You are on page 1of 34

A M E R I C A N N A T I O N A L S T A N D A R D NECA 400-2007

Standard for

Installing and Maintaining


Switchboards

Published by
National Electrical
Contractors Association
NECA 400-2007
Standard for

Installing and Maintaining


Switchboards

An American
National Standard

Published by
National Electrical
Contractors Association
NOTICE OF COPYRIGHT

This document is copyrighted by NECA

Reproduction of these documents either in hard copy or soft (including posting on the web) is prohibited
without copyright permission. For copyright permission to reproduce portions of this document, please
contact NECA Standards & Safety at (301) 215-4546, or send a fax to (301) 215-4500.

OR

National Electrical Contractors Association


3 Bethesda Metro Center, Suite 1100
Bethesda, Maryland 20814
(301) 657-3110

Organizations may obtain permission to reproduce a limited number of copies by entering into a license
agreement. For information, contact:

IHS
15 Iverness Way East
Englewood, CO 80112-5704 or call
1-800-854-7179 (USA and Canada)
(303) 397-7956 (International)
Table of Contents

Foreword . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .iii

1. Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
1.1 Products and Applications Included . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
1.2 Regulatory and Other Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1

2. Switchboard Receiving, Handling, and Storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2


2.1 Receiving the Switchboard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2
2.2 Handling the Switchboard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2
2.3 Storing the Switchboard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3

3. Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
3.1 Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
3.2 Foundation Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
3.3 General Installation Instructions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
3.4 Installing Vertical Sections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
3.5 Joining Switchboard Sections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
3.6 Anchoring the Switchboard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
3.7 Installing Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
3.8 Installing Interconnections Between Switchboard Sections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6
3.9 Ground Bus Splice Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
3.10 Grounding and Bonding . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7
3.11 Busway Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8
3.12 Conduit Area . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .8
3.13 Cable Pulling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9
3.14 Cable Terminations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9

4. Pre-Energizing Checkout Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10


4.1 Location . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10
4.2 Insulation Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10
4.3 Current Transformers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10
4.4 Circuit Breakers and Fusible Switches . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .10
4.5 Ground-fault Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
4.6 Interconnections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
4.7 Power Fuses and Control Power Disconnects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
4.8 Clean-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11
4.9 Close-up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .11

i ■
NECA 400 Recommended Practice for Installing and Maintaining Switchboards

5. Energizing the Switchboard . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .12

6. Switchboard Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13


6.1 Routine Inspections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .13
6.2 Safety Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
6.3 Cleaning and Inspections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
6.4 Maintenance and Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14
6.5 Insulation Resistance Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .17
6.6 Re-energizing Switchboards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .17

7. Adverse Circumstances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18


7.1 Inspection Following a Short-Circuit or Ground-Fault Condition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18
7.2 Replacing a Switchboard Soaked by or Submerged in Water . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18
7.3 Inspecting and Re-energizing a Switchboard Sprayed or Splashed
with Clean Water . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .18

8. Recommended Torque Values . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .20

9. Switchboard Insulation Resistance Chart . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .32

10. Operations and Maintenance Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .23

Annex A: Reference Standards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .24

■ ii
(This foreword is not a part of the standard)

Foreword

National Electrical Installation Standards™ (NEIS®) are Suggestions for revisions and improvements to this
designed to improve communication among speci- standard are welcome. They should be addressed to:
fiers, purchasers, and suppliers of electrical construc-
tion services. They define a minimum baseline of NECA Standards & Safety
quality and workmanship for installing electrical prod- 3 Bethesda Metro Center, Suite 1100
ucts and systems. NEIS are intended to be referenced Bethesda, MD 20814
in contract documents for electrical construction pro- (301) 657-3110 telephone
jects. The following language is recommended: (301) 215-4500 fax
www.neca-neis.org
Deadfront distribution switchboards rated 600 neis@necanet.org
volts or less shall be installed and maintained in
accordance with NECA 400, Standard for To purchase NEIS, contact the NECA Order Desk at
Installing and Maintaining Switchboards (ANSI). (301) 215-4504 tel, (301) 215-4500 fax, or
orderdesk@necanet.org. NEIS can also be purchased
Use of NEIS is voluntary, and the National Electrical in PDF format from www.neca-neis.org/standards.
Contractors Association assumes no obligation or lia-
bility to users of this publication. Existence of a stan- Copyright© 2007, National Electrical Contractors
dard shall not preclude any member or nonmember Association. All rights reserved. Unauthorized repro-
of NECA from specifying or using alternate con- duction prohibited.
struction methods permitted by applicable regula-
tions. National Electrical Installation Standards, NEIS, and the
NEIS logo are trademarks of the National Electrical
The installation and maintenance practices recom- Contractors Association. National Electrical Code and
mended by this publication are intended to NEC are registered trademarks of the National Fire
Protection Association.
comply with the edition of the National Electrical
Code® (NEC) in effect at the time of publication.
Because they are quality standards, NEIS may in
some instances go beyond the minimum safety
requirements of the NEC. It is the responsibility of
users of this standard to comply with state and local
electrical codes when installing electrical products
and systems.

iii ■
Revision History
NECA 400-1998 09/1998
NECA 400-2007 07/2007

■ iv
1. Scope

1.1 Products and Applications Included b) Only qualified persons familiar with the con-
struction and installation of motor control centers
This standard desribes installation procedures for
should perform the work described in this publica-
deadfront distribution switchboards rated 600 volts
tion. It is recommended that all work be performed
or less. This standard also covers periodic routine
in accordance with NFPA 70E, Standard for Electrical
maintenance procedures for switchboards, and spe-
Safety in the Workplace.
cial procedures to be used after adverse circum-
stances, such as a short circuit, ground-fault, or
c) General requirements for installing electrical
immersion in water.
products and systems are described in NECA 1,
Standard Practices for Good Workmanship in Electrical
1.2 Regulatory and Other Requirements
Construction (ANSI). Other National Electrical
a) All information in this publication is intended to Installation Standards provide additional guidance for
conform to the National Electrical Code installing particular types of electrical products and
(ANSI/NFPA 70). Installers should always follow the systems. A complete list of NEIS is provided in
NEC, applicable state and local codes, manufacturer’s Annex A.
instructions, and contract documents.

1 ■
2. Switchboard Receiving, Handling,
and Storing

2.1 Receiving the Switchboard 2.2.1 Handling with lifting straps


Switchboard manufacturers provide lifting straps as
a) Unload carefully, observing all packing label standard equipment when the weight of the switch-
warnings. board section(s) does not exceed the recommended
capacity of the lifting straps. Use a rigid spreader or
b) Use forklifts or other loading equipment only for a spanner beam to provide vertical lift on the lifting
palletized shipments. straps (see Figure 1), and avoid damage to the frame
or finish. Follow lifting warning labels on the switch-
c) Leaving protective coverings in place as much as board.
possible, open and inspect the switchboard complete-
ly for shipping damage. Undamaged material should 2.2.2 Handling without lifting straps
be carefully repacked unless intended for immediate
installation. Lifting straps are not furnished on switchboards
when the weight of the section(s) exceeds their
NOTE: Depending on company policy or project cir- capacity, or when the lifting straps would cause stress
cumstances, it may be necessary to receive, unpack, and to the switchboards. They also are not provided
check all material at the company shop or other staging when the design does not permit, such as NEMA
area, in which case, careful repacking is essential. Type 3R outdoor equipment with overhangs. These
switchboards can be handled by either slings, fork-
2.2 Handling the Switchboard lifts, rollers, or a combination of these means.
Switchboards are typically large, bulky pieces of Typically, a handling warning is provided on those
equipment weighing several hundred pounds or switchboard sections for which lifting straps are not
more. The packing provides the actual weight of provided.
each item. Handle the switchboard properly to avoid
injury to personnel and damage to equipment. Prior a) Sling: A crane or suitably rigged equipment with
to receiving the shipment, verify the type of truck a chain arranged in a sling, or wire cable with safety
making the delivery and that the lifting capacity of hooks and shackles, should be used to lift a switch-
the handling equipment is more than the shipping board shipping section not equipped with lifting
weight. Delivery on an open truck at the job site is
recommended.

