You are on page 1of 74

®

NECA 90-2015
Standard for

Commissioning Building
Electrical Systems

AN AM ERIC AN N ATI O NA L S TA NDA RD

Published by
National Electrical Contractors Association
NECA 90-2015
Standard for

Commissioning Building
Electrical Systems

An American
National Standard

®
TM

Published by
National Electrical
Contractors Association
Revision History
NECA 90-2004 originally published 03/2004
NECA 90-2009 revised 12/2009
NECA 90-2015 revised 09/2015

NOTICE OF COPYRIGHT
This document is copyrighted by NECA

ISBN: 978-1-944148-05-8

©2015. Reproduction of these documents either in hard copy or soft (including posting on the web) is
prohibited without copyright permission. For copyright permission to reproduce portions of this document,
please contact NECA Standards & Safety at (301) 215-4549, or send a fax to (301) 215-4500.

OR

National Electrical Contractors Association


3 Bethesda Metro Center, Suite 1100
Bethesda, Maryland 20814
(301) 657-3110
Table of Contents

Foreword...............................................................................................................................................v

1. Scope............................................................................................................................................... 1
1.1 Products and Applications Included................................................................................................................1
1.2 Products and Applications Excluded...............................................................................................................1
1.3 Regulatory and Other Requirements...............................................................................................................1
1.4 Mandatory Requirements, Permissive Requirements, Quality and Performance Recommendations,
Explanatory Material, and Informative Annexes.............................................................................................2

2. Definitions....................................................................................................................................... 3

3. Safety............................................................................................................................................... 6
3.1 General ..............................................................................................................................................................6
3.2 Safe Work Practices...........................................................................................................................................7
3.3 De-energizing Electrical Equipment ...............................................................................................................8
3.4 Battery Systems..................................................................................................................................................8
3.5 Automatic (Remote) Operation.....................................................................................................................10
3.6 Rotating Machinery........................................................................................................................................11
3.7 Operating Temperatures.................................................................................................................................11
3.8 Generator Fuel Systems and Exhaust Gases..................................................................................................11

4. Commissioning Process.................................................................................................................. 12
4.1 Overview .........................................................................................................................................................12
4.2 Commissioning Plan (CP)..............................................................................................................................13
4.3 Commissioning Authority (CxA) Roles and Responsibilities .....................................................................13
4.4 Electrical Design Engineer Roles and Responsibilities ................................................................................14
4.5 Contractor Roles and Responsibilities ..........................................................................................................15
4.6 Documentation...............................................................................................................................................17

5. Testing Requirements..................................................................................................................... 18
5.1 Test Equipment ...............................................................................................................................................18
5.2 Pre-Startup, Startup, and Post-Startup Procedures.......................................................................................19
5.3 Pre-Functional Performance Procedures and Checklists .............................................................................19
5.4 Functional Performance Procedures .............................................................................................................20
5.5 Commissioning Requirements of Electrical Equipment..............................................................................21
5.6 Deferred Functional and Seasonal Testing ...................................................................................................52

6. Recording and Documenting Performance.................................................................................... 53


6.1 Documentation...............................................................................................................................................53
6.2 Non-conformance Forms...............................................................................................................................53

iii n
NECA 90 Standard for Commissioning
Recommended Practice for Commissioning
Building Electrical
Building
Systems
Electrical Systems

7. Operating and Maintenance (O&M) Manuals................................................................................ 55

8. Training.......................................................................................................................................... 56

Annex A: Electrical Testing Procedures ............................................................................................. 57


A.1 General ............................................................................................................................................................57
A.2 Vibration Monitoring ....................................................................................................................................57
A.3 Contact Resistance .........................................................................................................................................57
A.4 Infrared Scan ..................................................................................................................................................57
A.5 Insulation Power Factor .................................................................................................................................58
A.6 Battery Impedance..........................................................................................................................................59
A.7 Breaker Timing ...............................................................................................................................................59
A.8 Insulation Resistance Testing .........................................................................................................................59
A.10 Tan-Delta (Dissipation Factor) Testing Using Very Low Frequency (VLF) Test Set...................................62
A.11 Partial Discharge Testing ................................................................................................................................63

Annex B: Reference Standards........................................................................................................... 64

n iv
(This foreword is not a part of the standard)

Foreword

National Electrical Installation Standards™ are Suggestions for revisions and improvements to this
intended to improve communication among standard are welcome. They should be addressed to:
specifiers, purchasers, and suppliers of electrical
construction services. They define a minimum NECA Standards & Safety
baseline of quality and workmanship for installing 3 Bethesda Metro Center, Suite 1100
electrical products and systems. NEIS™ are intended Bethesda, MD 20814
to be referenced in contract documents for electrical (301) 215-4521 telephone
construction projects. The following language is (301) 215-4500 fax
recommended: neis@necanet.org
www.neca-neis.org
All electrical systems shall be commissioned in
accordance with NECA 90-2015, Recommended To purchase National Electrical Installation
Practice for Commissioning Building Electrical Standards, contact the NECA Order Desk at (301)
Systems (ANSI). 215-4504 tel, (301) 215-4500 fax, or orderdesk@
necanet.org. NEIS can also be purchased in .pdf
Use of NEIS is voluntary, and the National Electrical download format from www.neca-neis.org/standards.
Contractors Association assumes no obligation or
liability to users of this publication. Existence of a Copyright © 2015, National Electrical Contractors
standard shall not preclude any member or non- Association. All rights reserved. Unauthorized
member of NECA from specifying or using alternate reproduction prohibited.
construction methods permitted or required by First edition (2004) jointly developed with Enviro-
applicable codes or regulations. Management & Research, Inc.

This publication is intended to comply with the National Electrical Installation Standards, NEIS, and
National Electrical Code (NEC). Because they are the NEIS logo are trademarks of the National Electrical
quality standards, NEIS may in some instances Contractors Association. National Electrical Code and
go beyond the minimum safety requirements of NEC are trademarks of the National Fire Protection
the NEC. It is the responsibility of users of this Association, Quincy, Massachusetts.
publication to comply with state and local electrical
codes and Federal and state OSHA safety regulations
as well as follow manufacturers installation Cover photo courtesy of Fluke Corporation.
instructions when installing electrical products and
systems.

v n
<This page intentionally left blank>
1. Scope

1.1 Products and Applications Included • Commissioning and acceptance testing required
in accordance with applicable national, state,
This standard describes installation procedures
and local codes and regulations for life safety
for start-up, testing, and commissioning newly
systems, emergency systems, and critical
installed or retrofitted building electrical systems,
operations power systems (COPS) in addition
equipment, and components. It defines the process
to the generic commissioning and acceptance
of commissioning building electrical systems,
testing required by this Standard.
equipment, and components, and provides
sample guidelines for attaining optimum system • On-going commissioning and/or maintenance
performance that conform to design, specification, testing required by applicable national, state,
and industry accepted codes and standards. and local codes and regulations for specific
applications and systems, such as healthcare
This Standard addresses those commissioning facilities and emergency systems.
activities that typically involve the electrical sub-
contractor and that are completed during and after
the construction phase. The commissioning process 1.3 Regulatory and Other Requirements
also involves activities that are beyond the scope of All information in this publication is intended to
this Standard. conform to the NEC (ANSI/NFPA 70). Installers
shall follow the NEC, applicable state and local
1.2 Products and Applications Excluded codes, manufacturer instructions, and contract
documents when commissioning building electrical
This standard is not intended to cover specific systems.
commissioning processes for every type of electrical
system, equipment, or component. Other NEIS Only qualified persons as defined in the NEC familiar
documents that include commissioning and testing with the commissioning of building electrical systems
requirements for electrical systems, equipment, and shall perform the technical work described in this
components are included as references and are listed publication. Administrative and commissioning
in Annex B. support functions such as receiving, handling and
storing and other tasks may be performed under the
In addition, this standard does not cover: supervision of a qualified person. All work shall be
performed in accordance with NFPA 70E, Standard
• Procedures for commissioning systems such
for Electrical Safety in the Workplace.
as fire alarm systems, telecommunications
networks, closed circuit television (CCTV) General requirements for installing electrical
systems, access control systems, and other products and systems are described in NECA 1,
limited energy systems. Standard for Good Workmanship in Electrical
• Testing of specialty equipment and systems, Construction (ANSI). Other NEIS provide additional
such as transformers, wiring, and line isolation guidance for installing particular types of electrical
monitors installed as part of isolated power products and systems. Other reference standards and
systems for wet locations in healthcare facilities. a complete list of NEIS are provided in Annex B.

1 n
NECA 90 Standard for Commissioning Building Electrical Systems

1.4 Mandatory Requirements, Permissive Quality and Performance Recommendations.


Requirements, Quality and Performance Quality and performance recommendations identify
Recommendations, Explanatory Material, actions that are recommended or not recommended
and Informative Annexes to improve the overall quality or performance of the
installation and are characterized by the use of the
Mandatory Requirements. Mandatory requirements term should or should not.
in manufacturer instructions, or of Codes or
other mandatory Standards that may or not be Explanatory Material. Explanatory material, such as
adopted into law, are those that identify actions references to other Codes, Standards, or documents,
that are specifically required or prohibited and references to related sections of this Standard,
are characterized by the use of the terms must or information related to another Code, Standard, or
must not, shall or shall not, or are not permitted, or document, and supplemental application and design
are required, or by the use of positive phrasing of information and data, is included throughout this
mandatory requirements. Examples of mandatory Standard to expand the understanding of mandatory
requirements may equally take the form of, requirements, permissive requirements, and
“equipment must be protected…,” “equipment shall quality and performance recommendations. Such
be protected…,” or “protect equipment…,” with the explanatory material is included for information
latter interpreted (understood) as “(it is necessary to) only, and is identified by the use of the term
protect equipment…”. “NOTE,” or by the use of italicized text.

Permissive requirements of manufacturer Informative Annexes. Non-mandatory information


instructions, or of Codes or other mandatory and other reference standards or documents relative
Standards that may or not be adopted into law, to the application and use of materials, equipment,
are those that identify actions that that are allowed and systems covered by this Standard are provided
but not required, or are normally used to describe in informative annexes. Informative annexes are
options or alternative means and methods, and not part of the enforceable requirements of this
are characterized in this Standard by the use of the Standard, but are included for information purposes
terms may or may not, or are permitted, or are not only.
required.

n 2
2. Definitions

A/E Architect/Engineer. The prime consultants Cx Commissioning. A systematic process for


who comprise the design team, generally the verifying that building electrical systems perform in
Architect, HVAC mechanical designer/engineer, the accordance with the design intent and the Owner’s
control system engineer/designer, and the electrical operational requirements. Commissioning is
designer/engineer. typically completed in phases (by system, by area,
or by floors, for example) due to the complexity of
Approval Acceptance that a piece of equipment or the project, size of the structure, or other scheduling
system has been properly installed and is functioning in issues, in order to minimize total construction time.
the tested modes according to the contract documents.
CxA Commissioning Authority. Individual
BOD Basis of Design. A document that records or company responsible for developing and
the design criteria upon which the design is based. coordinating the execution of a commissioning plan
(CP), observing and documenting performance,
Commissioning Checklists Verification checklists
and ensuring that building systems and equipment
developed and used during all phases of the
function in accordance with the design intent and
commissioning process to verify that the Owner’s
the Owner’s operational requirements.
project requirements are being achieved, including
general verification and construction checklists, Deferred Functional Tests Functional tests that
along with start-up checklists, pre-functional are performed after substantial completion due to
checklists, functional checklists and other specific partial occupancy, seasonal loading requirements,
requirements such as testing and training. design, or other site conditions that prevent
tests from being performed prior to substantial
Commissioning Team Working group made
completion.
up of representatives from the Architect/Engineer
(A/E), general contractor, sub-contractors, specialty Deficiency A condition in the installation or
manufacturers, suppliers, and the Owner as required function of a component, piece of equipment, or
for implementation of the CP. system that is not in compliance with the contract
documents.
Contract Documents Documents binding on
parties involved in the completion of the Project Design Intent A narrative description of systems
(contracts, amendments, drawings, specifications, and equipment and their intended modes and
contract modifications or change orders, and CP). sequences of operation as documented in the project
documents, drawings and specifications.
Contractor The general contractor or their
authorized representative. Factory Testing Testing of equipment at the
factory by factory personnel, with an Owner’s
CP Commissioning Plan. A document that
representative present if deemed necessary by
outlines the organization, scheduling, coordination,
Owner.
and allocation of resources and documentation
for the overall commissioning process from the
construction phase through the warranty period.

3 n
NECA 90 Standard for Commissioning Building Electrical Systems

Functional Performance Tests A full range One-Year Correction Period A contractual time
of checks and tests carried out to determine if all period during which a construction contractor has
systems, sub-systems, equipment, and components the right and/or obligation to rectify any failed work.
function in accordance with the design intent. The correction period addresses deficiencies that
Systems are tested under various modes of operation, arise after the project has been completed. NOTE:
such as during low loads, high loads, component During the correction period, it is generally necessary
failures, unoccupied periods, varying outside air to determine why the work failed. If the failure is
temperatures, fire alarm activation, and power due to misuse, abuse, lack of maintenance, or the
failure. Functional Performance Tests are performed like, the contractor is not considered responsible for
after start-ups and Pre-Functional Procedures are rectifying the failure. After the one-year correction
complete. period, the responsibility falls to the project Owner
to demonstrate that the original work was not
Integrated System Test A full range of checks completed according to specifications or that a specific
and tests carried out to determine if systems that component of the project didn’t last as long as it
are integrated together and are dependent upon should have.
other systems for proper operation function and
interact in accordance with the design intent. Owner’s Project Requirements Documentation
Systems are tested under various modes of operation, of the primary thought processes and assumptions
such as during low loads, high loads, component behind design decisions and that describes the
failures, unoccupied periods, varying outside air systems, components, conditions, and methods
temperatures, fire alarm activation, and power chosen to meet the Design Intent.
failure. Integrated System Tests are performed after
Functional Performance Tests are complete and Pre-Functional Procedures A full range of
prior to Substantial Completion. inspections and checks of materials and components
that verify proper installation of equipment (e.g.,
MOP Method of Procedure. A script that is anchor bolts tightened, grounding connections
normally prepared for working on critical systems complete, conductors terminated, connections
and equipment that details all elements of the work torqued, compartments cleaned, panels and covers
to be performed, typically in a checklist form, and installed, for example). Pre-functional procedures,
includes spaces for dates and times of critical steps, checks and tests, are completed before Functional
and for authorization and signatures of responsible tests. Pre-functional procedures are typically
parties. Elements typically incorporated into an MOP documented in a checklist format, and typically
include safety requirements, staffing requirements, include manufacturer start-up checklists.
tool inventories, lists of materials, parts, and supplies
needed, weather/environmental factors, notification Start-up Activities where equipment is initially
of interested and involved parties, back-out plans, energized, operated, and tested. Start-up is
emergency responses, and the specific step-by-step completed prior to Functional Performance Tests.
sequence of tasks involved, among others.
Test Requirements Requirements specifying the
Non-Compliance See Deficiency. systems, operating modes, and functions that must
be tested.
Non-Conformance See Deficiency.

n 4
Standard for Commissioning Building Electrical Systems NECA 90

Verification The full range of checks and tests


carried out to determine if all components, sub-
systems, systems, and interfaces between systems
operate in accordance with the design intent
and Owner’s requirements, including all modes
and sequences of control operation, interlocks
and conditional control responses, and specified
responses to abnormal or emergency conditions.

Warranty Period Contractual obligation for the


contractor to repair or replace defective materials
and/or workmanship within the specified period
of time. Warranty period covers equipment, parts,
and/or labor for the entire project, and includes any
individual equipment components and optional
extended warranties that are included in the project.
The Warranty period typically begins at the time of
Substantial Completion and typically extends for
a minimum of one year, unless specifically noted
otherwise in the Contract Documents and accepted
submittals. NOTE: The warranty period may be
overridden by obligations of the One-Year Correction
Period. See One-Year Correction Period.

5 n
3. Safety

3.1 General become familiar with the equipment and the hazards
specific to the equipment. Read all related safety
NOTE: Many tests on electrical equipment involve
instructions and carefully observe all instructions,
the use of high test voltages and currents that are life
warnings, and precautions in this Standard and in
hazards to personnel and are capable of damaging
the equipment manufacturer instructions. Observe
or destroying the equipment under test. Institute and
all safety warning labels on equipment.
practice safety rules to prevent injury to personnel
who are performing the tests and others who might be Individuals performing tests and inspections shall
exposed to hazards. Use test procedures designed to be capable of working in a safe manner and with
ensure that no intentional damage to equipment will complete knowledge of the hazards and methods of
result from the testing process. mitigating the risks involved.
Commissioning electrical equipment includes Safety practices shall include, but are not limited to,
inspecting and testing equipment during its the following requirements:
operation. Hazards exist as an unavoidable
characteristic of operating and testing electrical • All applicable provisions of the Occupational
equipment. While the hazard remains, risks can be Safety and Health Act, particularly OSHA 29
mitigated through good engineering design, proper CFR 1910.
work practices, and protective equipment.
• ANSI/NFPA 70E, Standard for Electrical Safety
Electrical equipment hazards include electrocution in the Workplace.
and electric shock (energized equipment, stored
energy in batteries and capacitors, multiple sources of • Accident Prevention Manual for Industrial
electricity), toxic chemicals (electrolyte and hydrogen Operations, National Safety Council.
from batteries, engine-generator oil and coolant), • Manufacturer instructions.
asphyxiation (engine-generator exhaust fumes,
products of combustion), explosion (hydrogen from • Applicable state and local safety operating
batteries, fuels from engine-generators, arc-flash), procedures.
rotating machinery (motors and engine-generators),
corrosive liquids (battery electrolyte), corrosive vapors • Owner’s safety practices.
(cracked or leaky batteries), fire and explosion hazard The following are examples of good procedures to
(hydrogen gas generated during battery charging follow when commissioning electrical equipment:
cycles, fuels for engine-generators), hazardous
fumes or vapors (products of combustion due to • Conduct a hazard identification and risk
fire), confined spaces (manholes), arc flash burns, assessment prior to any work on electrical
and thermal burns (engine-generator components, equipment. The risk assessment shall be
batteries, products of combustion), among others. applicable to the specific task to be performed,
and shall determine the appropriate level of
Prior to commissioning equipment, read all related personal protective equipment (PPE) to be worn
installation, operation, and Owner’s manuals to while performing the task.

n 6
Standard for Commissioning Building Electrical Systems NECA 90

• Follow manufacturer instructions and Maintain as much distance as practical from


recommendations for electrically isolating equipment and devices that may arc during
electrical equipment and components. operation or handling, but not less than the arc flash
protection boundary specified in NFPA 70E.
• Check electrical equipment and components for
AC and DC voltages to ensure that equipment Use appropriate Personal Protective Equipment
is electrically safe before performing any (PPE) and established safety procedures when
commissioning, inspections, or testing. working on or near energized electrical equipment
or equipment that has not been de-energized, tested,
• Open all external disconnects or circuit breakers locked out, grounded, and tagged in accordance with
to completely isolate equipment from all AC NFPA 70E. Wear appropriate personal protective
and DC power sources. equipment in accordance with the Arc Flash Hazard
• Open DC circuit breakers to completely isolate and incident energy level of the equipment.
equipment from batteries.
Use suitable insulated hand tools when working on
• Check capacitors for voltage and discharge. or around energized equipment. Use only properly
Wait a minimum of five minutes for capacitors rated tools for the energy present. Maintain tool
to discharge before entering electrical inventories to ensure that all tools are accounted
equipment cabinets. for prior to energizing equipment. Carefully inspect
the work area and remove any tools and objects left
Keep enclosure and access doors secured when inside before energizing equipment.
not working inside electrical equipment to ensure
proper cooling airflow and to protect personnel Operate electrical equipment only when all guards
from dangerous voltages inside equipment. Ensure and electrical enclosures are in place. Install all
that doors cannot create a hazard when open due to devices, doors, and covers before energizing. Do not
door swing or limited work space around equipment. tamper with or defeat safeties or interlocks. Do not
NOTE: Some equipment may have lock-bars for make any modifications to the equipment or operate
compartment doors or removable doors for this purpose. the system with interlocks or safety barriers removed.

During normal operation, hazardous voltages are


3.2 Safe Work Practices present on control circuits, potential transformers
Perform preliminary inspections and tests prior to (PTs) and terminal strips. PT and current
beginning work to determine existing conditions. transformers (CTs) secondary circuits are capable
Check existing conditions against available record of generating lethal voltages and currents with
documents. Resolve discrepancies between installed the primary circuits energized. Do not open-
conditions and electrical drawings. Have drawings circuit current transformer secondary circuits
corrected, if required. Provide warning labels on while equipment is energized. Open-circuited CT
equipment and cables where necessary to indicate terminals can develop extremely high voltage and are
unexpected and potentially hazardous conditions. a significant shock hazard. Follow standard safety
precautions, such as removing PT fuses and shorting
Visually verify conductor routing through all CT secondaries.
raceways, manholes, and vaults. Visually verify all
conductor connections to equipment. Confirm that All workers in manholes must have OSHA Training/
supply and load conductors are connected properly Certification for Confined Space Access. Crews
to equipment. Keep in mind that transposed working in confined spaces shall consist of two or
conductors may be connected to different terminals more persons with at least one remaining outside
than expected. the confined space at all times. Maintain a personnel
retrieval system at the site.

