Professional Documents
Culture Documents
To cite this article: Colin C. Caprani & Mayer M. Melhem (2019): On the use of MCFT per AS
5100.5 for the assessment of shear capacities of existing structures, Australian Journal of Structural
Engineering, DOI: 10.1080/13287982.2019.1664207
ARTICLE
On the use of MCFT per AS 5100.5 for the assessment of shear capacities of
existing structures
Colin C. Caprani and Mayer M. Melhem
Department of Civil Engineering, Monash University, Clayton, Victoria, Australia
concrete structures (AS 3600:2018 - Standards the effect of aggregate interlock, dowel action, and the
Australia 2018) and bridge standards (AS presence of steel reinforcement on the behaviour of the
5100.5:2017). cracked concrete. In a full MCFT analysis, 15 equations
of equilibrium, strain compatibility, and constitutive
relationships, shown in Figure 1, require an iterative
1.3. Problem outline process to obtain the shear capacity of a given concrete
member.
Based on anecdotal observations of structural engi-
The MCFT equations are implemented in
neering consulting reports made available to the
a software program called Response 2000, developed
authors, it is clear that the difference between shear
by Bentz and Collins (2000) at the University of
design and assessment to MCFT is not being ade-
Toronto. The software is a two-dimensional sectional
quately taken into account by all practicing engineers.
analysis program that evaluates the load-deformation
To be fair, iteration is required for capacity assess-
response, and thus capacity, of a given cross-section
ments as discussed in various publications such as
subject to shear, moment and axial loads. The soft-
Collins and Mitchell (2014), but this is not made clear
ware is considered accurate, with a number of studies
in Part 7 of AS 5100:2017. The purpose of this note is
indicating software results varying only 1% to 5%
to explain the theoretical background and code pro-
from concrete sections experimental tested to shear
visions, clarify how the design rules must be adapted
failure (Bentz 2010; Higgins et al. 2004; Metwally
for correct shear capacity assessments, demonstrate
2012). However, the shear capacity for sections with
the method through a series of example concrete
moment-shear (M/V) ratios less than 2d appear to be
sections, and make recommendations to remove the
not well predicted in the software, where d is the
ambiguity in the code.
distance from top fibre to the longitudinal reinforce-
ment centroid (Higgins et al. 2004).
2. Theoretical background
2.1. Full MCFT analysis 2.2. fib model code 2010 levels of
approximations
The modified compression field theory (MCFT) was
developed at the University of Toronto by Vecchio and The solution of the MCFT equations seen in Figure 1
Collins (1986). The theory assumes cracked concrete can is tedious for engineering practice. Hence, four
be treated as a new material with its own stress-strain ‘Levels of Approximation’ (LoA) are given in the fib
behaviour. MCFT considers concrete tension stresses, Model Code 2010 for assessing shear capacity in
Figure 1. Fifteen equations requiring iteration in a full modified compression field theory analysis for concrete member shear
capacity assessment (Bentz, Vecchio, and Collins 2006).
AUSTRALIAN JOURNAL OF STRUCTURAL ENGINEERING 3
concrete sections (Bentz 2010). The higher the level, 2.3. Adoptions to codes of practice for design
the greater the computational effort, but also greater
Simplified MCFT equations have now been adopted
accuracy of the results. In Levels I to III the two
to international codes of practice for shear design of
MCFT-based parameters based of the simplifications
concrete sections. Provisions from the American ACI
published by Bentz, Vecchio, and Collins (2006) are
code, and the Canadian simplified methods resemble
defined in closed-form equations. These parameters
fib Model Code LoA I (Bentz 2010). Meanwhile, the
are the angle of principal compression stresses in the
equations for LoA III are adapted in the Canadian
web of the member, θ v, and the factor to account the
CSA A23.3 (Bentz and Collins 2006), the American
shear resistance of cracked concrete, kv. For example,
AASHTO (Kuchma et al. 2008) and now the
in LoA I, θv = 36° and
200 Australian standards AS 5100.5:2017 for concrete
Asv ¼ 0 bridge structures and AS 3600:2018 for concrete
kv ¼ ð10001:3dÞ (1)
0:15 Asv Asv;min building structures.
