Kayapalat - to a Resurgent

Sinter Plant

During H1 of the year 2013-14, Sinter Plant was not able to meet its production target for which
Bara Steel Plant had to purchase Sinter from outside the premises. Because of this, profitability of
Bara Steel Plant got hampered and the only reason for this reduced profitability was Sinter Plant.
Sinter Plant became the only bottleneck in the steel making process of Bara Steel Plant because
all other shops/departments involved in direct production of steel met their respective targets
successfully. The utilization of Sinter machines was only 76.8% of available hours. If we dive deep
into the matter, then we can say that had Sinter not been purchased from outside, Bara Steel Plant
would have been able to achieve only 3/4th of its production target for steel. The impact of the
problem was so severe that we might not have been able to claim ourselves as the largest producer
of steel in India, which is the pride of our parent firm, had it not been dealt immediately.
It was recommended that Sinter Plant needed to reduce delay so as to achieve the production
target successfully. Apart from this, there were also other three solutions which could have been
implemented, but reducing delay was less capital intensive as well as less time consuming for which
it became the best option as per our research and study. In other words, this was the optimized
solution which consumed fewer resources as compared other solutions and gave maximum benefits
to Sinter Plant, which in turn helped Bara Steel Plant to meet its production target without
procuring Sinter from outside. It increased utilization of Sinter machines from 76.8% to 97.6%
i.e., a 27% increase in utilization of machines, and further stretching this to 100% wouldn’t be
cost effective for which this was the highest utilization factor which we could achieve.

S intering is the process of


agglomeration of fine iron ore
particles into a porous and lumpy mass
was not meeting its production targets
on a regular basis for a few months.
And during these periods, each and
by incipient fusion. In Indian scenario, every other shop/ department of Bara
sintering is most common process Steel Plant was meeting its respective
of utilising iron ore fines as Blast production target set by its top
Furnace feed economically. Bara Steel management. Hence, it was clear that
Plant (BaSP) is equipped with 3 sinter Sinter Plant had become a bottleneck
strands (designed and commissioned in steel making process. It needed to be
by erstwhile USSR during 1970’s). It dealt as soon as possible so as to meet
had been observed that Sinter plant the demands of customers of Bara Steel

20
Plant. And this was the reason which There is hardly any improvement
prompted for the investigation in Sinter possible further in the weak link which
Plant. To investigate into the matter, a had been found and mitigated as per
problem statement had been defined this report because it already improved
which was as follows. the utilization parameter from 76.8%
to 97.6%. Further stretching this to
After coming to a definite problem 100% may not have much impact on
statement, first point was to collect past production. In other ways, it would
data to start analysis. After the collection not be cost effective to stretch further
of data, second thing was to find weak to achieve 100%. i.e., the limitation of
links with the help of analysis tools this report was utilization parameter
from the past data. Third thing was to couldn’t be stretched more than 97.6%.
do brainstorming with both blue collar The reason for this limitation was the
workforce (non-executives) as well as fact that it would increase significant
executives separately so as to decide amount of cost which in turn might
which weak links could be attacked to reduce the profitability.
get maximum output with minimum
cost. And at last, the final thing was to Before starting the investigation,
build pragmatic solutions to mitigate historical evidence had been tried to
the weak links optimally. These were find out, whether any such instance had
the four steps which had been taken occurred in the past, and if occurred,
to strategize as well as implement the had there any type of action been
solution. taken to solve such problem or not.
There were two such things for which
The scope of this report was limited to no such historical evidence had been
reduce delay only. The reason for this found. First thing was that in case, even
is the fact that the need at that point of if any group had taken the initiative
time was to get a quick solution which to solve the problem, the group had
should be robust and cost effective. not documented the findings and
And other ways of improvement were solutions for which there was no such
increase in efficiency and productivity report available in this matter. Second
of machines as well as to improve the thing was the fact that as there were a
capacity of machines so as to assist few instances when multiple shops /
Sinter Plant in achieving its production departments could not achieve their
target. But these needed ample amount respective production targets, for
of resource in terms of manpower and which this problem in Sinter Plant had
capital along with significant amount been camouflaged and hence, nobody
of time for which these things had been thought that this problem needed so
rejected for further consideration. Hence much attention. It came to limelight
the scope was limited to reduce delay. because of two reasons. One of the

