RFI Transmittal

Perkins Eastman DC | One Thomas Circle NW, Suite 270 Washington DC 20005 United States

PROJECT: Forest City: Yards West: Parcel I DATE SENT: 5/25/2021


71220.00.J

SUBJECT: RFI 009 (General - Elevation RFI ID: RFI#0009


Clarification)
TYPE: RFI TRANSMITTAL ID: 00550

PURPOSE: Answered VIA: Email

QUESTION: Question from Laura Kuhn HITT Contracting, Inc. on Tuesday, May 25, 2021 at 10:27 AM EDT
Per the attached correspondence from March 2020, elevation 0'-0" noted in the Contract Documents
equates to 15.00'
DCDPW -- please confirm.

SUGGESTION:

ANSWER:
Response (Answered) from: Carmen Chan (Perkins Eastman DC)
Remarks:
PEDC RESPONSE:

THE PROJECT ELEVATION AT 0'-0" IS CONFIRMED TO EQUAL 15.00' DC DPW. FOR REFERENCE,
THE BUILDING HEIGHT MEASURING POINT AS INDICATED IN THE CONTRACT DOCUMENTS AT
PROJECT ELEVATION 1'-8" IS EQUAL TO 16.67' DC DPW.

C.CHAN / 05.25.2021

FROM

NAME COMPANY EMAIL PHONE


Perkins Eastman C.Chan@perkinseastma +1 202 971
Carmen Chan
DC n-dc.com 4966

TO

NAME COMPANY EMAIL PHONE


Laura Kuhn HITT Contracting LKuhn@hitt-gc.com (703) 677-6938

DESCRIPTION OF CONTENTS

QTY DATED TITLE NUMBER SCALE SIZE


009-General-
1 5/25/2021
Elevation_Clarification.pdf

COPIES:

Laura Kuhn (HITT Contracting)


Ray Matula (HITT Contracting)
Anthony Fusco (Perkins Eastman Architects)
Brett Swiatocha (Perkins Eastman Architects)

Page 1 of 2
RFI Transmittal
DATE: 5/25/2021
ID: 00550

Francisco Waltersdorfer
Joe Jewell (Brookfield Properties (WDC))
Meghan Davis (Brookfield Properties)