1. Cloud Services Entitlements impact the Testing Strategy & Plan.

What are
the key points to take into consideration for Test activity planning?
(1/1) Points
Lead times to Enable additional Cloud Services e.g. IP Whitelisting, VPN,
SSO, etc…
Lead times for Sizing evaluation & Concurrent patching requests
All of the above
Lead times for Provisioning ATE (Additional Test Environments)
Correct!

2. Automated Regression Testing may be carried out on all SaaS Products


(0/1) Points
True
False
Incorrect. Please review Continuous Testing Strategy and Plan to find the correct answer.

3. Adopting an Agile Testing Mindset & Approach for Cloud Applications


Projects means:
(0/1) Points
Conduct regression testing with simplified Test Scripts in an iterative and
incremental phased approach as you have unlimited time to test the updates
prior to progressing the changes to PRODUCTION Environment
Exploratory Testing to include Unplanned Consequences besides explicit
expectations
Conduct Regression Testing on Application Updates within 2 weeks’ sprints
with simplified Test Scripts
Automated Regression Testing to practice continuous improvement
Keep it simple and Practice Continuous Improvement
Incorrect. Please review Continuous Testing Strategy and Plan to find the correct answer.

4. Your Customer received an upcoming SaaS Update notification (in 1


week). As they are close to Go-Live in a month’s time, they seek your
advice. Which of the following may be best course of action to minimise
issues with Go-Live?
(0/1) Points
Review all the new features that the Customer might need and produce a
Change Request to be deployed after Go-Live.
Can’t skip an update, its mandatory. Continue with existing plan and raise
any issues with Oracle if they arise.
Log an SR with Oracle and request to Postpone the update for another 3
months
Consider revision of the Project plan - Updates are mandatory, and each
update requires a round of regression testing. The regression testing may
highlight issues that need fixes/ workarounds prior to the System going Live.

Conduct a pros and cons analysis - perhaps the Update may fit in the
Current Plan although not originally planned
Incorrect. Please review Continuous Testing Strategy and Plan to find the correct answer.

5. A partner is deploying an application on OCI. They would like to have


visibility to detect insecure OCI resources settings. Which Product caters for
such a requirement?
(0/1) Points
CASB
REST API
Cloud users cannot have visibility into OCI resource misconfigurations
OCI Audit Service
Incorrect. Please review Cloud Security

6. Your Customer needs Data Masking in their Fusion SaaS Test


environments. Which of the following statements about Data Masking
Service is correct?
(0/1) Points
Data masking is a chargeable service, and only standard PII fields are
masked during P2T (Production to Test) refreshes.
Data masking is ONLY required for European Union Customers.
Data masking is ONLY required for regulated Customers or Customers with
Highly sensitive “Cost” data. If Manufacturing /procurement is not there,
Data masking doesn’t apply.
Data Masking is a free service and Customer can choose any number of
fields, and their own rules, etc. by raising an SR.
Incorrect. Please review Cloud Security
7. Oracle Cloud Infrastructure’s security approach is based on seven core
pillars. Each pillar has multiple solutions designed to maximize the security
and compliance of the platform. Which of the following is NOT Considered
one of the pillars?
(0/1) Points
Disaster Recovery
Data Encryption
Customer Isolation
Visibility
High Availability
Incorrect. Please review Cloud Security

8. Your Customer currently uses Microsoft Active Directory as their Identity


Provider. On their transition to Oracle Infrastructure Cloud (OCI), they
intend to restrict OCI resources access initially to the Project Developers
ONLY. Which of the following Cloud Architect’s activity achieves this
requirement?
(0/1) Points
Create a group for developers on OCI and map the group to a similar group
in Microsoft Active Directory during the federation process.
Federate all Microsoft Active Directory groups with OCI to allow users to use
their existing credentials.
Create a group for developers on OCI, export all the developers from
Microsoft Active Directory, and then import them into the Identity and
Access Management (IAM) group.
Create a new user account for each user, and then create policies to provide
access to developers.
Incorrect. Please review Cloud Security

9. Which TWO statements about Fault Domains are true?


(Choose all correct answers)
(0/1) Points
A fault domain is selected automatically based on usage data
Each availability domain contains three fault domains
A fault domain is a grouping of hardware and infrastructure within an
availability domain
A failed instance in a fault domain is automatically relaunched
Incorrect. Please review Cloud Security
10. You propose implementing Virtual Private Network to restrict Customer
employee access outside their corporate network. What should you consider
in the Project Delivery Costs?
(1/1) Points
Oracle VPN is a subscription based paid service and needs to be budgeted
for the Project
Oracle VPN comes part of OCI under the Universal Credits subscription – so
no additional budget required.
Oracle VPN is a free service bundled with Oracle Cloud Service subscriptions.
So, there is no additional costs to budget for.
Oracle VPN is part of the application Services that is configured using the
Application Administrator login access rights. Hence, no additional effort/
Costs to budget for.
Correct!

11. For some Oracle Cloud Services or Services that support instances, you
can add your own Internet Protocol (IP) whitelist, blacklist rules and activate
the firewall for the Cloud service. Which statement is true?
(1/1) Points
For Customer security needs, you can define a range of IP range of address
to ‘Allow’ and “Block” using Cloud Portal self-service.
There is only Blacklist option available through the Cloud console
For Customer Security needs SSO (Single Sign-On) is the only option
There is NO concept of white listing. If needed Customer should go for free
Virtual Private network.
You can raise an SR to activate the IP white listing for one-off charge.
Correct!

