Professional Documents
Culture Documents
.
In mInes
.
by A. WHILLlER*, Pr. Eng., Se. D. (M.I.T.) (Fellow) and
J. VAN DER WALT*, Pr. Eng., B.A. Hons. (Bus. Admin.), Ph.D. (Eng.) (Visitor)
SYNOPSIS
South African mines often experience significant losses in production because of recurring shortages of water at
work places as the result of underground dams running dry. Similar shortages have occurred during fire-fighting
operations, and now, with the use of cold service water to aid in the cooling of mines, it is even more necessary
that such shortages should be prevented.
This paper draws attention to the primary cause of such water shortages, and an outline is given of some of the
fundamental hydraulic principles that must be followed in the design of gravity-fed water-supply systems on mines.
SAMEVATTING
Suid-Afrikaanse myne ondervind dikwels betekenisvolle verliese in produksie vanwee herhaalde watertekorte by
werkplekke omdat ondergrondse dam me opdroog. Dergelike tekorte het al tydens brandbestrydingswerk voorge-
kom en met die gebruik van koue dienswater om met die verkoeling in myne te help is dit tans nog meer noodsaaklik
om sulke tekorte te voorkom.
Hierdie referaat vestig die aandag op die primere oorsaak van sulke watertekorte en gee in hooftrekke 'n paar
van die grondliggende hidroulikabeginsels wat by die ontwerp van watervoorsieningstelsels met swaartekragtoevoer
in myne toegepas moet word.
JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY APRIL 1977 187
~ ---
-- ---
--""---"-""
v
~--
H
Volume =
Vx!! 02
f low rate
'-
Fig. I-Effect of shape of pipe inlet on the vena contracta
Head
(m)
I 06
Head'
(m)
l' 1.
"-"-
--"-"-
--
~ij~~~ I/~~~
Plain inLet to pipe Tapered inlet to pipe
Fig. 2-Minimum water depth (above top of pipe) to achieve the flow-rates indicated
Estimation of Water-flow Capacities centimetres above the pipe inlets, so that the rate of
A useful rule-of-thumb guide to the sizing of pipes is water flow is reduced considerably, resulting in shortages
that the water flow-rate in litres per second at a nominal of water. The problem is not that the water is drawn too
velocity of 2 m(s is equal to the square of the pipe rapidly from the dams, but rather that the feeding of
diameter expressed in inches. Thus, a 100 mm (4 inch) water into the dams is too slow because of inadequate
pipe will earry 16 lis, while a 200 mm (8 inch) pipe will design of the inlet opening in the pipes all the way up the
carry 64 lis, both at 2 m(s. shafts, often starting at the main supply dam at the top
of the shaft.
Effect of the Vena Contracta The calculations above indicate that, for the example
"If the water flows at a rate of 100 'is from a dam considered and for a straight inlet to the pipe, the water
through a 200 mm pipe in which the entrance shape is as level must remain at a height greater than about I m
illustrated in Fig. I, the nominal velocity in the pipe above the top of the outlet pipe if full flow is to be
would be (100(1000)((77(4 xO,22)=3,I8 m(s, and the maintained to the lower levels. Thus, the effective
head necessary to accelerate the water to this velocity, storage or surge volume in the dam is reduced con-
(V2(2g), would be 3,I82((2x9,79)=0,52 m. Thus, if air siderably, being only the volume of water above this I m
is not drawn into the pipe, the depth of water in the dam level to the top of the dam wall. It will be apparent
would have to be more than 0,52 m above the top of the therefore that, with the usual design of pipe inlets, the
pipe. This is illustrated in Fig. 2. useful storage volume in mine dams is considerably
If the pipe does not have a shaped inlet, the water smaller than the total volume of water, being unfortu-
velocity at the vena contracta would be about 40 per cent nately closer to half the total volume of water in the dam.
greater than the nominal velocity, or 4,45 m(s, and the The shape of the tapered inlet is not very critical,
corresponding head, V2(2g, necessary to accelerate the provided that it gives a smooth transition on the inside. A
water to this velocity would be 1,01 m. Thus, in this typical inlet cone might have a 30° slope, and a diameter
case the depth of water in the dam to avoid air being 30 to 40 per cent larger than, or even double, that of the
drawn into the pipe would have to be at least 1,01 m pipe itself.
above the top of the pipe.
