 9. Use proper PPE when performing all testing,


installation, and maintenance functions. (Courtesy of
NECA)

n 18
1. Scope
13. System Removal

13.1 System Cutover 13.3 Penetrations


Coordinate the system cutover from temporary Seal all penetrations of building partitions and
construction power to permanent power to minimize finishes after removal of temporary equipment,
disruption of construction operations and others that raceways, and conductors. For fire-resistance-rated
may be impacted by a shutdown. partitions, use only materials and methods listed to
maintain the fire resistance rating.
13.2 Removing Temporary System
Immediately after cutover to the permanent
power distribution system, completely disconnect
and remove all temporary equipment, raceway,
conductors, and other materials installed as part of
the temporary power distribution system not used as
part of the permanent installation.

19 n
(This annex is not part of the standard)

1. Scope
Annex A: OSHA 29 CFR 1926.56
Minimum Light Levels for
Construction Work

(a) General. Construction areas, ramps, (b) Other areas. For areas or operations not
runways, corridors, offices, shops, and storage covered above, refer to the American National
areas shall be lighted to no less that the minimum Standard A11.1-1965 (R1970), Practice for Industrial
illumination intensities listed in Table D-3 while any Lighting, for recommended values of illumination.
work is in progress:

Table D-3: Minimum Illumination Intensities in Foot-Candles

FOOT-CANDLES AREA OF OPERATION


5 General construction area lighting.
General construction areas, concrete placement, excavation and waste areas,
3 access ways, active storage areas, loading platforms, refueling, and field
maintenance areas.
5 Indoors: warehouses, corridors, hallways, and exitways.
Tunnels, shafts, and general underground work areas. (Exception: minimum of
10 foot-candles is required at tunnel and shaft heading during drilling, mucking,
5
and scaling. Bureau of Mines approved cap lights shall be acceptable for use in
the tunnel heading.
General construction plant and shops (e.g., batch plants, screening plants,
10 mechanical and electrical equipment rooms, carpenter shops, rigging lofts and
active store rooms, mess halls, and indoor toilets and workrooms.)
30 First aid stations, infirmaries, and offices.

n 20
(This annex is not part of the standard)

1. Scope
Annex B: Reference Standards

This publication, when used in conjunction with the National Electrical Code and product manufacturers’
literature, provides sufficient information to install and maintain temporary power systems at construction
sites. The following publications may also provide useful information:

National Fire Protection Association


1 Batterymarch Park
Quincy, MA 02169-7471
(617) 770-3000 tel
(617) 770-3500 fax
www.nfpa.org

NFPA 70-2017, National Electrical Code (ANSI)


NFPA 70E-2015, Standard for Electrical Safety in the Workplace (ANSI)

Institute of Electrical and Electronics Engineers


445 Hoes Lane
P.O. Box 1331
Piscataway, NJ 08855-1331
(800) 678-4333 tel
(732) 981-9667 fax
www.ieee.org

ANSI/IEEE C2-2017, National Electrical Safety Code

National Electrical Manufacturers Association


1300 North Seventeenth Street, Suite 1847
Rosslyn, VA 22209
(703) 841-3200 tel
(703) 841-3300 fax
www.nema.org

ANSI/NEMA WD 6-2016, Wiring Devices – Dimensional Requirements

21 n
NECA 200 Standard for Installing and Maintaining Temporary Electric Power at Construction Sites

Occupational Safety and Health Administration


200 Constitution Avenue, NW
Washington, DC 20210
(202) 401-0721 tel
www.osha.gov

Safety and Health Regulations for Construction – Electrical, 29 Code of Federal Regulations (CFR) Part 1926,
Subpart K

National Electrical Contractors Association


3 Bethesda Metro Center, Suite 1100
Bethesda, MD 20814
301-215-4521 tel
301-215-4500 fax
www.neca-neis.org

Current National Electrical Installation Standards™ published by NECA:

NECA 1-2015, Standard for Good Workmanship in Electrical Construction (ANSI)