12. Select the THREE build possibilities that use Oracle Serverless
programming model (Functions)
(Choose all correct answers)
(1/1) Points
Real-time processing of Files, Streams
API implementations
Web and Mobile Backends
Blockchain
Digital Assistant
Correct!

13. Which of the following best explains Visual Builder Cloud Service (VBCS)
that is used to extend the SaaS application?
(0/1) Points
JAVA
APEX
WYSIWYG
HTML
REST
Incorrect. Please review Implementation Approach: Cloud Applications and Extensions
Development in DevOps to find the correct answer.

14. What are the different types of environments recommended for


Developer Cloud Continuous Integration Server in order to Code, Build, Test
and Deploy Applications
(1/1) Points
Dev, Test, Prod
Dev, Test, Prod, QA, Staging
Test, prod, QA
Dev, Test, QA, Prod
Dev, Test, build, Prod
Correct!

15. The tool that manages, issues, releases source code, wikis, and snippets
is called:
(1/1) Points
Eclipse
Selenium
Maven
Git
Hudson
Correct!
16. Your Customer bought Universal Credits to build a custom application
but would like to know if they need to budget for Oracle Developer Cloud
Services separately. Which of the following is CORRECT?
(0/1) Points
Yes - ODCS requires a separate budget to be allocated based on usage
metrics
No separate budget is necessary - ODCS comes free of charge for all Oracle
Cloud Customers
Incorrect. Please review Implementation Approach: Cloud Applications and Extensions
Development in DevOps to find the correct answer.

17. Which of the following is NOT considered one of the benefits of Cloud
Native Development approach?
(0/1) Points
Sustainability: easily upgraded, managed and maintained environments
Portability: No lock-in
Developer Productivity: Packages entire runtime environment, allowing apps
to run on dev’s laptop, on-premises or in any Cloud
Cost Effectiveness: More efficient resource utilization, more containers per
server
Agility: Faster to spin-up / tear-down, compared to VMs and bare metal
Incorrect. Please review Implementation Approach: Cloud Applications and Extensions
Development in DevOps to find the correct answer.

18. Functions serverless application programming model have all of the


following characteristics EXCEPT
(0/1) Points
Triggered from user code or Cloud events
Short execution
Self-contained
Scales manually
Stateless
Incorrect. Please review Implementation Approach: Cloud Applications and Extensions
Development in DevOps to find the correct answer.

19. The TWO best contexts for using Container-Docker deployment in your
OCI deployment are -
(Choose all correct answers)
(0/1) Points
For proactive deployment and factoring
When Running less workloads on the same hardware
Packaged as containers with limited Choice of languages/frameworks
For responsive deployment and scaling
For fast and consistent delivery of an application
Incorrect. Please review Implementation Approach: Cloud Applications and Extensions
Development in DevOps to find the correct answer.

20. Which of the following best explains Kubernetes?


(0/1) Points
It is a drag and drop visual development tool with live WYSIWYG (What You
See Is What You Get) designer using Declarative Development approach
It is a standardized unit of software used to develop, ship and deploy
applications
It is a rapidly growing movement where there is less concern with underlying
infrastructure and more focus on writing code.
It is the de-facto technology to create, manage and run containers
It is a Container orchestration tool, which automates the scaling of
workloads in the Containers
Incorrect. Please review Implementation Approach: Cloud Applications and Extensions
Development in DevOps to find the correct answer.

21. Your Customers asks if Oracle Developer Cloud Services has agile Project
management tools. Which of the following is correct?
(0/1) Points
No - Agile Project management is handled externally on Project plans
Yes - you can set up sprints, teams boards within ODCS
Incorrect. Please review Implementation Approach: Cloud Applications and Extensions
Development in DevOps to find the correct answer.

22. A Customer would like to know exactly how the Database (DB) instances
will be managed in the Autonomous Database Service. Which of the
following options are correct?
(1/1) Points
Autonomous DB is managed by Oracle but Back-up and Restore is Customer
initiated
Autonomous DB updates are automated and managed by Oracle, but
backups are Customer initiated
Autonomous DB updates and Backups are automated and managed by
Oracle.
Autonomous DB updates and Backups are Customer initiated.
Autonomous Database will only self-scale its size
Correct!

23. You are assigned to a Customer Project in EMEA region who has
subscribed to SaaS Applications of Fusion ERP, SCM, Sales and HCM.
Customer has not activated the services yet. What considerations should be
made before activation of the Services?
(1/1) Points
Data Centre location in view of Data Residency requirements
Geographic locations
Timezones
All of the above
Language Packs
Correct!

24. Oracle offers its Fusion SaaS Cloud Customers, many service
entitlements such as P2T, T2T and T2P.
(0/1) Points
True
False
Incorrect. Please review Cloud Environments Provisioning and Management to find the correct
answer.

25. Your Project is in UAT phase with Production set Up activities scheduled
in 4 weeks’ time. You realise that a P2T request will not be fulfilled following
the set up as the source and target environment patch sets will be out of
sync. What risk mitigation activity could have avoided this situation?
(0/1) Points
Opting for monthly patching to minimize the impact of testing
No risk mitigation necessary, the source overrides the target regardless of
the patch sets
Scheduling a P2T as soon as the production set up is completed
Taking care of post P2T activities – this should address the risk.
Opting for concurrent Maintenance to ensure both PROD and TEST
environments are patched at the same time to avoid black out window
Incorrect. Please review Cloud Environments Provisioning and Management to find the correct
answer.

26. The role profile that includes responsibility of managing the Oracle Cloud
Service applications, creating additional MyService users, setting up security
profiles, adding other users or distribution lists to receive notifications is
called as -
(0/1) Points
MOS Administrator
Identity Domain Administrator
Application Administrator
Account Administrator
Service Cloud Administrator
Incorrect. Please review Cloud Environments Provisioning and Management to find the correct
answer.