It is well known that, during periods of heavy demand Benefits of a Goose-neck Inlet
for water in mines, the levels of dams fall to a few Better use can be made of the total volume in storage
188 APRIL 11)77 JOURNAL. OF THE $OUTH AFRICAN INSTITUTE OF MINING AND METALLURGY
dams if a tapered goose-neck inlet is provided to all the and air entrainment, it is essential that the available
pipes going out through the dam wall. This is illustrated head at the dam is sufficient to overcome friction losses
in Fig. 3, where, for the example shown, the flow of in the pipeline leading to the shaft, and also to accelerate
100 lis could be maintained with the level of watcr only the water to thc terminal velocity in the pipe going down
135 mm above the goose-neck inlet pipe. thc shaft. A uscful guideline is that the diamctcr of the
pi pc lcading from the dam to the shaft should hc at lcaR!,
twice thc diameter of the pipe going down the shaft.
Minimum level of water
The approximate terminal velocity and corresponding
to prevent entrainment flow-rate of water going down pipes in vertical shafts is as
of air (135mmforaflowof indicated in Table I. As there are few shaft systems at
1001/s.ifD=200mm) present using more than 150 lis on the 24-hour average,
u - it would appear that pipes of 150 mm diameter down
shafts should suffice if the capacity of the dams is
sufficient to meet peak demands. Indeed, in many mines
100 mm pipes would suffice in the shafts, provided that
Low wall to keep they were fed from the dams through 200 mm approach
sludge away from
pipe inlet; separate
pipes and provided the dams had adequate surge
drain-pipe to be provided capacity.
for periodic flushing
TABLE I
Fig. 3-Benefit of a tapered goose.neck inlet
TERMINAL FLOW IN VERTICAL PIPELINES
JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY APRIL 1977 189
hanging H2
H
D~2d
0.:,~ ~
HJ:: 10m Y'.'
"" ~""""~/""
~=
~ ~
--Dia d
"
""~~,_./
H2
""
Pipe carried on footwall
1
H,
~ j
~
if ""hia d
Fig. 4-Height of underground dam to ensure full flow of water
new, whereas, as the pipe ages, the on periods will extend down the shaft for a distance of about 10 m
increase towards about 100/144=69 per cent of the time. below the station footwall. (Referring to Fig. 4, the
The feed to the shaft pipe would have to be designed to diameter, D, should not be less than 2d, and the distance
provide water at the rate of 216 lis (for a 150 mm pipe, Ha should not be less than 10 m.)
see Table I) without the development of negative gauge
pressures in the pipeline. Over-sized Shaft Pipes
Returning again to the example of a 150 mm pipeline When pipes down shafts are over-sized in relation to
down the shaft, the terminal velocity in the pipe when the pipes feeding water to them, several practical
new will be about 12 m/so The corresponding velocity difficulties arise. For example, in pipelines in which the
head, V2/2g, is 7,35 m, so that, referring to Fig. 4, the flow is regulated from the top, severe surging occurs
minimum value of the head, Ha, above the entrance to unless a continuous bleed of air is allowed into the pipe
the 150 mm pipe must be 7,35 m if negative gauge at the top. This continuous bleed of air results in ac-
pressures are to be avoided. If the diameter, D, of the celerated corrosion of the pipelines internally because of
supply pipe from the dam is 300 mm, the head loss in the ready availability of oxygen in the warm, damp
this pipe at a flow-rate of 216 lis would be about 3 m environment. Such corrosion not only shortens the useful
per 100 m length. If the length of this 300 mm pipe, life of such pipes but also causes frequent blockages at
including the short portion down the shaft, is 150 m, the places in the pipe circuit where scale and debris can
frictional head loss in the pipe would be H 2=4,5 m, and accumulate. rrhe need for this continuous bleed of air
the total head, H, (see Fig. 4) necessary to ensure no falls away if the approach pipe is properly sized.
negative pressures in the pipeline would be 7,35+4,5= The rate of flow of water down such over-sized pipes is
11,85 m. It should be evident from this example that determined almost entirely by the design of the inlet pipe
dams must be developed at a level somewhat above that and is hence not increased by having a larger pipe down
of the station footwall, so as to avoid the need for the shaft. Thus, in situations where shortages of water
pumps to transfer the water out of dams to the shaft. occur, the mere provision of a larger pipe in the shaft
In practice it will be found that slight negative heads will not markedly increase the water flow down the
(up to a few metres) do not cause surges, giving a small shaft.
