Professional Documents
Culture Documents
HIS ARTICLE DISCUSSES GREEN These issues are not adequately discussed in IEEE
T
power distributed generation (DG) sources standard 1547, which addresses the interconnection of
(of 10 MW or less), which are connected to DG to utility systems.
a utility system at the distribution level,
and their impact on distribution Installation of Green Power
system reliability. The article also A significant amount of green
BY CHARLES J. MOZINA
summarizes the specific reliability power is being installed at the
and protection issues in inter- distribution level by means of green
connecting green power generators to utility systems power generation facilities in many parts of the United
to mitigate the aforementioned reliability issues. States and Canada. Green sources such as wind, solar,
methane (from landfills), hydro, and diesels powered from
55
Digital Object Identifier 10.1109/MIAS.2010.936970 synthetic fuel are some of the green generation being
1077-2618/10/$26.00©2010 IEEE
interconnected with the utility at the reclosers and sectionalizers while
distribution level. These generators others do not. Automatic reclos-
operate in parallel with utility distri- THE ENGINEER ing practices vary from utility to
bution feeders. utility.
It is forecasted by many experts that TYPICALLY n Various Types of DG Generators:
the installation of green power genera- SELECTS THE Three basic types of DG genera-
tion will be increased due to the need tors that are used have different
to provide more clean energy. Utility PROTECTION electrical characteristics. The
regulators are encouraging green power, basic types of green DG genera-
resulting in utilities seeing more and FUNCTIONS THAT tors are listed in a later section.
more green power installation on their n Interconnection Function Require-
distribution systems. ARE APPROPRIATE ments: These requirements vary
Until the passage of the Public Utility from utility to utility and are
Regulatory Policies Act (PURPA) in FOR A SPECIFIC different for various megawatt
1978, U.S. utilities were not required to sizes of generators.
interconnect with small generators. At
APPLICATION. IEEE Standard 1547 [1] was an
the transmission level, there were always attempt at a national standard for DG
nonutility cogenerating industrial facili- interconnection. In the author’s view,
ties such as petrochemical plants and pulp and paper mills that IEEE 1547 provides very limited guidance to the industry
operated in parallel with the utility. But at the distribution on interconnect protection requirements other than calling
level, utilities could simply say no to small-generator owners for over/underfrequency and over/undervoltage intercon-
that wanted to operate in parallel with their system. PURPA nection protection. It also clearly defines interconnection
was the first step in utility deregulation and required utilities protection to be installed at the point of common coupling
to interconnect with small generation as long as the owners of (PCC) between the DG and utility system. The standard
such generation followed reasonable requirements set forth by cites obvious requirements for DG interconnection opera-
the utility. PURPA also provided a substantial tax incentive to tion but offers few methods, solutions, or options to meet
DG owners. By the mid-1980s, however, the tax incentive these requirements. Key issues such as potential overvol-
had expired and DG died off. tages, interconnection transformer choices, loss-of-utility-
DG remained relatively dormant until the mid-1990s relay coordination, application of DG on secondary grid
when utility rates started to increase. The driving force for networks, damage to DG generators due to unbalanced
that resurgence was the belief that power could be gener- current caused by utility single phasing, and out-of-step
ated cheaper at the point of consumption rather than the protection are not addressed to any significant level. While
IEEE INDUSTRY APPLICATIONS MAGAZINE JULY j AUG 2010 WWW.IEEE.ORG/IAS
purchasing power from a utility. During this period, most the goal of 1547 was to provide standard technical require-
of the DG installations in the United States were in areas of ments for DG interconnection, it does this on a basic level
the country where the power costs were high. In these such that the solutions to problems are not addressed to the
areas, small industrial and commercial customers supplied degree required to help those struggling with the problems
from distribution circuits started to install DG in peak- cited in this article. IEEE Standard 1547 is not a document
shaving or load-following applications, where a significant that engineers in utilities or those consultants designing
portion of their load was generated on-site. Most of these DG interconnection protection can use to design their DG
generators were fired with natural gas. When natural gas facilities. In recognition that much more work was needed,
prices increased by a factor of four in the late 1990s, DG additional IEEE Standards Committees were formed.
died off again. It remained relatively dormant until the
mid-2000s when the issue of global warming came to the Basic Types of DG Generators
forefront of concerns by the states and the federal govern- IEEE 1547 discusses three basic types of DG generators.
ment. The idea of green power was born. Induction generators and synchronous generators are the
To promote green power, utility regulators either set high two traditional types of dispersed generators that operate
buyback prices for power generated from green sources or interconnectedly with the utility system. The third type is
required utilities to generate a portion of their future power an inverter-based DG that do not operate in synchronism
needs from green sources. Green sources included are as fol- with the utility system.