27. You are conducting requirement gathering for a Customer’s Cloud OCI
Project Data Transfer and Connectivity needs. There is a requirement for
large volumes of outbound Data traffic from the Oracle Data Centres to third
party systems. What cost impact will the Customer’s requirements have?
(1/1) Points
Data Ingress, which is Data traffic from Oracle Data Centre to external
sources bear additional charges depending on connection type – hence
Customer specific requirements will incur additional costs
Data Ingress and Egress involve exchange of Data traffic with Oracle Data
Centres. They are free of cost when accessed through VPN or Public
Internet.
Data Egress, which is Data traffic from Oracle Data Centre to external
sources bear additional charges depending on connection type – hence
Customer specific requirements will incur additional costs
Data Egress, which is Data traffic from external sources to Oracle Data
Centres bear no additional charges – hence no cost impact to meet
Customer specific requirement
Data Ingress, which is Data traffic from external sources to Oracle Data
Centres bear no additional charges – hence no cost impact to meet
Customer specific requirement.
Correct!

28. As a Project Manager, you should include the following SaaS


Environment activities in your schedule to plan ahead and mitigate risks:
(0/1) Points
Quarterly updates on Test / Production, Sizing, P2T, Back-Ups
Quarterly updates on Test / Production, Sizing, P2T, T2P
Quarterly updates on Test / Production, Sizing, Concurrent Patching
Quarterly updates on Test / Production, Sizing, P2T and optionally,
concurrent patching
Quarterly updates on Test / Production, P2T, Concurrent Patching
Incorrect. Please review Cloud Environments Provisioning and Management to find the correct
answer.

29. Customer has an SSO - Single Sign On Requirement for their Fusion ERP
and SCM, CPQ and Sales Cloud solution footprint Cloud Project. What is the
Best Practice implementation approach for this requirement?
(1/1) Points
Enable and test single sign-on in a non-production environment before
enabling it in production.
It depends on the Cloud applications in scope
Ensure that the identity provider is SSO enabled
Verify that the Cloud applications in scope supports SSO enablement and will
not require extra certifications. Enable SSO first in the TEST environment
and then in the PROD following thorough testing.
SSO is not possible in Cloud Applications - additional customisation/ build is
required.
Correct!

30. A Customer has completed the UAT of a Cloud Fusion ERP and HCM
Project and is close to Go-Live. The Customer insists to have a Gold Instance
- i.e. have a back-up of the Production Instance to restore from in case
PROD Data Migration went wrong. Is this possible?
(1/1) Points
This is an on-premise strategy and may be used for Cloud implementations.

Ask the Customer to buy an extra environment which will serve as Gold
instance, to carry out this activity
Back-Up and Restore is unavailable for Fusion SaaS Projects as in On-
Premise Projects. All activities must be thoroughly tested prior to Production
Migration as instance restore is not a service entitlement.
No need for Gold Instance, conduct a P2T after production configuration and
the Test Instance may be used to restore to PROD if necessary
There are alternative solutions in PaaS/OCI to be explored
Correct!

31. To take a systematic and methodical approach for a Project, it is


important to conduct a thorough analysis of which of the following the
Enterprise Architecture Layers:
(0/1) Points
Information, Data, Business processes, Technology
Business, Data, Software, Technology
Business, Databases, Applications, Technology
Strategy, Data, Applications, Infrastructure
Business, Data, Applications, Technology
Incorrect. Please review Cloud Architecture Envisioning and Planning to find the correct
answer.

32. Enterprise Business Analysis and Architecture processes continuously


refine an organization’s:
(1/1) Points
Internal and external Compliance and Regulatory requirements
Business Strategies and Requirements
All of the Above
Future-State Architecture
Cloud Strategy and Roadmap
Correct!

33. The Data Architecture framework approach that takes all the different
data sources during ‘Discovery’ phase and maps to the lifecycle through
‘Ingest, Transform and Refine’ stages to the equivalent core Oracle Cloud
Services is called as:
(1/1) Points
Data Refinery Architecture
Data Streams Architecture
Data Reservoir Architecture
Structured Enterprise Data Lake Architecture
Oracle Data eco-system reference architecture
Correct!

34. Your Cloud Project Architect is designing IT topologies for Specific


Business scenarios and intends to leverage any pre-existing reference
Architectures for SaaS Applications extensions using Cloud Native Approach.
Where can you find these?
(1/1) Points
Oracle Cloud Infrastructure Architecture Center
Solution Blueprints Architecture Center
My Oracle Support - Architecture Center
Oracle Cloud Architecture Marketplace - OPN Access only
There are no such reference Architectures for SaaS extensions
Correct!

35. You are managing a Move and Improve Project of a bespoke application
developed on WebLogic Server and Oracle Database. The heavily
transactional On-Premise System runs on Windows Servers and has variable
workloads across the week. As it is a core system, there is a lot of demand
for database administration to keep the lights-on. Which of the following
options serve as a Best Practice improvement solution to meet the
Customer’s needs in an efficient way?
(0/1) Points
Deploy the WebLogic workloads on Java Cloud Service
Integrate with Oracle Management Cloud Service to monitor the application
Modernize the application with the use of Containers and microservices
Migrate the database to Autonomous
Incorrect. Please review Implementation Approach for OCI Move and Improve to find the
correct answer.