Suitable protection against the weather must be pro-


vided if the equipment is designed only for indoor
Spreader Beam
installation (NEMA Type 1).
Lifting Straps

There are two primary ways of lifting the equipment:


with lifting straps and without lifting straps, using a
45° minimum angle
sling instead. Using the manufacturer’s lifting straps
is the preferable method when these are supplied. Figure 1: Handling switchboards with lifting straps

■ 2
Recommended Practice for Installing and Maintaining Switchboards NECA 400

straps. Rig the sling completely around the switch- be at least the width of the switchboard for stability.
board and shipping stringers (see Figure 2), and use a Extreme care should be taken when using rollers due
forklift or jacks to lift the switchboard vertically off to switchboard height and weight. Rollers are most
the floor to attach the sling. suitable for moving switchboards on a level surface;
use a winch or chainfall to prevent “runaway” where
b) Forklifts: Forklifts are an alternate method for inclines must be traveled.
handling switchboards. Verify that the capacity of
the forklift is more than the weight of the load to be 2.3 Storing the Switchboard
lifted. Always ensure that the form lengths extend
a) Cover the switchboard with a tarp or plastic to
under the entire switchboard and extend beyond the
keep the equipment from getting wet and accumulat-
opposite side (see Figure 3).
ing dust or debris (cement dust can be corrosive and
cause insulation breakdown when it accumulates
c) Rollers: If equipment is not available for lifting
across insulators). The cover should be heavy
the switchboard, or the ceiling is not high enough,
enough to keep from tearing during wind gusts at the
rollers suitable for the application may be used to
storage location.
move the switchboard into position. A forklift or
jacks can be used to initially lift the switchboard and
b) To reduce condensation within the switchboard
position it on the rollers. Rollers should be posi-
enclosure, store the switchboard indoors whenever
tioned approximately every 18 inches (457 mm), and
possible.

c) Install a minimum of 250 watts of heat per verti-


cal section, even for outdoor enclosures. Remove all
1/2 A loose packing or materials that could catch fire prior
or more
A
Do not pass ropes or cables to applying the heat.
through lift holes. Use slings
45° min. angle with safety hooks or shackles.

Spanner Bar
(channel)

Blocks
Switchboard
(front or rear)

Stringer
4x6 in
102x152 mm

Figure 2: Handling switchboards without lifting straps

SECURE MOTOR CONTROL


CENTER TO FORKLIFT WITH
SAFETY STRAP HERE.

FORKS
UNDER ENTIRE
MOTOR CONTROL
CENTER

Figure 3: Handling switchboards with forklift

3 ■
3. Installation

Proper installation is essential to the proper opera- Circumstances). The sump pump should be connect-
tion of all switchboard components. Thoroughly ed to a standby power source.
study associated instruction manuals, literature, and
drawings before attempting to install the switch- 3.2 Foundation Preparation
board. In most cases, this information will already
a) The floor or foundation on which the switch-
have been requested prior to the shipment of the
board will be installed needs to be strong enough to
switchboard to enable advanced planning.
support the weight of the switchboard without bow-
ing or sagging. A concrete surface is preferred.
3.1 Location
a) The floor plan of the structure for an inside b) In special instances where earthquakes may occur,
switchboard, or the site plan for an outdoor switch- 4000 psi concrete should be used along with specific
board will show the area where the switchboard is to anchoring means, such as stud anchors, sleeves
be installed. The location of the switchboard should anchors, or concrete anchor bolts (anchoring hard-
comply with all building codes, and at a minimum, ware is not supplied as a standard item with most
should meet the working space requirements of the switchboards). Performance of the switchboard
NEC 110.26. under earthquake conditions is directly related to the
foundation preparation.
NOTE: Provisions for temporary ramps or installation
hoists may require working clearances greater than NOTE: Local building codes may have seismic require-
NEC minimums. ments that affect switchboard installation. Installers
should consult these codes or coordinate with the gener-
b) Consult the switchboard drawings to determine al contractor prior to installing switchboards.
where accessibility is required for the switchboard
(e.g., a rear access switchboard cannot be placed c) A level mounting pad raised four inches (100
against a wall). mm) above the general floor level is typical with the
surrounding floor area gently sloping toward a drain.
c) Indoor switchboards in damp locations require To ensure correct bus bar alignment within the
shielding to prevent moisture and water from enter- switchboard, and to enable bolting vertical sections
ing and accumulating. If the room temperature together, it is critical that the mounting pad or floor
around the indoor switchboard is not between 77° – be smooth and level.
104°F (25° – 40°C), use a minimum of 250 watts of
heating per vertical section until the suitable environ- NOTE: Provisions for temporary ramps or installation
ment can be provided. hoists may require working clearances greater than
NEC minimums.
d) In locations where a sump pump is required, the
pump should be properly working before the switch- d) If floor channels are embedded in the concrete
board is installed to prevent accumulation of water pad, they should be level over the entire length of the
that may seriously damage the switchboard and its switchboard in order to avoid distortion of the
internal components (see Section 7, Adverse switchboard structure.

■ 4
Recommended Practice for Installing and Maintaining Switchboards NECA 400

e) Before pouring the concrete for the pad, install all b) If the switchboard is left-feed, start from the left.
conduits including future conduits required for bot- If right-feed, start from the right.
tom entry into the switchboard. Consult the bottom
view switchboard drawing during this process to ver- c) If the switchboard is close-coupled to a trans-
ify that the conduit layout matches the available con- former, start at the transformer and work away from
duit entry area into the switchboard. The manufac- the transformer.
turer will already have taken into account the NEC
and product listing requirements for conduit entry. 3.4.2 Positioning

