You are on page 1of 23

Kayapalat - to a Resurgent

Sinter Plant

During H1 of the year 2013-14, Sinter Plant was not able to meet its production target for which
Bara Steel Plant had to purchase Sinter from outside the premises. Because of this, profitability of
Bara Steel Plant got hampered and the only reason for this reduced profitability was Sinter Plant.
Sinter Plant became the only bottleneck in the steel making process of Bara Steel Plant
because all other shops/departments involved in direct production of steel met their
respective targets successfully. The utilization of Sinter machines was only 76.8% of available
hours. If we dive deep into the matter, then we can say that had Sinter not been purchased from
outside, Bara Steel Plant would have been able to achieve only 3/4th of its production target
for steel. The impact of the problem was so severe that we might not have been able to claim
ourselves as the largest producer of steel in India, which is the pride of our parent firm, had it
not been dealt immediately.
It was recommended that Sinter Plant needed to reduce delay so as to achieve the production
target successfully. Apart from this, there were also other three solutions which could have been
implemented, but reducing delay was less capital intensive as well as less time consuming for
which it became the best option as per our research and study. In other words, this was the
optimized solution which consumed fewer resources as compared other solutions and gave
maximum benefits to Sinter Plant, which in turn helped Bara Steel Plant to meet its production
target without procuring Sinter from outside. It increased utilization of Sinter machines from
76.8% to 97.6% i.e., a 27% increase in utilization of machines, and further stretching this to
100% wouldn’t be cost effective for which this was the highest utilization factor which we
could achieve.

intering is the process of


S agglomeration of fine iron ore
particles into a porous and lumpy mass
was not meeting its production targets
on a regular basis for a few months.
And during these periods, each and
by incipient fusion. In Indian scenario, every other shop/ department of Bara
sintering is most common process Steel Plant was meeting its respective
of utilising iron ore fines as Blast production target set by its top
Furnace feed economically. Bara Steel management. Hence, it was clear that
Plant (BaSP) is equipped with 3 sinter Sinter Plant had become a bottleneck
strands (designed and commissioned in steel making process. It needed to
by erstwhile USSR during 1970’s). It be dealt as soon as possible so as to
had been observed that Sinter plant meet the demands of customers of Bara
Steel

1
Plant. And this was the reason which There is hardly any improvement
prompted for the investigation in Sinter possible further in the weak link which
Plant. To investigate into the matter, a had been found and mitigated as per
problem statement had been defined this report because it already improved
which was as follows. the utilization parameter from 76.8%
to 97.6%. Further stretching this to
After coming to a definite problem
100% may not have much impact on
statement, first point was to collect past
production. In other ways, it would
data to start analysis. After the collection
not be cost effective to stretch further
of data, second thing was to find weak
to achieve 100%. i.e., the limitation of
links with the help of analysis tools
this report was utilization parameter
from the past data. Third thing was to
couldn’t be stretched more than 97.6%.
do brainstorming with both blue collar
The reason for this limitation was the
workforce (non-executives) as well as
fact that it would increase significant
executives separately so as to decide
amount of cost which in turn might
which weak links could be attacked to
reduce the profitability.
get maximum output with minimum
cost. And at last, the final thing was to Before starting the investigation,
build pragmatic solutions to mitigate historical evidence had been tried to
the weak links optimally. These were find out, whether any such instance had
the four steps which had been taken occurred in the past, and if occurred,
to strategize as well as implement the had there any type of action been
solution. taken to solve such problem or not.
There were two such things for which
The scope of this report was limited to
no such historical evidence had been
reduce delay only. The reason for this
found. First thing was that in case,
is the fact that the need at that point of
even if any group had taken the
time was to get a quick solution which
initiative to solve the problem, the
should be robust and cost effective.
group had not documented the
And other ways of improvement were
findings and solutions for which there
increase in efficiency and productivity was no such report available in this
of machines as well as to improve the matter. Second thing was the fact that
capacity of machines so as to assist as there were a few instances when
Sinter Plant in achieving its production multiple shops / departments could
target. But these needed ample amount not achieve their respective
of resource in terms of manpower and production targets, for which this
capital along with significant amount problem in Sinter Plant had been
of time for which these things had been camouflaged and hence, nobody
rejected for further consideration. Hence thought that this problem needed so
the scope was limited to reduce delay. much attention. It came to limelight
because of two reasons. One of the
reasons was Bara Steel Plant had to made so as to not to get carried away
purchase Sinter from outside especially in the mid-way while solving the
to meet the production target. Another problem. The vision statement should
reason was this time, only Sinter Plant not only be understood by each and
couldn’t meet its production target every employee, but also build the
whereas all other shops/departments confidence among each of them to turn
involved in direct production of steel the statement into reality for which
were able to meet their production after LAKSHYA, there came the fourth
targets, for which it grabbed the part i.e., SAKSHAM which explained
attention of management. All data about how the above things had been
had been collected from log books of planned to achieve. Then, after building
the required period, and information confidence among the workforce, the
regarding the ways to troubleshoot stage of KARMA came, which revealed
the problems had been gathered the process to achieve success and
through brainstorming sessions with threw some light on how 4R strategy
non-executives as well as executives had been implemented in Sinter Plant
in Sinter Plant. Before getting into the to make a vision statement into reality.
body of the report let us have a look at Then, it showed the results of all the
the flow chart as well as production above efforts and at last it provided
target of Sinter Plant in Bara Steel Plant the conclusion precisely.
which had been shown in Annexure I
and Annexure II respectively. SANKAT: Defining the crisis
Thereportfollowed astructural approach • During H1 of 2013-14, 97.6%
which was explained as follows. fulfilment of monthly production
First of all, it explained about the target could have been achieved.
crisis, which was named as SANKAT. But Sinter machines were running
This part elaborated two things. One only for 51.25 hours/day (There
was how the problem caught the were 3 Sinter machines running in
attention of the management and the Bara Steel Plant for which ideally
other one was how the mind-set of the the machines could run for 24
workforce had been changed by the top X 3=72 hours/day), resulting in
management to assist in overcoming 76.8% utilisation of available hours.
the problem. Then the second part Reliability of age old equipment
was named as ANUSANDHAN i.e., had become poor, and breakdowns
the inquisition stage, where bottom- were common in the shop floor.
up approach had been followed to get Figure.1 showed the fulfilment of
the root cause analysis. After that, the for H1 of the year 2013-14
third part was named as LAKSHYA, production target and Fig.2
where a vision statement had been showed the daily running hours of
all the three Sinter machines
combined together for H1
of the year 2013-14. of H1 of 2013-14 had been
• Frequent strand stoppages took toll depicted in Figure 4.
15.00 12.7 13
11.6

