Professional Documents
Culture Documents
CONTRACT, ESTIMATING,
& COSTING FOR BUILDING
SERVICES
CHAPTER 6
BUILT UP RATE METHODS
CHAPTER SUMMARY
The requirement and use of the price rates, schedule of
rates, basic criteria for price rate calculations,
materials, labour, plants, overheads and profits, price
rates calculations, concrete work using concrete
mixing machine and hand mixing, excavation work
rates calculation using hand and excavators.
INFORMATION REQUIRED :
• Required as much information as possible to produce more accurate
prices.
• Visit site – to determine site layout, where to build site facilities, to
dispose soil heaps, etc.
• Analyze tender documents – specifications, preambles, contract
conditions, fixed contract period, etc.
BUILT-UP RATE
• Involves the calculation of elements that contribute to the
direct cost of the work.
• Labour cost + material cost + plant cost + site overhead =
total cost of work.
i.e the cost to the contractor is prepared to out the work.
• Total cost + general overhead + profit = tender price
• i.e the price the contractor is prepared to carry out the work
– the figure to be submitted in his tender.
BUILT-UP RATE
BASIC CRITERIA OF PRICE RATE CALCULATION
• Selected items
B. Labour Cost
The cost of workmanship in executing the work.
Mainly the wages – including overtime pay, bonuses, etc.
For foreign worker –include levy charges, permits, etc.
All works require workers
Wages also differ – sex, market conditions, location of sites,
working condition, contract conditions, etc.
BUILT-UP RATE
COMPONENTS OF DIRECT COSTS
B. Labour Cost
Categories of workers:
Skilled workers – RM 60 – RM100/day
Semi-skilled workers – Rm 40 – Rm 60/day
Unskilled workers –RM 20 – RM40/day
Labour constant
is used in the calculation of labour cost for the work
the time spent by a workman to complete a specified work.
e.g for ½ brick wall – 1 bricklayer -1 hour/m2
- 1 unskilled worker – ½ hour/m2
A factor which cannot be fixed
Merely an average time taken after long research
BUILT-UP RATE
COMPONENTS OF DIRECT COSTS
C. Plant Cost
Consider only mechanical plant
Non-mechanical plant e.g tools scaffolding, buckets,
ladder, ropes, hammer, etc – to be included under
general overhead.
Own plant
Consider :
- Owning cost – Purchase price, depreciation
allowances, cost of capital/interest, plant
department overhead, insurance premiums, repair
and maintenance.
- Operating cost – Fuel, lubrication, operator.
BUILT-UP RATE
BUILT-UP RATE
BUILT-UP RATE
GENERAL OVERHEAD’S EXAMPLE:
Previous year’s turnover (total project costs) = RM10, 000,000.00
Deduct Profit = 500,000.00
9,500,000.00
Deduct Overhead = 700,000.00
8,800,000.00
Profit is very important element to the contractor. If the profit margin set
too high, the price rate will be less competitive. If the profit margin is too
low, the survival of the company will at risk.
Profit can be determined by the percentage of direct cost or a lump sum
figure.
Factors to be considered by contractor in determine the profit margin
are:
1. Current workload
2. Market situation
3. Risk
4. Availability of resources.
Strength
• strength of concrete – depends on the proportion of materials
in a particular mix.
Nominal Cube strength after Maximum size Minimum content
Mix of mixing (N/mm²) of aggregate of cement/m³
materials 7th day 28th day (mm) concrete (Kg)
1:1:2 20 30 19 380
1:1½:3 17 25.5 19 361
1:2:4 14 21 19 321
CONCRETOR
IN-SITU CONCRETE
Strength
• concrete may be specified according to:
• designed mixes – examples, Grade 20, Grade 30, etc. – user
specify the performance and producer will select the mix
proportions that will conform with the performance
requirements.
• prescribed mixes – examples, 1:1:2, 1:2:4, etc. – user specify
the mix proportion for the required performance and producer
will produce the concrete accordingly.
CONCRETOR
IN-SITU CONCRETE
Shrinkage, wastage & consolidation in concrete mix
• Reduction in bulk during mixing – finer particles of sand and cement
filling the voids between course aggregate.
• Wastage occurs during transporting, mixing and placing of concrete.
• Vibrating and compacting during placing - also cause reduction in bulk.
• To get the required volume in a mix – increase the quantities of
materials.
• Studies shows maximum shrinkages, etc = ⅓ of original quantity i.e.
33.33%
Allowance for shrinkages, etc. for 1m³ concrete = 0.333 m³ x 100 = 50%
0.667 m³
:. add 50% to material cost to compensate for the reduction in bulk.
CONCRETOR
IN-SITU CONCRETE
Mixing of concrete
Methods of mixing concrete on site:
a) By hand – normally for small quantities.
– labour constant – 2.00 hours/m³.
b) Using concrete mixer.