21
reasons was Bara Steel Plant had to made so as to not to get carried away
purchase Sinter from outside especially in the mid-way while solving the
to meet the production target. Another problem. The vision statement should
reason was this time, only Sinter Plant not only be understood by each and
couldn’t meet its production target every employee, but also build the
whereas all other shops/departments confidence among each of them to turn
involved in direct production of steel the statement into reality for which
were able to meet their production after LAKSHYA, there came the fourth
targets, for which it grabbed the part i.e., SAKSHAM which explained
attention of management. All data about how the above things had been
had been collected from log books of planned to achieve. Then, after building
the required period, and information confidence among the workforce, the
regarding the ways to troubleshoot stage of KARMA came, which revealed
the problems had been gathered the process to achieve success and
through brainstorming sessions with threw some light on how 4R strategy
non-executives as well as executives had been implemented in Sinter Plant
in Sinter Plant. Before getting into the to make a vision statement into reality.
body of the report let us have a look at Then, it showed the results of all the
the flow chart as well as production above efforts and at last it provided the
target of Sinter Plant in Bara Steel Plant conclusion precisely.
which had been shown in Annexure I
and Annexure II respectively. SANKAT: Defining the crisis
• During H1 of 2013-14, 97.6%
The report followed a structural approach
fulfilment of monthly production
which was explained as follows.
target could have been achieved.
First of all, it explained about the crisis, But Sinter machines were running
which was named as SANKAT. This only for 51.25 hours/day (There
part elaborated two things. One was were 3 Sinter machines running in
how the problem caught the attention Bara Steel Plant for which ideally
of the management and the other the machines could run for 24
one was how the mind-set of the X 3=72 hours/day), resulting in
workforce had been changed by the top 76.8% utilisation of available hours.
management to assist in overcoming Reliability of age old equipment had
the problem. Then the second part become poor, and breakdowns were
was named as ANUSANDHAN i.e., common in the shop floor. Figure.1
the inquisition stage, where bottom- showed the fulfilment of for H1
up approach had been followed to get of the year 2013-14 production
the root cause analysis. After that, the target and Fig.2 showed the daily
third part was named as LAKSHYA, running hours of all the three Sinter
where a vision statement had been machines combined together for H1

22
of the year 2013-14. of H1 of 2013-14 had been depicted
• Frequent strand stoppages took toll in Figure 4.
15.00 12.7 13
11.6
110.0 106.2

-5 mm in sinter, %
104.3 10.4
103.1 9.17 9.44
Target fulfilment, %

10.00
100.0
93.5 5.00
89.1 89.4
90.0
0.00
1 2 3 4 5 6
80.0
1 2 3 4 5 6 Months
Months
Fig. 3: -5 mm Sinter, H1, 2013-14
Fig. 1: Fulfilment of Production Target, H1,
2013-14 35689

External Sinter. Tons


40000

30000 27309 25465


19947 19174 19456
60.00
Daily running hours

55.20 20000
55.00 52.23
51.00 51.60 10000
48.60
50.00
46.44 0
45.00 1 2 3 4 5 6

40.00 Months

1 2 3 4 5 6 Fig. 4: External Sinter, H1, 2013-14


Months
• It was not only the visible under
Fig. 2: Daily Sinter Machines’ Running
Hours, H1, 2013-14 performance of Sinter Plant, but
also lack of any visible solution to
on sinter quality; -5 mm in sinter break the vicious circle which made
were hovering at 11.05%, which was employees low on confidence.
being shown in Figure 3. “Sinter Plant to Nahi Sudhrega”,
• It was necessitated to arrange “Naya Plant na ane se iska kuch nahi
external Sinter for feeding Blast hoga” was the statement made by
Furnaces. In H1 2013-14, external most of the workforce during those
sinter of average 24500 tons/month bleak days which meant that Sinter
was consumed, which acted against plant won’t change for betterment,
the profitability and integration of nothing could be done until new
BaSP. The amount of external Sinter plant comes in. Lack of hope was
consumed in each of the 6 months more dangerous than challenging

1
In a year, ideally there should be 365 X 24 X 3 = 26280 hrs. available for running all the three machines.
But on an average 27 days had been taken for capital repair and other repairs for each machine in a Year.
So practically, time available for running for all three machines = (365-27) X 24 X 3 = 24336 hrs. / year
But all three Sinter machines are running for 51.25 hrs. / day on an average.
Hence total running time for all three Sinter machines = 51.25 X 365 = 18706.25 hrs. / year
i.e., utilization of machines = (18706.25 / 24336) X 100 = 76.8% of available time