where Asv is the amount of transverse reinforcement in
the section, and Asv,min is the minimum amount of 2.4. Shear design in AS 5100.5
transverse reinforcement. LoA I is only applicable to
sections with selected material properties (Bentz 2010). Figure 2 depicts the MCFT-based shear design provi-
In LoA II, kv is taken as zero and θ v is a function of the sions found in AS 5100.5:2017+ Amdt 1:2018 for
longitudinal strain at the mid-depth of the member, εx . normal density concrete. In Figure 2, f’c is the com-
The equations for LoA II are intended to consider the pressive strength of concrete, bv is the effective web
effects of plasticity to better model heavily reinforced width, dv ¼ maxð0:72D; 0:9dÞ where D is the total
concrete beams (Bentz 2010). LoA III is an extension of depth of the section, Asv =s is the reinforcement per
LoA I, where both θv and kv are functions of εx. In unit length, and fsy is the yield strength of the steel
particular, kv is taken as a product of ‘strain effect’ and stirrups.
‘size effect’. That is: The prescribed equations for θv and kv in AS
8h ih i 5100.5:2017 Clause 8.2.4.2 are similar to those found
< 0:4 1300
Asv ¼ 0 in the Canadian and AASHTO standards. The only
kv ¼ h i
1þ1500εx 1000þsxe
(2)
: 0:4
Asv Asv;min difference is the use of 32, rather than 35, in the crack
1þ1500εx
spacing parameter equation (AS 5100.5:2017 Equation
where sxe is the crack spacing parameter. Finally, LoA 8.2.4.2(2)) – intended improve the fit against materials
IV is the use of sophisticated tools such Response 2000. test data for thinner sections with larger aggregate sizes
Figure 2. AS 5100.5 MCFT-based shear design provisions and their relationships. Equation numbers are those found in AS
5100.5:2017+ Amdt 1:2018. Note that M* and V* are defined to be absolute values (Clause 8.2.4.3/4(a)).
4 C. C. CAPRANI AND M. M. MELHEM
rffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
h i2ffi
2 0:9jV jηT uh
jV j ηM =dv þ ðjV j Pv Þ þ 2Ao þ 0:5jV j ηN Apt fpo
εx ¼ (3)
2 Es Ast þ Es Apt þ Ec Act
AUSTRALIAN JOURNAL OF STRUCTURAL ENGINEERING 5
Equation (4). However, θv and Vus are functions of εx, Graphically, this is converging towards the intersection
which in turn are functions of V (Equation (3)). between the solid black line and the solid blue line shown
Therefore, an iteration process is required to determine by the blue dashed arrows in Figure 4.
the value of V that satisfies the inequality. The results To determine the flexural-shear capacity (Vu f), θv
from this iteration provides the capacity of the flexural- and thus Vus are calculated for the initial guess (V*)
shear mode of failure (Vu f). and the resulting longitudinal force is compared with
The overall shear capacity of the section is then the the available longitudinal force capacity. If the avail-
lower of the web-shear and flexural shear capacities: able longitudinal force (Flt,u) is larger than the result-
ing force (Flt,), then V must be increased. Otherwise,
Vu ¼ min Vuf ; Vuw (5) if Flt,u > Flt, V is decreased. The longitudinal strain,
θv, and thus, Vus are re-calculated and the process
repeated until the relative difference in the longitu-
dinal forces is acceptably small (∈TOL = 1 × 10−4).