36. What is the difference between “Lift and Shift” and “Move and Improve”
Journey to Cloud?
(1/1) Points
Lift and Shift is for IT personas whereas Move and Improve is for Business
personas
They are both different Marketing terms for the same kind of Projects
Lift and Shift is pure (OS-based) move of an existing workload whereas
Move and Improve Project looks into optimizing the workload operation
across its lifecycle, and therefore has a wider scope.
Lift and shift is only for non-Production Environments while Move and
Improve is for Production Environments
Correct!

37. Your Customer’s back office Finance and HRMS is run on E-Business
Suite at their Data Centre. The application is heavily customised to meet
legislative requirements and the hosting servers will be going out of support
in the near future. They are keen to move to Cloud but require an interim
and long-term strategy to achieve their Cloud First vision, safe-guarding the
legislative interests. What approach is suggested in this case?
(1/1) Points
A big bang migration of Finance & HRMS to Oracle Cloud, discard all
customisations
Split the journey in 2 parallel phases (a) Move and Improve EBS-FINANCE to
OCI, (b) Move and Improve EBS-HRMS to OCI
Split the journey in 2 sequential phases (a) Move and Improve EBS to OCI,
(b) Migrate EBS-ERP to Oracle ERP Cloud and EBS-HRMS to Oracle HCM
Cloud
Split the journey in 2 sequential phases (a) Move EBS to OCI, (b) Improve
EBS by converting the database tier to Autonomous
Correct!
38. In a Move and Improve Project we consider the subject workload mostly
as a “black box”. Which of the follow statements describes this accurately?
(0/1) Points
We use the black colour to tag these workloads in the respective architecture
diagrams
All the above
We do not consider any changes of the functionality encapsulated in the
target workload, so that the end-users will experience no changes in their
nature of their work. Any improvements may just be to the wrapping so as
to improve the Quality of Service
The target workloads are boxed into VMs or Containers, so they run on
improved environment
Incorrect. Please review Implementation Approach for OCI Move and Improve to find the
correct answer.

39. As a PM for a Move and Improve to OCI Project, you’d like to have better
visibility of architectural components as well as better cost control on
resources being utilised. Select THREE options that enable you to achieve
your needs
(Choose all correct answers)
(0/1) Points
Define a proper and detailed inventory of migratable assets
Leverage OCI tagging in order to apply budgeting techniques on OCI
consumption
Contact Oracle Sales
Clearly define the detailed target and intermediate architectures
Incorrect. Please review Implementation Approach for OCI Move and Improve to find the
correct answer.

40. Which are the main categories to classify the migratable assets for an
OCI Move and improve Project?
(0/1) Points
Storage, Compute, Networking workloads
Packaged applications: Custom built on Oracle Technologies, Custom built on
non-Oracle Technologies
Packaged applications and non-packaged applications
Database workloads, Application workloads, Web-tier workloads
Incorrect. Please review Implementation Approach for OCI Move and Improve to find the
correct answer.
41. You are about to start the VALIDATE/TEST phase of a Move and Improve
to OCI Project and want to ensure all the key considerations are taken care
of. Which of the following should be considered?
(1/1) Points
Continuously test and validate the application data migrated to Cloud
Configure application logic/data approach to transfer to Cloud
Identify and Size the deployment environments with the correct Cloud
services
Design the target architecture
Correct!

42. A Customer is moving their On-Premise Forms Application to Application


Express on Autonomous. This is a Move and Improve Project
(1/1) Points
FALSE
True
Correct!

43. The Customer Project Manager calls for a meeting to discuss skills and
knowledge capabilities required to manage, maintain and evolve the Cloud
environments of SaaS/PaaS/OCI on an ongoing basis. Which of the following
should be considered for forming BAU (Business as Usual) Operations team
for the Customer?
(1/1) Points
All of the above
Cloud Infrastructure Architecture; Cloud Administration
Lifecycle, Configuration and Release Management; Continuous Validation and
Testing
Issue Management (MOS/Hlepdesk), Environments Management and
Monitoring
User Adoption and Change Management; Solution Management;
Correct!

44. For a Cloud Project to be successful in the longer run, the Sustainment
Plan and Adoption Strategy should include the following:
(0/1) Points
Oracle provides the needful Customer support for the Cloud services
subscribed through MOS - My Oracle Support and Cloud Portal; A reference
to this should be enough.
A detailed Customer Support plan with detailed SLAs to address issues
through tracking tools and ensure Customer satisfaction
Proactive and reactive Customer engagement to address issues, help
Customer realize value and progressively update solution to adopt new
features and Best Practices
Focus on Business value realization and value assessment with periodical
Business review workshops
Ensure that KPIs set at the beginning of the Project are met at the end of
the Project and the Customer realized the benefit for their investments
Incorrect. Please review Sustainment Plan and Adoption Strategy to find the correct answer.

45. Customer complains of failed integrations from Taleo Recruitment &


Learn Applications to their E-Business HRMS. You delivered this Project
including post Go-Live Support to the highest standards two years ago and
therefore called in to rescue. What could have gone wrong?
(1/1) Points
The Customer has taken a reactive issue resolution approach to maintain the
solution instead of proactively looking at the new updates and releases to
maintain the integrations
Post Go-Live support handover had incomplete tasks
Taleo Recruit and Learn are no longer positioned on the roadmap of HCM
solutions and hence integrations will not work
All of the above
Taleo is no longer supported and hence integrations fail.
Correct!

46. Which of the following Post Go-Live handover activities form part of your
‘Train the Trainer’ and ‘Transition’ activities for Customer IT team in a Cloud
Project?
(1/1) Points
All of the above
Technical overview on the application customizations, integrations and
analytical reporting tools along with respective documentation
Cloud Operations and Security review; hands on set up documentation for
the OCI/PaaS/SaaS applications
Orientation to data Conversion tools and processes
Functional flows overview and configuration walkthroughs
Correct!