-5 mm in sinter, %
110.0 106.2 10.4
103.1 104.3 9.17 9.44
Target fulfilment, %

10.00
100.0
93.5 5.00
89.1 89.4
90.0
0.00

80.0 12 3 456
12 34 56 Months
Months

Fig. 3: -5 mm Sinter, H1, 2013-14


Fig. 1: Fulfilment of Production Target, H1,
2013-14 35689

External Sinter. Tons


40000
30000 27309
20000 25465
19947 19174 19456
10000
Daily running hours

60.00
55.20
55.00 51.00 51.60 52.23
50.00 48.60
45.00 46.44 0
40.00 123456
Months

12 3 456 Fig. 4: External Sinter, H1, 2013-14


Months
• It was not only the visible under
Fig. 2: Daily Sinter Machines’
Running Hours, H1, 2013- performance of Sinter Plant, but
14 also lack of any visible solution to
break the vicious circle which made
on sinter quality; -5 mm in sinter employees low on confidence.
were hovering at 11.05%, which was “Sinter Plant to Nahi Sudhrega”,
being shown in Figure 3. “Naya Plant na ane se iska kuch nahi
• It was necessitated to arrange hoga” was the statement made by
external Sinter for feeding Blast most of the workforce during those
Furnaces. In H1 2013-14, external bleak days which meant that Sinter
sinter of average 24500 tons/month plant won’t change for betterment,
was consumed, which acted against nothing could be done until new
the profitability and integration of plant comes in. Lack of hope was
BaSP. The amount of external Sinter more dangerous than challenging
consumed in each of the 6 months
1
In a year, ideally there should be 365 X 24 X 3 = 26280 hrs. available for running all the three machines.
But on an average 27 days had been taken for capital repair and other repairs for each machine in a
Year. So practically, time available for running for all three machines = (365-27) X 24 X 3 = 24336 hrs. /
year But all three Sinter machines are running for 51.25 hrs. / day on an average.
Hence total running time for all three Sinter machines = 51.25 X 365 = 18706.25 hrs. / year
i.e., utilization of machines = (18706.25 / 24336) X 100 = 76.8% of available time
reality, and all symptoms of chronic While considering all the above
distress were evident in Sinter Plant solutions, it was evident that if these
collectively. solutions would be implemented, then
• But it was the new GM (General the mind-set of the workforce couldn’t
Manager), appointed from customer be changed. And it was very important
department who saw the mounting to change the mind-set of the workforce
challenges as golden opportunities. by looking at the long term perspective
First and foremost action he took of the plant. So, it was like a challenge
was to instil confidence, “Jo nahi ho which had to be converted into an
sakta hai, WOHI TO KARNA HAI” i.e., opportunity to kill two birds with one
the thing which can’t be done, is stone. i.e., one solution would be found
what we have to do. He was the out which could help Sinter Plant to
person who tried to change the achieve its production target as well as
mind-set of the workforce of Sinter change the mind-set of workers (The
Plant in order to build confidence mind-set of workers was “Sinter Plant
among them so as to get the to nahi sudhrega”, “Naya Plant na ane se
production back on track. iskaa kuch nahi hoga”). This perspective
had been put up in front of the top
ANUSANDHAN: Inquisition stage management of Sinter Plant, after
To delve deep into the problem, and which it was decided that an alternative
prepare pragmatic solution, first of all, had to be found out to solve this matter.
rigorous brainstorming sessions had This time, rigorous brainstorming
been done separately with executives as sessions had been conducted, and after
well as non-executives to gather ideas a few days of hard work, a solution
to improve the utilization of Sinter came, which was to reduce delay. The
machines so as to meet the production executives were ecstatic about this
target of Sinter Plant. After several solution, but there were also some
brainstorming sessions, it had been risks involved with this solution. The
found out that there were mainly four risk was in case the solution failed to
areas which could lead to improvement achieve the desired outcome, then the
in utilization of Sinter machines, if workforce of Sinter Plant would think
dealt carefully. These four areas of that they were always right i.e., “Sinter
improvement were:- Plant to nahi sudhrega”, “Naya Plant na ane
se iskaa kuch nahi hoga”. And in future it
A. Increase the productivity of machines
would be very difficult to change this
B. Increase the efficiency of machines mind-set, if the management would fail
(Reduce rejection of Sinter) by opting for the fourth option i.e., to
C. Capacity improvement of machines reduce delay. Again, the pros and cons
D. Reduce delays of this solution had been put up in
front of the top management of Sinter
Table 1: Comparisons of available options thought of during brainstorming

