Professional Documents
Culture Documents
L1 CHE STD 030 Track Drainage Standard
L1 CHE STD 030 Track Drainage Standard
L1-CHE-STD-030
TRACK DRAINAGE STANDARD
Version: 3
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
Approval
Amendment Record
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 2 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
PREFACE
Metro Trains Melbourne (MTM) Standards have been developed to ensure common approaches are
employed when designing, constructing or testing any part of the Melbourne Metropolitan Rail
Network. It is important to understand that Standards are living documents which take into account
learnings to achieve best practice.
All MTM Standards are periodically reviewed and new versions published which incorporate
learnings and Technical Notes (TNs). TNs are issued between editions which correct any errors or
ambiguities contained in an MTM Standard. Standards may also be withdrawn and replaced. As
Standards are uncontrolled once printed, it is imperative to check the currency of the Standard on
the MTM Intranet or MTM External Document Portal.
In the event of conflicts or discrepancies between Documents, refer to the order of precedence as
defined in ‘Chief Engineer’s Guideline Engineering Standards Listing’ (L1-CHE-GDL-005).
Note: Any clarification described in a TN shall take precedence over the impacted clause or clauses
in the associated MTM Standard.
In the event a clause within a Standard is not achievable a waiver must be raised in accordance with
‘Engineering Waiver Procedure’ - L1-CHE-PRO-001.
Note: MTM does not have the authority to grant waivers to any Standards which relate to
Government Regulations or Legislation, e.g. Disability Discrimination Act.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 3 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
Table of Contents
1 Purpose ........................................................................................................................... 6
2 Scope ............................................................................................................................... 6
3 Abbreviations .................................................................................................................. 6
4 Definitions ....................................................................................................................... 6
5 References & Legislations ............................................................................................. 7
5.1 General ............................................................................................................................... 7
5.2 MTM References................................................................................................................. 8
5.3 Industry References ............................................................................................................ 8
5.4 Australian References and Legislation ............................................................................... 8
6 Related Documents ........................................................................................................ 9
7 Safety & Environmental .................................................................................................. 9
8 Functionality ................................................................................................................. 10
9 General Principles for Track Drainage ........................................................................ 11
9.1 Design Considerations ...................................................................................................... 11
9.2 Flood Design ..................................................................................................................... 12
9.3 Peak Flow Rate ................................................................................................................. 12
9.4 Drainage Design Life ........................................................................................................ 12
9.5 Re-Use of Existing Infrastructure ...................................................................................... 13
9.6 Drainage Discharge .......................................................................................................... 13
10 Surface Drainage .......................................................................................................... 14
10.1 Catch Drains ..................................................................................................................... 14
10.2 Cess Drains ....................................................................................................................... 14
10.3 Retention Basins ............................................................................................................... 16
11 Subsurface Drainage .................................................................................................... 16
11.1 General ............................................................................................................................. 16
11.2 Pipe Size ........................................................................................................................... 18
11.3 Pipe Grades ...................................................................................................................... 18
11.4 Pipe Cover ........................................................................................................................ 18
11.5 Pipe Class ......................................................................................................................... 19
11.6 Trenching .......................................................................................................................... 19
11.7 Design Velocities............................................................................................................... 20
11.8 Pit Configuration and Sizing.............................................................................................. 20
11.9 Pit Covers and Ballast Cages ........................................................................................... 21
11.10 Geotextiles ........................................................................................................................ 22
11.11 Under Track Crossings ..................................................................................................... 23
11.12 Utility Clearance Requirements ........................................................................................ 23
12 Inlet/Outlet ..................................................................................................................... 23
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 4 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
13 Stations ......................................................................................................................... 24
14 Turnouts and Crossovers ............................................................................................ 24
15 Bridge and Tunnel Drainage ........................................................................................ 24
16 Pumped Systems .......................................................................................................... 25
17 Appendix A – Documentation Requirements.............................................................. 27
17.1 General Requirements ...................................................................................................... 27
17.2 Drawings ........................................................................................................................... 27
17.3 Design Report ................................................................................................................... 27
List of Tables
List of Figures
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 5 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
1 Purpose
1.1 The purpose of this document is to provide the technical requirements for drainage systems
within the rail corridor.