lows: wind, solar, hydro, fuel cells, biomass, diesels powered
from synthetic fuels, and methane from landfills that power Induction Generators
gas turbines or diesels. DG induction machines were typically small to less than
500 kVA. These machines were restricted in size, because
An Update on DG Interconnection their excitation is provided by an external source of var. In
Standards and Guidelines recent years, power electronic-controlled capacitors have
In an attempt to facilitate the installation of DG generation, been installed on the terminals of these units to provide a
a number of efforts have been made to try to standardize controlled source of excitation. This has allowed induction
interconnection protection requirements. This has proven generators to increase in size to approximately 3.0 MW.
to be extremely difficult due to the following variables: Induction generators are similar to induction motors and
n Design Variations of Utility Distribution Circuits: Some are started like a motor (no synchronizing equipment
utilities use fuse saving while others choose not to needed). Induction generators are less costly than synchro-
56
try to overtrip line fuses. Some utilities use line nous generators because they have no field windings. These
machines can supply real power (watts) to the utility but
require a source of reactive power (vars), which in some
cases is provided by the utility system. These generators
can provide fault current for only a few cycles for faults on Loads Feeder Island
the utility system. Interconnection protection associated
with induction generators typically requires only over-/ DG
undervoltage and frequency relaying. Self-commutation is
Loads
also possible with utility pole-top capacitors and can result in
nonsinusoidal waveforms and overvoltage. This point is dis-
cussed later in this article. Induction generators are typically DG creates a feeder
Loads island, inhibiting automatic
used in wind applications.
reclosing, and creates
Loads potential power-quality
Synchronous Generators issues.
Synchronous generators have a dc field winding to provide Loads
a source of machine excitation. They can be a source of both
watts and vars to the utility system and require synchroniz-
ing equipment to be paralleled with the utility. These gen-
erators can provide sustained fault current for faults on the
utility system. Synchronous generators are typically inter-
nal combustion engines (diesels), gas turbines, and small
hydrogenerators.
Low High
Voltage Voltage Problems Advantages
(Sec.) (Pri.)
Can supply the feeder circuit Provides no ground current for
from an ungrounded source faults at F1 and F2 to disrupt
after substation breaker A trips, ground relay coordination.
causing potential overvoltages. Ground relaying at breaker A
will not respond to ground
A faults at F3.
Utility Substation
Provides unwanted ground No overvoltages for ground
F2 current for supply faults at faults at F1. Ground relaying
Load F1and F2 that can disrupt as breaker A will not respond
Interconnection
Transformer Load relay coordination. System to ground faults at F3.
Connections unbalance current circulates
F1 in transformer delta.
DG Allows feeder ground relaying at No ground overvoltages for
breaker A to respond to ground ground faults at F1 if
F3
faults at F3. If the generator is generator is solidly
grounded with a resistor in the grounded.
neutral, it will create a high zero
sequence impedance that can
in effect unground the system
when breaker A trips for a
ground fault at F1.
5
59
Interconnection transformer connections.
4) there must be a transformer in the circuit to
provide nonlinearity.
2
VA
0
If all these conditions exist, ferroresonance can occur.
2
What are the techniques for mitigating the resulting over-
voltages? Studies have shown that both induction and
VB
0
2
synchronous generators are susceptible. Also, all types of
interconnection transformer connections (wye–delta, delta–
VC
0
–2
wye, wye–wye, and delta–delta) are susceptible. Surge arrest-
–4
ers will clip the peaks of the overvoltage but will not suppress
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 the ferroresonance condition and may be damaged in the
Time (s) process. Metal-oxide arresters have an increased ability to sur-
(6 kHz Sample Frequency, vive longer, but they can also be damaged. The most practical
1 kHz Plot Frequency Using Largest of Six Samples) solution is to trip the DG to remove the driving source. This
6 is not as simple as it sounds, since the voltage waveshape for
Overvoltages caused by ferroresonance. A 50-kW this resonance condition is nonsinusoidal.
synchronous DSG, 9-kW load, 100-kvar capacitance, and A major concern in trying to detect this condition with a
wye–delta step-up transformer. Maximum voltage: A ¼ 2.74 digital relay is that with frequency and voltage waveshapes
p.u., B ¼ 2.34 p.u., C ¼ 2.92 p.u. not sinusoidal and at normal system frequency, overvoltage
and frequency measurements will be effected to where the
but can also occur on synchronous machines. Overvoltages digital relay may not operate. The measurement of peak
of over 3.0 per unit can occur. The discharging and charging overvoltage rather than RMS provides the best solution for
of the system capacitance through nonlinear magnetizing the detection of this type of event. IEEE 1547 does not
reactance of the DG interconnection transformer produce mention the possibility of ferroresonance, another short-
these overvoltages. The ferroresonance associated with DG coming of the standard. An example of a ferroresonance
differs from the traditional ferroresonance caused by single- voltage waveform is shown in Figure 6 and was taken from
phase switching in that no unbalanced condition is neces- the field tests conducted in New York State in the 1980s.