Requirement Productivity Efficiency Capacity Delay


Capital High High High Low / Moderate
Manpower High High High High
Time More More More Moderate / More
Production Hamper Yes Yes Yes No
Change of Mind-set No No No Yes

Plant, after which the top management


51.25hrs. of daily running
decided to opt for the fourth option
as it was a situation like it’s now or
76.8% utilization of available hours
never. And the management was fully
97.6%
External Sinter in BaSP Blast Furnaces
committed to first craft a strategy which fulfilment of production target

would be robust so that there


Low Yield
wouldn’t be any chance of failure.
Hence, work started on fourth option. 11.05% of -5mm Sinter

To get a view of all the options, a small


comparison had been made which was Frequent Machine Stop

shown in Table 1.
Fig. 5: Root cause analysis of non
Essentially the first step was to break fulfillment of monthly production target
the complex topic of Sinter Plant delay
into smaller parts to gain a better which were being put in Annexure III
understanding of it, through data and Annexure IV. The 5Ws are:
collection and analysis. Number of
• Who filled out the check sheet?
interdependent causes acted behind
(Operator, fitter, welder, shift I/c,
the poor performance and any delay
section I/c etc.)
in small parts ultimately led to overall
plant stoppage; hence root-cause • What was collected? (Start / stop
analysis was carried out. Figure 5 shows time for delay, reasons for delay)
the diagram. • Where did the collection take place?
(machine, room, section)
Data Collection
• When did the collection take place?
Data from every available source were
(hour, shift, day of the week)
collected, recorded and organized. Both
Quantitative as well as Qualitative • Why did the data are collected?
data were collected through (characterize and analyze sinter
customized check sheetanswering the machine delays)
Five Ws,
Next level, inch arges of functional
areas e.g. Production, Mechanical, 40.00
37.83

Delay hours
and Electrical were required to fill 30.00
30.25
22.33
check sheet so as to enable 19.66 19.91
20.00
12.17
• To check the shape of the 10.00
probability distribution of a
process 0.00
123456
Months
• To quantify defects by type
• To quantify defects by location Fig. 8 : Production Delay, H1, 2013-14
• To quantify defects by cause
(machine, worker)
200.00 179.58
• To keep track of the completion of
steps in a multistep procedure (in Delay hours 15.00 123.08 127.16
116.08
109.67
other words, as an SOP/SMP) 86.16
100.00

The occurring of delay due to each of


50.00
the factors had been shown below.
0.00
123456
Months
37.91
40.00
31.66
29.08 Fig. 9 : Delay due to customer side, H1, 2013-
30.00
Delay hours

23.08 21.08 14
18.66
20.00

120.00 107.09
10.00 100.00
84.16 76.08
80.00
Delay hours

0.00 60.00
123456
40.00
Months 39.16
20.00
0.00 17.66
6.99
Fig. 6 : Electrical Delay, H1, 2013-14
123456
Months
119.41 114.66
120.00
100.00
98.33 Fig. 10 : Delay due to supplier side, H1, 2013-14
Delay hours

74.66 81.66
80.00
60.00 55.91 Data analysis
40.00
20.00 Analysing data involved examining it
0.00
in ways that reveal the relationships,
123456 patterns, trends, etc. that could be found
Months within it. By subjecting it to statistical
operations to find out what kinds of
Fig. 7 : Mechanical Delay, H1, 2013-14 relationships seemed to exist among
variables and to what level outcomes
500.00 100%
could be trusted. The basic objective
was to get an accurate assessment in 400.00
80%