f) Embedded conduits typically project above the Position each shipping section carefully, following the
finished pad approximately 2 inches (50.8 mm). If instructions in 2.2, Handling the Switchboard. Level
embedded conduits project more than 2 inches (50.8 with shims if necessary, and align each section with
mm) above the concrete pad, it may be necessary to the previous section. Proper alignment will make
lift each shipping section vertically into place using a joining the structures and through-bus easier.
crane, timbers, jacks, or forklift. After the sections NOTE: Improper alignment of the through-bus may
are installed, and approximate extension sleeves result in property loss, death, or serious injury.
added to the conduits, the maximum projection
should be 3 inches (76 mm); NEC Section 408.5 pro- 3.4.3 Lifting straps
hibits projections greater than 3 inches (76 mm).
Remove lifting straps or slings so that vertical sec-
3.3 General Installation Instructions tions can be joined flush. Leave lifting straps or
hardware on the switchboard if their removal is not
a) Clean dirt and debris from the pad and surround-
required to join adjacent sections flush together.
ing area where the switchboard will be located before
moving the switchboard into its final position.
3.5 Joining Switchboard Sections
b) Remove the shipping skids before installing the a) Open or remove the front, and, if necessary, the
switchboard on the pad. rear door or panels that provide access for bolting
adjacent shipping sections together.
c) If the switchboard is equipped with bottom clo-
sure plates, temporarily remove these plates and set b) Torque the bolts based on the manufacturer’s
them aside. Cut holes for the conduits entering the instructions.
bottom of each enclosure in the bottom plates (if
supplied). Once the vertical sections have been NOTE: The authority having jurisdiction (AHJ) may
installed, reinstall the bottom closure plates. require that all bolts connecting bus sections be inspect-
ed for proper torque prior to closing up the switch-
d) Block the opening of each conduit with material board.
that rodents will not be able to gnaw through,
squeeze through, or push out of the way. Bottom 3.6 Anchoring the Switchboard
closure plates will not keep out rodents that come in Switchboard sections are freestanding structures, but
through the conduits. hard bumps or shifting movements can result in
damage to interior components, conduit hubs, and
3.4 Installing Vertical Sections cable/busway connections. Therefore, each vertical
3.4.1 Initial placement section of the switchboard is anchored to the floor.
Some manufacturers provide formed base channels
a) If the switchboard has incoming cables or busway that run the entire length of the switchboard, mount-
near or in its center, start with that vertical section ing holes in the structure base, or both (see Figure 4).
first and work outward on each side.

5 ■
NECA 400 Recommended Practice for Installing and Maintaining Switchboards

Anchor each section using the hardware recommend- 3.8.1 Through-bus splice connections
ed (but not usually supplied by) the switchboard
manufacturer and torque the bolts to their recom- Through-bus splice connections are extremely
mended value. important to the performance of the switchboard,
since these connections are expected to carry the full
3.6.1 Seismic considerations current intended for their operation. Failure to
properly make through-bus splice connections may
Carefully follow the plans and specifications when result in property damage, death, or serious injury.
anchoring a switchboard for seismic conditions since
the top of the switchboard structure can move as a) Through-bus splice kits are provided by the
much as 3 inches (76 mm) in any direction. switchboard manufacturer when more than one sec-
tion is required to be electrically connected together
NOTE: Local building codes may have seismic require- by through-bus.
ments that affect switchboard installation. Installers
should consult these codes or coordinate with the gener- b) Splice kits may come in separate boxes, be
al contractor prior to installing switchboards. installed on the through-bus of one or more vertical
sections, or be stored inside the sections to be spliced.
3.7 Installing Cables
Install the incoming services conductors and load- c) Follow the proper sequence of hardware installa-
side cables after all switchboard sections are properly tion, as specified in the manufacturer’s installation
joined together and the entire switchboard structure instructions. Install conical washers such that their
is anchored to the floor. If the switchboard is in a convex or “top” side is against the nut (see Figure 5).
seismic environment and cables or busway enter at
the top of the switchboard, it is necessary to take into d) Torque the splice bolts to their recommended val-
account the motion of the top of the switchboard ues. Mark each torqued connection with a perma-
during a seismic occurrence. nent marker.

NOTE: If the switchboard consists of only one shipping e) The through-bus of some switchboards is covered
section, proceed to Section 3.10. with an insulating material. Follow the manufactur-
er’s instructions for installing insulation on each
3.8 Installing Interconnections Between through-bus splice connection.
Switchboard Sections
Switchboard vertical sections are electrically connect- 3.8.2 Cable Interconnections
ed together using either through-bus or cables.
Install the interconnection cables (which may or may
not be supplied by the manufacturer) between sec-
tions as shown on the manufacturer’s drawings.

Hex Nut
Washer—
1.13 in Diameter hole in each
(29 mm) corner for anchoring.
Marked “Top”

Switchboard Frame
Secure the switchboard to the
mounting surface using the holes
closest to the surface.

Formed Base Channel Washer—


Bolt Head Marked “Top”
Mounting Surface

Figure 4: Anchoring the switchboard Figure 5: Proper positioning of conical washers

■ 6
Recommended Practice for Installing and Maintaining Switchboards NECA 400

Torque all connections to the manufacturer’s recom- a) Run a grounding electrode conductor from the
mended values. grounding electrode at the installation site to the
grounding electrode conductor connection, com-
3.9 Ground Bus Splice Connections monly called a ground lug, located on the switch-
board ground bus (see Figure 7).
Ground bus splice kits are provided by the switch-
board manufacturers when more than one section is
b) NEC 250.67 describes requirements for ground-
required to be electrically connected (see Figure 6).
ing electrode conductor material, installation, and
Proper installation of ground bus splice connections
size.
is essential to providing a low-impedance path to
ground for temporary current resulting from phase-
c) Torque the ground lug binding screw based on the
to-ground faults.
manufacturer’s recommendation or crimp in accor-
dance with the crimp tool’s instructions.
a) Splice kits may come in separate boxes, be
installed on the ground bus of one or more sections,
d) For service entrance equipment, or a switchboard
or be stored inside the switchboard sections.
used on a separately derived system, install the sys-
tem bonding jumper between the neutral bus and the
b) Follow the proper sequence of hardware installa-
ground bus. A label on the front of the switchboard
tion, as specified in the manufacturer’s installation
will identify the section(s) that incorporate the sys-
instructions. Install conical washers such that their
tem bonding jumper(s).
convex side is against the nut.
e) Torque the hardware of the main bonding jumper
c) Torque the splice bolts to the recommended value.
in accordance with the manufacturer’s recommenda-
Mark each torqued connection with a permanent
tions.
marker.
f) Equipment ground-fault protection will be ren-
3.10 Grounding and Bonding
dered inoperative if the system is grounded down-
3.10.1 Ground systems – service-entrance stream from the ground fault sensor.
switchboards and switchboards used on sepa-
rately derived systems g) For switchboards with multiple sources of power,
there will be two or more main bonding jumpers to
NEC 250.64 describes complete grounding require- install.
ments for grounded separately derived systems.

Figure 6: Ground bus splice connections Figure 7: Ground lug

7 ■
NECA 400 Recommended Practice for Installing and Maintaining Switchboards

3.10.2 Ungrounded systems – service-entrance b) Confirm proper phasing of the busway before
switchboards and switchboards used on sepa- energizing the busway run.
rately derived systems.
c) Do not use the switchboard to support the weight
NEC 250.64 describes complete grounding require- of the busway. Support the busway independently of
ments for ungrounded separately derived systems. the switchboard.

