Professional Documents
Culture Documents
Sinter Plant
During H1 of the year 2013-14, Sinter Plant was not able to meet its production target for which
Bara Steel Plant had to purchase Sinter from outside the premises. Because of this, profitability of
Bara Steel Plant got hampered and the only reason for this reduced profitability was Sinter Plant.
Sinter Plant became the only bottleneck in the steel making process of Bara Steel Plant
because all other shops/departments involved in direct production of steel met their
respective targets successfully. The utilization of Sinter machines was only 76.8% of available
hours. If we dive deep into the matter, then we can say that had Sinter not been purchased from
outside, Bara Steel Plant would have been able to achieve only 3/4th of its production target
for steel. The impact of the problem was so severe that we might not have been able to claim
ourselves as the largest producer of steel in India, which is the pride of our parent firm, had it
not been dealt immediately.
It was recommended that Sinter Plant needed to reduce delay so as to achieve the production
target successfully. Apart from this, there were also other three solutions which could have been
implemented, but reducing delay was less capital intensive as well as less time consuming for
which it became the best option as per our research and study. In other words, this was the
optimized solution which consumed fewer resources as compared other solutions and gave
maximum benefits to Sinter Plant, which in turn helped Bara Steel Plant to meet its production
target without procuring Sinter from outside. It increased utilization of Sinter machines from
76.8% to 97.6% i.e., a 27% increase in utilization of machines, and further stretching this to
100% wouldn’t be cost effective for which this was the highest utilization factor which we
could achieve.
1
Plant. And this was the reason which There is hardly any improvement
prompted for the investigation in Sinter possible further in the weak link which
Plant. To investigate into the matter, a had been found and mitigated as per
problem statement had been defined this report because it already improved
which was as follows. the utilization parameter from 76.8%
to 97.6%. Further stretching this to
After coming to a definite problem
100% may not have much impact on
statement, first point was to collect past
production. In other ways, it would
data to start analysis. After the collection
not be cost effective to stretch further
of data, second thing was to find weak
to achieve 100%. i.e., the limitation of
links with the help of analysis tools
this report was utilization parameter
from the past data. Third thing was to
couldn’t be stretched more than 97.6%.
do brainstorming with both blue collar
The reason for this limitation was the
workforce (non-executives) as well as
fact that it would increase significant
executives separately so as to decide
amount of cost which in turn might
which weak links could be attacked to
reduce the profitability.
get maximum output with minimum
cost. And at last, the final thing was to Before starting the investigation,
build pragmatic solutions to mitigate historical evidence had been tried to
the weak links optimally. These were find out, whether any such instance had
the four steps which had been taken occurred in the past, and if occurred,
to strategize as well as implement the had there any type of action been
solution. taken to solve such problem or not.
There were two such things for which
The scope of this report was limited to
no such historical evidence had been
reduce delay only. The reason for this
found. First thing was that in case,
is the fact that the need at that point of
even if any group had taken the
time was to get a quick solution which
initiative to solve the problem, the
should be robust and cost effective.
group had not documented the
And other ways of improvement were
findings and solutions for which there
increase in efficiency and productivity was no such report available in this
of machines as well as to improve the matter. Second thing was the fact that
capacity of machines so as to assist as there were a few instances when
Sinter Plant in achieving its production multiple shops / departments could
target. But these needed ample amount not achieve their respective
of resource in terms of manpower and production targets, for which this
capital along with significant amount problem in Sinter Plant had been
of time for which these things had been camouflaged and hence, nobody
rejected for further consideration. Hence thought that this problem needed so
the scope was limited to reduce delay. much attention. It came to limelight
because of two reasons. One of the
reasons was Bara Steel Plant had to made so as to not to get carried away
purchase Sinter from outside especially in the mid-way while solving the
to meet the production target. Another problem. The vision statement should
reason was this time, only Sinter Plant not only be understood by each and
couldn’t meet its production target every employee, but also build the
whereas all other shops/departments confidence among each of them to turn
involved in direct production of steel the statement into reality for which
were able to meet their production after LAKSHYA, there came the fourth
targets, for which it grabbed the part i.e., SAKSHAM which explained
attention of management. All data about how the above things had been
had been collected from log books of planned to achieve. Then, after building
the required period, and information confidence among the workforce, the
regarding the ways to troubleshoot stage of KARMA came, which revealed
the problems had been gathered the process to achieve success and
through brainstorming sessions with threw some light on how 4R strategy
non-executives as well as executives had been implemented in Sinter Plant
in Sinter Plant. Before getting into the to make a vision statement into reality.