47. Why is it recommended to have the Train the trainer (TTT) approach in
Cloud Projects?
(1/1) Points
To ensure that the Customer is fully involved and engaged in the Project
To facilitate Change Management, faster adoption and to streamline the
Project timelines& costs
To minimize Project delivery costs and budgets
To build a sustainable model for post Go-Live support
To identify the key Super Users who can be potential trainers
Correct!

48. You are the Project Manager of a Cloud Project with the following scope:
Cloud HCM, ERP and Universal Credits for PaaS/OCI. Which of the following
does NOT form part of PaaS Scoping?
(0/1) Points
Number of SaaS Processes implemented
Number of Analytical reports, dashboard and complexity, number of
instances
Custom application Use cases to be developed and Number of App Dev
instances required
Number of integration points in the scope + and the instances required
Mobile applications development and extensions
Incorrect. Please review Project Management Plan and Delivery Approach to find the correct
answer.

49. Which one of the following is NOT a key process consideration for a
Quality Cloud Implementation
(0/1) Points
Environments Management
Project Governance
Support Management
Scope Management
Stakeholder Management
Incorrect. Please review Project Management Plan and Delivery Approach to find the correct
answer.

50. People formulate for 80% of the success of a quality Cloud Project
implementation. In this context, what would be the most important
consideration when engaging with the Customer?
(1/1) Points
Stakeholder Management
Executive Sponsorship
Business and IT Ownership
All of the Above
Change Management and Training
Correct!

51. Almost all of the Project Management Plan depicted processes and
components have a higher INTENSITY of engagement in the Cloud Delivery
Framework except for:
(1/1) Points
Issue Management
Scope Management
Change Management
Procurement Management
Environments Management
Correct!

52. You are Project Manager for a Greenfield (i.e. no legacy processes or
systems) SaaS Fusion ERP, HCM Project in a single country along with PaaS,
OCI Universal Credits available for third party integration and analytics.
What would be the key consideration to plan for this Project?
(0/1) Points
Different geographies and time zones mandating specific approach of
planning and control.
Dependency of modules and different non-Oracle Cloud technologies
Customer priorities, Business drivers and Project objectives
All of the above
The Customer’s current IT infrastructure status (requiring modernization to
Cloud native tools, move and improve etc…
Incorrect. Please review Project Management Plan and Delivery Approach to find the correct
answer.

53. As a Project Manager you are planning for a SaaS Cloud Project and
would like to understand risks related to the services that have a
dependency on Oracle; specifically relating to cloning and enabling certain
services like VPN and SSO. Which of the following gives you more
information in this regard?
(0/1) Points
Cloud Service Contracts
Cloud Provisioning Processes
Cloud Service Entitlements
Cloud Patching Cycles
Cloud Support Services
Incorrect. Please review Cloud Risk Management to find the correct answer.

54. Your Customer has raised a concern and Risk regarding Constraints on
Security testing for SaaS Products. Which of the following would provide
further information on standard security testing coverage as part of the
Service, that you may point to the Customer to address their concerns?
(0/1) Points
Cloud Services Hosting and Delivery Policies
Oracle Moat Services
Cloud Services and Service Descriptions
Cloud Support Service agreements
Oracle Advanced Customer Services Contracts
Incorrect. Please review Cloud Risk Management to find the correct answer.

55. A Telco industry Customer implementing Fusion Engagement Cloud


requires 24/7 high availability and is concerned of Quarterly patching
downtime. Before looking at alternative technical solutions as risk mitigation,
which of the following would you review to educate the Customer about
SaaS Updates?
(0/1) Points
CX unity Cloud services policies
Oracle Professional services contract
Oracle SaaS Services policies
Oracle Fusion Services Description
Oracle Hosting and Delivery Policies
Incorrect. Please review Cloud Risk Management to find the correct answer.

56. While preparing for a Cloud Project Risk Register what are the important
topics that you as a PM need to familiarize with and reflect in the Register?
(0/1) Points
Policies, Service Descriptions and Entitlements
Oracle Cloud Sales Agreement
Product features and functionalities
All of the above
Support SLAs with Oracle
Incorrect. Please review Cloud Risk Management to find the correct answer.

57. Your Customers stakeholders are keen to apply patterns and discover
anomalies with data in motion. What tool may be used to serve this case?
(0/1) Points
Big Data CS - Streams
SOACS and/or MFTCS
Oracle Integration Cloud
API Platform Cloud Service
OIC - Process Automation
Incorrect. Please review Implementation Approach for Cloud Integrations to find the correct
answer.

58. Oracle Integration Cloud provides adapters and Recipes. As part of your
Project you review the existing recipes and realise that the integration needs
are not fully met due to missing data elements in certain adapters and
recipes. What is the Best Practice approach to address this scenario?
(1/1) Points
Design, Build and deliver integration flows from scratch since you cannot
customize the integration flows
Recipes can be changed but adapters cannot be modified. Hence build new
adapters and modify the recipes
Customize Oracle delivered Integration flows to address the Customer
requirements
Adapters can be changed but recipes cannot be modified. Hence build new
recipes and modify the adapters
Leverage point to point integration instead of using OIC to save costs
Correct!

59. While preparing for an integration Project what are the most important
factors to consider?
(1/1) Points
Verify downtime requirement from Customer
Identify number of instances
Identify the volume and frequency of the data exchange
Verify the target Architecture integration requirements
All of the above
Correct!