NECA 90-2015, Standard for Commissioning Building Electrical Systems (ANSI)
NECA 100-2013, Symbols for Electrical Construction Drawings (ANSI)
NECA 101-2013, Standard for Installing Steel Conduits (Rigid, IMC, EMT) (ANSI)
NECA 102-2004, Standard for Installing Aluminum Rigid Metal Conduit (ANSI)
NECA/AA 104-2012, Standard for Installing Aluminum Building Wire and Cable (ANSI)
NECA/NEMA 105-2015, Standard for Installing Metal Cable Tray Systems (ANSI)
NECA 111-2003, Standard for Installing Nonmetallic Raceways (RNC, ENT, LFNC) (ANSI)
NECA/NACMA 120-2012, Standard for Installing Armored Cable (AC) and Metal-Clad Cable (MC) (ANSI)
NECA 121-2007, Standard for Installing Nonmetallic-Sheathed Cable (Type NM-B) and Underground Feeder
and Branch-Circuit Cable (Type UF) (ANSI)
NECA 130-2010, Standard for Installing and Maintaining Wiring Devices (ANSI)
NECA 169-2010, Standard for Installing and Maintaining Arc-Fault Circuit Interrupters (AFCIs) and Ground-
Fault Circuit Interrupters (GFCIs) (ANSI)
NECA 200-2016, Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
(ANSI)
NECA 202-2013, Standard for Installing and Maintaining Industrial Heat Tracing Systems (ANSI)
NECA 230-2010, Standard for Selecting, Installing, and Maintaining Electric Motors and Motor Controllers
(ANSI)
NECA/FOA 301-2009, Standard for Installing and Testing Fiber Optic Cables (ANSI)

n 22
Standard for Installing and Maintaining Temporary Electric Power at Construction Sites NECA 200

NECA 303-2005, Standard for Installing Closed-Circuit Television (CCTV) Systems (ANSI)
NECA 305-2010, Standard for Fire Alarm System Job Practices (ANSI)
NECA 331-2009, Standard for Building and Service Entrance Grounding and Bonding
NECA 400-2007, Standard for Installing and Maintaining Switchboards (ANSI)
NECA 402-2014, Standard for Installing and Maintaining Motor Control Centers (ANSI)
NECA/EGSA 404-2014, Standard for Installing Generator Sets (ANSI)
NECA 406-2014, Standard for Installing Residential Generator Sets (ANSI)
NECA 407-2015, Standard for Installing and Maintaining Panelboards (ANSI)
NECA 408-2015, Standard for Installing and Maintaining Busways (ANSI)
NECA 409-2015, Standard for Installing and Maintaining Dry-Type Transformers (ANSI)
NECA 410-2013, Standard for Installing and Maintaining Liquid-Filled Transformers (ANSI)
NECA 411-2014, Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS) (ANSI)
NECA 412-2012, Standard for Installing and Maintaining Photovoltaic (PV) Power Systems (ANSI)
NECA 413-2012, Standard for Installing and Maintaining Electric Vehicle Supply Equipment (ANSI)
NECA 420-2014, Standard for Fuse Applications (ANSI)
NECA 430-2006, Standard for Installing Medium-Voltage Metal-Clad Switchgear (ANSI)
NECA/IESNA 500-2006, Standard for Installing Indoor Commercial Lighting Systems (ANSI)
NECA/IESNA 501-2006, Standard for Installing Exterior Lighting Systems (ANSI)
NECA/IESNA 502-2006, Standard for Installing Industrial Lighting Systems (ANSI)
NECA 503-2005, Standard for Installing Fiber Optic Lighting Systems
NECA/BICSI 568-2006, Standard for Installing Commercial Building Telecommunications Cabling (ANSI)
NECA/NCSCB 600-2014, Standard for Installing and Maintaining Medium-Voltage Cable (ANSI)
NECA/NEMA 605-2005, Recommended Practice for Installing Underground Nonmetallic Utility Duct (ANSI)
NECA/BICSI 607-2011, Standard for Telecommunications Bonding and Grounding Planning and Installation
Methods for Commercial Buildings (ANSI)
NECA 700-2010, Standard for Installing Overcurrent Protection to Achieve Selective Coordination (ANSI)
NECA 701-2013, Standard for Energy Management, Demand Response and Energy Solutions (ANSI)

23 n
<This page intentionally left blank>
<This page intentionally left blank>
<This page intentionally left blank>
National Electrical Contractors Association
3 Bethesda Metro Center, Suite 1100
Bethesda, Maryland 20785
301-657-3110 • 301-214-4500 fax
www.necanet.org
Index # NECA 200-16 | 5C-6/16

You might also like