23
reality, and all symptoms of chronic While considering all the above
distress were evident in Sinter Plant solutions, it was evident that if these
collectively. solutions would be implemented, then
• But it was the new GM (General the mind-set of the workforce couldn’t
Manager), appointed from customer be changed. And it was very important
department who saw the mounting to change the mind-set of the workforce
challenges as golden opportunities. by looking at the long term perspective
First and foremost action he took was of the plant. So, it was like a challenge
to instil confidence, “Jo nahi ho sakta which had to be converted into an
hai, WOHI TO KARNA HAI” i.e., the opportunity to kill two birds with one
thing which can’t be done, is what stone. i.e., one solution would be found
we have to do. He was the person out which could help Sinter Plant to
who tried to change the mind-set achieve its production target as well as
of the workforce of Sinter Plant in change the mind-set of workers (The
order to build confidence among mind-set of workers was “Sinter Plant
them so as to get the production to nahi sudhrega”, “Naya Plant na ane se
back on track. iskaa kuch nahi hoga”). This perspective
had been put up in front of the top
ANUSANDHAN: Inquisition stage management of Sinter Plant, after
which it was decided that an alternative
To delve deep into the problem, and
had to be found out to solve this matter.
prepare pragmatic solution, first of all,
This time, rigorous brainstorming
rigorous brainstorming sessions had
sessions had been conducted, and after
been done separately with executives as
a few days of hard work, a solution
well as non-executives to gather ideas
came, which was to reduce delay. The
to improve the utilization of Sinter
executives were ecstatic about this
machines so as to meet the production
solution, but there were also some
target of Sinter Plant. After several
risks involved with this solution. The
brainstorming sessions, it had been
risk was in case the solution failed to
found out that there were mainly four
achieve the desired outcome, then the
areas which could lead to improvement
workforce of Sinter Plant would think
in utilization of Sinter machines, if
that they were always right i.e., “Sinter
dealt carefully. These four areas of
Plant to nahi sudhrega”, “Naya Plant na ane
improvement were:-
se iskaa kuch nahi hoga”. And in future it
A. Increase the productivity of machines would be very difficult to change this
B. Increase the efficiency of machines mind-set, if the management would fail
(Reduce rejection of Sinter) by opting for the fourth option i.e., to
C. Capacity improvement of machines reduce delay. Again, the pros and cons
of this solution had been put up in
D. Reduce delays
front of the top management of Sinter

24
Table 1: Comparisons of available options thought of during brainstorming

Requirement Productivity Efficiency Capacity Delay


Capital High High High Low / Moderate
Manpower High High High High
Time More More More Moderate / More
Production Hamper Yes Yes Yes No
Change of Mind-set No No No Yes

Plant, after which the top management


51.25hrs. of
decided to opt for the fourth option daily running

as it was a situation like it’s now or


76.8% utilization of
never. And the management was fully available hours
97.6% External
committed to first craft a strategy which fulfilment of
production
Sinter in
BaSP Blast
target Furnaces
would be robust so that there wouldn’t
Low Yield
be any chance of failure. Hence, work
started on fourth option. 11.05% of -5mm
Sinter
To get a view of all the options, a small
Frequent Machine
comparison had been made which was Stop
shown in Table 1.
Fig. 5: Root cause analysis of non
Essentially the first step was to break fulfillment of monthly production target
the complex topic of Sinter Plant delay
into smaller parts to gain a better which were being put in Annexure III
understanding of it, through data and Annexure IV. The 5Ws are:
collection and analysis. Number of • Who filled out the check sheet?
interdependent causes acted behind (Operator, fitter, welder, shift I/c,
the poor performance and any delay
section I/c etc.)
in small parts ultimately led to overall
plant stoppage; hence root-cause • What was collected? (Start / stop
analysis was carried out. Figure 5 shows time for delay, reasons for delay)
the diagram. • Where did the collection take place?
(machine, room, section)
Data Collection
• When did the collection take place?
Data from every available source were
(hour, shift, day of the week)
collected, recorded and organized. Both
Quantitative as well as Qualitative data • Why did the data are collected?
were collected through customized (characterize and analyze sinter
check sheetanswering the Five Ws, machine delays)

25
Next level, inch arges of functional
37.83
areas e.g. Production, Mechanical, 40.00

Delay hours
30.25
and Electrical were required to fill 30.00
22.33
19.66 19.91
check sheet so as to enable 20.00
12.17
• To check the shape of the probability 10.00
distribution of a process 0.00

• To quantify defects by type 1 2 3 4 5 6


Months
• To quantify defects by location
• To quantify defects by cause Fig. 8 : Production Delay, H1, 2013-14
(machine, worker)
• To keep track of the completion of 200.00 179.58
steps in a multistep procedure (in
Delay hours 15.00 123.08 127.16
other words, as an SOP/SMP) 109.67
116.08

100.00 86.16
The occurring of delay due to each of
the factors had been shown below. 50.00

0.00
1 2 3 4 5 6
37.91
40.00 Months
31.66
29.08
30.00 Fig. 9 : Delay due to customer side, H1, 2013-14
Delay hours

23.08 21.08
18.66
20.00
120.00 107.09
10.00
100.00 84.16 76.08
Delay hours

0.00 80.00
1 2 3 4 5 6 60.00
39.16
Months 40.00
17.66
20.00 6.99
Fig. 6 : Electrical Delay, H1, 2013-14 0.00
1 2 3 4 5 6

Months
119.41 114.66
120.00
98.33 Fig. 10 : Delay due to supplier side, H1, 2013-14
100.00
Delay hours

74.66 81.66
80.00
55.91 Data analysis
60.00
40.00 Analysing data involved examining it
20.00 in ways that reveal the relationships,
0.00
1 2 3 4 5 6 patterns, trends, etc. that could be found
Months within it. By subjecting it to statistical
operations to find out what kinds of
Fig. 7 : Mechanical Delay, H1, 2013-14 relationships seemed to exist among