2 Scope
2.1 This standard sets out MTM requirements for drainage systems within the rail corridor. It
covers the technical requirements for drainage of the track formation, supporting
embankments and cuttings.
2.2 This standard does not cover drainage from carparks, buildings, overbridges, footbridges,
airspace developments, external developments, access roads, roads outside the rail corridor,
council drains or properties adjacent to the rail corridor.
2.3 This standard does not include culvert design or design of other infrastructure used to allow
overland flow to cross the rail corridor.
2.4 The provisions in this standard are mandatory.
3 Abbreviations
AEP Annual Exceedance Probability
ARI Average Recurrence Interval
FRC Fibre Reinforced Concrete
MTM Metro Trains Melbourne
RSNL Rail Safety National Law
4 Definitions
Annual The likelihood of occurrence of a flood of given size or larger
Exceedance occurring in any one year expressed as a percentage. For
Probability (AEP) example, if a peak flood discharge of 500 m3/s has an AEP of 5%,
it means that there is a 5% risk (i.e., a risk of one-in-20) of a peak
flood discharge or larger occurring in any one year
Catch Drains Catch drains (also known as “top drains”) intercept overland flow or
runoff before it reaches the track. Catch drains are generally located
on the uphill side of a cutting or catch water flowing down the hill
and remove it prior to reaching the cutting.
Catchment The land area draining to a point of interest, such as a point on a
(Catchment Area) stream, river or stormwater drainage system. The catchment area
is used to determine the quantity of runoff through hydrological
assessment.
Cess Area From the edge of the ballast profile to either the edge of the
embankment or the toe of the cutting.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 6 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
Cess Drains Cess drains are surface drains located at the formation level at the
side of the tracks. They remove water that has percolated through
the ballast and is flowing across the capping layer towards the
outside of the formation. Cess drains are primarily intended for
protect the formation by keeping it dry.
Erosion The process by which the flow of water alters the ground surface in
an area by removing layers of soil.
Formation The formed, graded and compacted material, including fill material,
capping layer material (often referred to as sub-ballast) and any
drainage layers or materials, on which ballast is laid.
Peak Flow Rate The highest flow discharged from the catchment under
consideration having evaluated storm durations with a particular
average recurrence level.
Track Drainage Drainage of the track formation including diversion of water away
from cuttings and embankments.
Shall The term shall is used to express a clause that is mandatory to
achieve conformance to the standard.
Should Is used as the descriptive word to express a requirement that is
recommended in order to achieve compliance. ‘should’ can also be
used if a requirement is a desirable but not a mandatory
requirement.
Subsurface A pipe and sump drainage system to convey surface water
Drainage underground.
Subsoil Drainage A slotted pipe and/or aggregate drainage system to intercept
ground water or seepage.
6-foot Area between two tracks
5.1 General
5.1.1 Track drainage shall be designed and constructed in accordance with this standard,
other relevant MTM and Australian standards and MTM requirements documents.
5.1.2 Where a conflict arises between standards or clarification as to the applicability of
a standard or a part of a standard is required, the matter shall be referred to the
MTM Chief Engineer or delegate for determination.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 7 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 8 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
6 Related Documents
L1-CHE-STD-039 Track Design and Construction
L1-CHE-SPE-178 Earthworks & Formation Specification
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 9 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
7.5 Under RSNL (s47), reasonably practicable means that which is, or was at a particular time,
reasonably able to be done to ensure safety, taking into account and weighing up all relevant
matters including:
a) the likelihood of the hazard or the risk concerned occurring; and
b) the degree of harm that might result from the hazard or the risk; and
c) what the person concerned knows, or ought reasonably to know, about-
i. the hazard or risk, and ways of eliminating or minimising the risk; and
ii. the availability and suitability of ways to eliminate or minimise the risk; and
d) after assessing the extent of the risk and the available ways of eliminating or
minimising the risk, the cost associated with available ways of eliminating or
minimising the risk, including whether the cost is grossly disproportionate to the
risk.
