Document Transmittal

Transmittal Number: E0001-HIT-JBS-CT-00003 Issue Date: 9-Feb-22


TO: JACOBS ENGINEERING GROUPS FROM: HITACHI RAIL STS (HIT)
Abu Dhabi Abu Dhabi

CC: N/A

CONTACT: Please direct any enquiries relating to these documents to Document Controls by post at the above address, by e-mail to
christopher.bonifacio.ext@hitachirail.com or by phone on 0544285352.

DOCUMENTS

Doc. Reference No. Revision Description Package Status Format

00 2S/2B for Inspection PDF


E0001-S02-GQC-IR-20187 Cable Trench Excavation for Buried MV Cables Connection to ISS

00 2S/2B for Inspection PDF


E0001-S02-GQC-IR-20188 Cable Laying & Pulling for Buried MV Cables Connection to ISS

00 2S/2B for Inspection PDF


E0001-S02-GQC-IR-20189 Backfilling up to Cable covering Tiles for Buried MV Cables Connection to ISS

00 2S/2B for Inspection PDF


E0001-S02-GQC-IR-20190 Laying of Warning Tape for Buried MV Cables Connection to ISS

DOCUMENT SUBMITTED ISSUE MEDIA SUBMITTED FOR

Procedures Contractual ✘ e-mail Review and Comments - FR


Reports Forms CD ✘ For Implementation/Action - FIA
Specifications ✘ Full Size Prints As Requested - AR
Correspondence
Certifications Drawings Hard Copies For Information - FI
Standards Other(s) Other(s) For Approval/Acceptance - FA

Acknowledgement Required:
CONFIDENTIALITY: The information enclosed may only be used
on work relating to the Etihad Railway Project.
Yes ✘ No

Please acknowledge receipt of this document and the conditions for their use by returning a signed copy of this transmittal by email/Fax
to the CONTACT above.

ISSUED BY: HITACHI RAIL STS (HIT)

RECEIVED BY:
Print Name: Date: Signed:

E0001-HIT-JBS-CT-00003 Page 1 OF 1