body of the report let us have a look at Then, it showed the results of all the
the flow chart as well as production above efforts and at last it provided
target of Sinter Plant in Bara Steel Plant the conclusion precisely.
which had been shown in Annexure I
and Annexure II respectively. SANKAT: Defining the crisis
Thereportfollowed astructural approach • During H1 of 2013-14, 97.6%
which was explained as follows. fulfilment of monthly production
First of all, it explained about the target could have been achieved.
crisis, which was named as SANKAT. But Sinter machines were running
This part elaborated two things. One only for 51.25 hours/day (There
was how the problem caught the were 3 Sinter machines running in
attention of the management and the Bara Steel Plant for which ideally
other one was how the mind-set of the the machines could run for 24
workforce had been changed by the top X 3=72 hours/day), resulting in
management to assist in overcoming 76.8% utilisation of available hours.
the problem. Then the second part Reliability of age old equipment
was named as ANUSANDHAN i.e., had become poor, and breakdowns
the inquisition stage, where bottom- were common in the shop floor.
up approach had been followed to get Figure.1 showed the fulfilment of
the root cause analysis. After that, the for H1 of the year 2013-14
third part was named as LAKSHYA, production target and Fig.2
where a vision statement had been showed the daily running hours of
all the three Sinter machines
combined together for H1
of the year 2013-14. of H1 of 2013-14 had been
• Frequent strand stoppages took toll depicted in Figure 4.
15.00 12.7 13
11.6
-5 mm in sinter, %
110.0 106.2 10.4
103.1 104.3 9.17 9.44
Target fulfilment, %
10.00
100.0
93.5 5.00
89.1 89.4
90.0
0.00
80.0 12 3 456
12 34 56 Months
Months
60.00
55.20
55.00 51.00 51.60 52.23
50.00 48.60
45.00 46.44 0
40.00 123456
Months
shown in Table 1.
Fig. 5: Root cause analysis of non
Essentially the first step was to break fulfillment of monthly production target
the complex topic of Sinter Plant delay
into smaller parts to gain a better which were being put in Annexure III
understanding of it, through data and Annexure IV. The 5Ws are:
collection and analysis. Number of
• Who filled out the check sheet?
interdependent causes acted behind
(Operator, fitter, welder, shift I/c,
the poor performance and any delay
section I/c etc.)
in small parts ultimately led to overall
plant stoppage; hence root-cause • What was collected? (Start / stop
analysis was carried out. Figure 5 shows time for delay, reasons for delay)
the diagram. • Where did the collection take place?
(machine, room, section)
Data Collection
• When did the collection take place?
Data from every available source were
(hour, shift, day of the week)
collected, recorded and organized. Both
Quantitative as well as Qualitative • Why did the data are collected?
data were collected through (characterize and analyze sinter
customized check sheetanswering the machine delays)
Five Ws,
Next level, inch arges of functional
areas e.g. Production, Mechanical, 40.00
37.83
Delay hours
and Electrical were required to fill 30.00
30.25
22.33
check sheet so as to enable 19.66 19.91
20.00
12.17
• To check the shape of the 10.00
probability distribution of a
process 0.00
123456
Months
• To quantify defects by type
• To quantify defects by location Fig. 8 : Production Delay, H1, 2013-14
• To quantify defects by cause
(machine, worker)
200.00 179.58
• To keep track of the completion of
steps in a multistep procedure (in Delay hours 15.00 123.08 127.16
116.08
109.67
other words, as an SOP/SMP) 86.16
100.00
23.08 21.08 14
18.66
20.00
120.00 107.09
10.00 100.00
84.16 76.08
80.00
Delay hours
0.00 60.00
123456
40.00
Months 39.16
20.00
0.00 17.66
6.99
Fig. 6 : Electrical Delay, H1, 2013-14
123456
Months
119.41 114.66
120.00
100.00
98.33 Fig. 10 : Delay due to supplier side, H1, 2013-14
Delay hours
74.66 81.66
80.00
60.00 55.91 Data analysis
40.00
20.00 Analysing data involved examining it
0.00
in ways that reveal the relationships,
123456 patterns, trends, etc. that could be found
Months within it. By subjecting it to statistical
operations to find out what kinds of
Fig. 7 : Mechanical Delay, H1, 2013-14 relationships seemed to exist among
variables and to what level outcomes
500.00 100%
could be trusted. The basic objective
was to get an accurate assessment in 400.00
80%
Delay hrs.