7.6 Under RSNL (s50), rail safety is a shared responsibility of:
a) Rail transport operators; and
b) Rail safety workers; and
c) Other persons who:
i. Design, commission, construct, manufacture, supply, install, erect, maintain,
repair, modify or decommission rail infrastructure or rolling stock; or
ii. Supply rail infrastructure operations or rolling stock operations to rail
operators; or
iii. In relation to the transport of freight by railway—load or unload freight on or
from rolling stock.
7.7 Safety and risk assessments shall be undertaken to inform the design of railway drainage
systems. They shall take into account safety considerations for construction and
maintenance personnel and any other parties, including operations personnel, who may be
required to use the track. Risk assessments shall be conducted in accordance with the MTM
Enterprise Risk Management Procedure L0-SQE-PRO-031.
7.8 Where new materials or systems are to be introduced with the design and construction of the
railway drainage, the materials and systems shall be subject to MTM Type Approval
processes for use on the metropolitan train network.
7.9 Where the requirements of this standard cannot be met, a standard waiver shall be submitted
to seek approval from the Chief Engineer.
8 Functionality
8.1 The functional requirements for tracks, sidings, maintenance depots and related facilities
shall be described in the appropriate MTM standard, Final Operational Requirements and
Final Impact Statement for the Project.
8.2 The design shall ensure compliance with the Structure Gauge Envelopes applicable to the
category of ownership of the incumbent infrastructure as outlined in L1-CHE-STD-025.
8.3 The design shall provide documentation in accordance with Appendix A of this standard.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 10 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 11 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 12 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 13 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
10 Surface Drainage
10.1.5 Catch drains may be either lined or unlined depending on the local soil conditions.
10.1.6 Catch drains may not be required if the design can demonstrate a suitable
alternative has been provided, such as a containment barrier, or similar.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 14 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
10.2.3 Cess drains shall be provided on the downhill side of embankments to divert water
from the embankment toe. It is preferred that drains be 1000 mm minimum from
the toe of the embankment. Where this is not feasible, the cess drains shall have a
capacity 1.5 times the design flow rate to account for embankment erosion over the
life of the drain.
10.2.4 The preferred longitudinal gradient for an open channel shall be 1:100.
10.2.5 The absolute minimum longitudinal gradient for an open channel shall be 1:300 if
the channel is lined, or 1:200 if unlined.
10.2.6 The maximum longitudinal gradient for an open channel shall ensure that the
maximum velocity of a 1 in 10 year ARI event does not exceed the velocities in
Table 2.
10.2.7 The location of the open channel shall comply with the Formation shoulder distance
specified in Figure 2 and Figure 3.
10.2.8 Where track drainage is incorporated within existing constraints (for example,
cuttings, between tracks) and the shoulder distance cannot be achieved, open
channels shall not be installed closer than 3000mm from the nearest track
centreline to prevent ballast spill into the channel area.
10.2.9 This minimum edge distance shall be increased as required based on track
configuration (rail size, sleeper type, ballast depth) and track curvature.
10.2.10 The top of lined channels shall be lower than the top of an adjacent track formation
to ensure tracks are free draining.
10.2.11 Where the cess is in a publicly accessible area, velocity x depth checks shall be
completed to confirm maximum runoff velocities comply with Melbourne Water’s
Floodway Safety Criteria.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 15 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
10.2.12 The material forming the open channel shall be capable of withstanding the
maximum permissible design velocity for a 1 in 10 year ARI event.
10.2.13 Table 2 provides maximum velocity values for varying lining types.
11 Subsurface Drainage
11.1 General
11.1.1 Subsurface drains shall be used where adequate surface drainage cannot be
provided due to a restriction, or lack of available fall due to outlet restrictions.
