Professional Documents
Culture Documents
HYSD bar including 5% overlap and wastage =1.05 MT [Ref. Sl. No. 12.40 of Item & Material , Page No. 52 of NH PW(R)D Schedule 2019-20]
i)Basic Price of HYSD bar including 5% overlap and wastage =1.05 MT ( Rs.) 50280.15 /MT =Rs. 52794.16 /MT
Complete rate
a) Material ,Labour charges, T&P, Machinery etc.[ Ref. Sl. No.10A of chapter -
2, page-76 of N.H Schedule of Rates 2019-20 ]
=Rs. 439.90 /No.
Total Rs. 439.90 /No. ...(a)
b)Overhead Charge @ 10% on(a+b)of Rs. 439.90 43.99 /No. ...( b )
Total Rs. 483.89 /No. ...(a+b)
c)Contractor's profit @ 10%on (a+b+c) of Rs. 483.89 48.39 /No. ...(c)
Total Rs. 532.28 /No. …(a+b+c)
d)Labour welfare Cess @ 1% on (a+b+c+d) of Rs. 532.28 5.32 /No.
Total Rs. 537.60 /No.
Dismantling of Cement Concrete Grade M-15 by Mechanical Means
Complete rate
a) Material ,Labour charges, T&P, Machinery etc.[ Ref. Sl. No.4(i)II(A) of
chapter - 2, page-72 of N.H Schedule of Rates 2019-20 ]
=Rs. 410.30 /cum
Total Rs. 410.30 /cum ...(a)
b)Overhead Charge @ 10% on(a+b)of Rs. 410.30 41.03 /cum ...( b )
Total Rs. 451.33 /cum ...(a+b)
c)Contractor's profit @ 10%on (a+b+c) of Rs. 451.33 45.13 /cum ...(c)
Total Rs. 496.46 /cum …(a+b+c)
d)Labour welfare Cess @ 1% on (a+b+c+d) of Rs. 496.46 4.96 /cum
Total Rs. 501.42 /cum
Dismantling of Prestressed / Reinforced cement concrete grade M-20 & above by Mechanical Means
Complete rate
a) Material ,Labour charges, T&P, Machinery etc.[ Ref. Sl. No.4(i)II(B) of
chapter - 2, page-73 of N.H Schedule of Rates 2019-20 ]
=Rs. 719.90 /cum
Total Rs. 719.90 /cum ...(a)
b)Overhead Charge @ 10% on(a+b)of Rs. 719.90 71.99 /cum ...( b )
Total Rs. 791.89 /cum ...(a+b)
c)Contractor's profit @ 10%on (a+b+c) of Rs. 791.89 79.19 /cum ...(c)
Total Rs. 871.08 /cum …(a+b+c)
d)Labour welfare Cess @ 1% on (a+b+c+d) of Rs. 871.08 8.71 /cum
Total Rs. 879.79 /cum
Dismantling of Brick / Tile work in Cement Mortar
Complete rate
a) Material ,Labour charges, T&P, Machinery etc.[ Ref. Sl. No.4(ii)B of chapter
- 2, page-73 of N.H Schedule of Rates 2019-20 ]
=Rs. 295.50 /cum
Total Rs. 295.50 /cum ...(a)
b)Overhead Charge @ 10% on(a+b)of Rs. 295.50 29.55 /cum ...( b )
Total Rs. 325.05 /cum ...(a+b)
c)Contractor's profit @ 10%on (a+b+c) of Rs. 325.05 32.51 /cum ...(c)
Total Rs. 357.56 /cum …(a+b+c)
d)Labour welfare Cess @ 1% on (a+b+c+d) of Rs. 357.56 3.58 /cum
Total Rs. 361.14 /cum
Removing of all types of Hume Pipe
Complete rate
a) Material ,Labour charges, T&P, Machinery etc.[ Ref. Sl. No.(ix)C of chapter -
2, page-74 of N.H Schedule of Rates 2019-20 ]
=Rs. 427.90 /m
Total Rs. 427.90 /m ...(a)
b)Overhead Charge @ 10% on(a+b)of Rs. 427.90 42.79 /m ...( b )
Total Rs. 470.69 /m ...(a+b)
c)Contractor's profit @ 10%on (a+b+c) of Rs. 470.69 47.07 /m ...(c)
Total Rs. 517.76 /m …(a+b+c)
d)Labour welfare Cess @ 1% on (a+b+c+d) of Rs. 517.76 5.18 /m
Total Rs. 522.94 /m
Cost of different size of stone materials (Including Cost of Loading, Unloading, Stacking and Carriage) :
Cost of Pakur stones of different sizes from Burdwan Railway Stack yard
Lead of Carriage
Burdwan railway stackyard to ch. 560.450 of NH-2 = 5.200 Km.
ch. 560.450 to ch. 520.000 of N.H-2 = 40.450 Km.
Total distance from Burdwan railway stackyard to working zone of N.H-2 = Total = 45.650 Km.