7 n
NECA 90 Standard for Commissioning Building Electrical Systems

Test manholes and unventilated vaults for opening compartments and testing for potential and
combustible or flammable gases and for oxygen before applying personal protective grounds. Apply
deficiency before entry. Where combustible or locks and tags in accordance with NFPA 70E and
flammable gases are detected, ventilate the work area OSHA. Secure source circuit breakers and switches
to safe levels before entering. Provide continuous with locks and tags in accordance with NFPA 70E.
monitoring of occupied manholes and vaults for Leave locks and tags in place until the work is
gasses and oxygen deficiency. completed and the equipment is ready to be put into
service.
Provide continuous, mechanically supplied fresh
air to manholes and vaults when occupied. Provide Verify that circuit breakers and switches are open
blowers to force fresh air into manholes or confined by testing that desired cables and equipment are
areas where free movement or circulation of air de-energized. Use electrical testing equipment rated
is obstructed. Ensure air flow from manholes for the operating voltage of the system. Test voltage
or confined areas is properly ventilated at duct sensing equipment on a known, energized source
entrances into buildings. immediately before and after testing the equipment
to be tested to ensure that voltage sensing equipment
Ensure adequate ventilation where open flames must is operating properly.
be used in manholes or vaults.
Attach listed personal protective grounds on
Ensure that there is access to a fire extinguisher with conductors and equipment that are sufficient for
an ABC or BC rating, or as recommended by the the available short-circuit current from the supplier.
local Fire Code or an authorized agency, for electrical For conductors equipped with reconnectable
fires. terminations, disconnect conductors from
terminal bushings and park on stands. Follow the
3.3 De-energizing Electrical Equipment manufacturer instructions for grounding conductors
with reconnectable terminations. Connect personal
Consider all equipment and devices to be energized
protective grounds to the line terminals of the main
unless they are de-energized, tested, locked out, and
circuit breaker or main lugs, to the neutral terminal
tagged out in accordance with OSHA requirements.
bus bar, if so equipped, and to the grounding
Electrical equipment may have multiple sources
terminal of equipment.
of power. Expect hazardous voltages in all
interconnecting components and conductors.
3.4 Battery Systems
Do not work on energized conductors or equipment.
Follow manufacturer installation, servicing, and
Using established safety procedures, guard energized
maintenance instructions, or follow industry
conductors and equipment in close proximity to
standards.
work.
NOTE: A battery is a source of stored energy. Voltage
Place equipment in an electrically safe work
is always present in each battery string. Batteries
condition. De-energize as many loads as is practical
connected in series and strings connected in parallel
before performing any switching procedures.
can have high voltage and current capacities. Opening
Transfer loads to alternate sources of power, when
the battery disconnecting means does not de-energize
possible. Follow manufacturer instructions for
the voltage within the battery string itself. Shock
electrically isolating equipment. Open all external
potential is greatest at the terminals of a battery.
disconnects or circuit breakers to completely isolate
Battery voltages can cause injury and death if contact
all power sources, including batteries.
is made between positive and negative terminals or
Follow lock-out/tag-out (LOTO) procedures. Locks conductors. Take care to avoid contact with both
and tags should be placed on equipment prior to battery terminals at the same time.

n 8
Standard for Commissioning Building Electrical Systems NECA 90

NOTE: Contact of eyes and mucus membranes with and cracking battery containers, and the hazard
electrolyte can cause severe burns and blindness. of oxygen depletion within the space. Local codes
During charging, batteries can produce and/or emit identify the permissible fire protection methods.
a highly flammable mixture of hydrogen and oxygen
which can be explosive in high concentrations. If an emergency eye wash or quick-drench shower
are located near the battery area they shall be
Appropriate safety equipment shall be used as maintained in accordance with manufacturer
deemed necessary by a risk assessment of the instructions and federal, state, and local regulations
task being performed while in battery rooms or pertaining to such equipment.
when working near batteries. Personal protective
equipment (PPE) required for working on battery Do not attempt to disassemble or in any way handle
systems is identified in NFPA 70E. Remove all batteries that are, or have recently been, involved
jewelry before servicing equipment. Goggles shall in fire. Batteries can explode or release hazardous
always be worn. Other PPE typically includes, but substances when exposed to extreme heat or fire.
is not limited to, face shields, safety glasses with
3.4.1 Battery Electrical Safety
side shields and splash protection, head protection
appropriate for environments with electrical hazards, Adhere to the following practices when working
insulated rubber gloves and sleeves suitable for the around battery systems or other stored energy
voltage class of equipment present, acid- or alkali- devices to protect against electric shock or other
resistant gloves, protective or impermeable aprons, hazards:
and acid- or alkali-resistant boots or overshoes.
• Do not place tools or other conductive objects
Prior to work on a battery with free-flowing liquid on battery cells, racks, or tiers.
electrolyte (such as vented lead-acid or vented nickel-
cadmium batteries), verify the presence of a complete • Use insulated tools to protect against shorting of
spill clean-up kit in the room that is appropriate for the cells.
hazard and risk. Sufficient neutralizing agent shall be
• Use PPE based on the hazard analysis and risk
readily available to neutralize, at a minimum, the total
assessment performed prior to work on the
electrolyte in a single cell or multi-cell container, to a
battery. PPE shall be appropriate for the task to
pH of 5-9. Spill prevention, abatement methods and
be completed.
equipment shall be in accordance with IEEE Std. 1578,
IEEE Recommended Practice for Stationary Battery • Discharge static electricity from the body before
Electrolyte Spill Containment and Management. touching cell terminal posts by first touching a
grounded surface in the vicinity of the batteries
Egress from the work area shall be unobstructed.
but away from the cells and flame arrestors.
Verify that fire suppression systems are: Disconnect the charging source prior to connecting
• Suitable for use in electrical fires per the or disconnecting battery terminals.
equipment safety data sheets (SDS). Verify the battery grounding method prior to
• Suitable for use with any chemicals likely to be working on the battery system. Inspect batteries
liberated if the battery is consumed in flame. for inadvertent grounding during installation and
maintenance. Remove inadvertent grounds to
• Tested to be operational with the date of the reduce the likelihood of shock. Disconnect battery
most recent test readily available. ground connections only in accordance with the
manufacturer instructions.
Use of CO2 Class C fire extinguishers may not be
permitted due to the potential of thermal shock

9 n
NECA 90 Standard for Commissioning Building Electrical Systems

3.4.2 Electrolyte times faster than natural gas. Hydrogen is a severe fire
hazard when exposed to heat, flame, or oxidizer, and
NOTE: Electrolyte in contact with the eyes or mucus can become explosive in high enough concentrations.
membranes can cause severe burns or blindness. If The flammability range for hydrogen is very wide with
electrolyte comes in contact with eyes, nose, or mouth, a lower flammability limit of 4.1% by volume and the
flush the affected area immediately with copious upper limit of 74.2%.
amounts of water and obtain medical assistance
immediately. Electrolyte in contact with the skin can Verify that battery rooms and compartments
cause an allergic reaction to some people. Electrolyte is with lead-acid batteries are adequately ventilated
very acidic and caustic. If electrolyte comes in contact to prevent hydrogen levels from exceeding levels
with the skin, wash thoroughly with soap and water. specified in local codes. NOTE: Fire codes typically
Refer to battery safety data sheets (SDS) shipped with stipulate a 1% concentration by volume of the
the system for further information. space, and require alarm notification and forced air
ventilation for battery locations where concentrations
Wear personal protective equipment, including eye can be expected to rise above 1%. Gassing rates can
and skin protection, when performing tasks that be affected by temperature, air pressure, the battery
potentially expose a worker to electrolyte. construction, and the amount of charge current
passing through cells. Not all gas generated in a
Follow the manufacturer instructions to neutralize
battery escapes to the atmosphere. Calculations
an electrolyte leak or spill. NOTE: Some chemicals
for hydrogen ventilation shall be performed by a
can cause damage to the cell container. A common
qualified person based upon data provided by the
neutralizer for lead-acid electrolyte is a bicarbonate
battery manufacturer for the battery under specified
of soda solution in a concentration of one pound per
conditions. Additional ventilation may be required
gallon of water to neutralize acid spilled on clothing
during the activation charging cycle or other
or material. Apply the solution until bubbling stops,
charging regimens.
and then rinse with clear water.
Open flames, sparks, hot plates, smoking, or any
NOTE: Guidelines for the design of electrolyte spill
other ignition sources are prohibited near batteries,
protection and response to electrolyte spills can be
gas ventilation paths, or anywhere that hydrogen
found in IEEE 1578, IEEE Recommended Practice
can accumulate. Discharge static electricity from the
for Stationary Battery Electrolyte Spill Containment
body before touching batteries by first touching a
and Management. Guidelines for personal protective
grounded metal surface.
equipment around batteries can be found in the
manufacturers safety data sheets, in IEEE standards
applicable to the battery technology, or in NFPA 70E, 3.5 Automatic (Remote) Operation
Standard for Electrical Safety in the Workplace. NOTE: Equipment that is controlled remotely or
automatically may start and operate unexpectedly.
3.4.3 Hydrogen Gas
Accidental or unexpected starting can cause severe
NOTE: As batteries charge, hydrogen, which is a injury or death.
colorless, odorless, and tasteless gas that is non-toxic
under normal conditions, may be released. Hydrogen Protect against accidental energization of automatic
is the smallest, the lightest, and one of the most or remotely controlled equipment by identifying,
common molecules in the known universe. Hydrogen opening, locking, and tagging starting devices. Do
diffuses rapidly with the slightest amount of air not connect controls or control power to electrical
movement. Hydrogen is extremely difficult to contain equipment until the installation is complete and the
and can even penetrate concrete blocks. Hydrogen will equipment is ready to operate. Become familiar with
always tend to rise to the highest level of a confined equipment control schemes prior to commissioning.
space, rising two times faster than helium and six

n 10
Standard for Commissioning Building Electrical Systems NECA 90

3.6 Rotating Machinery present or other explosive conditions exist. Never


add fuel manually to a sub-base fuel tank or day
Ensure that all panels, doors and covers are attached
tank while the engine is running. NOTE: Spilled fuel
and closed whenever rotating equipment, such
may ignite on contact with hot parts or components,
as flywheels, motors, and engine-generators, are
or from sparks. When checking, draining, or adding
operating. Operate equipment only when all guards,
diesel fuel to a generator, take care not to ingest,
screens, and electrical enclosures are in place. Make
breathe the fumes, or contact the fuel.
sure that fasteners on equipment are secure. Ensure
that supports and clamps are tight. Do not smoke or permit flames, cigarettes, pilot
lights, sparks, arcing equipment or other ignition
If adjustments must be made while equipment
source near the carburetor, fuel line, fuel filter, fuel
is running with protective guards and barriers
pump, fuel tank, or other potential sources of spilled
removed, use extreme caution around moving parts.
fuels or fuel vapors.
Do not wear loose clothing or jewelry in the vicinity
Do not operate the generator with the air filter or air
of moving parts, or while working on electrical
cleaner cover removed. NOTE: A sudden backfire can
equipment. NOTE: Loose clothing, jewelry, hands,
cause severe injury or death.
and hair can become caught in moving parts. Jewelry
can short out electrical contacts and cause shock, NOTE: Exhaust gases contain carbon monoxide,
burns, or death. which is odorless, colorless, and poisonous. Avoid
breathing exhaust fumes when working on or near
3.7 Operating Temperatures the generator. Carbon monoxide can cause light-
headedness, throbbing in the temples, headache,
NOTE: Some electrical equipment components can
dizziness, stomachache, severe nausea, vomiting,
become extremely hot during operation and remain
weakness, sleepiness, fatigue, muscular twitching,
hot for a period of time after shutting down, such
inability to concentrate or speak clearly, fainting,
as motors, power electronics, and engines of engine-
unconsciousness, or death.
generators. Hot equipment components can cause
severe injury or death. If anyone experiences any symptoms of carbon
monoxide poisoning, evacuate the area, immediately
Avoid contact with hot components and parts. Do
move to fresh air, and stay active. Do not sit, lie
not work on equipment until it cools down. Use
down, or fall asleep. Alert others to the possibility of
extreme caution working around hot electrical
carbon monoxide poisoning. Seek medical attention
equipment when necessary to make adjustments
if the condition of affected persons does not improve
while equipment is running.
within minutes of breathing fresh air. Shut down the
generator and do not operate the generator until it
3.8 Generator Fuel Systems and Exhaust has been inspected and repaired. If symptoms persist,
Gases seek medical attention immediately.
NOTE: Generator fuels and fuel vapors are flammable
and highly explosive. Servicing the generator fuel
system can result in an explosion or flash fire that can
cause severe injury or death.

Do not operate the generator if the smell of fuel is

11 n
4. Commissioning Process

4.1 Overview NOTE: The commissioning process does not reduce


the responsibility of the installing contractors (general
The intention of commissioning is to ensure
contractor or sub-contractors) to provide a complete,
that all electrical equipment, components, sub-
finished and fully functioning product. In general,
systems, and systems are installed according to the
the CxA does not have the authority to provide
contract documents, construction drawings, and
direction to any contractors. Any issues arising
specifications, to manufacturer instructions, and
during commissioning which impact schedules, costs,
to industry-accepted standards, and that installed
or contractual obligations must be addressed by the
electrical equipment, components, sub-systems,
Owner for resolution.
and systems, are complete, and that they receive
adequate operational checkout and detailed testing, The documented procedures which comprise the
calibration, and adjustment by the installing construction-phase commissioning process generally
contractor (general contractor or sub-contractors). include the following:
NOTE: It is not the intent of the commissioning • Pre-Commissioning that consists of normally
process or this Standard to duplicate efforts or to specified checks and testing, and wiring and
require the general contractor or sub-contractors to controls point-to-point verification completed
perform any check or test twice. Checks and testing by the respective general contractor or sub-
are expected to occur once in the normal sequence of contractor before the formal commissioning
installation and checkout, if appropriate coordination process begins.
has occurred, allowing the Owner and the CxA to
witness installation and testing. • Pre-Functional Procedures (PFPs) that consist
of a series of field observations conducted
Commissioning of building electrical systems is a during the installation of equipment yet to be
systematic process of ensuring that all procedures, commissioned to verify that equipment and
checks, and testing is rigorously executed and components are installed in accordance with
documented, and that all systems perform in contract documents and are ready for startup.
accordance with the design intent and the Owner’s
requirements. This is achieved by verifying that the • Pre-Startup Testing that consists of the
performance meets or exceeds the designer’s intent as typically-specified testing, such as meter testing
documented in the project drawings and specifications. of electrical equipment.

The electrical commissioning process integrates the • Equipment Startup Procedures that ensure
traditionally separate functions of equipment startup, that startup is performed in accordance with
control system calibration, testing and balancing the manufacturer recommended procedures,
(including electrical load balancing as required in and that those startup activities and data are
the NEC), functional performance testing, system documented for future reference.
documentation, and training. Commissioning may
• Post-Startup Testing that consists of typical
include deferred functional and/or seasonal tests as
testing activities specified as required by
approved by the Owner.
contract documents that occurs after startup

n 12
Standard for Commissioning Building Electrical Systems NECA 90

and before Functional Performance Procedures, The CP is a dynamic document that is continuously
such as debugging. updated throughout the design, construction, and
warranty phases of the project.
• Functional Performance Procedures (FPPs) that
consist of determining if equipment and systems Commissioning of building electrical systems
operate in accordance with the design intent requires full cooperation and coordination between
and the contract documents. all trades. The roles and responsibilities of the CxA.
the electrical design engineer, general contractor,
• Operation and Maintenance Manuals that will mechanical sub-contractor, and electrical sub-
be reviewed for both content and organization. contractor are typically delineated in the contract
NOTE: The objective of the review process is documents and in the CP.
to provide the Owner with useful, complete,
project-specific information needed to successfully
operate and maintain the facility after turnover. 4.3 Commissioning Authority (CxA) Roles
and Responsibilities
• Operator Training that will be provided and
The CxA is responsible for coordinating and
coordinated by the general contractor and
directing commissioning activities in a logical,
overseen by the Owner to help ensure that
sequential, and efficient manner, using standard
operating and maintenance staff is adequately
forms and centralized documentation.
prepared to operate and maintain the facility at
turnover. The CxA is responsible for developing the CP
NOTE: The project is generally not considered to (typically during the design phase) and for
be substantially complete until the conclusion of coordinating the execution of the CP, such as
functional performance procedures as defined in the observing and documenting equipment and system
CP. The CxA reviews and coordinates the training performance, and ensuring that electrical systems
provided by any contractors and verifies that it was are functioning in accordance with the documented
completed. Deferred functional or seasonal testing is design intent and with contract documents. The
conducted as specified or required. CxA does not have authority to approve materials,
methods, and systems, but can recommend their
approval to the Owner, project manager, or
4.2 Commissioning Plan (CP) contracting officer.
The CP is typically developed and coordinated by the
CxA and is typically provided as part of the contract The CxA is the primary point of responsibility to
bid documents. The CP provides guidance for the inform the general contractor, sub-contractors,
execution of commissioning activities, and provides Owner, and design team on the status, integration,
a broad outline of the entire commissioning process. and performance of mechanical and electrical
systems within the facility. The CxA conducts
The CP typically details the commissioning an initial commissioning meeting where the
activities during design and construction, along commissioning process is reviewed with the
with occupancy and operational commissioning members, and conducts additional meetings
activities and the roles and responsibilities of all throughout construction, with necessary parties
commissioning team members, by name, firm, attending, to plan, coordinate, and schedule future
and trade specialty, for performance of each activities, and to resolve problems.
commissioning task. Commissioning team members
include the CxA, Owner, general contractor, The CxA is typically a knowledgeable industry
design engineers or Architect/Engineer (A/E), and professional, such as an electrical sub-contractor, an
mechanical and electrical sub-contractors. electrical design engineer, or a third party contracted
to perform the commissioning process. In general,

13 n
NECA 90 Standard for Commissioning Building Electrical Systems

the CxA is an independent third party agency for consistency of approach, and the type of
working under a separate contract and reporting information recorded.
directly to the Owner.
• Performing site visits, as necessary, to observe
Tasks typically completed by the CxA include, but equipment, component and system installations.
are not limited to:
• Reviewing submittals and shop drawings for
• Developing the Owners performance installation criteria and construction details as
requirements. they support and define system features.

• Developing and/or reviewing the basis of design • Coordinating, witnessing, reviewing,


(BOD). and verifying acceptability of functional
performance tests (acceptance tests) performed
• Developing the equipment energization plan. by the installing contractors (general contractor
and sub-contractors). Coordinating re-testing
• Obtaining and reviewing design and
as necessary until satisfactory performance is
construction documents to determine the
achieved.
overall design intent and the required system
configurations. • Notifying the Owner’s representative and
other concerned parties of the commissioning
• Preparing an initial CP, including an overall
schedule and of deficiencies and follow-up
testing plan and schedule for electrical systems
services undertaken to correct and re-test
that lists the equipment, modes to be tested,
deficient items for conformance with design
the scheduling requirements of testing, and the
intent and prevailing industry standards.
parties conducting the tests.
• Reviewing and verifying acceptability of
• Coordinating scheduled commissioning
Operation and Maintenance (O&M) materials,
activities with the overall project schedule,
control sequences and interlocks, startup
incorporating commissioning tests and
procedures, and checkout procedures for
tasks into the master construction schedule,
completeness and accuracy.
maintaining the CP, and updating the schedule.
• Providing detailed, data-driven reports of all
• Collaborating with the general contractor
test records, testing, results, and instructions.
and each sub-contractor to develop startup
Documenting the dates of acceptance as
plans, project-specific functional performance
determined by the general contractor, Owner
test procedures, checklists, and test forms for
and design team.
electrical equipment, components, and systems
scheduled for commissioning.
4.4 Electrical Design Engineer Roles and
• Periodically reviewing updated as-built Responsibilities
documentation for accuracy and completeness,
The electrical design engineer’s responsibilities
and verifying that documents are being kept
during the commissioning process typically include,
up-to-date.
but are not limited to:
• Developing and distributing standard
forms used by the commissioning team, • Developing design intent documentation and
including startup documentation formats establishing the basis of design (BOD) for the
and construction checklists to be completed project by evaluating the Owner’s requirements
during the installation and startup process, for equipment and systems.

n 14
Standard for Commissioning Building Electrical Systems NECA 90

• Establishing the design criteria, evaluating present during the agreed upon schedules and for
design concepts, and developing the technical sufficient duration to complete checks, sequences,
drawings and specifications for the project. procedures, tests, and adjustments, and to resolve
deficiencies that are identified in a timely fashion.
• Distributing equipment documentation to
the CxA during the normal submittal process, Installing contractors (general contractor and sub-
including detailed startup procedures. contractors) complete and submit the final as-built
documents, drawings and specifications, test reports,
• Reviewing submittals, shop drawings, and completed checklists, and updated shop drawings,
O&M documentation for conformance with after commissioning is complete for inclusion in the
project requirements, and recommending their O&M manuals that are turned over to the Owner as
approval or acceptance. part of the required deliverables for final acceptance.
• Responding to Requests for Information (RFIs).
Each sub-contractor participating in the
• Developing technical requirements for contract commissioning process should designate a single-
modifications or change orders, as needed. point contact person to work with the Owner and
other commissioning team members. The sub-
• Performing periodic construction progress contractor’s contact person should have the authority
inspections. to coordinate commissioning activities on behalf of
the sub-contractor.
• Ensuring compliance with applicable codes and
standards. Contractors (general contractor and sub-contractors)
typically provide the documentation required
• Converting red-lined as-built drawings to a
for commissioning, such as shop drawings and
digital format.
product submittal data, detailed startup procedures
(including manufacturer startup procedures),
4.5 Contractor Roles and Responsibilities pre-functional checklists, full sequences of
Contractors (general contractor and sub- operation, operating and maintenance data, factory
contractors) typically maintain current marked-up performance data, factory prototype test results,
as-built drawings and specifications of all contract functional performance test procedures, control
documents and contractor-generated coordination drawings, details of Owner-contracted tests,
and shop drawings during construction, including equipment startup certification forms, manufacturer
updating these documents after the completion of field or factory performance tests, and startup test
commissioning activities and any deferred functional documentation.
or seasonal testing. NOTE: Do not wait to update
When factory startup is specified by contract
drawings until the end of construction. Maintain
documents, the respective sub-contractor
updated documents at all times. As-built drawings and
coordinates factory startups with the witnessing
data books must be made available for review and use
parties, such as the CxA, Owner, A/E and/or other
by the design engineers (A/E) and other members of
interested commissioning team members. NOTE:
the commissioning team approximately two weeks
Factory startup activities are generally reviewed
prior to the start of commissioning activities.
and checked prior to field acceptance tests and field
Installing contractors (general contractor and sub- commissioning activities.
contractors) coordinate outside suppliers, equipment
Additionally, when acceptance testing is completed
manufacturers, test agencies and others as required
by one or more independent certified third party
by the contract documents and the CP. Sub-
testing agencies, the respective sub-contractor
contractors coordinate work schedules and staffing
typically coordinates with each independent testing
to ensure that qualified technicians are available and

15 n
NECA 90 Standard for Commissioning Building Electrical Systems

agency so that the CxA, Owner, A/E, and/or any updating the original sequences of operation to
interested commission team members can witness as-built conditions.
such tests to ensure that applicable aspects of the test
meet contractual and commissioning requirements, • Provide all requested submittal data, including
such as requirements of the pre-functional checklists, detailed startup procedures and specific
startups, and/or functional performance tests for the responsibilities of the Owner to keep warranties
equipment or systems. in force.