sary. A detailed description of the phenomenon is contained
in an IEEE article titled, “Relay Performance in DGS DG Interconnection Protection
Islands” [3]. It identifies the following conditions needed Methods and Practices
for ferroresonance: The functional levels of interconnection protection vary
1) the DG must be separated from the utility source widely depending on factors such as generator size, point of
(islanded condition) interconnection to the utility distribution system, type of
IEEE INDUSTRY APPLICATIONS MAGAZINE JULY j AUG 2010 WWW.IEEE.ORG/IAS
2) the kilowatt load in the island must be less than generator (induction, synchronous, and asynchronous), and
three times the rating of the DG interconnection transformer configuration. As shown in Table
3) the system capacitance must be greater than 25% 1, specific objectives of an interconnection protection system
and less than 500% of the rating of the DG as well as the relay functional requirements to accomplish
each objective can be listed. Other than a very simplistic
discussion of the detection of loss of parallel with the utility,
TABLE 1. INTERCONNECTION PROTECTION AREAS.
IEEE 1547 does not address protection areas such as use of
Interconnection Protection Protection fault current at the DG facility to detect supply tripping,
Objectives Functions Used abnormal power flow, and damaging system conditions.
Detection of loss of parallel 81 O/U, 81R*, 27/
with the utility system 59, TT**, 32*** Detection of Loss of Parallel
Operation with the Utility System
Supply fault detection Phase faults: 51 V, The most basic and universal means of detecting loss of paral-
67, 21 lel operation with the utility is to establish an over/ underfre-
Ground faults: quency (81 O/U) and over/undervoltage (27/59) window
51 N, 67 N, 59 N within which the DG is allowed to operate. The sensitive set-
27 N ting of both the underfrequency and voltage windows pre-
vents the DG from supporting the power system during
Detection of damaging 47, 46, 591, 78
emergency conditions. When the DG is islanded from the
system conditions
utility system, either due to a fault or other abnormal condi-
Abnormal power flow 32 tion, the frequency and voltage will quickly move outside the
detection operating window if there is a significant difference between
Restoration 25 load and dispersed generation levels. If the load and generator
are near a balance at the time of separation, voltage and
O/U: over/under frequency; 81 is the relay function number for frequency may stay within the normal operating window, and
frequency. under/overfrequency and over/undervoltage tripping may not
*
Rate of change of frequency. take place. If this is a possibility, then a transfer trip (TT)
**
Transfer trip. using a reliable means of communication may be necessary.
***
Rule 21 California. As discussed in the previous section, when induction or
60
synchronous DGs are islanded with pole-top capacitors and
the generator capacity is near that of the Restoration
islanded load, a resonant condition that OPERATING Once the DG has been separated from the
produces a non-sinusoidal overvoltage utility system, after interconnection pro-
can occur. For these cases, an instantane- GREEN POWER tection operation, the interconnection
ous overvoltage relay (59I) that responds must be restored. Two DG tripping/resto-
to peak overvoltage needs to be used to DGS IN PARALLEL ration practices are widely used within
detect this situation. Interconnection the industry. The first restoration method
protection requirements in the state of WITH UTILITY (Case 1) is used in applications where the
California are defined in a filing to the generation at the dispersed generation
state utility commission called Rule 21. DISTRIBUTION facility does not match the local load. In
A key provision of this rule is the unique SYSTEMS IS NOT these cases, interconnection protection
application of a directional power relay- typically trips the DG breakers, as illus-
ing (32) to detect loss of utility parallel WITHOUT trated in Figure 7. When the utility sys-
operation. This provision is only applica- tem is restored, the dispersed generators
ble to DG units that are installed for HAZARDS. are typically automatically resynchron-
peak shaving or load following and do ized. Many utilities require a synchro-
not sell power back to the utility. check relay (25) at the main incoming
breaker to supervise reclosing as a security measure to avoid
Supply Fault Detection unsynchronized closure. The synchrocheck relay is generally
On many small DGs, no specific supply fault detection is gen- equipped with dead bus undervoltage logic to allow reclosure
erally provided. Induction generators provide only two or three from the utility system for a dead bus condition at the dispersed
cycles of fault current to external faults similar to induction generation facility.
motors. Small synchronous machines are typically so overloaded The second restoration method (Case 2) is used where the
after the utility substation breaker trips that their fault current DG roughly matches the local load. In these cases, the inter-
contribution is very small. For these small generators as well as connection protection trips the main incoming breaker
asynchronous generators, the detection of loss of parallel opera- (breaker A), as illustrated in Figure 8. In many cases, the dis-
tion via 81 O/U and 27/59 relays is the only interconnection persed generation facility may have internal underfrequency
protection necessary. The larger the synchronous DG, the
greater is the chance that it will contribute significant current
to a utility system fault. For this situation, supply fault back- Utility
feed detection in addition to loss of parallel operation protection
is generally provided. Typically, relay functions, such as 67, 21, Multifunction