You are on page 1of 11

FITTER

GOVERNMENT OF INDIA
MINISTRY OF SKILL DEVELOPMENT & ENTREPRENEURSHIP
DIRECTORATE GENERAL OF TRAINING

COMPETENCY BASED CURRICULUM

FITTER
(Duration: Two Years)

CRAFTSMEN TRAINING SCHEME (CTS)


NSQF LEVEL- 5

SECTOR – PRODUCTION & MANUFACTURING


FITTER
8. SYLLABUS

First Semester
Duration: Six Month

Week Ref. Learning Professional Skills Professional Knowledge


No. Outcome with Indicative hrs.
1. Recognize & 1. Importance of trade training, List All necessary guidance to be provided to
comply safe of tools & Machinery used in the the new comers to become familiar with
working practices, trade. (1 hr.) the working of Industrial Training
environment 2. Safety attitude development of the Institute system including stores
regulation and trainee by educating them to use procedures.
housekeeping. Personal Protective Equipment Soft Skills, its importance and Job area
(PPE). (5 hrs.) after completion of training.
3. First Aid Method and basic Importance of safety and general
training.(2 hrs.) precautions observed in the in the
4. Safe disposal of waste materials industry/shop floor.
like cotton waste, metal Introduction of First aid. Operation of
chips/burrs etc. (2 hrs.) electrical mains and electrical safety.
5. Hazard identification and Introduction of PPEs.
avoidance. (2 hrs.) Response to emergencies e.g.; power
6. Safety signs for Danger, Warning, failure, fire, and system failure.
caution & personal safety Importance of housekeeping & good
message.(1 hrs.)
shop floor practices. Introduction to 5S
7. Preventive measures for electrical
accidents & steps to be taken in concept & its application.
such accidents.(2 hrs.) Occupational Safety & Health: Health,
8. Use of Fire extinguishers.(7 hrs.) Safety and Environment guidelines,
9. Practice and understand legislations & regulations as applicable.
precautions to be followed while
working in fitting jobs. (2 hrs.) Basic understanding on Hot work,
10. Safe use of tools and equipments confined space work and material
used in the trade. (1 hrs.) handling equipment.
2. Plan and organize 11. Identification of tools Linear measurements- its units, dividers,
the work to make &equipments as per desired calipers, hermaphrodite, centre punch,
job as per specifications for marking & dot punch, their description and uses of
specification sawing. (5 hrs.) different types of hammers. Description,
applying different 12. Selection of material as per use and care of „V‟ Blocks, marking off
types of basic application.(1 hrs.) table.
13. Visual inspection of raw material
fitting operation and
for rusting, scaling, corrosion
Check for etc.(1 hrs.)
dimensional 14. Marking out lines, gripping
accuracy. [Basic suitably in vice jaws, hacksawing
fitting operation – to given dimensions. (10 hrs.)
marking, 15. Sawing different types of metals of
Hacksawing, different sections. (8 hrs.)

24
FITTER
Chiseling, Filing,
Drilling, Taping
and Grinding etc.
Accuracy: ±
0.25mm]

3. -do- 16. Filing Channel, Parallel. (5 hrs.) Bench vice construction, types, uses, care
17. Filing- Flat and square (Rough & maintenance, vice clamps, hacksaw
finish), (10 hrs.) frames and blades, specification,
18. Filing practice, surface filing, description, types and their uses, method
marking of straight and parallel of using hacksaws.
lines with odd leg calipers and Files- specifications, description,
steel rule. (5 hrs.) materials, grades, cuts, file elements,
19. Marking practice with dividers, uses. Types of files, care and
odd leg calipers and steel rule maintenance of files.
(circles, ARCs, parallel lines). Measuring standards (English, Metric
(5 hrs.) Units), angular measurements.

4. -do- 20. Marking off straight lines and Marking off and layout tools, dividers,
ARCs using scribing block and scribing block, odd leg calipers, punches-
dividers. (5 hrs.) description, classification, material, care
21. Chipping flat surfaces along a & maintenance.
marked line. (10 hrs.) Try square, ordinary depth gauge,
22. Marking, filing, filing square and protractor- description, uses and cares.
check using tri-square.(10 hrs.) Calipers- types, material, constructional
details, uses, care & maintenance of cold
chisels- materials, types, cutting angles.
5&6 -do- 23. Marking according to simple blue Marking media, marking blue, Prussian
prints for locating, position of blue, red lead, chalk and their special
holes, scribing lines on chalked application, description.
surfaces with marking tools. (20 Use, care and maintenance of scribing
hrs.) block.
24. Finding center of round bar with Surface plate and auxiliary marking
the help of „V‟ block and marking equipment, „V‟ block, angle plates,
block. (5 hrs.) parallel block, description, types, uses,
25. Joining straight line to an ARC.(25 accuracy, care and maintenance.
hrs.)