3.3. Assessment process flowchart
Graphically, this is the shear force at the correspond-
A flowchart describing the process required to adapt the ing longitudinal strain where the intersection
design provisions in AS 5100.5 for shear assessment of between the solid red line and dashed red line in
concrete structures is shown in Figure 3. In addition, Figure 4 occurs (shown by red dashed arrows).
the process is depicted graphically in Figure 4 for a case It is interesting to note from Figure 4, that the
where flexural-shear is more critical than web-shear (Vu iteration for Vuf requires aroot finding trial-and-error
f
< Vu w). Indeed, it possible for web-shear to be more approach, whereas it is an automatic process for Vuw.
critical in other cases. In these curves (Figure 4–6) shear Such iterations can be conducted using standard soft-
capacity is plotted on the left (blue) axis and longitudi- ware tools such as Microsoft Excel Solver, Goal Seek,
nal forces is plotted on the right (red) axis, both against or MATLAB’s fsolve. The final shear capacity is then
the longitudinal strain. The solid black line represents the smaller of the two capacities and the capacity
the applied shear force increasing as the longitudinal reduction factor φ is applied as appropriate to give
strain increases (Equation (3)). The solid blue line the factored shear capacity of the assessed section.
depicts the relationship between the design provisions
in AS 5100.5 and the longitudinal strain (Figure 2). The
3.4. On the importance of the iteration process
relationship between longitudinal strain and the resul-
tant longitudinal force is the solid red line (right side of Anecdotal observations of consultants’ reports, show that
Equation (4)). Finally, the available longitudinal force is for shear assessment in existing concrete sections to AS
dashed red line (left side of Equation (4)) which does 5100:2017, some engineers define V in Figure 3 as V*, but
not depend on the longitudinal strain. ignore the need for iteration. Even further, checks on
To perform the calculations, first the material and longitudinal force (Flt) have been omitted. This is some-
geometric properties for the section under assessment what understandable as it is simply following what is
are established, and the available longitudinal force shown in Figure 2. However, it ignores the fact that V*
(Flt,u) is quantified (dashed red line in Figure 4). Then, is a value independent to an existing concrete section and
an initial guess of the longitudinal strain is required. should have only been used for its design.
The influence coefficients ηM, ηT, and ηN need to be The naïve approach of assuming V* and ignoring the
known. This can be achieved by conducting a structural necessary iteration processes gives false results on the
analysis of the bridge deck under the relevant applied capacity. This is depicted in the schematic shown in
loading case. The initial guess of longitudinal strain can Figure 5 for a case when web-shear is more critical
be determined from an initial guess of the shear capacity than flexural-shear (thus, the red axis and lines are
in the equation. A suggestion for this guess is to let this omitted for clarity). The naïve approach overestimates
be the design (or assessment) action, V*, at the section. the shear capacity when the applied shear is less than the
Once an initial longitudinal strain is obtained, the two shear capacity estimated using the correct approach (V1
iteration processes are required to separately obtain the *). This is unconservative and may potentially incorrectly
web-shear and flexural-shear capacities. conclude the bridge is safe from damage after applying
To determine the web-shear capacity, the AS 5100.5 the capacity reduction factor (V* < φVu), when the risks
shear provisions are followed (Figure 2) to give the out- of damage are indeed higher. Alternatively, overconser-
put shear capacity (Vuw). Most likely the output will not vative estimate of the shear capacity occurs using the
be equal to initial input guess. Thus the process is naïve approach if the applied shear load is more that
repeated, with the output as the new input for the long- the estimation from the correct approach (V2*). Indeed,
itudinal strain, until the relative difference between the since the true shear capacity is not known, without the
output shear capacity and input shear value are accepta- iterations, an engineer will not know if their estimate is
bly close (∈TOL = 1 × 10−4). Once the two values con- overconservative or unconservative. Thus, it is crucial the
verge, the capacity results for web-shear failure is known. iterations are conducted to provide the true capacity.
6 C. C. CAPRANI AND M. M. MELHEM
Figure 3. Flowchart for using design provisions of AS 5100.5 for the shear assessment of existing concrete structure.ϵTOL
= 1 × 10−4. Clause numbers are those found in AS 5100.5:2017+ Amdt 1:2018.