safety factor in these calculations. Furthermore, as a When the approach pipe is correctly sized, the gauge
further safety precaution, the measurement of the head pressure at the top of the vertical column will always be
H is taken from the bottom of the dam without allow- positive, so that no air can be drawn into the system and
ance for the depth of water. the flow down the vertical pipe will be at terminal
This example, and other similar calculations, lead to velocity.
the rule-of-thumb recommendation that the diameter of
the supply pipe leading from the dam to the shaft should Pin-pointing Troubles
be at least twice the diameter of the pipe down the shaft, When difficulty is experienced with the water supply
and that, before joining the smaller shaft pipe, it should in mines, a few simple measurements with pressure
190 APRIL 1977 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY
SOmm U-t.ube vent pipe
Fe
~old
l-- water
~
.~
I
E !
01
~
I
!
300mm
j
150mm
t
Fig. S-Plplng arrangement for feeding cold water down a shaft from surface
ISO
or
<00
/.f,Q~~~
',., £:Ir
o~ ${,f
l£:Iv '/:),01"
£:11 J'
ISO g Q60
to v£:l
l£:Iv $Et-t.
£:1 '0 I)
'1$
t I
6£:1{. /.f,o
°/.f,
JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY APRIL 1977 191
gauges will often suffice to indicate the causes. For this barometric head; typically it would be about 7 m, as
it is imperative that suitable pressure tappings are illustrated. The V-tube has a second purpose in that it
provided on the pipes so that pressure gauges can be prevents the flow of air down the pipe during the off-
fitted quickly. Two important measuring points in the periods, thus reducing internal corrosion.
pipe leading to the shaft are indicated in .Fig. 4. Allot,lwl'
place is at the bottom of the pipeline in cases where flow Inadequate Piping Systems
regulation is provided at this position, or where the flow Where water supply difficulties occur in existing
enters a pump or a heat exchanger such as a condenser. installations, it will often be possible to remedy matters
Measurements of these pressures, together with a by laying a new, larger approach pipe, and by combining
knowledge of the relative altitudes of the measuring all the pipe connections that are already built through
points from survey data, will usually indicate whether the dam wall to feed into a common header immediately
the difficulty is due to air entrainment, air accumulation outside the dam. Usually it will also be necessary to fit
resulting in pipelines running partially full, blockages, tapered goose-neck inlet sections to all the pipes that
inadequate pipe diameters, poor inlet design, etc. carry water out through the wall in order to prevent air
being drawn into the pipes, and hence enabling the full
Intermittent Flow volume of the dam to be utilized for surge capacity.
When long pipelines carry cold water intermittently, In the method illustrated in Fig. 6, the peak water
or when the flow stops for considerable periods over flow-rates can be handled without having to pass
weekends, the change in pipe temperature can give rise through the pipes in the dam wall, and delays in pro-
to difficulties as a result of thermal expansion. Thus, duction arising from broken pipes can be reduced
with a coefficient of thermal expansion of 10,7 X 10-6 pcr significantly.
°C, the change in length of a 1000 m long pipeline for a It is important to note that, with the arrangement of
temperature change of 30 °C is 0,32 m. Provision must be piping and valves shown in Fig. 6, the dam would serve
incorporated in the support of the pipeline for this essentially as an open stand-pipe since the level of the
expansion and contraction. water would vary by only a few centimetres each day.
One method for avoiding problems of expansion and The volume storage capacity of the dam would be
contraction resulting from intermittent operation (par. utilized only in the event of a broken pipe.
ticularly over weekends) is illustrated in Fig. 5, where a
small continuous flow of water is provided down the Conclusion
pipe, the flow-rate being adjusted so as not to draw air It is believed that adherence to the fundamental
down through the V-tube vent pipe. The height of the design principles outlined in this paper will ensure
V-tube must be one to two metres less than the adequate water supplies in mines under all conditions.
Hydrogen in metals
The second international congress on this suhjcd is should he addressed to the Secretariat General du
to be held in Paris from 6th to 10th June 1977. The 2 eme Congres, "L'Hydrogene dans les Metaux",
congress is being organized by the I.S.M.C.M. (L'Institut I.S.M.C.M., 3 rue Fernand Hainaut, 93407 St Quen
Superieur des Materiaux et de la Construction Cedex, Paris.
Mecanique). All correspondence concerning the congress
192 APRIL 1977 JOURNAL OF THE SOUTH AFRICAN INSTITUTE OF MINING AND METALLURGY