25
FITTER
7& -do- 26. Chipping, Chamfering, Chip slots Physical properties of engineering metal:
8. & oils grooves (Straight).(10 hrs.) colour, weight, structure, and
27. Filing flat, square, and parallel to conductivity, magnetic, fusibility,
an accuracy of 0.5mm. (10 hrs.) specific gravity. Mechanical properties:
28. Chip curve along a line-mark out, ductility, malleability hardness,
key ways at various angles & cut brittleness, toughness, tenacity, and
key ways.(15 hrs.) elasticity.
29. Sharpening of Chisel.(5 hrs.)
30. File thin metal to an accuracy of
0.5 mm.(10 hrs.)

9. -do- 31. Saw along a straight line, curved Power Saw, band saw, Circular saw
line, on different sections of machines used for metal cutting.
metal.(15 hrs.)
32. Straight saw on thick section, M.S.
angle and pipes.(10 hrs.)

10. -do- 33. File steps and finish with smooth Micrometer- outside and inside –
file to accuracy of ± 0.25 mm. principle, constructional features, parts
(10 hrs.) graduation, leading, use and care.
34. File and saw on M.S. Square and Micrometer depth gauge, parts,
pipe. (5 hrs.) graduation, leading, use and care. Digital
micrometer.

11. -do- 35. File radius along a marked line Vernier calipers, principle, construction,
(Convex & concave) & match. graduations, reading, use and care.
(15 hrs.) Vernier bevel protractor, construction,
36. Chip sheet metal (shearing). graduations, reading, use and care, dial
(5 hrs.) Vernier Caliper, Digital verniercaliper.
37. Chip step and file. (5 hrs.)

12. -do- 38. Mark off and drill through holes. Drilling processes: common type (bench
(5 hrs.) type, pillar type, radial type), gang and
39. Drill and tap on M.S. flat. (10 hrs.) multiple drilling machine.
40. Punch letter and number (letter Determination of tap drill size.
punch and number punch) (5 hrs.)
41. Practice use of different
punches.(5 hrs.)

13. Manufacture simple 42. Marking of straight lines, circles, Safety precautions to be observed in a
sheet metal items as profiles and various geometrical sheet metal workshop, sheet and sizes,
per drawing and join shapes and cutting the sheets with Commercial sizes and various types of
them by soldering, snips. (15 hrs.) metal sheets, coated sheets and their uses
brazing and riveting. 43. Marking out of simple as per BIS specifications. Shearing
development (5 hrs.) machine- description, parts and uses.
44. Marking out for flaps for soldering

26
FITTER
and sweating.(5 hrs.)
14 & -do- 45. Make various joints: wiring, Marking and measuring tools, wing
15. hemming, soldering and brazing, compass, Prick punch, tin man‟s square
form locked, grooved and knocked tools, snips, types and uses. Tin man‟s
up single hem straight and curved hammers and mallets type-sheet metal
edges form double hemming,.(15 tools, Soldering iron, types,
hrs.) specifications, uses. Trammel-
46. Punch holes-using hollow and description, parts, uses. Hand grooves-
solid punches. (2 hrs.) specifications and uses.
47. Do lap and butt joints.(8 hrs.)