Delay hrs.
order to better understand trends and 300.00
60%

its effects on Sinter Plant performance. 200.00


40%

The delay data so collected were first 100.00


20%
analyzed in graphical representation, 0.00

and Histograms were used to plot the


Agency
density of data, and often for density
estimation: estimating the probability
density function of the underlying Fig. 12 : Pareto analysis of Delays, June 2013
variable. BF (Blast Furnace) belt relationships underlying a particular
stoppage during July’13 is attached as problem. Application of the technique
Figure 11, showing the trend of small to determine high occurrence of
value but high frequency. mechanical and electrical delay is
presented in Figure. That encouraged
60
50 the troubleshooter to avoid assumptions
Frquency of stop

and logic traps and instead trace the


40
chain of causality in direct increments
30
from the effect through any layers of
abstraction to the root cause. The fifth
20 why suggested a broken process, which
10
was indicative of reaching the root-
cause level.
0
Fig. 11
1 3: Histogram
5 7 9 11 13of
15 daily machine
17 19 21 delay
23 25 27 29 The 5 Why technique had been depicted
Days
due to BF belt stop, July 2013 below.
Problem : Mechanical & Electrical
Data from check sheets, plotted stoppages are very high
against a Pareto chart, containing both
bars and a line graph. The chart 1. Why? Frequent breakdowns,
highlighted the most important among Machine reliability poor
a (typically large) set of delay reasons. 3. Why? Depleting manpower,
Hence, the most common sources of preventive maintenance limited
delays, the highest occurring type 2. Why? No condition based
shown in Figure 12, or the most maintenance of equipment
frequent reasons for customer 4. Why? Inspection schedule not
complaints could be identified. properly maintained
Besides the quantitative analysis, 5 5. Why? Poor house-keeping makes
why’s technique was also applied inspection impossible
to explore the cause-and-effect
LAKSHYA: Formulating vision communicated. The vision statement
statement
is as follows.
After analysis of the delay situation, it
Zero Delays
was evident that production target could
not be met with such high occurrence Zero Abnormalities
of delays. So, it was clear that if delay Perfect Quantity and Quality
could be reduced then production
target could have been met in future. SAKSHYAM: Capacity building
And, if delay could be minimized each stage
and every time, then production target “If you want to build a ship, don’t drum
would not have been missed even for up the men to gather wood, divide the work
a single time due to delay. Hence, to and give orders. Instead, teach them to
maintain the process for long term, it yearn for the vast and endless sea.”
was needed to make a vision statement, – Antoine de Saint-Exupery
so that even after getting success for a
In fulfilling the targets and realizing
few occasions in reducing delay to the the vision, first step was taken
optimum level, people wouldn’t forget towards capacity building. Building
to maintain or get carried away by capacity, that it could not only
other responsibilities. Hence, a vision, turnaround Sinter Plant by then, but
quite simply was being made and also during lasting future too.

Fig. 13 : Loss in productivity due to unplanned delays


Communication Brain storming
Communication initiatives had been Acting hands on the equipment,
taken to focus Sinter Plant team to employees could be the best judge of
achieve the overall objectives of their problems. Brainstorming sessions
department and organization as a were organized. Concerned people
whole. Objectives were broken down including executives and workforce
to identifiable targets in the audience were called, the situation/challenge
groups’ sphere of influence. Variety put forth and questions e.g. “HOW
of communications modes e.g., CAN WE?” were asked. Letting the
Public display boards in each section, possibilities come forward, discussed
presentation by sectional incharges about pros & cons, effective solutions
and closed group interaction were could be implemented on reality.
implemented, to hard hit all people
down the line.
In addition, top management of BaSP
e.g., CEO (Chief Executive Officer) and
ED (W) (Executive Director (Works)) Excellence Philosophy Method Tool
Idealistic, Functionality,
started to visit the shop periodically, Space/Time/Interface,
Complete problem solving
interacted directly with employees process
Trend Analysis, Best Practice,
and their concerns. SOP, SMP, Knowledge Sharing

• Communicatingcrossingthebarrier:
Informal communications at job Fig. 15 : Brainstorming to find out the
loca tions, to share concerns possible solution of problems

• Cross border communication: Morale boosting


Customers, suppliers and services Chronic under-performance mostly
units of BaSP were invited to attend eroded confidence of employees and
formal communication meetings attitude of no hope was evident. So the
and participate can–do approach was first traded to all
14393
of Sinter Plant. Through each and every
14194 interaction,pessimism of the future,
14194
12419
confidence on employees, trust and
12300
12000
mutual belief were traded.
12000