60. A Customer with several core Banking Systems and frontend CX


applications is looking for automation of manual updates to Customer
records across multiple applications and to streamline the operations. If all
the Applications have APIs, which of the following would you leverage to
achieve the outcome?
(0/1) Points
Leverage OIC adapters
Use Robotic Process Automation orchestrated with a process
Oracle Process Cloud
leverage UiPath RPA Adapter
Leverage OIC with Process Cloud
Incorrect. Please review Implementation Approach for Cloud Integrations to find the correct
answer.
61. A Customer requires seamless Data Migration from legacy Database
residing on obsolete infrastructure. They’d like to eliminate any down time
and also reduce unplanned outages. What tool is best used for this scenario?
(1/1) Points
Data Integration Cloud Service
Database Cloud Service
Oracle Integration Cloud
GoldenGate Cloud Service
Devise Integration through Big Data Cloud Services
Correct!

62. The implementation approach that avoids or minimises customizations


by promoting use of Best Practice standard functionality to meet common
Business needs is -
(0/1) Points
Product Driven
Requirement Driven
Strategy Driven
Solution Driven
Process Driven
Incorrect. Please review Implementation Approach for Solution in Scope to find the correct
answer.

63. Build, Measure and Learn Faster is an agile approach that works for:
(0/1) Points
MVF - minimum Viable feature
MMP - Minimum Marketable Product
MVP - Minimum Viable Product
Consumable Product
Working Software
Incorrect. Please review Implementation Approach for Solution in Scope to find the correct
answer.

64. Undertaking an Agile approach for system development is a fundamental


shift in thinking and not just change in methodology. What is (are) the most
important aspect(s) for Enterprises to adapt and adopt agile?
(1/1) Points
Type of culture
Business sponsors ownership of projects
Changing focus from “tactical” project level to “strategic”
How well the organization changes
All of the above
Correct!

65. Your Customer Project has the following in Scope – ERP Cloud, lift and
shift of legacy On-Premise Seibel CRM to OCI, Custom Build Mobile
Applications and integration between ERP Cloud and Seibel CRM using OIC
(Oracle Integration Cloud). What implementation approaches apply for this
scope?
(0/1) Points
ERP Cloud – Solution, Driven OIC and OCI - Requirement Driven, Mobile
apps - Agile
Waterfall Requirement driven will fit to the entire scope
ERP Cloud and OIC - Solution Driven, OCI - Requirement Driven, Mobile
apps - Agile
ERP Cloud and Mobile apps - Solution Driven OIC and OCI - Requirement
Driven
ERP Cloud, OIC and OCI -Requirement Driven, Mobile apps - Agile
Incorrect. Please review Implementation Approach for Solution in Scope to find the correct
answer.

66. Accelerating the process to deliver applications and software services at


a high speed and high velocity for infrastructure changes is referred to as:
(0/1) Points
Agile Development
Disciplined Agile
Continuous Integration
DevOps
Continuous Delivery
Incorrect. Please review Implementation Approach for Solution in Scope to find the correct
answer.
67. Your Customer Project scope includes Fusion Engagement Cloud, Service
Cloud (RightNow), Field Service (TOA), Commerce (ATG), CPQ, Marketing
Eloqua and Responsys, integrated through OIC (Oracle Integration Cloud)
recipes. What implementation approaches apply for this scope?
(0/1) Points
OIC - Requirement Driven; Marketing - Strategy Driven; Other CX Products -
Solution Driven
Agile - Iterative and incremental approach
Requirement Driven Approach is appropriate for this scope
Solution Driven approach fits the entire scope as there are OIC recipes which
are plug and play
There is no one-size fit all. It is mostly Solution Driven; Except for OIC,
some parts of Service Cloud extensions and Marketing where configuration is
shaped by changing Business Strategy.
Incorrect. Please review Implementation Approach for Solution in Scope to find the correct
answer.

68. The requirements gathering approach with User-Centred design process


to understand their needs, experiences, behaviours and goals for software
design is called -
(0/1) Points
Use Case Diagrams
Personas
WireFrame
Story Mapping
User Stories
Incorrect. Please review Implementation Approach for Solution in Scope to find the correct
answer.

69. Which of the following reporting tools may be used to leverage the pre-
built ETL to extract data from operational tables and load it into a
Datawarehouse
(0/1) Points
Oracle Business Intelligence Enterprise Edition
Oracle Business Intelligence Publisher
Oracle Business Intelligence Application
Oracle Transactional Business Intelligence
Oracle Analytics Cloud
Incorrect. Please review Implementation Appraoch for Reporting and Business Analytics to find
the correct answer.

70. As part of an ERP implementation a Customer has the following


requirements: Report on transactions such as invoices, payments, assets,
journals and on balances; Real-time online reporting; Wizard-driven easy-to-
use creation tool; Advanced formatting and multiple chart options. Which of
the following reporting tools addresses this requirement?
(1/1) Points
SmartView for Microsoft Office™
Financial Reports Centre
OTBI Reports
Account Monitor
BI Publisher reports
Correct!

71. The User Role that can create, share analyses and dashboards in OAC is
known as
(1/1) Points
DV Content Author
BI Content Author
BI Service Administrator
BI Data Model Author
BI Consumer
Correct!

72. Your Customer would like to Create and Manage (design, create and
modify) Cubes from Excel based application workbooks. Which Edition of
Oracle Analytics Cloud caters for this Use Case?
(0/1) Points
Standard Edition
Essbase Edition
Professional Edition
Special Edition
Enterprise Edition
Incorrect. Please review Implementation Appraoch for Reporting and Business Analytics to find
the correct answer.

