FAJAR ANUGERAH DINAMIKA JOB SCHEDULE SHEET ( JSS )


ACTIVITY PROGRESS
Model : PC400LCSE-8
Code Unit : FEX 429
HM : 16576
Month Desember' 2021 JANUARI 2022
NO JOB ACTIVITY DOWNTIME Date 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 Remarks
Day Mg Sen Sel Rab Kam Jum Sab Mg Sen Sel Sel Sel Sel Sel Sel Sel
Progress Activity 1 Shift
1 Overhaul Under Carriage Plan PLAN
Plan Plan
- Washing Unit Actual
Activity :
Plan Plan
- Remove Track Shoe Assy LH Activity : Remove track link assy LH
Actual
Plan Plan
Remove and Install Track Roller + Carriage
- Actual Activity : Install Final Drive LH (waiting Final Drive)
Roller + Idler LH + Sprocket
Actual
Plan Plan
- Install Track Shoe Assy LH Activity : Install Track Link LH
Actual
Plan Plan
- Remove Track Shoe Assy RH Activity : Remove track link assy RH
Actual
Plan Plan
Remove and Install Track Roller, Carrier
- Roller +Idler _ RH Actual Activity :Install Track Link RH (Waiting Recoil Spring)
Actual
- Final Check Under Carriage, Hyd system Plan Plan
- Washing Unit Plan Plan
- Groud Test & Finish Plan Plan
Total Down Time : 120 Hours

MP : Nasrudin ( GL Track )
Sugeng ( GL Track ) Prepared by, Approved by, Acknowledged by,
Mekanik Track ( 5 Orang )

Support: Cran Truck


Herberth. H Teddy Y. T Oke Dwi. P Agus Setiawan Rama Dauphian. G
SH Planner Plant Dept Head Dept. Engineering Dept. Production Project Manager
PLAN
PROGRESS / ACTUAL
WAITING PART