Functional test procedures are reviewed with the • Provide updated, final as-built documents,
A/E, CxA, and the respective sub-contractors. drawings and specifications, to the CxA and A/E
Functional testing and procedures are executed by for review, approval, and incorporation into
the respective sub-contractors under the direction record documentation.
of and documented by the CxA. During initial During the warranty period, the general contractor’s
functional testing and for critical equipment, the A/E responsibilities include, but are not limited to:
may also witness any testing.
• Ensure that sub-contractors execute seasonal
In general, all of the sub-contractors participate or deferred functional performance testing,
in the resolution of system deficiencies, non- witnessed by the CxA, in accordance with the
compliance in materials, installation, or setup specifications.
related to their trade that are identified during the
commissioning process in accordance with contract • Ensure that sub-contractors correct deficiencies
documents and the Owner’s project requirements. and make necessary adjustments to O&M
manuals and as-built drawings for applicable
4.5.1 General Contractor Roles and issues identified in any deferred functional or
Responsibilities seasonal testing.
During construction, the general contractor’s 4.5.2 Mechanical Sub-Contractor Roles and
responsibilities include, but are not limited to: Responsibilities
• Coordinate commissioning activities with the Mechanical equipment frequently has electrical and
CxA. electronic components, such as motors and controls.
The mechanical sub-contractor provides and installs
• Ensure that commissioning activities are
mechanical equipment in accordance with the
coordinated with the master construction
contract documents, performs pre-functional and
schedule.
functional tests as defined in the CP, and coordinates
• Ensure that O&M manual content, marked-up work with other trades.
as-built copies of drawings and specifications,
In general, motors are factory-installed on
component submittal drawings, and other
mechanical equipment or are field-installed on
pertinent documents are available at the project
mechanical equipment by the mechanical sub-
site during construction for review.
contractor. For this reason, the mechanical sub-
• Track and maintain all construction documents, contractor is typically responsible for functional
addenda, requests for information (RFIs), testing of motors involving vibration monitoring,
contract modifications or change orders, and balancing, and adjustment.
approved submittals and shop drawings related
to commissioned equipment. In general, the controls sub-contractor is
responsible for functional testing of mechanical and
• Prepare O&M manuals, according to the environmental control systems, such as a building
contract documents, including clarifying and automation system (BAS).

n 16
Standard for Commissioning Building Electrical Systems NECA 90

4.5.3 Electrical Sub-Contractor Roles and • Demonstrate the performance of each piece of
Responsibilities equipment to the CxA and/or Owner.

The electrical sub-contractor provides and installs • Participate in off-season mode testing as
the electrical equipment and furnishes all tools required to achieve the Owner’s performance
needed to start up, check out, and conduct functional requirement and the BOD.
performance procedures on electrical equipment,
components, and systems. • Provide O&M data on electrical equipment to
the general contractor.
The electrical sub-contractor’s responsibilities
include, but are not limited to: • Provide updated as-built documents, drawings
and specifications, to the general contractor.
• Coordinate commissioning activities with the
• Conduct training on electrical equipment,
general contractor and the CxA.
components, and systems.
• Assist the CxA in developing test procedures,
checklists, and forms, and to execute and 4.6 Documentation
document testing according to the specific
Commissioning documents which will be completed
commissioning requirements of the project.
by the various installing contractors (general
• Monitor the installation of equipment and contractor or sub-contractors) include, but are not
systems to ensure the equipment, configuration, limited to, the following:
and quality of construction meets the design
requirements and approved submittals and shop • Periodic commissioning status reports.
drawings. • Pre-startup test procedures and test forms.
• Coordinate electrical work related to mechanical • Equipment startup plans and forms.
systems, including power requirements of
mechanical equipment, and safeties and • Post-startup test forms and reports.
interlocks.
• Pre-functional tests and checklists.
• Participate in the functional performance
procedures as required to achieve the Owner’s • Functional performance procedures and tests.
performance requirement and the BOD. • Operating and maintenance (O&M) manuals.
• Schedule manufacturer or factory technicians Commissioning forms, checklists, and related
and representatives, or other specialty trade documents are completed concurrently with the
representatives as needed for factory startup and commissioning activities being documented. Do not
to demonstrate the performance of equipment document commissioning activities after-the-fact.
and systems in accordance with contract Commissioning forms are generally signed by the
requirements. individuals having responsibility and authority for
witnessing completion of the respective inspections
and tests.

17 n
5. Testing Requirements

In general, procedures and tests are witnessed by the tools, material, test instruments, instrumentation,
CxA, general contractor, and/or Owner. Coordinate equipment, labor, and technical supervision to
procedures and tests in advance to ensure that the perform such tests and inspections. Sources of
appropriate personnel will be available to witness power for test equipment are typically furnished in
procedures and tests. Keep in mind that tests that are accordance with contract documents.
not witnessed by the CxA or Owner may be rejected
and may be subject to retesting. Test equipment shall be calibrated, in good
mechanical and electrical condition, and used by
Perform inspections and testing with electrical qualified operators. Field test metering used to check
equipment de-energized when possible. Exercise care the calibration of power system meters must be more
when inspecting and testing energized equipment. accurate (a minimum of twice the accuracy) than
See Section 3. the instrument being tested. The calibrated accuracy
of metering in test equipment shall be appropriate
Upon completion of all testing, restore all for the test being performed. The waveshape and
connections, settings, programming, and equipment frequency of test equipment output waveforms shall
to normal operating condition in accordance with be appropriate for the test and for the equipment
contract documents. being tested.
Document any deficiencies discovered during testing Methods of Procedure (MOPs) that detail the
or other commissioning procedures. See Section 6.2 sequence of steps necessary to commission
for additional guidance. Correct deficiencies and equipment are typically developed by the
retest equipment, sub-systems, or systems to ensure organization completing the commissioning
conformance to the design intent. Let the Owner procedure. Emergency procedures must be
know of any outstanding deficiencies. developed in the event a problem occurs during
testing. Include the telephone numbers of the local
5.1 Test Equipment electric utility service provider in the MOP.
See Annex A for additional requirements for test and 5.1.1 Calibration
measurement equipment, testing procedures, and
methodologies. Use a regulated, high quality power supply for
test equipment during testing, as supply voltage,
Commissioning electrical equipment may require frequency, and waveform variation can produce
special tools and instruments for the measurement invalid results. Operate all equipment in accordance
of equipment performance. All electrical testing with its instruction manual.
equipment must be of sufficient quality and accuracy
to test and/or measure the system performance All test equipment and instrumentation used for
within tolerance levels specified in the manufacturer commissioning procedures shall be calibrated
specifications and design documents. according to the manufacturer recommended
intervals, and when mishandled, dropped, or
Companies providing testing should provide all damaged. Dated calibration labels or tags shall

n 18
Standard for Commissioning Building Electrical Systems NECA 90

be visible on all test equipment, or calibration completed at any time prior to acceptance testing or
certificates shall be readily available. Maintain up-to- final commissioning procedures. See Section 5.5 for
date testing and calibration records indicating the commissioning requirements of electrical equipment
dates and results of instruments calibrated or tested. that include inspections, checks, and tests that may
be completed during pre-startup, startup, and post-
Each testing organization shall have a calibration startup of equipment, components, and systems.
program and documentation that all applicable test
instruments are maintained within the required rated The equipment manufacturer standard startup
accuracy for each test instrument calibrated. Firms procedures and forms are typically used as the basis
providing calibration services shall maintain up-to-date of the commissioning equipment startup procedure
instrument calibration instructions and procedures and documentation. All startup forms are typically
for each test instrument calibrated. The accuracy submitted to the CxA and Owner for review and
of test equipment shall be traceable to the National approval prior to equipment startup, and are
Bureau of Standards (NBS) in an unbroken chain. submitted to the CxA and Owner for review and
acceptance upon completion.
Ensure that test equipment used for performance
verifications during the commissioning process has After equipment startup, adjust settings and
been calibrated within one year of its use for testing. calibration of equipment in accordance with
Field instruments should be calibrated within 6 manufacturer instructions, and in accordance with
months of use for testing. In the absence of other design intent documents, and contract documents,
calibration requirements, test instruments should drawings and specifications. Provide documentation
be calibrated in accordance with the following of the conditions under which tests and adjustments
maximum frequency schedule: were conducted, including (as applicable) ambient
conditions, set points, override conditions, and status
• Field instruments: Analog, 6 months maximum. and operating conditions that impact the results of
Digital, 12 months maximum. the test.
• Laboratory instruments: 12 months maximum.
5.3 Pre-Functional Performance
• Leased specialty equipment: 12 months Procedures and Checklists
maximum.
NOTE: See Section 5.5 for commissioning
5.1.2 Data Logging requirements of electrical equipment that include
inspections, checks, and tests that may be completed
Use data logging instruments and software as needed during pre-functional performance procedures for
to measure the performance of electrical equipment equipment, components, and systems.
and systems over a specified period of time to ensure
that equipment and systems are functioning in Pre-functional performance testing is performed to
accordance with the design intent and specifications. document that the specified equipment, components,
Data logging may require energy management sub-system, or system is installed correctly, has
control system trending, standalone data log started up properly, and is ready for functional
monitoring, or manual functional testing. performance testing. Pre-functional performance
tests include checking all operating modes, safety
5.2 Pre-Startup, Startup, and Post-Startup interlocks, control responses, and specific responses
Procedures to abnormal or emergency operating conditions. Pre-
functional performance tests are often documented
NOTE: General commissioning requirements of in a checklist format, and are based on design intent
electrical equipment, components, conductors, documentation and equipment submittals.
cables, connections, and terminations may be

19 n
NECA 90 Standard for Commissioning Building Electrical Systems

Completed checklists and forms are typically • Safety, operating ranges, and functions have
submitted to the CxA and Owner for review upon been reviewed by the CxA.
completion of the respective tests. Completed
original pre-functional checklists are typically • Sufficient clearance around equipment is
maintained on-site as part of the as-built record provided for service and maintenance.
commissioning documents to be delivered to the • A record has been made of all values for pre-test
Owner upon project completion. set points that were changed to accommodate
The CxA and/or Owner will generally provide testing. Check boxes can be used to verify that
oversight to the installing contractors during all pre-test set points (control parameters, limits,
the execution of pre-functional testing and will delays, lockouts, and schedules) have been
periodically review the installing contractors’ returned to original values.
in-progress pre-functional checklists for accuracy • Other operational, safety, alarm checks,
and completeness, and to verify that checklists are and startup reports have been completed
being updated. successfully.
Pre-functional performance checklists include, at a
minimum, that: 5.4 Functional Performance Procedures
NOTE: See Section 5.5 for commissioning
• Installed equipment matches the specifications
requirements of electrical equipment that include
and approved submittals and shop drawings.
inspections, checks, and tests that may be completed
• Equipment is installed in accordance during functional performance procedures for
with contract documents, drawings and equipment, components, and systems.
specifications, and manufacturer instructions.
In general, specific functional performance
• Utility connections to equipment have been procedures and forms are developed by the CxA
successfully completed. to verify and document proper operation of each
piece of equipment and each system. Procedures
• All related equipment has been started up, with and forms are based on the design intent, contract
start-up reports and pre-functional checklists documents, drawings and specifications, contract
submitted and approved as ready for functional modifications or change orders affecting equipment,
performance testing. approved submittals and shop drawings,
• Testing, balancing, and calibration is complete Complete functional performance procedures on
and accepted by the CxA. equipment and systems monitored or controlled by a
control system in conjunction with the controls sub-
• All control system functions and all interlocking
contractor. Prior to commissioning, verify that the
systems are programmed and operable per
controls sub-contractor has completed, debugged,
contract documents, including final set points
validated, and forwarded all documentation for the
and schedules, with debugging, loop tuning and
control system, including point-to-point checks
sensor calibrations completed.
listing command and response values, verification
• All architectural/engineering (A/E) punch list that network communication between all devices and
items for equipment, sub-systems, and systems systems is established, and the sequence of operation
have been corrected. checks out.

• Functional test procedures have been reviewed Begin functional performance testing after
and approved by the installing contractor. completing pre-functional checklists for systems,
sub-systems, and equipment, and checklists have

n 20
Standard for Commissioning Building Electrical Systems NECA 90

been approved, and after all issues and deficiencies Simulate conditions by imposing an artificial load
affecting equipment and system operation or when it is not practical to test design conditions
performance have been resolved. under actual operating conditions, and only
upon the approval of the CxA and Owner. Before
Each functional performance test should be simulating conditions, calibrate test instruments. Set
performed under conditions that simulate actual and document simulated conditions and methods
operating conditions as closely as possible. of simulation. When simulating conditions is not
Optimally, each system and sub-system should be practical, alter set points to conduct functional
operated through all modes of operation (seasonal, testing only upon approval of the CxA and Owner.
occupied, unoccupied, warm-up, cool-down, partial
load, and full-load) where there is a specified system Upon satisfactory completion of all verified tests,
response. return equipment and system settings to normal
operating conditions as required by the contract
Verify the proper sequence of operation for documents as a complete and operational system.
equipment, and verify the settings of adjustable
parameters for equipment and systems. Test each
step in every written sequence and other significant
5.5 Commissioning Requirements of
modes, sequences, and operational features not Electrical Equipment
mentioned in written sequences; including startup, For additional information, refer to ANSI/NETA
normal operation, shutdown, scheduled on and off, Standard for Acceptance Testing Specifications
unoccupied and manual modes, safeties, alarms, (ATS) and ANSI/NETA Standard for Electrical
over-rides, lockouts, and power failure. Commissioning (ECS).
Verify shut down and restart capabilities both for 5.5.1 General Electrical Commissioning
scheduled and unscheduled events, such as power Requirements
failure recovery and normal scheduled start/stop
functions. When applicable, demonstrate a full cycle Perform specific inspections and mechanical tests of
from off to on and no load to full load and then to equipment and components in accordance with the
no load and off. Verify time of day schedules and manufacturer instructions and ANSI/NETA ATS
setpoints. Verify all energy saving control strategies. and ECS specifications.

Conduct seasonal functional performance testing Compare equipment, components, conductors,


on equipment during the season it is intended to cables, connections, and terminations with
operate, such as testing air conditioning equipment contract documents, drawings and specifications,
during the peak cooling season, and testing heating and with approved submittals, product data and
equipment during the peak heating season. Verify shop drawings. Verify equipment nameplate
energy efficiency and self-diagnostic capability of information with contract documents, drawings
equipment and systems. and specifications, approved submittals, and
approved engineering studies, including short circuit,
Verify the proper operation of equipment and coordination, arc flash, and load flow studies, if
systems in normal and alternate modes of operation, applicable. Verify circuit breaker and fuse sizes,
and during abnormal operation conditions, such as types, and ratings conform to contract documents
(where applicable) fire, single-phasing, total power and approved submittals. Measure the resistance of
failure, equipment failure, and individual component fuses. Resistance values must not deviate by more
failure. Verify the proper operation of safeties than 15% between identical fuses.
and interlocks. Verify proper operation of control
systems, including response times, stability, and Perform point-to-point wiring checks to ensure
tunings. that each conductor is properly terminated. Verify
that temporary wiring jumpers are removed. Check

21 n
NECA 90 Standard for Commissioning Building Electrical Systems

the continuity of each conductor from end-to-end, and similar supports have been removed from
including ground conductors and ground shields equipment. Inspect all bus bracing and insulators
of shielded cables and conductors. Perform a for contamination, tracking, and broken or missing
shield-continuity test on each shielded cable using parts.
a low-resistance ohmmeter. Shielding must exhibit
continuity. Investigate any shield resistance values Check for physical damage. Inspect doors, panels,
that exceed ten ohms per 1000 feet of cable. and sections of equipment for paint, dents, and
scratches, paying particular attention to missing
Inspect the condition of exposed cable and and loose hardware, bent hinges, broken or missing
conductor insulation, jacketing, and field-applied lock handles or latches and warped panels. Check
fireproofing, where installed. Verify that visible cable for proper clearances, anchorage, fit, and alignment,
bends meet or exceed Insulated Cable Engineers considering seismic requirements. Check for proper
Assocation (ICEA) and/or manufacturer minimum alignment and fit of doors, access panels, and
allowable bending radius. Check that conductors and components. Check for loose parts and hardware.
cables are supported independently of terminations Verify that connections and terminations are free of
and connections. corrosion.

Verify correct connections in accordance with single- Using a calibrated torque wrench, verify the
line and three-line diagrams. Perform a phasing tightness of accessible bolted electrical connections
check on equipment supplied from multiple sources, in accordance with manufacturer published data.
such as double-ended switchgear, to insure correct Torque all connections in accordance with the
bus phasing from each source. manufacturer instructions and record the results
on a tabular form. Alternatively, inspect bolted
Verify proper mechanical, maintenance, and electrical connections for high resistance using a low-
ventilation clearances for equipment. Verify that field resistance ohmmeter. See Annex A for additional
wiring is clear of live bus. Verify that conductors and guidance.
cables are secured in accordance with manufacturer
instructions to withstand the effects of fault Inspect compression-applied connectors and
currents. Verify proper separation and clearances terminations for correct cable match and
of conductors and cables, including primary and indentation. Inspect conductor and cable shield
secondary conductors for transformers. grounding, cable support, and termination. If
cables are terminated through window-type current
Verify the identification and correct arrangement of transformers, inspect to verify that neutral and
cables, conductors, connections, and terminations. ground conductors are correctly placed and that
Check that each conductor, each connection, and shields are correctly terminated for operation of
each termination is properly identified (cable protective devices.
number, wire number) or color coded in accordance
with contract requirements and in accordance with Verify proper grounding in accordance with
the NEC. Verify identification of all lighting circuits contract documents, drawings and specifications,
and branch circuits on panel directories. and in accordance with the NEC. Ensure that
equipment grounding conductors, grounding
Perform a visual and mechanical inspection of electrode conductors, and bonding ground jumpers
equipment, components, conductors, cables, are properly sized, properly installed and properly
connections, and terminations. Verify that torqued.
equipment is completely assembled. Verify that
equipment and components are clean, dry, and Verify that all grounding and shorting contacts for
free of tools, debris, and storage of materials. instrument transformers (potential transformers and
Verify that shipping braces, blocking, brackets, current transformers) provide proper contact. Verify

n 22
Standard for Commissioning Building Electrical Systems NECA 90

proper operation of disconnecting and grounding Perform infrared scan (thermographic survey) of
devices associated with drawout devices, such as equipment and components under maximum load
circuit breakers, control power transformers, and conditions. See Annex A for additional information.
potential transformers, including control contacts,
grounding contacts, and withdrawal mechanisms, if Check for unusual sounds after energizing
applicable. equipment, components, conductors, and systems.

Test all safety devices, fail-safe functions, and all 5.5.2 Medium and High Voltage Power Cables
keyed, mechanical, and electrical safety and interlock (above 1000V)
systems for correct operation and sequencing.
Perform acceptance testing on cables, including
Attempt to close locked open devices. Attempt to
terminations and joints, after cable system
open locked closed devices. Exchange keys and
installation and before the cable system is placed into
attempt operation with devices operated in off-
service, in accordance with ANSI/IEEE 400, ICEA
normal positions.
S-93-639/NEMA WC 74, ICEA S-94-649 and ICEA
Verify that settings for alarm, control, and trip S-97-682.
setpoints for adjustable trip circuit breakers, relays,
Ensure that cables are disconnected from
meters, and temperature indicators are adjusted
equipment and de-energized. Lower test voltages
in accordance with contract documents, drawings
and test durations are required when cables remain
and specifications, approved submittals, product
connected to equipment and accessories. Insure
data and shop drawings, manufacturer instructions,
that the maximum test voltage does not exceed the
and approved short circuit and coordination
limits for terminators specified in ANSI/IEEE 48,
studies. Verify that circuit breaker addresses for
IEEE 386, or manufacturer specifications. Disconnect
microprocessor-communication packages correspond
and ground surge arresters, potential transformers,
to contract documents and approved submittals.
and capacitors. Ensure that conductors under test
Verify the correct level of liquid in liquid-filled are properly isolated from ground and are guarded
devices, such as liquid-filled transformers and against inadvertent contact by personnel. Tie back
bushings, and wet-cell batteries. Check for leaks. cables as needed to ensure adequate clearance from
Verify the presence of PCB content labeling for any grounded objects.
liquid-filled equipment, such as transformers,
Test each conductor individually. Test each cable
reactors, and capacitors. Verify that positive pressure
section individually. Ground all conductors and
is maintained on gas-blanketed transformers.
shields and drain wires not under test. Prepare
Manually operate disconnecting means, circuit and clean exposed ends of cable prior to testing
breakers and switches, to verify proper alignment in order to minimize any leakage current using
and smooth operation. Electrically exercise all manufacturer approved materials, such as
electrically-operated devices such as circuit denatured alcohol or approved equivalent. Perform
breakers, under no-load condition to verify proper testing after terminations and splices using hot
operation. Leave disconnecting means, circuit dielectric compounds have fully cooled to ambient
breakers and switches, in the OPEN (OFF) position temperature.
after inspecting and operating and before initial
Acceptance testing can be performed by means of
energization.
direct current (DC), alternating current (AC), partial
Verify the correct operation of all sensing devices, discharge (PD), or very low frequency (VLF) AC
alarms, and indicating devices. in accordance with Annex A. Evaluate alternative
methods in selecting the appropriate acceptance
Perform insulation resistance testing of conductors test for each given cable installation. Do not exceed
and busing. See Annex A for additional information. 80% of the cable manufacturer factory test value or

23 n
NECA 90 Standard for Commissioning Building Electrical Systems

the maximum test voltage in Annex A, whichever 5.5.3 Low Voltage Power Cable (below 1000V)
is less. Keep in mind that the maximum test voltage
may be limited by cable terminations or splices that Perform insulation resistance testing and continuity
may have lower maximum voltage ratings than the testing in accordance with Annex A.
maximum recommended acceptance test voltages.
5.5.4 Electrical Feeders and Branch Circuits
Perform high potential testing only on new (1000V or below)
conductors. Do not perform high potential testing Make operational checks on all lighting circuits
on conductors that have been in service for more and branch circuits to demonstrate that all circuits
than five (5) years, including testing when new perform all functions for which they were designed.
conductors are spliced onto existing conductors. In the presence of the CxA, field test for correct
Complete high potential testing on sections of new labeling of circuits and equipment by breaking
cable prior to connecting new cable to existing cable. current and observing loss of power at circuits
DC high potential, very low frequency (VLF) AC or equipment. Document, correct, and retest any
testing, or any other type of withstand or destructive incorrect equipment circuit identifications found.
testing is not recommended as a maintenance test
on any medium-voltage cable, especially XLPE cable 5.5.5 Liquid-Filled Transformers
that has been in service in a wet environment for
more than five years, unless approved by the cable Verify that transformer bushings are clean.
manufacturer.
Verify correct primary and secondary fuse sizing
Acceptance test must be performed on the new for voltage transformers with fusing as overcurrent
cable prior to splicing into existing cables. After test protection.
results are approved for new cable and the splice is
Verify correct liquid level in all tanks and bushings.
completed, perform insulation-resistance and shield-
continuity testing on the length of new and existing Where installed, verify that alarm, control and trip
cable including the splice. settings on temperature and level indicators, pressure
relief device, and fault pressure relay are as specified.
Current-sensing circuits in test equipment, when
used, must measure only the leakage current Where installed, verify that cooling fans and pumps
associated with the cable under test and must not operate correctly and that fan and pump motors
include internal leakage of the test equipment. have correct overcurrent protection.
Terminations must be adequately corona-suppressed
by guard ring, field reduction sphere, or other Perform a turns-ratio test on all no-load tap-changer
suitable method, as necessary. If acceptance testing is positions and all load tap-changer positions. Verify
performed by means of direct current (DC), reduce that the final tap setting is as specified. Verify that
the test set potential to zero and measure residual winding polarities are in accordance with nameplate
voltage at discrete intervals. Apply grounds for a data. Turns-ratio test results should not deviate
time period adequate to drain all stored charge. more than ½% from either the adjacent coils or the
calculated nameplate ratio.
After energizing cables, check for unusual sounds
that might indicate partial discharge (corona) or Measure resistance of each high-voltage winding
loose connections. Perform thermographic (infrared) in each no-load tap-changer position. Measure the
survey in accordance with Annex A. resistance of each low-voltage winding in each load
tap-changer position, if applicable. Consult the
See NECA 600 for additional information and manufacturer if winding-resistance measurements
guidance. vary more than 1% from adjacent windings.

n 24
Standard for Commissioning Building Electrical Systems NECA 90

Perform core resistance test. If the transformer core • Interfacial tension in accordance with ASTM
ground strap is removable, remove the core ground D-971 or ASTM D-2285.
strap and measure the insulation resistance of the
transformer core at 500 volts DC. Core insulation- • Color in accordance with ASTM D-1500.
resistance values should be comparable to factory test • Visual Condition in accordance with ASTM
results, but not less than 2.0 megohm at 500 volts DC. D-1524.
Perform liquid insulation tests for dielectric strength, • Parts per million of water in accordance with
acidity, interfacial tension, specific gravity, water ASTM D-1533. (Required for all liquid-filled
content, power factor/dissipation factor, and color. transformer rated 25 kV or higher, and for all
silicone-filled transformers.)
Perform excitation-current tests in accordance with
test equipment manufacturer published data. Typical • Measure dissipation factor or power factor in
excitation-current test data pattern for a three-legged accordance with ASTM D-924.
core transformer is two similar current readings and
one lower current reading. Insulating liquid must comply with manufacturer
instructions.
Where installed, test transformer neutral grounding
impedance device. Compare grounding impedance Investigate the presence of oxygen in the nitrogen
device results to manufacturer published data gas blanket, if applicable.