16. -do- 48. Bend sheet metal into various Stakes-bench types, parts, their uses.
curvature form, wired edges- Various types of metal joints, their
straight and curves. Fold sheet selection and application, tolerance for
metal at angle using stakes. (8 hrs.) various joints, their selection &
49. Make simple Square container application. Wired edges.
with wired edge and fix handle.(17
hrs.)
17. -do- 50. Make square tray with square Solder and soldering: Introduction-types
soldered corner.(15 hrs.) of solder and flux. Composition of
51. Practice in soft soldering and silver various types of solders and their heating
soldering. (10 hrs.)
media of soldering iron. Method of
soldering, selection and application-
joints. Hard solder- Introduction, types
and method of brazing.
18. Join metal 52. Make riveted lap and butt joint.(9 Various rivets shape and form of heads,
component by arc hrs.) importance of correct head size.
welding observing 53. Make funnel as per development Rivets-Tin man‟s rivets types, sizes, and
standard procedure. and solder joints.(10 hrs.) selection for various works.
54. Drill for riveting. (1 hrs.) Riveting tools, dolly snaps description
55. Riveting with as many types of and uses. Method of riveting,
rivet as available, use of counter The spacing of rivets. Flash riveting, use
sunk head rivets. (5 hrs.) of correct tools, compare hot and cold
riveting.
19. Cut and join metal 56. Welding - Striking and Safety-importance of safety and general
component by gas maintaining ARC, laying Straight- precautions observed in a welding shop.
(oxy-acetylene) line bead.(25 hrs.) Precautions in electric and gas welding.
(Before, during, after) Introduction to
safety equipment and their uses.
Machines and accessories, welding
transformer, welding generators.
20. Cut and join metal 57. Making square, butt joint and „T‟ Welding hand tools: Hammers, welding
component by gas fillet joint-gas and ARC. (15 hrs.) description, types and uses, description,
(oxy-acetylene) 58. Do setting up of flames, fusion principle, method of operating, carbon
& runs with and without filler rod, dioxide welding. H.P. welding
and gas.(10 hrs.) equipment: description, principle,

27
FITTER
Join metal method of operating L.P. welding
components by equipment: description, principle,
riveting observing method of operating. Types of Joints-
standard procedure. Butt and fillet as per BIS SP: 46-1988
specifications. Gases and gas cylinder
description, kinds, main difference and
uses.
21. Cut and join metal 59. Make butt weld and corner, fillet Setting up parameters for ARC welding
component by gas in ARC welding(25 hrs.) machines-selection of Welding
(oxy-acetylene) electrodes. Care to be taken in keeping
electrode.

22. Join metal 60. Gas cutting of MS plates(25 hrs.) Oxygen acetylene cutting-machine
components by description, parts, uses, method of
riveting observing handling, cutting torch-description, parts,
standard procedure. function and uses.

23-25 Revision

26 Examination

NOTE: -

1. More emphasis to be given on video/real-life pictures during theoretical classes. Some real-
life pictures/videos of industry on machine fitting, alignment of pump-motor, fitting of pipes &
tubes, assembling jobs, maintenance work, etc., may be shown to the trainees to give a feel of
Industry and their future assignment.

28
FITTER
Second Semester
Duration: Six Month

Week Learning Outcome Professional Skills Professional Knowledge


No. with Indicative hrs.
27. Produce components 61. Mark off and drill through holes. Drill- material, types, (Taper shank,
by different (5 hrs.) straight shank) parts and sizes. Drill
operations and 62. Drill on M.S. flat. (1 hrs.) angle-cutting angle for different
check accuracy 63. File radius and profile to suit materials, cutting speed feed. R.P.M. for
using appropriate gauge.(13 hrs.) different materials. Drill holding devices-
measuring 64. Sharpening of Drills.(1 hrs.) material, construction and their uses.
instruments.[Differe 65. Practice use of angular measuring
nt Operations - instrument. (5 hrs.)
Drilling, Reaming,
Taping, Dieing;
Appropriate
Measuring
Instrument –
Vernier, Screw
Gauge, Micrometer]

28. -do- 66. Counter sink, counter bore and Counter sink, counter bore and spot
ream split fit (three piece fitting).(5 facing-tools and nomenclature, Reamer-
hrs.) material, types (Hand and machine
67. Drill through hole and blind reamer), kinds, parts and their uses,
holes.(2 hrs.) determining hole size (or reaming),
68. Form internal threads with taps to Reaming procedure.
standard size (through holes and Screw threads: terminology, parts, types
blind holes).(3 hrs.) and their uses. Screw pitch gauge:
69. Prepare studs and bolt.(15 hrs.) material parts and uses. Taps British
standard (B.S.W., B.S.F., B.A. & B.S.P.)
and metric /BIS (course and fine)
material, parts (shank body, flute, cutting
edge).
29. -do- 70. Form external threads with dies to Tap wrench: material, parts, types (solid
standard size. (10 hrs.) &adjustable types) and their uses
71. Prepare nuts and match with removal of broken tap, studs (tap stud
bolts.(15 hrs.) extractor).
Dies: British standard, metric and BIS
standard, material, parts, types, Method
of using dies. Die stock: material, parts
and uses.
30. -do- 72. File and make Step fit, angular fit, Drill troubles: causes and remedy.
angle, surfaces (Bevel gauge Equality of lips, correct clearance, dead
accuracy 1 degree).(15 hrs.) centre, length of lips. Drill kinds:
73. Make simple open and sliding Fraction, metric, letters and numbers,
fits.(10 hrs.) grinding of drill.