73. Your Customer requires to distribute and share Analytics content (either
static or interactive). Considering Customer has Universal Credits
Constraints, which minimum Oracle Analytics Cloud Edition caters this Use
Case?
(0/1) Points
Enterprise Edition
Professional Edition
Standard Edition
Special Edition
Essbase Edition
Incorrect. Please review Implementation Appraoch for Reporting and Business Analytics to find
the correct answer.

74. A Telco Operator has been Live with Oracle CX Services for over six
months. When a new product launch was requested, the delivery turn-
around from IT department was more than three months, which is way too
much for the Marketing department. What could have gone wrong during the
implementation that may have resulted in this situation?
(0/1) Points
Customer Service team is complaining on the lack of a 360degree integrated
view of Customer which should be accessible to the Customer Service
Advisors
Marketing team has promotion bundles to be configured in addition to other
enhancements and the IT team is not able to deliver them on Time
Misalignment between IT and Business KPIs. Business KPIs were set without
taking into consideration the Time to Market T2M KPI of telco services to be
developed by IT
Oracle products are not addressing all the Customer requirements and need
more commitment from Oracle to address some of the ER-s
IT team is complaining that due to Cloud security they are not able to take
back-up to build analytical reports
Incorrect. Please review Transitioning Aligning Business Goals and Cloud Project Objectives to
find the correct answer.
75. Setting Project objectives and KPIs is important in the context of Cloud
Implementations because:
(1/1) Points
All of the above
If the Project delivers the desired outcome the Customer might not renew
the contract.
Shifting from CAPEX to OPEX budget might be impacted by Project failure
Customers might measure ROI based on Project Objectives
Subscription based Cloud model relies on successful Projects with
measurable Objectives linking back to Business Goals
Correct!

76. What are the key principles for Cloud Implementations preparation and
readiness to ensure alignment of Business goals and Project Objectives?
(1/1) Points
Business value identification; Business process improvement design; User
adoption strategies
Business and program strategic alignment; Goals and funding prioritization;

All of the Above


Trade-off analysis decision-making framework, Efficiency and effectiveness
measures and analysis
Program success accountability: Enterprise infrastructure and application
architecture design and standards
Correct!

77. One of your PM colleagues informs you that the Oracle Modern Best
Practices are just a marketing tool to use in presales. He suggests
conducting an activity level Business Process diagramming exercise (from
scratch) to capture Customer requirements. Which of the following is
recommended approach as guided by Oracle?
(0/1) Points
Proceed with the detailed mapping approach, as MBPs may only be used in
the Sales cycle.
No, MBP is not just marketing tool, you can leverage existing Level 3 (Visio)
diagrams in MOS through iterative and incremental approach during
implementation
MBPs are L2/L3 diagrams which can be used to deliver ANY process in the
Project why invent the wheel
Ensure conducting a fit/gap analysis of Business Processes and carry out 3
iterations of detailed diagramming to fully capture the Business Process
activities
Incorrect. Please review Implementation Approach for SaaS Applications to find the correct
answer.

78. A University SaaS Cloud Transformation Project has Oracle ERP,


Procurement, HCM (including Payroll) and Student Cloud in scope. The
Customer IT Team have detailed Business Process diagrams from existing
On-Premise systems but are open any improvements and count on you for
Project Approach advise. What SaaS Application Implementation approach
would you suggest?
(1/1) Points
As the Customer is open to improvements and new methods, follow a Show
& Tell approach for the entire Project based on the modern best practices
and the Level 3 diagrams as applicable.
Leverage their existing Process Maps, follow an “ASK & DO” approach to
identify Gaps and use PaaS to extend applications.
Show and Tell approach won`t work for any of the processes in scope
Leverage their existing Process Maps, map them to the SaaS Standard
Application flows for solution design and identify gaps. Engage C-Level
stakeholders for Change Management
Correct!

79. Modern Best Practices were used during pre-sales scoping for a
Customer’s multi pillar Project (ERP, HCM and CX). Given the Customer is
open to Solution Driven approach, what Business Process related activity is
recommended as a continuation into the implementation phase of the
Project?
(0/1) Points
It will be useful to identify the Customer pains areas and contrast them with
improvements possible with Oracle Modern Best Practice
Guide trust-building process/solution driven discussion with the Customer to
achieve quick win results
All of the above
Leverage the MBPs for familiarization training based on the Level 2 diagrams
of MBPs and drill down to Level 3 diagrams during implementation for
solution walkthrough workshops/CRP sessions
Better hone/define Customer’s objectives, focus, & obstacles to success, Map
processes to capabilities and craft digital transformation plans
Incorrect. Please review Implementation Approach for SaaS Applications to find the correct
answer.

80. The Project Management Balancing Act of Scope, Cost and Time in the
context of Cloud Projects is mainly impacted by which of the following?
(Select three)
(Choose all correct answers)
(0/1) Points
The quick win approach: shorter timelines of implementation and
mobilization
Resources Management
Subscription model of Cloud and the Universal Credits model of defining
budgets
Setting boundaries of the implementation scope to deliver in shorter
timeframes
Quality Management and expectations
Incorrect. Please review Introduction to Cloud Project Management and Delivery Framework to
find the correct answer.

81. You are documenting the lessons learned following delivery of a Cloud
Project. What high level Project Management ''habits'' would you document
as Best Practices for future Projects?
(1/1) Points
Ensure the Project objectives and the Business goals/KPIs are aligned
throughout the Project
Ensure that there is a proper Change Management Plan driven by the
Customer
Integrate the Environment and Instance Management activities with the
Project Plan
Project Delivery in shorter sprints bring quick win benefits to better realise
Cloud investment for Customers – a point to consider for future Project
proposals
All of the above
Correct!