order to better understand trends and 300.00
60%
• Communicatingcrossingthebarrier:
Informal communications at job Fig. 15 : Brainstorming to find out the
loca tions, to share concerns possible solution of problems
Heating Tightening
Lack ofWear & Tear lubrication
Greasing
Misalignment
Cleaning
Jam Corrosion
Equipment leading Equipment Not 100% Keep
to Filure Equipment T 100%
Repositioning
Repositioning is the strategy, to move
people for improved effectiveness and
Place Time
incorporation of various managerial
and operational changes.
Performing
Norming
Storming
Forming
Task
Individual Group Environment No
Opt Out? Agree? Yes
No
Yes Storming
Norming
Norming
Storming
Understanding & acceptance
of issues associated with the basic element by team Members.
Yes
Acceptance and understanding
of issues associted with the basic element by some team members.
Agree?
No
Non-Shared assumptions about
issues associated with the basic
In safety aspect, daily 10 minute safety Core competency was the specific factor
talk before job distribution (by sectional that was seemed central for long term
in-charges) and weekly safety meeting sustainable performance. Technical/
(by General Manager himself) instilled subject matter know-how, a reliable
a culture of safe working. process and/or close relationships with
customers and suppliers were the core
competencies targeted for improvement.
Knowledge
Performance Skill up renewal
enhancement gradation
Mentoring Delegation
Resource
provision
Enabling lower management to take bigger were otherwise left out in any such
Involvinglower management with more responsibility
Encouraging lower management to take more active training programs were covered. Basic
Get closer to customer objective was to update knowledge on
BaSP benefit Get closer to Supplier
Increase service delivery sinter making and disseminate latest
Innovate continuously
Enhance efficiency advancements in the same. Interactions
and discussions on problems and their
possible solutions were organised,
Fig. 22 : Enable, Involve, Encourage lower which helped in confidence building of
leadership each one.
Reaping the results
• Drastic reduction in internal delay i.e. due to mechanical, electrical and production
stoppages could be achieved which had been shown in figures 23, 24, and 25
respectively.
180
130
80
30
• Supplier side delay also reduced substantially, to near ZERO in March 2014
(Figure 27)
• Daily running hours could be improved up to 58.23 hours during H2, 2013-14
while 68 hours of running was realised on daily basis, which was all time record
(Figure 28)
Fig. 28 : Daily average running hours, FY 2013-14
• 101.5% fulfilment of monthly production target could be achieved in FY 13-14
(Shown in Figure 29)
Conclusion
This case study outlined the turnaround of an age-old sinter plant, from state of acute
distress to exceptional performance. Root causes for deterioration were identified
and analysed. The vision formed and well-marketed to have ‘Zero Delays’. First steps
taken were morale boosting and building capability of workforce. Then 4R strategy
was carefully designed and implemented in Sinter Plant. As a result, more than 100%
of targets could be achieved, just within 6 months.
The Steely Glitter in Eyes of Each Employee tells about the RESURGENT SINTER PLANT
References
1. www.LCE.com
2. www.cimaglobal.com/insight
3. www.globalturnaround.com
4. www.globalturnaround.com
5. www.insol.org
6. www.instituteforturnaround.com/default.asp
7. www.tma-uk.org
8. http://www.amazon.com/Autonomous-Maintenance-Seven-Steps-Implementing
9. http://www.implement-lean-manufacturing.com
10. www.tpmonline.com
11. http://bokarosteel.com/
12. Piotrowski, J., April 2, 2001. “Pro-Active Maintenance for Pumps”, Archives, February 2001,
Pump-Zone.com [Report online].