a) Run a grounding electrode conductor from the 3.12 Conduit Area


ground electrode at the installation site to the
grounding electrode conductor connection, com- a) The switchboard conduit entry drawings show the
monly called the ground lug, located on the switch- available conduit entry for the switchboard. External
board ground bus (see Figure 7). circuit cables for each section should be routed into
and through these designated conduit areas, then
b) NEC 250.66 describes requirements for ground- routed internally to their designed termination areas.
ing electrode conductor material, installation, and
size. b) Do not use the switchboard to support the weight
of the conduits. Support the conduits independently
c) Torque the ground lug binding screw based on the of the switchboard.
manufacturer’s recommendation or crimp per the
crimp tool’s instruction. c) If a bottom plate is furnished, remove it to cut
holes for the conduit and cable entry. Bottom plates
3.11 Busway Connections with holes are not furnished as a standard item.
Reinstall the bottom plates after the holes are made.
Power is often distributed from switchboards using Saw kerf between conduit holes in bottom plate for
busway, also called bus duct. Busway is provided in installations where conduits, such as duct bank risers,
different configurations by different manufacturers; carry phase conductors from only one phase (isolated
one typical configuration is shown in Figure 8. phase arrangement) to prevent a magnetic loop from
causing overheating within the switchboard.
a) When connecting busway, install conical washers
so the convex side of the washer is against the nut. d) Under seismic conditions, the top of the switch-
board may move up to 3 inches (76 mm) in any
direction. Any cables entering the top of the switch-
board need sufficient slack to accommodate this
motion. If the floor of the switchboard is designed
for movement during a seismic event, the cables
entering the bottom of the switchboard should also
have enough slack to accommodate this motion.

e) Use approved hubs and ring connectors to protect


the cables and prevent condensation from entering
the switchboard through the conduits.

f) Bond all conduits, stubs, and ring connectors to


the switchboard enclosure following the manufactur-
er’s recommendations.

Figure 8: Busway connector (bus duct)

■ 8
Recommended Practice for Installing and Maintaining Switchboards NECA 400

3.13 Cable Pulling g) Where required, brace or lace the conductors in


accordance with the manufacturer’s instructions or
Switchboard components are arranged to provide
consulting engineer’s specifications.
clearance and wire bending space for both line and
load cables. Each cable should be pulled into the
h) Train cables within wire gutters of switchboards
switchboard to conform to the arrangement specified
in a neat and workmanlike manner.
on the switchboard drawings.
3.14 Cable Terminations
a) Verify that the lugs correspond to the switchboard
cable schedule and are suitable for the cables being ter- Terminating and tightening cable connections to the
minated. Consult the markings on overcurrent pro- manufacturer’s recommended torque value is imper-
tective devices to determine that the conductor size ative to a satisfactory connection. Follow these steps
range is correct and the temperature rating is appro- when terminating conductors at the switchboard:
priate. Conductors rated 194°F (90°C) are permitted
to be used with most connectors and terminals, but a) Strip a sufficient length of insulation from the
only at 167°F (75°C) ampacity. Some overcurrent pro- cable end to fit into the full length of the lugs barrel.
tective devices, mostly those listed for operation at 100 Use a proper insulation stripping tool to avoid nick-
percent of rated ampacity, require the use of 194°F ing conductor strands. Stripping cable too long
(90°C) conductors sized at 167°F (75°C) ampacity. should be avoided since the through-air clearance
could be reduced below the minimums required by
b) Consult NEC Article 310 to calculate the proper the NEC.
size and number of conductors for the loads served.
b) Mechanical lugs (set-screw type) are the most
c) Prior to pulling the cables into the switchboard, common type of connector furnished with switch-
plan ahead as to which overcurrent device to cable boards. Torque these lugs in accordance with the
first. This is particularly important for group- manufacturer’s recommendations to avoid stripping
mounted constructions. threads or cracking the lug body.

d) Cable pulling lubricants should not be allowed to c) When compression lugs are used to terminate alu-
drip or come into contact with overcurrent devices minum conductors, remove oxides from the conduc-
and/or plating of the bus bars. Remove all pulling tors and apply an antioxidant compound to the alu-
compound from the interior of the switchboard prior minum conductor before inserting into the lug body.
to energizing the unit. Oxides on aluminum conductors are poor conductors
and will cause abnormal heating at the connection.
e) Position the conductors in the switchboard enclo-
sure so they are not subject to physical damage. If d) Remove compression lugs from their point of ter-
any conductors are in contact with structural mem- mination in order to crimp them onto cables. Follow
bers, place suitable protective material at the contact the manufacturer’s recommendation as to the proper
point to protect the cable insulation. number of crimps and their position on the lug. Use
the recommended sealant. Reinstall the crimp lugs
f) NEC 300.20(A) requires that all phase and to the lug pad and torque the hardware used with the
grounded conductors of the same circuit pass lugs.
through the same metal opening together.
Otherwise, a magnetic loop will be created causing
overheating within the switchboard.

9 ■
4. Pre-Energizing Checkout
Procedure

4.1 General 4.3 Current Transformers


Conduct a complete inspection of the switchboard Ensure that current transformers’ secondary termi-
before it is energized to ensure that the components nals are connected to a load or are shorted together
within the switchboard function properly. using shorting straps or terminal block shorting
screws.
a) Check all field-installed bus bar connections for
correct torque value. CAUTION: Open secondary terminals may have
high voltages, which could be a hazard to people or
b) Check all accessible connections for tightness. equipment.

c) Check all factory and field-installed lug termina- The shortening means are removed when the current
tions for the correct torque value. transformers operate normally with their intended
load.
d) Visually check the bussing insulators for cracks
and supports for damage. 4.4 Circuit Breakers and Fusible Switches
a) Manually open and close all circuit breakers and
e) Check to ensure that dents or other damage to the fusible switches to ensure proper operation.
enclosure have not resulted in clearances that violate
NEC requirements. b) Adjust the magnetic trip on thermal magnetic cir-
cuit breakers to their proper setting based on the sys-
f) Remove foam blocks, packing material, and tem- tem study or switchboard schedule. A setting too low
porary cushioning from the switchboard and compo- for a load that has a high peak inrush current will
nents inside the switchboard. trip the circuit breaker on start-up.

g) Check all relays, meters and instrumentation c) Electronic circuit breakers have functions such as
device wiring, and terminations. long-time, instantaneous, short-time, and ground-
fault, which require initial adjustment. Settings typi-
4.2 Insulation Test cally are provided in a coordination study prepared
Perform a direct current (DC) insulation test on the by the consulting engineer or other persons responsi-
switchboard and record the value for future mainte- ble for the switchboard set-up.
nance tests; a switchboard insulation resistance chart NOTE: These values typically are not found on the
is shown in Section 9. Values less than 1 megohm are drawings supplied by the switchboard manufacturer.
typically unacceptable. Prior to this test, remove
control power fuses and any other equipment that If values are not provided, consult the manufacturer’s
should not be subjected to this level of potential. circuit breaker instruction manual for values that will
set the electronic circuit breaker functions to emulate
thermal magnetic circuit breaker characteristics.

■ 10
Recommended Practice for Installing and Maintaining Switchboards NECA 400

4.5 Ground-fault Protection


a) The trip and time-delay on ground-fault protec-
tive equipment are typically set by the manufacturer
at their lowest settings. Adjust these settings based
on information provided in a coordination study
prepared by the consulting engineer or other persons
responsible for the switchboard set-up.

b) Some ground-fault protection systems require


field connections at the job site. Consult the switch-
board interconnection wiring diagram for details.

c) Check the ground-fault circuitry and establish


that there are no grounds on the neutral downstream
from the service entrance point.

d) The NEC requires that the ground-fault protec-


tion system be performance tested when first
installed, and that a written record of this test be
available to the AHJ. A testing group with experience
in switchboard ground-fault testing should perform
an injection test.

4.6 Interconnections
Verify that all interconnecting wiring between
switchboard sections has been connected.

4.7 Power Fuses and Control Power


Disconnects
Replace all control power fuses removed in the
Insulation Test (see Section 4.2) and turn on all con-
trol power disconnects.