26
variables and to what level outcomes 500.00 100%
could be trusted. The basic objective
400.00
80%
was to get an accurate assessment in

Delay hrs.
300.00
order to better understand trends and 60%

200.00
its effects on Sinter Plant performance. 40%

100.00
The delay data so collected were first 20%
0.00
analyzed in graphical representation,
and Histograms were used to plot the Agency
density of data, and often for density
estimation: estimating the probability
Fig. 12 : Pareto analysis of Delays, June 2013
density function of the underlying
variable. BF (Blast Furnace) belt relationships underlying a particular
stoppage during July’13 is attached as problem. Application of the technique
Figure 11, showing the trend of small to determine high occurrence of
value but high frequency. mechanical and electrical delay is
presented in Figure. That encouraged
60 the troubleshooter to avoid assumptions
Frquency of stop

50
and logic traps and instead trace the
40
chain of causality in direct increments
30
from the effect through any layers of
20

10
abstraction to the root cause. The fifth
0
why suggested a broken process, which
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 was indicative of reaching the root-
Days cause level.
Fig. 11 : Histogram of daily machine delay The 5 Why technique had been depicted
due to BF belt stop, July 2013 below.
Problem : Mechanical & Electrical
Data from check sheets, plotted against
stoppages are very high
a Pareto chart, containing both bars and
a line graph. The chart highlighted the 1. Why? Frequent breakdowns,
most important among a (typically large) Machine reliability poor
set of delay reasons. Hence, the most 3. Why? Depleting manpower,
common sources of delays, the highest preventive maintenance limited
occurring type shown in Figure 12, or 2. Why? No condition based
the most frequent reasons for customer maintenance of equipment
complaints could be identified. 4. Why? Inspection schedule not
Besides the quantitative analysis, 5 properly maintained
why’s technique was also applied 5. Why? Poor house-keeping makes
to explore the cause-and-effect inspection impossible

27
LAKSHYA: Formulating vision communicated. The vision statement is
statement as follows.
After analysis of the delay situation, it Zero Delays
was evident that production target could
Zero Abnormalities
not be met with such high occurrence
of delays. So, it was clear that if delay Perfect Quantity and Quality
could be reduced then production
target could have been met in future. SAKSHYAM: Capacity building
And, if delay could be minimized each stage
and every time, then production target “If you want to build a ship, don’t drum up
would not have been missed even for the men to gather wood, divide the work and
a single time due to delay. Hence, to give orders. Instead, teach them to yearn for
maintain the process for long term, it the vast and endless sea.”
was needed to make a vision statement, – Antoine de Saint-Exupery
so that even after getting success for a In fulfilling the targets and realizing
few occasions in reducing delay to the the vision, first step was taken towards
optimum level, people wouldn’t forget capacity building. Building capacity,
to maintain or get carried away by that it could not only turnaround Sinter
other responsibilities. Hence, a vision, Plant by then, but also during lasting
quite simply was being made and future too.

Fig. 13 : Loss in productivity due to unplanned delays

28
Communication Brain storming
Communication initiatives had been Acting hands on the equipment,
taken to focus Sinter Plant team to employees could be the best judge of
achieve the overall objectives of their problems. Brainstorming sessions
department and organization as a were organized. Concerned people
whole. Objectives were broken down including executives and workforce
to identifiable targets in the audience were called, the situation/challenge
groups’ sphere of influence. Variety put forth and questions e.g. “HOW
of communications modes e.g., CAN WE?” were asked. Letting the
Public display boards in each section, possibilities come forward, discussed
presentation by sectional incharges about pros & cons, effective solutions
and closed group interaction were could be implemented on reality.
implemented, to hard hit all people
down the line.
In addition, top management of BaSP
e.g., CEO (Chief Executive Officer) and Excellence
ED (W) (Executive Director (Works)) Idealistic, Functionality,
Philosophy Space/Time/Interface,
started to visit the shop periodically, Complete problem solving
interacted directly with employees and Method process
Trend Analysis, Best Practice,
their concerns. Tool SOP, SMP, Knowledge Sharing

• Communicatingcrossingthebarrier:
Fig. 15 : Brainstorming to find out the
Informal communications at job possible solution of problems
loca tions, to share concerns
• Cross border communication: Morale boosting
Customers, suppliers and services Chronic under-performance mostly
units of BaSP were invited to attend eroded confidence of employees and
formal communication meetings attitude of no hope was evident. So the
and participate can–do approach was first traded to all
of Sinter Plant. Through each and every
14393
14194
interaction,pessimism of the future,
14194 confidence on employees, trust and
12419
12300 mutual belief were traded.
12000 12000
“No matter how bad things got, no matter
how anxious the staff become, the commander
Sep Oct Nov Dec Jan Feb Mar
has to preserve optimism in himself and his
men”
2013 - 14
– Gen. D.E. Eisenhower, Supreme Commander,
Allied Expeditionary Force, WW II
Fig. 14 : Daily Sinter production target (in Tons)