29
FITTER
31. -do- 74. Enlarge hole and increase internal Grinding wheel: Abrasive, grade
dia. (2 hrs.) structures, bond, specification, use,
75. File cylindrical surfaces.(5 hrs.) mounting and dressing. Selection of
76. Make open fitting of curved grinding wheels. Bench grinder parts and
profiles.(18 hrs.) use.
Radius/fillet gauge, feeler gauge, hole
gauge, and their uses, care and
maintenance.
32. -do- 77. Correction of drill location by Pig Iron: types of pig Iron, properties and
binding previously drilled hole.(5 uses.
hrs.) Cast Iron: types, properties and uses.
78. Make inside square fit. (20 hrs.)

33. Make different fit of 79. Make sliding „T‟ fit.(25 hrs.) Interchangeability: Necessity in Engg,
components for field definition, BIS. Definition, types of
assembling as per limit, terminology of limits and fits-basic
required tolerance size, actual size, deviation, high and low
observing principle limit, zero line, tolerance zone Different
of interchangeability standard systems of fits and limits.
and check for British standard system, BIS system
functionality.
[Different Fit –
Sliding, Angular,
Step fit, ‘T’ fit,
Square fit and
Profile fit; Required
tolerance: ±0.04
mm, angular
tolerance: 30 min.]

34. -do- 80. File fit- combined, open angular Method of expressing tolerance as per
and sliding sides. (10 hrs.) BIS Fits: Definition, types, description of
81. File internal angles 30minutes each with sketch. Vernier height gauge:
accuracy open, angular fit.(15 hrs.) material construction, parts, graduations
(English & Metric) uses, care and
maintenance.
35- -do- 82. Make sliding fit with angles other Wrought iron- : properties and uses.
36. than 90o.(25 hrs.) Steel: plain carbon steels, types,
properties and uses.
Non-ferrous metals (copper, aluminum,
tin, lead, zinc) properties and uses.

30
FITTER
37. -do- 83. Scrap on flat surfaces, curved Simple scraper- circular, flat, half round,
surfaces and parallel surfaces and triangular and hook scraper and their
test. (5 hrs.) uses. Blue matching of scraped surfaces
84. Make & assemble, sliding flats, (flat and curved bearing surfaces)
plain surfaces. (15 hrs.)
85. Check for blue math of bearing
surfaces- both flat and curved
surfaces by wit worth method.(5
hrs.)
38. -do- 86. File and fit combined radius and Vernier micrometer, material, parts,
angular surface (accuracy ± 0.5 graduation, use, care and maintenance.
mm), angular and radius fit. (18 Calibration of measuring instruments.
hrs.) Introduction to mechanical fasteners and
87. Locate accurate holes & make its uses.
accurate hole for stud fit.(2 hrs.) Screw thread micrometer: Construction,
88. Fasten mechanical components / graduation and use.
sub-assemblies together using
screws, bolts and collars using
hand tools.(5 hrs.)
39. -do- 89. Make sliding fits assembly with Dial test indicator, construction, parts,
parallel and angular mating material, graduation, Method of use, care
surface. (± 0.04 mm)(25 hrs.) and maintenance. Digital dial indicator.
Comparators-measurement of quality in
the cylinder bores.
40. Produce components 90. Lathe operations- Safely precautions to be observed while
involving different 91. True job on four jaw chuck using working on a lathe, Lathe specifications,
operations on lathe knife tool.(5 hrs.) and constructional features. Lathe main
observing standard 92. Face both the ends for holding parts descriptions- bed, head stock,
procedure and check between centers. (9 hrs.) carriage, tail stock, feeding and thread
for accuracy. 93. Using roughing tool parallel turn ± cutting mechanisms. Holding of job
[Different 0.1 mm. (10 hrs.) between centers, works with catch plate,
Operations – facing, 94. Measure the diameter using dog, simple description of a facing and
plain turning, step outside caliper and steel rule.(1 roughing tool and their applications.
turning, parting, hrs.)
chamfering,
shoulder turn,
grooving, knurling,
boring, taper
turning, threading
(external ‘V’ only)]

41. -do- 95. Holding job in three jaw chuck.(2 Lathe cutting tools- Nomenclature of
hrs.) single point & multipoint cutting tools,
96. Perform the facing, plain turn, step Tool selection based on different
turn, parting, deburr, chamfer- requirements and necessity of correct
corner, round the ends, and use grinding, solid and tipped, throw away

