Professional Documents
Culture Documents
1.0 Scope
Many wells are produced using gas lift to lighten the fluid column. Slickline is often used to service (run
and pull) Gas Lift Valves (GLV’s) from these wells.
GLVs have a check valve (back check) to prevent flow from tubing into the annulus.
A Kick-Over Tool (KOT) is required to run and pull gas lift valves from Side Pocket Mandrels (SPM’s).
Some SPM’s contain orientating slots or guides and some are non-orienting.
The orienting-type SPM has a key slot built into it that aligns the KOT with the GLV pocket to ease in
setting and pulling. It is primarily used in deviated wells.
Often flowing wells are completed with SPM’s loaded with dummy GLV’s. These are later replaced with
live GLV’s.
3.0 Procedure
1. Record the Flowing Tubing Head Pressure (FTHP) and Flowing Casing Head Pressure (FCHP).
Important Note: At all times when pressures are recorded it must be performed with a digital
pressure gauge or by using the same gauge to record both pressures. Faulty gauge readings
could result in pressure differential not being detected.
2. Close gas lift supply valve on the gas lift manifold up stream of Merla Choke (in order to allow
SCADA to continue recording casing pressure) and tag out the valve. The casing annulus wing
valve must remain open to record actual casing pressure. In the event that manifold valves are
passing, the casing annulus wing valve should be closed during operations but will need to be re
opened whenever pressures are recorded. Report fault to Field Engineer.
3. Shut in the Production wing valve and rig up the Slickline equipment.
4. Record the Shut in Tubing Head Pressure (SITHP) and Shut in Casing Head Pressure (SICHP).
5. RIH with appropriate sized gauge ring and drift the tubing clear to the maximum OD of the valve
catcher and the KOT’s to be run. Record the tubing fluid level during Slickline runs.
6. If the KOT does not have a catcher on the tray, set an appropriate valve catcher in the tubing
below the lowest SPM, ensure the valve catcher will either hold the dropped valve above the
catcher fish neck or is long enough to swallow the GLV and allow the catcher to be recovered with
the valve inside the catcher, including sufficient travel for the pulling tool core to enable shearing
of the pulling tool.
LOCAL WORK METHOD
TITLE: HALLIBURTON MANAGEMENT SYSTEM
Gaslift Slickline Operations DOCUMENT NUMBER:
BUS. UNIT/SHARED SERVICES: REGION: FUNCTION: WM-ANG-HAL-SL-403
Drilling and Evaluation Europe and West Africa Wireline and
Perforating Services
OWNER: APPROVED BY: JOB REVISION BY: REV. DATE: REV. NO: SECTION: PAGE:
WPS Slickline Ramiro Rivera Fred Heller Nov 27, 2013 1 1 0f 1
Important note: When using KOT with catcher trays always ensure that the correct spacers are used
to allow the pulled valve to retract back into the tray above the catcher.
7. Calculate the Bottom Hole Pressure (BHP) of both the tubing and casing at the deepest GLV to be
pulled.
Record SITHP and SICHP again.
Note: equalization should be based on BHP, not surface pressures. When pulling GLV’s the
tubing BHP must be equal to or greater than the casing BHP same depth. (use TVD depths only
and call Field Engineer if help is needed).
10. As determined in Slickline program, commence changing the GLV’s always starting with the
deepest valve.
A. Pull one / run one GLV from the bottom up.
B. Pull all GLV’s from the bottom up and run all GLV’s from the top down.
Select the correct KOT, extension, pulling tools and running tools from the GLV Running and
Pulling Tool Table (inserted below).
A knuckle joint should always be placed in the tool string above the KOT.
Note: Do not run 2 arm L-type KOT when running GLV’s into side pockets mandrels with
positioning sleeves. The arms may hang up in the positioning sleeves key slot.
11. Record GLV Test Rack Opening Pressure (TRO) engraved on the valve, confirm the SPM # and
depth are correctly engraved on the valve. (Note: Dummy valves are not commonly engraved).
Important Note: If the well is returned to production at any time before the job is completed,
hydrostatic BHP’s will need to be recalculated and pressure equalized before recommencing
Slickline work.
Calculations.