Perform an insulation resistance test and calculate See NECA 410 for additional information and
dielectric absorption on all transformers in guidance.
accordance with Annex A. Perform testing for each
winding-to-winding and on each winding-to-ground. 5.5.6 Dry-Type Transformers

Verify that resilient mounts are free.


Perform a power factor test on transformer windings
and bushings that are equipped with test taps. Where installed, verify that auxiliary devices, such as
Perform hot collar watts-loss test on bushings that cooling fans and controls, alarms, indicators, and tap
are not equipped with test taps, in accordance with changers, operate correctly. Test temperature control
Annex A. panel and verify alarm settings on temperature
indicators, and test interlocks for shutdown. Adjust
Remove a sample of insulating liquid in accordance
settings in accordance with the manufacturer
with ASTM D 3613 and perform dissolved-gas
instructions as needed. Verify that cooling fan
analysis (DGA) in accordance with ANSI/IEEE
motors have correct overcurrent protection.
C57.104 or ASTM D3612. Evaluate results of
dissolved-gas analysis in accordance with ANSI/IEEE Perform a turns-ratio test on all no-load tap-changer
C57.104. Use results as baseline for future tests. positions and all load tap-changer positions. Verify
that the final tap setting is as specified. Verify that
Remove a sample of insulating liquid in accordance
winding polarities are in accordance with nameplate
with ASTM D-923 and test for the following:
data. Turns-ratio test results should not deviate
• Dielectric breakdown voltage in accordance with more than ½% from either the adjacent coils or the
ASTM D-877 and/or ASTM D-1816. calculated nameplate ratio.

• Acid neutralization number in accordance with Perform an insulation resistance test and calculate
ASTM D-974. dielectric absorption on all transformers in
accordance with Annex A. Perform testing for each
• Specific gravity in accordance with ASTM winding-to-winding and on each winding-to-ground.
D-1298.

25 n
NECA 90 Standard for Commissioning Building Electrical Systems

Measure excitation-current on each phase. Typical Measure secondary voltage with the secondary
excitation current results for a typical three-legged wiring disconnected. Verify correct potential at all
core transformer are the two outer legs have similar devices.
current readings, and the center leg has a lower
current reading. Perform a secondary saturation test of current
transformers (CTs) at a minimum of three points
Measure the resistance of each winding at each below and one point above the knee of the saturation
tap connection. Temperature corrected winding- curve.
resistance test results should compare within 1% of
previously obtained results. Measure voltage circuit burdens at transformer
terminals. Perform burden tests at the secondary
Perform core resistance test. If the transformer core leads of each CT to assure accurate translation of
is insulated and the core ground strap is removable, primary current.
remove the core ground strap and measure the
insulation resistance of the transformer core at 500 Check for PT secondary load with secondary voltage
volts DC. Core insulation-resistance values should be and current measurements. Transformer loading
comparable to factory test results, but not less than must be less than the volt-ampere capacity of the PT.
1.0 megohm at 500 volts DC.
Verify that current circuits are grounded and have
Perform power factor or dissipation factor tests on only one grounding point in accordance with ANSI/
all windings with a rating greater than 500 kVA. IEEE C57.13.3.

Verify correct secondary voltage phase-to-phase Measure the capacitance of coupling-capacitor


and phase-to-neutral after energization and prior to voltage transformer capacitor sections. Capacitance
loading. of capacitor sections of coupling-capacitance
voltage transformers must be in accordance with the
See NECA 409 for additional information and manufacturer published data.
guidance.
Perform secondary wiring integrity test. Disconnect
5.5.7 Instrument Transformers transformer at secondary terminals and connect
secondary wiring to a rated secondary voltage source.
Verify correct primary and secondary fuse sizing for Verify correct potential at each device.
voltage transformers.
5.5.8 Switchgear and Switchboard Assemblies
Perform insulation resistance testing in accordance Rated 1200A or Greater
with Annex A. Perform measurements from winding
to winding and from winding to ground. Perform an insulation resistance test on each bus
section, phase-to-phase, and phase-to-ground, and
Measure the transformer turns ratio. Confirm on control wiring in accordance with manufacturer
transformer polarity by electrical testing. instructions and Annex A. NOTE: When performing
dielectric tests, disconnect all instrument and control
Verify CT secondary connections by driving a low
transformers, lightning arresters, surge protective
current through the secondary leads and checking
devices (SPDs), digital meters and relays, and other
for this current at applicable devices.
sensitive electronic equipment that may cause
Verify potential transformer (PT) secondary erroneous results or cause damage to equipment
connections by applying a low voltage to the that is not rated in accordance with switchgear or
secondary leads and checking for this voltage at switchboard industry standards. Minimum test
applicable devices. Verify correct secondary voltage voltages and insulation resistances are shown in
by energizing primary winding with system voltage. Table 1.

n 26
Standard for Commissioning Building Electrical Systems NECA 90

Perform a power factor test. For switchgear rated 5 After energization, verify proper voltage with
kV and above, power factor should not exceed the system operating at load conditions. Operate every
values shown in Table 2. circuit breaker, switch and contactor, manually
and electrically, if so equipped. Modify tap settings
For medium-voltage switchgear, after achieving on transformers as needed for actual operating
acceptable insulation resistance test results, perform conditions. Measure line amperes with system
high potential testing on each bus section, each phase operating at load conditions.
to ground with phases not under test grounded in
accordance with the manufacturer published data Perform thermographic (infrared) survey in
(see Annex A for additional guidance). Perform accordance with Annex A. Identify all hot spots, and
an overpotential (high potential) test on each bus promptly correct sources of heating problems.
section, each phase to ground with phases not under
test grounded, in accordance with manufacturer See NECA 400 and NECA 430 for additional
published data. Apply test voltage for one minute. information and guidance.

Perform current tests by primary or secondary 5.5.9 Metal-Enclosed (Medium-Voltage) Bus


injection on all metering and relaying circuits in and Low-Voltage Busway
each section of switchgear with a sufficient current
Confirm the physical orientation of the busway is
magnitude to cause a minimum of 1.0 ampere
in accordance with manufacturer labels to insure
current flow in the secondary circuit. Verify correct
adequate cooling. Examine outdoor busway to
magnitude of current at each device in the circuit.
ensure the removal of weep-hole plugs, if applicable,
Verify that the insulating barriers and shutters are and the correct installation of joint shields.
properly installed and operating correctly. Inspect all
Measure insulation resistance of each bus phase-to-
mechanical indicating devices for correct operation.
phase and each phase-to-ground for a minimum of
Check indicating lights for proper operation.
one (1) minute in accordance with Annex A, with
Replaced burned-out lamps. Verify that filters are in
phases not under test grounded.
place and/or vents are clear. Verify proper operation
of switchgear/switchboard heaters. Perform an overpotential test of each phase-to-
ground with phases not under test grounded, in
Perform a phasing check on switchgear with multiple
accordance with manufacturer published data and
sources to insure correct bus phasing from each
in accordance with Annex A. Apply test voltage for
source. Verify the proper operation of control
one minute. Busway insulation should withstand the
transfer relays located in switchgear with multiple
overpotential test voltage applied.
control power sources.

Table 1 Minimum Test Voltage and Insulation


Resistance Table 2 Switchgear Power Factor Values
Minimum Power Factor Values
Minimum
Voltage Rating Insulation Voltage Rating Test Voltage Maximum
Test Voltage
Resistance (volts) (volts) Reading
0-250V 500V DC 25 ohms 5000 5000 2%
250-600V 1000V DC 100 ohms 7000 5000 2%
601-5000V 2500V DC DC 1000 ohms 15,000 10,000 2%
5001-15,000V 2500V DC DC 5000 ohms 35,000 10,000 2%

27 n
NECA 90 Standard for Commissioning Building Electrical Systems

Perform contact-resistance test on each connection 5.5.11 Low-Voltage Motor Starters


point of uninsulated busway. On insulated busway,
measure resistance of assembled busway sections and Verify contactors. Verify mechanical operation.
compare values with adjacent phases. See Annex A Inspect that contact gap, wipe, alignment, and
for additional guidance. pressure are in accordance with manufacturer
published data.
Perform phasing test on each busway tie section
energized by separate sources to insure correct Perform insulation-resistance tests on each
bus phasing from each source. Test with busway pole, phase-to-phase and phase-to-ground with
energized from permanent sources. starter closed and across each open pole for one
minute. Test voltage must be in accordance with
Verify proper operation of busway space heaters. manufacturer published data. See Annex A for
additional guidance.
After energizing busway, perform infrared scan
of all accessible bus joints and cable connections Perform insulation-resistance tests on all control
while maintaining maximum load on the bus for at wiring with respect to ground. For units with solid-
least one hour, or until temperature has stabilized, state components, follow manufacturer instructions.
to detect loose or high resistance connections and See Annex A for additional information.
other circuit anomalies. See Annex A for additional
guidance. Test motor protection devices in accordance with
manufacturer published data. Verify overload element
See NECA 408 for additional information and rating is correct for its application. If motor-running
guidance. protection is provided by fuses, verify correct fuse
rating. Set adjustable or programmable devices
5.5.10 Motor Control Centers according to the protective device coordination study.
Measure insulation resistance of the line bus phase- 5.5.12 Medium-Voltage Motor Starters
to-phase and phase-to-ground. See Annex A for
additional guidance. Verify racking mechanism operation for removable
units.
Perform operational tests on each starter. Test
overload relays by primary current injection and Verify contactors. Verify mechanical operation.
monitor the trip time of each overload relay. Inspect that contact gap, wipe, alignment, and
Compare against manufacturer published data and pressure are in accordance with manufacturer
either replace or resize relays that are deficient. published data.
Measure insulation resistance of motor starters,
phase-to-phase and phase-to-ground, with the starter Measure the resistance of power fuses. Resistance
contact closed and overload relays in the “open” values must not deviate by more than 15% between
position. See Annex A for additional guidance. identical fuses. Measure blowout coil circuit
resistance. Test starting transformers, if applicable.
After energizing, perform thermographic (infrared) Test starting reactors, if applicable. Verify operation
survey in accordance with Annex A. Identify all of cubicle space heaters, if applicable.
hot spots and correct sources of heating problems
promptly. Exercise all active components and confirm correct
operation of all indicating devices. Verify correct
See NECA 402 for additional information and barrier and shutter installation and operation.
guidance.
Perform insulation-resistance tests on contactors,
phase-to-phase, phase-to-ground, and across open
contacts for one minute. Test voltage must be in

n 28
Standard for Commissioning Building Electrical Systems NECA 90

accordance with manufacturer published data. See Perform an insulation resistance test. Measure
Annex A for additional guidance. insulation resistance phase-to-phase and phase-to-
ground and across open poles, using a minimum
Perform insulation-resistance tests on all control voltage of 2500V DC. See Annex A for additional
wiring with respect to ground. For units with solid- guidance.
state components, follow manufacturer instructions.
See Annex A for additional information. Perform a power factor/dissipation test with breaker
in open and closed positions. See Annex A for
Test motor protection devices in accordance with additional guidance.
manufacturer published data. Verify overload
element rating is correct for its application. If motor- Perform an overpotential test in accordance with
running protection is provided by fuses, verify manufacturer published data. See Annex A for
correct fuse rating. Set adjustable or programmable additional guidance.
devices according to the protective device
coordination study. See NECA 430 for additional information and
guidance.
Perform vacuum bottle integrity (overpotential)
testing across each vacuum bottle with the contacts 5.5.14 Medium-Voltage Air Circuit Breakers
in the open position in strict accordance with
Perform all mechanical operation tests on
manufacturer published data. Do not exceed
the operating mechanism in accordance with
the maximum voltage recommended by the
manufacturer instructions. Inspect moving and
manufacturer for this test. NOTE: Some dc high-
stationary contacts for condition, and alignment.
potential test sets are half wave rectified and may
Verify that the arc chutes are intact. Inspect puffer
produce peak voltages in excess of the vacuum
operation. Verify cell fit and element alignment.
bottle manufacturer recommended maximum. See
Verify racking mechanism operation for removable
Annex A for additional guidance. Provide adequate
breakers.
barriers and protection against x radiation during
this test. Do not perform this test unless the Perform time-travel analysis. Circuit breaker
contact displacement of each interrupter is within operation times must conform to manufacturer
manufacturer tolerance. The interrupter must published data. If recommended by manufacturer,
withstand the overpotential voltage applied. slow close/open breaker and check for binding,
friction, contact alignment, and penetration.
Energize each contactor using an auxiliary source.
Verify that contact sequence is in accordance with
Adjust armature to minimize operating vibration
manufacturer published data. In the absence of
where applicable.
manufacturer published data, refer to ANSI/IEEE
5.5.13 Medium-Voltage Circuit Breakers C37.04.

Verify racking mechanism operation for removable Perform insulation-resistance tests on each pole,
breakers. phase-to-phase and phase-to-ground with circuit
breaker closed and across each open pole for one
Perform circuit breaker time-travel analysis to minute. Test voltage must be in accordance with
determine the opening and closing speeds of each manufacturer published data. See Annex A for
breaker, the interval for closing and tripping, and the additional guidance.
contact bounce.
Perform insulation-resistance tests on all control
Perform a contact resistance test of each phase wiring with respect to ground. For units with solid-
and compare results. See Annex A for additional state components, follow manufacturer instructions.
guidance. See Annex A for additional information.

29 n
NECA 90 Standard for Commissioning Building Electrical Systems

Perform a contact/pole-resistance test. Measure with the breaker closed. Compare power-factor
blowout coil circuit resistance. or dissipation-factor test results to manufacturer
published data. In the absence of manufacturer
Perform minimum pickup voltage tests on trip and published data, compare results to similar breakers.
close coils. Minimum pickup for trip and close coils
must be in accordance with manufacturer published Perform power-factor or dissipation-factor tests
data. on each bushing. Use hot collar procedures if
bushings are not equipped with a power-factor tap.
With breaker in the test position, trip and close Power-factor or dissipation-factor test results and
breaker with the control switch. Trip each breaker capacitance test results should be within 10% of
by operating each of its protective relays. Verify trip- nameplate rating for bushings.
free and anti-pump functions. Perform minimum
pickup voltage tests on trip and close coils in Perform insulation-resistance tests on all control
accordance with manufacturer published data. wiring with respect to ground. For units with solid-
state components, follow manufacturer instructions.
Perform power-factor or dissipation-factor test See Annex A for additional information.
with breaker in both the open and closed positions.
Compare power-factor or dissipation-factor test Perform a contact/pole-resistance test. Verify trip,
results with previous tests of similar breakers or close, trip-free, and anti-pump functions. Trip
manufacturer published data. each circuit breaker by operation of each protective
device.
Perform an overpotential test in accordance with
manufacturer published data. The insulation must Perform minimum pickup voltage tests on trip and
withstand the overpotential test voltage applied. close coils. Minimum pickup for trip and close coils
must be in accordance with manufacturer published
5.5.15 Medium-Voltage Vacuum Circuit data.
Breakers
Perform vacuum bottle integrity (overpotential)
Perform all mechanical operation tests on both the testing across each vacuum bottle with the breaker
circuit breaker and its operating mechanism. Verify in the open position in strict accordance with
racking mechanism operation for removable breakers. manufacturer published data. Do not exceed
the maximum voltage recommended by the
Measure critical distances such as contact gap
manufacturer for this test. NOTE: Some dc high-
as recommended by manufacturer. Contact
potential test sets are half wave rectified and may
displacement must be in accordance with factory
produce peak voltages in excess of the vacuum
recorded data marked on the nameplate of each
bottle manufacturer recommended maximum. See
vacuum breaker or bottle.
Annex A for additional guidance. Provide adequate
Perform time-travel analysis. Compare travel and barriers and protection against x radiation during
velocity values to manufacturer published data. this test. Do not perform this test unless the
contact displacement of each interrupter is within
Perform insulation-resistance tests on each pole, manufacturer tolerance. The interrupter must
phase-to-phase and phase-to-ground with circuit withstand the overpotential voltage applied.
breaker closed and across each open pole for one
minute. Test voltage must be in accordance with 5.5.16 Medium-Voltage SF6 (Sulfur
manufacturer published data. See Annex A for Hexafluoride) Circuit Breakers
additional guidance.
Verify racking mechanism operation for removable
Perform power-factor or dissipation-factor tests breakers.
on each pole with the breaker open and each phase

n 30
Standard for Commissioning Building Electrical Systems NECA 90

Inspect operating mechanism and SF6 gas-insulated Perform a contact/pole-resistance test. Verify trip,
system in accordance with the manufacturer close, trip-free, and anti-pump functions. Trip
published data. each circuit breaker by operation of each protective
device.
Verify correct operation of alarms and pressure-
limit switches for pneumatic, hydraulic, and SF6 gas Perform minimum pickup voltage tests on trip and
pressure as recommended by the manufacturer. Test close coils. Minimum pickup for trip and close coils
for SF6 gas leaks if temperature-corrected pressure/ must be in accordance with manufacturer published
density alarms or meters indicate a need. Remove data.
a sample of SF6 gas (if provisions are made for
sampling) and test. Perform an overpotential test in accordance with
manufacturer published data. Perform SF6 bottle
If recommended by manufacturer, slow close/open integrity test (overpotential) across each SF6 bottle
breaker and check for binding, friction, contact with the contacts in the open position in strict
alignment, and penetration. Verify that contact accordance with manufacturer published data. Do
sequence is in accordance with manufacturer not exceed the maximum voltage recommended
published data. In the absence of manufacturer by the manufacturer for this test. See Annex A for
published data, refer to ANSI/IEEE C37.04. additional guidance. The insulation must withstand
the overpotential test voltage applied.
Perform time-travel analysis. Compare travel and
velocity values to manufacturer published data. 5.5.17 Low-Voltage Air-Insulated and Insulated
Case Circuit Breakers
Perform insulation-resistance tests on each pole,
phase-to-phase, and phase-to-ground with circuit Perform all mechanical operation tests on circuit
breaker closed and across each open pole for one breakers and the operating mechanism in accordance
minute. For single-tank breakers, perform insulation with the manufacturer published data. Check
resistance tests from pole-to-pole. Test voltage must adjustments on springs, gears, and liners. Check cell
be in accordance with manufacturer published data. fit and element alignment. Inspect arc chutes.
See Annex A for additional guidance.
Perform a contact resistance or millivolt drop test
Perform power-factor or dissipation-factor tests on each phase and compare results. See Annex A for
on each pole with the breaker open and each phase additional guidance.
with the breaker closed. Compare power-factor
or dissipation-factor test results to manufacturer Perform insulation-resistance tests on each pole,
published data. In the absence of manufacturer phase-to-phase, and phase-to-ground with circuit
published data, compare results to similar breakers. breaker closed and across each open pole for a
minimum of one minute. Test voltage must be in
Perform power-factor or dissipation-factor tests accordance with the manufacturer published data.
on each bushing. Use hot collar procedures if See Annex A for additional guidance.
bushings are not equipped with a power-factor tap.
Power-factor or dissipation-factor test results and Perform a primary current injection test to determine
capacitance test results should be within 10% of minimum pickup current and long-time delay (at
nameplate rating for bushings. 300% pickup current), short-time pickup and time
delay, instantaneous pickup current, and ground-
Perform insulation-resistance tests on all control fault pick up and time delay. Compare results with
wiring with respect to ground. For units with solid- the time-current coordination curve for each circuit
state components, follow manufacturer instructions. breaker. Verify trip unit characteristics. Set adjustable
See Annex A for additional information. or programmable devices according to the protective
device coordination study. Replace defective devices,

31 n
NECA 90 Standard for Commissioning Building Electrical Systems

and adjust and retest where necessary. NOTE: Remove Measure minimum pickup voltage of the motor
or otherwise bypass current-limiting fuses from circuit control relay. Verify that the motor can charge the
breakers so equipped prior to applying simulated closing mechanism at the minimum voltage specified
overload and fault current. by the manufacturer. Minimum acceptable motor
closing voltage must not exceed 75% of rated control
Verify proper operation of auxiliary functions, such circuit voltage.
as shunt trip, undervoltage relays, and ground-fault, if
applicable, in accordance with manufacturer instructions. Measure minimum pickup voltage of the trip
actuator. Minimum voltage to operate the trip
5.5.18 Low-Voltage (1000V Class) Network actuator must not exceed 7.5% of rated control
Protectors circuit voltage. Verify that the actuator resets
correctly.
Verify trip-free operation. Verify correct operation
of the auto-open-close control handle. Verify that the Calibrate the network protector relays in accordance
protector closes automatically with source voltage on with manufacturer instructions. Adjust relay settings
the transformer side only. Verify that the protector in accordance with the short circuit and coordination
opens automatically when the source feeder breaker study.
is opened.
Verify phase rotation, phasing, and synchronized
Verify arc chutes are intact. Inspect moving and operation as required by the application.
stationary contacts for condition and alignment.
Verify that primary and secondary contact wipe and 5.5.19 Low Voltage Air Switches
other dimensions vital to satisfactory operation of
the breaker are correct. Perform mechanical operator Verify correct blade alignment, blade penetration,
and contact alignment tests on both the breaker and travel stops, and mechanical operation. Verify
its operating mechanism. appropriate lubrication on moving current-carrying
parts. Verify appropriate lubrication on moving and
Verify cell fit and element alignment. Verify racking sliding surfaces.
mechanism operation. Verify appropriate lubrication
on moving current-carrying parts. Verify appropriate Measure contact-resistance across each switchblade
lubrication on moving and sliding surfaces. Perform and fuseholder. Measure fuse resistance. Investigate
a leak test on submersible enclosures in accordance fuse-resistance values that deviate from each other by
with manufacturer published data. more than 15%. Verify that each fuse has adequate
mechanical support and contact integrity. Check
Verify that maintenance devices are available for that fuse clips are tight, secure, and free of corrosion.
servicing and operating the breaker. Verify correct phase barrier installation.