11.1.2 Subsurface drainage systems shall be designed to transfer surface runoff and
water collected from other drainage systems to an approved point of discharge.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 16 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
11.1.3 Subsoil drainage shall be provided in locations where the water table is at or near
earthworks level. Subsoil drainage shall also be provided where artesian conditions
exist to relieve water pressure.
11.1.4 If a subsoil drainage system is required to remove ground water and seepage, a
detailed hydrological and geotechnical investigation is required to determine the
volume of water for the sizing of drains. If required due to levels of contaminants,
ground water and seepage may require a separate drainage system to enable it to
be discharged appropriately.
11.1.5 Both slotted and un-slotted pipes may be used depending on the system type and
its means of collecting and carrying water.
11.1.6 Slotted pipes shall be used as collector drains as these do not rely on surface flow
between pits to collect runoff. Drainage schemes that rely solely on grated pits to
collect runoff shall be avoided where possible and are subject to approval from the
Chief Engineer or delegate.
11.1.7 Within the 6-foot, the maximum length of subsurface drainage (based on catchment
area and flow path) for slotted pipes shall be 100m. For subsurface drainage runs
longer than 100m, a separate carrier pipe shall be provided as per Figure 3 to
minimise risk of drainage failure damaging the Formation of two tracks. Maximum
pit spacing specified in 11.8.5 shall still apply.
11.1.8 In restricted areas where longitudinal subsurface drainage has an invert level
deeper than 600mm below top of capping, a separate carrier pipe shall be provided
in conjunction with the collector pipe to minimise the depth of the collector pipe.
This is to improve maintenance during limited occupation windows. A typical
arrangement is shown in Figure 3.
11.1.9 When selecting a pipe, the environment (whether the water is abrasive, acidic or
alkaline) shall be considered. The manufacturer's specifications shall be referred to
in relation to the various environmental conditions and circumstances for which the
pipe is deemed to be suitable.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 17 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
11.1.10 Materials and products used in the drainage system shall be approved by the MTM
Type Approval process. Approved proprietary products shall be designed and
installed in accordance with Australian standards, manufacturer’s specifications
and conditions of the type approval.
11.1.11 Aggregate drains are only suitable for use where a small flow of ground water or
seepage is expected. They are not to be used for the collection of surface water.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 18 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
11.4.5 Depth of pipes under sealed roads shall be 600mm minimum from top of road to
the top of pipe or pipe encasing.
11.4.6 Pipes running parallel to the track shall be the greater value of 900mm from top of
rail or 300mm below the top of capping.
11.6 Trenching
11.6.1 The bedding support of all flexible pipes shall be in accordance with AS 2566.1.
Typically the minimum trench width shall be pipe diameter plus 150mm on each
side.
11.6.2 The bedding support of all concrete pipes shall be in accordance with AS 3725.
Typically the minimum trench width shall be pipe diameter plus 150mm on each
side.
11.6.3 For pipes running in parallel, a clear space of 300mm between pipes shall be
provided to allow compaction to take place.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 19 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
11.6.4 Trenches shall be backfilled with suitable material and compacted to not less than
95% maximum standard dry density as determined in AS 1289 ( as per Test 5.1.1
and Test 5.3.1) in nominal 150mm layers.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 20 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
11.8.8 Where an upstream pipe run is not fitted with a pit, a flush out riser or headwall
shall be provided for maintenance purposes.
11.8.9 Flushing points for drainage pipes shall have the same diameter as the pipe.
Flushing points shall consist of ‘T’ or ‘L’ connection in the subsurface pipe, with pipe
connections extending to the surface for regular flushing with water to clear the
subsurface drain of fouling material.
11.8.10 The minimum internal plan dimensions of a pit shall be 600mm x 600mm. For
depths greater than 900mm, the minimum internal plan dimensions shall be
increased to 900mm x 900mm unless the pit is located within the 6-foot between
tracks.