29
Instilling Confidence upon i.e. Cleaning Program Checklist
front line managers by assigning
1. Cleaning main body of machine,
greater responsibility created
checking and tightening bolts
exceptional positive spirit. One-to-
one communication with senior 2. Cleaning ancillary equipment,
management level and problem facing checking and tightening bolts
head-on inspired all to Win. 3. Cleaning lubrication areas before
performing lubrication
KARMA: Application stage
4. Cleaning around equipment
To attain the goal, emphasis was
5. Treating the causes of dirt, dust,
given to Preventive Maintenance i.e.
leaks, and contamination
to treat causes of breakdowns before
they actually happen. In realizing the 6. Improving access to hard-to-reach
goal, 4R strategy i.e. Retrenchment, areas
Repositioning, Reorganisation and 7. Developing cleaning standards
Renewal were applied.
“This hand-on approach also increased
Retrenchment the person’s respect for the machine. This
The Retrenchment strategy included process of cleaning, seeing, touching, and
respecting the machine was essential to
wide-ranging short-term actions, aimed
increase reliability”
to stabilize the delays and to work
against the root causes. – GM, Sinter Plant
Besides, keeping overall cleanliness
Improve upon House keeping
of area was another priority, scrap
House-keeping was outsourced section- removal and peripheral cleaning was
wise, with specific mention to the quantity carried out in massive scale. This could
in the payment terms. On contract to the be ensured by systematic elimination
earlier practice of private supervision, of sources of dirt and clutter such
monitoring by Sinter Plant employees as misplaced trash containers, lack
was introduced. Cleaning being a hands- of proper storage, broken tools, bad
on activity, people supervising during ventilation, inadequate lighting etc.;
cleaning the machines had the best which ultimately helped in spreading
chance of detecting any failure. As they positive mood and morale among
touched and looked at the machine, workforce.
loose bolts shouted to them. Part of the
cleaning process was looking for ways Vigorous inspection
to make cleaning easier or maintenance All three key aspects of an inspection
avoidable. In some cases, the source of i.e. inspector competence, reliability of
dirt could be isolated to reduce the need inspection and quality of information
for cleaning. used and created by the inspector

30
were carefully enhanced. Inspector preventative maintenance practices
competence in terms of skill, knowledge focusing on the entire equipment life
and ability to assess risk; to recognize a cycle was established. Implemented
defect, while categorizing and reporting team-based (including all departments
defects reliably and quickly were e.g. operation, mechanical, electrical,
ensured. Inspectors visually inspected and instrumentation) activities aimed
the item and, where relevant listened to at the organization-wide goal of zero
it, felt it and possibly smelt it. Inspection
defects and zero breakdowns. A work
data were recorded and made accurate
order system and equipment data base
comparisons from one inspection to
maintained, to monitor and support
the next, thereby allowing defects to
be monitored and either repaired, or continuous equipment improvement.
replaced in an organized manner. Also it was ensured that maintenance to
treat root cause and not the symptom,
Besides, 3-tier inspection, by operator,
so that maintenance personnel could be
supervisor and sectional incharges were
moved from the “fire-fighting” mode to
introduced, which could seal any possible
the prevention mode. Daily 2-3 hours
leakages in single layer of inspection.
planned shutdown and immediate
Autonomous maintenance practice liquidation of defects identified
Reliability based maintenance system (Schedule for monitoring is attached in
utilizing proactive, predictive, and (Annexure V) was introduced.

Reacting Responding Prevention


Detecting Continous Continuous Rectification of
Detecting
Equipment Improvement improvement Reasons
Reasons for

Noise Vibration Deformation Loose Align

Heating Tightening
Lack of
Wear & Tear
lubrication Greasing
Misalignment
Cleaning
Jam Corrosion
Equipment leading Equipment Not Keep
to Filure 100% Equipment
T 100%

FIX IT FIX IT MAINTAIN IT

Fig. 16 : Autonomous maintenance parctic

31
Step Process name Activities
1 Clean & inspect CGT (Cleaning, greasing, Tightening)
2 Eliminate problem sources and Correction of dirt sources, preventing spillage,
inaccessible areas improving accessibility and shorten time
3 Draw up cleaning and greasing Standards and schedule for CGT well
standards documented and reviewed periodically
4 Conduct general inspection Skill training and enhancing capabilities
5 Conduct autonomous inspection Standard check sheets and standards for
inspection prepared and followed
6 Standardise through visual Standardise all work process:
workplace management • Work area material flow
• Data recording methods
• Spare management
7 Implementing autonomous Improvement in everyday practices, maintain
equipment management reliable MTBF (mean time before failures) data,
analysis and using it for further improvement

Repositioning
Repositioning is the strategy, to move
people for improved effectiveness and Place Time
incorporation of various managerial
and operational changes.