Perform insulation-resistance tests on each pole, Verify correct operation of all indicating and control
phase-to-phase, and phase-to-ground with protector devices. Test ground-fault protection systems in
closed and across each open pole for a minimum accordance with Section 5.5.25.
of one minute. Test voltage must be in accordance
with manufacturer published data. See Annex A for Perform insulation-resistance tests on each pole,
additional guidance. phase-to-phase, and phase-to-ground with switch
closed and across each open pole for a minimum
Verify current transformer ratios. of one minute. Test voltage must be in accordance
with manufacturer published data. See Annex A for
Perform a contact/pole-resistance test. Measure additional guidance.
the resistance of each power fuse for protectors so
equipped. Verify cubicle space heater operation, if so equipped.

n 32
Standard for Commissioning Building Electrical Systems NECA 90

5.5.20 High and Medium-Voltage Air Switches Clean relays. If relay design permits, remove each
relay from its case to inspect and clean. Inspect for
Verify correct blade alignment, blade penetration, loose screws, friction in moving parts, iron filings
travel stops, and mechanical operation. Verify that between the induction disk and permanent magnet,
expulsion-limiting devices are in place on all holders and any evidence of distress with the relay.
having expulsion-type elements. Verify that each
fuseholder has adequate mechanical support and Verify meter connections in accordance with
contact integrity. Check that fuse clips are tight, single line meter and relay diagrams. Tighten case
secure, and free of corrosion. connections. Verify tightness of mounting hardware
and connections. Inspect covers for correct gasket
Measure contact-resistance across each switchblade seal. Clean cover glass. Inspect shorting hardware,
and fuseholder. Measure fuse resistance. Investigate case-shorting contacts, connection paddles, and/or
fuse-resistance values that deviate from each other by knife switches. Verify the target reset.
more than 15%. Verify that each fuse has adequate
mechanical support and contact integrity. Check Inspect meters and relays for foreign material,
that fuse clips are tight, secure, and free of corrosion. particularly in disk slots of damping and
Verify correct phase barrier installation. electromagnets. Remove any foreign material from
the case.
Verify correct operation of all indicating and control
devices. Verify appropriate lubrication on moving Verify disk clearances. Verify contact clearance
current-carrying parts. Verify appropriate lubrication and spring bias. Inspect spiral spring convolutions.
on moving and sliding surfaces. Inspect disks and contacts for freedom of movement,
end play, alignment of rotating disk(s) and correct
Perform insulation-resistance tests on each pole, travel. Burnish contacts as needed. Inspect bearings
phase-to-phase and phase-to-ground with switch and/or pivots.
closed and across each open pole for a minimum
of one minute. Test voltage must be in accordance Determine the accuracy of all meters and verify
with manufacturer published data. See Annex A for watthour meter operation. Verify accuracy of
additional guidance. meters at all cardinal points. Calibrate watthour
meters according to manufacturer published data.
After achieving acceptable insulation resistance test Calibrate all meters at mid-scale. NOTE: Calibration
results, perform high potential testing on each pole instrument precision should be 50-percent or less
with the switch closed. Test each pole-to-ground than the precision of the instrument being tested.
with all other poles not under test grounded in For example, if the instrument being tested has a
accordance with the manufacturer published data precision of plus or minus 10-percent, the precision of
(see Annex A for additional guidance). Apply the calibration instrument should be plus or minus
test voltage for one minute. The insulation must 5-percent or better. Calibrate watt-hour meters to
withstand the overpotential test voltage applied. 0.50-percent. Verify instrument multipliers.
Verify cubicle space heater operation. Set relays and confirm proper fuse sizes and types
in accordance with the engineer’s specified values
5.5.21 Protective Relays and Metering Devices
indicated in the coordination study report and
Inspect meters, relays, and cases for physical related material. Test meters and protective relays at
damage, especially where subject to movement or the the specified settings.
possibility of pinched wires in doors or access panels,
broken parts, and indication of shipping damage. Perform insulation resistance tests in accordance
Remove shipping restraint material from protective with relay or metering component and test
relays, meters, and cases, if applicable. instrument manufacturer instructions. Disconnect
and isolate conductors, components, and equipment

33 n
NECA 90 Standard for Commissioning Building Electrical Systems

normally connected to equipment under test, time delay. Determine the time delay at a second
including phase and neutral connections, surge point on the timing curve for inverse time
protective devices, meters, relays, and control power relays.
and instrument transformers. Ground conductors,
components, and equipment not being tested. • Directional Power Relay (ANSI Device Number
Perform insulation resistance tests on protective 32): Determine the minimum pickup at
and control relays, from circuit-to-frame. Follow maximum torque angle. Determine the closing
the manufacturer instructions for allowable testing zone. Determine the maximum torque angle.
procedures for solid-state and microprocessor-based Determine the time delay. Verify the time delay
relays. at a second point on the timing curve for inverse
time relays. Perform phase angle and magnitude
NOTE: Do not perform insulation resistance testing contribution tests, to vectorially prove polarity
or over-potential (high-potential) testing of solid and connection of differential and directional
state, electronic devices, relays or meters. Perform relays.
diagnostic tests on electronic, solid-state components
in accordance with manufacturer instructions. • Loss of Excitation Relay (ANSI Device Number
40): Determine the maximum reach. Determine
Inspect targets and indicators. Determine pickup and the maximum torque. Determine the offset.
dropout of electromechanical targets. Verify correct
• Reverse Phase or Phase Current Balance Relay
operation of all light-emitting diode indicators. Set
(ANSI Device Number 46): Determine the
contrast for liquid-crystal display readouts.
pickup of each unit. Determine the percent
Set relays per engineer’s specified values, electrically slope. Determine the time delay.
test, and verify functional operation of relays:
• Negative Sequence Current Relay (ANSI Device
• Timing Relay (ANSI Device Number 2 or Number 46N): Determine the negative sequence
62): Determine the time delay. Verify proper alarm level. Determine the negative sequence
operation of the instantaneous contacts. minimum trip level. Determine the maximum
time delay. Verify two points on the time-
• Distance Relay (ANSI Device Number 21): current characteristic curve.
Determine the maximum reach. Determine the
maximum torque angle. Determine the offset. • Phase Sequence Voltage Relay (ANSI Device
Number 47): Determine the positive sequence
• Volts Per Hertz Relay (ANSI Device Number voltage to close the normally open contact.
24): Determine the pickup frequency at rated Determine the positive sequence voltage to open
voltage. Determine the pickup frequency at a the normally closed contact (undervoltage trip).
second voltage level. Determine the time delay. Verify the negative sequence trip. Determine
time delay to close the normally open contact
• Synchronism-Check Relay (ANSI Device with sudden application of 120% of pickup.
Number 25): Determine the closing zone at Determine the time delay to close the normally
rated voltage. Determine the maximum voltage closed contact upon removal of voltage when
differential that permits closing at zero degrees. previously set to rated system voltage.
Determine the live line, live bus, dead line, and
dead bus set points. Determine the time delay. • Machine or Transformer Replica-type Thermal
Verify the dead bus/live line, dead line/live bus, Relay (ANSI Device Number 49R): Determine
and dead bus/dead line control functions. the time delay at 300% of setting. Determine a
second point on the operating curve. Determine
• Undervoltage Relay (ANSI Device Number 27): the pickup.
Determine the dropout voltage. Determine the

n 34
Standard for Commissioning Building Electrical Systems NECA 90

• Machine or Transformer Temperature Relay reclosing interval. Verify lockout for


(ANSI Device Number 49T): Determine the trip unsuccessful reclosing. Determine the reset time.
resistance. Determine the reset resistance. Verify the instantaneous overcurrent lockout.

• Instantaneous Overcurrent Relay (ANSI Device • Frequency Relay (ANSI Device Number 81):
Number 50): Determine the pickup. Determine Verify the frequency set points. Determine the
the dropout. Determine the time delay. time delay. Determine the undervoltage cutoff.

• AC Time Overcurrent Relay (ANSI Device • Carrier or Pilot-Wire Receiver Relay (ANSI
Number 51): Determine the minimum pickup. Device Number 85): Determine the overcurrent
Determine the time delays at two points on the pickup. Determine the undercurrent pickup.
time current curve. Determine the pilot wire ground pickup level.

• Power Factor Relay (ANSI Device Number 55): • Differential Relay (ANSI Device Number 87):
Determine the tripping angle. Determine the Determine the operating unit pickup. Determine
time delay. the operation of each restraint unit. Determine
the slope. Determine the harmonic restraint.
• Overvoltage Relay (ANSI Device Number 59): Determine the instantaneous pickup. Perform
Determine the overvoltage pickup. Determine phase angle and magnitude contribution tests,
the time delay to close the contact with sudden to vectorially prove polarity and connection of
application of 120% of pickup. differential and directional relays.
• Voltage Balance Relay (ANSI Device Number • Multi-function processor: Perform manufacturer
60): Determine the voltage difference to close recommended tests and self-testing of relays.
the contacts with one source at rated voltage. Document functional settings of relays using
• Transformer Sudden Pressure Relay (ANSI printouts or by scrolling through relay settings.
Device 63): Determine the rate-of-rise or the Record model number, style number, serial
pickup level of suddenly applied pressure in number, firmware revision, software revision,
accordance with manufacturer specifications. and rated control voltage. Download all events
Verify the operation of the 63 FPX seal-in from the event recorder in filtered and unfiltered
circuit. Verify the trip circuit to remote breaker. mode before performing any tests on the relay.
Download the sequence-of-events recorder prior
• Ground-Protective Relay (ANSI Device Number to testing the relay. Verify operation of light-
64): Determine the maximum impedance to emitting diodes, display, and targets. Record
ground causing relay pickup. the passwords for all access levels. Clean the
front panel and remove foreign material from
• AC Directional Overcurrent Relay (ANSI the case. Check tightness of connections. Verify
Device Number 67): Determine the directional that the frame is grounded in accordance with
unit minimum pickup at maximum torque manufacturer instructions. Download settings
angle. Determine the closing zone. Determine from the relay. Print a copy of the settings for
the overcurrent unit pickup. Determine the the report and compare the settings to those
overcurrent unit time delay at two points on specified in the coordination study. Apply
the time-current curve. Perform phase angle voltage or current to all analog inputs and verify
and magnitude contribution tests, to vectorially correct registration of the relay meter functions.
prove polarity and connection of differential Check functional operation of each element
and directional relays. used in the protection scheme as described
• AC Reclosing Relay (ANSI Device Number 79): for electromechanical and solid-state relays in
Determine the time delay for each programmed accordance each relay function. Check operation

35 n
NECA 90 Standard for Commissioning Building Electrical Systems

of all active digital inputs. Check all output Perform an insulation resistance test from each pole-
contacts or SCRs, preferably by operating the to-pole and each pole-to-ground with breaker closed
controlled device such as circuit breaker, auxiliary and across open contacts of each phase using a test
relay, or alarm. For pilot schemes, perform a voltage in accordance with manufacturer instructions
loop-back test to check the receive and transmit for a minimum of one minute. See Annex A for
communication circuits. For pilot schemes with additional guidance.
direct transfer trip (DTT), perform transmit and
received DTT at each terminal. Upon completion Perform insulation-resistance tests on all control
of testing, reset all min/max recorders, fault wiring with respect to ground. For units with solid-
counters, sequence of events recorder, and all state components, follow manufacturer instructions.
event records. Verify all inputs, outputs, internal See Annex A for additional information.
logic, and timing elements used in protection,
Check circuit breakers for proper mounting, conductor
metering, and control functions. Verify relays
size (ampacity), and feeder designation. Operate circuit
display correct date and time. If connected
breakers to insure smooth operation. Inspect case
to a time synchronization source, verify time
and arc chutes for cracks and other defects. Check
synchronization.
the tightness of connections with torque wrench in
Verify that each set of relay contacts perform its accordance with manufacturer instructions.
intended function in the control scheme including
breaker trip tests, close inhibit tests, 86 lockout Perform a primary current injection test to
tests, and alarm function. Verify applicable determine minimum pickup current and long-time
communication points end device(s). delay (at 300% pickup current), short-time pickup
and time delay, instantaneous pickup current, and
After the equipment is initially energized, measure ground-fault pick up and time delay. Determine
the magnitude and phase angle of all inputs and instantaneous pickup current by run-up or pulse
compare to expected values. method. Clearing times should be within six (6)
cycles or less. Record trip times. Compare results
Use the manufacturer recommended tolerances with the time-current coordination curve for each
when other tolerances are not specified. When circuit breaker. Verify trip unit characteristics. Set
critical test points are specified in contract adjustable or programmable devices according to
documents or engineering reports, calibrate the relay the protective device coordination study. Replace
to those points even though other test points may be defective devices, adjust and retest where necessary.
out of tolerance. NOTE: Remove or otherwise bypass current-limiting
fuses from circuit breakers so equipped prior to
See NECA 430 for additional information and applying simulated overload and fault current. NOTE:
guidance. All tripping times should fall within the manufacturer
time current coordination tolerance band. Circuit
5.5.22 Molded-Case Circuit Breakers
breakers with trip times varying from published
Operate each circuit breaker to insure smooth tolerance band more than 10% at 300% current
operation. Inspect the case, operating mechanism, should be replaced.
contacts, and arc chutes for cracks and other defects.
Verify proper operation of circuit breaker charging Perform minimum operation voltage test on shunt
mechanism, if so equipped. Check trip unit reset trip and close coils in accordance with manufacturer
operation. instructions.

Perform a contact resistance test of each phase Activate auxiliary protective devices, such as ground-
and compare results. See Annex A for additional fault or undervoltage relays, to verify operation
guidance. of shunt trip devices. Test ground-fault to ensure

n 36
Standard for Commissioning Building Electrical Systems NECA 90

activation based on time current coordination curve Perform an insulation resistance test from each pole-
for the ground-fault relay. to-pole and each pole-to-ground with breaker closed
and across open contacts of each phase using a test
Verify correct operation of any auxiliary features voltage in accordance with manufacturer instructions
such as trip and pickup indicators, zone interlocking, for a minimum of one minute. See Annex A for
electrical close and trip operation, trip-free, and anti- additional guidance.
pump functions.
Perform insulation-resistance tests on all control
Test AFCI and GFCI circuit breakers in accordance wiring with respect to ground. For units with solid-
with manufacturer instructions. Turn off and state components, follow manufacturer instructions.
unplug all appliances from receptacles supplied by See Annex A for additional information.
AFCI and GFCI circuit breakers prior to testing.
Test circuit breakers by pressing the TEST button. Perform a contact resistance test of each phase and
Circuit breakers should trip when the TEST button is compare results. See Annex A for additional guidance.
pressed, and the handle should move to the center or
TRIPPED position. Reset circuit breakers by moving Perform a primary current injection test to
the handle fully to the OFF position, then fully to the determine minimum pickup current and long-time
ON position. If the circuit breaker opens when the delay (at 300% pickup current), short-time pickup
TEST button is pressed and can be reset, the circuit and time delay, instantaneous pickup current, and
breaker is functioning properly. If the circuit breaker ground-fault pick up and time delay. Determine
does not open when the test button is pressed or instantaneous pickup current by run-up or pulse
cannot be reset, the circuit breaker is defective and method. Clearing times should be within six (6)
must be replaced. NOTE: OSHA does not recognize cycles or less. Record trip times. Compare results
the use of hand held AFCI test indicators, and circuit with the time-current coordination curve for each
breaker manufacturers only recognize the use of circuit breaker. Verify trip unit characteristics. Set
the test button on circuit breakers as the proper test adjustable or programmable devices according to
method for AFCI circuit breakers. the protective device coordination study. Replace
defective devices adjust and retest where necessary.
See NECA 407 for additional information and NOTE: Remove or otherwise bypass current-limiting
guidance. See NECA 169 for additional information fuses from circuit breakers so equipped prior to
for GFCI/AFCI circuit breakers. applying simulated overload and fault current. NOTE:
All tripping times should fall within the manufacturer
5.5.23 Low-Voltage Power Circuit Breakers time current coordination tolerance band. Circuit
breakers with trip times varying from published
Perform all mechanical operator and contact
tolerance band more than 10% at 300% current
alignment tests on both the breaker and its operating
should be replaced.
mechanism in accordance with manufacturer
published data. Perform minimum operation voltage test on shunt
trip and close coils in accordance with manufacturer
Verify the arc chutes are intact. Inspect moving and
instructions.
stationary contacts for condition, wear, and alignment.
Verify that primary and secondary contact wipe and Verify proper operation of any auxiliary features
other dimensions vital to satisfactory operation of such as trip and pickup indicators, zone interlocking,
the breaker are correct. Verify cell fit and element electrical close and trip operation, trip-free, anti-
alignment. Verify racking mechanism operation. pump function, trip unit battery condition, and reset
Verify appropriate lubrication on moving current- all trip logs and indicators.
carrying parts. Verify appropriate lubrication on
moving and sliding surfaces. Verify proper operation of circuit breaker charging
mechanism.

37 n
NECA 90 Standard for Commissioning Building Electrical Systems

5.5.24 Grounding Systems by the voltage drop method. Investigate point-to-point


resistance values which exceed 0.5 ohm.
Visually examine grounding conductors and paths,
such as raceway couplings, fittings, and connectors. Verify equipment grounding path to earth, including
Check the tightness of conductor and raceway ground rods and interconnecting wiring, ground bus
connections. on equipment, room and pullbox connections, and
associated intermediate copper ground conductors,
Confirm that the neutral is grounded only at and structural steel or reinforcing bar connection,
the service equipment. Confirm that the neutral rod connection and intermediate conductor in tests,
is not grounded on the load side of the service where applicable.
disconnecting means enclosure. NOTE: It is
important to coordinate this testing and follow proper Notify the CxA immediately in writing if the
test procedures when performing insulation resistance specified ground resistance cannot be obtained with
testing on conductors and equipment. the ground system installed in accordance with the
construction documents and in accordance with the
Inspect ground conductors, ground buses, NEC.
and connections for conformance with design
specifications and NEC requirements. Verify ground After energizing, measure phase-to-phase, phase-to-
system is in compliance with drawings, specifications, neutral, and neutral-to-ground voltages to confirm
and NFPA 70 National Electrical Code. proper neutral-to-ground bonding.