Determine the pressure differential and direction of flow from highest pressure to lowest pressure.
Deep TVD – Shallow TVD / Deep MD – Shallow MD 4500 – 3500 / 3719 – 2997 = .722
Inverse of Cos .722 = Deviation Angle 43.78 Degrees
2 7/8'' 1'' KBM M, BK-2 2'' - 2 1/2'' L, 2 1/2'' K 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR
1'' TMPD M, BK-2 2 7/7'' TMP, OK-6 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR
1 1/2'' MMA T2, RA 2'' - 2 1/2'' L, 2 1/2'' R 2'' JDC, 40 SM 1 (*2) TER, JC-3
1 1/2'' TPD T2, RA 2 7/8'' TP, OM-1, OM-5, KOT-2 2'' JDC, 40 SM 1 (*3) TER, JC-3
1 1/2'' MMG RK, TG 2 7/8'' TP, OM-1, OM-5, KOT-2 1 5/8'' JDS, 40 SS 3, ML (*3) RK-1
1 1/2'' SFO-2 RK, TG 2 7/8'' TP, OM-1, OM-5, KOT-2 1 5/8'' JDS, 40 SS 3, ML (*3) RK-1
1 1/2'' SFO-2WF Integral, RK 2 7/8'' TP, OM-1, OM-5, KOT-2 Prong 1 1/4" - Valve 1 5/8" (*4)(*5) RK-1
1'' SFO-1 BK-2, M 2-1/2'' TMP, OK-6, KOT-1 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR
1" Chem Inj SFO-1Ci BK-2, M 2-1/2" TMP, KOT-1, OK-6 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR
3 1/2'' 1'' KBUG M, Bk-2 3 1/2'' TMP, OK-6, KOT-1 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR
1'' TMPD M, Bk-2 3 1/2'' TMP, OK-6, KOT-1 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR
1 1/2'' TPD T2, RA 3 1/2'' TP, OM-1, OM-5, KOT-2 2'' JDC, 40 SM 1 (*3) TER, JC-3
1 1/2'' TGPD TG, RK 3 1/2'' TP, OM-1, OM-5, KOT-2 1 5/8'' JDS, 40 SS 3, ML(*3) TGR, RK-1
1 1/2" SFO-2 RK 3 1/2'' TP, OM-1, OM-5, KOT-2 1 5/8'' JDS, 40 SS 3, ML (*3) RK-1
1 1/2" SFO-2WF Integral, RK 3 1/2'' TP, OM-1, OM-5, KOT-2 Prong 1 1/4" - Valve 1 5/8" (*4)(*5) RK-1
1 1/2" SBRO-2DWF Integral, RK 3 1/2" Modified OM-1, KOT-2 DWF Prong 1 1/4" - Valve 1 5/8" (*4)(*5) RK-1
1'' SFO-1 BK-2, M 3-1/2'' TMP, OK-6, KOT-1 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR
1" Chem Inj SFO-1Ci BK-2, M 3-1/2" TMP, KOT-1, OK-6 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR
4 1/2'' 1 1/2'' MMG TG, RK 4 1/2'' TP, OM-1, OM-5, KOT-2 1 5/8'' JDS, 40 SS 3, ML (*3) TGR, RK-1
1 1/2'' TPD T-2, RA 4 1/2'' TP, OM-1, OM-5, KOT-2 2'' JDC (*1) TER, JC-3
1 1/2'' SFO-2 RK, RK 4 1/2'' TP, OM-1, OM-5, KOT-2 1 5/8'' JDS, 40 SS 3, ML(*3) RK-1
1 1/2" SFO-2WF Integral, RK 4 1/2'' TP, OM-1, OM-5, KOT-2 Prong 1 1/4" - Valve 1 5/8" (*4)(*5) RK-1
1 1/2" SBRO-2DWF Integral, RK 4 1/2" Modified OM-1, KOT-2 DWF Prong 1 1/4" - Valve 1 5/8" (*4)(*5) RK-1
1" Chem Inj SFO-1Ci BK-2, M 4-1/2" TMP, KOT-1, OK-6 1 1/4 JDC, 40 SM 4, 1.25 ML JK, MR