“No matter how bad things got, no


matter how anxious the staff become, the
SepOctNovDecJanFebMar commander has to preserve optimism in
himself and his men”
2013 - 14
– Gen. D.E. Eisenhower, Supreme Commander,
Fig. 14 : Daily Sinter production target (in Tons) Allied Expeditionary Force, WW II
Instilling Confidence upon i.e. Cleaning Program Checklist
front line managers by assigning
greater responsibility created 1. Cleaning main body of machine,
exceptional positive spirit. One-to- checking and tightening bolts
one communication with senior 2. Cleaning ancillary equipment,
management level and problem facing checking and tightening bolts
head-on inspired all to Win. 3. Cleaning lubrication areas before
KARMA: Application stage performing lubrication
4. Cleaning around equipment
To attain the goal, emphasis was
given to Preventive Maintenance i.e. 5. Treating the causes of dirt, dust,
to treat causes of breakdowns before leaks, and contamination
they actually happen. In realizing the 6. Improving access to hard-to-reach
goal, 4R strategy i.e. Retrenchment, areas
Repositioning, Reorganisation and
Renewal were applied. 7. Developing cleaning standards
“This hand-on approach also increased
Retrenchment
the person’s respect for the machine. This
The Retrenchment strategy included process of cleaning, seeing, touching, and
wide-ranging short-term actions, aimed respecting the machine was essential to
to stabilize the delays and to work increase reliability”
against the root causes. – GM, Sinter Plant
Improve upon House keeping Besides, keeping overall cleanliness
House-keeping was outsourced section- of area was another priority, scrap
wise, with specificmention to removal and peripheral cleaning was
thequantity in the payment terms. On carried out in massive scale. This
contract to the earlier practice of private could be ensured by systematic
supervision, monitoring by Sinter Plant elimination of sources of dirt and
employees was introduced. Cleaning clutter such as misplaced trash
being a hands- on activity, people containers, lack of proper storage,
supervising during cleaning the broken tools, bad ventilation,
machines had the best chance of inadequate lighting etc.; which
detecting any failure. As they touched ultimately helped in spreading
and looked at the machine, loose bolts positive mood and morale among
shouted to them. Part of the cleaning workforce.
process was looking for ways to make Vigorous inspection
cleaning easier or maintenance
All three key aspects of an inspection
avoidable. In some cases, the source of
i.e. inspector competence, reliability of
dirt could be isolated to reduce the need
inspection and quality of information
for cleaning.
used and created by the inspector
were carefully enhanced. Inspector preventative maintenance practices
competence in terms of skill, knowledge focusing on the entire equipment life
and ability to assess risk; to recognize cycle was established. Implemented
a defect, while categorizing and
team-based (including all departments
reporting defects reliably and quickly
e.g. operation, mechanical, electrical,
were ensured. Inspectors visually
and instrumentation) activities aimed
inspected the item and, where relevant
listened to it, felt it and possibly smelt it. at the organization-wide goal of zero
Inspection data were recorded and defects and zero breakdowns. A work
made accurate comparisons from one order system and equipment data base
inspection to the next, thereby maintained, to monitor and support
allowing defects to be monitored and continuous equipment improvement.
either repaired, or replaced in an Also it was ensured that maintenance to
organized manner. treat root cause and not the symptom,
Besides, 3-tier inspection, by operator, so that maintenance personnel could be
supervisor and sectional incharges were moved from the “fire-fighting” mode to
introduced, which could seal any the prevention mode. Daily 2-3 hours
possible leakages in single layer of planned shutdown and immediate
inspection. liquidation of defects identified
(Schedule for monitoring is attached in
Autonomous maintenance practice (Annexure V) was introduced.
Reliability based maintenance system
utilizing proactive, predictive, and

Reacting Responding Prevention


Detecting Equipment Rectification of Reasons
Continous Continuous
Improvement Detecting Reasons for
improvement

Noise Vibration Deformation Loose Align

Heating Tightening
Lack ofWear & Tear lubrication
Greasing
Misalignment
Cleaning
Jam Corrosion
Equipment leading Equipment Not 100% Keep
to Filure Equipment T 100%

FIX IT FIX IT MAINTAIN IT

Fig. 16 : Autonomous maintenance parctic


Step Process name Activities
1 Clean & inspect CGT (Cleaning, greasing, Tightening)
2 Eliminate problem sources and Correction of dirt sources, preventing
inaccessible areas spillage, improving accessibility and shorten
time
3 Draw up cleaning and greasing Standards and schedule for CGT well
standards documented and reviewed periodically
4 Conduct general inspection Skill training and enhancing capabilities
5 Conduct autonomous inspection Standard check sheets and standards for
inspection prepared and followed
6 Standardise through visual Standardise all work process:
workplace management • Work area material flow
• Data recording methods
• Spare management
7 Implementing autonomous Improvement in everyday practices, maintain
equipment management reliable MTBF (mean time before failures) data,
analysis and using it for further improvement

Repositioning
Repositioning is the strategy, to move
people for improved effectiveness and
Place Time
incorporation of various managerial
and operational changes.