Concrete mixer
Size, example 5/3:
• Maximum quantity of materials loaded into mixer (before
mixing) = 5 f.c.
• Quantity of concrete discharged (after mixing) = 3 f.c.
CONCRETOR
IN-SITU CONCRETE
Concrete mixer
No. of workers Output/hour Diesel/hour Lubricant/hour
Size required (m³) (litre) (litre)
RM195.81
15% profit and overhead
CONCRETOR
Example 2
Reinforced in situ concrete Grade 25 in isolated column. – m³
Data:
• Same situation as in Example 1 but own concrete mixer is
used for mixing concrete.
• Concrete mixer type 7/5.
• Economic life of concrete mixer = 4 years
• Initial cost of concrete mixer = RM15,000.00
• Resale value of concrete mixer = RM2,000.00
CONCRETOR
Example 2
Material cost
1 m³ cement = 28 bags x RM10.50 = RM 294.00
1.5 m³ sand = 1.5 m³ x RM28.00 = 42.00
3 m³ aggregate = 3 m³ x RM35.00 = 105.00
= 441.00
Add 50% for shrinkages, compaction and = 220.50
wastages = RM661.00
Material cost for 5.50 m³ = RM120.27
20 = 23,250.00
Less = 2,000.00
Resale value = 21,250.00
1,600 hours
Example 2 RM120.27
Running cost/day
Operator = RM 50.00
= 120.00
3 unskilled workers @ RM40.00 = 21.76
Diesel = 1.60 litres x 8 hours x RM1.70 = 9.60
Lubricant = 0.06 litre x 8 ours RM201.36
x RM20.00
Total = RM25.17
Running cost/hour = RM201.36
8 hours
EXCAVATION WORKS
EXCAVATOR
EXCAVATOR
• Works associated with excavation works:
• Excavation.
• Disposal of excavated materials.
• Filling.
EXCAVATION
• Factors affecting cost of excavation:
• Type of soil.
• Method of excavation.
• Type of excavation.
EXCAVATOR
Earthwork Supports
• This is to protect sides of
excavations. Starting Level
Labour cost
Excavation
1 unskilled worker = 4.00 hours x RM40.00 = RM20.00
8 = 3.00
Planking and strutting, say 23.00
= 3.45
15% for profit and overhead
Price/m³
EXCAVATOR
Machine Excavation
Cost of plant
• is much dependent on the plant procurement methods.
Hired plant
a) Rental cost
b) Operating cost
• cost of running the plant on site.
• Factors to be considered:
i. Cost of fuel.
ii. Cost of plant operator and other workers handling the plant.
iii. Capacity and output of plant
iv. Number of hours the plant is utilized in a year.
EXCAVATOR
Machine Excavation
• Fuel required for excavators
¼ 4 9
⅜ 5 12
½ 6 14
¾ 7 16
1 9 18
EXCAVATOR
Machine Excavation
Owned plant
a) Capital cost
Factors to be considered:
i. Initial cost (purchase price).
ii. Interest on capital.
iii. Economic life of the plant.
iv. Maintenance cost throughout the economic life of plant.
v. Cost of transporting plant to site.
b) Operating cost
• same as that for hired plant.
Capacity of plant
• important for the estimator to determine the type or size of
plant to be employed for the work.
EXCAVATOR
Machine Excavation
Output of excavator
• amount of work that can be completed by using the plant within
a certain amount of time.
Output of excavator for excavating Output of excavator for excavating
and loading ordinary earth. and loading other types of soils.
Type/capacity (m³) Average output/hour (m³) Types of soils Multipliers
¼ 8 (hours/m³)
⅜ 9 Sand x 1.00
½ 12 Heavy clay x 1.25
¾ 18 Soft rock x 1.50
1 25 Rock x 4.50
10
Maintenance cost for 5 years = 15,000.00
= 1 x RM150,000.00
10 = 7,500.00
Transportation cost for 5 years = 247,500.00
= 1 x RM150,000.00 8,000.00
20
= RM239,500.00
Less resale value
= RM47,900.00
Cost for 5 years
Machine Excavation
Example 5
• Excavate to reduce level not exceeding 1.00 m maximum depth. – m³
Assumption: Average no. of working
days for excavator per year = 200 days.
Total no. of hours per year = 200 x 8
= 1,600 hours = RM47,900.00 = RM29.94
Capital cost/hour 1,600
Operating cost
Operator = RM 50.00
Diesel = 6 litres x 8 hours x RM1.70 = 81.60
Lubricant = 14 litres x RM20.00 = 40.00
7 days = RM171.60
= RM171.60 = 21.45
Operating cost/day = 8 hours = RM51.39
Operating cost/hour
Total cost/hour = RM51.39 RM4.28
Output/hour = 12 m³ 12 m³ 0.64
:. Cost of excavating & unloading/m³ = RM4.92
Allow 15% profit and overhead
THANK YOU