Job defining and placing people Mind


accordingly
Job definition is the list that an employee
had to do with a position. The skills Fig. 17 : Right People, Right Job, Right Time
required and expectations in terms
of quantified outcomes were clearly Gap analysis and revival strategy
spelled out. Accordingly, employees Analysing the Gap i.e. comparison
were relocated as per requirement. of actual performance with potential
Some key position demanded people to performance pointed areas where best
develop future plan and projections of use of available resources was missing.
needs. Efficient utilization of available It involved determining, documenting,
resources could improve collective and approving the difference between
performances. requirements and current capabilities.

32
Identify core Internal External data Analysis Change
issues baseline data collection Implementation

Issues Process Benchmark Compare and Implementation


overview questionnaire contrast plan
• Customer
demand Current benchmark
• Performance measures
data
gap Other
• Problem areas departments

• Defined • Process flow • Other SAIL • Gap • Plan to close


benchmark mapping units • Process gap
area • Validate • Process reengineering • Actions
• Overview of • Target sister analysis, opportunities • Recalibrate
key process departments performance • New benchmarks
• Selected • Short term assessment o Flows • Additional
performance operational and measures o Policies analysis
measures improvements o Procedures
• Implementation
plan

Fig. 18 : comparison of actual performance with potential performance

Gap analysis also used to compare Technical interventions for recurring


existing processes to processes problems
performed elsewhere, such as those For system reliability study and
obtained by benchmarking. In this failure analysis, first Failure Mode
usage, each process was compared side- and Effects Analysis (FMEA) was
by-side and step-by-step and actions applied. It involved reviewing as
planned for differences (Annexure VI). many components, assemblies, and
Step Description subsystems as possible to identify failure
1 Existing process identified modes, and their causes and effects. For
each component, the failure modes and
2 Existing outcome identified
their resulting effects on the rest of the
3 Desired outcome identified
system were recorded in specific FMEA
4 Process to achieve desired worksheet (Annexure VII). It helped to
outcome identified identify potential failure modes based
5 Identify the Gap and document it on experience with similar products
6 Develop means to fill the Gap and processes - or based on common
7 Develop and prioritize physics of failure logic. And through
requirements to bridge the Gap this analysis, frequent failure of hot

33
screen could be identified. Accordingly,
technical interventions e.g.
• Heat shield modification
Value Value Creation
• Additional grease station for vibrator Proposition How will you work
What will your with your customers
• Changing grease quality to servic do? and supplier to
creat and deliver the
withstand heatwere implemented service?
as per in-house design
“This power of thinking out and executing Value Capture
is initiative, and freedom to propose and to How will you ensure that you
benefit from creating the
execute belongs too in a way, to initiative. service?
The collective initiative of all employees
represents a great source of strength of
businesses. Henri”
Fig. 19 : Development of value creation point
– Henri Fayol
of uninterrupted supply in required
Applying JIT in Spare Management quantity, flux and fuel crushing section
Applying Just-In-Time (JIT) in spare was given target to maintain crushing
management i.e.,‘the exact item needed, index respectively at 80 & 85%. Each
when it is needed, and in the quantity section was defined as customer and
needed’. Weekly projection of spare supplier to another, and ought to deliver
demand and managing supply chain to value to them. It was also a goal clearly
ensure required items to be available on tied to the system output, a collective
site close to when they were needed and overarching goal that subsumed
not held in inventory for a lengthy time. functional goals and depended upon
Extensive planning and scheduling concerted efforts of people at all levels.
requiring highly responsive production It created a super-charged atmosphere
and supply systems were introduced. in Sinter Plant whole, with people knew
what exactly their role in quantitative
Reorganization terms and wanted to fulfill them. There
The reorganization strategy introduced was a buzz in the workplace and a number
some managerial changes in Sinter of small initiatives in every section began
Plant as: to have a cumulative effect in terms of
better coordination and performance.
Each section as value creation point
Here goal of each section clearly stated Teamwork at its best
so that every employee, working in any “Talent wins games, but teamwork wins
section could relate to it. For example, championships”
stock bin sections were given targets - Michael Jordan

34
The Integrated Team Development Framework

Performing
Norming
Storming
Forming

Task
Individual No
Opt Out? Agree? Yes
Group
Environment

No
Yes Storming

Norming

Norming
Storming
Understanding & acceptance
of issues associated with the
basic element by team
Members.
Yes
Acceptance and understanding
of issues associted with the
Agree?
basic element by some team
members.