Job defining and placing people


Mind
accordingly
Job definition is the list that an
employee had to do with a position.
Fig. 17 : Right People, Right Job, Right Time
The skills required and expectations
in terms of quantified outcomes were Gap analysis and revival strategy
clearly spelled out. Accordingly,
Analysing the Gap i.e. comparison
employees were relocated as per
of actual performance with potential
requirement. Some key position
performance pointed areas where best
demanded people to develop future
use of available resources was
plan and projections of needs. Efficient
missing. It involved determining,
utilization of available resources could
documenting, and approving the
improve collective performances.
difference between requirements and
current capabilities.
Identify core Internal External data Analysis Change
issues baseline data collection Implementation

Issues Process Benchmark Compare and Implementation


overview questionnaire contrast plan
• Customer
demand Current benchmark
• Performance measures
gap data
Other
• Problem areas departments

• Defined • Process flow • Other SAIL • Gap • Plan to close


benchmark mapping units • Process gap
area • Validate • Process reengineering • Actions
• Overview of • Target sister analysis, opportunities • Recalibrate
key process departments performance • New benchmarks
• Selected • Short term assessment o Flows • Additional
performance operational and measures o Policies analysis
measures improvements o Procedures
• Implementation
plan

Fig. 18 : comparison of actual performance with potential performance

Gap analysis also used to compare Technical interventions for recurring


existing processes to processes problems
performed elsewhere, such as those
obtained by benchmarking. In this For system reliability study and
usage, each process was compared side- failure analysis, first Failure Mode
by-side and step-by-step and actions and Effects Analysis (FMEA) was
planned for differences (Annexure VI). applied. It involved reviewing as
many components, assemblies, and
Step Description
subsystems as possible to identify
1 Existing process identified failure modes, and their causes and
2 Existing outcome identified effects. For each component, the failure
3 Desired outcome identified modes and their resulting effects on
4 Process to achieve desired the rest of the system were recorded
outcome identified in specific FMEA worksheet (Annexure
VII). It helped to identify potential
5 Identify the Gap and document it
failure modes based on experience
6 Develop means to fill the Gap
with similar products and processes -
7 Develop and prioritize or based on common physics of failure
requirements to bridge the Gap logic. And through this analysis,
frequent failure of hot
screen could be identified. Accordingly,
technical interventions e.g.
• Heat shield modification
Value
ValueCreation
Proposition
HowWhat
will you
willwork
your with
servicyour
do?customers and supplier to creat and d
• Additional grease station for vibrator
• Changing grease quality to
withstand heatwere implemented
as per in-house design
“This power of thinking out and Value Capture
executing is initiative, and freedom to How will you ensure that you benefit from creating the service?
propose and to execute belongs too in a
way, to initiative. The collective initiative
of all employees represents a great
source of strength of businesses. Henri”
Fig. 19 : Development of value creation point
– Henri
Fayol of uninterrupted supply in required
quantity, flux and fuel crushing section
Applying JIT in Spare Management
was given target to maintain crushing
Applying Just-In-Time (JIT) in spare index respectively at 80 & 85%. Each
management i.e.,‘the exact item needed, section was defined as customer and
when it is needed, and in the quantity supplier to another, and ought to deliver
needed’. Weekly projection of spare value to them. It was also a goal clearly
demand and managing supply chain to tied to the system output, a collective
ensure required items to be available on overarching goal that subsumed
site close to when they were needed and functional goals and depended upon
not held in inventory for a lengthy time. concerted efforts of people at all levels.
Extensive planning and scheduling It created a super-charged atmosphere
requiring highly responsive production in Sinter Plant whole, with people knew
and supply systems were introduced. what exactly their role in quantitative
terms and wanted to fulfill them. There
Reorganization
was a buzz in the workplace and a
The reorganization strategy introduced number of small initiatives in every
some managerial changes in Sinter section began to have a cumulative
Plant as: effect in terms of better coordination
Each section as value creation point and performance.

Here goal of each section clearly stated Teamwork at its best


so that every employee, working in any “Talent wins games, but teamwork wins
section could relate to it. For example, championships”
stock bin sections were given targets - Michael Jordan
The Integrated Team Development Framework

Performing
Norming
Storming
Forming

Task
Individual Group Environment No
Opt Out? Agree? Yes

No
Yes Storming

Norming

Norming
Storming
Understanding & acceptance
of issues associated with the basic element by team Members.

Yes
Acceptance and understanding
of issues associted with the basic element by some team members.
Agree?