4.8 Clean-up
Vacuum all scrap, wire, dust, and other debris from
the switchboard. Do not use compressed air to blow
debris out of the switchboard, since debris may
instead settle inside devices and impair their ability
to function.

4.9 Close-up
Replace all covers. Check for any pinched wires and
close all doors. Make sure that the enclosure parts
are properly aligned and fastened securely.

11 ■
5. Energizing the Switchboard

WARNING: Arc flash, arc blast, and shock hazards Step 2 Use remote operators, if available, to close
exist when energizing switchboards. Switchboards devices and energize switchboards and loads for the
should only be energized by qualified persons, following first time.
work practices defined in NFPA 70E.
Step 3 Prior to energizing any circuit that supplies
If a short circuit or ground-fault condition, caused rotating machinery, verify that the phase sequence is
by damage or poor installation practices exists, and correct. Serious damage can result to motors and
this is not detected and corrected during the check- similar equipment rotating in the wrong direction.
out procedures, serious personal injury and/or dam-
age to the switchboard can result when the switch- Step 4 One by one, close each circuit breaker or
board is first energized. Follow the steps below to fusible switch in the switchboard.
energize the switchboards; read all steps before pro-
ceeding. Step 5 Proceed to energize (turn on) the down-
stream loads (lighting circuits, contactors, heaters,
Step 1 Turn off all downstream loads. No load motors, etc.) one at a time.
should be on the switchboard when it is first ener-
gized.

■ 12
6. Switchboard Maintenance

Periodic maintenance of switchboards extends ser- boards. Use the rate of accumulation of dust and
vice life and increases reliability. Cleaning, inspec- moisture on visible surfaces as a guide for scheduling
tion, maintenance, and testing should only be per- cleaning, inspections, maintenance, and testing.
formed by qualified personnel on switchboards to
which power has been turned-off, disconnected, and Inspect switchboards for external signs of overheat-
electrically isolated, unless required for testing, so ing. Measure and record the ambient temperature.
that no accidental contact can be made with ener- Check equipment installed near switchboards that
gized parts. Follow all manufacturer’s warnings and might be an external source of heat. Eliminate exter-
instructions. nal sources of heat to switchboards. Check the oper-
ating temperature of switchboards that have been
The interval between maintenance checks varies operating under normal load and at normal ambient
depending on the environment, such as ambient temperature for a minimum of 3 hours by measuring
temperature and conditions in the switchboard the surface temperature of switchboard access covers,
room, and usage of the equipment. For switchboards doors, circuit breakers, and switches. If the tempera-
energized and in service, perform periodic routine ture exceeds manufacturer recommendations, de-
inspections, such as making limited visual observa- energize switchboard and investigate sources of over-
tions and recording operational data. heating.

Perform cleaning, inspections, maintenance, and test- Record switchboard voltage and load currents, if
ing of switchboards at least annually, but as often as equipped with meters, noting the date and time of
the operating environment requires keeping switch- day. Provide comments regarding known causes of
boards clean. Perform the first inspection and main- variations in loading, such as load additions or
tenance no more than one year after the original equipment maintenance outages.
installation. Plan cleaning, inspections, maintenance,
and testing to minimize outages. Check all accessible exterior switchboard hardware
for tightness.
In accordance with manufacturer recommendations,
clean, inspect, maintain, and test switchboards fol- Visually inspect enclosures for physical damage.
lowing any unusual operating condition, such as Repair physical damage, if practical, and as approved
whenever an overcurrent protective device opens, or by the manufacturer. Consult owner and switch-
a phase-to-phase short circuit or ground-fault occurs board manufacturer for recommendations for suit-
(see Section 7.1). able protective barriers to prevent future damage.

6.1 Routine Inspections Inspect areas and spaces around switchboards for
evidence of water or moisture. Eliminate sources of
Inspect areas and spaces around switchboards for any
water or moisture, or provide switchboards suitable
accumulation of dirt or dust. Remove any accumula-
protection from sources of water.
tions of dirt or dust. Remove trash, combustible
material, and other debris from areas around switch-

13 ■
NECA 400 Recommended Practice for Installing and Maintaining Switchboards

6.2 Safety Procedures conditions that cause the overheating, and replace the
affected parts before re-energizing the switchboard.
Before cleaning, inspecting, testing, or maintaining,
de-energize and electrically isolate equipment in Vacuum the inside of switchboards to remove any
accordance with established procedures. Consider all debris, dirt, or dust that has accumulated, noting
circuits live until they are confirmed to be de-ener- anything unusual, such as signs of insects, rodent
gized by testing and are locked out of operation. Do activity, or moisture. Avoid blowing dust into
not work on energized equipment. Guard energized switchboards. Do not use a blower or compressed
conductors and equipment in close proximity to air. Maintain adequate ventilation during cleaning.
work. Failure to observe these precautions may
result in severe personal injury or death. Wipe bus bars, insulators, conductors and other parts
with a clean, dry lint-free cloth. Do not use chemi-
Personnel working on or near energized switch- cals or petroleum-based solvents that may degrade
boards should follow the safe work practices plastics or insulating materials.
described in NFPA 70E, including the use of personal
protective equipment (PPE) appropriate for the task Visually inspect the inside of the switchboard for
being performed. moisture, condensation build-up, or signs of any pre-
vious wetness. Moisture causes insulation failures
Apply lockout/tagout procedures in accordance with and rapid oxidation of current-carrying parts. Pay
documented and established policies and practices. particular attention to conduit entrances and the top
Render electrical circuit conductors and circuit parts of the switchboard between sections. Remove any
electrically safe by removing all sources of energy by moisture present inside the switchboard and seal off
opening all upstream source disconnecting means, all leaks. Replace any components that show evi-
locking and tagging out all source disconnecting dence of damage from moisture.
means, verifying the absence of voltage using an
Carefully inspect all switchboard devices for any
approved voltage testing device, and guarding any
worn-out, cracked, or missing parts. Inspect termi-
exposed energized components.
nations, connections, and lugs for alignment, physical
damage, burns, corrosion, discoloration, flaking, heat
Remove the front cover of the switchboard and attach
damage, arcing, pitting, melting, deterioration, car-
grounding leads to the line terminals of the main cir-
bonization, cracks, chips, breaks, partial discharge, or
cuit breaker or main lugs, to the neutral terminal bus
moisture. Replace damaged components. Investigate
bar, if so equipped, and to the grounding terminal.
and eliminate sources of damage.
6.3 Cleaning and Inspections Plated parts may become dark over a period of time
Consult manufacturer recommendations for cleaning due to oxidation. Removing this discoloration will
and inspecting switchboards and components. De- reduce the thickness of the plating. Consult the
energize switchboards in accordance with Section 6.2 manufacturer for recommendations regarding discol-
prior to performing any cleaning or inspections. oration of parts.

Visually inspect switchboards for evidence of discol- Verify that all key interlocks and door interlocking
oration, abnormal dust accumulation, metal shards, provisions are working properly.
or any other indication of overheating, wear, or other
abnormal conditions prior to cleaning. 6.4 Maintenance and Testing
Consult manufacturer recommendations for main-
Visually inspect the switchboard for signs of overheat- taining and testing switchboards and components.
ing. Discoloration and flaking of insulation or metal De-energize switchboards in accordance with Section
parts are indications of possible overheating. Correct 6.2 prior to performing any maintenance or testing.