Perform fall-of-potential tests in accordance with 5.5.25 Ground-Fault Protection Systems


IEEE 81, on the main grounding electrode system.
Test each ground rod individually, and test all Test ground-fault protection systems installed on
ground rods interconnected as a system. Resistance services when first installed on site. Conduct testing
values must be no greater than those specified in the in accordance with manufacturer instructions.
contract documents. NOTE: In general, maximum Maintain a written record of testing, and make
resistance to ground should be less than 5 ohms. available to the authority having jurisdiction when
requested. For Healthcare Facilities and Critical
Ground resistance testing should be conducted Operations Power Systems, test each level of ground-
only when the earth is dry, and a minimum of 48 fault protection. Ensure that all levels of ground-fault
hours after the most recent precipitation. Record the protection achieve 100% selectivity. See NECA 700
ambient temperature, date, time, approximate water for additional information and guidance.
table level (as obtained from local geologists), type of
earth materials, and measured earth resistivity. Inspect ground-fault protection system components
for damage and errors in polarity or conductor
Perform point-to-point tests in accordance with IEEE routing. Inspect the neutral main bonding connection.
81to determine the ground resistance between the Verify that ground connection is made upstream of
main ground system and all major electrical equipment the neutral disconnect link and on the line side of any
frames, system neutral, and/or derived neutral points. ground-fault sensor. Verify that the neutral sensors are
Resistance values must be no greater than those connected with correct polarity on both primary and
specified in the contract documents. NOTE: In general, secondary. Verify that all phase conductors and the
maximum resistance to ground should be less than 5 neutral pass through the sensor in the same direction
ohms. Alternatively, perform ground continuity test for zero sequence systems. Verify that grounding
between main ground system and equipment frame, conductors do not pass through the zero sequence
system neutral and/or derived neutral point by passing sensors. Verify that the grounded conductor is solidly
a minimum of 10 amperes DC current between the grounded. Verify correct operation of all functions of
ground reference system and the ground point to be the self-test panel. Verify trip operation, no trip test,
tested. Measure voltage drop and calculate resistance and non-automatic reset.

n 38
Standard for Commissioning Building Electrical Systems NECA 90

For summation type systems utilizing phase and Set pick up and time delay settings in accordance
neutral current transformers, verify correct polarities with the short circuit and coordination study.
by applying current to each phase-neutral current
transformer pair. This test also applies to molded- See NECA 400 for additional information and
case breakers utilizing an external neutral current guidance.
transformer. Relay should operate when current
5.5.26 Panelboards
direction is the same relative to polarity marks in the
two current transformers. Relay should not operate Check all panelboards for proper load balance
when current direction is opposite relative to polarity between phase conductors and adjust the loads as
marks in the two current transformers. necessary to bring unbalanced phases within 20% of
average load. Measure and record current readings
Disconnect the neutral link and perform neutral
on all phase conductors and the neutral conductor.
insulation resistance testing. See Annex A for
Ensure that the circuit directory for each panel is
additional guidance. Record the insulation resistance,
updated after load balancing, typed, and placed in
and replace the neutral link. NOTE: Insulation
each panel.
resistance test results should indicate that no shunt
ground paths exist. Check torque and tighten all accessible connections
to manufacturer specifications.
Perform insulation-resistance tests on all control
wiring with respect to ground. For units with solid- Perform infrared scan in accordance with Annex
state components, follow manufacturer instructions. A. Perform infrared scan after each panel has been
See Annex A for additional information. operating with maximum load for at least one hour
or until the temperature has stabilized. Identify all
Determine the relay pickup current by primary
hot spots, and promptly correct sources of heating
current injection at the sensor and the circuit
problems.
interrupting device operated. Relay pickup current
must be within 10% of the device dial or fixed See NECA 407 for additional information and
setting, and in no case greater than 1200 amperes. guidance.
Verify that the relay does not operate at 90% of the
pickup setting. Verify pickup is less than 125% of 5.5.27 Receptacles and Wiring Devices
setting or 1200 amperes, whichever is less.
Test every installed receptacle and wiring device
Test the relay timing by injecting 150% and 300% for proper phasing and grounding. Test for open
of pickup current into sensor. Electrically monitor ground, reversed polarity, open hot, open neutral,
and record total trip time. Relay timing must be hot and ground reversed, and neutral and hot open.
in accordance with manufacturer published time Verify the continuity of the grounding circuit in each
current characteristics curves but in no case longer receptacle and wiring device.
than one second at 3000 amperes.
Test the retention force of the grounding blade of each
Test system operation at 57% of rated voltage. receptacle (except pin-and-sleeve and locking-type
receptacles). Replace devices with less than 115 g (4
Test the zone interlock system by simultaneous ounces) of retention force.
sensor current injection and monitor the zone
blocking function. Test each GFCI receptacle and each GFCI circuit
breaker to ensure that the ground-fault circuit
Inspect zero sequence systems for symmetrical interrupter will not operate when subjected to a
alignment of core balance transformers about all ground-fault current of less than 4 milliamperes, and
current carrying conductors. will operate when subjected to a ground-fault current
exceeding 6 milliamperes. Perform testing with an

39 n
NECA 90 Standard for Commissioning Building Electrical Systems

instrument specifically designed and manufactured 5.5.28 Engine Generators


for testing ground-fault circuit interrupters. NOTE:
Pushing the receptacle or circuit breaker “TEST” button Verify that the generator is mounted in such a
operation is not acceptable as a substitute for this test. manner to prevent combustible materials from
Replace GFCI receptacles or circuit breakers that do accumulating under the generator. Inspect for and
not shut off power at 5 milliamperes within 1/40th of remove any foreign objects or loose debris, such as
a second. Test the replacement unit the same way. remaining packing materials, building materials,
tools, hardware, rags, paper, and leaves, that could
Test AFCI receptacles using the test button on the be drawn into the generator or alternator air intakes.
receptacle in accordance with the manufacturer Ensure that the generator and the surrounding area
instructions. NOTE: OSHA does not recognize the are clean, dry, and free from obstructions. Ensure
use of hand held test indicators, and receptacle that all covers and guards are in place and secure.
manufacturers only recognize the use of the test
button on receptacles as the proper test method for Perform a phase rotation test. Verify that the
AFCI receptacles. alternator is connected for the required voltage
and phase rotation. Measure the clearance in the
Replace defective AFCI and GFCI devices and retest. If generator and exciter air gap. Verify that the air gap
the new receptacle provides the same result, troubleshoot is in accordance with manufacturer specifications.
devices, fixed wiring, and appliances connected to Check the alternator for loose items such as shaft
the circuit. Correct any deficiencies and retest. keys, and couplings. Tighten or replace loose or
damaged components.
After energizing receptacles and wiring devices and
placing under normal loads, check for evidence Inspect the insulation on all conductors. Replace
of thermal damage. Where there is evidence of conductors with damaged insulation. Inspect
overheating or failure, perform appropriate thermal connections and terminations for damage. Repair
evaluation and other tests to determine the extent of or replace damaged connections and terminations.
damage. Make repairs, rework wiring, and replace Support all conductors to prevent stress on
damaged devices as needed. connections and termination, and to protect
conductors from damage from rotating parts or
Test receptacle circuits for voltage drop, impedance sharp edges.
on phase and neutral conductors, and proper GFCI/
AFCI operation at the last receptacle on the branch Check bolts, fasteners, and hardware for tightness.
line. NOTE: At design amperage, voltage drop should Torque hardware in accordance with manufacturer
not exceed 6% for circuits used for computers or instructions.
voltage sensitive equipment, and should not exceed
10% for all other circuits. At all times the load voltage Measure the winding resistance using a DC bridge
should not drop below 111 volts. and a meter capable of readings in the milli-ohm
range. Correct measured values to operating
Demonstrate the operation of each switch, timer, temperature and calculate copper (I2R) losses
and other electrical control wiring device with the and efficiency, and compare with manufacturer
systems fully energized and operating. Demonstrate specifications.
each operation a minimum of three times.
Perform insulation resistance and dielectric
Replace receptacles and devices that are deficient, tests. Calculate polarization index and dielectric
and retest. absorption, and perform insulation power factor
testing in accordance with IEEE standard 43. See
See NECA 130 and NECA 169 for additional Annex A for additional guidance. Perform tests on
information and guidance. armature and rotating or stationary field windings.

n 40
Standard for Commissioning Building Electrical Systems NECA 90

Perform an overpotential (high-potential) test on each step. Operate generator at 100% of full load
alternators with ratings greater than 600 Volts. See nameplate rating for a minimum of four hours.
Annex A for additional guidance. Test each phase Record voltage, current, frequency, and all gaged
separately with the other phases and the winding engine conditions every 15 minutes during full-load
temperature detectors grounded. Disconnect any test. Verify all generator-running characteristics.
capacitors and surge arrestors during the test. Verify starting battery-charging system.

Perform vibration test for each main bearing Perform functional testing of generator systems,
cap. Vibration levels must be in accordance with including automatic transfer switches (ATSs) and
manufacturer published data. uninterruptible power supplies (UPSs). Include power
outage simulation, start-up and transfer of power to
Verify proper operation of the engine governor the generator system, operation of loads connected
and alternator voltage regulator systems upon to the generator system, start-up and shut-down of
initial start-up in accordance with manufacturer equipment related to the fire alarm system, electrical
instructions. Verify proper frequency and voltage power distribution systems, motor control centers and
magnitude at no-load with the engine operating at starters, and variable frequency drives. Load bank test
rated speed. the UPS if necessary to supply load during testing.
Using a power line disturbance monitor, measure
Verify all generator functions. Functionally test
and record time delays for power failure to engine
engine shutdown for low oil pressure, over-
start command, engine start command to engine start
temperature, over-speed, and other protection
(cranking time), engine start to the point where the
features as applicable. Verify all alarms, meters, and
generator is operating at rated voltage and frequency
auxiliaries and interlocks to the BAS. Verify fuel
and total time from power failure until generators are
system, fuel storage tank, and level and low fuel
connected to the load.
indication alarms.
Verify that adjustable settings are set in
Verify appropriate mechanical system and control
accordance with manufacturer instructions and
system restart functions of all equipment served by
recommendations.
the generator. Verify combustion and ventilation air
damper functions and pressure drop of exhaust for See NECA/EGSA 404 and NECA 406 for additional
generators located indoors. information and guidance.
Verify proper operation of multiple generators 5.5.29 Automatic Transfer Switches (ATSs)
operating in parallel, including operating sequence,
lead-lag generator controls, governors, regulators, Check transfer switches for completeness of
speed control, and load sharing, including sharing assembly. Check switches for proper alignment, and
real and reactive power. Verify that load-sharing for loose parts and insulation damage. Verify proper
controls are set in accordance with manufacturer grounding.
instructions. Functionally test the system by
removing one generator from the system and Verify that manual transfer warnings are attached
verifying that the remaining generator(s) operate and visible. Perform manual transfer operation.
automatically and properly. Verify soft-loading Verify positive mechanical interlocking between
capability of each generator for systems with a normal and alternate sources.
closed-transition between sources.
Perform an insulation resistance test on each pole
Perform load bank testing of each generator. Apply from phase-to-phase and phase-to-ground with
step (block) loads of 0%, 25%, 50% and 100% of the switch closed and across each open pole in
full load nameplate rating. Record voltage, current, accordance with manufacturer instructions for a
frequency, and all gaged engine conditions at minimum of one minute. Perform test with the

41 n
NECA 90 Standard for Commissioning Building Electrical Systems

switch in both source positions. See Annex A for 5.5.30 Variable Frequency Drives (VFDs)
additional guidance.
Ensure that the branch-circuit, short-circuit, and
Perform insulation-resistance tests on all control ground-fault protective device specified in the
wiring with respect to ground. For units with solid- manufacturer instruction is installed.
state components, follow manufacturer instructions.
Verify the tightness of all control connections. See Verify that the VFD rated output current is greater
Annex A for additional information. than the motor FLA. NOTE: VFDs are current rated,
not horsepower rated.
Perform a contact resistance test of each phase and
compare results. See Annex A for additional guidance. Make sure that supply voltage, VFD rated voltage,
and motor voltage match. Check for proper jumper,
Monitor and document ATS settings and timers screw, or switch settings for given drive supply
for manual testing/transfer, normal voltage sensing voltage parameters, if so equipped.
relays, emergency voltage sensing relays, in-phase
monitor, time delay upon transfer, alternate voltage Ensure that VFDs are installed with an ambient
sensing relay, interlocks and limit switch functions, temperature no greater than 40°C (104°F) with a
timing delay and retransfer upon normal power humidity level from 10 to 90% non-condensing.
restoration over the course of testing transfer Ensure that there is adequate clearance around VFDs
switches. Adjust timer settings in accordance with for cooling in accordance with the manufacturer
contract documents and manufacturer instructions instructions. Ensure vent path openings are free from
for proper operation. debris and that heat transfer surfaces are clean.

For engine-generator applications, perform system Verify that there are no power factor improvement
operational testing. Verify that the generator is capacitors installed on the VFD output between the
stopped with the control switch in the AUTO VFD and the motor. NOTE: Power factor capacitors
position. Verify that the utility bus is energized, and connected on the VFD output will cause VFD damage.
manually close utility breaker. Verify the position Verify that there are no power factor improvement
of the transfer switch and indication light status. capacitors are installed within 100m (300ft) of the
Measure input and output voltage of the transfer VFD input without a line reactor on the VFD input.
switch. Check the phasing of the normal (utility) bus NOTE: Upstream capacitors may cause nuisance
to the output bus of the transfer switch. Manually overvoltage tripping of VFDs.
open the utility breaker. Verify that generation
For 460Vac or 575Vac installations, verify that the
systems start, and that transfer switches transfer the
motor specification for the cable length and carrier
loads to the generation system. Check the phasing
frequency limitations are within recommended
of the emergency (generator) bus to the output bus
limits. NOTE: A load reactor or an output filter may
of the transfer switch. Manually close the utility
be needed, if recommended by the manufacturer.
breaker. Verify that the transfer switch transfers
the loads to the utility, and that generation systems Verify that all electrical connections are tight.
cooldown, stop, and reset for automatic operation. Verify correct connections of circuit boards, wiring,
Push the TEST switch to simulate normal source disconnects, and ribbon cables. Make sure that VFDs
failure. Verify that transfer switches and generation and all the electrical connections are free of debris.
systems operate properly.
Verify that the motor and the load rotate freely.
Verify appropriate lubrication on moving current- Check for bad bearings, correct belt tension, belt
carrying parts. Verify appropriate lubrication on alignment, and/or shaft alignment.
moving and sliding surfaces.

n 42
Standard for Commissioning Building Electrical Systems NECA 90

Perform startup of VFDs in accordance with Verify the phase rotation of the VFD output in both
manufacturer instructions. Prior to starting the VFD mode and the BYPASS mode, if so equipped.
system, verify that the VFD system can be operated Correct incorrect phase rotation in accordance with
at full speed (60Hz) without causing damage to the manufacturer instructions.
other equipment or endangering personnel.
Record harmonic distortion at the VFD output,
NOTE: VFDs will cause noise on neutral and at the VFD input, and at the upstream source that
ground conductors and voltage fluctuations on phase supplies the VFD.
conductors during normal operation. Additionally,
VFDs induce motor bearing currents and shaft Check and program all the necessary software
voltages that will cause pitting of the shaft and parameters such as acceleration time, deceleration
premature motor failure. Check motors for excessive time, application (constant torque, variable torque),
voltages and currents. Install shaft voltage/current carrier frequency, motor voltage, and motor overload
eliminators when needed in accordance with protection level in accordance with manufacturer
manufacturer instructions. instructions. NOTE: Incorrect software programming
may result in equipment malfunction or damage.
Without applying power to the VFD, check the Record any changes to the software for future
supply line phase-to-phase voltages. Voltages should reference.
be within 3% of each other and within 10% of the
VFD nameplate rating. Perform operational tests by initiating control
devices. Slowly vary VFD speed between minimum
Start and run the drive while observing the test, and maximum speeds. Observe motor and load for
metering, and fault indicators, if so equipped. unusual noise or vibration. Program VFDs to skip
Activate the various safety devices when possible, to frequencies that cause excessive noise or vibration.
ensure proper operation. Calibrate relays and test Verify operation of VFDs from remote start/stop and
parameters for input phase loss protection, input speed control signals.
overvoltage protection, output phase rotation, over-
temperature protection, DC overvoltage protection, 5.5.31 AC Synchronous Motors and Generators
over-frequency protection, drive overload protection,
Inspect for physical damage and for completion
and fault alarm outputs. Test the motor overload
of installation. Check for loose items such as
relay elements by injecting primary current through
shaft keys and couplings. Inspect air baffles, filter
the overload circuit and monitoring trip time of the
media, cooling fans, slip rings, brushes, and brush
overload element.
rigging. Slip ring wear and brushes should be within
Calibrate VFDs to the system’s minimum and manufacturer tolerances for continued use. Brush
maximum speed control signals. Set adjustable rigging should be intact.
parameters to match the settings provided. Verify
Check all connections for tightness and proper
drive overcurrent setpoints are correct for their
insulation.
application. If a VFD is used to operate multiple
motors, verify individual overload element ratings Uncouple the motor from the load (drive
are correct for their application. Apply minimum machinery), and manually rotate motors to
and maximum speed setpoints. Verify that setpoints verify that motors rotate freely and are free from
are within limitations of the load coupled to the interference.
motor. Test and record output volts and amps
while the drive is at 25%, 50%, and 100% of rated Verify the application of appropriate lubrication and
speed and attached load. Observe for balance and lubrication systems.
performance within manufacturer specifications.

43 n
NECA 90 Standard for Commissioning Building Electrical Systems

Measure the resistance of machine-field winding, Perform insulation-resistance tests and dielectric
exciter-stator winding, exciter-rotor windings, and absorption tests (polarization index and dielectric
field discharge resistors. absorption ratio) on the main rotating field winding,
the exciter field winding, and the exciter-armature
Prior to re-energizing, apply voltage to the exciter supply winding in accordance with ANSI/IEEE Standard 43
and adjust exciter-field current to nameplate value. and in accordance with manufacturer instructions.
Verify that the field application timer and the enable • For motors 200 HP and less, rated 600V and
timer for the power-factor relay have been tested and set less, perform insulation resistance and dielectric
to the motor drive manufacturer recommended values. absorption testing.
Perform phase-to-phase stator resistance test on • For motors greater than 200 HP and rated from
machines 2300 volts and greater. Perform resistance 600V to 2400 V, perform insulation resistance
tests on resistance temperature detector (RTD) testing and calculate dielectric absorption ratio
circuits. Verify that resistance temperature detector and polarization index.
(RTD) circuits conform to drawings.
• For motors exceeding 200 HP and 2400V,
Perform insulation-resistance test on insulated bearings perform insulation resistance and calculate
in accordance with manufacturer instructions. dielectric absorption ratio and polarization
index, and perform high potential testing.

Table 3 Motor Vibration Criteria


Frequency (X RPM) Motor Maximum Amplitude Maximum Amplitude
Component (in/sec Peak) (mm/sec Peak)
Overall 0.1 2.5
0.4 – 0.5 Not detectable
1X See Motor Balance Specifications
2X 0.02 0.5
Harmonics (NX) Not detectable
Roller Element Bearings Not detectable
Side Bands Not detectable
Rotor Bar/Stator Slot Not detectable
Line Frequency (60 Hz) Not detectable
2X Line Frequency (120 Hz) 0.02 0.5

Table 4 Motor Balance Specifications


Motor Speed Special Application Standard Application
(RPM) (in/sec Peak) (mm/sec Peak) (in/sec Peak) (mm/sec Peak)
900 0.02 0.5 0.08 2.0
1200 0.026 0.66 0.08 2.0
1800 0.04 1.0 0.08 2.0
3600 0.04 1.0 0.08 2.0

n 44
Standard for Commissioning Building Electrical Systems NECA 90

See Annex A for additional guidance. Perform critical to operations). This includes motors, pumps,
tests on armature and rotating or stationary field turbines, compressors, engines, bearing, gearboxes,
windings. Disconnect the neutral connection on agitators, fans, blowers, and shafts. All tests should
the stator, and test each winding with respect to be conducted at normal operating speed at full load
the other windings and ground. Perform high- conditions. The motor must meet the applicable
potential testing on each phase separately with the vibration criteria as specified in Tables 3 and 4.
other phases and the winding temperature detectors
grounded. Disconnect any capacitors and surge Perform laser alignment on all shaft coupled
arrestors during the test. machines (see Figure 1). All shaft-to-shaft center line
alignments should meet the requirements of Table
Momentarily energize (bump) motors to verify 5 unless more precise tolerances are specified by
proper phase rotation. the machine manufacturer. The tolerances specified
in Table 5 are the maximum allowable deviations
Perform vibration monitoring on all rotating from Zero-Zero Specifications or alignment target
equipment greater than 7.5 HP (or smaller if highly

Figure 1. Coupled Shafts Alignment

Table 5 Coupled Shaft Alignment Tolerance Values


RPM Tolerance Specification
Soft Foot All <0.002 inch (0.0508 mm) at each foot
Horizontal & Vertical Parallel Angularity/Gap Inch/10 inch
Offset per Inch (25.4 mm) of (mm/254 mm) Coupling Diameter
Spacer Length
Short Couplings <1000 0.005 in (1.2700 mm) 0.015 in (0.3810 mm)
1200 0.004 in (1.0160 mm) 0.010 in (0.2540 mm)
1800 0.003 in (0.7620 mm) 0.005 in (0.1270 mm)
3600 0.002 in (0.5080 mm) 0.003 in (0.0762 mm)
7200 0.001 in (0.2540 mm) 0.0025 in (0.0635 mm)

Couplings with <1000 0.0020 in (0.0508 mm)


Spacers 1200 0.0015 in (0.0381 mm)
1800 0.0010 in (0.0254 mm)
3600 0.0005 in (0.0127 mm)
7200 0.0003 in (0.0076 mm)

45 n
NECA 90 Standard for Commissioning Building Electrical Systems

specifications (i.e., an intention targeted offset and/or Verify the absence of unusual mechanical or
angularity). Figure 2 illustrates the concept of offset electrical noise or signs of overheating during initial
and angular motor alignment. test run.

Upon startup, verify the absence of unusual Perform insulation-resistance tests and dielectric
mechanical or electrical noise or signs of overheating. absorption tests (polarization index and dielectric
absorption ratio) on the main rotating field winding,
Verify operation of machine space heater, if the exciter field winding, and the exciter-armature
applicable. winding in accordance with ANSI/IEEE Standard 43
and in accordance with manufacturer instructions.
Perform vibration test.
• For motors 200 HP and less, perform insulation
5.5.32 AC Induction Motors and Generators
resistance testing and calculate the dielectric
(Alternators)
absorption ratio.
Inspect air baffles, filter media, cooling fans, slip
• For motors greater than 200 HP, perform
rings, brushes, and brush rigging. Verify that
insulation resistance testing and calculate
resistance temperature detector (RTD) circuits
polarization index.
conform to drawings. Verify that metering or
relaying devices utilizing RTDs have the correct • For motors exceeding 1000 HP and 4000V,
rating. perform insulation resistance, dielectric
absorption, and calculate polarization index,
Verify correct application of appropriate lubrication and perform high potential testing.
and lubrication systems.

Figure 2. Offset and Angular Motor Alignment

n 46
Standard for Commissioning Building Electrical Systems NECA 90

See Annex A for additional guidance. Perform winding in accordance with ANSI/IEEE Standard 43
tests on armature and rotating or stationary field and in accordance with manufacturer instructions.
windings. Disconnect the neutral connection on See Annex A for additional guidance.
the stator, and test each winding with respect to
the other windings and ground. Perform high- • For motors 200 HP and less, perform insulation
potential testing on each phase separately with the resistance testing and calculate the dielectric
other phases and the winding temperature detectors absorption ratio.
grounded. Disconnect any capacitors and surge
• For motors greater than 200 HP, perform
arrestors during the test.
insulation resistance testing and calculate
Perform stator resistance test phase-to-phase. polarization index.

Perform insulation-resistance test on bearing Perform an insulation-resistance test on bearing


pedestal in accordance with manufacturer pedestal in accordance with manufacturer
instructions. instructions. Pedestal bearing insulation resistance
must not be less than 1.0 megohm at 500 volts DC.
Perform resistance tests on RTDs.
Perform resistance tests on RTDs.
Verify operation of the motor space heater, if
applicable. Verify operation of the motor space heater, if
applicable.
Momentarily energize (bump) motors to verify
proper phase rotation. Measure armature running current and field current
or voltage. Compare to nameplate.
Measure running current and evaluate relative to
load conditions and nameplate full-load amperes. 5.5.34 Battery Systems

Torque battery rack connections to manufacturer


5.5.33 DC Motors and Generators
instructions. Inspect battery racks and insulating
Inspect baffles, filter media, cooling fans, slip rings, covers for physical damage, loose connections,
brushes, and brush rigging. cracking, dielectric leaks, dirt, corrosion, and seismic
parts and spacers.
Verify correct application of appropriate lubrication
and lubrication systems. Check DC power, control power, and battery
connections including cell-to-cell, tier-to-tier, rack-
Inspect commutator and tachometer generator. to-rack, and UPS to battery module connections, if
applicable, for correct polarity.
Verify the absence of unusual mechanical or
electrical noise or signs of overheating during initial Check battery jars and covers for cracking,
test run. distortion, dielectric leaks, dirt, and corrosion.
Inspect jar and post seals. Check electrolyte levels,
Verify that resistance temperature detector (RTD) if applicable. Check vented lead-acid batteries and
circuits conform to drawings. Verify that metering vented Nickel-Cadmium batteries for clogged flame
or relaying devices utilizing RTDs have the correct arresters. Inspect vented lead-acid battery cells, and
rating. check plates for cracks, sulfate, and hydration.
Perform insulation-resistance tests and dielectric Measure and record the cell-to-cell and terminal
absorption tests (polarization index and dielectric connection resistance with a digital low-resistance
absorption ratio) on the main rotating field winding, ohmmeter. Remake connections having a resistance
the exciter field winding, and the exciter-armature of more than 10% above the average.