11.8.11 Where pits are located in the 6-foot between tracks, the minimum internal plan
dimensions of the pit shall be 600mm wide (perpendicular to the tracks) x 900mm
to accommodate inspection and access. The width shall be the maximum size
available to enable proper placement of the pit without clashing with the sleepers.
11.8.12 Where the internal pit height (including risers and/or ballast cages) exceeds
1200mm, step rungs shall be provided at 300mm vertical centres. Where practical,
pits shall be orientated so the step rungs are on the side of the pit facing oncoming
traffic unless the track is bi-directional, installed within the 6-foot between the tracks
or interferes with pipe openings
11.8.13 Pit riser heights shall be selected such that step rungs do not come within 50mm of
the top or bottom of the riser.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 21 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
11.9.9 Where pits are located within the 6-foot between tracks, pits lids, grates or ballast
cages shall be designed so the top of the pit is 100mm above the top of adjacent
sleeper level to prevent the pit becoming covered with ballast, and to account for
future track lifts.
If located in a siding, pits lids shall be installed at pathway level where located in a
walking area. If located between tracks with different levels the pit shall not infringe
on the clearance of the lower track.
11.10 Geotextiles
11.10.1 An appropriate geotextile filter fabric shall be selected which satisfies both the
required strength and filtration criteria.
11.10.2 As a guide, the selected geotextile is to exhibit the mechanical properties outlined
in Table 3 when tested in accordance with AS 3706: Geotextiles - Methods of test
- General introduction and list of methods: These properties are indicative only. The
final selection must take account of any local condition such as harsh environments.
Table 3: Geotextile mechanical properties
Strength1 Filtration3
Strength (N)
Strength (N)
Q100 (l/m2/s)
Elongation2
Permittivity
Flow Rate
G Rating
Ψ (s-1)
Grab
EOS
Tear
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 22 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
5
Applies to the material on which the geotextile is placed. Drainage blanket design
based on maximum stone particle size <75mm.
11.10.3 Geotextile used in subsurface drainage shall fully line the trench and have a
minimum lap at the top of 300 mm but not exceeding 50% of the width at the top.
The geotextile shall be covered by a minimum of 100 mm of aggregate.
11.10.4 Geotextile products used shall be approved by the MTM Type Approval process
12 Inlet/Outlet
12.1 To prevent blockage of pipes, all inlets shall be designed with appropriate protection to
prevent debris entering the drainage system.
12.2 To prevent soil erosion, all inlet and outlet points shall be provided with an appropriate size
concrete headwall, pit or rock beaching/rip rap to suit the ground profile.
12.3 Outlets shall be designed to minimise the likelihood of weed growth, erosion and other
blockages that can prevent free flow of water. The ground covering at the pipe exit points
shall be capable of withstanding the exit flow rates. The maximum permissible velocities
provided in Table 2 shall be used as the ground covering limits.
12.4 If provided, concrete headwalls shall be designed to provide strength and stability to resist
the applied loadings to AS 5100.2: Bridge Design – Design Loads.
12.5 Where the sediment load of the water being discharged from a drainage system is high, a silt
trap shall be included.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 23 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
13 Stations
13.1 For stations with island platforms, the drainage infrastructure shall be designed on the outside
of the rail corridor where it can be easily inspected and maintained.
13.2 For stations with side face platforms, the sub-surface drainage may be placed within the 6-
foot for the length of the station due to restrictions accessing and maintaining drainage
infrastructure.
13.3 MTM operational procedures require faulty trains to proceed to the nearest station, if they are
physically capable of doing so, for passenger evacuation. Junction pits with maintenance
access shall be located immediately downstream of a station to assist capturing and treating
contaminants that may be generated from faulty rolling stock.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 24 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
15.8 On ballasted structures, ballast cages shall be utilised at all grated inlets for ease of
maintenance.
16 Pumped Systems
16.1 If the drainage system cannot provide an appropriate gravity outlet, a pumped system shall
be provided.