No
Non-Shared assumptions about
issues associated with the basic

Fig. 20 : The integrated team development framework

Conventional concept of teamwork


development i.e. Forming, Storming, Renewal
Norming and Performing were Renewals, strategy pursuing long-
implemented in all new cross-functional term actions were supposed to end in
(Goal Congruence) paradigms. Enabling a successful managerial performance.
factors of teamwork i.e. focusing on the The first step was analysing the existing
goal, placing the right people, enabling structures within the organisation.
to working together were all provided This examination lead to enhancing
on one hand; on the other teams were innovative core competencies,
continuously challenged with one concluded in an increase of knowledge
another. Improving Cross functional and a stabilization of the organisation
collaboration conflicted at a number of value.
levels both up and down the hierarchy
and across functions andwork groups. Improve upon core competencies of employees

In safety aspect, daily 10 minute safety Core competency was the specific factor
talk before job distribution (by sectional that was seemed central for long term
in-charges) and weekly safety meeting sustainable performance. Technical/
(by General Manager himself) instilled subject matter know-how, a reliable
a culture of safe working. process and/or close relationships with
customers and suppliers were the core
competencies targeted for improvement.
Knowledge
Performance Skill up renewal
enhancement gradation

Improving core competency

Mentoring Delegation
Resource
provision

Fig. 21 : Fish Bone diagram for improving core competency

Shown in fig. 21. For that, subjective Promoting innovative culture


delegation of authority to employees
Challenging target demanded
and committing them resources were
creativity, i.e. viewing existing facts
implemented.
from a new perspective allowed
Nurturing young leaders individuals to come up with ingenious
Nurturing young leaders through ways to solve seemingly impossible
Encouraging, Involving & Enabling problems. Experimentation based on
front line managers paid excellent reverse logic was encouraged, which
dividends not only in enhanced ultimately lead shaping many ideas at
decision making speed, but also competitive cost. Introduction of a ‘Flap
boosted confidence in long term. gate arrangement’ in sinter transfer belt
Shift managers were empowered to was classic example of such realistic
communicate with customer & supplier innovation, which actually reduced
department and resolve issues delay due to BF belt substantially.
quickly. Similarly quick shutdown for
smaller maintenance jobs was Development of human resources
authorized to shift level executives. “Workshop on Sintering Technology”
was organized in Sinter Plant seminar
room, and shift level employees who
Degree of Empowered Lower Leadership

Enabling lower management to take bigger were otherwise left out in any such
Involvinglower management with more responsibility
Encouraging lower management to take more active training programs were covered. Basic
Get closer to customer objective was to update knowledge on
BaSP benefit Get closer to Supplier
Increase service delivery sinter making and disseminate latest
Innovate continuously
Enhance efficiency advancements in the same. Interactions
and discussions on problems and their
possible solutions were organised,
Fig. 22 : Enable, Involve, Encourage lower which helped in confidence building of
leadership each one.
Reaping the results
• Drastic reduction in internal delay i.e. due to mechanical, electrical and production
stoppages could be achieved which had been shown in figures 23, 24, and 25
respectively.

Fig. 23 : Delay due to electrical stoppages, FY 2013-14

Fig. 24 : Delay due to mechanical stoppages, FY 2013-14

Fig. 25 : Delay due to production stoppages, FY 2013-14


• Delay due to BF belt stoppage reduced by around 50% (shown in Figure 26

180

130

80

30

Fig. 26 : Delay due to BF belt stoppage, FY 2013-14

• Supplier side delay also reduced substantially, to near ZERO in March 2014
(Figure 27)

Fig. 27 : Delay due to supplier side, FY 2013-14

• Daily running hours could be improved up to 58.23 hours during H2, 2013-14
while 68 hours of running was realised on daily basis, which was all time record

(Figure 28)
Fig. 28 : Daily average running hours, FY 2013-14
• 101.5% fulfilment of monthly production target could be achieved in FY 13-14
(Shown in Figure 29)

Fig. 29 : %age of Fulfilment of production target, FY 2013-14

• Requirement of external sinter in BaSP reduced to 3893 tons/moth only, thus


improving productivity and overall cost efficiency of BaSP
• Operational stability as achieved could improve sinter quality. -5 mm in sinter
reduced by 20% (Shown in Figure 30)