47 n
NECA 90 Standard for Commissioning Building Electrical Systems

Inspect terminals for loose or broken connections, and After charging batteries, measure each cell voltage
burned insulation. Check for liquid contamination and total battery voltage with charger in float mode
(battery electrolyte and oil from capacitors). of operation. Measure ripple current, specific gravity,
De-energize equipment and make corrections or electrolyte temperature, electrolyte fill level, overall
repairs for any abnormal operating conditions in float voltage measured at the battery terminals,
accordance with manufacturer instructions. charger output current and voltage, ambient
temperature, condition of ventilation and monitoring
Verify the presence of flame arresters, adequacy equipment, and temperature of the negative terminal
of battery support racks, mounting, anchorage, of each cell of the battery.
grounding, and clearances, ventilation of battery
room enclosure, and existence of suitable eyewash Load test batteries in accordance with manufacturer
equipment. instructions. The values for discharge time and end
point voltage should be selected from the battery
Measure the voltage drop across all battery cells manufacturer published ratings and the values used
and across all DC connections with a digital for the acceptance test should be approximately
voltage meter. Set the voltage range of the meter the same as that of the intended application. The
to the maximum open-circuit voltage range of the discharge rate should be at a constant current
connection. Investigate readings that deviate from or constant power load equal to the selected
other readings by 25% or more. manufacturer rating of the battery. Set up a load and
the necessary instrumentation to maintain the test
Perform a battery impedance test and record the
discharge rate determined in above. Disconnect the
results.
charging source, connect the load to the battery, start
Energize and test batteries in accordance with the timing, and continue to maintain the selected
contract documents and manufacturer instructions. discharge rate. If the charging source cannot be
Inspect all parts for evidence of overheating and disconnected, the current being drawn by the load
evidence of physical damage, including warn has to be increased to compensate for the current
insulation and corrosion, at each step during being supplied by the charging source to the battery.
energization. Close the battery circuit breaker, and Read and record the individual cell voltages and
measure and record the battery charging voltage the battery terminal voltage. The readings should
and current. Allow the batteries to charge for a be taken while the load is applied at the beginning
minimum of 24 hours, or until the batteries are fully and at the completion of the test and at specified
charged, whichever is less. Record the time. Measure intervals. There should be a minimum of three sets
and record the battery float voltage and current and of readings. Individual cell voltage readings should
rectifier/battery charger output voltage and current be taken between respective posts of like polarity of
every 4 hours while charging. adjacent cells so as to include the voltage drop of the
intercell connectors. Maintain the discharge rate and
After charging, check batteries for signs of vibration, record the elapsed time at the point when the battery
and check vented lead-acid batteries for signs of terminal voltage decreases to a value equal to the
excessive gassing. For vented (flooded) batteries, add minimum average voltage per cell as specified by the
electrolyte to batteries as required to fill cells up to design of the installation times the number of cells.
the bottom of the high-level line using manufacturer Upon completion of testing, inspect bus bar bolts,
recommended materials and methods. Equalize repair and re-torque to specifications as necessary.
non-valve regulated batteries in accordance with Replace any failed batteries or bus bars and note on
manufacturer instructions. the record of the test.

Verify that the batteries are fully charged and are on Remove and dispose of empty, partially full, and
float charge. Measure and record the float voltage excess acid drums, including shipping containers and
and charging current. obsolete batteries, in accordance with local laws and

n 48
Standard for Commissioning Building Electrical Systems NECA 90

regulations regarding disposal of hazardous material. Measure the battery system voltage from positive to
Do not dispose of batteries in a fire. ground and negative to ground.

5.5.35 Battery Chargers 5.5.37 Valve-Regulated Lead Acid (VRLA)


Batteries
Verify that the battery charger is compatible with the
type and configuration of the battery plant. Check Verify ventilation of battery room or enclosure.
the settings of the charger and calibrate in accordance Verify existence of suitable eyewash equipment.
with the manufacturer instructions to match the float Verify adequacy of battery support racks or cabinets,
and equalizing levels required by the battery. mounting, anchorage, and clearances. Verify the
application of an oxide inhibitor on battery terminal
Inspect filter and tank capacitors. connections.
Verify operation of cooling fans. Clean filters if Measure negative post temperature. Measure charger
provided. float and equalizing voltage levels. Verify all charger
functions and alarms. Measure each monoblock/
Before connecting the battery charger to the battery,
cell voltage and total battery voltage with charger
measure and record the battery charger output
energized and in float mode of operation. Measure
voltage. Verify proper operation of all charger
intercell connection resistances. Perform internal
functions and alarms. Verify proper polarity of the
ohmic measurement tests.
battery charger and the battery.
5.5.38 Uninterruptible Power Supply (UPS)
Upon energizing the battery charger, verify float
Systems
voltage, equalize voltage, and high voltage shutdown
settings. Verify current limit. Verify correct load Verify that the air inlets are not obstructed. Verify
sharing of parallel battery chargers. Verify the connections against the wiring schematic to ensure
calibration of meters. Verify operation of alarms. proper phasing and voltage connections. Check the
Measure and record input and output voltage and battery charger connections to the battery and the
current. Measure and record AC ripple current and/ battery connections to the inverter to insure that
or voltage imposed on the battery. Perform full load they have the correct polarity. Verify operation of
testing of charger. forced ventilation. Verify that filters are in place and/
or vents are clear.
5.5.36 Flooded Lead Acid Batteries
Simulate critical malfunctions. Verify annunciation
Verify that battery area ventilation system is
and protective device functions.
operable. Verify existence of suitable eyewash
equipment. Verify electrolyte level. Measure Coordinate UPS testing with generator/transfer
electrolyte specific gravity and temperature levels. switch testing, if applicable.
Verify presence of flame arresters. Verify adequacy
of battery support racks, mounting, anchorage, and Measure and record battery voltage. Measure and
clearances. Inspect spill containment installation, if record the inverter output voltage and current.
applicable. Verify application of an oxide inhibitor
on battery terminal connections. Test all electrical and mechanical interlock systems
for correct operation and sequencing.
Measure charger float and equalizing voltage levels.
Adjust to battery manufacturer recommended Test static transfer from inverter to bypass and back.
settings. Verify all charger functions and alarms. Use the actual UPS load, if possible. Set free running
Measure each cell voltage and total battery voltage frequency of oscillator. Test DC undervoltage trip
with charger energized and in float mode of level on inverter input breaker. Set according to
operation. Measure intercell connection resistances. manufacturer instructions. Test alarm circuits. Verify

49 n
NECA 90 Standard for Commissioning Building Electrical Systems

synchronizing indicators for static switch and bypass and comply with the specifications. Verify that
switches. dimming does not cause lower than specified light
levels in spaces to daylight harvesting. Verify that the
Perform infrared scan in accordance with Annex A. controls and sensors are tamper-resistant, not easily
overridden or disabled by occupants. Verify that
See NECA 411 for additional information and
photo sensors are in appropriate locations for the
guidance.
lights being controlled and are not affected by direct
5.5.39 Lighting sunlight or obstructions (shadows). Adjust system
and component settings as needed in accordance with
Perform operational tests on completed lighting contract documents, drawings and specifications, and
system including testing all switches and emergency in accordance with manufacturer instructions.
lights, switching ballasts, and batteries. Test
the operation of lighting controls and integral See NECA/IESNA 500, NECA/IESNA 501, and
components to ensure they respond appropriately to NECA/IESNA 502 for additional information and
changing conditions and parameters, as specified. guidance.

Measure lighting levels in all areas to assure they 5.5.40 System Testing
meet the requirements specified in the contract
Perform system function testing upon completion
documents. Demonstrate lighting levels at desk level
of the acceptance tests on individual equipment and
after dark to ensure that they are not affected by
components. Develop test parameters and perform
daylight, and record readings.
tests for the purpose of evaluating performance of
Walk-test areas equipped with occupancy sensors all integral components and their functioning as an
to ensure that lights turn on and off automatically. integrated system within design requirements and in
Adjust time delay and sensitivity settings as needed. accordance with manufacturer instructions.
Verify proper occupant override operation. Record
Test interconnections of the electrical equipment
blind spots or issues with occupancy sensors not
with other systems, such as mechanical, security, and
performing properly.
fire alarm systems. If a building automation system
For lighting control relay panels, verify that the time (BAS) is installed, verify the overall system function,
clock, if so equipped, has been programmed with including data points derived from or delivered to
correct lighting zones and correct on/off controls. the electrical system.
Simulate time-changes to witness automatic light
Verify electrical equipment and devices under load.
controls. Verify proper occupant override operation.
Coordinate testing as needed to allow for testing
Record any issues observed during testing.
the electrical system while the mechanical system is
For daylight harvesting systems, test dimming running.
controls during daylight hours when controls should
5.5.41 Medium and High-Voltage Surge
automatically dim lighting. Verify that amperage
Protective Devices (SPDs)
changes in light fixtures are proportional to external
light changes. Verify that light levels at the specified Inspect for correct mounting and adequate
work plane remain within specified limits using a clearances. Verify the arresters are clean. Verify
combination of daylight and dimmable lighting. that the ground lead on each device is individually
Measure and record light levels in each room. attached to a ground bus or grounding electrode.
Verify that all, and only, specified light fixtures are Verify that the stroke counter is correctly mounted
dimming. Verify that dimming delays and ramp and electrically connected, if applicable.
times are set and functioning so that changes in light
fixture output are gradual, do not bother occupants,

n 50
Standard for Commissioning Building Electrical Systems NECA 90

Test the ground connection for continuity. Measure Measure ground and/or neutral current, and
the resistance of the ground connection. The determine harmonics. Consult the manufacturer for
resistance between the arrester ground terminal and instructions when harmonic currents are found.
the ground system should be less than 0.5 Ohm.
Perform infrared scan. See Annex A for additional
Perform insulation-resistance testing at voltage levels guidance.
in accordance with the manufacturer instructions.
See Annex A for additional guidance. 5.5.44 Dry-Type Reactors (Shunt and Current-
Limiting)
5.5.42 Low-Voltage Surge Protective Devices
(SPDs) Verify that tap connections are as specified, if
applicable.
Inspect for correct mounting and adequate
clearances. Verify that the ground lead on each Perform winding-to-ground insulation-resistance
device is individually attached to a ground bus or tests. Apply voltage in accordance with manufacturer
ground electrode. Verify that the stroke counter, published data. See Annex A for additional guidance.
if present, is correctly mounted and electrically
Measure winding resistance. See Annex A for
connected.
additional guidance. Consult the manufacturer for
Test the ground connection for continuity. Measure instructions if winding-resistance test results vary
the resistance of the ground connection. The more than 1% from factory tests.
resistance between the arrester ground terminal and
5.5.45 Liquid-Filled Reactors (Shunt and
the ground system should be less than 0.5 Ohm.
Current-Limiting)
Perform insulation-resistance testing in accordance
Verify settings and operation of all temperature
with manufacturer instructions. Perform an
devices, if applicable. Verify that cooling fan and
insulation power factor test. Power factor tests
pump motors have correct overcurrent protection, if
should indicate similar dielectric loss between similar
applicable. Verify operation of all alarm, control, and
arrests. See Annex A for additional guidance.
trip circuits from temperature and level indicators,
5.5.43 Capacitors pressure relief device, and fault pressure relay, if
applicable. Verify correct liquid level in all tanks and
Inspect capacitors for correct mounting and required bushings. Verify that positive pressure is maintained
clearances in accordance with NEC requirements on nitrogen-blanketed reactors. Verify that tap
and in accordance with the manufacturer connections are as specified, if applicable.
instructions. Verify that capacitors are electrically
connected in their specified configuration and in Perform winding-to-ground insulation-resistance
accordance with their nameplate ratings. tests. Apply voltage in accordance with manufacturer
published data. See Annex A for additional guidance.
Measure the capacitance of all terminal combinations Perform insulation power-factor or dissipation-
and compare with the manufacturer published data. factor tests on windings in accordance with the test
Measure the resistance of internal discharge resistors equipment manufacturer published data. Perform
and compare with the manufacturer published data. power-factor or dissipation-factor or hot collar
watts-loss tests on bushings in accordance with
Perform insulation-resistance tests from the the test equipment manufacturer published data.
terminals to case for one minute on capacitors with Measure winding resistance. Measure the percentage
more than one bushing. Test voltage and minimum of oxygen in the nitrogen gas blanket, if applicable.
resistance must be in accordance with manufacturer
instructions. See Annex A for additional guidance. Remove a sample of insulating liquid in accordance
with ASTM D-923. Test the sample for:

51 n
NECA 90 Standard for Commissioning Building Electrical Systems

• Dielectric breakdown voltage: ASTM D-877 5.6 Deferred Functional and Seasonal
and/or ASTM D-1816. Testing
• Acid neutralization number: ASTM D-974. If any check or test cannot be completed due to
the need for seasonal testing, weather conditions,
• Specific gravity: ASTM D-1298. building structure, required occupancy levels, or
other testing factor where system loadings are closer
• Interfacial tension: ASTM D-971 or ASTM
to the system’s design criteria, or other deficiency,
D-2285.
the execution of checklists and functional testing
• Color: ASTM D-1500. may be delayed until after Substantial Completion,
but before the expiration of the warranty period,
• Visual Condition: ASTM D-1524. upon approval of the CxA and Owner. Perform
these tests and checks as soon as conditions permit
• Water in insulating liquids: ASTM D-1533.
adequate testing.
(Required on 25 kV or higher voltages and on
all silicone-filled units.) Perform and document the specified testing and
• Measure power-factor or dissipation-factor in the results. Correct deficiencies identified during
accordance with ASTM D-924. deferred functional and seasonal testing. Update
record documents, O&M manuals, as-build
• Remove a sample of insulating liquid in drawings, and other commissioning documents as
accordance with ASTM D-3613 and perform needed for any modifications made during deferred
dissolved-gas-analysis in accordance with ANSI/ functional or seasonal testing.
IEEE C57.104 or ASTM D-3612.

n 52
6. Recording and Documenting
Performance

Documentation is an essential component of the • Completed as-built drawings signed by the


commissioning process. Record and collect all installing contractor.
formal and informal communications during the
commissioning process. Document all pre-functional • Copies of the operation and maintenance
and functional performance checks and tests. Submit (O&M) manuals.
documentation in format(s) as required in contract
documents. 6.2 Non-conformance Forms
NOTE: In general, the A/E is the final interpretive
6.1 Documentation authority regarding technical non-compliance issues
NOTE: Since the results of the commissioning tests or deficiencies (compared with Design Intent or Basis
become baseline test values to compare with later of Design (BOD) documents) and their resolution (in
tests and the results of the routine maintenance tests accordance with the Design Intent or Basis of Design
are compiled to identify any downward trend in (BOD) documents).
performance, it is vital to the maintenance program to NOTE: In general, the Owner is the ultimate decision
have accurate and complete records. The acceptance authority in resolving deficiencies or issues of non-
testing, integrated system testing, operational tune-up, conformance. The Owner may decide whether
and start-up testing is the process by which baseline modifications are required to correct deficiencies,
test results verify the proper operation and sequence or whether tests will be accepted as submitted.
of operation of electrical equipment, in addition to If corrective work is performed, the Owner may
developing baseline criteria by which future trend determine whether tests will be repeated and a revised
analysis can identify equipment deterioration. report submitted.
Commissioning documentation includes, but is not Non-conformance items or deficiencies may be
limited to, the following: identified at any point during the commissioning
• Approved submittals, test, balance, and process. All deficiencies should be recorded in a
calibration reports for the equipment, sub- comprehensive log that is maintained by the CxA, is
systems, and systems being commissioned. continuously updated, and is periodically reviewed
by the entire commissioning team.
• All approved shop drawings of electrical
equipment. Fold full-size sheets as required to Deficiencies identified during commissioning should
fit in binders. be documented on the standardized forms and/or
checklists used to document that particular phase of
• All pre-functional performance test checklists, commissioning for the specific equipment or system.
signed by indicating personnel, organized by Deficiencies that can be corrected during the normal
system and sub-system. course of performing testing and commissioning
procedures (minor deficiencies) should be corrected,
• All verification and functional performance test with appropriate notations made on the forms and/
checklists/results, signed by indicated personnel, or checklists.
organized by system and sub-system.

53 n
NECA 90 Standard for Commissioning Building Electrical Systems

Deficiencies or non-conformance items that cannot


be corrected during the normal course of performing
testing and commissioning procedures should be
documented on standardized Resolution Tracking
Form or Non-Conformance Form that summarizes
each deficiency and outlines possible options for
resolving the deficiency, along with recommending
a preferred option for resolution, and submitted to
the A/E for review. NOTE: The Resolution Tracking
Form or Non-Compliance Form should contain a
Statement of Correction that is signed after resolution
of the deficiency, and to certify that the equipment or
system is ready for retesting.

n 54
7. Operating and Maintenance
(O&M) Manuals

Operating and Maintenance (O&M) Manuals • Full warranty information, including clearly
typically include, but are not limited to, the identifying all responsibilities of the Owner to
following: keep the warranty in force.

• System descriptions, including narratives • Copies of the installation, start-up, and checkout
of the theory of operation, overall system materials that are supplied with and shipped
layout, description of major components, inside equipment.
interconnections with utilities and other
systems, description of control system layout • Forms and checklists completed in the field by
and operation, identification of unusual features factory or field technicians.
or functions, and major safety precautions. • Preventive maintenance procedures including
• Manufacturer installation, start-up, and recommended frequency for each preventive
operating instructions. maintenance task, such as cleaning, inspection,
lubrication, and scheduled overhauls. Group
• Control sequences describing start-up, all modes tasks and sort by frequency, such as daily,
of operation, and shut down. weekly, quarterly, and annually.

• Troubleshooting procedures. The CxA should review the O&M manuals early
in the commissioning process to become familiar
• References to drawings, schematics, sequences with the equipment, sub-systems, and systems
of operation, and other information included being tested, and to assist the CxA in developing
as part of the construction contract drawings commissioning and test procedures.
and specifications that show distribution system
layout, equipment arrangements and items of Organize O&M Manuals by each major system.
control, as appropriate. Submit O&M Manuals in digital formats when
permitted. For hard copies, submit O&M Manuals in
• Spare parts lists. three-ring binders.
• Manufacturer, vendor, supplier, and sub- All information included in the final O&M Manuals,
contractor 24-hour contact information. including equipment schedules, manufacturer
• Approved and corrected shop drawings, such literature, and drawings, must represent the as-built
as wiring, control, and one-line diagrams, and condition of systems and equipment. Include all data
marked-up catalog data. concerning changes made during construction.

• Owner-contracted tests, if any. Each section must include the information required
in the appropriate section of the specifications plus
• Factory testing reports, if any. any additional information necessary for the Owner’s
personnel to successfully operate and maintain the
• Field test reports, checklists, and forms.
systems and equipment covered in that section.

55 n
8. Training

Conduct comprehensive training for the Owner’s In general, vendors should be responsible for
operating and maintenance (O&M) personnel in providing training on their respective equipment.
the operation, maintenance, and troubleshooting of Vendors should submit a written training plan for
all commissioned systems and equipment. Ensure review and approval by the Owner’s representative
that training meets any requirements listed in the and the CxA prior to training.
contract documents. Provide video/audio recording
of the training as a record document and for use for Use approved O&M manuals as training resources
future training. whenever possible.

Interview the Owner’s O&M personnel to determine


any special training needs, to verify areas in which
training will be most valuable, and to determine
how rigorous training should be for each piece of
commissioned equipment.

n 56
(This annex is not part of the standard)

Annex A: Electrical Testing


Procedures

A.1 General • Minimum amplitude accuracy over the selected


frequency range of plus/minus 20% or plus/
Perform electrical testing in accordance with test
minus 1.5 dB
equipment manufacturer instructions. Use test
equipment of suitable ratings and sensitivity. Follow The vibration data collector device must use either
the manufacturer instructions for testing equipment a stud-mounted or a low mass rare earth magnet-
and conductors. Observe all manufacturer mounted accelerometer. Do not use hand-held
warning labels. See Section 3 for additional safety accelerometers. The mass of the accelerometer and
requirements and precautions. its mounting must have minimal influence on the
frequency response of the system over the selected
Limit test voltages to prevent damage to equipment measurement range.
and conductors, to prevent damage to splices,
terminations, attached equipment, and accessories Sound discs must be a minimum of 1 inch in
that are not rated to withstand test voltages, and to diameter, manufactured of a magnetic stainless steel,
prevent voiding equipment warranties. Disconnect such as alloy 410 or 416, have a surface finish of 32
surge protective devices, potential transformers, and micro-inches rms, and be attached by tack weld, be
sensitive electronic components from equipment stud mounted, or be epoxy glued.
under test to prevent damage.

Maintain a permanent record of all test results. A.3 Contact Resistance


Record wet- and dry-bulb temperatures or relative Inspect bolted electrical connections for high
humidity and temperature. resistance using a low-resistance ohmmeter.
Compare bolted connection resistances to values
A.2 Vibration Monitoring of similar connections. Microhm or millivolt drop
values should not exceed the high levels of the
Use a vibration data collector with the following normal range as indicated in the manufacturer
minimum requirements: published data. If manufacturer data is not available,
• Minimum of 400 lines of resolution investigate any values which deviate from similar
connections by more than 50% of the lowest value.
• Dynamic range greater than 70dB

• Frequency response of 5Hz-10kHz (300 to A.4 Infrared Scan


600,000 cycles per minute (cpm) Perform infrared testing in accordance with test
equipment manufacturer instructions. Use an
• Capability to perform ensemble averaging infrared testing device designed to measure actual
• Use of a Hanning window operating temperatures, or designed to detect
significant deviations from surrounding conditions.
• Auto-ranging frequency Provide documentation of device calibration.

Provide supplemental barriers and safety precautions

57 n
NECA 90 Standard for Commissioning
Recommended Practice for Commissioning
Building Electrical
Building
Systems
Electrical Systems

during infrared testing to prevent accidental or replacement recommendations if infrared test


contact with exposed energized components. Use results indicate overheating of components.
appropriate personal protective equipment (PPE).