Figure 4. Schematic depicting the double iteration process as per Figure 3. Automated iteration for web-shear (Vu w) is indicated
by blue dashed arrows. Trial-and-error iteration for flexural-shear (Vu f) is indicated by red dashed arrows. Equation numbers as
per this paper. Clause numbers are those found in AS 5100.5:2017+ Amdt 1:2018.
Figure 5. Schematic depicting how false results arise when V* is used and iterations are ignored.
in the assessment of some forms of existing bridge forces and torsion does not need to be considered for
structures in Australia. The geometries of the sections calculating εx following Clause 8.2.1.2 of AS 5100.5.
are shown in Figure 7 with other key properties sum- Section 1 and 2 are the critical sections for reinforced
marised in Table 1. For all sections there are no axial concrete rectangular crossheads from the substructure
8 C. C. CAPRANI AND M. M. MELHEM
Figure 6. Difference between shear capacities for (a) Section 2 (reinforced concrete) and (b) Section 3 (prestressed concrete) (see
Figure 7). For Section 2 flexural-shear is more critical (Vu w > Vu f). For Section 3, web shear is more critical (Vu w < Vu f). Since, Section 3
is a prestressed concrete section, the shape of the curve is different due to the Aptfpo term in Equation (3). Equation numbers as per
this paper. Clause numbers are those found in AS 5100.5:2017+ Amdt 1:2018. Forces in kN.
Figure 7. Geometry for representative sections (Section 1 to 5). All dimensions in mm.
Table 2. Comparison between naïve and correct approaches for shear capacity assessment of Section 1 to 5 (Figure 7).
Includes results from computer software Response 2000. All results are prior to application of the capacity reduction
factor, φ.
Shear Capacity (Vu) Section 1 Section 2 Section 3 Section 4 Section 5
Naïve Approach 583.9 556.3 1767 457.9 707.3
Error1 49% 58% 3% −4% −2%
Correct Approach 392.6 352.5 1717 475.5 721.1
Difference2 −16% −6% 4% −17% −5%
Response 2000 456.4 373.4 1645 557.3 756.8
1
Percentage error of the naïve approach compared to the correct approach
2
Difference between correct implementation of AS5100.5 rules for assessment and Response 2000 implementation of full MCFT
equations (‘truth’).
and 5, the naïve approach is conservative because the flexural-shear is more critical, and thus if the trial-
true capacity of the section is greater than the esti- and-error iteration is ignored, significantly large
mated capacity. For Sections 1 and 2 (Figure 6), errors arise (49% and 58%, respectively). Meanwhile,
10 C. C. CAPRANI AND M. M. MELHEM
Sections 3 (Figure 6) to 5 fail through web-shear. then the compression flanges may experience strain in
Intriguingly, for Section 3, the correct approach pro- the same direction as the tension flanges (CSA Standards
vides a slightly larger estimated capacity to that of 2011). It becomes unconservative then to assume the
Response 2000. Section 3 is the only section out of the longitudinal strain is half of the tensile strain in the tensile
five that is prestressed. Because of the presence of the Aptfpo flange. For Section 3 this condition is true, hence it is
term as per Equation (3), the curves for prestressed con- more accurate to calculate the longitudinal strain as the
crete are different to that of reinforcement concrete mem- average of compression and tension flanges, and not half
bers (Figure 6). For prestressed members, the AS5100.5 of the tension flange. When this is done for Section 3, the
MCFT rules state fpo (see Equation (3)) can be assumed as correct approach provides 1707 kN, which is lower than
70% of the breaking strength of the tendons (Clause considering the tension flange alone (using Equation 3),
8.2.4.3/4 Note (c)). In the Response 2000 model we have but still higher than that of Response 2000 (by 3.7%).