No
Non-Shared assumptions about
issues associated with the basic

Fig. 20 : The integrated team development framework

Conventional concept of teamwork Renewal


development i.e. Forming, Storming, Renewals, strategy pursuing long-
Norming and Performing were term actions were supposed to end in
implemented in all new cross-functional a successful managerial performance.
(Goal Congruence) paradigms. Enabling The first step was analysing the existing
factors of teamwork i.e. focusing on the structures within the organisation.
goal, placing the right people, enabling This examination lead to enhancing
to working together were all provided innovative core competencies, concluded
on one hand; on the other teams were in an increase of knowledge and a
continuously challenged with one stabilization of the organisation value.
another. Improving Cross functional
collaboration conflicted at a number of Improve upon core competencies of employees
levels both up and down the hierarchy Core competency was the specific factor
and across functions andwork groups. that was seemed central for long term
In safety aspect, daily 10 minute safety sustainable performance. Technical/
talk before job distribution (by sectional subject matter know-how, a reliable
in-charges) and weekly safety meeting process and/or close relationships with
(by General Manager himself) instilled customers and suppliers were the core
a culture of safe working. competencies targeted for improvement.

35
Knowledge
Performance Skill up renewal
enhancement gradation

Improving core
competency
Mentoring Delegation
Resource
provision

Fig. 21 : Fish Bone diagram for improving core competency

Shown in fig. 21. For that, subjective Promoting innovative culture


delegation of authority to employees Challenging target demanded
and committing them resources were creativity, i.e. viewing existing facts
implemented. from a new perspective allowed
Nurturing young leaders individuals to come up with ingenious
Nurturing young leaders through ways to solve seemingly impossible
Encouraging, Involving & Enabling problems. Experimentation based on
front line managers paid excellent reverse logic was encouraged, which
dividends not only in enhanced ultimately lead shaping many ideas at
decision making speed, but also competitive cost. Introduction of a ‘Flap
boosted confidence in long term. gate arrangement’ in sinter transfer belt
Shift managers were empowered to was classic example of such realistic
communicate with customer & supplier innovation, which actually reduced
department and resolve issues delay due to BF belt substantially.
quickly. Similarly quick shutdown for
Development of human resources
smaller maintenance jobs was
authorized to shift level executives. “Workshop on Sintering Technology”
was organized in Sinter Plant seminar
room, and shift level employees who
Degree of Empowered Lower

Enabling lower
management to
were otherwise left out in any such
take bigger training programs were covered. Basic
Involving lower
management with
objective was to update knowledge on
 Get closer to customer
more responsibility  Get closer to Supplier sinter making and disseminate latest
Leadership

Encouraging lower  Increase service delivery


management to  Innovate continuously advancements in the same. Interactions
take more active  Enhance efficiency
and discussions on problems and their
BaSP benefit possible solutions were organised, which
Fig. 22 : Enable, Involve, Encourage lower helped in confidence building of each
leadership one.

36
Reaping the results
• Drastic reduction in internal delay i.e. due to mechanical, electrical and production
stoppages could be achieved which had been shown in figures 23, 24, and 25
respectively.

Fig. 23 : Delay due to electrical stoppages, FY 2013-14

Fig. 24 : Delay due to mechanical stoppages, FY 2013-14

Fig. 25 : Delay due to production stoppages, FY 2013-14

37
• Delay due to BF belt stoppage reduced by around 50% (shown in Figure 26

180

130

80

30

Fig. 26 : Delay due to BF belt stoppage, FY 2013-14

• Supplier side delay also reduced substantially, to near ZERO in March 2014
(Figure 27)

Fig. 27 : Delay due to supplier side, FY 2013-14

• Daily running hours could be improved up to 58.23 hours during H2, 2013-14 while
68 hours of running was realised on daily basis, which was all time record (Figure 28)

Fig. 28 : Daily average running hours, FY 2013-14

38
• 101.5% fulfilment of monthly production target could be achieved in FY 13-14
(Shown in Figure 29)

Fig. 29 : %age of Fulfilment of production target, FY 2013-14

• Requirement of external sinter in BaSP reduced to 3893 tons/moth only, thus


improving productivity and overall cost efficiency of BaSP
• Operational stability as achieved could improve sinter quality. -5 mm in sinter
reduced by 20% (Shown in Figure 30)

Fig. 30 : 5 mm Sinter, FY 2013-14

Conclusion
This case study outlined the turnaround of an age-old sinter plant, from state of acute
distress to exceptional performance. Root causes for deterioration were identified
and analysed. The vision formed and well-marketed to have ‘Zero Delays’. First steps
taken were morale boosting and building capability of workforce. Then 4R strategy
was carefully designed and implemented in Sinter Plant. As a result, more than 100%
of targets could be achieved, just within 6 months.
The Steely Glitter in Eyes of Each Employee tells about the RESURGENT SINTER PLANT

