REKAPITULASI PROGGRES SPILLWAY

BULAN : JULI 2020

MINGGU KE-4
TOTAL MINGGU TOTAL s/d MINGGU
NO PEKERJAAN SAT SENIN SELASA RABU KAMIS JUMAT SABTU MINGGU KET
LALU INI
06-Jul-20 07-Jul-20 08-Jul-20 09-Jul-20 10-Jul-20 11-Jul-20 12-Jul-20
1 2 3 4 5 6 7 8 9 10 11 12 13
1 PEMBESIAN SEGMEN C-46, C-45
COVER (D32, D16, D10) kg 85,322.86 3,757.85 89,080.71
2 PEMBESIAN SEGMEN C-46
LT. SLAB (D32, D19, D16, D10) kg 434,943.64 10,747.78 445,691.42
DOWEL LT. SLAB (D32) Btg 1,307.00 37.00 1,344.00
3 PEMBESIAN SEGMEN
LT.SLAB + COVERAN (D32, D19, D16, D10) kg 11,797.64 11,797.64
DOWEL LT.SLAB (D32) Btg 52.00 52.00
4 PEMBESIAN SEGMEN
PONDASI + DINIDING (D32, D25, D19, D16, D10) kg 71,752.39 71,752.39
DOWEL DINDING (D32) Btg -
5 WATER STOP (30 CM) m' 1,078.10 25.20 1,103.30
6 PIPA PORFORATED 4" m' 1,198.60 1,198.60
7 BETON SEGMEN
8 LC LT. SLAB + COVER (K-125) m3 478.23 478.23
9 BETON SEGMEN
LC DINDING (K-125) m3 255.18 255.18
10 BETON SEGMEN C-48 C-46, C-45
COVER (K-225) m3 577.51 13.13 26.25 616.88
11 BETON SEGMEN C-49 C-46
LT. SLAB (K-225) m3 2,946.00 76.50 76.50 3,099.00
12 BETON SEGMEN
LT.SLAB + COVERAN (K-225) m3 88.13 88.13
13 BETON SEGMEN S.24 (Kanan)
PONDASI DINDING (K-225) m3 1,040.35 147.20 1,187.55
14 BETON SEGMEN
DINDING (K-225) m3 - -

Dibuat Oleh, Dibuat Oleh,


Inspector Spillway Inspector Spillway

Kharisma Utama, ST Fahmi Andrian Sya, ST