De-energize equipment and conductors in


A.5 Insulation Power Factor
accordance with established safety procedures. Use a power factor test set with the following
Remove accessible covers, plates, weathershields, and minimum requirements:
doors of equipment, manholes, junction boxes, splice
boxes, and switchgear to reveal cables, terminations, • Test voltage range of 500V to 12 kV.
and splices.
• Ability to perform UST, GST, and GST-with
Energize equipment and conductors, and turn on guard tests.
all normal loads. All equipment and conductor • Readings for power factor, dissipation factor,
temperatures to normalize. capacitance, and watts-loss.
Perform infrared testing of all accessible current- • Power factor/dissipation factor range of 0 to
carrying electrical components while conductors 200%.
and equipment are energized and operating under
maximum load conditions, but not less than 40% • Capacitance measuring range of 0 to 0.20 pico-
of rated load of the electrical equipment being farads.
inspected. NOTE: Infrared scan results could be
inconclusive if equipment and conductors are lightly Perform an insulation power factor test on each
loaded. winding of transformers in accordance with the
transformer manufacturer published data or the
Inspect distribution systems, equipment, and test equipment manufacturer published data.
conductors with imaging equipment capable of Correct results to 20°C in accordance with test
detecting a minimum temperature difference of 1°C equipment manufacturer instructions. Compare to
at 30°C. Equipment should detect emitted radiation manufacturer factory test results. If manufacturer
and convert detected radiation to a visual signal. data is not available, acceptance tests results will
serve as baseline data for future reference. Investigate
Prepare a report identifying the equipment and power factor test values more than 3-percent for dry-
conductors tested, and describing the results of type transformers.
the infrared test. Include notations of deficiencies
detected, causes of temperature differences, remedial Perform a power factor test on transformer bushings
action taken, results from retesting after remedial that are equipped with power factor taps, and
action, and inaccessible or unobservable areas and perform hot collar watts-loss test on filled bushings
equipment. Maintain a permanent record of all that are not equipped with power factor taps. Correct
infrared test results to track electrical characteristics results to 20°C in accordance with test equipment
of cables, terminations, and splices over time. manufacturer instructions. Maximum power factor
of liquid-filled transformers corrected to 20°C must
Temperature differences of 1°C to 3°C indicate be in accordance with transformer manufacturer
possible deficiency and warrant investigation. published data. Compare with test equipment
Temperature differences of 4°C to 15°C indicate manufacturer published data. Investigate bushing
deficiency; repair as time permits. Temperature power factors and capacitances that vary from
differences of 16°C and above indicate major nameplate values by more than 10%. Investigate any
deficiency and must be repaired immediately. bushing hot collar watts-loss results that exceed the
test equipment manufacturer published data.
Consult equipment, conductor, termination, splice,
accessories, and component manufacturers for repair

n 58
Standard for Commissioning Building Electrical Systems NECA 90

A.6 Battery Impedance • A short-circuit terminal current of a minimum


of 2.5 milliamps
Use a battery impedance test set with the following
minimum requirements: Conduct tests of electrical equipment, sub-
systems, and systems using normal procedures and
• Ability to test battery cells of up to 2500 amp- requirements to ensure safety. Disconnect sensitive
hour capacities electronic equipment, such as surge protective
• Maximum battery test voltage of 25 Volts DC devices (SPDs), before insulation resistance testing.
Disconnect one side of transformers and coils before
• Impedance range of 0.0 to 100 milliohms testing.
• Ability to test both lead-acid and nickel- Insulation resistance measurements specified are
cadmium batteries the minimum acceptable values at an ambient
temperature of 16°C (60°F) with a relative humidity
• Test voltage stability of plus/minus 0.1%
of less than 60%. Do not perform insulation
• Resistance accuracy of plus/minus 5% at 1 resistance tests during times of high relative
megohm humidity. When insulation resistance measurements
are taken at other than 16°C (60°F), convert
quantities to equivalent values at 16°C (60°F).
A.7 Breaker Timing
Use a breaker timing test set with the following Do not perform tests on outdoor equipment during
minimum requirements: inclement weather. Do not perform tests on direct
burial ground conductors or on ground rods within a
• Perform contact timing during breaker close, 48-hour period following rainfall.
open, open-close, close-open, and open-close-
open. During cable tests, station an individual at each point
where cable has exposed connections.
• Have a minimum of three dry contact inputs
Perform insulation-resistance testing from phase-
• Have a minimum of two wet-input channels to to-ground and from phase-to-phase for equipment
monitor breaker secondary contacts and conductors in accordance with the equipment
and the test instrument manufacturer instructions.
• Have a minimum resolution of plus-0.0001
Measure insulation resistance of low-voltage circuit
seconds over a one-second duration
breakers, switches, and equipment phase-to-phase
• Have travel transducers capable of linear and and phase-to-ground and across open poles. Isolate
rotary motion conductors and cables by opening switches or
breakers at each end of cable before testing, when
• Be capable of slow close contact point possible. NOTE: Where conductors and cables are
measurement direct connected to equipment with no disconnecting
means, test as connected; do not disconnect conductors
A.8 Insulation Resistance Testing or cables. Ground equipment, conductors, and cable
shields not being tested.
Use an insulation resistance test set with the
following minimum requirements: Do not exceed the voltage rating of the equipment and
conductors under test. In general, perform insulation
• Test voltage increments of 500V, 1000V, 2500V,
resistance testing using a test voltage of 1000V DC
and 5000V DC
for 600 V rated insulation, and 500V DC for 300
• Resistance range of 0.0 to 500,000 megohms at V rated insulation. For transformers rated 600V
500,000V DC and below, use a minimum voltage of 1000V DC.

59 n
NECA 90 Standard for Commissioning Building Electrical Systems

For transformers rated 601-5000V, use a minimum to-ground for ten minutes. Apply test voltage for 10
voltage of 2500V DC. For transformers rated above minutes or more to develop the dielectric-absorption
5000V, use a minimum voltage of 5000V DC. characteristic.

Measure insulation resistance at one minute Plot insulation resistance against time to determine
following the application of the test voltage. the presence of moist or dirty windings. A steady
Record the megohm values of each phase-to- rising curve is indicative of a clean, dry winding.
ground and between each phase-to-phase, along A quickly flattening curve is the result of leakage
with the description of the instrument, voltage current through or over the surface of the winding
level, humidity, temperature, time, and date of the and is indicative of moist or dirty winding.
test. Ground equipment and conductors at the
completion of the test. If facilities are not available for a 10-minute test,
perform calculate the polarization index by taking
Compare test results with previous test results and insulation resistance readings at 30 and 60 seconds.
with manufacturer data corrected for temperature The ratio of the 60-to-30-second or the 10-to-l-
variations using manufacturer recommended minute ratio will serve as an indication of the
correction factors. Consult the equipment winding condition.
manufacturer published data for acceptable test
results. If published data is not available, investigate The dielectric absorption ratio or polarization index
any values which deviate from previous test results should be greater than 1.0 and should be recorded
under similar conditions by more than 50% of the and maintained for future reference. For DC motors
lowest value. and generators, investigate dielectric absorption
ratios less than 1.4 and polarization index ratios less
Insulation resistance should not be less than 2 than 2.0 for Class B insulation and Class F insulation.
megohms for circuits under 115V, 6 megohms Compare to manufacturer factory test results. If
between conductor and ground on those 115-600V manufacturer data is not available, acceptance tests
circuits (115V-600V) with total single conductor results will serve as baseline data for future reference.
length of 2500 feet and over, and not less than
8 megohms for 115-600V circuits with single A.9 High-Potential Acceptance Testing (DC
conductor length of less than 2500 feet. For low- High Potential and Very Low Frequency (VLF)
voltage, air-insulated and insulated case circuit AC High Potential Testing)
breakers, insulation resistance should not be less
NOTE: DC high potential (overpotential) testing
than fifty (50) megohms.
can cause insulation failure and should be used with
When insulation resistance measurements fall caution. Complete all insulation resistance testing
below the specified minimum values at 16°C (60°F), prior to high potential testing. Review insulation
apply heat and dry equipment and conductors in resistance test results to determine suitability for high
accordance with manufacturer instructions, subject potential testing. Do not perform DC high potential
to the approval of the CxA. If drying is to be done by tests until insulation-resistance levels are raised above
applying an electric potential to equipment, do not minimum levels.
exceed the continuous voltage or current ratings of
Provide supplemental barriers and safety precautions
the equipment being dried, directly or by induction.
during high potential testing to prevent accidental
A.8.1 Dielectric Absorption and Polarization contact with exposed energized components. Clean
Index and dry equipment found in a wet or dirty condition
before performing high-potential testing.
Perform a dielectric absorption test for rotating
machinery, motors and alternators, and dry-type
transformers from winding-to-winding and winding-

n 60
Standard for Commissioning Building Electrical Systems NECA 90

Humidity, wind, and surface conditions strongly A.9.1 DC High Potential Testing
affect the results of DC high-potential testing. Do
not perform high potential tests during times of Apply the test voltage slowly in a minimum of five
high relative humidity. Follow the manufacturer equal increments until maximum test voltage is
instructions for performing high potential testing reached, with no increment exceeding the conductor
of equipment and conductors. Follow the test or equipment voltage rating, and with each voltage
equipment manufacturer instructions. Use the step being held for an equal interval of time long
lowest possible test voltages as recommended by the enough to allow the leakage current to reach stability,
equipment or conductor manufacturer and the test approximately 1 to 2 minutes. See Table A.9.1 for
equipment manufacturer. the maximum recommended DC high potential test
voltages. Record readings of leakage current at 30
Check the high-potential test set for proper seconds and one minute, and at one minute intervals
operation. Ensure that the input voltage to the thereafter until the 15 minute test duration is met.
test set is regulated. Ensure that DC high potential
test equipment only measures the leakage current Record leakage current in microamperes at the end
associated with the cable under test and does not of each interval before the voltage is raised to the
include the internal leakage of the test equipment. next level. Plot test voltage versus leakage current
Follow the test set manufacturer instructions for on graph paper as test progresses. NOTE: A linear
connecting leads and performing tests. increase in leakage current is expected, and it should
stabilize or decrease from the initial value at each
Apply the test voltage for a minimum of 15 minutes. step. Calculate the resistance at each step. As long as
Graph microampere leakage versus time. Plot the leakage current decreases or remains steady after
values plotted every 30 to 60 seconds. Discontinue it has leveled off, the test is considered satisfactory.
tests if erratic results are observed. Make notations
including the data and time of testing, and the Any excessive or nonlinear increase in leakage
ambient temperature and relative humidity at the current can indicate imminent insulation failure.
time of testing. If the leakage current starts to increase (excluding
momentary increases due to test equipment
Consult the manufacturer for equipment and power supply disturbances), extend the test to
conductors that fail high potential testing. Repair determine whether the rising trend continues.
or replace equipment and conductors that fail high Increasing leakage current will result in the
potential withstand testing. Repeat high potential complete breakdown of already-damaged insulation,
testing in its entirety for equipment and conductors evidenced by an abrupt increase in leakage current
that are repaired or replaced. accompanied by a sharp decrease in test voltage.
In this case, discontinue the test and consult the

Table A.9.1 Recommended Maximum Voltages for DC High Potential Testing


Test Voltage (kV)
Rated Circuit Voltage (KV)
100 % Insulation 133 % Insulation
5 25 35
8 35 45
15 55 65
25 80 96
28 85 100
35 100 125

61 n
NECA 90 Standard for Commissioning Building Electrical Systems

manufacturer for recommendations. NOTE: This is VLF test voltage levels. If the VLF testing frequency is
characteristic of approximately 80% of all DC high- adjusted from a nominal 0.1 Hz, such as to compensate
potential test failures on cables with elastomeric for very long cables, adjust the test time accordingly.
insulation.
Several VLF test waveforms are possible. In the
At any step where the calculated leakage resistance absence of other recommendations, perform VLF
decreases approximately 50% or more of that of testing using a smooth, load independent Sinusoidal
the next lower voltage level, discontinue the test waveform (similar to that found in nominal 60 Hz
to prevent insulation failure and to retain the AC power systems) with an optimized frequency
equipment in a serviceable condition until its held as close as possible to 0.1 Hz.
replacement can be scheduled.
Multiple parallel conductors within each phase may
Sudden failure or flashover can occur if the be connected together for testing purposes to reduce
insulation is already completely or nearly punctured. overall test times. If test results are questionable with
Voltage increases until it reaches the sparkover parallel conductors, test each conductor separately.
potential of the air gap length, then flashover occurs.
NOTE: Polyethylene cables exhibit this characteristic Cable that has been VLF withstand tested is
for all failure modes. considered to have good insulation when no failure
is detected during the withstand test and the percent
After recording all measurements, rapidly turn standard deviation of Tan-Delta measurements at
the test equipment to zero volts and monitor cable all test voltages is less than 0.02 (See Section A.10).
voltage. Record the decaying voltage every 15 Cable with a percent standard deviation of Tan-Delta
seconds for 90 seconds, and then every 60 seconds measurements is greater than 0.02 should be tested
until the charge is down to 10% or less of the test further to determine the cause.
voltage, then solidly ground the cable. Remove the
test lead for connection to the next conductor. After A.10 Tan-Delta (Dissipation Factor) Testing
testing, ground cables for a minimum of four times Using Very Low Frequency (VLF) Test Set
as long as the test voltage was applied during the
high potential tests to assure complete discharge, but NOTE: Tan-Delta testing is used to evaluate overall
not less than 30 minutes. cable condition and can be used to detect water trees in
medium-voltage cable. Test results may not be accurate
A.9.2 Very Low Frequency (VLF) AC High for cables exceeding 1,600 m (5,000 feet) in length.
Potential Testing
Perform Tan-Delta testing only on shielded cables.
Apply the test voltage for a minimum of 30 minutes. NOTE: Unshielded cables do not have a consistent
See Table A.9.2 for the maximum recommended reference to ground.

Table A.9.2 Recommended Maximum Voltages for VLF AC High Potential Testing
Installation Test Acceptance Test
Rated Circuit Voltage (kV) Maximum RMS Voltage Maximum RMS Voltage
(Phase-to-Ground) (Phase-to-Ground)
5 9 10
8 11 13
15 18 20
25 27 31
35 39 44

n 62
Standard for Commissioning Building Electrical Systems NECA 90

Ensure that conductors are disconnected from A.11 Partial Discharge Testing
equipment. Test only one conductor at a time.
Partial Discharge testing is used to detect physical
Disconnect parallel conductors.
damage of cables, terminations, and splices,
Select the test voltage in accordance with contamination on terminations or improper
manufacturer instructions. NOTE: The test voltage, spacing of unshielded parts of terminations that
Vo, is typically calculated from the nominal system causes tracking, improperly connected, damaged,
voltage, from phase-to-ground for wye-connected or corroded metallic shields, electrical trees
three-phase four-wire systems, and from phase-to- resulting from water trees, and thermal damage
phase for delta-connected three-phase, three-wire due to overloads. Partial Discharge testing may be
systems. The test voltage may be lowered, such as performed using very low frequency (VLF) AC test
when testing cables that are known to be degraded or methods.
when spare conductors are not available.
Any PD in the cable insulation at voltage levels near
Tan-Delta testing is conducted from each conductor or slightly above the nominal operating voltage of the
to ground in three steps of three minutes each, with cable indicates that cable failure is imminent under
readings taken at the end of each three-minute step, normal operating conditions.
with an applied test voltage of 0.5 times Vo for Step 1,
When partial discharges are identified, measure
1.0 times Vo for Step 2, and 1.5 times Vo for Step 3.
and record the Partial Discharge Inception Voltage
NOTE: Undamaged cable behaves like a capacitor (PDIV), or the voltage at which point the PD is
with a 90‚ phase shift between the voltage waveform initiated, and the PD Extinction Voltage (PDEV),
and the current waveform. Cable that is damaged or or the lower voltage at which point the PD is
degraded will have increased leakage current resulting extinguished, which will help in evaluating the
in a measured phase displacement of less than 90°. overall condition of the cable, which is a subjective
process open to interpretation.
Tan-Delta test results are typically that values
increase with voltage level (higher Tan-Delta results One drawback to partial discharge testing is that one
at higher test voltages). Negative differences in Tan- location of significant partial discharge can mask
Delta test results may indicate a faulty test procedure areas of lesser PD.
or may indicate significant defects with the cable,
Maintain a record of Partial Discharge test results to
and further testing is recommended. Poor Tan-
track cable electrical characteristics over time.
Delta test values typically indicate significant cable
degradation of the overall cable.

Maintain a record of Tan-Delta measurements to


track cable electrical characteristics over time.

63 n
(This annex is not part of the standard)

Annex B: Reference Standards

This publication, when used in conjunction with the National Electrical Code and manufacturers’ literature,
provides recommended guidelines for commissioning building electrical systems. The following publications
may also provide useful information:

National Fire Protection Association


1 Batterymarch Park
Quincy, MA 02169-7471
(617) 770-3000 tel
(617) 770-3500 fax
www.nfpa.org

NFPA 70-2014, National Electrical Code (ANSI)

Institute of Electrical and Electronics Engineers


445 Hoes Lane
P.O. Box 1331
Piscataway, NJ 08855-1331
(732) 981-0060 tel
(732) 981-9667 fax
www.ieee.org

IEEE 43-2001, Recommended Practice for Testing Insulation Resistance of Rotating Machinery

InterNational Electrical Testing Association


106 Stone St.
P.O. Box 687
Morrison, CO 80465
(303) 697-8441 tel
(303) 697-8431 fax
www.netaworld.org

NETA ETT-2010, Standard for the Certification of Electrical Testing Technicians

NETA ATS-2013, Standard for Acceptance Testing Specification for Electric Power and Systems (ANSI)

National Electrical Contractors Association


3 Bethesda Metro Center, Suite 1100
Bethesda, MD 20814
301-215-4521 tel
301-215-4500 fax
www.neca-neis.org

n 64
Standard for Commissioning Building Electrical Systems NECA 90

Current National Electrical Installation Standards™ published by NECA:

NECA 1-2015, Standard for Good Workmanship in Electrical Construction (ANSI)


NECA 90-2015, Standard for Commissioning Building Electrical Systems (ANSI)
NECA 100-2013, Symbols for Electrical Construction Drawings (ANSI)
NECA 101-2013, Standard for Installing Steel Conduits (Rigid, IMC, EMT) (ANSI)
NECA 102-2004, Standard for Installing Aluminum Rigid Metal Conduit (ANSI)
NECA/AA 104-2012, Standard for Installing Aluminum Building Wire and Cable (ANSI)
NECA/NEMA 105-2007, Standard for Installing Metal Cable Tray Systems (ANSI)
NECA 111-2003, Standard for Installing Nonmetallic Raceways (RNC, ENT, LFNC) (ANSI)
NECA/NACMA 120-2012, Standard for Installing Armored Cable (AC) and Metal-Clad Cable (MC) (ANSI)
NECA 121-2007, Standard for Installing Nonmetallic-Sheathed Cable (Type NM-B) and Underground Feeder
and Branch-Circuit Cable (Type UF) (ANSI)
NECA 130-2010, Standard for Installing and Maintaining Wiring Devices (ANSI)
NECA 169-2010, Standard for Installing and Maintaining Arc-Fault Circuit Interrupters (AFCIs) and Ground-
Fault Circuit Interrupters (GFCIs) (ANSI)
NECA 200-2010, Standard for Installing and Maintaining Temporary Electric Power at Construction Sites
(ANSI)
NECA 202-2013, Standard for Installing and Maintaining Industrial Heat Tracing Systems (ANSI)
NECA 230-2010, Standard for Selecting, Installing, and Maintaining Electric Motors and Motor Controllers
(ANSI)
NECA/FOA 301-2009, Standard for Installing and Testing Fiber Optic Cables (ANSI)
NECA 303-2005, Standard for Installing Closed-Circuit Television (CCTV) Systems (ANSI)
NECA 305-2010, Standard for Fire Alarm System Job Practices (ANSI)
NECA 331-2009, Standard for Building and Service Entrance Grounding and Bonding
NECA 400-2007, Standard for Installing and Maintaining Switchboards (ANSI)
NECA 402-2014, Standard for Installing and Maintaining Motor Control Centers (ANSI)
NECA/EGSA 404-2014, Standard for Installing Generator Sets (ANSI)
NECA 406-2014, Standard for Installing Residential Generator Sets (ANSI)
NECA 407-2015, Standard for Installing and Maintaining Panelboards (ANSI)
NECA 408-2015, Standard for Installing and Maintaining Busways (ANSI)
NECA 409-2015, Standard for Installing and Maintaining Dry-Type Transformers (ANSI)
NECA 410-2013, Standard for Installing and Maintaining Liquid-Filled Transformers (ANSI)

65 n
NECA 90 Standard for Commissioning
Recommended Building Electrical
Practice for Commissioning Systems
Building Electrical Systems

NECA 411-2014, Standard for Installing and Maintaining Uninterruptible Power Supplies (UPS) (ANSI)
NECA 412-2012, Standard for Installing and Maintaining Photovoltaic (PV) Power Systems (ANSI)
NECA 413-2012, Standard for Installing and Maintaining Electric Vehicle Supply Equipment (ANSI)
NECA 420-2014, Standard for Fuse Applications (ANSI)
NECA 430-2006, Standard for Installing Medium-Voltage Metal-Clad Switchgear (ANSI)
NECA/IESNA 500-2006, Standard for Installing Indoor Commercial Lighting Systems (ANSI)
NECA/IESNA 501-2006, Standard for Installing Exterior Lighting Systems (ANSI)
NECA/IESNA 502-2006, Standard for Installing Industrial Lighting Systems (ANSI)
NECA 503-2005, Standard for Installing Fiber Optic Lighting Systems
NECA/BICSI 568-2006, Standard for Installing Commercial Building Telecommunications Cabling (ANSI)
NECA/NCSCB 600-2014, Standard for Installing and Maintaining Medium-Voltage Cable (ANSI)
NECA/NEMA 605-2005, Recommended Practice for Installing Underground Nonmetallic Utility Duct (ANSI)
NECA/BICSI 607-2011, Standard for Telecommunications Bonding and Grounding Planning and Installation
Methods for Commercial Buildings (ANSI)
NECA 700-2010, Standard for Installing Overcurrent Protection to Achieve Selective Coordination (ANSI)
NECA 701-2013, Standard for Energy Management, Demand Response and Energy Solutions (ANSI)

n 66
National Electrical Contractors Association
3 Bethesda Metro Center, Suite 1100
Bethesda, Maryland 20785
301-657-3110 • 301-214-4500 fax
www.necanet.org
Index # NECA 90-15 | 5C-12/15

You might also like