ANCHORING TRIAL SEQUENCE PLAN

PLB-88

Introduction
This procedure is served for the purpose of conducting the anchooring,mooring, and tensioning
trial of refurbished PLB-88 as a requirement for performance test of PLB before offshore
campaign for 6 km pipeline installation on Balongan. Anchoring trial be executed on Cirebon on
Long: 108˚35'44.7"E Lat: 6˚40'58.9"S.

Marine Vessel List


1. Pipe Laying Barge PLB Alpha DMB-88
2. AHT ALS Prima III as tug

Anchoring Trial Location


Anchoring Trial will be held on Cirebon on Long: 108˚35'44.7"E Lat: 6˚40'58.9"S, Image below
show the line for anchoring trial in Cirebon:
Pre-requisite
Anchoring will be held while in good weather condition, calm sea with wave height less than 1.5
m and wind less than 15 knots.

Anchor Set Up
Image below show the anchoring set-up of the PLB-88 vessel and pipeline dummy trial data(500
m) for anchoring trial in Cirebon.

Anchor Anchor to first Anchor to second


No
name side range(m) side range(m)
1 S4 530 666
2 S3 470 567
3 S2 650 510
4 S1 650 473
5 P4 530 666
6 P3 470 567
7 P2 650 510
8 P1 650 473

Sequence
Anchor
No Step
target
1 P1 AHT Prima III recover the stand by anchor(P1) and rack it back to PLB-88
2 - AHT Prima III tow the PLB-88 to the pipelay trial line initial position
3 AHT Prima III stand by on port side
4 Transfer anchor pendant wire from PLB-88 to AHT Prima III by the rigger
5 AHT Prima III cast off from PLB-88 barge prosheet to anchor/fairlead P4
P4
Once connected, PLB-88 surveyor will give command intended coordinate
6 to AHT's survey
7 AHT Prima III deploy the anchor to P4 coordinate deploy target
8 - AHT Prima III move to PLB-88's P3 side
9 AHT Prima III stand by on P3
10 Transfer anchor pendant wire from PLB-88 to AHT Prima III by the rigger
11 P3 AHT Prima III cast off from PLB-88 barge prosheet to anchor/fairlead P3
12 Once connected, PLB-88 surveyor will give command intended coordinate
13 AHT Prima III deploy the anchor to P3 coordinate deploy target
14 - AHT Prima III move to PLB-88's S1 side
15 AHT Prima III stand by on S1
16 Transfer anchor pendant wire from PLB-88 to AHT Prima III by the rigger
17 S1 AHT Prima III cast off from PLB-88 barge prosheet to anchor/fairlead S1
18 Once connected, PLB-88 surveyor will give command intended coordinate
19 AHT Prima III deploy the anchor to S1 coordinate deploy target
20 - AHT Prima III move to PLB-88's S4 side
21 AHT Prima III stand by on S4
22 Transfer anchor pendant wire from PLB-88 to AHT Prima III by the rigger
23 S4 AHT Prima III cast off from PLB-88 barge prosheet to anchor/fairlead S4
24 Once connected, PLB-88 surveyor will give command intended coordinate
25 AHT Prima III deploy the anchor to S4 coordinate deploy target
26 - AHT Prima III move to PLB-88's S3 side
27 AHT Prima III stand by on S3
28 Transfer anchor pendant wire from PLB-88 to AHT Prima III by the rigger
29 S3 AHT Prima III cast off from PLB-88 barge prosheet to anchor/fairlead S3
30 Once connected, PLB-88 surveyor will give command intended coordinate
31 AHT Prima III deploy the anchor to S3 coordinate deploy target
32 - AHT Prima III move to PLB-88's S2 side
33 AHT Prima III stand by on S2
34 Transfer anchor pendant wire from PLB-88 to AHT Prima III by the rigger
35 S2 AHT Prima III cast off from PLB-88 barge prosheet to anchor/fairlead S2
36 Once connected, PLB-88 surveyor will give command intended coordinate
37 AHT Prima III deploy the anchor to S2 coordinate deploy target
38 - AHT Prima III move to PLB-88's P1 side
39 AHT Prima III stand by on P1
40 Transfer anchor pendant wire from PLB-88 to AHT Prima III by the rigger
41 P1 AHT Prima III cast off from PLB-88 barge prosheet to anchor/fairlead P1
42 Once connected, PLB-88 surveyor will give command intended coordinate
43 AHT Prima III deploy the anchor to P1 coordinate deploy target
44 - AHT Prima III move to PLB-88's P2 side
45 AHT Prima III stand by on P2
46 Transfer anchor pendant wire from PLB-88 to AHT Prima III by the rigger
47 P2 AHT Prima III cast off from PLB-88 barge prosheet to anchor/fairlead P2
48 Once connected, PLB-88 surveyor will give command intended coordinate
49 AHT Prima III deploy the anchor to P2 coordinate deploy target
Once all the anchors have been deployed, Barge will move forward per 12
meter and survey will provide GHOST data of barge to keep the barge still
50 - on pipeline plan. Barge will move forward per 12 m till reach the max
range of anchor pattern. After sea trial success and been aproved by client
MWS, Then continue to recovering anchors.
AHT move to P2 deployed point to recovery
51 P2
AHT lift the buoy and anchor to the deck
Rack it back to PLB 88 P2 side and rigged back to PLB-88
AHT move to P3 deployed point
52 P3
AHT lift the buoy and anchor to the deck
Rack it back to PLB 88 P3 side and rigged back to PLB-88
53 P4
53 P4
AHT move to P4 deployed point
AHT lift the buoy and anchor to the deck
Rack it back to PLB 88 P4 side and rigged back to PLB-88
AHT move to S3 deployed point
54 S3
AHT lift the buoy and anchor to the deck
Rack it back to PLB 88 S3 side and rigged back to PLB-88
AHT move to S4 deployed point
55 S4
AHT lift the buoy and anchor to the deck
Rack it back to PLB 88 S4 side and rigged back to PLB-88
AHT move to S2 deployed point
56 S2
AHT lift the buoy and anchor to the deck
Rack it back to PLB 88 S2 side and rigged back to PLB-88
AHT move to P1 deployed point
57 P1
AHT lift the buoy and anchor to the deck
Rack it back to PLB 88 P1 side and rigged back to PLB-88
AHT move to P2 deployed point
58 P2
AHT lift the buoy and anchor to the deck
Rack it back to PLB 88 P2 side and rigged back to PLB-88

*Note: : Deployed Anchor


: Recovery Anchor

Prepared by Checked by

M. Ihsan Habibi I Gusti Bagus Hermawan