■ 14
Recommended Practice for Installing and Maintaining Switchboards NECA 400

6.4.1 Infrared Scan Replace parts that show indications of pitting, corro-
sion, discoloration, or annealing due to overheating.
After cleaning and inspecting switchboards and com- Do not use abrasive materials on bus bar joints. Use
ponents in accordance with Section 6.3, perform an hardware and washers of a grade identical to or bet-
infrared scan in accordance with switchboard and ter than the hardware replaced.
test equipment manufacturer recommendations.
With the switchboard de-energized, remove accessi- 6.4.3 Molded-Case Circuit Breakers
ble covers, plates, weathershields, etc. Provide sup-
plemental barriers and safety precautions during a) Clean circuit breaker surfaces. Remove dust, soot,
infrared scan to prevent accidental contact with grease, moisture, and foreign material.
exposed energized components. Personnel working
on or near energized switchboards should follow the b) Operate circuit breakers several times to exercise
safe work practices described in NFPA 70E, including the mechanism and contacts, and to ensure smooth
the use of personal protective equipment (PPE) operation. Many circuit breakers have a test feature
appropriate for the task being performed. which trips, exercises, and lubricates the mechanism.
This method of exercising circuit breakers should be
Energize the switchboard in accordance with Section used if available. If unavailable, operate circuit
6.6, and turn on all normal loads supplied by the breakers manually. Do not oil or grease parts of
switchboard. Perform an infrared scan of all switch- molded case circuit breakers. Replace circuit breakers
board electrical connections and terminals while ener- that do not operate smoothly.
gized and operating under normal load conditions.
c) Check circuit breakers for visual defects, chips,
Use an infrared scanning device designed to measure cracks, breaks, burns, and deterioration. Visually
actual operating temperatures or designed to detect check circuit breakers for evidence of overheating
significant deviations from surrounding conditions. and thermal damage. Investigate and eliminate
Provide documentation of device calibration. sources of overheating. Replace damaged circuit
breakers.
Prepare a certified report identifying the switchboard
tested and describing the results of the infrared scan. d) For circuit breakers that use solid-state circuitry
Include notations of deficiencies detected, remedial or a microprocessor, run the self-diagnostic program,
actions taken, and results from retesting after remedi- if available. For electronic circuit breakers, use the
al actions. test set to run trip unit test automatically with user
prompts. Repair or replace circuit breakers in accor-
Consult switchboard manufacturer for repair or dance with manufacturer recommendations.
replacement recommendations if infrared scan
results indicate overheating of components. 6.4.4 Bolted Pressure Switches

De-energize the switchboard in accordance with Exercise bolted pressure switch operating mecha-
Section 6.2. nisms. Check the cover interlock with the switch in
the “on” position. The cover should not open using
6.4.2 Bus Bar Joints normal hand force. Lubricate parts using materials
and methods in accordance with manufacturer rec-
Consult the manufacturer’s recommendations con- ommendations.
cerning bus bar joints, and retorque where required.
Some switchboard bus bar joints are maintenance- 6.4.5 Fusible Switches
free. Additional tightening after installation may
degrade these connections. a) Thoroughly clean fusible switches inside and out-
side. Clean contact areas of fuses and fuse holders.

15 ■
NECA 400 Recommended Practice for Installing and Maintaining Switchboards

Wipe insulating areas of fuses with a clean, dry, lint- 6.4.6 Inspecting and Replacing Fuses
free cloth.
Ensure that equipment is de-energized before
b) Operate each switch several times to ensure that inspecting and replacing fuses. Test line and load ter-
all mechanisms are free and in proper working order. minals of switches for the presence of voltage before
Check switches for damaged or broken parts, free replacing fuses. Turn the switches to the “off ” posi-
movement, corrosion, dirt, and excessive wear. Verify tion before opening the door. Do not defeat cover
proper blade penetration, travel stops, and mechani- interlocks to gain access to fuses.
cal operation. Repair or replace switches in accor-
dance with manufacturer recommendations. Visually inspect switch blades to verify that all blades
are disconnected from the line connections. Consult
c) Inspect contact surfaces, blades, and jaws for dis- the manufacturer for recommendations when blades
coloration, overheating, pitting, arcing, and corona. do not disconnect from line connections.
Inspect arc chutes. Clean and dress readily-accessible
copper electrical contacts, blades, and jaws in accor- a) Check all fuses to ensure that the correct type and
dance with manufacturer recommendations. Repair rating are installed. Where renewable fuses are used,
or replace burned contacts. Many contact surfaces, examine fuse links to ensure that the correct link is
such as arcing contacts, are silver tungsten or other installed.
types of materials that must never be dressed. When
NOTE: Some switchboard manufacturers do not recom-
contacts of these materials require maintenance, they
mend the use of renewable link fuses in their equipment.
must be replaced. If contact clips have lost their ten-
sion, replace clips or replace the switch. Consult the
b) Look for fuses that have been bridged with wire,
manufacturer for recommendations.
metal strips, disks, or appear to have been forced or
hammered in, etc. Replace with correct fuses and
d) Tighten fuse holder connections in accordance
consult the manufacturer for recommendations for
with manufacturer recommendations. Inspect each
preventing a recurrence.
fuse holder to determine whether it seems to be ade-
quately supporting the fuse and that the fuse holder
c) Look for evidence of overheating of cartridge
is securely attached to the mounting base. Inspect
fuses. Replace fuses having discolored or weakened
fuse clips for discoloration, overheating, corrosion, or
casings. Investigate the cause of overheating.
physical damage. Replace weak or burned clips.
Install new fuse clips and suitable clamps. Use man-
d) Inspect ferruled or knife blades of cartridge fuses
ufacturers’ replacement parts.
for corrosion or oxidation. Clean and polish contact
surfaces. Clean surfaces with a noncorrosive cleaning
e) Lubricate operating mechanisms and sliding con-
agent. Plated parts may become dark over a period
tact surfaces, if required, according to manufacturer’s
of time due to oxidation. Removing this discol-
instructions. If no instructions are given on the devices,
oration will reduce the thickness of the plating.
sliding copper contacts, operating mechanisms, and
Consult the manufacturer for recommendations
interlocks may be lubricated with clean, light grease.
regarding discoloration of parts.
Wipe off excess lubrication to avoid contamination.
e) Measure fuse resistance. Investigate fuse-resis-
f) Check the cover interlock with the switch in the “on”
tance values that deviate from each other by more
position. The cover should not open using normal
than 15 percent. Replace defective or partially-
hand force. Inspect switches for any damaged or bro-
burned fuses. Retighten plug fuses.
ken parts. Check the fuse mounting clips or bolted
contact area for corrosion or discoloration due to over-
f) Replace fuses with fuses of like types and ratings.
heating. Replace damaged or broken parts as necessary.
Ensure that non-current-limiting devices are not