82. The Partner Cloud Project Manager should be typically responsible for:
(0/1) Points
Oversee Cloud architecture and solution design
Manage Change
Manage Cloud Environments
Manage resources
The entire Delivery of the Project transitioning from Sales to Delivery up to
Go-Live
Incorrect. Please review Introduction to Cloud Project Management and Delivery Framework to
find the correct answer.

83. Your Project Scope includes Database Migration. What preparation


activity (activities) must you factor in during the ‘Analyse and Prepare’ phase
of Cloud Delivery Framework?
(1/1) Points
Identify mode of transfer (file or data) with/without transformation from
source to target.
Identify the volume and frequency of the data exchange
All of the above
Analyse the nature of data being transferred among different applications;
source and target databases
Identify the data sources - what is achievable, supportable, reasonable
Correct!

84. Your Telco Industry Customer requires their core CRM system available
24/7 and cannot afford any downtime as part of Transition to the new CX
Cloud Application. To cater for this requirement, which of the following
strategies allows you to move Data and maintain future Data changes using
Real-Time Processes?
(0/1) Points
This Approach is Not Possible
Transformative Data Migration Strategy
Phased Data Migration Strategy
Big Bang Data Migration Strategy
Trickle Data Migration Strategy
Incorrect. Please review Data Management and Migration Plan to find the correct answer.

85. You are involved in an OCI Project where you need to quickly set up a
Test environment based on the current production Data. What is the best
tool that may be used in order to migrate your current data into the new
Autonomous Database Environment
(0/1) Points
Zero Down Time Migration (ZDM)
Maximum availability Architecture
Data Import, Export with Oracle Data Pump or PDB Import/Export
Remote cloning with ADG
MV2ADB
Incorrect. Please review Data Management and Migration Plan to find the correct answer.

86. Your Customer requires the application software to remain up and


running during the Data Migration process. What tool is best suited to
perform the Data Migration?
(0/1) Points
Oracle SQL Developer
Remote cloning with ADG
Maximum availability Architecture
Data Import, Export with Oracle Data Pump or PDB Import/Export
MV2ADB
Incorrect. Please review Data Management and Migration Plan to find the correct answer.

87. In your ‘White Board’ session with Customer’s DBAs and Network
Admins, you have listed the following factors as Information gathering areas
to define Data Migration Approach: Downtime and Outage; Database
Schema Size; Network Bandwidth; Cross-Platform Migration; Database
Character Set; Data Encryption; Data Type and Quality; Sizing. What other
areas have you missed?
(0/1) Points
(C) DB Objects, Source Database, Data In-transit volume, Database
Patches, DB Time Zone
(B) and (C)
(A) DB Users and Privileges, Storage for Data Staging, Target Database,
Database Version and Edition
(A) and (B)
(B) Databases Patches, DB Name, DB Block Size, DB Time Zone, Database
OS Versions and Edition
Incorrect. Please review Data Management and Migration Plan to find the correct answer.

88. “This is how we do things here”- Is a typical statement from an On-


Premise E-Business Finance Super User highly focused on his requirements.
What positioning/ action would be most appropriate in SaaS Cloud Projects
context?
(0/1) Points
It is crucial for the success of the Project, that every user’s wants are
fulfilled. Develop customisations to meet Business requirements and
replicate existing processes.
Review the requirements in detail, take Executive sponsorship to baseline
requirements as per existing practices.
By strictly following the traditional waterfall methodology and Good PM
Practices; obtain requirements sign off as a key milestone. This will set the
Cloud Project to success.
To avoid this situation, undertake a detailed requirement gathering session
is an important Project activity.
Initial resistance is natural. It is important to do the benefit selling in any
Cloud Project. Showing the bigger picture and end results will help.
Incorrect. Please review Organizational Change Management in Cloud Projects to find the
correct answer.

89. An insurance company's IT department has decided to modernize their


legacy On-Premise application that has custom forms, reports and
integrations. Your Programme Scope includes Technology Delivery, Change
Management and Training the existing IT Team that will manage the System
post Go-Live. What Change Management activities would you incorporate in
your scoping and planning?
(0/1) Points
No need for any Change Management activities as the Customer will retire
their IT team and outsource maintenance to the Partner through a Managed
Services contract
Ensure the Business is monitoring and involved in this Project as the
financing model is moving from CAPEX to an OPEX model with optimization
of the IT team and headcount reduction
Depends on the scope of work. If it`s only modernization from forms and
reports to Cloud native applications, it’s a simple technology change and has
no impact on processes or people
Orient the Customer IT team to the new Cloud technologies. Upskill IT Team
for Cloud specific relevant skills for ongoing maintenance of the solution.
None of the above.
Incorrect. Please review Organizational Change Management in Cloud Projects to find the
correct answer.

90. Which of the following activities should be part of a Change Management


Plan for Oracle SaaS CX Project with OIC integration to E-Business Suite?
(0/1) Points
Conduct organizational impact assessment for shifting from On-Premise to
Cloud for the Business and IT operations departments
All of be above
Train the Customer IT team on Cloud Environments Management, Cloud
console and portal usage
For the SaaS applications, leverage the Oracle Modern Best Practices to
facilitate adoption and process change. For integrations, leverage integration
recipes
Set up of Cloud communication notifications to target audience to embed the
new Cloud culture in the Customer organization
Incorrect. Please review Organizational Change Management in Cloud Projects to find the
correct answer.