16.2 The pump shall be located (in plan), at a location where a mobile crane and staff can access
it for maintenance purposes without requiring the need for occupations or electrical isolation.
This location shall be on the MTM Infrastructure Lease. Unrestricted access for maintenance
staff shall be maintained in a 1% AEP (100 year ARI) event.
16.3 The pump system shall contain a lifting system which allows the raising/lowering of pumps
to enable minor works or inspections to be undertaken without requiring the use of a crane.
16.4 The pumped system shall provide storage capacity for a 2 hour, 1% AEP (100 year ARI)
event in case of pump system failure. A 2 hour period has been determined as an acceptable
response time for maintenance staff to reinstate the operation of the pump system after the
high water level warning is triggered by the alarm system.
16.5 The pumped system shall provide sufficient redundancy in the pump and pipe sets that when
one unit or inlet/outlet pipe is temporarily offline (e.g. maintenance or fault), all drainage
requirements can still be satisfied.
16.6 The pump station shall have a connection for a backup generator and pump in case of power
failure. The connection type shall be compatible with equipment used by emergency services
and MTM.
16.7 Power supply to pumps, operation of the pumps and high water level alarms shall be
connected to the Challenger System. All pump alarms shall be monitored individually.
16.8 The alarm systems shall be connected to a UPS.
16.9 Pumps shall operate automatically, based on both level controller transducers and
mechanical floats for failsafe operation. Each pump shall be provided with actuation controls
and sensors. Soft start shall be used for pump motors due to frequent start/stop during
operation.
16.10 The power supply to pumps shall be from the station supply or a separate feed from the
Supply Authority.
16.11 Metal pipes attached to the structure shall be fitted with insulating sections where the pipe
leaves the structure. Refer to Clause 20 of L1-SDD-STD-006.
16.12 Pumps shall be mounted on insulated pedestals to mitigate against electrolytic corrosion.
16.13 If the drainage system includes an enclosed/retention basin, it shall be designed in
accordance with AS2865 Confined Spaces. Design consideration shall include but not limited
to:
• Provision of outlets and facilities for cleaning to eliminate or reduce the need for entry.
• Provision of ventilation facilities to avoid the build-up of any contaminants or
combustible atmospheres.
• Provision of adequate and convenient means of entry and exit for persons who may be
required to wear personal protective equipment, including respiratory protective
devices and clothing.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 25 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
• Provision for persons to conduct tasks in other than stooped, awkward or cramped
positions.
• Provision of fixed ladders, platforms and walkways complying with AS1657.
• Provision levels of illumination, complying with AS1680.1, that will be sufficient to
permit safe entry, conduct of tasks and exit.
16.14 Materials and products used in the drainage system shall be approved by the MTM Type
Approval Process.
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 26 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
17.2 Drawings
Design drawings shall include a site survey and plan as well as details of the following:
• track alignments and levels
• drainage layout and details, including existing drainage, outlet details
• location of structures, natural features and services
• design average recurrence interval
• cross sections
• longitudinal sections of pipe runs, including depth of pipes
• pipe jacking or boring under tracks
• pipe, trench and open channel installation details
• pit details, including a pit table
• scour protection
• detention basin details
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 27 of 28
ENGINEERING STANDARD
TRACK DRAINAGE STANDARD
L1-CHE-STD-030 Version: 3 Effective from: 17th July 2018
o Catchment Details
o Hydrologic Parameters Adopted
o Hydraulic Parameters Adopted
o Analysis Results (existing and proposed)
o Design flows and velocities
o Load calculations on drainage infrastructure
o Water Quality
o Pumping Systems
• Record of safety in design assessment
Approving Manager: Chief Engineer Approval Date: 17/07/2018 Next Review Date: 17/07/2021
PRINTOUT MAY NOT BE UP-TO-DATE; REFER TO METRO INTRANET FOR THE LATEST VERSION Page 28 of 28