31
FITTER
form tools. (11 hrs.) type tools, cutting speed and feed and
97. Shoulder turn: square, filleted, comparison for H.S.S., carbide tools. Use
beveled undercut shoulder, of coolants and lubricants.
turning-filleted under cut, square
beveled.(11 hrs.)
98. Sharpening of -Single point
Tools.(1 hrs.)
42. -do- 99. Cut grooves- square, round, „V‟ Chucks and chucking the independent
groove. (10 hrs.) four-jaw chuck. Reversible features of
100. Make a mandrel-turn diameter to jaws, the back plate, Method of clearing
sizes. (5 hrs.) the thread of the chuck-mounting and
101. Knurl the job.(1 hrs.) dismounting, chucks, chucking true, face
102. Bore holes –spot face, pilot drill, plate, drilling - method of holding drills
enlarge hole using boring tools. in the tail stock, Boring tools and
(9 hrs.) enlargement of holes.
43. -do- 103. Make a bush step bore-cut General turning operations- parallel or
recess, turn hole diameter to straight, turning. Stepped turning,
sizes.(5 hrs.) grooving, and shape of tools for the
104. Turn taper (internal and above operations. Appropriate method of
external).(10 hrs.) holding the tool on tool post or tool rest,
105. Turn taper pins. (5 hrs.) Knurling: - tools description, grade, uses,
106. Turn standard tapers to suit with speed and feed, coolant for knurling,
gauge.(5 hrs.) speed, feed calculation.
Taper – definition, use and method of
expressing tapers. Standard tapers-taper,
calculations morse taper.
44. -do- 107. Practice threading using taps, Screw thread definition – uses and
dies on lathe by hand. (2 hrs.) application. Square, worm, buttress,
108. Make external „V‟ thread.(8 hrs.) acme ( non standard-screw threads),
109. Prepare a nut and match with the Principle of cutting screw thread in
bolt.(15 hrs.) centre lathe –principle of chasing the
screw thread – use of centre gauge,
setting tool for cutting internal and
external threads, use of screw pitch
gauge for checking the screw thread.
45– Plan & perform 110. Simple repair work: Simple Maintenance
46. simple repair, assembly of machine parts from -Total productive maintenance
overhauling of blue prints. (15 hrs.) -Autonomous maintenance
different machines 111. Rectify possible assembly faults -Routine maintenance
and check for during assembly.(19 hrs.) -Maintenance schedule
functionality. 112. Perform the routine maintenance -Retrieval of data from machine manuals
[Different Machines with check list (10 hrs.) Preventive maintenance-objective and
– Drill Machine, 113. Monitor machine as per routine function of Preventive maintenance,
Power Saw, Bench checklist (3 hrs.) section inspection. Visual and detailed,
Grinder and Lathe] 114. Read pressure gauge, lubrication survey, system of symbol and
temperature gauge, oil level (1 colour coding. Revision, simple
hrs.) estimation of materials, use of handbooks

32
FITTER
115. Set pressure in pneumatic system and reference table. Possible causes for
(2 hrs.) assembly failures and remedies.

47. -do- 116. Assemble simple fitting using Assembling techniques such as aligning,
dowel pins and tap screw bending, fixing, mechanical jointing,
assembly using torque wrench. threaded jointing, sealing, and torquing.
(25 hrs.) Dowel pins: material, construction, types,
accuracy and uses.
48- In-plant training / Project work
49 1. Pipe Fixture
2. Adjustable Clamp
3. Hermaphrodite/ Inside Caliper
4. Chuck Key
50- Revision
51.
52. Examination

Note: -

1. Some of the sample project works (indicative only) are given against each semester.
2. Instructor may design their own project and also inputs from local industry may be taken
for designing such new project.
3. The project should broadly covered maximum skills in the particular trade and must
involve some problem solving skill. Emphasis should be on Teamwork: Knowing the
power of synergy/ collaboration, Work to be assigned in a group (Group of at least 4
trainees). The group should demonstrate Planning, Execution, Contribution and
application of Learning. They need to submit Project report.
4. If the instructor feels that for execution of specific project more time is required than he
may plan accordingly to produce components/ sub-assemblies in appropriate time i.e.,
may be in the previous semester or during execution of normal trade practical.
5. More emphasis to be given on video/real-life pictures during theoretical classes. Some
real-life pictures/videos of industry on machine fitting, alignment of pump-motor, fitting
of pipes & tubes, assembling jobs, maintenance work, etc., may be shown to the trainees
to give a feel of Industry and their future assignment.