13. Arunagiri. P. & Babu, Dr A.Gnanavel, “Review on Reduction of Delay in manufacturing process
using Lean six sigma (LSS) systems”, International Journal of Scientific and Research Publications,
Volume 3, Issue 2, February 2013 1 ISSN 2250-3153
14. “Root Cause Analysis For Beginners” by James J. Rooney and Lee N. Vanden Heuvel
15. Gupta Desh & Sathye Milind, “Financial Turnaround of the Indian Railways: A Case Study”,
Faculty of Business & Government , University of Canberra, Canberra, Australia
Teaching Notes
KAYAPALAT – to a Resurgent Sinter Plant
The case had been prepared after the implementation of a strategy to assist Sinter
plant in achieving its production target. It had been observed in H1 of the year 2013-
14 that Sinter Plant was not able to meet its desired production target, but other shops
/ departments which were involved directly with steel production, met their
production targets successfully for which Sinter Plant became the bottleneck in Steel
making process for Bara Steel Plant. A thorough research revealed that Sinter machines
were being used only for 76.8% of its available running hours. After getting this clue,
the job was to how to solve this problem. Various questions could be framed at this
juncture which were:
1. What were the reasons for which utilization factor for machines was only 76.8%?
2. Was this the only reason for which production target had not been met or else apart
from this, there was/were other reason/s also, which was/were significant?
3. Was there any raw material issue like the raw materials procured for Sinter Plant was
having low quality during this period, for which it was like garbage in, garbage out?
4. If utilization factor for machines being 76.8% was the only reason, then what were the
causes for this problem?
Then, after having brainstorming sessions with executives as well as with non-executives,
the team found various ways to solve the issue of utilization factor to be only 76.8%.
These were:
• Increase efficiency of machines
• Increase productivity of machines
• Increase capacity of machines
Apart from these three solutions, one insight came to the team was that the mind-set of
people working in Sinter Plant i.e., “Sinter Plant to nahi sudhrega”, “Naya Plant na ane
se iskaa kuch nahi hoga”. This was the general sentiment among the workforce of Sinter
Plant. At this point various questions could come to any leader’s mind:
I. Should we solve all the three or only one or else any two among these options?
II. Should we upgrade all the three machines simultaneously and during these
periods, procure Sinter from outside temporarily?
Or else Stop the production during these periods, and start capital repair in all other
shops/ departments so that all our guns will blaze after a few days even with high
production capacity to mitigate the production loss occurred during these days?
III. By following Step-II could we satisfy our customers (Were they ready to wait for that
period or else did we have enough inventories to satisfy their respective demands
on time?)?
IV. Should we upgrade one machine at a time so that desired production target wouldn’t
get hampered as extra Sinter could be procured from outside till all machines got
upgraded one by one?
V. Were any of the above steps actually right by looking in the long term?
VI. What about the mind-set of the workforce? If machines would be upgraded right
now, could the mind-set of workforce be changed?
VII. Was changing the mind-set of workforce important for Sinter Plant?
VIII. Which one would be better in long term? Upgrading machines or changing the
mind-set of the workforce of Sinter Plant.
After looking at the above options, the team decided that changing the mind-set of people
was more important than upgrading the machines of Sinter Plant, and it discussed this
important issue with higher authorities of Sinter Plant to find a way anyhow to solve the
issue as well as change the mind-set of the workforce. In other words, the team took this
challenge as a golden opportunity to kill two birds with one stone. After many days of
rigorous brainstorming the team found a way to solve the problem and the way was to
reduce the delay. Even at this point, the team faced many questions regarding the impact
of the solution which could be
1st. Would this solution help Sinter Plant to achieve the production target?
2nd. If this wouldn’t fulfill the target, what might happen to customer satisfaction?
3rd. Wouldn’t the credibility of Bara Steel Plant be at stake?
4th. If this solution would fail, then could the mind-set of workforce i.e., “Sinter Plant to
nahi sudhrega”, “Naya Plant na ane se iskaa kuch nahi hoga” be changed in future?
5th. Who knows if it would fail, workers would laugh at the leadership of the top
management and the grip of shop floor managers on workers would be lost. Even
because of the negative mind-set, workers would always have an excuse i.e., nothing
could be done without new machines.
The stakes were high, for which the executives planned to make sure that they would
make it happen because the situation was kind of it’s now or never. After careful
consideration, strategies had been crafted to turnaround the situation and the successful
implementation had been done with the help of 4R strategy, which helped immensely
in achieving the objective set by management of Sinter Plant.
This report tries to throw some light on how the management of a Sinter Plant
overcame from the problem of not achieving its production target. But, more
importantly, it tries to show the thought process of how the management tried change
the mind-set of the workforce by changing the way to achieve the desired objective for
long term benefit of its parent firm.