■ 16
Recommended Practice for Installing and Maintaining Switchboards NECA 400

used as replacements for current-limiting devices. instrumentation and control fuses removed, and no
Do not defeat any rejection feature in any switch- loads connected to the switchboard. Ground all
board fusible device. phases not being tested. Connect megohmmeter
between each phase and ground, and between each
6.4.7 Ground-Fault Protection Systems phase. Measure insulation resistance at one minute
intervals following the application of the test voltage.
a) Check the torque of terminal connections on
ground-fault protection systems annually. Inspect Record the megohm values of each phase and
for corrosion and for physical, thermal, and electrical between each phase, along with the description of the
damage. Replace any damaged components. instrument, voltage level, humidity, temperature,
time, and date of the test. Consult switchboard man-
b) Test the ground-fault protection system in accor- ufacturer's published data for acceptable test results.
dance with manufacturer recommendations. Testing If published data is not available, investigate any val-
may be conducted with or without tripping main or ues that deviate from previous test results under sim-
branch overcurrent protective devices. Testing with ilar conditions by more than 50 percent of the lowest
trip is preferable since it ensures the whole system is value. Investigate any results less than 1 megohm
functioning. Energize the switchboard in accordance with the overcurrent protective devices in the open
with Section 6.6 prior to testing. position for possible tracking on insulation or insula-
tion breakdown. Ground each phase at the comple-
c) If the ground-fault protection system does not tion of the test. Maintain records of testing for
operate properly and additional equipment has been future reference.
connected to the installation since the last maintenance
test/check, de-energize the entire system in accordance 6.6 Re-energizing Switchboards
with Section 6.2, disconnect the main bonding jumper,
and check for continuity between the neutral and Energize switchboards in accordance with Section 5.
ground on the load-side of the main bonding jumper. Remove grounding leads from the line terminals of
If grounds are found, remove them and test again. If the switchboard. Visually inspect the system to
no grounds are detected, and the ground-fault protec- ensure that all tools, electrical jumpers, test devices,
tion system is still not functioning properly, consult the etc., have been removed. Visually inspect equipment
switchboard manufacturer for recommendations. and areas around equipment to ensure that all per-
sons are clear from circuits and equipment to be re-
d) If the ground-fault protection system does not energized. Remove locks and tags only after work is
operate properly, and no additional equipment has complete and tested, and all personnel are clear of
been connected to the installation since the last the area.
maintenance test/check, check the devices for physi-
cal or electrical damage and replace accordingly. Test for short circuits or ground-faults. Energize cir-
Check wiring for damage or loose connections and cuits using established switching procedures. Close
correct any problems found. Consult the switch- disconnect means starting at the source, working
board manufacturer for recommendations. toward the load. Measure phase-to-phase and phase-
to-neutral voltages, if applicable. Investigate source
6.5 Insulation Resistance Test of voltage imbalance greater than 3 percent. Measure
switchboard feeder and branch load currents. Verify
Perform an insulation resistance test on switchboards that conductors are properly sized and protected for
using a 1000 VDC megohmmeter. Disconnect all actual loading.
accessories and electronic devices that may be sub-
jected to the test voltage. Test from phase-to-ground
and from phase-to-phase with all switches and circuit
breakers in both the open and closed positions, all

17 ■
7. Adverse Circumstances

Special procedures are necessary to determine whether of the bussing system through the switchboard, and
a switchboard can safely remain in service following a the greatest damage may not occur where the arcing
short circuit, ground-fault, or exposure to water. condition originated. Conduct an insulation test to
determine the integrity of the switchboard insulation
7.1 Inspection Following a Short-Circuit or prior to re-energizing the switchboard.
Ground-Fault Condition
7.1.2 Ground-faults are unintentional current
Do not attempt to re-energize a switchboard follow-
paths between a phase conductor and ground
ing a short-circuit or ground-fault condition within
the switchboard. Do not re-energize a feeder or Depending on the magnitude of the ground-fault
branch overcurrent protection device in the switch- and its duration, carbon build-up and metallic splat-
board that has opened due to a short circuit or ter may need to be removed, insulators cleaned or
ground-fault until the problem downstream has been replaced. Perform phase-to-phase and phase-to-
corrected. ground insulation tests, with a minimum reading of
one megohm, prior to turning the switchboard
Following a short-circuit or ground-fault within a power back on.
switchboard, inspect the equipment thoroughly as
described in Section 6.1 to verify that damage has not 7.2 Replacing a Switchboard Soaked by or
occurred to conductors or insulators within the Submerged in Water
switchboard.
a) Do not work on energized electrical equipment
NOTE: The insulating properties of some organic insu- when standing in water.
lating materials may deteriorate during an electrical
arc. Replacement of the damaged insulating material is b) Do not energize a switchboard that is wet.
the only remedy.
c) Do not clean or repair a switchboard that has
7.1.1 Short-circuits develop high mechanical been submerged in or exposed to large volumes of
stresses that can damage conductors and insula- water. Current-carrying parts, insulation systems,
tion and electrical/electronic components may be dam-
aged beyond repair through contamination by chem-
Improper and loosened connections may result in icals, river or creek water, sewage, and other pollu-
conductors pulling out of their terminations on sub- tants. In this event, replace the switchboard rather
sequent short-circuits. For this reason, all connections than attempt to repair it.
should be inspected and, if necessary, re-evaluated.
Great care must be taken in evaluating the cause of 7.3 Inspecting and Re-Energizing a
the short circuit. Do not replace the fuse(s) and turn
Switchboard Sprayed or Splashed with Clean
the overcurrent protective device back on, or reset the
circuit breaker, without first determining whether it is
Water
safe to energize the circuit. Phase-to-phase short cir- Apply heat (a minimum of 250 watts per section) to
cuits that originate on bus bars can travel the length the switchboard to dry it out until visible signs of

■ 18
Recommended Practice for Installing and Maintaining Switchboards NECA 400

dampness cannot be seen. Remove materials that Voltage cannot be present on the switchboard during
could catch fire prior to applying the heat. Consult the insulation resistance test.
the manufacturer’s recommendations for specific
guidelines on how to ensure that it is safe to re-ener- Step 4 Use a DC insulation-resistance tester with a
gize the switchboard, or follow this procedure. capacity of 500-1000 volts DC to perform phase-to-
ground and phase-to-phase insulation tests.
7.3.1 Preliminary Inspection
NOTE: Use of an AC dielectric tester is not recom-
Follow the steps in Section 7.3.2 to re-energize the mended.
switchboard only if a preliminary inspection verifies
that the following conditions are satisfied: a) Measure each phase-to-ground (A, B, C) with the
circuit breakers or fusible switches “on”.
a) There are no signs of physical damage to the b) Measure each phase to another phase with the
equipment. circuit breakers or fusible switches “on”. Record
the values of the insulation resistance on the
b) The switchboard has not been soaked by or sub- insulation resistance chart shown in Section 9.
merged in water.

c) The water that has been in contact with the Step 5 Do not re-energize the equipment if any of
switchboard has not been contaminated with sewage, the resistance measurements are not at least 0.5
chemicals, or other substances. megohm. If moisture is the cause of the low resis-
tance readings, the moisture can be removed from
d) Water has not entered any area of the switchboard the switchboard by providing a minimum of 250
enclosure that contains wiring, and has not come watts of heat per vertical section.
into contact with any live part. Look for water enter-
ing through conduits. Step 6 If the resistance measurements are greater
than 0.5 megohom, the equipment can be re-ener-
If all of the conditions listed above are satisfied, pro- gized.
ceed as follows.

7.3.2 Cleaning, testing, and re-energizing a


switchboard
Step 1 Completely de-energize and electrically iso-
late the switchboard so that contact cannot be made
with energized parts.

Step 2 Wipe off all moisture from bus bars, insula-


tors, and insulating materials with a clean, dry, lint-
free cloth. Never use cleaning agents or sprays unless
specifically recommended by the switchboard manu-
facturer.