39
References
1. www.LCE.com
2. www.cimaglobal.com/insight
3. www.globalturnaround.com
4. www.globalturnaround.com
5. www.insol.org
6. www.instituteforturnaround.com/default.asp
7. www.tma-uk.org
8. http://www.amazon.com/Autonomous-Maintenance-Seven-Steps-Implementing
9. http://www.implement-lean-manufacturing.com
10. www.tpmonline.com
11. http://bokarosteel.com/
12. Piotrowski, J., April 2, 2001. “Pro-Active Maintenance for Pumps”, Archives, February 2001,
Pump-Zone.com [Report online].
13. Arunagiri. P. & Babu, Dr A.Gnanavel, “Review on Reduction of Delay in manufacturing process
using Lean six sigma (LSS) systems”, International Journal of Scientific and Research Publications,
Volume 3, Issue 2, February 2013 1 ISSN 2250-3153
14. “Root Cause Analysis For Beginners” by James J. Rooney and Lee N. Vanden Heuvel
15. Gupta Desh & Sathye Milind, “Financial Turnaround of the Indian Railways: A Case Study”,
Faculty of Business & Government , University of Canberra, Canberra, Australia

40
Teaching Notes
KAYAPALAT – to a Resurgent Sinter Plant
The case had been prepared after the implementation of a strategy to assist Sinter
plant in achieving its production target. It had been observed in H1 of the year 2013-14
that Sinter Plant was not able to meet its desired production target, but other shops /
departments which were involved directly with steel production, met their production
targets successfully for which Sinter Plant became the bottleneck in Steel making process
for Bara Steel Plant. A thorough research revealed that Sinter machines were being used
only for 76.8% of its available running hours. After getting this clue, the job was to how
to solve this problem. Various questions could be framed at this juncture which were:
1. What were the reasons for which utilization factor for machines was only 76.8%?
2. Was this the only reason for which production target had not been met or else apart
from this, there was/were other reason/s also, which was/were significant?
3. Was there any raw material issue like the raw materials procured for Sinter Plant was
having low quality during this period, for which it was like garbage in, garbage out?
4. If utilization factor for machines being 76.8% was the only reason, then what were the
causes for this problem?
Then, after having brainstorming sessions with executives as well as with non-executives,
the team found various ways to solve the issue of utilization factor to be only 76.8%.
These were:
• Increase efficiency of machines
• Increase productivity of machines
• Increase capacity of machines
Apart from these three solutions, one insight came to the team was that the mind-set of
people working in Sinter Plant i.e., “Sinter Plant to nahi sudhrega”, “Naya Plant na ane
se iskaa kuch nahi hoga”. This was the general sentiment among the workforce of Sinter
Plant. At this point various questions could come to any leader’s mind:
I. Should we solve all the three or only one or else any two among these options?
II. Should we upgrade all the three machines simultaneously and during these periods,
procure Sinter from outside temporarily?

Or else Stop the production during these periods, and start capital repair in all other shops/
departments so that all our guns will blaze after a few days even with high production
capacity to mitigate the production loss occurred during these days?
III. By following Step-II could we satisfy our customers (Were they ready to wait for that
period or else did we have enough inventories to satisfy their respective demands
on time?)?

41
IV. Should we upgrade one machine at a time so that desired production target wouldn’t
get hampered as extra Sinter could be procured from outside till all machines got
upgraded one by one?
V. Were any of the above steps actually right by looking in the long term?
VI. What about the mind-set of the workforce? If machines would be upgraded right
now, could the mind-set of workforce be changed?
VII. Was changing the mind-set of workforce important for Sinter Plant?
VIII. Which one would be better in long term? Upgrading machines or changing the
mind-set of the workforce of Sinter Plant.
After looking at the above options, the team decided that changing the mind-set of people
was more important than upgrading the machines of Sinter Plant, and it discussed this
important issue with higher authorities of Sinter Plant to find a way anyhow to solve the
issue as well as change the mind-set of the workforce. In other words, the team took this
challenge as a golden opportunity to kill two birds with one stone. After many days of
rigorous brainstorming the team found a way to solve the problem and the way was to
reduce the delay. Even at this point, the team faced many questions regarding the impact
of the solution which could be
1st. Would this solution help Sinter Plant to achieve the production target?
2nd. If this wouldn’t fulfill the target, what might happen to customer satisfaction?
3rd. Wouldn’t the credibility of Bara Steel Plant be at stake?
4th. If this solution would fail, then could the mind-set of workforce i.e., “Sinter Plant to
nahi sudhrega”, “Naya Plant na ane se iskaa kuch nahi hoga” be changed in future?
5th. Who knows if it would fail, workers would laugh at the leadership of the top
management and the grip of shop floor managers on workers would be lost. Even
because of the negative mind-set, workers would always have an excuse i.e., nothing
could be done without new machines.
The stakes were high, for which the executives planned to make sure that they would
make it happen because the situation was kind of it’s now or never. After careful
consideration, strategies had been crafted to turnaround the situation and the successful
implementation had been done with the help of 4R strategy, which helped immensely in
achieving the objective set by management of Sinter Plant.
This report tries to throw some light on how the management of a Sinter Plant overcame
from the problem of not achieving its production target. But, more importantly, it tries
to show the thought process of how the management tried change the mind-set of the
workforce by changing the way to achieve the desired objective for long term benefit of
its parent firm.