Fig. 30 : 5 mm Sinter, FY 2013-14

Conclusion
This case study outlined the turnaround of an age-old sinter plant, from state of acute
distress to exceptional performance. Root causes for deterioration were identified
and analysed. The vision formed and well-marketed to have ‘Zero Delays’. First steps
taken were morale boosting and building capability of workforce. Then 4R strategy
was carefully designed and implemented in Sinter Plant. As a result, more than 100%
of targets could be achieved, just within 6 months.
The Steely Glitter in Eyes of Each Employee tells about the RESURGENT SINTER PLANT
References
1. www.LCE.com
2. www.cimaglobal.com/insight
3. www.globalturnaround.com
4. www.globalturnaround.com
5. www.insol.org
6. www.instituteforturnaround.com/default.asp
7. www.tma-uk.org
8. http://www.amazon.com/Autonomous-Maintenance-Seven-Steps-Implementing
9. http://www.implement-lean-manufacturing.com
10. www.tpmonline.com
11. http://bokarosteel.com/
12. Piotrowski, J., April 2, 2001. “Pro-Active Maintenance for Pumps”, Archives, February 2001,
Pump-Zone.com [Report online].
13. Arunagiri. P. & Babu, Dr A.Gnanavel, “Review on Reduction of Delay in manufacturing process
using Lean six sigma (LSS) systems”, International Journal of Scientific and Research Publications,
Volume 3, Issue 2, February 2013 1 ISSN 2250-3153
14. “Root Cause Analysis For Beginners” by James J. Rooney and Lee N. Vanden Heuvel
15. Gupta Desh & Sathye Milind, “Financial Turnaround of the Indian Railways: A Case Study”,
Faculty of Business & Government , University of Canberra, Canberra, Australia
Teaching Notes
KAYAPALAT – to a Resurgent Sinter Plant
The case had been prepared after the implementation of a strategy to assist Sinter
plant in achieving its production target. It had been observed in H1 of the year 2013-
14 that Sinter Plant was not able to meet its desired production target, but other shops
/ departments which were involved directly with steel production, met their
production targets successfully for which Sinter Plant became the bottleneck in Steel
making process for Bara Steel Plant. A thorough research revealed that Sinter machines
were being used only for 76.8% of its available running hours. After getting this clue,
the job was to how to solve this problem. Various questions could be framed at this
juncture which were:
1. What were the reasons for which utilization factor for machines was only 76.8%?
2. Was this the only reason for which production target had not been met or else apart
from this, there was/were other reason/s also, which was/were significant?
3. Was there any raw material issue like the raw materials procured for Sinter Plant was
having low quality during this period, for which it was like garbage in, garbage out?
4. If utilization factor for machines being 76.8% was the only reason, then what were the
causes for this problem?
Then, after having brainstorming sessions with executives as well as with non-executives,
the team found various ways to solve the issue of utilization factor to be only 76.8%.
These were:
• Increase efficiency of machines
• Increase productivity of machines
• Increase capacity of machines
Apart from these three solutions, one insight came to the team was that the mind-set of
people working in Sinter Plant i.e., “Sinter Plant to nahi sudhrega”, “Naya Plant na ane
se iskaa kuch nahi hoga”. This was the general sentiment among the workforce of Sinter
Plant. At this point various questions could come to any leader’s mind:
I. Should we solve all the three or only one or else any two among these options?
II. Should we upgrade all the three machines simultaneously and during these
periods, procure Sinter from outside temporarily?

Or else Stop the production during these periods, and start capital repair in all other
shops/ departments so that all our guns will blaze after a few days even with high
production capacity to mitigate the production loss occurred during these days?
III. By following Step-II could we satisfy our customers (Were they ready to wait for that
period or else did we have enough inventories to satisfy their respective demands
on time?)?
IV. Should we upgrade one machine at a time so that desired production target wouldn’t
get hampered as extra Sinter could be procured from outside till all machines got
upgraded one by one?
V. Were any of the above steps actually right by looking in the long term?
VI. What about the mind-set of the workforce? If machines would be upgraded right
now, could the mind-set of workforce be changed?
VII. Was changing the mind-set of workforce important for Sinter Plant?
VIII. Which one would be better in long term? Upgrading machines or changing the
mind-set of the workforce of Sinter Plant.
After looking at the above options, the team decided that changing the mind-set of people
was more important than upgrading the machines of Sinter Plant, and it discussed this
important issue with higher authorities of Sinter Plant to find a way anyhow to solve the
issue as well as change the mind-set of the workforce. In other words, the team took this
challenge as a golden opportunity to kill two birds with one stone. After many days of
rigorous brainstorming the team found a way to solve the problem and the way was to
reduce the delay. Even at this point, the team faced many questions regarding the impact
of the solution which could be
1st. Would this solution help Sinter Plant to achieve the production target?
2nd. If this wouldn’t fulfill the target, what might happen to customer satisfaction?
3rd. Wouldn’t the credibility of Bara Steel Plant be at stake?
4th. If this solution would fail, then could the mind-set of workforce i.e., “Sinter Plant to
nahi sudhrega”, “Naya Plant na ane se iskaa kuch nahi hoga” be changed in future?
5th. Who knows if it would fail, workers would laugh at the leadership of the top
management and the grip of shop floor managers on workers would be lost. Even
because of the negative mind-set, workers would always have an excuse i.e., nothing
could be done without new machines.
The stakes were high, for which the executives planned to make sure that they would
make it happen because the situation was kind of it’s now or never. After careful
consideration, strategies had been crafted to turnaround the situation and the successful
implementation had been done with the help of 4R strategy, which helped immensely
in achieving the objective set by management of Sinter Plant.
This report tries to throw some light on how the management of a Sinter Plant
overcame from the problem of not achieving its production target. But, more
importantly, it tries to show the thought process of how the management tried change
the mind-set of the workforce by changing the way to achieve the desired objective for
long term benefit of its parent firm.

You might also like