Step 3 Prepare the switchboard for an insulation


resistance test by disconnecting all line-side supply
conductors and all load-side conductors to isolate the
switchboard from the wiring system. Turn all circuit
breakers or fusible switches to the “on” position.

19 ■
8. Recommended Torque Values

If the switchboard manufacturer does not provide specific torque recommendations, use the following as a
guide.

Hardware
Description Torque Value

1/2 inch 780-900 lb-in (88-102 N*m)

Hardware
Description Torque Value

1/4 inch 50-75 lb-in (6-8 N*m)

5/16 inch 80-125 lb-in (9-14 N*m)

3/8 inch 175-225 lb-in (20-25 N*m)


1/2 inch 250-350 lb-in (28-40 N*m)

Hardware
Description Torque Value

3/8 inch 175-225 lb-in (20-25 N*m)

1/2 inch 250-350 lb-in (28-40 N*m)

■ 20
Hardware
Description Torque Value
Square Head (Tee)
Conical Washer OD Bolt Conical Washer

0.87 inches (22 mm) 250-280 lb-in (28-32 N*m)


3/8 inch
1 inch (25 mm) 130-150 lb-in (15-17 N*m)

1.25 inches (32 mm)


1/2 inch
2.25 inches (57 mm) 450-550 lb-in (51-62 N*m)

Hardware
Description Torque Value
Hex Head Bolt
Conical Washer OD (2) Conical Washers

5/16 inch 0.90 inches (23 mm) 145-260 lb-in (16-29 N*m)

0.87 inches (22 mm) 250-280 lb-in (28-32 N*m)


3/8 inch
1 inch (25 mm) 130-150 lb-in (15-17 N*m)

1.25 inches (32 mm)


1/2 inch 2.25 inches (57 mm) 780-900 lb-in (88-102 N*m)
3.00 inches (75 mm)

21 ■
9. Switchboard Insulation Resistance
Chart

NOTE: The use of a AC dielectric tester for testing the motor control center is not recommended. Use an insulation
resistance tester with a capacity of 500-1000 V DC.

Phase-to-Phase Phase-to-Ground Neutral-to-Ground

Date All Disconnects Open


A-B B-C C-A A-GND B-GND C-GND N-GND

Phase-to-Phase Phase-to-Ground Neutral-to-Ground

Date All Disconnects Closed


A-B B-C C-A A-GND B-GND C-GND N-GND

■ 22
10. Operations and Maintenance
Documents

This standard refers to manufacturers’ packing label 4.5a, 4.5d). This material, plus as-built drawings,
warnings (2.1a), instruction manuals, literature, should be assembled, identified, and delivered to the
drawings (Section 3), recorded values of tests (4.2, owner of the facility at the completion of the installa-
7.3.2, 9), and set values of adjustable trips (4.4 and tion.

23 ■
(This annex is not part of the standard)

Annex A: Reference Standards

This publication, when used in conjunction with the National Electrical Code and manufacturers’ literature,
provides sufficient information to install and maintain switchboards.

National Fire Protection Association


1 Batterymarch Park
P.O. Box 9101
Quincy, MA 02269-9101
(617) 770-3000 tel
(617) 770-3500 fax
www.nfpa.org

NFPA 70-2005, National Electrical Code (ANSI)

NFPA 70E-2004, Standard for Electrical Safety in the Workplace

Current National Electrical Installation Standards™ Published by NECA:

National Electrical Contractors Association


3 Bethesda Metro Center, Suite 1100
Bethesda, MD 20814
(301) 215-4504 tel, (301) 215-4500 fax
www.neca-neis.org

NECA 1-2006, Standard for Good Workmanship in Electrical Construction (ANSI)


NECA 90-2004, Recommended Practice for Commissioning Building Electrical Systems (ANSI)
NECA 100-2006, Symbols for Electrical Construction Drawings (ANSI)
NECA 101-2006, Standard for Installing Steel Conduits (Rigid, IMC, EMT) (ANSI)
NECA 102-2004, Standard for Installing Aluminum Rigid Metal Conduit (ANSI)
NECA/AA 104-2006, Recommended Practice for Installing Aluminum Building Wire and Cable (ANSI)
NECA/NEMA 105-2002, Recommended Practice for Installing Metal Cable Tray Systems
NECA 111-2003, Standard for Installing Nonmetallic Raceways (RNC, ENT, LFNC) (ANSI)
NECA/NACMA 120-2006, Standard for Installing Armored Cable (AC) and Metal-Clad Cable (MC) (ANSI)

■ 24
Recommended Practice for Installing and Maintaining Switchboards NECA 400

NECA 200-2002, Recommended Practice for Installing and Maintaining Temporary Electrical Power at
Construction Sites (ANSI)
NECA 202-2006, Standard for Installing and Maintaining Industrial Heat Tracing Systems (ANSI)
NECA 230-2003, Standard for Selecting, Installing, and Maintaining Electric Motors and Motor Controllers (ANSI)
NECA/FOA 301-2004, Standard for Installing and Testing Fiber Optic Cables (ANSI)
NECA 303-2005, Standard for Installing Closed-Circuit Television (CCTV) Systems (ANSI)
NECA 305-2001, Standard for Fire Alarm System Job Practices (ANSI)
NECA 331-2004, Standard for Building and Service Entrance Grounding and Bonding
NECA 400-2007, Standard for Installing and Maintaining Switchboards (ANSI)
NECA 402-2007, Recommended Practice for Installing and Maintaining Motor Control Centers (ANSI)
NECA/EGSA 404-2007, Standard for Installing Generator Sets (ANSI)
NECA 406-2003, Standard for Installing Residential Generator Sets (ANSI)
NECA 407-2002, Recommended Practice for Installing and Maintaining Panelboards (ANSI)
NECA 408-2002, Recommended Practice for Installing and Maintaining Busways (ANSI)
NECA 409-2002, Recommended Practice for Installing and Maintaining Dry-Type Transformers (ANSI)
NECA 410-2005, Standard for Installing and Maintaining Liquid-Filled Transformers (ANSI)
NECA 411-2006, Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS) (ANSI)
NECA 430-2006, Standard for Installing Medium-Voltage Metal-Clad Switchgear (ANSI)
NECA/IESNA 500-2006, Standard for Installing Indoor Commercial Lighting Systems (ANSI)
NECA/IESNA 501-2006, Standard for Installing Exterior Lighting Systems (ANSI)
NECA/IESNA 502-2006, Standard for Installing Industrial Lighting Systems (ANSI)
NECA 503-2005, Standard for Installing Fiber Optic Lighting Systems
NECA/BICSI 568-2006, Standard for Installing Commercial Building Telecommunications Cabling (ANSI)
NECA/MACSCB 600-2003, Recommended Practice for Installing and Maintaining Medium-Voltage Cable (ANSI)
NECA/NEMA 605-2005, Recommended Practice for Installing Underground Nonmetallic Utility Duct (ANSI)

24 ■
<This page intentionally left blank.>
N A T I O N A L E L E C T R I C A L I N S T A L L A T I O N S T A N D A R D S

National Electrical
Contractors Association
3 Bethesda Metro Center
Suite 1100
Bethesda, MD 20814
301-657-3110
fax: 301-215-4500
www.neca-neis.org

Standards & Safety


Index: NECA 400 (R-07)
2.5K/7-07

You might also like