used this assumption, with a 6.7 mm/m (= 0.7fpbEp) pre- Indeed, Collins and Mitchell (2014) have presented an
strain. However, the values are still smaller compared to example section where the code provisions can be slightly
the AS 5100.5 output. As a subcase, Section 3 is re-con- unconservative (3% error) when compared to results of
sidered but with its prestress reinforcement now converted the same section tested to failure. However, such small
to passive reinforcement (Ast = 628 + 2460 = 3088 mm2, fsy, variations are allowed for in the reliability calibrations of
Es). That is, all prestress is removed from the section. For the shear capacity reduction factors.
this subcase, Response 2000 results in a higher capacity
output (1001 kN) than the correct approach using AS
5100.5 (870.3 kN). This suggests the reasons for 5. Conclusions & recommendations
Response 2000 providing a smaller output in the original The equations found in AS 5100.5 for concrete shear
Section 3, is not due to the I-girder geometry, but rather are applicable to design while AS 5100.7 directs engi-
due to the presence of prestress. neers to make use of these for assessment. Our review
Response 2000 software requires detailed additional of the underlying theory of MCFT shows that
properties to be defined such as the concrete tension and a modification to the design equations is required
reinforcement strengths. For this work, the Popovics/ for assessment. A flowchart (Figure 3) is presented
Thorenfeldt/Collins model is used for the concrete mate- to make clear the need for iteration when adopting
rial base curve with the default peak strain of 2.17 mm/m the MCFT-based shear design provisions of AS
(for 45 MPa). However, the software includes a range of 5100.5 for shear capacity assessments. Further, by
different models for concrete compression softening and considering a series of representative sections, the
tension stiffening. Hence, the capacities from Response ramifications of naively ignoring the need for itera-
2000 are approximate and differ slightly when alternative tion has been demonstrated.
material models are used (something not possible with It is found that the influence of prestress may not
the other approaches). For example, for the original be adequately captured by the AS 5100.5 MCFT rules
Section 3, when the peak strain is reduced to 1.33 mm/ when used for assessment. Further investigation of
m, (which is f’c divided Ec for the section), but the same this, particularly in the longitudinal strain assump-
base curve is used, the capacity predicted by the software tions, is recommended.
is now higher (1767 kN, coincidently the same as the Finally, it is recommended that an additional clause
naïve approach) than that of AS 5100.5. Nevertheless, as be inserted into AS 5100.7 that explains the modifica-
described in Section 2.2 earlier, one would expect that tion required, perhaps including a flowchart similar to
a LoA III approach to be more conservative than a LoA Figure 3, for the correct use of the MCFT design equa-
IV approach, and so it is possible that the AS5100.5 tions of AS 5100.5 in a shear capacity assessment.
MCFT rules are somewhat non-conservative for pres-
tress concrete members.
As discussed in Section 3.1, the longitudinal strain is Acknowledgments
assumed as half of the tensile strain in the flexural tensile
‘flange’ (Collins et al. 2018). More precisely, it is average The authors wish to thank the valuable inputs and efforts
from Mr Brandon Gerber, and the data provided from
of the strains in the compression and tension ‘flanges’.
Dr Geoff Taplin, Prof Riadh Al-Mahaidi, and the staff in
For reinforced concrete, when under-reinforced, the VicRoads. The research work is completed under a Noel
compression flange has a small negative strain (compres- Murray Scholarship at Monash University and supported
sion), while the tension flange has larger positive strains by the Australian Government Research Training Program
(tension). Hence, as a conservative approach the com- Scholarship.
pression strains are taken as zero, resulting in Equation
(3). However, for prestressed concrete, it is possible for
both compression and tension flanges to have negative Disclosure statement
strain due to the prestress. As discussed in the commen- No potential conflict of interest was reported by the
tary on CSA-S6-06 (Clause 8.9.3.8), when M < (V – Vp)dv, authors.
AUSTRALIAN JOURNAL OF STRUCTURAL ENGINEERING 11