Cost of Loading, Unloading, Stacking and Carriage of hard stone materials per Cum. [ref. Sl. No. 1.1(a) & 1.4(c) of Chapter - 1,
Page No. 68 of NH PW(R)D Schedule 2019-20]
Carriage for Stone Agg.
(i) Surfaced Road 45.65 Km. @Rs.11.10/Km. Rs. 506.72
Total 2158.72 2158.72 2218.72 2178.72 2268.72 2288.72 1938.72 1608.72 1588.72 798 625
Cost of Coarse sand [ref. Sl. No. a of Table- I (PART-A), Page No. 275 of NH PW(R)D Schedule 2019-20]
Cost of Cement
(ref. Sl. No. 1(A) of Annexure-I , Page No.
283 of NH PW(R)D Schedule 2019-20) 5873 TON
RATE ANALYSIS OF BITUMEN (FROM HALDIA.)
Carriage Cost( VG-30, VG-40, Emulsion) including loading, unloading & stacking
Working distance between ch. 520.103 and ch.584.929 of N H-2 = 584.929-520.103= 64.826 km.
Mid point between ch. 520.103 and ch. 584.929= (584.929-520.103)/2= 552.516 km.
Source:- Haldia
Haldia refinary to Palsit ch. 584.929 189.000 km
Page 17 of 25
Sl.No Description of Work Unit Quantity Rate Amount Remarks
Basic cost for 50 nos pillar 153,157
Add price escalation @ 10% 15,315.72
Cost including escalation 168,473
Add GST @ 12% 20,216.75
Total cost for 50 nos 188,690
cost for 1 no pillar 3,773.79
Page 18 of 25
Sl.No Description of Work Unit Quantity Rate Amount Remarks
Pathway 1.5 mtr width with interlocking paver
block 60mm thick with sand cushioning 30mm
D RM 1700 -
thick over 150mm thick PCC 1:3:6 thick over
150mm sand/ clinker/ stone dust filling
Pathway 1.5m with paver block 60mm with sand
1 Sqm 2550.000 784.95 2,001,610
30mm thick
2 Sand filling of 150 mm thick Cum 382.500 1,043.79 399,250
3 PCC-M-15 below paver block Cum 382.500 4,994.81 1,910,513
Basic cost for 1700 RMT 4,311,373
Add price escalation @ 10% 431,137.29
Cost including escalation 4,742,510
Add GST @ 12% 569,101
Total cost for 1700 RMT 5,311,611
cost for 1 RMT 3,124
E RCC Gate Nos 3
1 Excavation Cum 17.328 165.45 2,867
2 PCC-M-15 Cum 1.625 4,994.81 8,114
3 RCC-M25 - found. Cum 7.680 7,539.79 57,906
4 RCC-M25 --sub-structure Cum 10.800 8,720.57 94,182
5 Steel MT 1.848 75,075.37 138,739
6 Dismantling RCC Cum 18.480 879.79 16,259
Basic cost for 3 nos 318,067
Add price escalation @ 10% 31,806.65
Cost including escalation 349,873
Add GST @ 12% 41,984.78
Total cost for 3 nos 391,858
cost for 1 no 130,619
F Indian Army Banner No 1 -
1 Banner Sqm 12.000 19,475.26 233,703
Add price escalation @ 10% 23,370.31
Cost including escalation 257,073
Add GST @ 12% 30,848.81
cost per No. 287,922.24
Page 19 of 25
Annexure-A
EVI Cost
Sl. No. Description of Work Unit Quantity Cost per RM Amount (Rs.) Remarks
(A) Cost of land for transfer of Defence Land = Rs. 15.48 crore
(B) Equivalent cost of Brick Boundary Wall with RCC Pillar = Rs. 17,897/RM
(C) Length of Security Boundary Brick Wall with RCC Pillar in respect of equivalent land value = Rs. 8.65 Km (approx.)
Annexure-B
Total 20,826,736.23
Total 61,116,839.86
E & M Infrastructure
Sl. No. Description of Work Unit Quantity Total Cost Amount (Rs.) Remarks
Total 4,259,732.29
Communication Infrastructure
Sl. No. Description of Work Unit Quantity Cost per RM Amount (Rs.) Remarks
Total -
Summary of Cost for Reconstruction of Damaged/ Demolished Infrastructure for Transfer of 1.617 Hectare (3.996 Acres) of Defence
Land of Panagarh Military Station
Sl. No. Description of Work Unit Quantity Cost per Item Amount Remarks
A Civil Works Infrastructure
Construction of RCC Security wall of height of
3.00 mtr with concertina coil over Y shape
1 Mtr 1700 17,897.93 30,426,485.92
angle iron fencing 0.6 mtr height surmounted
over the wall 8,793.14
1 Construction of Chain Link Fencing wall Mtr 1700 6,575.29 11,177,986.09
2 RCC Box Type Culverts Nos 4 3,598,979.51 14,395,918.06 17897932.8958908
3 RCC Demarcation Pillars Nos 50 3,773.79 188,689.62